Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into...

118
COBAR MANAGEMENT PTY LTD CSA Mine Annual Environmental Management Report AEMR 2012

Transcript of Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into...

Page 1: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

COBAR MANAGEMENT PTY LTD

CSA Mine

Annual Environmental Management Report

AEMR 2012

Page 2: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

i

Blank Page

Page 3: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care
Page 4: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

iii

CONTENTS 1 INTRODUCTION ....................................................................................................................................... 1

1.1 History of Operations ............................................................................................................................... 1

1.2 Consents, Leases and Licenses ................................................................................................................. 2

Mine Contacts .................................................................................................................................................... 5

1.3 Actions required from 2011 AEMR review ............................................................................................... 6

2 SUMMARY OF OPERATIONS DURING THE REPORTING PERIOD .......................................... 10

2.1 Mineral Exploration ............................................................................................................................... 11

2.2 Land Preparation.................................................................................................................................... 12

2.3 Construction ........................................................................................................................................... 14

2.4 Mining ..................................................................................................................................................... 16

2.5 Mineral Processing ................................................................................................................................. 21

2.6 Waste Management ................................................................................................................................. 23

2.7 Ore and Product Stockpiles .................................................................................................................... 26

2.8 Water Management ................................................................................................................................. 29

2.9 Hazardous Materials .............................................................................................................................. 39

2.10 Other Infrastructure Management ..................................................................................................... 42

3 ENVIRONMENTAL MANAGEMENT AND PERFORMANCE ........................................................ 44

3.1 Pollution Incident Response Management Plan ..................................................................................... 44

3.2 Air Pollution ........................................................................................................................................... 45

3.3 Erosion and Sedimentation ..................................................................................................................... 54

3.4 Surface Water Quality ............................................................................................................................ 55

3.5 Groundwater Quality .............................................................................................................................. 62

3.6 Groundwater Levels ................................................................................................................................ 67

3.7 Contaminated Polluted Land .................................................................................................................. 73

3.8 Threatened Flora .................................................................................................................................... 74

3.9 Threatened Fauna ................................................................................................................................... 75

3.10 Weeds ................................................................................................................................................. 77

3.11 Blasting .............................................................................................................................................. 78

3.12 Operational Noise .............................................................................................................................. 78

3.13 Visual, Stray Light ............................................................................................................................. 78

3.14 Aboriginal Heritage ........................................................................................................................... 78

Page 5: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

iv

3.15 Natural and European Heritage ........................................................................................................ 79

3.16 Spontaneous Combustion ................................................................................................................... 80

3.17 Bushfire .............................................................................................................................................. 80

3.18 Mine Subsidence ................................................................................................................................ 80

3.19 Hydrocarbon Contamination ............................................................................................................. 81

3.20 Methane Drainage / Ventilation......................................................................................................... 81

3.21 Public Safety ...................................................................................................................................... 82

3.22 Other Issues and Risks ....................................................................................................................... 82

4 COMMUNITY RELATIONS .................................................................................................................. 90

4.1 Environmental Complaints ..................................................................................................................... 90

4.2 Community Liaison ................................................................................................................................. 90

5 REHABILITATION ................................................................................................................................. 95

5.1 Buildings ................................................................................................................................................. 95

5.2 Redundant Piping Removal .................................................................................................................... 95

5.3 Rehabilitation of Disturbed Land ........................................................................................................... 96

5.4 Other Infrastructure ................................................................................................................................ 97

5.5 Rehabilitation Trials and Research ........................................................................................................ 98

5.6 Further Development of the Final Rehabilitation Plan ........................................................................ 103

6 ACTIVITIES PROPOSED FOR 2013 ................................................................................................... 107

7 REFERENCES ........................................................................................................................................ 108

8 Plans .......................................................................................................................................................... 109

9 Appendices ............................................................................................................................................... 109

TABLES

Table 1 CMPL Mining and Exploration Leases (as at 31/12/12) .................................................................. 3

Table 2 CMPL Land Tenure (as of 31/12/12) ................................................................................................. 4

Table 3 CMPL Licences and Permits (as of 31/12/2012) ............................................................................... 4

Table 4 CSA Mine Management and Environmental Contacts .................................................................... 5

Table 5 Actions Required from the 2011 AEMR Review .............................................................................. 7

Table 6 Update on Proposed activities for the 2012 AEMR Period .............................................................. 8

Table 7 Actual and Forecast Production (dmt) (as of 31/12/2012) .............................................................. 16

Table 8 Backfill Production and Final Tailings 2012 ................................................................................... 18

Table 9 CMPL Current Mining Equipment (as of 31/12/12) ...................................................................... 19

Table 10 CSA Budget versus Actual Mine Production 2012 ....................................................................... 21

Table 11 Metal Recovery 2012 ....................................................................................................................... 22

Table 12 Reagent Consumption 2012 ............................................................................................................ 23

Table 13 Waste Collection Results (2010, 2011, 2012) ..................................................................................... 24

Page 6: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

v

Table 14 CSA Identified Topsoil Stockpiles .................................................................................................. 28

Table 15 CSA Cumulative Waste and Stockpile Production ...................................................................... 29

Table 16 Summary of Catchment Areas ....................................................................................................... 31

Table 17 CSA Mine Water Storage ............................................................................................................... 33

Table 18 CSA 2012 Water Balance ................................................................................................................ 36

Table 19 CSA Bulk Hazardous and Dangerous Goods Storage (as of 31/12/12) ....................................... 40

Table 20 Comparison of NPI Emission Sources by Activity Levels for 2010-11 and 2011-12 .................. 48

Table 21 Summary of CMPL Energy Consumption and Greenhouse Gas Emissions (2011-2012) ......... 49

Table 22 Short-Medium Term Energy Saving and Carbon Emission Reduction Opportunities ............ 51

Table 23 Long Term Energy Saving and Carbon Emission Reduction Opportunities ............................. 52

Table 24 Priority Management Practice Actions ......................................................................................... 53

Table 25 Adopted Guidelines .......................................................................................................................... 56

Table 26 CSA Surface Water Monitoring Results 2011 and 2012 .............................................................. 57

Table 27 CSA Piezometer Water Quality Monitoring Results 2012 ........................................................... 64

Table 28 STSF Piezometers and Trigger Depths.......................................................................................... 69

Table 29 CSA Environmental Incidents 2012 ............................................................................................... 89

Table 30 CMPL Donation Recipients 2012 ................................................................................................... 94

Table 31 LFA Rehabilitation Monitoring Results 2012 ............................................................................. 102

Table 32 Summary of Proposed Rehabilitation .......................................................................................... 105

Table 33 Maintenance Activities on Rehabilitated Land 2012 .................................................................. 106

Table 34 Proposed activities for 2013 .......................................................................................................... 107

FIGURES

Figure 1 CMPL Organisation Chart 2012 ...................................................................................................... 5

Figure 2 CSA Mine General Waste Management Performance 2012 ........................................................ 25

Figure 3 CSA Topsoil Stockpile Locations.................................................................................................... 28

Figure 4 Burrendong Dam Water Storage Level (%) and Rainfall (mm) 2012 ........................................ 30

Figure 5 Long Term Raw Water Used per Tonne Milled ............................................................................ 35

Figure 6 CSA Mine Water Balance 2012 ...................................................................................................... 38

Figure 7 2012 Cobar Mean temperatures and CSA Mine Rainfall ............................................................ 45

Figure 8 CSA Depositional Dust Monitoring Results 2012.......................................................................... 47

Figure 9 CSA Mine Total Energy Consumption (GJ) 2011-2012 ............................................................... 49

Figure 10 CSA Mine Total Greenhouse Gas Emissions (t CO2-e) 2011-2012 ........................................... 50

Figure 11 Management Practices Assessment – Level of Development ..................................................... 53

Figure 12 Surface Water Quality (pH, Pb, Cu) 2012 ................................................................................... 60

Figure 13 Surface Water Quality (SO4, Fe, Zn) 2012 .............................................................................. 61

Figure 14 Groundwater Quality Results (pH, Pb, Cu) 2012 .................................................................... 65

Figure 15 Groundwater quality results (SO4, Fe, Zn) 2012 .................................................................... 66

Figure 16 CSA Piezometer Water Levels 2012 ......................................................................................... 68

Figure 17 Cross Section of TSF Piezometer Setup ................................................................................... 71

Figure 18 CSA Mine Groundwater Levels 2012 ....................................................................................... 72

Page 7: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

vi

Figure 19 CSA Contaminated Sites Register (as of 31/12/12) .................................................................. 74

Figure 20 CMPL Environmental Incidents by Type 2011 and 2012 ....................................................... 88

Figure 21 Conceptual Stages of Sustainable Ecosystem Development ................................................. 104

PLANS

1 Mine Context

2 Land Preparation and Mining Activities

3 Rehabilitation

4 Mining Plan - Vertical Section

5 Site Layout

APPENDICES

A Environmental Protection Licence 1864

B 2011 AEMR Review Meeting Minutes

C CMPL Environment and Community Policy

D CSA Air and Water Quality Monitoring Data 2012

E STSF Surveillance Report 2011

F 2012 Annual Return EPL 1864

G 2012 CSA Rehabilitation Monitoring Report

H 2012 Biodiversity Assessment

I 2012 Pollution Incident response Management Plan

ABBREVIATIONS

ANZECC Australia and New Zealand Conservation

Council

LPMA Land and Property Management Authority

ARPANSA Australian Radiation Protection and Nuclear

Safety Authority

LFA Landform Function Analysis

CHF Cemented Hydraulic Fill Mt Mega Tonne

CMPL Cobar Mining Pty Ltd m Meter

CML Consolidated Mining Lease mm Milli meter

Cu Copper MOP Mining Operations Plan

CSA Cornish, Scottish, Australian Mine NATA National Association of Testing Authorities

DSC Dam Safety Committee NGER National Greenhouse and Energy Reporting

Act 2007

DSEWPC Department of Sustainability, Environment,

Water, Population and Communities

NPI National Pollutant Inventory

DRE Department of Trade and Investment,

Resources and Energy

NORM Naturally Occurring radioactive materials

DMP Derelict Mines Program NTSF North Tailings Storage Facility

DEM

DFS

Digital Elevation Model

Definitive Feasibility Studies

OEH Office of Environment and Heritage

DRE Division of Energy and Resources PJ Pentajoule

dmt Dry Metric Tonnes PET Polyethylene Terephthalate

EEO Energy Efficiency Opportunities Act PAF Potentially Acid Forming

ESAP Energy Savings Action Plan REMP Rehabilitation and Environment Management

Plan

ESS Energy Savings Scheme RC Reverse Circulation

Page 8: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

vii

EPA Environment Protection Authority SWMP Site Water Management Plan

EPL Environment Protection Licence STSF South Tailings Storage Facility

EL Exploration Lease SG Specific Gravity

ft Foot TSF Tailings Storage Facility

GJ Gigajoules t Tonnes

HDPE High Density Polyethylene WRF Waste Rock Fill

KPI Key Performance Indicator wmt Wet Metric Tonne

Page 9: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

1

1 INTRODUCTION

This document has been written in line with the Guidelines to the Mining, Rehabilitation and Environmental

Management Process (MREMP)1 provided by the New South Wales (NSW) Department of Trade and

Investment, Resources and Energy (DRE) (formerly the Department of Industry and Investment).

Under the Mining Act 1992, environmental protection and rehabilitation are regulated by mining lease

conditions, including requirements for the leaseholder to prepare two main documents:

A Mining Operations Plan (MOP) which describes the manner in which the leaseholder proposes to

conduct mining, processing and rehabilitation consistent with development consent, and the conditions

imposed by the DPI and other agencies; and

An Annual Environmental Management Report (AEMR) which reports on the performance of the

leaseholder and ‘fine tunes’ the MOP.

Collectively, the MREMP aims to facilitate the development of mining in NSW and to ensure all mining

operations are safe, the resources are efficiently extracted, the environment is protected and rehabilitation

achieves a stable, satisfactory outcome.

This document will be provided to the following regulatory bodies for review:

NSW Department of Trade and Investment, Resources and Energy (DRE) (formerly the Department of

Industry and Investment);

Department of primary Industries;

NSW Office of Environment and Heritage (OEH) (formerly the Department of Environment, Climate

Change and Water);

NSW Dam Safety Committee (DSC); and

Cobar Shire Council (CSC).

1.1 History of Operations

Cobar Management Pty Ltd (CMPL) operates the Cornish, Scottish and Australian (CSA) Mine located 11 km

north of Cobar in the west of NSW. Mining has occurred intermittently on the CSA leases since the discovery of

copper, lead and zinc in 1871. However, it was not until 1961 that a significant resource was proven by Broken

Hill South Pty Ltd. Medium-scale mechanised underground mining subsequently commenced in 1965. The

mine was acquired by CRA in 1980 and sold to Golden Shamrock Mines Pty Ltd (GSM) in 1993. GSM was in

turn acquired by Ashanti Gold Fields in the same year. The mine continued to operate until 1997, when the

operation ran into financial difficulties and was placed in receivership. The mine was placed on care and

maintenance on the 20th

January 1998.

Conditions for reopening the mine were negotiated with the liquidator, and concessions were obtained from the

Government, including the excision of three areas of concern from the lease: the North Tailings Dam; the

1 DRE (2006) Guidelines to the Mining, Rehabilitation and Environmental Management Process. EDG03 version 3

Page 10: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

2

subsidence hole and adjacent old spoil material; and, a major coarse rejects stockpile (Big Mt Brown). CMPL

committed to reopening the mine in February 1999 with current underground and processing operations

commencing in July 1999 following the purchase of the leases and site facilities.

CMPL, a wholly owned Australian subsidiary of Glencore Xstrata continues to operate the CSA Mine, which is

currently the highest grade Copper and second deepest mine in Australia.

1.2 Consents, Leases and Licenses

CMPL has a large number of statutory approvals and associated legal obligations that regulate mining activities

on site. The status of CMPL main statutory approvals are listed in Table 1 to Table 3.

CMPL holds Consolidated Mining Lease 5 (CML5) for the CSA Mine operations and two small mining

purposes leases 1093 and 1094 (MPL1093 and MPL1094). CML5 occupies portions of five Western Land

Leases and Crown Land including parts of the Cobar Regeneration Belt. MPL1093 and MPL1094 occupy

Crown Land. These details are shown in Plan 1. Throughout this document these leases are collectively referred

to as the CSA Mine.

During the period 1 January 2012 to the 31 December 2012, CSA Mine operated in accordance with the CSA

Mine 2007-2012 MOP.

Page 11: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

3

Table 1 CMPL Mining and Exploration Leases (as at 31/12/12)

Lease Number Details Issue Date Expiry Date

CML5 CSA mine site. Licensed for Group 1 minerals (Sb, Cu, Zn, Pb, Fe, In, Au, Ge, Co, Cd, Bi & Fe

minerals).

2/12/1993 24/6/2028

MPL1093 Mining Purposes Lease for Water Harvesting.

Not licensed for minerals. 5/2/1947 5/2/2029

MPL1094 Mining Purposes Lease for Water Harvesting.

Not licensed for minerals. 5/2/1947 5/2/2029

EL5693 Exploration Lease (CSA Regional) 20 km north

of Cobar. The lease surrounds CML5. 8/2/2002 7/2/20121

EL5983 Exploration Lease (Delta) 20 km north of Cobar

and lies wholly within EL5693. 30/8/2006 29/8/20121

EL6140 Exploration Lease (Restdown) 40 km east

southeast of Cobar. Joint Venture (JV) project with Oxley Exploration Pty Ltd.

22/10/2003 21/10/20132

EL6501 Exploration Lease (South Restdown) 40 km southeast of Cobar. JV project with Oxley

Exploration Pty Ltd.

5/1/2006 4/1/2014

EL6739

Exploration Lease (Horseshoe 2) 65 km east of

Cobar. JV project with Oxley Exploration Pty Ltd.

26/3/2011 26/3/20132

EL6223 Exploration Lease (Shuttleton) 75km south

southeast of Cobar. JV project with AuriCular Mines Pty Ltd.

5/4/2004 4/4/2014

EL6907 Exploration Lease (Mt Hope) 145 km south of Cobar. JV project with AuriCular Mines Pty Ltd.

11/10/2007 10/10/20132

EL6868 Exploration Lease (Mt Hope) 160km south of

Cobar. JV project with AuriCular Mines Pty Ltd. 6/9/2007 5/9/20132

EL6381

Exploration Lease (Captain’s Flat) 15 km south of Captain’s Flat in south-eastern NSW. JV

project with Forge Resources Ltd and Ironbark Zinc Limited.

22/2/2005 21/2/2014

EL6840

Exploration Lease (Captain’s Flat North) 17 km north of Captain’s Flat in south-eastern NSW. JV project with Forge Resources Ltd and Ironbark

Zinc Limited.

19/7/2007 19/7/20132

Notes: 1. Renewal applications have been submitted

2. Renewal applications will be submitted during 2013

Page 12: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

4

Table 2 CMPL Land Tenure (as of 31/12/12)

Property Name

Locality WLL County Parish Plan

Number Lot Number

Red Tank CSA Mine 9565 Robinson Kaloogleguy 766965 4277

Red Tank East of mine 731 Robinson Kaloogleguy 766922 6336

Red Tank Immediately south

of mine 13844 Robinson Kaloogleguy 766965 4278

Gattaca South of mine 13844 Robinson Kaloogleguy 766741 4174

Gattaca South of mine 13844 Robinson Kaloogleguy 765641 927

Mopone Northeast of

tailings facility 1009 Robinson Mullimutt 768325 5414

Terramia South and east of

tailings facility 3667 Robinson Mopone 763396 1594

Table 3 CMPL Licences and Permits (as of 31/12/2012)

Licence Details Renewal Date

EPL No. 1864 Environmental Protection License. 28 April 2014 (review date)

Bore Licence No.

85BL256081

Bore licence certification under

Section 115 of the Water Act 1912. For the purposes of Test Bores.

8 October 2013

Workcover Licence Workcover NSW Licence to store Class 002 5.1 and 11D 1.1

explosives.

8 April 2013

07-100157-001

Radiation Licence

Licence to sell/possess radiation apparatus and/or radioactive

substances or items containing radioactive substances

No. 29023 - RR761, RR1384, RR911, RR907 6 May 2013

- RR21459 5 May 2014

- RR12793 18 October 2013

- RR12484 27 April 2013

- RR8858, RR8859 28 November 2013

Bonded Asbestos Removal

Licence No. 204696

Granted by NSW WorkCover for on-site removal of bonded asbestos

only.

12 December 2014

Local Development Consent No. 31/95

CSC Permit for use of CSA Mine Site by CMPL

Granted 26 June 1998

Local Development Consent No. 2006/LDA-00009

CSC Permit for Construction and

Operation of South Tailing Dam

Extension

Granted 22 June 2006

Local Development Consent No. 2009/LDA-00035

CSC Permit for South Tailings Storage facility Wall Raise

Granted 7 April 2010

Page 13: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

5

Mine Contacts

The management structure at the CSA Mine is displayed in the organisational chart in Figure 1. The structure

was revised during the 2012 AEMR reporting period with the appointment of a new General Mine Manager. The

CSA Mine management team and environmental contacts are listed in Table 4.

Table 4 CSA Mine Management and Environmental Contacts

Title Name Phone Email

General Manager Geoffrey Hender 6836 5111 [email protected]

Ore Processing Manager Derek Beehan 6836 5394 [email protected]

Mining Manager Aaron Nankivell 6836 5178 [email protected]

Health Safety

Environment & Training Manager

Tanya Gilbert 6836 5357 [email protected]

Finance Manger Michael Cox 6836 5124 [email protected]

Shaft Project Manager Les Kennedy 6836 5367 [email protected]

Graduate Environmental Officer

Susannah Sage 6836 5384 [email protected]

CSA Pollution Complaints

Line CSA switchboard 6836 5100 [email protected]

Figure 1 CMPL Organisation Chart 2012

Records

Management

Environmental

Ore Processing

Surface Maintenance

Tailings Dam

Project Mining

Engineers

Project Cost Controller

General Manager Geoffrey Hender

Manager Ore Processing

Derek Beehan

Manager Finance

Michael Cox

Manager Health, Safety Environment &

Training Tanya Gilbert

Manager Mining

Aaron Nankivell

Shaft Project Manager

Les Kennedy

Mining

UG Maintenance

Geology & Exploration

Technical Services

Accounts

Supply & Contracts

Health & Safety

Training

Page 14: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

6

1.3 Actions required from 2011 AEMR review

The 2011 AEMR review meeting and site inspection was held at the CSA Mine on the 3rd April 2012 and was

attended by representatives from the Western Catchment Authority, OEH, DRE, Cobar Shire Council and Peak

Gold Mine (PGM).

The 2011 AEMR review meeting minutes are provided in Appendix B. Actions arising from the meeting and the

sections of this report in which they are addressed are listed in Table 5. Table 6 provides an update on all

activities proposed for 2012 as listed in Section 6 of the 2011 AEMR.

Page 15: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

7

Table 5 Actions Required from the 2011 AEMR Review

Action Status Update and Reference

Surface Water Management CMPL to prepare and submit updated Surface Water Management Plan for the CSA Mine site (requirement from 2010 AEMR).

In Progress: Due Q1 2013 Section: 2.8.2

MOP 2013-2017 Develop and submit a MOP for 2013-2017 period for approval. The plan will be developed in accordance with existing MOP guidelines and draft REMP guidelines that are available.

Completed: December 2012

Elouera site CMPL to further investigate any requirements to manage the Eloura site and

determine if it is within the Mining Lease or CMPL owned property.

Completed: July 2012

Section: 3.15

Piping Requirements Complete a site wide audit of the current piping requirements. Remove all redundant pipes and ensure adequate bund capacity is available for all necessary pipes (such as tailings, backfill, process water, etc).

Completed: July 2012

Section: 5.2

Backfill Plant Ongoing focus on improving housekeeping in and around the Backfill Plant.

Ongoing Section: 2.10

TSF Embankment Drains Drainage to be designed and implemented on the TSF embankments to prevent erosion.

Completed: July 2012

Section: 2.8.2 & 3.22

TSF Embankments Formalise a monitoring schedule and documentation on inspections of TSF embankments for drainage, erosion, and the placement of green waste. Ensure the placement of green waste is justified and documented, and monitored.

Complete January and July

2012 Section: 2.8.5 &

3.22

TSF Rehabilitation Trial Ensure a monitoring and documentation program are in place to monitor the rehabilitation trials and vegetation growth on the tailings facility.

Completed: Aug 2012

Section: 5.5

Piezometer Data Review and improve the Piezometer Data interpretation and justification section of the AEMR Report.

Completed: Mar 2012

Section: 3.6

EPA requirements Develop and submit Pollution Incident Response Management Plan. Publish pollution monitoring data publically.

Completed: Jun 2012

Section: 3.1

Completed: October 2012 And Ongoing

Page 16: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

8

Table 6 Update on Proposed activities for the 2012 AEMR Period

Proposed Activity Priority

Ranking

Status Update

and Reference

Conduct annual TSF Surveillance Inspection by qualified Dam

Engineer. H

Completed:

January 2012

Section: 3.22

Finalise draft SWMP and submit to DRE and OEH. H

In Progress

Due: Q1 2013

Section: 2.8.2

Complete a site wide audit of the current piping requirements,

remove redundant pipes and ensure adequate bund capacity is

available for all necessary pipes.

H

Completed:

July 2012

Section: 5.2

Address design adequacies in concrete settling bund at the mill

including enlargement of the sump. H

Completed:

March 2012

Section: 2.3.1

Complete remediation works to manage the further separation

movement of concrete panels at the STSF western spillway as

recommended in the 2011 TSF Surveillance Inspection Report.

H

Completed:

July 2012

Section: 3.22

Develop and submit a MOP for the 2013 – 2017 period to DRE for

approval. H

Completed:

December 2012

Assess energy usage to determine commitments under EEO. If

triggered, CMPL will register by March 2013 and submit an

assessment plan by December 2013.

H

Completed:

October 2012

Section: 3.2.5

Investigate alternative backfilling methodologies to optimise the use

of waste rock fill underground and minimise any requirement to hoist

waste in the future.

H

In Progress

Section:

2.4.4

Investigate additional dust mitigation measures from the TSF

including: increasing the size, thickness and extent of waste rock

emplacement; and potential chemical treatments.

H

Incomplete

Rescheduled for

2013

Replace tailings thickener. H

In Progress:

October 2012

Section: 2.3.1

Complete scoping study to determine the options for introducing a

surface ore stockpile as part of the works associated with the Mill

Grinding Circuit upgrade.

H Complete:

Section: 2.3.2

Complete feasibility study on the use of paste fill in underground

operations and submit MOP amendment if required. H

In Progress

Section: 2.3.2

Implementation of new goat control contractor to improve the

management of feral goats. M

Completed:

January 2012

Section: 3.9

Consult with OEH to finalise commitments under ESAP including the

submission of a final report. M

In Progress

Section: 3.2.5

Page 17: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

9

Proposed Activity Priority

Ranking

Status Update

and Reference

Progress rehabilitation works at the Mill, Big Mount Brown and old

Slag Pile rehabilitation sites including the spreading of topsoil and

seeding.

M In Progress

Section:5.3 & 5.5.2

Prioritise and assess the feasibility of energy efficiency projects

identified through the energy assessment and develop an action plan

for implementation.

M

Completed:

July 2012

Section: 3.2.5

Investigate requirements to manage the Eloura site and determine if

it is within the Mining Lease or CMPL owned property. M

Completed:

July 2012

Section: 3.15

Investigate the remaining 4 areas on site suspected of

contamination. Data on the nature and level of contamination of

sites will assist in progressive rehabilitation to meet performance and

closure criteria.

M In Progress

Section: 3.7

Monitor prickly pear population and assess implement control

measures where required including the possible reintroduction of

cochineal infected segments.

M

Completed:

May 2012

Section: 3.10

Address key actions identified in the energy assessment gap analysis

to further develop sustainable energy and carbon management

practices.

M Ongoing

Section 3.2.5

Continue removing remaining pile of crushed Big Mount Brown

contaminated waste material. M Ongoing

Develop an underground settling and pumping system to allow

effective reuse of recycled water underground. M

Ongoing

Section 2.8.5

Liaise with DRE Derelict Mines to further progress the potential for a

NTSF rehabilitation project. M

Completed:

October 2012

Section: 5.4.1

Work with DRE Derelict Mines to plan for the rehabilitation of the

excised Big Mount Brown area and surrounding CSA Mine disturbed

land.

M Incomplete

Section 5.4.1

Conduct educational campaigns to achieve a recycling rate

consistently greater than 30%. M

Ongoing

Section: 2.6.1

Progress works to upgrade the grinding circuit in the mill in

conjunction with the ongoing shaft extension project. M

In Progress

Section:2.3.2

Implement fox baiting program in conjunction with surrounding

landholders. L Not Required

Page 18: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

10

2 SUMMARY OF OPERATIONS DURING THE REPORTING PERIOD

In 2012, the production rate was unable to be maintained above 1,000,000 tonnes (t); this was a poor result for

the mine after having 3 excellent years prior to this. Prior to 2009 the previous five years production average

was 720,000 t.

In 2012, budgeted production rates were set at 1,100,000 dry metric tonnes (dmt) of ore which would produce

175,708 dmt of concentrate and 50,077 t of copper (Cu). Actual production achieved in 2012 was below target

with 938,325 dmt ore milled, 127,644 dmt concentrate produced and 34,529 t of Cu.

The primary focus of the Ore Processing department for 2012 was to modify the plant and services to an extent

where long-term production and budget throughput could be maintained consistently. To this extent a number of

major projects were undertaken and completed during the year, including;

Mill HV Upgrade completed.

Feeder impact bed replacement completed.

150ft thickener repairs. Repairs completed in January and now construction is underway on

installation on a new tails thickener ready in Q1 2013.

Flotation floor concrete removal was completed.

Powerhouse HV Upgrade completed, currently working on disposal of redundant HV switchgear.

Power factor correction Stage 1 completed and Stage 2 underway.

MCC 01 power & distribution upgrade ongoing.

Conveyor 2/3 Diverter chute installation completed.

Works undertaken to upgrade the Mill grinding circuit in conjunction with the ongoing shaft extension project

commenced in 2012 with a scheduled completion date of Q3 2014. Projects include;

The construction and installation of a new surface coarse ore stockpile;

Installation of a new grinding mill; and

Installation of overland conveyors and associated equipment.

The primary focus for the Mining Department for 2012 was achieving projected ore production at the budgeted

grade and cost. A number of projects were completed or commenced in 2012, including:

Continued No1 Shaft Extension Project;

Continued Development of the infrastructure for, and support of, the No1 Shaft Extension Project;

Upgrade of the existing surface refrigeration plant;

Power supply ring main;

Introduction of a proximity detection technology underground;

Commenced extending fibre optic capability to the bottom of the mine; and

Introduction of new filters to minimize Diesel Particulate Matter from trucking fleet.

Page 19: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

11

The key projects planned for the underground mine in 2013 and 2014 include:

Progression of the No1 Shaft Extension Project;

Development of the drives and chambers required for the No1 Shaft Extension Project including

construction of new crusher, conveyors, drives and workshops;

Changing stope void fill medium from cemented hydraulic fill (CHF) to paste fill; and

New surface to 11 Level ventilation fresh air intake shaft.

Projects completed in 2012, coupled with those to be completed in 2013, will ensure an increase in sustainability

and a reduction in major process disruptions. This will provide more positive improvements and opportunities to

the operation.

2.1 Mineral Exploration

The CSA Mine 2012 exploration activities were principally focussed on underground drilling, however, A

number of surface exploration programmes were also completed. Surface exploration activities conducted

during 2012 are summarised in the following sections.

During 2012, pre-disturbance baseline studies for all new surface exploration programs requiring ground

disturbance and an annual inspection of rehabilitated exploration programs were completed by the Environment

Team. Both programs will be continued in 2013.

2.1.1 CML5

One diamond drill hole was completed on CML5 during 2012 targeting a magnetotelluric (MT) geophysical

anomaly to the south of the existing QTS South ore body. The drill site for this hole was rehabilitated during

2012 and inspected by CSA Mine Environment personnel. It is CMPL policy to inspect exploration drill hole

sites on the completion of rehabilitation works and annually thereafter to monitor the progress and success of

rehabilitation. Further MT surveys were conducted over the CSA Mine area during 2012. Disturbance from these

surveys was minimal (small electrode pits) and rehabilitation was carried out as the surveys progressed.

2.1.2 EL5693 CSA Regional

EL5693 field work during 2012 involved the completion of the reverse circulation (RC) drilling program and the

drilling of one diamond drill hole at Kendi prospect. Rehabilitation of all 2012 drill sites was completed during

2012. Sections of some lines from the CSA Mine MT surveys extended into EL5693. As with those lines within

CML5, rehabilitation was carried out as the surveys progressed.

2.1.3 EL5983 Delta

No field work was carried out on EL5983 during 2012. Approximately 300m of RC drilling that was planned

within the lease during 2012 will now be completed during 2013.

Page 20: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

12

2.1.4 EL6140, EL6501, EL6739 (Restdown, South Restdown and Horseshoe)

No field work has been conducted by CMPL on EL6140, EL6501, or EL6739 since 2009. These leases are

subject to a farm-out arrangement with Oxley Exploration NL. Eleven RC holes were completed by Oxley

within the EL6140 during 2012. All drill sites have been rehabilitated.

A total of 2,405 soil samples were collected across the three tenements. Sample sites were rehabilitated

immediately following collection of the samples, as per standard practice.

2.1.5 EL6223 (Shuttleton)

Three diamond drill holes were completed within EL6223 during 2012 and a fourth was in progress at year’s

end. Sites for the three completed holes were rehabilitated during the year. CSAMT/ AMT surveys were also

conducted on the lease during the year. As with the MT surveys conducted on CML5, these surveys involve very

little surface disturbance and rehabilitation was carried out as the surveys progressed.

Field work planned for EL6223 during 2013 involves completion of the diamond drill hole that was in progress

at the end of 2012. Further CSAMT/ AMT surveys and limited RC drilling was carried out as part of initial

testing of anomalies highlighted during the geophysical surveys.

2.1.6 EL6907, EL6868 (Mount Hope)

Four diamond holes were drilled from three sites during 2012. All three sites were rehabilitated. Third party

environmental consultants were engaged to provide CMPL with a review of environmental factors (REF). The

purpose of the REF is to assess environmental and heritage factors for exploration within the Nombinnie State

Conservation Area. The REF is expected to be completed early in 2013. Non-invasive soil sampling and surface

geophysical surveys are planned for 2013.

2.1.7 EL6381, EL6840 (Captain’s Flat)

Drilling planned for the Captain’s Flat project during 2012 was not completed. A non-disturbing fixed loop

surface electromagnetic (EM) survey was completed during the year. Diamond drilling, RC drilling and surface

geophysics programs are planned for 2013.

Surface exploration activities for the 2013 AEMR period will cover all tenements and will include diamond and

RC drilling as well as the basic non-invasive ground geophysical surveys and soil sampling. Sites will be

rehabilitated as soon as practicable after completion of programs, in line with departmental guidelines and

CMPL policy. Rehabilitation activities will include cleaning up the site, filling sumps, ripping (where

appropriate), and capping of drill holes.

2.2 Land Preparation

CSA Mining activities continue to minimise land clearing as best practice in order to preserve the natural

vegetation and stability of the surrounding environment. Where any clearing is required, it is managed through

the CSA Mine Work Permit System. Permission to excavate is granted through this procedure to ensure that the

Page 21: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

13

proposed area of disturbance has been checked for underground services (power and water) and approved for

vegetation clearing by the Environment Team.

This system applies to all employees and contractors at the CSA Mine and ensures considerations such as the

size of the proposed site, the stockpiling of soil and vegetation, search for any historical or cultural sites, and

drainage are all accounted for prior to approval of the works. Any actions or conditions associated with the

works are documented and signed off on the permit.

2.2.1 Topsoil

Land preparation and surface material stockpiling is assessed in all CSA Mine operations to ensure long term

storage requirements are met without further disturbance or unnecessary clearing. Approximately 29,700 m3

of

historically cleared areas at the CSA Mine have been identified as potential topsoil stockpile locations. The

majority of the areas are located in cleared areas surrounding the Tailings Storage Facility (TSF), hence

minimising potential future losses due to double handling and transport during rehabilitation works.

The management of all topsoil on site is carried out in accordance with the CMPL Topsoil Management Plan

which has been developed to ensure all topsoil handling, stockpiling and use is carried out in line with Mining

Lease conditions and Environmental Protection Licence (EPL) requirements.

Permanent stockpile height restrictions exist on site, with a maximum of 3m for topsoil and 5m for waste rock

stockpiles. CSA Mine encourages the establishment of vegetation on all topsoil stockpiles to enhance soil

viability and minimise erosion losses. Cleared vegetation around project sites or surrounding areas is often

spread over the topsoil stockpile sites to assist with revegetation.

No projects requiring land clearing occurred over the 2012 AEMR period and there are no plans for any major

land clearing works in 2013.

2.2.2 Underground Waste Rock

Underground mining operations at the CSA Mine produce approximately 400,000 t of waste rock annually.

Waste rock produced is predominantly disposed of into underground voids left by stoping operations. There are

occasionally cases in which the volume of waste rock generated by development exceeds the volume of void

produced by stoping operations (generally during the development of accesses to new resources). In order to

prevent production loss from development curtailment, surface hoisting of development waste has been

permitted during such times. Material permitted for hoisting is only from areas pre-assessed for acid generation

potential. Material identified as potentially acid forming (PAF) or acid forming (AF) is not permitted for

hoisting to surface. Waste rock is either used in rehabilitation activities (for capping) or as a resource for

construction works. The temporary Waste Rock Emplacement area at the CSA Mine is currently located between

the refrigeration plant and the concentrate storage sheds.

In the event that there are insufficient voids to fill underground for the volume of the waste rock that is projected

over the next five years, the CSA Mine proposes to develop a temporary waste rock stockpile for the initial three

years. This stockpile is to be located to the north east of the main site i.e. adjacent to the “Big Mount Brown”

Page 22: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

14

excised area. Pending the economic climate and the associated site production surface stockpiling of waste rock

will be further investigated in 2013 and 2014, as an additional temporary stockpiling area may be required.

Should this be the case then CSA Mine would liaise with the relevant regulators with the view to taking the

option on the mining lease area for the currently excised Big Mount Brown. This approach, being the preferred

option rather than seeking approval to clear an additional land area for the storage of rock. The intention is that

this would be a temporary stockpile location only, with material to be tested for Acid Mine Drainage (AMD)

potential and clean material to be used in future tailings storage construction with all remaining material to return

underground to fill empty voids at the end of the mine life (and progressively during mine life if practical).

2.2.3 Contaminated Land

Waste from the clean-up of contaminated materials, process spills and the de-silting of dirty or contaminated

catchment dams are disposed of at the South Tailings Storage Facility (STSF). During 2012, thirteen overflow

incidents involving tailings, backfill, hydrocarbons, grout, and non-hazardous chemicals were recorded at CSA

Mine. These spills resulted in a total of approximately 3,000 m3

of contaminated material being disposed of at

the STSF.

2.3 Construction

2.3.1 Construction Activities

Several construction projects were completed at the CSA Mine in 2012 including:

Tailings thickener upgrade:

Works commenced in October 2012 to construct and install a new tailings thickener. The present thickener is

structurally weak and needs increasing maintenance to ensure operability. The new thickener is 18m in diameter

and will be located to the south of the existing concentrate thickener with new bunding installed. The new

thickener has been designed to meet the demands of future production expansion throughput. Completion of this

project is scheduled for March 2013. Once the new thickener is commissioned and operating correctly the old

thickener will be removed.

Underground internal shaft extension:

Works commenced in early 2010 to extend the No. 1 Shaft by approximately 500m and to install a new winder.

These works will enable hoisting of ore and waste rock to the surface from a lower level in the mine, help deliver

fresh air to the bottom of the mine, and enable efficient transport of personnel to and from the surface.

Due to the top 250m of the underground shaft extension self-mining during the Raise Bore Operations in

December 2011 to January 2012, progress on the project was held up. Glencore accepted a project

recommendation to alter the method and take a Tandem Blind Sink (BS) approach to both sections of the

extension. The Shaft Extension Project Team & Contractor set about designing & supplying equipment,

resources and expertise for both BS arrangements for sinking from 9240m RL & 8958m RL. The project

convened an expert group of senior managers (inside Australia with conference call meetings weekly) to explore

a Ground Support Design (GSD) for sinking through the broken ground (this included overseas experts, such as

Glencore and Redpath, on an as needs basis).

Page 23: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

15

GSD and the associated testing program was completed after approximately 29 weeks of trials & tests. Final

Ground Support Designs were presented on 10th

December 2012 and sinking commenced 19th

December 2012

on the top section from 9240m RL. Risk Assessments were also carried out during this process. The GSD for this

top broken ground section also changed the GSD for the lower 250m section. During the 2012 period, the Mine

continued to drive roadways for the project to open up multiple work sites for the contractor. Progress also

continued over 2012 on the design, manufacture and delivery of essential equipment. The upper shaft

correctional works and clean up continued. This also involved surveying of the 3 critical locations for shaft

alignment (being surface down, 9240m RL and 8958m RL. The upper shaft correctional works also included a

review of the off shaft roadways by geo-technicians and the condition of the old concrete lining for a life of 25

years.

2.3.2 Scheduled Construction Activities 2013

Several construction works and smaller infrastructure improvement upgrades are planned for 2013, these

include:

Underground Internal Shaft Extension

The Shaft Extension Project team will upgrade its resources (CSA, Contractor and consultant resources) with

additional expertise during early 2013 as the sinking process at both sites begins. The first stage will be the

setting up of the lower sink site from approximately the 1st February 2013, followed by installation of the

furniture in the upper shaft 1,000m, ongoing detailed scheduled work at multiple work sites and finalisation of

the designs for the project.

Tailings Thickener Replacement:

As discussed in Section 2.3.1, a new fit for purpose 18m diameter, high rate tailings thickener will be installed

and operational by March 2013. This will replace the existing 46m diameter thickener which requires increasing

maintenance to ensure continual operation, and presents a risk of structural failure. The bunding apron has been

laid and the walls have been poured. The thickener installation was commenced in January 2013.

Mill Grinding Circuit Upgrade

In conjunction with the No.1 shaft upgrade, the installation of a new grinding classification circuit in the mill is

planned. This will include a conveyance system (comprising of 3 overland conveyors), a 30,000t conical

stockpile with 3 subterranean feeders (2 pans and 1 apron), a new 24x22ft SAG mill, and a classification circuit.

Tender selection and Definitive Feasibility Studies (DFS) for the Mill Grinding Circuit Upgrade have

commenced in 2012. The area where the new mill will be located is being prepared at present and construction

works are planned for later in the year with a completion date of Q1-2 2014.

Backfill area

A feasibility study on the use of paste fill in underground operations was initiated in 2012 and will be further

investigated during 2013. Pending the outcome of the feasibility study, CMPL will seek to implement paste fill

Page 24: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

16

to replace the current fill medium of Cemented Hydraulic Fill (CHF). The proposed works will involve a

significant alteration of the current plant and an associated stockpile. The project is set to begin construction in

2014 with the plant to be commissioned in the final quarter of 2015. Appropriate approvals will be sought prior

to works occurring in 2014.

2.4 Mining

2.4.1 Underground Resource Status

The current resource is estimated at 11.4 Mt with 5.9% Cu between 9275 m relative level (RL) to 8400m RL.

The 8400m RL is approximately 1900m below the surface. There is potential for further resources to exist at

depth and also within this RL range.

The current proved and probable reserves in the CSA Mine active ore bodies (QTS North and South systems)

from 9250m RL to 8400m RL stand at 6.0 Mt with 4.56% Cu. There is also potential for further reserves in

other systems, which are yet to be evaluated.

2.4.2 Production History and Production Forecast

Table 7 summarises the CSA Mine’s history from 2009 and the forecast for the next five years. Annual

production was subpar during 2012. Copper metal production for 2012 was 34,529 dmt; this is down from 2011

due to a lower head grade during 2012. Forecast mine production for the next five years is based on the shaft

extension works progressing during 2013 and finishing in 2014 allowing an increase in production.

Table 7 Actual and Forecast Production (dmt) (as of 31/12/2012)

Year 2009 2010 2011 2012 2013 2014 2015 2016 2017

Ore 1,067,927 1,067,459 1,035,000 938,325 1,100,000 1,100,000 1,100,000 1,200,000 1,300,000

Grade 5.00% 4.88% 4.33% 3.83% 4.72% 4.60% 4.82% 4.89% 4.70%

Cu Metal

53,936 50,059 56,500 34,529 50,081 48,725 51,177 56,705 58,931

Ore mined over the period 2009, 2010, 2011 and 2012 is between 30 – 40% greater than originally predicted in

the 2007-2012 MOP. The Grade however has been 13 – 15% lower than predicted in the MOP, with the overall

Cu metal production therefore 17% greater than MOP predictions. The increased production and lower grades

experienced over the past four years is reflected in future predictions as well as the updated CSA Mine 2013-

2017 MOP, which was completed at the end of 2012.

2.4.3 Estimated Mine Life

The short term plan is to continue mining at the current rate of approximately 1.1 Mt/a (dmt) to the 8670 level

(1600m below surface) in the QTS North and between the 9045 and 8985 levels (between 1195m and 1255m

below surface) in the QTS South. Current proved and probable reserves can sustain this rate for approximately 5

years, while there appears to be adequate resource below this depth in the QTS North and within the QTS South,

Page 25: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

17

Eastern and Western systems to sustain the current mining rate for at least a further six years. The current

mining rate equates to approximately 50m vertical advance per year.

During 2013, work will continue on the No. 1 Shaft to extend it down to the 8740m RL which will enable

hoisting up this shaft to the surface. The key benefits of this extension are to provide a far more efficient

hoisting and ventilation system for the mine. By hoisting ore from lower levels in the mine, there will be

reduced truck haulage distances and truck fleet numbers. It is anticipated that this shaft extension will allow the

mine production rate to increase to approximately 1.4 Mt/a (dmt) for the long term. With this mine production

rate and with current resource estimates, mine life is expected to be approximately 10 years.

2.4.4 Backfilling and Tailings

The CSA Mine continues to use CHF and waste rock to fill underground openings created by production

activities. Hydraulic fill is obtained by separating a suitable fraction of tailings and adding cement as required.

The target for contained fines in hydraulic fill is no greater than 10% less than 10 microns (µm), and this is

consistently achieved or bettered.

Over 300,000t of cemented and un-cemented hydraulic fill was placed into underground voids during the 2012

period, representing 54.70% of flotation tailings produced by milling operations. In addition, approximately

254,000t of waste rock was used to supplement the hydraulic fill and to fill other voids not requiring cemented

fill. The average (± standard deviation) size of the backfill product was 4.16% (± 0.28) passing 10 microns and

the average specific gravity was 1.78 (± 0.01). Total backfill was lower during 2012 due to issues with the

underground reticulation as well as shortfalls in production ore. Backfilling is planned to be back to over

450,000t per annum in 2013. Table 8 shows the total backfill production and final tailings loads for 2012.

Page 26: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

18

Table 8 Backfill Production and Final Tailings 2012

2012

Backfill Production Final Tailings

Cemented (dmt)

Un-cemented

(dmt)

% passing

10 microns

Specific Gravity

(dmt)

%

Flotation Tailings

Jan 33,899 6,184 4.10 1.80 40,176 50.06

Feb 14,802 2,970 3.78 1.80 58,194 76.61

Mar 24,344 6,679 3.94 1.78 39,626 56.09

Apr 36,625 6,564 4.24 1.78 28,480 39.74

May 25,549 7,070 3.92 1.78 36,787 53.00

Jun 18,228 3,435 4.59 1.79 32,671 60.13

Jul 10,182 2,262 4.27 1.78 21,081 62.88

Aug 28,610 5,338 4.26 1.79 44,200 55.28

Sep 31,227 4,311 4.35 1.78 38,895 52.25

Oct 26,361 5,798 4.64 1.77 35,164 52.23

Nov 24,723 5,394 3.91 1.77 36,174 54.57

Dec 35,387 5,822 3.93 1.79 31,862 43.60

Total 309,937 61,827 4.16 1.78 443,308 54.70

2013 Estimate

495,000 <10 1.78 - 1.82

429,292 53.50

Note:

dmt = dry metric tonnes

During 2013, CMPL will continue to investigate alternative backfilling methodologies to optimise the use of

waste rock fill and minimise any requirement to hoist waste, therefore decreasing the cycle time of the stoping

sequence. See Section 2.3.2 for information on the paste fill feasibility study planned for 2013.

2.4.5 Mining Equipment

During 2012there have been no significant changes in the overall number of mining equipment used at the CSA

Mine. In 2012, CMPL added several new pieces of mining equipment to the CSA fleet as part of the site

equipment management process. This includes: 3 Atlas 6020 dump trucks; 1 JCB 714 Cement Agitator; 1

Forklift; 1 Dieci Telehandler; 2 Isuzu NPS300 Service Trucks; 2 Isuzu FVZ140; 2 Kubota R420 and 2

Roboshot Maxijet Shotcrete. There are no significant changes in the number of mining equipment on site

projected for 2013.

With the continuation of the shaft extension project throughout 2012 and into 2013 there was an increase in the

number of contractors associated with these projects, and therefore an increase in the number of contractor light

vehicles. The number of contractor light vehicles increased from 20 in 2011 to 50 in 2012.

The current status of surface and underground equipment at the CSA Mine is shown in Table 9.

Page 27: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

19

Table 9 CMPL Current Mining Equipment (as of 31/12/12)

CMPL Equipment 2011 2012 Projected

2013

Atlas Copco M2D Rocket Boomer Drill 0 0 0

Atlas Copco Simba L6C Production Drill Rig 2 2 2

Atlas Copco MT5010 Dump Truck 1 1 1

Atlas Copco MT5010 Ejector Truck 2 2 2

Caterpillar AD55B Dump Truck 2 0 0

Atlas Copco MT6020 Dump Truck 2 5 5

Caterpillar 980H Loader 1 1 1

Caterpillar IT28F Tool Carrier 0 0 0

Caterpillar IT28G Tool Carrier 2 2 2

Caterpillar 930H 2 2 2

Caterpillar 12G Grader 2 2 2

Caterpillar TH460B Telehandler 1 0 0

Caterpillar TH360 Telehandler 0 0 0

Caterpillar D25-D Cement Agitator 0 0 0

JCB 714 Cement Agitator 0 1 1

Caterpillar Elphinstone AD40 dump truck 1 1 1

Caterpillar Elphinstone R2900 Loader (LHD) 7 7 6

Coles 25 tonne Crane 0 0 0

Tadano 35 Tonne Crane 1 1 1

Forklifts 4 5 4

Isuzu FTS 800 Water Truck 1 1 1

Isuzu FSS 550 Explosives Truck 1 1 0

Isuzu FTS 800 Explosives Truck 1 1 1

Isuzu FSR 700 Stores Truck 1 1 1

Isuzu MPR300 1 0 0

Light Vehicles 47 47 47

Merlo Telehandler 1 1 1

Sandvick DD420 Jumbo 3 2 1

Tamrock Cabolter 1 1 1

Terex UC15 Franna Crane 1 1 1

Normet Spraymec 1 0 0

Normet Scamec 0 0 0

Normet Chamec 1 1 0

Dieci Telehandler 0 1 1

Isuzu NPS300 Service Truck 0 2 2

Isuzu FVZ1400 0 2 2

Kubota R420 0 2 2

Normet Unilift 0 0 0

Page 28: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

20

Normet Utimec 0 0 0

Roboshot Maxijet Shotcreter 0 2 2

Contractor Equipment 2011 2012 Projected

2013

Caterpillar R2900 Loader (Pybar) 1 2 2

Caterpillar AD45 Haul Truck 2 2 2

Solo Production Drill 1 0 0

Robbins 32R Raise Drill (Raisebore Australia) 1 1 1

Caterpillar IT28B Loader (Raisebore Australia) 1 1 1

Caterpillar 926 Front End Loader 0 0 0

Cement Agitator JACON 0 2 8

Hino Cement Agitator (EDMS) 0 0 0

Caterpillar Telehandler (EDMS) 0 0 0

Fibre Crete Maxi jet 1 0 0

Light Vehicles 30 50 50

Tamrock Cabolter 7-5 (Macmahons) 1 0 0

Sandvick 7-5 Cabolter Drill (PYBAR) 0 1 1

Manitou MT1030S Telehandler (PYBAR) 0 1 1

Volvo L60E IT Loader (PYBAR) 0 1 1

Normet Agitator (PYBAR) 2 2 2

2.4.6 Mining Method

The mining method used at CSA Mine for the majority of stoping remains the same as in previous years, that is,

top down, continuous advance, long-hole open stoping. Most stopes are filled with CHF and the balance is filled

with development waste. Some bottom up long-hole open stoping was carried out in 2012 and this will continue

in the 2013 reporting period.

2.4.7 Mine Development

During the 2012 AEMR period, underground horizontal development advancement totaled 4,822 m. The Mine

vertical section provided (Plan 4) details mine development over 2012 and the outlook for 2013. Section 2.2.3

provides further detail on the Shaft Extension development project.

Mining has focused on the K, O and S lenses of the QTS North system and from the QR1 lens in the QTS South

system during the past five years and will continue to do so for the 2013 AEMR period. Ore has been extracted

as required from other smaller QTS North lenses to supplement ore supply and to provide an optimal feed grade

to the mill, as allowed by mining sequences and ground stress management. A similar approach will be taken

over the 2013 mining period. In addition it is planned to mine crown pillars from the upper sections of the QTS

north ore bodies as required.

Page 29: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

21

Stoping is almost complete above the 8850 level in the QTS North except for some crown recoveries. The QTS

South mining is complete above the 9045 level, with a new stoping block to be developed below 9045 in the

QTS South, the bottom of the ore body is currently estimated at 8985. During the 2013 reporting period, mining

will continue below the 8890 level in the QTS North and below 9045 level in the QTS South.

2.4.8 Mine Production

Actual stope performance and metal output for 2012 was below the budgeted figures. This was mainly the result

of lower utilisation of equipment, issues with the stoping and unplanned delays. Variations in monthly grades,

against budgeted figures, reflect timing fluctuations of individual stopes. Table 10 shows the comparison of

monthly budget and actual production performance during 2012.

Mine production was sourced from a variety of stopes within the mine. The QTS North Ore System provided

100% of the ore produced.

Table 10 CSA Budget versus Actual Mine Production 2012

2012

Budget Actual

Tonnes (dmt)

% Cu Tonnes (dmt)

% Cu

Jan 90,795 4.97% 92,393 4.00%

Feb 81,916 5.22% 86,503 3.26%

Mar 92,547 4.32% 83,382 3.59%

Apr 91,034 4.74% 79,415 3.22%

May 93,388 4.94% 83,726 4.35%

Jun 89,114 5.07% 58,043 2.65%

Jul 93,838 4.57% 37,417 3.01%

Aug 91,860 4.38% 92,677 4.72%

Sep 91,379 5.17% 88,431 4.37%

Oct 93,691 4.62% 73,467 3.23%

Nov 95,850 3.87% 74,997 3.37%

Dec 94,229 4.90% 82,323 3.51%

2012 Total 1,100,000 4.66% 932,774 3.69%

Note:

dmt = dry metric tonnes

2.5 Mineral Processing

2.5.1 Ore Characteristics

Minerals present in the CSA Mine ores are mainly chalcopyrite, with lesser cubanite, pyrite and pyrrhotite and

very minor bornite, sphalerite and galena with traces of silver. Quartz, siltstone clasts, calcite, magnetite and

chlorite form the gangue to the sulphide minerals.

Page 30: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

22

2.5.2 Metallurgy

The milling circuit consists of two primary semi-autogenous mills (SAG) in either open or closed circuit as

required, with hydrocyclones, and a third mill of same size that originally operated as a SAG mill but is now

used as a secondary ball mill. After grinding, ore slurry is pumped to the flotation circuit comprising of rougher,

scavenger, cleaner and re-cleaner stages that use mechanically agitated flotation cells. Two banks of Wemco

rougher cells and one bank of Outotec scavenger tank cells float the sulphides until generating a final tail that is

sent to the tailings thickener. Two banks of Denver cells and two banks of Dorr Oliver cells perform cleaning

and re-cleaning flotation of rougher concentrate. Recovery of Cu minerals, mainly chalcopyrite, is excellent

with typically 95% to 98% of the Cu and around 83% of the silver reporting to the concentrate. The concentrate

grade generally ranges between 26.5% and 29.0% Cu and 58% and 92% silver (Ag). Metal Recovery for 2012 is

shown in Table 11.

Table 11 Metal Recovery 2012

2012

Tonnes Treated

Feed Metal Concentrate

Grade Recovery Production

dmt Cu (%) Ag

(g/t) Cu (%) Ag (%) dmt Cu (%)

Ag (g/t)

Jan 93,896 4.17 14.6 96.92 86.87 13,873 27.39 85.85

Feb 85,888 3.36 14.09 96.16 82.83 10,071 27.56 99.57

Mar 81,566 3.87 15.64 95.84 77.92 10,894 27.74 91.26

Apr 81,015 3.24 11.63 96.43 82.28 9,686 26.1 80.01

May 81,533 4.47 14.73 96.73 86.25 13,127 26.86 78.93

Jun 61,261 2.88 10.35 95.91 79.02 6,176 27.44 81.13

Jul 37,697 2.99 12.28 93.57 80.68 4,044 26.07 92.33

Aug 93,661 4.87 21.24 95.89 83.33 16,369 26.73 101.25

Sep 87,716 4.57 16.68 96.42 88.2 14,241 27.11 90.61

Oct 76,036 3.4 11.9 96.35 71.81 8,530 29.22 76.39

Nov 74,307 3.62 14.34 95.23 79.04 9,763 26.24 86.28

Dec 83,729 3.54 13.05 95.83 81.53 10,871 26.11 80.96

Total/Avg 968,221 3.83 14.51 96.11 82.22 127,644 27.05 92.71

(+/- SD) -69829 -0.87 -2.7 -0.31 4.06 -31743 -1.45 6.21

2013 Estimate 1,100,000 4.72 18 96.45 80 195,856 28.1 88.87 Note:

dmt = dry metric tonnes

%= percent g/t= grams per tonne

Flotation concentrate is pumped to a conventional thickener where it is dewatered. Thickener underflow is

pumped to a Filter Feed Tank. This slurry is pumped to two Ceramic Vacuum Disc Filters where water is

removed. The filtered concentrate is discharged by conveyor to stockpiles located within either of two

concentrate storage sheds. The concentrate has a moisture content of approximately 9.5%. Reagent

consumption figures for ore processing in 2012 are provided in Table 12.

Page 31: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

23

Table 12 Reagent Consumption 2012

2012

Reagent Consumption (t)

Cement Grinding

Media Flocculent Lime Collector Frother

Nitric Acid

Delvocrete

Jan 130.90 87.38 0.28 0.00 1.42 0.06 11.55 1.28

Feb 628.47 75.89 0.05 0.00 0.38 0.53 3.92 1.92

Mar 226.74 39.09 0.05 0.00 1.19 -0.36 3.84 0.67

Apr 5,228.04 69.07 0.15 0.00 1.61 0.07 4.33 0.14

May 1,571.63 65.24 0.20 0.00 1.33 0.00 3.92 1.01

Jun 1,348.73 51.49 0.10 0.00 0.65 0.02 12.53 2.07

Jul 564.50 29.49 0.10 0.00 0.38 0.01 1.96 1.27

Aug 2,283.56 60.19 0.13 7.80 1.57 0.03 6.42 1.49

Sep 1,610.61 71.75 0.20 5.28 1.15 0.08 6.14 1.72

Oct 2,221.97 30.29 0.05 5.66 2.35 0.64 6.01 1.58

Nov 1,753.44 57.82 0.10 2.26 0.74 -0.13 5.60 0.78

Dec 2,241.80 70.91 0.10 0.00 0.00 0.27 7.92 1.42

Total 19,810 708.57 1.5 21 12.78 1.22 74.16 15.35

2013 24,000 1,200 9.00 25.00 19.80 3.62 79.05 17.00

Estimate

2.5.3 Concentrate Storage, Handling and Transport

Concentrate is loaded by a Front End Loader into purpose built, fully enclosed, steel containers on railway flat

cars (wagons). An automatic lid lifter assists with the container loading process. The trains currently in service

can carry approximately 2,313 wet metric tonnes (wmt) of concentrate. This is railed to ConPorts Pty Ltd’s ship

loader at Port Waratah, Newcastle, for storage and export shipment by ocean freight. This concentrate is

exported to overseas smelters in India, China and Malaysia.

2.6 Waste Management

CMPL have long recognised the need for a reliable and regular waste removal and recycling service for the CSA

Mine that meets environmental, safety, operational, future growth and financial requirements. The CSA Mine

Waste Management System aims to achieve the following objectives:

Cost effective waste management and recycling system;

A holistic approach to waste minimisation and recycling;

Maximise recycling outcomes where possible to minimise waste to landfill;

Provide accurate invoicing and waste tracking receipts; and

Assist where possible to enable the provision of recycling for the town of Cobar.

Page 32: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

24

2.6.1 General Waste

General waste at the CSA Mine is separated into co-mingled recyclables and non-recyclable/putrescible waste.

Dubbo based company JR Richards & Sons Waste and Recycling Services (JRR) is contracted for the collection

of both waste streams from the CSA Mine. This service includes the supply and servicing of separate, colour-

coded general waste and co-mingled recycle bins.

All non-recyclable and putrescible waste is taken to the Cobar landfill facility for disposal, while all co-mingled

recyclable waste is transported to the JRR Material Recovery Facility in Dubbo for processing and eventual sale.

This co-mingled service allows for all recycle materials to be collected together, including paper, cardboard,

PET/HDPE plastics, aluminium, glass and tin.

The average recycling rate for 2012 was 23%, and ranged between 16% (January) to 35% (July). The average

recycling rate decreased between 2011 (26%) and 2012 (23%). Although the percentage of waste recycled in

2012 had decreased since 2011, the overall volume of waste recycled had increased in the 2012 reporting year,

see Table 13. Increased recycling volumes and a marginally decreased recycling rate can be attributed to the

increased number of contractors working on site and generating additional waste during 2012.

Table 13 Waste Collection Results (2010, 2011, 2012)

Year General

waste (kg) Recyclables

(kg) Total (kg)

Per cent Recycled

2010 70,100 18,620 88,720 21.0%

2011 60,420 20,740 81,160 25.6%

2012 93,400 29,840 131,590 22.7%

In 2012, recycling educational campaigns continued and included newsletter articles and site wide emails aimed

at encouraging CSA Mine employees to recycle on site, and also to bring their recycling from home and utilise

the recycling bins provided in the car park. In 2012, CSA Mine also promoted recycling through their first

“Waste to Art Competition” which was undertaken in November 2012 as a part of National Recycling Week

(refer to Section 4.2.4).

Figure 2 below shows the monthly general waste volumes and the recyclable component as a percentage.

The aim over in the 2013 reporting period is to achieve a recycling rate consistently greater than 30% recycled.

Ongoing educational campaigns in 2013 will continue to include National Recycling Week and Clean Up

Australia Day.

In 2012, CSA Mine also trialled different bins on site (hook bins) and increased the size of some bins in key

locations (from 1.5m3 to 3m

3). The frequencies of waste collections also changed in 2012. Waste has previously

been collected fortnightly since 2009 and is now collected weekly. In terms of waste management, the focus of

2013 is to further investigate underground waste management to improve the separation of general waste and

recycling in the underground mining operation. With the implementation of successful waste separation

strategies underground, the recycling rate is expected to significantly improve in 2013.

Page 33: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

25

16%

23% 24%

27%

31%

24%

35%

30%

23%

19% 20% 20%

0

2000

4000

6000

8000

10000

12000

14000

Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12

Waste

(kg

)

CSA Mine Waste Management Performance 2012

General waste (kg) Recyclables (kg) % Recycled

Figure 2 CSA Mine General Waste Management Performance 2012

2.6.2 Industrial Waste

Industrial waste at the CSA Mine is split into the main waste streams: metals, rubber, hydrocarbons, and

sewerage waste. Each of these waste streams is managed and tracked separately.

Metal waste includes steel and copper cables, both of which are removed off site for recycling. A total of 513.75t

of scrap steel was sold to external contractors during 2012 for recycling, which has greatly increased since 2011

(132t). In 2012, 38 loader and 27 truck tyres were also sent off-site for recycling.

Hydrocarbons are recycled where possible from surface (processing plant and workshops) and underground

(workshops). An EPA licensed contractor collects the waste oil on an as needs basis. During 2012, 87,750L of

waste oil was collected by Renewable Oil Services Pty Ltd (EPA Transport Licence No. 12991; EPA Depot

Licence No. 13092). Waste grease and other mixed oily products (rags, plastic liners, gloves, filters, filters etc.)

are collected by the same licensed contractor on an as need basis. A total of 8,364kg of waste grease and

8,028kg of hydrocarbon contaminated products were removed from site during 2012. A further 4.12t of waste

batteries were removed from site for recycling over the 2012 period.

Underground sewage waste is removed from site by a licensed contractor and disposed of at a designated pit

provided at the CSC landfill. During 2012, approximately 342,100L of sewage waste was removed by Cobar

Mining Contractors.

Page 34: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

26

2.6.3 Underground Waste Rock

Waste rock produced by underground mining operations is disposed of into underground voids left by stoping

operations, or hoisted to the surface (only during periods of low void inventory). Cumulative mine waste

production is provided in Table 15 in Section 2.7.4. A total of 431,675t of waste rock production is budgeted

underground for the 2013 period.

2.6.4 Tailings Waste

Backfill fines, or flotation tailings when backfill is not required, are sent to the Final Tailings Thickener

for dewatering prior to pumping to the TSF. Target moisture content of final tailings is Specific Gravity

(SG) = 1.5. Tailings are pumped approximately 2.2 km in a High Density Polyethylene (HDPE)

pipeline to the TSF and deposited from a central raised causeway.

The amount of tailings deposited is regularly monitored; a monthly summary is provided in Table 8 of

Section 2.4.4. A total of 438,917t of tailings were deposited between 1 January and 31 December 2012 at

an average production rate of just over 1,199t per day. This accounted for 54.1% of flotation tailings.

The remaining 45.9% of the flotation tailings was backfilled into the underground workings.

Thickened tailings will continue to be deposited in the STSF over the 2013 AEMR period. Tailings will

be deposited in thin discrete layers, approximately 100mm in thickness from the end of the discharge

causeway. Discharge is distributed between 9 spigots close to the end of the causeway to limit the

discharge velocity of tailings from the pipes. The distribution of flow via at least three spigots has

resulted in the development of a well-defined beach.

Deposition of tailings will be alternated between the North West side and South East side of the causeway.

This approach is intended to maximise evaporative drying by sun and wind exposure of the non-active

tailings beach area. This structured deposition method will help reduce rate of rise of the tailings by

allowing tailings on the beach to dry and desiccate before it is subsequently covered with fresh wet

tailings. This will achieve a high dry density of the tailings, increase water recovery and optimise storage

capacity. Based on our survey report in December 2012 the STSF has approximately 11months deposition

remaining and will reach capacity in October 2013. CSA Mine is currently working towards a lift on the

STSFE scheduled for mid-2013 which will increase deposition capacity of the STSF through to 2015.

2.7 Ore and Product Stockpiles

2.7.1 Ore Stockpiles

Ore hoisted to surface is stored in any of four concrete, open topped storage bins. Total capacity is

approximately 6,000 wmt.

Two definitive feasibility studies were completed in 2012 to ascertain the most suitable ore storage

system for the mill department with the future mill upgrade in mind. The studies concluded that a

Page 35: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

27

30,000t conical stockpile is the best option for future operations. Ore from the surface stockpile will be

delivered to the mill via 3 feeders (one apron and two vibratory pan feeders).

2.7.2 Product Stockpiles

Flotation concentrate is stored in either of two concentrate storage sheds, with combined storage

capacity of approximately 25,000wmt. The sheds are covered and partially enclosed which assists in

the minimisation of dust generation. Each shed has a concrete floor and wall bunds which

minimises concentrate losses to the environment.

Approximately 3,970dmt of Cu concentrate was stored in the concentrate storage sheds as of 31

st

December 2012. A stockpile of approximately 7,376dmt was stored at the port awaiting shipment.

2.7.3 Topsoil Stockpiles

Current stockpiles of topsoil at the CSA Mine total approximately 63,329m3. An estimated 5,500m

3 of topsoil is

stockpiled behind the NTSF from operations prior to CMPL taking over in 1999. All remaining topsoil on site

resulted from the development of the STSFE in 2006 (50,969m3) and the extension to the TSF Decant Dam in

2010 (6,680m3).

Topsoil and subsoil was handled according to best practice procedures by separating topsoil and subsoil in two

separate stockpiles during the construction of the Decant Dam Extension in 2010. Topsoil from the STSFE

development is stockpiled along the TSF access road (18,714 m3) and at the site of the original interim stockpile

adjacent to Railway Dam (32,255 m3). The new stockpile resulting from the Decant Dam extension is stockpiled

adjacent to the southern wall of the Decant Dam facility. These small stockpiles (based on a maximum height of

3 m) are located close to the TSF to ensure potential losses due to excessive handling are minimised. This

topsoil will remain stockpiled until required for rehabilitation purposes on site. Where available, green waste

has been placed on topsoil stockpiles and stockpiles seeded to encourage organic matter growth and the

maintenance of a viable seed bank.

Page 36: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

28

Table 14 displays CSA topsoil stockpile information and Figure 3 displays topsoil stockpile locations.

Page 37: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

29

Table 14 CSA Identified Topsoil Stockpiles

Stockpile No.

Stockpile Location

Volume (m3)

Storage Capacity

Remaining (m3)

Source Date

Placed Treatment

1 TSF Access

Road 18,474 18,823

Development of STSF Extension

2006 Green waste placed

2 Adjacent TSF Decant Dams

(topsoil) 3,420 0

Extension of the TSF Decant Dam required

for STSF wall lift 2010

Oat cover crop seeding (June 2011)

Adjacent TSF Decant Dams

(clay) 3,440 0

Extension of the TSF Decant Dam required

for STSF wall lift 2010

Oat cover crop seeding (June 2011)

3 Adjacent

Railway Dam 32,255 3,577

Development of STSF Extension.

2006 n/a

4 NTSF 5,500 0 Unknown (placed prior to CMPL taking over operations in 1999)

Prior to 1999 n/a

TOTAL 63089 22400

Figure 3 CSA Topsoil Stockpile Locations

No major excavation works were undertaken in 2012 or are planned for 2013, therefore no significant volumes

of topsoil are expected to be generated. Any useful quantities of topsoil from any land disturbance activities will

Page 38: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

30

continue to be stripped and stored with existing stockpiles to provide suitable material to facilitate future

rehabilitation.

2.7.4 Waste rock Stockpiles

In 2012, a total of 3,051t of underground waste rock was hoisted to the surface. The volume of waste rock

hoisted to the surface is a function of underground mine development progress. In 2012, development progress

achieved led to a deficit in available underground waste storage capacity. Prior to hoisting to surface, all

material is tested to ensure it is not potentially acid generating. The material hosted to the surface in 2012 is

currently stockpiled at the temporary stockpile area, located near the ore processing plant, and will be utilised in

2013 as a part of TSF improvement works.

Table 15 summarises stockpile estimates and waste production at the CSA Mine for 2012 and the forecast for

2013.

Table 15 CSA Cumulative Waste and Stockpile Production

Cumulative Waste & Stockpile Production

Start of 2012 reporting period

End of 2012 reporting period

End of 2013 reporting period

(estimate)

Topsoil stripped (m3)

63,089 63,089 63,089

Topsoil used / spread (m3)

1,340 1,340 1,340

Waste Rock (t) (surface hoisted)

318,836 321,887 551,887

Ore (dmt) 9,278,654 10,216,980 11,316,980

Processing Waste (tailings) (dmt)

5,560,969 5,999,886 6,442,242

Backfill (dmt) 2,616,711 2,988,475 3,467,694

Cu Concentrate (dmt)

1,637,574 1,765,218 1,943,643

In comparison to the predicted waste and stockpile production figures estimated in the 2007 – 2012 MOP for the

2012 period, actual production volumes of ore, backfill and copper concentrate were higher than predicted in the

MOP due to better than originally forecast production rates and ore grades. The updated 2013 – 2017 MOP will

reflect the revised and improved production rates for future forecasts.

2.8 Water Management

2.8.1 External Water Sources

The CSA Mine lies within the Darling River Basin with the nearest tributary being the Bogan River located

approximately 120 km to the east of the mine. CMPL purchase bulk raw water from the Cobar Water Board.

Page 39: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

31

Cobar raw water comes from Burrendong Dam via the Macquarie River and the Albert Priest Channel, and is

supplemented by the ground catchment area around the Cobar storages during periods of rainfall. Water from

the Macquarie River is diverted at Warren via a 73 km open channel (Albert Priest Channel) to the Bogan River

Weir Pools in Nyngan. From here it is pumped via a dual underground 130km long steel pipeline that can

deliver 200 l/s or 17.2 ML per day to the 1.4 ML storage tank at Fort Bourke and the Cobar reservoir

approximately 4 km north west of Cobar.

Water from the Cobar storages is pumped to the local mines via an underground pipeline. The mine water

allocation is part of a water entitlement which is shared between CMPL, Peak Gold Mine and CBH Resources

(Endeavor). The CSA Mine site is entitled to a raw water allocation of 1,356 ML per annum (determined by the

period of July – June each year) and processes raw water to produce potable water on site.

During periods of drought and low rainfall, the Cobar Township, and therefore the CSA Mine, relies on this

external supply of raw water to maintain operations. Figure 4 shows the water storage level and rainfall for the

Burrendong Dam over 2012.

0

5

10

15

20

25

30

35

40

45

0

20

40

60

80

100

120

140

Jan-12 Mar-12 May-12 Jul-12 Sep-12 Nov-12

Rai

nfa

ll (m

m)

Effe

ctiv

e F

ull

Sto

rage

vo

lum

e (

%)

Burrendong Dam 2012

Rainfall (mm) Effective Full Storage Volume (%) Mean

Figure 4 Burrendong Dam Water Storage Level (%) and Rainfall (mm) 2012

2.8.2 Surface Water Sources

In 2011, consultants were commissioned by CMPL to develop a Site Water Management Plan (SWMP). The

SWMP is currently in draft, finalisation is expected in quarter one 2013. CMPL acknowledges the finalisation of

the CSA Mine SWMP is long overdue; this project was started in partnership with a consultant in May 2011

with the intention of completion by December 2011. The quality of the initially submitted report was very poor,

Page 40: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

32

and therefore the project started over with a more defined and clear approach in 2012. This document is still

unsatisfactory and incomplete. CSA are working through the contractual arrangements to have this document

closed out by March 2013, and may consider seeking alternative external assistance in 2013 to redo the CSA

SWMP with the desired quality outputs by mid-2013. The plan will be submitted to DRE on finalisation. The

SWMP strategically manages water on site in order to:

Prevent discharge of contaminated water;

Reduce reliance on water from external sources;

Reduce losses from evaporation and seepage;

Maximise water re-use on site by recycling where practicable;

Separate clean, contaminated and dirty water sources where practicable.

The SWMP outlines operational procedures to cover critical water management issues and events (e.g. forecast

high rainfall events and water storage dams are at capacity). These procedures ensure there are appropriate

responses to events with controls put in place to prevent breaches of EPL1864 including the discharge of

contaminated water. The procedures also outline measures to ensure there is maximum efficiency in water re-

use.

As part of the SWMP CSA Mine catchment boundaries were detailed and mapped using the Digital Elevation

Model (DEM). There are thirty five catchments within the mine lease boundaries for which rainfall runoff is

controlled and prevented from leaving site. These catchments are summarised in Table 16

Table 16 Summary of Catchment Areas

Catchment Identification

Catchment Area (m2)

Classification Direction of Flow Is Rainfall

utilised

C1 15,110 Clean Borrow Pit Dam Yes

C2A 17,790 Clean C2B Yes

C2B 9,645 Clean C4 Yes

C3A 2,855 Clean C4 Yes

C3B 32,280 Clean C4 Yes

C4 15,040 Clean C4 Yes

C5A 37,935 Dirty C2B Yes

C5B 9,645 Dirty C1 Yes

C6 33,830 Clean C2A Yes

C7A 8,025 Dirty C8B Yes

C7B 6,325 Dirty C8C Yes

C8A 9,145 Dirty C7A Yes

C8B 16,420 Dirty C8C Yes

C8C 14,550 Dirty C9B Yes

C9A 5,705 Dirty C8C Yes

C9B 15,195 Dirty Borrow Pit Dam Yes

Page 41: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

33

C10 7,454 Dirty C9B Yes

C11 9,695 Dirty C10 Yes

C12A 14,815 Dirty C12B Yes

C12B 14,880 Dirty C11 Yes

C13 30,130 Dirty C9B Yes

C14A 10,940 Dirty C12B Yes

C14B 24,345 Dirty C13 Yes

C15 24,115 Clean - No

C16A 17,055 Clean C20B Yes

C16B 29,146 Clean C12B Yes

C17A 52,350 Dirty C17B, C17C No

C17B 13,520 Dirty C17C No

C17C 82,205 Dirty - No

C18 116,155 Dirty - No

C19A 19,290 Clean - No

C19B 13,785 Clean - No

C19C 21,775 Clean - No

C20A 11,990 Dirty C8A Yes

C20B 9,920 Dirty C20C Yes

C20C 10,725 Dirty C12B Yes

Catchment areas classified as contaminated or dirty make up the bulk of the catchment areas (approximately

57ha) and lie generally around the Ore Processing Mill and site infrastructure areas. These areas all currently

drain to the Operational Water Dam and Borrow Pit Dam. The catchment areas for the clean water runoff lie to

the south and west of the mill area and comprise approximately 2 ha. These catchments also currently drain to

the Borrow Pit Dam. Water from the Borrow Pit Dam is pumped directly into the Pork Pie Dam. This is the

process water dam which makes up the Pork Pie catchment (C16). The Borrow Pit Dam is the key storm water

catchment dam, while Pork Pie Dam and the Operational Water Dam are the key process water storages.

In addition to the surface water catchment dams within CML5, the two old mine dams (sample locations S15 and

S16 in Plan 2) located on the MPL’s to the north-west of the site were constructed as a water supply for mine

operations prior to the 1960’s. Both catchment areas are large and relatively undisturbed comprising open grass

areas and scattered to dense scrub, hence both dams are used to monitor baseline water quality. These dams act

as a potential alternative water supply for the CSA Mine operations in the future. Water can be pumped from

these dams to the process water system if required.

A summary of all current water storages at the CSA Mine is shown in Table 17. Plan 2 shows the location of

existing storage dams and dam sampling locations.

Page 42: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

34

Table 17 CSA Mine Water Storage

Stored Water

Volumes Held (ML) Freeboard (m)#

Storage Capacity

Start of 2012 Reporting

Period

End of 2012 Reporting

Period

End of 2012 Reporting

Period

Clean Water

Old Mine Dam (N) MPL1093 (S15) 240* 180* 0

Old Mine Dam (S) MPL 1094 (S16) 240* 180* 0

TSF Stormwater Collection Dam (S11) 5* 0 0

Raw Water Storage Tank (S2) 25 25 25

Dirty Water

Railway Dam (S8) 4.79 0 0

Wash Bay Evaporation Pond 0.03* 0.03* 0

Contaminated Water

Borrow Pit Dam (S4) 17.57 0 0

Retention Dam (S9) 2.99 0 0

Old Smelter Runoff Dam (S13) 2.04 0 0

North Runoff Dam (S10) 1.34 0 0

Old CSA Spoils Dam (S1) Excised Area 4.66 0 0

Pork Pie Dam (S14) 25.9 15.9 12.5

North TSF (Excised Area) 1060* 0 0

South TSF (S3) 17 0 0

STSF Extension 5* 0 0

TSF Decant Dams (combined) (S5) 93 0 0

Operational Water Dam 7* 3.5* 4*

Total 1751.32 404.43 41.5

Notes:

1. Values marked * are estimates based on site measurements as up to date survey data does not exist.

2. # Freeboard levels were not measured at the end of 2012. Freeboard will be measures for all subsequent AEMR’s.

The STSF catchment, despite its large surface area, does not retain any water. All water from the STSF

catchment reports to the STSF Decant Dams to be pumped back to Pork Pie Dam for use as process water. A

new discharge drain was built in the STSF in March 2010, designed to allow for gravity release of supernatant

water and stormwater from the toe of the tailings mound into the lined compartment of the Decant Dam. Due to

operational issues with low density material and flushing of blocked lines, excess tailings have flowed into this

drain and subsequently into the lined decant dam. The construction of the additional compartment of the Decant

Dam in 2010 means there is still adequate capacity to provide environmental flood containment under the Dam

Safety Committee (DSC) guidelines (i.e. rainfall runoff resulting from a 1 in 10 year 72 hour design storm

event).

Dams on site must maintain a 300 mm freeboard at all times. Dams above 5 ML have spillways that ensure water

levels cannot overtop the dam walls. Old Mine Dams (S15 and S16) do not have a spillway and are not used

operationally. Borrow Pit Dam (S4) also does not have a spillway at present, this dam is kept empty and any

stored water following rainfall is pumped to Pork Pie Dam. Installation of a spillway on the Borrow Pit is

Page 43: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

35

scheduled for 2014. As part of everyday site management the water levels in all of the operational water dams

are checked every 6 hours. If any dams are reaching capacity water is pumped to Pork Pie Dam for use in the

Mill and underground.

2.8.3 Surface Water Drainage

Improvement of the surface water drainage system at the CSA Mine continued in 2012. Surface water drainage

works were completed in 2012 partially around the TSF catchments to satisfy the recommendations made in the

2011 NSW Dam Safety Committee Surveillance Report Inspection.

These surface water drainage improvements include;

The drainage bund along the toe of the old perimeter embankment on the eastern side of the STSF was

remediated where erosion damage had occurred. The erosion points were all filled using a combination

of topsoil and rock filling and then battened down to prevent damage to the toe of the STSF.

The rockfill used to buttress the side slopes of the STSF deposition causeway was repaired as a result of

tension cracks that had developed at the crest edge. The process required removing the deposition line

off the causeway using an excavator transportation of the material onto the causeway using haul trucks,

and dumping the material into piles along the causeway. The piles were then pushed out using a D6

caterpillar dozer followed by battering down the edges using the excavator. Once completed, the

deposition line was reinstated.

Silt traps and filter bunds formed using waste rock were installed in the stormwater drains, just

upstream of the outlets into Stormwater Collection Pond to limit sediment accumulation in the Pond.

The silt traps were constructed using a mullock base covered in geotextile membrane cloth and covered

over using a combination of topsoil and rock. A total of 4 silt traps were constructed along the perimeter

of the STSFE towards the storm water collection pond.

Repaired STSF deposition causeway Silt traps installed in stormwater drains

Furthermore, the Erosion Inspection Record Sheet (FRM-285) was prepared in January 2012. This record sheet

documents the results of erosion inspections undertaken after every rainfall event exceeding 25mm in a 24 hour

period and at least once every three months. It also documents corrective actions identified during the inspection.

Page 44: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

36

2.8.4 Groundwater Sources

Exploration for near mine groundwater sources at CSA began in June 2007 following raw water allocation

reductions due to serious drought. The exploration program primarily focussed on the area to the east of the TSF

in the interpreted area of the Chesney Fault. The aim of the program was to secure a groundwater supply

through either existing boreholes, or by discovering new productive water extraction points. The investigation

led to the discovery of a potential aquifer at a depth of 79 m.

Two water bore test holes and eighteen test pilot holes were drilled in the study area in 2007 and 2010

respectively. The test pilot holes did not show any indication of sufficient groundwater to justify drilling of

further water bore holes.

Further investigations into the suitability of an alternate water resource will continued as opportunities arise. No

investigations were undertaken in 2012 and there are currently no plans to progress this research in 2013.

2.8.5 Site Water Balance

A total of 749 ML of raw water was consumed at CSA Mine in 2012. This represents a reduction in consumption

of approximately 1.6% from 2011 (761 ML) and 16% from 2010 (894 ML). The efficiency gain in 2012 reflects

the overall long term trend displayed in Figure 5, which can be attributed to CSA Mine using recycled water

more efficiently. The decrease experienced between 2011 and 2012 can also be attributed to CSA Mine not

achieving their production targets in 2012, which would subsequently reduce water usage.

Figure 5 Long Term Raw Water Used per Tonne Milled

The total site usage of water (which includes both raw water and recycled water usage) during the reporting

period was 1,477 ML. This usage has increased by 18% from 2011 (1,251 ML). The reduction in raw water

Page 45: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

37

consumed can be attributed to a significant increase in the volume of recycled water used at the CSA Mine in

2012 with 49% of all water used on site coming from a recycled source. This represents an increase from the

previous reporting period where 44% of all water used on site came from a recycled source. There has been an

improvement in underground dewatering recovery and increased utilisation of pork pie return water which can

be attributed to increased storage capacity through the construction of the Operational Water Dams, installation

of new pumps, and improved operational practices returning water to the process water dam for re-use.

Water efficiency improvements were also made in 2012 and include the modifications of tailings discharge

spigots to reduce washout ruts. It is expected further water efficiency improvements will be made in 2013 with

the four week trial of a dewatering plant in March 2013.

Table 18 summarises site water usage at the CSA Mine for 2012 and Figure 6 shows the 2012 Site Water

Balance.

Table 18 CSA 2012 Water Balance

Water Recycling

Total Site Input 964,483.3 kL

Total Site Usage 188,410.4 kL

Total Recycle 195%

Water Losses

Mine Ventilation Losses 150,811.6 kL 15%

Water Retained in Backfill 96,803.9 kL 9%

Water Retained in Tailings 184,712.2 kL 18%

Tailings Dam Evaporation Losses 591,939.6 kL 57%

Water in Concentrate 13,249 kL 1%

Total 1,037,516 kL 100%

Water Recovery

Underground Dewatering 63%

Tailings Dam Dewatering 93.77%*

Note:

* Includes rainfall runoff collected and reclaimed from TSF

CMPL aims to continue minimising the reliance on external raw water supplies to ensure the operation can

remain sustainable into the future, and to safeguard against the future onset of drought conditions and potential

allocation restrictions that have been experienced in the past.

Page 46: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

38

Minor improvements to the underground dewatering system during 2012 also assist in the site recycling

capacity, as we continuously seek ways to optimise the recovery of water from the underground mine back to the

surface operations. Upgrades to the 8855 Pump Station during 2012 have ensured it is working to capacity and

improving the quality of the water recycled (less solids).

Upcoming plans for 2013 include the installation of a new mono pump station up at the 8700 Level (current

deepest level in mine) to create an efficient pumping system at the bottom of the mine. The drive has been mined

and the pumping holes drilled in readiness for this installation as soon as the design for the pump station is

determined. Mining will then pour a concrete pad and set up services so that the pumps can be installed and

hooked into the operational system.

Over the longer term (post 2014), CSA Mine is currently looking at the design for the next Life-Of-Mine

underground Pump Station that will be down around the 8670 Level to be used in conjunction with the No. 1

Shaft. The feasibility review for this project is currently focusing on LOM pumping requirements, piping size in

the new shaft, pump selection and excavation design. As soon as this new proposed pump station is ready for

installation, CSA Mine will progress this work likely before the No. 1 Shaft is active. By commissioning this new

Pump Station and plumbing it in to our existing dewatering system, it will make some of our current (older)

system redundant and increase the efficiency even before Shaft No. 1 comes online.

Page 47: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

39

Figure 6 CSA Mine Water Balance 2012

concentrate (dry tonnes)

123,451

total raw water (klitres) ventilation losses (klitres) water in concentrate (klitres) evaporation losses (klitres)

964,483 150,812 13,249 591,940

raw water (klitres) raw water (klitres) water in tailings (klitres)

394,884 485,782 776,652

mine dewatering (klitres)

backfill (dry tonnes) 275,180 tailings (dry tonnes) Rain (kLitres)

371,568 Underground Mine ore (dry tonnes) Concentrator 443,308 Tailings Dam 19,934

water contained in backfill (klitres) 975,044

96,804 water in ore (klitres) tailings return water (klitres)

35,364 728,258

96,804 184,712

water retained in backfill (klitres) water retained in tailings (klitres)

96,804

water in backfill (klitres) 296,228

raw water (klitres) 371,568 water stored in dam

83,817 backfill (dry tonnes)

Surface & General Usage

Process Water Dam

Page 48: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

40

2.9 Hazardous Materials

Current WorkCover licensing requirements for Hazardous materials and Dangerous Goods management in NSW

requires CSA Mine to annually submit a Notification of Dangerous Goods on Premises form to notify

WorkCover of Hazardous and Dangerous Goods stored on the premises.

The minimum requirements for storage of Hazardous and Dangerous Goods at the CSA Mine site are:

Bunding to contain at least 110% of the largest container;

The display of signs for each hazardous product stored within the facility illustrating the substance

name, dangerous goods class, packaging group and emergency response details;

The display of labels on all individual containers (product name, UN number, dangerous goods class

and packaging group);

Material Safety Data Sheets (MSDS) to be available within immediate storage area;

Effective measures to exclude rain and surface stormwater runoff from the storage area;

Spill containment kits and/or fire extinguisher within the vicinity of storage areas appropriate to the

volume of hazardous material stored; and

Easy access for emergency response and spill clean-up kits.

Hydrocarbons are stored on site in the following areas:

Underground workshops and fuelling facilities;

Surface workshops;

Bulk diesel self bunded tanks; and

Designated waste hydrocarbon collection areas.

These areas and all other major Hazardous and Dangerous Goods storage locations are detailed in Table 19.

Page 49: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

41

Table 19 CSA Bulk Hazardous and Dangerous Goods Storage (as of 31/12/12)

Location Dangerous Goods Tank

Product Name Un No. Class PG Tank Capacity

Refrigeration Plant Ammonia Anhydrous 1005 2.3 (8) I a/g 2,450 kg

Flam Gd Shed Interfroth 4500 1993 3 III a/g 1,000 L

Flam Gd Shed Interseal paint 1263 3 III a/g 400 L

Dyno Nobel Yard Titan 7000 Emulsion 3375 5.1 II a/g 100,000 kg

Frother Station Interfroth 4500 1993 3 II a/g 1,000 L

Nitric Acid Tank Nitric Acid 60% 2031 8 II a/g 18,500 L

Backfill Plant Delvocrete Stabiliser 1760 8 II a/g 1,000 L

Stores Yard R134a 3159 2.2 N/A a/g 40 kg

Stores Yard Integra CWT BT202 2014 5.1 ll a/g 205 L

Stores Yard Integra CWT 7665 1760 8 lll a/g 240 L

Stores Yard Integra CWT BT 3265 8 lll a/g 480 L

Delvocrete Stabiliser Delvocrete Stabiliser 1760 8 ll a/g 3000 L

Stores Yard Oil 00C1 C1 N/A a/g 25,000 L

Stores Yard Argon Gas 1006 2.2 N/A a/g 44 kg

Stores Yard Marathon Gas 1075 2.1 N/A a/g 120 kg

Stores Yard Compressed Argoshield 1956 2.2 N/A a/g 200 kg

Stores Yard Acetylene 1001 2.1 N/A a/g 200 kg

Stores Yard Oxygen, Compressed 1072 2.2 III a/g 500 kg

Stores Yard Nitrogen, compressed 1066 2.2 N/A a/g 700 kg

Bulk Storage Tanks Diesel Fuel N/A C1 N/A a/g 180,000L

Brace Transfer Tanks Diesel Fuel N/A C1 N/A a/g 2,500 L

L 8960 UG Tank Diesel Fuel N/A C1 N/A u/g 2,500 L

L 10 UG Tank Diesel Fuel N/A C1 N/A u/g 10,000 L

L9 UG tank Diesel Fuel 00C1 C1 N/A u/g 10,000 L

L11 UG Magazine Explosive, blasting, type B 331 1.5D II u/g 22,000 kg

L11 UG Magazine Explosive, blasting, type B 82 1.1D II u/g 5,200 kg

L11 UG Magazine Explosive, blasting, type E 241 1.1D II u/g 7,500 kg

L11 UG Magazine Cord, detonating 65 1.1D N/A u/g 50 kg

L11 UG Magazine Detonators, non-electric 29 1.1B N/A u/g 350 kg

L11 UG Magazine Boosters 42 1.1D N/A u/g 370 kg

L11 UG Magazine Detonators, electric 30 1.1B N/A u/g 500 kg

Store Oxalic Acid Shed Oxalic Acid 3261 8 III a/g 1,000 kg

Note:

u/g = underground

a/g = above ground or surface

Page 50: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

42

2.9.1 Hazardous and Dangerous Goods Audit

A Hazardous and Dangerous Goods Audit was conducted at the CSA Mine in December 2012 to ensure the

CMPL Dangerous Goods Register is up to date and all handling and storage of Hazardous and Dangerous Goods

remains compliant with legislative requirements. No major storage issues were identified during the audit with

all areas meeting compliance requirements. Issues highlighted in the audit included general housekeeping of

signage and MSDS documents to ensure they are visible and accessible. The site Dangerous Goods Audit

Report was distributed to each department with all audit actions scheduled to be successfully addressed by the

end of February 2013.

2.9.2 Radiation

CMPL is licensed to sell/possess radiation apparatus and radioactive substances or items containing radioactive

substances. See Table 3 in Section 1.2 for licence details. A small amount of radioactive material is held on site

in “in-stream-analysis” probes and density level gauges. These are stored according to the recommended

procedures and locked away from general access. All qualified electrical personnel at CSA Mine are trained and

certified in Industrial Radiation Safety which allows the electrical team to work with radiation devices on site in

relation to safety and maintenance.

2.9.3 Polychlorinated biphenyls (PCBs)

The last of the transformers testing positive for the presence of PCB levels above the allowable limit (as per tests

conducted in 2009) were removed from site during 2011. This work was completed by a licensed contractor,

with all oil removed from the units prior to relocating from the mine site. All high voltage electricity

transformers continued to be PCB tested in 2012 as part of routine oil testing process.

2.9.4 Asbestos

Due to the age of numerous structures on the CSA Mine site there are some materials containing asbestos

present. CMPL has an obligation to ensure that Asbestos Containing Materials (ACM) is managed in

accordance with legislative requirements to prevent health and environment related risks.

All ACM present at the CSA Mine is in a bonded form and includes concrete and fibro walls on the surface of

industrial buildings, the majority of building roofs, and the majority of concrete pipes on site. ACM in a bonded

form does not present an immediate health risk, if it remains undisturbed and in good condition.

The CSA Mine Asbestos Management Plan is maintained to assist CMPL workers to comply with asbestos

prohibitions and prevent exposure to airborne asbestos fibres. While the ultimate goal is for all work areas to be

free of ACM, it is generally impracticable, especially with the limited life of mine timeframe. Due consideration

is given to the removal of ACM during any refurbishment or maintenance where practicable, in preference to

other control measures such as enclosure, encapsulation or sealing.

CSA Mine conducts an inspection of each building and structure on surface on an annual basis. The CSA Mine

Asbestos Register is maintained with regular updates of the results from these inspections. The register contains

details of the location, type and condition of any asbestos products found on site. Where no asbestos is found, a

Page 51: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

43

record of such a finding is also kept. The Asbestos Register is available on the CSA Hub (intranet), and is made

available for inspection by employees, contractors, maintenance personnel and government representatives. All

asbestos material and air samples are analysed by a National Association of Testing Authorities (NATA)

accredited laboratory.

The most recent Annual Asbestos Audit and Air Monitoring were carried out on all surface buildings that

contain asbestos material during September 2012. Results showed that all samples remain below exposure limits

and highlighted areas were maintenance is required to allow CSA workplaces to remain safe from asbestos

exposure. The annual monitoring results were used to update the Site Asbestos Register in December 2012.

The long term outlook for bonded asbestos products on site is to monitor, maintain and replace as required.

There are no plans to replace any buildings at this stage. Any building modifications or repairs will see the

removal of any associated asbestos material and replaced with new materials. This approach has seen a

progressive reduction of asbestos material on site since the program began in 2006.

2.10 Other Infrastructure Management

Additional activities undertaken by CMPL during the reporting period that did not require any changes to the

MOP include:

Dust Collection System for the Backfill Circuit:

The dust collection system that was proposed and budgeted for installation in 2011 did not go ahead, following a

review of the cost and benefits compared to the timeframe before replacement of the current backfill plant with a

paste fill plant in quarter one 2013.Temporary exhaust fans were being installed in early 2012 to provide a short

term solution while the plant is still in use. Modifications were made to the backfill cement mixer lid by

installing a dust breather system with water addition to supress dust, and the use of sealing foam to seal the

backfill plant door has reduced the spread of dust outside the bunded area

Dust Collection System for the Lime System:

It was highlighted during 2010 that the current bag filter system on the floatation ground floor of the Ore

Processing Mill was not capable of fully containing the generated lime dust. The system was hard to maintain

as it required direct exposure to lime which is classified as a hazardous material. The inadequacy of the system

caused high dust levels around the flotation area, offices and mill facilities which was causing corrosion of the

supporting steel work. As a result the use of lime was ceased and was only reintroduced back into the process on

occasions in late August 2012 until November when required.

The lime dust system was inspected and existing equipment faults such as faulty dust indicator and clogged dust

bag were found to be main problem with the system. A new dust bag was installed, perished gaskets were

replaced, faulty electrical wiring was fixed and a new sensor was installed. With the replacement of faulty parts

the system is now operating adequately. Due to the age of the system and compatibility with new equipment

there is an intermittent problem with the dust sensor becoming clogged and allowing fugitive lime dust to

escape. This fault does not happen often and when it does the system is shut down and the sensor cleaned to

Page 52: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

44

allow continued normal operation. Maintenance is currently exploring options of a new sensor setup to ensure

the system can operate effectively without intermittent faults. As part of the new grinding mill project a new

system will be installed.

Page 53: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

45

3 ENVIRONMENTAL MANAGEMENT AND PERFORMANCE

Ongoing improvements to the CSA Mine Environmental Management System (EMS) continued over the 2012

period. The CMPL Environmental and Community Policy is included as Appendix C.

3.1 Pollution Incident Response Management Plan

In 2012, a Pollution Incident Response Management Plan was prepared in accordance with the NSW

Environmental Protection Authority’s (EPA) Guidelines for the Preparation of Pollution Incident Response

Management Plans (2012). The purpose of this plan is to satisfy the requirements of the Protection of the

Environment Legislation (General) Amendment Act 2011 (POELA Act) for CSA Mines’ Environmental

Protection Licence 1864.

The objectives of this plan are to:

Ensure comprehensive and timely communication about a pollution incident at the CSA Mine to staff,

the EPA, and other relevant authorities, and people outside the facility who may be affected by the

impacts of the pollution incident;

Minimise and control the risk of a pollution incident at the facility through the identification of risks

and the development of planned actions to minimise and manage those risks;

Ensure pollution incident response is properly implemented by trained staff, identifying persons

responsible for implementing it, and ensuring the plan is regularly tested for accuracy, currency and

suitability.

This plan relates to the CSA Mine and its immediate surrounds and is implemented in conjunction with the Site

Emergency Management Plan (MHP-006) and key External Emergency Services providers (NSW fire Brigade,

SES, NSW Ambulance, Police, Rural Fire, Hospital) and local, state and federal government authorities where

contingencies are required.

A copy of the Pollution Incident Response Management Plan is provided in Appendix I.

Page 54: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

46

3.2 Air Pollution

3.2.1 Meteorological Monitoring

The semi-arid climate of Cobar has a median annual rainfall of 390 mm. Two rainfall monitoring gauges are

located at the CSA Mine site, one west of the administration building and the other at the TSF. The total rainfall

on site for 2012 (measured at the administration building rain gauge) was 414.4 mm, which was higher than the

rainfall received in 2011 (369.2 mm). Figure 7 provides an overview of 2012 monthly average rainfall and

temperatures at the CSA Mine.

0.00

20.00

40.00

60.00

80.00

100.00

120.00

140.00

160.00

0

5

10

15

20

25

30

35

40

Rain

fall

(mm

)

Tem

pera

ture

C)

2012 CSA (Admin) Monthly Rainfall 2012 Mean Daily Minimum Temp

2012 Mean Daily Maximum Temp

Figure 7 2012 Cobar Mean temperatures and CSA Mine Rainfall

3.2.2 Dust Emissions

Operations at the CSA Mine potentially contribute to air pollution through dust emissions generated from the

operation of equipment and other emissions generated from the usage of fuel and explosives.

The principal dust-generating activities associated with the CSA operation include:

Long term drought conditions resulting in minimal groundcover on the lease and surrounding district;

Operation of mobile machinery on unsealed roads and tracks;

Topsoil stripping and spreading;

Exposed stockpiles of waste rock, topsoil and/or additional materials;

Surface exploration drilling operations; and

Page 55: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

47

Underground mine ventilation exhaust.

CSA Mine is committed to ensuring dust generation is minimised from all operations on site. Water sprays and

water trucks are utilised in the underground mine to supress dust in work areas and hence minimise dust emitted

to the air through the ventilation fans. The exception is after a blast when the ventilation system is designed to

clear dust from the workings as quickly as possible to mitigate health risks to underground employees. Blasting

of small development headings occurs twice a day at shift changes (7am and 7pm) to ensure there are a limited

number of personnel underground. Larger stopes are blasted approximately 2-3 times a week. The ventilation

outlets from underground are located away from the main operations on site and away from any sensitive

receptors. Dust deposition monitoring points are set up around the site and the levels of dust reaching the surface

from blasting operations are considered to be negligible in the context of the mine.

All roads and tracks on the CSA Mine have a restricted speed limit imposed to reduce the amount of dust

generated by traffic. When unsealed roads are being used intensively, the roads are sprayed with a water cart to

suppress dust. Recycled water is used for dust suppression sourced from the Process Water Dam; its suitability

for use is determined using monthly water quality results.

Continuous improvements to minimise dust pollution are investigated and implemented at the CSA Mine where

possible and monthly monitoring is undertaken to assist. A total of ten dust gauges are monitored on the mine

site. The locations of the CSA Mine dust monitors are listed below and also shown in Plan 2:

D1: North-east corner of the STSF;

D2: Northern boundary of the NTSF;

D3: 100m north-east of concentrate storage and train loading station;

D4: West of the administration building (undisturbed control site);

D5: Beside TSF access road before the booster hopper;

D6: Southern corner of STSF Extension;

D7: Opposite Railway Dam alongside the TSF access road;

D8: North-west corner of the NTSF (adjacent to the waste rock stockpile site);

D9: Decline access road; and

D10: North of the Backfill Plant.

Samples are collected monthly and are analysed by an external NATA accredited laboratory for determination of

dust composition and metals content. The results of dust deposition from the ten sample sites are summarised in

Figure 8.

Page 56: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

48

0

1

2

3

4

5

6

Jan

Mar

May Ju

lSe

pN

ov

Jan

Mar

May Ju

lSe

pN

ov

Jan

Mar

May Ju

lSe

pN

ov

Jan

Mar

May Ju

lSe

pN

ov

Jan

Mar

May Ju

lSe

pN

ov

Jan

Mar

May Ju

lSe

pN

ov

Jan

Mar

May Ju

lSe

pN

ov

Jan

Mar

May Ju

lSe

pN

ov

Jan

Mar

May Ju

lSe

pN

ov

Jan

Mar

May Ju

lSe

pN

ov

D1 D2 D3 D4 D5 D6 D7 D8 D9 D10

min

era

l co

nte

nt

(g/

m.m

/mo

nth

)

Mineral Content Impact Assessment Criteria

Figure 8 CSA Depositional Dust Monitoring Results 2012

The EPA recommended limit for dust deposition of 4 g/m2/month and was only exceeded once during 2012 at

location D5 during November). The D5 monitoring location is situated next to the main access road to the TSFs.

This spike is likely to be the result of increased traffic in the area over the November monitoring period, during

which time earthmoving contract works were taking place on the surface of the STSF approximately 30m from

the monitoring gauge. Also, during November there were a few days of high winds that could have also

contributed the elevated dust emissions recorded in November.

Other than the exceedance at D5 recorded in November 2012, there have been no other notable spikes in dust

deposition (greater than 2 g/m2/month) over the reporting period. Raw air quality monitoring data, including

historical data, is tabulated in Appendix D.

3.2.3 National Pollution Inventory

The CSA mining operation generates emissions to air through the use of machinery (diesel emissions) and other

chemical substances. These emissions are quantified on an annual basis via the National Pollutant Inventory

(NPI). The NPI is the national public database designed to provide the community, industry and government

with information on the types and amounts of substances being emitted to the environment. The NPI is managed

by the Australian Government Department of Sustainability, Environment, Water, Population and Communities

Page 57: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

49

(DSEWPC). The CSA Mine NPI report was submitted in September 2012 and will be on public display on the

DSEWPC website2.

During the 2011-2012 reporting period (July 2011-June 2012) 24 substances were triggered by activities at the

CSA Mine. These substances have been predominantly triggered due to fuel and energy use, explosives and on

site tailings transfers. Table 20 compares key emission sources by activity levels on site, for the 2010 – 2011

and 2011 – 2012 reporting periods.

Table 20 shows all emissions for the NPI sources reduced in the last reporting period, with the exception of dust

generated from combustion and wheel dust associated with vehicle travel on unsealed roads. An increase in the

number of workers on site and therefore the number of vehicles travelling on site (particularly contractors) has

seen the use of vehicles travelling on site increase significantly. This level of activity is expected to continue

until the end of 2013 when the shaft project is completed and the number of workers on site again decreases to

the normal workforce average.

Table 20 Comparison of NPI Emission Sources by Activity Levels for 2010-11 and 2011-12

Emission Source

2010 - 2011

2011-2012 % Change Emission

Type

Diesel fuel combustion (L)

3,387,699 3,990,964 17.8% Combustion

Concentrate exported (t)

151,564 164,520 8.5% Dust

Ore handled -

dry (t) 1,028,493 996,639 -3.1% Dust

Developmental Waste handled

(t) 203,463 237,437 16.7% Dust

Vehicle travel on unsealed roads (km)

82,173 44,070 -46.4% Combustion &

wheel dust

Exposed Areas (Ha)

104 104 0.0% Wind Erosion

Explosives (t) 856 860.4375 0.5% Mainly CO &

NOx

3.2.4 National Greenhouse and Energy Reporting

The National Greenhouse and Energy Reporting Act 2007 (NGER) is a single national framework for energy use

and greenhouse gas emissions. It sets a mandatory system for companies to assess their energy use and

greenhouse gas emissions and report them if they exceed set thresholds. The Act is administered by the

Australian Department of Climate Change and Energy Efficiency.

2 http://www.npi.gov.au/

Page 58: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

50

The CSA Mine has total emissions that exceed the threshold for a single site; hence it is mandatory to submit

energy consumption and greenhouse gas emissions data annually.

Table 21 Summary of CMPL Energy Consumption and Greenhouse Gas Emissions (2011-2012)

Emission Source Emission Source

Units GJ Tonnes CO2-e

Electricity 300,088 73,355

Diesel 147,781 10,271

LPG 55 3.3

Waste Oil / Grease 9,283 643

Refrigerant HFC-134A

515

Total 457,207 84,787

Figure 9 CSA Mine Total Energy Consumption (GJ) 2011-2012

Page 59: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

51

Figure 10 CSA Mine Total Greenhouse Gas Emissions (t CO2-e) 2011-2012

Electricity, predominantly used in crushing and grinding, is the dominant energy use and source of emissions at

the CSA Mine. CSA Mine is committed to undertaking investigations into energy use with the intent of

identifying opportunities to improve efficiency and reduce the overall carbon footprint of the mine.

3.2.5 Compressive Emissions and Energy Audit

During 2011, CMPL engaged external consultants to undertake an assessment of overall energy usage and

carbon emissions at the CSA Mine in order to develop a suitable action plan for the implementation of cost

effective projects validated by the CSA Mine management team. The assessment:

Identified the range of energy savings available to improve energy performance and achieve cost

savings;

Determined opportunities to obtain and trade Energy Savings Certificates (ESC) under the NSW Energy

Savings Scheme (ESS) from viable energy projects;

Reviewed CSA Mine’s various compliance and reporting obligations at State and Federal level

including the Energy Efficiency Opportunities (EEO) program and confirming obligations under the

Energy Savings Action Plan (ESAP) program;

Assessed CSA Mine’s carbon emission profile including Scope 1 and 2 covered in the NGER Act as

well as the potential exposure due to Scope 3 emissions;

Focussed on management opportunities to ensure appropriate steps are taken to facilitate continuous

improvement in the future; and

Incorporated previously identified energy saving opportunities.

The assessment identified short to medium and long term energy savings and carbon emission reduction

opportunities, these are listed in Table 22 and Table 23.

Page 60: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

52

Table 22 Short-Medium Term Energy Saving and Carbon Emission Reduction Opportunities

Actions

Estimates Annual Energy

Savings GJ pa

Estimated Annual Carbon Savings

tCO2E pa

Estimated Annual Energy

Cost Savings $

pa

Projected Indirect Carbon

Cost Savings

% pa

Projected Total

Savings $ pa

Estimated Project Costs $

Estimated Simple

Payback yrs

Ventilation- Optimising

energy use of primary fans

12,733 3,158 279,618 80,914 360,532 _(1) _(1)

Automatic control of

secondary fans 4,730 1,169 103,556 26,887 130,443 _(1) _(1)

Reduction of leaks and operating

pressure of compressed air

system

4,043 999 88,504 22,977 111,481 70k - 120k 0.63 - 1.08

Optimisation of compressor

control 817 202 17,890 4,646 22,536 35k - 45k 1.55 - 2

Electricity demand

management - - - - 31,272 65k 2.08

Biodiesel blend trials

- - - 21,160(2) - Negligible Immediate

- - - 43,320(3) -

Reduced water pumping through

increased recycling

underground

994 246 21,752 5,658 27,410 _(1) _(1)

Derrick Stack Sizer application

in milling process

5,184 1,282 113,486 29,486 142,972 _(1) _(1)

Notes:

1. To be estimated upon availability of additional project cost data 2. Projected carbon cost savings through the replacement of diesel with B10 biodiesel

3. Projected carbon cost savings through the replacement of diesel with B20 diesel

Page 61: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

53

Table 23 Long Term Energy Saving and Carbon Emission Reduction Opportunities

Actions

Estimates Annual Energy

Savings GJ pa

Estimated Annual Carbon

Savings tCO2e pa

Estimated Annual Energy

Savings $ pa

Projected Indirect

Carbon Cost Savings $ pa

Potential Annual Cost Saving $ pa

Under ground water turbine

2,988 739 65,412 16,997 82,409

Mill expert system for improved

control 6,188 1,530 135,474 35,190 170,664

Installation of air compressor unit

underground 1,656 409 36,253 9,407 45,660

Filter press _(1) _(1) _(1) _(1) _(1)

Relocation of backfill plant

_(1) _(1) _(1) _(1) _(1)

Underground conveyor

_(1) _(1) _(1) _(1) _(1)

Higher efficiency motor program and

motor rewind program

2,268 - 3,028 560 - 748 50,000 - 60,000

12,880 - 17,204

62,880 - 82,204

Notes:

1. To be estimated upon availability of additional project information.

The September 2012 energy review has identified that CSA Mine has not yet reached the threshold for EEO

participation (0.5 PJ) as identified in the 2011 energy assessment. With the expansion of the mine and

deepening of the No.1 shaft it is anticipated CSA Mine will trigger the EEO threshold in the next financial year

(2012 – 2013). The energy assessment recommends steps for preparation and participation in the EEO program

once the threshold has been triggered. If EEO is triggered in the 2012-2013 financial year CSA Mine will fulfil

its commitments by registering by March 2014 and submitting an assessment plan by December 2014.

The energy assessment also analysed the CSA Mine’s liability under the Clean Energy Act 2011 which came

into effect in July 2012. The CSA Mine will not be a direct participant in the scheme as the Scope 1 Emissions

threshold has not been met. However, CSA Mine incurs increased electricity costs and increased fuel costs

through a reduction in fuel tax credits.

The assessment outlined steps for CMPL to achieve an integrated approach to energy management based on

continuous improvement principles. Steps include the implementation of management practices alongside

traditional technical approaches to energy efficiency. Current performance was assessed against a set of best

practice criteria of 25 key elements; results are shown in Figure 11. A gap analysis of energy management at the

CSA Mine was conducted and priority actions were identified, these are shown in Table 24.

Page 62: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

54

Figure 11 Management Practices Assessment – Level of Development

Table 24 Priority Management Practice Actions

Element Key Action

Corporate Commitment & Support

Establish Energy Policy with long term reduction target

Undertake formal monthly reporting on progress

Development of Targets and Performance Tracking

Track progress towards defined targets on a minimum of a monthly basis

Progress against site targets are regularly reported and posted

Ownership and Responsibility for Energy

Identify line management responsible for significant energy usage

Training and Knowledge Transfer

Develop an emergency awareness program that highlights potential improvements in performance

Incorporate a process to track attendance at the awareness training program

Capital Planning Capital project requests require confirmation that energy efficiency has been considered

Designing for Efficiency Incorporate a mechanism to ensure key energy efficiency concepts are addressed within all process designs and new facilities

Page 63: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

55

Energy Metering Practices The site to install electricity meters that allow the breakdown of total consumption by key plant areas

Energy Monitoring and Control The site energy team regularly reviews site energy consumption and costs vs. production to identify any anomalies

Progress Against Targets Track and report progress against annual site-wide targets for energy and carbon reduction

Program Review and Enhancement

Periodically review and enhance the Program and processes

During the first half of 2012, Golder Associates and CSA Mine identified the methodology, carried out a

baseline assessment and assessed project eligibility for the generation of Energy saving Certificates (ESC) for

the CSA Mine site.

CMPL agreed to progress four projects for preparation and submission of applications to the independent Pricing

and Regulatory Tribunal (IPART) for approval and accreditation to the Energy Saving Scheme (ESS), which

will allow CSA Mine to generate ESCs from these projects.

The four selected projects include:

1. Compressed AIR ESC_02

2. Jamison Cell ESC_04

3. Primary Vent Fan ESC_07

4. Scavenger Cell Replacement ESC_08.

CSA Mine has since added the decommissioning of the booster fans project to the list for ESC generation.

Golder also identified and recommended three other projects with substantial ESC creation potential which will

be further investigated over 2013:

1. Mill Upgrade ESC_05

2. Paste For Backfilling ESC_06

3. Secondary Ventilation Fans ESC_09.

3.3 Erosion and Sedimentation

CMPL has numerous bunds, water diversion drains and catchment dams within the CSA Mine to control erosion

and sedimentation on site. The Stormwater Drainage Improvement Plan sets out improvement objectives to the

system. The plan identified that the current open drainage system is inadequate and recommended

improvements which CSA implemented in 2011 through:

Improving the capacity of existing drains through removing excess sediment and reshaping.

Establishing new drains.

Cleaning out culverts.

Placing rock check dams upstream of culverts to reduce the build-up sediment and material in culverts.

Rock lining of drains receiving high velocity water.

Improvement works completed in 2012 were mainly undertaken as actions resulting from recommendations

made as a part of the 2011 NSW Dam Safety Committee Surveillance Report inspection (See Section 3.22). The

Page 64: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

56

TSF is not included in the Stormwater Drainage Improvement Plan because all drainage, erosion and water

catchment issues are dealt with through the TSF Operations Plan, dam engineers, surveyors and DSC

Surveillance reports. The TSF is monitored for structural erosion in the 3 monthly compliance surveys, in

addition to weekly monitoring and inspections after rainfall events exceeding 25mm in a 24 hour period by the

Ore Processing Superintendent. Furthermore, a general TSF inspection occurs twice per 12 hour shift by Mill

Operators.

Access tracks are kept to a minimum on site and are positioned so that they do not cause any unnecessary

damage to the land. Temporary access tracks are ripped, topsoiled and revegetated where necessary when they

are no longer required for mining operations.

Within 24 hours of a large rainfall event (greater than 25 mm over 24 hours) an erosion and sediment control

inspection is conducted by a member of the Environment Department. A visual inspection is completed of key

water storages, drainage channels and bunds across site to identify any erosion damage, drainage issues,

blockages, storage capacities and risks of overflow or discharge. Corrective actions are assigned with priority

given to those that maintain the capacity of storages and minimise the risk of damage to the structural integrity of

facilities. The Erosion Inspection Record Sheet (FRM-285) was prepared in January 2012. This record sheet

documents the results of erosion inspections and documents corrective actions identified during the inspection.

Three inspections were completed in 2012, which were conducted after rainfall events of greater than 25 mm.

There were no incidents of sediment overflow or discharge in 2012.

3.4 Surface Water Quality

Surface water quality samples are collected monthly from active water storage structures around the site (Plan 2).

Many parts of the site and associated dams only become wet immediately after large rainfall events therefore the

number of water quality samples for each catchment varies. All surface water samples are tested for pH and

electrical conductivity in the field. Water samples are also sent off site to a NATA approved laboratory for

determination of copper, iron, lead, zinc, and sulphate concentrations. As stock is not permitted on the mine site,

and the catchment dams are used for storage of water for use at the plant, water quality is compared to the

Australian and New Zealand Conservation Council (ANZECC) guidelines for irrigation and general use water.

In the absence of ANZECC general water use guidelines, ANZECC stock water guidelines have been used.

Page 65: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

57

Table 25 Adopted Guidelines

ANZECC (2000) Guidelines for Irrigation and General Water Use

pH 6-9

Electrical Conductivity (uS/cm) 7,700

Copper (mg/L) 5

Iron (mg/L) 10

Lead (mg/L) 5

Sulphates (mg/L) 1,000

Zinc (mg/L) 5

The locations of surface water quality monitoring sites are shown in Plan 2. The surface water quality results for

2011 and 2012 are summarised in Table 26. Raw data is included in Appendix D.

Sampling sites S1, S10, S13 and S9 surround the base of the catchments associated with the excised old

Subsidence Area and the old Smelter Area. Therefore these locations often show signs of contamination.

Samples collected from site S2 are taken directly from the Raw Water Tank. This is CSA Mine’s incoming

external water supply from the Cobar Water Board, and therefore provides a comparative analysis for surface

water catchment samples collected from other dams around the mine site. Any exceedances detected in these S2

samples are therefore assumed to be the naturally occurring levels in the uncontaminated water supply.

Sample site S4, the Borrow Pit Dam, generally receives clean rainfall runoff, but can also receive surface runoff

from the mine site in cases of overflows and spills. It is therefore expected to show levels indicative of

contaminated water. Pork Pie dam (S14) is the process water dam and receives the water from Borrow Pit and

the Operational Water dam, thus is likely to show similar water quality characteristics.

Each parameter of surface water quality summarised in Table 26 is briefly discussed below. Surface water

quality results are displayed further in Figures 12 and 13.

Page 66: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

58

Table 26 CSA Surface Water Monitoring Results 2011 and 2012

Sampling Location

Parameter pH Electrical Conductivity (μS/cm)

Total Copper -mg/L Total Iron - mg/L Total Lead - mg/L Sulphates mg/L Total Zinc - mg/L

ANZECC Guideline 6-8.5 7,700 5 10 5 1000 5

Year 2011 2012 2011 2012 2011 2012 2011 2012 2011 2012 2011 2012 2011 2012

S1 - Catch dam North of

old CSA spoils

Average 3.48 4.50 34.93 13870.0 20 20 9.85 15.07 0.04 0.03 1,267 1,613 76.16 95.87

(± Std Dev) 0.42 1.85 13.3 1850.9 7.34 6.27 4.61 20.45 0.02 0.00 453 452 29.33 32.09

Minimum 3.14 3.29 16.50 12110 8.34 15.30 5.70 1.63 0.01 0.03 699 1,250 32 68.10

Maximum 4.13 6.63 56 15800.0 31.80 26.80 18.30 38.60 0.08 0.04 2,020 2,120 121 131.00

n 7 3 7 3 7 3 7 3 7 3 7 3 7 3

S2 - Raw Water Tank

Average 7.36 6.83 24.03 3644.79 0.02 0.11 2.30 5.56 0.01 0.08 18.50 10.56 0.44 1.25

(± Std Dev) 0.70 0.55 22.15 7339.64 0.02 0.22 3.25 11.50 0.01 0.17 11.43 9.23 0.37 1.71

Minimum 6.45 6.02 1.80 100.00 0.00 0.00 0.09 0.01 0.00 <0.001 2.00 <1 0.11 <0.005

Maximum 8.18 7.70 85.40 21100.00 0.07 0.63 9.09 38.10 0.03 0.47 32.00 30.00 1.42 4.29

n 12 9 12 8 12 10 12 10 12 10 12 10 12 10

S4 - Borrow Pit Dam

Average 6.14 7.306 57.40 1718.50 3.58 3.28 0.82 1.09 0.03 0.49 632.33 691.17 6.50 4.16

(± Std Dev) 0.50 2.80 44.11 517.03 2.79 3.58 0.69 1.09 0.03 1.06 342.40 388.52 3.40 3.47

Minimum 5.56 4.65 12.80 1000.00 1.32 0.26 0.35 0.01 0.01 0.01 242.00 216.00 3.52 0.14

Maximum 6.45 11.30 101.00 2170.00 6.69 8.37 1.62 3.10 0.06 2.66 882.00 1280.00 10.20 8.99

n 3 5 3 4 3 6 3 6 3 6 3 6 3 6

S5 - TSF Decant Dam

Average 7.02 6.10 45.71 6160.00 0.12 0.07 0.76 1.28 0.00 na 1290.67 845.50 0.25 0.12

(± Std Dev) 0.44 0.81 47.18 8739.16 0.09 0.04 0.56 2.67 0.00 na 301.05 321.44 0.41 0.17

Minimum 6.55 5.12 0.40 100.00 0.02 0.02 0.05 0.08 0.00 <0.001 858.00 444.00 0.04 0.01

Maximum 7.68 7.31 143.70 21400.00 0.29 0.11 1.92 6.73 0.00 0.01 1680.00 1370.00 1.34 0.46

n 3 6 3 5 3 6 3 6 3 6 3 6 3 6

S8 - Railway Dam

Average

No Samples Taken in

2011

No Samples Taken in

2012

No Samples taken in

2011

No Samples Taken in

2012

No Samples taken in

2011

No Samples Taken in

2012

No Samples taken in

2011

No Samples Taken in

2012

No Samples taken in

2011

No Samples Taken in

2012

No Samples taken in

2011

No Samples Taken in

2012

No Samples taken in

2011

No Samples Taken in

2012

(± Std Dev)

Minimum

Maximum

n

S9 - Retention

Basin

Average

No Samples Taken in

2011

No Samples Taken in

2012

No Samples taken in

2011

No Samples Taken in

2012

No Samples taken in

2011

No Samples Taken in

2012

No Samples taken in

2011

No Samples Taken in

2012

No Samples taken in

2011

No Samples Taken in

2012

No Samples taken in

2011

No Samples Taken in

2012

No Samples taken in

2011

No Samples Taken in

2012

(± Std Dev)

Minimum

Maximum

n

S10 - North Run Off Dam

Average 6.20 4.49 26.77 17500.00 0.95 1.22 0.76 1.15 0.15 0.22 109.67 113.00 3.96 6.06

(± Std Dev) 0.59 na 21.53 na 0.34 na 0.46 na 0.10 na 34.00 na 0.72 na

Minimum 5.61 4.49 6.40 17500.00 0.73 1.22 0.26 1.15 0.05 0.22 76.00 113.00 3.27 6.06

Maximum 6.78 4.49 49.30 17500.00 1.34 1.22 1.17 1.15 0.25 0.22 144.00 113.00 4.70 6.06

n 3 1 3 1 3 1 3 1 3 1 3 1.00 3 1.00

S11 - STDE Stormwater Catchment

Average 7.41 6.63 25.18 5506.02 0.17 0.20 0.33 0.85 0.00 0.01 122.00 922.18 0.03 0.18

(± Std Dev) 0.41 1.16 21.27 7325.54 0.13 0.31 0.34 1.63 0.00 0.01 17.06 213.42 0.03 0.26

Minimum 6.79 4.71 3.30 100 0.05 0.02 0.05 <0.05 0.00 <0.001 93.00 608.00 0.01 0.01

Maximum 7.94 8.31 66.70 21100 0.51 0.96 1.07 4.16 0.00 0.02 151.00 1200.00 0.11 0.77

n 12 11 12 9 12 11 12 11 12 11 12 11 12 11

S13 - Western

Run-off Dam

Average

No Samples Taken in

2011

No Samples Taken in

2012

No Samples taken in

2011

No Samples Taken in

2012

No Samples taken in

2011

No Samples Taken in

2012

No Samples taken in

2011

No Samples Taken in

2012

No Samples taken in

2011

No Samples Taken in

2012

No Samples taken in

2011

No Samples Taken in

2012

No Samples taken in

2011

No Samples Taken in

2012

(± Std Dev)

Minimum

Maximum

n

S14 - Pork Pie Dam

Average 7.25 6.78 46.77 8289.67 1.65 1.3371 0.73 0.32 0.02 0.04 667.08 762.00 2.39 1.66

(± Std Dev) 1.09 2.07 32.23 12948.40 2.54 1.900701 0.69 0.25 0.03 0.08 182.47 135.65 2.03 1.45

Minimum 4.84 4.56 5.30 1021.00 0.05 0.066 0.05 0.00 0.00 0.00 451.00 566.00 0.10 0.23

Maximum 9.14 11.67 132.40 36600.00 8.81 6.34 1.84 0.90 0.09 0.23 992.00 961.00 6.82 4.63

n 12 10 12 9 12 10 12 10 12 10 12 10 12 10

S15 - Old Mine Water Dam (MPL

1093)

Average 7.67 6.43 18.35 1211.18 0.02 0.04 1.68 0.88 0.01 0.30 16.38 37.57 0.39 0.47

(± Std Dev) 0.71 0.44 14.19 1686.27 0.01 0.04 1.62 0.78 0.01 0.71 10.85 18.97 0.54 0.41

Minimum 6.98 5.77 2.60 32.00 0.00 0.01 0.46 0.02 0.00 <0.001 8.00 <1 0.02 0.02

Maximum 8.58 7.01 47.10 4100.00 0.02 0.11 5.27 2.51 0.03 1.74 37.00 80.00 1.49 1.18

n 8 8 8 5 8 8 8 8 8 8 8 8 8 8

S16 - Old Mine Water Dam (MPL

1094)

Average 7.71 7.51 9.33 9256.85 0.09 0.05 3.94 2.00 0.20 0.08 1.50 18.50 0.06 0.19

(± Std Dev) 0.54 2.15 4.58 20091.45 0.04 0.04 2.30 3.45 0.11 0.10 0.90 19.09 0.03 0.37

Minimum 6.93 6.42 1.30 132.00 0.04 0.01 0.85 0.06 0.05 <0.001 1.00 <1 0.01 0.02

Maximum 8.46 12.80 18.40 50200.00 0.16 0.14 8.24 11.10 0.44 0.31 4.00 32.00 0.10 1.14

n 12 8 12 6 12 9 12 9 12 9 12 9 12 9

Notes: - n represents the number of months sampled (samples unable to be taken when dam is dry, therefore n<12).

Page 67: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

59

3.4.1 pH

The pH of water is a measure of its acidity or alkalinity and should be maintained between 6 and 9 for surface

waters. Generally, pH itself is not a water quality issue of concern, but it can indicate the presence of a number

of related problems. Soil and animal health will not generally be affected by water with pH in the range of 4 – 9.

Sampling locations that fell below the lower guideline limit were the S1 (catch dam North of old CSA spoils)

and S10 (North Run Off Dam). The only pH measurements that exceeded the upper guideline limit was recorded

at S4 in November 2012 (pH 9.12). A comparison of average pH values between 2011 and 2012 indicates pH

has slightly decreased at most monitoring locations. The greatest increase in pH was found at S4 (Borrow Pit

Dam) rising from 6.14 to 7.31. The greatest decline in pH was found at S10 (North Run off Dam) decreasing

from 6.20 to 4.49.

Improvement in water quality at the Borrow Pit is a likely indication of the improvement of the site water

drainage system and construction of the new Operational Water Storage Dam capturing the majority of

contaminated run-off.

3.4.2 Electrical Conductivity (Salinity)

Salinity is the presence of soluble salts in soils or waters. High salinity levels in soils may result in reduced plant

productivity, development of salt scald areas, and in extreme cases the elimination of native vegetation from an

area. Four sampling locations (S1, S10, S14 and S16) recorded higher average salinity levels than the ANZECC

guideline value of 7,700µS/cm. In general, all sampling locations (where samples were able to be obtained)

showed an increase in salinity since 2011. This is likely due to the decline in water stored within these sampling

locations over the 2012 monitoring period.

3.4.3 Copper

Copper (Cu) is an essential trace element for vegetation with an ANZECC guideline limit for irrigation and

general water of 5 mg/L. Copper is an enzyme activator, therefore a lack of this element leads to vegetation

mottling and yellowing in leaves. In 2012, copper concentrations recorded in surface water sampling locations

generally remained below the adopted ANZECC guideline criteria (5 mg/L), with the exception of S1, S4 and

S14 where concentrations fluctuated throughout the monitoring period. The highest average surface water copper

concentration was recorded at the S1contaminated dam (Catch damn North of old CSA spoils) at 20mg/L. This

recording is unchanged since 2011.

3.4.4 Iron

Iron (Fe) is also an essential trace element for vegetation and must be present in small quantities for proper plant

formation. The recommended iron concentration for irrigation and general use water supplies should remain

below 10 mg/L. All of the average surface water iron data for 2012 fell below the guideline value of 10mg/L,

with the exception of S1 in January 2012 (38.6 mg/L). The S14 (Pork Pie Dam) sampling location recorded the

lowest average concentration of 0.32mg/L. Compared with the results of 2011, more than half of the samples

taken displayed an increase in average iron concentration, although most of them still remain below the

ANZECC guideline value.

Page 68: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

60

3.4.5 Lead

The ANZECC irrigation and general use guideline for lead (Pb) concentration is 5 mg/L. No surface water

monitoring results exceeded this limit in 2012. The highest surface water lead concentration was found at S4

(Borrow Pit Dam), which recorded an average concentration of 0.49mg/L. Since 2011, only two sampling sites

have had a reduction in average lead concentrations (S1 and S16).

3.4.6 Sulphates

ANZECC guidelines for irrigation and general use water do not have a recommended value for sulphates. The

guideline for stock drinking water states that no adverse effects to soil and animal health are expected if the

concentration of sulphate does not exceed 1,000 mg/L. Average sulphate concentrations at all of the surface

water sampling locations fell below the ANZECC guideline value except location S1 (catch dam North of old

CSA spoils).

Some major decreases in yearly average surface water sulphate concentrations were observed since 2011 and the

most notable was found at sampling location S5 reducing from 1291mg/L to 12mg/L.

3.4.7 Zinc

Zinc (Zn) is an essential trace element that acts as an enzyme activator for vegetation growth. A lack of this

element leads to leaf mottling and yellowing in younger leaves. The ANZECC guideline for irrigation and

general use water (5 mg/L) was used to compare CSA surface water results.

All of the average surface water concentrations for zinc fell below the guideline value of 5 mg/L with the

exception of sampling location S1 (catch dam North of old CSA spoils), which recorded an average zinc

concentration of 96mg/L. Compared with the 2011 results, the most notable change in average zinc

concentrations was observed at site S1, increasing from 76mg/L to 96mg/L.

Elevated Zn concentrations do not cause any major health problems when taken up by plants or consumed by

stock, however, it can contribute to cosmetic and aesthetic effects on water and plant quality. While it is not

ideal to have Zn concentrations exceeding guideline values, it is not believed to be detrimental to stock, plant or

human health.

Page 69: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

Figure 13 Surface Water Quality 2012 (pH, Lead, Copper)

0

2

4

6

8

10

12

Jan-12 Feb-12 Apr-12 May-12 Jul-12 Sep-12 Oct-12 Dec-12

pH

Surface Water pH

S1 S2 S4S5 S10 S11S13 S14 S15S16 ANZECC Guideline (lower) ANZECC Guideline (upper)

0

1

2

3

4

5

6

Jan-12 Apr-12 Jul-12 Oct-12

mg

/L

Surface Water Lead

S1 S2 S4 S5

S10 S11 S13 S14

S15 S16 ANZECC Guideline

0

5

10

15

20

25

30

Jan-12 Feb-12 Apr-12 May-12 Jul-12 Sep-12 Oct-12 Dec-12

(mg

/L)

Surface Water Copper

S1 S2 S4 S5

S10 S11 S13 S14

S15 S16 ANZECC Guideline

Page 70: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

Figure 14 Surface Water Quality 2012 (Sulfates, Iron, Zinc)

0

500

1000

1500

2000

2500

Jan-12 Apr-12 Jul-12 Oct-12

mg

/L

Surface Water Sulfates

S1 S2 S4 S5

S10 S11 S13 S14

S15 S16 ANZECC Guideline

0

5

10

15

20

25

30

35

40

45

Jan-12 Apr-12 Jul-12 Oct-12

mg

/L

Surface Water Iron

S1 S2 S4 S5 S10 S11 S13 S14 S15 S16

0

20

40

60

80

100

120

140

Jan-12 Apr-12 Jul-12 Oct-12

mg

/L

Surface Water Zinc

S1 S2 S4 S5

S10 S11 S13 S14

S15 S16 ANZECC Guideline

Page 71: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

63

3.5 Groundwater Quality

Each parameter of piezometer and groundwater quality is summarised in Table 27 and is briefly discussed

below. Groundwater quality results recorded in 2012 are displayed in Figures 14 and 15. Since October 2012,

groundwater samples have been tested for dissolved metals (rather than total metals) and this is likely to impact

the result trends.

3.5.1 pH

Samples collected at piezometer monitoring locations were generally acidic and fell below the lower guideline

limit (pH 6), including P35, P26, P56 and P7. The lowest pH that was measured was at piezometer location P26

with a value of 2.64. The pH at site P26 indicates that the water is highly acidic. No groundwater locations

exceeded the upper guideline limit (pH 8.5). In 2012, sampling indicated seven of the nine sample locations have

increased in pH since 2011. This is a positive change as the pH is becoming less acidic and is moving closer to

the desirable guideline limit.

3.5.2 Electrical Conductivity (Salinity)

All of the piezometer sampling locations recorded higher average salinity levels than the ANZECC guidelines.

The greatest increase since 2011 was an increase of 40,679 µS/cm at the P33 monitoring location. This may be

the result of issues with the electrical conductivity probe used for sampling in the months of January through to

October 2012. Therefore salinity results in 2012 are generally unreliable.

3.5.3 Copper

All of the groundwater sampling locations fell well below the ANZECC guideline value (5 mg/L). In 2012, P15

recorded the highest copper concentration of 1.86 mg/L (May). The majority of the piezometer sampling

locations have shown a reduction in average copper concentrations since 2011. In 2012, P33, P26, P34, P56, P5,

and P7 showed a decrease in copper concentrations. Locations P35 and MB3 experienced an increase in average

copper concentrations since 2011, but they still remain well below the guideline value.

3.5.4 Iron

Groundwater sampling locations recorded the highest average iron concentrations compared with surface water.

Piezometer sampling location P26 recorded the highest concentration of 3,183mg/L. Site P34 had the lowest

average iron concentration at 1.33mg/L. Compared with 2011, more than half of the piezometer sampling

locations have experienced an increase in average iron concentrations. In 2012, groundwater iron concentrations

appeared to vary according to the rainfall. During the higher rainfall periods, concentrations of iron peaked

particularly at piezometer location P56.

3.5.5 Lead

In 2012, no groundwater monitoring locations exceeded the adopted ANZECC criteria for lead (5 mg/L). The

P56 and P15 sampling locations were the only sites that exceeded 0.1 mg/L. The most notable decrease in lead

concentrations since 2011 was recorded at the P56 sampling location, which reduced from 0.74mg/L to

Page 72: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

64

0.47mg/L. On average, lead concentrations collected from groundwater sampling locations remain unchanged

since 2011.

3.5.6 Sulphates

All sulphate concentrations, recorded at groundwater monitoring locations in 2012, exceeded the ANZECC

guideline value of 1,000 mg/L, except MB3. The most notable was at piezometer sampling location P5 which

had an average sulphate concentration of 15,333mg/L. In comparison with 2011 results all of the piezometer

sampling locations experienced a reduction in average sulphate concentrations, with the exception of MB3 and

P56.

3.5.7 Zinc

The P7, P8. P15, P26 and P35 groundwater sampling locations exceeded the adopted ANZECC guideline value

for zinc (5 mg/L). In 2012, the highest zinc concentrations were recorded at P35 (average 41 mg/L) and P26

(average 43 mg/L). Since 2011, the majority of groundwater sampling locations have experienced a decline in

average zinc concentrations.

Page 73: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

65

Table 27 CSA Piezometer Water Quality Monitoring Results 2012

Piezometer Location

Parameter pH Electrical

Conductivity uS/cm

Copper - mg/L Iron - mg/L Lead - mg/L Sulphates - mg/L Zinc - mg/L

ANZECC Guideline 6-9 7,700 5 10 5 1000 5

Year 2011 2012 2011 2012 2011 2012 2011 2012 2011 2012 2011 2012 2011 2012

P35

Average 5.31 5.58 126.74 25477.29 0.15 0.28 909.93 1108.35 0.01 0.01 9982.73 10806 26.24 41.27

(± Std Dev) 0.41 0.42 115.22 48039.15 0.2 0.23 520.74 957.68 0.01 0.01 2559 2489.94 7.31 28.98882

Minimum 4.79 4.95 9.3 2450 0.03 0.04 35.4 19.5 0 <0.001 6470 7440 14.9 6.4

Maximum 5.94 6.1 458 133700 0.74 0.73 1440 2280 0.05 0.02 13200 14700 39.6 91.6

n 12 9 12 7 12 10 12 10 12 10 12 10 12 10

P37

Average 4.09

No Sample Taken in

2012

107.55

No Sample Taken in

2012

30.38

No Sample Taken in 2012

2757.5

No Sample Taken in

2012

4.64

No Sample Taken in

2012

9642.5

No Sample Taken in 2012

160.95

No Sample Taken in

2012

(± Std Dev) 0.09 86.16 52.53 1449.65 8.98 1113.2 69.47

Minimum 4.02 55.2 1.3 1370 0.01 8170 93.8

Maximum 4.22 236 109 4500 18.1 10600 255

n 4 4 4 4 4 4 4

P33

Average 6.75 7.08 141.12 40820.25 0.05 0.03 1.81 3.09 0.01 0.01 2324 2346.36 0.07 0.04

(± Std Dev) 0.53 0.97 100.94 58574.36 0.04 0.02 1.98 5.43 0.01 0.01 234.62 111.29 0.12 0.02

Minimum 5.64 6.4 5 6400 0.01 0.01 0.39 0.08 0 <0.001 1760 2200 0.01 <0.005

Maximum 7.23 9.75 458 182200 0.13 0.07 5.9 18.7 0.02 0.03 2610 2520 0.39 0.09

n 10 10 10 8 10 11 10 11 10 11 10 11 10 11

P26

Average 2.63 2.64 117.39 17928.57 0.5 0.16 2771.43 3183 0.02 0.02 11315.71 12314 49.71 43.44

(± Std Dev) 0.1 0.25 87.99 16441.22 0.14 0.05 280.32 309.48 0.01 0.02 3504.32 1501.62 5.46 6.11

Minimum 2.47 2.26 16 4210 0.34 0.1 2330 2610 0 <0.001 8440 8640 39.9 31.4

Maximum 2.74 3.08 243 53900 0.78 0.24 3090 3600 0.04 0.05 17600 13600 56.7 50.6

n 7 9 7 7 7 10 7 10 7 10 7 10 7 10

P38

Average 2.19

No Sample Taken in

2012

556

No Sample Taken in

2012

35.8

No Sample Taken in 2012

2640

No Sample Taken in

2012

0.06

No Sample Taken in

2012

9010

No Sample Taken in 2012

66.2

No Sample Taken in

2012

(± Std Dev) na na na na na na na

Minimum 2.19 556 35.8 2640 0.06 9010 66.2

Maximum 2.19 556 35.8 2640 0.06 9010 66.2

n 1 1 1 1 1 1 1

MB3

Average 6.13 6.34 52.68 8878.37 0.09 0.1 2.21 4.43 0.01 0.02 244.5 117.29 0.44 0.72

(± Std Dev) 0.08 0.4 12.07 18627.99 0.04 0.15 1.97 5.76 0.01 0.02 136.11 51.27 0.09 0.57

Minimum 6.07 5.82 35 1111.23 0.05 0.03 0.43 15.6 0 0.06 163 177 0.56 0.22

Maximum 6.25 6.99 62.2 46900 0.15 0.45 4.18 0.26 0.03 <0.001 448 17 0.36 1.97

n 4 7 4 6 4 7 4 7 4 7 4 7 4 7

P34

Average 5.48 6.01 100.06 11735.29 0.21 0.04 4.1 1.33 0.01 0 5416.25 6855 0.57 0.32

(± Std Dev) 2.01 0.39 97.47 9852.78 0.24 0.02 4.68 1.38 0.01 0 1333.73 526.44 0.44 0.1

Minimum 0.57 5.14 4.5 18.57 0.04 0.02 0.05 0.1 0 <0.001 8380 5900 0.17 0.22

Maximum 6.73 6.59 220 21300 0.69 0.08 14.3 4.31 0.02 0.01 4050 7560 1.37 0.51

n 11 9 11 7 11 10 11 10 11 10 11 10 11 10

P56

Average 5.82 5.98 65.34 18447.14 0.28 0.12 2919.6 2728.56 0.74 0.47 12032 11165.6 1.37 0.59

(± Std Dev) 0.5 1.37 37.73 22425.22 0.39 0.09 1759.3 2728.59 1.12 0.5 3676.43 3682.76 1.92 0.5

Minimum 5.15 4.6 6.2 400 0.01 <0.001 528 107 0.01 0.01 8000 6770 0.07 0.03

Maximum 6.31 9.08 100 62600 0.89 0.29 4820 6490 2.58 1.38 17100 15700 4.51 1.44

n 5 9 5 7 5 9 5 9 5 9 5 9 5 9

P37

Average 4.09

No Sample Taken in

2012

107.55

No Sample Taken in

2012

30.38

No Sample Taken in 2012

2757.5

No Sample Taken in

2012

4.64

No Sample Taken in

2012

9642.5

No Sample Taken in 2012

160.95

No Sample Taken in

2012

(± Std Dev) 0.09 86.16 52.53 1449.65 8.98 1113.2 69.47

Minimum 4.02 55.2 1.3 1370 0.01 8170 93.8

Maximum 4.22 236 109 4500 18.1 10600 255

n 2 2 2 2 2 2 2

P5

Average 6.8 6.26 18.3 19275 0.37 0.14 29.9 21.08 0.09 0.09 4895 15333.3 0.75 0.51

(± Std Dev) 0.42 0.21 2.26 14463.04 0.4 0.13 24.47 25.83 0.07 0.09 388.91 22874.2 0.17 0.19

Minimum 6.5 5.97 16.7 8100 0.09 0.01 12.6 1.02 0.04 0 4620 5110 0.63 0.34

Maximum 7.1 6.55 19.9 39300 0.65 0.37 47.2 66 0.13 0.22 5170 62000 0.87 0.88

n 2 5 2 4 2 6 2 6 2 6 2 6 2 6

P15

Average

No Samples Taken in

2011

6.28

No Samples Taken in

2011

2200

No Samples Taken in 2011

0.95

No Samples Taken in

2011

62.27

No Samples Taken in

2011

0.47

No Samples Taken in

2011

3793.33

No Samples Taken in

2011

5.42

(± Std Dev) 0.36 - 0.79 52.06 0.37 215.95 1.03

Minimum 5.86 2200 0.5 21.8 0.15 3590 4.24

Maximum 6.5 2200 1.86 121 0.87 4020 6.13

n 3 1 3 3 3 3 3

P7

Average 3.66 4.64 53.26 7870 0.32 0.17 1466.91 1842.5 0.03 0.04 5207.5 6556.25 13.43 13.08

(± Std Dev) 0.6 0.78 23.25 3577.94 0.29 0.12 611.85 142.3 0.02 0.04 2108.51 524.16 1.3 2.05

Minimum 2.66 3.9 15.5 2800 0.09 0.01 25.3 1660 0.01 0 1160 5820 12.1 9.12

Maximum 4.41 5.77 82.1 11140 0.95 0.32 1920 2120 0.07 0.12 8510 7280 16.4 15.3

n 8 6 8 4 8 8 8 8 8 8 8 8 8 8

Page 74: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

Figure 15 Surface Water Quality 2012 (pH, Lead, Copper)

0

2

4

6

8

10

Jan-12 Apr-12 Jul-12 Oct-12

pH

Groundwater pH

MB1 MB3 P5P7 P8 P15P26 P33 P34P35 P56 ANZECC Guideline (lower)ANZECC Guideline (upper)

0

1

2

3

4

5

6

Jan-12 Apr-12 Jul-12 Oct-12

(mg

/L)

Groundwater Copper

MB1 MB3 P5

P7 P8 P15

P26 P33 P34

0

1

2

3

4

5

6

Jan-12 Apr-12 Jul-12 Oct-12

mg

/L

Groundwater Lead

MB1 MB3 P5

P7 P8 P15

P26 P33 P34

P35 P56 ANZECC Guideline

Page 75: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

Figure 16 Surface Water Quality 2012 (Sulfates, Iron, Zinc)

0

1000

2000

3000

4000

5000

6000

7000

Jan-12 Apr-12 Jul-12 Oct-12

mg

/L

Groundwater Iron

MB1 MB3 P5 P7 P8 P15 P26 P33 P34 P35 P56

0

5000

10000

15000

20000

25000

30000

Jan-12 Feb-12 Apr-12 May-12 Jul-12 Sep-12 Oct-12 Dec-12

mg

/L

Groundwater Sulfates

MB1 MB3 P5P7 P8 P15P26 P33 P34P35 P56 ANZECC Guideline

0

20

40

60

80

100

Jan-12 Apr-12 Jul-12 Oct-12

mg

/L

Groundwater Zinc

MB1 MB3 P5P7 P8 P15P26 P33 P34P35 P56 ANZECC Guideline

Page 76: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

68

3.6 Groundwater Levels

3.6.1 TSF Embankment Phreatic Surface Monitoring

There are 42 piezometer monitoring sites positioned around the TSF to measure the phreatic surface of the TSF

embankment walls. These are used to monitor the depth and quality of any water generated by seepage from the

TSF. Of these monitoring sites, 22 recorded water variations during 2012, while the remainder were dry for the

entire year. Wet piezometers indicate water as shallow as 1.8 m below ground level (bgl) and as deep as

19.45 m bgl.

Locations of piezometers are displayed in Plan 2. Figure 16 shows the depths of the wet piezometers around the

TSF. The raw data is provided in Appendix D.

Page 77: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

69

Note: 1. (---) indicates a piezometer dried up during 2012.

Figure 16 CSA Piezometer Water Levels 2012

Page 78: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

70

CSA Mine consultant TSF Dam Engineers (Golder Associates) identified trigger levels for 16 key piezometers

surrounding the STSF in 2011 to comply with DSC requirements from the 2010 TSF surveillance report; these

are displayed in Table 28 . The trigger levels were based on a stability analysis undertaken for the STSF wall

raise design. If trigger levels are breached, the risk of seepage from the toe of the embankment wall and local

sloughing may be increased. None of these trigger levels have been breached in 2012, with the exception of

P35, indicating the STSF is being operated safely and well within design limits.

P35 breached its trigger level of 2.0m by (variation of 0.2m) for three consecutive months (July-October).

Piezometer 35 is located at the downstream toe of the southern embankment of the STSF and has risen

consistently since 2009. The increase in water level can be attributed to water ponding at the toe of the

embankment with limited drainage. During the time the P35 trigger level was breeched, the area was inspected

more frequently, dam engineers were consulted and inspection pits were dug to monitor seepage. Although no

water has seeped into the pits, P35 will continue to be investigated in 2013 and monitored monthly to ensure the

trigger level is not breached.

Table 28 STSF Piezometers and Trigger Depths

Piezometer Trigger Depth

(m)

2012 Minimum

Depth Recorded Date Minimum Depth Recorded

P1 4.6 5.95 12/03/2012

P5 4.4 10.16 12/03/2012

P6 4.3 11.52 19/06/2012

P7 4.4 6.58 19/06/2012

P9 4.2 11.08 27/11/2012

P35 2.0 1.8 25/07/2012

P26 4.6 8.22 28/08/2012

P27 4.3 7.75 12/03/2012

P28 4.4 8.6 all year

P38 4.4 13.5 12/03/2012, 25/07/2012, 30/10/2012

P41 6.0 9.17 28/12/2012

P42 4.0 4.75 all year

P43 6.0 10.25 19/06/2012

P44 4.0 5.03 27/11/2012

P45 6.0 9.765 12/03/2012, 8/05/2012, 19/06/2012,

27/11/2012, 28/12/2012

P46 4.0 5.01 3/10/2012

P51 2.0 4.15 all year

P52 2.0 5.125 27/11/2012, 28/12/2012

P53 6.0 10.15 all year

Page 79: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

71

Piezometer Trigger Depth

(m)

2012 Minimum

Depth Recorded Date Minimum Depth Recorded

P54 6.0 9 23/01/2012, 25/07/2012, 3/10/2012,

30/10/2012, 27/11/2012, 28/12/2012

P55 6.0 10.22 27/11/2012

P56 6.0 10 12/04/2012

P57 6.0 10.98 23/01/2012

All piezometers, with the exception of P14, P15 and P17, are located around the STSF. Piezometers 14, 15 and

17 are located on the north-eastern wall of the NTSF. The water level remained stable at these three sites for

most of the year, with any variations generally corresponding with rainfall.

Water levels recorded for P1, P5 and P7 remained wet throughout 2012. Water levels for P1 and P7 remained

relatively stable while water levels in P5 fluctuated throughout the year, ranging from 10.16 m below ground

level (bgl) (March) to 12.6 m bgl (April). P8 was wet for two months in March and April and ranged from

2.32m to 3.30m. This is expected to be the result of heavy rainfall experienced during this time. P8 has since

dried out, indicating previous seepage issues around this location (the old penstock) may be resolved.

P57 remained dry for most of the year from March to October. Piezometers 14 (variation 0.47m) and 27

(variation 0.1m) remained wet only in the months of March, May and June.

Piezometers 34, 35, 41, 43, 45 and 56 remained wet for the whole year experiencing some minor fluctuations.

P33 experienced a major increase in water level in April, and in the same month the water level in P5 decreased

by a variation of 2.44m since the previous month.

Fluctuations in monitoring bores MB1, MB2 and MB3 are minor. The most notable fluctuation was observed in

MB1 varying by 2.7m and is likely to be the result of rainfall recharge as these are located well away from the

TSF embankment and are very deep bores (92 m, 54 m and 14.8 m respectively) thought to be associated with

separate water fractures or aquifers as discussed in Section 2.8.4. Water quality results from MB3 also show no

connection with seepage water recorded in TSF wall piezometers and were within ANZECC water quality

guidelines as outlined above.

Figure 17 shows a cross-sectional drawing of the typical set up of piezometers around the TSF illustrating how

piezometer readings can be influenced by the discharge of wet tailings material and periods of rainfall. As

indicated in Figure 18, the position of a wet piezometer on the tailings embankment assists with an assessment of

whether or not water detected is due to moisture in the tailings material below, or if it is moisture below ground

level.

Page 80: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

72

Figure 17 Cross Section of TSF Piezometer Setup

The list below indicates which of the wet piezometers are located on the embankment walls or on ground level:

Location / Position:

Ground Level P8, P17, P33, P35

Original Wall P41, P43, P44, P45

Wall Raise 1 P7, P15, P26, P27, P38

Wall Raise 2 P14, P37

Wall Raise 3 P56, P57

Page 81: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

73

3.6.2 Groundwater Monitoring

CSA Mine established a monitoring program in 2011 to measure the depth of ground water from pilot holes

drilled in 2010 surrounding the STSF and NTSF. Consultants were commissioned to investigate the potential for

groundwater harvesting in local ground water systems. The report by consultants Aquaterra completed in 2010

(included in the 2010 AEMR) concluded that there was no likely connection between the TSF and local ground

water systems.

To confirm the findings of the report and understand local groundwater conditions over an extended period of

time, water bores were measured monthly. The measured depths of the 17 pilot holes in 2012 are shown in

Figure 18. The recorded depths indicate the groundwater bores were very stable throughout 2012, with the

maximum variation in depth recorded at 2.74 m in WERC10003, between March 2012 and June 2012. The

small variations (0 m – 3 m) recorded in deep pilot holes (80 m – 100 m) are a likely result of infiltration from

rainfall. The results of the groundwater monitoring confirm the findings of the AquaTerra report indicating no

connection between the TSF and local ground water systems. Pilot holes will continue to be monitored in 2013

to provide baseline data of local groundwater systems and as supporting evidence for any future TSF upgrades.

0

5

10

15

20

25

30

35

400.0

10.0

20.0

30.0

40.0

50.0

60.0

70.0

80.0

90.0

100.0

Mar-12 May-12 Jun-12 Aug-12 Sep-12 Nov-12

Rai

nfa

ll (m

m)

De

pth

(m

bgl

)

Rainfall (tailings Dam Rain Gauge) WERC10001 WERC10002WERC10003 WERC10004 WERC10005WERC10006 WERC10007 WERC10008WERC10009 WERC10010 WERC10011WERC10012 WEBRC10013 WEBRC10014WEBRC10015 WEBRC10016 WEBRC10017

Figure 18 CSA Mine Groundwater Levels 2012

Page 82: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

74

3.7 Contaminated Polluted Land

Surface contamination of soils has occurred throughout the CSA Mine site from various previous mining

activities, including old tailings deposits, decline waste stockpiles, and wastes from a surface smelter. Elevated

levels of copper, lead, zinc and other heavy metals are likely to remain in these areas although the dumps have

since been removed.

Site observations suggest that current mining operations are only one contributor to rehabilitation requirements,

with undocumented legacy issues also relevant. There is high variability in soil quality across the CSA mining

lease, and within individual areas, with minimal vegetation in most areas.

CSA Mine commissioned a progressive soil sampling program in December 2010 to investigate areas of known

and suspected contamination on the CSA Mine Site in order to update the CSA Mine Contaminated Soils

Register. A total of 15 sites with suspected soil contamination were sampled along with five background sites.

These background sites were sampled to build a robust dataset of baseline metal concentrations, pH, salinity and

acid production potential of soils within CML5 that are unaffected by mining activities.

To build on the sampling that was conducted in 2010, a further ten sites were sampled in 2011 to determine

whether sites were contaminated and the level and type of contamination. An additional five background sites

were sampled to build the analogue database of local soil conditions.

Given these sites will ultimately be rehabilitated, additional reference data on the success of vegetation growth

were in addition to the National Environment Protection (Assessment of Site Contamination) Measure 1999

(NEPM) Environmental Investigation Levels (EILs) and background data, to provide an indication of the

potential success of vegetation establishment at each site for given pH and salinity levels.

Of the 10 sites targeted, a total of 8 areas were confirmed as sites of known contamination and two areas were

confirmed as having contamination not significant enough to prohibit rehabilitation and vegetation growth.

These areas are displayed in Figure 19.

Confirmed sites of contamination were primarily the result of elevated Pb, Cu and Zn concentrations above

NEPM EILs and background levels. Contaminated sites were PAF and exhibited a lower pH likely to prohibit

the establishment of vegetation. Contaminated sites also had higher salinity levels compared to measured

background levels; however in the majority of contaminated sites salinity levels were not high enough to be a

limiting factor in rehabilitation.

Page 83: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

75

Figure 19 CSA Contaminated Sites Register (as of 31/12/12)

In 2013, the remaining 4 areas on site suspected of contamination will be further investigated by an expert

consultant commissioned by CSA Mine. In addition, background sites will continue to be sampled in order to

capture local baseline conditions not affected by mining activities. Data on the nature and level of contamination

of sites will assist in defining the requirements for progressive rehabilitation to meet performance and closure

criteria set out in CMPL’s Rehabilitation Monitoring Methodology and Determination of Completion Criteria for

Rehabilitation Ecosystems report. The commitments and actions implemented for rehabilitation on site is

discussed further in Section 5.

3.8 Threatened Flora

The CSA mine is situated within the Cobar Peneplain Bioregion which extends from just south of Bourke to

north of Griffith. It has a total area of 7,334,664 ha and occupies 9.2% of the state. The Cobar bioregion is

characterised by an undulating to hilly landscape with shallow, red earth soils where the vegetation is mainly

open woodlands dominated by bimble box (Eucalyptus populnea), red box (Eucalyptus intertexta) and white

cypress (Callitris glaucophylla). The woodlands of the Cobar Peneplain Bioregion are the most extensive

woodland communities to remain in western NSW.

The 2012 Biodiversity Assessment found 197 flora species presently or previously recorded within CML5 and

concluded the area has high floral diversity. Six Biometric vegetation communities were identified as occurring

at the site, including:

- Gum Coolabah woodland on sedimentary substrates mainly in the Cobar Peneplain Bioregion;

- Gum Coolabah - Mulga open woodland on gravel ridges of the Cobar Peneplain Bioregion;

- Poplar Box - Gum Coolabah and White Cypress Pine Shrubby Woodland mainly in the Cobar

Peneplain Bioregion;

Page 84: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

76

- Mallee - Gum Coolabah woodland on red earth flats of the eastern Cobar Peneplain Bioregion;

- Green Mallee - White Cypress Pine very tall mallee woodland on gravel rises mainly in the Cobar

Peneplain Bioregion;

- Derived mixed shrubland on loamy-clay soils in the Cobar Peneplain Bioregion; and

- Cleared/developed land (Non-native vegetation).

None of these vegetation communities are representative of an Endangered Ecological Community (EEC) listed

under the Threatened Species Conservation Act 1995 (TSC Act) or the Environment Protection and Biodiversity

Conservation Act 1999 (EPBC Act). However, two vegetation communities present within the study area are

likely to be of conservation significance. According to Benson et al. (2006), ‘Popular Box-Gum Coolabah and

White Cypress Shrubby Woodland’ is considered ‘near threatened’ while ‘Mallee-Gum Coolabah Woodland’ is

considered ‘vulnerable’. Both communities are threatened by inappropriate fire regimes, clearing, grazing by

stock and goats, woody weed invasion (likely a result of changes to grazing and fire regimes) and sheet erosion.

No threatened flora species as listed by the TSC Act or the EPBC Act were detected on CML5 during the 1999,

2006 or 2012 biodiversity assessments.

Several factors relating to vegetation condition and disturbance were identified during the 2012 study. These

being overgrazing, alterations to fire regimes, weeds and previous timber harvesting and clearing.

Employees of the CSA Mine undertaking surface exploration activities are provided with information to allow

them to recognise relevant flora and fauna species. All proposed drill sites, roads and tracks are inspected prior

to any exploration activity taking place. The inspections include an assessment of potential risks to flora, fauna

and cultural heritage. CSA Mine employees and contractors are instructed to notify the Environment Team of

the presence of any species or sites of potential importance so that they may be further examined and appropriate

controls or actions put in place. Details of the inspection are documented including the location and any

identified species. The appropriate department is then notified of any follow up and management conditions

required. If exploration personnel have any doubt they are instructed not to proceed with the exploration

activities until clearance is received.

3.9 Threatened Fauna

Flora and fauna surveys conducted before CMPL began operations in 1999 concluded that the re-opening of the

mine and continuation of works would have negligible impact on the surrounding fauna and flora habitat on the

greater lease area. The immediate area up to 5 km in radius from the mine and beyond is covered by the original

Bimble Box woodland providing adequate refuge for ranging species.

The diverse landscape and vegetation of the Cobar Peneplain Bioregion supports a wide variety of fauna species.

A total of 160 Fauna species have been identified within CML5 during the 2006 and 2012 biodiversity surveys,

comprising: 110 bird species; 20 reptile species; 3 frog species, 15 mammal species and 12 bat species.

Nine threatened fauna species and one migratory fauna species listed under TSC Act and EPBC Act were

detected within CML5 during the 2012 Biodiversity Assessment, including:

Page 85: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

77

- Chestnut Quail Thrush (Cinclosoma castanotum) listed as Vulnerable under TSC Act;

- Grey-crowned Babbler (Pomatostomus temporalis temporalis) listed as Vulnerable under TSC Act;

- Hooded Robin (Melanodryas cucullata cucullata) listed as Vulnerable under TSC Act;

- Little Eagle (Hieraaetus morphnoides) listed as Vulnerable under TSC Act;

- Pink Cockatoo (Lophochroa leadbeateri) listed as Vulnerable under TSC Act;

- Varied Sittella (Daphoenositta chrysoptera) listed as Vulnerable under TSC Act;

- Little Pied Bat (Chalinolobus picatus) listed as Vulnerable under TSC Act;

- Yellow-bellied Sheathtail Bat (Saccolaimus flaviventris) listed as Vulnerable under TSC Act;

- Inland Forest Bat (Vespadelus baverstocki) listed as Vulnerable under TSC Act; and

- Rainbow Bee-eater (Merops ornatus) listed as Migratory under EPBC Act.

An evaluation of the likelihood of threatened and migratory species revealed that a further 12 species were either

known to occur, or have the potential to occur in the area based on habitat quality and availability. Three distinct

fauna habitats have been identified across the study area comprising Woodland, Shrubland and Mine

Disturbance.

Six key threatening processes listed under the TSC or EPBC Acts which could threaten (or potentially threaten)

the survival or evolutionary development of a species, population or ecological community, have been identified

as relevant to CML5. These include:

- Competition and habitat degradation by Feral Goats;

- Removal of dead wood and dead trees;

- Clearing of Native Vegetation;

- Predation by European Red Fox;

- Predation by Feral Cats;

- Predation and hybridisation by Feral Dogs.

CSA Mine’s environmental objectives aim to ensure the clearing of native vegetation is minimised where

possible. The mine understands the value of connectivity and is fortunate to be within the Cobar Peneplain

Bioregion, which is the most extensive woodland community to remain in western NSW.

Competition, grazing and predation by feral animals on the CML5 lease are addressed in the CSA Mine Pest

Animal Management Plan. This management plan was first implemented in 2007, and is updated annually. This

management plan will continue to be implemented in the future in order to keep identified feral animals under

control. No fox baiting took place during 2012 as it was agreed collectively between local landholders not to be

required.

During 2012, a total of 1,240 goats were removed from CMPL managed lands. All goats removed from site are

recorded through a Livestock Production Assurance National Vendor Declaration (NVD). A goat cannot be sold

without an NVD which is used to document numbers and locations of goats harvested, provide assurance

landholder access was granted and more importantly to declare information about the food safety status of the

livestock. This compulsory process is managed by Meat and Livestock Australia (MLA).

Page 86: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

78

Feral goat management improved in 2012 with the appointment of a new feral pest control contractor.

Additional personnel and resources were invested into the management of feral goats by the new contractor. It is

expected that the additional investments in goat management will produce further improvements in 2013.

3.10 Weeds

During the 2012 Biodiversity Assessment, nine noxious or environmental weeds were identified within the study

area. These being:

• Onion Weed (Asphodelus fistulosus), intermittent along bitumen road and railway line.

• Patterson's Curse (Echium plantagineum), intermittent along bitumen road and railway line.

• Bathurst Burr (Xanthium spinosum), found downslope of straw mulch in rehabilitation area and at old

house estate.

• Fierce Thornapple (Datura ferox), found downslope of straw mulch in rehabilitation area and at old

housing estate.

• Century Plant (Agave americana), found at old housing estate.

• Aloe (Aloe sp.), found at old housing estate.

• Prickly Pear (Opuntia ?stricta), found at old housing estate.

• Saffron Thistle (Carthamus lanatus) and Spear Thistle (Cirsium vulgare), occasional around perimeter

of mine facility and highly disturbed areas such as tanks.

Exotic flora species are generally only present in developed areas (e.g. bitumen roadsides, railway easement,

some parts of the electricity transmission easements, farm dams, and in/around the mine facility.

The CSC Weeds Officer conducted the annual Noxious Weeds Inspection of the CSA Mine site during May

2012. The weeds officer inspected the site focusing on the most likely locations for weed establishment

including topsoil stockpiles and newly disturbed areas. The CSC Weeds Officer concluded that the CMPL

owned property Red Tank was compliant with Local, State and Federal statutory requirements in regards to the

control of listed noxious weeds.

During the 2012 annual weed inspection, Bathurst Burr was present in patches around the CSA Mine Site and in

isolated patches along the railway edges. The patches of Bathurst burr will be monitored for new growth during

2013 and any necessary actions will be taken to ensure the population is controlled.

The old housing estate behind administration was also inspected to observe the known Prickly Pear infestation.

This infested area has been closely monitored by CMPL since it was originally discovered in mid-2008. Some

cochineal infected segments were released in the infested area in August 2008 as an attempt to biologically

control this outbreak. Unfortunately the infested segments did not take to the shrub and died off. CMPL

environmental staff and the CSC Weeds Officer investigated other options for biological control over 2009,

before resorting to spraying the area with herbicide in November 2009. This herbicide treatment proved

effective in wilting the plant and preventing flowering during 2010. The plant was given a follow up spray in

November 2010 to prevent regrowth. It was determined by the weeds officer that the prickly pear population had

been sufficiently controlled by previous spraying. The population was assessed in 2012 and will be assessed

again in 2013.

Page 87: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

79

Wild Tobacco plants were found colonising disturbed ground during the inspection in the former Everyday

Mining Services (EDMS) yard. Control measures were not considered necessary given the small population and

the low risk which the weed posed. Wild Tobacco was monitored throughout 2012 and no further infestations

occurred. Should further weed infestations be encountered in the future, CMPL will employ species specific

management strategies as outlined in the CSA Mine Weed Management Plan and Handbook.

Weeds have not been noted as problematic in the past and no outbreaks have been recorded. CMPL conducts

annual weed inspections of CML5 in cooperation with the CSC Weeds Officer. Furthermore, Environmental and

Exploration Personnel are trained in the identification and reporting of noxious weeds. Should the CSA Mine

encounter weed infestations in the future, CMPL will employ species specific management strategies as outlined

in the Weed Management Plan.

3.11 Blasting

All blasting and air blasting is confined to the underground mine workings at a depth greater than 1 km. The

mining method adopted at CSA uses bulk emulsion and ANFO initiated by the use of electronic detonation, less

than 500 kg of explosives are consumed per delay. While this method remains in use, no surface monitoring for

vibration is required.

3.12 Operational Noise

Blasting and crushing are the two noisiest operations at the CSA mine site. Both occur more than 700m

underground and are not audible at the surface. The grinding circuit, adjacent to the concentrator, is the loudest

operation on the mines surface. Various pieces of mobile plant equipment are occasionally used for surface

projects, such as for TSF construction works. Such surface activities are typical operations of a mine site, and

thus do not require noise monitoring. The distance of the CSA mine site from the township of Cobar (11 km)

and from residential properties on surrounding land (minimum 3 km) contributes to a lack of operational noise

complaints.

3.13 Visual, Stray Light

Stray light pollution does not impact on surrounding neighbours due to lighted areas on surface being restricted

to a small operational area, and the location of the mine being over 3 km from the nearest residence and 11 km

from the township of Cobar. CMPL has never received a complaint in regard to light, and as such has no need to

amend current practices.

3.14 Aboriginal Heritage

The CSA Mine is located on the traditional homelands of the Ngiyampaa people. This land is of cultural,

economic and spiritual importance to the Ngiyampaa people, and many Elders still hold a deep interest in

cultural matters. Any potential disturbance is therefore carefully considered and agreed upon by all relevant

parties prior to works commencing.

Page 88: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

80

CSA Mine is committed to maintaining good relations with all external stakeholders. Any Aboriginal

archaeological finds, artefacts or information concerning aboriginal sites that are passed on to the company are

appropriately handled and reported to the Office of Environment and Heritage (OEH) as soon as practicable. No

Aboriginal place, object or relic is to be disturbed or damaged without the consent or authorisation of the OEH.

In August 2012, CMPL engaged the Cobar Local Aboriginal Land Council to undertake an Aboriginal Heritage

Survey before undertaking clearing works for a towpath which was required for the installation of a HV cable.

The survey was undertaken as a part of CMPL’s commitment to the NSW Mineral’s Due Diligence Code of

Practice for the Protection of Aboriginal Objects. No items of Aboriginal cultural heritage were found in the

study area. Although not affected by the development, a dead tree stump was identified as having a possible scar;

however, it was determined not to be of cultural importance or an Aboriginal modified tree.

Ongoing open communication and involvement will be maintained and advice sought from the local Aboriginal

community and the regulatory authorities when necessary throughout all future mining operations.

3.15 Natural and European Heritage

Heritage items within CML5 are managed according to the relevant legislation and guidelines, namely the three

pieces of legislation governing the conservation of environmental heritage in NSW: the National Parks and

Wildlife Act 1974, the Heritage Act 1977, and the Environmental Planning and Assessment Act 1979. Any

heritage assessments required will be conducted in line with the CSC Local Environmental Plan (LEP).

There are no identified species, habitats or ecosystems within CML5 that require particular attention or

management with regards to natural heritage. No significant geological and physiographical features have been

identified on sites that are not common throughout the district.

European heritage sites on CML5 include:

Mining Quarters

The site of a miner’s quarters (old housing estate) which was erected in the 1960’s is located on CML5

approximately 400 m south-west of the administration building. The site once contained five houses and

one swimming pool; these were removed after mine closure in 1998. The only remaining remnants are the

bitumen road, some cleared areas with stockpiles of topsoil, and some garden beds that continue to grow

exotic garden species.

“Eloura”

The “Eloura” site is located 1.5 km from the CSA Mine site. This area shows remnants of old rock

gardens and buildings. It is understood that most of the older buildings were removed during mine

upgrades in the 1950s and 1960s. There are some remains of human settlement including scattered broken

glass, ceramics, tin and some intact ornate brick and rock garden beds. The uppermost corner of the site is

located within CML5, however the majority of the site is on the property ‘Gattaca’ on land not owned or

managed by CSA Mine.

Page 89: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

81

CSA Power House

The CSA powerhouse contains five HSF8 Mirrlees diesel engines, manufactured in 1951 by Mirrlees,

Bickerton and Day in Stockport, England. These engines provided the main power supply for CSA Mine

from the early 1960’s, when they were relocated to Cobar from Kempsey, until Cobar was connected to the

State power grid in 1966. The five engines represent excellent examples of medium sized stationary

engines of the mid-20th century and combined with the brush alternators they are an increasingly rare

example of turbocharged technology fitted to diesel engines, a technology previously used to provide

power in rural Australia. The powerhouse building and engines are not listed on any statutory heritage

registers (NSW State Heritage Register, CSC LEP or the Commonwealth Heritage List).

3.16 Spontaneous Combustion

History has shown that there are no items which pose a high direct risk of spontaneous combust ion at the

CSA Mine. Two minor incidents have been recorded since reopening the CSA Mine in 1999. Both

incidents occurred on surface and involved smouldering Cu concentrate at the mill. Mineralogical assessment

of the concentrate at the time failed to identify any contributing factors for these incidents. Whilst some CSA

Cu concentrate has shown signs of spontaneous combustion, it is considered a minor risk, and has not

occurred on site in a number of years. Spontaneous combustion is easily prevented by regular hosing down,

clean-up and stockpile management including stock rotation.

3.17 Bushfire

No fires have been recorded on site in the past and as a result of the prolonged drought and minimal

groundcover, the current threat is quite low. To reduce the risk of fire, firebreaks are regularly maintained

around the perimeter of the operational and infrastructure areas. No open fires are permitted on site for land

clearing or fire breaks, except in accordance with a bush fire hazard reduction certificate issued by local council.

All total fire bans are observed. Hot work permits are mandatory on site for all work performed outside

workshops (and other designated areas) that could generate a flame, fire, heat or sparks. This could include (but

is not limited to) welding, soldering, thermal cutting/heating, grinding, use of electric power tools or lighting

fires.

All on site staff are inducted and educated on the dangers of fire. They are trained in the location and correct use

of fire extinguishers and hydrants in their work areas. The Cobar Rural Fire Brigade is situated on the north side

of town and can be at the CSA mine site within 15 minutes to respond to any surface vegetation fires. The

CMPL Mine Rescue Team is equipped and trained to assist in the event of bushfires on/near the mining lease.

3.18 Mine Subsidence

The CSA Mine subsidence zone is located over 1 km from the current stoping and development activities.

Subsidence occurred prior to the CMPLs operation of the mine; hence the area is excised from the mining lease.

It is very unlikely that there will be another failure through to the surface due to the current mining operation

being significantly deeper in the mine and much more advanced in the mining technique and ground support

used today. The only open void of concern is located underground at 4 Level just off the main decline. This

Page 90: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

82

underground stope has been open for approximately 20 years and is monitored periodically. There have been no

changes to the void recorded during the past 10 years.

The current backfilling method is a combination of CHF and waste rock fill (WRF). The methodology is to fill

all voids created by stope extraction. Stope voids which are going to be exposed again by the stope extraction

activities adjacent to them are filled by placing a 10-15 m high 10% CHF ‘plug’ in the bottom of the void and

then filling the remaining void with 2-4% CHF depending on the geometry of the stope void. If only one side of

the stope void is to be exposed by the next stope then WRF can be placed in the non-exposed side of the void

creating what is termed co-disposal. Stope voids which are not going to be exposed are filled with a 10-15 m

high 10% CHF ‘plug’ followed by WRF. The top down mining method used at the CSA mine requires that a 10-

15 m 10% CHF plug be placed at the bottom of stope voids to allow development back through the bottom of the

stopes for the extraction of the stopes below. If there are no stopes planned below a stope void then the void is

completely WRF.

Given these backfilling methods, it is considered that the likelihood of any underground voids collapsing and

propagating to the surface is extremely unlikely.

3.19 Hydrocarbon Contamination

Hydrocarbon storage, handling and disposal are carried out in accordance with the CMPL Chemical and

Hydrocarbon Storage and Disposal Procedure (PRO-159) developed in compliance with all relevant Dangerous

Goods legislation, WorkCover Codes of Practice, and applicable Australian Standards.

Spill kits are available at various locations around the site and staff and contractors are trained in the use of such

kits during site inductions. Hydrocarbon contaminated soils are removed and disposed of in the TSF. This is a

rare occurrence on site as all fuel and oil tanks on site are bunded.

3.20 Methane Drainage / Ventilation

Deep exploration diamond drilling within the underground mine occasionally encounters a flammable gas

mixture comprising hydrogen (approximately 80%) and methane (approximately 20%). Such occurrences are

rare, short term and of a very small magnitude. Gas levels are generally undetectable or at trace levels when

measured in the exhaust airway. The very minimal amounts of gas that may occur in the mine are released with

all other underground air via the Main Return Air Ways (RAW) on surface. These releases are highly unlikely

to have any reportable detrimental effect on the environment, if any at all, due to the minuscule levels

encountered.

All localised and short term safety implications at the CSA Mine site are managed as per the CMPL

Underground Flammable Gas Management Plan (MHP-003).

Ventilation in the underground mine is managed through the Mine Ventilation System. This system circulates

fresh air through the underground workings in order to:

Supply breathable, oxygenated air to underground personnel;

Page 91: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

83

Remove dust, fumes, toxic and flammable gases from the underground environment (through return air

ways) and cool working areas by removing heat emitted by the surrounding rock and diesel equipment.

3.21 Public Safety

The CSA Mine site is clearly signposted on the main access road and is fenced to prevent accidental entry. The

main entry area is subject to high security gates and an electronic tag entry system. CMPL ensures all activities

permitted on the lease do not interfere with or damage fences and that all gates within the lease areas are closed

or left open in accordance with the requirements of the landholder. The boundary fences are signposted and

monitored regularly for damage or any sign of intrusion. A perimeter inspection of the site is carried out on a

monthly basis.

All persons entering the site must undergo a site induction. Employees and contractors complete (at a minimum)

a general surface induction, with additional inductions also completed for specific work areas (e.g.

underground). All visitors, delivery drivers or short term contractors are inducted through the CMPL visitor

induction program. They are required to conform to site PPE requirements and are accompanied on site at all

times by a fully inducted CMPL or contracted employee.

3.22 Other Issues and Risks

3.22.1 NSW Dam Safety Committee Surveillance Report

TSF Inspection reports are completed annually by qualified Dam Engineers (Golder Associates) for submission

to the NSW Dam Safety Committee (DCS). In 2012, the Surveillance Inspection took place on the 24 January

2012 and the next annual inspection is scheduled for January 2013.

The 2011 Surveillance Report included 12 recommendations, which were all been completed in 2012 and

include;

The hole in the crest of the old perimeter embankment was plugged with concrete following the

inspection. The plugged hole should be subject to observation during routine CMPL inspections as

further settlement may occur. The plugged hole is now subject to observation during the weekly

inspection (as per the CSA Mine South Tailings Storage Facility Weekly Inspection Checklist).

Erosion of the safety bund up slope from Piezometer P28 should be remediated. Completed at the end

of July 2012 by outside resources, the area of the erosion was cleared using light machinery. A

combination of topsoil and rock was placed into the erosion point along the lower eastern side of the

STSF. This process was repeated until the bunding wall was reinstated and battered down.

Page 92: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

84

Erosion ruts on the upstream slope should continue to be monitored. They are currently too small to

warrant remedial work and will be progressively buried by tailings deposition. Work has been included

in the weekly inspections and will be monitored weekly (as per the CSA Mine South Tailings Storage

Facility Weekly Inspection Checklist).

The Erosion rut downstream slope of the eastern embankment (where slope flattening works were

undertaken) should be remediated. This area should continue to be monitored prior to establishment of

vegetation. This was completed in July 2012 by outside resources using heavy machinery. The erosion

rut was dug down 500mm and widened 5,000mm, a geotextile membrane cloth was laid into the new

rock wall drainage system then covered by 200mm of waste rock material. The top road way and drain

were then diverted to the one wall drainage system to prevent further erosion points along the east side

wall of the STSF.

The drainage bund along the toe of the old perimeter embankment on the eastern side of the STSF

should be remediated where erosion damage has occurred. This was completed in July 2012. The toe

was repaired using outside resources and light machinery. The erosion points were all filled using a

Page 93: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

85

combination of topsoil and rock filling at each erosion point and then battered down to prevent damage

to the toe of the STSF. The area was returned to normal weekly inspections.

Rockfill should be used to buttress the side slopes of the STSF deposition causeway where tension

cracks have developed at the crest edge. Cracks on the crest should continue to be monitored. This was

completed in July 2012 by outside resources using heavy machinery. The causeway was repaired and

raised as per the recommendations of Golder Associates in the July 2012 capacity assessment report.

The process required removing the deposition line off the causeway using an excavator and transporting

the combination material and dumping in piles along the causeway using haul trucks. The piles were

then pushed out with a D6 caterpillar dozer and battered down by the excavator. Once completed the

deposition line was reinstated and the area was returned to normal weekly inspections (as per the CSA

Mine South Tailings Storage Facility Weekly Inspection Checklist).

Tailings that have deposited from a pipeline leak at the North West corner of the STSFE should be

removed. Bunding around the pipeline should be formed to limit the spread of potential future leaks.

This was completed at the end of July 2012 by outside resources. The area of leaked material was

cleaned up using light machinery and placed onto the STSF deposition. A new bunding wall was

constructed along each side of the piping using topsoil and rock material to prevent the future spread of

leaks.

Page 94: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

86

Cracks and separated joints at the concrete spillways should remain on the agenda for repair until

contractors become available. This was completed in December 2012. A Submission of a scope of

work to repair the spillway and the construction of the retaining plates was completed and installed by

CSA Mine. The retaining plates were constructed from 6mm flat bar cut in to 1m lengths and two pack

painted. The separation point was then filled using a combination of fill foam, stixaflex and grout. Each

plate was then measured to fit for each selected location and dyno-bolted down using 12x70mm bolts.

Erosion ruts on the rockfill buttress over the old penstock should be monitored. The extent of erosion

currently does not warrant remedial work. This area is now subject to observation during the weekly

inspection (as per the CSA Mine South Tailings Storage Facility Weekly Inspection Checklist).

The geo-membrane liner in the western compartment of the Decant Dam should be inspected for holes

and other damage when it becomes dry. A geo-synthetics contractor should be engaged for all geo-

membrane repairs. The base of the dam geo-membrane liner has been inspected during and the summer

period and no holes were identified.

The holes and cracks in the crest of the perimeter embankment to the eastern compartment of the

Decant Dam should be monitored. Remedial works may be required if these holes and cracks increase

in size. The Crest of the eastern side of the STSF was repaired in July 2012 by outside resources using

heavy machinery.

Page 95: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

87

Silt traps or filter bunds formed with waste rock (should be installed in the stormwater drains, just

upstream of the outlets into Stormwater Collection Pond to limit sediment accumulation in the Pond.

This was completed in July 2012 using an outside resource. The silt traps were constructed using a

waste rock base covered in geotextile membrane cloth and a combination of topsoil and rock. A total of

4 silt traps were constructed along STSFE towards the storm water collection pond.

The next Annual STSF Surveillance Inspection is due on the 17 January 2013 by the Golders Dam Engineers.

CMPL is committed to continuing to improve its processes for the safe operation of the TSF.

3.22.2 External Environmental Compliance Audit 2012

In August 2012, CSA Mine commissioned an environmental compliance audit to measure compliance against:

Consolidated Mining Lease 5 (CML5);

Environment Protection Licence 1864 (EPL 1864);

Local Development Consent No. 31/95;

Local Development Consent No. 2006/LDA-00009;

Local Development Consent No. 2009/LDA-00035 and associated Statement of Environmental Effects;

CMPL Mining Operations Plan 2008-2012; and

Other legislative and due diligence observations.

Out of the total 171 compliance requirements audited, CMPL achieved an overall compliance rate of 96.4%, of

the applicable compliance requirements, including all “Compliance” and “Part Compliance” results recorded.

There were five Non Compliances observed at the time of the audit, amounting to 3.6% of the overall number of

Page 96: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

88

applicable compliance requirements. There were 20 part compliances identified (14.5%), and 33 of the 171

requirements were not applicable at the time of the audit (19.3%). A total of 37 recommendations were made. It

should be emphasised that the bulk of the non-compliances identified in this audit relate to the process of

reviewing management plans and other documentation associated with the 2010 Project Approval, and do not

detract from the audit finding that the fundamental processes of environmental management and monitoring at

the site are undertaken to a high standard.

The principal finding of the audit was that the CSA Mine is operated materially in accordance with the

regulatory documents and with good mining practice.

3.22.3 Annual Return

The CMPL 2011-2012 Annual Return was submitted to the EPA in June 2012. For the seventh consecutive year

the CSA Mine had no EPL non-compliances. A copy of the Annual Return in provided in Appendix F.

3.22.4 Environmental Incidents

CMPL maintains a detailed internal incident database for the recording of all incidents reported on site. All

CMPL employees and contractors are trained in incident reporting as part of the site induction program. An

online event report must be submitted for any unplanned incident or event that occurs at the CSA Mine. This

includes environmental incidents, as well as any personal injury, property loss or damage, hazards and near

misses.

The degree of reporting undertaken by CSA Mine is much greater than is statutorily required, and the general

culture at the CSA Mine is a preference to reporting everything over under reporting. The majority of

environmental incidents generally involve leaks and spills, which are reported regardless of whether they are

contained in a bund or not, and regardless of the material spilt (e.g. tailings, process water, backfill).

Major incidents that can occur on site and require notification of the Environmental Pollution Hotline (EPA) are

those involving the death or injury to fauna on or associated with the TSF, and/or incidents causing or

threatening material harm to the environment. In the event of such an incident, the EPA is notified verbally

within 24 hours, and by written report within 7 days, of the incident occurring. During 2012, three EPA

reportable incidents occurred, two relating to kangaroo deaths and the other a 500-600 L oil spill.

Overall, there was a rise in fauna deaths from 2011 (7) to 2012 (11). Most of the faunal deaths in 2012 were

birds (7) and kangaroos (2). Verbal and written reports were provided as per CMPLs EPL requirements to the

OEH (EPA).

In 2012, there was a decrease in the number of tailings spills as well as hydrocarbon spills. Tailings spills

decreased from nine in 2011 to six in 2012 and predominately occurred at the Tailings Booster Hopper at the

TSF. A reduction of spills in this location over 2012 can be attributed to an upgrade of the booster hopper

containment pond in June 2011. This upgrade improved the containment pond’s capacity and access.

Furthermore procedures relating to the operation of the hopper were reviewed and an environmental training

package was rolled out to members of the Ore Processing Team in June 2011. The training emphasised the need

to implement procedures reducing and minimising the risk of spills of tailings and other contaminated

Page 97: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

89

substances. As a result, a significant improvement was expected in 2012 and the number of spills is expected to

continue to decrease in 2013.

Figure 20 provides a comparison of incidents occurring in 2010 and 2011. Table 29 provides information on all

environmental incidents occurring at CSA in 2011.

Figure 20 CMPL Environmental Incidents by Type 2011 and 2012

Page 98: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

90

Table 29 CSA Environmental Incidents 2012

Incident Number Date of Incident

Incident Type

Incident Details Immediate Corrective Actions

504350 (Risk: N/A) 2-Jan-12 Tailings spill Tailings line failure. When changing over the tails lines to send it to the tailings thickener the line to the thickener failed

due to the flange bolts being rusted through on the T-piece. Spill was let to dry out and cleaned-up. Tailings overflow material was taken to the TSF.

504362 (Risk: N/A) 4-Jan-12 Battery Acid

Spill

When moving a pallet of plastic wrapped batteries from the LV Workshop to the collection truck the forklift hit a bump causing plastic to break and one battery to fall off the pallet. The battery was pierced and leaked approximately 0.5 L of

battery acid on the paved roadway.

Battery acid was cleaned up immediately with a spill absorbent pad and disposed of appropriately.

504889 (Risk: N/A) 26-Mar-12 Tailings Spill Density gauge failed and tripped out power to the backfill plant causing the sand transfer tank to overfill and splash over. As the wind was up it caused it to blow on the ground outside the bund. There was around 100lt of tailings spilt outside

of the bund. Spill was left to dry out and cleaned-up. Tailings overflow material was taken to the TSF.

1 ( Risk: Low) 1-Jul-12 Tailings

overflow Tailings Booster Pump overflowed – all material remained inside bunded area. Spill was let to dry out and the bund cleaned-up.

3 ( Risk: Low) 2-Jul-12 Tailings overflow

Tailings Booster Hopper overflow – all material remained inside bunded area. Spill was let to dry out and the bund cleaned-up.

INC232 ( Risk: Low) 11-Jul-12 Fauna death Kangaroo found drowned in the Tailings Storage Facility. The incident was reported to EPA via their hotline, followed by a written report.

INC284 ( Risk: Low) 25-Jul-12 Grout spill Approximately 300lts of grout spillage leaked from the Ground Support Design Trial pad for the Shaft Extension Project.

The pump was immediately stopped. The material was left to dry out and clean-up was completed once material was dry enough to scrape up. All contaminated material was taken to the TSF designated disposal area. The environmental team was notified and attended scene for

inspection.

INC269 ( Risk: Low) 31-Jul-12 Fauna death A dead turtle was found at the Pork Pie Dam. Reported to supervisor and removed turtle.

INC144 (Risk: N/A) 6-Aug-12 Hydrocarbon

spill Old diesel line was hit during excavation, leaking approximately 40lts of old diesel into the trench.

The damaged Diesel line was repaired and the contamination was cleaned up and disposal of t the designated disposal site of the TSF.

INC107 ( Risk: Low) 12-Sep-12 Hydrocarbon

spill Oil Spill at store yard 500-600lts caused by a pierced pod (from contact with a forklift).

The spilled oil was redirected into a bunded drain nearby, approximately 2 meters from the pierced pod. Absorbent material (MOP) was used to soak the residue left in the affected area

and immediately disposed of.

INC108 (Risk: N/A) 16-Sep-12 Fauna death A dead kangaroo was found in the tailings dam. The incident was reported to EPA via their hotline, followed by a written report.

INC113 (Risk: N/A) 16-Sep-12 Fauna death A dead owl found near the tailings booster hopper. No defined cause could be determined.

INC27 (Risk: N/A) 26-Sep-12 Fauna death A large dead bird was found at the setting ponds. Bird was removed and put into bin. No defined cause could be determined.

INC97 ( Risk: Low) 3-Oct-12 Fauna death A dead bird was found on mill 3 platform. Bird was removed and put into bin. No defined cause could be determined.

INC19 (Risk: N/A) 3-Oct-12 Tailings spill The Booster Hopper at the tailings dam overflow – all material remained inside the designated bunded area. The pump was restarted and flow to the dam was re-established. Once the spillage had dried,

the material was removed from the bund and disposed of in the TSF.

INC35 ( Risk: Low) 3-Oct-12 Fauna death Dead Bird found under residue pump hopper Bird was removed and put into bin. No defined cause could be determined.

INC301 (Risk: N/A) 3-Oct-12 Tailings overflow

The Booster Hopper at the tailings dam overflow – all material remained inside the designated bunded area. The pump was restarted and the flow to the dam was re-established. Once the spillage had dried, the material was removed from the bund and disposed of in the TSF.

INC99 ( Risk: Low) 17-Oct-12 Fauna death Dead bird found at copper thickener The dead bird was removed and placed in a bin. No defined cause could be determined.

363 (Risk: Medium) 20-Oct-12 Fauna death Dead Bird found on flotation floor between banks 1 & 2 The dead bird was removed and placed in a bin. No defined cause could be determined.

INC141 ( Risk: Low) 15-Nov-12 Fauna death A dead snake was found on the road near reclaim conveyor. The dead snake was removed and placed in a bin.

INC77 ( Risk: Low) 27-Nov-12 Fauna death Dead Bird found at copper thickener bund The dead bird was removed and placed in a bin. No defined cause could be determined.

INC91 ( Risk: Low) 7-Dec-12 Non-

hazardous spill

Non Hazardous spill was caused when a drum was backed into and pierced. The spill was contained and supervisor was informed and substance is diluted.

INC162 (Risk: N/A) 11-Dec-12 Hydrocarbon

spill Storm water contaminated with hydrocarbons contaminated soil after a storm drain was unblocked.

All contaminated soil was scrapped and disposed of in tailings dam. The drainage in the area was also re-established and the stormwater drains inspected.

Page 99: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

91

4 COMMUNITY RELATIONS

The CSA Mine is an owner operated mine currently employing 351 permanent staff (including apprentices) and

on average 195 contractors. The mine is operated on a 24 hour basis, 365 days a year. The majority of

underground and mill workers do shift work on a four-on four-off roster system, whilst day staff (management,

administration, maintenance) work 5 days per week. The bulk of the CSA workforce lives within the Cobar

Township, contributing a considerable flow on economic benefit to the local community and local economy.

The CSA Mine apprenticeship scheme continued into 2012 with 17 apprentices employed at the end of the

reporting period. Three apprentices successfully completed their apprenticeships at the end of 2012.

In addition to this program CSA Mine also hosts visitors from several universities for vocational work

experience and major projects, during 2012 a total of 8 students were employed at the CSA Mine.

CMPL continued its partnership with the University of Tasmania during 2012. A project by a Geology PhD

student titled “Controls on mineralization, including sulphide mineralogy, at the CSA Mine, Cobar NSW”

commenced in 2010 and was continued throughout 2011 & 2012. The PhD student and the CSA Geology team

are attempting to improve the success rate from drilling within and around the mine and regional exploration.

The main aim of the project is to deliver an enhanced and more predictive model of the CSA Mine via

understanding the controls on mineralization (including the development of an understanding of the spatial

variability of sulphide mineralogy and the dependence of sulphide mineralogy on mineralization controls).

4.1 Environmental Complaints

In compliance with the CSA Mine’s EPL conditions, CMPL maintains a 24 hour telephone pollution complaints

line through the CMPL reception switchboard. The phone number is advertised to the local community via the

local newspapers and the White Pages. All environmental complaints are directed to the Health, Safety &

Environment Team, and are recorded as per the CMPL Environmental Complaints Procedure and Record Form.

No complaints were received from the public during 2012.

4.2 Community Liaison

Community support is essential in maintaining the CSA Mine’s future operations in Cobar. To secure ongoing

links with the community, CSA Mine’s Human Resources Superintendent now holds a position on the recently

formed Cobar Health Services Advisory Committee, the purpose of this committee is to make recommendations

aimed at improving health care services in Cobar to the Western Area Health Services Board. CSA Mine

regularly communicates its operational plans to the local community. This is undertaken through:

Ongoing liaison with Cobar Shire Council (CSC);

Providing open and honest feedback to the workforce and contracting companies;

Local newspaper media releases; and

Involvement with key community groups and projects.

Examples of CMPL’s involvement in the community are detailed in the following sections.

Page 100: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

92

4.2.1 Working with the Cobar High School

In 2012, eight new apprentices started a four year apprenticeship in the field of Mechanical Trades, Electrical

Trades and Metal Fabrication & Welding at CSA Mine. This represents an increase of 5 apprentices from the

intake of 2011. CSA Mine received 100 applications for the 8 apprenticeships, the majority of which were local

school leavers.

CSA Mine staff attended a “Try and Trade” careers day at Cobar High School in 2012 which involved engineers

from CSA Mine giving interactive presentations on the many different careers they can pursue with the CSA

Mine. CSA Mine staff from the Environmental, Mining Engineering and Metallurgy Departments also

volunteered their time as supervisors for the Outback Science and Engineering Challenge in May 2012.

CSA Mine continue to host an annual visit for the Year 9 Geography excursion to the mine, which took place in

June 2012. Students learnt how to measure distance and height changes, length and vertical exaggeration on a

GPS by collecting data and drawing a cross sectional diagram of the TSF. The students and teachers were given

a site tour and enjoyed learning about the CSA Mine.

Cobar High School Students Visiting the CSA Mine

4.2.2 Clean Up Australia Day

CSA Mine participated in the Business Clean Up Australia Day for the seventh consecutive year on the 21st

March 2012 by hosting a site wide clean up at the CSA Mine. All employees were encouraged to participate and

do their part for the local environment. Participation was good with 17 enthusiastic volunteers putting their

energy into the clean-up and managed to clean the entire length of the mine access road to the highway

collecting 13.5 bags of recyclables and 8.5 bags of general waste. A BBQ lunch was held following the clean-up

to thank all volunteers.

Page 101: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

93

CSA Staff Volunteers Taking Part in Clean Up Australia Day 2012

4.2.3 National Tree Day

On the 27th

July, CSA Mine participated in National Schools Tree Day by planting 60 trees at Cobar High School

with students from year 7 and 8. By participating in tree day, CSA Mine is able to promote the message of caring

for trees and restoring habitat to disturbed areas. It also gave the CSA Mine Environment Team an opportunity to

talk to the students about the importance of biodiversity for ecosystem health.

The students were responsible for preparing the ground, planting, fertilizing and erecting a protective guard

around each tree. The trees were sponsored by the CSA Mine to foster their ongoing relationship with Cobar

High School and encourage kids to learn about sustainability.

CSA Employees taking part in 2012 National Tree Day at CSA Mine

4.2.4 National Recycling Week

CSA Mine took part in the National Recycling Week campaign 2012, which ran from Monday 12th

to Sunday

18th

November. As National Recycling Week promotes the importance of reducing, reusing and recycling, CSA

Mine participated by running its first ‘Waste to Art’ competition for CSA Mine workers and their kids. The task

of the ‘Waste to Art’ competition was to create something interesting, useful or beautiful out of something that

would usually be thrown away. The artworks celebrated the re-use and recycling of materials that would

normally end up in landfill.

Page 102: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

94

Winners of the 2012 ‘Waste to Art” Competition

4.2.5 Ride to Work Day

A group of 3 CSA Mine employees opted for two wheels instead of four on their journey to work on 17th

October 2012 as part of CSA Mine’s participation in the National Ride to Work Day.

Ride to Work participants met up on the edge of town on the Wednesday morning to complete the 15 km

journey. A volunteer support crew travelled with the riders who all successfully arrived at the CSA Mine in

times varying between 25 to 40 minutes

Ride to Work day is an annual event at the CSA Mine, which aims to encourage more people to park up the car

and take up riding on a more regular basis. CSA Mine employees were part of more than 36,000 people across

the country who took part in the national event.

4.2.6 Community Contributions

CMPL contributed $118,280 to the local economy over the 2012 period through awarding employees with Cobar

Quids to be spent as part of our Rewards and Recognition program.

CMPL contributed $73,533 in donations during 2012, the recipients of which are listed in Table 30.

Page 103: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

95

Table 30 CMPL Donation Recipients 2012

Local Community Groups

Sporting Organisations

Charities Local Schools

Buckwaroon Landcare

Yarrabin

Cobar Business Association Inc.

Cobar Cemetery Restoration

Cobar Community Radio Station

Cobar Enterprise Facilitation

Cobar Memorial Services Club

Miners Ghost festival (CSC)

Cobar Primary Health Care Centre

Cobar Show Society Inc.

Cobar Theatre Company

Cobar Youth Council

Cobar Blues Football & Netball Club

Cobar Judo Club

Cobar Junior Rugby League

Cobar Junior Soccer Club

Cobar Lady Golfers

Cobar Little Athletics

Cobar Clay Target Club

Cobar & District Rugby Union

Cobar Senior Rugby League Club

CSA Men's basketball team

CSA cricket team

Hannah Kritz - to attend PSSA champs

Copper City Dog Trial

Cobar Miners Race Club

Cobar Rodeo Committee Inc.

St John’s School

Variety, the Children’s Charity

White Ribbon

Isolated Children & Parents Ass’n

Mickayla Strudwick- mobility scooter

Jones Family fund raiser

Kidney Health (Kar Rally)

Royal Flying Doctor Service

Cobar Police Charity Golf Day

Brian Mitchell- support for Far West Academy of Sport

Cobar High School programs

Cobar Outside of School Hours Service

Cobar Public School P&C

Jerangle Public School

Cobar High School- Outback Science & Engineering

Other

AusIMM Student Chapter

Scout Association of Australia

Golden Mile Foot Race

Page 104: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

96

5 REHABILITATION

CSA Mining Lease conditions state that land disturbed must be rehabilitated to a stable and permanent form

suitable for a subsequent land use that is compatible with the surrounding land and land use requirements.

CSA Mine is currently in the operational stage of mining with most surface disturbance already taken place and

the mine in steady production. All expansion and upgrade works that occurred in 2012 at the CSA Mine were

simply replacements which did not generate any significant additional disturbance. The sections below detail

what CMPL is doing to ensure the rehabilitation requirements of the Mining Lease are met.

5.1 Buildings

Significant clean up works were carried out over 2012 with the removal of a number of redundant buildings and

infrastructure from the surface working areas. An experienced demolition and scrap steel contractor was

commissioned over a 2 month period and removed the following items from site:

Removal of old copper thickener and storage tank.

Removal of old mill 4 plinth.

The Old EDMS batch plant is due to be removed in early 2013 and the remainder of the infrastructure, such as

the storage shelter, concrete bunds, and concrete pad, is scheduled to be removed later in 2013.

The clean up works on site are to remove redundant infrastructure. There are currently no plans to remediate or

rehabilitate any of the sites remaining once the infrastructure has been removed.

5.2 Redundant Piping Removal

In 2012, an audit was undertaken at the CSA Mine site to ensure adequate bund capacity for necessary pipes and

to identify redundant pipework for removal. Surface piping and associated bunding were inspected at the

following areas:

Ore Processing Plant and associated areas;

Southern Tailings Storage Facility (STSF);

Backfill Plant; and

Surface Wash bay.

The audit revealed many redundant pipes requiring removal on the surface operational area. The removal of

these pipes was completed in August 2012. Some minor pipes not currently in use will remain intact until

proposed new infrastructure is installed as part of the proposed Mill Upgrade Project in 2014. Bunding of pipes

was assessed and found to be sufficient across site except in one area next to the tailings thickener booster pump.

Construction of adequate bunding in this area was completed in 2012.

In 2013, it is anticipated that a more comprehensive site wide surface audit for current piping requirements will

be conducted.

Page 105: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

97

Examples of redundant pipes that were removed from site during 2012.

5.3 Rehabilitation of Disturbed Land

The total area of the CML5 Mining Lease is 2,474 ha, with approximately 243 ha of this subject to disturbance

associated with the CSA Mine surface operations. Of the 248 ha site disturbance area, 117 ha is excised from the

lease leaving approximately 130 ha of land requiring rehabilitation by CSA Mine prior to mine closure. The

currently operating TSF accounts for approximately 87 ha of disturbance.

The CSA Mine 2008-2012 MOP committed to undertaking 42.3 ha of rehabilitation. The underground internal

shaft extension project was commissioned in 2010 which resulted in the majority of areas identified for

rehabilitation being utilised as laydown areas. Due to the small size of the CSA Mine operational footprint and

the area requirements of proposed major projects, no additional areas were identified for rehabilitation during the

2008-2012 MOP period. Instead, efforts were focused on securing a Property Vegetation Plan for CML5, the

removal of redundant infrastructure, and the identification of methods to further improve existing rehabilitation

areas. These efforts will aid CSA Mine’s progressive rehabilitation plan in the future. The soil remediation trial

plots, located adjacent to the excised old subsidence area (north-west of Administration building), were not

required to accommodate contractors on site and were successfully rehabilitated during the 2008-2012 MOP

period.

In 2013 CMPL will implement a 5 year rehabilitation strategy for the CSA Mine. This strategy is intended to

identify areas currently available for rehabilitation, prioritising these areas and budgeting for ongoing

rehabilitation works and maintenance.

5.3.1 Little Mount Brown and Subsidence Area

Rehabilitation works were undertaken at the Little Mount Brown and Subsidence Areas in 2009 to manage the

overland flow of storm water and improve surface stability. The works were designed to ensure the long term

stability of the site and satisfy performance criteria of landform establishment outlined in CMPL’s Rehabilitation

Monitoring Methodology and Determination of Completion Criteria for Rehabilitation Ecosystems report. While

this work created a stable landform, past contamination and the limited growth media present has limited

ecosystem development.

Previous attempts at seeding with native grass seeds have not been successful at establishing vegetative cover.

The soil profile at the CSA Mine is typical of ridge areas in the Cobar Peneplain Bioregion with very shallow

Page 106: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

98

soils; bedrock is visibly present on the surface in some areas. Observations of the rocks at this rehabilitation site

reveal discolouring, indicating a high metal content. This contamination is likely due to residues from a smelter

which once existed in close proximity to the site and was removed many years ago.

To assist with ecosystem establishment, the principles of Land Form Function Analysis (LFA) are utilised to

create a series of patches and inter patches for monitoring. Monitoring of the rehabilitation at Little Mount

Brown and the Old Subsidence Area was undertaken by specialist consultants in 2011 and again in 2012 as part

of CMPL’s annual Rehabilitation Monitoring program. Results are briefly discussed below and in more detail in

Section 5.5.2. The Rehabilitation Monitoring Program Report (2012) is available as Appendix G.

Monitoring results revealed both sites reached key performance indicator (KPI) targets set out in the

Rehabilitation Monitoring Methodology and Determination of Completion Criteria for Rehabilitation

Ecosystems report for riling and exchangeable soil percentage. However, the sites continued to fall below target

ranges for organic matter, ground cover, as well as mature and juvenile trees and shrubs. These short comings

will be investigated further in 2013.

Results have been positive with Punty Bush (Senna artemisiodes) shrubs establishing on the site. The

performance of rehabilitation progress will be assessed against KPIs including infiltration, stability, nutrient

recycling, organic matter and ground cover through the Rehabilitation Monitoring Program in 2013.

An inspection of the Subsidence Area Rehabilitation Project was undertaken on 10th

September 2012 to identify

further rehabilitation works required in the area. The inspection determined the need for drainage repairs on the

eastern wall, the fencing of vegetation establishment trial plots, investigating the poisoning of rabbits, the

construction of drainage on the western side of the hill, and repairs made to the fencing surrounding the

subsidence zone area to deter pest goats. The fencing of trial plots was completed in December 2012. The

remainder of these requirements will be investigated further in 2013.

Little Mount Brown Rehabilitation Area Following Topsoiling and Spreading of Barley Straw

5.4 Other Infrastructure

5.4.1 Excised Areas

Discussions between the DRE Derelict Mines Department and CMPL continued throughout 2012 in order to

further progress with a potential Excised Area rehabilitation project.

Page 107: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

99

During 2012, CMPL submitted an Environmental Desktop Review of the North Tailings Storage Facility

(NTSF) in conjunction with Dam Engineers and Rehabilitation specialists from Golder Associates. This was

developed with the intention of getting all available detail around the existing environmental issues associated

with the NTSF reviewed and identifying information gaps and recommendations for further assessment. The

proposed recommendations included further assessment of landform stability, erosion management and tailings

assessment. This report was submitted to the Derelict Mines Program (DMP) for consideration in June 2012.

A response was received from the Department in October 2012 stating that it is considerd the current proposal to

use mine generated fill material to form a non-free draining surface without provisions for a permanent cover

will not result in significant benefit or asssit in the long term management of the site. The response states that the

proposal will not be considered further unless there is committement by CSA Mine to construct a permanent

cover which meets industry guidelines.

CSA Mine and Golders have therefore not progressed any further with this potential NTSF rehabilitation project.

No further discussions or investigatory works are proposed for the future in regards to the NTSF rehabilitation

works by CSA Mine.

5.5 Rehabilitation Trials and Research

CSA Mine actively works towards progressive rehabilitation over the operational life of the mine. The

rehabilitation of sections of the mine site as they become available will assist in reducing the long-term closure

liability. Obvious benefits of progressively rehabilitating non-operational areas of the mine include:

Reduction of the overall un-rehabilitated ‘footprint’ of the mine;

Ability to trial various options and demonstrate rehabilitation outcomes well before mine closure;

Reduction of closure costs; and

Reduction of the ‘security bond’ posted with regulatory authorities.

CSA Mine continues to research, trial and monitor the availability of rehabilitation options suitable to our

specific site conditions and climate.

5.5.1 Tailings Dam Rehabilitation Trials

CSA Mine commissioned a vegetation trial on the STSF during 2011, which continued to be maintained and

monitored over 2012. The trial is located in the north west corner of the STSF and is aimed at trialling different

methods to successfully establish vegetation on the tailings surface. The results of the trial will provide ongoing

feedback into CMPL’s completion criteria for rehabilitation ecosystems by providing potential methods to

achieve identified performance and closure criteria.

Following review of CSA’s TSF cover design options, a store and release cover system was selected largely

based on climatic factors and resources available for rehabilitation. Store and release cover systems are designed

to cover sulphide bearing waste rock which stores moisture during wet periods and releases moisture during dry

periods and are well suited to semi-arid conditions. The function of this design is to limit rainfall infiltration and

oxygen ingress into underlying waste material.

Page 108: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

100

Four cover treatments were selected for the trials on four separate plots. The treatments were selected on their

ability to provide a potential growing medium and their availability on site as a resource for large scale

rehabilitation. These included:

Control (no cover treatment).

Clean topsoil placed on the tailings surface.

Compacted waste rock placed on the tailings surface.

Virotec Terra B Reagent placed on the tailings surface.

Virotec Terra B is a commercially available product used to treat mine wastes including sulphidic mine tailings.

The product is design to permanently neutralise acid and trap trace metals by creating strong ionic bonds

immobilising metals into insoluble non-reactive sediment.

Vegetation species for the trials were selected based on their ability to achieve closure criteria as set out in CSA

Mine’s Rehabilitation Monitoring Methodology and Determination of Completion Criteria for Rehabilitation

Ecosystems report and STSF Rehabilitation and Closure Plan whilst maintaining integrity with surrounding

vegetation. On each plot the following species were trialled:

Native tube stock including Bimble Box (Eucalyptus populnea), Punty Bush (Senna artemisiodes).

Silk Sourgham (Sourgham X. alum Parodi). This vigorous summer annual was selected to act a cover

crop and provide favourable conditions for the establishment of perennial species.

Native Pasture Seed Mix including Corkscrew Grass (Stipa setacea) and Windmill Grass (Chloris

truncarta).

Initial results have been promising with vigorous growth of the Silk Sorghum on the topsoil covered plots.

Limited growth of Silk Sorghum occurred on the Virotec and waste rock plots. Expectantly, mortality of tree

and shrub species has been high in the control plots with none of the planted tube stock establishing. Tree and

shrubs have successfully established in the topsoil plots, whilst there has been limited establishment in the waste

rock and Virotec Plots.

Rehabilitation on the trial plots continued to be monitored (as a part of the Land Function Analysis (LFA) in

2012 to assess the performance of cover treatments against STSF Rehabilitation and Closure Criteria and

completion criteria outlined in the CSA Mine Rehabilitation Monitoring Methodology and Determination of

Completion Criteria for Rehabilitation Ecosystems report. These criteria are used to assess the effectiveness of

the cover treatments.

In August 2012, the Rehabilitation Trial Monitoring Inspection Sheet (FRM-373) was introduced to assist in

ensuring a consistent and documented approach for the program to monitor the rehabilitation trials and

vegetation growth on the Tailings Facility and future rehabilitation trials and research.

Rehabilitation on the trial plots will continue to be monitored in 2013, however, it is expected that these trial

plots will be disturbed by future TSF upgrades in late 2013 or 2014.

Page 109: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

101

5.5.2 Analogue Long Term Monitoring Sites

CSA Mine has two long term analogue monitoring programs conducted on land undisturbed by mining activities

on and surrounding CML5. These two programs continued in 2012 and are based on widely acknowledged and

accepted methods of analogue sampling in the Western NSW Region: Rangeland Assessment Program (RAP)

and Land Function Analysis (LFA).

The aim of long term analogue monitoring is to provide suitable rehabilitation goals and closure criteria to feed

in to the CSA Rehabilitation Monitoring Methodology and Determination of Completion Criteria for

Rehabilitation Ecosystems report. Analogue monitoring fulfils CMPL’s regulatory requirement to provide

achievable and measureable closure criteria based on local environmental conditions.

Land Function Analysis

The services of DnA Environmental consultants were utilised again in 2012 to continue with the annual

rehabilitation monitoring program based on the principles of LFA. The annual rehabilitation monitoring

program is designed to provide quantified data from representative reference sites. The data will be used as a

benchmark when assessing rehabilitation outcomes and will therefore assist in measuring compliance with the

CSA Mine Rehabilitation Monitoring Methodology and Determination of Completion Criteria for Rehabilitation

Ecosystems report. The main objective of the annual rehabilitation monitoring program is to assess the progress

of rehabilitated landforms towards fulfilling long-term land use objectives by comparing a selection of

ecological targets or completion criteria against unmined areas of remnant vegetation (reference sites) that are

representative of the final land use and vegetation assemblage.

CSA Mine aims to create stable rehabilitated landforms that integrate with surrounding landscapes in areas

disturbed by mining. The current planned long term land use is rangeland grazing. Therefore local grazing areas

on lower slopes containing sparse to moderate endemic tree and shrub cover were used as a point of reference for

rehabilitation targets. Three grazed rangeland communities and two ridge reference sites were established as

primary ecological targets.

Three areas of rehabilitation were monitored in 2011 and again in 2012 as a part of the annual rehabilitation

monitoring program. These included:

Little Mount Brown (CSA LMB).

CSA Mill.

Old Subsidence Area (CSA OS).

Results of the 2012 LFA Rehabilitation Monitoring are displayed in Table 31. This Table highlights 14 Key

Performance Indicators (KPI’s) to determine the success of rehabilitation conducted on site and determines if a

rehabilitation site has successfully met the desired KPI targets during 2012 or not. The results of the

rehabilitation monitoring conducted during 2012 determined that all three rehabilitation areas on site currently

do not meet the required completion criteria for rehabilitation. The complete Rehabilitation Monitoring Report

for 2012 is provided in Appendix G and can be referred to for further detail on the rehabilitation monitoring

methodology used and the determination of completion criteria for rehabilitated ecosystems. The report also

notes the changes in land function found between the 2011 monitoring program and the 2012 monitoring

program.

Page 110: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

102

LFA Monitoring of the CSA Mill, CSA OS and CSA LMB Rehabilitation Sites

Page 111: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

103

Table 31 LFA Rehabilitation Monitoring Results 2012

KPI Rehabilitation Site

Comment CSA LMB

CSA OS CSA MILL

Stability and Nutrient Cycling

Active erosion at the rehabilitation sites has led to a decline in nutrient cycling and stability.

Infiltration There is a decline in infiltration across all rehabilitation sites. CSA OS and CSA Mill still meet the target.

Mature Trees No mature trees were recorded at CSA LMB and CSA OS. Mature tree population at CSA Mill was comprised of Eucalyptus populnea, Eremophila mitchelli and Acacia aneura.

Shrubs and Juvenile Trees

No shrubs or juvenile trees were recorded at CSA LMB. CSA OS had shrubs which germinated from the topsoil which was sourced from the TSF extension. CSA MILL had shrubs which regenerated from the surrounding remnant vegetation.

Ground Cover

CSA LMB, CSA OS and CSA Mill all yielded ground cover values which were below the lower limit KPI. CSA OS’s majority of cover attributable to extensive logs piles. Some also provided by dead leaf litter and small occurrences of perennial and annual vegetation and cryptogams.

Native Species Diversity (per m2)

CSA LMB recorded one native shrub and no exotic species. CSA OS had a large number of herbs and a diversity of tree, shrubs, sub-shrubs and grasses similar to the range of the reference sites. The only rehabilitation site to contain exotic species. CSA Mill, despite relatively low diversity overall contained similar proportions of species found in the range of reference sites and no exotic species.

Riling Rehabilitation work has ameliorated the rills at CSA LMB. No rills were present at any of the rehabilitation sites.

Soil pH All sites fell well below target levels. This indicates that the soil remains at a strongly acidic pH and will require lime remediation.

Electrical Conductivity

There was a reduction in electrical conductivity at CSA LMB and CSA Mill. Although all sites remain significantly above the target.

Organic Matter and Phosphorous

All sites had low levels; however this was also reflected in the reference sites.

Nitrates All sites experienced a reduction in nitrate levels. CSA Mill and CSA OS nitrate levels remain higher than the desirable range. CSA LMB nitrate levels are below the desirable range.

Cation Exchange Capacity (CEC)

All sites had very high levels exceeding the desirable range. These results may indicate they are likely to have good retention ability and potentially high soil fertility however due to excessive EC (and nitrates) these are more likely to be related to earlier mining related activities rather than natural hydrological and agricultural influences.

ESP CSA LMB and CSA OS fell well below the desirable levels. Results indicate soils at CSA MILL are likely to be non-sodic.

Metals

All sites had excessively high levels of Sulphur, Zinc, Manganese and Lead. CSA LMB and CSA MILL had excessively high levels of Cu, Silicon, Selenium, Lead and Arsenic. All sites had unusually high levels of Ca, Mg and K likely to be reflected in the high EC and CEC levels recorded at the site. While some elements slightly elevated in the reference sites (e.g. Iron, Silicon, Lead and Arsenic) those recorded within the rehabilitation areas far exceeded these and are likely to provide further implications for plant

establishment and growth.

Notes:

Indicates characteristic meet key performance indicator targets Indicates characteristic did not meet key performance indicator targets

Page 112: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

104

5.6 Further Development of the Final Rehabilitation Plan

In 2011 CSA Mine engaged consultants AECOM to develop a Rehabilitation and Environmental Management

Plan (REMP) to address commitments made in the 2010 AEMR and support the renewal of the CSA MOP

which was due for renewal at the end of 2012. The purpose of the REMP was to create a framework for mine

closure which has measurable performance and closure criteria to achieve sustainable ecosystem development.

The REMP was finalised in early 2012.

The performance measures and indicators in the REMP are designed to form the basis of the CSA Mine Closure

Criteria. They provide the ability to track progress towards final land use and development of sustainable

ecosystems through a series of conceptual stages shown in Figure 21 and described as:

Stage 1 Decommissioning: Removal, where relevant, of hard stand areas, buildings, contaminated

materials, hazardous materials.

Stage 2 Landform Establishment: Incorporates gradient, slope, aspect, drainage, substrate material

characterisation and morphology.

Stage 3 Growing Media Development: Incorporates physical, chemical and biological components of

the growing media and ameliorants that are used to optimise the potential of the media in terms of the

preferred vegetative cover.

Stage 4 Ecosystem and Land use Establishment: Incorporates operational and non-operational lands,

revegetated lands and habitat augmentation; management and establishment of flora, retained

infrastructure and adjoining predicted land use.

Stage 5 Ecosystem and Land use Sustainability: Incorporates components of floristic structure, nutrient

cycling recruitment and recovery, community structure and function which are the key elements of a

sustainable landscape, together with economic and social impact or benefit.

Page 113: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

105

Figure 21 Conceptual Stages of Sustainable Ecosystem Development

To evaluate the progress of rehabilitation fulfilling long term land use objectives and closure criteria, CSA Mine

implemented an annual rehabilitation monitoring program as described in Section 5.5.2. Rehabilitation

procedures and completion criteria are updated when required to continually improve rehabilitation standards, as

more data on reference sites or the targeted vegetation community becomes available.

Table 32 and Table 33 summarise rehabilitation which occurred in 2012, rehabilitation proposed for 2013 and an

update on the maintenance activities of rehabilitated land.

Page 114: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

106

Table 32 Summary of Proposed Rehabilitation

Area Affected/Rehabilitated (hectares) 2011 2012

2013

(estimated)

A: MINE LEASE AREA

A1 Mine lease area 2474.1 ha 2474.1 ha 2474.1 ha

B: DISTRTURBED AREA

B1 Infrastructure Area (other disturbed areas to be rehabilitated at closure including facilities, roads)

18.56 ha 18.56 ha 18.56 ha

B2 Active Mining Area (excluding items B3-B5 below)

10.02 ha 10.02 ha 10.02 ha

B3 Waste Emplacements (active/unshaped/in or out of pit)

15 ha 15 ha 15 ha

B4 Tailings Emplacement (active/unshaped/uncapped)

87 ha 87 ha 87 ha

B5 Shaped Waste Emplacement (awaits for maintenance)

0 ha 0 ha 0 ha

TOTAL ALL DISTURBED AREAS 130.58 ha 130.58 ha 130.58 ha

C: REHABILITATION

C1 Total Rehabilitated Area (except for maintenance)

4.5 ha 0 ha 1.6 ha

D: REHABILITATION

D1 10 to 18 degrees 2.2 ha 0 ha 0 ha

D2 Greater than 18 degrees 0 ha 0 ha 0 ha

E SURFACE OF REHABILITATED LAND

E1 Pasture and grasses 4.5 ha 0 ha 1.6 ha

E2 Native forest/ecosystems 0 ha 0 ha 0 ha

E3 Plantations and crops 0 ha 0 ha 0 ha

E4 Other (include non-vegetative outcomes) 0 ha 0 ha 0 ha

Note:

1. These figures do not include excised areas as they are not the responsibility of CMPL

Table 32 shows nil further disturbance areas were created during 2012 and no further plans to disturb areas in

2013. No rehabilitation took place during the reporting period (as detailed in section 5.3); however, 1.6 ha is

planned for 2013 (mill rehabilitation area).

Page 115: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

107

Table 33 Maintenance Activities on Rehabilitated Land 2012

Nature of Treatment Area Treated (ha) Comment/control

strategies/treatment detail

2012 2013

Additional erosion control works

0.2 0 Drainage re-established around rehabilitation works for Old Subsidence Area. (drainage and water

diversion)

Re-covering

0.5 0 3,051 tonnes of waste rock was surface stockpiled

during 2012. (Topsoil and waste rock stockpiling on surface)

Soil treatment 0 0 Nil soil treatment activities occurred during 2012.

Treatment/Management (grazing, cropping, slashing etc)

0 0 Nil land management / treatment activities occurred during 2012.

Re-seeding/Replanting 0 0 Nil re-seeding or replanting activities occurred during 2012.

Adversely Affected by Weeds

0 0 Nil.

Feral animal control

2474 2474

Feral Goat removal continued in 2012 over the CML5 mining lease, in addition to a perimeter fence upgrade. (via additional fencing, trapping,

baiting, etc)

Page 116: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

108

6 ACTIVITIES PROPOSED FOR 2013

Key activities CMPL intends to progress in 2013 are listed in Table 34.

Table 34 Proposed activities for 2013

Proposed Activity Priority Ranking Scheduled

Completion Date

Finalise draft SWMP and submit to DRE and OEH H Q2 2013

Investigate underground waste management to improve the separation

of general waste and recycling in the underground mining operation. H Q1 2013

Complete the replacement of tailings thickener. H Q1/Q2 2013

Complete feasibility study on the use of paste fill in underground

operations and submit MOP amendment if required. H Q4 2013

Successfully address all actions from the 2012 CSA Mine Independent

External Environmental Compliance Audit. H Q2 2013

Successfully address all audit actions from the 2012 the CSA Mine site

Dangerous Goods Audit Report. M Q1 2013

Completion of a TSF Surveillance Inspection by qualified Dam

Engineers. M Q1 2013

Investigate water efficiency improvements, including the completion of

a four week trial of a dewatering plant. M Q2 2013

Complete a full site contamination study including an investigation of

the remaining 4 areas on site suspected of contamination. M Q2 2013

Complete the removal of the Old EDMS batch plant, including the

removal of the storage shelter, concrete bunds, and concrete pad. M Q2 2013

Consult with OEH to finalise commitments under ESAP including the

submission of a final report. M Q2 2013

Address key actions identified in the energy assessment gap analysis to

further develop sustainable energy and carbon management practices. M Q3 2013

Continue removing the remaining pile of crushed Big Mount Brown

contaminated waste material. M Q4 2013

Installation of a new mono pump station up at the 8700 Level (current

deepest level in mine) to create an efficient pumping system at the

bottom of the mine.

M Q4 2013

Conduct educational campaigns and other initiatives to achieve a

recycling rate consistently greater than 30%. M Q4 2013

Page 117: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

109

7 REFERENCES

Australian and New Zealand Environment and Conservation Council (ANZECC) and

Agriculture and Resource Management Council of Australia and New Zealand (2002)

Australian and New Zealand Guidelines for Fresh and Marine Water Quality, National Water

Quality Management Strategy.

Benson J. S. (2006) New South Wales Vegetation Classification and Assessment: the

classification, database assessment of protected areas and threat status of plant communities.

Cunninghamia 9, 331-82.

Bureau of Meteorology (2011) Website www.BOM.gov.au. Data accessed 15/01/2013.

Cobar Management Pty Ltd (CMPL) (2007) Mining Operations Plan 2008-2012, December

2007.

Cobar Management Pty Ltd (CMPL) (2012) Mining Operations Plan 2013-2017, December

2012.

Doos, Stephanie (Oct 2011) A Geophysical and Hydrogeological Approach to Delineating

the Great Chesney Fault, Cobar, NSW. The Australian National University.

DRE (formally DTIRIS) (2006) Guidelines to the Mining, Rehabilitation and Environmental

Management Process. EDG03 version 3

DnA Environmental (2011) Rehabilitation Monitoring Methodology and Determination of

Completion Criteria for Rehabilitation Ecosystems report.

DnA Environmental (2012) Rehabilitation Monitoring Report, December 2012.

EnviroKey (2012) Biodiversity Assessment CML5, CSA Mine, Cobar NS, October 2012.

Golder Associates (2012) South Tailings Storage Facility-Surveillance Report Year 2011,

March 2012.

National Environment Protection Council (1999) National Environmental Protection

Measure for Site Investigations (NEPM) guidelines.

Page 118: Cobar Management Pty Ltd · The mine continued to operate until 1997, when the operation ran into financial difficulties and was placed in receivership. The mine was placed on care

CMPL 2012 AEMR

110

8 PLANS

1 Mine Context

2 Land Preparation and Mining Activities

3 Rehabilitation

4 Mining Plan - Vertical Section

5 Site Layout

9 APPENDICES

A Environmental Protection License 1864

B 2011 AEMR Review Meeting Minutes

C CMPL Environment and Community Policy

D CSA Air and Water Quality Monitoring Data 2012

E STSF Surveillance Report 2011

F 2012 Annual Return EPL 1864

G 2012 CSA Rehabilitation Monitoring Report

H 2012 Biodiversity Assessment

I 2012 Pollution Incident response Management Plan