Stationary Fuel Cell Evaluation
Project ID # TV016
This presentation does not contain any proprietary, confidential, or otherwise restricted information.
2014 DOE Annual Merit Review
Genevieve Saur (PI), Jennifer Kurtz, Chris Ainscough, Michael Peters
National Renewable Energy Laboratory
June 19, 2014
2
Overview
Timeline Project start date: Oct. 2011 Project end date: Sep. 2014* Percent complete: On-going
Barriers B. Lack of Data on Stationary Fuel Cells in Real-World Applications E. Codes & Standards
Budget FY13 DOE Funding:$200k Planned FY14 DOE Funding:$100k Total DOE Project value:$365k
Partners • California Stationary Fuel Cell
Collaborative, (review results) • National Fuel Cell Research
Center (UCI), (subcontractor) • Five OEM data providers,
developing others. *Project continuation and direction determined annually by DOE
3
Relevance - Objectives
Independently assess, validate, and report operation targets and stationary fuel cell system performance under real operating conditions.
B. Lack of Data on Stationary Fuel Cells in Real-World Applications
Addressing the gap in knowledge as stationary fuel cell installations have increased dramatically
E. Codes & Standards Providing data and context to C&S activities.
3
4 4
Approach - Milestones
• Quarterly data analysis (based on available data) • Publication of technical stationary fuel cell
composite data products
FY12 Q4 FY13 Q1 FY13 Q2 FY13 Q3 FY13 Q4
Completed
Scheduled
FY14 Q1 FY14 Q2 FY14 Q3 FY14 Q4
5
CDPs
DDPs
Public
Composite Data Products (CDPs) • Aggregated data across multiple systems,
sites, and teams • Publish analysis results every six months
without revealing proprietary data
Detailed Data Products (DDPs) • Individual data analyses
• Identify individual contribution to CDPs • Shared every six months only with the
partner who supplied the data
www.nrel.gov/hydrogen/proj_tech_validation.html
Approach: NFCTEC Analysis and Reporting of Real-World Operation Data
Results
Bundled data (operation & maintenance/safety) delivered
to NREL quarterly Internal analysis
completed quarterly in NFCTEC
National Fuel Cell Technology Evaluation Center
6 6
Approach - Stationary Fuel Cell Systems • Deployment and cost data
o Publically available data from California SGIP (2001-present) o Includes systems providing prime, continuous, or regular
power to a site (not backup power) o Includes multiple fuel cell types - proton exchange membrane
(high and low temperature), solid oxide, phosphoric acid, and molten carbonate
o Includes fuel types for fuel cells (natural gas, biomass, digester gas, landfill gas)
o Small, kilowatt-scale to large, megawatt-scale o Cost data for projects including incentives
• Operations data o All data voluntary
• 28 total cdps
7 7
Approach - Data Processing, Analysis, and Reporting Tools
• NREL Fleet Analysis Toolkit (NRELFAT) — Developed first under fuel cell vehicle
Learning Demonstration — Restructured architecture and interface to
effectively handle new applications and projects and for flexible analysis
— Leverage analyses already created
• Report results – Detailed and composite results – Target key stakeholders such as fuel cell and hydrogen developers,
and end users
8
Accomplishments and Progress
3%
4%
10%
11%64%
Deployment Count By Status*
Other Categories: ICF ReviewICF Technical ReviewICF Pending PaymentPPM Technical ReviewRRF ReviewRRF Technical Review
Definitions: RRF = Reservation Request Form, is the first step in the SGIP incentive claim process.PPM = Proof of Project Milestone; the applicant must prove progress and committment to the project.ICF = Incentive Claim Form is the step where the appliant, after meeting all SGIP requirements requests payment of the incentive.PBI = Performance Based Incentive is the way in which the incentive is paid out over time based on performance of the system.
OtherICF InspectionRRF ReservedPPM ConfirmedPayment PBI in ProcessPayment Completed
2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 20130
100
200
300
400
Proj
ect C
ount
Cumulative Deployment Count by Year*
Total = 317 units
TotalFuel Cell CHPFuel Cell Electric
2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 20130
50
100
150
Cap
acity
[MW
]
Cumulative Capacity by Year*
Total = 131 MW
TotalFuel Cell CHPFuel Cell Electric
1
California SGIP program has 317 fuel cell projects (CHP and electric) in various stages of development.
California SGIP has 317 fuel cell projects (CHP and electric) in various stages of development.
Fuel cell projects in the California SGIP account for 21% of projects with CHP potential technologies* (317 projects out of 1493) and 28% of the capacity (131 MW out of 460 MW). * Technologies included: fuel cell, gas turbine, internal combustion engine, microturbine, pressure reduction turbine
9
Accomplishments and Progress • Most of the recent projects since 2011
have been natural gas. There was a small resurgence of biomass projects in late 2013.
• Renewable fuels project have generally larger capacities by project.
• Digester gas has several large projects
Biomass Digester Gas Landfill Gas Natural Gas0
100
200
300
400
500
600
700
Inst
alle
d C
apac
ity (k
W)
Installation Capacity Statistics by Fuel Type*
75% Percentile
Median
25% Percentile
Mean
2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 20130
10
20
30
40
50
60
Year
Tota
l Ann
ual I
nsta
lled
Cap
acity
(MW
)
Installed Fuel Type By Year*
BiomassDigester GasLandfill GasNatural Gas
74% of California SGIP fuel cell projects use natural gas and they
account for 66% of the capacity
10
Accomplishments and Progress
0
10
20
30
Average Prices No Incentive, Incentive0-50 kW = $10,808/kW, $8,299/kWAverage Prices No Incentive, Incentive
51-200 kW = $10,932/kW, $6,725/kW
Average Prices No Incentive, Incentive
201-400 kW = $9,950/kW, $6,046/kW
Average Prices No Incentive, Incentive
401+ kW = $9,524/kW, $5,587/kWData points with less than 2 projects filtered.
0 10
00 20
00 30
00 40
00 50
00 60
00 70
00 80
00 90
00
1000
011
00012
00013
00014
00015
00016
00017
00018
00019
00020
00021
000
proj
ect c
ount
Price [$2010/kW] No Incentive
Installed Eligible Cost Per kW By Capacity*Adjusted To 2010 Dollars
0-50kW
51-200 kW
201-400 kW
>400 kW
DOE 2020 Target
0
10
20
30
0 10
00 20
00 30
00 40
00 50
00 60
00 70
00 80
00 90
00
1000
011
00012
00013
00014
00015
00016
00017
00018
00019
00020
00021
000
proj
ect c
ount
Price [$2010/kW] With IncentiveNREL cdp_stat_26Created: Apr 16 14 9:36 AM | Data Range: 2001Q2 2013Q3
Eligible Costs May Include: Planning & Feasibility Study,Engineering & Design, Permitting, Self-GenerationEquipment, Waste Heat Recovery Costs, Construction &Installation Costs, Gas & Electric Interconnection, Warranty,Maintenance Contract, Metering, Monitoring & DataAcquisition System, Emission Control Equipment Capital,Gasline Installation, Fuel Gas Clean-up Equipment,Electricity Storage Devices, Bond to Certify RenewableFuel, Sales Tax, Fuel Supply (digesters, gas gathering, etc.),Thermal Load, & Other Eligible Costs
• Larger projects generally have lower unit prices($/kW) • Larger projects generally receive more incentives thereby lowering the average unit
prices($/kW) more than smaller projects • Few projects with incentives meet the DOE target of $1,500/kW
Average All Projects
$10,189/kW no
incentive
$6,722/kW with incentive
11
Accomplishments and Progress
2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 20130
20
40
60
80
100
120
140
Cap
acity
[MW
]
Year2000
2500
3000
3500
4000
4500
5000
5500
Ince
ntiv
e Sp
endi
ng ($
2010
) Per
kW
Inst
alle
d
Total Incentive ($2010) per kW by Year*
• The average unit prices for fuel cell
projects has fluctuated very little, but more variation is seen when separated by size
• Total incentive spending in fuel cell projects have decreased since 2010 while project counts continues to increase steadily
23 new fuel cell projects have been accepted into the California SGIP with a total capacity of 10 MW between Q2 2013 and Q4 2013
2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 20130
5
10
15
Ave
rage
$20
10/W
of In
stal
led
Cap
acity
Average Eligible Cost $2010/W Trend for Overall Deployments*
Without IncentiveWith IncentiveDOE 2020 Target
0
5
10
15
200120
0220
0320
0420
0520
0620
0720
0820
0920
1020
1120
1220
13
Capacity < 500 kW
Ave
rage
$20
10/W
of In
stal
led
Cap
acity
0
5
10
15
200120
0220
0320
0420
0520
0620
0720
0820
0920
1020
1120
1220
13
500 kW <= Capacity < 1000 kW
0
5
10
15
200120
0220
0320
0420
0520
0620
0720
0820
0920
1020
1120
1220
13
Capacity >= 1000 kW
12
Accomplishments and Progress
0 200 400 600 800 1000 >10000
5
10
15
20
25
30
35
40
45
50
System Size (kW)
Tota
l Ins
talle
d C
apac
ity (M
W)
Installed Capacity And Fuel Type*
BiomassDigester GasLandfill GasNatural Gas
0
0 200 400 600 800 1000 >10000
3000
6000
9000
12000
15000
18000
System Size (kW)
$201
0/kW
of In
stal
led
Cap
acity
Range of Installed Eligible Cost Per kW Biogas Sources by Capacity
Biogas Sources with IncentiveBiogas Sources without IncentiveMean with IncentiveMedian with IncentiveMean without IncentiveMedian without Incentive
cdp_stat_28d: Apr-16-14 9:37 AM | Data Range: 2001Q2-2013Q3
Insufficientdata toprotect
anonymity
Insufficientdata toprotect
anonymity
*Data from the Cal
Eligible Costs May Include: Planning & Feasibility Study, Engineering & Design, Permitting, Self-Generation Equipment, Waste HeatRecovery Costs, Construction & Installation Costs, Gas & Electric Interconnection, Warranty, Maintenance Contract, Metering, Monitoring &Data Acquisition System, Emission Control Equipment Capital, Gasline Installation, Fuel Gas Clean-up Equipment, Electricity StorageDevices, Bond to Certify Renewable Fuel, Sales Tax, Fuel Supply (digesters, gas gathering, etc.), Thermal Load, & Other Eligible Costs
• 25% of fuel cell sites have biogas fuel sources and account for 33% of the capacity
• The average and range of the cost ($/kW) of biogas sourced fuel cell projects generally decreases with project size.
25% of 317 fuel cell sites have biogas fuel sources and account for 33% of 131 MW of the total fuel cell capacity
12% of 112 fuel cell CHP sites have biogas fuel sources for 45% of the 28 MW of total capacity
Biogas fuel cells
13
Accomplishments and Progress
2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 20130
500
1000
1500
Proj
ect C
ount
Cumulative Deployment Count by Category and Year*
Total = 1493 units
TotalFuel Cell CHPFuel Cell ElectricGas TurbineInternal CombustionMicroturbinePressure Reduction Turbine
2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 20130
100
200
300
400
500
Cap
acity
[MW
]
Cumulative Capacity by Category and Year*
Total = 460 MW
TotalFuel Cell CHPFuel Cell ElectricGas TurbineInternal CombustionMicroturbinePressure Reduction Turbine
0 200 400 600 800 1000 1200 1400 1600 1800 2000 >20000
50
100
150
200
250Distribution of Capacity by Equipment Type*
Capacity (kW)
Tota
l # o
f Sys
tem
s
Fuel Cell CHPFuel Cell ElectricGas TurbineInternal CombustionMicroturbinePressure Reduction Turbine
4
• Fuel cells mainly compete with internal
combustion engines and microturbines in terms of capacity ranges
• Since 2010 fuel cells are making significant progress compared to other technologies by numbers of installations and capacity
• Fuel cells are generally more expensive than the competing technologies even with incentives
2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 20130
5
10
15
20
25
Ave
rage
$20
10/W
of In
stal
led
Cap
acity
Average Eligible Cost $2010/W Trend for Overall Deployments*Without Incentives
2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 20130
5
10
15
20
25
Average Eligible Cost $2010/W Trend for Overall Deployments*With Incentives
Ave
rage
$20
10/W
of In
stal
led
Cap
acity
Fuel Cell CHPFuel Cell ElectricGas TurbineInternal CombustionMicroturbinePressure Reduction Turbine
14
Accomplishments and Progress
0 1000 2000 3000 4000 5000 6000 7000 8000 9000 10000 11000 12000 13000 140000
5
10
15
20
25
30
35
40
% o
f Uni
ts
Mean Time (hr) between Stoppages
Mean Time Between Stoppage (hours)*
Overall Mean = 2742 hours
10 15 20 25 30 35 40 450
5
10
15
20
25
30
35
% o
f Uni
ts
Mean Unit Electrical Efficiency (% HHV)
Unit Lifetime Mean Electrical Efficiency (HHV)*†
04 PM | Data Range: 2010Q10-2013Q2
Overall Mean = 27 %
†Includes startup, shutdown, transient and partial power operation *Data from outs
40 45 50 55 60 65 70 75 80 85 90 95 1000
5
10
15
20
25
30
35
40
% o
f Uni
ts
Mean Unit Availability (%)
Unit Mean Availability*
Overall Mean = 93 %
NREL has begun to collect operations data, additional data is
expected in the Q4 results
* Unit refers to a single fuel cell system
15
Accomplishments and Progress: Responses to Previous Year Reviewers’ Comments
• “The pre-commercial days are over, so stationary fuel cells will need to compete with heat engines and the grid on cost and value.” o Several new cdp’s have been developed to compare fuel cells to other
competing technologies from a size and cost standpoint.
• However, few data are given about the operations of the systems themselves. o 3 new cdp’s have been developed to begin to address operational
usage and key areas as efficiency and availability. o More data is expected and we are continuing to investigate additional
data partners.
• The data span a large set of power levels, combined heat and power (CHP)/non-CHP and other various technologies, so it is a bit hard to see trends, draw conclusions, etc. o We have begun to create cdp’s which separate sizes and CHP systems.
16
Collaborations • Partners for data delivered at the end of 2012
o National Fuel Cell Research Center
o Five fuel cell OEMs
o California Stationary Fuel Cell Collaborative
• Communicating with several organizations to establish agreements for sharing data with NREL o State and regional fuel cell organizations
o Fuel cell developers
17
Remaining Challenges and Barriers
• Develop additional state project partners for deployment numbers, cost trends, and operations data.
• Work with fuel cell companies to obtain data for assessing key DOE targets
• Analyze key deployment barriers and identify elements of successful deployment.
18
Proposed Future Work
• Q4 2014 milestone: Update all cdp’s with current data • Remainder of 2014:
o Continue to analyze current California SGIP deployment data o Collect additional operations data for updates to operations
cdps o Expand analysis to include new cdps which address further
segmentation of the data (CHP/non-CHP, competing technologies, fuel sources) and trends over time
o Look into other data partners (state and federal programs) o Work with fuel cell OEMs for possibility of additional data sets
19
Summary • NREL is leveraging a large pool of technology validation analyses
and knowledge • Stationary fuel cell deployment is increasing steadily, incentive
expenditure (in California SGIP) is decreasing, but project prices are still generally higher for fuel cells.
• Natural gas is the leading fuel source, but a significant number of larger installations are using biogas fuel sources (23 biogas FC projects are ≥ 600 kW)
• Fuel cells continue to be installed in the California SGIP (23 new FC projects between Q2 2013 and Q4 2013)
• Larger projects tend to have lower unit cost ($/kW) and often take advantage of more incentives.
• The mean availability of fuel cells systems is 93% with ~35% of systems over 95%.
• The mean electrical efficiency of fuel cells is 27% with <3% of the systems analysed over 35% electrical efficiency (based on HHV).
Technical Back-Up Slides
21
CDP-STAT-06 Fuel Cell Stationary Capacity and Average Prices
0 200 400 600 800 1000 >10000
5
10
15
20
25
30Distribution of Capacity and Average Eligible Cost $2010/kW*
Capacity (kW)
% o
f sys
tem
s
0 200 400 600 800 1000 >10000
2,000
4,000
6,000
8,000
10,000
12,000
Avg
. $/k
W
$/kW w/o Incentive$/kW w/ Incentive2020 DOE Target†
0 200 400 600 800 1000 0
5
10
15
20
Capacity (kW)
% o
f sys
tem
s
Detailed Capacity Distribution
0 10 20 30 40 500
20406080
Capacity (kW)
% o
f sys
tem
s
NREL cdp_stat_06Created: Apr-16-14 9:36 AM | Data Range: 2001Q2-2013Q3
†for the year 2020, operating on natural gas.*Data from the California SGIP.
Eligible Costs May Include: Planning & Feasibility Study, Engineering & Design, Permitting, Self-Generation Equipment, WasteHeat Recovery Costs, Construction & Installation Costs, Gas & Electric Interconnection, Warranty, Maintenance Contract,Metering, Monitoring & Data Acquisition System, Emission Control Equipment Capital, Gasline Installation, Fuel Gas Clean-upEquipment, Electricity Storage Devices, Bond to Certify Renewable Fuel, Sales Tax, Fuel Supply (digesters, gas gathering,etc.), Thermal Load, & Other Eligible Costs
22
CDP-STAT-22 Distribution of Capacity and Eligible Cost (CHP Fuel Cells)
0 200 400 600 800 1000 >10000
10
20
30
40
50
60
70Distribution of Capacity and Average Eligible Cost $2010/kW (CHP Fuel Cell)*
Capacity (kW)
% o
f sys
tem
s
0 200 400 600 800 1000 >10000
2,000
4,000
6,000
8,000
10,000
Avg
. $/k
W
$/kW w/o Incentive$/kW w/ Incentive2020 DOE Target†
0 200 400 600 800 1000 0
10
20
30
40
50
Capacity (kW)
% o
f sys
tem
s
Detailed Capacity Distribution
0 10 20 30 40 500
20406080
Capacity (kW)
% o
f sys
tem
s
NREL cdp_stat_22Created: Apr-16-14 9:36 AM | Data Range: 2001Q2-2013Q3
†for the year 2020, operating on natural gas.*Data from the California SGIP.
Eligible Costs May Include: Planning & Feasibility Study, Engineering & Design, Permitting, Self-Generation Equipment, WasteHeat Recovery Costs, Construction & Installation Costs, Gas & Electric Interconnection, Warranty, Maintenance Contract,Metering, Monitoring & Data Acquisition System, Emission Control Equipment Capital, Gasline Installation, Fuel Gas Clean-upEquipment, Electricity Storage Devices, Bond to Certify Renewable Fuel, Sales Tax, Fuel Supply (digesters, gas gathering,etc.), Thermal Load, & Other Eligible Costs
23
CDP-STAT-04 Stationary Fuel Cell System Count and Capacity by Fuel Type
4%10%
11%
74%
Site Count by Fuel Type*
Biomass
Digester Gas
Landfill Gas
Natural Gas
4%
17%
13%
66%
Installed Capacity by Fuel Type
NREL cdp_stat_04Created: Apr-16-14 9:37 AM | Data Range: 2001Q2-2013Q3
Includes Status Categories:ICF InspectionICF Pending PaymentICF ReviewICF Technical ReviewPPM ConfirmedPPM Technical ReviewPayment CompletedPayment PBI in ProcessRRF ReservedRRF ReviewRRF Technical ReviewTotal Capacity: 131 MWTotal Sites: 316
Installations by Fuel Type(All Fuel Cell Systems)
Definitions: RRF = Reservation Request Form, is the first step in the SGIP incentive claim process.PPM = Proof of Project Milestone; the applicant must prove progress and committment to the project.ICF = Incentive Claim Form is the step where the appliant, after meeting all SGIP requirements requests payment of the incentive.PBI = Performance Based Incentive is the way in which the incentive is paid out over time based on performance of the system. *Data from the California SGIP.
24
CDP-STAT-20 Installations By Fuel Type (CHP Fuel Cells)
8%
4%
88%
Site Count by Fuel Type*
Digester Gas
Landfill Gas
Natural Gas
32%
13%
55%
Installed Capacity by Fuel Type
NREL cdp_stat_20Created: Apr-16-14 9:36 AM | Data Range: 2001Q2-2013Q3
Includes Status Categories:ICF Technical ReviewPPM ConfirmedPPM Technical ReviewPayment CompletedPayment PBI in ProcessRRF ReservedRRF Technical Review
Total Capacity: 28 MWTotal Sites: 112
Installations by Fuel Type(CHP Fuel Cell Systems)
Definitions: RRF = Reservation Request Form, is the first step in the SGIP incentive claim process.PPM = Proof of Project Milestone; the applicant must prove progress and committment to the project.ICF = Incentive Claim Form is the step where the appliant, after meeting all SGIP requirements requests payment of the incentive.PBI = Performance Based Incentive is the way in which the incentive is paid out over time based on performance of the system. *Data from the California SGIP.
25
CDP-STAT-07 Distribution of Stationary Fuel Cell Install Price with and without Incentives
0
20
40
60
80
0
1000
20
00
3000
40
00
5000
60
00
7000
80
00
9000
1000
011
000
1200
013
000
1400
015
000
1600
017
000
1800
019
000
2000
021
000
proj
ect c
ount
Price without incentives [$2010/kW]
Installed Eligible Cost Per kW*Adjusted To 2010 Dollars
Avg** = $10,189 $/kW
CurrentDOE 2020 Target
0
20
40
60
0
1000
20
00
3000
40
00
5000
60
00
7000
80
00
9000
1000
011
000
1200
013
000
1400
015
000
1600
017
000
1800
019
000
2000
021
000
proj
ect c
ount
Price with incentives [$2010/kW]
Avg** = $6,722 $/kW
CurrentDOE 2020 Target
NREL cdp_stat_07Created: Apr-16-14 9:37 AM | Data Range: 2001Q2-2013Q3 *Data from the California SGIP.
Eligible Costs May Include: Planning & Feasibility Study, Engineering & Design, Permitting, Self-Generation Equipment, WasteHeat Recovery Costs, Construction & Installation Costs, Gas & Electric Interconnection, Warranty, Maintenance Contract,Metering, Monitoring & Data Acquisition System, Emission Control Equipment Capital, Gasline Installation, Fuel Gas Clean-upEquipment, Electricity Storage Devices, Bond to Certify Renewable Fuel, Sales Tax, Fuel Supply (digesters, gas gathering,etc.), Thermal Load, & Other Eligible Costs
**Data points with less than 2projects filtered.
26
CDP-STAT-23 Distribution of Eligible Cost with and w/o Incentives (CHP Fuel Cells)
0
10
20
30
0
1000
20
00
3000
40
00
5000
60
00
7000
80
00
9000
1000
011
000
1200
013
000
1400
015
000
1600
017
000
1800
019
000
2000
021
000
proj
ect c
ount
Price without incentives [$2010/kW]
Installed Eligible Cost Per kW (CHP Fuel Cell)*Adjusted To 2010 Dollars
Avg** = $9,997 $/kW
CurrentDOE 2020 Target
0
10
20
30
40
0
1000
20
00
3000
40
00
5000
60
00
7000
80
00
9000
1000
011
000
1200
013
000
1400
015
000
1600
017
000
1800
019
000
2000
021
000
proj
ect c
ount
Price with incentives [$2010/kW]
Avg** = $7,107 $/kW
CurrentDOE 2020 Target
NREL cdp_stat_23Created: Apr-16-14 9:37 AM | Data Range: 2001Q2-2013Q3 *Data from the California SGIP.
Eligible Costs May Include: Planning & Feasibility Study, Engineering & Design, Permitting, Self-Generation Equipment, WasteHeat Recovery Costs, Construction & Installation Costs, Gas & Electric Interconnection, Warranty, Maintenance Contract,Metering, Monitoring & Data Acquisition System, Emission Control Equipment Capital, Gasline Installation, Fuel Gas Clean-upEquipment, Electricity Storage Devices, Bond to Certify Renewable Fuel, Sales Tax, Fuel Supply (digesters, gas gathering,etc.), Thermal Load, & Other Eligible Costs
**Data points with less than 2projects filtered.
27
CDP-STAT-27 Installed Eligible Cost per kW By Capacity (CHP Fuel Cell)
0
10
20
30
Average Prices No Incentive, Incentive0-50 kW = $10,830/kW, $8,320/kWAverage Prices No Incentive, Incentive
51-200 kW = $NaN/kW, $NaN/kW
Average Prices No Incentive, Incentive
201-400 kW = $8,817/kW, $5,330/kW
Average Prices No Incentive, Incentive
401+ kW = $7,582/kW, $3,647/kWData points with less than 2 projects filtered.
0 10
00 20
00 30
00 40
00 50
00 60
00 70
00 80
00 90
00
1000
011
00012
00013
00014
00015
00016
00017
00018
00019
00020
00021
000
proj
ect c
ount
Price [$2010/kW] No Incentive
Installed Eligible Cost Per kW By Capacity (CHP Fuel Cell)*Adjusted To 2010 Dollars
0-50kW
51-200 kW
201-400 kW
>400 kW
DOE 2020 Target
0
10
20
30
0 10
00 20
00 30
00 40
00 50
00 60
00 70
00 80
00 90
00
1000
011
00012
00013
00014
00015
00016
00017
00018
00019
00020
00021
000
proj
ect c
ount
Price [$2010/kW] With IncentiveNREL cdp_stat_27Created: Apr-16-14 9:37 AM | Data Range: 2001Q2-2013Q3 *Data from the California SGIP.
Eligible Costs May Include: Planning & Feasibility Study,Engineering & Design, Permitting, Self-GenerationEquipment, Waste Heat Recovery Costs, Construction &Installation Costs, Gas & Electric Interconnection, Warranty,Maintenance Contract, Metering, Monitoring & DataAcquisition System, Emission Control Equipment Capital,Gasline Installation, Fuel Gas Clean-up Equipment,Electricity Storage Devices, Bond to Certify RenewableFuel, Sales Tax, Fuel Supply (digesters, gas gathering, etc.),Thermal Load, & Other Eligible Costs