Update on FCPS Construction/Renovation Projects
April 2009
April 2009
Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects
General Contractor: D.W. Wilburn, Inc.
Substantial Completion Date: August, 2010 Contract Sum: $9,061,000
Change Orders to Date: $0
Current Phase: 1 (On Schedule)
April 2009
Cassidy Elementary – RenovationRendering of Final Façade
April 2009
Cassidy Elementary – RenovationWork Completed in Last 30 Days:
GC Construction Office located on sitePerimeter fencing in placeBarriers erected to separate demolition and construction activities from
school operationsMusic room and stage structure demolished
Current Work Effort (April):New parking lot will be cut and temp stone placed for construction parking
and stagingFoundations will begin to be pouredPlumbing and Electrical rough-ins below slab on grade to start
Other Notes of Interest:Safety Committee created consisting of staff and parents working in
conjunction with Risk Management & Safety
April 2009
Cassidy Elementary – RenovationNew 2-Story Admin. Addition Site Existing Music Room/Stage Demo
April 2009
Interior Classroom Demo Interior Classroom Demo
Russell Cave Elementary – Renovation
Architect: Pearson & Peters Architects
General Contractor: Congleton-Hacker Construction
Substantial Completion Date: August, 2010
Contract Sum: $5,001,150
Change Orders to Date: $0
Current Phase: 1
April 2009
Russell Cave Elementary – RenovationRendering of Final Façade
April 2009
Russell Cave Elementary – RenovationWork Completed in Last 30 Days:
GC staging area and construction site fencedDemolition of library buildingPortable classrooms installed
Current Work Effort (April):Excavation and geotechnical work to begin
April 2009
Russell Cave Elementary – RenovationSite Work 4/7/09 Site Work 4/7/09
April 2009
Arlington Elementary – Renovation
Architect: RossTarrant Architects
General Contractor: TBD
Substantial Completion Date: August, 2010
Contract Sum: TBD
Change Orders: $36,900 (#1--Demo)
Current Phase: Demolition Complete
April 2009
Arlington Elementary – RenovationRendering of Final Façade
April 2009
Arlington Elementary – RenovationWork Completed in Last 30 Days:
Demolition completedWork at Site to begin in May
April 2009
Arlington Elementary – RenovationDemo – Main Bldg. Demo – Main Bldg.
April 2009
Demo – Gym Demo – Gym
Bryan Station Middle – Renovation
Architect: Clotfelter-Samokar Architects
General Contractor: Preston Construction Group
Substantial Completion Date: August, 2010
Contract Sum: $10,769,400
Change Orders to Date: $0
Current Phase: Phase 1 to begin June 1
April 2009
Bryan Station Middle – RenovationRendering of Final Façade
April 2009
Bryan Station Middle – RenovationWork Completed in Last 30 Days:
GC conducting preparatory activitiesWork at Site to Begin June 1
April 2009
Leestown Middle – Renovation
Architect: Lucas/Schwering Architects
General Contractor: D.W. Wilburn, Inc.
Substantial Completion Date: August, 2010
Contract Sum: $11,182,000
Change Orders to Date: $0
Current Phase: Phase 1a, 1b, 1c to begin June 1
April 2009
Leestown Middle – RenovationRendering of Final Façade
April 2009
Leestown Middle – RenovationWork Completed in Last 30 Days:
GC conducting preparatory activitiesWork at Site to Begin June 1
April 2009
Lafayette High Stadium – Replacement
Architect: Strand & Associates
General Contractor: Set to bid mid-June
Substantial Completion Date: July, 2010
Contract Sum: TBD
Change Orders to Date: $0
Current Phase: Construction Documents
April 2009
Lafayette High Stadium – Replacement
UPDATED Site Plan of Stadium
April 2009
Central Bus Garage – Adaptive Reuse
Architect: Lucas/Schwering Architects
General Contractor: James R. Leake & Sons, Inc.
Substantial Completion Date: August, 2009
Contract Sum: $2,782,000
Change Orders to Date: $0
Current Phase: Construction
April 2009
Central Bus Garage – Adaptive ReuseFaçade
April 2009
Central Bus Garage – Adaptive ReuseProposed Floor Plan
April 2009
Tonight’s Agenda ItemsProject Agenda Item
Central Bus Garage Approval of Bid, Revised BG-1 & GC Contract James R. Leake & Sons: $2,782,000 Total Project Cost: $5,672,810
Leestown Middle Approval of Bid, Revised BG-1 & GC Contract D.W. Wilburn, Inc.: $11,182,000 Total Project Cost: $13,682,854
New Elementary @ Keithshire
Approval of BG-1 Total Estimated Cost: $17,137,625
Veterans Park Roof Replacement
Approval of BG-1, Construction Documents & Advertise for Bids Total Estimated Cost: $1,422,400
Sandersville Elementary Approval of Change Order # 3 Total Credit for Unused DPOs:
($15,167.67)
April 2009