Update on FCPS Construction/Renovation Projects · 2017-02-15 · W. burli n, Inc. GC Contract Sum:...

22
Update on FCPS Construction/Renovation Projects July 2016

Transcript of Update on FCPS Construction/Renovation Projects · 2017-02-15 · W. burli n, Inc. GC Contract Sum:...

Page 1: Update on FCPS Construction/Renovation Projects · 2017-02-15 · W. burli n, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000 Change Orders to Date (13): $219,052.72

Update on FCPS Construction/Renovation Projects

July 2016

Page 2: Update on FCPS Construction/Renovation Projects · 2017-02-15 · W. burli n, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000 Change Orders to Date (13): $219,052.72

Squires Elementary -- Renovation Architect: JRA Architects

General Contractor: D.W. Wilburn, Inc.

GC Contract Sum: $12,166,000

Total Project Cost: $15,207,000

Change Orders to Date (13): $219,052.72

Scheduled Contract Completion Date: July 2016

% of Contract Completed: 91.2%

Revised Completion Date per GC: August 2016

July 2016

Page 3: Update on FCPS Construction/Renovation Projects · 2017-02-15 · W. burli n, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000 Change Orders to Date (13): $219,052.72

Squires Elementary -- Renovation Rendering of Final Façade

July 2016

Presenter
Presentation Notes
New
Page 4: Update on FCPS Construction/Renovation Projects · 2017-02-15 · W. burli n, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000 Change Orders to Date (13): $219,052.72

Squires Elementary -- Renovation Work Completed to Date: Kitchen hood, walk-in cooler/freezer installed (Phase 3).

Ceramic tile completed (Phase 3).

Demolition/removal of bus drop off canopy (Change Order 13).

Bleachers installed (Phase 3).

Brick and limestone band completed at the kitchen (Phase 3).

Current Work Effort (July): Install Kitchen equipment (Phase 3).

Install lower level curtain wall (Change Order 11).

Complete the lower level parking lot (Phase 3).

Complete installation of Gym equipment (Phase 3).

Complete site work and landscaping (Phase 3).

July 2016

Presenter
Presentation Notes
New information
Page 5: Update on FCPS Construction/Renovation Projects · 2017-02-15 · W. burli n, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000 Change Orders to Date (13): $219,052.72

Squires Elementary -- Renovation

July 2016

Lower Level Parking Drop-off Canopy

Canopy Concrete Columns Kitchen Equipment

Presenter
Presentation Notes
New pictures
Page 6: Update on FCPS Construction/Renovation Projects · 2017-02-15 · W. burli n, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000 Change Orders to Date (13): $219,052.72

Squires Elementary -- Renovation

July 2016

Café – Acoustical Spray Rubber Flooring

Bleacher Installation Terrazzo – Lower Level

Presenter
Presentation Notes
New pictures
Page 7: Update on FCPS Construction/Renovation Projects · 2017-02-15 · W. burli n, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000 Change Orders to Date (13): $219,052.72

Garrett Morgan Elementary Architect: Moody-Nolan Architects

General Contractor: Griggs Enterprises, Inc.

GC Contract Sum: $14,980,350

Total Project Cost: $19,478,511

Change Orders to Date (11): $117,123.67

Scheduled Contract Completion Date: July 2016

% of Contract Completed: 99%

Revised Completion Date per GC: No Change

July 2016

Page 8: Update on FCPS Construction/Renovation Projects · 2017-02-15 · W. burli n, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000 Change Orders to Date (13): $219,052.72

Garrett Morgan Elementary Rendering of Final Façade

July 2016

Presenter
Presentation Notes
New
Page 9: Update on FCPS Construction/Renovation Projects · 2017-02-15 · W. burli n, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000 Change Orders to Date (13): $219,052.72

Garrett Morgan Elementary Work Completed to Date: Complete Kitchen equipment hook-up.

Complete interior storefronts and glass.

Install blinds & shades.

Install stage equipment.

Install remaining asphalt.

Current Work Effort (July): Complete with final grading.

Install seed, sod, and plants.

Complete pre-school fencing & dumpster.

Complete asphalt.

Complete punch list.

July 2016

Presenter
Presentation Notes
New information
Page 10: Update on FCPS Construction/Renovation Projects · 2017-02-15 · W. burli n, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000 Change Orders to Date (13): $219,052.72

Garrett Morgan Elementary

July 2016

Front Elevation Media Center

Entry Mural Mechanical Room

Presenter
Presentation Notes
New pictures
Page 11: Update on FCPS Construction/Renovation Projects · 2017-02-15 · W. burli n, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000 Change Orders to Date (13): $219,052.72

Garrett Morgan Elementary

July 2016

Kitchen Media Ctr.

Typical Classroom Gym

Presenter
Presentation Notes
New pictures
Page 12: Update on FCPS Construction/Renovation Projects · 2017-02-15 · W. burli n, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000 Change Orders to Date (13): $219,052.72

Coventry Oak Elementary Architect: Clotfelter-Samokar Architects

General Contractor: D.W. Wilburn, Inc.

GC Contract Sum: $14,874,000

Total Project Cost: $19,848,291

Change Orders to Date (11): $51,342.32

Scheduled Contract Completion Date: July 2016

% of Contract Completed: 98.0%

Revised Completion Date per GC: No Change

July 2016

Page 13: Update on FCPS Construction/Renovation Projects · 2017-02-15 · W. burli n, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000 Change Orders to Date (13): $219,052.72

Coventry Oak Elementary Rendering of Final Façade

July 2016

Presenter
Presentation Notes
New
Page 14: Update on FCPS Construction/Renovation Projects · 2017-02-15 · W. burli n, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000 Change Orders to Date (13): $219,052.72

Coventry Oak Elementary Work Completed to Date: Mechanical, plumbing will complete, electrical will continue.

Interior drywall, painting, VCT/rubber flooring, ceramic tile, gym wall pads and ceiling grid/pads, doors/hardware will complete.

Rood top units will start-up. Test and Balancing will begin.

Current Work Effort (July): Mechanical, plumbing will complete, electrical will continue.

Landscaping installation will complete.

Painting, VCT/rubber flooring, ceiling grid/pads, doors/hardware will complete.

Roof coping will complete.

Electrical rough-in will complete

Aluminum dock rail will complete.

Rood top units will start-up. Test and Balancing will complete.

Temporary Certificate of Occupancy obtained.

July 2016

Presenter
Presentation Notes
New information
Page 15: Update on FCPS Construction/Renovation Projects · 2017-02-15 · W. burli n, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000 Change Orders to Date (13): $219,052.72

Coventry Oak Elementary

July 2016

Front Art Room

Classroom Corridor Front Office

Presenter
Presentation Notes
New pictures
Page 16: Update on FCPS Construction/Renovation Projects · 2017-02-15 · W. burli n, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000 Change Orders to Date (13): $219,052.72

Coventry Oak Elementary

July 2016

Gym Mail Room

Media Ctr. Resource Room

Presenter
Presentation Notes
New pictures
Page 17: Update on FCPS Construction/Renovation Projects · 2017-02-15 · W. burli n, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000 Change Orders to Date (13): $219,052.72

New High at Winchester Road Architect: Tate Hill Jacobs: Architects

General Contractor: D.W. Wilburn, Inc.

GC Contract Sum: $62,044,000

Total Project Cost: $81,511,696

Change Orders to Date (9): $177,128.94

Scheduled Contract Completion Date: July 2017

% of Contract Completed: 49.86%

Revised Completion Date per GC: No Change

July 2016

Page 18: Update on FCPS Construction/Renovation Projects · 2017-02-15 · W. burli n, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000 Change Orders to Date (13): $219,052.72

New High at Winchester Road Schematic Rendering of Final Façade

July 2016

Presenter
Presentation Notes
New
Page 19: Update on FCPS Construction/Renovation Projects · 2017-02-15 · W. burli n, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000 Change Orders to Date (13): $219,052.72

New High at Winchester Road Work Completed to Date: Grading is complete in the west parking lot. Curb/gutter work has started. Work

continued on site utilities. Site concrete has begun at the playing field area. Cafeteria concrete slab has been placed. Concessions building & athletic restroom slabs have been placed and CMU started. CMU has continued at the fieldhouse. Locker glazed CMU base has begun. Brick has continued at Areas A & D.

Steel joist/deck has been completed at the Auditorium. Roofing dry-ins continued in Area D. Metal panels have begun in Area C, B, E4 & E3. Air Barrier has continued in Areas E1 & E2 and begun at the fieldhouse.

Windows have been installed in Areas B & C. Drywall finishing has continued in Area C and hanging has continued in Area B. Block filler has continued in Areas B & E4.

In Area B, 1st floor HVAC rough-ins have been completed, and 1st & 2nd floor hydronic piping has been completed. In Area E3 & E4, HVAC rough-ins are at 80% complete, hydronic piping and plumbing rough-ins are complete. Plumbing and HVAC work continues in areas A, D, E1 & E2. Under slab rough-ins are complete and above grade rough-ins have started at the athletics buildings. Water main installation to main building is at 90% and gas main at 95%, while the sanitary sewer work has continued.

July 2016

Presenter
Presentation Notes
New information
Page 20: Update on FCPS Construction/Renovation Projects · 2017-02-15 · W. burli n, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000 Change Orders to Date (13): $219,052.72

New High at Winchester Road Current Work Effort (July): Curb/gutter will continue, grading and spoil removal will continue at the playing

field area. West parking lot DGA will begin. Concrete wall at the loading dock & dugout slabs will be placed. Site concrete will continue at the playing fields. Brick will be completed in Areas A & D.

Stairs will be completed in Area A. Steel will continue in Area E1. Steel joists and decking will start at the fieldhouse. Area D & Auditorium will have roofs dried-in. Standing seam roofing will begin. Metal wall panels will continue in Areas E3 & E4. Air Barrier will continue at Athletics buildings.

Mechanical insulation will be completed in Area B. Second floor plumbing rough-ins will continue and HVAC rough-ins will begin on both floors in Area A. HVAC rough-ins continue in both gyms and mechanical insulation will be completed in Area E3 & E4.

Electrical wall rough-ins and overhead conduit will continue in all areas. Cable tray to continue in Area A & E1. Panel tubs and branch wire to continue. Will start pulling main feeders to electrical closets. Main feed will be pulled after KU sets transformer. Continue with underground site conduits.

July 2016

Presenter
Presentation Notes
New information
Page 21: Update on FCPS Construction/Renovation Projects · 2017-02-15 · W. burli n, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000 Change Orders to Date (13): $219,052.72

New High at Winchester Road

July 2016

Area C – Fascia & Gutter Area D – Exterior

Café – Slab & Social Stair Auxiliary Gym

Presenter
Presentation Notes
New pictures
Page 22: Update on FCPS Construction/Renovation Projects · 2017-02-15 · W. burli n, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000 Change Orders to Date (13): $219,052.72

New High at Winchester Road

July 2016

Main Gym Academic Bldg. (back)

Fieldhouse Concessions Bldg.

Presenter
Presentation Notes
New pictures