Update on FCPS Construction/Renovation Projects · 2017-02-15 · W. burli n, Inc. GC Contract Sum:...
Transcript of Update on FCPS Construction/Renovation Projects · 2017-02-15 · W. burli n, Inc. GC Contract Sum:...
Update on FCPS Construction/Renovation Projects
July 2016
Squires Elementary -- Renovation Architect: JRA Architects
General Contractor: D.W. Wilburn, Inc.
GC Contract Sum: $12,166,000
Total Project Cost: $15,207,000
Change Orders to Date (13): $219,052.72
Scheduled Contract Completion Date: July 2016
% of Contract Completed: 91.2%
Revised Completion Date per GC: August 2016
July 2016
Squires Elementary -- Renovation Rendering of Final Façade
July 2016
Squires Elementary -- Renovation Work Completed to Date: Kitchen hood, walk-in cooler/freezer installed (Phase 3).
Ceramic tile completed (Phase 3).
Demolition/removal of bus drop off canopy (Change Order 13).
Bleachers installed (Phase 3).
Brick and limestone band completed at the kitchen (Phase 3).
Current Work Effort (July): Install Kitchen equipment (Phase 3).
Install lower level curtain wall (Change Order 11).
Complete the lower level parking lot (Phase 3).
Complete installation of Gym equipment (Phase 3).
Complete site work and landscaping (Phase 3).
July 2016
Squires Elementary -- Renovation
July 2016
Lower Level Parking Drop-off Canopy
Canopy Concrete Columns Kitchen Equipment
Squires Elementary -- Renovation
July 2016
Café – Acoustical Spray Rubber Flooring
Bleacher Installation Terrazzo – Lower Level
Garrett Morgan Elementary Architect: Moody-Nolan Architects
General Contractor: Griggs Enterprises, Inc.
GC Contract Sum: $14,980,350
Total Project Cost: $19,478,511
Change Orders to Date (11): $117,123.67
Scheduled Contract Completion Date: July 2016
% of Contract Completed: 99%
Revised Completion Date per GC: No Change
July 2016
Garrett Morgan Elementary Rendering of Final Façade
July 2016
Garrett Morgan Elementary Work Completed to Date: Complete Kitchen equipment hook-up.
Complete interior storefronts and glass.
Install blinds & shades.
Install stage equipment.
Install remaining asphalt.
Current Work Effort (July): Complete with final grading.
Install seed, sod, and plants.
Complete pre-school fencing & dumpster.
Complete asphalt.
Complete punch list.
July 2016
Garrett Morgan Elementary
July 2016
Front Elevation Media Center
Entry Mural Mechanical Room
Garrett Morgan Elementary
July 2016
Kitchen Media Ctr.
Typical Classroom Gym
Coventry Oak Elementary Architect: Clotfelter-Samokar Architects
General Contractor: D.W. Wilburn, Inc.
GC Contract Sum: $14,874,000
Total Project Cost: $19,848,291
Change Orders to Date (11): $51,342.32
Scheduled Contract Completion Date: July 2016
% of Contract Completed: 98.0%
Revised Completion Date per GC: No Change
July 2016
Coventry Oak Elementary Rendering of Final Façade
July 2016
Coventry Oak Elementary Work Completed to Date: Mechanical, plumbing will complete, electrical will continue.
Interior drywall, painting, VCT/rubber flooring, ceramic tile, gym wall pads and ceiling grid/pads, doors/hardware will complete.
Rood top units will start-up. Test and Balancing will begin.
Current Work Effort (July): Mechanical, plumbing will complete, electrical will continue.
Landscaping installation will complete.
Painting, VCT/rubber flooring, ceiling grid/pads, doors/hardware will complete.
Roof coping will complete.
Electrical rough-in will complete
Aluminum dock rail will complete.
Rood top units will start-up. Test and Balancing will complete.
Temporary Certificate of Occupancy obtained.
July 2016
Coventry Oak Elementary
July 2016
Front Art Room
Classroom Corridor Front Office
Coventry Oak Elementary
July 2016
Gym Mail Room
Media Ctr. Resource Room
New High at Winchester Road Architect: Tate Hill Jacobs: Architects
General Contractor: D.W. Wilburn, Inc.
GC Contract Sum: $62,044,000
Total Project Cost: $81,511,696
Change Orders to Date (9): $177,128.94
Scheduled Contract Completion Date: July 2017
% of Contract Completed: 49.86%
Revised Completion Date per GC: No Change
July 2016
New High at Winchester Road Schematic Rendering of Final Façade
July 2016
New High at Winchester Road Work Completed to Date: Grading is complete in the west parking lot. Curb/gutter work has started. Work
continued on site utilities. Site concrete has begun at the playing field area. Cafeteria concrete slab has been placed. Concessions building & athletic restroom slabs have been placed and CMU started. CMU has continued at the fieldhouse. Locker glazed CMU base has begun. Brick has continued at Areas A & D.
Steel joist/deck has been completed at the Auditorium. Roofing dry-ins continued in Area D. Metal panels have begun in Area C, B, E4 & E3. Air Barrier has continued in Areas E1 & E2 and begun at the fieldhouse.
Windows have been installed in Areas B & C. Drywall finishing has continued in Area C and hanging has continued in Area B. Block filler has continued in Areas B & E4.
In Area B, 1st floor HVAC rough-ins have been completed, and 1st & 2nd floor hydronic piping has been completed. In Area E3 & E4, HVAC rough-ins are at 80% complete, hydronic piping and plumbing rough-ins are complete. Plumbing and HVAC work continues in areas A, D, E1 & E2. Under slab rough-ins are complete and above grade rough-ins have started at the athletics buildings. Water main installation to main building is at 90% and gas main at 95%, while the sanitary sewer work has continued.
July 2016
New High at Winchester Road Current Work Effort (July): Curb/gutter will continue, grading and spoil removal will continue at the playing
field area. West parking lot DGA will begin. Concrete wall at the loading dock & dugout slabs will be placed. Site concrete will continue at the playing fields. Brick will be completed in Areas A & D.
Stairs will be completed in Area A. Steel will continue in Area E1. Steel joists and decking will start at the fieldhouse. Area D & Auditorium will have roofs dried-in. Standing seam roofing will begin. Metal wall panels will continue in Areas E3 & E4. Air Barrier will continue at Athletics buildings.
Mechanical insulation will be completed in Area B. Second floor plumbing rough-ins will continue and HVAC rough-ins will begin on both floors in Area A. HVAC rough-ins continue in both gyms and mechanical insulation will be completed in Area E3 & E4.
Electrical wall rough-ins and overhead conduit will continue in all areas. Cable tray to continue in Area A & E1. Panel tubs and branch wire to continue. Will start pulling main feeders to electrical closets. Main feed will be pulled after KU sets transformer. Continue with underground site conduits.
July 2016
New High at Winchester Road
July 2016
Area C – Fascia & Gutter Area D – Exterior
Café – Slab & Social Stair Auxiliary Gym
New High at Winchester Road
July 2016
Main Gym Academic Bldg. (back)
Fieldhouse Concessions Bldg.