Update on FCPS Construction/Renovation Projects July 2020

Transcript of Update on FCPS Construction/Renovation Projects...450 Park Place – Central Office Current Work...

Page 1: Update on FCPS Construction/Renovation Projects...450 Park Place – Central Office Current Work Effort (July): Continue installation of new casework in main lobby. Install chiller

Update on FCPSConstruction/Renovation Projects

July 2020

Page 2: Update on FCPS Construction/Renovation Projects...450 Park Place – Central Office Current Work Effort (July): Continue installation of new casework in main lobby. Install chiller

STEAM & Success Academies Architect: Ross Tarrant Architects

General Contractor: D.W. Wilburn, Inc.

GC Contract Sum: $22,108,500.00

Total Project Cost: $26,990,125.53

Change Orders to Date (9): $443,225.00

Scheduled Contract Completion Date: October 15, 2020

% of Contract Completed: 76.67%

Revised Completion Date per GC: August 7, 2020(District will begin moving in)

July 2020

Page 3: Update on FCPS Construction/Renovation Projects...450 Park Place – Central Office Current Work Effort (July): Continue installation of new casework in main lobby. Install chiller

STEAM & Success AcademiesSchematic Rendering of Front Façade

July 2020

Page 4: Update on FCPS Construction/Renovation Projects...450 Park Place – Central Office Current Work Effort (July): Continue installation of new casework in main lobby. Install chiller

STEAM & Success Academies Work Completed (June):

Curb and gutter continued to 85% completion. Sidewalks and loading dock concrete continued. DGA and asphalt continued.

Structural steel is complete inside the building and began for the canopies. Roofing installation continued. Prep work for GFRC siding locations began. Window installation continued. Door frame installation continued. Aluminum canopy installation is near completion.

Terrazzo flooring continued on the second floor to 75% complete. Ceiling tile and grid continued, and above-ceiling punch lists were completed by the design team in Areas B & C. Locker installation is complete. Tile installation is nearly complete.

Metal stud wall framing continued at the front entrance. Gypsum board finishing is near completion. Painting continued in all areas. Gym floor logos painting was completed.

Kitchen equipment is onsite, hookups started. Ductwork, HVAC pipingwere completed and grilles and diffusers continued. Plumbing fixture installation began. Electrical above-ceiling rough-ins continued. Light fixture installation continued. Sprinkler trim-outs continued.

EIFS recoating completed.

July 2020

Page 5: Update on FCPS Construction/Renovation Projects...450 Park Place – Central Office Current Work Effort (July): Continue installation of new casework in main lobby. Install chiller

STEAM & Success Academies Current Work Effort (July):

All site concrete to be completed. Heavy-duty asphalt installation to be completed.

Canopy steel to be completed. Roofing to be completed. GFRC siding to be completed. Window, Door and aluminum canopy installation to be completed. Custom canopy installation to continue.

Terrazzo flooring and ceramic tile installation to be completed. Ceiling tile and grid to continue. LVT flooring installation to be completed in Area B and move to the Commons areas.

Metal stud framing and gypsum board to be completed. Painting to continue. Corner guard installation to be completed. Laminate casework installation to begin on the first floor.

Kitchen equipment start-up and testing to begin. HVAC grilles and diffusers to continue. Plumbing fixture installation to continue. Light fixture installation to continue. Sprinkler trim-outs to continue.

July 2020

Page 6: Update on FCPS Construction/Renovation Projects...450 Park Place – Central Office Current Work Effort (July): Continue installation of new casework in main lobby. Install chiller

STEAM & Success Academies

July 2020

Success Academy Canopy 2nd Fl. Terrazzo - Commons Area

Bus Canopy at Cafeteria EIFS Coating

Page 7: Update on FCPS Construction/Renovation Projects...450 Park Place – Central Office Current Work Effort (July): Continue installation of new casework in main lobby. Install chiller

STEAM & Success Academies

July 2020

STEAM Entrance Gym Floor Logo

LVT Flooring Multipurpose Space

Page 8: Update on FCPS Construction/Renovation Projects...450 Park Place – Central Office Current Work Effort (July): Continue installation of new casework in main lobby. Install chiller

450 Park Place – Central Office Engineer: Staggs & Fischer Engineers

General Contractor: Marrillia Design & Construction

GC Contract Sum: $5,112,848.00

Total Project Cost: $6,817,686.00

Change Orders to Date (9): $175,944.00

Scheduled Contract Completion Date: September 21, 2020

% of Contract Completed: 52%

Revised Completion Date per GC: No Change

July 2020

Page 9: Update on FCPS Construction/Renovation Projects...450 Park Place – Central Office Current Work Effort (July): Continue installation of new casework in main lobby. Install chiller

450 Park Place – Central OfficeFront Façade

July 2020

Page 10: Update on FCPS Construction/Renovation Projects...450 Park Place – Central Office Current Work Effort (July): Continue installation of new casework in main lobby. Install chiller

450 Park Place – Central Office Work Completed (June):

Fourth floor ceiling grid is 95% complete. Third floor grid is complete. Second floor is 90% complete.

Started laying carpet tiles in rooms following ceiling grids. TV studio is complete.

Adjusting sprinklers to fit into new ceiling grids.

Primer paint coat has been applied on all walls.

95% complete with gas piping to boilers. Water to boilers is nearing tie-in (90% complete).

Working to bring chilled water into building to chillers.

Received electrical equipment. Shut down scheduled for this Saturday to take 208V system offline and connect to new transformer and cabinet.

Water vault and PIV is set and tied in at road. Working this week to tie-in domestic water and sprinkler water to building.

Working on tile walls/floors in restrooms.

Casework starting in main lobby.

Duct work mostly complete on first floor. Starting hydronic piping on first floor.

July 2020

Page 11: Update on FCPS Construction/Renovation Projects...450 Park Place – Central Office Current Work Effort (July): Continue installation of new casework in main lobby. Install chiller

450 Park Place – Central Office Current Work Effort (July):

Continue installation of new casework in main lobby.

Install chiller and remove Lexmark chilled water piping.

Finish work on second and third floors and schedule punch list observations.

Continue hydronic piping.

Continue installation of ceiling grid and light fixtures on fourth floor.

Continue MEP installations in ceiling grids.

Continue drywall installation on first floor.

July 2020

Page 12: Update on FCPS Construction/Renovation Projects...450 Park Place – Central Office Current Work Effort (July): Continue installation of new casework in main lobby. Install chiller

450 Park Place – Central Office

July 2020

New Chilled Water Pump New Large Meeting Rm.

New Plumbing Fixtures Theatrical Pipe Grid in TV Studio

Page 13: Update on FCPS Construction/Renovation Projects...450 Park Place – Central Office Current Work Effort (July): Continue installation of new casework in main lobby. Install chiller

450 Park Place – Central Office

July 2020

Ceiling Grid & Light Fixtures New Carpet in Office

New Carpet in TV Studio New Carpet

Page 14: Update on FCPS Construction/Renovation Projects...450 Park Place – Central Office Current Work Effort (July): Continue installation of new casework in main lobby. Install chiller

Security Vestibules (28 Sites) Architects: Sherman Carter Barnhart Architects

Ross Tarrant ArchitectsJRA Architects

General Contractor: E.C. Matthews Co., Inc.

GC Contracts Sum: $4,227,000.00

Total Projects Cost: $4,776,624.00

Change Orders to Date (13): $45,888.20

Scheduled Contract Completion Date: December 2020

Revised Completion Date per GC: No Change

July 2020

Page 15: Update on FCPS Construction/Renovation Projects...450 Park Place – Central Office Current Work Effort (July): Continue installation of new casework in main lobby. Install chiller

Security Vestibules (28 Sites) General Overview:

Construction Ongoing: Ashland Elementary (50%) Harrison Elementary, includes vestibule and clinic (98%) Henry Clay High (50%) Maxwell Elementary (10%) Paul Laurence Dunbar High (10%)

Pre-construction Meetings Held & Construction to Start: Beaumont Middle (August 10) Southern Middle (August 24)

Pre-construction Meetings Scheduled: Eastside Technical Center MLK Academy

Construction Complete: 14 Sites

July 2020

Page 16: Update on FCPS Construction/Renovation Projects...450 Park Place – Central Office Current Work Effort (July): Continue installation of new casework in main lobby. Install chiller

Security Vestibules (28 Sites) Work Completed (June):

Ashland Elementary Demolition is 95% complete.

Hollow metal frames are set, and first coat of paint applied.

Drywall is complete.

Security hardware switch over is complete.

Week of 7/20: Extend ductwork, door and hardware installation, paint, and VCT/walk-off carpet to be completed.

Casework installation to begin on 8/10.

Harrison Elementary (Includes Clinic)

Vestibule -- Architectural and interiors punch list was completed by the architect. Contractor has two outstanding items to correct from the punch list.

Clinic -- Architectural and interiors punch list was completed by the architect. Contractor has two outstanding items to correct from the punch list.

July 2020

Page 17: Update on FCPS Construction/Renovation Projects...450 Park Place – Central Office Current Work Effort (July): Continue installation of new casework in main lobby. Install chiller

Security Vestibules (28 Sites) Work Completed (June):

Henry Clay High

CMU walls of the two additions is laid to roof structure bearing height.

Structural steel columns, beams and roof joists have been set.

Structural steel will be inspected prior to the completion of the CMU walls, the metal deck, and the roof installation.

Testing results of the concrete cylinders taken last month exceeded he required structural strength for the new slabs.

Maxwell Elementary

Construction began 7/20.

Paul Laurence Dunbar High

Construction began 7/20.

July 2020

Page 18: Update on FCPS Construction/Renovation Projects...450 Park Place – Central Office Current Work Effort (July): Continue installation of new casework in main lobby. Install chiller

Security Vestibules (28 Sites)

July 2020

Demo Complete Hollow Metal Frames

ASHLAND ELEMENTARY

Page 19: Update on FCPS Construction/Renovation Projects...450 Park Place – Central Office Current Work Effort (July): Continue installation of new casework in main lobby. Install chiller

Security Vestibules (28 Sites)

July 2020

Vestibule & New Reception Area New Clinic Exam Room

HARRISON ELEMENTARY

Page 20: Update on FCPS Construction/Renovation Projects...450 Park Place – Central Office Current Work Effort (July): Continue installation of new casework in main lobby. Install chiller

Security Vestibules (28 Sites)

July 2020

New CMU Walls of the Addition New Steel Column

HENRY CLAY HIGH

Page 21: Update on FCPS Construction/Renovation Projects...450 Park Place – Central Office Current Work Effort (July): Continue installation of new casework in main lobby. Install chiller

Tates Creek High -- New Construction Architect: Tate Hill Jacobs Architects

General Contractor: D.W. Wilburn, Inc.

GC Contract Sum: $70,971,000.00

Total Project Cost: $84,570,295.16

Change Orders to Date (0): $0

Scheduled Contract Completion Date: July 2022 (Building) November 2022 (Site)

% of Contract Completed: 3.24%

Revised Completion Date per GC: No Change

July 2020

Page 22: Update on FCPS Construction/Renovation Projects...450 Park Place – Central Office Current Work Effort (July): Continue installation of new casework in main lobby. Install chiller

Tates Creek High -- New Construction3D Rendering

July 2020

Page 23: Update on FCPS Construction/Renovation Projects...450 Park Place – Central Office Current Work Effort (July): Continue installation of new casework in main lobby. Install chiller

Tates Creek High -- New Construction Work Completed (June):

Mass excavation and demolition at the existing baseball field is ongoing and excavation and fill at the new softball field has begun.

Mass excavation has occurred in Areas A, E and F at the basement level and Area B lower level has been brought up to rough grade.

The existing chiller has been relocated and restarted.

Footings are complete and concrete walls have begun in Area A.

Caissons are being drilled in Area A.

July 2020

Page 24: Update on FCPS Construction/Renovation Projects...450 Park Place – Central Office Current Work Effort (July): Continue installation of new casework in main lobby. Install chiller

Tates Creek High -- New Construction Current Work Effort (July):

Continue caisson drilling in Area A and begin caissons in Areas E and F.

Continue concrete footings in Areas E and F.

Continue mass excavation in Area E lower level.

Begin ICF (insulated concrete form) walls in Area A.

Begin geothermal well drilling on the north side of the site.

July 2020

Page 25: Update on FCPS Construction/Renovation Projects...450 Park Place – Central Office Current Work Effort (July): Continue installation of new casework in main lobby. Install chiller

Tates Creek High -- New Construction

July 2020

Excavation at Baseball Field Excavation - Area A

Site Fill - Areas A & B Footings - Area A

Page 26: Update on FCPS Construction/Renovation Projects...450 Park Place – Central Office Current Work Effort (July): Continue installation of new casework in main lobby. Install chiller

Tates Creek High -- New Construction

July 2020

Forming Concrete – Area A Rebar for Caissons

Excavation – Area E Caisson Drilling – Area A