Update on FCPS Construction/Renovation Projects...New High at Winchester Road Architect: Tate Hill...

22
Update on FCPS Construction/Renovation Projects December 2015

Transcript of Update on FCPS Construction/Renovation Projects...New High at Winchester Road Architect: Tate Hill...

Page 1: Update on FCPS Construction/Renovation Projects...New High at Winchester Road Architect: Tate Hill Jacobs: Architects General Contractor: D.W. Wilburn, Inc. GC Contract Sum: $62,044,000

Update on FCPS

Construction/Renovation Projects

December 2015

Page 2: Update on FCPS Construction/Renovation Projects...New High at Winchester Road Architect: Tate Hill Jacobs: Architects General Contractor: D.W. Wilburn, Inc. GC Contract Sum: $62,044,000

Squires Elementary -- Renovation

Architect: JRA Architects

General Contractor: D.W. Wilburn, Inc.

GC Contract Sum: $12,166,000

Total Project Cost: $15,207,000

Change Orders to Date (8): $52,818

Scheduled Contract Completion Date: July 2016

% of Contract Completed: 70.0%

Revised Completion Date per GC: No Change

December 2015

Page 3: Update on FCPS Construction/Renovation Projects...New High at Winchester Road Architect: Tate Hill Jacobs: Architects General Contractor: D.W. Wilburn, Inc. GC Contract Sum: $62,044,000

Squires Elementary -- Renovation

Rendering of Final Façade

December 2015

Page 4: Update on FCPS Construction/Renovation Projects...New High at Winchester Road Architect: Tate Hill Jacobs: Architects General Contractor: D.W. Wilburn, Inc. GC Contract Sum: $62,044,000

Squires Elementary -- Renovation

Work Completed to Date:

Area “B” plumbing rough-in and fixtures are complete (Phase 2).

Area “B” ceramic tile is complete (Phase 2).

Area “B” casework is complete (Phase 2).

Area “B” interior masonry partition walls are complete (Phase 2A).

Area “B” roof joists and decking are complete (Phase 2A).

Current Work Effort (December):

Area “B” terrazzo to complete (Phase 2).

Area “B” doors and hardware to complete (Phase 2).

Area “B” exterior spray insulation to complete (Phase 2A).

Area “B” brick to continue (Phase 2A).

Area “D” selective demolition to begin (Phase 3).

December 2015

Page 5: Update on FCPS Construction/Renovation Projects...New High at Winchester Road Architect: Tate Hill Jacobs: Architects General Contractor: D.W. Wilburn, Inc. GC Contract Sum: $62,044,000

Squires Elementary -- Renovation

December 2015

Completed Restroom VCT Flooring

Completed Casework Terrazzo Base

Page 6: Update on FCPS Construction/Renovation Projects...New High at Winchester Road Architect: Tate Hill Jacobs: Architects General Contractor: D.W. Wilburn, Inc. GC Contract Sum: $62,044,000

Squires Elementary -- Renovation

December 2015

Supply Ducts Exterior Doors

Prepping CMU Walls Exterior Spray Insulation

Page 7: Update on FCPS Construction/Renovation Projects...New High at Winchester Road Architect: Tate Hill Jacobs: Architects General Contractor: D.W. Wilburn, Inc. GC Contract Sum: $62,044,000

New Elementary at Passage Mound

Architect: Moody-Nolan Architects

General Contractor: Griggs Enterprises, Inc.

GC Contract Sum: $14,980,350

Total Project Cost: $19,478,511

Change Orders to Date (6): $143,211

Scheduled Contract Completion Date: July 2016

% of Contract Completed: 50.93%

Revised Completion Date per GC: No Change

December 2015

Page 8: Update on FCPS Construction/Renovation Projects...New High at Winchester Road Architect: Tate Hill Jacobs: Architects General Contractor: D.W. Wilburn, Inc. GC Contract Sum: $62,044,000

New Elementary at Passage Mound

Rendering of Final Façade

December 2015

Page 9: Update on FCPS Construction/Renovation Projects...New High at Winchester Road Architect: Tate Hill Jacobs: Architects General Contractor: D.W. Wilburn, Inc. GC Contract Sum: $62,044,000

New Elementary at Passage Mound

Work Completed to Date:

Install metal studs & drywall in Administration Area.

Start Media Center metal Studs.

Install ceiling grid - Area A Classrooms.

Start metal roof panels - Area A.

Start windows - Area A.

Current Work Effort (December):

Continue with above-ceiling MEP installation.

Continue with window installation Area A and Area B.

Complete brick on the Media Center.

Permanent power on to the building.

Start ceiling grid in Area B - Classrooms.

December 2015

Page 10: Update on FCPS Construction/Renovation Projects...New High at Winchester Road Architect: Tate Hill Jacobs: Architects General Contractor: D.W. Wilburn, Inc. GC Contract Sum: $62,044,000

New Elementary at Passage Mound

December 2015

Site – Towards Area B Entrance

Typical Classroom Media Center - Exterior

Page 11: Update on FCPS Construction/Renovation Projects...New High at Winchester Road Architect: Tate Hill Jacobs: Architects General Contractor: D.W. Wilburn, Inc. GC Contract Sum: $62,044,000

New Elementary at Passage Mound

December 2015

Media Center -- Interior Kitchen

Street View Last Corridor Cap

Page 12: Update on FCPS Construction/Renovation Projects...New High at Winchester Road Architect: Tate Hill Jacobs: Architects General Contractor: D.W. Wilburn, Inc. GC Contract Sum: $62,044,000

New Elementary at Georgetown Road

Architect: Clotfelter-Samokar Architects

General Contractor: D.W. Wilburn, Inc.

GC Contract Sum: $14,874,000

Total Project Cost: $19,848,291

Change Orders to Date (6): $48,441

Scheduled Contract Completion Date: July 2016

% of Contract Completed: 49.0%

Revised Completion Date per GC: No Change

December 2015

Page 13: Update on FCPS Construction/Renovation Projects...New High at Winchester Road Architect: Tate Hill Jacobs: Architects General Contractor: D.W. Wilburn, Inc. GC Contract Sum: $62,044,000

New Elementary at Georgetown Road

Rendering of Final Façade

December 2015

Page 14: Update on FCPS Construction/Renovation Projects...New High at Winchester Road Architect: Tate Hill Jacobs: Architects General Contractor: D.W. Wilburn, Inc. GC Contract Sum: $62,044,000

New Elementary at Georgetown Road

Work Completed to Date:

Fine grading behind installed curb & gutter continues.

Installation of DGA base for parking lots and drive lanes on-going.

Begin exterior window installation starting in Area C.

CMU in Areas A & D are around 95% complete. Brick veneer is on-going.

Mechanical, Plumbing & Electrical are on-going

Tectum Roof deck installation complete. Area A & D roof insulation on-going.

Current Work Effort (December):

Site contractor to continue grading parking lot and begin binder installation.

Exterior window installation on-going.

Structural steel framing and roof decking will complete.

Foam cavity insulation to begin in Area D & complete in Area A.

CMU and brick veneer installation will continue.

Installation of above deck roof insulation and dry-in will continue.

December 2015

Page 15: Update on FCPS Construction/Renovation Projects...New High at Winchester Road Architect: Tate Hill Jacobs: Architects General Contractor: D.W. Wilburn, Inc. GC Contract Sum: $62,044,000

New Elementary at Georgetown Road

December 2015

Entrance Front

Gym Roof Base Sheet Mezzanine Sprinkler Piping

Page 16: Update on FCPS Construction/Renovation Projects...New High at Winchester Road Architect: Tate Hill Jacobs: Architects General Contractor: D.W. Wilburn, Inc. GC Contract Sum: $62,044,000

New Elementary at Georgetown Road

December 2015

Mezzanine Raceway Roof Deck Installation

South End South Wall Gym

Page 17: Update on FCPS Construction/Renovation Projects...New High at Winchester Road Architect: Tate Hill Jacobs: Architects General Contractor: D.W. Wilburn, Inc. GC Contract Sum: $62,044,000

New High at Winchester Road

Architect: Tate Hill Jacobs: Architects

General Contractor: D.W. Wilburn, Inc.

GC Contract Sum: $62,044,000

Total Project Cost: $81,511,696

Change Orders to Date (2): ($16,111)

Scheduled Contract Completion Date: July 2017

% of Contract Completed: 21.13%

Revised Completion Date per GC: No Change

December 2015

Page 18: Update on FCPS Construction/Renovation Projects...New High at Winchester Road Architect: Tate Hill Jacobs: Architects General Contractor: D.W. Wilburn, Inc. GC Contract Sum: $62,044,000

New High at Winchester Road

Rendering of Final Façade

December 2015

Page 19: Update on FCPS Construction/Renovation Projects...New High at Winchester Road Architect: Tate Hill Jacobs: Architects General Contractor: D.W. Wilburn, Inc. GC Contract Sum: $62,044,000

New High at Winchester Road

Work Completed to Date:

Fill at the Athletic Fields has continued. Storm drain installation has continued in

parking lot. Geothermal wells have continued.

Field house foundations have begun. Foundations are 99% complete for academic

building. ICF walls are to roof bearing height in Area C. ICF walls are to second

floor bearing height in Area B. Floor slabs have begun in Area D.

Masonry is up to roof bearing height in the Main Gym. Masonry is up to roof

bearing height in Area C. Masonry is up to second floor bearing height in Area B

and Area E3. Area E2 masonry has begun. Stem wall CMU has been completed in

Areas E1 and D and has begun in Area A.

Steel joist and metal deck work has begun on the second floor of Area B and at

the roof of Area C.

Mechanical rough-ins have continued above ceiling in Area C on the first floor.

Underground plumbing in Areas A, D, and E1 has continued and is near

completion. Underslab electrical rough-ins have been completed in Area E1 and

have begun in Area D. Electric primaries have been roughed-in at the mechanical

room. December 2015

Page 20: Update on FCPS Construction/Renovation Projects...New High at Winchester Road Architect: Tate Hill Jacobs: Architects General Contractor: D.W. Wilburn, Inc. GC Contract Sum: $62,044,000

New High at Winchester Road

Current Work Effort (December):

Fill at athletic fields will be completed. Storm drains will continue at the parking

lot. Geothermal drilling and tie-ins will continue.

Foundations will be completed at the field house. Foundations will begin at the

grandstand bleachers and restrooms at the bleachers. Floor slabs will be

completed in Area D. Floor slabs will be placed on the second floor in Areas E3,

E4, and B. Floor slabs will begin in Area A.

Masonry will begin in Area B on the second floor and on the first floor in Area E1

and D. Foundation CMU will be completed in Area A. Second floor masonry will

begin in Areas E3 and E4. All CMU masonry will be completed in Area C.

Roof Joist and metal deck will continue in Area C. Second floor joist/deck will be

completed in Area E3 and E4 and will begin in the Main Gym.

Above ceiling MEP work on the first floor of Area C will continue and will begin

in Area E4. Underground plumbing will be complete in all areas of the academic

building. Underslab electrical will continue in Areas A, D, & E1. Underground

plumbing will begin in the Field House. Secondary electrical rough-ins will begin

in the Field House. December 2015

Page 21: Update on FCPS Construction/Renovation Projects...New High at Winchester Road Architect: Tate Hill Jacobs: Architects General Contractor: D.W. Wilburn, Inc. GC Contract Sum: $62,044,000

New High at Winchester Road

December 2015

Area A Progress Area D Progress

Area E1 Progress Area E4 and C

Page 22: Update on FCPS Construction/Renovation Projects...New High at Winchester Road Architect: Tate Hill Jacobs: Architects General Contractor: D.W. Wilburn, Inc. GC Contract Sum: $62,044,000

New High at Winchester Road

December 2015

Area C Ductwork Stored Ductwork

Gym CMU Gym Upper Bleachers