Update on FCPS Construction/Renovation Projects
March 2009
March 2009

Cassidy Elementary – Renovation
Architect: Tate.Hill.Jacobs: Architects
General Contractor: D.W. Wilburn, Inc.
Substantial Completion Date: August, 2010
Contract Sum: $11,069,360
Change Orders to Date: $0
Current Phase: 1
March 2009

Cassidy Elementary – RenovationRendering of Final Façade
March 2009

Cassidy Elementary – RenovationMarch 4 •Pre-construction meeting held at school with
Owner, A/E Team and construction personnelMarch 9 •Begin on-site staging with setting of office
trailer and fencing by GCMarch 16 •Site demolition in area of new addition,
including removal of existing portable classroom and location of utilities
•Movement of 4 classrooms to portablesMarch 23 •Earth excavation for foundation systems of
new addition•Prepare gym stage area for demolition
March 30 •Demolition of gym stage area over spring break
March 2009

Cassidy Elementary – RenovationAbatement Issues
Asbestos – abatement will begin spring break and continue throughout course of project, as neededLead – no abatement activities at this time but will be addressed
throughout course of project, as neededInformation will be sent this week providing parents of younger children with information pertaining to lead abatement
ALL abatement work will be conducted when students are NOT present in the building
March 2009

Cassidy Elementary – RenovationStaging Area View to Portables
March 2009
View from Portables
Demo Work

Russell Cave Elementary – Renovation
Architect: Pearson & Peters Architects
General Contractor: Congleton-Hacker Construction
Substantial Completion Date: August, 2010
Contract Sum: $5,001,150
Change Orders to Date: $0
Current Phase: 1
March 2009

Russell Cave Elementary – RenovationRendering of Final Façade
March 2009

Arlington Elementary – Renovation
Architect: RossTarrant Architects
General Contractor: Set to bid on April 21
Substantial Completion Date: August, 2010
Contract Sum: TBD
Change Orders Pending: $36,900 (#1)
Current Phase: Demolition
March 2009

Arlington Elementary – RenovationRendering of Final Façade
March 2009

Arlington Elementary – RenovationFebruary 2 •Phase ‘A’ demolition begins at Arlington Elementary School
siteMarch 4 •Phase ‘A’ progress meeting – high water table is
documented, demolition scope is 75% complete•Excavation of debris continues
March 10 •Demolition of gymnasium is submitted as a change order and pricing approved
March 13 •Gymnasium is taken down and on-site refuse continues to be excavated
March 30 •Phase ‘B’ plans to advertise for bid. Phase ‘B’ includes the remainder of the scope of the addition/renovation project
April 3 •Substantial completion of Phase ‘A’ is set for reviewApril 15 •Final completion of Phase ‘A’. Site turned over to FCPS
until award of Phase ‘B’ contract
March 2009

Arlington Elementary – RenovationDemo – Main Bldg. Demo – Main Bldg.
March 2009
Demo – Gym Demo – Gym

Bryan Station Middle – Renovation
Architect: Clotfelter-Samokar Architects
General Contractor: Preston Construction Group
Substantial Completion Date: August, 2010
Contract Sum: $10,769,400
Change Orders to Date: $0
Current Phase: Phase 1 to begin June 1
March 2009

Bryan Station Middle – RenovationRendering of Final Façade
March 2009

Leestown Middle – Renovation
Architect: Lucas/Schwering Architects
General Contractor: Set to bid on April 9
Substantial Completion Date: August, 2010
Contract Sum: TBD
Change Orders to Date: $0
Current Phase: N/A
March 2009

Leestown Middle – RenovationRendering of Final Façade
March 2009

Lafayette High Stadium – Replacement
Architect: Strand & Associates
General Contractor: Set to bid mid-July
Substantial Completion Date: July, 2010
Contract Sum: TBD
Change Orders to Date: $0
Current Phase: Construction Documents
March 2009

Lafayette High Stadium – Replacement
Rendering of Stadium
March 2009

Central Bus Garage – Adaptive Reuse
Architect: Lucas/Schwering Architects
General Contractor: Set to bid on April 23
Substantial Completion Date: August, 2009
Contract Sum: TBD
Change Orders to Date: $0
Current Phase: Construction Documents
March 2009

Central Bus Garage – Adaptive ReuseFaçade
March 2009

Central Bus Garage – Adaptive ReuseProposed Floor Plan
March 2009

2009 District Facilities Plan
Approved by Kentucky Board of Education
February 2009
March 2009

2009 District Facilities Plan
2009-10 Projects
New Elementary @ Keithshire
Equine/Agriscience Center
Clays Mill Elementary Renovation
Tates Creek Middle Renovation
Yates Elementary Renovation
March 2009

2009 District Facilities Plan
2010-11 Projects
Breckinridge Elementary Renovation
Cardinal Valley Elementary Renovation
Mary Todd Elementary Renovation
Millcreek Elementary Renovation
March 2009

Tonight’s Agenda ItemsProject Agenda Item
Clays Mill Elementary Approval of Design Consultant Clotfelter-Samokar Architects
Yates Elementary Approval of Design Consultant Sherman•Carter•Barnhart Architects
Tates Creek Middle Approval of Design Consultant RossTarrant Architects
Elementary @ Keithshire Approval of Design Consultant GBBN Architects
Equine/Agriscience Center Approval of Design Consultant Tate.Hill.Jacobs: Architects
Arlington Elementary Approval of Change Order #1—Demolition of Gym
$36,900
Central Bus Garage Approval of Construction Documents & Advertisement for Bids $6,039,531
Bryan Station Middle Approval of Bid, Revised BG-1 & GC Contract Preston Construction Group: $10,769,400 Total Project Cost: $13,345,600 March 2009