Update on FCPS Construction/Renovation Projects August 2009.
-
Author
ruben-proby -
Category
Documents
-
view
214 -
download
1
Embed Size (px)
Transcript of Update on FCPS Construction/Renovation Projects August 2009.

Update on FCPS Construction/Renovation Projects
August 2009
August 2009

Cassidy Elementary – Renovation
Architect: Tate.Hill.Jacobs: Architects
General Contractor: D.W. Wilburn, Inc.
Substantial Completion Date: August, 2010 Contract Sum: $9,061,000
Change Orders to Date (1): $2,878.14
Current Phase: 1 (On Schedule)
Estimated Completion: 19%
August 2009

Cassidy Elementary – RenovationRendering of Final Façade
August 2009

Cassidy Elementary – RenovationWork Completed in Last 30 Days:Storm sewers installed on south side and across new front parking lot.Grading complete around new Morton Parking Lot. Concrete curbs and subgrade installed.Grading started at sidewalks and playground. Concrete retaining walls in place.Fire Protection water pit installed at Cassidy Rd. Gas main installed. Sanitary sewer manholes and connector piping installed.Demolition continues with new stage opening and new openings and doorways for corridor extensions. Stairway demolition is approximately 75% complete.Foundations for stage complete.Music Classroom addition foundation, 1st floor slab, 2nd floor joist and slab installed. Masonry bearing walls and steel column/beams complete. Interior masonry partition walls on going. Plumbing rough-ins have continued as masonry walls are installed.Electric conduits and rough-ins continue in Admin Addition above ceiling and in masonry walls as needed.
August 2009

Cassidy Elementary – RenovationCurrent Work Effort (August):Storm sewers will continue as site work allows.New 3” domestic water main service will complete.Site grading will complete around the playground. Sidewalk/paving work will complete at playground area.Chimney demolition to begin the first week of September – pending confirmation that chimney swifts have vacated.Stage concrete slab and masonry bearing walls to be complete. Roof joists for Music Rm. and Stage Addition to be in place.HVAC ducting and piping to start in the Admin. Addition and existing building in Phase 1 area.Sprinkler piping to start in the Admin. Addition and existing building in Phase 1 area.Electric conduit and rough-ins to continue.
August 2009

Cassidy Elementary – RenovationNew Admin. Addition 2nd Fl. New Playground Retaining Walls
August 2009
Interior Gym New Stage & Music Room Addition

Russell Cave Elementary – Renovation
Architect: Pearson & Peters Architects
General Contractor: Congleton-Hacker
Construction
Substantial Completion Date: August, 2010
Contract Sum: $5,001,150
Change Orders to Date (2): $12,098.51
Current Phase: 1 (On Schedule)
Estimated Completion: 30%
August 2009

Russell Cave Elementary – RenovationRendering of Final Façade
August 2009

Russell Cave Elementary – RenovationWork Completed in Last 30 Days:Exterior walls at new addition are complete, block and brick. Interior walls are complete.Roof trusses and metal deck at new addition have been installed.Interior of Kitchen/Cafeteria is complete.Renovation of (4) classrooms on the south side continues.Masonry restoration on the exterior of the original building in process.New electric service for new addition to be complete before school begins.
Current Work Effort (August):Interior ramp and stair in new addition will be poured.Masonry restoration of the east wall will be completed.Roof at new addition will be installed.Install new ductwork in new addition and four classrooms.Install overhead electrical rough-in and temporary power and lights in new addition and four classrooms.Construction fence will be reinstalled around new addition before the start of school.
August 2009

Russell Cave Elementary – RenovationNew Addition New Addition
August 2009
New Serving Line in Kitchen
Interior of Cafeteria

Arlington Elementary – Renovation
Architect: RossTarrant Architects
General Contractor: W/S Construction
Substantial Completion Date: August, 2010
Contract Sum: $9,920,194
Change Orders: $36,900 (#1--Demo)
Current Phase: 1 (On Schedule)
Estimated Completion: 8%
August 2009

Arlington Elementary – RenovationRendering of Final Façade
August 2009

Arlington Elementary – RenovationWork Completed in Last 30 Days:Selective demolition in existing building.Earthwork and Site utilities are ongoing.Building foundations are in place at the gym, kitchen and cafeteria.Relocation of utilities and installation of manhole in Arceme are in progress.Under slab utilities at custodial receiving and Mechanical room are in place.Masonry and hollow metal door frames started on west wall of the gymnasium.
Current Work Effort (August):Demolition of existing masonry at building to remain and construction of replacement wall.Site storm sewer installation.Underground utilities will continue.Masonry wall construction at the addition continues.95% complete with demolition in existing building.Continue utility rough-in at the existing building.Installation of temporary roof at the existing building.
August 2009

Arlington Elementary – RenovationDemolition Work Earthwork & Site Utilities
August 2009
Foundation Work Under Slab Utilities

Bryan Station Middle – Renovation
Architect: Clotfelter-Samokar Architects
General Contractor: Preston Construction Group
Substantial Completion Date: August, 2010
Contract Sum: $10,769,400
Change Orders to Date (1): $8,667
Current Phase: 1A (On Schedule)
Estimated Completion: 29%
August 2009

Bryan Station Middle – RenovationRendering of Final Façade
August 2009

Bryan Station Middle – RenovationWork Completed in Last 30 Days:Cafeteria prepared for student use. Finishes and HVAC completed in this area.Corridors barricaded from construction areas and safe egress signs put in place.New sanitary sewer lines nearly complete.New kitchen and kitchen dock work progressing.
Current Work Effort (August):Installing new HVAC rooftop equipment.Installing footers for new Music Suite addition at rear of building.Concentrate on library renovation for turnover to owner as soon as possible.Repair Wood gym floor.
August 2009

Bryan Station Middle – RenovationFoundations for New Addition Earthwork Prep for New Addition
August 2009
Concrete Poured at New Dock
Café Prior to New Floor

Leestown Middle – Renovation
Architect: Lucas/Schwering Architects
General Contractor: D.W. Wilburn, Inc.
Substantial Completion Date: August, 2010
Contract Sum: $11,182,000
Change Orders to Date (1): $2,732.40
Current Phase: 1, 1a, 1b (On Schedule)
Estimated Completion: 16%
August 2009

Leestown Middle – RenovationRendering of Final Façade
August 2009

Leestown Middle – RenovationWork Completed in Last 30 Days:Phase 1demolition efforts continue.Structural shoring at Cafeteria and in Corridor.Kitchen foundation wall and plumbing rough-in complete.Existing utilities have been tied back in.Interior masonry wall erection started.
Current Work Effort (August):Demolition in Phases 1, 1a & 1b will continue.Floor slab for the new Kitchen will be poured.Electrical and Plumbing rough-ins on-going.Masonry load bearing masonry at Kitchen to start.Erection of new Fire Walls to begin.Masonry restoration has begun.Erection of structural steel to begin.
August 2009

Leestown Middle – RenovationKitchen Plumbing Rough In Demo for New Café Window
August 2009
Admin. Suite Demo Looking From
Courtyard
Demo Admin. Suite

Lafayette High Stadium – Replacement
Architect: Strand & Associates
General Contractor: Judy Construction Co. (proposed) Substantial Completion Date: Fall 2010 (est.)
Contract Sum: $4,333,000 (pending Board approval)
Change Orders to Date: $0
Current Phase: Phase 1
August 2009

Lafayette High Stadium – Replacement
Existing Campus
August 2009

Lafayette High Stadium – Replacement
Existing Football Stadium
August 2009

Lafayette High Stadium – Replacement
New Football Stadium
August 2009

Central Bus Garage – Adaptive Reuse
Architect: Lucas/Schwering Architects
General Contractor: James R. Leake & Sons, Inc.
Substantial Completion Date: August, 2009
Contract Sum: $2,782,000
Change Orders to Date (2): $10,044.51
Current Phase: Construction
Estimated Completion: 51%
August 2009

Central Bus Garage – Adaptive ReuseFaçade
August 2009

Central Bus Garage – Adaptive ReuseWork Completed in Last 30 Days:ExteriorBollards installedLight pole bases have been installedDumpster pad completedExterior plumbing completedGenerator gas line installedWaste management systems in placeFluid storage steel erectedInteriorMezzanine in place and elevated slab pouredUnderslab plumbing in placeSlab under mezzanine has been placedBus lifts poured in placeExcavation complete for trench drains
August 2009

Central Bus Garage – Adaptive ReuseCurrent Work Effort (August):Parking lot to be completedWheel stops at the bus parking to be placedPaint booth to be complete by the 21stInterior MEP continues
August 2009

Central Bus Garage – Adaptive Reuse
August 2009
New Fluid Storage Addition Bus Parking
Equipment Installation

Tonight’s Agenda ItemsProject Agenda Item
Miles Point Way (Bus Garage)
Approval of Change Order #3 Total Cost: $18,977.30
Henry Clay High Girls Softball Field
Approval of Bid, Proposed Contract and Revision to BG-1 Project Application WS Construction: $746,830 Total Project Cost: $898,241.25
August 2009