Updating the MA DG Interconnection Report

33
Updating the MA DG Interconnection Report DOER analysis of the Utility reporting of DG interconnection projects following the Expedited and Standard Review Processes from January 1, 2009 to May 1, 2012* * This analysis does not include applications submitted before January 2009 or projects following the Simplified Process (<10 kW on single-phase lines and <25 kW on three-phase lines after Jan 2009). The DG Report summarized projects through 2010 and is Presentation to the DG Working Group - May 31, 2012 Gerry Bingham, Senior Coordinator / Distributed Generation

description

Updating the MA DG Interconnection Report. Presentation to the DG Working Group - May 31, 2012 Gerry Bingham, Senior Coordinator / Distributed Generation. - PowerPoint PPT Presentation

Transcript of Updating the MA DG Interconnection Report

Page 1: Updating the MA DG Interconnection Report

Updating the MA DG Interconnection Report

DOER analysis of the Utility reporting of DG interconnection projects following the

Expedited and Standard Review Processes from January 1, 2009 to May 1, 2012*

* This analysis does not include applications submitted before January 2009 or projects following the Simplified Process (<10 kW on single-phase lines and <25 kW on three-phase lines after Jan 2009).

The DG Report summarized projects through 2010 and is available at the MA Interconnection and Distributed Generation Website.

Presentation to the DG Working Group - May 31, 2012

Gerry Bingham, Senior Coordinator / Distributed Generation

Page 2: Updating the MA DG Interconnection Report

Figure 4.22 (2009-May 2012) Applications by Year and Company

(Standard and Expedited)

2009 2010 2011 20120

50

100

150

200

250

300

350

400

450

National GridNSTARWMECoUnitil

Page 3: Updating the MA DG Interconnection Report
Page 4: Updating the MA DG Interconnection Report

Figure 4.1 (2011-April 2012):Capacity of Projects By Size (kW)

EXP '11 STD '11 EXP '12 STD '120

50,000

100,000

150,000

200,000

250,000

300,000

350,000

1000 and >500-<1000100-<50050-<1000-<50

*NOTE: 92 projects (208 MW) have not yet been assigned a process.

Page 5: Updating the MA DG Interconnection Report
Page 6: Updating the MA DG Interconnection Report

Figure 4.2 (2011-April 2012): Number of Applications By Technology

EXP '11 STD '11 EXP '12 STD '120

50

100

150

200

250

300

350

SolarWindNatGasOther

*NOTE: 92 projects (208 MW) have not yet been assigned a process.

Page 7: Updating the MA DG Interconnection Report
Page 8: Updating the MA DG Interconnection Report

Figure 4.3 (2011-April 2012): Capacity of Projects by Technology (kW)

EXP '11 STD '11 EXP '12 STD '120

50,000

100,000

150,000

200,000

250,000

300,000

350,000

SolarWindNatGasOther

Page 9: Updating the MA DG Interconnection Report
Page 10: Updating the MA DG Interconnection Report

Figure 4.8 (2011-April 2012): Percentage of Applications Exceeding

Timeline Specified by Tariff (This tracks only projects that rec’d Agreements in each year)

EXP '11 STD '11 EXP '12 STD '120%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

17%

53%

20%

50%

Page 11: Updating the MA DG Interconnection Report

Review Paths Side-by-Side

11

Page 12: Updating the MA DG Interconnection Report

Expedited and Standard Process Flowchart

12

Customer submits

application

App complete (10 days)

No

Acknowledge w/i 3 days

Initial review and screening

(25 days)

Provide Additional

info

Reviews needed?

Perform Supplemental

(20 days)

All rqmts determine

dPerform Studies

(55 days/30 days)

Send agreement (15 days)

Complete system

modifications

D Facility Modification needed

Customer pays for

modifications

No

No

Yes

Yes

Information Exchange as needed

Customer signs agreement, builds facility, provides insurance, relay test results and test

plan, pays for witness test, etc.

Relay Witness Test

Authorize Interconnect

Yes

None

Provide Additional

info

Information Exchange

as needed

Customer

Utility

Start

Page 13: Updating the MA DG Interconnection Report

Expedited and Standard Process Flowchart

13

Customer submits

application

App complete (10 days)

No

Acknowledge w/i 3 days

Initial review and screening

(25 days)

Provide Additional

info

Reviews needed?

Perform Supplemental

(20 days)

All rqmts determine

dPerform Studies

(55 days/30 days)

Send agreement (15 days)

Complete system

modifications

D Facility Modification needed

Customer pays for

modifications

No

No

Yes

Yes

Information Exchange as needed

Customer signs agreement, builds facility, provides insurance, relay test results and test

plan, pays for witness test, etc.

Relay Witness Test

Authorize Interconnect

Yes

None

Provide Additional

info

Information Exchange

as needed

Customer

Utility

Start

Page 14: Updating the MA DG Interconnection Report

14

Customer submits

application

App complete (10 days)

Send agreement

(60/150 days)

Yes

Authorize Interconnect

Customer

Utility

Start

Page 15: Updating the MA DG Interconnection Report

15

Customer submits

application

App complete (10 days)

Send agreement

(60/150 days)

Yes

Authorize Interconnect

Customer

Utility

Start

2

1

3

4

5

Process Phases Using Existing Reporting

Page 16: Updating the MA DG Interconnection Report

16

Customer

Utility

Page 17: Updating the MA DG Interconnection Report

17

Customer

Utility

Rec’dAgreement

In Study

App. Deemed

Complete

Application Rec’d

Information Exchange

Authorized!

Post-Agreement / Construction

3

4

5

Page 18: Updating the MA DG Interconnection Report

18

Customer

Utility

628MW

In Study

App. Deemed

Complete

Application Rec’d

Projects Stuck at “Application Complete” Calendar Days Lapsed

Page 19: Updating the MA DG Interconnection Report

0 200 400 600 800 1000 1200 14000

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

18,000

20,000

Expedited: 84 calendar days

Projects Stuck at “Application Complete” Calendar Days Lapsed

Days

Size (kW)

563 Projects628 MWNote: There are 37 Projects reported as “0” kW.

Standard: 210 calendar days

Page 20: Updating the MA DG Interconnection Report

20

Customer

Utility

99.5 MW

Rec’dAgreement

In Study

App. Deemed

Complete

Application Rec’d

Projects that Received an Agreement

Page 21: Updating the MA DG Interconnection Report

0 100 200 300 400 500 600 700 8000

200

400

600

800

1,000

1,200

1,400

Expedited Projects – Time Lapsed for Received Agreement

Days

Expedited Review Max Timeline: 84 calendar days(Tariff: 60 business days)

Size (kW)

378 Projects39 MW

Page 22: Updating the MA DG Interconnection Report

0 100 200 300 400 500 600 700 800 900 10000

1,000

2,000

3,000

4,000

5,000

6,000

7,000

Standard Review Projects – Time Lapsed for Received Agreement

Days

Standard Review Max Timeline: 210 calendar days(Tariff: 150 business days)

Size (kW)

59 Projects60.5 MW

Page 23: Updating the MA DG Interconnection Report

23

Customer

Utility

41 MW

Post-Agreement / Construction

Rec’dAgreement

In Study

App. Deemed

Complete

Application Rec’d

Page 24: Updating the MA DG Interconnection Report

Post-Agreement Projects Awaiting Signature/Construction/Approval to Connect

Size (kW)

Days

0 200 400 600 800 1000 12000

1,000

2,000

3,000

4,000

5,000

6,000

7,000

207 Projects41 MW

Timelines for Construction are treated on a project by project basis by utility commitment in the Agreement.

Page 25: Updating the MA DG Interconnection Report

DG Applications Submitted vs. Processed Starting Jan 2009 (Cumulative kW)

1/6/09 11/16/09 3/29/10 8/11/2010 11/30/2010 3/8/11 06/08/2011 8/30/2011 10/20/2011 12/21/11 02/13/2012 4/10/120

200,000

400,000

600,000

800,000

1,000,000

1,200,000

-------- Applied-------- Authorized

Page 26: Updating the MA DG Interconnection Report
Page 27: Updating the MA DG Interconnection Report

Figure 4.23: DG Applications Submitted vs. Processed Each Year (Cumulative kW)

2009 2010 2011 20120

200,000

400,000

600,000

800,000

1,000,000

1,200,000

AppliedAuthorized

Page 28: Updating the MA DG Interconnection Report

NU-NSTAR DG Applications Submitted vs. Processed

Each Year (Cumulative kW)

2009 2010 2011 20120

100,000

200,000

300,000

400,000

500,000

600,000

AppliedAuthorized

  AppliedAuthorized

2009 40,241 3,9452010 147,465 13,2092011 316,272 32,0252012 395,651 43,695

Page 29: Updating the MA DG Interconnection Report

National Grid DG Applications Submitted vs. Processed

Each Year (Cumulative kW)

2009 2010 2011 20120

100,000

200,000

300,000

400,000

500,000

600,000

AppliedAuthorized

  AppliedAuthorized

2009 16,510 2,4172010 79,741 13,5232011383,229 34,5992012502,718 50,960

Page 30: Updating the MA DG Interconnection Report

NU-WMECo DG Applications Submitted vs. Processed

Each Year (Cumulative kW)

2009 2010 2011 20120

100,000

200,000

300,000

400,000

500,000

600,000

AppliedAuthorized

  AppliedAuthorize

d2009 10,492 5552010 16,177 1,3502011 32,750 4,3012012 87,044 8,807

Page 31: Updating the MA DG Interconnection Report

Unitil DG Applications Submitted vs. Processed Each Year (Cumulative kW)

2009 2010 2011 20120

500

1,000

1,500

2,000

2,500

3,000

AppliedAuthorized

 Applie

dAuthorize

d2009 0 02010 139 392011 2,541 5512012 2,541 2,541

Page 32: Updating the MA DG Interconnection Report

Freshness of Complete Applications Awaiting Agreement

<84 Days84-210 Days >210 Days Total

<500kWApps 37 11 10 58

Avg (MW) 0.172 0.087 0.107

MW 6.355 0.958 1.067 8.380

500kW-1MW

Apps 54 23 14 91Avg (MW) 0.902 0.93 0.921

MW 48.691 21.4 12.892 82.983

>1MWApps 29 33 21 83

Avg (MW) 2.754 1.931 2.066

MW 79.859 63.724 43.384 186.967

TotalApps 120 67 45 232

Avg (MW) 1.125 1.284 1.267

MW 135.000 86.000 57.000 278.000

< 84 Days > 210 Days

48.76.4

79.91.0 21.4

63.71.1 12.9

43.4

<500kW 500kW-1MW >1MW <500kW 500kW-1MW >1MW <500kW 500kW-1MW >1MW

Snapshot: November 2011Should DOER update?

Page 33: Updating the MA DG Interconnection Report

< 84 Days > 210 Days

48.7

6.4

79.9

1.0

21.4

63.7

1.1 12.9

43.4

<500kW 500kW-1MW >1MW <500kW 500kW-1MW >1MW <500kW 500kW-1MW >1MW

84-210 Days

Freshness of Complete Applications Awaiting Agreement (distribution by size)

Snapshot: November 2011Should DOER update?