Update on FCPS Construction/Renovation Projects July 2009 July 2009

Transcript of Update on FCPS Construction/Renovation Projects July 2009.

Page 1: Update on FCPS Construction/Renovation Projects July 2009.

Update on FCPS Construction/Renovation Projects

July 2009

July 2009

Page 2: Update on FCPS Construction/Renovation Projects July 2009.

Cassidy Elementary – Renovation

Architect: Tate.Hill.Jacobs: Architects

General Contractor: D.W. Wilburn, Inc.

Substantial Completion Date: August, 2010 Contract Sum: $9,061,000

Change Orders to Date (1): $3,152.42

Current Phase: 1 (On Schedule)

Estimated Completion: 19%

July 2009

Page 3: Update on FCPS Construction/Renovation Projects July 2009.

Cassidy Elementary – RenovationRendering of Final Façade

July 2009

Page 4: Update on FCPS Construction/Renovation Projects July 2009.

Cassidy Elementary – RenovationWork Completed in Last 30 Days:Asphalt removal at Stage Addition complete.Primary electric installed and secondary conduits installed to transformer pad location.Selective interior demolition continuing with removal of walls, ceilings and doors in Phase 1. Mechanical demolition on-going.New Admin. Addition and Music Rm. Addition first floor slab in place.Bearing CMU walls up to first floor height at New Admin. Addition. CMU begun on Music Rm. Addition.Steel columns and beams begun for new Media Center at New Admin. Addition.Door frames installed in new CMU walls at New Admin. Addition.Under-slab plumbing and electrical rough-ins complete in New Admin. and Music Rm. Additions with wall rough-ins continuing with new CMU wall construction. New HVAC delivered to site.

July 2009

Page 5: Update on FCPS Construction/Renovation Projects July 2009.

Cassidy Elementary – RenovationCurrent Work Effort (July):Storm sewer begun along front of building with new underground retention structures starting.Gas main line to begin between Morton M.S. and Cassidy Elem. with completion prior to start of school. Sanitary sewer work begun with completion prior to start of school.Fire Protection/Water Main work started with completion prior to start of school.Morton M.S. parking lot extension to start with completion prior to start of school.Selective demolition of interior areas to continue as needed for Phase 1 work.Concrete foundation and slab for Stage Addition to start with CMU walls following.Coordination Meeting to be held on site 1½ week prior to start of school with contractors, local fire department officials and FCPS staff to review life safety and emergency egress compliance prior to staff/student occupancy.

July 2009

Page 6: Update on FCPS Construction/Renovation Projects July 2009.

Cassidy Elementary – RenovationExisting Gym During Demo New Admin Addition

July 2009

New Stage & Music Room Addition

New Media Center Addition

Page 7: Update on FCPS Construction/Renovation Projects July 2009.

Russell Cave Elementary – Renovation

Architect: Pearson & Peters Architects

General Contractor: Congleton-Hacker

Construction

Substantial Completion Date: August, 2010

Contract Sum: $5,001,150

Change Orders to Date (1): $0

Current Phase: 1 (On Schedule)

Estimated Completion: 16%

July 2009

Page 8: Update on FCPS Construction/Renovation Projects July 2009.

Russell Cave Elementary – RenovationRendering of Final Façade

July 2009

Page 9: Update on FCPS Construction/Renovation Projects July 2009.

Russell Cave Elementary – RenovationWork Completed in Last 30 Days:Exterior concrete block walls are being installed.Interior of Kitchen/Cafeteria has been demolished and renovation has begun.Renovation of (4) classrooms on the south side has begun.Concrete slab at the new addition has been poured.Masonry restoration on the exterior of the original building in process.Existing elevator has been upgraded.

Current Work Effort (July):Roof trusses at the new additional will be set.Kitchen/Cafeteria renovation will be completed.Interior work on the new addition and the (4) classrooms on the south side will continue. They are scheduled to be completed in October.Complete new electrical and mechanical systems in Kitchen/Cafeteria.

July 2009

Page 10: Update on FCPS Construction/Renovation Projects July 2009.

Russell Cave Elementary – RenovationNew Addition New Addition

July 2009

Masonry RestorationInterior of Cafeteria

Page 11: Update on FCPS Construction/Renovation Projects July 2009.

Arlington Elementary – Renovation

Architect: RossTarrant Architects

General Contractor: W/S Construction

Substantial Completion Date: August, 2010

Contract Sum: $9,920,194

Change Orders: $36,900 (#1--Demo)

Current Phase: 1 (On Schedule)

Estimated Completion: Demo – 100%

July 2009

Page 12: Update on FCPS Construction/Renovation Projects July 2009.

Arlington Elementary – RenovationRendering of Final Façade

July 2009

Page 13: Update on FCPS Construction/Renovation Projects July 2009.

Arlington Elementary – RenovationWork Completed in Last 30 Days:Earthwork continuesInterior selective demolition continuesFoundation footers, stem walls and foundation drains are currently being installedSite utilities being brought to the buildingInterior plumbing being installed

Current Work Effort (July):Structural shoring to begin ASAP and subsequent demolition of the remainder of that scope of work to existing to remainMasonry scheduled to begin 7/20

July 2009

Page 14: Update on FCPS Construction/Renovation Projects July 2009.

Arlington Elementary – RenovationEarthwork Continues Interior Selective Demo

July 2009

Foundation Footers Being Installed

Site Utilities to Building

Page 15: Update on FCPS Construction/Renovation Projects July 2009.

Bryan Station Middle – Renovation

Architect: Clotfelter-Samokar Architects

General Contractor: Preston Construction Group

Substantial Completion Date: August, 2010

Contract Sum: $10,769,400

Change Orders to Date: $0

Current Phase: 1A (On Schedule)

Estimated Completion: 14%

July 2009

Page 16: Update on FCPS Construction/Renovation Projects July 2009.

Bryan Station Middle – RenovationRendering of Final Façade

July 2009

Page 17: Update on FCPS Construction/Renovation Projects July 2009.

Bryan Station Middle – RenovationWork Completed in Last 30 Days:Portable classrooms in placeMajority of demolition work in Phase 1 completeConcrete sidewalk and stairs at rear of building complete

Current Work Effort (July):Contractors preparing sub-grade for new addition and revised bus laneExisting storm drains being replaced with newNew sanitary sewer line being installed to replace old, inadequate “pump-station” type sewer systemKitchen/Cafeteria renovation work progressing rapidly to meet deadlinesOwner installing portable restroom units

July 2009

Page 18: Update on FCPS Construction/Renovation Projects July 2009.

Bryan Station Middle – RenovationNew Storm Sewer Drains New Sanitary Sewer Line

July 2009

Kitchen/Café Renovation

Portable Restroom Units

Page 19: Update on FCPS Construction/Renovation Projects July 2009.

Leestown Middle – Renovation

Architect: Lucas/Schwering Architects

General Contractor: D.W. Wilburn, Inc.

Substantial Completion Date: August, 2010

Contract Sum: $11,182,000

Change Orders to Date: $0

Current Phase: 1, 1a, 1b (On Schedule)

Estimated Completion: 12%

July 2009

Page 20: Update on FCPS Construction/Renovation Projects July 2009.

Leestown Middle – RenovationRendering of Final Façade

July 2009

Page 21: Update on FCPS Construction/Renovation Projects July 2009.

Leestown Middle – RenovationWork Completed in Last 30 Days:Phase 1demolition and Asbestos abatement efforts on-going.Phase 1 site demolition completeStructural shoring at Cafeteria and in CorridorKitchen foundation walls pouredDemolition of existing kitchen, front entrance and administration suite are complete

Current Work Effort (July):Interior and exterior demolition in Phases 1, 1a & 1b will continuePlumbing, HVAC, electrical demolition on-goingStructural shoring will continue to be erectedFloor slab for the new Kitchen will be pouredElectrical and Plumbing rough-ins to beginMasonry load bearing and erection of new fire walls to startMasonry restoration has begunErection of structural steel to begin

July 2009

Page 22: Update on FCPS Construction/Renovation Projects July 2009.

Leestown Middle – RenovationFront Entrance Demo Admin Suite Demo

July 2009

Admin Suite Demo Looking From

Courtyard

Existing Kitchen Demo

Page 23: Update on FCPS Construction/Renovation Projects July 2009.

Lafayette High Stadium – Replacement

Architect: Strand & Associates

General Contractor: Venture One Construction

Substantial Completion Date: June, 2010

Contract Sum: $4,100,000

Change Orders to Date: $0

Current Phase: Phase 1 to begin August 1

July 2009

Page 24: Update on FCPS Construction/Renovation Projects July 2009.

Lafayette High Stadium – Replacement

Existing Campus

July 2009

Page 25: Update on FCPS Construction/Renovation Projects July 2009.

Lafayette High Stadium – Replacement

Existing Football Stadium

July 2009

Page 26: Update on FCPS Construction/Renovation Projects July 2009.

Lafayette High Stadium – Replacement

New Football Stadium

July 2009

Page 27: Update on FCPS Construction/Renovation Projects July 2009.

Central Bus Garage – Adaptive Reuse

Architect: Lucas/Schwering Architects

General Contractor: James R. Leake & Sons, Inc.

Substantial Completion Date: August, 2009

Contract Sum: $2,782,000

Change Orders to Date (1): $4,346.17

Current Phase: Construction

Estimated Completion: 27%

July 2009

Page 28: Update on FCPS Construction/Renovation Projects July 2009.

Central Bus Garage – Adaptive ReuseFaçade

July 2009

Page 29: Update on FCPS Construction/Renovation Projects July 2009.

Central Bus Garage – Adaptive ReuseProposed Floor Plan

July 2009

Page 30: Update on FCPS Construction/Renovation Projects July 2009.

Central Bus Garage – Adaptive ReuseWork Completed in Last 30 Days:Rock removal continuesExterior concrete continues to be placed, approximately 95% completeElectric standards in parking lot being installedUnder-slab plumbing installed and being testedShoring in place for lift pits   Bus exhaust evacuation system in place

Current Work Effort (July):Steel erection for mezzanine to start 7/20Concrete placement at mezzanine to occur 7/24Electrical installation continuesInterior concrete slab placement to continueTrench drain installation to commenceNew parking lot water quality units to be installedParking lot curbs to be placed

July 2009

Page 31: Update on FCPS Construction/Renovation Projects July 2009.

Central Bus Garage – Adaptive Reuse

July 2009

Install of Sanitary

Sewer LineUnder-slab Plumbing

Under-slab Plumbing

Foundation Wall

for Bus Lift

Page 32: Update on FCPS Construction/Renovation Projects July 2009.

Tonight’s Agenda ItemsProject Agenda Item

Cassidy Elementary Approval of Third-Party Special Inspection Agreement Cost: $45,200

Arlington Elementary Approval of Third-Party Special Inspection Agreement Cost: $37,345

Bryan Station Middle Approval of Third-Party Special Inspection Agreement Cost: $42,000

Leestown Middle Approval of Third-Party Special Inspection Agreement Cost: $22,500

Lafayette High School Stadium

Approval of Bid, Proposed Contract and Revision to BG-1 Project Application Venture One Construction: $4,100,000 Total Project Cost: $4,616,180

Miles Point Way (Bus Garage)

Approval of Change Order #2 Total Cost: $6,575.94

Russell Cave Elementary Approval of Change Order #2 Total Cost: $11,179.62

Bryan Station Middle Approval of Change Order #1 Total Cost: $9,118.00

July 2009

Page 33: Update on FCPS Construction/Renovation Projects July 2009.

Tonight’s Agenda Items - continuedProject Agenda Item

Leestown Middle Approval of Change Order #1 Total Cost: $2,874.40

New Elementary at Keithshire

Approval of Schematic Design Documents

July 2009