Update on FCPS Construction/Renovation Projects
September 2009
September 2009
Cassidy Elementary – Renovation
Architect: Tate.Hill.Jacobs: Architects
General Contractor: D.W. Wilburn, Inc.
Substantial Completion Date: August, 2010
GC Contract Sum: $9,061,000
Total Project Cost: $11,067,360
Change Orders to Date (1): $3,152
Current Phase: 1 (On Schedule)
Estimated Completion: 34%
September 2009
Cassidy Elementary – RenovationRendering of Final Façade
September 2009
Cassidy Elementary – RenovationWork Completed in Last 30 Days:Concrete seating walls complete at playground and mulch in place.Storm sewers at rear of building complete.Morton parking lot extension complete.Second floor joist and slab structure complete at new additions.Masonry load bearing walls complete on Admin Addition. Brick Veneer complete on rear addition.Mechanical and electrical work rough-ins continue in new additions.
September 2009
Cassidy Elementary – RenovationCurrent Work Effort (September):Storm sewer and underground detention system to complete.Stage floor to be poured and masonry load bearing walls installed.Roof joists and deck to be installed. Roofing finish to start before end of month.Interior metal framing to begin in enclosed areas.Elevator installation to be complete by end of month.Sprinkler rough-ins to begin.Rooftop mechanical units to be installed.Electric transformer to be installed.
September 2009
Cassidy Elementary – RenovationNew Admin. Addition New Classroom Wing Corridor 2nd Fl
September 2009
New Media Center from 2nd Fl. New Stage Addition
Russell Cave Elementary – Renovation
Architect: Pearson & Peters Architects
General Contractor: Congleton-Hacker Construction
Substantial Completion Date: August, 2010
GC Contract Sum: $5,001,150
Total Project Cost: $6,103,400
Change Orders to Date (2): $11,180
Current Phase: 1 (On Schedule)
Estimated Completion: 42%
September 2009
Russell Cave Elementary – RenovationRendering of Final Façade
September 2009
Russell Cave Elementary – RenovationWork Completed in Last 30 Days:Roof at new addition is complete and the addition is dried in.Renovation of (4) classrooms on the south side continues, demolition is complete, new mechanical and electrical rough-in is in process.Stone veneer on addition base is in process.New windows have been installed at (4) classroom renovation.
Current Work Effort (September):Interior ramp and stair in new addition will be poured.New horizontal blinds will be installed in cafeteria.Framing for knee walls at new windows and soffits in renovated classrooms will be installed.Block filler and painting will begin. New floor material will be delivered the first week of SeptemberDemolition of the general construction items will begin in the gymnasium.
September 2009
Russell Cave Elementary – RenovationNew Classroom Windows New Media Center
September 2009
New KitchenInterior of Cafeteria
Arlington Elementary – Renovation
Architect: RossTarrant Architects
General Contractor: WS Construction
Substantial Completion Date: August, 2010
GC Contract Sum: $9,920,194
Total Project Cost: $12,450,800
Change Orders: $36,900 (#1--Demo)
Current Phase: 1 (On Schedule)
Estimated Completion: 17%
September 2009
Arlington Elementary – RenovationRendering of Final Façade
September 2009
Arlington Elementary – RenovationWork Completed in Last 30 Days:Mock up of exterior wall materials has been completed.Water detention system is in place.Joists have been set in the gymnasium and the slab is scheduled to be poured on 9/16.CMU walls continue in the kitchen.
Current Work Effort (September):Demolition is almost complete.The shoring of the existing structure is in place and reconstruction of the bearing wall between existing and new construction has begun.Mechanical, electrical and plumbing work continues on site and in the existing building.Foundations continue at the main entry and in the media center.
September 2009
Arlington Elementary – RenovationWater Detention System New Walls for Kitchen
September 2009
Bearing Wall Between Old & New Construction
Mechanical, Electrical Plumbing Work
Bryan Station Middle – Renovation
Architect: Clotfelter-Samokar Architects
General Contractor: Preston Construction Group
Substantial Completion Date: August, 2010
GC Contract Sum: $10,769,400
Total Project Cost: $13,345,600
Change Orders to Date (1): $9,118
Current Phase: 1A (On Schedule)
Estimated Completion: 39%
September 2009
Bryan Station Middle – RenovationRendering of Final Façade
September 2009
Bryan Station Middle – RenovationWork Completed in Last 30 Days:Renovated Cafeteria now being used. Media Center Renovation nearing “finishes” stage. Science Room renovation work in progress. New Music Suite Addition progressing well.
Current Work Effort (September):Science and Computer room renovation to progress rapidly to meet November 1 scheduled substantial completion date. This also includes kitchen and Media Center.New addition to progress to the point where roof joist can begin installation.HVAC preparations to be made for switchover in phasing.Site-work to develop so that bus lane can be reinstalled.
September 2009
Bryan Station Middle – RenovationRenovated Cafeteria Media Center
September 2009
Science Room Renovation New Music Suite Addition
Leestown Middle – Renovation
Architect: Lucas/Schwering Architects
General Contractor: D.W. Wilburn, Inc.
Substantial Completion Date: August, 2010
GC Contract Sum: $11,182,000
Total Project Cost: $13,682,854
Change Orders to Date (1): $2,874
Current Phase: 1, 1a, 1b (On Schedule)
Estimated Completion: 24%
September 2009
Leestown Middle – RenovationRendering of Final Façade
September 2009
Leestown Middle – RenovationWork Completed in Last 30 Days:Phase 1 A, B & C demolition efforts on-going. Phase 1B Asbestos abatement on-going.Phase 1 A, B & C hollow metal door frames.Phase 1 A & B interior masonry wall erection on-going.Phase 1 A & B interior masonry in-fill & patch work started.Phase 1 A, B & C Erection of Structural steel started.Phase 1 A, B & C setting of bar joists started.Court yard seating walls and concrete paving are on-going.Foundations for the courtyard addition are on-going.Metal stud walls in Administration Suite are complete.Cafeteria soffits are on-going.Above ceiling ductwork has started in the Cafeteria.
September 2009
Leestown Middle – RenovationCurrent Work Effort (September):General demolition in Phases 1A, B & C will continue.Plumbing, HVAC, electrical demolition on-going.Structural steel and bar joists will continue to be erectedMetal roof decking to start.Electrical and Plumbing rough-ins on-going.Masonry load bearing masonry at Kitchen to be completed.Phase 1C (Courtyard addition) foundation to be completed.Phase 1C slab to start.Erection of two story Fire Wall to begin.Installation of hollow metal door frames on-going in Phase 1B & C.Phase 1A & B, Work at existing built-up roofs to start.Installation of new built-up roof at Phase C.
September 2009
Leestown Middle – RenovationNew Addition at Kitchen Steel Erection at Courtyard Addition
September 2009
Seating Wall at Courtyard
New Addition Kitchen Serving Line
Lafayette High Stadium – Replacement
Architect: Strand & Associates
General Contractor: Judy Construction Co.
Substantial Completion Date: Fall 2010
GC Contract Sum: $4,333,000
Total Project Cost: $4,899,578
Change Orders to Date: $0
Current Phase: Phase 1
September 2009
Lafayette High Stadium – Replacement
Existing Campus
September 2009
Lafayette High Stadium – Replacement
Existing Football Stadium
September 2009
Lafayette High Stadium – Replacement
New Football Stadium
September 2009
Central Bus Garage – Adaptive Reuse
Architect: Lucas/Schwering Architects
General Contractor: James R. Leake & Sons, Inc.
Substantial Completion Date: August, 2009
GC Contract Sum: $2,782,000
Total Project Cost: $5,672,810
Change Orders to Date (3): $31,275
Current Phase: Construction
Estimated Completion: 72%
September 2009
Central Bus Garage – Adaptive ReuseFaçade
September 2009
Central Bus Garage – Adaptive ReuseWork Completed in Last 30 Days:All new shop equipment has been delivered with lifts, hose reels, exhaust system and work tables installed.Paving for car parking has been completed. Striping is complete.Installation of plant material and sod is proceeding.Exterior overhead sectional doors have been installedAll masonry is complete90% of overhead electric completePainting is proceeding.Installation of floor tile and carpet in the administration area is proceeding.Ceramic wall tile is proceeding in the toilet areas.Mechanical work is proceeding.Installation of electrical devices is proceeding.
September 2009
Central Bus Garage – Adaptive ReuseCurrent Work Effort (September):Complete installation of all plant material.Complete administration area and prepare punch list September 23rd.Owner to start floor waxing floors and move in at the administration area September 25th.Parking lot light poles to be installed.Installation of interior doors and hardware proceedingContinue work on the shop area.
September 2009
Central Bus Garage – Adaptive Reuse
September 2009
Service Equipment and Lifts at Shop area Administration Area
Ceramic Wall Tile at Toilet Rooms
Plant Material at Car Parking Lot
Tonight’s Agenda ItemsProject Agenda Item
Clays Mill Elem. (Renovation)
Approval of Schematic Design Documents
Yates Elem. (Renovation) Approval of Schematic Design Documents
Tates Creek Middle (Renovation)
Approval of Schematic Design Documents Approval of Survey for Tates Creek Campus
Total Cost: $29,400.00
Veterans Park Elem. (Roof Repair)
Approval of Change Order #1 Total Cost: $9,151.70
Cassidy Elem. (Renovation) Approval of Change Order #2 Total Cost: $8,386.58
Bryan Station Middle (Renovation)
Approval of Change Order #2 Total Cost: $3,526.34
Approval of Change Order #3 Total Cost: $30,273.66
Russell Cave Elem. (Renovation)
Approval of Change Order #3 Total Cost: $6,057.82
Miles Point Way (Bus Garage)
Approval of Change Order #4 Total Cost: ($3,421.25)