Update on FCPS Construction/Renovation Projects April 2009.

25
Update on FCPS Construction/Renovation Projects April 2009 April 2009

Transcript of Update on FCPS Construction/Renovation Projects April 2009.

Page 1: Update on FCPS Construction/Renovation Projects April 2009.

Update on FCPS Construction/Renovation Projects

April 2009

April 2009

Page 2: Update on FCPS Construction/Renovation Projects April 2009.

Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects

General Contractor: D.W. Wilburn, Inc.

Substantial Completion Date: August, 2010 Contract Sum: $9,061,000

Change Orders to Date: $0

Current Phase: 1 (On Schedule)

April 2009

Page 3: Update on FCPS Construction/Renovation Projects April 2009.

Cassidy Elementary – RenovationRendering of Final Façade

April 2009

Page 4: Update on FCPS Construction/Renovation Projects April 2009.

Cassidy Elementary – RenovationWork Completed in Last 30 Days:

GC Construction Office located on sitePerimeter fencing in placeBarriers erected to separate demolition and construction activities from

school operationsMusic room and stage structure demolished

Current Work Effort (April):New parking lot will be cut and temp stone placed for construction parking

and stagingFoundations will begin to be pouredPlumbing and Electrical rough-ins below slab on grade to start

Other Notes of Interest:Safety Committee created consisting of staff and parents working in

conjunction with Risk Management & Safety

April 2009

Page 5: Update on FCPS Construction/Renovation Projects April 2009.

Cassidy Elementary – RenovationNew 2-Story Admin. Addition Site Existing Music Room/Stage Demo

April 2009

Interior Classroom Demo Interior Classroom Demo

Page 6: Update on FCPS Construction/Renovation Projects April 2009.

Russell Cave Elementary – Renovation

Architect: Pearson & Peters Architects

General Contractor: Congleton-Hacker Construction

Substantial Completion Date: August, 2010

Contract Sum: $5,001,150

Change Orders to Date: $0

Current Phase: 1

April 2009

Page 7: Update on FCPS Construction/Renovation Projects April 2009.

Russell Cave Elementary – RenovationRendering of Final Façade

April 2009

Page 8: Update on FCPS Construction/Renovation Projects April 2009.

Russell Cave Elementary – RenovationWork Completed in Last 30 Days:

GC staging area and construction site fencedDemolition of library buildingPortable classrooms installed

Current Work Effort (April):Excavation and geotechnical work to begin

April 2009

Page 9: Update on FCPS Construction/Renovation Projects April 2009.

Russell Cave Elementary – RenovationSite Work 4/7/09 Site Work 4/7/09

April 2009

Page 10: Update on FCPS Construction/Renovation Projects April 2009.

Arlington Elementary – Renovation

Architect: RossTarrant Architects

General Contractor: TBD

Substantial Completion Date: August, 2010

Contract Sum: TBD

Change Orders: $36,900 (#1--Demo)

Current Phase: Demolition Complete

April 2009

Page 11: Update on FCPS Construction/Renovation Projects April 2009.

Arlington Elementary – RenovationRendering of Final Façade

April 2009

Page 12: Update on FCPS Construction/Renovation Projects April 2009.

Arlington Elementary – RenovationWork Completed in Last 30 Days:

Demolition completedWork at Site to begin in May

April 2009

Page 13: Update on FCPS Construction/Renovation Projects April 2009.

Arlington Elementary – RenovationDemo – Main Bldg. Demo – Main Bldg.

April 2009

Demo – Gym Demo – Gym

Page 14: Update on FCPS Construction/Renovation Projects April 2009.

Bryan Station Middle – Renovation

Architect: Clotfelter-Samokar Architects

General Contractor: Preston Construction Group

Substantial Completion Date: August, 2010

Contract Sum: $10,769,400

Change Orders to Date: $0

Current Phase: Phase 1 to begin June 1

April 2009

Page 15: Update on FCPS Construction/Renovation Projects April 2009.

Bryan Station Middle – RenovationRendering of Final Façade

April 2009

Page 16: Update on FCPS Construction/Renovation Projects April 2009.

Bryan Station Middle – RenovationWork Completed in Last 30 Days:

GC conducting preparatory activitiesWork at Site to Begin June 1

April 2009

Page 17: Update on FCPS Construction/Renovation Projects April 2009.

Leestown Middle – Renovation

Architect: Lucas/Schwering Architects

General Contractor: D.W. Wilburn, Inc.

Substantial Completion Date: August, 2010

Contract Sum: $11,182,000

Change Orders to Date: $0

Current Phase: Phase 1a, 1b, 1c to begin June 1

April 2009

Page 18: Update on FCPS Construction/Renovation Projects April 2009.

Leestown Middle – RenovationRendering of Final Façade

April 2009

Page 19: Update on FCPS Construction/Renovation Projects April 2009.

Leestown Middle – RenovationWork Completed in Last 30 Days:

GC conducting preparatory activitiesWork at Site to Begin June 1

April 2009

Page 20: Update on FCPS Construction/Renovation Projects April 2009.

Lafayette High Stadium – Replacement

Architect: Strand & Associates

General Contractor: Set to bid mid-June

Substantial Completion Date: July, 2010

Contract Sum: TBD

Change Orders to Date: $0

Current Phase: Construction Documents

April 2009

Page 21: Update on FCPS Construction/Renovation Projects April 2009.

Lafayette High Stadium – Replacement

UPDATED Site Plan of Stadium

April 2009

Page 22: Update on FCPS Construction/Renovation Projects April 2009.

Central Bus Garage – Adaptive Reuse

Architect: Lucas/Schwering Architects

General Contractor: James R. Leake & Sons, Inc.

Substantial Completion Date: August, 2009

Contract Sum: $2,782,000

Change Orders to Date: $0

Current Phase: Construction

April 2009

Page 23: Update on FCPS Construction/Renovation Projects April 2009.

Central Bus Garage – Adaptive ReuseFaçade

April 2009

Page 24: Update on FCPS Construction/Renovation Projects April 2009.

Central Bus Garage – Adaptive ReuseProposed Floor Plan

April 2009

Page 25: Update on FCPS Construction/Renovation Projects April 2009.

Tonight’s Agenda ItemsProject Agenda Item

Central Bus Garage Approval of Bid, Revised BG-1 & GC Contract James R. Leake & Sons: $2,782,000 Total Project Cost: $5,672,810

Leestown Middle Approval of Bid, Revised BG-1 & GC Contract D.W. Wilburn, Inc.: $11,182,000 Total Project Cost: $13,682,854

New Elementary @ Keithshire

Approval of BG-1 Total Estimated Cost: $17,137,625

Veterans Park Roof Replacement

Approval of BG-1, Construction Documents & Advertise for Bids Total Estimated Cost: $1,422,400

Sandersville Elementary Approval of Change Order # 3 Total Credit for Unused DPOs:

($15,167.67)

April 2009