Generator Interconnection Supplement To DTE Energy Generator
Massachusetts DTE DG Interconnection Collaborative DG Cluster Proposal November 12, 2002
description
Transcript of Massachusetts DTE DG Interconnection Collaborative DG Cluster Proposal November 12, 2002
1
Massachusetts DTEDG Interconnection Collaborative
DG Cluster ProposalNovember 12, 2002
2
What Is An Interconnect (Nomenclature)?
Basically, the interface between Distributed Generation (DG) equipment and the grid, called the Area Electrical Power System (EPS)
Load3
EPS
Customer Facility
Customer Facility
Customer Facility
Customer Facility
Customer Facility
EPS
DGLoad
2
Point of Common Coupling (PCC)
Load1Customer
CustomerCustomer
CustomerCustomer
EPS EPS
Network
Radial
3
DG Cluster Proposal Overview
Standardized Process and Requirements Ensure safety and reliability
Follows national standards Equipment must be certified or undergoes design review
For small generation <20MW
Differentiating By: One of three generator size thresholds Potential “impact” of generator on Electric Power
System (EPS) Type of EPS at Point Of Common Coupling (PCC)
4
Process Overview
Scope of process shrinks considerably when expeditedDefines screens for certified equipment
Generator Application
>20MW?
Historic Application
Process
Interconnect Agreement
>2MW?
Expedited Application
Process Super Expedited
Application Process
Meets Screens?
Yes
Yes
Yes
5
Size Threshold CategoriesLess than 10kW
Accepts utility proposal Three page application/agreement No review/payments necessary
Less than 2 MW eligible for super-expedited process
Certified equipment De minimis grid impact No connection to transmission lines
2-20MW eligible for expedited process Check for distribution and transmission impact
6
10 kW To 2 MW
Units certified by UL or other NRTL against UL1741 (representing IEEE Std1547 Draft 10)2 screens for determination of no grid impact Primary screen – conservative, utility origin
100% of units that pass are OK Secondary screen - less conservative
80-99% of units are OK?
Creates presumption of acceptance
7
CertificationVerifies that equipment is designed to ensure electrical protection safetyWebsite registryUL or similar NRTL describes equipment package and test resultsPosted w/ 6 week comment periodUL responds to any commentsOnce certified -- no type testing and no other equipment can be requiredAlready UL-approved equipment is grandfathered
8
IEEE Std1547OverviewReferencesDefinitions and AcronymnsTechnical Specs and Requirements
General Requirements Response to Area EPS Abnormal Conditions Power Quality Islanding
Test Specifications and Requirements Interconnection Test Production Tests Interconnection Installation Evaluation Commissioning Tests Periodic Interconnection Tests
Annexes (Informative)
Flicker Information Interconnection
Tests Commissioning
Tests Bibliography
9
Overall Super-ExpeditedProcess Flow
SG Submits Complete
Application
Interconnect Agreement
Passes Primary
Screens?
Yes Yes
IP Conducts Initial
Review
Passes Secondary Screens?
If Needed, IP & SG Agree To Minor Mods?
Yes
Technical Dispute
Resolution
No (IP Initiates)
IP Conducts Limited IC
Review
Meeting To Discuss
Initial Review NoNo
IP Conducts Supplemental Review (If SG
Agrees)
SGInitiates
To Expedited Process
If Needed, IP & SG
Agree To Mods?
Yes
No
Note: “SG” is Small Generator “IP” is Interconnection Provider
10
Basis For ScreensCircuit size versus DG
size
DG contribution to fault
Short circuit interrupting capability limit
Three-wire and four-wire circuit criteria
Nameplate limits
Circuit impact
Fault handling, fuse desensitizing & nuisance trip
Short circuit handling
Proper connection
Single phase imbalance
11
Screens – PrimaryAggregate DG capacity limited to a low percentage of the peak load of a distribution circuit (different limits for radial vs spot network vs secondary grid network)DG contribution to circuit fault current is limitedDG not allowed to cause grid protective devices to exceed 90% of their short circuit interrupting capabilityIn aggregate, DG cannot be > 10MW where transient stability limits postedInterconnection configuration-specific limits on single-phase generator hookup and capacity to avoid imbalance, overload, and possible neutral/grounding problems
12
Screens – SecondaryAggregate DG capacity limited to a higher percentage of the peak load of the distribution circuitBasically the same limits on fault current contribution and short circuit interrupting impact as primary screen
13
10kW-2MW Costs
Application feeAdditional surcharge for interconnection review Limited to reasonable amounts based on
size
No other costs for interconnection under Super Expedited procedures
14
Dispute Resolution
Elements Technical Master Hotline ADR for non-technical disputes
IP must initiate if SG Applicant clears secondary screenGen Applicant has burden if both screens failed
15
Metering
Only metering required for this agreement is that necessary to implement the interconnection
16
Timing10 days to review application15 days to review screens5 days to execute IA (Interconnect Agreement)If Primary Screen failed 10 days for additional review (after
surcharge is paid) 5 days to notify applicant of results 5 days to send IA
17
Interconnection Agreement
Standard form AgreementShorter form for generators <2MW Can be pre-executed
18
Interconnection Application
Standard formShorter Form for generators <2MW
19
2-20MW Interconnection
Includes transmission impact issuesDirect transmission interconnection as well as distributionUsed by all generator sizes for which <2MW procedures do not apply
20
Basic Process
Optional scoping meeting up frontThree main components Feasibility study Impact study (if needed) Facilities study (if needed)
Patterned after Utility proposal
21
Feasibility Study
Checks to see if generator has an impact distribution or transmission system load flow (unless no export) short circuit grounding
IP shall rely to extent practical on existing studiesGives generator developer idea of interconnection costs
22
Transmission Impact Study
Only undertaken if Feasibility Study raises questions of transmission impactsUsually costly -- to be avoided if possibleIf no impact study needed - generator drops from queue
23
Distribution Impact StudyPurpose
Identify generator design elements that protect distribution system
Assess impact of generator on distribution
No design review needed if Certified Generator meets criteria similar to 0-2MW secondary
screens (without secondary network items)
Includes Distribution load flow study Equipment interrupt rating analysis Protection coordination study System operation impact analysis
24
Facilities Study
Identifies attachment facilities needed for interconnection including distribution system upgradesIf no facilities needed (customer sited generation), no study undertaken
25
2-20MW Costs
To be discussedLimit interconnection costs to only those directly related to the application
26
Transmission Queue
To be discussedFERC is scheduling a conference and possible NOPR on the subject
27
Interconnection Agreement/Application
Forms to be developed
28
Massachusetts DTEDG Interconnection Collaborative
Background
29
IEEE Std 1547 General Requirements Summary
Voltage regulation inside ANSI C84.1 Range AGrounding coordinated with Area EPSSynchronize without voltage fluctuation at PCC >±5% of prevailing voltagesNetworks: Spot networks only for now
CustomerCustomer
CustomerCustomer
Customer
Feeder
NP NP
Feeder
30
1547 General Requirements Summary (Continued)
DG shall not energize EPS when EPS is de-energizedDG > 250kVA (unit or aggregate at PCC) shall have provisions for monitoring DG status, real power, reactive powerWhen required by EPS, accessible, lockable, visible-break isolation device (switch) located between DG and EPS
Isolation Switch Suitable for 70kW DG
31
1547 Abnormal Conditions Response Summary
Voltages outside of table below shall cause DG to cease to energize within clearing timeDetected at PCC or point of DG connection if:
Aggregate DG capacity <= 30kW Interconnect equipment certified to pass non-islanding test Aggregate DG capacity < 50% total local EPS demand AND
export of power prohibited
Voltage Range (% base voltage) Clearing Time (s)
V < 50 0.16
50 <= V < 88 2.00
110 <V < 120 1.00
V >= 120 0.16
32
1547 Abnormal Conditions Response Summary (Continued)
DG <= 30 kW, frequencies shall fall in range of 59.3 to 60.5 Hz else cease to energize within 0.16 secondsDG > 30 kW
cease to energize within 0.16 seconds if >60.5 Hz cease to energize within an adjustable time delay if undervoltage in range of 59.8
to 57 Hz cease to energize within 0.16 seconds if <57.0 Hz
After a disturbance, DG reconnect only if voltage and frequency within rangeInterconnection equipment shall be designed to coordinate with EPS reclosing practices and include ability to delay reconnect up to 5 minutes
33
Power Quality Summary
DG connected to single phase distribution shall not inject DC current >0.5% DG full rating“The DG shall not create objectionable flicker for other customers on the area EPS”DG harmonic injection shall not exceed:
Maximum Harmonic Current Distortion (% of current)
Harmonic Order (h)h<11 11<=h<17 17<=h<23 17<=h<23 35<=h
Percent (%) 4.0 2.0 1.5 0.6 0.3
Total Demand Distortion Maximum = 5.0%
Harmonic
Cu
rren
tD
isto
rtio
n
34
Testing Requirements Summary
Five kinds of test are defined: Design test – certifies that interconnection
equipment meets the standard requirements Production test – factory test of DG’s conformance to
voltage and frequency variation limits Interconnection installation evaluation – basically a
verification that the DG and interconnection design meet the standard
Commissioning test – conducted at the facility to verify adjustable settings are correct and protective functions are operating properly
Periodic interconnection tests – A periodic test of the interconnect protection system
35
Screens – Primary<5% of annual peak load on radial circuits<5% of peak load (or 50kW max) on spot networks (inverters only)Secondary grid distribution networks
induction generator or inverter not exceeding 50% of facility minimum load
<10% contribution to circuit max fault currentNot cause grid protective devices to exceed 90% of their short circuit interrupting capabilityIn aggregate, cannot be >10MW where transient stability limits postedPhase imbalance limits if single-phase and connected to center tap neutral of a 240V service<20kVA if single-phase and on a shared secondary Single-phase connection requirements<10% of line capacity if single phase and section configuration is three-phase, 4-wire or a mix
36
Screens – SecondaryRadial circuits: <15% of line section design capacitySpot networks: <5% of peak load on spot networksSecondary grid networks On any network, use reverse power
protection except: if generator <50% of min facility load or
500kW
Basically same limits on fault current contribution and short circuit interrupting impact as primary screen