Brattle Testimony AWC 400 403

download Brattle Testimony AWC 400 403

of 135

Transcript of Brattle Testimony AWC 400 403

  • 7/31/2019 Brattle Testimony AWC 400 403

    1/135

    UNITED STATES OF AMERICABEFORE THE

    FEDERAL ENERGY REGULATORY COMMISSION

    Atlantic Grid Operations A LLC

    Atlantic Grid Operations B LLC

    Atlantic Grid Operations C LLC

    Atlantic Grid Operations D LLC

    Atlantic Grid Operations E LLC

    Docket Nos. EL11-____-000ER11-____-000

    DIRECT TESTIMONY OF

    JOHANNES P. PFEIFENBERGER AND

    SAMUEL A. NEWELL

    ON BEHALF OF

    THE AWC COMPANIES

  • 7/31/2019 Brattle Testimony AWC 400 403

    2/135

    TABLE OF CONTENTS(Exhibit AWC-400)

    I. INTRODUCTION ................................................................................

    II. PURPOSE AND SUMMARY OF TESTIMONY..............................

    III. BACKGROUND: STATE RPS REQUIREMENTS AND ECONOBENEFITS OF OFFSHORE RENEWABLE POWER DEVELOP

    1. State Renewable Energy Policy Requirements ......................

    2. Production Cost, Energy Price, and Emissions Benefits ......

    3. Employment and Economic Stimulus Benefits .....................

    IV. AWC PROJECT CONFIGURATION AND COSTS .......................

    V. PUBLIC POLICY BENEFITS ASSOCIATED WITH THE AWC

    VI. RELIABILITY AND OPERATIONAL BENEFITS ........................

    VII. CONGESTION RELIEF AND OTHER ECONOMIC BENEFITSAWC PROJECT RELATIVE TO A RADIAL ALTERNATIVE ...

    1. Congestion Relief and Related Benefits .................................

    2. Capacity Value ........................................................................

    3. Reduced System Operating Costs ...........................................

    4. Emission Reduction Benefits..................................................

    Qualifications of Johannes Pfeifenberger (Exhibit AWC

    Qualifications of Samuel Newell (Exhibit AWC

  • 7/31/2019 Brattle Testimony AWC 400 403

    3/135

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

    UNITED STATES OF AMERICABEFORE THE

    FEDERAL ENERGY REGULATORY COMMISSION

    Atlantic Grid Operations A LLC

    Atlantic Grid Operations B LLC

    Atlantic Grid Operations C LLC

    Atlantic Grid Operations D LLC

    Atlantic Grid Operations E LLC

    Docket Nos. EL11-____-000ER11-____-00

    DIRECT TESTIMONY OFJOHANNES P. PFEIFENBERGER and SAMUEL A. NEWELL

    I. INTRODUCTIONQ. PLEASE STATE YOUR NAMES, EMPLOYER, TITLE, AND BU1

    ADDRESS.2

    A. My name is Johannes P. Pfeifenberger and my name is Dr. Samuel A3

    We are both Principals ofThe Brattle Group, an economic consulting 4

    offices in Cambridge, Massachusetts; Washington, D.C.; San Francisco5

    Brussels; and Madrid. Our business address is 44 Brattle Street, C6

    Massachusetts 02138.7

    Q. ON WHOSE BEHALF ARE YOU TESTIFYING?8

  • 7/31/2019 Brattle Testimony AWC 400 403

    4/135

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

    A. I am an economist with a background in power engineering and over 21

    work experience in the areas of regulated industries, energy policy, and 2

    received a M.A. in Economics and Finance from Brandeis University a3

    in Electrical Engineering with a specialization in Power Engineering an4

    Economics from the University of Technology, Vienna, Austria. I 5

    Brattle Groups utilities practice area and am the author and co-6

    numerous articles, reports, and presentations on subject areas relat7

    economic benefits of transmission investment, planning, market design8

    allocation.9

    I have filed testimony before the Federal Energy Regulatory Co10

    (the Commission or FERC) and numerous state regulatory commis11

    range of subject areas, including the economic benefits of tra12

    investments. For example, I filed testimony with the Public Service Co13

    of Wisconsin on behalf of American Transmission Company LLC 14

    Management Inc. in Docket No. 137-CE-149 discussing the economic b15

    the Paddock-Rockdale Transmission Project, which was the first e16

    transmission project evaluated by the Wisconsin commission. On 17

    Southern California Edison Company, I testified before the Arizona Po18

    and Transmission Line Siting Committee in Docket No. L-00000A19

  • 7/31/2019 Brattle Testimony AWC 400 403

    5/135

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

    analysis of the economic stimulus benefits associated with the const1

    proposed SPP transmission and wind generation, which SPP filed 2

    Docket No. ER10-1069 in support of the proposed Highway/Byway tra3

    cost allocation methodology. I also filed with the Commission (co-auth4

    colleagues on behalf of ourselves) comments in Docket Nos. AD5

    RM10-23 on regional transmission planning and cost allocation, and 6

    testimonies on transmission tariff design, the costs and benefits of a7

    transmission access charge methodologies, and regional transmission org8

    (RTO) scope and configuration issues on behalf of variou9

    Exhibit AWC-401 to our testimony contains a more complete descript10

    qualifications and expert witness experience.11

    Q. DR. NEWELL, PLEASE DESCRIBE YOUR BACKG12

    EDUCATION, AND PROFESSIONAL EXPERIENCE AS IT R13

    TO THIS DIRECT TESTIMONY.14

    A. I am an economist and engineer with 12 years of work experience in the15

    and analysis of electricity markets and their relationship to the tra16

    system. I received a Ph.D. in technology management and policy 17

    Massachusetts Institute of Technology, a M.S. in materials sci18

    engineering from Stanford University, and a B.A. in chemistry and phy19

  • 7/31/2019 Brattle Testimony AWC 400 403

    6/135

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

    author or co-author of numerous articles, reports, and presentations o1

    range of subject areas related to wholesale electricity markets and transm2

    I have submitted testimony with FERC in RTO-related cases and3

    expert reports for PJM, other RTOs, and transmission clients that have 4

    with both state regulatory commissions and the FERC. For example, I w5

    the co-authors of a report filed by American Transmission Company 6

    the Public Service Commission of Wisconsin in Docket No. 137

    discussing the economic benefits of the Paddock-Rockdale Transmissio8

    My role was to advise staff at American Transmission Company LLC 9

    of PROMOD IV simulations, to compute customer benefits, and to10

    several categories of benefits outside the scope of the model. Recen11

    testified on behalf of Connecticut Light & Power and The United Illu12

    Company in their Integrated Resource Planning proceeding be13

    Connecticut Department of Public Utility Control. My role, as the lea14

    Brattle team in that assignment, was to analyze customer impacts a15

    implications of various resource strategies regarding renewables develop16

    energy efficiency. Exhibit AWC-402 to our testimony contains a more17

    description of my qualifications and expert witness experience.18

    19

  • 7/31/2019 Brattle Testimony AWC 400 403

    7/135

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

    II. PURPOSE AND SUMMARY OF TESTIMONY1Q. WHAT IS THE PURPOSE OF YOUR TESTIMONY?2

    A. The purpose of our testimony is to describe and quantify some of t3

    policy, reliability, congestion relief, and other economic benefits assoc4

    the Atlantic Wind Connection Project (AWC Project or Project).5

    Q. WHAT IS THE AWC PROJECT?6

    A. The AWC Project is a double-circuit, high-voltage direct current (7

    offshore transmission backbone with twelve offshore AC-DC converte8

    capable of integrating at least 6,000 MW of offshore wind gene9

    geographic locations ranging from northern New Jersey to southern Virg10

    Project will also have onshore DC-AC converter stations at seven lo11

    New Jersey, Maryland, Delaware, and Virginia, where renewable pow12

    injected into the existing transmission grid in controlled proportions. Th13

    which will be built in five phases, can also be used to transmit up to 2,0014

    energy and capacity between interconnection points along the coast, pro15

    offshore reinforcement to the existing onshore grid in the congested Mi16

    power market.17

    Q. WHAT ARE THE AWC PROJECTS MAIN BENEFITS?18

    A. The AWC Project provides a platform on which offshore wind devel19

  • 7/31/2019 Brattle Testimony AWC 400 403

    8/135

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

    Offshore wind generation facilitated by the AWC Project will lo1

    emissions by reducing coal, gas, and oil usage, and it will reduce ener2

    across the PJM footprint. The Project will also enhance reliability a3

    congestion in what the Department of Energy (DOE) has designated 4

    the most congested National Interest Electric Transmission C5

    Importantly, this is true of the AWC Project whether viewed without w6

    out, full wind build-out, or simply in comparison to a scenario in which7

    wind is interconnected by radial transmission lines.8

    The Mid-Atlantic region offers the most abundant and most 9

    offshore wind resources in the country. The AWC Project can help10

    Atlantic and other PJM states take advantage of this resource to achieve 11

    requirements. In doing so, the Project offers significant economi12

    compared to individual radial interconnections for each offshore wind 13

    reducing siting, permitting, and interconnection barriers to wind develop14

    Project will expedite the installation of offshore wind on a scale that v15

    spurs the development of local industry to provide equipment and servic16

    will substantially lower the cost of offshore wind development.17

    Of particular importance, the AWC Projects HVDC back18

    AC-DC converters are controllable which, unlike the typical radial tra19

  • 7/31/2019 Brattle Testimony AWC 400 403

    9/135

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

    more effective solution for developing Mid-Atlantic offshore wind reso1

    provides significantly higher economic, reliability, congestion relief, 2

    and environmental benefits to the PJM grid and to the region. Our 3

    explains these public policy, reliability, congestion relief, and other 4

    benefits in detail.5

    Q. PLEASE SUMMARIZE THE EXTENT TO WHICH THE AWC P6

    WILL ENABLE STATES TO MEET THEIR RPS.7

    A. The AWC Project helps meet states RPS policies, which require loa8

    entities to buy increasing amounts of energy from renewable resources,9

    offshore wind. PJM projects that meeting these state RPS requireme10

    footprint would require up to 25,000 MW of wind by 2015 and 50,0011

    2025. Of the states directly interconnected by the AWC Project, N12

    requires 22.5% renewables by 2020, Delaware 25% by 2025, Marylan13

    2022, and Virginia has a goal of 15% by 2025.14

    Offshore wind power has received an increasing amount of pub15

    attention as a key resource for the eastern U.S. because it is abundant an16

    close to load centers. In contrast, other local renewable resources are s17

    remote resources (such as onshore wind in the Midwest) would requ18

    transmission investments without much local economic development 19

  • 7/31/2019 Brattle Testimony AWC 400 403

    10/135

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

    Delaware, Maryland and Virginia, and providing nearly 65% of the re1

    by 2025before considering the potential demand for offshore wind f2

    states. Moreover, since wind conditions rarely allow entire wind 3

    simultaneously generate at their maximum rated capacity, it is more cost4

    to install wind capacity in excess of the transmission capacity to max5

    value of the overall investment. In our analysis of benefits, we have ass6

    6,600 MW of nameplate wind generation would be interconnected to 7

    Project, which will result in 10% additional wind energy generated 8

    0.2% in curtailments.9

    Q. PLEASE SUMMARIZE SOME OF THE COSTS AND BE10

    ASSOCIATED WITH THE SCALE OF OFFSHORE 11

    DEVELOPMENT SUPPORTED BY THE AWC PROJECT.12

    A. Developing this amount of offshore wind generation will require a13

    investment of approximately $30 billion. This investment has to be con14

    the context of associated benefits. As shown in Table 1, integrati15

    6,600 MW of offshore wind generation facilitated by the AWC Pr16

    reduce customer locational marginal prices (LMPs) by appr17

    $1.6 billion per year (net of offsetting impacts on capacity market pri18

    analysis shows that this benefit is widespread: load-weighted annua19

  • 7/31/2019 Brattle Testimony AWC 400 403

    11/135

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

    In addition, the development of offshore wind will create 1

    economic stimulus for the local economy, as shown in Table 2. Ther2

    other benefits and costs, including the capacity value of wind, wind in3

    costs, and the AWC Project-specific benefits discussed in Sections IV th4

    of our testimony.5

    Table 16Electricity Market and Emissions Benefits of Integrating 6,600 M7

    Offshore Wind Generation in New Jersey, Delaware, Maryland, and8(relative to a Base Case without offshore wind)9

    Type of Benefit Annual Value

    (in 2016 $s)

    20-yea

    (in 20

    Emission reductions 16 million tons CO225,000 tons SO211,000 tons NOx

    Value of CO2 emission reductions(assuming $30/ton CO2)

    $500 million $5.2 b

    Reduction in fossil fuel productioncosts in Eastern Interconnection

    Customer value of LMP reductions inPJM (net of $480 million/yearoffsetting impact on capacity prices)

    $1.1 billion

    $1.6 billion

    $12 b

    $17 b

    Table 210Economic Stimulus Benefit of 6,600 MW of Offshore Wind Gen11

    and Related Offshore Transmission12(relative to a Base Case without offshore wind)13

    Economic ActivityJobs Earnings

    Ec

  • 7/31/2019 Brattle Testimony AWC 400 403

    12/135

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

    Q. PLEASE EXPLAIN THE DIFFERENCE BETWEEN LOW IN-R1

    AND HIGH IN-REGION MANUFACTURING IN TABLE 22

    A. As Table 2 shows, the overall magnitude of the economic stimulus b3

    offshore wind investments to the local economies is significant. How4

    magnitude of this economic benefit also strongly depends on the extent5

    wind turbines and other plant and equipment are manufactured within6

    Atlantic region (rather than being imported) and the extent to which co7

    services and logistical support are provided by companies and employe8

    the region. Achieving a high in-region provision of these equipment an9

    will require a scale of offshore wind power development that jus10

    investment in manufacturing and logistical facilities.11

    Q. DOES YOUR TESTIMONY EVALUATE THE ECONOMICS 12

    REQUIREMENTS AND OFFSHORE WIND GENERATION RE13

    TO OTHER POLICY OPTIONS?14

    A. No. While we recognize the above benefits and costs of offsh15

    generation, the focus of our testimony is to identify the public policy, r16

    congestion relief, and other economic benefits of the AWC Project itse17

    so primarily by comparing the Project to more conventional ways to int18

    offshore wind through radial transmission lines. The rest of this summ19

  • 7/31/2019 Brattle Testimony AWC 400 403

    13/135

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

    A. The AWC Project is able to reliably deliver 6,000 MW of offshore wi1

    and additionally provide a fully controllable 2,000 MW HVDC transmi2

    between southern Virginia and northern New Jersey at a total constructi3

    approximately $5 billion. In comparison, we estimate that delivering 64

    of wind power with radial transmission lines from individual wind plant5

    would incur construction costs of $3.4 billion to $5.3 billion without of6

    substantial additional public policy, reliability, congestion relief, a7

    economic benefits we have identified and partially quantified for t8

    Project. We estimate that interconnecting offshore wind with the AW9

    provides $9-15 billion of benefits over a radial approach (including th10

    costs of radial transmission lines), in addition to reliability and operatin11

    we have not quantified.12

    Q. PLEASE SUMMARIZE HOW THE AWC PROJECT WOULD S13

    STATE POLICY OBJECTIVES.14

    A. The AWC Project will support meeting the states renewable energy15

    reducing permitting and planning barriers and achieving significant eco16

    scale for offshore wind development. The Project creates a one-stop p17

    landing-point selection, state environmental siting, and PJM tra18

    planning. Compared to a plant-by-plant permitting and transmission19

  • 7/31/2019 Brattle Testimony AWC 400 403

    14/135

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

    locations independently of these landing points and with a greatly 1

    permitting process.2

    Q. HAVE YOU QUANTIFIED THE VALUE OF SOME OF THESE 3

    POLICY BENEFITS THAT THE AWC PROJECT WOULD PROV4

    A. Yes. Increased scale and predictability of offshore wind development 5

    by the AWC Project offers the prospect of significant cost savings f6

    every aspect of offshore wind development. It will facilitate investmen7

    manufacturing of wind turbines and related components and the develo8

    more cost-effective construction and logistical infrastructure. We est9

    streamlined permitting and increased scale that allows local manufact10

    sourcing will reduce total offshore costs by approximately 20 percent. 11

    $30 billion of offshore wind generation investment supported by t12

    Project, this results in total cost reductions of approximately $6.0 b13

    addition, promoting in-region manufacturing and sourcing results in sig14

    greater employment and economic development benefits, as indicate15

    difference between low and high in-region manufacturing benefits in16

    Q. PLEASE SUMMARIZE HOW THE AWC PROJECT PR17

    RELIABILITY AND OPERATIONAL BENEFITS.18

    A. The AWC Project will provide significant reliability and operational19

  • 7/31/2019 Brattle Testimony AWC 400 403

    15/135

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

    2,000 MW transfer capability between landing points in Virginia, M1

    Delaware, and New Jersey reinforces the onshore grid in the constrai2

    Atlantic region, reducing the need for future onshore reinforcements; a3

    Projects controllable HVDC technology provides PJM with additional 4

    to address reliability challenges whenever they arise.5

    The capabilities of the Projects advanced HVDC technology als6

    operating benefits that enhance reliability and reduce the cost o7

    operations. These include: (a) the ability to redirect power flows instan8

    to address system contingencies; (b) improved system stability; (c9

    support and improved reactive performance; and (d) blackstart capabi10

    Project further provides for more reliable delivery of offshore wind po11

    individual radial connections by being able to redirect power away fro12

    points with temporary reliability-related transmission constraints.13

    We have not quantified the economic value of these reliab14

    operational benefits, nor have we quantified the value of the Project15

    reliability benefits. However, if the AWC Project avoids the need for16

    major onshore transmission project, the savings would likely exceed $1 b17

    Q. HOW DOES THE AWC PROJECT PROVIDE CONGESTION RE18

    A. The Projects offshore backbone and controllability allows energy from19

  • 7/31/2019 Brattle Testimony AWC 400 403

    16/135

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

    We analyzed the economic value of this benefit using Ventyxs P1

    simulation model. Working with Ventyx staff, we simulated market 2

    for 2016 with the addition of 6,600 MW of nameplate offshore wind g3

    added in two ways: one case with the AWC Project and an alternative 4

    radial interconnections. These simulations showed that the AW5

    significantly reduces congestion. Instead of simply injecting wind po6

    closest onshore location, the AWC Project transfers power to the best7

    along the backbone, where the LMP is the highest. It also transfers po8

    low-priced onshore interconnection points to higher-priced locations. T9

    benefits reduce system-wide congestion costs by $196 million annually 10

    to radial interconnections of individual wind plants. Most of the relief 11

    constraints near the wind power injection points and also on constra12

    western Pennsylvania into eastern PJM. Compared to the radial interc13

    of individual wind plants, the congestion relief provided by the AW14

    helps to reduce system-wide production costs by $33 million per y15

    approximately $350 million over the initial 20 years of the Project.16

    Q. WHAT IMPACT WOULD THE AWC PROJECT HAVE ON LM17

    CUSTOMER PAYMENTS RELATIVE TO A RADIAL ALTERNA18

    A. The LMP benefits from the AWC Project with full wind build-out (com19

  • 7/31/2019 Brattle Testimony AWC 400 403

    17/135

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

    impacts would save PJM customers approximately $126 million per1

    $1.35 billion over 20 years. However, the lower LMPs will increase2

    prices, which offsets $110 million annually ($1.2 billion over 20 years3

    LMP reductions.4

    Q. ARE THERE ANY SIGNIFICANT FACTORS THAT AR5

    INCLUDED IN THE ABOVE ESTIMATES OF CONGESTION-RE6

    BENEFITS?7

    A. Yes. The above estimates significantly understate the value that the AW8

    will provide under real-time system operations. This is because a n9

    operational factors that cause price volatility in the real-time marke10

    captured in PROMOD simulations, including wind generation uncert11

    forecasting errors, load forecasting errors, sudden outages of generat12

    transmission outages, unexpected loop flows from neighboring regions, a13

    rate limitations on generators.14

    Analysis of historical hourly day-ahead and real-time LMP di15

    among the AWC Projects interconnection points shows that the ability 16

    power flows in real time is worth approximately twice as much as in17

    ahead market. Since PROMOD simulations are more comparable to18

    ahead market than the real-time market, we estimate that the Projects19

  • 7/31/2019 Brattle Testimony AWC 400 403

    18/135

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

    A. We simulated the effects of the AWC Project without any offsh1

    generation. Compared to a 2016 Base Case that includes only2

    transmission and generation additions, adding the AWC Project reduce3

    congestion by transmitting power from less congested, lower-priced lo4

    more congested, higher-priced locations. The results of this analysis 5

    congestion costs would decrease by $147 million and production 6

    $51 million per year.7

    Q. WHAT OTHER CONGESTION-RELATED ECONOMIC BE8

    DOES THE AWC PROJECT PROVIDE?9

    A. In addition to transmitting the capacity value of 6,000 MW of offshor10

    which PJM is likely to count as less than 2,000 MW for resource 11

    purposesthe AWC Project will be able to transmit 2,000 MW of capa12

    unconstrained southern Virginia northward into the constrained EMAA13

    of PJM. The Project also allows transmission of capacity betw14

    constrained subareas within EMAAC if capacity prices were to differ ac15

    subareas again in the future.16

    We have not forecasted future capacity market conditions and t17

    impact of the Project on such future prices. However, using a scenari18

    PJM recently conducted to assess the impact of added transfer cap19

  • 7/31/2019 Brattle Testimony AWC 400 403

    19/135

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

    without considering the capacity price benefits to all retail customers, th1

    transmitting up to 2,000 MW of capacity from southern Virginia to EM2

    five years would be worth $180 million.3

    Q. WHAT EFFECTS DOES THE AWC PROJECT HAVE ON EMISS4

    A. By facilitating the development of offshore wind more quickly and 5

    scale than if individual wind developers had to plan, permit, and build 6

    interconnections, the AWC Project will give rise to major emissions r7

    As shown in Table 1, the 6,600 MW of offshore wind interconnected by 8

    Project would eliminate 16 million tons of CO2 emissions from fossil9

    generation per year. That is equivalent to taking 3 million cars off the ro10

    Q. PLEASE SUMMARIZE YOUR MAIN CONCLUSIONS ABOU11

    AWC PROJECTS BENEFITS.12

    A. Table 3 summarizes the benefits discussed and quantified in our testim13

    Table 3 shows, the approximately $5 billion construction cost of the AW14

    is more than offset by a number of economic benefits that the Project off15

    plant-by-plant development of offshore wind generation and the interc16

    of individual wind power plants through radial HVAC transmission li17

    onshore grid. Interconnecting offshore wind with the AWC Project18

    $9-15 billion of benefits over a radial approach (including the avoided19

  • 7/31/2019 Brattle Testimony AWC 400 403

    20/135

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

    Table 31Types and Approximate Magnitude of AWC Project-Related2Economic Benefits Over Individual Radial Interconnections3

    of 6,600 MW Offshore Wind Generation4

    Type of AWC Project BenefitEstimat

    Economic

    Avoided cost of radial HVAC transmission links to shore Economic value of ability to access better wind locations

    $3.4-5.3 bnot quant

    Scale-related benefits (streamlined planning and permitting): Reduced cost from higher in-region turbine manufacturing Scale-related savings for other equipment and installation Reduced planning, permitting, and siting costs/uncertainties Shoreline siting-related environmental benefits

    $3.2 bil$1.2-3.0 b

    $0.6 bilnot quant

    Reliability benefits: Avoided cost of on-shore reliability upgrades

    Reinforced existing grid through offshore backbone HVDC operational benefits (voltage support,improved reactive performance, stability, and control ofAC power flows, blackstart capability)

    not quant

    not quant

    not quant

    Congestion relief benefits: NPV of reduced production costs measured in PROMOD NPV of additional production cost savings in real-time

    or, alternatively:

    NPV of additional reduction in PJM Load LMP NPV of capacity price offset to LMP decreases

    Related (locational) capacity market benefit: Capacity value of 2,000 MW EMAAC import capability:

    NPV of resource cost savings*or, alternatively:NPV of reduced customer payments due to price impact*

    * these are order-of-magnitude estimates that are not

    included in the low end of total benefits below

    $350 mil$310 mil

    $1.35 bil-$1.2 bil

    $180 mil$2.7 bil

    Approximate overall magnitude of AWC Projectbenefits over radial interconnection of individualwind plants (compared to approximately$5 billion in AWC Project cost)

    > $9-15 b

  • 7/31/2019 Brattle Testimony AWC 400 403

    21/135

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

    Q. HOW HAVE YOU ORGANIZED THE REMAINDER OF1

    TESTIMONY?2

    A. The remainder of our testimony is organized as follows:3

    Section III provides an overview of state renewable energy po4associated renewable energy requirements, and the economic i5

    offshore wind generation facilitated by the AWC Project.6

    Section IV analyzes the AWC Project configuration and costs comp7the radial interconnection of individual wind farms.8

    Section V evaluates the public policy and scale-related benefi9AWC Project.10

    Section VI discusses and provides preliminary estimates of the relia11operational benefits associated with the AWC Project.12

    And, finally, Section VII discusses the congestion relief and related 13benefits associated with the AWC Project.14

    III. BACKGROUND: STATE RPS REQUIREMENTS AND15ECONOMIC BENEFITS OF OFFSHORE RENEWABLE16

    POWER DEVELOPMENT17

    1. State Renewable Energy Policy Requirements18Q WHAT ARE THE RENEWABLE ENERGY REQUIREMEN19

  • 7/31/2019 Brattle Testimony AWC 400 403

    22/135

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

    West Virginia and the District of Columbiahave renewable portfolio1

    or goals ranging from 15% to 25% by 2025. PJM projects that meeting 2

    RPS requirements in its footprint would require up to 25,000 MW of3

    2015 and 50,000 MW by 2025.14

    Q. WHAT ARE THE RENEWABLE ENERGY REQUIREMENTS 5

    FOUR COASTAL MID-ATLANTIC STATES WITH AWC L6

    POINTS?7

    A. All four coastal Mid-Atlantic states with AWC landing points hav8

    legislation or regulations establishing renewable energy requirements9

    ranging from 15 to 25 percent of total supply over the next 10 to 15 year10

    New Jerseys RPS requires investor-owned utilities and retail su11procure 22.5% of their electricity sales from qualifying r12

    resources by 2020. Qualifying resources include wind, solar, sm13

    resource recovery facilities, biomass, fuel cells, geothermal, lan14

    and tidal energy. In-state solar generation must provide appr15

    2% of the total energy supply, and approved small hydro and16

    recovery facilities must provide at least 2.5% of the total energ17

    Legislation enacted in August 2010 also requires offshore wind t18

    t f th bl l lth h th d t il f thi li9

  • 7/31/2019 Brattle Testimony AWC 400 403

    23/135

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

    under development. That legislation aims to support the develo1

    at least 1,100 MW of offshore wind.2

    Delawares RPS requires all utility and retail suppliers to procu3their electricity sales from qualifying renewable resources by 24

    at least 3.5% from solar generation. Solar PV and fuel cell resou5

    before December 31, 2014 receive 300% credit (i.e., each MWh 6

    counts for three MWh). Onshore wind resources sited before 7

    31, 2012 receive 150% credit, and offshore wind resources sit8

    December 31, 2017 receive 350% credit toward meeting the st9

    requirements.10

    Marylands RPS requires all utility and retail suppliers to procu11their electricity sales from qualifying renewable resources by 212

    at least 2% from solar generation. On November 2010, the 13

    Ocean Energy Management, Regulation and Enforcement (BO14

    accepted the planning recommendations of the Maryland Offsh15

    Task Force and issued a Request for Interest (RFI) and also a m16

    offshore wind leasing area in federal waters adjacent to M17

    Atlantic Coast (which made Maryland only the second state in 18

    after Delaware to reach this point in the planning process).19

  • 7/31/2019 Brattle Testimony AWC 400 403

    24/135

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

    year (2007) electricity sales that are supplied by non-nuclear ge1

    According to the legislation, the utilities participating in the RPS2

    are allowed to recover all incremental costs and also given inc3

    the form of increased rate of return. In addition, utilities rece4

    credit for the energy derived from onshore wind, and 300% cred5

    energy derived from offshore wind. A study by the Virgini6

    Energy Research Consortium, which was established by the 2007

    Energy Plan legislation, has now identified 25 lease blo8

    3,200 MW of potential offshore wind capacity in shallow wate9

    the visible horizon.310

    Figure 1 below summarizes the projected demand for renewable energy11

    these state RPS requirements and goals. As Figure 1 shows, the total 12

    estimated to increase from 11,700 GWh in 2010, to more than 40,00013

    2020, and approximately 54,000 GWh in 2025. Assuming an averag14

    factor of 37%, this demand is equivalent to 3,600 MW of renewable pow15

    in 2010, more than 12,000 MW in 2020, and approximately 16,600 MW16

    As discussed below, however, due to RPS credit multipliers, less offsh17

    generating capacity would be needed to satisfy the existing requirement.18

  • 7/31/2019 Brattle Testimony AWC 400 403

    25/135

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

    Figure 11Renewable Demand in Mid-Atlantic Coastal States by Year2

    0

    10,000

    20,000

    30,000

    40,000

    50,000

    60,000

    2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024

    Year

    GWh

    Sources and Notes:

    [1] RPS targets from DOE's Database of State Incentives for Renewables and Energy Efficiency (DSIRE).

    [2] Load forecasts based on EIA 2008 state electricity profiles; applied RTO-wide load growth rates from 2010 PJM Load F

    [3] Virginia RPS goal is defined as a percent of base year (2007) sales minus average nuclear generation between 2004-06.

    3

    Q. HOW MUCH RENEWABLE CAPACITY CURRENTLY EXISTS 4

    THESE STATES?5

    A. Table 4 below summarizes renewable generation supply in the coa6

    Atlantic states based on the unit-level database compiled by Ventyx, Th7

    Velocity Suite. As the table shows, approximately 1,250 MW of 8

    supply already exists, is under construction, or is at least partially 9

    within states boundaries (mostly biomass and landfill gas). 10

  • 7/31/2019 Brattle Testimony AWC 400 403

    26/135

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

    Table 41Renewable Supply in Mid-Atlantic Coastal States by Technolo2

    Status Delaware Maryland New Jersey Virginia

    TOTAL

    CAPACITY

    Assume

    Capacit

    Facto

    (MW) (MW) (MW) (MW) (MW) (%)

    Biomass 0 117 150 263 530 85%

    Landfill Gas 7 26 65 128 226 85%

    Onshore Wind 2 108 8 188 306 32%

    Small Hydro 0 18 4 121 144 48%Solar 0 4 43 0 48 16%

    TOTAL 9 274 270 700 1,253

    Sources and Notes:

    [1] Capacity calculated based on data compiled by Ventyx, The Velocity Suite (downloaded on 10/21/2010).

    [2] Generation estimated based on technology-specific capacity factors.

    [3] Includes existing units, and units that are under construction or permitted.

    [4] "Small Hydro" includes only the units with a nameplate capacity of less than 30 MW.

    [5] "Solar" does not include customer-sited generators.

    [6] Bluewater's proposed 350 MW project is not included because its status is listed as "Application Pending".3

    Q. IS THE SUPPLY DESCRIBED ABOVE SUFFICIENT TO ME4

    STATED RENEWABLE REQUIREMENTS OR GOALS OF C5

    MID-ATLANTIC STATES?6

    A. No. There is a large gap that will need to be met by additional reso7

    addition to the 7,150 GWh from renewable energy plants that already 8

    under construction, or are partially permitted, approximately 47,0009

    additional renewable generation will be needed to meet state RPS targets10

    Considering that at least 6,600 GWh is required to come from solar resou11

    leaves approximately 40,000 GWh in additional demand from other 12

    Di T i f J h Pf if b d S

  • 7/31/2019 Brattle Testimony AWC 400 403

    27/135

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

    approximately 16,000 GWh from offshore wind.4 Taking the states R1

    multipliers into account, this number goes up to more than 26,000 G2

    approximately 22,000 GWh from offshore wind, which is only two thi3

    incremental 40,000 GWh needed for RPS compliance by 2025.4

    Q. HOW MUCH OFFSHORE WIND POTENTIAL EXISTS IN TH5

    ATLANTIC REGION?6

    A. The Mid-Atlantic offshore region has been recognized as one of the m7

    locations for offshore wind generation. The National Renewabl8

    Laboratory (NREL) has determined that total Mid-Atlantic offsh9

    energy potential is over 480,000 MW, of which 44,000 MW is located i10

    waters between 12 and 50 nautical miles off the shores of PJMs f11

    Atlantic coastal states.512

    Q. HOW MUCH ADDITIONAL OFFSHORE WIND CAPACITY WO13

    NEEDED TO SATISFY ONLY THE REMAINING REQUIREM14

    THE FOUR MID-ATLANTIC STATES RPS TARGETS?15

    A. If the incremental 40,200 GWh required for RPS compliance of the f16

    came only from onshore wind resources with an average 32% capac17

    then approximately 12,800 MW of additional onshore wind capacity 18

    needed (taking into account solar carveouts and the 200% RPS credit 19

    Di t T ti f J h Pf if b d S

  • 7/31/2019 Brattle Testimony AWC 400 403

    28/135

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

    come only from offshore wind resources with an average 40% capac1

    then approximately 9,200 MW of new capacity would be needed (ta2

    account solar carveouts and the 300% RPS credit for offshore wind in3

    and 350% in Delaware). Thus, not even considering any potential de4

    offshore wind energy in other PJM and neighboring states, the RPS req5

    of the four Mid-Atlantic states with AWC landing points already sig6

    exceeds the 6,000 MW of offshore wind generation that can be delivere7

    by the Project.8

    Q. HOW MUCH OF THE FOUR STATES RENEWABLE REQUIR9

    WOULD LIKELY BE IMPORTED FROM STATES OUTSIDE TH10

    ATLANTIC REGION?11

    A. That is difficult to assess at this point. Most other states demand for re12

    similarly exceeds their local supply, limiting the potential for onsh13

    imports by the coastal Mid-Atlantic states. Only states in the Upper14

    have significant long-term export potential. While these Upper Midwes15

    have a large amount of high-quality onshore wind that could meet som16

    coastal states RPS requirements, development of these resources is al17

    by severe transmission constraints. In addition, the east coast states hav18

    strong preference in favor of developing renewable resources within th19

    Direct Testimony of Johannes Pfeifenberger and Sam

  • 7/31/2019 Brattle Testimony AWC 400 403

    29/135

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

    Q. WHAT IS THE MID-ATLANTIC STATES RATIONAL1

    SUPPORTING OFFSHORE WIND OVER ONSHORE ALTERNA2

    A. The coastal states support the development of offshore wind resour3

    number of reasons. First, the Mid-Atlantic offers attractive wind speeds4

    capacity factors that are comparable to or exceed those in the Upper Mi5

    addition, the Mid-Atlantic coast has large areas of shallow water tha6

    suited for deployment of offshore wind generation at lower cost than 7

    incurred in deep-water locations. As mentioned above, NREL estimate8

    Mid-Atlantic has a very large offshore wind potential in shallow wa9

    attractive wind speeds (almost half of the U.S. total).710

    Second, offshore wind generation can be located close to the co11

    centers, which avoids the transmission investment costs and losses 12

    with integrating much more distant onshore renewable resources.8

    Fi13

    coastal states have expressed a clear preference for offshore wind devel14

    their efforts to create a clean-tech industry and reach a scale of offsh15

    power development that would support local manufacturing of wind tur16

    related equipment as well as the development of supporting infrastructur17

    specialized vessels and on-shore staging areas. The availability of 18

    manufacturing and other infrastructure is seen as a critical factor in red19

    Direct Testimony of Johannes Pfeifenberger and Sam

  • 7/31/2019 Brattle Testimony AWC 400 403

    30/135

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

    cost of renewable power options, in particular the still evolving offsh1

    technologies.92

    2. Production Cost, Energy Price, and Emissions Benefits3Q. WHAT ARE THE MAIN COSTS AND BENEFITS ASSOCIATE4

    OFFSHORE WIND DEVELOPMENT?5

    A. While developing this amount of offshore wind resources requires s6

    investmentsapproximately $30 billion for 6,600 MW of installed c7

    these investments have to be considered in the context of associated8

    Some of these benefits include: (1) environmental benefits through9

    emissions of CO2 and other pollutants; (2) promotion of a strategic ind10

    the economic stimulus associated with manufacturing, constructi11

    operations, and other economic activities; (3) electricity market benef12

    form of reduced LMPs and production costs from fossil fuel power plant13

    Q. HAVE YOU QUANTIFIED THESE BENEFITS?14

    A. Yes, we have. We have analyzed the electricity market and emissions i15

    injecting 6,600 MW of offshore wind using PROMOD simulations. We16

    estimated the employment and economic stimulus impact of this leve17

    investment, using the Job and Economic Development Impact 18

    Direct Testimony of Johannes Pfeifenberger and Sam

  • 7/31/2019 Brattle Testimony AWC 400 403

    31/135

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

    Q. PLEASE EXPLAIN HOW YOU SIMULATED THE ELECT1

    MARKET AND EMISSION IMPACTS OF OFFSHORE WIND 2

    DEVELOPMENT.3

    A. As discussed further in Section VII of our testimony and Exhibit AWC4

    directed staff of Ventyx, the vendor of the PROMOD simulation 5

    simulate market conditions for 2016 with and without the addition of 66

    of nameplate offshore wind generation. These simulations showed tha7

    wind via the AWC Project significantly reduces LMPs, as well as the 8

    and production costs from fossil fuel generating plants.9

    Q. WHAT ARE THE EMISSIONS REDUCTIONS ASSOCIATED10

    6,600 MW OF OFFSHORE WIND?11

    A. The approximately 23,000 GWh of energy produced by 6,600 MW of 12

    displace more than 23,000 GWh of fossil generation (the displacemen13

    than one-for-one because injecting power closer to the coastal loa14

    reduces electrical losses by approximately 1,000 GWh, or more than 1015

    average). Approximately 61% of the displaced generation is gas-fire16

    coal-fired, and 1.5% oil-fired, and all of the associated emissions are e17

    As previously shown in Table 1, injecting up to 6,000 MW of ene18

    6,600 MW of offshore wind capacity will reduce CO2 emissions from 19

    Direct Testimony of Johannes Pfeifenberger and Sam

  • 7/31/2019 Brattle Testimony AWC 400 403

    32/135

    y gExhibi

    P

    an economic value of approximately $500 million per year.10 The pre1

    of these emissions cost savings over 20 years from 2016 through 2035 2

    $5.2 billion (expressed in 2010 dollars).11 These benefits are ad3

    production cost benefits, since the production costs in the PROMOD m4

    not include CO2 allowance price adders, reflecting the currently poor 5

    for near-term climate legislation.6

    Q. WHAT ARE THE IMPACTS OF 6,600 MW OF WIND GENERAT7

    SYSTEM PRODUCTION COSTS?8

    A. The PROMOD simulations show that injecting up to 6,000 MW of en9

    6,600 MW of offshore wind capacity reduces system-wide production10

    $1.1 billion per year. The present value of the $1.1 billion in annual p11

    cost savings over 20 years from 2016 through 2035 would be at least $12

    (expressed in 2010 dollars). The savings are primarily derived from13

    fossil fuel-fired generation with zero-variable-cost generation, but14

    substantially reducing congestion and losses on the prevailing west-to-15

    on the onshore system. In fact, our simulations show that annual conges16

    decrease by $410 million and losses decrease by more than 115 MW on 17

    Direct Testimony of Johannes Pfeifenberger and Sam

  • 7/31/2019 Brattle Testimony AWC 400 403

    33/135

    ExhibiP

    Q. HOW MUCH WOULD ADDING 6,600 MW OF OFFSHORE1

    CAPACITY SAVE CUSTOMERS BY REDUCING ENERGY PRIC2

    A. The PROMOD simulation results also show that this amount of offsh3

    energy will reduce energy prices paid by customers by approximately $64

    New Jersey, by $2-4/MWh in Delaware, Maryland and Virginia, by $2-55

    Pennsylvania, and by $0.5-1.6/MWh in western PJM, with effects outsid6

    as well. These price impacts, which are shown in Table 5, would reduce7

    payments by $2.2 billion per year in PJM alone, without counting red8

    other regions. Net of reduced loss refunds in the AWC Wind case9

    system losses and LMPs are lower, which reduces marginal-loss-relate10

    by $79 millionthe customer savings are only $2.1 billion, as describ11

    Technical Appendix report filed as Exhibit AWC-403 with this testimon12

    However, lower energy prices can be expected to increase capaci13

    As energy prices decrease, so do the energy margins earned by generato14

    will induce them to bid commensurately more in the capacity mar15

    example, the potential developer of a new combustion turbine in EMAA16

    anticipate $9/kW-yr lower energy margins and thus would bid that mu17

    for capacity in order to be willing to enter the market.18

    Assuming new combustion turbines set the capacity prices w19

    Direct Testimony of Johannes Pfeifenberger and Sam

  • 7/31/2019 Brattle Testimony AWC 400 403

    34/135

    ExhibiP

    per year ($5 billion NPV), offsetting some of their savings from reduc1

    This yields a $1.6 billion annual netbenefit in terms of customer wholes2

    purchase costs, calculated as $2.2 billion in annual LMP reductions net o3

    marginal loss refunds ($79 million) and capacity price increases ($480 m4

    5

    Table 56Impacts of the AWC Project with Wind on PJM Load LMPs7

    Compared to the Base Case (without AWC and without Offshore 8

    Region State PJM Area Annual Base AWC AWC Wind A

    Load Case Wind vs. Base Case vs

    LMP LMP LMP Loa

    (GWh) ($/MWh) ($/MWh) ($/MWh)

    [1] [2] [3] [4]= [3]-[2]

    AWC States DE DPLC 20,517 $55.4 $51.7 ($3.7)

    AWC States NJ AE 13,978 $58.2 $52.2 ($6.0)

    AWC States NJ JCPL 29,004 $62.5 $56.2 ($6.3)

    AWC States NJ PSEG 54,250 $60.4 $53.7 ($6.8)

    AWC States NJ RECO 1,751 $64.6 $61.6 ($3.0)

    AWC States VA VP 114,406 $53.2 $50.9 ($2.2)

    AWC States MD BGE 39,503 $54.3 $50.9 ($3.4)

    AWC States MD PEPCO 36,283 $54.8 $51.2 ($3.6)Other PJM-E PA METED 18,518 $55.8 $51.3 ($4.5)

    Other PJM-E PA PECO 47,010 $57.7 $52.1 ($5.6)

    Other PJM-E PA PENN Elec 21,574 $48.0 $46.0 ($2.0)

    Other PJM-E PA PPL 47,100 $56.1 $51.1 ($5.0)

    Other PJM-E PA UGI 1,159 $57.6 $52.1 ($5.5)

    PJM-W IL COMED 125,253 $43.1 $42.5 ($0.6)

    PJM-W OH AEP 188,533 $44.4 $43.9 ($0.5)

    PJM-W OH FE OHIO 78,361 $43.9 $43.4 ($0.5)

    PJM-W WV APS 55,414 $48.7 $47.0 ($1.6)

    PJM TOTAL 892,613 $50.2 $47.7 ($2.4)

    AWC States 309,692 $56.1 $52.1 ($4.0)

    Other PJM-E 135,361 $55.3 $50.7 ($4.7)

    PJM W 447 561 $44 5 $43 8 ($0 7)

    Direct Testimony of Johannes Pfeifenberger and SamE hibi

  • 7/31/2019 Brattle Testimony AWC 400 403

    35/135

    ExhibiP

    Employment and Economic Stimulus Benefits1

    Q. WHAT ARE ECONOMIC STIMULUS BENEFITS?2

    A. The development of offshore wind and associated transmission infrastru3

    provide economic stimulus benefits for the Mid-Atlantic region through 4

    employment, earnings by employees, and overall economic activity (i.e5

    revenues associated with sales and re-sales of goods and services st6

    These employment and economic activity benefits arise as direct, ind7

    induced impacts associated with the investment. Direct impacts ca8

    jobs, earnings, and economic activity generated by the direct co9

    activities and spending on transmission infrastructure and wind g10

    facilities. Indirect impacts arise as in-region suppliers to the transmi11

    wind generation industries, as well as other upstream producers, benefi12

    increased investment in infrastructure and generation. Finally, induced13

    are created when the increased income from jobs supported by the tra14

    and offshore wind construction is spent on products and services15

    industries, generating a ripple effect throughout the regional economy.16

    Q. HOW DID YOU ESTIMATE THE ECONOMIC STIMULUS BE17

    PROVIDED BY THE 6,600 MW OF WIND AND ASSO18

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

  • 7/31/2019 Brattle Testimony AWC 400 403

    36/135

    ExhibiP

    Development Impact (JEDI) Model.12 The economic stimulus1

    associated with the transmission infrastructure build-out was estimated b2

    recent study that quantified transmission investment benefits for the S3

    Power Pool (SPP) based on analysis conducted using the Minnesota 4

    Group Model.13 JEDI and IMPLAN are widely-used by economists a5

    analysts to estimate how specific investments affect a regional economy6

    Q. FOR WHAT LEVEL OF WIND AND TRANSMISSION INVES7

    AMOUNTS HAVE YOU ANALYZED ECONOMIC ST8

    BENEFITS TO THE MID-ATLANTIC REGION?9

    A. The investment assumptions we used for this analysis are summarized i10

    below. As the table shows, these investments consist of appr11

    $23 billion of investments in wind turbines and their foundations, appr12

    $2.8 billion in lower voltage AC transmission cables to connect the turbi13

    offshore substations, and $5 billion in HVDC-related transmission exp14

    AWC Project) to interconnect these offshore wind farms to shore.15

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

  • 7/31/2019 Brattle Testimony AWC 400 403

    37/135

    ExhibiP

    Table 61

    Estimated Wind Plant, AC Collector System, and2AWC Project Investment Summary3

    ComponentsTotal Cost

    (2010$)

    Percentage of

    Total

    Investment

    Uni

    (20

    ($ Billion) ($

    6,600 MW Wind Plant Investment 23.0 75%

    Offshore AC Collector System Investment 2.8 9%AWC Project Investment 5.0 16%

    Total 30.8 100%

    Sources & Notes:

    Wind Plant Investment includes turbines, blades, towers, foundations, and

    additional labor and development, and permitting costs.

    AWC Project Investment includes HVDC system components: off- and onshore

    converters and HVDC backbone and lateral cables.4

    5

    Q. HOW HAVE YOU USED THESE INVESTMENT ASSUMPTI6

    YOUR ANALYSIS?7

    A. For the purposes of this analysis, the JEDI model was used with p8

    settings for the state of New Jersey (as a proxy for the region), but th9

    turbines, blades, towers, and foundations were adjusted to reflect10

    equipment and construction costs as summarized in Table 6. To11

    preliminary estimate of transmission-related benefits, we simply s12

    benefits per billion dollar of investments derived from the SPP stu13

    necessary investment in the offshore collector system that connects th14

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

  • 7/31/2019 Brattle Testimony AWC 400 403

    38/135

    ExhibiP

    Q. HAVE YOU ANALYZED TO WHAT EXTENT THE ECO1

    STIMULUS BENEFITS OF OFFSHORE WIND PLANT AND RE2

    TRANSMISSION INVESTMENT DEPENDS ON THE DEGR3

    WHICH THE WIND GENERATION AND TRANSM4

    COMPONENTS ARE MANUFACTURED WITHIN THE MID-AT5

    REGION?6

    A. Yes, we have. To analyze the extent to which economic stimulus benef7

    on the degree of in-region manufacturing of wind plant and tra8

    components, we analyzed the impact of three cases:Low, Medium, and9

    region manufacturing. Table 7 summarizes the in-region man10

    assumptions associated with each of these three cases.11

    Table 712Local Manufacturing Share13

    Assumptions for the Economic Analysis Impact14

    Share of In-Reg

    Manufacturi

    Wind Farm Low MediumEquipment

    Turbines 0% 0%

    Blades 0% 100%

    Towers 0% 100%

    Transportation 0% 100%Balance of Plant 82% 93%

    Total Wind Farm Local Manufacturing Share 26% 55%

    Offshore AC Collector SystemWires and electrical equipment 0% 50%

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

  • 7/31/2019 Brattle Testimony AWC 400 403

    39/135

    P

    For the wind farm construction-related analysis, these 1

    manufacturing assumptions were analyzed with the JEDI model. 2

    transmission-related analysis, we relied on the SPP study, which 3

    analyzed transmission build-out scenarios for aLow in-region manufact4

    (assuming all transmission equipment would be imported from out5

    suppliers) and a Medium case (assuming that 50% of transmission 6

    related electrical equipment facilities would be manufactured within th7

    These SPP investment levels and economic stimulus results were used to8

    normalized ratios for the amount of jobs, earnings, and overall econom9

    stimulated by the transmission investment for both theLow andMedium10

    manufacturing cases. These ratios were then applied to the tra11

    investments associated with the AWC Project. The difference between12

    and the Medium in-region manufacturing case was then applied to 13

    estimate of theHigh in-region manufacturing case.14

    Q. WHAT ARE THE RESULTS FROM THIS ANALYSIS?15

    A. The results from our preliminary economic stimulus analysis are summ16

    Table 8 below. As Table 8 shows, the combination of the offshore 17

    associated transmission investment are estimated to support a total of 118

    263,000 full-time equivalent (FTE) years of employment du19

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

  • 7/31/2019 Brattle Testimony AWC 400 403

    40/135

    P

    benefits as described earlier. Of the approximately 120,000 FTE-ye1

    Medium in-region manufacturing case for wind plant construction, appr2

    39,000 (33%) are directly supported by on-site construction, enginee3

    design work; approximately 62,000 (52%) are supported indirectly at4

    of wind power generation components and construction materials; an5

    18,000 (15%) are induced by the additional spending (food, housing6

    etc.) of employees supported by the direct and indirect economic activiti7

    As Table 8 also shows, the total earnings by employees w8

    construction-period jobs supported by the wind and associated tra9

    investment range from $7.6 to $17.4 billion, depending on the level of10

    manufacturing. The estimated overall economic activity stimulated11

    investments during the construction period ranges from $16.4 to $51.5 b12

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

  • 7/31/2019 Brattle Testimony AWC 400 403

    41/135

    P

    Table 81

    Analysis of Jobs, Earnings, and Economic Activity2

    Full-Tme

    Equivalent

    Years

    Total

    Earnings

    (2010$)

    To

    (FTE-Years) ($ Billion)

    Low In-Region Manufacturing (19% of All Equipment)

    Wind Plant Construction (6,600 MW) 79,000 $5.0

    Offshore AC Collector System Construction 18,000 $0.9

    AWC Project Construction 33,000 $1.6

    Total 130,000 $7.6

    Medium In-Region Manufacturing (54% of All Equipment)

    Wind Plant Construction (6,600 MW) 120,000 $8.2

    Offshore AC Collector System Construction 23,000 $1.1

    AWC Project Construction 41,000 $2.1

    Total 184,000 $11.4

    High In-Region Manufacturing (98% of All Equipment)

    Wind Plant Construction (6,600 MW) 184,000 $13.3Offshore AC Collector System Construction 28,000 $1.5

    AWC Project Construction 51,000 $2.6

    Total 263,000 $17.4

    NREL (Musial, 2007)*

    Wind Plant Construction (Scaled to 6,600 MW) 257,000 NA

    Wind Farm Operation Over 20 years 145,000 NA

    Ontario Offshore Wind Study (2010)**

    Base Case (55% Local Sourcing of Development Costs)

    Wind Plant Construction (Scaled to 6,600 MW) 166,551

    High Case (63% Local Sourcing of Development Costs)

    Wind Plant Construction (Scaled to 6,600 MW) 191,080

    Sources & Notes:

    * "Large-Scale Offshore Wind Power in the United States: Assesment of Opportunities and Barriers,"NREL , Sepetember 2010.

    "Offshore Wind: Viable Option for Coastal Regions of the United States",Marine Technology Society Journal , 2007

    ** "Employment and Economic Impacts of Ontario's Future Offshore Wind Power Industry", The Conference Board of Canada, December 20103

    4

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

  • 7/31/2019 Brattle Testimony AWC 400 403

    42/135

    P

    Q. HOW MUCH OF THE ECONOMIC STIMULUS BENEFIT 1

    OFFSHORE WIND INVESTMENT IS DEPENDENT ON THE E2

    TO WHICH COMPONENTS CAN BE MANUFACTURED WITH3

    MID-ATLANTIC REGION?4

    A. As Table 8 documents, the extent to which these investments benefit5

    Atlantic region depends to a considerable extent on how much of the 6

    equipment can be manufactured within the region. For example, the7

    region manufacturing case (in which only 19% of all equipment i8

    locally) supports only 130,000 FTE-years of employment while theMe9

    (with 54% of all equipment manufactured sourced locally) supports ove10

    FTE-years, an increase of almost 50%. As we discuss further in Section11

    testimony, this means developing offshore wind at a pace and scale12

    support the creation of local supply-chain industries should be an import13

    policy goal that provides significantly greater economic benefits for the 14

    Q. WHAT ARE THE EMPLOYMENT BENEFITS THAT CO15

    AFTER THE CONSTRUCTION OF OFFSHORE FACILITIES HA16

    COMPLETED?17

    A. Once construction of the AWC Project and the 6,600 MW of offshore w18

    has been completed, employment and related benefits to the local econ19

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

  • 7/31/2019 Brattle Testimony AWC 400 403

    43/135

    P

    over a 20-year operation period. Second, the development of 6,601

    offshore wind generation in the Mid-Atlantic region will create a manu2

    base and local supply chain for logistical services that can support th3

    expansion of offshore wind generation beyond the 6,600 MW facilitat4

    AWC Project. If additional offshore facilities are added at a steady r5

    employment and associated economic benefits would continue 6

    Considering the enormous offshore wind generation potential of the Mi7

    region, this is a plausible outcome.8

    Q. IS THE MAGNITUDE OF YOUR PRELIMINARY ESTIMA9

    THESE ECONOMIC STIMULUS BENEFITS OF OFFSHORE10

    DEVELOPMENT CONSISTENT WITH THE MAGNITUDE OF11

    BENEFITS FOUND BY OTHER STUDIES?12

    A. Yes. As shown in Table 8, NRELs research has found employment imp13

    close to the upper bound of the benefits we estimated.14 The table also s14

    results from a recent study for Ontario offshore wind development15

    similar to our estimates.1516

    17

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

  • 7/31/2019 Brattle Testimony AWC 400 403

    44/135

    P

    IV. AWC PROJECT CONFIGURATION1AND COSTS2

    Q. PLEASE SUMMARIZE THE CONFIGURATION OF TH3

    PROJECT.4

    A. As explained in the testimony of Mr. Paul McCoy, the AWC Project is c5

    as a double-circuit HVDC offshore transmission backbone with twelve6

    AC-DC converter stations interconnected at seven existing substatio7

    onshore grid. As shown in Figure 2, each circuit will be able to trans8

    MW of energy and capacity between interconnection points along 9

    accommodate six 500 MW offshore AC-DC converter stations to int10

    offshore wind plants, and interconnect a total of 3,000 MW of onshor11

    converter stations at four locations.12

    As also shown in Figure 2, both circuits interconnect with 113

    converter stations at PJMs Fentress substation in southern Virginia. 14

    interconnection points are: 500 MW at Piney Grove (MD), 500 MW at15

    (NJ), and 1,000 MW at Hudson (NJ) for one of the circuits, and 10016

    Indian River (DE), 500 MW at Cardiff (NJ), and 500 MW at Sewaren (N17

    other circuit. In addition to facilitating the interconnection of offsh18

    power plants, this configuration provides an offshore reinforcement to th19

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

  • 7/31/2019 Brattle Testimony AWC 400 403

    45/135

    P

    Figure 21

    Preliminary AWC 2-Circuit Design2

    1000

    Hudson

    1000

    IndianRiver

    500

    Cardiff

    500

    Larrabee

    500

    Sewaren

    500

    PineyGrove10

    Fentr

    500MWOffshorePlatform,ConverterandSwitchesDCSwitch 500MWOnshoreC

    1000MWOnshore

    3

    4

    Q. WHAT IS THE TOTAL INSTALLED NAMEPLATE CAPACITY5

    OFFSHORE WIND FARMS FACILITATED BY THE AWC PROJ6

    A. Considering the transmission capability to inject 6,000 MW, we have7

    6,600 MW of installed offshore nameplate wind generation capacity 8

    interconnected to the AWC Project. Building slightly more wind capac9

    the overall cost of renewable power For example National Grid t10

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

  • 7/31/2019 Brattle Testimony AWC 400 403

    46/135

    Q. DOES BUILDING WIND CAPACITY IN EXCESS O1

    TRANSMISSION CAPABILITY RESULT IN SIGNI2

    CURTAILMENT OF WIND GENERATION?3

    A. No, not if the wind capacity exceeds the transmission capacity by onl4

    we have assumed. Analyzing the NREL data for the AWC sites, we f5

    only 0.2% of the potential energy generated from 6,600 MW of offsh6

    would have to be curtailed to avoid exceeding the 500 MW output limit7

    the 12 offshore converters. This minimal curtailment was incorporate8

    market simulations.9

    Q. HOW DO THE AWC PROJECTS COSTS COMPA10

    CONVENTIONAL RADIAL INTERCONNECTION OF INDI11

    OFFSHORE WIND PLANTS?12

    A. The AWC Project is able to reliably deliver 6,000 MW of offshore wi13

    and additionally provide a fully controllable 2,000 MW HVDC transmi14

    between southern Virginia and northern New Jersey at a total15

    approximately $5 billion. In comparison, we estimate that delivering 616

    of wind power with radial high-voltage alternating current (17

    transmission lines from individual wind plants to shore would cost18

    $3.4 and $5.3 billion without offering the substantial additional publ19

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

  • 7/31/2019 Brattle Testimony AWC 400 403

    47/135

    Q. YOU NOTED THAT IT WOULD COST BETWEEN $3.4 BILLI1

    $5.3 BILLION TO INTERCONNECT OFFSHORE WIND FARM2

    INDIVIDUAL RADIAL HVAC TRANSMISSION LINES. HOW D3

    ESTIMATE THESE COSTS?4

    A. We have estimated these costs by analyzing the installed costs of the 5

    transmission elements needed to interconnect individual offshore wind6

    the onshore grid. These transmission elements include: (1) an offshore 7

    consisting of switchgear, transformation, and platform; (2) several HVA8

    from the offshore substation to shore; and (3) an onshore substatio9

    transformation (as a conservative assumption). These cost estimates are10

    publicly-available information on the costs and project configuratio11

    variety of sources, including actual project proposals. They do not in12

    cost of wind turbines, turbine foundations, and the transmission collect13

    that connects the individual turbines of a wind farm to the offshore s14

    because these cost elements will be identical or approximately 15

    irrespective of whether the individual wind farms are integrated16

    individual HVAC lines to shore or through the AWC Project.17

    Q. HOW MANY INDIVIDUAL WIND FARMS DID YOU ASSUME 18

    BE DEVELOPED TO DELIVER 6,000 MW OF OFFSHORE19

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

  • 7/31/2019 Brattle Testimony AWC 400 403

    48/135

    The second scenario we evaluated consisted of twenty radial HVAC tra1

    lines with a capacity of 300 MW each. Either of these radial tra2

    scenarios can thus deliver 6,000 MW of offshore wind generation simi3

    capability of the AWC Project.4

    Q. WHAT VOLTAGE LEVELS AND HOW MANY INDIVIDUAL 5

    WOULD BE NEEDED TO ACHIEVE THESE 500 MW AND 6

    TRANSFER CAPABILITIES TO INTERCONNECT INDIVIDUA7

    FARMS TO THE ONSHORE GRID?8

    A. We evaluated two configurations to achieve 500 MW transfer capabi9

    230 kV HVAC submarine cable system consisting of two parallel circuit10

    a 138 kV HVAC cable system consisting of three parallel circuits.11

    300 MW transfer scenario, we developed the costs for a 138 kV HV12

    configuration with two parallel circuits.13

    Q. WHAT ARE THE OVERALL COSTS AND INDIVIDUAL14

    ELEMENTS ASSOCIATED WITH EACH OF THESE THREE15

    RADIAL OFFSHORE TRANSMISSION CONFIGURATIONS?16

    A. Our estimates of the overall costs and cost elements of these three HV17

    transmission configurations are summarized in Table 9.18

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

  • 7/31/2019 Brattle Testimony AWC 400 403

    49/135

    Table 91

    Estimated Costs of Radial HVAC Transmission Lines2Interconnecting Individual Wind Power Plants to the Onshore Grid3

    Description of Illustrative HVAC Systems

    Interconnection of 12

    offshore wind farms based

    on two 230 kV cables laid

    in parallel trenches

    Interconnection of 12

    offshore wind farms based

    on three 138 kV cables

    laid in three parallel

    trenches

    Interconn

    offshore win

    on two 138 k

    in paralle

    Category (2010$ Billion) (2010$ Billion) (2010$

    [A] [B] [C] [

    [1] Offshore substations

    and platforms$1.0 $1.0 $

    [2] Offshore radial

    cables$1.6 $1.9 $

    [3] Onshore landing and

    radial cables $0.5 $0.6 $

    [4] Onshore substations $0.2 $0.2 $

    [5] Total HVAC

    System Cost$3.4 $3.8 $

    Sources and Notes:

    [1A]:

    [1B]: 12 offshore substations and platforms.

    [1C]: 12 offshore substations and platforms.

    [1D]: 20 offshore substations and platforms.

    [2]:

    All systems assume 6,600 MW of installed wind generation capacity which is equivalent to a 10% overbu

    MW of transfer capability. Each illustrative HVAC system has equally sized wind farms (i.e., 12 wind fa

    of installed capacity each).Offshore substation costs based on onshore substation (with transformer) costs based on estimates from E

    Reliability Organzation of Texas ("ERCOT"), "CREZ Transmission Optimization Study," April 2, 2008, p

    platforms based on cost estimates from National Grid, "2010 Offshore Development Information Stateme

    September 2010, p. A-69.

    Cable cost estimates based on similar technology from National Grid, "2010 Offshore Development Infor

    Statement: Appendix," September 2010, pp. A-67-68. All cable costs are based on 3-core cross-linked po

    (XLPE) technology. Each offshore wind farm is 25 miles from the shoreline. A total of 55 miles of addit

    was assumed from the shoreline to the onshore substation. Includes cable installation costs based on vari

    costs per mile (excludes materials, ancillary vessels, and surveys) from National Grid, "2010 Offshore De

    Information Statement: Appendix," September 2010, p. A-70. Fixed installation costs per radial interconn

    surveys, engineering, mobilization/demobilization based on estimates from Green, J., Bowen, A., Fingeris

    Y., "Electrical Collection and Transmission Systems for Offshore Wind Power," March 2007, p. 3.

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

  • 7/31/2019 Brattle Testimony AWC 400 403

    50/135

    Q. WHICH OF THESE THREE RADIAL HVAC TRANSM1

    CONFIGURATIONS WOULD MOST LIKELY GET BUILT?2

    A. Assuming 6,600 MW of offshore wind could actually get develop3

    through radial interconnections without an offshore backbone, we be4

    most likely outcome would be a mix of these three configurations depen5

    number of factors, including the availability of onshore interconnecti6

    (e.g., existing 138 kV and 230 kV facilities close to shore), the abil7

    onshore grid to accommodate injections of wind generation in the 308

    500 MW range, and the size of wind farms that individual developers a9

    finance through individual power purchase agreements. While t10

    configurations of radial cable system interconnecting individual wind 11

    certainly differ from the three configurations we evaluated, total costs o12

    radial cable systems to interconnect individual wind farms with the on13

    will very likely be within the $3.4 to $5.3 billion range of our cost14

    These costs of interconnecting individual wind farms with their o15

    transmission cables will be avoided if this amount of offshore wind gen16

    integrated by means of the AWC Project.17

    Q. HAVE YOU VERIFIED THAT YOUR COST ESTIMATES FO18

    RADIAL INTERCONNECTIONS OF INDIVIDUAL WIND FA19

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

  • 7/31/2019 Brattle Testimony AWC 400 403

    51/135

    A. Yes. We have used the same approach to estimate the cost of the AW1

    This yielded cost estimates ranging from $4.9 to $5.6 billion, which is v2

    consistent with the $5 billion estimate from the Project sponsors.3

    Q. YOU MENTIONED THAT THERE ARE ADDITIONAL BENEFIT4

    THE AWC PROJECT OFFERS OVER RADIAL INTERCONNE5

    OF INDIVIDUAL WIND PLANTS WITH THE ONSHORE GRID6

    ARE THESE BENEFITS?7

    A. As we discuss in the next three sections of our testimony, the additiona8

    offered by the AWC Project over the individual radial interconnection o9

    wind power plants with the onshore grid includes a number of publ10

    reliability, and congestion relief-related economic benefits. As the11

    presented in Sections V, VI, and VII show, the modest incremental c12

    offshore transmission backbone over the cost of radial interconnection13

    than offset by the cost savings and economic benefits associated w14

    economies, reduced siting and permitting uncertainties, and the relia15

    congestion relief advantages offered by the AWC Project compared16

    interconnections of individual offshore wind power plants.17

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

  • 7/31/2019 Brattle Testimony AWC 400 403

    52/135

    V. PUBLIC POLICY BENEFITS1ASSOCIATED WITH THE AWC PROJECT2

    Q. WHAT ARE THE PUBLIC POLICY BENEFITS THAT TH3

    PROJECT PROVIDES COMPARED TO INTERCONN4

    OFFSHORE WIND VIA CONVENTIONAL RADIAL LINES?5

    A. The AWC Project will facilitate meeting the coastal Mid-Atlant6

    renewable energy policy requirements and goals. It will do so in a7

    substantially reduces the barriers, uncertainties and costs of developing8

    wind generation, and that attracts more in-region manufacturing. It9

    reduce the environmental shoreline impact of siting the needed transmiss10

    Q. HOW DOES THE AWC PROJECT REDUCE THE UNCERT11

    AND OVERALL COSTS OF DEVELOPING OFFSHORE12

    GENERATION?13

    A. The AWC Projected reduced the uncertainties and overall costs of d14

    offshore wind generation in several important ways. First, it significant15

    environmental permitting barriers and associated uncertainties with offs16

    developments. Second, it greatly streamlines the PJM transmission pla17

    interconnection process for developing significant amounts of offsh18

    generation in the region. Third, the Project allows for a decoupli19

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

  • 7/31/2019 Brattle Testimony AWC 400 403

    53/135

    offshore wind developments, leading to reduced costs and increased loc1

    of wind turbines, plant components, and logistics services.2

    Q. PLEASE EXPLAIN HOW THE AWC PROJECT R3

    ENVIRONMENTAL PERMITTING BARRIERS AND UNCERTA4

    ASSOCIATED WITH OFFSHORE WIND DEVELOPMENT.5

    A. Environmental permitting of any transmission project, large or small,6

    time consuming, and uncertain. The Department of Energys Electricity7

    Committee, for example, noted that the fragmented nature of tra8

    permitting and siting is exacerbated by a lack of coordination which ma9

    delay the already lengthy siting process, add to the cost of transmission10

    and increase the financial risk to a transmission developer. As the d11

    Cape Wind permitting process has shown, permitting constra12

    environmental sensitivities create costly barriers and significant dela13

    siting process.14

    A major advantage of the AWC Project is that it prov15

    coordination and economies of scale for the permitting process: it rep16

    many individual offshore-to-shore permitting efforts with a single17

    permitting process for all 6,600 MW of offshore plants supported by the 18

    The value of a coordinated and streamlined single shoreline p19

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

  • 7/31/2019 Brattle Testimony AWC 400 403

    54/135

    tourist and residential areas, aviation routes, fishing zones, and shippin1

    These constraints will limit the number of viable sites for both offsh2

    farms and associated onshore landing points. In fact, because of such ov3

    shoreline and offshore constraints, the Maryland Offshore Wind Dev4

    study found that there may be only a few locations where wind farms5

    interconnected.186

    In short, in addition to offering a smaller environmental foot7

    single streamlined permitting process of the AWC Project will greatly r8

    uncertainties and costs of offshore wind development.9

    Q. PLEASE EXPLAIN HOW THE PROJECT STREAMLINES T10

    TRANSMISSION PLANNING AND INTERCONNECTION PROC11

    A. Similar to streamlined environmental permitting, the AWC Project als12

    substantially streamlined PJM transmission planning process compar13

    interconnection of individual wind power projects. The AWC Proje14

    evaluated in the PJM interconnection and transmission planning effort a15

    project for injecting up to 6,000 MW from 6,600 MW of offshore wind n16

    capacity into the onshore grid. Evaluating the interconnection of this a17

    offshore wind generation as a single transmission project and interc18

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

  • 7/31/2019 Brattle Testimony AWC 400 403

    55/135

    request avoids a lengthy iterative transmission planning and interc1

    process for many individual projects. Given that individual wind power2

    may be delayed or withdrawn, PJM would constantly have to re-evaluate3

    combinations of wind plant and on-shore locations in its interconnecti4

    For the AWC Project, a single planning effort can identify the best land5

    for all 6,000 MW of potential injections from the offshore wind plants. 6

    will this single planning step save time and effort, it will also result 7

    optimal configuration for both onshore and offshore transmission.8

    Q. YOU NOTED THAT THE AWC PROJECT ALLOWS 9

    DECOUPLING OF THE SELECTION AND OPTIMIZATI10

    LOCATIONS FOR ONSHORE LANDING POINTS AND OFF11

    WIND PLANTS. HOW DOES THE PROJECT ACHIEVE THAT?12

    A. Unlike individual radial transmission interconnections from offshore w13

    to shore, the AWC Project is able to decouple the landing point and w14

    locations so that each can be separately optimized. In the case of tran15

    the AWC Project does not require a straight radial interconnection 16

    offshore wind farm to shore. Instead, the Project allows for the select17

    best locations for submarine cables to come on shore and interconnec18

    onshore grid, while offshore wind plant locations can be developed 19

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

  • 7/31/2019 Brattle Testimony AWC 400 403

    56/135

    HVDC backbone stretching from northern New Jersey to southern1

    almost independently from the selected landing points.2

    Q. DOES THIS DECOUPLING ALSO SIMPLIFY THE PERM3

    PROCESS FOR WIND DEVELOPERS?4

    A. Yes, very much so. The fact that onshore permitting and PJM interc5

    processes are resolved through the AWC Project greatly simplifies the 6

    permitting requirements for wind plant developers by limiting the 7

    permitting needs to federal waters at locations that are mostly beyond t8

    horizon from shore. Once these offshore permits are obtained, th9

    developers can simply interconnect their plants with the AWC Proj10

    various offshore locations. This expedited and simplified siting proce11

    the Dutch grid operator, TenneT, referred to as a plug and play sol12

    2009 position paper evaluating a proposed offshore transmission grid. 13

    further noted that:14

    [The] availability of offshore cables, grids and connections en15wind farm operators to plug in directly in order to supply elect16to the grid. This provides developers and financial backers with17assurances in advance, allowing national and international objec18

    to be achieved more quickly.

    19

    19

    Q. ARE OFFSHORE GRIDS SIMILAR TO THE AWC PROJECT20

    DEVELOPMENT ELSEWHERE?21

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

  • 7/31/2019 Brattle Testimony AWC 400 403

    57/135

    1,600 MW of offshore wind);20 TenneTs North Sea analysis to int1

    6,000 MW of offshore wind capacity;21 and the Irish Scottish Links o2

    Study (connecting Scotland, Ireland, and Northern Ireland).22 More3

    European countries recently signed a memorandum of understanding4

    offshore grid networks in the North Sea to interconnect 150,000 MW5

    capacity by 2030.236

    With over 2,000 MW of installed offshore wind capacity and m7

    under construction and planned, Europe currently has the most offsh8

    development experience. This has evolved from embracing the idea o9

    grids as an infrastructure priority to help meet renewable energy targ10

    most cost effective and efficient manner.24 The AWC Project would 11

    nascent U.S. offshore wind experience leapfrog past individually interc12

    single offshore wind farms and bring offshore wind power developm13

    U.S. more on par with that in Europe.14

    Q. HAVE YOU QUANTIFIED THE POTENTIAL ECONOMIC VA15

    THE AWC PROJECTS ABILITY TO INCREASE THE CERT16

    RAMP-UP, AND SCALE OF OFFSHORE WIND DEVELOPM17

    THE MID-ATLANTIC REGION?18

  • 7/31/2019 Brattle Testimony AWC 400 403

    58/135

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

  • 7/31/2019 Brattle Testimony AWC 400 403

    59/135

    attributed to a combination of support structures (20% to 30%) and log1

    installation (as high as 20%). If we assume that the reduced uncertai2

    ramp-up, larger scale and local supply facilitated by the AWC Project3

    save 20% on that portion of total offshore wind generation costs, thes4

    will reduce the overall costs of developing 6,600 MW of offshore wind5

    between $1.2 billion to $3.0 billion.286

    Finally, the streamlined environmental permitting and PJM tra7

    planning and interconnection process will reduce the costs and time 8

    development efforts. If we assume a coordinated effort in streamlined p9

    development, and transmission planning and interconnection process 10

    20% of the total project development and permitting costs, the associate11

    for 6,600 MW of wind development would be approximately $600 mill12

    on estimates by NREL that approximately 10% of total installed offsh13

    generation costs are attributable to project development and permitting e14

    The combination of these scale-related cost savings on offsh15

    development$3.2 billion lower wind turbine costs, $1.2 to 3.0 billion16

    construction, logistics, and installation costs, and $0.6 billion i17

    development and permitting costsamounts to $5.0 billion to $6.8 18

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

  • 7/31/2019 Brattle Testimony AWC 400 403

    60/135

    approximately 20% of a total $30 billion investment need. These co1

    alone have the potential to offset the entire cost of the AWC Project, ev2

    considering that the Project offers substantial reliability and energ3

    benefits and avoids between $3.4 billion and $5.3 billion in transmiss4

    that would be associated with radial interconnections of individual wind 5

    Q. IS THE ESTIMATED 20% SCALE AND COORDINATION-R6

    REDUCTION IN OFFSHORE WIND PLANT COSTS CONS7

    WITH THE SAVINGS ESTIMATED BY OTHERS?8

    A. Yes. For example, Steve Holliday, the Chief Executive Officer of t9

    Kingdoms National Grid (the countrys regulated transmission c10

    recently noted in the context of planning an offshore grid to interconnec11

    wind plants that [u]nless we get coordination between offshore and12

    right, the investment overall will be much higher than it needs to b13

    further stressed that [a]n uncoordinated approach may cost 25 perc14

    overall, past the end of the 2020s. And [we] will have to pay in our 15

    bills more for unnecessary investments.31 Similarly, and as already not16

    the Virginia Coastal Energy Research Consortium has estimated t17

    manufacturing of wind turbines and towers would reduce the 18

    approximately 22%.19

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

  • 7/31/2019 Brattle Testimony AWC 400 403

    61/135

    Q. SOME OF THE ESTIMATED COST REDUCTIONS ARE ASSO1

    WITH LOCAL MANUFACTURING AND LOGISTICS SERVICE2

    WOULD THE AWC PROJECT HELP DEVELOP SUCH A 3

    SUPPLY CHAIN?4

    A. Attracting local manufacturing and logistics services requires that offs5

    development has sufficient predictability and annual scale so that sup6

    justify the upfront investments needed for building up the local ind7

    manufacturing and investing in the necessary supporting infrastructure. 8

    manufacturing of wind farm components, VCERC notes that:9

    [The] one-time investment to build a turbine manufacturing 10(including a foundry for large castings, and separate facilitie11blade fabrication, tower fabrication, and nacelle assembly12estimated to be at least $500 million. Review of trade publica13and conversations with turbine manufacturers suggest that a de14of 100 to 150 turbines per year (or 500 to 800 MW per year) 15minimum of 5 years is required to justify such an investment.3216

    17

    Similarly, investments will be needed in supporting infrastructu18

    harbor facilities and specialized vessels to erect offshore wind turbin19

    offshore platforms, and lay submarine cables. NREL estimates that 20

    capital outlay for vessels alone would be more than $100 million and21

    construction of the initial dedicated offshore wind vessel might requir22

    large-scale wind project with sufficient capital investment to offset th23

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

  • 7/31/2019 Brattle Testimony AWC 400 403

    62/135

    pipeline.33 Without such supporting local infrastructure, offshore win1

    will be more expensive and may also be delayed by the limited availabi2

    recent Ontario study of offshore wind development noted:3

    The [local] supply potential for offshore wind will depend critica4the pace at which specialized construction, manufacturing, ass5and staging facilities can be developed. These factors will be far6

    important than the availability of suitable sites in determining ho7the industry can be established and the extent to which it can gr8As a result, the industry must address a critical mass issue.349

    10

    The AWC Project can spur local manufacturing by cre11

    predictability, ramp-up, and scale needed to overcome these initial in12

    hurdles to achieve cost reductions and facilitate timely project compl13

    avoid supply bottlenecks.14

    Q. WHAT IS THE ADDITIONAL EMPLOYMENT AND ECO15

    DEVELOPMENT BENEFIT OF INCREASED 16

    MANUFACTURING AND SUPPLY OF LOGISTICS SERVICES?17

    A. As discussed in Section III of our testimony, an increase of local manu18

    local construction, and other services substantially magnify the employ19

    economic stimulus benefits of the offshore wind investment to the Mi20

    region. As we estimated in Section III of our testimony, increa21

    manufacturing and supply of logistics services can easily increase em22

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

  • 7/31/2019 Brattle Testimony AWC 400 403

    63/135

    (in which only 19% of all equipment is sourced locally) supports only1

    full-time-equivalent years of employment while the medium case (with 52

    equipment manufactured or sourced locally) supports over 180,000 FTE3

    increase of almost 50%. As our analysis showed, the increase would4

    larger if more than 54% of all equipment would be manufactured o5

    locally. This means that developing offshore wind at a pace and scale 6

    by the AWC Project not only reduces overall costs but also provides sig7

    greater economic benefits for the region.8

    Q. YOU MENTIONED THAT THE AWC PROJECT WILL REDU9

    ENVIRONMENTAL IMPACTS OF SITING OFFSHORE10

    GENERATION. PLEASE EXPLAIN.11

    A. The AWC Project allows for a single, coordinated environmental permit12

    focusing on the best onshore interconnection points that avoid nature 13

    and other sensitive coastal areas. The Project makes this possible by 14

    high capacity and the offshore backbone, which enables the selection o15

    points to be largely independent of the wind farms offshore locatio16

    coordinated landing point selection benefit has also been recognized i17

    where several offshore grids are under development. For example, the D18

    operator TenneT noted that: [c]ompared with separate private connecti19

    Direct Testimony of Johannes Pfeifenberger and SamExhibi

    P

  • 7/31/2019 Brattle Testimony AWC 400 403

    64/135

    spatial planning. For instance, there is less disruption to sea and coasta1

    because transsections of dykes and dunes are kept to a minimum.352

    In addition, the Projects HVDC technology allows for the transm3

    6,000 MW of offshore power with fewer cables than AC techno4

    therefore, narrower right-of-ways. This smaller environmental fo5

    HVDC technology has also been recognized by PJM in its analysis of6

    Atlantic Power Pathway (MAPP) project, where it found that the HVD7

    requires less space for the same power transfer, reducing the disturbe8

    40% compared to an HVAC solution.36

    9

    Finally, the environmental impact of offshore wind is reduced f10

    the fact that