ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35...

494
TATA Consulting Engineers Ltd 1 DISMANTLING AND EXPANSION JOINTS 1.1 MILD STEEL DISMANTLING JOINTS 1.1.1 1.1.1.1 100 mm nominal dia ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARK S Details of cost for 10 dismantling joints MATERIAL: Quotation_Volu me III_pg no_2 Supplying Dismantling Joints Nos 10 2520.00 25200.00 Weight of dismantling Joints 11.6 kg 10 Nos SOR 2014_Andhra pradesh_pg no 81 Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work. L.S. 5% 1260.00 (A) 18.24 Labour for laying dismantling Joints quint al 1.16 255.40 296.26 (B) 18.30.2 Providing flanged joints to fixing dismantling joints with bolts, nuts and rubber insertion etc. each 20 195.70 3914.00 (C) Total 30670.26 Total without ED 27898.17 Add Water Charges @ 1% except on (A+B+C) 1% 224.28 Add CPOH @ 15% except on (A+B+C) 15% 3397.83 Cost for 10 no's of dismantling joint 31520.28 Cost for each dismantling joint 3152.03 Say 3152.00 1.1.1.2 125 mm nominal dia ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARK S Details of cost for 10 dismantling joints MATERIAL: Quotation_Volu me III_pg no_2 Supplying Dismantling Joints Nos 10 3307.50 33075.00 Weight of dismantling Joints 13.5 kg 10 Nos SOR 2014_Andhra pradesh_pg no 81 Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work. L.S. 5% 1653.75 (A) 18.24 Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing Mild Steel Dismantling Joints of pressure rating PN 1.6 with both side flange end suitable for installation in between flange end pipes. The rates are excluding excise duty component. Delhi Jal Board 22 Schedule of Rates 2014 - 2015

Transcript of ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35...

Page 1: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

1 DISMANTLING AND EXPANSION JOINTS1.1 MILD STEEL DISMANTLING JOINTS

1.1.1

1.1.1.1 100 mm nominal dia

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR)

REMARKS

Details of cost for 10 dismantling jointsMATERIAL:

Quotation_Volume III_pg no_2 Supplying Dismantling Joints Nos 10 2520.00 25200.00

Weight of dismantling Joints11.6 kg

10 NosSOR

2014_Andhra pradesh_pg no

81

Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work.

L.S. 5% 1260.00 (A)

18.24 Labour for laying dismantling Joints quintal 1.16 255.40 296.26 (B)

18.30.2 Providing flanged joints to fixing dismantling jointswith bolts, nuts and rubber insertion etc. each 20 195.70 3914.00 (C)

Total 30670.26Total without ED 27898.17

Add Water Charges @ 1% except on (A+B+C) 1% 224.28Add CPOH @ 15% except on (A+B+C) 15% 3397.83

Cost for 10 no's of dismantling joint 31520.28Cost for each dismantling joint 3152.03

Say 3152.00

1.1.1.2 125 mm nominal dia

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR)

REMARKS

Details of cost for 10 dismantling jointsMATERIAL:

Quotation_Volume III_pg no_2 Supplying Dismantling Joints Nos 10 3307.50 33075.00

Weight of dismantling Joints13.5 kg

10 NosSOR

2014_Andhra pradesh_pg no

81

Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work.

L.S. 5% 1653.75 (A)

18.24 Labour for laying dismantling Joints quintal 1.35 255.40 344.79 (B)

ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS

Providing and Fixing Mild Steel Dismantling Joints of pressure rating PN 1.6 with both side flange end suitable for installation in between flange end pipes. The rates are excluding excise duty component.

Delhi Jal Board 22 Schedule of Rates 2014 - 2015

Page 2: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR)

REMARKS

18.30.3Providing flanged joints to fixing dismantling jointswith bolts, nuts and rubber insertion etc.

each 20 198.00 3960.00 (C)

Total 39033.54Total without ED 35395.17

Add Water Charges @ 1% except on (A+B+C) 1% 294.37Add CPOH @ 15% except on (A+B+C) 15% 4459.65

Cost for 10 no's of dismantling joint 40149.19Cost for each dismantling joint 4014.92

Say 4014.90

1.1.1.3 150 mm nominal dia

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR)

REMARKS

Details of cost for 10 dismantling jointsMATERIAL:

Quotation_Volume III_pg no_3 Supplying Dismantling Joints Nos 10 4882.50 48825.00

Weight of dismantling Joints17.7 kg

10 NosSOR

2014_Andhra pradesh_pg no

81

Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work.

L.S. 5% 2441.25 (A)

18.24 Labour for laying dismantling Joints quintal 1.77 255.40 452.06 (B)

18.30.4Providing flanged joints to fixing dismantling jointswith bolts, nuts and rubber insertion etc.

each 20 234.55 4691.00 (C)

Total 56409.31Total without ED 51038.38

Add Water Charges @ 1% except on (A+B+C) 1% 434.54Add CPOH @ 15% except on (A+B+C) 15% 6583.29

Cost for 10 no's of dismantling joint 58056.22Cost for each dismantling joint 5805.62

Say 5805.60

1.1.1.4 200 mm nominal dia

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR)

REMARKS

Details of cost for 10 dismantling jointsMATERIAL:

Quotation_Volume III_pg no_3 Supplying Dismantling Joints Nos 10 6090.00 60900.00

Weight of dismantling Joints24.3 kg

10 NosSOR

2014_Andhra pradesh_pg no

81

Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work.

L.S. 5% 3045.00 (A)

Delhi Jal Board 23 Schedule of Rates 2014 - 2015

Page 3: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR)

REMARKS

18.24 Labour for laying dismantling Joints quintal 2.43 255.40 620.62 (B)

18.30.5Providing flanged joints to fixing dismantling jointswith bolts, nuts and rubber insertion etc.

each 20 240.35 4807.00 (C)

Total 69372.62Total without ED 62673.41

Add Water Charges @ 1% except on (A+B+C) 1% 542.01Add CPOH @ 15% except on (A+B+C) 15% 8211.42

Cost for 10 no's of dismantling joint 71426.83Cost for each dismantling joint 7142.68

Say 7142.70

1.1.1.5 250 mm nominal dia

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR)

REMARKS

Details of cost for 10 dismantling jointsMATERIAL:

Quotation_Volume III_pg no_3 Supplying Dismantling Joints Nos 10 8872.50 88725.00

Weight of dismantling Joints29.6 kg

10 NosSOR

2014_Andhra pradesh_pg no

81

Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work.

L.S. 5% 4436.25 (A)

18.24 Labour for laying dismantling Joints quintal 2.96 255.40 755.98 (B)

18.30.6Providing flanged joints to fixing dismantling jointswith bolts, nuts and rubber insertion etc.

each 20 359.00 7180.00 (C)

Total 101097.23Total without ED 91337.17

Add Water Charges @ 1% except on (A+B+C) 1% 789.65Add CPOH @ 15% except on (A+B+C) 15% 11963.19

Cost for 10 no's of dismantling joint 104090.01Cost for each dismantling joint 10409.00

Say 10409.00

1.1.1.6 300 mm nominal dia

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR)

REMARKS

Details of cost for 10 dismantling jointsMATERIAL:

Quotation_Volume III_pg no_3 Supplying Dismantling Joints Nos 10 10395.00 103950.00

Weight of dismantling Joints36.2 kg

10 Nos

Delhi Jal Board 24 Schedule of Rates 2014 - 2015

Page 4: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR)

REMARKS

SOR 2014_Andhra

pradesh_pg no 81

Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work.

L.S. 5% 5197.50 (A)

18.24 Labour for laying dismantling Joints quintal 3.62 255.40 924.55 (B)

18.30.7Providing flanged joints to fixing dismantling jointswith bolts, nuts and rubber insertion etc.

each 20 364.80 7296.00 (C)

Total 117368.05Total without ED 105933.18

Add Water Charges @ 1% except on (A+B+C) 1% 925.15Add CPOH @ 15% except on (A+B+C) 15% 14016.04

Cost for 10 no's of dismantling joint 120874.37Cost for each dismantling joint 12087.44

Say 12087.40

1.1.1.7 350 mm nominal dia

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR)

REMARKS

Details of cost for 10 dismantling jointsMATERIAL:

Quotation_Volume III_pg no_3 Supplying Dismantling Joints Nos 10 16380.00 163800.00

Weight of dismantling Joints57.7 kg

10 NosSOR

2014_Andhra pradesh_pg no

81

Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work.

L.S. 5% 8190.00 (A)

18.24 Labour for laying dismantling Joints quintal 5.77 255.40 1473.66 (B)

18.30.8Providing flanged joints to fixing dismantling jointswith bolts, nuts and rubber insertion etc.

each 20 499.45 9989.00 (C)

Total 183452.66Total without ED 165434.07

Add Water Charges @ 1% except on (A+B+C) 1% 1457.81Add CPOH @ 15% except on (A+B+C) 15% 22085.88

Cost for 10 no's of dismantling joint 188977.77Cost for each dismantling joint 18897.78

Say 18897.80

1.1.1.8 400 mm nominal dia

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR)

REMARKS

Details of cost for 10 dismantling jointsMATERIAL:

Quotation_Volume III_pg no_3 Supplying Dismantling Joints Nos 10 19635.00 196350.00

Delhi Jal Board 25 Schedule of Rates 2014 - 2015

Page 5: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR)

REMARKS

Weight of dismantling Joints68.9 kg

10 NosSOR

2014_Andhra pradesh_pg no

81

Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work.

L.S. 5% 9817.50 (A)

18.24 Labour for laying dismantling Joints quintal 6.89 255.40 1759.71 (B)

18.30.9Providing flanged joints to fixing dismantling jointswith bolts, nuts and rubber insertion etc.

each 20 712.55 14251.00 (C)

Total 222178.21Total without ED 200579.01

Add Water Charges @ 1% except on (A+B+C) 1% 1747.51Add CPOH @ 15% except on (A+B+C) 15% 26474.75

Cost for 10 no's of dismantling joint 228801.26Cost for each dismantling joint 22880.13

Say 22880.10

1.1.1.9 450 mm nominal dia

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR)

REMARKS

Details of cost for 10 dismantling jointsMATERIAL:

Quotation_Volume III_pg no_3 Supplying Dismantling Joints Nos 10 22680.00 226800.00

Weight of dismantling Joints87.2 kg

10 NosSOR

2014_Andhra pradesh_pg no

81

Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work.

L.S. 5% 11340.00 (A)

18.24 Labour for laying dismantling Joints quintal 8.72 255.40 2227.09 (B)

18.30.10Providing flanged joints to fixing dismantling jointswith bolts, nuts and rubber insertion etc.

each 20 882.05 17641.00 (C)

Total 258008.09Total without ED 233059.28

Add Water Charges @ 1% except on (A+B+C) 1% 2018.51Add CPOH @ 15% except on (A+B+C) 15% 30580.46

Cost for 10 no's of dismantling joint 265658.25Cost for each dismantling joint 26565.82

Say 26565.80

1.1.1.10 500 mm nominal dia

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR)

REMARKS

Details of cost for 10 dismantling jointsMATERIAL:

Delhi Jal Board 26 Schedule of Rates 2014 - 2015

Page 6: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR)

REMARKS

Quotation_Volume III_pg no_3 Supplying Dismantling Joints Nos 10 27195.00 271950.00

Weight of dismantling Joints97.1 kg

10 NosSOR

2014_Andhra pradesh_pg no

81

Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work.

L.S. 5% 13597.50 (A)

18.24 Labour for laying dismantling Joints quintal 9.71 255.40 2479.93 (B)

18.30.11Providing flanged joints to fixing dismantling jointswith bolts, nuts and rubber insertion etc.

each 20 1004.55 20091.00 (C)

Total 308118.43Total without ED 278202.97

Add Water Charges @ 1% except on (A+B+C) 1% 2420.35Add CPOH @ 15% except on (A+B+C) 15% 36668.23

Cost for 10 no's of dismantling joint 317291.54Cost for each dismantling joint 31729.15

Say 31729.20

1.1.1.11 600 mm nominal dia

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR)

REMARKS

Details of cost for 10 dismantling jointsMATERIAL:

Quotation_Volume III_pg no_3 Supplying Dismantling Joints Nos 10 35280.00 352800.00

Weight of dismantling Joints120.0 kg

10 NosSOR

2014_Andhra pradesh_pg no

81

Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work.

L.S. 5% 17640.00 (A)

18.24 Labour for laying dismantling Joints quintal 12.00 255.40 3064.80 (B)

18.30.12Providing flanged joints to fixing dismantling jointswith bolts, nuts and rubber insertion etc.

each 20 1178.95 23579.00 (C)

Total 397083.80Total without ED 358274.54

Add Water Charges @ 1% except on (A+B+C) 1% 3139.91Add CPOH @ 15% except on (A+B+C) 15% 47569.60

Cost for 10 no's of dismantling joint 408984.05Cost for each dismantling joint 40898.40

Say 40898.40

1.1.1.12 700 mm nominal dia

Delhi Jal Board 27 Schedule of Rates 2014 - 2015

Page 7: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR)

REMARKS

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR)

REMARKS

Details of cost for 10 dismantling jointsMATERIAL:

Quotation_Volume III_pg no_3 Supplying Dismantling Joints Nos 10 36435.00 364350.00

Weight of dismantling Joints146.0 kg

10 NosSOR

2014_Andhra pradesh_pg no

81

Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work.

L.S. 5% 18217.50 (A)

18.24 Labour for laying dismantling Joints quintal 14.60 255.40 3728.84 (B)

RA 2.7.1.1 Providing flanged joints to fixing dismantling jointswith bolts, nuts and rubber insertion etc. each 20 1249.70 24994.00 (C)

Total 411290.34Total without ED 371210.54

Add Water Charges @ 1% except on (A+B+C) 1% 3242.70Add CPOH @ 15% except on (A+B+C) 15% 49126.94

Cost for 10 no's of dismantling joint 423580.18Cost for each dismantling joint 42358.02

Say 42358.00

1.1.1.13 800 mm nominal dia

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR)

REMARKS

Details of cost for 10 dismantling jointsMATERIAL:

Quotation_Volume III_pg no_3 Supplying Dismantling Joints Nos 10 43890.00 438900.00

Weight of dismantling Joints167.0 kg

10 NosSOR

2014_Andhra pradesh_pg no

81

Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work.

L.S. 5% 21945.00 (A)

18.24 Labour for laying dismantling Joints quintal 16.70 255.40 4265.18 (B)

RA 2.7.1.3Providing flanged joints to fixing dismantling jointswith bolts, nuts and rubber insertion etc.

each 20 1593.80 31876.00 (C)

Total 496986.18Total without ED 448705.62

Add Water Charges @ 1% except on (A+B+C) 1% 3906.19Add CPOH @ 15% except on (A+B+C) 15% 59178.84

Cost for 10 no's of dismantling joint 511790.66Cost for each dismantling joint 51179.07

Delhi Jal Board 28 Schedule of Rates 2014 - 2015

Page 8: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR)

REMARKS

Say 51179.10

1.1.1.14 900 mm nominal dia

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR)

REMARKS

Details of cost for 10 dismantling jointsMATERIAL:

Quotation_Volume III_pg no_3 Supplying Dismantling Joints Nos 10 49245.00 492450.00

Weight of dismantling Joints211.0 kg

10 NosSOR

2014_Andhra pradesh_pg no

81

Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work.

L.S. 5% 24622.50 (A)

18.24 Labour for laying dismantling Joints quintal 21.10 255.40 5388.94 (B)

RA 2.7.1.4Providing flanged joints to fixing dismantling jointswith bolts, nuts and rubber insertion etc.

each 20 1837.90 36758.00 (C)

Total 559219.44Total without ED 505048.19

Add Water Charges @ 1% except on (A+B+C) 1% 4382.79Add CPOH @ 15% except on (A+B+C) 15% 66399.23

Cost for 10 no's of dismantling joint 575830.20Cost for each dismantling joint 57583.02

Say 57583.00

1.1.1.15 1000 mm nominal dia

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR)

REMARKS

Details of cost for 10 dismantling jointsMATERIAL:

Quotation_Volume III_pg no_3 Supplying Dismantling Joints Nos 10 67410.00 674100.00

Weight of dismantling Joints246.0 kg

10 NosSOR

2014_Andhra pradesh_pg no

81

Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work.

L.S. 5% 33705.00 (A)

18.24 Labour for laying dismantling Joints quintal 24.60 255.40 6282.84 (B)

RA 2.7.1.5Providing flanged joints to fixing dismantling jointswith bolts, nuts and rubber insertion etc.

each 20 2299.80 45996.00 (C)

Total 760083.84Total without ED 685930.44

Add Water Charges @ 1% except on (A+B+C) 1% 5999.47

Delhi Jal Board 29 Schedule of Rates 2014 - 2015

Page 9: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR)

REMARKS

Add CPOH @ 15% except on (A+B+C) 15% 90891.91Cost for 10 no's of dismantling joint 782821.82

Cost for each dismantling joint 78282.18Say 78282.20

1.1.1.16 1100 mm nominal dia

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR)

REMARKS

Details of cost for 10 dismantling jointsMATERIAL:

Quotation_Volume III_pg no_3 Supplying Dismantling Joints Nos 10 89040.00 890400.00

Weight of dismantling Joints276.0 kg

10 NosSOR

2014_Andhra pradesh_pg no

81

Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work.

L.S. 5% 44520.00 (A)

18.24 Labour for laying dismantling Joints quintal 27.60 255.40 7049.04 (B)

RA 2.7.1.7Providing flanged joints to fixing dismantling jointswith bolts, nuts and rubber insertion etc.

each 20 2745.10 54902.00 (C)

Total 996871.04Total without ED 898923.87

Add Water Charges @ 1% except on (A+B+C) 1% 7924.53Add CPOH @ 15% except on (A+B+C) 15% 120056.60

Cost for 10 no's of dismantling joint 1026905.00Cost for each dismantling joint 102690.50

Say 102690.50

1.1.1.17 1200 mm nominal dia

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR)

REMARKS

Details of cost for 10 dismantling jointsMATERIAL:

Quotation_Volume III_pg no_3 Supplying Dismantling Joints Nos 10 114345.00 1143450.00

Weight of dismantling Joints414.0 kg

10 NosSOR

2014_Andhra pradesh_pg no

81

Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work.

L.S. 5% 57172.50 (A)

18.24 Labour for laying dismantling Joints quintal 41.40 255.40 10573.56 (B)

RA 2.7.1.8Providing flanged joints to fixing dismantling jointswith bolts, nuts and rubber insertion etc.

each 20 3213.70 64274.00 (C)

Delhi Jal Board 30 Schedule of Rates 2014 - 2015

Page 10: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR)

REMARKS

Total 1275470.06Total without ED 1149686.49

Add Water Charges @ 1% except on (A+B+C) 1% 10176.66Add CPOH @ 15% except on (A+B+C) 15% 154176.46

Cost for 10 no's of dismantling joint 1314039.62Cost for each dismantling joint 131403.96

Say 131404.00

1.1.1.18 1400 mm nominal dia

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR)

REMARKS

Details of cost for 10 dismantling jointsMATERIAL:

Quotation_Volume III_pg no_3 Supplying Dismantling Joints Nos 10 134505.00 1345050.00

Weight of dismantling Joints509.0 kg

10 NosSOR

2014_Andhra pradesh_pg no

81

Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work.

L.S. 5% 67252.50 (A)

18.24 Labour for laying dismantling Joints quintal 50.90 255.40 12999.86 (B)

RA 2.7.1.9Providing flanged joints to fixing dismantling jointswith bolts, nuts and rubber insertion etc.

each 20 4134.90 82698.00 (C)

Total 1508000.36Total without ED 1360040.07

Add Water Charges @ 1% except on (A+B+C) 1% 11970.90Add CPOH @ 15% except on (A+B+C) 15% 181359.09

Cost for 10 no's of dismantling joint 1553370.06Cost for each dismantling joint 155337.01

Say 155337.00

1.1.1.19 1500 mm nominal dia

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR)

REMARKS

Details of cost for 10 dismantling jointsMATERIAL:

Quotation_Volume III_pg no_3 Supplying Dismantling Joints Nos 10 249900.00 2499000.00

Weight of dismantling Joints606.0 kg

10 NosSOR

2014_Andhra pradesh_pg no

81

Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work.

L.S. 5% 124950.00 (A)

18.24 Labour for laying dismantling Joints quintal 60.60 255.40 15477.24 (B)

Delhi Jal Board 31 Schedule of Rates 2014 - 2015

Page 11: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR)

REMARKS

RA 2.7.1.10Providing flanged joints to fixing dismantling jointswith bolts, nuts and rubber insertion etc.

each 20 4813.00 96260.00 (C)

Total 2735687.24Total without ED 2460788.34

Add Water Charges @ 1% except on (A+B+C) 1% 22241.01Add CPOH @ 15% except on (A+B+C) 15% 336951.32

Cost for 10 no's of dismantling joint 2819980.67Cost for each dismantling joint 281998.07

Say 281998.10

Delhi Jal Board 32 Schedule of Rates 2014 - 2015

Page 12: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

1.2 EXPANSION JOINTS (BELLOWS)1.2.1

1.2.1.1

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Details of cost for 10 expansion jointsMATERIAL:

Quotation_Volume III_pg no_7 Supplying Expansion Joints Nos 10 3871.77 38717.70

Weight of Expansion Joints6.00 kg

10 Nos

SOR 2014_Andhra pradesh_pg no 81

Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work. L.S. 5% 1935.89 (A)

18.24 Labour for laying Expansion Joints quintal 0.60 255.40 153.24 (B)

18.30.2 Providing flanged joints to fixing expansion joints with bolts,nuts and rubber insertion etc. each 20 195.70 3914.00 (C)

Total without ED 44720.83Add Water Charges @ 1% except on (A+B+C) 1% 387.18

Add CPOH @ 15% except on (A+B+C) 15% 5865.73Cost for 10 no's of dismantling joint 50973.73

Cost for each dismantling joint 5097.37Say 5097.40

1.2.1.2

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Details of cost for 10 expansion jointsMATERIAL:

Quotation_Volume III_pg no_7 Supplying Expansion Joints Nos 10 4304.37 43043.70

Weight of Expansion Joints8.00 kg

10 Nos

SOR 2014_Andhra pradesh_pg no 81

Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work. L.S. 5% 2152.19 (A)

18.24 Labour for laying Expansion Joints quintal 0.80 255.40 204.32 (B)

18.30.4 Providing flanged joints to fixing expansion joints with bolts,nuts and rubber insertion etc. each 20 234.55 4691.00 (C)

Total without ED 50091.21Add Water Charges @ 1% except on (A+B+C) 1% 430.44

Add CPOH @ 15% except on (A+B+C) 15% 6521.12Cost for 10 no's of dismantling joint 57042.76

Cost for each dismantling joint 5704.28Say 5704.30

1.2.1.3

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Details of cost for 10 expansion jointsMATERIAL:

Providing and Fixing Expansion Joints of pressure rating PN 1.6 with SA240 TP 304 bellows, SA240 TP 304inner protective sleeve, flange joints, IS 2062 Gr B fix flanges and lugs, etc including all cost of material, labourrequired, transportation upto site, loading, unloading & stacking, complete as per specifications or as directedby Engineer-In-Charge. The rates are excluding excise duty component.

Size : 100 mm

Size : 150 mm

Size : 200 mm

Delhi Jal Board 35 Schedule of Rates 2014 - 2015

Page 13: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Quotation_Volume III_pg no_7 Supplying Expansion Joints Nos 10 5494.02 54940.20

Weight of Expansion Joints12.00 kg

10 Nos

SOR 2014_Andhra pradesh_pg no 81

Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work. L.S. 5% 2747.01 (A)

18.24 Labour for laying Expansion Joints quintal 1.20 255.40 306.48 (B)

18.30.5 Providing flanged joints to fixing expansion joints with bolts,nuts and rubber insertion etc. each 20 240.35 4807.00 (C)

Total without ED 62800.69Add Water Charges @ 1% except on (A+B+C) 1% 549.40

Add CPOH @ 15% except on (A+B+C) 15% 8323.44Cost for 10 no's of dismantling joint 71673.53

Cost for each dismantling joint 7167.35Say 7167.40

1.2.1.4

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Details of cost for 10 expansion jointsMATERIAL:

Quotation_Volume III_pg no_7 Supplying Expansion Joints Nos 10 7008.12 70081.20

Weight of Expansion Joints15.00 kg

10 Nos

SOR 2014_Andhra pradesh_pg no 81

Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work. L.S. 5% 3504.06 (A)

18.24 Labour for laying Expansion Joints quintal 1.50 255.40 383.10 (B)

18.30.6 Providing flanged joints to fixing expansion joints with bolts,nuts and rubber insertion etc. each 20 359.00 7180.00 (C)

Total without ED 81148.36Add Water Charges @ 1% except on (A+B+C) 1% 700.81

Add CPOH @ 15% except on (A+B+C) 15% 10617.30Cost for 10 no's of dismantling joint 92466.47

Cost for each dismantling joint 9246.65Say 9246.60

1.2.1.5

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Details of cost for 10 expansion jointsMATERIAL:

Quotation_Volume III_pg no_7 Supplying Expansion Joints Nos 10 10685.22 106852.20

Weight of Expansion Joints21.00 kg

10 Nos

SOR 2014_Andhra pradesh_pg no 81

Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work. L.S. 5% 5342.61 (A)

18.24 Labour for laying Expansion Joints quintal 2.10 255.40 536.34 (B)

Size : 300 mm

Size : 250 mm

Delhi Jal Board 36 Schedule of Rates 2014 - 2015

Page 14: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

18.30.7 Providing flanged joints to fixing expansion joints with bolts,nuts and rubber insertion etc. each 20 364.80 7296.00 (C)

Total without ED 120027.15Add Water Charges @ 1% except on (A+B+C) 1% 1068.52

Add CPOH @ 15% except on (A+B+C) 15% 16188.11Cost for 10 no's of dismantling joint 137283.78

Cost for each dismantling joint 13728.38Say 13728.40

1.2.1.6

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Details of cost for 10 expansion jointsMATERIAL:

Quotation_Volume III_pg no_7 Supplying Expansion Joints Nos 10 11766.72 117667.20

Weight of Expansion Joints26.00 kg

10 Nos

SOR 2014_Andhra pradesh_pg no 81

Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work. L.S. 5% 5883.36 (A)

18.24 Labour for laying Expansion Joints quintal 2.60 255.40 664.04 (B)

18.30.8 Providing flanged joints to fixing expansion joints with bolts,nuts and rubber insertion etc. each 20 499.45 9989.00 (C)

Total without ED 134203.60Add Water Charges @ 1% except on (A+B+C) 1% 1176.67

Add CPOH @ 15% except on (A+B+C) 15% 17826.58Cost for 10 no's of dismantling joint 153206.85

Cost for each dismantling joint 15320.69Say 15320.70

1.2.1.7

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Details of cost for 10 expansion jointsMATERIAL:

Quotation_Volume III_pg no_7 Supplying Expansion Joints Nos 10 15443.82 154438.20

Weight of Expansion Joints31.00 kg

10 Nos

SOR 2014_Andhra pradesh_pg no 81

Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work. L.S. 5% 7721.91 (A)

18.24 Labour for laying Expansion Joints quintal 3.10 255.40 791.74 (B)

18.30.9 Providing flanged joints to fixing expansion joints with bolts,nuts and rubber insertion etc. each 20 712.55 14251.00 (C)

Total without ED 177202.85Add Water Charges @ 1% except on (A+B+C) 1% 1544.38

Add CPOH @ 15% except on (A+B+C) 15% 23397.39Cost for 10 no's of dismantling joint 202144.62

Cost for each dismantling joint 20214.46Say 20214.50

1.2.1.8

Size : 350 mm

Size : 400 mm

Size : 450 mm

Delhi Jal Board 37 Schedule of Rates 2014 - 2015

Page 15: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Details of cost for 10 expansion jointsMATERIAL:

Quotation_Volume III_pg no_7 Supplying Expansion Joints Nos 10 19986.12 199861.20

Weight of Expansion Joints32.00 kg

10 Nos

SOR 2014_Andhra pradesh_pg no 81

Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work. L.S. 5% 9993.06 (A)

18.24 Labour for laying Expansion Joints quintal 3.20 255.40 817.28 (B)

18.30.10 Providing flanged joints to fixing expansion joints with bolts,nuts and rubber insertion etc. each 20 882.05 17641.00 (C)

Total without ED 228312.54Add Water Charges @ 1% except on (A+B+C) 1% 1998.61

Add CPOH @ 15% except on (A+B+C) 15% 30278.97Cost for 10 no's of dismantling joint 260590.12

Cost for each dismantling joint 26059.01Say 26059.00

1.2.1.9

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Details of cost for 10 expansion jointsMATERIAL:

Quotation_Volume III_pg no_7 Supplying Expansion Joints Nos 10 27145.65 271456.50

Weight of Expansion Joints36.00 kg

10 Nos

SOR 2014_Andhra pradesh_pg no 81

Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work. L.S. 5% 13572.83 (A)

18.24 Labour for laying Expansion Joints quintal 3.60 255.40 919.44 (B)

18.30.11 Providing flanged joints to fixing expansion joints with bolts,nuts and rubber insertion etc. each 20 1004.55 20091.00 (C)

Total without ED 306039.77Add Water Charges @ 1% except on (A+B+C) 1% 2714.57

Add CPOH @ 15% except on (A+B+C) 15% 41125.66Cost for 10 no's of dismantling joint 349879.99

Cost for each dismantling joint 34988.00Say 34988.00

1.2.1.10

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Details of cost for 10 expansion jointsMATERIAL:

Quotation_Volume III_pg no_7 Supplying Expansion Joints Nos 10 34802.67 348026.70

Weight of Expansion Joints67.00 kg

10 Nos

Size : 500 mm

Size : 600 mm

Delhi Jal Board 38 Schedule of Rates 2014 - 2015

Page 16: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

SOR 2014_Andhra pradesh_pg no 81

Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work. L.S. 5% 17401.34 (A)

18.24 Labour for laying Expansion Joints quintal 6.70 255.40 1711.18 (B)

18.30.12 Providing flanged joints to fixing expansion joints with bolts,nuts and rubber insertion etc. each 20 1178.95 23579.00 (C)

Total without ED 390718.22Add Water Charges @ 1% except on (A+B+C) 1% 3480.27

Add CPOH @ 15% except on (A+B+C) 15% 52726.05Cost for 10 no's of dismantling joint 446924.53

Cost for each dismantling joint 44692.45Say 44692.50

1.2.1.11

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Details of cost for 10 expansion jointsMATERIAL:

Quotation_Volume III_pg no_7 Supplying Expansion Joints Nos 10 39344.97 393449.70

Weight of Expansion Joints81.00 kg

10 Nos

SOR 2014_Andhra pradesh_pg no 81

Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work. L.S. 5% 19672.49 (A)

18.24 Labour for laying Expansion Joints quintal 8.10 255.40 2068.74 (B)

RA 2.7.1.1 Providing flanged joints to fixing expansion joints with bolts,nuts and rubber insertion etc. each 20 1249.70 24994.00 (C)

Total without ED 440184.93Add Water Charges @ 1% except on (A+B+C) 1% 3934.50

Add CPOH @ 15% except on (A+B+C) 15% 59607.63Cost for 10 no's of dismantling joint 503727.05

Cost for each dismantling joint 50372.71Say 50372.70

1.2.1.12

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Details of cost for 10 expansion jointsMATERIAL:

Quotation_Volume III_pg no_7 Supplying Expansion Joints Nos 10 41507.97 415079.70

Weight of Expansion Joints89.00 kg

10 Nos

SOR 2014_Andhra pradesh_pg no 81

Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work. L.S. 5% 20753.99 (A)

18.24 Labour for laying Expansion Joints quintal 8.90 255.40 2273.06 (B)

RA 2.7.1.2 Providing flanged joints to fixing expansion joints with bolts,nuts and rubber insertion etc. each 20 1271.10 25422.00 (C)

Total without ED 463528.75Add Water Charges @ 1% except on (A+B+C) 1% 4150.80

Add CPOH @ 15% except on (A+B+C) 15% 62884.57Cost for 10 no's of dismantling joint 530564.12

Size : 750 mm

Size : 700 mm

Delhi Jal Board 39 Schedule of Rates 2014 - 2015

Page 17: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Cost for each dismantling joint 53056.41Say 53056.40

1.2.1.13

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Details of cost for 10 expansion jointsMATERIAL:

Quotation_Volume III_pg no_7 Supplying Expansion Joints Nos 10 44211.72 442117.20

Weight of Expansion Joints105.00 kg

10 Nos

SOR 2014_Andhra pradesh_pg no 81

Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work. L.S. 5% 22105.86 (A)

18.24 Labour for laying Expansion Joints quintal 10.50 255.40 2681.70 (B)

RA 2.7.1.3 Providing flanged joints to fixing expansion joints with bolts,nuts and rubber insertion etc. each 20 1593.80 31876.00 (C)

Total without ED 498780.76Add Water Charges @ 1% except on (A+B+C) 1% 4421.17

Add CPOH @ 15% except on (A+B+C) 15% 66980.76Cost for 10 no's of dismantling joint 570182.69

Cost for each dismantling joint 57018.27Say 57018.30

1.2.1.14

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Details of cost for 10 expansion jointsMATERIAL:

Quotation_Volume III_pg no_7 Supplying Expansion Joints Nos 10 50376.27 503762.70

Weight of Expansion Joints120.00 kg

10 Nos

SOR 2014_Andhra pradesh_pg no 81

Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work. L.S. 5% 25188.14 (A)

18.24 Labour for laying Expansion Joints quintal 12.00 255.40 3064.80 (B)

RA 2.7.1.4 Providing flanged joints to fixing expansion joints with bolts,nuts and rubber insertion etc. each 20 1837.90 36758.00 (C)

Total without ED 568773.64Add Water Charges @ 1% except on (A+B+C) 1% 5037.63

Add CPOH @ 15% except on (A+B+C) 15% 76320.05Cost for 10 no's of dismantling joint 650131.31

Cost for each dismantling joint 65013.13Say 65013.10

1.2.1.15

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Details of cost for 10 expansion jointsMATERIAL:

Quotation_Volume III_pg no_7 Supplying Expansion Joints Nos 10 58487.52 584875.20

Size : 900 mm

Size : 800 mm

Size : 1000 mm

Delhi Jal Board 40 Schedule of Rates 2014 - 2015

Page 18: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Weight of Expansion Joints135.00 kg

10 Nos

SOR 2014_Andhra pradesh_pg no 81

Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work. L.S. 5% 29243.76 (A)

18.24 Labour for laying Expansion Joints quintal 13.50 255.40 3447.90 (B)

RA 2.7.1.5 Providing flanged joints to fixing expansion joints with bolts,nuts and rubber insertion etc. each 20 2299.80 45996.00 (C)

Total without ED 663562.86Add Water Charges @ 1% except on (A+B+C) 1% 5848.75

Add CPOH @ 15% except on (A+B+C) 15% 88608.59Cost for 10 no's of dismantling joint 758020.20

Cost for each dismantling joint 75802.02Say 75802.00

1.2.1.16

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Details of cost for 10 expansion jointsMATERIAL:

Quotation_Volume III_pg no_7 Supplying Expansion Joints Nos 10 67031.37 670313.70

Weight of Expansion Joints150.00 kg

10 Nos

SOR 2014_Andhra pradesh_pg no 81

Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work. L.S. 5% 33515.69 (A)

18.24 Labour for laying Expansion Joints quintal 15.00 255.40 3831.00 (B)

RA 2.7.1.7 Providing flanged joints to fixing expansion joints with bolts,nuts and rubber insertion etc. each 20 2745.10 54902.00 (C)

Total without ED 762562.39Add Water Charges @ 1% except on (A+B+C) 1% 6703.14

Add CPOH @ 15% except on (A+B+C) 15% 101552.53Cost for 10 no's of dismantling joint 870818.05

Cost for each dismantling joint 87081.80Say 87081.80

1.2.1.17

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Details of cost for 10 expansion jointsMATERIAL:

Quotation_Volume III_pg no_7 Supplying Expansion Joints Nos 10 83578.32 835783.20

Weight of Expansion Joints165.00 kg

10 Nos

Size : 1100 mm

Size : 1200 mm

Delhi Jal Board 41 Schedule of Rates 2014 - 2015

Page 19: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

SOR 2014_Andhra pradesh_pg no 81

Conveyance of joints and accessories including loading at factory and unloading, stacking at site of work. L.S. 5% 41789.16 (A)

18.24 Labour for laying Expansion Joints quintal 16.50 255.40 4214.10 (B)

RA 2.7.1.8 Providing flanged joints to fixing expansion joints with bolts,nuts and rubber insertion etc. each 20 3213.70 64274.00 (C)

Total without ED 946060.46Add Water Charges @ 1% except on (A+B+C) 1% 8357.83

Add CPOH @ 15% except on (A+B+C) 15% 126621.15Cost for 10 no's of dismantling joint 1081039.45

Cost for each dismantling joint 108103.94Say 108103.90

Delhi Jal Board 42 Schedule of Rates 2014 - 2015

Page 20: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

2.0 PIPES AND SPECIALS2.1 GALVANIZED IRON (G.I.) PIPES (LIGHT)

2.1.1

2.1.1.1 100 mm dia

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Details of cost for 10 metreMATERIAL:

Quotation_Volume III_pg no_48 GI pipe of 100mm dia Rm 10 506.55 5065.50

Weight of pipe kg/mtr 10.06

DSR 2014_18.12 Weight for carriage of 10 mtr pipe = pipe weight + 2% for fiitings 2%

=10.06*1.02*10=102.612 kg kg 102.612

Refer Rate Analysis_Volume

II_Carriage Code_pg no 16

Carriage of pipe tonne 0.10261 150.29 15.42

Nabhi's text book_item no

23.1.2_pg no 1253Add for White lead, hemp, oil, cement, sand and grit, etc L.S. 56.92 1.78 101.31

LABOUR:0116 Fitter grade 1 day 0.34 435.00 147.900114 Beldar day 0.99 329.00 325.71

Trenching and refilling etc0114 Beldar day 0.66 329.00 217.140115 Coolie day 0.66 329.00 217.14

Total without excise duty 6090.13Add Water Charges @ 1% 60.90

Add CPOH @ 15% 922.65Cost of 10 metre 7073.68Cost of 1 metre 707.37

Say 707.40

2.2 GALVANIZED IRON (GI) PIPES (MEDIUM)2.2.1

2.2.1.1 100 mm dia

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Details of cost for 10 metreMATERIAL:

Quotation_Volume III_pg no_48 GI pipe of 100mm dia Rm 10 582.81 5828.05

Weight of pipe kg/mtr 12.50

DSR 2014_18.12 Weight for carriage of 10 mtr pipe = pipe weight + 2% for fiitings 2%

=12.5*1.02*10=127.5 kg kg 127.500

Refer Rate Analysis_Volume

II_Carriage Code_pg no 16

Carriage of pipe tonne 0.12750 150.29 19.16

Providing and fixing G.I. Pipes (light) complete with G.I. fittings for external works including trenching andrefilling complete in all respect as directed by Engineer-in-charge. The rates are excluding Excise duty.

Providing and fixing G.I. Pipes (medium) complete with G.I. fittings for external works including trenching andrefilling complete in all respect as directed by Engineer-in-charge. The rates are excluding Excise duty.

For detail calculations please refer

soft copy

For detail

Delhi Jal Board 45 Schedule of Rates 2014 -2015

Page 21: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Nabhi's text book_item no

23.1.2_pg no 1253Add for White lead, hemp, oil, cement, sand and grit, etc L.S. 65.48 1.78 116.56

LABOUR:0116 Fitter grade 1 day 0.34 435.00 147.900114 Beldar day 0.99 329.00 325.71

Trenching and refilling etc0114 Beldar day 0.66 329.00 217.140115 Coolie day 0.66 329.00 217.14

Total without excise duty 6871.67Add Water Charges @ 1% 68.72

Add CPOH @ 15% 1041.06Cost of 10 metre 7981.44Cost of 1 metre 798.14

Say 798.10

2.2.1.2 150 mm dia

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Details of cost for 10 metreMATERIAL:

Quotation_Volume III_pg no_48 GI pipe of 100mm dia Rm 10 942.29 9422.93

Weight of pipe kg/mtr 19.50

DSR 2014_18.12 Weight for carriage of 10 mtr pipe = pipe weight + 2% for fiitings 2%

=19.5*1.02*10=198.9 kg kg 198.900

Refer Rate Analysis_Volume

II_Carriage Code_pg no 16

Carriage of pipe tonne 0.19890 205.93 40.96

Nabhi's text book_item no

23.1.2_pg no 1253Add for White lead, hemp, oil, cement, sand and grit, etc L.S. 105.88 1.78 188.46

LABOUR:0116 Fitter grade 1 day 0.43 435.00 187.050114 Beldar day 1.32 329.00 434.28

Trenching and refilling etc0114 Beldar day 0.66 329.00 217.140115 Coolie day 0.66 329.00 217.14

Total without excise duty 10707.95Add Water Charges @ 1% 107.08

Add CPOH @ 15% 1622.25Cost of 10 metre 12437.29Cost of 1 metre 1243.73

Say 1243.70

2.3 GALVANIZED IRON (GI) PIPES (HEAVY)2.3.1

2.3.1.1 100 mm dia

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Details of cost for 10 metreMATERIAL:

Quotation_Volume III_pg no_48 GI pipe of 100mm dia Rm 10 700.82 7008.19

Providing and fixing G.I. Pipes (heavy) complete with G.I. fittings for external works including trenching andrefilling complete in all respect as directed by Engineer-in-charge. The rates are excluding Excise duty.

For detail calculations please refer

soft copy

For detail calculations please refer

soft copy

Delhi Jal Board 46 Schedule of Rates 2014 -2015

Page 22: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Weight of pipe kg/mtr 14.80

DSR 2014_18.12 Weight for carriage of 10 mtr pipe = pipe weight + 2% for fiitings 2%

=14.8*1.02*10=150.96 kg kg 150.960

Refer Rate Analysis_Volume

II_Carriage Code_pg no 16

Carriage of pipe tonne 0.15096 150.29 22.69

Nabhi's text book_item no

23.1.2_pg no 1253Add for White lead, hemp, oil, cement, sand and grit, etc L.S. 78.74 1.78 140.16

LABOUR:0116 Fitter grade 1 day 0.34 435 147.900114 Beldar day 0.99 329 325.71

Trenching and refilling etc0114 Beldar day 0.66 329 217.140115 Coolie day 0.66 329 217.14

Total without excise duty 8078.93Add Water Charges @ 1% 80.79

Add CPOH @ 15% 1223.96Cost of 10 metre 9383.68Cost of 1 metre 938.37

Say 938.40

2.3.1.2 150 mm dia

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Details of cost for 10 metreMATERIAL:

Quotation_Volume III_pg no_48 GI pipe of 100mm dia Rm 10 1059.40 10593.98

Weight of pipe kg/mtr 21.90

DSR 2014_18.12 Weight for carriage of 10 mtr pipe = pipe weight + 2% for fiitings 2%

=21.9*1.02*10=223.38 kg kg 223.380

Refer Rate Analysis_Volume

II_Carriage Code_pg no 16

Carriage of pipe tonne 0.22338 205.93 46.00

Nabhi's text book_item no

23.1.2_pg no 1253Add for White lead, hemp, oil, cement, sand and grit, etc L.S. 119.03 1.78 211.88

LABOUR:0116 Fitter grade 1 day 0.43 435 187.050114 Beldar day 1.32 329 434.28

Trenching and refilling etc 0.000114 Beldar day 0.66 329 217.140115 Coolie day 0.66 329 217.14

Total without excise duty 11907.47Add Water Charges @ 1% 119.07

Add CPOH @ 15% 1803.98Cost of 10 metre 13830.53Cost of 1 metre 1383.05

Say 1383.10

For detail calculations please refer

soft copy

For detail calculations please refer

soft copy

Delhi Jal Board 47 Schedule of Rates 2014 -2015

Page 23: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

2.5 MILD STEEL PIPE COATING2.5.1

2.5.1.1

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.172 0.005

thickness of CML (t2) =

Length of pipe =

0.006 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.172-0.005)*0.005*1*7850= kg 20.592Add 5 % wastage

5% kg 1.030Total Weight kg 21.622

#REF! Cost of MS plate kg 21.622 45.00 972.99 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 20.592 6.63 136.53 (B)

Quotation_Volume III_pg no_272 Cost of scrap kg 1.030 27.00 27.80

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 289.78 2.90 (C)

Material cost per meter Rs/meter 1084.61

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.172-(0.005*2+0.006))*0.006*1*2080= kg 6.12

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.172*1= sqmt 0.540 100.33 54.21 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.172-(0.005*2+0.006))*1= sqmt 0.490 450.00 220.54 (E)

Total (A+B+C+D+E) 1359.37Total without ED 1210.15

Add Water Charges @ 1% 1% 12.10Add CPOH @ 15% 15% 183.34

Total cost per meter for pipe 1405.59Total cost per kg for specials 52.63

Providing Mild Steel Pipes / specials fabricated / manufactured out of MS plate of steel grade Fe410 as per IS 3589:2001; internally linedwith cement mortar lining and external / outside epoxy coating; minimum thickness of M.S. Plate as specified; complete in all respect;with upto date amendments in relevant IS codes and as directed by Engineer-in-charge. The rates are excluding excise duty component.150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 104 Schedule of Rates 2014 - 2015

Page 24: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outside2.5.1.2

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.222 0.005

thickness of CML (t2) =

Length of pipe =

0.006 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.222-0.005)*0.005*1*7850= kg 26.758Add 5 % wastage

5% kg 1.338Total Weight kg 28.096

#REF! Cost of MS plate kg 28.096 45.00 1264.30 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 26.758 6.63 177.40 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.338 27.00 36.12

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 471.38 4.71 (C)

Material cost per meter Rs/meter 1410.30

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.222-(0.005*2+0.006))*0.006*1*2080= kg 8.08

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.222*1= sqmt 0.697 100.33 69.97 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.222-(0.005*2+0.006))*1= sqmt 0.647 450.00 291.23 (E)

Total (A+B+C+D+E) 1771.50Total without ED 1577.14

Add Water Charges @ 1% 1% 15.77Add CPOH @ 15% 15% 238.94

Total cost per meter for pipe 1831.85Total cost per kg for specials 52.59

2.5.1.3

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.224 0.006

thickness of CML (t2) =

Length of pipe =

0.006 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.224-0.006)*0.006*1*7850= kg 32.257Add 5 % wastage

5% kg 1.613Total Weight kg 33.870

#REF! Cost of MS plate kg 33.870 45.00 1524.15 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 32.257 6.63 213.87 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.613 27.00 43.55

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 471.38 4.71 (C)

Material cost per meter Rs/meter 1699.19

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.224-(0.006*2+0.006))*0.006*1*2080= kg 8.08

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.224*1= sqmt 0.704 100.33 70.60 (D)

200 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsideepoxy coating

200 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 105 Schedule of Rates 2014 - 2015

Page 25: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsideQuotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.224-(0.006*2+0.006))*1= sqmt 0.647 450.00 291.23 (E)

Total (A+B+C+D+E) 2061.02Total without ED 1834.82

Add Water Charges @ 1% 1% 18.35Add CPOH @ 15% 15% 277.97

Total cost per meter for pipe 2131.14Total cost per kg for specials 52.84

2.5.1.4

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.2246 0.0063

thickness of CML (t2) =

Length of pipe =

0.006 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.2246-0.0063)*0.0063*1*7850= kg 33.917Add 5 % wastage

5% kg 1.696Total Weight kg 35.613

#REF! Cost of MS plate kg 35.613 45.00 1602.56 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 33.917 6.63 224.87 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.696 27.00 45.79

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 471.38 4.71 (C)

Material cost per meter Rs/meter 1786.36

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.2246-(0.0063*2+0.006))*0.006*1*2080= kg 8.08

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.2246*1= sqmt 0.706 100.33 70.79 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.2246-(0.0063*2+0.006))*1= sqmt 0.647 450.00 291.23 (E)

Total (A+B+C+D+E) 2148.38Total without ED 1912.57

Add Water Charges @ 1% 1% 19.13Add CPOH @ 15% 15% 289.75

Total cost per meter for pipe 2221.45Total cost per kg for specials 52.90

2.5.1.5

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.272 0.005

thickness of CML (t2) =

Length of pipe =

0.006 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.272-0.005)*0.005*1*7850= kg 32.923Add 5 % wastage

5% kg 1.646Total Weight kg 34.569

#REF! Cost of MS plate kg 34.569 45.00 1555.62 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 32.923 6.63 218.28 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.646 27.00 44.45

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 669.85 6.70 (C)

Material cost per meter Rs/meter 1736.15

250 mm nominal dia (clear internal dia) of pipe with 5.0 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsideepoxy coating

200 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 106 Schedule of Rates 2014 - 2015

Page 26: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outside

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.272-(0.005*2+0.006))*0.006*1*2080= kg 10.04

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.272*1= sqmt 0.855 100.33 85.73 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.272-(0.005*2+0.006))*1= sqmt 0.804 450.00 361.91 (E)

Total (A+B+C+D+E) 2183.79Total without ED 1944.31

Add Water Charges @ 1% 1% 19.44Add CPOH @ 15% 15% 294.56

Total cost per meter for pipe 2258.31Total cost per kg for specials 52.57

2.5.1.6

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.274 0.006

thickness of CML (t2) =

Length of pipe =

0.006 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.274-0.006)*0.006*1*7850= kg 39.656Add 5 % wastage

5% kg 1.983Total Weight kg 41.638

#REF! Cost of MS plate kg 41.638 45.00 1873.73 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 39.656 6.63 262.92 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.983 27.00 53.54

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 669.85 6.70 (C)

Material cost per meter Rs/meter 2089.81

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.274-(0.006*2+0.006))*0.006*1*2080= kg 10.04

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.274*1= sqmt 0.861 100.33 86.36 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.274-(0.006*2+0.006))*1= sqmt 0.804 450.00 361.91 (E)

Total (A+B+C+D+E) 2538.09Total without ED 2259.62

Add Water Charges @ 1% 1% 22.60Add CPOH @ 15% 15% 342.33

Total cost per meter for pipe 2624.55Total cost per kg for specials 52.82

2.5.1.7

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.2746 0.0063

thickness of CML (t2) =

Length of pipe =

0.006 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.2746-0.0063)*0.0063*1*7850= kg 41.685Add 5 % wastage

5% kg 2.084

250 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsideepoxy coating

250 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 107 Schedule of Rates 2014 - 2015

Page 27: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsideTotal Weight kg 43.769

#REF! Cost of MS plate kg 43.769 45.00 1969.62 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 41.685 6.63 276.37 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.084 27.00 56.27

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 669.85 6.70 (C)

Material cost per meter Rs/meter 2196.42

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.2746-(0.0063*2+0.006))*0.006*1*2080= kg 10.04

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.2746*1= sqmt 0.863 100.33 86.55 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.2746-(0.0063*2+0.006))*1= sqmt 0.804 450.00 361.91 (E)

Total (A+B+C+D+E) 2644.88Total without ED 2354.67

Add Water Charges @ 1% 1% 23.55Add CPOH @ 15% 15% 356.73

Total cost per meter for pipe 2734.95Total cost per kg for specials 52.88

2.5.1.8

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.322 0.005

thickness of CML (t2) =

Length of pipe =

0.006 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.322-0.005)*0.005*1*7850= kg 39.088Add 5 % wastage

5% kg 1.954Total Weight kg 41.043

#REF! Cost of MS plate kg 41.043 45.00 1846.93 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 39.088 6.63 259.16 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.954 27.00 52.77

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 827.95 8.28 (C)

Material cost per meter Rs/meter 2061.60

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.322-(0.005*2+0.006))*0.006*1*2080= kg 12.00

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.322*1= sqmt 1.012 100.33 101.49 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.322-(0.005*2+0.006))*1= sqmt 0.961 450.00 432.60 (E)

Total (A+B+C+D+E) 2595.69Total without ED 2311.06

Add Water Charges @ 1% 1% 23.11Add CPOH @ 15% 15% 350.13

Total cost per meter for pipe 2684.30Total cost per kg for specials 52.54

2.5.1.9

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

300 mm nominal dia (clear internal dia) of pipe with 5.6 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsideepoxy coating

300 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 108 Schedule of Rates 2014 - 2015

Page 28: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsideDetail for 1 meter Outer dia (d) =

thickness of pipe (t1) =

0.3232 0.0056thickness of

CML (t2) =Length of pipe

=0.006 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.3232-0.0056)*0.0056*1*7850= kg 43.862Add 5 % wastage

5% kg 2.193Total Weight kg 46.055

#REF! Cost of MS plate kg 46.055 45.00 2072.48 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 43.862 6.63 290.80 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.193 27.00 59.21

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 827.95 8.28 (C)

Material cost per meter Rs/meter 2312.35

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.3232-(0.0056*2+0.006))*0.006*1*2080= kg 12.00

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.3232*1= sqmt 1.015 100.33 101.87 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.3232-(0.0056*2+0.006))*1= sqmt 0.961 450.00 432.60 (E)

Total (A+B+C+D+E) 2846.82Total without ED 2534.57

Add Water Charges @ 1% 1% 25.35Add CPOH @ 15% 15% 383.99

Total cost per meter for pipe 2943.90Total cost per kg for specials 52.70

2.5.1.10

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.3262 0.0071

thickness of CML (t2) =

Length of pipe =

0.006 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.3262-0.0071)*0.0071*1*7850= kg 55.873Add 5 % wastage

5% kg 2.794Total Weight kg 58.667

#REF! Cost of MS plate kg 58.667 45.00 2640.02 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 55.873 6.63 370.44 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.794 27.00 75.43

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 827.95 8.28 (C)

Material cost per meter Rs/meter 2943.31

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.3262-(0.0071*2+0.006))*0.006*1*2080= kg 12.00

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.3262*1= sqmt 1.025 100.33 102.82 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.3262-(0.0071*2+0.006))*1= sqmt 0.961 450.00 432.60 (E)

Total (A+B+C+D+E) 3478.72

300 mm nominal dia (clear internal dia) of pipe with 7.1 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 109 Schedule of Rates 2014 - 2015

Page 29: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsideTotal without ED 3096.96Add Water Charges @ 1% 1% 30.97

Add CPOH @ 15% 15% 469.19Total cost per meter for pipe 3597.12

Total cost per kg for specials 53.00

2.5.1.11

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.374 0.005

thickness of CML (t2) =

Length of pipe =

0.007 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.374-0.005)*0.005*1*7850= kg 45.500Add 5 % wastage

5% kg 2.275Total Weight kg 47.775

#REF! Cost of MS plate kg 47.775 45.00 2149.90 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 45.500 6.63 301.67 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.275 27.00 61.43

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 1159.12 11.59 (C)

Material cost per meter Rs/meter 2401.73

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.374-(0.005*2+0.007))*0.007*1*2080= kg 16.33

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.374*1= sqmt 1.175 100.33 117.88 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.374-(0.005*2+0.007))*1= sqmt 1.122 450.00 504.70 (E)

Total (A+B+C+D+E) 3024.31Total without ED 2692.90

Add Water Charges @ 1% 1% 26.93Add CPOH @ 15% 15% 407.97

Total cost per meter for pipe 3127.80Total cost per kg for specials 50.59

2.5.1.12

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.3752 0.0056

thickness of CML (t2) =

Length of pipe =

0.007 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.3752-0.0056)*0.0056*1*7850= kg 51.043Add 5 % wastage

5% kg 2.552Total Weight kg 53.596

#REF! Cost of MS plate kg 53.596 45.00 2411.80 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 51.043 6.63 338.42 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.552 27.00 68.91

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 1159.12 11.59 (C)

Material cost per meter Rs/meter 2692.90

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.3752-(0.0056*2+0.007))*0.007*1*2080= kg 16.33

350 mm nominal dia (clear internal dia) of pipe with 5.0 mm thick plate, 7 mm thick internal cement mortar lining and exterior / outsideepoxy coating

350 mm nominal dia (clear internal dia) of pipe with 5.6 mm thick plate, 7 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 110 Schedule of Rates 2014 - 2015

Page 30: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsideOutside epoxy coating

13.52.1 Area of coating = pi()*d*L(3.14159265358979)*0.3752*1= sqmt 1.179 100.33 118.26 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.3752-(0.0056*2+0.007))*1= sqmt 1.122 450.00 504.70 (E)

Total (A+B+C+D+E) 3315.86Total without ED 2952.38

Add Water Charges @ 1% 1% 29.52Add CPOH @ 15% 15% 447.29

Total cost per meter for pipe 3429.19Total cost per kg for specials 50.90

2.5.1.13

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.38 0.008

thickness of CML (t2) =

Length of pipe =

0.007 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.38-0.008)*0.008*1*7850= kg 73.393Add 5 % wastage

5% kg 3.670Total Weight kg 77.062

#REF! Cost of MS plate kg 77.062 45.00 3467.80 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 73.393 6.63 486.59 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.670 27.00 99.08

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 1159.12 11.59 (C)

Material cost per meter Rs/meter 3866.91

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.38-(0.008*2+0.007))*0.007*1*2080= kg 16.33

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.38*1= sqmt 1.194 100.33 119.77 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.38-(0.008*2+0.007))*1= sqmt 1.122 450.00 504.70 (E)

Total (A+B+C+D+E) 4491.38Total without ED 3998.58

Add Water Charges @ 1% 1% 39.99Add CPOH @ 15% 15% 605.79

Total cost per meter for pipe 4644.36Total cost per kg for specials 51.76

2.5.1.14

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.424 0.005

thickness of CML (t2) =

Length of pipe =

0.007 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.424-0.005)*0.005*1*7850= kg 51.666Add 5 % wastage

5% kg 2.583Total Weight kg 54.249

#REF! Cost of MS plate kg 54.249 45.00 2441.21 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 51.666 6.63 342.54 (B)

350 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick plate, 7 mm thick internal cement mortar lining and exterior / outsideepoxy coating

400 mm nominal dia (clear internal dia) of pipe with 5.0 mm thick plate, 7 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 111 Schedule of Rates 2014 - 2015

Page 31: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsideQuotation_Volume III_pg no_272 Cost of Scrap kg 2.583 27.00 69.75

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 1580.62 15.81 (C)

Material cost per meter Rs/meter 2729.81

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.424-(0.005*2+0.007))*0.007*1*2080= kg 18.62

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.424*1= sqmt 1.332 100.33 133.64 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.424-(0.005*2+0.007))*1= sqmt 1.279 450.00 575.38 (E)

Total (A+B+C+D+E) 3438.84Total without ED 3062.29

Add Water Charges @ 1% 1% 30.62Add CPOH @ 15% 15% 463.94

Total cost per meter for pipe 3556.85Total cost per kg for specials 50.61

2.5.1.15

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.426 0.006

thickness of CML (t2) =

Length of pipe =

0.007 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.426-0.006)*0.006*1*7850= kg 62.147Add 5 % wastage

5% kg 3.107Total Weight kg 65.254

#REF! Cost of MS plate kg 65.254 45.00 2936.45 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 62.147 6.63 412.03 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.107 27.00 83.90

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 1580.62 15.81 (C)

Material cost per meter Rs/meter 3280.39

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.426-(0.006*2+0.007))*0.007*1*2080= kg 18.62

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.426*1= sqmt 1.338 100.33 134.27 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.426-(0.006*2+0.007))*1= sqmt 1.279 450.00 575.38 (E)

Total (A+B+C+D+E) 3990.04Total without ED 3552.86

Add Water Charges @ 1% 1% 35.53Add CPOH @ 15% 15% 538.26

Total cost per meter for pipe 4126.65Total cost per kg for specials 51.10

2.5.1.16

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.4266 0.0063

thickness of CML (t2) =

Length of pipe =

0.007 1.0

400 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick plate, 7 mm thick internal cement mortar lining and exterior / outsideepoxy coating

400 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick plate, 7 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 112 Schedule of Rates 2014 - 2015

Page 32: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsideWeight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.4266-0.0063)*0.0063*1*7850= kg 65.301Add 5 % wastage

5% kg 3.265Total Weight kg 68.566

#REF! Cost of MS plate kg 68.566 45.00 3085.47 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 65.301 6.63 432.95 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.265 27.00 88.16

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 1580.62 15.81 (C)

Material cost per meter Rs/meter 3446.06

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.4266-(0.0063*2+0.007))*0.007*1*2080= kg 18.62

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.4266*1= sqmt 1.340 100.33 134.46 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.4266-(0.0063*2+0.007))*1= sqmt 1.279 450.00 575.38 (E)

Total (A+B+C+D+E) 4155.91Total without ED 3700.48

Add Water Charges @ 1% 1% 37.00Add CPOH @ 15% 15% 560.62

Total cost per meter for pipe 4298.11Total cost per kg for specials 51.22

2.5.1.17

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.4316 0.0088

thickness of CML (t2) =

Length of pipe =

0.007 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.4316-0.0088)*0.0088*1*7850= kg 91.757Add 5 % wastage

5% kg 4.588Total Weight kg 96.344

#REF! Cost of MS plate kg 96.344 45.00 4335.50 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 91.757 6.63 608.35 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 4.588 27.00 123.87

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 1580.62 15.81 (C)

Material cost per meter Rs/meter 4835.78

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.4316-(0.0088*2+0.007))*0.007*1*2080= kg 18.62

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.4316*1= sqmt 1.356 100.33 136.04 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.4316-(0.0088*2+0.007))*1= sqmt 1.279 450.00 575.38 (E)

Total (A+B+C+D+E) 5547.20Total without ED 4938.73

Add Water Charges @ 1% 1% 49.39Add CPOH @ 15% 15% 748.22

Total cost per meter for pipe 5736.33Total cost per kg for specials 51.97

400 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick plate, 7 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 113 Schedule of Rates 2014 - 2015

Page 33: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outside2.5.1.18

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.476 0.006

thickness of CML (t2) =

Length of pipe =

0.007 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.476-0.006)*0.006*1*7850= kg 69.545Add 5 % wastage

5% kg 3.477Total Weight kg 73.023

#REF! Cost of MS plate kg 73.023 45.00 3286.02 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 69.545 6.63 461.09 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.477 27.00 93.89

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 3672.54

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.476-(0.006*2+0.007))*0.007*1*2080= kg 20.90

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.476*1= sqmt 1.495 100.33 150.03 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.476-(0.006*2+0.007))*1= sqmt 1.436 450.00 646.07 (E)

Total (A+B+C+D+E) 4468.64Total without ED 3979.20

Add Water Charges @ 1% 1% 39.79Add CPOH @ 15% 15% 602.85

Total cost per meter for pipe 4621.84Total cost per kg for specials 51.10

2.5.1.19

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.4766 0.0063

thickness of CML (t2) =

Length of pipe =

0.007 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.4766-0.0063)*0.0063*1*7850= kg 73.069Add 5 % wastage

5% kg 3.653Total Weight kg 76.723

#REF! Cost of MS plate kg 76.723 45.00 3452.53 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 73.069 6.63 484.45 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.653 27.00 98.64

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 3857.65

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.4766-(0.0063*2+0.007))*0.007*1*2080= kg 20.90

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.4766*1= sqmt 1.497 100.33 150.22 (D)

450 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick plate, 7 mm thick internal cement mortar lining and exterior / outsideepoxy coating

450 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick plate, 7 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 114 Schedule of Rates 2014 - 2015

Page 34: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsideQuotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.4766-(0.0063*2+0.007))*1= sqmt 1.436 450.00 646.07 (E)

Total (A+B+C+D+E) 4653.94Total without ED 4144.11

Add Water Charges @ 1% 1% 41.44Add CPOH @ 15% 15% 627.83

Total cost per meter for pipe 4813.39Total cost per kg for specials 51.22

2.5.1.20

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.484 0.01

thickness of CML (t2) =

Length of pipe =

0.007 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.484-0.01)*0.01*1*7850= kg 116.896Add 5 % wastage

5% kg 5.845Total Weight kg 122.740

#REF! Cost of MS plate kg 122.740 45.00 5523.31 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 116.896 6.63 775.02 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 5.845 27.00 157.81

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 6159.84

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.484-(0.01*2+0.007))*0.007*1*2080= kg 20.90

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.484*1= sqmt 1.521 100.33 152.55 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.484-(0.01*2+0.007))*1= sqmt 1.436 450.00 646.07 (E)

Total (A+B+C+D+E) 6958.46Total without ED 6195.13

Add Water Charges @ 1% 1% 61.95Add CPOH @ 15% 15% 938.56

Total cost per meter for pipe 7195.65Total cost per kg for specials 52.22

2.5.1.21

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.526 0.006

thickness of CML (t2) =

Length of pipe =

0.007 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.526-0.006)*0.006*1*7850= kg 76.944Add 5 % wastage

5% kg 3.847Total Weight kg 80.791

#REF! Cost of MS plate kg 80.791 45.00 3635.60 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 76.944 6.63 510.14 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.847 27.00 103.87

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 4061.18

450 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick plate, 7 mm thick internal cement mortar lining and exterior / outsideepoxy coating

500 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick plate, 7 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 115 Schedule of Rates 2014 - 2015

Page 35: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outside

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.526-(0.006*2+0.007))*0.007*1*2080= kg 23.19

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.526*1= sqmt 1.652 100.33 165.79 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.526-(0.006*2+0.007))*1= sqmt 1.593 450.00 716.75 (E)

Total (A+B+C+D+E) 4943.73Total without ED 4402.02

Add Water Charges @ 1% 1% 44.02Add CPOH @ 15% 15% 666.91

Total cost per meter for pipe 5112.95Total cost per kg for specials 51.06

2.5.1.22

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.5266 0.0063

thickness of CML (t2) =

Length of pipe =

0.007 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.5266-0.0063)*0.0063*1*7850= kg 80.838Add 5 % wastage

5% kg 4.042Total Weight kg 84.880

#REF! Cost of MS plate kg 84.880 45.00 3819.58 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 80.838 6.63 535.95 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 4.042 27.00 109.13

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 4265.72

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.5266-(0.0063*2+0.007))*0.007*1*2080= kg 23.19

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.5266*1= sqmt 1.654 100.33 165.98 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.5266-(0.0063*2+0.007))*1= sqmt 1.593 450.00 716.75 (E)

Total (A+B+C+D+E) 5148.46Total without ED 4584.23

Add Water Charges @ 1% 1% 45.84Add CPOH @ 15% 15% 694.51

Total cost per meter for pipe 5324.59Total cost per kg for specials 51.18

2.5.1.23

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.536 0.011

thickness of CML (t2) =

Length of pipe =

0.007 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.536-0.011)*0.011*1*7850= kg 142.420Add 5 % wastage

5% kg 7.121

500 mm nominal dia (clear internal dia) of pipe with 11.0 mm thick plate, 7 mm thick internal cement mortar lining and exterior / outsideepoxy coating

500 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick plate, 7 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 116 Schedule of Rates 2014 - 2015

Page 36: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsideTotal Weight kg 149.541

#REF! Cost of MS plate kg 149.541 45.00 6729.35 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 142.420 6.63 944.25 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 7.121 27.00 192.27

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 7500.65

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.536-(0.011*2+0.007))*0.007*1*2080= kg 23.19

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.536*1= sqmt 1.684 100.33 168.94 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.536-(0.011*2+0.007))*1= sqmt 1.593 450.00 716.75 (E)

Total (A+B+C+D+E) 8386.35Total without ED 7465.95

Add Water Charges @ 1% 1% 74.66Add CPOH @ 15% 15% 1131.09

Total cost per meter for pipe 8671.70Total cost per kg for specials 52.36

2.5.1.24

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.626 0.006

thickness of CML (t2) =

Length of pipe =

0.007 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.626-0.006)*0.006*1*7850= kg 91.741Add 5 % wastage

5% kg 4.587Total Weight kg 96.328

#REF! Cost of MS plate kg 96.328 45.00 4334.75 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 91.741 6.63 608.24 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 4.587 27.00 123.85

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 4848.12

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.626-(0.006*2+0.007))*0.007*1*2080= kg 27.77

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.626*1= sqmt 1.967 100.33 197.31 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.626-(0.006*2+0.007))*1= sqmt 1.907 450.00 858.13 (E)

Total (A+B+C+D+E) 5903.56Total without ED 5257.33

Add Water Charges @ 1% 1% 52.57Add CPOH @ 15% 15% 796.49

Total cost per meter for pipe 6106.39Total cost per kg for specials 51.10

2.5.1.25

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

600 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick plate, 7 mm thick internal cement mortar lining and exterior / outsideepoxy coating

600 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick plate, 7 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 117 Schedule of Rates 2014 - 2015

Page 37: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsideDetail for 1 meter Outer dia (d) =

thickness of pipe (t1) =

0.6266 0.0063thickness of

CML (t2) =Length of pipe

=0.007 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.6266-0.0063)*0.0063*1*7850= kg 96.374Add 5 % wastage

5% kg 4.819Total Weight kg 101.193

#REF! Cost of MS plate kg 101.193 45.00 4553.69 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 96.374 6.63 638.96 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 4.819 27.00 130.11

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 5091.53

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.6266-(0.0063*2+0.007))*0.007*1*2080= kg 27.77

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.6266*1= sqmt 1.969 100.33 197.50 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.6266-(0.0063*2+0.007))*1= sqmt 1.907 450.00 858.13 (E)

Total (A+B+C+D+E) 6147.15Total without ED 5474.13

Add Water Charges @ 1% 1% 54.74Add CPOH @ 15% 15% 829.33

Total cost per meter for pipe 6358.20Total cost per kg for specials 51.22

2.5.1.26

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.63 0.008

thickness of CML (t2) =

Length of pipe =

0.007 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.63-0.008)*0.008*1*7850= kg 122.716Add 5 % wastage

5% kg 6.136Total Weight kg 128.851

#REF! Cost of MS plate kg 128.851 45.00 5798.31 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 122.716 6.63 813.60 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 6.136 27.00 165.67

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 6475.23

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.63-(0.008*2+0.007))*0.007*1*2080= kg 27.77

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.63*1= sqmt 1.979 100.33 198.57 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.63-(0.008*2+0.007))*1= sqmt 1.907 450.00 858.13 (E)

Total (A+B+C+D+E) 7531.93

600 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick plate, 7 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 118 Schedule of Rates 2014 - 2015

Page 38: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsideTotal without ED 6706.58Add Water Charges @ 1% 1% 67.07

Add CPOH @ 15% 15% 1016.05Total cost per meter for pipe 7789.69

Total cost per kg for specials 51.77

2.5.1.27

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.639 0.0125

thickness of CML (t2) =

Length of pipe =

0.007 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.639-0.0125)*0.0125*1*7850= kg 193.130Add 5 % wastage

5% kg 9.657Total Weight kg 202.787

#REF! Cost of MS plate kg 202.787 45.00 9125.41 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 193.130 6.63 1280.45 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 9.657 27.00 260.73

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 10174.12

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.639-(0.0125*2+0.007))*0.007*1*2080= kg 27.77

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.639*1= sqmt 2.007 100.33 201.41 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.639-(0.0125*2+0.007))*1= sqmt 1.907 450.00 858.13 (E)

Total (A+B+C+D+E) 11233.65Total without ED 10001.10

600 mm nominal dia (clear internal dia) of pipe with 12.5 mm thick plate, 7 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 119 Schedule of Rates 2014 - 2015

Page 39: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsideAdd Water Charges @ 1% 1% 100.01Add CPOH @ 15% 15% 1515.17

Total cost per meter for pipe 11616.28Total cost per kg for specials 52.59

2.5.1.28

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.73 0.006

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.73-0.006)*0.006*1*7850= kg 107.130Add 5 % wastage

5% kg 5.356Total Weight kg 112.486

#REF! Cost of MS plate kg 112.486 45.00 5061.87 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 107.130 6.63 710.27 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 5.356 27.00 144.62

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 5656.49

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.73-(0.006*2+0.009))*0.009*1*2080= kg 41.70

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.73*1= sqmt 2.293 100.33 230.09 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.73-(0.006*2+0.009))*1= sqmt 2.227 450.00 1002.33 (E)

Total (A+B+C+D+E) 6888.91Total without ED 6134.29

Add Water Charges @ 1% 1% 61.34Add CPOH @ 15% 15% 929.35

Total cost per meter for pipe 7124.98Total cost per kg for specials 47.87

2.5.1.29

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.7306 0.0063

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.7306-0.0063)*0.0063*1*7850= kg 112.533Add 5 % wastage

5% kg 5.627Total Weight kg 118.159

#REF! Cost of MS plate kg 118.159 45.00 5317.17 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 112.533 6.63 746.09 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 5.627 27.00 151.92

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 5940.32

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.7306-(0.0063*2+0.009))*0.009*1*2080= kg 41.70

700 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outsideepoxy coating

700 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 120 Schedule of Rates 2014 - 2015

Page 40: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsideOutside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.7306*1= sqmt 2.295 100.33 230.28 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.7306-(0.0063*2+0.009))*1= sqmt 2.227 450.00 1002.33 (E)

Total (A+B+C+D+E) 7172.92Total without ED 6387.06

Add Water Charges @ 1% 1% 63.87Add CPOH @ 15% 15% 967.64

Total cost per meter for pipe 7418.57Total cost per kg for specials 48.10

2.5.1.30

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.7322 0.0071

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.7322-0.0071)*0.0071*1*7850= kg 126.963Add 5 % wastage

5% kg 6.348Total Weight kg 133.311

#REF! Cost of MS plate kg 133.311 45.00 5998.98 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 126.963 6.63 841.76 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 6.348 27.00 171.40

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 6698.32

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.7322-(0.0071*2+0.009))*0.009*1*2080= kg 41.70

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.7322*1= sqmt 2.300 100.33 230.78 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.7322-(0.0071*2+0.009))*1= sqmt 2.227 450.00 1002.33 (E)

Total (A+B+C+D+E) 7931.43Total without ED 7062.13

Add Water Charges @ 1% 1% 70.62Add CPOH @ 15% 15% 1069.91

Total cost per meter for pipe 8202.67Total cost per kg for specials 48.63

2.5.1.31

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.734 0.008

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.734-0.008)*0.008*1*7850= kg 143.234Add 5 % wastage

5% kg 7.162Total Weight kg 150.396

#REF! Cost of MS plate kg 150.396 45.00 6767.81 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 143.234 6.63 949.64 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 7.162 27.00 193.37

700 mm nominal dia (clear internal dia) of pipe with 7.1 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outsideepoxy coating

700 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 121 Schedule of Rates 2014 - 2015

Page 41: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsidePlease refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 7553.06

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.734-(0.008*2+0.009))*0.009*1*2080= kg 41.70

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.734*1= sqmt 2.306 100.33 231.35 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.734-(0.008*2+0.009))*1= sqmt 2.227 450.00 1002.33 (E)

Total (A+B+C+D+E) 8786.74Total without ED 7823.35

Add Water Charges @ 1% 1% 78.23Add CPOH @ 15% 15% 1185.24

Total cost per meter for pipe 9086.82Total cost per kg for specials 49.14

2.5.1.32

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.7464 0.0142

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.7464-0.0142)*0.0142*1*7850= kg 256.412Add 5 % wastage

5% kg 12.821Total Weight kg 269.232

#REF! Cost of MS plate kg 269.232 45.00 12115.45 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 256.412 6.63 1700.01 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 12.821 27.00 346.16

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 13498.28

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.7464-(0.0142*2+0.009))*0.009*1*2080= kg 41.70

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.7464*1= sqmt 2.345 100.33 235.26 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.7464-(0.0142*2+0.009))*1= sqmt 2.227 450.00 1002.33 (E)

Total (A+B+C+D+E) 14735.86Total without ED 13118.05

Add Water Charges @ 1% 1% 131.18Add CPOH @ 15% 15% 1987.38

Total cost per meter for pipe 15236.62Total cost per kg for specials 51.11

2.5.1.33

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.8322 0.0071

thickness of CML (t2) =

Length of pipe =

0.009 1.0

700 mm nominal dia (clear internal dia) of pipe with 14.2 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outsideepoxy coating

800 mm nominal dia (clear internal dia) of pipe with 7.1 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 122 Schedule of Rates 2014 - 2015

Page 42: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsideWeight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.8322-0.0071)*0.0071*1*7850= kg 144.472Add 5 % wastage

5% kg 7.224Total Weight kg 151.696

#REF! Cost of MS plate kg 151.696 45.00 6826.31 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 144.472 6.63 957.85 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 7.224 27.00 195.04

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 7618.11

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.8322-(0.0071*2+0.009))*0.009*1*2080= kg 47.58

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.8322*1= sqmt 2.614 100.33 262.30 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.8322-(0.0071*2+0.009))*1= sqmt 2.542 450.00 1143.70 (E)

Total (A+B+C+D+E) 9024.11Total without ED 8034.61

Add Water Charges @ 1% 1% 80.35Add CPOH @ 15% 15% 1217.24

Total cost per meter for pipe 9332.20Total cost per kg for specials 48.59

2.5.1.34

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.834 0.008

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.834-0.008)*0.008*1*7850= kg 162.963Add 5 % wastage

5% kg 8.148Total Weight kg 171.111

#REF! Cost of MS plate kg 171.111 45.00 7700.01 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 162.963 6.63 1080.45 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 8.148 27.00 220.00

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 8589.44

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.834-(0.008*2+0.009))*0.009*1*2080= kg 47.58

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.834*1= sqmt 2.620 100.33 262.87 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.834-(0.008*2+0.009))*1= sqmt 2.542 450.00 1143.70 (E)

Total (A+B+C+D+E) 9996.00Total without ED 8899.59

Add Water Charges @ 1% 1% 89.00Add CPOH @ 15% 15% 1348.29

Total cost per meter for pipe 10336.88Total cost per kg for specials 49.10

800 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 123 Schedule of Rates 2014 - 2015

Page 43: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outside2.5.1.35

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.854 0.018

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.854-0.018)*0.018*1*7850= kg 371.106Add 5 % wastage

5% kg 18.555Total Weight kg 389.662

#REF! Cost of MS plate kg 389.662 45.00 17534.77 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 371.106 6.63 2460.43 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 18.555 27.00 500.99

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 19523.19

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.854-(0.018*2+0.009))*0.009*1*2080= kg 47.58

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.854*1= sqmt 2.683 100.33 269.17 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.854-(0.018*2+0.009))*1= sqmt 2.542 450.00 1143.70 (E)

Total (A+B+C+D+E) 20936.06Total without ED 18636.21

Add Water Charges @ 1% 1% 186.36Add CPOH @ 15% 15% 2823.39

Total cost per meter for pipe 21645.96Total cost per kg for specials 51.70

2.5.1.36

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.934 0.008

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.934-0.008)*0.008*1*7850= kg 182.692Add 5 % wastage

5% kg 9.135Total Weight kg 191.827

#REF! Cost of MS plate kg 191.827 45.00 8632.22 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 182.692 6.63 1211.25 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 9.135 27.00 246.63

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 4346.71 43.47 (C)

Material cost per meter Rs/meter 9640.30

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.934-(0.008*2+0.009))*0.009*1*2080= kg 53.46

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.934*1= sqmt 2.934 100.33 294.39 (D)

800 mm nominal dia (clear internal dia) of pipe with 18.0 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outsideepoxy coating

900 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 124 Schedule of Rates 2014 - 2015

Page 44: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsideQuotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.934-(0.008*2+0.009))*1= sqmt 2.856 450.00 1285.07 (E)

Total (A+B+C+D+E) 11219.76Total without ED 9990.33

Add Water Charges @ 1% 1% 99.90Add CPOH @ 15% 15% 1513.53

Total cost per meter for pipe 11603.76Total cost per kg for specials 49.14

2.5.1.37

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.9356 0.0088

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.9356-0.0088)*0.0088*1*7850= kg 201.135Add 5 % wastage

5% kg 10.057Total Weight kg 211.192

#REF! Cost of MS plate kg 211.192 45.00 9503.64 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 201.135 6.63 1333.53 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 10.057 27.00 271.53

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 4346.71 43.47 (C)

Material cost per meter Rs/meter 10609.10

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.9356-(0.0088*2+0.009))*0.009*1*2080= kg 53.46

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.9356*1= sqmt 2.939 100.33 294.89 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.9356-(0.0088*2+0.009))*1= sqmt 2.856 450.00 1285.07 (E)

Total (A+B+C+D+E) 12189.07Total without ED 10853.01

Add Water Charges @ 1% 1% 108.53Add CPOH @ 15% 15% 1644.23

Total cost per meter for pipe 12605.77Total cost per kg for specials 49.51

2.5.1.38

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.938 0.01

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.938-0.01)*0.01*1*7850= kg 228.859Add 5 % wastage

5% kg 11.443Total Weight kg 240.302

#REF! Cost of MS plate kg 240.302 45.00 10813.58 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 228.859 6.63 1517.33 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 11.443 27.00 308.96

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 4346.71 43.47 (C)

Material cost per meter Rs/meter 12065.42

900 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outsideepoxy coating

900 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 125 Schedule of Rates 2014 - 2015

Page 45: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outside

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.938-(0.01*2+0.009))*0.009*1*2080= kg 53.46

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.938*1= sqmt 2.947 100.33 295.65 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.938-(0.01*2+0.009))*1= sqmt 2.856 450.00 1285.07 (E)

Total (A+B+C+D+E) 13646.14Total without ED 12149.79

Add Water Charges @ 1% 1% 121.50Add CPOH @ 15% 15% 1840.69

Total cost per meter for pipe 14111.99Total cost per kg for specials 49.99

2.5.1.39

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.953 0.0175

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.953-0.0175)*0.0175*1*7850= kg 403.740Add 5 % wastage

5% kg 20.187Total Weight kg 423.927

#REF! Cost of MS plate kg 423.927 45.00 19076.70 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 403.740 6.63 2676.79 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 20.187 27.00 545.05

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 4346.71 43.47 (C)

Material cost per meter Rs/meter 21251.91

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.953-(0.0175*2+0.009))*0.009*1*2080= kg 53.46

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.953*1= sqmt 2.994 100.33 300.38 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.953-(0.0175*2+0.009))*1= sqmt 2.856 450.00 1285.07 (E)

Total (A+B+C+D+E) 22837.36Total without ED 20329.95

Add Water Charges @ 1% 1% 203.30Add CPOH @ 15% 15% 3079.99

Total cost per meter for pipe 23613.23Total cost per kg for specials 51.65

2.5.1.40

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.0356 0.0088

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.0356-0.0088)*0.0088*1*7850= kg 222.837Add 5 % wastage

5% kg 11.142

1000 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outsideepoxy coating

900 mm nominal dia (clear internal dia) of pipe with 17.5 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 126 Schedule of Rates 2014 - 2015

Page 46: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsideTotal Weight kg 233.979

#REF! Cost of MS plate kg 233.979 45.00 10529.07 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 222.837 6.63 1477.41 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 11.142 27.00 300.83

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 11763.60

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.0356-(0.0088*2+0.009))*0.009*1*2080= kg 59.34

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.0356*1= sqmt 3.253 100.33 326.41 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.0356-(0.0088*2+0.009))*1= sqmt 3.170 450.00 1426.44 (E)

Total (A+B+C+D+E) 13516.46Total without ED 12035.97

Add Water Charges @ 1% 1% 120.36Add CPOH @ 15% 15% 1823.45

Total cost per meter for pipe 13979.78Total cost per kg for specials 49.54

2.5.1.41

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.038 0.01

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.038-0.01)*0.01*1*7850= kg 253.520Add 5 % wastage

5% kg 12.676Total Weight kg 266.196

#REF! Cost of MS plate kg 266.196 45.00 11978.83 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 253.520 6.63 1680.84 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 12.676 27.00 342.25

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 13375.37

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.038-(0.01*2+0.009))*0.009*1*2080= kg 59.34

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.038*1= sqmt 3.261 100.33 327.17 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.038-(0.01*2+0.009))*1= sqmt 3.170 450.00 1426.44 (E)

Total (A+B+C+D+E) 15128.98Total without ED 13471.12

Add Water Charges @ 1% 1% 134.71Add CPOH @ 15% 15% 2040.87

Total cost per meter for pipe 15646.70Total cost per kg for specials 50.01

2.5.1.42

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

1000 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outsideepoxy coating

1000 mm nominal dia (clear internal dia) of pipe with 20.0 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 127 Schedule of Rates 2014 - 2015

Page 47: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsideDetail for 1 meter Outer dia (d) =

thickness of pipe (t1) =

1.058 0.02thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.058-0.02)*0.02*1*7850= kg 511.973Add 5 % wastage

5% kg 25.599Total Weight kg 537.571

#REF! Cost of MS plate kg 537.571 45.00 24190.71 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 511.973 6.63 3394.38 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 25.599 27.00 691.16

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 26951.89

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.058-(0.02*2+0.009))*0.009*1*2080= kg 59.34

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.058*1= sqmt 3.324 100.33 333.47 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.058-(0.02*2+0.009))*1= sqmt 3.170 450.00 1426.44 (E)

Total (A+B+C+D+E) 28711.80Total without ED 25559.78

Add Water Charges @ 1% 1% 255.60Add CPOH @ 15% 15% 3872.31

Total cost per meter for pipe 29687.68Total cost per kg for specials 51.96

2.5.1.43

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.0856 0.0088

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.0856-0.0088)*0.0088*1*7850= kg 233.688Add 5 % wastage

5% kg 11.684Total Weight kg 245.373

#REF! Cost of MS plate kg 245.373 45.00 11041.78 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 233.688 6.63 1549.35 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 11.684 27.00 315.48

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 12333.61

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.0856-(0.0088*2+0.009))*0.009*1*2080= kg 62.28

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.0856*1= sqmt 3.411 100.33 342.17 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.0856-(0.0088*2+0.009))*1= sqmt 3.327 450.00 1497.13 (E)

Total (A+B+C+D+E) 14172.91

1050 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 128 Schedule of Rates 2014 - 2015

Page 48: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsideTotal without ED 12620.21Add Water Charges @ 1% 1% 126.20

Add CPOH @ 15% 15% 1911.96Total cost per meter for pipe 14658.38

Total cost per kg for specials 49.53

2.5.1.44

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.088 0.01

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.088-0.01)*0.01*1*7850= kg 265.851Add 5 % wastage

5% kg 13.293Total Weight kg 279.144

#REF! Cost of MS plate kg 279.144 45.00 12561.46 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 265.851 6.63 1762.59 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 13.293 27.00 358.90

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 14023.11

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.088-(0.01*2+0.009))*0.009*1*2080= kg 62.28

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.088*1= sqmt 3.418 100.33 342.93 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.088-(0.01*2+0.009))*1= sqmt 3.327 450.00 1497.13 (E)

Total (A+B+C+D+E) 15863.16Total without ED 14124.54

Add Water Charges @ 1% 1% 141.25Add CPOH @ 15% 15% 2139.87

Total cost per meter for pipe 16405.65Total cost per kg for specials 50.00

2.5.1.45

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.09 0.011

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.09-0.011)*0.011*1*7850= kg 292.707Add 5 % wastage

5% kg 14.635Total Weight kg 307.343

#REF! Cost of MS plate kg 307.343 45.00 13830.42 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 292.707 6.63 1940.65 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 14.635 27.00 395.15

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 15433.87

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.09-(0.011*2+0.009))*0.009*1*2080= kg 62.28

1050 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outsideepoxy coating

1050 mm nominal dia (clear internal dia) of pipe with 11.0 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 129 Schedule of Rates 2014 - 2015

Page 49: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsideOutside epoxy coating

13.52.1 Area of coating = pi()*d*L(3.14159265358979)*1.09*1= sqmt 3.424 100.33 343.56 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.09-(0.011*2+0.009))*1= sqmt 3.327 450.00 1497.13 (E)

Total (A+B+C+D+E) 17274.56Total without ED 15380.67

Add Water Charges @ 1% 1% 153.81Add CPOH @ 15% 15% 2330.17

Total cost per meter for pipe 17864.65Total cost per kg for specials 50.32

2.5.1.46

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.1356 0.0088

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.1356-0.0088)*0.0088*1*7850= kg 244.540Add 5 % wastage

5% kg 12.227Total Weight kg 256.766

#REF! Cost of MS plate kg 256.766 45.00 11554.49 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 244.540 6.63 1621.30 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 12.227 27.00 330.13

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 12903.62

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.1356-(0.0088*2+0.009))*0.009*1*2080= kg 65.22

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.1356*1= sqmt 3.568 100.33 357.93 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.1356-(0.0088*2+0.009))*1= sqmt 3.484 450.00 1567.81 (E)

Total (A+B+C+D+E) 14829.36Total without ED 13204.45

Add Water Charges @ 1% 1% 132.04Add CPOH @ 15% 15% 2000.47

Total cost per meter for pipe 15336.97Total cost per kg for specials 49.51

2.5.1.47

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.138 0.01

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.138-0.01)*0.01*1*7850= kg 278.182Add 5 % wastage

5% kg 13.909Total Weight kg 292.091

#REF! Cost of MS plate kg 292.091 45.00 13144.09 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 278.182 6.63 1844.34 (B)

1100 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outsideepoxy coating

1100 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 130 Schedule of Rates 2014 - 2015

Page 50: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsideQuotation_Volume III_pg no_272 Cost of Scrap kg 13.909 27.00 375.55

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 14670.84

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.138-(0.01*2+0.009))*0.009*1*2080= kg 65.22

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.138*1= sqmt 3.575 100.33 358.69 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.138-(0.01*2+0.009))*1= sqmt 3.484 450.00 1567.81 (E)

Total (A+B+C+D+E) 16597.34Total without ED 14777.95

Add Water Charges @ 1% 1% 147.78Add CPOH @ 15% 15% 2238.86

Total cost per meter for pipe 17164.59Total cost per kg for specials 49.98

2.5.1.48

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.14 0.011

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.14-0.011)*0.011*1*7850= kg 306.271Add 5 % wastage

5% kg 15.314Total Weight kg 321.585

#REF! Cost of MS plate kg 321.585 45.00 14471.31 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 306.271 6.63 2030.58 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 15.314 27.00 413.47

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 16146.38

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.14-(0.011*2+0.009))*0.009*1*2080= kg 65.22

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.14*1= sqmt 3.581 100.33 359.32 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.14-(0.011*2+0.009))*1= sqmt 3.484 450.00 1567.81 (E)

Total (A+B+C+D+E) 18073.51Total without ED 16091.74

Add Water Charges @ 1% 1% 160.92Add CPOH @ 15% 15% 2437.90

Total cost per meter for pipe 18690.55Total cost per kg for specials 50.31

2.5.1.49

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.244 0.01

thickness of CML (t2) =

Length of pipe =

0.012 1.0

1100 mm nominal dia (clear internal dia) of pipe with 11.0 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outsideepoxy coating

1200 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 131 Schedule of Rates 2014 - 2015

Page 51: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsideWeight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.244-0.01)*0.01*1*7850= kg 304.323Add 5 % wastage

5% kg 15.216Total Weight kg 319.539

#REF! Cost of MS plate kg 319.539 45.00 14379.26 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 304.323 6.63 2017.66 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 15.216 27.00 410.84

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 16044.04

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.244-(0.01*2+0.012))*0.012*1*2080= kg 95.04

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.244*1= sqmt 3.908 100.33 392.10 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.244-(0.01*2+0.012))*1= sqmt 3.808 450.00 1713.42 (E)

Total (A+B+C+D+E) 18149.56Total without ED 16159.42

Add Water Charges @ 1% 1% 161.59Add CPOH @ 15% 15% 2448.15

Total cost per meter for pipe 18769.17Total cost per kg for specials 47.00

2.5.1.50

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.246 0.011

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.246-0.011)*0.011*1*7850= kg 335.027Add 5 % wastage

5% kg 16.751Total Weight kg 351.778

#REF! Cost of MS plate kg 351.778 45.00 15830.00 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 335.027 6.63 2221.23 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 16.751 27.00 452.29

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 17656.90

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.246-(0.011*2+0.012))*0.012*1*2080= kg 95.04

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.246*1= sqmt 3.914 100.33 392.73 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.246-(0.011*2+0.012))*1= sqmt 3.808 450.00 1713.42 (E)

Total (A+B+C+D+E) 19763.05Total without ED 17595.42

Add Water Charges @ 1% 1% 175.95Add CPOH @ 15% 15% 2665.71

Total cost per meter for pipe 20437.08Total cost per kg for specials 47.52

1200 mm nominal dia (clear internal dia) of pipe with 11.0 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 132 Schedule of Rates 2014 - 2015

Page 52: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outside2.5.1.51

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.248 0.012

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.248-0.012)*0.012*1*7850= kg 365.779Add 5 % wastage

5% kg 18.289Total Weight kg 384.068

#REF! Cost of MS plate kg 384.068 45.00 17283.08 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 365.779 6.63 2425.12 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 18.289 27.00 493.80

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 19272.35

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.248-(0.012*2+0.012))*0.012*1*2080= kg 95.04

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.248*1= sqmt 3.921 100.33 393.36 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.248-(0.012*2+0.012))*1= sqmt 3.808 450.00 1713.42 (E)

Total (A+B+C+D+E) 21379.13Total without ED 19033.73

Add Water Charges @ 1% 1% 190.34Add CPOH @ 15% 15% 2883.61

Total cost per meter for pipe 22107.68Total cost per kg for specials 47.97

2.5.1.52

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.249 0.0125

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.249-0.0125)*0.0125*1*7850= kg 381.174Add 5 % wastage

5% kg 19.059Total Weight kg 400.233

#REF! Cost of MS plate kg 400.233 45.00 18010.49 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 381.174 6.63 2527.19 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 19.059 27.00 514.59

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 20081.04

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.249-(0.0125*2+0.012))*0.012*1*2080= kg 95.04

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.249*1= sqmt 3.924 100.33 393.68 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

1200 mm nominal dia (clear internal dia) of pipe with 12.0 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

1200 mm nominal dia (clear internal dia) of pipe with 12.5 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 133 Schedule of Rates 2014 - 2015

Page 53: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outside(3.1416)*(1.249-(0.0125*2+0.012))*1= sqmt 3.808 450.00 1713.42 (E)

Total (A+B+C+D+E) 22188.15Total without ED 19753.75

Add Water Charges @ 1% 1% 197.54Add CPOH @ 15% 15% 2992.69

Total cost per meter for pipe 22943.98Total cost per kg for specials 48.18

2.5.1.53

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.448 0.012

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.448-0.012)*0.012*1*7850= kg 424.967Add 5 % wastage

5% kg 21.248Total Weight kg 446.215

#REF! Cost of MS plate kg 446.215 45.00 20079.69 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 424.967 6.63 2817.53 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 21.248 27.00 573.71

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 7244.52 72.45 (C)

Material cost per meter Rs/meter 22395.96

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.448-(0.012*2+0.012))*0.012*1*2080= kg 110.72

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.448*1= sqmt 4.549 100.33 456.40 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.448-(0.012*2+0.012))*1= sqmt 4.436 450.00 1996.17 (E)

Total (A+B+C+D+E) 24848.53Total without ED 22123.07

Add Water Charges @ 1% 1% 221.23Add CPOH @ 15% 15% 3351.65

Total cost per meter for pipe 25695.95Total cost per kg for specials 47.97

2.5.1.54

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.449 0.0125

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.449-0.0125)*0.0125*1*7850= kg 442.828Add 5 % wastage

5% kg 22.141Total Weight kg 464.970

#REF! Cost of MS plate kg 464.970 45.00 20923.63 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 442.828 6.63 2935.95 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 22.141 27.00 597.82

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 7244.52 72.45 (C)

Material cost per meter Rs/meter 23334.21

1400 mm nominal dia (clear internal dia) of pipe with 12 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

1400 mm nominal dia (clear internal dia) of pipe with 12.5 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 134 Schedule of Rates 2014 - 2015

Page 54: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsideWeight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.449-(0.0125*2+0.012))*0.012*1*2080= kg 110.72

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.449*1= sqmt 4.552 100.33 456.71 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.449-(0.0125*2+0.012))*1= sqmt 4.436 450.00 1996.17 (E)

Total (A+B+C+D+E) 25787.09Total without ED 22958.39

Add Water Charges @ 1% 1% 229.58Add CPOH @ 15% 15% 3478.20

Total cost per meter for pipe 26666.16Total cost per kg for specials 48.17

2.5.1.55

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.4524 0.0142

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.4524-0.0142)*0.0142*1*7850= kg 503.648Add 5 % wastage

5% kg 25.182Total Weight kg 528.830

#REF! Cost of MS plate kg 528.830 45.00 23797.37 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 503.648 6.63 3339.19 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 25.182 27.00 679.92

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 7244.52 72.45 (C)

Material cost per meter Rs/meter 26529.08

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.4524-(0.0142*2+0.012))*0.012*1*2080= kg 110.72

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.4524*1= sqmt 4.563 100.33 457.79 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.4524-(0.0142*2+0.012))*1= sqmt 4.436 450.00 1996.17 (E)

Total (A+B+C+D+E) 28983.03Total without ED 25802.76

Add Water Charges @ 1% 1% 258.03Add CPOH @ 15% 15% 3909.12

Total cost per meter for pipe 29969.91Total cost per kg for specials 48.78

2.5.1.56

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.548 0.012

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.548-0.012)*0.012*1*7850= kg 454.561Add 5 % wastage

5% kg 22.728Total Weight kg 477.289

1400 mm nominal dia (clear internal dia) of pipe with 14.2 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

1500 mm nominal dia (clear internal dia) of pipe with 12 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 135 Schedule of Rates 2014 - 2015

Page 55: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outside#REF! Cost of MS plate kg 477.289 45.00 21478.00 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 454.561 6.63 3013.74 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 22.728 27.00 613.66

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 8693.42 86.93 (C)

Material cost per meter Rs/meter 23965.01

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.548-(0.012*2+0.012))*0.012*1*2080= kg 118.56

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.548*1= sqmt 4.863 100.33 487.92 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.548-(0.012*2+0.012))*1= sqmt 4.750 450.00 2137.54 (E)

Total (A+B+C+D+E) 26590.47Total without ED 23674.99

Add Water Charges @ 1% 1% 236.75Add CPOH @ 15% 15% 3586.76

Total cost per meter for pipe 27498.50Total cost per kg for specials 47.98

2.5.1.57

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.6524 0.0142

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.6524-0.0142)*0.0142*1*7850= kg 573.687Add 5 % wastage

5% kg 28.684Total Weight kg 602.371

#REF! Cost of MS plate kg 602.371 45.00 27106.70 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 573.687 6.63 3803.54 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 28.684 27.00 774.48

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 8693.42 86.93 (C)

Material cost per meter Rs/meter 30222.70

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.6524-(0.0142*2+0.012))*0.012*1*2080= kg 126.40

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.6524*1= sqmt 5.191 100.33 520.82 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.6524-(0.0142*2+0.012))*1= sqmt 5.064 450.00 2278.91 (E)

Total (A+B+C+D+E) 33022.43Total without ED 29399.41

Add Water Charges @ 1% 1% 293.99Add CPOH @ 15% 15% 4454.01

Total cost per meter for pipe 34147.42Total cost per kg for specials 48.78

2.5.1.58

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.656 0.016

1600 mm nominal dia (clear internal dia) of pipe with 14.2 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

1600 mm nominal dia (clear internal dia) of pipe with 16.0 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 136 Schedule of Rates 2014 - 2015

Page 56: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsidethickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.656-0.016)*0.016*1*7850= kg 647.118Add 5 % wastage

5% kg 32.356Total Weight kg 679.474

#REF! Cost of MS plate kg 679.474 45.00 30576.32 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 647.118 6.63 4290.39 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 32.356 27.00 873.61

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 8693.42 86.93 (C)

Material cost per meter Rs/meter 34080.03

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.656-(0.016*2+0.012))*0.012*1*2080= kg 126.40

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.656*1= sqmt 5.202 100.33 521.96 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.656-(0.016*2+0.012))*1= sqmt 5.064 450.00 2278.91 (E)

Total (A+B+C+D+E) 36880.90Total without ED 32833.44

Add Water Charges @ 1% 1% 328.33Add CPOH @ 15% 15% 4974.27

Total cost per meter for pipe 38136.04Total cost per kg for specials 49.30

2.5.1.59

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.8524 0.0142

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.8524-0.0142)*0.0142*1*7850= kg 643.725Add 5 % wastage

5% kg 32.186Total Weight kg 675.912

#REF! Cost of MS plate kg 675.912 45.00 30416.02 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 643.725 6.63 4267.90 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 32.186 27.00 869.03

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 10142.33 101.42 (C)

Material cost per meter Rs/meter 33916.32

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.8524-(0.0142*2+0.012))*0.012*1*2080= kg 142.09

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.8524*1= sqmt 5.819 100.33 583.86 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.8524-(0.0142*2+0.012))*1= sqmt 5.693 450.00 2561.65 (E)

Total (A+B+C+D+E) 37061.84Total without ED 32996.06

Add Water Charges @ 1% 1% 329.96Add CPOH @ 15% 15% 4998.90

1800 mm nominal dia (clear internal dia) of pipe with 14.2 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 137 Schedule of Rates 2014 - 2015

Page 57: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsideTotal cost per meter for pipe 38324.92Total cost per kg for specials 48.77

2.5.1.60

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.856 0.016

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.856-0.016)*0.016*1*7850= kg 726.035Add 5 % wastage

5% kg 36.302Total Weight kg 762.336

#REF! Cost of MS plate kg 762.336 45.00 34305.14 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 726.035 6.63 4813.61 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 36.302 27.00 980.15

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 10142.33 101.42 (C)

Material cost per meter Rs/meter 38240.02

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.856-(0.016*2+0.012))*0.012*1*2080= kg 142.09

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.856*1= sqmt 5.831 100.33 585.00 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.856-(0.016*2+0.012))*1= sqmt 5.693 450.00 2561.65 (E)

Total (A+B+C+D+E) 41386.67Total without ED 36845.15

Add Water Charges @ 1% 1% 368.45Add CPOH @ 15% 15% 5582.04

Total cost per meter for pipe 42795.64Total cost per kg for specials 49.30

2.5.1.61

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.859 0.0175

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.859-0.0175)*0.0175*1*7850= kg 794.748Add 5 % wastage

5% kg 39.737Total Weight kg 834.485

#REF! Cost of MS plate kg 834.485 45.00 37551.83 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 794.748 6.63 5269.18 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 39.737 27.00 1072.91

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 10142.33 101.42 (C)

Material cost per meter Rs/meter 41849.52

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.859-(0.0175*2+0.012))*0.012*1*2080= kg 142.09

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

1800 mm nominal dia (clear internal dia) of pipe with 16.0 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

1800 mm nominal dia (clear internal dia) of pipe with 17.5 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 138 Schedule of Rates 2014 - 2015

Page 58: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outside(3.14159265358979)*1.859*1= sqmt 5.840 100.33 585.94 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.859-(0.0175*2+0.012))*1= sqmt 5.693 450.00 2561.65 (E)

Total (A+B+C+D+E) 44997.12Total without ED 40058.43

Add Water Charges @ 1% 1% 400.58Add CPOH @ 15% 15% 6068.85

Total cost per meter for pipe 46527.87Total cost per kg for specials 49.67

2.5.1.62

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =2.056 0.016

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(2.056-0.016)*0.016*1*7850= kg 804.951Add 5 % wastage

5% kg 40.248Total Weight kg 845.199

#REF! Cost of MS plate kg 845.199 45.00 38033.96 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 804.951 6.63 5336.83 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 40.248 27.00 1086.68

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 11591.23 115.91 (C)

Material cost per meter Rs/meter 42400.01

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(2.056-(0.016*2+0.012))*0.012*1*2080= kg 157.77

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*2.056*1= sqmt 6.459 100.33 648.04 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(2.056-(0.016*2+0.012))*1= sqmt 6.321 450.00 2844.40 (E)

Total (A+B+C+D+E) 45892.45

2000 mm nominal dia (clear internal dia) of pipe with 16.0 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 139 Schedule of Rates 2014 - 2015

Page 59: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsideTotal without ED 40856.86Add Water Charges @ 1% 1% 408.57

Add CPOH @ 15% 15% 6189.81Total cost per meter for pipe 47455.25

Total cost per kg for specials 49.29

2.5.1.63

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =2.059 0.0175

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(2.059-0.0175)*0.0175*1*7850= kg 881.063Add 5 % wastage

5% kg 44.053Total Weight kg 925.116

#REF! Cost of MS plate kg 925.116 45.00 41630.23 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 881.063 6.63 5841.45 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 44.053 27.00 1189.44

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 11591.23 115.91 (C)

Material cost per meter Rs/meter 46398.15

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(2.059-(0.0175*2+0.012))*0.012*1*2080= kg 157.77

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*2.059*1= sqmt 6.469 100.33 648.98 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(2.059-(0.0175*2+0.012))*1= sqmt 6.321 450.00 2844.40 (E)

Total (A+B+C+D+E) 49891.53Total without ED 44416.04

Add Water Charges @ 1% 1% 444.16Add CPOH @ 15% 15% 6729.03

Total cost per meter for pipe 51589.23Total cost per kg for specials 49.66

2.5.1.64

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =2.064 0.02

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(2.064-0.02)*0.02*1*7850= kg 1008.162Add 5 % wastage

5% kg 50.408Total Weight kg 1058.570

#REF! Cost of MS plate kg 1058.570 45.00 47635.66 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 1008.162 6.63 6684.12 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 50.408 27.00 1361.02

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 11591.23 115.91 (C)

Material cost per meter Rs/meter 53074.67

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(2.064-(0.02*2+0.012))*0.012*1*2080= kg 157.77

2000 mm nominal dia (clear internal dia) of pipe with 17.5 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

2000 mm nominal dia (clear internal dia) of pipe with 20.0 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 140 Schedule of Rates 2014 - 2015

Page 60: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsideOutside epoxy coating

13.52.1 Area of coating = pi()*d*L(3.14159265358979)*2.064*1= sqmt 6.484 100.33 650.56 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(2.064-(0.02*2+0.012))*1= sqmt 6.321 450.00 2844.40 (E)

Total (A+B+C+D+E) 56569.63Total without ED 50359.52

Add Water Charges @ 1% 1% 503.60Add CPOH @ 15% 15% 7629.47

Total cost per meter for pipe 58492.58Total cost per kg for specials 50.17

2.5.1.65

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =2.259 0.0175

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(2.259-0.0175)*0.0175*1*7850= kg 967.378Add 5 % wastage

5% kg 48.369Total Weight kg 1015.747

#REF! Cost of MS plate kg 1015.747 45.00 45708.62 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 967.378 6.63 6413.72 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 48.369 27.00 1305.96

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 13040.13 130.40 (C)

Material cost per meter Rs/meter 50946.78

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(2.259-(0.0175*2+0.012))*0.012*1*2080= kg 173.45

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*2.259*1= sqmt 7.097 100.33 712.02 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(2.259-(0.0175*2+0.012))*1= sqmt 6.949 450.00 3127.14 (E)

Total (A+B+C+D+E) 54785.94Total without ED 48773.64

Add Water Charges @ 1% 1% 487.74Add CPOH @ 15% 15% 7389.21

Total cost per meter for pipe 56650.58Total cost per kg for specials 49.66

2.5.1.66

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =2.264 0.02

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(2.264-0.02)*0.02*1*7850= kg 1106.808Add 5 % wastage

5% kg 55.340Total Weight kg 1162.149

#REF! Cost of MS plate kg 1162.149 45.00 52296.69 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 1106.808 6.63 7338.14 (B)

2200 mm nominal dia (clear internal dia) of pipe with 17.5 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

2200 mm nominal dia (clear internal dia) of pipe with 20.0 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 141 Schedule of Rates 2014 - 2015

Page 61: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsideQuotation_Volume III_pg no_272 Cost of Scrap kg 55.340 27.00 1494.19

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 13040.13 130.40 (C)

Material cost per meter Rs/meter 58271.04

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(2.264-(0.02*2+0.012))*0.012*1*2080= kg 173.45

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*2.264*1= sqmt 7.113 100.33 713.60 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(2.264-(0.02*2+0.012))*1= sqmt 6.949 450.00 3127.14 (E)

Total (A+B+C+D+E) 62111.78Total without ED 55293.60

Add Water Charges @ 1% 1% 552.94Add CPOH @ 15% 15% 8376.98

Total cost per meter for pipe 64223.52Total cost per kg for specials 50.16

2.5.1.67

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =2.2684 0.0222

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(2.2684-0.0222)*0.0222*1*7850= kg 1229.762Add 5 % wastage

5% kg 61.488Total Weight kg 1291.250

#REF! Cost of MS plate kg 1291.250 45.00 58106.24 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 1229.762 6.63 8153.32 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 61.488 27.00 1660.18

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 13040.13 130.40 (C)

Material cost per meter Rs/meter 64729.78

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(2.2684-(0.0222*2+0.012))*0.012*1*2080= kg 173.45

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*2.2684*1= sqmt 7.126 100.33 714.98 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(2.2684-(0.0222*2+0.012))*1= sqmt 6.949 450.00 3127.14 (E)

Total (A+B+C+D+E) 68571.90Total without ED 61043.09

Add Water Charges @ 1% 1% 610.43Add CPOH @ 15% 15% 9248.03

Total cost per meter for pipe 70901.55Total cost per kg for specials 50.53

2.5.1.68

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =2.564 0.02

thickness of CML (t2) =

Length of pipe =

0.012 1.0

2200 mm nominal dia (clear internal dia) of pipe with 22.2 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

2500 mm nominal dia (clear internal dia) of pipe with 20.0 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 142 Schedule of Rates 2014 - 2015

Page 62: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outsideWeight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(2.564-0.02)*0.02*1*7850= kg 1254.777Add 5 % wastage

5% kg 62.739Total Weight kg 1317.516

#REF! Cost of MS plate kg 1317.516 45.00 59288.22 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 1254.777 6.63 8319.17 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 62.739 27.00 1693.95

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 14489.04 144.89 (C)

Material cost per meter Rs/meter 66058.34

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(2.564-(0.02*2+0.012))*0.012*1*2080= kg 196.98

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*2.564*1= sqmt 8.055 100.33 808.15 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(2.564-(0.02*2+0.012))*1= sqmt 7.892 450.00 3551.26 (E)

Total (A+B+C+D+E) 70417.75Total without ED 62687.48

Add Water Charges @ 1% 1% 626.87Add CPOH @ 15% 15% 9497.15

Total cost per meter for pipe 72811.51Total cost per kg for specials 50.15

2.5.1.69

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =2.5684 0.0222

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(2.5684-0.0222)*0.0222*1*7850= kg 1394.007Add 5 % wastage

5% kg 69.700Total Weight kg 1463.708

#REF! Cost of MS plate kg 1463.708 45.00 65866.84 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 1394.007 6.63 9242.27 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 69.700 27.00 1881.91

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 14489.04 144.89 (C)

Material cost per meter Rs/meter 73372.09

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(2.5684-(0.0222*2+0.012))*0.012*1*2080= kg 196.98

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*2.5684*1= sqmt 8.069 100.33 809.54 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(2.5684-(0.0222*2+0.012))*1= sqmt 7.892 450.00 3551.26 (E)

Total (A+B+C+D+E) 77732.89Total without ED 69197.93

Add Water Charges @ 1% 1% 691.98Add CPOH @ 15% 15% 10483.49

Total cost per meter for pipe 80373.40Total cost per kg for specials 50.52

2500 mm nominal dia (clear internal dia) of pipe with 22.2 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 143 Schedule of Rates 2014 - 2015

Page 63: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outside2.5.1.70

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =2.574 0.025

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS Plate = pi()*(d-t1)*t1*L*7850(3.1416)*(2.574-0.025)*0.025*1*7850= kg 1571.554Add 5 % wastage

5% kg 78.578Total Weight kg 1650.132

#REF! Cost of MS plate kg 1650.1 45.00 74255.94 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 1571.6 6.63 10419.40 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 78.578 27.00 2121.60

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 14489.04 144.89 (C)

Material cost per meter Rs/meter 82698.63

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(2.574-(0.025*2+0.012))*0.012*1*2080= kg 196.98

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*2.574*1= sqmt 8.086 100.33 811.31 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(2.574-(0.025*2+0.012))*1= sqmt 7.892 450.00 3551.26 (E)

Total (A+B+C+D+E) 87061.20Total without ED 77500.09

Add Water Charges @ 1% 1% 775.00Add CPOH @ 15% 15% 11741.26

Total cost per meter for pipe 90016.36Total cost per kg for specials 50.90

2500 mm nominal dia (clear internal dia) of pipe with 25.0 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 144 Schedule of Rates 2014 - 2015

Page 64: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

2.5.2

2.5.2.1

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.172 0.005

thickness of CML (t2) =

Length of pipe =

0.006 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.172-0.005)*0.005*1*7850= kg 20.592Add 2 % wastage

2% kg 0.412Total Weight kg 21.004

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 21.004 34.21 718.56 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 20.592 6.63 136.53 (B)

Quotation_Volume III_pg no_272 Cost of scrap kg 0.412 27.00 11.12

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 289.78 2.90 (C)

Material cost per meter Rs/meter 846.86

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.172-(0.005*2+0.006))*0.006*1*2080= kg 6.12

Outside epoxy coatingQuotation_Volume

III_pg no_448 Area of coating = pi()*d*L

(3.14159265358979)*0.172*1= sqmt 0.540 100.33 54.21 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.172-(0.005*2+0.006))*1= sqmt 0.490 450.00 220.54 (E)

Total (A+B+C+D+E) 1121.62Total without ED 998.55

Add Water Charges @ 1% 1% 9.99Add CPOH @ 15% 15% 151.28

Total cost per meter for pipe 1159.82Total cost per kg for specials 43.42

2.5.2.2

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.222 0.005

thickness of CML (t2) =

Length of pipe =

0.006 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.222-0.005)*0.005*1*7850= kg 26.758Add 2 % wastage

2% kg 0.535Total Weight kg 27.293

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 27.293 34.21 933.70 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 26.758 6.63 177.40 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.535 27.00 14.45

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 471.38 4.71 (C)

Material cost per meter Rs/meter 1101.36

Providing Mild Steel Pipes / specials fabricated / manufactured out of MS coil of steel grade Fe410 as per IS 3589:2001; internally lined withcement mortar lining and external / Outside epoxy coating; minimum thickness of M.S. Coil as specified; complete in all respect; with uptodate amendments in relevant IS codes and as directed by Engineer-in-charge. The rates are excluding excise duty component.

200 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, 6 mm thick internal cement mortar lining and exterior / outside epoxycoating

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, 6 mm thick internal cement mortar lining and exterior / outside epoxycoating

Delhi Jal Board 155 Schedule of rates 2014-2015

Page 65: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.222-(0.005*2+0.006))*0.006*1*2080= kg 8.08

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.222*1= sqmt 0.697 100.33 69.97 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.222-(0.005*2+0.006))*1= sqmt 0.647 450.00 291.23 (E)

Total (A+B+C+D+E) 1462.56Total without ED 1302.19

Add Water Charges @ 1% 1% 13.02Add CPOH @ 15% 15% 197.28

Total cost per meter for pipe 1512.50Total cost per kg for specials 43.42

2.5.2.3

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.224 0.006

thickness of CML (t2) =

Length of pipe =

0.006 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.224-0.006)*0.006*1*7850= kg 32.257Add 2 % wastage

2% kg 0.645Total Weight kg 32.902

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 32.902 34.21 1125.60 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 32.257 6.63 213.87 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.645 27.00 17.42

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 471.38 4.71 (C)

Material cost per meter Rs/meter 1326.76

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.224-(0.006*2+0.006))*0.006*1*2080= kg 8.08

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.224*1= sqmt 0.704 100.33 70.60 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.224-(0.006*2+0.006))*1= sqmt 0.647 450.00 291.23 (E)

Total (A+B+C+D+E) 1688.59Total without ED 1503.36

Add Water Charges @ 1% 1% 15.03Add CPOH @ 15% 15% 227.76

Total cost per meter for pipe 1746.15Total cost per kg for specials 43.29

2.5.2.4

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.2246 0.0063

thickness of CML (t2) =

Length of pipe =

0.006 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.2246-0.0063)*0.0063*1*7850= kg 33.917Add 2 % wastage

2% kg 0.678

200 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick coil, 6 mm thick internal cement mortar lining and exterior / outside epoxycoating

200 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick coil, 6 mm thick internal cement mortar lining and exterior / outside epoxycoating

Delhi Jal Board 156 Schedule of rates 2014-2015

Page 66: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Total Weight kg 34.595

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 34.595 34.21 1183.51 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 33.917 6.63 224.87 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.678 27.00 18.32

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 471.38 4.71 (C)

Material cost per meter Rs/meter 1394.77

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.2246-(0.0063*2+0.006))*0.006*1*2080= kg 8.08

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.2246*1= sqmt 0.706 100.33 70.79 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.2246-(0.0063*2+0.006))*1= sqmt 0.647 450.00 291.23 (E)

Total (A+B+C+D+E) 1756.79Total without ED 1564.06

Add Water Charges @ 1% 1% 15.64Add CPOH @ 15% 15% 236.95

Total cost per meter for pipe 1816.65Total cost per kg for specials 43.26

2.5.2.5

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.272 0.005

thickness of CML (t2) =

Length of pipe =

0.006 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.272-0.005)*0.005*1*7850= kg 32.923Add 2 % wastage

2% kg 0.658Total Weight kg 33.582

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 33.582 34.21 1148.83 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 32.923 6.63 218.28 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.658 27.00 17.78

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 669.85 6.70 (C)

Material cost per meter Rs/meter 1356.03

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.272-(0.005*2+0.006))*0.006*1*2080= kg 10.04

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.272*1= sqmt 0.855 100.33 85.73 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.272-(0.005*2+0.006))*1= sqmt 0.804 450.00 361.91 (E)

Total (A+B+C+D+E) 1803.68Total without ED 1606.00

Add Water Charges @ 1% 1% 16.06Add CPOH @ 15% 15% 243.31

Total cost per meter for pipe 1865.37Total cost per kg for specials 43.42

2.5.2.6

250 mm nominal dia (clear internal dia) of pipe with 5.0 mm thick coil, 6 mm thick internal cement mortar lining and exterior / outside epoxycoating

250 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick coil, 6 mm thick internal cement mortar lining and exterior / outside epoxycoating

Delhi Jal Board 157 Schedule of rates 2014-2015

Page 67: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.274 0.006 0

thickness of CML (t2) =

Length of pipe =

0.006 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.274-0.006)*0.006*1*7850= kg 39.656Add 2 % wastage

2% kg 0.793Total Weight kg 40.449

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 40.449 34.21 1383.76 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 39.656 6.63 262.92 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.793 27.00 21.41

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 669.85 6.70 (C)

Material cost per meter Rs/meter 1631.97

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.274-(0.006*2+0.006))*0.006*1*2080= kg 10.04

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.274*1= sqmt 0.861 100.33 86.36 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.274-(0.006*2+0.006))*1= sqmt 0.804 450.00 361.91 (E)

Total (A+B+C+D+E) 2080.24Total without ED 1852.14

Add Water Charges @ 1% 1% 18.52Add CPOH @ 15% 15% 280.60

Total cost per meter for pipe 2151.26Total cost per kg for specials 43.29

2.5.2.7

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.2746 0.0063

thickness of CML (t2) =

Length of pipe =

0.006 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.2746-0.0063)*0.0063*1*7850= kg 41.685Add 2 % wastage

2% kg 0.834Total Weight kg 42.519

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 42.519 34.21 1454.58 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 41.685 6.63 276.37 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.834 27.00 22.51

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 669.85 6.70 (C)

Material cost per meter Rs/meter 1715.14

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.2746-(0.0063*2+0.006))*0.006*1*2080= kg 10.04

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.2746*1= sqmt 0.863 100.33 86.55 (D)

250 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick coil, 6 mm thick internal cement mortar lining and exterior / outside epoxycoating

Delhi Jal Board 158 Schedule of rates 2014-2015

Page 68: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.2746-(0.0063*2+0.006))*1= sqmt 0.804 450.00 361.91 (E)

Total (A+B+C+D+E) 2163.60Total without ED 1926.34

Add Water Charges @ 1% 1% 19.26Add CPOH @ 15% 15% 291.84

Total cost per meter for pipe 2237.44Total cost per kg for specials 43.26

2.5.2.8

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.322 0.005 0

thickness of CML (t2) =

Length of pipe =

0.006 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.322-0.005)*0.005*1*7850= kg 39.088Add 2 % wastage

2% kg 0.782Total Weight kg 39.870

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 39.870 34.21 1363.97 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 39.088 6.63 259.16 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.782 27.00 21.11

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 827.95 8.28 (C)

Material cost per meter Rs/meter 1610.30

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.322-(0.005*2+0.006))*0.006*1*2080= kg 12.00

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.322*1= sqmt 1.012 100.33 101.49 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.322-(0.005*2+0.006))*1= sqmt 0.961 450.00 432.60 (E)

Total (A+B+C+D+E) 2144.39Total without ED 1909.41

Add Water Charges @ 1% 1% 19.09Add CPOH @ 15% 15% 289.28

Total cost per meter for pipe 2217.78Total cost per kg for specials 43.41

2.5.2.9

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.3232 0.0056

thickness of CML (t2) =

Length of pipe =

0.006 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.3232-0.0056)*0.0056*1*7850= kg 43.862Add 2 % wastage

2% kg 0.877Total Weight kg 44.739

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 44.739 34.21 1530.54 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 43.862 6.63 290.80 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.877 27.00 23.69

300 mm nominal dia (clear internal dia) of pipe with 5.6 mm thick coil, 6 mm thick internal cement mortar lining and exterior / outside epoxycoating

300 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, 6 mm thick internal cement mortar lining and exterior / outside epoxycoating

Delhi Jal Board 159 Schedule of rates 2014-2015

Page 69: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 827.95 8.28 (C)

Material cost per meter Rs/meter 1805.94

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.3232-(0.0056*2+0.006))*0.006*1*2080= kg 12.00

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.3232*1= sqmt 1.015 100.33 101.87 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.3232-(0.0056*2+0.006))*1= sqmt 0.961 450.00 432.60 (E)

Total (A+B+C+D+E) 2340.41Total without ED 2083.86

Add Water Charges @ 1% 1% 20.84Add CPOH @ 15% 15% 315.71

Total cost per meter for pipe 2420.41Total cost per kg for specials 43.33

2.5.2.10

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.3262 0.0071 0

thickness of CML (t2) =

Length of pipe =

0.006 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.3262-0.0071)*0.0071*1*7850= kg 55.873Add 2 % wastage

2% kg 1.117Total Weight kg 56.991

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 56.991 34.21 1949.67 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 55.873 6.63 370.44 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.117 27.00 30.17

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 827.95 8.28 (C)

Material cost per meter Rs/meter 2298.22

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.3262-(0.0071*2+0.006))*0.006*1*2080= kg 12.00

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.3262*1= sqmt 1.025 100.33 102.82 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.3262-(0.0071*2+0.006))*1= sqmt 0.961 450.00 432.60 (E)

Total (A+B+C+D+E) 2833.63Total without ED 2522.83

Add Water Charges @ 1% 1% 25.23Add CPOH @ 15% 15% 382.21

Total cost per meter for pipe 2930.27Total cost per kg for specials 43.17

2.5.2.11

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.374 0.005 0

thickness of CML (t2) =

Length of pipe =

350 mm nominal dia (clear internal dia) of pipe with 5.0 mm thick coil, 7 mm thick internal cement mortar lining and exterior / outside epoxycoating

300 mm nominal dia (clear internal dia) of pipe with 7.1 mm thick coil, 6 mm thick internal cement mortar lining and exterior / outside epoxycoating

Delhi Jal Board 160 Schedule of rates 2014-2015

Page 70: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

0.007 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.374-0.005)*0.005*1*7850= kg 45.500Add 2 % wastage

2% kg 0.910Total Weight kg 46.410

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 46.410 34.21 1587.71 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 45.500 6.63 301.67 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.910 27.00 24.57

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1159.12 11.59 (C)

Material cost per meter Rs/meter 1876.40

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.374-(0.005*2+0.007))*0.007*1*2080= kg 16.33

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.374*1= sqmt 1.175 100.33 117.88 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.374-(0.005*2+0.007))*1= sqmt 1.122 450.00 504.70 (E)

Total (A+B+C+D+E) 2498.98Total without ED 2225.36

Add Water Charges @ 1% 1% 22.25Add CPOH @ 15% 15% 337.14

Total cost per meter for pipe 2584.76Total cost per kg for specials 41.80

2.5.2.12

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.3752 0.0056 0

thickness of CML (t2) =

Length of pipe =

0.007 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.3752-0.0056)*0.0056*1*7850= kg 51.043Add 2 % wastage

2% kg 1.021Total Weight kg 52.064

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 52.064 34.21 1781.13 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 51.043 6.63 338.42 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.021 27.00 27.56

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1159.12 11.59 (C)

Material cost per meter Rs/meter 2103.58

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.3752-(0.0056*2+0.007))*0.007*1*2080= kg 16.33

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.3752*1= sqmt 1.179 100.33 118.26 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.3752-(0.0056*2+0.007))*1= sqmt 1.122 450.00 504.70 (E)

Total (A+B+C+D+E) 2726.53Total without ED 2427.88

Add Water Charges @ 1% 1% 24.28

350 mm nominal dia (clear internal dia) of pipe with 5.6 mm thick coil, 7 mm thick internal cement mortar lining and exterior / outside epoxycoating

Delhi Jal Board 161 Schedule of rates 2014-2015

Page 71: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add CPOH @ 15% 15% 367.82Total cost per meter for pipe 2819.98

Total cost per kg for specials 41.86

2.5.2.13

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.38 0.008 0

thickness of CML (t2) =

Length of pipe =

0.007 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.38-0.008)*0.008*1*7850= kg 73.393Add 2 % wastage

2% kg 1.468Total Weight kg 74.860

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 74.860 34.21 2561.00 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 73.393 6.63 486.59 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.468 27.00 39.63

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1159.12 11.59 (C)

Material cost per meter Rs/meter 3019.55

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.38-(0.008*2+0.007))*0.007*1*2080= kg 16.33

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.38*1= sqmt 1.194 100.33 119.77 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.38-(0.008*2+0.007))*1= sqmt 1.122 450.00 504.70 (E)

Total (A+B+C+D+E) 3644.02Total without ED 3244.44

Add Water Charges @ 1% 1% 32.44Add CPOH @ 15% 15% 491.53

Total cost per meter for pipe 3768.42Total cost per kg for specials 42.00

2.5.2.14

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.424 0.005 0

thickness of CML (t2) =

Length of pipe =

0.007 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.424-0.005)*0.005*1*7850= kg 51.666Add 2 % wastage

2% kg 1.033Total Weight kg 52.699

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 52.699 34.21 1802.85 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 51.666 6.63 342.54 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.033 27.00 27.90

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1580.62 15.81 (C)

Material cost per meter Rs/meter 2133.30

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

400 mm nominal dia (clear internal dia) of pipe with 5.0 mm thick coil, 7 mm thick internal cement mortar lining and exterior / outside epoxycoating

350 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick coil, 7 mm thick internal cement mortar lining and exterior / outside epoxycoating

Delhi Jal Board 162 Schedule of rates 2014-2015

Page 72: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

(3.1416)*(0.424-(0.005*2+0.007))*0.007*1*2080= kg 18.62

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.424*1= sqmt 1.332 100.33 133.64 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.424-(0.005*2+0.007))*1= sqmt 1.279 450.00 575.38 (E)

Total (A+B+C+D+E) 2842.33Total without ED 2531.40

Add Water Charges @ 1% 1% 25.31Add CPOH @ 15% 15% 383.51

Total cost per meter for pipe 2940.22Total cost per kg for specials 41.83

2.5.2.15

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.426 0.006 0

thickness of CML (t2) =

Length of pipe =

0.007 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.426-0.006)*0.006*1*7850= kg 62.147Add 2 % wastage

2% kg 1.243Total Weight kg 63.390

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 63.390 34.21 2168.59 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 62.147 6.63 412.03 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.243 27.00 33.56

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1580.62 15.81 (C)

Material cost per meter Rs/meter 2562.87

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.426-(0.006*2+0.007))*0.007*1*2080= kg 18.62

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.426*1= sqmt 1.338 100.33 134.27 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.426-(0.006*2+0.007))*1= sqmt 1.279 450.00 575.38 (E)

Total (A+B+C+D+E) 3272.52Total without ED 2914.27

Add Water Charges @ 1% 1% 29.14Add CPOH @ 15% 15% 441.51

Total cost per meter for pipe 3384.93Total cost per kg for specials 41.91

2.5.2.16

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.4266 0.0063

thickness of CML (t2) =

Length of pipe =

0.007 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.4266-0.0063)*0.0063*1*7850= kg 65.301Add 2 % wastage

2% kg 1.306Total Weight kg 66.607

400 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick coil, 7 mm thick internal cement mortar lining and exterior / outside epoxycoating

400 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick coil, 7 mm thick internal cement mortar lining and exterior / outside epoxycoating

Delhi Jal Board 163 Schedule of rates 2014-2015

Page 73: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 66.607 34.21 2278.64 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 65.301 6.63 432.95 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.306 27.00 35.26

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1580.62 15.81 (C)

Material cost per meter Rs/meter 2692.13

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.4266-(0.0063*2+0.007))*0.007*1*2080= kg 18.62

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.4266*1= sqmt 1.340 100.33 134.46 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.4266-(0.0063*2+0.007))*1= sqmt 1.279 450.00 575.38 (E)

Total (A+B+C+D+E) 3401.97Total without ED 3029.48

Add Water Charges @ 1% 1% 30.29Add CPOH @ 15% 15% 458.97

Total cost per meter for pipe 3518.74Total cost per kg for specials 41.93

2.5.2.17

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.4316 0.0088 0

thickness of CML (t2) =

Length of pipe =

0.007 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.4316-0.0088)*0.0088*1*7850= kg 91.757Add 2 % wastage

2% kg 1.835Total Weight kg 93.592

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 93.592 34.21 3201.80 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 91.757 6.63 608.35 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.835 27.00 49.55

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1580.62 15.81 (C)

Material cost per meter Rs/meter 3776.40

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.4316-(0.0088*2+0.007))*0.007*1*2080= kg 18.62

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.4316*1= sqmt 1.356 100.33 136.04 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.4316-(0.0088*2+0.007))*1= sqmt 1.279 450.00 575.38 (E)

Total (A+B+C+D+E) 4487.82Total without ED 3995.88

Add Water Charges @ 1% 1% 39.96Add CPOH @ 15% 15% 605.38

Total cost per meter for pipe 4641.22Total cost per kg for specials 42.05

2.5.2.18

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

400 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick coil, 7 mm thick internal cement mortar lining and exterior / outside epoxycoating

450 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick coil, 7 mm thick internal cement mortar lining and exterior / outside epoxycoating

Delhi Jal Board 164 Schedule of rates 2014-2015

Page 74: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.476 0.006 0

thickness of CML (t2) =

Length of pipe =

0.007 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.476-0.006)*0.006*1*7850= kg 69.545Add 2 % wastage

2% kg 1.391Total Weight kg 70.936

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 70.936 34.21 2426.75 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 69.545 6.63 461.09 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.391 27.00 37.55

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 2869.60

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.476-(0.006*2+0.007))*0.007*1*2080= kg 20.90

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.476*1= sqmt 1.495 100.33 150.03 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.476-(0.006*2+0.007))*1= sqmt 1.436 450.00 646.07 (E)

Total (A+B+C+D+E) 3665.70Total without ED 3264.59

Add Water Charges @ 1% 1% 32.65Add CPOH @ 15% 15% 494.58

Total cost per meter for pipe 3791.82Total cost per kg for specials 41.92

2.5.2.19

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.4766 0.0063 0

thickness of CML (t2) =

Length of pipe =

0.007 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.4766-0.0063)*0.0063*1*7850= kg 73.069Add 2 % wastage

2% kg 1.461Total Weight kg 74.531

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 74.531 34.21 2549.71 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 73.069 6.63 484.45 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.461 27.00 39.46

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 3014.02

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.4766-(0.0063*2+0.007))*0.007*1*2080= kg 20.90

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.4766*1= sqmt 1.497 100.33 150.22 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.4766-(0.0063*2+0.007))*1= sqmt 1.436 450.00 646.07 (E)

450 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick coil, 7 mm thick internal cement mortar lining and exterior / outside epoxycoating

Delhi Jal Board 165 Schedule of rates 2014-2015

Page 75: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Total (A+B+C+D+E) 3810.31Total without ED 3393.29

Add Water Charges @ 1% 1% 33.93Add CPOH @ 15% 15% 514.08

Total cost per meter for pipe 3941.31Total cost per kg for specials 41.94

2.5.2.20

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.484 0.01 0

thickness of CML (t2) =

Length of pipe =

0.007 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.484-0.01)*0.01*1*7850= kg 116.896Add 2 % wastage

2% kg 2.338Total Weight kg 119.233

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 119.233 34.21 4079.01 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 116.896 6.63 775.02 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.338 27.00 63.12

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 4810.22

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.484-(0.01*2+0.007))*0.007*1*2080= kg 20.90

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.484*1= sqmt 1.521 100.33 152.55 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.484-(0.01*2+0.007))*1= sqmt 1.436 450.00 646.07 (E)

Total (A+B+C+D+E) 5608.84Total without ED 4993.97

Add Water Charges @ 1% 1% 49.94Add CPOH @ 15% 15% 756.59

Total cost per meter for pipe 5800.50Total cost per kg for specials 42.09

2.5.2.21

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.526 0.006 0

thickness of CML (t2) =

Length of pipe =

0.007 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.526-0.006)*0.006*1*7850= kg 76.944Add 2 % wastage

2% kg 1.539Total Weight kg 78.483

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 78.483 34.21 2684.91 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 76.944 6.63 510.14 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.539 27.00 41.55

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 3172.82

500 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick coil, 7 mm thick internal cement mortar lining and exterior / outside epoxycoating

450 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick coil, 7 mm thick internal cement mortar lining and exterior / outside epoxycoating

Delhi Jal Board 166 Schedule of rates 2014-2015

Page 76: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.526-(0.006*2+0.007))*0.007*1*2080= kg 23.19

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.526*1= sqmt 1.652 100.33 165.79 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.526-(0.006*2+0.007))*1= sqmt 1.593 450.00 716.75 (E)

Total (A+B+C+D+E) 4055.37Total without ED 3611.39

Add Water Charges @ 1% 1% 36.11Add CPOH @ 15% 15% 547.13

Total cost per meter for pipe 4194.63Total cost per kg for specials 41.89

2.5.2.22

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.5266 0.0063 0

thickness of CML (t2) =

Length of pipe =

0.007 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.5266-0.0063)*0.0063*1*7850= kg 80.838Add 2 % wastage

2% kg 1.617Total Weight kg 82.454

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 82.454 34.21 2820.79 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 80.838 6.63 535.95 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.617 27.00 43.65

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 3332.41

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.5266-(0.0063*2+0.007))*0.007*1*2080= kg 23.19

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.5266*1= sqmt 1.654 100.33 165.98 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.5266-(0.0063*2+0.007))*1= sqmt 1.593 450.00 716.75 (E)

Total (A+B+C+D+E) 4215.14Total without ED 3753.59

Add Water Charges @ 1% 1% 37.54Add CPOH @ 15% 15% 568.67

Total cost per meter for pipe 4359.79Total cost per kg for specials 41.91

2.5.2.23

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.536 0.011 0

thickness of CML (t2) =

Length of pipe =

0.007 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.536-0.011)*0.011*1*7850= kg 142.420

500 mm nominal dia (clear internal dia) of pipe with 11.0 mm thick coil, 7 mm thick internal cement mortar lining and exterior / outside epoxycoating

500 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick coil, 7 mm thick internal cement mortar lining and exterior / outside epoxycoating

Delhi Jal Board 167 Schedule of rates 2014-2015

Page 77: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add 2 % wastage2% kg 2.848

Total Weight kg 145.269

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 145.269 34.21 4969.67 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 142.420 6.63 944.25 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.848 27.00 76.91

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 5856.33

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.536-(0.011*2+0.007))*0.007*1*2080= kg 23.19

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.536*1= sqmt 1.684 100.33 168.94 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.536-(0.011*2+0.007))*1= sqmt 1.593 450.00 716.75 (E)

Total (A+B+C+D+E) 6742.03Total without ED 6002.51

Add Water Charges @ 1% 1% 60.03Add CPOH @ 15% 15% 909.38

Total cost per meter for pipe 6971.91Total cost per kg for specials 42.10

2.5.2.24

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.626 0.006 0

thickness of CML (t2) =

Length of pipe =

0.007 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.626-0.006)*0.006*1*7850= kg 91.741Add 2 % wastage

2% kg 1.835Total Weight kg 93.576

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 93.576 34.21 3201.24 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 91.741 6.63 608.24 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.835 27.00 49.54

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 3788.92

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.626-(0.006*2+0.007))*0.007*1*2080= kg 27.77

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.626*1= sqmt 1.967 100.33 197.31 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.626-(0.006*2+0.007))*1= sqmt 1.907 450.00 858.13 (E)

Total (A+B+C+D+E) 4844.36Total without ED 4314.65

Add Water Charges @ 1% 1% 43.15Add CPOH @ 15% 15% 653.67

Total cost per meter for pipe 5011.47Total cost per kg for specials 41.93

600 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick coil, 7 mm thick internal cement mortar lining and exterior / outside epoxycoating

Delhi Jal Board 168 Schedule of rates 2014-2015

Page 78: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

2.5.2.25

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.6266 0.0063 0

thickness of CML (t2) =

Length of pipe =

0.007 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.6266-0.0063)*0.0063*1*7850= kg 96.374Add 2 % wastage

2% kg 1.927Total Weight kg 98.302

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 98.302 34.21 3362.93 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 96.374 6.63 638.96 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.927 27.00 52.04

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 3978.83

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.6266-(0.0063*2+0.007))*0.007*1*2080= kg 27.77

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.6266*1= sqmt 1.969 100.33 197.50 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.6266-(0.0063*2+0.007))*1= sqmt 1.907 450.00 858.13 (E)

Total (A+B+C+D+E) 5034.46Total without ED 4483.84

Add Water Charges @ 1% 1% 44.84Add CPOH @ 15% 15% 679.30

Total cost per meter for pipe 5207.98Total cost per kg for specials 41.95

2.5.2.26

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.63 0.008 0

thickness of CML (t2) =

Length of pipe =

0.007 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.63-0.008)*0.008*1*7850= kg 122.716Add 2 % wastage

2% kg 2.454Total Weight kg 125.170

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 125.170 34.21 4282.10 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 122.716 6.63 813.60 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.454 27.00 66.27

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 5058.41

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.63-(0.008*2+0.007))*0.007*1*2080= kg 27.77

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

600 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick coil, 7 mm thick internal cement mortar lining and exterior / outside epoxycoating

600 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick coil, 7 mm thick internal cement mortar lining and exterior / outside epoxycoating

Delhi Jal Board 169 Schedule of rates 2014-2015

Page 79: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

(3.14159265358979)*0.63*1= sqmt 1.979 100.33 198.57 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.63-(0.008*2+0.007))*1= sqmt 1.907 450.00 858.13 (E)

Total (A+B+C+D+E) 6115.11Total without ED 5445.61

Add Water Charges @ 1% 1% 54.46Add CPOH @ 15% 15% 825.01

Total cost per meter for pipe 6325.08Total cost per kg for specials 42.03

2.5.2.27

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.639 0.0125 0

thickness of CML (t2) =

Length of pipe =

0.007 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.639-0.0125)*0.0125*1*7850= kg 193.130Add 2 % wastage

2% kg 3.863Total Weight kg 196.993

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 196.993 34.21 6739.18 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 193.130 6.63 1280.45 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.863 27.00 104.29

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 7944.32

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.639-(0.0125*2+0.007))*0.007*1*2080= kg 27.77

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.639*1= sqmt 2.007 100.33 201.41 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.639-(0.0125*2+0.007))*1= sqmt 1.907 450.00 858.13 (E)

Total (A+B+C+D+E) 9003.86Total without ED 8016.59

Add Water Charges @ 1% 1% 80.17Add CPOH @ 15% 15% 1214.51

Total cost per meter for pipe 9311.27Total cost per kg for specials 42.15

2.5.2.28

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.73 0.006 0

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.73-0.006)*0.006*1*7850= kg 107.130Add 2 % wastage

2% kg 2.143Total Weight kg 109.272

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 109.272 34.21 3738.23 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 107.130 6.63 710.27 (B)

600 mm nominal dia (clear internal dia) of pipe with 12.5 mm thick coil, 7 mm thick internal cement mortar lining and exterior / outside epoxycoating

700 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside epoxycoating

Delhi Jal Board 170 Schedule of rates 2014-2015

Page 80: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.143 27.00 57.85

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 4419.62

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.73-(0.006*2+0.009))*0.009*1*2080= kg 41.70

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.73*1= sqmt 2.293 100.33 230.09 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.73-(0.006*2+0.009))*1= sqmt 2.227 450.00 1002.33 (E)

Total (A+B+C+D+E) 5652.04Total without ED 5033.48

Add Water Charges @ 1% 1% 50.33Add CPOH @ 15% 15% 762.57

Total cost per meter for pipe 5846.39Total cost per kg for specials 39.28

2.5.2.29

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.7306 0.0063 0

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.7306-0.0063)*0.0063*1*7850= kg 112.533Add 2 % wastage

2% kg 2.251Total Weight kg 114.783

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 114.783 34.21 3926.77 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 112.533 6.63 746.09 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.251 27.00 60.77

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 4641.07

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.7306-(0.0063*2+0.009))*0.009*1*2080= kg 41.70

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.7306*1= sqmt 2.295 100.33 230.28 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.7306-(0.0063*2+0.009))*1= sqmt 2.227 450.00 1002.33 (E)

Total (A+B+C+D+E) 5873.67Total without ED 5230.74

Add Water Charges @ 1% 1% 52.31Add CPOH @ 15% 15% 792.46

Total cost per meter for pipe 6075.50Total cost per kg for specials 39.39

2.5.2.30

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.7322 0.0071 0

700 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside epoxycoating

700 mm nominal dia (clear internal dia) of pipe with 7.1 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside epoxycoating

Delhi Jal Board 171 Schedule of rates 2014-2015

Page 81: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.7322-0.0071)*0.0071*1*7850= kg 126.963Add 2 % wastage

2% kg 2.539Total Weight kg 129.502

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 129.502 34.21 4430.29 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 126.963 6.63 841.76 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.539 27.00 68.56

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 5232.47

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.7322-(0.0071*2+0.009))*0.009*1*2080= kg 41.70

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.7322*1= sqmt 2.300 100.33 230.78 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.7322-(0.0071*2+0.009))*1= sqmt 2.227 450.00 1002.33 (E)

Total (A+B+C+D+E) 6465.58Total without ED 5757.53

Add Water Charges @ 1% 1% 57.58Add CPOH @ 15% 15% 872.27

Total cost per meter for pipe 6687.37Total cost per kg for specials 39.65

2.5.2.31

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.734 0.008 0

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.734-0.008)*0.008*1*7850= kg 143.234Add 2 % wastage

2% kg 2.865Total Weight kg 146.099

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 146.099 34.21 4998.07 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 143.234 6.63 949.64 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.865 27.00 77.35

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 5899.35

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.734-(0.008*2+0.009))*0.009*1*2080= kg 41.70

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.734*1= sqmt 2.306 100.33 231.35 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.734-(0.008*2+0.009))*1= sqmt 2.227 450.00 1002.33 (E)

Total (A+B+C+D+E) 7133.02

700 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside epoxycoating

Delhi Jal Board 172 Schedule of rates 2014-2015

Page 82: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Total without ED 6351.55Add Water Charges @ 1% 1% 63.52

Add CPOH @ 15% 15% 962.26Total cost per meter for pipe 7377.33

Total cost per kg for specials 39.89

2.5.2.32

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.7464 0.0142 0

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.7464-0.0142)*0.0142*1*7850= kg 256.412Add 2 % wastage

2% kg 5.128Total Weight kg 261.540

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 261.540 34.21 8947.34 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 256.412 6.63 1700.01 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 5.128 27.00 138.46

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 10537.87

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.7464-(0.0142*2+0.009))*0.009*1*2080= kg 41.70

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.7464*1= sqmt 2.345 100.33 235.26 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.7464-(0.0142*2+0.009))*1= sqmt 2.227 450.00 1002.33 (E)

Total (A+B+C+D+E) 11775.45Total without ED 10483.30

Add Water Charges @ 1% 1% 104.83Add CPOH @ 15% 15% 1588.22

Total cost per meter for pipe 12176.35Total cost per kg for specials 40.85

2.5.2.33

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.8322 0.0071 0

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.8322-0.0071)*0.0071*1*7850= kg 144.472Add 2 % wastage

2% kg 2.889Total Weight kg 147.362

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 147.362 34.21 5041.28 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 144.472 6.63 957.85 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.889 27.00 78.02

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 5950.09

700 mm nominal dia (clear internal dia) of pipe with 14.2 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside epoxycoating

800 mm nominal dia (clear internal dia) of pipe with 7.1 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside epoxycoating

Delhi Jal Board 173 Schedule of rates 2014-2015

Page 83: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.8322-(0.0071*2+0.009))*0.009*1*2080= kg 47.58

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.8322*1= sqmt 2.614 100.33 262.30 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.8322-(0.0071*2+0.009))*1= sqmt 2.542 450.00 1143.70 (E)

Total (A+B+C+D+E) 7356.10Total without ED 6550.09

Add Water Charges @ 1% 1% 65.50Add CPOH @ 15% 15% 992.34

Total cost per meter for pipe 7607.93Total cost per kg for specials 39.61

2.5.2.34

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.834 0.008 0

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.834-0.008)*0.008*1*7850= kg 162.963Add 2 % wastage

2% kg 3.259Total Weight kg 166.222

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 166.222 34.21 5686.51 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 162.963 6.63 1080.45 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.259 27.00 88.00

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 6707.94

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.834-(0.008*2+0.009))*0.009*1*2080= kg 47.58

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.834*1= sqmt 2.620 100.33 262.87 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.834-(0.008*2+0.009))*1= sqmt 2.542 450.00 1143.70 (E)

Total (A+B+C+D+E) 8114.50Total without ED 7225.07

Add Water Charges @ 1% 1% 72.25Add CPOH @ 15% 15% 1094.60

Total cost per meter for pipe 8391.92Total cost per kg for specials 39.86

2.5.2.35

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.854 0.018 0

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.854-0.018)*0.018*1*7850= kg 371.106Add 2 % wastage

2% kg 7.422

800 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside epoxycoating

800 mm nominal dia (clear internal dia) of pipe with 18.0 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside epoxycoating

Delhi Jal Board 174 Schedule of rates 2014-2015

Page 84: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Total Weight kg 378.528

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 378.528 34.21 12949.55 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 371.106 6.63 2460.43 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 7.422 27.00 200.40

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 15238.57

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.854-(0.018*2+0.009))*0.009*1*2080= kg 47.58

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.854*1= sqmt 2.683 100.33 269.17 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.854-(0.018*2+0.009))*1= sqmt 2.542 450.00 1143.70 (E)

Total (A+B+C+D+E) 16651.44Total without ED 14822.91

Add Water Charges @ 1% 1% 148.23Add CPOH @ 15% 15% 2245.67

Total cost per meter for pipe 17216.81Total cost per kg for specials 41.12

2.5.2.36

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.934 0.008 0

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.934-0.008)*0.008*1*7850= kg 182.692Add 2 % wastage

2% kg 3.654Total Weight kg 186.346

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 186.346 34.21 6374.95 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 182.692 6.63 1211.25 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.654 27.00 98.65

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 4346.71 43.47 (C)

Material cost per meter Rs/meter 7531.02

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.934-(0.008*2+0.009))*0.009*1*2080= kg 53.46

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.934*1= sqmt 2.934 100.33 294.39 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.934-(0.008*2+0.009))*1= sqmt 2.856 450.00 1285.07 (E)

Total (A+B+C+D+E) 9110.47Total without ED 8113.07

Add Water Charges @ 1% 1% 81.13Add CPOH @ 15% 15% 1229.13

Total cost per meter for pipe 9423.33Total cost per kg for specials 39.90

2.5.2.37

900 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside epoxycoating

900 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside epoxycoating

Delhi Jal Board 175 Schedule of rates 2014-2015

Page 85: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.9356 0.0088 0

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.9356-0.0088)*0.0088*1*7850= kg 201.135Add 2 % wastage

2% kg 4.023Total Weight kg 205.158

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 205.158 34.21 7018.51 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 201.135 6.63 1333.53 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 4.023 27.00 108.61

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 4346.71 43.47 (C)

Material cost per meter Rs/meter 8286.89

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.9356-(0.0088*2+0.009))*0.009*1*2080= kg 53.46

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.9356*1= sqmt 2.939 100.33 294.89 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.9356-(0.0088*2+0.009))*1= sqmt 2.856 450.00 1285.07 (E)

Total (A+B+C+D+E) 9866.85Total without ED 8786.24

Add Water Charges @ 1% 1% 87.86Add CPOH @ 15% 15% 1331.12

Total cost per meter for pipe 10205.22Total cost per kg for specials 40.08

2.5.2.38

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.938 0.01 0

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.938-0.01)*0.01*1*7850= kg 228.859Add 2 % wastage

2% kg 4.577Total Weight kg 233.436

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 233.436 34.21 7985.90 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 228.859 6.63 1517.33 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 4.577 27.00 123.58

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 4346.71 43.47 (C)

Material cost per meter Rs/meter 9423.12

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.938-(0.01*2+0.009))*0.009*1*2080= kg 53.46

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.938*1= sqmt 2.947 100.33 295.65 (D)

900 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside epoxycoating

Delhi Jal Board 176 Schedule of rates 2014-2015

Page 86: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.938-(0.01*2+0.009))*1= sqmt 2.856 450.00 1285.07 (E)

Total (A+B+C+D+E) 11003.84Total without ED 9798.16

Add Water Charges @ 1% 1% 97.98Add CPOH @ 15% 15% 1484.42

Total cost per meter for pipe 11380.56Total cost per kg for specials 40.31

2.5.2.39

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.953 0.0175

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.953-0.0175)*0.0175*1*7850= kg 403.740Add 2 % wastage

2% kg 8.075Total Weight kg 411.814

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 411.814 34.21 14088.27 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 403.740 6.63 2676.79 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 8.075 27.00 218.02

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 4346.71 43.47 (C)

Material cost per meter Rs/meter 16590.52

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(0.953-(0.0175*2+0.009))*0.009*1*2080= kg 53.46

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*0.953*1= sqmt 2.994 100.33 300.38 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(0.953-(0.0175*2+0.009))*1= sqmt 2.856 450.00 1285.07 (E)

Total (A+B+C+D+E) 18175.96Total without ED 16181.32

Add Water Charges @ 1% 1% 161.81Add CPOH @ 15% 15% 2451.47

Total cost per meter for pipe 18794.61Total cost per kg for specials 41.11

2.5.2.40

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.0356 0.0088 0

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.0356-0.0088)*0.0088*1*7850= kg 222.837Add 2 % wastage

2% kg 4.457Total Weight kg 227.294

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 227.294 34.21 7775.79 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 222.837 6.63 1477.41 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 4.457 27.00 120.33

900 mm nominal dia (clear internal dia) of pipe with 17.5 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside epoxycoating

1000 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside epoxycoating

Delhi Jal Board 177 Schedule of rates 2014-2015

Page 87: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 9190.82

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.0356-(0.0088*2+0.009))*0.009*1*2080= kg 59.34

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.0356*1= sqmt 3.253 100.33 326.41 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.0356-(0.0088*2+0.009))*1= sqmt 3.170 450.00 1426.44 (E)

Total (A+B+C+D+E) 10943.68Total without ED 9746.21

Add Water Charges @ 1% 1% 97.46Add CPOH @ 15% 15% 1476.55

Total cost per meter for pipe 11320.22Total cost per kg for specials 40.12

2.5.2.41

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.038 0.01 0

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.038-0.01)*0.01*1*7850= kg 253.520Add 2 % wastage

2% kg 5.070Total Weight kg 258.591

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 258.591 34.21 8846.45 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 253.520 6.63 1680.84 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 5.070 27.00 136.90

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 10448.34

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.038-(0.01*2+0.009))*0.009*1*2080= kg 59.34

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.038*1= sqmt 3.261 100.33 327.17 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.038-(0.01*2+0.009))*1= sqmt 3.170 450.00 1426.44 (E)

Total (A+B+C+D+E) 12201.96Total without ED 10866.07

Add Water Charges @ 1% 1% 108.66Add CPOH @ 15% 15% 1646.21

Total cost per meter for pipe 12620.94Total cost per kg for specials 40.34

2.5.2.42

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.058 0.02 0

thickness of CML (t2) =

Length of pipe =

1000 mm nominal dia (clear internal dia) of pipe with 20.0 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside epoxycoating

1000 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside epoxycoating

Delhi Jal Board 178 Schedule of rates 2014-2015

Page 88: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

0.009 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.058-0.02)*0.02*1*7850= kg 511.973Add 2 % wastage

2% kg 10.239Total Weight kg 522.212

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 522.212 34.21 17865.01 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 511.973 6.63 3394.38 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 10.239 27.00 276.47

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 21040.88

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.058-(0.02*2+0.009))*0.009*1*2080= kg 59.34

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.058*1= sqmt 3.324 100.33 333.47 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.058-(0.02*2+0.009))*1= sqmt 3.170 450.00 1426.44 (E)

Total (A+B+C+D+E) 22800.80Total without ED 20299.00

Add Water Charges @ 1% 1% 202.99Add CPOH @ 15% 15% 3075.30

Total cost per meter for pipe 23577.29Total cost per kg for specials 41.27

2.5.2.43

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.0856 0.0088 0

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.0856-0.0088)*0.0088*1*7850= kg 233.688Add 2 % wastage

2% kg 4.674Total Weight kg 238.362

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 238.362 34.21 8154.43 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 233.688 6.63 1549.35 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 4.674 27.00 126.19

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 9635.55

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.0856-(0.0088*2+0.009))*0.009*1*2080= kg 62.28

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.0856*1= sqmt 3.411 100.33 342.17 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.0856-(0.0088*2+0.009))*1= sqmt 3.327 450.00 1497.13 (E)

Total (A+B+C+D+E) 11474.85Total without ED 10218.95

Add Water Charges @ 1% 1% 102.19

1050 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside epoxycoating

Delhi Jal Board 179 Schedule of rates 2014-2015

Page 89: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add CPOH @ 15% 15% 1548.17Total cost per meter for pipe 11869.31

Total cost per kg for specials 40.10

2.5.2.44

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.088 0.01 0

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.088-0.01)*0.01*1*7850= kg 265.851Add 2 % wastage

2% kg 5.317Total Weight kg 271.168

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 271.168 34.21 9276.73 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 265.851 6.63 1762.59 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 5.317 27.00 143.56

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 10953.71

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.088-(0.01*2+0.009))*0.009*1*2080= kg 62.28

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.088*1= sqmt 3.418 100.33 342.93 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.088-(0.01*2+0.009))*1= sqmt 3.327 450.00 1497.13 (E)

Total (A+B+C+D+E) 12793.77Total without ED 11392.79

Add Water Charges @ 1% 1% 113.93Add CPOH @ 15% 15% 1726.01

Total cost per meter for pipe 13232.72Total cost per kg for specials 40.33

2.5.2.45

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.09 0.011 0

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.09-0.011)*0.011*1*7850= kg 292.707Add 2 % wastage

2% kg 5.854Total Weight kg 298.562

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 298.562 34.21 10213.86 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 292.707 6.63 1940.65 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 5.854 27.00 158.06

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 12054.41

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

1050 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside epoxycoating

1050 mm nominal dia (clear internal dia) of pipe with 11.0 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside epoxycoating

Delhi Jal Board 180 Schedule of rates 2014-2015

Page 90: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

(3.1416)*(1.09-(0.011*2+0.009))*0.009*1*2080= kg 62.28

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.09*1= sqmt 3.424 100.33 343.56 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.09-(0.011*2+0.009))*1= sqmt 3.327 450.00 1497.13 (E)

Total (A+B+C+D+E) 13895.09Total without ED 12372.96

Add Water Charges @ 1% 1% 123.73Add CPOH @ 15% 15% 1874.50

Total cost per meter for pipe 14371.19Total cost per kg for specials 40.48

2.5.2.46

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.1356 0.0088 0

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.1356-0.0088)*0.0088*1*7850= kg 244.540Add 2 % wastage

2% kg 4.891Total Weight kg 249.430

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 249.430 34.21 8533.07 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 244.540 6.63 1621.30 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 4.891 27.00 132.05

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 10080.27

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.1356-(0.0088*2+0.009))*0.009*1*2080= kg 65.22

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.1356*1= sqmt 3.568 100.33 357.93 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.1356-(0.0088*2+0.009))*1= sqmt 3.484 450.00 1567.81 (E)

Total (A+B+C+D+E) 12006.02Total without ED 10691.69

Add Water Charges @ 1% 1% 106.92Add CPOH @ 15% 15% 1619.79

Total cost per meter for pipe 12418.40Total cost per kg for specials 40.09

2.5.2.47

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.138 0.01 0

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.138-0.01)*0.01*1*7850= kg 278.182Add 2 % wastage

2% kg 5.564Total Weight kg 283.745

1100 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside epoxycoating

1100 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside epoxycoating

Delhi Jal Board 181 Schedule of rates 2014-2015

Page 91: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 283.745 34.21 9707.00 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 278.182 6.63 1844.34 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 5.564 27.00 150.22

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 11459.08

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.138-(0.01*2+0.009))*0.009*1*2080= kg 65.22

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.138*1= sqmt 3.575 100.33 358.69 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.138-(0.01*2+0.009))*1= sqmt 3.484 450.00 1567.81 (E)

Total (A+B+C+D+E) 13385.58Total without ED 11919.50

Add Water Charges @ 1% 1% 119.19Add CPOH @ 15% 15% 1805.80

Total cost per meter for pipe 13844.50Total cost per kg for specials 40.32

2.5.2.48

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.14 0.011 0

thickness of CML (t2) =

Length of pipe =

0.009 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.14-0.011)*0.011*1*7850= kg 306.271Add 2 % wastage

2% kg 6.125Total Weight kg 312.397

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 312.397 34.21 10687.17 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 306.271 6.63 2030.58 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 6.125 27.00 165.39

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 12610.31

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.14-(0.011*2+0.009))*0.009*1*2080= kg 65.22

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.14*1= sqmt 3.581 100.33 359.32 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.14-(0.011*2+0.009))*1= sqmt 3.484 450.00 1567.81 (E)

Total (A+B+C+D+E) 14537.45Total without ED 12944.65

Add Water Charges @ 1% 1% 129.45Add CPOH @ 15% 15% 1961.11

Total cost per meter for pipe 15035.21Total cost per kg for specials 40.47

2.5.2.49

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

1200 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

1100 mm nominal dia (clear internal dia) of pipe with 11.0 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside epoxycoating

Delhi Jal Board 182 Schedule of rates 2014-2015

Page 92: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.244 0.01 0

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.244-0.01)*0.01*1*7850= kg 304.323Add 2 % wastage

2% kg 6.086Total Weight kg 310.409

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 310.409 34.21 10619.18 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 304.323 6.63 2017.66 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 6.086 27.00 164.33

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 12530.47

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.244-(0.01*2+0.012))*0.012*1*2080= kg 95.04

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.244*1= sqmt 3.908 100.33 392.10 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.244-(0.01*2+0.012))*1= sqmt 3.808 450.00 1713.42 (E)

Total (A+B+C+D+E) 14635.99Total without ED 13032.35

Add Water Charges @ 1% 1% 130.32Add CPOH @ 15% 15% 1974.40

Total cost per meter for pipe 15137.08Total cost per kg for specials 37.90

2.5.2.50

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.246 0.011 0

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.246-0.011)*0.011*1*7850= kg 335.027Add 2 % wastage

2% kg 6.701Total Weight kg 341.727

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 341.727 34.21 11690.57 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 335.027 6.63 2221.23 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 6.701 27.00 180.91

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 13788.83

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.246-(0.011*2+0.012))*0.012*1*2080= kg 95.04

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.246*1= sqmt 3.914 100.33 392.73 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.246-(0.011*2+0.012))*1= sqmt 3.808 450.00 1713.42 (E)

1200 mm nominal dia (clear internal dia) of pipe with 11.0 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 183 Schedule of rates 2014-2015

Page 93: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Total (A+B+C+D+E) 15894.99Total without ED 14152.86

Add Water Charges @ 1% 1% 141.53Add CPOH @ 15% 15% 2144.16

Total cost per meter for pipe 16438.55Total cost per kg for specials 38.22

2.5.2.51

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.248 0.012

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.248-0.012)*0.012*1*7850= kg 365.779Add 2 % wastage

2% kg 7.316Total Weight kg 373.095

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 373.095 34.21 12763.67 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 365.779 6.63 2425.12 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 7.316 27.00 197.52

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 15049.23

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.248-(0.012*2+0.012))*0.012*1*2080= kg 95.04

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.248*1= sqmt 3.921 100.33 393.36 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.248-(0.012*2+0.012))*1= sqmt 3.808 450.00 1713.42 (E)

Total (A+B+C+D+E) 17156.01Total without ED 15275.16

Add Water Charges @ 1% 1% 152.75Add CPOH @ 15% 15% 2314.19

Total cost per meter for pipe 17742.10Total cost per kg for specials 38.50

2.5.2.52

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.249 0.0125

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.249-0.0125)*0.0125*1*7850= kg 381.174Add 2 % wastage

2% kg 7.623Total Weight kg 388.798

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 388.798 34.21 13300.87 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 381.174 6.63 2527.19 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 7.623 27.00 205.83

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 15680.18

1200 mm nominal dia (clear internal dia) of pipe with 12.0 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

1200 mm nominal dia (clear internal dia) of pipe with 12.5 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 184 Schedule of rates 2014-2015

Page 94: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.249-(0.0125*2+0.012))*0.012*1*2080= kg 95.04

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.249*1= sqmt 3.924 100.33 393.68 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.249-(0.0125*2+0.012))*1= sqmt 3.808 450.00 1713.42 (E)

Total (A+B+C+D+E) 17787.28Total without ED 15836.99

Add Water Charges @ 1% 1% 158.37Add CPOH @ 15% 15% 2399.30

Total cost per meter for pipe 18394.66Total cost per kg for specials 38.63

2.5.2.53

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.448 0.012 0

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.448-0.012)*0.012*1*7850= kg 424.967Add 2 % wastage

2% kg 8.499Total Weight kg 433.466

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 433.466 34.21 14828.99 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 424.967 6.63 2817.53 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 8.499 27.00 229.48

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 7244.52 72.45 (C)

Material cost per meter Rs/meter 17489.49

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.448-(0.012*2+0.012))*0.012*1*2080= kg 110.72

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.448*1= sqmt 4.549 100.33 456.40 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.448-(0.012*2+0.012))*1= sqmt 4.436 450.00 1996.17 (E)

Total (A+B+C+D+E) 19942.05Total without ED 17756.33

Add Water Charges @ 1% 1% 177.56Add CPOH @ 15% 15% 2690.08

Total cost per meter for pipe 20623.97Total cost per kg for specials 38.50

2.5.2.54

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.449 0.0125 0

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.449-0.0125)*0.0125*1*7850= kg 442.828

1400 mm nominal dia (clear internal dia) of pipe with 12 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outside epoxycoating

1400 mm nominal dia (clear internal dia) of pipe with 12.5 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 185 Schedule of rates 2014-2015

Page 95: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add 2 % wastage2% kg 8.857

Total Weight kg 451.685

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 451.685 34.21 15452.24 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 442.828 6.63 2935.95 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 8.857 27.00 239.13

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 7244.52 72.45 (C)

Material cost per meter Rs/meter 18221.51

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.449-(0.0125*2+0.012))*0.012*1*2080= kg 110.72

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.449*1= sqmt 4.552 100.33 456.71 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.449-(0.0125*2+0.012))*1= sqmt 4.436 450.00 1996.17 (E)

Total (A+B+C+D+E) 20674.40Total without ED 18408.11

Add Water Charges @ 1% 1% 184.08Add CPOH @ 15% 15% 2788.83

Total cost per meter for pipe 21381.02Total cost per kg for specials 38.63

2.5.2.55

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.4524 0.0142 0

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.4524-0.0142)*0.0142*1*7850= kg 503.648Add 2 % wastage

2% kg 10.073Total Weight kg 513.721

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 513.721 34.21 17574.52 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 503.648 6.63 3339.19 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 10.073 27.00 271.97

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 7244.52 72.45 (C)

Material cost per meter Rs/meter 20714.19

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.4524-(0.0142*2+0.012))*0.012*1*2080= kg 110.72

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.4524*1= sqmt 4.563 100.33 457.79 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.4524-(0.0142*2+0.012))*1= sqmt 4.436 450.00 1996.17 (E)

Total (A+B+C+D+E) 23168.14Total without ED 20627.53

Add Water Charges @ 1% 1% 206.28Add CPOH @ 15% 15% 3125.07

Total cost per meter for pipe 23958.88Total cost per kg for specials 39.00

1400 mm nominal dia (clear internal dia) of pipe with 14.2 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 186 Schedule of rates 2014-2015

Page 96: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

2.5.2.56

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.548 0.012 0

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.548-0.012)*0.012*1*7850= kg 454.561Add 2 % wastage

2% kg 9.091Total Weight kg 463.652

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 463.652 34.21 15861.65 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 454.561 6.63 3013.74 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 9.091 27.00 245.46

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 8693.42 86.93 (C)

Material cost per meter Rs/meter 18716.86

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.548-(0.012*2+0.012))*0.012*1*2080= kg 118.56

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.548*1= sqmt 4.863 100.33 487.92 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.548-(0.012*2+0.012))*1= sqmt 4.750 450.00 2137.54 (E)

Total (A+B+C+D+E) 21342.32Total without ED 19004.15

Add Water Charges @ 1% 1% 190.04Add CPOH @ 15% 15% 2879.13

Total cost per meter for pipe 22073.32Total cost per kg for specials 38.51

2.5.2.57

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.6524 0.0142 0

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.6524-0.0142)*0.0142*1*7850= kg 573.687Add 2 % wastage

2% kg 11.474Total Weight kg 585.160

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 585.160 34.21 20018.48 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 573.687 6.63 3803.54 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 11.474 27.00 309.79

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 8693.42 86.93 (C)

Material cost per meter Rs/meter 23599.17

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.6524-(0.0142*2+0.012))*0.012*1*2080= kg 126.40

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

1500 mm nominal dia (clear internal dia) of pipe with 12 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outside epoxycoating

1600 mm nominal dia (clear internal dia) of pipe with 14.2 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 187 Schedule of rates 2014-2015

Page 97: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

(3.14159265358979)*1.6524*1= sqmt 5.191 100.33 520.82 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.6524-(0.0142*2+0.012))*1= sqmt 5.064 450.00 2278.91 (E)

Total (A+B+C+D+E) 26398.91Total without ED 23504.50

Add Water Charges @ 1% 1% 235.04Add CPOH @ 15% 15% 3560.93

Total cost per meter for pipe 27300.47Total cost per kg for specials 39.00

2.5.2.58

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.656 0.016 0

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.656-0.016)*0.016*1*7850= kg 647.118Add 2 % wastage

2% kg 12.942Total Weight kg 660.060

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 660.060 34.21 22580.82 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 647.118 6.63 4290.39 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 12.942 27.00 349.44

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 8693.42 86.93 (C)

Material cost per meter Rs/meter 26608.70

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.656-(0.016*2+0.012))*0.012*1*2080= kg 126.40

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.656*1= sqmt 5.202 100.33 521.96 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.656-(0.016*2+0.012))*1= sqmt 5.064 450.00 2278.91 (E)

Total (A+B+C+D+E) 29409.58Total without ED 26183.98

Add Water Charges @ 1% 1% 261.84Add CPOH @ 15% 15% 3966.87

Total cost per meter for pipe 30412.69Total cost per kg for specials 39.32

2.5.2.59

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.8524 0.0142 0

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.8524-0.0142)*0.0142*1*7850= kg 643.725Add 2 % wastage

2% kg 12.875Total Weight kg 656.600

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 656.600 34.21 22462.45 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 643.725 6.63 4267.90 (B)

1600 mm nominal dia (clear internal dia) of pipe with 16.0 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

1800 mm nominal dia (clear internal dia) of pipe with 14.2 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 188 Schedule of rates 2014-2015

Page 98: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_272 Cost of Scrap kg 12.875 27.00 347.61

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 10142.33 101.42 (C)

Material cost per meter Rs/meter 26484.16

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.8524-(0.0142*2+0.012))*0.012*1*2080= kg 142.09

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.8524*1= sqmt 5.819 100.33 583.86 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.8524-(0.0142*2+0.012))*1= sqmt 5.693 450.00 2561.65 (E)

Total (A+B+C+D+E) 29629.67Total without ED 26381.46

Add Water Charges @ 1% 1% 263.81Add CPOH @ 15% 15% 3996.79

Total cost per meter for pipe 30642.07Total cost per kg for specials 38.99

2.5.2.60

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.856 0.016 0

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.856-0.016)*0.016*1*7850= kg 726.035Add 2 % wastage

2% kg 14.521Total Weight kg 740.555

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 740.555 34.21 25334.58 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 726.035 6.63 4813.61 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 14.521 27.00 392.06

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 10142.33 101.42 (C)

Material cost per meter Rs/meter 29857.56

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.856-(0.016*2+0.012))*0.012*1*2080= kg 142.09

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.856*1= sqmt 5.831 100.33 585.00 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.856-(0.016*2+0.012))*1= sqmt 5.693 450.00 2561.65 (E)

Total (A+B+C+D+E) 33004.21Total without ED 29384.79

Add Water Charges @ 1% 1% 293.85Add CPOH @ 15% 15% 4451.79

Total cost per meter for pipe 34130.43Total cost per kg for specials 39.32

2.5.2.61

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.859 0.0175 0

1800 mm nominal dia (clear internal dia) of pipe with 16.0 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

1800 mm nominal dia (clear internal dia) of pipe with 17.5 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 189 Schedule of rates 2014-2015

Page 99: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.859-0.0175)*0.0175*1*7850= kg 794.748Add 2 % wastage

2% kg 15.895Total Weight kg 810.643

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 810.643 34.21 27732.29 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 794.748 6.63 5269.18 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 15.895 27.00 429.16

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 10142.33 101.42 (C)

Material cost per meter Rs/meter 32673.73

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(1.859-(0.0175*2+0.012))*0.012*1*2080= kg 142.09

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*1.859*1= sqmt 5.840 100.33 585.94 (D)

Delhi Jal Board 190 Schedule of rates 2014-2015

Page 100: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(1.859-(0.0175*2+0.012))*1= sqmt 5.693 450.00 2561.65 (E)

Total (A+B+C+D+E) 35821.32Total without ED 31892.01

Add Water Charges @ 1% 1% 318.92Add CPOH @ 15% 15% 4831.64

Total cost per meter for pipe 37042.57Total cost per kg for specials 39.54

2.5.2.62

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =2.056 0.016 0

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(2.056-0.016)*0.016*1*7850= kg 804.951Add 2 % wastage

2% kg 16.099Total Weight kg 821.050

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 821.050 34.21 28088.34 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 804.951 6.63 5336.83 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 16.099 27.00 434.67

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 11591.23 115.91 (C)

Material cost per meter Rs/meter 33106.41

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(2.056-(0.016*2+0.012))*0.012*1*2080= kg 157.77

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*2.056*1= sqmt 6.459 100.33 648.04 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(2.056-(0.016*2+0.012))*1= sqmt 6.321 450.00 2844.40 (E)

Total (A+B+C+D+E) 36598.84Total without ED 32585.59

Add Water Charges @ 1% 1% 325.86Add CPOH @ 15% 15% 4936.72

Total cost per meter for pipe 37848.16Total cost per kg for specials 39.31

2.5.2.63

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =2.059 0.0175 0

thickness of CML (t2) =

Length of pipe =

2000 mm nominal dia (clear internal dia) of pipe with 16.0 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

2000 mm nominal dia (clear internal dia) of pipe with 17.5 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 191 Schedule of rates 2014-2015

Page 101: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

0.012 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(2.059-0.0175)*0.0175*1*7850= kg 881.063Add 2 % wastage

2% kg 17.621Total Weight kg 898.684

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 898.684 34.21 30744.21 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 881.063 6.63 5841.45 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 17.621 27.00 475.77

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 11591.23 115.91 (C)

Material cost per meter Rs/meter 36225.80

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(2.059-(0.0175*2+0.012))*0.012*1*2080= kg 157.77

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*2.059*1= sqmt 6.469 100.33 648.98 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(2.059-(0.0175*2+0.012))*1= sqmt 6.321 450.00 2844.40 (E)

Total (A+B+C+D+E) 39719.18Total without ED 35362.68

Add Water Charges @ 1% 1% 353.63Add CPOH @ 15% 15% 5357.45

Total cost per meter for pipe 41073.75Total cost per kg for specials 39.54

2.5.2.64

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =2.064 0.02 0

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(2.064-0.02)*0.02*1*7850= kg 1008.162Add 2 % wastage

2% kg 20.163Total Weight kg 1028.325

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 1028.325 34.21 35179.27 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 1008.162 6.63 6684.12 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 20.163 27.00 544.41

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 11591.23 115.91 (C)

Material cost per meter Rs/meter 41434.89

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(2.064-(0.02*2+0.012))*0.012*1*2080= kg 157.77

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*2.064*1= sqmt 6.484 100.33 650.56 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(2.064-(0.02*2+0.012))*1= sqmt 6.321 450.00 2844.40 (E)

Total (A+B+C+D+E) 44929.85Total without ED 40000.15

Add Water Charges @ 1% 1% 400.00

2000 mm nominal dia (clear internal dia) of pipe with 20.0 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 192 Schedule of rates 2014-2015

Page 102: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add CPOH @ 15% 15% 6060.02Total cost per meter for pipe 46460.18

Total cost per kg for specials 39.85

2.5.2.65

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =2.259 0.0175 0

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(2.259-0.0175)*0.0175*1*7850= kg 967.378Add 2 % wastage

2% kg 19.348Total Weight kg 986.726

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 986.726 34.21 33756.14 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 967.378 6.63 6413.72 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 19.348 27.00 522.38

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 13040.13 130.40 (C)

Material cost per meter Rs/meter 39777.87

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(2.259-(0.0175*2+0.012))*0.012*1*2080= kg 173.45

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*2.259*1= sqmt 7.097 100.33 712.02 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(2.259-(0.0175*2+0.012))*1= sqmt 6.949 450.00 3127.14 (E)

Total (A+B+C+D+E) 43617.03Total without ED 38833.35

Add Water Charges @ 1% 1% 388.33Add CPOH @ 15% 15% 5883.25

Total cost per meter for pipe 45104.93Total cost per kg for specials 39.54

2.5.2.66

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =2.264 0.02 0

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(2.264-0.02)*0.02*1*7850= kg 1106.808Add 2 % wastage

2% kg 22.136Total Weight kg 1128.944

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 1128.944 34.21 38621.47 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 1106.808 6.63 7338.14 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 22.136 27.00 597.68

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 13040.13 130.40 (C)

Material cost per meter Rs/meter 45492.33

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

2200 mm nominal dia (clear internal dia) of pipe with 17.5 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

2200 mm nominal dia (clear internal dia) of pipe with 20.0 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 193 Schedule of rates 2014-2015

Page 103: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

(3.1416)*(2.264-(0.02*2+0.012))*0.012*1*2080= kg 173.45

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*2.264*1= sqmt 7.113 100.33 713.60 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(2.264-(0.02*2+0.012))*1= sqmt 6.949 450.00 3127.14 (E)

Total (A+B+C+D+E) 49333.07Total without ED 43920.60

Add Water Charges @ 1% 1% 439.21Add CPOH @ 15% 15% 6653.97

Total cost per meter for pipe 51013.78Total cost per kg for specials 39.85

2.5.2.67

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =2.2684 0.0222 0

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(2.2684-0.0222)*0.0222*1*7850= kg 1229.762Add 2 % wastage

2% kg 24.595Total Weight kg 1254.357

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 1254.357 34.21 42911.86 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 1229.762 6.63 8153.32 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 24.595 27.00 664.07

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 13040.13 130.40 (C)

Material cost per meter Rs/meter 50531.51

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(2.2684-(0.0222*2+0.012))*0.012*1*2080= kg 173.45

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*2.2684*1= sqmt 7.126 100.33 714.98 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(2.2684-(0.0222*2+0.012))*1= sqmt 6.949 450.00 3127.14 (E)

Total (A+B+C+D+E) 54373.63Total without ED 48406.69

Add Water Charges @ 1% 1% 484.07Add CPOH @ 15% 15% 7333.61

Total cost per meter for pipe 56224.36Total cost per kg for specials 40.07

2.5.2.68

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =2.564 0.02 0

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(2.564-0.02)*0.02*1*7850= kg 1254.777Add 2 % wastage

2% kg 25.096Total Weight kg 1279.873

2500 mm nominal dia (clear internal dia) of pipe with 20.0 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

2200 mm nominal dia (clear internal dia) of pipe with 22.2 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 194 Schedule of rates 2014-2015

Page 104: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 1279.873 34.21 43784.77 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 1254.777 6.63 8319.17 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 25.096 27.00 677.58

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 14489.04 144.89 (C)

Material cost per meter Rs/meter 51571.25

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(2.564-(0.02*2+0.012))*0.012*1*2080= kg 196.98

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*2.564*1= sqmt 8.055 100.33 808.15 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(2.564-(0.02*2+0.012))*1= sqmt 7.892 450.00 3551.26 (E)

Total (A+B+C+D+E) 55930.66Total without ED 49794.03

Add Water Charges @ 1% 1% 497.94Add CPOH @ 15% 15% 7543.80

Total cost per meter for pipe 57835.76Total cost per kg for specials 39.84

2.5.2.69

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =2.5684 0.0222 0

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(2.5684-0.0222)*0.0222*1*7850= kg 1394.007Add 2 % wastage

2% kg 27.880Total Weight kg 1421.887

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 1421.887 34.21 48643.12 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 1394.007 6.63 9242.27 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 27.880 27.00 752.76

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 14489.04 144.89 (C)

Material cost per meter Rs/meter 57277.51

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(2.5684-(0.0222*2+0.012))*0.012*1*2080= kg 196.98

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*2.5684*1= sqmt 8.069 100.33 809.54 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(2.5684-(0.0222*2+0.012))*1= sqmt 7.892 450.00 3551.26 (E)

Total (A+B+C+D+E) 61638.31Total without ED 54873.82

Add Water Charges @ 1% 1% 548.74

2500 mm nominal dia (clear internal dia) of pipe with 22.2 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 195 Schedule of rates 2014-2015

Page 105: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add CPOH @ 15% 15% 8313.38Total cost per meter for pipe 63735.94

Total cost per kg for specials 40.06

2.5.2.70

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =2.574 0.025 0

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(2.574-0.025)*0.025*1*7850= kg 1571.554Add 2 % wastage

2% kg 31.431Total Weight kg 1602.985

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 1602.985 34.21 54838.53 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 1571.554 6.63 10419.40 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 31.431 27.00 848.64

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 14489.04 144.89 (C)

Material cost per meter Rs/meter 64554.18

Weight of Cement Morter Lining (CML) = pi()*(d-( t1*2+t2))*t2*L*2000

(3.1416)*(2.574-(0.025*2+0.012))*0.012*1*2080= kg 196.98

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.14159265358979)*2.574*1= sqmt 8.086 100.33 811.31 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t1*2+t2))*L

(3.1416)*(2.574-(0.025*2+0.012))*1= sqmt 7.892 450.00 3551.26 (E)

Total (A+B+C+D+E) 68916.75Total without ED 61351.60

Add Water Charges @ 1% 1% 613.52Add CPOH @ 15% 15% 9294.77

Total cost per meter for pipe 71259.88Total cost per kg for specials 40.29

2500 mm nominal dia (clear internal dia) of pipe with 25.0 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outsideepoxy coating

Delhi Jal Board 196 Schedule of rates 2014-2015

Page 106: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

2.5.3

2.5.3.1

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.18 0.005 0.004thickness of

CML (t2) =Length of pipe

=0.006 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.18-((0.004*2)+0.005))*0.005*1*7850= kg 20.592Add 5 % wastage

5% kg 1.030Total Weight kg 21.622

#REF! Cost of MS plate kg 21.622 45.00 972.99 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 20.592 6.63 136.53 (B)

Quotation_Volume III_pg no_272 Cost of scrap kg 1.030 27.00 27.80

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 289.78 2.90 (C)

Material cost per meter Rs/meter 1084.61

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.18-(0.004*2+0.005*2+0.006))*0.006*1*2080= kg 6.12

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.18-0.004)*1= sqmt 0.553 575.00 317.93 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.18-(0.004*2+0.005*2+0.006))*1= sqmt 0.490 450.00 220.54 (E)

Total (A+B+C+D+E) 1623.08Total without ED 1444.86

Add Water Charges @ 1% 1% 14.45Add CPOH @ 15% 15% 218.90

Total cost per meter for pipe 1678.20Total cost per kg for specials 62.83

2.5.3.2

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.23 0.005 0.004thickness of

CML (t2) =Length of pipe

=0.006 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.23-((0.004*2)+0.005))*0.005*1*7850= kg 26.758Add 5 % wastage

5% kg 1.338Total Weight kg 28.096

#REF! Cost of MS plate kg 28.096 45.00 1264.30 (A)

Providing Mild Steel Pipes / specials fabricated / manufactured out of MS plate of steel grade Fe410 as per IS 3589:2001; internally lined with cementmortar lining and external / outside 4mm coaltar coating and wrapping shall confirm to IS 10221:2008; minimum thickness of M.S. Plate as specified;complete in all respect; with upto date amendments in relevant IS codes and as directed by Engineer-in-charge. The rates are excluding excise dutycomponent.

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outside 4mm coaltar coatingand wrapping

200 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outside 4mm coaltar coatingand wrapping

Delhi Jal Board 213 Schedule of Rates 2014 - 2015

Page 107: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_320 Cost of Fabrication kg 26.758 6.63 177.40 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.338 27.00 36.12

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 471.38 4.71 (C)

Material cost per meter Rs/meter 1410.30

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.23-(0.004*2+0.005*2+0.006))*0.006*1*2080= kg 8.08

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.23-0.004)*1= sqmt 0.710 575.00 408.25 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.23-(0.004*2+0.005*2+0.006))*1= sqmt 0.647 450.00 291.23 (E)

Total (A+B+C+D+E) 2109.77Total without ED 1878.21

Add Water Charges @ 1% 1% 18.78Add CPOH @ 15% 15% 284.55

Total cost per meter for pipe 2181.54Total cost per kg for specials 62.63

2.5.3.3

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.232 0.006 0.004thickness of

CML (t2) =Length of pipe

=0.006 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.232-((0.004*2)+0.006))*0.006*1*7850= kg 32.257Add 5 % wastage

5% kg 1.613Total Weight kg 33.870

#REF! Cost of MS plate kg 33.870 45.00 1524.15 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 32.257 6.63 213.87 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.613 27.00 43.55

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 471.38 4.71 (C)

Material cost per meter Rs/meter 1699.19

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.232-(0.004*2+0.006*2+0.006))*0.006*1*2080= kg 8.08

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.232-0.004)*1= sqmt 0.716 575.00 411.86 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.232-(0.004*2+0.006*2+0.006))*1= sqmt 0.647 450.00 291.23 (E)

Total (A+B+C+D+E) 2402.28Total without ED 2138.53

Add Water Charges @ 1% 1% 21.39

200 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 214 Schedule of Rates 2014 - 2015

Page 108: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add CPOH @ 15% 15% 323.99Total cost per meter for pipe 2483.91

Total cost per kg for specials 61.58

2.5.3.4

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.2326 0.0063 0.004thickness of

CML (t2) =Length of pipe

=0.006 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.2326-((0.004*2)+0.0063))*0.0063*1*7850= kg 33.917Add 5 % wastage

5% kg 1.696Total Weight kg 35.613

#REF! Cost of MS plate kg 35.613 45.00 1602.56 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 33.917 6.63 224.87 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.696 27.00 45.79

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 471.38 4.71 (C)

Material cost per meter Rs/meter 1786.36

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.2326-(0.004*2+0.0063*2+0.006))*0.006*1*2080= kg 8.08

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.2326-0.004)*1= sqmt 0.718 575.00 412.95 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.2326-(0.004*2+0.0063*2+0.006))*1= sqmt 0.647 450.00 291.23 (E)

Total (A+B+C+D+E) 2490.53Total without ED 2217.08

Add Water Charges @ 1% 1% 22.17Add CPOH @ 15% 15% 335.89

Total cost per meter for pipe 2575.14Total cost per kg for specials 61.32

2.5.3.5

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.28 0.005 0.004thickness of

CML (t2) =Length of pipe

=0.006 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.28-((0.004*2)+0.005))*0.005*1*7850= kg 32.923Add 5 % wastage

5% kg 1.646Total Weight kg 34.569

#REF! Cost of MS plate kg 34.569 45.00 1555.62 (A)

250 mm nominal dia (clear internal dia) of pipe with 5.0 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

200 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 215 Schedule of Rates 2014 - 2015

Page 109: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_320 Cost of Fabrication kg 32.923 6.63 218.28 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.646 27.00 44.45

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 669.85 6.70 (C)

Material cost per meter Rs/meter 1736.15

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.28-(0.004*2+0.005*2+0.006))*0.006*1*2080= kg 10.04

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.28-0.004)*1= sqmt 0.867 575.00 498.57 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.28-(0.004*2+0.005*2+0.006))*1= sqmt 0.804 450.00 361.91 (E)

Total (A+B+C+D+E) 2596.63Total without ED 2311.73

Add Water Charges @ 1% 1% 23.12Add CPOH @ 15% 15% 350.23

Total cost per meter for pipe 2685.07Total cost per kg for specials 62.50

2.5.3.6

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.282 0.006 0.004thickness of

CML (t2) =Length of pipe

=0.006 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.282-((0.004*2)+0.006))*0.006*1*7850= kg 39.656Add 5 % wastage

5% kg 1.983Total Weight kg 41.638

#REF! Cost of MS plate kg 41.638 45.00 1873.73 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 39.656 6.63 262.92 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.983 27.00 53.54

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 669.85 6.70 (C)

Material cost per meter Rs/meter 2089.81

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.282-(0.004*2+0.006*2+0.006))*0.006*1*2080= kg 10.04

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.282-0.004)*1= sqmt 0.873 575.00 502.18 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.282-(0.004*2+0.006*2+0.006))*1= sqmt 0.804 450.00 361.91 (E)

Total (A+B+C+D+E) 2953.91Total without ED 2629.70

Add Water Charges @ 1% 1% 26.30

250 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 216 Schedule of Rates 2014 - 2015

Page 110: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add CPOH @ 15% 15% 398.40Total cost per meter for pipe 3054.40

Total cost per kg for specials 61.47

2.5.3.7

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.2826 0.0063 0.004thickness of

CML (t2) =Length of pipe

=0.006 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.2826-((0.004*2)+0.0063))*0.0063*1*7850= kg 41.685Add 5 % wastage

5% kg 2.084Total Weight kg 43.769

#REF! Cost of MS plate kg 43.769 45.00 1969.62 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 41.685 6.63 276.37 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.084 27.00 56.27

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 669.85 6.70 (C)

Material cost per meter Rs/meter 2196.42

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.2826-(0.004*2+0.0063*2+0.006))*0.006*1*2080= kg 10.04

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.2826-0.004)*1= sqmt 0.875 575.00 503.27 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.2826-(0.004*2+0.0063*2+0.006))*1= sqmt 0.804 450.00 361.91 (E)

Total (A+B+C+D+E) 3061.60Total without ED 2725.55

Add Water Charges @ 1% 1% 27.26Add CPOH @ 15% 15% 412.92

Total cost per meter for pipe 3165.72Total cost per kg for specials 61.21

2.5.3.8

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.33 0.005 0.004thickness of

CML (t2) =Length of pipe

=0.006 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.33-((0.004*2)+0.005))*0.005*1*7850= kg 39.088Add 5 % wastage

5% kg 1.954Total Weight kg 41.043

#REF! Cost of MS plate kg 41.043 45.00 1846.93 (A)

300 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outside 4mm coaltar coatingand wrapping

250 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 217 Schedule of Rates 2014 - 2015

Page 111: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_320 Cost of Fabrication kg 39.088 6.63 259.16 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.954 27.00 52.77

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 827.95 8.28 (C)

Material cost per meter Rs/meter 2061.60

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.33-(0.004*2+0.005*2+0.006))*0.006*1*2080= kg 12.00

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.33-0.004)*1= sqmt 1.024 575.00 588.89 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.33-(0.004*2+0.005*2+0.006))*1= sqmt 0.961 450.00 432.60 (E)

Total (A+B+C+D+E) 3083.09Total without ED 2744.85

Add Water Charges @ 1% 1% 27.45Add CPOH @ 15% 15% 415.84

Total cost per meter for pipe 3188.14Total cost per kg for specials 62.41

2.5.3.9

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.3312 0.0056 0.004thickness of

CML (t2) =Length of pipe

=0.006 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.3312-((0.004*2)+0.0056))*0.0056*1*7850= kg 43.862Add 5 % wastage

5% kg 2.193Total Weight kg 46.055

#REF! Cost of MS plate kg 46.055 45.00 2072.48 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 43.862 6.63 290.80 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.193 27.00 59.21

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 827.95 8.28 (C)

Material cost per meter Rs/meter 2312.35

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.3312-(0.004*2+0.0056*2+0.006))*0.006*1*2080= kg 12.00

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.3312-0.004)*1= sqmt 1.028 575.00 591.06 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.3312-(0.004*2+0.0056*2+0.006))*1= sqmt 0.961 450.00 432.60 (E)

Total (A+B+C+D+E) 3336.00Total without ED 2969.94

Add Water Charges @ 1% 1% 29.70

300 mm nominal dia (clear internal dia) of pipe with 5.6 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 218 Schedule of Rates 2014 - 2015

Page 112: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add CPOH @ 15% 15% 449.95Total cost per meter for pipe 3449.59

Total cost per kg for specials 61.75

2.5.3.10

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.3342 0.0071 0.004thickness of

CML (t2) =Length of pipe

=0.006 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.3342-((0.004*2)+0.0071))*0.0071*1*7850= kg 55.873Add 5 % wastage

5% kg 2.794Total Weight kg 58.667

#REF! Cost of MS plate kg 58.667 45.00 2640.02 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 55.873 6.63 370.44 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.794 27.00 75.43

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 827.95 8.28 (C)

Material cost per meter Rs/meter 2943.31

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.3342-(0.004*2+0.0071*2+0.006))*0.006*1*2080= kg 12.00

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.3342-0.004)*1= sqmt 1.037 575.00 596.48 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.3342-(0.004*2+0.0071*2+0.006))*1= sqmt 0.961 450.00 432.60 (E)

Total (A+B+C+D+E) 3972.38Total without ED 3536.32

Add Water Charges @ 1% 1% 35.36Add CPOH @ 15% 15% 535.75

Total cost per meter for pipe 4107.43Total cost per kg for specials 60.52

2.5.3.11

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.382 0.005 0.004thickness of

CML (t2) =Length of pipe

=0.007 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.382-((0.004*2)+0.005))*0.005*1*7850= kg 45.500Add 5 % wastage

5% kg 2.275Total Weight kg 47.775

#REF! Cost of MS plate kg 47.775 45.00 2149.90 (A)

300 mm nominal dia (clear internal dia) of pipe with 7.1 mm thick plate, 6 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

350 mm nominal dia (clear internal dia) of pipe with 5.0 mm thick plate, 7 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 219 Schedule of Rates 2014 - 2015

Page 113: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_320 Cost of Fabrication kg 45.500 6.63 301.67 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.275 27.00 61.43

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 1159.12 11.59 (C)

Material cost per meter Rs/meter 2401.73

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.382-(0.004*2+0.005*2+0.007))*0.007*1*2080= kg 16.33

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.382-0.004)*1= sqmt 1.188 575.00 682.83 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.382-(0.004*2+0.005*2+0.007))*1= sqmt 1.122 450.00 504.70 (E)

Total (A+B+C+D+E) 3589.25Total without ED 3195.70

Add Water Charges @ 1% 1% 31.96Add CPOH @ 15% 15% 484.15

Total cost per meter for pipe 3711.80Total cost per kg for specials 60.03

2.5.3.12

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.3832 0.0056 0.004thickness of

CML (t2) =Length of pipe

=0.007 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.3832-((0.004*2)+0.0056))*0.0056*1*7850= kg 51.043Add 5 % wastage

5% kg 2.552Total Weight kg 53.596

#REF! Cost of MS plate kg 53.596 45.00 2411.80 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 51.043 6.63 338.42 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.552 27.00 68.91

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 1159.12 11.59 (C)

Material cost per meter Rs/meter 2692.90

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.3832-(0.004*2+0.0056*2+0.007))*0.007*1*2080= kg 16.33

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.3832-0.004)*1= sqmt 1.191 575.00 684.99 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.3832-(0.004*2+0.0056*2+0.007))*1= sqmt 1.122 450.00 504.70 (E)

Total (A+B+C+D+E) 3882.59Total without ED 3456.77

Add Water Charges @ 1% 1% 34.57

350 mm nominal dia (clear internal dia) of pipe with 5.6 mm thick plate, 7 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 220 Schedule of Rates 2014 - 2015

Page 114: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add CPOH @ 15% 15% 523.70Total cost per meter for pipe 4015.03

Total cost per kg for specials 59.59

2.5.3.13

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.388 0.008 0.004thickness of

CML (t2) =Length of pipe

=0.007 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.388-((0.004*2)+0.008))*0.008*1*7850= kg 73.393Add 5 % wastage

5% kg 3.670Total Weight kg 77.062

#REF! Cost of MS plate kg 77.062 45.00 3467.80 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 73.393 6.63 486.59 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.670 27.00 99.08

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 1159.12 11.59 (C)

Material cost per meter Rs/meter 3866.91

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.388-(0.004*2+0.008*2+0.007))*0.007*1*2080= kg 16.33

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.388-0.004)*1= sqmt 1.206 575.00 693.66 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.388-(0.004*2+0.008*2+0.007))*1= sqmt 1.122 450.00 504.70 (E)

Total (A+B+C+D+E) 5065.27Total without ED 4509.34

Add Water Charges @ 1% 1% 45.09Add CPOH @ 15% 15% 683.17

Total cost per meter for pipe 5237.60Total cost per kg for specials 58.38

2.5.3.14

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.432 0.005 0.004thickness of

CML (t2) =Length of pipe

=0.007 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.432-((0.004*2)+0.005))*0.005*1*7850= kg 51.666Add 5 % wastage

5% kg 2.583Total Weight kg 54.249

#REF! Cost of MS plate kg 54.249 45.00 2441.21 (A)

350 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick plate, 7 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

400 mm nominal dia (clear internal dia) of pipe with 5.0 mm thick plate, 7 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 221 Schedule of Rates 2014 - 2015

Page 115: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_320 Cost of Fabrication kg 51.666 6.63 342.54 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.583 27.00 69.75

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 1580.62 15.81 (C)

Material cost per meter Rs/meter 2729.81

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.432-(0.004*2+0.005*2+0.007))*0.007*1*2080= kg 18.62

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.432-0.004)*1= sqmt 1.345 575.00 773.15 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.432-(0.004*2+0.005*2+0.007))*1= sqmt 1.279 450.00 575.38 (E)

Total (A+B+C+D+E) 4078.34Total without ED 3631.45

Add Water Charges @ 1% 1% 36.31Add CPOH @ 15% 15% 550.16

Total cost per meter for pipe 4217.93Total cost per kg for specials 60.01

2.5.3.15

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.434 0.006 0.004thickness of

CML (t2) =Length of pipe

=0.007 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.434-((0.004*2)+0.006))*0.006*1*7850= kg 62.147Add 5 % wastage

5% kg 3.107Total Weight kg 65.254

#REF! Cost of MS plate kg 65.254 45.00 2936.45 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 62.147 6.63 412.03 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.107 27.00 83.90

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 1580.62 15.81 (C)

Material cost per meter Rs/meter 3280.39

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.434-(0.004*2+0.006*2+0.007))*0.007*1*2080= kg 18.62

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.434-0.004)*1= sqmt 1.351 575.00 776.76 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.434-(0.004*2+0.006*2+0.007))*1= sqmt 1.279 450.00 575.38 (E)

Total (A+B+C+D+E) 4632.53Total without ED 4124.67

Add Water Charges @ 1% 1% 41.25

400 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick plate, 7 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 222 Schedule of Rates 2014 - 2015

Page 116: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add CPOH @ 15% 15% 624.89Total cost per meter for pipe 4790.81

Total cost per kg for specials 59.32

2.5.3.16

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.4346 0.0063 0.004thickness of

CML (t2) =Length of pipe

=0.007 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.4346-((0.004*2)+0.0063))*0.0063*1*7850= kg 65.301Add 5 % wastage

5% kg 3.265Total Weight kg 68.566

#REF! Cost of MS plate kg 68.566 45.00 3085.47 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 65.301 6.63 432.95 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.265 27.00 88.16

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 1580.62 15.81 (C)

Material cost per meter Rs/meter 3446.06

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.4346-(0.004*2+0.0063*2+0.007))*0.007*1*2080= kg 18.62

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.4346-0.004)*1= sqmt 1.353 575.00 777.84 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.4346-(0.004*2+0.0063*2+0.007))*1= sqmt 1.279 450.00 575.38 (E)

Total (A+B+C+D+E) 4799.29Total without ED 4273.09

Add Water Charges @ 1% 1% 42.73Add CPOH @ 15% 15% 647.37

Total cost per meter for pipe 4963.19Total cost per kg for specials 59.14

2.5.3.17

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.4396 0.0088 0.004thickness of

CML (t2) =Length of pipe

=0.007 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.4396-((0.004*2)+0.0088))*0.0088*1*7850= kg 91.757Add 5 % wastage

5% kg 4.588Total Weight kg 96.344

#REF! Cost of MS plate kg 96.344 45.00 4335.50 (A)

400 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick plate, 7 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

400 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick plate, 7 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 223 Schedule of Rates 2014 - 2015

Page 117: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_320 Cost of Fabrication kg 91.757 6.63 608.35 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 4.588 27.00 123.87

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 1580.62 15.81 (C)

Material cost per meter Rs/meter 4835.78

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.4396-(0.004*2+0.0088*2+0.007))*0.007*1*2080= kg 18.62

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.4396-0.004)*1= sqmt 1.368 575.00 786.87 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.4396-(0.004*2+0.0088*2+0.007))*1= sqmt 1.279 450.00 575.38 (E)

Total (A+B+C+D+E) 6198.04Total without ED 5517.97

Add Water Charges @ 1% 1% 55.18Add CPOH @ 15% 15% 835.97

Total cost per meter for pipe 6409.12Total cost per kg for specials 58.07

2.5.3.18

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.484 0.006 0.004thickness of

CML (t2) =Length of pipe

=0.007 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.484-((0.004*2)+0.006))*0.006*1*7850= kg 69.545Add 5 % wastage

5% kg 3.477Total Weight kg 73.023

#REF! Cost of MS plate kg 73.023 45.00 3286.02 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 69.545 6.63 461.09 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.477 27.00 93.89

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 3672.54

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.484-(0.004*2+0.006*2+0.007))*0.007*1*2080= kg 20.90

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.484-0.004)*1= sqmt 1.508 575.00 867.08 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.484-(0.004*2+0.006*2+0.007))*1= sqmt 1.436 450.00 646.07 (E)

Total (A+B+C+D+E) 5185.69Total without ED 4617.37

Add Water Charges @ 1% 1% 46.17

450 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick plate, 7 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 224 Schedule of Rates 2014 - 2015

Page 118: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add CPOH @ 15% 15% 699.53Total cost per meter for pipe 5363.07

Total cost per kg for specials 59.29

2.5.3.19

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.4846 0.0063 0.004thickness of

CML (t2) =Length of pipe

=0.007 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.4846-((0.004*2)+0.0063))*0.0063*1*7850= kg 73.069Add 5 % wastage

5% kg 3.653Total Weight kg 76.723

#REF! Cost of MS plate kg 76.723 45.00 3452.53 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 73.069 6.63 484.45 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.653 27.00 98.64

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 3857.65

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.4846-(0.004*2+0.0063*2+0.007))*0.007*1*2080= kg 20.90

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.4846-0.004)*1= sqmt 1.510 575.00 868.16 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.4846-(0.004*2+0.0063*2+0.007))*1= sqmt 1.436 450.00 646.07 (E)

Total (A+B+C+D+E) 5371.88Total without ED 4783.08

Add Water Charges @ 1% 1% 47.83Add CPOH @ 15% 15% 724.64

Total cost per meter for pipe 5555.55Total cost per kg for specials 59.12

2.5.3.20

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.492 0.01 0.004thickness of

CML (t2) =Length of pipe

=0.007 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.492-((0.004*2)+0.01))*0.01*1*7850= kg 116.896Add 5 % wastage

5% kg 5.845Total Weight kg 122.740

#REF! Cost of MS plate kg 122.740 45.00 5523.31 (A)

450 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick plate, 7 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

450 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick plate, 7 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 225 Schedule of Rates 2014 - 2015

Page 119: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_320 Cost of Fabrication kg 116.896 6.63 775.02 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 5.845 27.00 157.81

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 6159.84

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.492-(0.004*2+0.01*2+0.007))*0.007*1*2080= kg 20.90

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.492-0.004)*1= sqmt 1.533 575.00 881.53 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.492-(0.004*2+0.01*2+0.007))*1= sqmt 1.436 450.00 646.07 (E)

Total (A+B+C+D+E) 7687.44Total without ED 6843.92

Add Water Charges @ 1% 1% 68.44Add CPOH @ 15% 15% 1036.85

Total cost per meter for pipe 7949.21Total cost per kg for specials 57.69

2.5.3.21

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.534 0.006 0.004thickness of

CML (t2) =Length of pipe

=0.007 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.534-((0.004*2)+0.006))*0.006*1*7850= kg 76.944Add 5 % wastage

5% kg 3.847Total Weight kg 80.791

#REF! Cost of MS plate kg 80.791 45.00 3635.60 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 76.944 6.63 510.14 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.847 27.00 103.87

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 4061.18

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.534-(0.004*2+0.006*2+0.007))*0.007*1*2080= kg 23.19

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.534-0.004)*1= sqmt 1.665 575.00 957.40 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.534-(0.004*2+0.006*2+0.007))*1= sqmt 1.593 450.00 716.75 (E)

Total (A+B+C+D+E) 5735.34Total without ED 5106.55

Add Water Charges @ 1% 1% 51.07

500 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick plate, 7 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 226 Schedule of Rates 2014 - 2015

Page 120: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add CPOH @ 15% 15% 773.64Total cost per meter for pipe 5931.26

Total cost per kg for specials 59.23

2.5.3.22

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.5346 0.0063 0.004thickness of

CML (t2) =Length of pipe

=0.007 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.5346-((0.004*2)+0.0063))*0.0063*1*7850= kg 80.838Add 5 % wastage

5% kg 4.042Total Weight kg 84.880

#REF! Cost of MS plate kg 84.880 45.00 3819.58 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 80.838 6.63 535.95 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 4.042 27.00 109.13

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 4265.72

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.5346-(0.004*2+0.0063*2+0.007))*0.007*1*2080= kg 23.19

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.5346-0.004)*1= sqmt 1.667 575.00 958.48 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.5346-(0.004*2+0.0063*2+0.007))*1= sqmt 1.593 450.00 716.75 (E)

Total (A+B+C+D+E) 5940.96Total without ED 5289.56

Add Water Charges @ 1% 1% 52.90Add CPOH @ 15% 15% 801.37

Total cost per meter for pipe 6143.82Total cost per kg for specials 59.06

2.5.3.23

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.544 0.011 0.004thickness of

CML (t2) =Length of pipe

=0.007 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.544-((0.004*2)+0.011))*0.011*1*7850= kg 142.420Add 5 % wastage

5% kg 7.121Total Weight kg 149.541

#REF! Cost of MS plate kg 149.541 45.00 6729.35 (A)

500 mm nominal dia (clear internal dia) of pipe with 11.0 mm thick plate, 7 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

500 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick plate, 7 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 227 Schedule of Rates 2014 - 2015

Page 121: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_320 Cost of Fabrication kg 142.420 6.63 944.25 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 7.121 27.00 192.27

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 7500.65

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.544-(0.004*2+0.011*2+0.007))*0.007*1*2080= kg 23.19

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.544-0.004)*1= sqmt 1.696 575.00 975.46 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.544-(0.004*2+0.011*2+0.007))*1= sqmt 1.593 450.00 716.75 (E)

Total (A+B+C+D+E) 9192.87Total without ED 8183.75

Add Water Charges @ 1% 1% 81.84Add CPOH @ 15% 15% 1239.84

Total cost per meter for pipe 9505.42Total cost per kg for specials 57.40

2.5.3.24

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.634 0.006 0.004thickness of

CML (t2) =Length of pipe

=0.007 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.634-((0.004*2)+0.006))*0.006*1*7850= kg 91.741Add 5 % wastage

5% kg 4.587Total Weight kg 96.328

#REF! Cost of MS plate kg 96.328 45.00 4334.75 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 91.741 6.63 608.24 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 4.587 27.00 123.85

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 4848.12

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.634-(0.004*2+0.006*2+0.007))*0.007*1*2080= kg 27.77

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.634-0.004)*1= sqmt 1.979 575.00 1138.04 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.634-(0.004*2+0.006*2+0.007))*1= sqmt 1.907 450.00 858.13 (E)

Total (A+B+C+D+E) 6844.29Total without ED 6094.58

Add Water Charges @ 1% 1% 60.95

600 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick plate, 7 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 228 Schedule of Rates 2014 - 2015

Page 122: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add CPOH @ 15% 15% 923.33Total cost per meter for pipe 7078.86

Total cost per kg for specials 59.23

2.5.3.25

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.6346 0.0063 0.004thickness of

CML (t2) =Length of pipe

=0.007 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.6346-((0.004*2)+0.0063))*0.0063*1*7850= kg 96.374Add 5 % wastage

5% kg 4.819Total Weight kg 101.193

#REF! Cost of MS plate kg 101.193 45.00 4553.69 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 96.374 6.63 638.96 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 4.819 27.00 130.11

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 5091.53

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.6346-(0.004*2+0.0063*2+0.007))*0.007*1*2080= kg 27.77

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.6346-0.004)*1= sqmt 1.981 575.00 1139.13 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.6346-(0.004*2+0.0063*2+0.007))*1= sqmt 1.907 450.00 858.13 (E)

Total (A+B+C+D+E) 7088.78Total without ED 6312.18

Add Water Charges @ 1% 1% 63.12Add CPOH @ 15% 15% 956.29

Total cost per meter for pipe 7331.59Total cost per kg for specials 59.06

2.5.3.26

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.638 0.008 0.004thickness of

CML (t2) =Length of pipe

=0.007 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.638-((0.004*2)+0.008))*0.008*1*7850= kg 122.716Add 5 % wastage

5% kg 6.136Total Weight kg 128.851

#REF! Cost of MS plate kg 128.851 45.00 5798.31 (A)

600 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick plate, 7 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

600 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick plate, 7 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 229 Schedule of Rates 2014 - 2015

Page 123: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_320 Cost of Fabrication kg 122.716 6.63 813.60 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 6.136 27.00 165.67

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 6475.23

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.638-(0.004*2+0.008*2+0.007))*0.007*1*2080= kg 27.77

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.638-0.004)*1= sqmt 1.992 575.00 1145.27 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.638-(0.004*2+0.008*2+0.007))*1= sqmt 1.907 450.00 858.13 (E)

Total (A+B+C+D+E) 8478.62Total without ED 7549.13

Add Water Charges @ 1% 1% 75.49Add CPOH @ 15% 15% 1143.69

Total cost per meter for pipe 8768.32Total cost per kg for specials 58.27

2.5.3.27

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.647 0.0125 0.004thickness of

CML (t2) =Length of pipe

=0.007 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.647-((0.004*2)+0.0125))*0.0125*1*7850= kg 193.130Add 5 % wastage

5% kg 9.657Total Weight kg 202.787

#REF! Cost of MS plate kg 202.787 45.00 9125.41 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 193.130 6.63 1280.45 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 9.657 27.00 260.73

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 10174.12

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.647-(0.004*2+0.0125*2+0.007))*0.007*1*2080= kg 27.77

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.647-0.004)*1= sqmt 2.020 575.00 1161.53 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.647-(0.004*2+0.0125*2+0.007))*1= sqmt 1.907 450.00 858.13 (E)

Total (A+B+C+D+E) 12193.77Total without ED 10855.60

Add Water Charges @ 1% 1% 108.56

600 mm nominal dia (clear internal dia) of pipe with 12.5 mm thick plate, 7 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 230 Schedule of Rates 2014 - 2015

Page 124: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add CPOH @ 15% 15% 1644.62Total cost per meter for pipe 12608.78

Total cost per kg for specials 57.08

2.5.3.28

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.738 0.006 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.738-((0.004*2)+0.006))*0.006*1*7850= kg 107.130Add 5 % wastage

5% kg 5.356Total Weight kg 112.486

#REF! Cost of MS plate kg 112.486 45.00 5061.87 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 107.130 6.63 710.27 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 5.356 27.00 144.62

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 5656.49

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.738-(0.004*2+0.006*2+0.009))*0.009*1*2080= kg 41.70

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.738-0.004)*1= sqmt 2.306 575.00 1325.91 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.738-(0.004*2+0.006*2+0.009))*1= sqmt 2.227 450.00 1002.33 (E)

Total (A+B+C+D+E) 7984.73Total without ED 7109.57

Add Water Charges @ 1% 1% 71.10Add CPOH @ 15% 15% 1077.10

Total cost per meter for pipe 8257.76Total cost per kg for specials 55.49

2.5.3.29

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.7386 0.0063 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.7386-((0.004*2)+0.0063))*0.0063*1*7850= kg 112.533Add 5 % wastage

5% kg 5.627Total Weight kg 118.159

#REF! Cost of MS plate kg 118.159 45.00 5317.17 (A)

700 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

700 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 231 Schedule of Rates 2014 - 2015

Page 125: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_320 Cost of Fabrication kg 112.533 6.63 746.09 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 5.627 27.00 151.92

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 5940.32

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.7386-(0.004*2+0.0063*2+0.009))*0.009*1*2080= kg 41.70

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.7386-0.004)*1= sqmt 2.308 575.00 1326.99 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.7386-(0.004*2+0.0063*2+0.009))*1= sqmt 2.227 450.00 1002.33 (E)

Total (A+B+C+D+E) 8269.64Total without ED 7363.13

Add Water Charges @ 1% 1% 73.63Add CPOH @ 15% 15% 1115.51

Total cost per meter for pipe 8552.28Total cost per kg for specials 55.45

2.5.3.30

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.7402 0.0071 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.7402-((0.004*2)+0.0071))*0.0071*1*7850= kg 126.963Add 5 % wastage

5% kg 6.348Total Weight kg 133.311

#REF! Cost of MS plate kg 133.311 45.00 5998.98 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 126.963 6.63 841.76 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 6.348 27.00 171.40

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 6698.32

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.7402-(0.004*2+0.0071*2+0.009))*0.009*1*2080= kg 41.70

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.7402-0.004)*1= sqmt 2.313 575.00 1329.88 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.7402-(0.004*2+0.0071*2+0.009))*1= sqmt 2.227 450.00 1002.33 (E)

Total (A+B+C+D+E) 9030.53Total without ED 8040.33

Add Water Charges @ 1% 1% 80.40

700 mm nominal dia (clear internal dia) of pipe with 7.1 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 232 Schedule of Rates 2014 - 2015

Page 126: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add CPOH @ 15% 15% 1218.11Total cost per meter for pipe 9338.84

Total cost per kg for specials 55.37

2.5.3.31

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.742 0.008 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.742-((0.004*2)+0.008))*0.008*1*7850= kg 143.234Add 5 % wastage

5% kg 7.162Total Weight kg 150.396

#REF! Cost of MS plate kg 150.396 45.00 6767.81 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 143.234 6.63 949.64 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 7.162 27.00 193.37

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 7553.06

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.742-(0.004*2+0.008*2+0.009))*0.009*1*2080= kg 41.70

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.742-0.004)*1= sqmt 2.318 575.00 1333.13 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.742-(0.004*2+0.008*2+0.009))*1= sqmt 2.227 450.00 1002.33 (E)

Total (A+B+C+D+E) 9888.52Total without ED 8803.94

Add Water Charges @ 1% 1% 88.04Add CPOH @ 15% 15% 1333.80

Total cost per meter for pipe 10225.77Total cost per kg for specials 55.30

2.5.3.32

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.7544 0.0142 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.7544-((0.004*2)+0.0142))*0.0142*1*7850= kg 256.412Add 5 % wastage

5% kg 12.821Total Weight kg 269.232

#REF! Cost of MS plate kg 269.232 45.00 12115.45 (A)

700 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

700 mm nominal dia (clear internal dia) of pipe with 14.2 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 233 Schedule of Rates 2014 - 2015

Page 127: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_320 Cost of Fabrication kg 256.412 6.63 1700.01 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 12.821 27.00 346.16

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 13498.28

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.7544-(0.004*2+0.0142*2+0.009))*0.009*1*2080= kg 41.70

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.7544-0.004)*1= sqmt 2.357 575.00 1355.53 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.7544-(0.004*2+0.0142*2+0.009))*1= sqmt 2.227 450.00 1002.33 (E)

Total (A+B+C+D+E) 15856.14Total without ED 14115.09

Add Water Charges @ 1% 1% 141.15Add CPOH @ 15% 15% 2138.44

Total cost per meter for pipe 16394.68Total cost per kg for specials 55.00

2.5.3.33

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.8402 0.0071 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.8402-((0.004*2)+0.0071))*0.0071*1*7850= kg 144.472Add 5 % wastage

5% kg 7.224Total Weight kg 151.696

#REF! Cost of MS plate kg 151.696 45.00 6826.31 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 144.472 6.63 957.85 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 7.224 27.00 195.04

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 7618.11

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.8402-(0.004*2+0.0071*2+0.009))*0.009*1*2080= kg 47.58

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.8402-0.004)*1= sqmt 2.627 575.00 1510.52 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.8402-(0.004*2+0.0071*2+0.009))*1= sqmt 2.542 450.00 1143.70 (E)

Total (A+B+C+D+E) 10272.33Total without ED 9145.52

Add Water Charges @ 1% 1% 91.46

800 mm nominal dia (clear internal dia) of pipe with 7.1 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 234 Schedule of Rates 2014 - 2015

Page 128: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add CPOH @ 15% 15% 1385.55Total cost per meter for pipe 10622.52

Total cost per kg for specials 55.31

2.5.3.34

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.842 0.008 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.842-((0.004*2)+0.008))*0.008*1*7850= kg 162.963Add 5 % wastage

5% kg 8.148Total Weight kg 171.111

#REF! Cost of MS plate kg 171.111 45.00 7700.01 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 162.963 6.63 1080.45 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 8.148 27.00 220.00

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 8589.44

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.842-(0.004*2+0.008*2+0.009))*0.009*1*2080= kg 47.58

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.842-0.004)*1= sqmt 2.633 575.00 1513.78 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.842-(0.004*2+0.008*2+0.009))*1= sqmt 2.542 450.00 1143.70 (E)

Total (A+B+C+D+E) 11246.91Total without ED 10012.90

Add Water Charges @ 1% 1% 100.13Add CPOH @ 15% 15% 1516.95

Total cost per meter for pipe 11629.98Total cost per kg for specials 55.24

2.5.3.35

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.862 0.018 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.862-((0.004*2)+0.018))*0.018*1*7850= kg 371.106Add 5 % wastage

5% kg 18.555Total Weight kg 389.662

#REF! Cost of MS plate kg 389.662 45.00 17534.77 (A)

800 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

800 mm nominal dia (clear internal dia) of pipe with 18.0 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 235 Schedule of Rates 2014 - 2015

Page 129: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_320 Cost of Fabrication kg 371.106 6.63 2460.43 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 18.555 27.00 500.99

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 19523.19

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.862-(0.004*2+0.018*2+0.009))*0.009*1*2080= kg 47.58

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.862-0.004)*1= sqmt 2.695 575.00 1549.90 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.862-(0.004*2+0.018*2+0.009))*1= sqmt 2.542 450.00 1143.70 (E)

Total (A+B+C+D+E) 22216.79Total without ED 19776.05

Add Water Charges @ 1% 1% 197.76Add CPOH @ 15% 15% 2996.07

Total cost per meter for pipe 22969.89Total cost per kg for specials 54.86

2.5.3.36

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.942 0.008 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.942-((0.004*2)+0.008))*0.008*1*7850= kg 182.692Add 5 % wastage

5% kg 9.135Total Weight kg 191.827

#REF! Cost of MS plate kg 191.827 45.00 8632.22 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 182.692 6.63 1211.25 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 9.135 27.00 246.63

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 4346.71 43.47 (C)

Material cost per meter Rs/meter 9640.30

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.942-(0.004*2+0.008*2+0.009))*0.009*1*2080= kg 53.46

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.942-0.004)*1= sqmt 2.947 575.00 1694.42 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.942-(0.004*2+0.008*2+0.009))*1= sqmt 2.856 450.00 1285.07 (E)

Total (A+B+C+D+E) 12619.79Total without ED 11236.35

Add Water Charges @ 1% 1% 112.36

900 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 236 Schedule of Rates 2014 - 2015

Page 130: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add CPOH @ 15% 15% 1702.31Total cost per meter for pipe 13051.02

Total cost per kg for specials 55.27

2.5.3.37

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.9436 0.0088 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.9436-((0.004*2)+0.0088))*0.0088*1*7850= kg 201.135Add 5 % wastage

5% kg 10.057Total Weight kg 211.192

#REF! Cost of MS plate kg 211.192 45.00 9503.64 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 201.135 6.63 1333.53 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 10.057 27.00 271.53

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 4346.71 43.47 (C)

Material cost per meter Rs/meter 10609.10

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.9436-(0.004*2+0.0088*2+0.009))*0.009*1*2080= kg 53.46

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.9436-0.004)*1= sqmt 2.952 575.00 1697.31 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.9436-(0.004*2+0.0088*2+0.009))*1= sqmt 2.856 450.00 1285.07 (E)

Total (A+B+C+D+E) 13591.48Total without ED 12101.15

Add Water Charges @ 1% 1% 121.01Add CPOH @ 15% 15% 1833.32

Total cost per meter for pipe 14055.49Total cost per kg for specials 55.21

2.5.3.38

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.946 0.01 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.946-((0.004*2)+0.01))*0.01*1*7850= kg 228.859Add 5 % wastage

5% kg 11.443Total Weight kg 240.302

#REF! Cost of MS plate kg 240.302 45.00 10813.58 (A)

900 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

900 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 237 Schedule of Rates 2014 - 2015

Page 131: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_320 Cost of Fabrication kg 228.859 6.63 1517.33 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 11.443 27.00 308.96

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 4346.71 43.47 (C)

Material cost per meter Rs/meter 12065.42

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.946-(0.004*2+0.01*2+0.009))*0.009*1*2080= kg 53.46

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.946-0.004)*1= sqmt 2.959 575.00 1701.64 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.946-(0.004*2+0.01*2+0.009))*1= sqmt 2.856 450.00 1285.07 (E)

Total (A+B+C+D+E) 15052.13Total without ED 13401.12

Add Water Charges @ 1% 1% 134.01Add CPOH @ 15% 15% 2030.27

Total cost per meter for pipe 15565.40Total cost per kg for specials 55.13

2.5.3.39

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.961 0.0175 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.961-((0.004*2)+0.0175))*0.0175*1*7850= kg 403.740Add 5 % wastage

5% kg 20.187Total Weight kg 423.927

#REF! Cost of MS plate kg 423.927 45.00 19076.70 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 403.740 6.63 2676.79 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 20.187 27.00 545.05

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 4346.71 43.47 (C)

Material cost per meter Rs/meter 21251.91

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.961-(0.004*2+0.0175*2+0.009))*0.009*1*2080= kg 53.46

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.961-0.004)*1= sqmt 3.007 575.00 1728.74 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.961-(0.004*2+0.0175*2+0.009))*1= sqmt 2.856 450.00 1285.07 (E)

Total (A+B+C+D+E) 24265.72Total without ED 21601.18

Add Water Charges @ 1% 1% 216.01

900 mm nominal dia (clear internal dia) of pipe with 17.5 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 238 Schedule of Rates 2014 - 2015

Page 132: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add CPOH @ 15% 15% 3272.58Total cost per meter for pipe 25089.78

Total cost per kg for specials 54.88

2.5.3.40

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.0436 0.0088 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.0436-((0.004*2)+0.0088))*0.0088*1*7850= kg 222.837Add 5 % wastage

5% kg 11.142Total Weight kg 233.979

#REF! Cost of MS plate kg 233.979 45.00 10529.07 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 222.837 6.63 1477.41 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 11.142 27.00 300.83

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 11763.60

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.0436-(0.004*2+0.0088*2+0.009))*0.009*1*2080= kg 59.34

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.0436-0.004)*1= sqmt 3.266 575.00 1877.95 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.0436-(0.004*2+0.0088*2+0.009))*1= sqmt 3.170 450.00 1426.44 (E)

Total (A+B+C+D+E) 15067.99Total without ED 13416.84

Add Water Charges @ 1% 1% 134.17Add CPOH @ 15% 15% 2032.65

Total cost per meter for pipe 15583.66Total cost per kg for specials 55.23

2.5.3.41

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.046 0.01 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.046-((0.004*2)+0.01))*0.01*1*7850= kg 253.520Add 5 % wastage

5% kg 12.676Total Weight kg 266.196

#REF! Cost of MS plate kg 266.196 45.00 11978.83 (A)

1000 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

1000 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 239 Schedule of Rates 2014 - 2015

Page 133: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_320 Cost of Fabrication kg 253.520 6.63 1680.84 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 12.676 27.00 342.25

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 13375.37

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.046-(0.004*2+0.01*2+0.009))*0.009*1*2080= kg 59.34

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.046-0.004)*1= sqmt 3.274 575.00 1882.29 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.046-(0.004*2+0.01*2+0.009))*1= sqmt 3.170 450.00 1426.44 (E)

Total (A+B+C+D+E) 16684.10Total without ED 14855.16

Add Water Charges @ 1% 1% 148.55Add CPOH @ 15% 15% 2250.56

Total cost per meter for pipe 17254.27Total cost per kg for specials 55.15

2.5.3.42

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.066 0.02 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.066-((0.004*2)+0.02))*0.02*1*7850= kg 511.973Add 5 % wastage

5% kg 25.599Total Weight kg 537.571

#REF! Cost of MS plate kg 537.571 45.00 24190.71 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 511.973 6.63 3394.38 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 25.599 27.00 691.16

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 26951.89

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.066-(0.004*2+0.02*2+0.009))*0.009*1*2080= kg 59.34

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.066-0.004)*1= sqmt 3.336 575.00 1918.41 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.066-(0.004*2+0.02*2+0.009))*1= sqmt 3.170 450.00 1426.44 (E)

Total (A+B+C+D+E) 30296.74Total without ED 26970.37

Add Water Charges @ 1% 1% 269.70

1000 mm nominal dia (clear internal dia) of pipe with 20.0 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 240 Schedule of Rates 2014 - 2015

Page 134: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add CPOH @ 15% 15% 4086.01Total cost per meter for pipe 31326.08

Total cost per kg for specials 54.83

2.5.3.43

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.0936 0.0088 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.0936-((0.004*2)+0.0088))*0.0088*1*7850= kg 233.688Add 5 % wastage

5% kg 11.684Total Weight kg 245.373

#REF! Cost of MS plate kg 245.373 45.00 11041.78 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 233.688 6.63 1549.35 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 11.684 27.00 315.48

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 12333.61

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.0936-(0.004*2+0.0088*2+0.009))*0.009*1*2080= kg 62.28

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.0936-0.004)*1= sqmt 3.423 575.00 1968.27 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.0936-(0.004*2+0.0088*2+0.009))*1= sqmt 3.327 450.00 1497.13 (E)

Total (A+B+C+D+E) 15799.01Total without ED 14067.44

Add Water Charges @ 1% 1% 140.67Add CPOH @ 15% 15% 2131.22

Total cost per meter for pipe 16339.33Total cost per kg for specials 55.21

2.5.3.44

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.096 0.01 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.096-((0.004*2)+0.01))*0.01*1*7850= kg 265.851Add 5 % wastage

5% kg 13.293Total Weight kg 279.144

#REF! Cost of MS plate kg 279.144 45.00 12561.46 (A)

1050 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

1050 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 241 Schedule of Rates 2014 - 2015

Page 135: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_320 Cost of Fabrication kg 265.851 6.63 1762.59 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 13.293 27.00 358.90

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 14023.11

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.096-(0.004*2+0.01*2+0.009))*0.009*1*2080= kg 62.28

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.096-0.004)*1= sqmt 3.431 575.00 1972.61 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.096-(0.004*2+0.01*2+0.009))*1= sqmt 3.327 450.00 1497.13 (E)

Total (A+B+C+D+E) 17492.84Total without ED 15574.94

Add Water Charges @ 1% 1% 155.75Add CPOH @ 15% 15% 2359.60

Total cost per meter for pipe 18090.29Total cost per kg for specials 55.13

2.5.3.45

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.098 0.011 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.098-((0.004*2)+0.011))*0.011*1*7850= kg 292.707Add 5 % wastage

5% kg 14.635Total Weight kg 307.343

#REF! Cost of MS plate kg 307.343 45.00 13830.42 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 292.707 6.63 1940.65 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 14.635 27.00 395.15

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 15433.87

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.098-(0.004*2+0.011*2+0.009))*0.009*1*2080= kg 62.28

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.098-0.004)*1= sqmt 3.437 575.00 1976.22 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.098-(0.004*2+0.011*2+0.009))*1= sqmt 3.327 450.00 1497.13 (E)

Total (A+B+C+D+E) 18907.22Total without ED 16833.73

Add Water Charges @ 1% 1% 168.34

1050 mm nominal dia (clear internal dia) of pipe with 11.0 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 242 Schedule of Rates 2014 - 2015

Page 136: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add CPOH @ 15% 15% 2550.31Total cost per meter for pipe 19552.38

Total cost per kg for specials 55.08

2.5.3.46

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.1436 0.0088 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.1436-((0.004*2)+0.0088))*0.0088*1*7850= kg 244.540Add 5 % wastage

5% kg 12.227Total Weight kg 256.766

#REF! Cost of MS plate kg 256.766 45.00 11554.49 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 244.540 6.63 1621.30 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 12.227 27.00 330.13

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 12903.62

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.1436-(0.004*2+0.0088*2+0.009))*0.009*1*2080= kg 65.22

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.1436-0.004)*1= sqmt 3.580 575.00 2058.59 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.1436-(0.004*2+0.0088*2+0.009))*1= sqmt 3.484 450.00 1567.81 (E)

Total (A+B+C+D+E) 16530.02Total without ED 14718.03

Add Water Charges @ 1% 1% 147.18Add CPOH @ 15% 15% 2229.78

Total cost per meter for pipe 17095.00Total cost per kg for specials 55.19

2.5.3.47

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.146 0.01 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.146-((0.004*2)+0.01))*0.01*1*7850= kg 278.182Add 5 % wastage

5% kg 13.909Total Weight kg 292.091

#REF! Cost of MS plate kg 292.091 45.00 13144.09 (A)

1100 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

1100 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 243 Schedule of Rates 2014 - 2015

Page 137: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_320 Cost of Fabrication kg 278.182 6.63 1844.34 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 13.909 27.00 375.55

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 14670.84

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.146-(0.004*2+0.01*2+0.009))*0.009*1*2080= kg 65.22

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.146-0.004)*1= sqmt 3.588 575.00 2062.93 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.146-(0.004*2+0.01*2+0.009))*1= sqmt 3.484 450.00 1567.81 (E)

Total (A+B+C+D+E) 18301.58Total without ED 16294.72

Add Water Charges @ 1% 1% 162.95Add CPOH @ 15% 15% 2468.65

Total cost per meter for pipe 18926.32Total cost per kg for specials 55.11

2.5.3.48

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.148 0.011 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.148-((0.004*2)+0.011))*0.011*1*7850= kg 306.271Add 5 % wastage

5% kg 15.314Total Weight kg 321.585

#REF! Cost of MS plate kg 321.585 45.00 14471.31 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 306.271 6.63 2030.58 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 15.314 27.00 413.47

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 16146.38

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.148-(0.004*2+0.011*2+0.009))*0.009*1*2080= kg 65.22

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.148-0.004)*1= sqmt 3.594 575.00 2066.54 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.148-(0.004*2+0.011*2+0.009))*1= sqmt 3.484 450.00 1567.81 (E)

Total (A+B+C+D+E) 19780.73Total without ED 17611.16

Add Water Charges @ 1% 1% 176.11

1100 mm nominal dia (clear internal dia) of pipe with 11.0 mm thick plate, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 244 Schedule of Rates 2014 - 2015

Page 138: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add CPOH @ 15% 15% 2668.09Total cost per meter for pipe 20455.36

Total cost per kg for specials 55.06

2.5.3.49

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.252 0.01 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.252-((0.004*2)+0.01))*0.01*1*7850= kg 304.323Add 5 % wastage

5% kg 15.216Total Weight kg 319.539

#REF! Cost of MS plate kg 319.539 45.00 14379.26 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 304.323 6.63 2017.66 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 15.216 27.00 410.84

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 16044.04

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.252-(0.004*2+0.01*2+0.012))*0.012*1*2080= kg 95.04

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.252-0.004)*1= sqmt 3.921 575.00 2254.41 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.252-(0.004*2+0.01*2+0.012))*1= sqmt 3.808 450.00 1713.42 (E)

Total (A+B+C+D+E) 20011.87Total without ED 17816.87

Add Water Charges @ 1% 1% 178.17Add CPOH @ 15% 15% 2699.26

Total cost per meter for pipe 20694.29Total cost per kg for specials 51.82

2.5.3.50

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.254 0.011 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.254-((0.004*2)+0.011))*0.011*1*7850= kg 335.027Add 5 % wastage

5% kg 16.751Total Weight kg 351.778

#REF! Cost of MS plate kg 351.778 45.00 15830.00 (A)

1200 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

1200 mm nominal dia (clear internal dia) of pipe with 11.0 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 245 Schedule of Rates 2014 - 2015

Page 139: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_320 Cost of Fabrication kg 335.027 6.63 2221.23 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 16.751 27.00 452.29

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 17656.90

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.254-(0.004*2+0.011*2+0.012))*0.012*1*2080= kg 95.04

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.254-0.004)*1= sqmt 3.927 575.00 2258.02 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.254-(0.004*2+0.011*2+0.012))*1= sqmt 3.808 450.00 1713.42 (E)

Total (A+B+C+D+E) 21628.34Total without ED 19255.52

Add Water Charges @ 1% 1% 192.56Add CPOH @ 15% 15% 2917.21

Total cost per meter for pipe 22365.29Total cost per kg for specials 52.00

2.5.3.51

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.256 0.012 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.256-((0.004*2)+0.012))*0.012*1*7850= kg 365.779Add 5 % wastage

5% kg 18.289Total Weight kg 384.068

#REF! Cost of MS plate kg 384.068 45.00 17283.08 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 365.779 6.63 2425.12 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 18.289 27.00 493.80

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 19272.35

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.256-(0.004*2+0.012*2+0.012))*0.012*1*2080= kg 95.04

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.256-0.004)*1= sqmt 3.933 575.00 2261.63 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.256-(0.004*2+0.012*2+0.012))*1= sqmt 3.808 450.00 1713.42 (E)

Total (A+B+C+D+E) 23247.41Total without ED 20696.48

Add Water Charges @ 1% 1% 206.96

1200 mm nominal dia (clear internal dia) of pipe with 12.0 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 246 Schedule of Rates 2014 - 2015

Page 140: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add CPOH @ 15% 15% 3135.52Total cost per meter for pipe 24038.97

Total cost per kg for specials 52.17

2.5.3.52

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.257 0.0125 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.257-((0.004*2)+0.0125))*0.0125*1*7850= kg 381.174Add 5 % wastage

5% kg 19.059Total Weight kg 400.233

#REF! Cost of MS plate kg 400.233 45.00 18010.49 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 381.174 6.63 2527.19 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 19.059 27.00 514.59

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 20081.04

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.257-(0.004*2+0.0125*2+0.012))*0.012*1*2080= kg 95.04

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.257-0.004)*1= sqmt 3.936 575.00 2263.44 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.257-(0.004*2+0.0125*2+0.012))*1= sqmt 3.808 450.00 1713.42 (E)

Total (A+B+C+D+E) 24057.91Total without ED 21417.83

Add Water Charges @ 1% 1% 214.18Add CPOH @ 15% 15% 3244.80

Total cost per meter for pipe 24876.81Total cost per kg for specials 52.24

2.5.3.53

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.456 0.012 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.456-((0.004*2)+0.012))*0.012*1*7850= kg 424.967Add 5 % wastage

5% kg 21.248Total Weight kg 446.215

#REF! Cost of MS plate kg 446.215 45.00 20079.69 (A)

1400 mm nominal dia (clear internal dia) of pipe with 12 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

1200 mm nominal dia (clear internal dia) of pipe with 12.5 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 247 Schedule of Rates 2014 - 2015

Page 141: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_320 Cost of Fabrication kg 424.967 6.63 2817.53 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 21.248 27.00 573.71

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 7244.52 72.45 (C)

Material cost per meter Rs/meter 22395.96

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.456-(0.004*2+0.012*2+0.012))*0.012*1*2080= kg 110.72

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.456-0.004)*1= sqmt 4.562 575.00 2622.92 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.456-(0.004*2+0.012*2+0.012))*1= sqmt 4.436 450.00 1996.17 (E)

Total (A+B+C+D+E) 27015.05Total without ED 24051.26

Add Water Charges @ 1% 1% 240.51Add CPOH @ 15% 15% 3643.77

Total cost per meter for pipe 27935.54Total cost per kg for specials 52.15

2.5.3.54

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.457 0.0125 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.457-((0.004*2)+0.0125))*0.0125*1*7850= kg 442.828Add 5 % wastage

5% kg 22.141Total Weight kg 464.970

#REF! Cost of MS plate kg 464.970 45.00 20923.63 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 442.828 6.63 2935.95 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 22.141 27.00 597.82

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 7244.52 72.45 (C)

Material cost per meter Rs/meter 23334.21

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.457-(0.004*2+0.0125*2+0.012))*0.012*1*2080= kg 110.72

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.457-0.004)*1= sqmt 4.565 575.00 2624.72 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.457-(0.004*2+0.0125*2+0.012))*1= sqmt 4.436 450.00 1996.17 (E)

Total (A+B+C+D+E) 27955.10Total without ED 24887.90

Add Water Charges @ 1% 1% 248.88

1400 mm nominal dia (clear internal dia) of pipe with 12.5 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 248 Schedule of Rates 2014 - 2015

Page 142: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add CPOH @ 15% 15% 3770.52Total cost per meter for pipe 28907.30

Total cost per kg for specials 52.22

2.5.3.55

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.4604 0.0142 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.4604-((0.004*2)+0.0142))*0.0142*1*7850= kg 503.648Add 5 % wastage

5% kg 25.182Total Weight kg 528.830

#REF! Cost of MS plate kg 528.830 45.00 23797.37 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 503.648 6.63 3339.19 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 25.182 27.00 679.92

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 7244.52 72.45 (C)

Material cost per meter Rs/meter 26529.08

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.4604-(0.004*2+0.0142*2+0.012))*0.012*1*2080= kg 110.72

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.4604-0.004)*1= sqmt 4.575 575.00 2630.86 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.4604-(0.004*2+0.0142*2+0.012))*1= sqmt 4.436 450.00 1996.17 (E)

Total (A+B+C+D+E) 31156.11Total without ED 27736.80

Add Water Charges @ 1% 1% 277.37Add CPOH @ 15% 15% 4202.12

Total cost per meter for pipe 32216.29Total cost per kg for specials 52.44

2.5.3.56

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.556 0.012 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.556-((0.004*2)+0.012))*0.012*1*7850= kg 454.561Add 5 % wastage

5% kg 22.728Total Weight kg 477.289

#REF! Cost of MS plate kg 477.289 45.00 21478.00 (A)

1400 mm nominal dia (clear internal dia) of pipe with 14.2 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

1500 mm nominal dia (clear internal dia) of pipe with 12 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 249 Schedule of Rates 2014 - 2015

Page 143: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_320 Cost of Fabrication kg 454.561 6.63 3013.74 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 22.728 27.00 613.66

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 8693.42 86.93 (C)

Material cost per meter Rs/meter 23965.01

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.556-(0.004*2+0.012*2+0.012))*0.012*1*2080= kg 118.56

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.556-0.004)*1= sqmt 4.876 575.00 2803.56 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.556-(0.004*2+0.012*2+0.012))*1= sqmt 4.750 450.00 2137.54 (E)

Total (A+B+C+D+E) 28906.11Total without ED 25735.90

Add Water Charges @ 1% 1% 257.36Add CPOH @ 15% 15% 3898.99

Total cost per meter for pipe 29892.25Total cost per kg for specials 52.16

2.5.3.57

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.6604 0.0142 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.6604-((0.004*2)+0.0142))*0.0142*1*7850= kg 573.687Add 5 % wastage

5% kg 28.684Total Weight kg 602.371

#REF! Cost of MS plate kg 602.371 45.00 27106.70 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 573.687 6.63 3803.54 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 28.684 27.00 774.48

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 8693.42 86.93 (C)

Material cost per meter Rs/meter 30222.70

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.6604-(0.004*2+0.0142*2+0.012))*0.012*1*2080= kg 126.40

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.6604-0.004)*1= sqmt 5.204 575.00 2992.15 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.6604-(0.004*2+0.0142*2+0.012))*1= sqmt 5.064 450.00 2278.91 (E)

Total (A+B+C+D+E) 35493.76Total without ED 31598.88

Add Water Charges @ 1% 1% 315.99

1600 mm nominal dia (clear internal dia) of pipe with 14.2 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 250 Schedule of Rates 2014 - 2015

Page 144: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add CPOH @ 15% 15% 4787.23Total cost per meter for pipe 36702.10

Total cost per kg for specials 52.42

2.5.3.58

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.664 0.016 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.664-((0.004*2)+0.016))*0.016*1*7850= kg 647.118Add 5 % wastage

5% kg 32.356Total Weight kg 679.474

#REF! Cost of MS plate kg 679.474 45.00 30576.32 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 647.118 6.63 4290.39 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 32.356 27.00 873.61

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 8693.42 86.93 (C)

Material cost per meter Rs/meter 34080.03

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.664-(0.004*2+0.016*2+0.012))*0.012*1*2080= kg 126.40

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.664-0.004)*1= sqmt 5.215 575.00 2998.65 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.664-(0.004*2+0.016*2+0.012))*1= sqmt 5.064 450.00 2278.91 (E)

Total (A+B+C+D+E) 39357.59Total without ED 35037.68

Add Water Charges @ 1% 1% 350.38Add CPOH @ 15% 15% 5308.21

Total cost per meter for pipe 40696.27Total cost per kg for specials 52.61

2.5.3.59

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.8604 0.0142 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.8604-((0.004*2)+0.0142))*0.0142*1*7850= kg 643.725Add 5 % wastage

5% kg 32.186Total Weight kg 675.912

#REF! Cost of MS plate kg 675.912 45.00 30416.02 (A)

1600 mm nominal dia (clear internal dia) of pipe with 16.0 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

1800 mm nominal dia (clear internal dia) of pipe with 14.2 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 251 Schedule of Rates 2014 - 2015

Page 145: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_320 Cost of Fabrication kg 643.725 6.63 4267.90 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 32.186 27.00 869.03

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 10142.33 101.42 (C)

Material cost per meter Rs/meter 33916.32

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.8604-(0.004*2+0.0142*2+0.012))*0.012*1*2080= kg 142.09

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.8604-0.004)*1= sqmt 5.832 575.00 3353.43 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.8604-(0.004*2+0.0142*2+0.012))*1= sqmt 5.693 450.00 2561.65 (E)

Total (A+B+C+D+E) 39831.40Total without ED 35460.96

Add Water Charges @ 1% 1% 354.61Add CPOH @ 15% 15% 5372.34

Total cost per meter for pipe 41187.91Total cost per kg for specials 52.41

2.5.3.60

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.864 0.016 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.864-((0.004*2)+0.016))*0.016*1*7850= kg 726.035Add 5 % wastage

5% kg 36.302Total Weight kg 762.336

#REF! Cost of MS plate kg 762.336 45.00 34305.14 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 726.035 6.63 4813.61 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 36.302 27.00 980.15

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 10142.33 101.42 (C)

Material cost per meter Rs/meter 38240.02

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.864-(0.004*2+0.016*2+0.012))*0.012*1*2080= kg 142.09

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.864-0.004)*1= sqmt 5.843 575.00 3359.93 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.864-(0.004*2+0.016*2+0.012))*1= sqmt 5.693 450.00 2561.65 (E)

Total (A+B+C+D+E) 44161.61Total without ED 39314.83

Add Water Charges @ 1% 1% 393.15

1800 mm nominal dia (clear internal dia) of pipe with 16.0 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 252 Schedule of Rates 2014 - 2015

Page 146: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add CPOH @ 15% 15% 5956.20Total cost per meter for pipe 45664.18

Total cost per kg for specials 52.60

2.5.3.61

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.867 0.0175 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.867-((0.004*2)+0.0175))*0.0175*1*7850= kg 794.748Add 5 % wastage

5% kg 39.737Total Weight kg 834.485

#REF! Cost of MS plate kg 834.485 45.00 37551.83 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 794.748 6.63 5269.18 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 39.737 27.00 1072.91

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 10142.33 101.42 (C)

Material cost per meter Rs/meter 41849.52

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.867-(0.004*2+0.0175*2+0.012))*0.012*1*2080= kg 142.09

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.867-0.004)*1= sqmt 5.853 575.00 3365.35 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.867-(0.004*2+0.0175*2+0.012))*1= sqmt 5.693 450.00 2561.65 (E)

Total (A+B+C+D+E) 47776.53Total without ED 42532.10

Add Water Charges @ 1% 1% 425.32Add CPOH @ 15% 15% 6443.61

Total cost per meter for pipe 49401.03Total cost per kg for specials 52.73

2.5.3.62

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

2.064 0.016 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(2.064-((0.004*2)+0.016))*0.016*1*7850= kg 804.951Add 5 % wastage

5% kg 40.248Total Weight kg 845.199

#REF! Cost of MS plate kg 845.199 45.00 38033.96 (A)

1800 mm nominal dia (clear internal dia) of pipe with 17.5 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

2000 mm nominal dia (clear internal dia) of pipe with 16.0 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 253 Schedule of Rates 2014 - 2015

Page 147: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_320 Cost of Fabrication kg 804.951 6.63 5336.83 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 40.248 27.00 1086.68

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 11591.23 115.91 (C)

Material cost per meter Rs/meter 42400.01

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(2.064-(0.004*2+0.016*2+0.012))*0.012*1*2080= kg 157.77

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(2.064-0.004)*1= sqmt 6.472 575.00 3721.22 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(2.064-(0.004*2+0.016*2+0.012))*1= sqmt 6.321 450.00 2844.40 (E)

Total (A+B+C+D+E) 48965.63Total without ED 43591.98

Add Water Charges @ 1% 1% 435.92Add CPOH @ 15% 15% 6604.19

Total cost per meter for pipe 50632.09Total cost per kg for specials 52.59

2.5.3.63

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

2.067 0.0175 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(2.067-((0.004*2)+0.0175))*0.0175*1*7850= kg 881.063Add 5 % wastage

5% kg 44.053Total Weight kg 925.116

#REF! Cost of MS plate kg 925.116 45.00 41630.23 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 881.063 6.63 5841.45 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 44.053 27.00 1189.44

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 11591.23 115.91 (C)

Material cost per meter Rs/meter 46398.15

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(2.067-(0.004*2+0.0175*2+0.012))*0.012*1*2080= kg 157.77

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(2.067-0.004)*1= sqmt 6.481 575.00 3726.64 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(2.067-(0.004*2+0.0175*2+0.012))*1= sqmt 6.321 450.00 2844.40 (E)

Total (A+B+C+D+E) 52969.19Total without ED 47155.14

Add Water Charges @ 1% 1% 471.55

2000 mm nominal dia (clear internal dia) of pipe with 17.5 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 254 Schedule of Rates 2014 - 2015

Page 148: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add CPOH @ 15% 15% 7144.00Total cost per meter for pipe 54770.69

Total cost per kg for specials 52.72

2.5.3.64

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

2.072 0.02 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(2.072-((0.004*2)+0.02))*0.02*1*7850= kg 1008.162Add 5 % wastage

5% kg 50.408Total Weight kg 1058.570

#REF! Cost of MS plate kg 1058.570 45.00 47635.66 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 1008.162 6.63 6684.12 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 50.408 27.00 1361.02

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 11591.23 115.91 (C)

Material cost per meter Rs/meter 53074.67

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(2.072-(0.004*2+0.02*2+0.012))*0.012*1*2080= kg 157.77

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(2.072-0.004)*1= sqmt 6.497 575.00 3735.67 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(2.072-(0.004*2+0.02*2+0.012))*1= sqmt 6.321 450.00 2844.40 (E)

Total (A+B+C+D+E) 59654.74Total without ED 53105.26

Add Water Charges @ 1% 1% 531.05Add CPOH @ 15% 15% 8045.45

Total cost per meter for pipe 61681.76Total cost per kg for specials 52.90

2.5.3.65

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

2.267 0.0175 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(2.267-((0.004*2)+0.0175))*0.0175*1*7850= kg 967.378Add 5 % wastage

5% kg 48.369Total Weight kg 1015.747

#REF! Cost of MS plate kg 1015.747 45.00 45708.62 (A)

2200 mm nominal dia (clear internal dia) of pipe with 17.5 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

2000 mm nominal dia (clear internal dia) of pipe with 20.0 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 255 Schedule of Rates 2014 - 2015

Page 149: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_320 Cost of Fabrication kg 967.378 6.63 6413.72 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 48.369 27.00 1305.96

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 13040.13 130.40 (C)

Material cost per meter Rs/meter 50946.78

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(2.267-(0.004*2+0.0175*2+0.012))*0.012*1*2080= kg 173.45

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(2.267-0.004)*1= sqmt 7.109 575.00 4087.92 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(2.267-(0.004*2+0.0175*2+0.012))*1= sqmt 6.949 450.00 3127.14 (E)

Total (A+B+C+D+E) 58161.84Total without ED 51778.18

Add Water Charges @ 1% 1% 517.78Add CPOH @ 15% 15% 7844.39

Total cost per meter for pipe 60140.35Total cost per kg for specials 52.72

2.5.3.66

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

2.272 0.02 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(2.272-((0.004*2)+0.02))*0.02*1*7850= kg 1106.808Add 5 % wastage

5% kg 55.340Total Weight kg 1162.149

#REF! Cost of MS plate kg 1162.149 45.00 52296.69 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 1106.808 6.63 7338.14 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 55.340 27.00 1494.19

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 13040.13 130.40 (C)

Material cost per meter Rs/meter 58271.04

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(2.272-(0.004*2+0.02*2+0.012))*0.012*1*2080= kg 173.45

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(2.272-0.004)*1= sqmt 7.125 575.00 4096.95 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(2.272-(0.004*2+0.02*2+0.012))*1= sqmt 6.949 450.00 3127.14 (E)

Total (A+B+C+D+E) 65495.13Total without ED 58304.78

Add Water Charges @ 1% 1% 583.05

2200 mm nominal dia (clear internal dia) of pipe with 20.0 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 256 Schedule of Rates 2014 - 2015

Page 150: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add CPOH @ 15% 15% 8833.17Total cost per meter for pipe 67721.00

Total cost per kg for specials 52.90

2.5.3.67

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

2.2764 0.0222 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(2.2764-((0.004*2)+0.0222))*0.0222*1*7850= kg 1229.762Add 5 % wastage

5% kg 61.488Total Weight kg 1291.250

#REF! Cost of MS plate kg 1291.250 45.00 58106.24 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 1229.762 6.63 8153.32 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 61.488 27.00 1660.18

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 13040.13 130.40 (C)

Material cost per meter Rs/meter 64729.78

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(2.2764-(0.004*2+0.0222*2+0.012))*0.012*1*2080= kg 173.45

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(2.2764-0.004)*1= sqmt 7.139 575.00 4104.90 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(2.2764-(0.004*2+0.0222*2+0.012))*1= sqmt 6.949 450.00 3127.14 (E)

Total (A+B+C+D+E) 71961.82Total without ED 64060.11

Add Water Charges @ 1% 1% 640.60Add CPOH @ 15% 15% 9705.11

Total cost per meter for pipe 74405.81Total cost per kg for specials 53.03

2.5.3.68

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

2.572 0.02 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(2.572-((0.004*2)+0.02))*0.02*1*7850= kg 1254.777Add 5 % wastage

5% kg 62.739Total Weight kg 1317.516

#REF! Cost of MS plate kg 1317.516 45.00 59288.22 (A)

2200 mm nominal dia (clear internal dia) of pipe with 22.2 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

2500 mm nominal dia (clear internal dia) of pipe with 20.0 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 257 Schedule of Rates 2014 - 2015

Page 151: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_320 Cost of Fabrication kg 1254.777 6.63 8319.17 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 62.739 27.00 1693.95

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 14489.04 144.89 (C)

Material cost per meter Rs/meter 66058.34

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(2.572-(0.004*2+0.02*2+0.012))*0.012*1*2080= kg 196.98

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(2.572-0.004)*1= sqmt 8.068 575.00 4638.88 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(2.572-(0.004*2+0.02*2+0.012))*1= sqmt 7.892 450.00 3551.26 (E)

Total (A+B+C+D+E) 74248.47Total without ED 66096.81

Add Water Charges @ 1% 1% 660.97Add CPOH @ 15% 15% 10013.67

Total cost per meter for pipe 76771.45Total cost per kg for specials 52.88

2.5.3.69

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

2.5764 0.0222 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(2.5764-((0.004*2)+0.0222))*0.0222*1*7850= kg 1394.007Add 5 % wastage

5% kg 69.700Total Weight kg 1463.708

#REF! Cost of MS plate kg 1463.708 45.00 65866.84 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 1394.007 6.63 9242.27 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 69.700 27.00 1881.91

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 14489.04 144.89 (C)

Material cost per meter Rs/meter 73372.09

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(2.5764-(0.004*2+0.0222*2+0.012))*0.012*1*2080= kg 196.98

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(2.5764-0.004)*1= sqmt 8.081 575.00 4646.82 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(2.5764-(0.004*2+0.0222*2+0.012))*1= sqmt 7.892 450.00 3551.26 (E)

Total (A+B+C+D+E) 81570.17Total without ED 72613.10

Add Water Charges @ 1% 1% 726.13

2500 mm nominal dia (clear internal dia) of pipe with 22.2 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 258 Schedule of Rates 2014 - 2015

Page 152: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add CPOH @ 15% 15% 11000.88Total cost per meter for pipe 84340.11

Total cost per kg for specials 53.01

2.5.3.70

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

2.582 0.025 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS plate = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(2.582-((0.004*2)+0.025))*0.025*1*7850= kg 1571.554Add 5 % wastage

5% kg 78.578Total Weight kg 1650.132

#REF! Cost of MS plate kg 1650.132 45.00 74255.94 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 1571.554 6.63 10419.40 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 78.578 27.00 2121.60

Please refer Rate Analysis_Vol II_pg no

20Carriage of steel 100m 1.00 14489.04 144.89 (C)

Material cost per meter Rs/meter 82698.63

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(2.582-(0.004*2+0.025*2+0.012))*0.012*1*2080= kg 196.98

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg

no 448Area of coating = pi()*(d-t3 )*L

(3.1416)*(2.582-0.004)*1= sqmt 8.099 575.00 4656.94 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(2.582-(0.004*2+0.025*2+0.012))*1= sqmt 7.892 450.00 3551.26 (E)

Total (A+B+C+D+E) 90906.83Total without ED 80922.69

Add Water Charges @ 1% 1% 809.23Add CPOH @ 15% 15% 12259.79

Total cost per meter for pipe 93991.71Total cost per kg for specials 53.15

2500 mm nominal dia (clear internal dia) of pipe with 25.0 mm thick plate, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 259 Schedule of Rates 2014 - 2015

Page 153: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

2.5.4

2.5.4.1

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.18 0.005 0.004thickness of

CML (t2) =Length of pipe

=0.006 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.18-((0.004*2)+0.005))*0.005*1*7850= kg 20.592Add 2 % wastage

2% kg 0.412Total Weight kg 21.004

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 21.004 34.21 718.56 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 20.592 6.63 136.53 (B)

Quotation_Volume III_pg no_272 Cost of scrap kg 0.412 27.00 11.12

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 289.78 2.90 (C)

Material cost per meter Rs/meter 846.86

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.18-(0.004*2+0.005*2+0.006))*0.006*1*2080= kg 6.12

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.18-0.004)*1= sqmt 0.553 575.00 317.93 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.18-(0.004*2+0.005*2+0.006))*1= sqmt 0.490 450.00 220.54 (E)

Total (A+B+C+D+E) 1385.33Total without ED 1233.26

Add Water Charges @ 1% 1% 12.33Add CPOH @ 15% 15% 186.84

Providing Mild Steel Pipes / specials fabricated / manufactured out of MS coil of steel grade Fe410 as per IS 3589:2001; internally lined with cementmortar lining and external / outside 4mm coaltar coating and wrapping shall confirm to IS 10221:2008; minimum thickness of M.S. Coil as specified;complete in all respect; with upto date amendments in relevant IS codes and as directed by Engineer-in-charge. The rates are excluding excise dutycomponent.

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, 6 mm thick internal cement mortar lining and exterior / outside 4mm coaltar coatingand wrapping

Delhi Jal Board 273 Schedule of Rates 2014 - 2015

Page 154: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Total cost per meter for pipe 1432.43Total cost per kg for specials 53.63

2.5.4.2

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.23 0.005 0.004thickness of

CML (t2) =Length of pipe

=0.006 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.23-((0.004*2)+0.005))*0.005*1*7850= kg 26.758Add 2 % wastage

2% kg 0.535Total Weight kg 27.293

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 27.293 34.21 933.70 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 26.758 6.63 177.40 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.535 27.00 14.45

Rate anlalysis enclosed Carriage of steel 100m 1.00 471.38 4.71 (C)

Material cost per meter Rs/meter 1101.36

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.23-(0.004*2+0.005*2+0.006))*0.006*1*2080= kg 8.08

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.23-0.004)*1= sqmt 0.710 575.00 408.25 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.23-(0.004*2+0.005*2+0.006))*1= sqmt 0.647 450.00 291.23 (E)

Total (A+B+C+D+E) 1800.84Total without ED 1603.26

Add Water Charges @ 1% 1% 16.03Add CPOH @ 15% 15% 242.89

Total cost per meter for pipe 1862.19Total cost per kg for specials 53.46

2.5.4.3

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.232 0.006 0.004thickness of

CML (t2) =Length of pipe

=0.006 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.232-((0.004*2)+0.006))*0.006*1*7850= kg 32.257Add 2 % wastage

2% kg 0.645Total Weight kg 32.902

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 32.902 34.21 1125.60 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 32.257 6.63 213.87 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.645 27.00 17.42

200 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, 6 mm thick internal cement mortar lining and exterior / outside 4mm coaltar coatingand wrapping

200 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick coil, 6 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 274 Schedule of Rates 2014 - 2015

Page 155: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Rate anlalysis enclosed Carriage of steel 100m 1.00 471.38 4.71 (C)

Material cost per meter Rs/meter 1326.76

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.232-(0.004*2+0.006*2+0.006))*0.006*1*2080= kg 8.08

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.232-0.004)*1= sqmt 0.716 575.00 411.86 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.232-(0.004*2+0.006*2+0.006))*1= sqmt 0.647 450.00 291.23 (E)

Total (A+B+C+D+E) 2029.85Total without ED 1807.08

Add Water Charges @ 1% 1% 18.07Add CPOH @ 15% 15% 273.77

Total cost per meter for pipe 2098.92Total cost per kg for specials 52.04

2.5.4.4

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.2326 0.0063 0.004thickness of

CML (t2) =Length of pipe

=0.006 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.2326-((0.004*2)+0.0063))*0.0063*1*7850= kg 33.917Add 2 % wastage

2% kg 0.678Total Weight kg 34.595

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 34.595 34.21 1183.51 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 33.917 6.63 224.87 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.678 27.00 18.32

Rate anlalysis enclosed Carriage of steel 100m 1.00 471.38 4.71 (C)

Material cost per meter Rs/meter 1394.77

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.2326-(0.004*2+0.0063*2+0.006))*0.006*1*2080= kg 8.08

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.2326-0.004)*1= sqmt 0.718 575.00 412.95 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.2326-(0.004*2+0.0063*2+0.006))*1= sqmt 0.647 450.00 291.23 (E)

Total (A+B+C+D+E) 2098.94Total without ED 1868.57

Add Water Charges @ 1% 1% 18.69Add CPOH @ 15% 15% 283.09

Total cost per meter for pipe 2170.35Total cost per kg for specials 51.68

2.5.4.5

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

200 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick coil, 6 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

250 mm nominal dia (clear internal dia) of pipe with 5.0 mm thick coil, 6 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 275 Schedule of Rates 2014 - 2015

Page 156: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.28 0.005 0.004thickness of

CML (t2) =Length of pipe

=0.006 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.28-((0.004*2)+0.005))*0.005*1*7850= kg 32.923Add 2 % wastage

2% kg 0.658Total Weight kg 33.582

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 33.582 34.21 1148.83 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 32.923 6.63 218.28 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.658 27.00 17.78

Rate anlalysis enclosed Carriage of steel 100m 1.00 669.85 6.70 (C)

Material cost per meter Rs/meter 1356.03

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.28-(0.004*2+0.005*2+0.006))*0.006*1*2080= kg 10.04

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.28-0.004)*1= sqmt 0.867 575.00 498.57 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.28-(0.004*2+0.005*2+0.006))*1= sqmt 0.804 450.00 361.91 (E)

Total (A+B+C+D+E) 2216.52Total without ED 1973.43

Add Water Charges @ 1% 1% 19.73Add CPOH @ 15% 15% 298.97

Total cost per meter for pipe 2292.14Total cost per kg for specials 53.36

2.5.4.6

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.282 0.006 0.004thickness of

CML (t2) =Length of pipe

=0.006 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.282-((0.004*2)+0.006))*0.006*1*7850= kg 39.656Add 2 % wastage

2% kg 0.793Total Weight kg 40.449

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 40.449 34.21 1383.76 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 39.656 6.63 262.92 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.793 27.00 21.41

Rate anlalysis enclosed Carriage of steel 100m 1.00 669.85 6.70 (C)

Material cost per meter Rs/meter 1631.97

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

250 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick coil, 6 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 276 Schedule of Rates 2014 - 2015

Page 157: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

(3.1416)*(0.282-(0.004*2+0.006*2+0.006))*0.006*1*2080= kg 10.04

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.282-0.004)*1= sqmt 0.873 575.00 502.18 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.282-(0.004*2+0.006*2+0.006))*1= sqmt 0.804 450.00 361.91 (E)

Total (A+B+C+D+E) 2496.06Total without ED 2222.22

Add Water Charges @ 1% 1% 22.22Add CPOH @ 15% 15% 336.67

Total cost per meter for pipe 2581.11Total cost per kg for specials 51.94

2.5.4.7

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.2826 0.0063 0.004thickness of

CML (t2) =Length of pipe

=0.006 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.2826-((0.004*2)+0.0063))*0.0063*1*7850= kg 41.685Add 2 % wastage

2% kg 0.834Total Weight kg 42.519

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 42.519 34.21 1454.58 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 41.685 6.63 276.37 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.834 27.00 22.51

Rate anlalysis enclosed Carriage of steel 100m 1.00 669.85 6.70 (C)

Material cost per meter Rs/meter 1715.14

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.2826-(0.004*2+0.0063*2+0.006))*0.006*1*2080= kg 10.04

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.2826-0.004)*1= sqmt 0.875 575.00 503.27 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.2826-(0.004*2+0.0063*2+0.006))*1= sqmt 0.804 450.00 361.91 (E)

Total (A+B+C+D+E) 2580.32Total without ED 2297.21

Add Water Charges @ 1% 1% 22.97Add CPOH @ 15% 15% 348.03

Total cost per meter for pipe 2668.21Total cost per kg for specials 51.59

2.5.4.8

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.33 0.005 0.004

300 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, 6 mm thick internal cement mortar lining and exterior / outside 4mm coaltar coatingand wrapping

250 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick coil, 6 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 277 Schedule of Rates 2014 - 2015

Page 158: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

thickness of CML (t2) =

Length of pipe =

0.006 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.33-((0.004*2)+0.005))*0.005*1*7850= kg 39.088Add 2 % wastage

2% kg 0.782Total Weight kg 39.870

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 39.870 34.21 1363.97 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 39.088 6.63 259.16 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.782 27.00 21.11

Rate anlalysis enclosed Carriage of steel 100m 1.00 827.95 8.28 (C)

Material cost per meter Rs/meter 1610.30

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.33-(0.004*2+0.005*2+0.006))*0.006*1*2080= kg 12.00

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.33-0.004)*1= sqmt 1.024 575.00 588.89 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.33-(0.004*2+0.005*2+0.006))*1= sqmt 0.961 450.00 432.60 (E)

Total (A+B+C+D+E) 2631.79Total without ED 2343.19

Add Water Charges @ 1% 1% 23.43Add CPOH @ 15% 15% 354.99

Total cost per meter for pipe 2721.62Total cost per kg for specials 53.28

2.5.4.9

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.3312 0.0056 0.004thickness of

CML (t2) =Length of pipe

=0.006 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.3312-((0.004*2)+0.0056))*0.0056*1*7850= kg 43.862Add 2 % wastage

2% kg 0.877Total Weight kg 44.739

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 44.739 34.21 1530.54 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 43.862 6.63 290.80 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.877 27.00 23.69

Rate anlalysis enclosed Carriage of steel 100m 1.00 827.95 8.28 (C)

Material cost per meter Rs/meter 1805.94

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.3312-(0.004*2+0.0056*2+0.006))*0.006*1*2080= kg 12.00

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.3312-0.004)*1= sqmt 1.028 575.00 591.06 (D)

300 mm nominal dia (clear internal dia) of pipe with 5.6 mm thick coil, 6 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 278 Schedule of Rates 2014 - 2015

Page 159: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.3312-(0.004*2+0.0056*2+0.006))*1= sqmt 0.961 450.00 432.60 (E)

Total (A+B+C+D+E) 2829.59Total without ED 2519.24

Add Water Charges @ 1% 1% 25.19Add CPOH @ 15% 15% 381.66

Total cost per meter for pipe 2926.10Total cost per kg for specials 52.38

2.5.4.10

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.3342 0.0071 0.004thickness of

CML (t2) =Length of pipe

=0.006 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.3342-((0.004*2)+0.0071))*0.0071*1*7850= kg 55.873Add 2 % wastage

2% kg 1.117Total Weight kg 56.991

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 56.991 34.21 1949.67 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 55.873 6.63 370.44 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.117 27.00 30.17

Rate anlalysis enclosed Carriage of steel 100m 1.00 827.95 8.28 (C)

Material cost per meter Rs/meter 2298.22

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.3342-(0.004*2+0.0071*2+0.006))*0.006*1*2080= kg 12.00

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.3342-0.004)*1= sqmt 1.037 575.00 596.48 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.3342-(0.004*2+0.0071*2+0.006))*1= sqmt 0.961 450.00 432.60 (E)

Total (A+B+C+D+E) 3327.29Total without ED 2962.19

Add Water Charges @ 1% 1% 29.62Add CPOH @ 15% 15% 448.77

Total cost per meter for pipe 3440.58Total cost per kg for specials 50.69

2.5.4.11

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.382 0.005 0.004thickness of

CML (t2) =Length of pipe

=0.007 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.382-((0.004*2)+0.005))*0.005*1*7850= kg 45.500Add 2 % wastage

300 mm nominal dia (clear internal dia) of pipe with 7.1 mm thick coil, 6 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

350 mm nominal dia (clear internal dia) of pipe with 5.0 mm thick coil, 7 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 279 Schedule of Rates 2014 - 2015

Page 160: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

2% kg 0.910Total Weight kg 46.410

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 46.410 34.21 1587.71 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 45.500 6.63 301.67 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.910 27.00 24.57

Rate anlalysis enclosed Carriage of steel 100m 1.00 1159.12 11.59 (C)

Material cost per meter Rs/meter 1876.40

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.382-(0.004*2+0.005*2+0.007))*0.007*1*2080= kg 16.33

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.382-0.004)*1= sqmt 1.188 575.00 682.83 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.382-(0.004*2+0.005*2+0.007))*1= sqmt 1.122 450.00 504.70 (E)

Total (A+B+C+D+E) 3063.93Total without ED 2728.16

Add Water Charges @ 1% 1% 27.28Add CPOH @ 15% 15% 413.32

Total cost per meter for pipe 3168.76Total cost per kg for specials 51.25

2.5.4.12

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.3832 0.0056 0.004thickness of

CML (t2) =Length of pipe

=0.007 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.3832-((0.004*2)+0.0056))*0.0056*1*7850= kg 51.043Add 2 % wastage

2% kg 1.021Total Weight kg 52.064

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 52.064 34.21 1781.13 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 51.043 6.63 338.42 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.021 27.00 27.56

Rate anlalysis enclosed Carriage of steel 100m 1.00 1159.12 11.59 (C)

Material cost per meter Rs/meter 2103.58

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.3832-(0.004*2+0.0056*2+0.007))*0.007*1*2080= kg 16.33

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.3832-0.004)*1= sqmt 1.191 575.00 684.99 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.3832-(0.004*2+0.0056*2+0.007))*1= sqmt 1.122 450.00 504.70 (E)

Total (A+B+C+D+E) 3293.27Total without ED 2932.27

350 mm nominal dia (clear internal dia) of pipe with 5.6 mm thick coil, 7 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 280 Schedule of Rates 2014 - 2015

Page 161: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add Water Charges @ 1% 1% 29.32Add CPOH @ 15% 15% 444.24

Total cost per meter for pipe 3405.83Total cost per kg for specials 50.55

2.5.4.13

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.388 0.008 0.004thickness of

CML (t2) =Length of pipe

=0.007 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.388-((0.004*2)+0.008))*0.008*1*7850= kg 73.393Add 2 % wastage

2% kg 1.468Total Weight kg 74.860

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 74.860 34.21 2561.00 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 73.393 6.63 486.59 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.468 27.00 39.63

Rate anlalysis enclosed Carriage of steel 100m 1.00 1159.12 11.59 (C)

Material cost per meter Rs/meter 3019.55

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.388-(0.004*2+0.008*2+0.007))*0.007*1*2080= kg 16.33

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.388-0.004)*1= sqmt 1.206 575.00 693.66 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.388-(0.004*2+0.008*2+0.007))*1= sqmt 1.122 450.00 504.70 (E)

Total (A+B+C+D+E) 4217.91Total without ED 3755.20

Add Water Charges @ 1% 1% 37.55Add CPOH @ 15% 15% 568.91

Total cost per meter for pipe 4361.66Total cost per kg for specials 48.61

2.5.4.14

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.432 0.005 0.004thickness of

CML (t2) =Length of pipe

=0.007 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.432-((0.004*2)+0.005))*0.005*1*7850= kg 51.666Add 2 % wastage

2% kg 1.033

350 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick coil, 7 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

400 mm nominal dia (clear internal dia) of pipe with 5.0 mm thick coil, 7 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 281 Schedule of Rates 2014 - 2015

Page 162: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Total Weight kg 52.699

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 52.699 34.21 1802.85 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 51.666 6.63 342.54 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.033 27.00 27.90

Rate anlalysis enclosed Carriage of steel 100m 1.00 1580.62 15.81 (C)

Material cost per meter Rs/meter 2133.30

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.432-(0.004*2+0.005*2+0.007))*0.007*1*2080= kg 18.62

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.432-0.004)*1= sqmt 1.345 575.00 773.15 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.432-(0.004*2+0.005*2+0.007))*1= sqmt 1.279 450.00 575.38 (E)

Total (A+B+C+D+E) 3481.83Total without ED 3100.56

Add Water Charges @ 1% 1% 31.01Add CPOH @ 15% 15% 469.73

Total cost per meter for pipe 3601.30Total cost per kg for specials 51.24

2.5.4.15

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.434 0.006 0.004thickness of

CML (t2) =Length of pipe

=0.007 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.434-((0.004*2)+0.006))*0.006*1*7850= kg 62.147Add 2 % wastage

2% kg 1.243Total Weight kg 63.390

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 63.390 34.21 2168.59 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 62.147 6.63 412.03 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.243 27.00 33.56

Rate anlalysis enclosed Carriage of steel 100m 1.00 1580.62 15.81 (C)

Material cost per meter Rs/meter 2562.87

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.434-(0.004*2+0.006*2+0.007))*0.007*1*2080= kg 18.62

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.434-0.004)*1= sqmt 1.351 575.00 776.76 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.434-(0.004*2+0.006*2+0.007))*1= sqmt 1.279 450.00 575.38 (E)

Total (A+B+C+D+E) 3915.01Total without ED 3486.08

Add Water Charges @ 1% 1% 34.86

400 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick coil, 7 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 282 Schedule of Rates 2014 - 2015

Page 163: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add CPOH @ 15% 15% 528.14Total cost per meter for pipe 4049.08

Total cost per kg for specials 50.13

2.5.4.16

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.4346 0.0063 0.004thickness of

CML (t2) =Length of pipe

=0.007 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.4346-((0.004*2)+0.0063))*0.0063*1*7850= kg 65.301Add 2 % wastage

2% kg 1.306Total Weight kg 66.607

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 66.607 34.21 2278.64 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 65.301 6.63 432.95 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.306 27.00 35.26

Rate anlalysis enclosed Carriage of steel 100m 1.00 1580.62 15.81 (C)

Material cost per meter Rs/meter 2692.13

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.4346-(0.004*2+0.0063*2+0.007))*0.007*1*2080= kg 18.62

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.4346-0.004)*1= sqmt 1.353 575.00 777.84 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.4346-(0.004*2+0.0063*2+0.007))*1= sqmt 1.279 450.00 575.38 (E)

Total (A+B+C+D+E) 4045.36Total without ED 3602.09

Add Water Charges @ 1% 1% 36.02Add CPOH @ 15% 15% 545.72

Total cost per meter for pipe 4183.83Total cost per kg for specials 49.86

2.5.4.17

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.4396 0.0088 0.004thickness of

CML (t2) =Length of pipe

=0.007 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.4396-((0.004*2)+0.0088))*0.0088*1*7850= kg 91.757Add 2 % wastage

2% kg 1.835Total Weight kg 93.592

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 93.592 34.21 3201.80 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 91.757 6.63 608.35 (B)

400 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick coil, 7 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

400 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick coil, 7 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 283 Schedule of Rates 2014 - 2015

Page 164: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.835 27.00 49.55

Rate anlalysis enclosed Carriage of steel 100m 1.00 1580.62 15.81 (C)

Material cost per meter Rs/meter 3776.40

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.4396-(0.004*2+0.0088*2+0.007))*0.007*1*2080= kg 18.62

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.4396-0.004)*1= sqmt 1.368 575.00 786.87 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.4396-(0.004*2+0.0088*2+0.007))*1= sqmt 1.279 450.00 575.38 (E)

Total (A+B+C+D+E) 5138.66Total without ED 4575.12

Add Water Charges @ 1% 1% 45.75Add CPOH @ 15% 15% 693.13

Total cost per meter for pipe 5314.01Total cost per kg for specials 48.15

2.5.4.18

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.484 0.006 0.004thickness of

CML (t2) =Length of pipe

=0.007 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.484-((0.004*2)+0.006))*0.006*1*7850= kg 69.545Add 2 % wastage

2% kg 1.391Total Weight kg 70.936

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 70.936 34.21 2426.75 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 69.545 6.63 461.09 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.391 27.00 37.55

Rate anlalysis enclosed Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 2869.60

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.484-(0.004*2+0.006*2+0.007))*0.007*1*2080= kg 20.90

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.484-0.004)*1= sqmt 1.508 575.00 867.08 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.484-(0.004*2+0.006*2+0.007))*1= sqmt 1.436 450.00 646.07 (E)

Total (A+B+C+D+E) 4382.75Total without ED 3902.76

Add Water Charges @ 1% 1% 39.03Add CPOH @ 15% 15% 591.27

Total cost per meter for pipe 4533.05Total cost per kg for specials 50.12

2.5.4.19 450 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick coil, 7 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

450 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick coil, 7 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 284 Schedule of Rates 2014 - 2015

Page 165: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.4846 0.0063 0.004thickness of

CML (t2) =Length of pipe

=0.007 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.4846-((0.004*2)+0.0063))*0.0063*1*7850= kg 73.069Add 2 % wastage

2% kg 1.461Total Weight kg 74.531

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 74.531 34.21 2549.71 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 73.069 6.63 484.45 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.461 27.00 39.46

Rate anlalysis enclosed Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 3014.02

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.4846-(0.004*2+0.0063*2+0.007))*0.007*1*2080= kg 20.90

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.4846-0.004)*1= sqmt 1.510 575.00 868.16 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.4846-(0.004*2+0.0063*2+0.007))*1= sqmt 1.436 450.00 646.07 (E)

Total (A+B+C+D+E) 4528.26Total without ED 4032.26

Add Water Charges @ 1% 1% 40.32Add CPOH @ 15% 15% 610.89

Total cost per meter for pipe 4683.47Total cost per kg for specials 49.84

2.5.4.20

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.492 0.01 0.004thickness of

CML (t2) =Length of pipe

=0.007 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.492-((0.004*2)+0.01))*0.01*1*7850= kg 116.896Add 2 % wastage

2% kg 2.338Total Weight kg 119.233

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 119.233 34.21 4079.01 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 116.896 6.63 775.02 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.338 27.00 63.12

Rate anlalysis enclosed Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 4810.22

450 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick coil, 7 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 285 Schedule of Rates 2014 - 2015

Page 166: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.492-(0.004*2+0.01*2+0.007))*0.007*1*2080= kg 20.90

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.492-0.004)*1= sqmt 1.533 575.00 881.53 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.492-(0.004*2+0.01*2+0.007))*1= sqmt 1.436 450.00 646.07 (E)

Total (A+B+C+D+E) 6337.82Total without ED 5642.76

Add Water Charges @ 1% 1% 56.43Add CPOH @ 15% 15% 854.88

Total cost per meter for pipe 6554.07Total cost per kg for specials 47.56

2.5.4.21

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.534 0.006 0.004thickness of

CML (t2) =Length of pipe

=0.007 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.534-((0.004*2)+0.006))*0.006*1*7850= kg 76.944Add 2 % wastage

2% kg 1.539Total Weight kg 78.483

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 78.483 34.21 2684.91 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 76.944 6.63 510.14 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.539 27.00 41.55

Rate anlalysis enclosed Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 3172.82

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.534-(0.004*2+0.006*2+0.007))*0.007*1*2080= kg 23.19

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.534-0.004)*1= sqmt 1.665 575.00 957.40 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.534-(0.004*2+0.006*2+0.007))*1= sqmt 1.593 450.00 716.75 (E)

Total (A+B+C+D+E) 4846.98Total without ED 4315.92

Add Water Charges @ 1% 1% 43.16Add CPOH @ 15% 15% 653.86

Total cost per meter for pipe 5012.94Total cost per kg for specials 50.06

2.5.4.22

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

500 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick coil, 7 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

500 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick coil, 7 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 286 Schedule of Rates 2014 - 2015

Page 167: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.5346 0.0063 0.004thickness of

CML (t2) =Length of pipe

=0.007 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.5346-((0.004*2)+0.0063))*0.0063*1*7850= kg 80.838Add 2 % wastage

2% kg 1.617Total Weight kg 82.454

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 82.454 34.21 2820.79 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 80.838 6.63 535.95 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.617 27.00 43.65

Rate anlalysis enclosed Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 3332.41

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.5346-(0.004*2+0.0063*2+0.007))*0.007*1*2080= kg 23.19

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.5346-0.004)*1= sqmt 1.667 575.00 958.48 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.5346-(0.004*2+0.0063*2+0.007))*1= sqmt 1.593 450.00 716.75 (E)

Total (A+B+C+D+E) 5007.65Total without ED 4458.91

Add Water Charges @ 1% 1% 44.59Add CPOH @ 15% 15% 675.53

Total cost per meter for pipe 5179.03Total cost per kg for specials 49.78

2.5.4.23

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.544 0.011 0.004thickness of

CML (t2) =Length of pipe

=0.007 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.544-((0.004*2)+0.011))*0.011*1*7850= kg 142.420Add 2 % wastage

2% kg 2.848Total Weight kg 145.269

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 145.269 34.21 4969.67 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 142.420 6.63 944.25 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.848 27.00 76.91

Rate anlalysis enclosed Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 5856.33

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

500 mm nominal dia (clear internal dia) of pipe with 11.0 mm thick coil, 7 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 287 Schedule of Rates 2014 - 2015

Page 168: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

(3.1416)*(0.544-(0.004*2+0.011*2+0.007))*0.007*1*2080= kg 23.19

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.544-0.004)*1= sqmt 1.696 575.00 975.46 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.544-(0.004*2+0.011*2+0.007))*1= sqmt 1.593 450.00 716.75 (E)

Total (A+B+C+D+E) 7548.55Total without ED 6720.31

Add Water Charges @ 1% 1% 67.20Add CPOH @ 15% 15% 1018.13

Total cost per meter for pipe 7805.64Total cost per kg for specials 47.13

2.5.4.24

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.634 0.006 0.004thickness of

CML (t2) =Length of pipe

=0.007 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.634-((0.004*2)+0.006))*0.006*1*7850= kg 91.741Add 2 % wastage

2% kg 1.835Total Weight kg 93.576

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 93.576 34.21 3201.24 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 91.741 6.63 608.24 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.835 27.00 49.54

Rate anlalysis enclosed Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 3788.92

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.634-(0.004*2+0.006*2+0.007))*0.007*1*2080= kg 27.77

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.634-0.004)*1= sqmt 1.979 575.00 1138.04 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.634-(0.004*2+0.006*2+0.007))*1= sqmt 1.907 450.00 858.13 (E)

Total (A+B+C+D+E) 5785.09Total without ED 5151.90

Add Water Charges @ 1% 1% 51.52Add CPOH @ 15% 15% 780.51

Total cost per meter for pipe 5983.93Total cost per kg for specials 50.07

2.5.4.25

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.6346 0.0063 0.004

600 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick coil, 7 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

600 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick coil, 7 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 288 Schedule of Rates 2014 - 2015

Page 169: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

thickness of CML (t2) =

Length of pipe =

0.007 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.6346-((0.004*2)+0.0063))*0.0063*1*7850= kg 96.374Add 2 % wastage

2% kg 1.927Total Weight kg 98.302

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 98.302 34.21 3362.93 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 96.374 6.63 638.96 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.927 27.00 52.04

Rate anlalysis enclosed Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 3978.83

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.6346-(0.004*2+0.0063*2+0.007))*0.007*1*2080= kg 27.77

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.6346-0.004)*1= sqmt 1.981 575.00 1139.13 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.6346-(0.004*2+0.0063*2+0.007))*1= sqmt 1.907 450.00 858.13 (E)

Total (A+B+C+D+E) 5976.08Total without ED 5321.88

Add Water Charges @ 1% 1% 53.22Add CPOH @ 15% 15% 806.26

Total cost per meter for pipe 6181.36Total cost per kg for specials 49.79

2.5.4.26

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.638 0.008 0.004thickness of

CML (t2) =Length of pipe

=0.007 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.638-((0.004*2)+0.008))*0.008*1*7850= kg 122.716Add 2 % wastage

2% kg 2.454Total Weight kg 125.170

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 125.170 34.21 4282.10 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 122.716 6.63 813.60 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.454 27.00 66.27

Rate anlalysis enclosed Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 5058.41

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.638-(0.004*2+0.008*2+0.007))*0.007*1*2080= kg 27.77

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.638-0.004)*1= sqmt 1.992 575.00 1145.27 (D)

600 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick coil, 7 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 289 Schedule of Rates 2014 - 2015

Page 170: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.638-(0.004*2+0.008*2+0.007))*1= sqmt 1.907 450.00 858.13 (E)

Total (A+B+C+D+E) 7061.81Total without ED 6288.17

Add Water Charges @ 1% 1% 62.88Add CPOH @ 15% 15% 952.66

Total cost per meter for pipe 7303.71Total cost per kg for specials 48.54

2.5.4.27

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.647 0.0125 0.004thickness of

CML (t2) =Length of pipe

=0.007 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.647-((0.004*2)+0.0125))*0.0125*1*7850= kg 193.130Add 2 % wastage

2% kg 3.863Total Weight kg 196.993

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 196.993 34.21 6739.18 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 193.130 6.63 1280.45 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.863 27.00 104.29

Rate anlalysis enclosed Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 7944.32

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.647-(0.004*2+0.0125*2+0.007))*0.007*1*2080= kg 27.77

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.647-0.004)*1= sqmt 2.020 575.00 1161.53 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.647-(0.004*2+0.0125*2+0.007))*1= sqmt 1.907 450.00 858.13 (E)

Total (A+B+C+D+E) 9963.97Total without ED 8871.09

Add Water Charges @ 1% 1% 88.71Add CPOH @ 15% 15% 1343.97

Total cost per meter for pipe 10303.77Total cost per kg for specials 46.65

2.5.4.28

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.738 0.006 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.738-((0.004*2)+0.006))*0.006*1*7850= kg 107.130Add 2 % wastage

700 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

600 mm nominal dia (clear internal dia) of pipe with 12.5 mm thick coil, 7 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 290 Schedule of Rates 2014 - 2015

Page 171: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

2% kg 2.143Total Weight kg 109.272

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 109.272 34.21 3738.23 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 107.130 6.63 710.27 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.143 27.00 57.85

Rate anlalysis enclosed Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 4419.62

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.738-(0.004*2+0.006*2+0.009))*0.009*1*2080= kg 41.70

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.738-0.004)*1= sqmt 2.306 575.00 1325.91 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.738-(0.004*2+0.006*2+0.009))*1= sqmt 2.227 450.00 1002.33 (E)

Total (A+B+C+D+E) 6747.86Total without ED 6008.76

Add Water Charges @ 1% 1% 60.09Add CPOH @ 15% 15% 910.33

Total cost per meter for pipe 6979.17Total cost per kg for specials 46.89

2.5.4.29

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.7386 0.0063 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.7386-((0.004*2)+0.0063))*0.0063*1*7850= kg 112.533Add 2 % wastage

2% kg 2.251Total Weight kg 114.783

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 114.783 34.21 3926.77 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 112.533 6.63 746.09 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.251 27.00 60.77

Rate anlalysis enclosed Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 4641.07

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.7386-(0.004*2+0.0063*2+0.009))*0.009*1*2080= kg 41.70

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.7386-0.004)*1= sqmt 2.308 575.00 1326.99 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.7386-(0.004*2+0.0063*2+0.009))*1= sqmt 2.227 450.00 1002.33 (E)

Total (A+B+C+D+E) 6970.39Total without ED 6206.81

700 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 291 Schedule of Rates 2014 - 2015

Page 172: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add Water Charges @ 1% 1% 62.07Add CPOH @ 15% 15% 940.33

Total cost per meter for pipe 7209.21Total cost per kg for specials 46.74

2.5.4.30

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.7402 0.0071 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.7402-((0.004*2)+0.0071))*0.0071*1*7850= kg 126.963Add 2 % wastage

2% kg 2.539Total Weight kg 129.502

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 129.502 34.21 4430.29 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 126.963 6.63 841.76 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.539 27.00 68.56

Rate anlalysis enclosed Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 5232.47

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.7402-(0.004*2+0.0071*2+0.009))*0.009*1*2080= kg 41.70

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.7402-0.004)*1= sqmt 2.313 575.00 1329.88 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.7402-(0.004*2+0.0071*2+0.009))*1= sqmt 2.227 450.00 1002.33 (E)

Total (A+B+C+D+E) 7564.68Total without ED 6735.73

Add Water Charges @ 1% 1% 67.36Add CPOH @ 15% 15% 1020.46

Total cost per meter for pipe 7823.54Total cost per kg for specials 46.39

2.5.4.31

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.742 0.008 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.742-((0.004*2)+0.008))*0.008*1*7850= kg 143.234Add 2 % wastage

2% kg 2.865Total Weight kg 146.099

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 146.099 34.21 4998.07 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 143.234 6.63 949.64 (B)

700 mm nominal dia (clear internal dia) of pipe with 7.1 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

700 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 292 Schedule of Rates 2014 - 2015

Page 173: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.865 27.00 77.35

Rate anlalysis enclosed Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 5899.35

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.742-(0.004*2+0.008*2+0.009))*0.009*1*2080= kg 41.70

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.742-0.004)*1= sqmt 2.318 575.00 1333.13 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.742-(0.004*2+0.008*2+0.009))*1= sqmt 2.227 450.00 1002.33 (E)

Total (A+B+C+D+E) 8234.81Total without ED 7332.14

Add Water Charges @ 1% 1% 73.32Add CPOH @ 15% 15% 1110.82

Total cost per meter for pipe 8516.28Total cost per kg for specials 46.05

2.5.4.32

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.7544 0.0142 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.7544-((0.004*2)+0.0142))*0.0142*1*7850= kg 256.412Add 2 % wastage

2% kg 5.128Total Weight kg 261.540

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 261.540 34.21 8947.34 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 256.412 6.63 1700.01 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 5.128 27.00 138.46

Rate anlalysis enclosed Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 10537.87

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.7544-(0.004*2+0.0142*2+0.009))*0.009*1*2080= kg 41.70

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.7544-0.004)*1= sqmt 2.357 575.00 1355.53 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.7544-(0.004*2+0.0142*2+0.009))*1= sqmt 2.227 450.00 1002.33 (E)

700 mm nominal dia (clear internal dia) of pipe with 14.2 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 293 Schedule of Rates 2014 - 2015

Page 174: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Total (A+B+C+D+E) 12895.73Total without ED 11480.34

Add Water Charges @ 1% 1% 114.80Add CPOH @ 15% 15% 1739.27

Total cost per meter for pipe 13334.41Total cost per kg for specials 44.73

2.5.4.33

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.8402 0.0071 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.8402-((0.004*2)+0.0071))*0.0071*1*7850= kg 144.472Add 2 % wastage

2% kg 2.889Total Weight kg 147.362

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 147.362 34.21 5041.28 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 144.472 6.63 957.85 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.889 27.00 78.02

Rate anlalysis enclosed Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 5950.09

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.8402-(0.004*2+0.0071*2+0.009))*0.009*1*2080= kg 47.58

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.8402-0.004)*1= sqmt 2.627 575.00 1510.52 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.8402-(0.004*2+0.0071*2+0.009))*1= sqmt 2.542 450.00 1143.70 (E)

Total (A+B+C+D+E) 8604.32Total without ED 7661.00

Add Water Charges @ 1% 1% 76.61Add CPOH @ 15% 15% 1160.64

Total cost per meter for pipe 8898.25Total cost per kg for specials 46.33

2.5.4.34

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.842 0.008 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.842-((0.004*2)+0.008))*0.008*1*7850= kg 162.963Add 2 % wastage

2% kg 3.259Total Weight kg 166.222

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 166.222 34.21 5686.51 (A)

800 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

800 mm nominal dia (clear internal dia) of pipe with 7.1 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 294 Schedule of Rates 2014 - 2015

Page 175: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_320 Cost of Fabrication kg 162.963 6.63 1080.45 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.259 27.00 88.00

Rate anlalysis enclosed Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 6707.94

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.842-(0.004*2+0.008*2+0.009))*0.009*1*2080= kg 47.58

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.842-0.004)*1= sqmt 2.633 575.00 1513.78 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.842-(0.004*2+0.008*2+0.009))*1= sqmt 2.542 450.00 1143.70 (E)

Total (A+B+C+D+E) 9365.41Total without ED 8338.37

Add Water Charges @ 1% 1% 83.38Add CPOH @ 15% 15% 1263.26

Total cost per meter for pipe 9685.02Total cost per kg for specials 46.00

2.5.4.35

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.862 0.018 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.862-((0.004*2)+0.018))*0.018*1*7850= kg 371.106Add 2 % wastage

2% kg 7.422Total Weight kg 378.528

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 378.528 34.21 12949.55 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 371.106 6.63 2460.43 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 7.422 27.00 200.40

Rate anlalysis enclosed Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 15238.57

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.862-(0.004*2+0.018*2+0.009))*0.009*1*2080= kg 47.58

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.862-0.004)*1= sqmt 2.695 575.00 1549.90 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.862-(0.004*2+0.018*2+0.009))*1= sqmt 2.542 450.00 1143.70 (E)

Total (A+B+C+D+E) 17932.17Total without ED 15962.75

Add Water Charges @ 1% 1% 159.63Add CPOH @ 15% 15% 2418.36

Total cost per meter for pipe 18540.74Total cost per kg for specials 44.28

800 mm nominal dia (clear internal dia) of pipe with 18.0 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 295 Schedule of Rates 2014 - 2015

Page 176: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

2.5.4.36

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.942 0.008 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.942-((0.004*2)+0.008))*0.008*1*7850= kg 182.692Add 2 % wastage

2% kg 3.654Total Weight kg 186.346

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 186.346 34.21 6374.95 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 182.692 6.63 1211.25 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.654 27.00 98.65

Rate anlalysis enclosed Carriage of steel 100m 1.00 4346.71 43.47 (C)

Material cost per meter Rs/meter 7531.02

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.942-(0.004*2+0.008*2+0.009))*0.009*1*2080= kg 53.46

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.942-0.004)*1= sqmt 2.947 575.00 1694.42 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.942-(0.004*2+0.008*2+0.009))*1= sqmt 2.856 450.00 1285.07 (E)

Total (A+B+C+D+E) 10510.50Total without ED 9359.09

Add Water Charges @ 1% 1% 93.59Add CPOH @ 15% 15% 1417.90

Total cost per meter for pipe 10870.58Total cost per kg for specials 46.03

2.5.4.37

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.9436 0.0088 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.9436-((0.004*2)+0.0088))*0.0088*1*7850= kg 201.135Add 2 % wastage

2% kg 4.023Total Weight kg 205.158

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 205.158 34.21 7018.51 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 201.135 6.63 1333.53 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 4.023 27.00 108.61

Rate anlalysis enclosed Carriage of steel 100m 1.00 4346.71 43.47 (C)

Material cost per meter Rs/meter 8286.89

900 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

900 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 296 Schedule of Rates 2014 - 2015

Page 177: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.9436-(0.004*2+0.0088*2+0.009))*0.009*1*2080= kg 53.46

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.9436-0.004)*1= sqmt 2.952 575.00 1697.31 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.9436-(0.004*2+0.0088*2+0.009))*1= sqmt 2.856 450.00 1285.07 (E)

Total (A+B+C+D+E) 11269.26Total without ED 10034.39

Add Water Charges @ 1% 1% 100.34Add CPOH @ 15% 15% 1520.21

Total cost per meter for pipe 11654.94Total cost per kg for specials 45.78

2.5.4.38

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.946 0.01 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.946-((0.004*2)+0.01))*0.01*1*7850= kg 228.859Add 2 % wastage

2% kg 4.577Total Weight kg 233.436

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 233.436 34.21 7985.90 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 228.859 6.63 1517.33 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 4.577 27.00 123.58

Rate anlalysis enclosed Carriage of steel 100m 1.00 4346.71 43.47 (C)

Material cost per meter Rs/meter 9423.12

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.946-(0.004*2+0.01*2+0.009))*0.009*1*2080= kg 53.46

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.946-0.004)*1= sqmt 2.959 575.00 1701.64 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.946-(0.004*2+0.01*2+0.009))*1= sqmt 2.856 450.00 1285.07 (E)

Total (A+B+C+D+E) 12409.83Total without ED 11049.49

Add Water Charges @ 1% 1% 110.49Add CPOH @ 15% 15% 1674.00

Total cost per meter for pipe 12833.98Total cost per kg for specials 45.46

2.5.4.39

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

900 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

900 mm nominal dia (clear internal dia) of pipe with 17.5 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 297 Schedule of Rates 2014 - 2015

Page 178: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

0.961 0.0175 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(0.961-((0.004*2)+0.0175))*0.0175*1*7850= kg 403.740Add 2 % wastage

2% kg 8.075Total Weight kg 411.814

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 411.814 34.21 14088.27 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 403.740 6.63 2676.79 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 8.075 27.00 218.02

Rate anlalysis enclosed Carriage of steel 100m 1.00 4346.71 43.47 (C)

Material cost per meter Rs/meter 16590.52

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(0.961-(0.004*2+0.0175*2+0.009))*0.009*1*2080= kg 53.46

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(0.961-0.004)*1= sqmt 3.007 575.00 1728.74 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(0.961-(0.004*2+0.0175*2+0.009))*1= sqmt 2.856 450.00 1285.07 (E)

Total (A+B+C+D+E) 19604.32Total without ED 17452.56

Add Water Charges @ 1% 1% 174.53Add CPOH @ 15% 15% 2644.06

Total cost per meter for pipe 20271.15Total cost per kg for specials 44.34

2.5.4.40

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.0436 0.0088 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.0436-((0.004*2)+0.0088))*0.0088*1*7850= kg 222.837Add 2 % wastage

2% kg 4.457Total Weight kg 227.294

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 227.294 34.21 7775.79 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 222.837 6.63 1477.41 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 4.457 27.00 120.33

Rate anlalysis enclosed Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 9190.82

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

1000 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 298 Schedule of Rates 2014 - 2015

Page 179: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

(3.1416)*(1.0436-(0.004*2+0.0088*2+0.009))*0.009*1*2080= kg 59.34

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.0436-0.004)*1= sqmt 3.266 575.00 1877.95 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.0436-(0.004*2+0.0088*2+0.009))*1= sqmt 3.170 450.00 1426.44 (E)

Total (A+B+C+D+E) 12495.21Total without ED 11127.07

Add Water Charges @ 1% 1% 111.27Add CPOH @ 15% 15% 1685.75

Delhi Jal Board 299 Schedule of Rates 2014 - 2015

Page 180: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Total cost per meter for pipe 12924.09Total cost per kg for specials 45.80

2.5.4.41

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.046 0.01 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.046-((0.004*2)+0.01))*0.01*1*7850= kg 253.520Add 2 % wastage

2% kg 5.070Total Weight kg 258.591

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 258.591 34.21 8846.45 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 253.520 6.63 1680.84 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 5.070 27.00 136.90

Rate anlalysis enclosed Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 10448.34

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.046-(0.004*2+0.01*2+0.009))*0.009*1*2080= kg 59.34

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.046-0.004)*1= sqmt 3.274 575.00 1882.29 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.046-(0.004*2+0.01*2+0.009))*1= sqmt 3.170 450.00 1426.44 (E)

Total (A+B+C+D+E) 13757.07Total without ED 12250.12

Add Water Charges @ 1% 1% 122.50Add CPOH @ 15% 15% 1855.89

Total cost per meter for pipe 14228.51Total cost per kg for specials 45.48

2.5.4.42

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.066 0.02 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.066-((0.004*2)+0.02))*0.02*1*7850= kg 511.973Add 2 % wastage

2% kg 10.239Total Weight kg 522.212

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 522.212 34.21 17865.01 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 511.973 6.63 3394.38 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 10.239 27.00 276.47

1000 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

1000 mm nominal dia (clear internal dia) of pipe with 20.0 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 300 Schedule of Rates 2014 - 2015

Page 181: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Rate anlalysis enclosed Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 21040.88

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.066-(0.004*2+0.02*2+0.009))*0.009*1*2080= kg 59.34

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.066-0.004)*1= sqmt 3.336 575.00 1918.41 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.066-(0.004*2+0.02*2+0.009))*1= sqmt 3.170 450.00 1426.44 (E)

Total (A+B+C+D+E) 24385.74Total without ED 21709.59

Add Water Charges @ 1% 1% 217.10Add CPOH @ 15% 15% 3289.00

Total cost per meter for pipe 25215.69Total cost per kg for specials 44.14

2.5.4.43

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.0936 0.0088 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.0936-((0.004*2)+0.0088))*0.0088*1*7850= kg 233.688Add 2 % wastage

2% kg 4.674Total Weight kg 238.362

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 238.362 34.21 8154.43 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 233.688 6.63 1549.35 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 4.674 27.00 126.19

Rate anlalysis enclosed Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 9635.55

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.0936-(0.004*2+0.0088*2+0.009))*0.009*1*2080= kg 62.28

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.0936-0.004)*1= sqmt 3.423 575.00 1968.27 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.0936-(0.004*2+0.0088*2+0.009))*1= sqmt 3.327 450.00 1497.13 (E)

Total (A+B+C+D+E) 13100.95Total without ED 11666.17

Add Water Charges @ 1% 1% 116.66Add CPOH @ 15% 15% 1767.42

Total cost per meter for pipe 13550.26Total cost per kg for specials 45.78

2.5.4.44

1050 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

1050 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 301 Schedule of Rates 2014 - 2015

Page 182: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.096 0.01 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.096-((0.004*2)+0.01))*0.01*1*7850= kg 265.851Add 2 % wastage

2% kg 5.317Total Weight kg 271.168

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 271.168 34.21 9276.73 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 265.851 6.63 1762.59 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 5.317 27.00 143.56

Rate anlalysis enclosed Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 10953.71

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.096-(0.004*2+0.01*2+0.009))*0.009*1*2080= kg 62.28

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.096-0.004)*1= sqmt 3.431 575.00 1972.61 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.096-(0.004*2+0.01*2+0.009))*1= sqmt 3.327 450.00 1497.13 (E)

Total (A+B+C+D+E) 14423.45Total without ED 12843.19

Add Water Charges @ 1% 1% 128.43Add CPOH @ 15% 15% 1945.74

Total cost per meter for pipe 14917.37Total cost per kg for specials 45.46

2.5.4.45

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.098 0.011 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.098-((0.004*2)+0.011))*0.011*1*7850= kg 292.707Add 2 % wastage

2% kg 5.854Total Weight kg 298.562

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 298.562 34.21 10213.86 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 292.707 6.63 1940.65 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 5.854 27.00 158.06

Rate anlalysis enclosed Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 12054.41

1050 mm nominal dia (clear internal dia) of pipe with 11.0 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 302 Schedule of Rates 2014 - 2015

Page 183: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.098-(0.004*2+0.011*2+0.009))*0.009*1*2080= kg 62.28

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.098-0.004)*1= sqmt 3.437 575.00 1976.22 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.098-(0.004*2+0.011*2+0.009))*1= sqmt 3.327 450.00 1497.13 (E)

Total (A+B+C+D+E) 15527.75Total without ED 13826.02

Add Water Charges @ 1% 1% 138.26Add CPOH @ 15% 15% 2094.64

Total cost per meter for pipe 16058.92Total cost per kg for specials 45.24

2.5.4.46

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.1436 0.0088 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.1436-((0.004*2)+0.0088))*0.0088*1*7850= kg 244.540Add 2 % wastage

2% kg 4.891Total Weight kg 249.430

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 249.430 34.21 8533.07 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 244.540 6.63 1621.30 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 4.891 27.00 132.05

Rate anlalysis enclosed Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 10080.27

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.1436-(0.004*2+0.0088*2+0.009))*0.009*1*2080= kg 65.22

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.1436-0.004)*1= sqmt 3.580 575.00 2058.59 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.1436-(0.004*2+0.0088*2+0.009))*1= sqmt 3.484 450.00 1567.81 (E)

Total (A+B+C+D+E) 13706.68Total without ED 12205.27

Add Water Charges @ 1% 1% 122.05Add CPOH @ 15% 15% 1849.10

Total cost per meter for pipe 14176.42Total cost per kg for specials 45.77

2.5.4.47

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

1100 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

1100 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 303 Schedule of Rates 2014 - 2015

Page 184: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.146 0.01 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.146-((0.004*2)+0.01))*0.01*1*7850= kg 278.182Add 2 % wastage

2% kg 5.564Total Weight kg 283.745

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 283.745 34.21 9707.00 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 278.182 6.63 1844.34 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 5.564 27.00 150.22

Rate anlalysis enclosed Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 11459.08

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.146-(0.004*2+0.01*2+0.009))*0.009*1*2080= kg 65.22

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.146-0.004)*1= sqmt 3.588 575.00 2062.93 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.146-(0.004*2+0.01*2+0.009))*1= sqmt 3.484 450.00 1567.81 (E)

Total (A+B+C+D+E) 15089.82Total without ED 13436.26

Add Water Charges @ 1% 1% 134.36Add CPOH @ 15% 15% 2035.59

Total cost per meter for pipe 15606.22Total cost per kg for specials 45.45

2.5.4.48

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.148 0.011 0.004thickness of

CML (t2) =Length of pipe

=0.009 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.148-((0.004*2)+0.011))*0.011*1*7850= kg 306.271Add 2 % wastage

2% kg 6.125Total Weight kg 312.397

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 312.397 34.21 10687.17 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 306.271 6.63 2030.58 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 6.125 27.00 165.39

Rate anlalysis enclosed Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 12610.31

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

1100 mm nominal dia (clear internal dia) of pipe with 11.0 mm thick coil, 9 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 304 Schedule of Rates 2014 - 2015

Page 185: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

(3.1416)*(1.148-(0.004*2+0.011*2+0.009))*0.009*1*2080= kg 65.22

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.148-0.004)*1= sqmt 3.594 575.00 2066.54 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.148-(0.004*2+0.011*2+0.009))*1= sqmt 3.484 450.00 1567.81 (E)

Total (A+B+C+D+E) 16244.67Total without ED 14464.07

Add Water Charges @ 1% 1% 144.64Add CPOH @ 15% 15% 2191.31

Total cost per meter for pipe 16800.02Total cost per kg for specials 45.22

2.5.4.49

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.252 0.01 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.252-((0.004*2)+0.01))*0.01*1*7850= kg 304.323Add 2 % wastage

2% kg 6.086Total Weight kg 310.409

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 310.409 34.21 10619.18 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 304.323 6.63 2017.66 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 6.086 27.00 164.33

Rate anlalysis enclosed Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 12530.47

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.252-(0.004*2+0.01*2+0.012))*0.012*1*2080= kg 95.04

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.252-0.004)*1= sqmt 3.921 575.00 2254.41 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.252-(0.004*2+0.01*2+0.012))*1= sqmt 3.808 450.00 1713.42 (E)

Total (A+B+C+D+E) 16498.30Total without ED 14689.80

Add Water Charges @ 1% 1% 146.90Add CPOH @ 15% 15% 2225.50

Total cost per meter for pipe 17062.20Total cost per kg for specials 42.72

2.5.4.50

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.254 0.011 0.004

1200 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

1200 mm nominal dia (clear internal dia) of pipe with 11.0 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 305 Schedule of Rates 2014 - 2015

Page 186: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.254-((0.004*2)+0.011))*0.011*1*7850= kg 335.027Add 2 % wastage

2% kg 6.701Total Weight kg 341.727

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 341.727 34.21 11690.57 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 335.027 6.63 2221.23 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 6.701 27.00 180.91

Rate anlalysis enclosed Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 13788.83

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.254-(0.004*2+0.011*2+0.012))*0.012*1*2080= kg 95.04

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.254-0.004)*1= sqmt 3.927 575.00 2258.02 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.254-(0.004*2+0.011*2+0.012))*1= sqmt 3.808 450.00 1713.42 (E)

Total (A+B+C+D+E) 17760.28Total without ED 15812.96

Add Water Charges @ 1% 1% 158.13Add CPOH @ 15% 15% 2395.66

Total cost per meter for pipe 18366.75Total cost per kg for specials 42.71

2.5.4.51

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.256 0.012 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.256-((0.004*2)+0.012))*0.012*1*7850= kg 365.779Add 2 % wastage

2% kg 7.316Total Weight kg 373.095

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 373.095 34.21 12763.67 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 365.779 6.63 2425.12 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 7.316 27.00 197.52

Rate anlalysis enclosed Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 15049.23

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.256-(0.004*2+0.012*2+0.012))*0.012*1*2080= kg 95.04

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.256-0.004)*1= sqmt 3.933 575.00 2261.63 (D)

1200 mm nominal dia (clear internal dia) of pipe with 12.0 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 306 Schedule of Rates 2014 - 2015

Page 187: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.256-(0.004*2+0.012*2+0.012))*1= sqmt 3.808 450.00 1713.42 (E)

Total (A+B+C+D+E) 19024.28Total without ED 16937.92

Add Water Charges @ 1% 1% 169.38Add CPOH @ 15% 15% 2566.09

Total cost per meter for pipe 19673.39Total cost per kg for specials 42.69

2.5.4.52

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.257 0.0125 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.257-((0.004*2)+0.0125))*0.0125*1*7850= kg 381.174Add 2 % wastage

2% kg 7.623Total Weight kg 388.798

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 388.798 34.21 13300.87 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 381.174 6.63 2527.19 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 7.623 27.00 205.83

Rate anlalysis enclosed Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 15680.18

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.257-(0.004*2+0.0125*2+0.012))*0.012*1*2080= kg 95.04

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.257-0.004)*1= sqmt 3.936 575.00 2263.44 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.257-(0.004*2+0.0125*2+0.012))*1= sqmt 3.808 450.00 1713.42 (E)

Total (A+B+C+D+E) 19657.04Total without ED 17501.07

Add Water Charges @ 1% 1% 175.01Add CPOH @ 15% 15% 2651.41

Total cost per meter for pipe 20327.50Total cost per kg for specials 42.69

2.5.4.53

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.456 0.012 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.456-((0.004*2)+0.012))*0.012*1*7850= kg 424.967Add 2 % wastage

1200 mm nominal dia (clear internal dia) of pipe with 12.5 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

1400 mm nominal dia (clear internal dia) of pipe with 12 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 307 Schedule of Rates 2014 - 2015

Page 188: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

2% kg 8.499

Delhi Jal Board 308 Schedule of Rates 2014 - 2015

Page 189: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Total Weight kg 433.466

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 433.466 34.21 14828.99 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 424.967 6.63 2817.53 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 8.499 27.00 229.48

Rate anlalysis enclosed Carriage of steel 100m 1.00 7244.52 72.45 (C)

Material cost per meter Rs/meter 17489.49

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.456-(0.004*2+0.012*2+0.012))*0.012*1*2080= kg 110.72

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.456-0.004)*1= sqmt 4.562 575.00 2622.92 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.456-(0.004*2+0.012*2+0.012))*1= sqmt 4.436 450.00 1996.17 (E)

Total (A+B+C+D+E) 22108.57Total without ED 19684.52

Add Water Charges @ 1% 1% 196.85Add CPOH @ 15% 15% 2982.20

Total cost per meter for pipe 22863.57Total cost per kg for specials 42.68

2.5.4.54

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.457 0.0125 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.457-((0.004*2)+0.0125))*0.0125*1*7850= kg 442.828Add 2 % wastage

2% kg 8.857Total Weight kg 451.685

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 451.685 34.21 15452.24 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 442.828 6.63 2935.95 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 8.857 27.00 239.13

Rate anlalysis enclosed Carriage of steel 100m 1.00 7244.52 72.45 (C)

Material cost per meter Rs/meter 18221.51

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.457-(0.004*2+0.0125*2+0.012))*0.012*1*2080= kg 110.72

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.457-0.004)*1= sqmt 4.565 575.00 2624.72 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.457-(0.004*2+0.0125*2+0.012))*1= sqmt 4.436 450.00 1996.17 (E)

Total (A+B+C+D+E) 22842.40Total without ED 20337.63

Add Water Charges @ 1% 1% 203.38

1400 mm nominal dia (clear internal dia) of pipe with 12.5 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 309 Schedule of Rates 2014 - 2015

Page 190: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add CPOH @ 15% 15% 3081.15Total cost per meter for pipe 23622.15

Total cost per kg for specials 42.67

2.5.4.55

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.4604 0.0142 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.4604-((0.004*2)+0.0142))*0.0142*1*7850= kg 503.648Add 2 % wastage

2% kg 10.073Total Weight kg 513.721

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 513.721 34.21 17574.52 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 503.648 6.63 3339.19 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 10.073 27.00 271.97

Rate anlalysis enclosed Carriage of steel 100m 1.00 7244.52 72.45 (C)

Material cost per meter Rs/meter 20714.19

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.4604-(0.004*2+0.0142*2+0.012))*0.012*1*2080= kg 110.72

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.4604-0.004)*1= sqmt 4.575 575.00 2630.86 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.4604-(0.004*2+0.0142*2+0.012))*1= sqmt 4.436 450.00 1996.17 (E)

Total (A+B+C+D+E) 25341.22Total without ED 22561.56

Add Water Charges @ 1% 1% 225.62Add CPOH @ 15% 15% 3418.08

Total cost per meter for pipe 26205.26Total cost per kg for specials 42.65

2.5.4.56

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.556 0.012 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.556-((0.004*2)+0.012))*0.012*1*7850= kg 454.561Add 2 % wastage

2% kg 9.091Total Weight kg 463.652

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 463.652 34.21 15861.65 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 454.561 6.63 3013.74 (B)

1500 mm nominal dia (clear internal dia) of pipe with 12 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

1400 mm nominal dia (clear internal dia) of pipe with 14.2 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 310 Schedule of Rates 2014 - 2015

Page 191: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_272 Cost of Scrap kg 9.091 27.00 245.46

Rate anlalysis enclosed Carriage of steel 100m 1.00 8693.42 86.93 (C)

Material cost per meter Rs/meter 18716.86

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.556-(0.004*2+0.012*2+0.012))*0.012*1*2080= kg 118.56

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.556-0.004)*1= sqmt 4.876 575.00 2803.56 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.556-(0.004*2+0.012*2+0.012))*1= sqmt 4.750 450.00 2137.54 (E)

Total (A+B+C+D+E) 23657.96Total without ED 21065.06

Add Water Charges @ 1% 1% 210.65Add CPOH @ 15% 15% 3191.36

Total cost per meter for pipe 24467.07Total cost per kg for specials 42.69

2.5.4.57

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.6604 0.0142 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.6604-((0.004*2)+0.0142))*0.0142*1*7850= kg 573.687Add 2 % wastage

2% kg 11.474Total Weight kg 585.160

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 585.160 34.21 20018.48 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 573.687 6.63 3803.54 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 11.474 27.00 309.79

Rate anlalysis enclosed Carriage of steel 100m 1.00 8693.42 86.93 (C)

Material cost per meter Rs/meter 23599.17

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.6604-(0.004*2+0.0142*2+0.012))*0.012*1*2080= kg 126.40

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.6604-0.004)*1= sqmt 5.204 575.00 2992.15 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.6604-(0.004*2+0.0142*2+0.012))*1= sqmt 5.064 450.00 2278.91 (E)

Total (A+B+C+D+E) 28870.23Total without ED 25703.96

Add Water Charges @ 1% 1% 257.04Add CPOH @ 15% 15% 3894.15

Total cost per meter for pipe 29855.15Total cost per kg for specials 42.64

2.5.4.58

1600 mm nominal dia (clear internal dia) of pipe with 14.2 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

1600 mm nominal dia (clear internal dia) of pipe with 16.0 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 311 Schedule of Rates 2014 - 2015

Page 192: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.664 0.016 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.664-((0.004*2)+0.016))*0.016*1*7850= kg 647.118Add 2 % wastage

2% kg 12.942Total Weight kg 660.060

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 660.060 34.21 22580.82 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 647.118 6.63 4290.39 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 12.942 27.00 349.44

Rate anlalysis enclosed Carriage of steel 100m 1.00 8693.42 86.93 (C)

Material cost per meter Rs/meter 26608.70

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.664-(0.004*2+0.016*2+0.012))*0.012*1*2080= kg 126.40

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.664-0.004)*1= sqmt 5.215 575.00 2998.65 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.664-(0.004*2+0.016*2+0.012))*1= sqmt 5.064 450.00 2278.91 (E)

Total (A+B+C+D+E) 31886.27Total without ED 28388.23

Add Water Charges @ 1% 1% 283.88Add CPOH @ 15% 15% 4300.82

Total cost per meter for pipe 32972.93Total cost per kg for specials 42.63

2.5.4.59

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.8604 0.0142 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.8604-((0.004*2)+0.0142))*0.0142*1*7850= kg 643.725Add 2 % wastage

2% kg 12.875Total Weight kg 656.600

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 656.600 34.21 22462.45 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 643.725 6.63 4267.90 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 12.875 27.00 347.61

Rate anlalysis enclosed Carriage of steel 100m 1.00 10142.33 101.42 (C)

Material cost per meter Rs/meter 26484.16

1800 mm nominal dia (clear internal dia) of pipe with 14.2 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 312 Schedule of Rates 2014 - 2015

Page 193: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.8604-(0.004*2+0.0142*2+0.012))*0.012*1*2080= kg 142.09

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.8604-0.004)*1= sqmt 5.832 575.00 3353.43 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.8604-(0.004*2+0.0142*2+0.012))*1= sqmt 5.693 450.00 2561.65 (E)

Total (A+B+C+D+E) 32399.24Total without ED 28846.37

Add Water Charges @ 1% 1% 288.46Add CPOH @ 15% 15% 4370.22

Total cost per meter for pipe 33505.05Total cost per kg for specials 42.64

2.5.4.60

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.864 0.016 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.864-((0.004*2)+0.016))*0.016*1*7850= kg 726.035Add 2 % wastage

2% kg 14.521Total Weight kg 740.555

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 740.555 34.21 25334.58 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 726.035 6.63 4813.61 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 14.521 27.00 392.06

Rate anlalysis enclosed Carriage of steel 100m 1.00 10142.33 101.42 (C)

Material cost per meter Rs/meter 29857.56

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.864-(0.004*2+0.016*2+0.012))*0.012*1*2080= kg 142.09

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.864-0.004)*1= sqmt 5.843 575.00 3359.93 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.864-(0.004*2+0.016*2+0.012))*1= sqmt 5.693 450.00 2561.65 (E)

Total (A+B+C+D+E) 35779.14Total without ED 31854.47

Add Water Charges @ 1% 1% 318.54Add CPOH @ 15% 15% 4825.95

Total cost per meter for pipe 36998.96Total cost per kg for specials 42.62

2.5.4.61

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

1800 mm nominal dia (clear internal dia) of pipe with 16.0 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

1800 mm nominal dia (clear internal dia) of pipe with 17.5 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 313 Schedule of Rates 2014 - 2015

Page 194: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

1.867 0.0175 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(1.867-((0.004*2)+0.0175))*0.0175*1*7850= kg 794.748Add 2 % wastage

2% kg 15.895Total Weight kg 810.643

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 810.643 34.21 27732.29 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 794.748 6.63 5269.18 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 15.895 27.00 429.16

Rate anlalysis enclosed Carriage of steel 100m 1.00 10142.33 101.42 (C)

Material cost per meter Rs/meter 32673.73

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(1.867-(0.004*2+0.0175*2+0.012))*0.012*1*2080= kg 142.09

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(1.867-0.004)*1= sqmt 5.853 575.00 3365.35 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(1.867-(0.004*2+0.0175*2+0.012))*1= sqmt 5.693 450.00 2561.65 (E)

Total (A+B+C+D+E) 38600.73Total without ED 34365.67

Add Water Charges @ 1% 1% 343.66Add CPOH @ 15% 15% 5206.40

Total cost per meter for pipe 39915.73Total cost per kg for specials 42.61

2.5.4.62

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

2.064 0.016 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(2.064-((0.004*2)+0.016))*0.016*1*7850= kg 804.951Add 2 % wastage

2% kg 16.099Total Weight kg 821.050

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 821.050 34.21 28088.34 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 804.951 6.63 5336.83 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 16.099 27.00 434.67

Rate anlalysis enclosed Carriage of steel 100m 1.00 11591.23 115.91 (C)

Material cost per meter Rs/meter 33106.41

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

2000 mm nominal dia (clear internal dia) of pipe with 16.0 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 314 Schedule of Rates 2014 - 2015

Page 195: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

(3.1416)*(2.064-(0.004*2+0.016*2+0.012))*0.012*1*2080= kg 157.77

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(2.064-0.004)*1= sqmt 6.472 575.00 3721.22 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(2.064-(0.004*2+0.016*2+0.012))*1= sqmt 6.321 450.00 2844.40 (E)

Total (A+B+C+D+E) 39672.02Total without ED 35320.71

Add Water Charges @ 1% 1% 353.21Add CPOH @ 15% 15% 5351.09

Total cost per meter for pipe 41025.00Total cost per kg for specials 42.61

2.5.4.63

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

2.067 0.0175 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(2.067-((0.004*2)+0.0175))*0.0175*1*7850= kg 881.063Add 2 % wastage

2% kg 17.621Total Weight kg 898.684

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 898.684 34.21 30744.21 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 881.063 6.63 5841.45 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 17.621 27.00 475.77

Rate anlalysis enclosed Carriage of steel 100m 1.00 11591.23 115.91 (C)

Material cost per meter Rs/meter 36225.80

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(2.067-(0.004*2+0.0175*2+0.012))*0.012*1*2080= kg 157.77

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(2.067-0.004)*1= sqmt 6.481 575.00 3726.64 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(2.067-(0.004*2+0.0175*2+0.012))*1= sqmt 6.321 450.00 2844.40 (E)

Total (A+B+C+D+E) 42796.83Total without ED 38101.78

Add Water Charges @ 1% 1% 381.02Add CPOH @ 15% 15% 5772.42

Total cost per meter for pipe 44255.22Total cost per kg for specials 42.60

2.5.4.64

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

2.072 0.02 0.004

2000 mm nominal dia (clear internal dia) of pipe with 20.0 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

2000 mm nominal dia (clear internal dia) of pipe with 17.5 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 315 Schedule of Rates 2014 - 2015

Page 196: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

thickness of CML (t2) =

Length of pipe =

0.012 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(2.072-((0.004*2)+0.02))*0.02*1*7850= kg 1008.162Add 2 % wastage

2% kg 20.163Total Weight kg 1028.325

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 1028.325 34.21 35179.27 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 1008.162 6.63 6684.12 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 20.163 27.00 544.41

Rate anlalysis enclosed Carriage of steel 100m 1.00 11591.23 115.91 (C)

Material cost per meter Rs/meter 41434.89

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(2.072-(0.004*2+0.02*2+0.012))*0.012*1*2080= kg 157.77

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(2.072-0.004)*1= sqmt 6.497 575.00 3735.67 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(2.072-(0.004*2+0.02*2+0.012))*1= sqmt 6.321 450.00 2844.40 (E)

Total (A+B+C+D+E) 48014.96Total without ED 42745.89

Add Water Charges @ 1% 1% 427.46Add CPOH @ 15% 15% 6476.00

Total cost per meter for pipe 49649.35Total cost per kg for specials 42.58

2.5.4.65

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

2.267 0.0175 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(2.267-((0.004*2)+0.0175))*0.0175*1*7850= kg 967.378Add 2 % wastage

2% kg 19.348Total Weight kg 986.726

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 986.726 34.21 33756.14 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 967.378 6.63 6413.72 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 19.348 27.00 522.38

Rate anlalysis enclosed Carriage of steel 100m 1.00 13040.13 130.40 (C)

Material cost per meter Rs/meter 39777.87

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(2.267-(0.004*2+0.0175*2+0.012))*0.012*1*2080= kg 173.45

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(2.267-0.004)*1= sqmt 7.109 575.00 4087.92 (D)

2200 mm nominal dia (clear internal dia) of pipe with 17.5 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 316 Schedule of Rates 2014 - 2015

Page 197: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(2.267-(0.004*2+0.0175*2+0.012))*1= sqmt 6.949 450.00 3127.14 (E)

Total (A+B+C+D+E) 46992.93Total without ED 41837.89

Add Water Charges @ 1% 1% 418.38Add CPOH @ 15% 15% 6338.44

Total cost per meter for pipe 48594.70Total cost per kg for specials 42.60

2.5.4.66

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

2.272 0.02 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(2.272-((0.004*2)+0.02))*0.02*1*7850= kg 1106.808Add 2 % wastage

2% kg 22.136Total Weight kg 1128.944

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 1128.944 34.21 38621.47 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 1106.808 6.63 7338.14 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 22.136 27.00 597.68

Rate anlalysis enclosed Carriage of steel 100m 1.00 13040.13 130.40 (C)

Material cost per meter Rs/meter 45492.33

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(2.272-(0.004*2+0.02*2+0.012))*0.012*1*2080= kg 173.45

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(2.272-0.004)*1= sqmt 7.125 575.00 4096.95 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(2.272-(0.004*2+0.02*2+0.012))*1= sqmt 6.949 450.00 3127.14 (E)

Total (A+B+C+D+E) 52716.42Total without ED 46931.77

Add Water Charges @ 1% 1% 469.32Add CPOH @ 15% 15% 7110.16

Total cost per meter for pipe 54511.26Total cost per kg for specials 42.58

2.5.4.67

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

2.2764 0.0222 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(2.2764-((0.004*2)+0.0222))*0.0222*1*7850= kg 1229.762Add 2 % wastage

2200 mm nominal dia (clear internal dia) of pipe with 20.0 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

2200 mm nominal dia (clear internal dia) of pipe with 22.2 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 317 Schedule of Rates 2014 - 2015

Page 198: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

2% kg 24.595Total Weight kg 1254.357

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 1254.357 34.21 42911.86 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 1229.762 6.63 8153.32 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 24.595 27.00 664.07

Rate anlalysis enclosed Carriage of steel 100m 1.00 13040.13 130.40 (C)

Material cost per meter Rs/meter 50531.51

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(2.2764-(0.004*2+0.0222*2+0.012))*0.012*1*2080= kg 173.45

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(2.2764-0.004)*1= sqmt 7.139 575.00 4104.90 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(2.2764-(0.004*2+0.0222*2+0.012))*1= sqmt 6.949 450.00 3127.14 (E)

Total (A+B+C+D+E) 57763.55Total without ED 51423.70

Add Water Charges @ 1% 1% 514.24Add CPOH @ 15% 15% 7790.69

Total cost per meter for pipe 59728.63Total cost per kg for specials 42.57

2.5.4.68

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

2.572 0.02 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(2.572-((0.004*2)+0.02))*0.02*1*7850= kg 1254.777Add 2 % wastage

2% kg 25.096Total Weight kg 1279.873

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 1279.873 34.21 43784.77 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 1254.777 6.63 8319.17 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 25.096 27.00 677.58

Rate anlalysis enclosed Carriage of steel 100m 1.00 14489.04 144.89 (C)

Material cost per meter Rs/meter 51571.25

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(2.572-(0.004*2+0.02*2+0.012))*0.012*1*2080= kg 196.98

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(2.572-0.004)*1= sqmt 8.068 575.00 4638.88 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(2.572-(0.004*2+0.02*2+0.012))*1= sqmt 7.892 450.00 3551.26 (E)

Total (A+B+C+D+E) 59761.38Total without ED 53203.36

2500 mm nominal dia (clear internal dia) of pipe with 20.0 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 318 Schedule of Rates 2014 - 2015

Page 199: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add Water Charges @ 1% 1% 532.03Add CPOH @ 15% 15% 8060.31

Total cost per meter for pipe 61795.70Total cost per kg for specials 42.57

2.5.4.69

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

2.5764 0.0222 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(2.5764-((0.004*2)+0.0222))*0.0222*1*7850= kg 1394.007Add 2 % wastage

2% kg 27.880Total Weight kg 1421.887

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 1421.887 34.21 48643.12 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 1394.007 6.63 9242.27 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 27.880 27.00 752.76

Rate anlalysis enclosed Carriage of steel 100m 1.00 14489.04 144.89 (C)

Material cost per meter Rs/meter 57277.51

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(2.5764-(0.004*2+0.0222*2+0.012))*0.012*1*2080= kg 196.98

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(2.5764-0.004)*1= sqmt 8.081 575.00 4646.82 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(2.5764-(0.004*2+0.0222*2+0.012))*1= sqmt 7.892 450.00 3551.26 (E)

Total (A+B+C+D+E) 65475.59Total without ED 58288.98

Add Water Charges @ 1% 1% 582.89Add CPOH @ 15% 15% 8830.78

Total cost per meter for pipe 67702.66Total cost per kg for specials 42.55

2.5.4.70

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =

thickness of coaltar coating and wrapping

(t3) =

2.582 0.025 0.004thickness of

CML (t2) =Length of pipe

=0.012 1.0

Weight of MS coil = pi()*(d-(t3*2+t1))*t1*L*7850(3.1416)*(2.582-((0.004*2)+0.025))*0.025*1*7850= kg 1571.554Add 2 % wastage

2% kg 31.431Total Weight kg 1602.985

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 1602.985 34.21 54838.53 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 1571.554 6.63 10419.40 (B)

2500 mm nominal dia (clear internal dia) of pipe with 22.2 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

2500 mm nominal dia (clear internal dia) of pipe with 25.0 mm thick coil, 12 mm thick internal cement mortar lining and exterior / outside 4mm coaltarcoating and wrapping

Delhi Jal Board 319 Schedule of Rates 2014 - 2015

Page 200: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_272 Cost of Scrap kg 31.431 27.00 848.64

Rate anlalysis enclosed Carriage of steel 100m 1.00 14489.04 144.89 (C)

Material cost per meter Rs/meter 64554.18

Weight of Cement Morter Lining (CML) = pi()*(d-(t 3*2+t1*2+t2))*t2*L*2000

(3.1416)*(2.582-(0.004*2+0.025*2+0.012))*0.012*1*2080= kg 196.98

Outside 4mm coaltar coating and wrappingQuotation_Vol III_pg no 448

Area of coating = pi()*(d-t3 )*L

(3.1416)*(2.582-0.004)*1= sqmt 8.099 575.00 4656.94 (D)

Quotation_Volume III_pg no_448

Inside cement morter lining (CML) = pi()*(d-(t3*2+t1*2+t2))*L

(3.1416)*(2.582-(0.004*2+0.025*2+0.012))*1= sqmt 7.892 450.00 3551.26 (E)

Total (A+B+C+D+E) 72762.38Total without ED 64774.20

Add Water Charges @ 1% 1% 647.74Add CPOH @ 15% 15% 9813.29

Total cost per meter for pipe 75235.23Total cost per kg for specials 42.54

Delhi Jal Board 320 Schedule of Rates 2014 - 2015

Page 201: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

2.5.5

2.5.5.1

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =0.16 0.005

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.16-0.005)*0.005*1*7850= kg 19.113Add 5 % wastage

5% kg 0.956Total Weight kg 20.068

#REF! Cost of MS plate kg 20.068 45.00 903.07 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 19.113 6.63 126.72 (B)

Quotation_Volume III_pg no_272 Cost of scrap kg 0.956 27.00 25.80

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 289.78 2.90 (C)

Material cost per meter Rs/meter 1006.89

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.16*1= sqmt 0.503 100.33 50.43 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.16-(0.005*2))*1= sqmt 0.471 640.00 301.59 (E)

Total (A+B+C+D+E) 1358.91Total without ED 1209.74

Providing Mild Steel Pipes / specials fabricated / manufactured out of MS plate of steel grade Fe410 as per IS 3589:2001; internally coated withfood grade epoxy coating and external / outside epoxy coating; minimum thickness of M.S. Plate as specified; complete in all respect; withupto date amendments in relevant IS codes and as directed by Engineer-in-charge . The rates are excluding excise duty component.

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outsideepoxy coating

Total without ED 1209.74Add Water Charges @ 1% 1% 12.10

Add CPOH @ 15% 15% 183.28Total cost per meter for pipe 1405.12

Total cost per kg for specials 73.52

2.5.5.2

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =0.21 0.005

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.21-0.005)*0.005*1*7850= kg 25.278Add 5 % wastage

5% kg 1.264Total Weight kg 26.542

#REF! Cost of MS plate kg 26.542 45.00 1194.39 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 25.278 6.63 167.59 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.264 27.00 34.13

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 471.38 4.71 (C)

Material cost per meter Rs/meter 1332.57

200 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 335 Schedule of Rates 2014 - 2015

Page 202: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outsideOutside epoxy coating

13.52.1 Area of coating = pi()*d*L(3.1416)*0.21*1= sqmt 0.660 100.33 66.19 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.21-(0.005*2))*1= sqmt 0.628 640.00 402.12 (E)

Total (A+B+C+D+E) 1800.88Total without ED 1603.30

Add Water Charges @ 1% 1% 16.03Add CPOH @ 15% 15% 242.90

Total cost per meter for pipe 1862.23Total cost per kg for specials 73.67

2.5.5.3

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =0.212 0.006

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.212-0.006)*0.006*1*7850= kg 30.482Add 5 % wastage

5% kg 1.524Total Weight kg 32.006

#REF! Cost of MS plate kg 32.006 45.00 1440.26 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 30.482 6.63 202.09 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.524 27.00 41.15

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 471.38 4.71 (C)

Material cost per meter Rs/meter 1605.91

200 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick plate, internally coated with food grade epoxy coating and external / outsideepoxy coating

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.212*1= sqmt 0.666 100.33 66.82 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.212-(0.006*2))*1= sqmt 0.628 640.00 402.12 (E)

Total (A+B+C+D+E) 2074.86Total without ED 1847.13

Add Water Charges @ 1% 1% 18.47Add CPOH @ 15% 15% 279.84

Total cost per meter for pipe 2145.45Total cost per kg for specials 70.39

2.5.5.4

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =0.2126 0.0063

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.2126-0.0063)*0.0063*1*7850= kg 32.052Add 5 % wastage

5% kg 1.603Total Weight kg 33.655

200 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick plate, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 336 Schedule of Rates 2014 - 2015

Page 203: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outside#REF! Cost of MS plate kg 33.655 45.00 1514.47 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 32.052 6.63 212.51 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.603 27.00 43.27

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 471.38 4.71 (C)

Material cost per meter Rs/meter 1688.42

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.2126*1= sqmt 0.668 100.33 67.01 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.2126-(0.0063*2))*1= sqmt 0.628 640.00 402.12 (E)

Total (A+B+C+D+E) 2157.56Total without ED 1920.74

Add Water Charges @ 1% 1% 19.21Add CPOH @ 15% 15% 290.99

Total cost per meter for pipe 2230.93Total cost per kg for specials 69.60

2.5.5.5

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =0.26 0.005

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.26-0.005)*0.005*1*7850= kg 31.443Add 5 % wastage

5% kg 1.572Total Weight kg 33.016

250 mm nominal dia (clear internal dia) of pipe with 5.0 mm thick plate, internally coated with food grade epoxy coating and external / outsideepoxy coating

#REF! Cost of MS plate kg 33.016 45.00 1485.70 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 31.443 6.63 208.47 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.572 27.00 42.45

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 669.85 6.70 (C)

Material cost per meter Rs/meter 1658.42

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.26*1= sqmt 0.817 100.33 81.95 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.26-(0.005*2))*1= sqmt 0.785 640.00 502.65 (E)

Total (A+B+C+D+E) 2243.03Total without ED 1997.02

Add Water Charges @ 1% 1% 19.97Add CPOH @ 15% 15% 302.55

Total cost per meter for pipe 2319.54Total cost per kg for specials 73.77

2.5.5.6

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

250 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick plate, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 337 Schedule of Rates 2014 - 2015

Page 204: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outsideDetail for 1 meter

Outer dia (d) = thickness of pipe (t1) =

0.262 0.006Length of pipe

=1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.262-0.006)*0.006*1*7850= kg 37.880Add 5 % wastage

5% kg 1.894Total Weight kg 39.774

#REF! Cost of MS plate kg 39.774 45.00 1789.83 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 37.880 6.63 251.14 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.894 27.00 51.14

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 669.85 6.70 (C)

Material cost per meter Rs/meter 1996.54

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.262*1= sqmt 0.823 100.33 82.58 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.262-(0.006*2))*1= sqmt 0.785 640.00 502.65 (E)

Total (A+B+C+D+E) 2581.77Total without ED 2298.51

Add Water Charges @ 1% 1% 22.99Add CPOH @ 15% 15% 348.22

Total cost per meter for pipe 2669.72Total cost per kg for specials 70.48

2.5.5.7

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

250 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick plate, internally coated with food grade epoxy coating and external / outsideepoxy coating

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =0.2626 0.0063

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.2626-0.0063)*0.0063*1*7850= kg 39.821Add 5 % wastage

5% kg 1.991Total Weight kg 41.812

#REF! Cost of MS plate kg 41.812 45.00 1881.53 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 39.821 6.63 264.01 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.991 27.00 53.76

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 669.85 6.70 (C)

Material cost per meter Rs/meter 2098.48

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.2626*1= sqmt 0.825 100.33 82.77 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.2626-(0.0063*2))*1= sqmt 0.785 640.00 502.65 (E)

Delhi Jal Board 338 Schedule of Rates 2014 - 2015

Page 205: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outsideTotal (A+B+C+D+E) 2683.90Total without ED 2389.40

Add Water Charges @ 1% 1% 23.89Add CPOH @ 15% 15% 361.99

Total cost per meter for pipe 2775.29Total cost per kg for specials 69.69

2.5.5.8

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =0.31 0.005

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.31-0.005)*0.005*1*7850= kg 37.609Add 5 % wastage

5% kg 1.880Total Weight kg 39.489

#REF! Cost of MS plate kg 39.489 45.00 1777.02 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 37.609 6.63 249.35 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.880 27.00 50.77

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 827.95 8.28 (C)

Material cost per meter Rs/meter 1983.87

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.31*1= sqmt 0.974 100.33 97.71 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.31-(0.005*2))*1= sqmt 0.942 640.00 603.19 (E)

300 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outsideepoxy coating

Total (A+B+C+D+E) 2684.76Total without ED 2390.34

Add Water Charges @ 1% 1% 23.90Add CPOH @ 15% 15% 362.14

Total cost per meter for pipe 2776.38Total cost per kg for specials 73.82

2.5.5.9

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =0.3112 0.0056

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.3112-0.0056)*0.0056*1*7850= kg 42.205Add 5 % wastage

5% kg 2.110Total Weight kg 44.315

#REF! Cost of MS plate kg 44.315 45.00 1994.17 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 42.205 6.63 279.82 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.110 27.00 56.98

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 827.95 8.28 (C)

Material cost per meter Rs/meter 2225.29

300 mm nominal dia (clear internal dia) of pipe with 5.6 mm thick plate, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 339 Schedule of Rates 2014 - 2015

Page 206: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outside

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.3112*1= sqmt 0.978 100.33 98.09 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.3112-(0.0056*2))*1= sqmt 0.942 640.00 603.19 (E)

Total (A+B+C+D+E) 2926.57Total without ED 2605.54

Add Water Charges @ 1% 1% 26.06Add CPOH @ 15% 15% 394.74

Total cost per meter for pipe 3026.34Total cost per kg for specials 71.71

2.5.5.10

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =0.3142 0.0071

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.3142-0.0071)*0.0071*1*7850= kg 53.772Add 5 % wastage

5% kg 2.689Total Weight kg 56.461

#REF! Cost of MS plate kg 56.461 45.00 2540.74 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 53.772 6.63 356.51 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.689 27.00 72.59

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 827.95 8.28 (C)

Material cost per meter Rs/meter 2832.93

300 mm nominal dia (clear internal dia) of pipe with 7.1 mm thick plate, internally coated with food grade epoxy coating and external / outsideepoxy coating

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.3142*1= sqmt 0.987 100.33 99.03 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.3142-(0.0071*2))*1= sqmt 0.942 640.00 603.19 (E)

Total (A+B+C+D+E) 3535.15Total without ED 3147.18

Add Water Charges @ 1% 1% 31.47Add CPOH @ 15% 15% 476.80

Total cost per meter for pipe 3655.45Total cost per kg for specials 67.98

2.5.5.11

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =0.36 0.005

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.36-0.005)*0.005*1*7850= kg 43.774Add 5 % wastage

350 mm nominal dia (clear internal dia) of pipe with 5.0 mm thick plate, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 340 Schedule of Rates 2014 - 2015

Page 207: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outside5% kg 2.189Total Weight kg 45.963

#REF! Cost of MS plate kg 45.963 45.00 2068.33 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 43.774 6.63 290.22 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.189 27.00 59.10

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1159.12 11.59 (C)

Material cost per meter Rs/meter 2311.05

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.36*1= sqmt 1.131 100.33 113.47 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.36-(0.005*2))*1= sqmt 1.100 640.00 703.72 (E)

Total (A+B+C+D+E) 3128.23Total without ED 2785.39

Add Water Charges @ 1% 1% 27.85Add CPOH @ 15% 15% 421.99

Total cost per meter for pipe 3235.23Total cost per kg for specials 73.91

2.5.5.12

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =0.3612 0.0056

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.3612-0.0056)*0.0056*1*7850= kg 49.110Add 5 % wastage

350 mm nominal dia (clear internal dia) of pipe with 5.6 mm thick plate, internally coated with food grade epoxy coating and external / outsideepoxy coating

Add 5 % wastage5% kg 2.455

Total Weight kg 51.565

#REF! Cost of MS plate kg 51.565 45.00 2320.44 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 49.110 6.63 325.60 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.455 27.00 66.30

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1159.12 11.59 (C)

Material cost per meter Rs/meter 2591.34

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.3612*1= sqmt 1.135 100.33 113.85 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.3612-(0.0056*2))*1= sqmt 1.100 640.00 703.72 (E)

Total (A+B+C+D+E) 3408.90Total without ED 3035.18

Add Water Charges @ 1% 1% 30.35Add CPOH @ 15% 15% 459.83

Total cost per meter for pipe 3525.37Total cost per kg for specials 71.79

2.5.5.13 350 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick plate, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 341 Schedule of Rates 2014 - 2015

Page 208: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outsideITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT

(INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =0.366 0.008

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.366-0.008)*0.008*1*7850= kg 70.631Add 5 % wastage

5% kg 3.532Total Weight kg 74.162

#REF! Cost of MS plate kg 74.162 45.00 3337.29 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 70.631 6.63 468.28 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.532 27.00 95.35

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1159.12 11.59 (C)

Material cost per meter Rs/meter 3721.81

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.366*1= sqmt 1.150 100.33 115.36 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.366-(0.008*2))*1= sqmt 1.100 640.00 703.72 (E)

Total (A+B+C+D+E) 4540.89Total without ED 4042.65

Add Water Charges @ 1% 1% 40.43Add CPOH @ 15% 15% 612.46

Total cost per meter for pipe 4695.54Total cost per kg for specials 66.48

2.5.5.14 400 mm nominal dia (clear internal dia) of pipe with 5.0 mm thick plate, internally coated with food grade epoxy coating and external / outsideepoxy coating

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =0.41 0.005

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.41-0.005)*0.005*1*7850= kg 49.940Add 5 % wastage

5% kg 2.497Total Weight kg 52.437

#REF! Cost of MS plate kg 52.437 45.00 2359.64 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 49.940 6.63 331.10 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.497 27.00 67.42

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1580.62 15.81 (C)

Material cost per meter Rs/meter 2639.13

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.41*1= sqmt 1.288 100.33 129.23 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.41-(0.005*2))*1= sqmt 1.257 640.00 804.25 (E)

Delhi Jal Board 342 Schedule of Rates 2014 - 2015

Page 209: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outside

Total (A+B+C+D+E) 3572.61Total without ED 3181.35

Add Water Charges @ 1% 1% 31.81Add CPOH @ 15% 15% 481.97

Total cost per meter for pipe 3695.13Total cost per kg for specials 73.99

2.5.5.15

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =0.412 0.006

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.412-0.006)*0.006*1*7850= kg 60.075Add 5 % wastage

5% kg 3.004Total Weight kg 63.079

#REF! Cost of MS plate kg 63.079 45.00 2838.56 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 60.075 6.63 398.30 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.004 27.00 81.10

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1580.62 15.81 (C)

Material cost per meter Rs/meter 3171.57

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.412*1= sqmt 1.294 100.33 129.86 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.412-(0.006*2))*1= sqmt 1.257 640.00 804.25 (E)

400 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick plate, internally coated with food grade epoxy coating and external / outsideepoxy coating

Total (A+B+C+D+E) 4105.68Total without ED 3655.78

Add Water Charges @ 1% 1% 36.56Add CPOH @ 15% 15% 553.85

Total cost per meter for pipe 4246.18Total cost per kg for specials 70.68

2.5.5.16

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =0.4126 0.0063

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.4126-0.0063)*0.0063*1*7850= kg 63.126Add 5 % wastage

5% kg 3.156Total Weight kg 66.282

#REF! Cost of MS plate kg 66.282 45.00 2982.69 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 63.126 6.63 418.52 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.156 27.00 85.22

400 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick plate, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 343 Schedule of Rates 2014 - 2015

Page 210: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outsidePlease refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1580.62 15.81 (C)

Material cost per meter Rs/meter 3331.80

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.4126*1= sqmt 1.296 100.33 130.05 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.4126-(0.0063*2))*1= sqmt 1.257 640.00 804.25 (E)

Total (A+B+C+D+E) 4266.10Total without ED 3798.55

Add Water Charges @ 1% 1% 37.99Add CPOH @ 15% 15% 575.48

Total cost per meter for pipe 4412.02Total cost per kg for specials 69.89

2.5.5.17

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =0.4176 0.0088

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.4176-0.0088)*0.0088*1*7850= kg 88.718Add 5 % wastage

5% kg 4.436Total Weight kg 93.154

#REF! Cost of MS plate kg 93.154 45.00 4191.94 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 88.718 6.63 588.20 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 4.436 27.00 119.77

400 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick plate, internally coated with food grade epoxy coating and external / outsideepoxy coating

III_pg no_272Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1580.62 15.81 (C)

Material cost per meter Rs/meter 4676.18

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.4176*1= sqmt 1.312 100.33 131.62 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.4176-(0.0088*2))*1= sqmt 1.257 640.00 804.25 (E)

Total (A+B+C+D+E) 5612.05Total without ED 4996.44

Add Water Charges @ 1% 1% 49.96Add CPOH @ 15% 15% 756.96

Total cost per meter for pipe 5803.37Total cost per kg for specials 65.41

2.5.5.18

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =0.462 0.006

Length of pipe =

1.0

450 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick plate, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 344 Schedule of Rates 2014 - 2015

Page 211: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outsideWeight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.462-0.006)*0.006*1*7850= kg 67.474Add 5 % wastage

5% kg 3.374Total Weight kg 70.848

#REF! Cost of MS plate kg 70.848 45.00 3188.14 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 67.474 6.63 447.35 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.374 27.00 91.09

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 3563.72

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.462*1= sqmt 1.451 100.33 145.62 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.462-(0.006*2))*1= sqmt 1.414 640.00 904.78 (E)

Total (A+B+C+D+E) 4614.12Total without ED 4108.67

Add Water Charges @ 1% 1% 41.09Add CPOH @ 15% 15% 622.46

Total cost per meter for pipe 4772.23Total cost per kg for specials 70.73

2.5.5.19

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =0.4626 0.0063

Length of pipe =

1.0

450 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick plate, internally coated with food grade epoxy coating and external / outsideepoxy coating

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.4626-0.0063)*0.0063*1*7850= kg 70.894Add 5 % wastage

5% kg 3.545Total Weight kg 74.439

#REF! Cost of MS plate kg 74.439 45.00 3349.75 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 70.894 6.63 470.03 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.545 27.00 95.71

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 3743.39

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.4626*1= sqmt 1.453 100.33 145.81 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.4626-(0.0063*2))*1= sqmt 1.414 640.00 904.78 (E)

Total (A+B+C+D+E) 4793.98Total without ED 4268.75

Add Water Charges @ 1% 1% 42.69Add CPOH @ 15% 15% 646.72

Total cost per meter for pipe 4958.15Total cost per kg for specials 69.94

Delhi Jal Board 345 Schedule of Rates 2014 - 2015

Page 212: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outside2.5.5.20

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =0.47 0.01

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.47-0.01)*0.01*1*7850= kg 113.443Add 5 % wastage

5% kg 5.672Total Weight kg 119.115

#REF! Cost of MS plate kg 119.115 45.00 5360.18 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 113.443 6.63 752.13 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 5.672 27.00 153.15

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 5978.47

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.47*1= sqmt 1.477 100.33 148.14 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.47-(0.01*2))*1= sqmt 1.414 640.00 904.78 (E)

Total (A+B+C+D+E) 7031.39Total without ED 6260.04

Add Water Charges @ 1% 1% 62.60Add CPOH @ 15% 15% 948.40

Total cost per meter for pipe 7271.04Total cost per kg for specials 64.09

450 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick plate, internally coated with food grade epoxy coating and external /outside epoxy coating

2.5.5.21

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =0.512 0.006

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.512-0.006)*0.006*1*7850= kg 74.872Add 5 % wastage

5% kg 3.744Total Weight kg 78.616

#REF! Cost of MS plate kg 78.616 45.00 3537.72 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 74.872 6.63 496.40 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.744 27.00 101.08

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 3952.36

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.512*1= sqmt 1.608 100.33 161.38 (D)

500 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick plate, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 346 Schedule of Rates 2014 - 2015

Page 213: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outsideQuotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.512-(0.006*2))*1= sqmt 1.571 640.00 1005.31 (E)

Total (A+B+C+D+E) 5119.05Total without ED 4558.06

Add Water Charges @ 1% 1% 45.58Add CPOH @ 15% 15% 690.55

Total cost per meter for pipe 5294.19Total cost per kg for specials 70.71

2.5.5.22

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =0.5126 0.0063

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.5126-0.0063)*0.0063*1*7850= kg 78.663Add 5 % wastage

5% kg 3.933Total Weight kg 82.596

#REF! Cost of MS plate kg 82.596 45.00 3716.81 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 78.663 6.63 521.53 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.933 27.00 106.19

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 4151.46

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.5126*1= sqmt 1.610 100.33 161.57 (D)

500 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick plate, internally coated with food grade epoxy coating and external / outsideepoxy coating

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.5126-(0.0063*2))*1= sqmt 1.571 640.00 1005.31 (E)

Total (A+B+C+D+E) 5318.34Total without ED 4735.43

Add Water Charges @ 1% 1% 47.35Add CPOH @ 15% 15% 717.42

Total cost per meter for pipe 5500.20Total cost per kg for specials 69.92

2.5.5.23

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =0.522 0.011

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.522-0.011)*0.011*1*7850= kg 138.622Add 5 % wastage

5% kg 6.931Total Weight kg 145.553

#REF! Cost of MS plate kg 145.553 45.00 6549.90 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 138.622 6.63 919.07 (B)

500 mm nominal dia (clear internal dia) of pipe with 11.0 mm thick plate, internally coated with food grade epoxy coating and external /outside epoxy coating

Delhi Jal Board 347 Schedule of Rates 2014 - 2015

Page 214: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outsideQuotation_Volume III_pg no_272 Cost of Scrap kg 6.931 27.00 187.14

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 7301.15

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.522*1= sqmt 1.640 100.33 164.53 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.522-(0.011*2))*1= sqmt 1.571 640.00 1005.31 (E)

Total (A+B+C+D+E) 8470.99Total without ED 7541.27

Add Water Charges @ 1% 1% 75.41Add CPOH @ 15% 15% 1142.50

Total cost per meter for pipe 8759.19Total cost per kg for specials 63.19

2.5.5.24

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =0.612 0.006

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.612-0.006)*0.006*1*7850= kg 89.669Add 5 % wastage

5% kg 4.483Total Weight kg 94.153

#REF! Cost of MS plate kg 94.153 45.00 4236.87 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 89.669 6.63 594.51 (B)

600 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick plate, internally coated with food grade epoxy coating and external / outsideepoxy coating

Quotation_Volume III_pg no_272 Cost of Scrap kg 4.483 27.00 121.05

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 4739.30

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.612*1= sqmt 1.923 100.33 192.90 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.612-(0.006*2))*1= sqmt 1.885 640.00 1206.37 (E)

Total (A+B+C+D+E) 6138.57Total without ED 5466.49

Add Water Charges @ 1% 1% 54.66Add CPOH @ 15% 15% 828.17

Total cost per meter for pipe 6349.33Total cost per kg for specials 70.81

2.5.5.25

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =0.6126 0.0063

Length of pipe =

600 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick plate, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 348 Schedule of Rates 2014 - 2015

Page 215: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outside1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.6126-0.0063)*0.0063*1*7850= kg 94.199Add 5 % wastage

5% kg 4.710Total Weight kg 98.909

#REF! Cost of MS plate kg 98.909 45.00 4450.92 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 94.199 6.63 624.54 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 4.710 27.00 127.17

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 4977.27

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.6126*1= sqmt 1.925 100.33 193.09 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.6126-(0.0063*2))*1= sqmt 1.885 640.00 1206.37 (E)

Total (A+B+C+D+E) 6376.73Total without ED 5678.45

Add Water Charges @ 1% 1% 56.78Add CPOH @ 15% 15% 860.29

Total cost per meter for pipe 6595.52Total cost per kg for specials 70.02

2.5.5.26

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =0.616 0.008

Length of pipe =

600 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick plate, internally coated with food grade epoxy coating and external / outsideepoxy coating

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.616-0.008)*0.008*1*7850= kg 119.954Add 5 % wastage

5% kg 5.998Total Weight kg 125.951

#REF! Cost of MS plate kg 125.951 45.00 5667.81 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 119.954 6.63 795.29 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 5.998 27.00 161.94

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 6330.14

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.616*1= sqmt 1.935 100.33 194.16 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.616-(0.008*2))*1= sqmt 1.885 640.00 1206.37 (E)

Total (A+B+C+D+E) 7730.67Total without ED 6883.45

Add Water Charges @ 1% 1% 68.83Add CPOH @ 15% 15% 1042.84

Total cost per meter for pipe 7995.13

Delhi Jal Board 349 Schedule of Rates 2014 - 2015

Page 216: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outsideTotal cost per kg for specials 66.65

2.5.5.27

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =0.625 0.0125

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.625-0.0125)*0.0125*1*7850= kg 188.815Add 5 % wastage

5% kg 9.441Total Weight kg 198.255

#REF! Cost of MS plate kg 198.255 45.00 8921.49 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 188.815 6.63 1251.84 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 9.441 27.00 254.90

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 9947.41

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.625*1= sqmt 1.963 100.33 197.00 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.625-(0.0125*2))*1= sqmt 1.885 640.00 1206.37 (E)

Total (A+B+C+D+E) 11350.78Total without ED 10105.34

Add Water Charges @ 1% 1% 101.05Add CPOH @ 15% 15% 1530.96

Total cost per meter for pipe 11737.35

600 mm nominal dia (clear internal dia) of pipe with 12.5 mm thick plate, internally coated with food grade epoxy coating and external /outside epoxy coating

Total cost per meter for pipe 11737.35Total cost per kg for specials 62.16

2.5.5.28

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =0.712 0.006

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.712-0.006)*0.006*1*7850= kg 104.466Add 5 % wastage

5% kg 5.223Total Weight kg 109.689

#REF! Cost of MS plate kg 109.689 45.00 4936.02 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 104.466 6.63 692.61 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 5.223 27.00 141.03

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 5516.58

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

700 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick plate, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 350 Schedule of Rates 2014 - 2015

Page 217: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outside(3.1416)*0.712*1= sqmt 2.237 100.33 224.42 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.712-(0.006*2))*1= sqmt 2.199 640.00 1407.43 (E)

Total (A+B+C+D+E) 7148.43Total without ED 6365.27

Add Water Charges @ 1% 1% 63.65Add CPOH @ 15% 15% 964.34

Total cost per meter for pipe 7393.26Total cost per kg for specials 70.77

2.5.5.29

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =0.7126 0.0063

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.7126-0.0063)*0.0063*1*7850= kg 109.736Add 5 % wastage

5% kg 5.487Total Weight kg 115.223

#REF! Cost of MS plate kg 115.223 45.00 5185.03 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 109.736 6.63 727.55 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 5.487 27.00 148.14

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 5793.41

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

700 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick plate, internally coated with food grade epoxy coating and external / outsideepoxy coating

(3.1416)*0.7126*1= sqmt 2.239 100.33 224.61 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.7126-(0.0063*2))*1= sqmt 2.199 640.00 1407.43 (E)

Total (A+B+C+D+E) 7425.45Total without ED 6611.81

Add Water Charges @ 1% 1% 66.12Add CPOH @ 15% 15% 1001.69

Total cost per meter for pipe 7679.62Total cost per kg for specials 69.98

2.5.5.30

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =0.7142 0.0071

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.7142-0.0071)*0.0071*1*7850= kg 123.811Add 5 % wastage

5% kg 6.191Total Weight kg 130.001

#REF! Cost of MS plate kg 130.001 45.00 5850.06 (A)

700 mm nominal dia (clear internal dia) of pipe with 7.1 mm thick plate, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 351 Schedule of Rates 2014 - 2015

Page 218: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outsideQuotation_Volume III_pg no_320 Cost of Fabrication kg 123.811 6.63 820.87 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 6.191 27.00 167.14

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 6532.76

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.7142*1= sqmt 2.244 100.33 225.11 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.7142-(0.0071*2))*1= sqmt 2.199 640.00 1407.43 (E)

Total (A+B+C+D+E) 8165.31Total without ED 7270.28

Add Water Charges @ 1% 1% 72.70Add CPOH @ 15% 15% 1101.45

Total cost per meter for pipe 8444.43Total cost per kg for specials 68.20

2.5.5.31

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =0.716 0.008

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.716-0.008)*0.008*1*7850= kg 139.683Add 5 % wastage

5% kg 6.984Total Weight kg 146.667

#REF! Cost of MS plate kg 146.667 45.00 6600.01 (A)

700 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick plate, internally coated with food grade epoxy coating and external / outsideepoxy coating

Quotation_Volume III_pg no_320 Cost of Fabrication kg 139.683 6.63 926.10 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 6.984 27.00 188.57

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 7366.51

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.716*1= sqmt 2.249 100.33 225.68 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.716-(0.008*2))*1= sqmt 2.199 640.00 1407.43 (E)

Total (A+B+C+D+E) 8999.62Total without ED 8012.82

Add Water Charges @ 1% 1% 80.13Add CPOH @ 15% 15% 1213.94

Total cost per meter for pipe 9306.89Total cost per kg for specials 66.63

2.5.5.32

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =0.7284 0.0142

700 mm nominal dia (clear internal dia) of pipe with 14.2 mm thick plate, internally coated with food grade epoxy coating and external /outside epoxy coating

Delhi Jal Board 352 Schedule of Rates 2014 - 2015

Page 219: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outsideLength of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.7284-0.0142)*0.0142*1*7850= kg 250.108Add 5 % wastage

5% kg 12.505Total Weight kg 262.613

#REF! Cost of MS plate kg 262.613 45.00 11817.61 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 250.108 6.63 1658.22 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 12.505 27.00 337.65

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 13167.16

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.7284*1= sqmt 2.288 100.33 229.59 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.7284-(0.0142*2))*1= sqmt 2.199 640.00 1407.43 (E)

Total (A+B+C+D+E) 14804.18Total without ED 13178.85

Add Water Charges @ 1% 1% 131.79Add CPOH @ 15% 15% 1996.60

Total cost per meter for pipe 15307.24Total cost per kg for specials 61.20

2.5.5.33

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =0.8142 0.0071

800 mm nominal dia (clear internal dia) of pipe with 7.1 mm thick plate, internally coated with food grade epoxy coating and external / outsideepoxy coating

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.8142-0.0071)*0.0071*1*7850= kg 141.321Add 5 % wastage

5% kg 7.066Total Weight kg 148.387

#REF! Cost of MS plate kg 148.387 45.00 6677.39 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 141.321 6.63 936.96 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 7.066 27.00 190.78

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 7452.54

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.8142*1= sqmt 2.558 100.33 256.63 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.8142-(0.0071*2))*1= sqmt 2.513 640.00 1608.50 (E)

Total (A+B+C+D+E) 9317.67Total without ED 8295.88

Add Water Charges @ 1% 1% 82.96

Delhi Jal Board 353 Schedule of Rates 2014 - 2015

Page 220: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outsideAdd CPOH @ 15% 15% 1256.83Total cost per meter for pipe 9635.67

Total cost per kg for specials 68.18

2.5.5.34

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =0.816 0.008

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.816-0.008)*0.008*1*7850= kg 159.412Add 5 % wastage

5% kg 7.971Total Weight kg 167.383

#REF! Cost of MS plate kg 167.383 45.00 7532.21 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 159.412 6.63 1056.90 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 7.971 27.00 215.21

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 8402.89

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.816*1= sqmt 2.564 100.33 257.20 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.816-(0.008*2))*1= sqmt 2.513 640.00 1608.50 (E)

Total (A+B+C+D+E) 10268.58Total without ED 9142.19

Add Water Charges @ 1% 1% 91.42

800 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick plate, internally coated with food grade epoxy coating and external / outsideepoxy coating

Add CPOH @ 15% 15% 1385.04Total cost per meter for pipe 10618.65

Total cost per kg for specials 66.61

2.5.5.35

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =0.836 0.018

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.836-0.018)*0.018*1*7850= kg 363.116Add 5 % wastage

5% kg 18.156Total Weight kg 381.272

#REF! Cost of MS plate kg 381.272 45.00 17157.23 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 363.116 6.63 2407.46 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 18.156 27.00 490.21

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 19103.46

800 mm nominal dia (clear internal dia) of pipe with 18.0 mm thick plate, internally coated with food grade epoxy coating and external /outside epoxy coating

Delhi Jal Board 354 Schedule of Rates 2014 - 2015

Page 221: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outsideOutside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.836*1= sqmt 2.626 100.33 263.50 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.836-(0.018*2))*1= sqmt 2.513 640.00 1608.50 (E)

Total (A+B+C+D+E) 20975.46Total without ED 18671.27

Add Water Charges @ 1% 1% 186.71Add CPOH @ 15% 15% 2828.70

Total cost per meter for pipe 21686.68Total cost per kg for specials 59.72

2.5.5.36

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =0.916 0.008

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.916-0.008)*0.008*1*7850= kg 179.141Add 5 % wastage

5% kg 8.957Total Weight kg 188.098

#REF! Cost of MS plate kg 188.098 45.00 8464.42 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 179.141 6.63 1187.71 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 8.957 27.00 241.84

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 4346.71 43.47 (C)

Material cost per meter Rs/meter 9453.75

900 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick plate, internally coated with food grade epoxy coating and external / outsideepoxy coating

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.916*1= sqmt 2.878 100.33 288.72 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.916-(0.008*2))*1= sqmt 2.827 640.00 1809.56 (E)

Total (A+B+C+D+E) 11552.03Total without ED 10286.04

Add Water Charges @ 1% 1% 102.86Add CPOH @ 15% 15% 1558.34

Total cost per meter for pipe 11947.24Total cost per kg for specials 66.69

2.5.5.37

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =0.9176 0.0088

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.9176-0.0088)*0.0088*1*7850= kg 197.229Add 5 % wastage

5% kg 9.861Total Weight kg 207.090

900 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick plate, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 355 Schedule of Rates 2014 - 2015

Page 222: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outside#REF! Cost of MS plate kg 207.090 45.00 9319.06 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 197.229 6.63 1307.63 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 9.861 27.00 266.26

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 4346.71 43.47 (C)

Material cost per meter Rs/meter 10403.90

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.9176*1= sqmt 2.883 100.33 289.22 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.9176-(0.0088*2))*1= sqmt 2.827 640.00 1809.56 (E)

Total (A+B+C+D+E) 12502.68Total without ED 11132.12

Add Water Charges @ 1% 1% 111.32Add CPOH @ 15% 15% 1686.52

Total cost per meter for pipe 12929.96Total cost per kg for specials 65.56

2.5.5.38

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =0.92 0.01

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.92-0.01)*0.01*1*7850= kg 224.420Add 5 % wastage

5% kg 11.221Total Weight kg 235.641

900 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick plate, internally coated with food grade epoxy coating and external /outside epoxy coating

#REF! Cost of MS plate kg 235.641 45.00 10603.83 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 224.420 6.63 1487.90 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 11.221 27.00 302.97

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 4346.71 43.47 (C)

Material cost per meter Rs/meter 11832.23

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.92*1= sqmt 2.890 100.33 289.98 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.92-(0.01*2))*1= sqmt 2.827 640.00 1809.56 (E)

Total (A+B+C+D+E) 13931.77Total without ED 12404.00

Add Water Charges @ 1% 1% 124.04Add CPOH @ 15% 15% 1879.21

Total cost per meter for pipe 14407.25Total cost per kg for specials 64.20

2.5.5.39

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

900 mm nominal dia (clear internal dia) of pipe with 17.5 mm thick plate, internally coated with food grade epoxy coating and external /outside epoxy coating

Delhi Jal Board 356 Schedule of Rates 2014 - 2015

Page 223: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outsideDetail for 1 meter

Outer dia (d) = thickness of pipe (t1) =

0.935 0.0175Length of pipe

=1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.935-0.0175)*0.0175*1*7850= kg 395.971Add 5 % wastage

5% kg 19.799Total Weight kg 415.770

#REF! Cost of MS plate kg 415.770 45.00 18709.64 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 395.971 6.63 2625.29 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 19.799 27.00 534.56

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 4346.71 43.47 (C)

Material cost per meter Rs/meter 20843.84

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.935*1= sqmt 2.937 100.33 294.71 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.935-(0.0175*2))*1= sqmt 2.827 640.00 1809.56 (E)

Total (A+B+C+D+E) 22948.10Total without ED 20428.51

Add Water Charges @ 1% 1% 204.29Add CPOH @ 15% 15% 3094.92

Total cost per meter for pipe 23727.71Total cost per kg for specials 59.92

2.5.5.40

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

1000 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick plate, internally coated with food grade epoxy coating and external /outside epoxy coating

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =1.0176 0.0088

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.0176-0.0088)*0.0088*1*7850= kg 218.931Add 5 % wastage

5% kg 10.947Total Weight kg 229.878

#REF! Cost of MS plate kg 229.878 45.00 10344.49 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 218.931 6.63 1451.51 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 10.947 27.00 295.56

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 11558.40

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.0176*1= sqmt 3.197 100.33 320.74 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.0176-(0.0088*2))*1= sqmt 3.142 640.00 2010.62 (E)

Delhi Jal Board 357 Schedule of Rates 2014 - 2015

Page 224: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outsideTotal (A+B+C+D+E) 13889.76Total without ED 12368.21

Add Water Charges @ 1% 1% 123.68Add CPOH @ 15% 15% 1873.78

Total cost per meter for pipe 14365.68Total cost per kg for specials 65.62

2.5.5.41

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =1.02 0.01

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.02-0.01)*0.01*1*7850= kg 249.081Add 5 % wastage

5% kg 12.454Total Weight kg 261.535

#REF! Cost of MS plate kg 261.535 45.00 11769.09 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 249.081 6.63 1651.41 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 12.454 27.00 336.26

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 13142.19

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.02*1= sqmt 3.204 100.33 321.50 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.02-(0.01*2))*1= sqmt 3.142 640.00 2010.62 (E)

1000 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick plate, internally coated with food grade epoxy coating and external /outside epoxy coating

Total (A+B+C+D+E) 15474.31Total without ED 13778.45

Add Water Charges @ 1% 1% 137.78Add CPOH @ 15% 15% 2087.44

Total cost per meter for pipe 16003.67Total cost per kg for specials 64.25

2.5.5.42

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =1.04 0.02

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.04-0.02)*0.02*1*7850= kg 503.095Add 5 % wastage

5% kg 25.155Total Weight kg 528.249

#REF! Cost of MS plate kg 528.249 45.00 23771.22 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 503.095 6.63 3335.52 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 25.155 27.00 679.18

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

1000 mm nominal dia (clear internal dia) of pipe with 20.0 mm thick plate, internally coated with food grade epoxy coating and external /outside epoxy coating

Delhi Jal Board 358 Schedule of Rates 2014 - 2015

Page 225: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outsideMaterial cost per meter Rs/meter 26485.52

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.04*1= sqmt 3.267 100.33 327.80 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.04-(0.02*2))*1= sqmt 3.142 640.00 2010.62 (E)

Total (A+B+C+D+E) 28823.94Total without ED 25659.58

Add Water Charges @ 1% 1% 256.60Add CPOH @ 15% 15% 3887.43

Total cost per meter for pipe 29803.60Total cost per kg for specials 59.24

2.5.5.43

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =1.0676 0.0088

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.0676-0.0088)*0.0088*1*7850= kg 229.782Add 5 % wastage

5% kg 11.489Total Weight kg 241.271

#REF! Cost of MS plate kg 241.271 45.00 10857.20 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 229.782 6.63 1523.46 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 11.489 27.00 310.21

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

1050 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick plate, internally coated with food grade epoxy coating and external /outside epoxy coating

no 20Material cost per meter Rs/meter 12128.41

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.0676*1= sqmt 3.354 100.33 336.50 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.0676-(0.0088*2))*1= sqmt 3.299 640.00 2111.15 (E)

Total (A+B+C+D+E) 14576.06Total without ED 12979.02

Add Water Charges @ 1% 1% 129.79Add CPOH @ 15% 15% 1966.32

Total cost per meter for pipe 15075.13Total cost per kg for specials 65.61

2.5.5.44

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =1.07 0.01

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.07-0.01)*0.01*1*7850= kg 261.412

1050 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick plate, internally coated with food grade epoxy coating and external /outside epoxy coating

Delhi Jal Board 359 Schedule of Rates 2014 - 2015

Page 226: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outsideAdd 5 % wastage

Delhi Jal Board 360 Schedule of Rates 2014 - 2015

Page 227: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outside5% kg 13.071Total Weight kg 274.483

#REF! Cost of MS plate kg 274.483 45.00 12351.71 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 261.412 6.63 1733.16 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 13.071 27.00 352.91

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 13789.92

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.07*1= sqmt 3.362 100.33 337.26 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.07-(0.01*2))*1= sqmt 3.299 640.00 2111.15 (E)

Total (A+B+C+D+E) 16238.33Total without ED 14458.43

Add Water Charges @ 1% 1% 144.58Add CPOH @ 15% 15% 2190.45

Total cost per meter for pipe 16793.47Total cost per kg for specials 64.24

2.5.5.45

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =1.072 0.011

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.072-0.011)*0.011*1*7850= kg 287.824Add 5 % wastage

1050 mm nominal dia (clear internal dia) of pipe with 11.0 mm thick plate, internally coated with food grade epoxy coating and external /outside epoxy coating

Add 5 % wastage5% kg 14.391

Total Weight kg 302.216

#REF! Cost of MS plate kg 302.216 45.00 13599.70 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 287.824 6.63 1908.28 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 14.391 27.00 388.56

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 15177.37

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.072*1= sqmt 3.368 100.33 337.89 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.072-(0.011*2))*1= sqmt 3.299 640.00 2111.15 (E)

Total (A+B+C+D+E) 17626.41Total without ED 15693.82

Add Water Charges @ 1% 1% 156.94Add CPOH @ 15% 15% 2377.61

Total cost per meter for pipe 18228.37Total cost per kg for specials 63.33

2.5.5.46 1100 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick plate, internally coated with food grade epoxy coating and external /outside epoxy coating

Delhi Jal Board 361 Schedule of Rates 2014 - 2015

Page 228: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outsideITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT

(INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =1.1176 0.0088

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.1176-0.0088)*0.0088*1*7850= kg 240.633Add 5 % wastage

5% kg 12.032Total Weight kg 252.665

#REF! Cost of MS plate kg 252.665 45.00 11369.92 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 240.633 6.63 1595.40 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 12.032 27.00 324.85

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 12698.41

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.1176*1= sqmt 3.511 100.33 352.26 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.1176-(0.0088*2))*1= sqmt 3.456 640.00 2211.68 (E)

Total (A+B+C+D+E) 15262.36Total without ED 13589.82

Add Water Charges @ 1% 1% 135.90Add CPOH @ 15% 15% 2058.86

Total cost per meter for pipe 15784.57Total cost per kg for specials 65.60

2.5.5.47 1100 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick plate, internally coated with food grade epoxy coating and external /outside epoxy coating

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =1.12 0.01

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.12-0.01)*0.01*1*7850= kg 273.743Add 5 % wastage

5% kg 13.687Total Weight kg 287.430

#REF! Cost of MS plate kg 287.430 45.00 12934.34 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 273.743 6.63 1814.91 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 13.687 27.00 369.55

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 14437.66

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.12*1= sqmt 3.519 100.33 353.02 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.12-(0.01*2))*1= sqmt 3.456 640.00 2211.68 (E)

Delhi Jal Board 362 Schedule of Rates 2014 - 2015

Page 229: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outside

Total (A+B+C+D+E) 17002.36Total without ED 15138.41

Add Water Charges @ 1% 1% 151.38Add CPOH @ 15% 15% 2293.47

Total cost per meter for pipe 17583.27Total cost per kg for specials 64.23

2.5.5.48

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =1.122 0.011

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.122-0.011)*0.011*1*7850= kg 301.388Add 5 % wastage

5% kg 15.069Total Weight kg 316.458

#REF! Cost of MS plate kg 316.458 45.00 14240.59 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 301.388 6.63 1998.20 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 15.069 27.00 406.87

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 15889.88

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.122*1= sqmt 3.525 100.33 353.65 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.122-(0.011*2))*1= sqmt 3.456 640.00 2211.68 (E)

1100 mm nominal dia (clear internal dia) of pipe with 11.0 mm thick plate, internally coated with food grade epoxy coating and external /outside epoxy coating

Total (A+B+C+D+E) 18455.21Total without ED 16431.44

Add Water Charges @ 1% 1% 164.31Add CPOH @ 15% 15% 2489.36

Total cost per meter for pipe 19085.12Total cost per kg for specials 63.32

2.5.5.49

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =1.22 0.01

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.22-0.01)*0.01*1*7850= kg 298.404Add 5 % wastage

5% kg 14.920Total Weight kg 313.324

#REF! Cost of MS plate kg 313.324 45.00 14099.60 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 298.404 6.63 1978.42 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 14.920 27.00 402.85

1200 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick plate, internally coated with food grade epoxy coating and external /outside epoxy coating

Delhi Jal Board 363 Schedule of Rates 2014 - 2015

Page 230: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outsidePlease refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 15733.13

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.22*1= sqmt 3.833 100.33 384.54 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.22-(0.01*2))*1= sqmt 3.770 640.00 2412.74 (E)

Total (A+B+C+D+E) 18530.41Total without ED 16498.37

Add Water Charges @ 1% 1% 164.98Add CPOH @ 15% 15% 2499.50

Total cost per meter for pipe 19162.86Total cost per kg for specials 64.22

2.5.5.50

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =1.222 0.011

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.222-0.011)*0.011*1*7850= kg 328.516Add 5 % wastage

5% kg 16.426Total Weight kg 344.942

#REF! Cost of MS plate kg 344.942 45.00 15522.37 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 328.516 6.63 2178.06 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 16.426 27.00 443.50

1200 mm nominal dia (clear internal dia) of pipe with 11.0 mm thick plate, internally coated with food grade epoxy coating and external /outside epoxy coating

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 17314.89

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.222*1= sqmt 3.839 100.33 385.17 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.222-(0.011*2))*1= sqmt 3.770 640.00 2412.74 (E)

Total (A+B+C+D+E) 20112.80Total without ED 17906.70

Add Water Charges @ 1% 1% 179.07Add CPOH @ 15% 15% 2712.86

Total cost per meter for pipe 20798.63Total cost per kg for specials 63.31

2.5.5.51

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =1.224 0.012

Length of pipe =

1.0

1200 mm nominal dia (clear internal dia) of pipe with 12.0 mm thick plate, internally coated with food grade epoxy coating and external /outside epoxy coating

Delhi Jal Board 364 Schedule of Rates 2014 - 2015

Page 231: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outsideWeight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.224-0.012)*0.012*1*7850= kg 358.677Add 5 % wastage

5% kg 17.934Total Weight kg 376.611

#REF! Cost of MS plate kg 376.611 45.00 16947.48 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 358.677 6.63 2378.03 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 17.934 27.00 484.21

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 18899.25

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.224*1= sqmt 3.845 100.33 385.80 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.224-(0.012*2))*1= sqmt 3.770 640.00 2412.74 (E)

Total (A+B+C+D+E) 21697.79Total without ED 19317.33

Add Water Charges @ 1% 1% 193.17Add CPOH @ 15% 15% 2926.58

Total cost per meter for pipe 22437.08Total cost per kg for specials 62.56

2.5.5.52

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =1.225 0.0125

Length of pipe =

1.0

1200 mm nominal dia (clear internal dia) of pipe with 12.5 mm thick plate, internally coated with food grade epoxy coating and external /outside epoxy coating

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.225-0.0125)*0.0125*1*7850= kg 373.776Add 5 % wastage

5% kg 18.689Total Weight kg 392.465

#REF! Cost of MS plate kg 392.465 45.00 17660.91 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 373.776 6.63 2478.13 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 18.689 27.00 504.60

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 19692.40

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.225*1= sqmt 3.848 100.33 386.11 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.225-(0.0125*2))*1= sqmt 3.770 640.00 2412.74 (E)

Total (A+B+C+D+E) 22491.26Total without ED 20023.52

Add Water Charges @ 1% 1% 200.24Add CPOH @ 15% 15% 3033.56

Total cost per meter for pipe 23257.31Total cost per kg for specials 62.22

Delhi Jal Board 365 Schedule of Rates 2014 - 2015

Page 232: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outside2.5.5.53

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =1.424 0.012

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.424-0.012)*0.012*1*7850= kg 417.864Add 5 % wastage

5% kg 20.893Total Weight kg 438.758

#REF! Cost of MS plate kg 438.758 45.00 19744.10 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 417.864 6.63 2770.44 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 20.893 27.00 564.12

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 7244.52 72.45 (C)

Material cost per meter Rs/meter 22022.87

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.424*1= sqmt 4.474 100.33 448.83 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.424-(0.012*2))*1= sqmt 4.398 640.00 2814.87 (E)

Total (A+B+C+D+E) 25286.57Total without ED 22512.93

Add Water Charges @ 1% 1% 225.13Add CPOH @ 15% 15% 3410.71

Total cost per meter for pipe 26148.76Total cost per kg for specials 62.58

1400 mm nominal dia (clear internal dia) of pipe with 12 mm thick plate, internally coated with food grade epoxy coating and external / outsideepoxy coating

2.5.5.54

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =1.425 0.0125

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.425-0.0125)*0.0125*1*7850= kg 435.430Add 5 % wastage

5% kg 21.771Total Weight kg 457.201

#REF! Cost of MS plate kg 457.201 45.00 20574.05 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 435.430 6.63 2886.90 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 21.771 27.00 587.83

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 7244.52 72.45 (C)

Material cost per meter Rs/meter 22945.56

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.425*1= sqmt 4.477 100.33 449.15 (D)

1400 mm nominal dia (clear internal dia) of pipe with 12.5 mm thick plate, internally coated with food grade epoxy coating and external /outside epoxy coating

Delhi Jal Board 366 Schedule of Rates 2014 - 2015

Page 233: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outsideQuotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.425-(0.0125*2))*1= sqmt 4.398 640.00 2814.87 (E)

Total (A+B+C+D+E) 26209.58Total without ED 23334.40

Add Water Charges @ 1% 1% 233.34Add CPOH @ 15% 15% 3535.16

Total cost per meter for pipe 27102.91Total cost per kg for specials 62.24

2.5.5.55

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =1.4284 0.0142

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.4284-0.0142)*0.0142*1*7850= kg 495.243Add 5 % wastage

5% kg 24.762Total Weight kg 520.006

#REF! Cost of MS plate kg 520.006 45.00 23400.25 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 495.243 6.63 3283.46 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 24.762 27.00 668.58

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 7244.52 72.45 (C)

Material cost per meter Rs/meter 26087.58

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.4284*1= sqmt 4.487 100.33 450.22 (D)

1400 mm nominal dia (clear internal dia) of pipe with 14.2 mm thick plate, internally coated with food grade epoxy coating and external /outside epoxy coating

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.4284-(0.0142*2))*1= sqmt 4.398 640.00 2814.87 (E)

Total (A+B+C+D+E) 29352.67Total without ED 26131.74

Add Water Charges @ 1% 1% 261.32Add CPOH @ 15% 15% 3958.96

Total cost per meter for pipe 30352.02Total cost per kg for specials 61.29

2.5.5.56

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =1.524 0.012

Length of pipe =

1500 mm nominal dia (clear internal dia) of pipe with 12 mm thick plate, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 367 Schedule of Rates 2014 - 2015

Page 234: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outside1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.524-0.012)*0.012*1*7850= kg 447.458Add 5 % wastage

5% kg 22.373Total Weight kg 469.831

#REF! Cost of MS plate kg 469.831 45.00 21142.40 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 447.458 6.63 2966.65 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 22.373 27.00 604.07

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 8693.42 86.93 (C)

Material cost per meter Rs/meter 23591.92

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.524*1= sqmt 4.788 100.33 480.35 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.524-(0.012*2))*1= sqmt 4.712 640.00 3015.93 (E)

Total (A+B+C+D+E) 27088.20Total without ED 24117.97

Add Water Charges @ 1% 1% 241.18Add CPOH @ 15% 15% 3653.87

Total cost per meter for pipe 28013.02Total cost per kg for specials 62.60

2.5.5.57

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =1.6284 0.0142

Length of pipe =

1600 mm nominal dia (clear internal dia) of pipe with 14.2 mm thick plate, internally coated with food grade epoxy coating and external /outside epoxy coating

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.6284-0.0142)*0.0142*1*7850= kg 565.282Add 5 % wastage

5% kg 28.264Total Weight kg 593.546

#REF! Cost of MS plate kg 593.546 45.00 26709.58 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 565.282 6.63 3747.82 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 28.264 27.00 763.13

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 8693.42 86.93 (C)

Material cost per meter Rs/meter 29781.20

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.6284*1= sqmt 5.116 100.33 513.26 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.6284-(0.0142*2))*1= sqmt 5.027 640.00 3216.99 (E)

Total (A+B+C+D+E) 33511.45Total without ED 29834.64

Add Water Charges @ 1% 1% 298.35Add CPOH @ 15% 15% 4519.95

Total cost per meter for pipe 34652.93

Delhi Jal Board 368 Schedule of Rates 2014 - 2015

Page 235: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outsideTotal cost per kg for specials 61.30

2.5.5.58

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =1.632 0.016

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.632-0.016)*0.016*1*7850= kg 637.648Add 5 % wastage

5% kg 31.882Total Weight kg 669.530

#REF! Cost of MS plate kg 669.530 45.00 30128.86 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 637.648 6.63 4227.60 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 31.882 27.00 860.82

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 8693.42 86.93 (C)

Material cost per meter Rs/meter 33582.57

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.632*1= sqmt 5.127 100.33 514.39 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.632-(0.016*2))*1= sqmt 5.027 640.00 3216.99 (E)

Total (A+B+C+D+E) 37313.96Total without ED 33218.85

Add Water Charges @ 1% 1% 332.19Add CPOH @ 15% 15% 5032.66

Total cost per meter for pipe 38583.70

1600 mm nominal dia (clear internal dia) of pipe with 16.0 mm thick plate, internally coated with food grade epoxy coating and external /outside epoxy coating

Total cost per kg for specials 60.51

2.5.5.59

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =1.8284 0.0142

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.8284-0.0142)*0.0142*1*7850= kg 635.321Add 5 % wastage

5% kg 31.766Total Weight kg 667.087

#REF! Cost of MS plate kg 667.087 45.00 30018.91 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 635.321 6.63 4212.18 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 31.766 27.00 857.68

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 10142.33 101.42 (C)

Material cost per meter Rs/meter 33474.82

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

1800 mm nominal dia (clear internal dia) of pipe with 14.2 mm thick plate, internally coated with food grade epoxy coating and external /outside epoxy coating

Delhi Jal Board 369 Schedule of Rates 2014 - 2015

Page 236: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outside(3.1416)*1.8284*1= sqmt 5.744 100.33 576.30 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.8284-(0.0142*2))*1= sqmt 5.655 640.00 3619.11 (E)

Total (A+B+C+D+E) 37670.24Total without ED 33537.53

Add Water Charges @ 1% 1% 335.38Add CPOH @ 15% 15% 5080.94

Total cost per meter for pipe 38953.84Total cost per kg for specials 61.31

2.5.5.60

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =1.832 0.016

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.832-0.016)*0.016*1*7850= kg 716.565Add 5 % wastage

5% kg 35.828Total Weight kg 752.393

#REF! Cost of MS plate kg 752.393 45.00 33857.68 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 716.565 6.63 4750.82 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 35.828 27.00 967.36

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 10142.33 101.42 (C)

Material cost per meter Rs/meter 37742.56

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

1800 mm nominal dia (clear internal dia) of pipe with 16.0 mm thick plate, internally coated with food grade epoxy coating and external /outside epoxy coating

(3.1416)*1.832*1= sqmt 5.755 100.33 577.43 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.832-(0.016*2))*1= sqmt 5.655 640.00 3619.11 (E)

Total (A+B+C+D+E) 41939.11Total without ED 37336.82

Add Water Charges @ 1% 1% 373.37Add CPOH @ 15% 15% 5656.53

Total cost per meter for pipe 43366.71Total cost per kg for specials 60.52

2.5.5.61

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =1.835 0.0175

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.835-0.0175)*0.0175*1*7850= kg 784.390Add 5 % wastage

5% kg 39.219Total Weight kg 823.609

#REF! Cost of MS plate kg 823.609 45.00 37062.42 (A)

1800 mm nominal dia (clear internal dia) of pipe with 17.5 mm thick plate, internally coated with food grade epoxy coating and external /outside epoxy coating

Delhi Jal Board 370 Schedule of Rates 2014 - 2015

Page 237: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outsideQuotation_Volume III_pg no_320 Cost of Fabrication kg 784.390 6.63 5200.51 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 39.219 27.00 1058.93

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 10142.33 101.42 (C)

Material cost per meter Rs/meter 41305.43

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.835*1= sqmt 5.765 100.33 578.38 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.835-(0.0175*2))*1= sqmt 5.655 640.00 3619.11 (E)

Total (A+B+C+D+E) 45502.92Total without ED 40508.59

Add Water Charges @ 1% 1% 405.09Add CPOH @ 15% 15% 6137.05

Total cost per meter for pipe 47050.73Total cost per kg for specials 59.98

2.5.5.62

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =2.032 0.016

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(2.032-0.016)*0.016*1*7850= kg 795.481Add 5 % wastage

5% kg 39.774Total Weight kg 835.255

#REF! Cost of MS plate kg 835.255 45.00 37586.50 (A)

2000 mm nominal dia (clear internal dia) of pipe with 16.0 mm thick plate, internally coated with food grade epoxy coating and external /outside epoxy coating

Quotation_Volume III_pg no_320 Cost of Fabrication kg 795.481 6.63 5274.04 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 39.774 27.00 1073.90

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 11591.23 115.91 (C)

Material cost per meter Rs/meter 41902.55

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*2.032*1= sqmt 6.384 100.33 640.47 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(2.032-(0.016*2))*1= sqmt 6.283 640.00 4021.24 (E)

Total (A+B+C+D+E) 46564.26Total without ED 41454.78

Add Water Charges @ 1% 1% 414.55Add CPOH @ 15% 15% 6280.40

Total cost per meter for pipe 48149.72Total cost per kg for specials 60.53

2.5.5.63

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =2.035 0.0175

2000 mm nominal dia (clear internal dia) of pipe with 17.5 mm thick plate, internally coated with food grade epoxy coating and external /outside epoxy coating

Delhi Jal Board 371 Schedule of Rates 2014 - 2015

Page 238: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outsideLength of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(2.035-0.0175)*0.0175*1*7850= kg 870.705Add 5 % wastage

5% kg 43.535Total Weight kg 914.240

#REF! Cost of MS plate kg 914.240 45.00 41140.82 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 870.705 6.63 5772.78 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 43.535 27.00 1175.45

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 11591.23 115.91 (C)

Material cost per meter Rs/meter 45854.05

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*2.035*1= sqmt 6.393 100.33 641.42 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(2.035-(0.0175*2))*1= sqmt 6.283 640.00 4021.24 (E)

Total (A+B+C+D+E) 50516.71Total without ED 44972.44

Add Water Charges @ 1% 1% 449.72Add CPOH @ 15% 15% 6813.33

Total cost per meter for pipe 52235.49Total cost per kg for specials 59.99

2.5.5.64

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =2.04 0.02

2000 mm nominal dia (clear internal dia) of pipe with 20.0 mm thick plate, internally coated with food grade epoxy coating and external /outside epoxy coating

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(2.04-0.02)*0.02*1*7850= kg 996.325Add 5 % wastage

5% kg 49.816Total Weight kg 1046.141

#REF! Cost of MS plate kg 1046.141 45.00 47076.34 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 996.325 6.63 6605.63 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 49.816 27.00 1345.04

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 11591.23 115.91 (C)

Material cost per meter Rs/meter 52452.85

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*2.04*1= sqmt 6.409 100.33 642.99 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(2.04-(0.02*2))*1= sqmt 6.283 640.00 4021.24 (E)

Total (A+B+C+D+E) 57117.08Total without ED 50846.75

Add Water Charges @ 1% 1% 508.47

Delhi Jal Board 372 Schedule of Rates 2014 - 2015

Page 239: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outsideAdd CPOH @ 15% 15% 7703.28Total cost per meter for pipe 59058.50

Total cost per kg for specials 59.28

2.5.5.65

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =2.235 0.0175

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(2.235-0.0175)*0.0175*1*7850= kg 957.020Add 5 % wastage

5% kg 47.851Total Weight kg 1004.871

#REF! Cost of MS plate kg 1004.871 45.00 45219.22 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 957.020 6.63 6345.05 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 47.851 27.00 1291.98

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 13040.13 130.40 (C)

Material cost per meter Rs/meter 50402.68

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*2.235*1= sqmt 7.021 100.33 704.46 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(2.235-(0.0175*2))*1= sqmt 6.912 640.00 4423.36 (E)

Total (A+B+C+D+E) 55530.50Total without ED 49436.29

Add Water Charges @ 1% 1% 494.36

2200 mm nominal dia (clear internal dia) of pipe with 17.5 mm thick plate, internally coated with food grade epoxy coating and external /outside epoxy coating

Add Water Charges @ 1% 1% 494.36Add CPOH @ 15% 15% 7489.60

Total cost per meter for pipe 57420.26Total cost per kg for specials 60.00

2.5.5.66

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =2.24 0.02

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(2.24-0.02)*0.02*1*7850= kg 1094.971Add 5 % wastage

5% kg 54.749Total Weight kg 1149.719

#REF! Cost of MS plate kg 1149.719 45.00 51737.37 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 1094.971 6.63 7259.66 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 54.749 27.00 1478.21

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 13040.13 130.40 (C)

Material cost per meter Rs/meter 57649.21

2200 mm nominal dia (clear internal dia) of pipe with 20.0 mm thick plate, internally coated with food grade epoxy coating and external /outside epoxy coating

Delhi Jal Board 373 Schedule of Rates 2014 - 2015

Page 240: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outsideOutside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*2.24*1= sqmt 7.037 100.33 706.03 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(2.24-(0.02*2))*1= sqmt 6.912 640.00 4423.36 (E)

Total (A+B+C+D+E) 62778.61Total without ED 55887.08

Add Water Charges @ 1% 1% 558.87Add CPOH @ 15% 15% 8466.89

Total cost per meter for pipe 64912.84Total cost per kg for specials 59.28

2.5.5.67

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =2.2444 0.0222

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(2.2444-0.0222)*0.0222*1*7850= kg 1216.622Add 5 % wastage

5% kg 60.831Total Weight kg 1277.453

#REF! Cost of MS plate kg 1277.453 45.00 57485.39 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 1216.622 6.63 8066.20 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 60.831 27.00 1642.44

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 13040.13 130.40 (C)

Material cost per meter Rs/meter 64039.55

2200 mm nominal dia (clear internal dia) of pipe with 22.2 mm thick plate, internally coated with food grade epoxy coating and external /outside epoxy coating

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*2.2444*1= sqmt 7.051 100.33 707.42 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(2.2444-(0.0222*2))*1= sqmt 6.912 640.00 4423.36 (E)

Total (A+B+C+D+E) 69170.33Total without ED 61575.70

Add Water Charges @ 1% 1% 615.76Add CPOH @ 15% 15% 9328.72

Total cost per meter for pipe 71520.17Total cost per kg for specials 58.79

2.5.5.68

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =2.54 0.02

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(2.54-0.02)*0.02*1*7850= kg 1242.940Add 5 % wastage

5% kg 62.147Total Weight kg 1305.087

2500 mm nominal dia (clear internal dia) of pipe with 20.0 mm thick plate, internally coated with food grade epoxy coating and external /outside epoxy coating

Delhi Jal Board 374 Schedule of Rates 2014 - 2015

Page 241: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outside#REF! Cost of MS plate kg 1305.087 45.00 58728.90 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 1242.940 6.63 8240.69 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 62.147 27.00 1677.97

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 14489.04 144.89 (C)

Material cost per meter Rs/meter 65436.51

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*2.54*1= sqmt 7.980 100.33 800.59 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(2.54-(0.02*2))*1= sqmt 7.854 640.00 5026.55 (E)

Total (A+B+C+D+E) 71263.65Total without ED 63440.33

Add Water Charges @ 1% 1% 634.40Add CPOH @ 15% 15% 9611.21

Total cost per meter for pipe 73685.95Total cost per kg for specials 59.28

2.5.5.69

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meterOuter dia (d) = thickness of

pipe (t1) =2.5444 0.0222

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(2.5444-0.0222)*0.0222*1*7850= kg 1380.868Add 5 % wastage

5% kg 69.043Total Weight kg 1449.911

2500 mm nominal dia (clear internal dia) of pipe with 22.2 mm thick plate, internally coated with food grade epoxy coating and external /outside epoxy coating

#REF! Cost of MS plate kg 1449.911 45.00 65245.99 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 1380.868 6.63 9155.15 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 69.043 27.00 1864.17

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 14489.04 144.89 (C)

Material cost per meter Rs/meter 72681.86

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*2.5444*1= sqmt 7.993 100.33 801.98 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(2.5444-(0.0222*2))*1= sqmt 7.854 640.00 5026.55 (E)

Total (A+B+C+D+E) 78510.39Total without ED 69889.90

Add Water Charges @ 1% 1% 698.90Add CPOH @ 15% 15% 10588.32

Total cost per meter for pipe 81177.12Total cost per kg for specials 58.79

2.5.5.70

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

2500 mm nominal dia (clear internal dia) of pipe with 25.0 mm thick plate, internally coated with food grade epoxy coating and external /outside epoxy coating

Delhi Jal Board 375 Schedule of Rates 2014 - 2015

Page 242: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outsideDetail for 1 meter

Outer dia (d) = thickness of pipe (t1) =

2.55 0.025Length of pipe

=1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(2.55-0.025)*0.025*1*7850= kg 1556.757Add 5 % wastage

5% kg 77.838Total Weight kg 1634.595

#REF! Cost of MS plate kg 1634.595 45.00 73556.78 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 1556.757 6.63 10321.30 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 77.838 27.00 2101.62

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 14489.04 144.89 (C)

Material cost per meter Rs/meter 81921.35

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*2.55*1= sqmt 8.011 100.33 803.74 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(2.55-(0.025*2))*1= sqmt 7.854 640.00 5026.55 (E)

Total (A+B+C+D+E) 87751.64Total without ED 78114.59

Add Water Charges @ 1% 1% 781.15Add CPOH @ 15% 15% 11834.36

Total cost per meter for pipe 90730.09Total cost per kg for specials 58.28

Delhi Jal Board 376 Schedule of Rates 2014 - 2015

Page 243: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

2.5.6

2.5.6.1

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.16 0.005 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.16-0.005)*0.005*1*7850= kg 19.113Add 2 % wastage

2% kg 0.382Total Weight kg 19.495

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 19.495 34.21 666.93 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 19.113 6.63 126.72 (B)

Quotation_Volume III_pg no_272 Cost of scrap kg 0.382 27.00 10.32

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 289.78 2.90 (C)

Material cost per meter Rs/meter 786.22

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.16*1= sqmt 0.503 100.33 50.43 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.16-(0.005*2))*1= sqmt 0.471 640.00 301.59 (E)

Total (A+B+C+D+E) 1138.24Total without ED 1013.35

Add Water Charges @ 1% 1% 10.13Add CPOH @ 15% 15% 153.52

Total cost per meter for pipe 1177.01Total cost per kg for specials 61.58

2.5.6.2

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.21 0.005 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.21-0.005)*0.005*1*7850= kg 25.278Add 2 % wastage

2% kg 0.506Total Weight kg 25.784

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 25.784 34.21 882.06 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 25.278 6.63 167.59 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.506 27.00 13.65

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 471.38 4.71 (C)

Material cost per meter Rs/meter 1040.72

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.21*1= sqmt 0.660 100.33 66.19 (D)

Providing Mild Steel Pipes / specials fabricated / manufactured out of MS coil of steel grade Fe410 as per IS 3589:2001; internally coated with foodgrade epoxy coating and external / outside epoxy coating; minimum thickness of M.S. Coil as specified; complete in all respect; with upto dateamendments in relevant IS codes and as directed by Engineer-in-charge . The rates are excluding excise duty component.

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxycoating

200 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxycoating

Delhi Jal Board 393 Schedule of Rates 2014 - 2015

Page 244: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxyQuotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.21-(0.005*2))*1= sqmt 0.628 640.00 402.12 (E)

Total (A+B+C+D+E) 1509.03Total without ED 1343.55

Add Water Charges @ 1% 1% 13.44Add CPOH @ 15% 15% 203.55

Total cost per meter for pipe 1560.54Total cost per kg for specials 61.74

2.5.6.3

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.212 0.006 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.212-0.006)*0.006*1*7850= kg 30.482Add 2 % wastage

2% kg 0.610Total Weight kg 31.091

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 31.091 34.21 1063.64 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 30.482 6.63 202.09 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.610 27.00 16.46

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 471.38 4.71 (C)

Material cost per meter Rs/meter 1253.99

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.212*1= sqmt 0.666 100.33 66.82 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.212-(0.006*2))*1= sqmt 0.628 640.00 402.12 (E)

Total (A+B+C+D+E) 1722.93Total without ED 1533.92

Add Water Charges @ 1% 1% 15.34Add CPOH @ 15% 15% 232.39

Total cost per meter for pipe 1781.65Total cost per kg for specials 58.45

2.5.6.4

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.2126 0.0063

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.2126-0.0063)*0.0063*1*7850= kg 32.052Add 2 % wastage

2% kg 0.641Total Weight kg 32.693

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 32.693 34.21 1118.45 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 32.052 6.63 212.51 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.641 27.00 17.31

200 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

200 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 394 Schedule of Rates 2014 - 2015

Page 245: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxyPlease refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 471.38 4.71 (C)

Material cost per meter Rs/meter 1318.36

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.2126*1= sqmt 0.668 100.33 67.01 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.2126-(0.0063*2))*1= sqmt 0.628 640.00 402.12 (E)

Total (A+B+C+D+E) 1787.49Total without ED 1591.38

Add Water Charges @ 1% 1% 15.91Add CPOH @ 15% 15% 241.09

Total cost per meter for pipe 1848.39Total cost per kg for specials 57.67

2.5.6.5

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.26 0.005 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.26-0.005)*0.005*1*7850= kg 31.443Add 2 % wastage

2% kg 0.629Total Weight kg 32.072

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 32.072 34.21 1097.20 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 31.443 6.63 208.47 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.629 27.00 16.98

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 669.85 6.70 (C)

Material cost per meter Rs/meter 1295.39

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.26*1= sqmt 0.817 100.33 81.95 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.26-(0.005*2))*1= sqmt 0.785 640.00 502.65 (E)

Total (A+B+C+D+E) 1879.99Total without ED 1673.93

Add Water Charges @ 1% 1% 16.74Add CPOH @ 15% 15% 253.60

Total cost per meter for pipe 1944.26Total cost per kg for specials 61.83

2.5.6.6

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.262 0.006 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.262-0.006)*0.006*1*7850= kg 37.880Add 2 % wastage

250 mm nominal dia (clear internal dia) of pipe with 5.0 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

250 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 395 Schedule of Rates 2014 - 2015

Page 246: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxy2% kg 0.758Total Weight kg 38.638

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 38.638 34.21 1321.80 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 37.880 6.63 251.14 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.758 27.00 20.46

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 669.85 6.70 (C)

Material cost per meter Rs/meter 1559.19

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.262*1= sqmt 0.823 100.33 82.58 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.262-(0.006*2))*1= sqmt 0.785 640.00 502.65 (E)

Total (A+B+C+D+E) 2144.43Total without ED 1909.27

Add Water Charges @ 1% 1% 19.09Add CPOH @ 15% 15% 289.25

Total cost per meter for pipe 2217.62Total cost per kg for specials 58.54

2.5.6.7

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.2626 0.0063

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.2626-0.0063)*0.0063*1*7850= kg 39.821Add 2 % wastage

2% kg 0.796Total Weight kg 40.617

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 40.617 34.21 1389.52 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 39.821 6.63 264.01 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.796 27.00 21.50

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 669.85 6.70 (C)

Material cost per meter Rs/meter 1638.73

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.2626*1= sqmt 0.825 100.33 82.77 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.2626-(0.0063*2))*1= sqmt 0.785 640.00 502.65 (E)

Total (A+B+C+D+E) 2224.15Total without ED 1980.22

Add Water Charges @ 1% 1% 19.80Add CPOH @ 15% 15% 300.00

Total cost per meter for pipe 2300.03Total cost per kg for specials 57.76

2.5.6.8

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

300 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxycoating

250 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 396 Schedule of Rates 2014 - 2015

Page 247: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxyDetail for 1 meter Outer dia (d) =

thickness of pipe (t1) =

0.31 0.005 0.000Length of pipe

=1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.31-0.005)*0.005*1*7850= kg 37.609Add 2 % wastage

2% kg 0.752Total Weight kg 38.361

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 38.361 34.21 1312.34 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 37.609 6.63 249.35 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.752 27.00 20.31

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 827.95 8.28 (C)

Material cost per meter Rs/meter 1549.66

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.31*1= sqmt 0.974 100.33 97.71 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.31-(0.005*2))*1= sqmt 0.942 640.00 603.19 (E)

Total (A+B+C+D+E) 2250.55Total without ED 2003.89

Add Water Charges @ 1% 1% 20.04Add CPOH @ 15% 15% 303.59

Total cost per meter for pipe 2327.52Total cost per kg for specials 61.89

2.5.6.9

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.3112 0.0056 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.3112-0.0056)*0.0056*1*7850= kg 42.205Add 2 % wastage

2% kg 0.844Total Weight kg 43.049

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 43.049 34.21 1472.71 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 42.205 6.63 279.82 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.844 27.00 22.79

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 827.95 8.28 (C)

Material cost per meter Rs/meter 1738.02

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.3112*1= sqmt 0.978 100.33 98.09 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.3112-(0.0056*2))*1= sqmt 0.942 640.00 603.19 (E)

Total (A+B+C+D+E) 2439.29Total without ED 2171.87

300 mm nominal dia (clear internal dia) of pipe with 5.6 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 397 Schedule of Rates 2014 - 2015

Page 248: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxyAdd Water Charges @ 1% 1% 21.72Add CPOH @ 15% 15% 329.04

Total cost per meter for pipe 2522.63Total cost per kg for specials 59.77

2.5.6.10

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.3142 0.0071 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.3142-0.0071)*0.0071*1*7850= kg 53.772Add 2 % wastage

2% kg 1.075Total Weight kg 54.848

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 54.848 34.21 1876.35 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 53.772 6.63 356.51 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.075 27.00 29.04

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 827.95 8.28 (C)

Material cost per meter Rs/meter 2212.10

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.3142*1= sqmt 0.987 100.33 99.03 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.3142-(0.0071*2))*1= sqmt 0.942 640.00 603.19 (E)

Total (A+B+C+D+E) 2914.32Total without ED 2594.65

Add Water Charges @ 1% 1% 25.95Add CPOH @ 15% 15% 393.09

Total cost per meter for pipe 3013.68Total cost per kg for specials 56.05

2.5.6.11

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.36 0.005 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.36-0.005)*0.005*1*7850= kg 43.774Add 2 % wastage

2% kg 0.875Total Weight kg 44.650

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 44.650 34.21 1527.48 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 43.774 6.63 290.22 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.875 27.00 23.64

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1159.12 11.59 (C)

Material cost per meter Rs/meter 1805.65

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

350 mm nominal dia (clear internal dia) of pipe with 5.0 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

300 mm nominal dia (clear internal dia) of pipe with 7.1 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 398 Schedule of Rates 2014 - 2015

Page 249: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxy(3.1416)*0.36*1= sqmt 1.131 100.33 113.47 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.36-(0.005*2))*1= sqmt 1.100 640.00 703.72 (E)

Total (A+B+C+D+E) 2622.84Total without ED 2335.59

Add Water Charges @ 1% 1% 23.36Add CPOH @ 15% 15% 353.84

Total cost per meter for pipe 2712.79Total cost per kg for specials 61.97

2.5.6.12

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.3612 0.0056 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.3612-0.0056)*0.0056*1*7850= kg 49.110Add 2 % wastage

2% kg 0.982Total Weight kg 50.092

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 50.092 34.21 1713.66 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 49.110 6.63 325.60 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.982 27.00 26.52

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1159.12 11.59 (C)

Material cost per meter Rs/meter 2024.33

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.3612*1= sqmt 1.135 100.33 113.85 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.3612-(0.0056*2))*1= sqmt 1.100 640.00 703.72 (E)

Total (A+B+C+D+E) 2841.90Total without ED 2530.56

Add Water Charges @ 1% 1% 25.31Add CPOH @ 15% 15% 383.38

Total cost per meter for pipe 2939.24Total cost per kg for specials 59.85

2.5.6.13

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.366 0.008 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.366-0.008)*0.008*1*7850= kg 70.631Add 2 % wastage

2% kg 1.413Total Weight kg 72.043

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 72.043 34.21 2464.61 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 70.631 6.63 468.28 (B)

350 mm nominal dia (clear internal dia) of pipe with 5.6 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

350 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 399 Schedule of Rates 2014 - 2015

Page 250: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxyQuotation_Volume III_pg no_272 Cost of Scrap kg 1.413 27.00 38.14

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1159.12 11.59 (C)

Material cost per meter Rs/meter 2906.35

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.366*1= sqmt 1.150 100.33 115.36 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.366-(0.008*2))*1= sqmt 1.100 640.00 703.72 (E)

Total (A+B+C+D+E) 3725.42Total without ED 3316.89

Add Water Charges @ 1% 1% 33.17Add CPOH @ 15% 15% 502.51

Total cost per meter for pipe 3852.57Total cost per kg for specials 54.55

2.5.6.14

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.41 0.005 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.41-0.005)*0.005*1*7850= kg 49.940Add 2 % wastage

2% kg 0.999Total Weight kg 50.938

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 50.938 34.21 1742.61 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 49.940 6.63 331.10 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.999 27.00 26.97

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1580.62 15.81 (C)

Material cost per meter Rs/meter 2062.55

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.41*1= sqmt 1.288 100.33 129.23 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.41-(0.005*2))*1= sqmt 1.257 640.00 804.25 (E)

Total (A+B+C+D+E) 2996.03Total without ED 2668.19

Add Water Charges @ 1% 1% 26.68Add CPOH @ 15% 15% 404.23

Total cost per meter for pipe 3099.11Total cost per kg for specials 62.06

2.5.6.15

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.412 0.006 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850

400 mm nominal dia (clear internal dia) of pipe with 5.0 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

400 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 400 Schedule of Rates 2014 - 2015

Page 251: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxy(3.1416)*(0.412-0.006)*0.006*1*7850= kg 60.075Add 2 % wastage

2% kg 1.202Total Weight kg 61.277

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 61.277 34.21 2096.30 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 60.075 6.63 398.30 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.202 27.00 32.44

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1580.62 15.81 (C)

Material cost per meter Rs/meter 2477.96

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.412*1= sqmt 1.294 100.33 129.86 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.412-(0.006*2))*1= sqmt 1.257 640.00 804.25 (E)

Total (A+B+C+D+E) 3412.07Total without ED 3038.47

Add Water Charges @ 1% 1% 30.38Add CPOH @ 15% 15% 460.33

Total cost per meter for pipe 3529.18Total cost per kg for specials 58.75

2.5.6.16

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.4126 0.0063 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.4126-0.0063)*0.0063*1*7850= kg 63.126Add 2 % wastage

2% kg 1.263Total Weight kg 64.388

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 64.388 34.21 2202.74 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 63.126 6.63 418.52 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.263 27.00 34.09

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1580.62 15.81 (C)

Material cost per meter Rs/meter 2602.98

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.4126*1= sqmt 1.296 100.33 130.05 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.4126-(0.0063*2))*1= sqmt 1.257 640.00 804.25 (E)

Total (A+B+C+D+E) 3537.28Total without ED 3149.90

Add Water Charges @ 1% 1% 31.50Add CPOH @ 15% 15% 477.21

Total cost per meter for pipe 3658.61Total cost per kg for specials 57.96

2.5.6.17

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

400 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

400 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 401 Schedule of Rates 2014 - 2015

Page 252: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxyDetail for 1 meter Outer dia (d) =

thickness of pipe (t1) =

0.4176 0.0088 0.000Length of pipe

=1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.4176-0.0088)*0.0088*1*7850= kg 88.718Add 2 % wastage

2% kg 1.774Total Weight kg 90.493

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 90.493 34.21 3095.78 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 88.718 6.63 588.20 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.774 27.00 47.91

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1580.62 15.81 (C)

Material cost per meter Rs/meter 3651.88

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.4176*1= sqmt 1.312 100.33 131.62 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.4176-(0.0088*2))*1= sqmt 1.257 640.00 804.25 (E)

Total (A+B+C+D+E) 4587.75Total without ED 4084.82

Add Water Charges @ 1% 1% 40.85Add CPOH @ 15% 15% 618.85

Total cost per meter for pipe 4744.52Total cost per kg for specials 53.48

2.5.6.18

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.462 0.006 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.462-0.006)*0.006*1*7850= kg 67.474Add 2 % wastage

2% kg 1.349Total Weight kg 68.823

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 68.823 34.21 2354.46 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 67.474 6.63 447.35 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.349 27.00 36.44

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 2784.70

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.462*1= sqmt 1.451 100.33 145.62 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.462-(0.006*2))*1= sqmt 1.414 640.00 904.78 (E)

Total (A+B+C+D+E) 3835.10Total without ED 3415.35

450 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 402 Schedule of Rates 2014 - 2015

Page 253: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxyAdd Water Charges @ 1% 1% 34.15Add CPOH @ 15% 15% 517.43

Total cost per meter for pipe 3966.93Total cost per kg for specials 58.79

2.5.6.19

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.4626 0.0063 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.4626-0.0063)*0.0063*1*7850= kg 70.894Add 2 % wastage

2% kg 1.418Total Weight kg 72.312

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 72.312 34.21 2473.81 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 70.894 6.63 470.03 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.418 27.00 38.28

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 2924.88

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.4626*1= sqmt 1.453 100.33 145.81 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.4626-(0.0063*2))*1= sqmt 1.414 640.00 904.78 (E)

Total (A+B+C+D+E) 3975.46Total without ED 3540.27

Add Water Charges @ 1% 1% 35.40Add CPOH @ 15% 15% 536.35

Total cost per meter for pipe 4112.03Total cost per kg for specials 58.00

2.5.6.20

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.47 0.01 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.47-0.01)*0.01*1*7850= kg 113.443Add 2 % wastage

2% kg 2.269Total Weight kg 115.712

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 115.712 34.21 3958.53 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 113.443 6.63 752.13 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.269 27.00 61.26

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 4668.71

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

450 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

450 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 403 Schedule of Rates 2014 - 2015

Page 254: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxy(3.1416)*0.47*1= sqmt 1.477 100.33 148.14 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.47-(0.01*2))*1= sqmt 1.414 640.00 904.78 (E)

Total (A+B+C+D+E) 5721.63Total without ED 5094.36

Add Water Charges @ 1% 1% 50.94Add CPOH @ 15% 15% 771.80

Total cost per meter for pipe 5917.10Total cost per kg for specials 52.16

2.5.6.21

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.512 0.006 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.512-0.006)*0.006*1*7850= kg 74.872Add 2 % wastage

2% kg 1.497Total Weight kg 76.370

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 76.370 34.21 2612.63 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 74.872 6.63 496.40 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.497 27.00 40.43

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 3087.92

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.512*1= sqmt 1.608 100.33 161.38 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.512-(0.006*2))*1= sqmt 1.571 640.00 1005.31 (E)

Total (A+B+C+D+E) 4254.61Total without ED 3788.71

Add Water Charges @ 1% 1% 37.89Add CPOH @ 15% 15% 573.99

Total cost per meter for pipe 4400.59Total cost per kg for specials 58.77

2.5.6.22

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.5126 0.0063

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.5126-0.0063)*0.0063*1*7850= kg 78.663Add 2 % wastage

2% kg 1.573Total Weight kg 80.236

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 80.236 34.21 2744.89 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 78.663 6.63 521.53 (B)

500 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

500 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 404 Schedule of Rates 2014 - 2015

Page 255: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxyQuotation_Volume III_pg no_272 Cost of Scrap kg 1.573 27.00 42.48

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 3243.26

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.5126*1= sqmt 1.610 100.33 161.57 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.5126-(0.0063*2))*1= sqmt 1.571 640.00 1005.31 (E)

Total (A+B+C+D+E) 4410.14Total without ED 3927.13

Add Water Charges @ 1% 1% 39.27Add CPOH @ 15% 15% 594.96

Total cost per meter for pipe 4561.36Total cost per kg for specials 57.99

2.5.6.23

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.522 0.011 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.522-0.011)*0.011*1*7850= kg 138.622Add 2 % wastage

2% kg 2.772Total Weight kg 141.395

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 141.395 34.21 4837.15 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 138.622 6.63 919.07 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.772 27.00 74.86

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 5700.68

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.522*1= sqmt 1.640 100.33 164.53 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.522-(0.011*2))*1= sqmt 1.571 640.00 1005.31 (E)

Total (A+B+C+D+E) 6870.52Total without ED 6116.86

Add Water Charges @ 1% 1% 61.17Add CPOH @ 15% 15% 926.70

Total cost per meter for pipe 7104.74Total cost per kg for specials 51.25

2.5.6.24

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.612 0.006 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850

500 mm nominal dia (clear internal dia) of pipe with 11.0 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

600 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 405 Schedule of Rates 2014 - 2015

Page 256: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxy(3.1416)*(0.612-0.006)*0.006*1*7850= kg 89.669Add 2 % wastage

2% kg 1.793Total Weight kg 91.463

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 91.463 34.21 3128.96 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 89.669 6.63 594.51 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.793 27.00 48.42

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 3704.02

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.612*1= sqmt 1.923 100.33 192.90 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.612-(0.006*2))*1= sqmt 1.885 640.00 1206.37 (E)

Total (A+B+C+D+E) 5103.29Total without ED 4545.10

Add Water Charges @ 1% 1% 45.45Add CPOH @ 15% 15% 688.58

Total cost per meter for pipe 5279.13Total cost per kg for specials 58.87

2.5.6.25

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.6126 0.0063 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.6126-0.0063)*0.0063*1*7850= kg 94.199Add 2 % wastage

2% kg 1.884Total Weight kg 96.083

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 96.083 34.21 3287.03 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 94.199 6.63 624.54 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.884 27.00 50.87

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 3889.68

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.6126*1= sqmt 1.925 100.33 193.09 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.6126-(0.0063*2))*1= sqmt 1.885 640.00 1206.37 (E)

Total (A+B+C+D+E) 5289.14Total without ED 4710.51

Add Water Charges @ 1% 1% 47.11Add CPOH @ 15% 15% 713.64

Total cost per meter for pipe 5471.25Total cost per kg for specials 58.08

2.5.6.26

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

600 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

600 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 406 Schedule of Rates 2014 - 2015

Page 257: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxyDetail for 1 meter Outer dia (d) =

thickness of pipe (t1) =

0.616 0.008 0.000Length of pipe

=1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.616-0.008)*0.008*1*7850= kg 119.954Add 2 % wastage

2% kg 2.399Total Weight kg 122.353

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 122.353 34.21 4185.71 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 119.954 6.63 795.29 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.399 27.00 64.77

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 4945.21

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.616*1= sqmt 1.935 100.33 194.16 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.616-(0.008*2))*1= sqmt 1.885 640.00 1206.37 (E)

Total (A+B+C+D+E) 6345.74Total without ED 5650.87

Add Water Charges @ 1% 1% 56.51Add CPOH @ 15% 15% 856.11

Total cost per meter for pipe 6563.49Total cost per kg for specials 54.72

2.5.6.27

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.625 0.0125 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.625-0.0125)*0.0125*1*7850= kg 188.815Add 2 % wastage

2% kg 3.776Total Weight kg 192.591

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 192.591 34.21 6588.58 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 188.815 6.63 1251.84 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.776 27.00 101.96

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 7767.44

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.625*1= sqmt 1.963 100.33 197.00 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.625-(0.0125*2))*1= sqmt 1.885 640.00 1206.37 (E)

Total (A+B+C+D+E) 9170.81Total without ED 8165.18

600 mm nominal dia (clear internal dia) of pipe with 12.5 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 407 Schedule of Rates 2014 - 2015

Page 258: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxyAdd Water Charges @ 1% 1% 81.65Add CPOH @ 15% 15% 1237.02

Total cost per meter for pipe 9483.85Total cost per kg for specials 50.23

2.5.6.28

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.712 0.006 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.712-0.006)*0.006*1*7850= kg 104.466Add 2 % wastage

2% kg 2.089Total Weight kg 106.555

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 106.555 34.21 3645.29 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 104.466 6.63 692.61 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.089 27.00 56.41

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 4310.47

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.712*1= sqmt 2.237 100.33 224.42 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.712-(0.006*2))*1= sqmt 2.199 640.00 1407.43 (E)

Total (A+B+C+D+E) 5942.32Total without ED 5291.83

Add Water Charges @ 1% 1% 52.92Add CPOH @ 15% 15% 801.71

Total cost per meter for pipe 6146.46Total cost per kg for specials 58.84

2.5.6.29

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.7126 0.0063

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.7126-0.0063)*0.0063*1*7850= kg 109.736Add 2 % wastage

2% kg 2.195Total Weight kg 111.931

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 111.931 34.21 3829.18 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 109.736 6.63 727.55 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.195 27.00 59.26

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 4526.45

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

700 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

700 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 408 Schedule of Rates 2014 - 2015

Page 259: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxy(3.1416)*0.7126*1= sqmt 2.239 100.33 224.61 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.7126-(0.0063*2))*1= sqmt 2.199 640.00 1407.43 (E)

Total (A+B+C+D+E) 6158.49Total without ED 5484.22

Add Water Charges @ 1% 1% 54.84Add CPOH @ 15% 15% 830.86

Total cost per meter for pipe 6369.92Total cost per kg for specials 58.05

2.5.6.30

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.7142 0.0071 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.7142-0.0071)*0.0071*1*7850= kg 123.811Add 2 % wastage

2% kg 2.476Total Weight kg 126.287

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 126.287 34.21 4320.31 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 123.811 6.63 820.87 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.476 27.00 66.86

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 5103.30

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.7142*1= sqmt 2.244 100.33 225.11 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.7142-(0.0071*2))*1= sqmt 2.199 640.00 1407.43 (E)

Total (A+B+C+D+E) 6735.84Total without ED 5998.06

Add Water Charges @ 1% 1% 59.98Add CPOH @ 15% 15% 908.71

Total cost per meter for pipe 6966.75Total cost per kg for specials 56.27

2.5.6.31

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.716 0.008 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.716-0.008)*0.008*1*7850= kg 139.683Add 2 % wastage

2% kg 2.794Total Weight kg 142.476

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 142.476 34.21 4874.15 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 139.683 6.63 926.10 (B)

700 mm nominal dia (clear internal dia) of pipe with 7.1 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

700 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 409 Schedule of Rates 2014 - 2015

Page 260: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxyQuotation_Volume III_pg no_272 Cost of Scrap kg 2.794 27.00 75.43

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 5753.80

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.716*1= sqmt 2.249 100.33 225.68 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.716-(0.008*2))*1= sqmt 2.199 640.00 1407.43 (E)

Total (A+B+C+D+E) 7386.91Total without ED 6577.51

Add Water Charges @ 1% 1% 65.78Add CPOH @ 15% 15% 996.49

Total cost per meter for pipe 7639.78Total cost per kg for specials 54.69

2.5.6.32

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.7284 0.0142 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.7284-0.0142)*0.0142*1*7850= kg 250.108Add 2 % wastage

2% kg 5.002Total Weight kg 255.110

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 255.110 34.21 8727.38 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 250.108 6.63 1658.22 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 5.002 27.00 135.06

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 10279.52

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.7284*1= sqmt 2.288 100.33 229.59 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.7284-(0.0142*2))*1= sqmt 2.199 640.00 1407.43 (E)

Total (A+B+C+D+E) 11916.54Total without ED 10608.87

Add Water Charges @ 1% 1% 106.09Add CPOH @ 15% 15% 1607.24

Total cost per meter for pipe 12322.20Total cost per kg for specials 49.27

2.5.6.33

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.8142 0.0071 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850

800 mm nominal dia (clear internal dia) of pipe with 7.1 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

700 mm nominal dia (clear internal dia) of pipe with 14.2 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 410 Schedule of Rates 2014 - 2015

Page 261: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxy(3.1416)*(0.8142-0.0071)*0.0071*1*7850= kg 141.321Add 2 % wastage

2% kg 2.826Total Weight kg 144.147

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 144.147 34.21 4931.30 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 141.321 6.63 936.96 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.826 27.00 76.31

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 5820.92

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.8142*1= sqmt 2.558 100.33 256.63 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.8142-(0.0071*2))*1= sqmt 2.513 640.00 1608.50 (E)

Total (A+B+C+D+E) 7686.05Total without ED 6843.74

Add Water Charges @ 1% 1% 68.44Add CPOH @ 15% 15% 1036.83

Total cost per meter for pipe 7949.01Total cost per kg for specials 56.25

2.5.6.34

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.816 0.008 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.816-0.008)*0.008*1*7850= kg 159.412Add 2 % wastage

2% kg 3.188Total Weight kg 162.600

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 162.600 34.21 5562.59 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 159.412 6.63 1056.90 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.188 27.00 86.08

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 6562.39

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.816*1= sqmt 2.564 100.33 257.20 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.816-(0.008*2))*1= sqmt 2.513 640.00 1608.50 (E)

Total (A+B+C+D+E) 8428.08Total without ED 7504.15

Add Water Charges @ 1% 1% 75.04Add CPOH @ 15% 15% 1136.88

Total cost per meter for pipe 8716.07Total cost per kg for specials 54.68

2.5.6.35

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

800 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

800 mm nominal dia (clear internal dia) of pipe with 18.0 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 411 Schedule of Rates 2014 - 2015

Page 262: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxyDetail for 1 meter Outer dia (d) =

thickness of pipe (t1) =

0.836 0.018 0.000Length of pipe

=1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.836-0.018)*0.018*1*7850= kg 363.116Add 2 % wastage

2% kg 7.262Total Weight kg 370.378

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 370.378 34.21 12670.73 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 363.116 6.63 2407.46 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 7.262 27.00 196.08

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 14911.09

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.836*1= sqmt 2.626 100.33 263.50 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.836-(0.018*2))*1= sqmt 2.513 640.00 1608.50 (E)

Total (A+B+C+D+E) 16783.08Total without ED 14940.07

Add Water Charges @ 1% 1% 149.40Add CPOH @ 15% 15% 2263.42

Total cost per meter for pipe 17352.89Total cost per kg for specials 47.79

2.5.6.36

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.916 0.008 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.916-0.008)*0.008*1*7850= kg 179.141Add 2 % wastage

2% kg 3.583Total Weight kg 182.724

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 182.724 34.21 6251.03 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 179.141 6.63 1187.71 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.583 27.00 96.74

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 4346.71 43.47 (C)

Material cost per meter Rs/meter 7385.47

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.916*1= sqmt 2.878 100.33 288.72 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.916-(0.008*2))*1= sqmt 2.827 640.00 1809.56 (E)

Total (A+B+C+D+E) 9483.74Total without ED 8445.28

900 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 412 Schedule of Rates 2014 - 2015

Page 263: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxyAdd Water Charges @ 1% 1% 84.45Add CPOH @ 15% 15% 1279.46

Total cost per meter for pipe 9809.19Total cost per kg for specials 54.76

2.5.6.37

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.9176 0.0088 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.9176-0.0088)*0.0088*1*7850= kg 197.229Add 2 % wastage

2% kg 3.945Total Weight kg 201.173

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 201.173 34.21 6882.19 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 197.229 6.63 1307.63 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.945 27.00 106.50

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 4346.71 43.47 (C)

Material cost per meter Rs/meter 8126.79

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.9176*1= sqmt 2.883 100.33 289.22 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.9176-(0.0088*2))*1= sqmt 2.827 640.00 1809.56 (E)

Total (A+B+C+D+E) 10225.56Total without ED 9105.50

Add Water Charges @ 1% 1% 91.05Add CPOH @ 15% 15% 1379.48

Total cost per meter for pipe 10576.03Total cost per kg for specials 53.62

2.5.6.38

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.92 0.01 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.92-0.01)*0.01*1*7850= kg 224.420Add 2 % wastage

2% kg 4.488Total Weight kg 228.908

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 228.908 34.21 7831.00 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 224.420 6.63 1487.90 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 4.488 27.00 121.19

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 4346.71 43.47 (C)

Material cost per meter Rs/meter 9241.18

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

900 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

900 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 413 Schedule of Rates 2014 - 2015

Page 264: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxy(3.1416)*0.92*1= sqmt 2.890 100.33 289.98 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.92-(0.01*2))*1= sqmt 2.827 640.00 1809.56 (E)

Total (A+B+C+D+E) 11340.72Total without ED 10097.98

Add Water Charges @ 1% 1% 100.98Add CPOH @ 15% 15% 1529.84

Total cost per meter for pipe 11728.81Total cost per kg for specials 52.26

2.5.6.39

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.935 0.0175 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(0.935-0.0175)*0.0175*1*7850= kg 395.971Add 2 % wastage

2% kg 7.919Total Weight kg 403.891

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 403.891 34.21 13817.20 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 395.971 6.63 2625.29 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 7.919 27.00 213.82

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 4346.71 43.47 (C)

Material cost per meter Rs/meter 16272.13

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*0.935*1= sqmt 2.937 100.33 294.71 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.935-(0.0175*2))*1= sqmt 2.827 640.00 1809.56 (E)

Total (A+B+C+D+E) 18376.40Total without ED 16359.71

Add Water Charges @ 1% 1% 163.60Add CPOH @ 15% 15% 2478.50

Total cost per meter for pipe 19001.80Total cost per kg for specials 47.99

2.5.6.40

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.0176 0.0088 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.0176-0.0088)*0.0088*1*7850= kg 218.931Add 2 % wastage

2% kg 4.379Total Weight kg 223.310

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 223.310 34.21 7639.48 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 218.931 6.63 1451.51 (B)

1000 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

900 mm nominal dia (clear internal dia) of pipe with 17.5 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 414 Schedule of Rates 2014 - 2015

Page 265: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxyQuotation_Volume III_pg no_272 Cost of Scrap kg 4.379 27.00 118.22

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 9030.72

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.0176*1= sqmt 3.197 100.33 320.74 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.0176-(0.0088*2))*1= sqmt 3.142 640.00 2010.62 (E)

Total (A+B+C+D+E) 11362.08Total without ED 10118.59

Add Water Charges @ 1% 1% 101.19Add CPOH @ 15% 15% 1532.97

Total cost per meter for pipe 11752.74Total cost per kg for specials 53.68

2.5.6.41

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.02 0.01 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.02-0.01)*0.01*1*7850= kg 249.081Add 2 % wastage

2% kg 4.982Total Weight kg 254.063

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 254.063 34.21 8691.55 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 249.081 6.63 1651.41 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 4.982 27.00 134.50

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 10266.41

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.02*1= sqmt 3.204 100.33 321.50 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.02-(0.01*2))*1= sqmt 3.142 640.00 2010.62 (E)

Total (A+B+C+D+E) 12598.53Total without ED 11219.02

Add Water Charges @ 1% 1% 112.19Add CPOH @ 15% 15% 1699.68

Total cost per meter for pipe 13030.89Total cost per kg for specials 52.32

2.5.6.42

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.04 0.02 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850

1000 mm nominal dia (clear internal dia) of pipe with 20.0 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

1000 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 415 Schedule of Rates 2014 - 2015

Page 266: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxy(3.1416)*(1.04-0.02)*0.02*1*7850= kg 503.095Add 2 % wastage

2% kg 10.062Total Weight kg 513.157

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 513.157 34.21 17555.21 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 503.095 6.63 3335.52 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 10.062 27.00 271.67

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 20677.02

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.04*1= sqmt 3.267 100.33 327.80 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.04-(0.02*2))*1= sqmt 3.142 640.00 2010.62 (E)

Total (A+B+C+D+E) 23015.44Total without ED 20490.03

Add Water Charges @ 1% 1% 204.90Add CPOH @ 15% 15% 3104.24

Total cost per meter for pipe 23799.17Total cost per kg for specials 47.31

2.5.6.43

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.0676 0.0088 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.0676-0.0088)*0.0088*1*7850= kg 229.782Add 2 % wastage

2% kg 4.596Total Weight kg 234.378

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 234.378 34.21 8018.12 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 229.782 6.63 1523.46 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 4.596 27.00 124.08

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 9475.45

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.0676*1= sqmt 3.354 100.33 336.50 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.0676-(0.0088*2))*1= sqmt 3.299 640.00 2111.15 (E)

Total (A+B+C+D+E) 11923.10Total without ED 10617.89

Add Water Charges @ 1% 1% 106.18Add CPOH @ 15% 15% 1608.61

Total cost per meter for pipe 12332.68Total cost per kg for specials 53.67

2.5.6.44

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

1050 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

1050 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 416 Schedule of Rates 2014 - 2015

Page 267: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxyDetail for 1 meter Outer dia (d) =

thickness of pipe (t1) =

1.07 0.01 0.000Length of pipe

=1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.07-0.01)*0.01*1*7850= kg 261.412Add 2 % wastage

2% kg 5.228Total Weight kg 266.640

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 266.640 34.21 9121.83 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 261.412 6.63 1733.16 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 5.228 27.00 141.16

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 10771.78

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.07*1= sqmt 3.362 100.33 337.26 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.07-(0.01*2))*1= sqmt 3.299 640.00 2111.15 (E)

Total (A+B+C+D+E) 13220.19Total without ED 11772.30

Add Water Charges @ 1% 1% 117.72Add CPOH @ 15% 15% 1783.50

Total cost per meter for pipe 13673.52Total cost per kg for specials 52.31

2.5.6.45

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.072 0.011 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.072-0.011)*0.011*1*7850= kg 287.824Add 2 % wastage

2% kg 5.756Total Weight kg 293.581

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 293.581 34.21 10043.48 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 287.824 6.63 1908.28 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 5.756 27.00 155.43

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 11854.28

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.072*1= sqmt 3.368 100.33 337.89 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.072-(0.011*2))*1= sqmt 3.299 640.00 2111.15 (E)

Total (A+B+C+D+E) 14303.32Total without ED 12736.28

1050 mm nominal dia (clear internal dia) of pipe with 11.0 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 417 Schedule of Rates 2014 - 2015

Page 268: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxyAdd Water Charges @ 1% 1% 127.36Add CPOH @ 15% 15% 1929.55

Total cost per meter for pipe 14793.19Total cost per kg for specials 51.40

2.5.6.46

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.1176 0.0088 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.1176-0.0088)*0.0088*1*7850= kg 240.633Add 2 % wastage

2% kg 4.813Total Weight kg 245.446

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 245.446 34.21 8396.76 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 240.633 6.63 1595.40 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 4.813 27.00 129.94

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 9920.17

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.1176*1= sqmt 3.511 100.33 352.26 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.1176-(0.0088*2))*1= sqmt 3.456 640.00 2211.68 (E)

Total (A+B+C+D+E) 12484.11Total without ED 11117.19

Add Water Charges @ 1% 1% 111.17Add CPOH @ 15% 15% 1684.25

Total cost per meter for pipe 12912.62Total cost per kg for specials 53.66

2.5.6.47

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.12 0.01 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.12-0.01)*0.01*1*7850= kg 273.743Add 2 % wastage

2% kg 5.475Total Weight kg 279.218

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 279.218 34.21 9552.10 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 273.743 6.63 1814.91 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 5.475 27.00 147.82

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 11277.15

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

1100 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

1100 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 418 Schedule of Rates 2014 - 2015

Page 269: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxy(3.1416)*1.12*1= sqmt 3.519 100.33 353.02 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.12-(0.01*2))*1= sqmt 3.456 640.00 2211.68 (E)

Total (A+B+C+D+E) 13841.85Total without ED 12325.57

Add Water Charges @ 1% 1% 123.26Add CPOH @ 15% 15% 1867.32

Total cost per meter for pipe 14316.15Total cost per kg for specials 52.30

2.5.6.48

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.122 0.011 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.122-0.011)*0.011*1*7850= kg 301.388Add 2 % wastage

2% kg 6.028Total Weight kg 307.416

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 307.416 34.21 10516.78 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 301.388 6.63 1998.20 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 6.028 27.00 162.75

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 12410.19

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.122*1= sqmt 3.525 100.33 353.65 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.122-(0.011*2))*1= sqmt 3.456 640.00 2211.68 (E)

Total (A+B+C+D+E) 14975.52Total without ED 13334.53

Add Water Charges @ 1% 1% 133.35Add CPOH @ 15% 15% 2020.18

Total cost per meter for pipe 15488.06Total cost per kg for specials 51.39

2.5.6.49

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.22 0.01 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.22-0.01)*0.01*1*7850= kg 298.404Add 2 % wastage

2% kg 5.968Total Weight kg 304.372

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 304.372 34.21 10412.65 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 298.404 6.63 1978.42 (B)

1100 mm nominal dia (clear internal dia) of pipe with 11.0 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

1200 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 419 Schedule of Rates 2014 - 2015

Page 270: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxyQuotation_Volume III_pg no_272 Cost of Scrap kg 5.968 27.00 161.14

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 12287.89

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.22*1= sqmt 3.833 100.33 384.54 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.22-(0.01*2))*1= sqmt 3.770 640.00 2412.74 (E)

Total (A+B+C+D+E) 15085.17Total without ED 13432.12

Add Water Charges @ 1% 1% 134.32Add CPOH @ 15% 15% 2034.97

Total cost per meter for pipe 15601.41Total cost per kg for specials 52.28

2.5.6.50

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.222 0.011 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.222-0.011)*0.011*1*7850= kg 328.516Add 2 % wastage

2% kg 6.570Total Weight kg 335.086

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 335.086 34.21 11463.38 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 328.516 6.63 2178.06 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 6.570 27.00 177.40

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 13522.00

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.222*1= sqmt 3.839 100.33 385.17 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.222-(0.011*2))*1= sqmt 3.770 640.00 2412.74 (E)

Total (A+B+C+D+E) 16319.91Total without ED 14531.04

Add Water Charges @ 1% 1% 145.31Add CPOH @ 15% 15% 2201.45

Total cost per meter for pipe 16877.80Total cost per kg for specials 51.38

2.5.6.51

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.224 0.012 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850

1200 mm nominal dia (clear internal dia) of pipe with 11.0 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

1200 mm nominal dia (clear internal dia) of pipe with 12.0 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 420 Schedule of Rates 2014 - 2015

Page 271: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxy(3.1416)*(1.224-0.012)*0.012*1*7850= kg 358.677Add 2 % wastage

2% kg 7.174Total Weight kg 365.850

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 365.850 34.21 12515.83 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 358.677 6.63 2378.03 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 7.174 27.00 193.69

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 14758.13

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.224*1= sqmt 3.845 100.33 385.80 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.224-(0.012*2))*1= sqmt 3.770 640.00 2412.74 (E)

Total (A+B+C+D+E) 17556.67Total without ED 15631.75

Add Water Charges @ 1% 1% 156.32Add CPOH @ 15% 15% 2368.21

Total cost per meter for pipe 18156.28Total cost per kg for specials 50.62

2.5.6.52

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.225 0.0125 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.225-0.0125)*0.0125*1*7850= kg 373.776Add 2 % wastage

2% kg 7.476Total Weight kg 381.251

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 381.251 34.21 13042.71 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 373.776 6.63 2478.13 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 7.476 27.00 201.84

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 15376.96

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.225*1= sqmt 3.848 100.33 386.11 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.225-(0.0125*2))*1= sqmt 3.770 640.00 2412.74 (E)

Total (A+B+C+D+E) 18175.81Total without ED 16182.78

Add Water Charges @ 1% 1% 161.83Add CPOH @ 15% 15% 2451.69

Total cost per meter for pipe 18796.30Total cost per kg for specials 50.29

2.5.6.53

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

1400 mm nominal dia (clear internal dia) of pipe with 12 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

1200 mm nominal dia (clear internal dia) of pipe with 12.5 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 421 Schedule of Rates 2014 - 2015

Page 272: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxyDetail for 1 meter Outer dia (d) =

thickness of pipe (t1) =

1.424 0.012 0.000Length of pipe

=1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.424-0.012)*0.012*1*7850= kg 417.864Add 2 % wastage

2% kg 8.357Total Weight kg 426.222

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 426.222 34.21 14581.15 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 417.864 6.63 2770.44 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 8.357 27.00 225.65

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 7244.52 72.45 (C)

Material cost per meter Rs/meter 17198.39

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.424*1= sqmt 4.474 100.33 448.83 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.424-(0.012*2))*1= sqmt 4.398 640.00 2814.87 (E)

Total (A+B+C+D+E) 20462.10Total without ED 18219.16

Add Water Charges @ 1% 1% 182.19Add CPOH @ 15% 15% 2760.20

Total cost per meter for pipe 21161.56Total cost per kg for specials 50.64

2.5.6.54

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.425 0.0125

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.425-0.0125)*0.0125*1*7850= kg 435.430Add 2 % wastage

2% kg 8.709Total Weight kg 444.138

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 444.138 34.21 15194.08 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 435.430 6.63 2886.90 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 8.709 27.00 235.13

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 7244.52 72.45 (C)

Material cost per meter Rs/meter 17918.29

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.425*1= sqmt 4.477 100.33 449.15 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.425-(0.0125*2))*1= sqmt 4.398 640.00 2814.87 (E)

Total (A+B+C+D+E) 21182.31Total without ED 18860.15

1400 mm nominal dia (clear internal dia) of pipe with 12.5 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 422 Schedule of Rates 2014 - 2015

Page 273: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxyAdd Water Charges @ 1% 1% 188.60Add CPOH @ 15% 15% 2857.31

Total cost per meter for pipe 21906.06Total cost per kg for specials 50.31

2.5.6.55

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.4284 0.0142 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.4284-0.0142)*0.0142*1*7850= kg 495.243Add 2 % wastage

2% kg 9.905Total Weight kg 505.148

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 505.148 34.21 17281.25 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 495.243 6.63 3283.46 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 9.905 27.00 267.43

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 7244.52 72.45 (C)

Material cost per meter Rs/meter 20369.73

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.4284*1= sqmt 4.487 100.33 450.22 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.4284-(0.0142*2))*1= sqmt 4.398 640.00 2814.87 (E)

Total (A+B+C+D+E) 23634.81Total without ED 21042.87

Add Water Charges @ 1% 1% 210.43Add CPOH @ 15% 15% 3187.99

Total cost per meter for pipe 24441.29Total cost per kg for specials 49.35

2.5.6.56

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.524 0.012 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.524-0.012)*0.012*1*7850= kg 447.458Add 2 % wastage

2% kg 8.949Total Weight kg 456.407

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 456.407 34.21 15613.81 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 447.458 6.63 2966.65 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 8.949 27.00 241.63

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 8693.42 86.93 (C)

Material cost per meter Rs/meter 18425.77

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

1400 mm nominal dia (clear internal dia) of pipe with 14.2 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

1500 mm nominal dia (clear internal dia) of pipe with 12 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 423 Schedule of Rates 2014 - 2015

Page 274: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxy(3.1416)*1.524*1= sqmt 4.788 100.33 480.35 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.524-(0.012*2))*1= sqmt 4.712 640.00 3015.93 (E)

Total (A+B+C+D+E) 21922.05Total without ED 19520.11

Add Water Charges @ 1% 1% 195.20Add CPOH @ 15% 15% 2957.30

Total cost per meter for pipe 22672.61Total cost per kg for specials 50.67

2.5.6.57

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.6284 0.0142 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.6284-0.0142)*0.0142*1*7850= kg 565.282Add 2 % wastage

2% kg 11.306Total Weight kg 576.588

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 576.588 34.21 19725.21 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 565.282 6.63 3747.82 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 11.306 27.00 305.25

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 8693.42 86.93 (C)

Material cost per meter Rs/meter 23254.71

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.6284*1= sqmt 5.116 100.33 513.26 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.6284-(0.0142*2))*1= sqmt 5.027 640.00 3216.99 (E)

Total (A+B+C+D+E) 26984.96Total without ED 24026.08

Add Water Charges @ 1% 1% 240.26Add CPOH @ 15% 15% 3639.95

Total cost per meter for pipe 27906.30Total cost per kg for specials 49.37

2.5.6.58

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.632 0.016 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.632-0.016)*0.016*1*7850= kg 637.648Add 2 % wastage

2% kg 12.753Total Weight kg 650.401

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 650.401 34.21 22250.37 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 637.648 6.63 4227.60 (B)

1600 mm nominal dia (clear internal dia) of pipe with 14.2 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

1600 mm nominal dia (clear internal dia) of pipe with 16.0 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 424 Schedule of Rates 2014 - 2015

Page 275: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxyQuotation_Volume III_pg no_272 Cost of Scrap kg 12.753 27.00 344.33

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 8693.42 86.93 (C)

Material cost per meter Rs/meter 26220.58

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.632*1= sqmt 5.127 100.33 514.39 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.632-(0.016*2))*1= sqmt 5.027 640.00 3216.99 (E)

Total (A+B+C+D+E) 29951.97Total without ED 26666.71

Add Water Charges @ 1% 1% 266.67Add CPOH @ 15% 15% 4040.01

Total cost per meter for pipe 30973.38Total cost per kg for specials 48.57

2.5.6.59

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.8284 0.0142 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.8284-0.0142)*0.0142*1*7850= kg 635.321Add 2 % wastage

2% kg 12.706Total Weight kg 648.027

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 648.027 34.21 22169.17 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 635.321 6.63 4212.18 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 12.706 27.00 343.07

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 10142.33 101.42 (C)

Material cost per meter Rs/meter 26139.70

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.8284*1= sqmt 5.744 100.33 576.30 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.8284-(0.0142*2))*1= sqmt 5.655 640.00 3619.11 (E)

Total (A+B+C+D+E) 30335.11Total without ED 27009.30

Add Water Charges @ 1% 1% 270.09Add CPOH @ 15% 15% 4091.91

Total cost per meter for pipe 31371.30Total cost per kg for specials 49.38

2.5.6.60

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.832 0.016 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850

1800 mm nominal dia (clear internal dia) of pipe with 14.2 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

1800 mm nominal dia (clear internal dia) of pipe with 16.0 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 425 Schedule of Rates 2014 - 2015

Page 276: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxy(3.1416)*(1.832-0.016)*0.016*1*7850= kg 716.565Add 2 % wastage

2% kg 14.331Total Weight kg 730.896

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 730.896 34.21 25004.13 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 716.565 6.63 4750.82 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 14.331 27.00 386.94

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 10142.33 101.42 (C)

Material cost per meter Rs/meter 29469.43

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.832*1= sqmt 5.755 100.33 577.43 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.832-(0.016*2))*1= sqmt 5.655 640.00 3619.11 (E)

Total (A+B+C+D+E) 33665.98Total without ED 29973.76

Add Water Charges @ 1% 1% 299.74Add CPOH @ 15% 15% 4541.02

Total cost per meter for pipe 34814.52Total cost per kg for specials 48.59

2.5.6.61

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.835 0.0175 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(1.835-0.0175)*0.0175*1*7850= kg 784.390Add 2 % wastage

2% kg 15.688Total Weight kg 800.078

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 800.078 34.21 27370.86 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 784.390 6.63 5200.51 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 15.688 27.00 423.57

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 10142.33 101.42 (C)

Material cost per meter Rs/meter 32249.22

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*1.835*1= sqmt 5.765 100.33 578.38 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.835-(0.0175*2))*1= sqmt 5.655 640.00 3619.11 (E)

Total (A+B+C+D+E) 36446.71Total without ED 32448.60

Add Water Charges @ 1% 1% 324.49Add CPOH @ 15% 15% 4915.96

Total cost per meter for pipe 37689.05Total cost per kg for specials 48.05

2.5.6.62

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

1800 mm nominal dia (clear internal dia) of pipe with 17.5 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

2000 mm nominal dia (clear internal dia) of pipe with 16.0 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 426 Schedule of Rates 2014 - 2015

Page 277: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxyDetail for 1 meter Outer dia (d) =

thickness of pipe (t1) =

2.032 0.016 0.000Length of pipe

=1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(2.032-0.016)*0.016*1*7850= kg 795.481Add 2 % wastage

2% kg 15.910Total Weight kg 811.391

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 811.391 34.21 27757.89 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 795.481 6.63 5274.04 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 15.910 27.00 429.56

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 11591.23 115.91 (C)

Material cost per meter Rs/meter 32718.28

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*2.032*1= sqmt 6.384 100.33 640.47 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(2.032-(0.016*2))*1= sqmt 6.283 640.00 4021.24 (E)

Total (A+B+C+D+E) 37379.99Total without ED 33280.81

Add Water Charges @ 1% 1% 332.81Add CPOH @ 15% 15% 5042.04

Total cost per meter for pipe 38655.66Total cost per kg for specials 48.59

2.5.6.63

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =2.035 0.0175 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(2.035-0.0175)*0.0175*1*7850= kg 870.705Add 2 % wastage

2% kg 17.414Total Weight kg 888.119

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 888.119 34.21 30382.78 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 870.705 6.63 5772.78 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 17.414 27.00 470.18

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 11591.23 115.91 (C)

Material cost per meter Rs/meter 35801.29

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*2.035*1= sqmt 6.393 100.33 641.42 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(2.035-(0.0175*2))*1= sqmt 6.283 640.00 4021.24 (E)

Total (A+B+C+D+E) 40463.94Total without ED 36025.52

2000 mm nominal dia (clear internal dia) of pipe with 17.5 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 427 Schedule of Rates 2014 - 2015

Page 278: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxyAdd Water Charges @ 1% 1% 360.26Add CPOH @ 15% 15% 5457.87

Total cost per meter for pipe 41843.64Total cost per kg for specials 48.06

2.5.6.64

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =2.04 0.02 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(2.04-0.02)*0.02*1*7850= kg 996.325Add 2 % wastage

2% kg 19.926Total Weight kg 1016.251

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 1016.251 34.21 34766.21 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 996.325 6.63 6605.63 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 19.926 27.00 538.02

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 11591.23 115.91 (C)

Material cost per meter Rs/meter 40949.74

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*2.04*1= sqmt 6.409 100.33 642.99 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(2.04-(0.02*2))*1= sqmt 6.283 640.00 4021.24 (E)

Total (A+B+C+D+E) 45613.97Total without ED 40609.02

Add Water Charges @ 1% 1% 406.09Add CPOH @ 15% 15% 6152.27

Total cost per meter for pipe 47167.38Total cost per kg for specials 47.34

2.5.6.65

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =2.235 0.0175 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(2.235-0.0175)*0.0175*1*7850= kg 957.020Add 2 % wastage

2% kg 19.140Total Weight kg 976.161

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 976.161 34.21 33394.71 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 957.020 6.63 6345.05 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 19.140 27.00 516.79

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 13040.13 130.40 (C)

Material cost per meter Rs/meter 39353.36

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

2000 mm nominal dia (clear internal dia) of pipe with 20.0 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

2200 mm nominal dia (clear internal dia) of pipe with 17.5 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 428 Schedule of Rates 2014 - 2015

Page 279: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxy(3.1416)*2.235*1= sqmt 7.021 100.33 704.46 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(2.235-(0.0175*2))*1= sqmt 6.912 640.00 4423.36 (E)

Total (A+B+C+D+E) 44481.18Total without ED 39602.44

Add Water Charges @ 1% 1% 396.02Add CPOH @ 15% 15% 5999.77

Total cost per meter for pipe 45998.23Total cost per kg for specials 48.06

2.5.6.66

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =2.24 0.02 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(2.24-0.02)*0.02*1*7850= kg 1094.971Add 2 % wastage

2% kg 21.899Total Weight kg 1116.870

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 1116.870 34.21 38208.41 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 1094.971 6.63 7259.66 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 21.899 27.00 591.28

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 13040.13 130.40 (C)

Material cost per meter Rs/meter 45007.18

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*2.24*1= sqmt 7.037 100.33 706.03 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(2.24-(0.02*2))*1= sqmt 6.912 640.00 4423.36 (E)

Total (A+B+C+D+E) 50136.57Total without ED 44635.72

Add Water Charges @ 1% 1% 446.36Add CPOH @ 15% 15% 6762.31

Total cost per meter for pipe 51844.38Total cost per kg for specials 47.35

2.5.6.67

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =2.2444 0.0222 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(2.2444-0.0222)*0.0222*1*7850= kg 1216.622Add 2 % wastage

2% kg 24.332Total Weight kg 1240.954

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 1240.954 34.21 42453.36 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 1216.622 6.63 8066.20 (B)

2200 mm nominal dia (clear internal dia) of pipe with 20.0 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

2200 mm nominal dia (clear internal dia) of pipe with 22.2 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 429 Schedule of Rates 2014 - 2015

Page 280: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxyQuotation_Volume III_pg no_272 Cost of Scrap kg 24.332 27.00 656.98

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 13040.13 130.40 (C)

Material cost per meter Rs/meter 49992.99

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*2.2444*1= sqmt 7.051 100.33 707.42 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(2.2444-(0.0222*2))*1= sqmt 6.912 640.00 4423.36 (E)

Total (A+B+C+D+E) 55123.77Total without ED 49074.30

Add Water Charges @ 1% 1% 490.74Add CPOH @ 15% 15% 7434.76

Total cost per meter for pipe 56999.80Total cost per kg for specials 46.85

2.5.6.68

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =2.54 0.02 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(2.54-0.02)*0.02*1*7850= kg 1242.940Add 2 % wastage

2% kg 24.859Total Weight kg 1267.799

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 1267.799 34.21 43371.70 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 1242.940 6.63 8240.69 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 24.859 27.00 671.19

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 14489.04 144.89 (C)

Material cost per meter Rs/meter 51086.10

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*2.54*1= sqmt 7.980 100.33 800.59 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(2.54-(0.02*2))*1= sqmt 7.854 640.00 5026.55 (E)

Total (A+B+C+D+E) 56913.23Total without ED 50668.51

Add Water Charges @ 1% 1% 506.69Add CPOH @ 15% 15% 7676.28

Total cost per meter for pipe 58851.48Total cost per kg for specials 47.35

2.5.6.69

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =2.5444 0.0222 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850

2500 mm nominal dia (clear internal dia) of pipe with 22.2 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

2500 mm nominal dia (clear internal dia) of pipe with 20.0 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 430 Schedule of Rates 2014 - 2015

Page 281: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outside epoxy(3.1416)*(2.5444-0.0222)*0.0222*1*7850= kg 1380.868Add 2 % wastage

2% kg 27.617Total Weight kg 1408.485

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 1408.485 34.21 48184.62 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 1380.868 6.63 9155.15 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 27.617 27.00 745.67

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 14489.04 144.89 (C)

Material cost per meter Rs/meter 56738.99

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*2.5444*1= sqmt 7.993 100.33 801.98 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(2.5444-(0.0222*2))*1= sqmt 7.854 640.00 5026.55 (E)

Total (A+B+C+D+E) 62567.52Total without ED 55700.81

Add Water Charges @ 1% 1% 557.01Add CPOH @ 15% 15% 8438.67

Total cost per meter for pipe 64696.49Total cost per kg for specials 46.85

2.5.6.70

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =2.55 0.025 0.000

Length of pipe =

1.0

Weight of MS coil = pi()*(d-t1)*t1*L*7850(3.1416)*(2.55-0.025)*0.025*1*7850= kg 1556.757Add 2 % wastage

2% kg 31.135Total Weight kg 1587.892

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 1587.892 34.21 54322.20 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 1556.757 6.63 10321.30 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 31.135 27.00 840.65

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 14489.04 144.89 (C)

Material cost per meter Rs/meter 63947.74

Outside epoxy coating13.52.1 Area of coating = pi()*d*L

(3.1416)*2.55*1= sqmt 8.011 100.33 803.74 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(2.55-(0.025*2))*1= sqmt 7.854 640.00 5026.55 (E)

Total (A+B+C+D+E) 69778.03Total without ED 62118.14

Add Water Charges @ 1% 1% 621.18Add CPOH @ 15% 15% 9410.90

Total cost per meter for pipe 72150.22Total cost per kg for specials 46.35

2500 mm nominal dia (clear internal dia) of pipe with 25.0 mm thick coil, internally coated with food grade epoxy coating and external / outsideepoxy coating

Delhi Jal Board 431 Schedule of Rates 2014 - 2015

Page 282: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

2.5.7

2.5.7.1

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.16 0.005

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.16-0.005)*0.005*1*7850= kg 19.113Add 5 % wastage

5% kg 0.956Total Weight kg 20.068

#REF! Cost of MS plate kg 20.068 45.00 903.07 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 19.113 6.63 126.72 (B)

Quotation_Volume III_pg no_272 Cost of scrap kg 0.956 27.00 25.80

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 289.78 2.90 (C)

Material cost per meter Rs/meter 1006.89

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.16*1= sqmt 0.503 52.88 26.58 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.16-(0.005*2))*1= sqmt 0.471 640.00 301.59 (E)

Total (A+B+C+D+E) 1335.06Total without ED 1188.52

Add Water Charges @ 1% 1% 11.89Add CPOH @ 15% 15% 180.06

Total cost per meter for pipe 1380.46Total cost per kg for specials 72.23

2.5.7.2

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.209 0.0045

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.209-0.0045)*0.0045*1*7850= kg 22.695Add 5 % wastage

5% kg 1.135Total Weight kg 23.829

#REF! Cost of MS plate kg 23.829 45.00 1072.33 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 22.695 6.63 150.47 (B)

200 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Providing Mild Steel Pipes / specials fabricated / manufactured out of MS plate of steel grade Fe410 as per IS 3589:2001; internally coated withfood grade epoxy coating and external / outside bitumastic coating; minimum thickness of M.S. Plate as specified; complete in all respect; withupto date amendments in relevant IS codes and as directed by Engineer-in-charge . The rates are excluding excise duty component.

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 448 Schedule of Rates 2014 - 2015

Page 283: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.135 27.00 30.64

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 471.38 4.71 (C)

Material cost per meter Rs/meter 1196.87

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.209*1= sqmt 0.657 52.88 34.72 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.209-(0.0045*2))*1= sqmt 0.628 640.00 402.12 (E)

Total (A+B+C+D+E) 1633.71Total without ED 1454.52

Add Water Charges @ 1% 1% 14.55Add CPOH @ 15% 15% 220.36

Total cost per meter for pipe 1689.42Total cost per kg for specials 74.44

2.5.7.3

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.212 0.006

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.212-0.006)*0.006*1*7850= kg 30.482Add 5 % wastage

5% kg 1.524Total Weight kg 32.006

#REF! Cost of MS plate kg 32.006 45.00 1440.26 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 30.482 6.63 202.09 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.524 27.00 41.15

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 471.38 4.71 (C)

Material cost per meter Rs/meter 1605.91

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.212*1= sqmt 0.666 52.88 35.22 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.212-(0.006*2))*1= sqmt 0.628 640.00 402.12 (E)

Total (A+B+C+D+E) 2043.25Total without ED 1819.01

Add Water Charges @ 1% 1% 18.19Add CPOH @ 15% 15% 275.58

Total cost per meter for pipe 2112.78Total cost per kg for specials 69.31

2.5.7.4

200 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

200 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 449 Schedule of Rates 2014 - 2015

Page 284: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.2126 0.0063

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.2126-0.0063)*0.0063*1*7850= kg 32.052Add 5 % wastage

5% kg 1.603Total Weight kg 33.655

#REF! Cost of MS plate kg 33.655 45.00 1514.47 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 32.052 6.63 212.51 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.603 27.00 43.27

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 471.38 4.71 (C)

Material cost per meter Rs/meter 1688.42

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.2126*1= sqmt 0.668 52.88 35.32 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.2126-(0.0063*2))*1= sqmt 0.628 640.00 402.12 (E)

Total (A+B+C+D+E) 2125.86Total without ED 1892.53

Add Water Charges @ 1% 1% 18.93Add CPOH @ 15% 15% 286.72

Total cost per meter for pipe 2198.17Total cost per kg for specials 68.58

2.5.7.5

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.26 0.005

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.26-0.005)*0.005*1*7850= kg 31.443Add 5 % wastage

5% kg 1.572Total Weight kg 33.016

#REF! Cost of MS plate kg 33.016 45.00 1485.70 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 31.443 6.63 208.47 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.572 27.00 42.45

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 669.85 6.70 (C)

Material cost per meter Rs/meter 1658.42

250 mm nominal dia (clear internal dia) of pipe with 5.0 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 450 Schedule of Rates 2014 - 2015

Page 285: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.26*1= sqmt 0.817 52.88 43.19 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.26-(0.005*2))*1= sqmt 0.785 640.00 502.65 (E)

Total (A+B+C+D+E) 2204.27Total without ED 1962.53

Add Water Charges @ 1% 1% 19.63Add CPOH @ 15% 15% 297.32

Total cost per meter for pipe 2279.47Total cost per kg for specials 72.49

2.5.7.6

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.262 0.006

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.262-0.006)*0.006*1*7850= kg 37.880Add 5 % wastage

5% kg 1.894Total Weight kg 39.774

#REF! Cost of MS plate kg 39.774 45.00 1789.83 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 37.880 6.63 251.14 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.894 27.00 51.14

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 669.85 6.70 (C)

Material cost per meter Rs/meter 1996.54

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.262*1= sqmt 0.823 52.88 43.52 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.262-(0.006*2))*1= sqmt 0.785 640.00 502.65 (E)

Total (A+B+C+D+E) 2542.72Total without ED 2263.74

Add Water Charges @ 1% 1% 22.64Add CPOH @ 15% 15% 342.96

Total cost per meter for pipe 2629.34Total cost per kg for specials 69.41

2.5.7.7

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.2626 0.0063

Length of pipe =

1.0

250 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

250 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 451 Schedule of Rates 2014 - 2015

Page 286: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.2626-0.0063)*0.0063*1*7850= kg 39.821Add 5 % wastage

5% kg 1.991Total Weight kg 41.812

#REF! Cost of MS plate kg 41.812 45.00 1881.53 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 39.821 6.63 264.01 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.991 27.00 53.76

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 669.85 6.70 (C)

Material cost per meter Rs/meter 2098.48

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.2626*1= sqmt 0.825 52.88 43.62 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.2626-(0.0063*2))*1= sqmt 0.785 640.00 502.65 (E)

Total (A+B+C+D+E) 2644.76Total without ED 2354.56

Add Water Charges @ 1% 1% 23.55Add CPOH @ 15% 15% 356.72

Total cost per meter for pipe 2734.82Total cost per kg for specials 68.68

2.5.7.8

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.31 0.005

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.31-0.005)*0.005*1*7850= kg 37.609Add 5 % wastage

5% kg 1.880Total Weight kg 39.489

#REF! Cost of MS plate kg 39.489 45.00 1777.02 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 37.609 6.63 249.35 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.880 27.00 50.77

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 827.95 8.28 (C)

Material cost per meter Rs/meter 1983.87

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.31*1= sqmt 0.974 52.88 51.50 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.31-(0.005*2))*1= sqmt 0.942 640.00 603.19 (E)

300 mm nominal dia (clear internal dia) of pipe with 5 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 452 Schedule of Rates 2014 - 2015

Page 287: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Total (A+B+C+D+E) 2638.55Total without ED 2349.21

Add Water Charges @ 1% 1% 23.49Add CPOH @ 15% 15% 355.91

Total cost per meter for pipe 2728.61Total cost per kg for specials 72.55

2.5.7.9

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.3112 0.0056

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.3112-0.0056)*0.0056*1*7850= kg 42.205Add 5 % wastage

5% kg 2.110Total Weight kg 44.315

#REF! Cost of MS plate kg 44.315 45.00 1994.17 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 42.205 6.63 279.82 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.110 27.00 56.98

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 827.95 8.28 (C)

Material cost per meter Rs/meter 2225.29

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.3112*1= sqmt 0.978 52.88 51.69 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.3112-(0.0056*2))*1= sqmt 0.942 640.00 603.19 (E)

Total (A+B+C+D+E) 2880.17Total without ED 2564.25

Add Water Charges @ 1% 1% 25.64Add CPOH @ 15% 15% 388.48

Total cost per meter for pipe 2978.38Total cost per kg for specials 70.57

2.5.7.10

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.3142 0.0071

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.3142-0.0071)*0.0071*1*7850= kg 53.772Add 5 % wastage

5% kg 2.689Total Weight kg 56.461

#REF! Cost of MS plate kg 56.461 45.00 2540.74 (A)

300 mm nominal dia (clear internal dia) of pipe with 5.6 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

300 mm nominal dia (clear internal dia) of pipe with 7.1 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 453 Schedule of Rates 2014 - 2015

Page 288: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_320 Cost of Fabrication kg 53.772 6.63 356.51 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.689 27.00 72.59

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 827.95 8.28 (C)

Material cost per meter Rs/meter 2832.93

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.3142*1= sqmt 0.987 52.88 52.19 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.3142-(0.0071*2))*1= sqmt 0.942 640.00 603.19 (E)

Total (A+B+C+D+E) 3488.31Total without ED 3105.50

Add Water Charges @ 1% 1% 31.05Add CPOH @ 15% 15% 470.48

Total cost per meter for pipe 3607.03Total cost per kg for specials 67.08

2.5.7.11

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.36 0.005

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.36-0.005)*0.005*1*7850= kg 43.774Add 5 % wastage

5% kg 2.189Total Weight kg 45.963

#REF! Cost of MS plate kg 45.963 45.00 2068.33 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 43.774 6.63 290.22 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.189 27.00 59.10

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1159.12 11.59 (C)

Material cost per meter Rs/meter 2311.05

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.36*1= sqmt 1.131 52.88 59.80 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.36-(0.005*2))*1= sqmt 1.100 640.00 703.72 (E)

Total (A+B+C+D+E) 3074.57Total without ED 2737.63

Add Water Charges @ 1% 1% 27.38Add CPOH @ 15% 15% 414.75

Total cost per meter for pipe 3179.76Total cost per kg for specials 72.64

350 mm nominal dia (clear internal dia) of pipe with 5.0 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 454 Schedule of Rates 2014 - 2015

Page 289: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

2.5.7.12

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.3612 0.0056

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.3612-0.0056)*0.0056*1*7850= kg 49.110Add 5 % wastage

5% kg 2.455Total Weight kg 51.565

#REF! Cost of MS plate kg 51.565 45.00 2320.44 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 49.110 6.63 325.60 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.455 27.00 66.30

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1159.12 11.59 (C)

Material cost per meter Rs/meter 2591.34

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.3612*1= sqmt 1.135 52.88 60.00 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.3612-(0.0056*2))*1= sqmt 1.100 640.00 703.72 (E)

Total (A+B+C+D+E) 3355.05Total without ED 2987.26

Add Water Charges @ 1% 1% 29.87Add CPOH @ 15% 15% 452.57

Total cost per meter for pipe 3469.70Total cost per kg for specials 70.65

2.5.7.13

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.366 0.008

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.366-0.008)*0.008*1*7850= kg 70.631Add 5 % wastage

5% kg 3.532Total Weight kg 74.162

#REF! Cost of MS plate kg 74.162 45.00 3337.29 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 70.631 6.63 468.28 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.532 27.00 95.35

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1159.12 11.59 (C)

Material cost per meter Rs/meter 3721.81

350 mm nominal dia (clear internal dia) of pipe with 5.6 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

350 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 455 Schedule of Rates 2014 - 2015

Page 290: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.366*1= sqmt 1.150 52.88 60.80 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.366-(0.008*2))*1= sqmt 1.100 640.00 703.72 (E)

Total (A+B+C+D+E) 4486.33Total without ED 3994.09

Add Water Charges @ 1% 1% 39.94Add CPOH @ 15% 15% 605.10

Total cost per meter for pipe 4639.14Total cost per kg for specials 65.68

2.5.7.14

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.41 0.005

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.41-0.005)*0.005*1*7850= kg 49.940Add 5 % wastage

5% kg 2.497Total Weight kg 52.437

#REF! Cost of MS plate kg 52.437 45.00 2359.64 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 49.940 6.63 331.10 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.497 27.00 67.42

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1580.62 15.81 (C)

Material cost per meter Rs/meter 2639.13

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.41*1= sqmt 1.288 52.88 68.11 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.41-(0.005*2))*1= sqmt 1.257 640.00 804.25 (E)

Total (A+B+C+D+E) 3511.49Total without ED 3126.95

Add Water Charges @ 1% 1% 31.27Add CPOH @ 15% 15% 473.73

Total cost per meter for pipe 3631.95Total cost per kg for specials 72.73

2.5.7.15

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.412 0.006

400 mm nominal dia (clear internal dia) of pipe with 5.0 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

400 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 456 Schedule of Rates 2014 - 2015

Page 291: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.412-0.006)*0.006*1*7850= kg 60.075Add 5 % wastage

5% kg 3.004Total Weight kg 63.079

#REF! Cost of MS plate kg 63.079 45.00 2838.56 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 60.075 6.63 398.30 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.004 27.00 81.10

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1580.62 15.81 (C)

Material cost per meter Rs/meter 3171.57

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.412*1= sqmt 1.294 52.88 68.44 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.412-(0.006*2))*1= sqmt 1.257 640.00 804.25 (E)

Total (A+B+C+D+E) 4044.26Total without ED 3601.11

Add Water Charges @ 1% 1% 36.01Add CPOH @ 15% 15% 545.57

Total cost per meter for pipe 4182.69Total cost per kg for specials 69.62

2.5.7.16

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.4126 0.0063

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.4126-0.0063)*0.0063*1*7850= kg 63.126Add 5 % wastage

5% kg 3.156Total Weight kg 66.282

#REF! Cost of MS plate kg 66.282 45.00 2982.69 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 63.126 6.63 418.52 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.156 27.00 85.22

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1580.62 15.81 (C)

Material cost per meter Rs/meter 3331.80

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.4126*1= sqmt 1.296 52.88 68.54 (D)

400 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 457 Schedule of Rates 2014 - 2015

Page 292: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.4126-(0.0063*2))*1= sqmt 1.257 640.00 804.25 (E)

Total (A+B+C+D+E) 4204.59Total without ED 3743.81

Add Water Charges @ 1% 1% 37.44Add CPOH @ 15% 15% 567.19

Total cost per meter for pipe 4348.44Total cost per kg for specials 68.89

2.5.7.17

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.4176 0.0088

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.4176-0.0088)*0.0088*1*7850= kg 88.718Add 5 % wastage

5% kg 4.436Total Weight kg 93.154

#REF! Cost of MS plate kg 93.154 45.00 4191.94 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 88.718 6.63 588.20 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 4.436 27.00 119.77

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1580.62 15.81 (C)

Material cost per meter Rs/meter 4676.18

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.4176*1= sqmt 1.312 52.88 69.37 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.4176-(0.0088*2))*1= sqmt 1.257 640.00 804.25 (E)

Total (A+B+C+D+E) 5549.79Total without ED 4941.04

Add Water Charges @ 1% 1% 49.41Add CPOH @ 15% 15% 748.57

Total cost per meter for pipe 5739.01Total cost per kg for specials 64.69

2.5.7.18

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.462 0.006

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.462-0.006)*0.006*1*7850= kg 67.474Add 5 % wastage

400 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

450 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 458 Schedule of Rates 2014 - 2015

Page 293: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

5% kg 3.374Total Weight kg 70.848

#REF! Cost of MS plate kg 70.848 45.00 3188.14 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 67.474 6.63 447.35 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.374 27.00 91.09

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 3563.72

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.462*1= sqmt 1.451 52.88 76.75 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.462-(0.006*2))*1= sqmt 1.414 640.00 904.78 (E)

Total (A+B+C+D+E) 4545.24Total without ED 4047.38

Add Water Charges @ 1% 1% 40.47Add CPOH @ 15% 15% 613.18

Total cost per meter for pipe 4701.03Total cost per kg for specials 69.67

2.5.7.19

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.4626 0.0063

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.4626-0.0063)*0.0063*1*7850= kg 70.894Add 5 % wastage

5% kg 3.545Total Weight kg 74.439

#REF! Cost of MS plate kg 74.439 45.00 3349.75 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 70.894 6.63 470.03 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.545 27.00 95.71

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 3743.39

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.4626*1= sqmt 1.453 52.88 76.84 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.4626-(0.0063*2))*1= sqmt 1.414 640.00 904.78 (E)

Total (A+B+C+D+E) 4725.01Total without ED 4207.37

Add Water Charges @ 1% 1% 42.07Add CPOH @ 15% 15% 637.42

450 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 459 Schedule of Rates 2014 - 2015

Page 294: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Total cost per meter for pipe 4886.86Total cost per kg for specials 68.93

2.5.7.20

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.47 0.01

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.47-0.01)*0.01*1*7850= kg 113.443Add 5 % wastage

5% kg 5.672Total Weight kg 119.115

#REF! Cost of MS plate kg 119.115 45.00 5360.18 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 113.443 6.63 752.13 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 5.672 27.00 153.15

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 5978.47

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.47*1= sqmt 1.477 52.88 78.07 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.47-(0.01*2))*1= sqmt 1.414 640.00 904.78 (E)

Total (A+B+C+D+E) 6961.33Total without ED 6197.68

Add Water Charges @ 1% 1% 61.98Add CPOH @ 15% 15% 938.95

Total cost per meter for pipe 7198.61Total cost per kg for specials 63.46

2.5.7.21

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.512 0.006

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.512-0.006)*0.006*1*7850= kg 74.872Add 5 % wastage

5% kg 3.744Total Weight kg 78.616

#REF! Cost of MS plate kg 78.616 45.00 3537.72 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 74.872 6.63 496.40 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.744 27.00 101.08

450 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

500 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 460 Schedule of Rates 2014 - 2015

Page 295: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 3952.36

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.512*1= sqmt 1.608 52.88 85.05 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.512-(0.006*2))*1= sqmt 1.571 640.00 1005.31 (E)

Total (A+B+C+D+E) 5042.72Total without ED 4490.13

Add Water Charges @ 1% 1% 44.90Add CPOH @ 15% 15% 680.25

Total cost per meter for pipe 5215.29Total cost per kg for specials 69.66

2.5.7.22

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.5126 0.0063

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.5126-0.0063)*0.0063*1*7850= kg 78.663Add 5 % wastage

5% kg 3.933Total Weight kg 82.596

#REF! Cost of MS plate kg 82.596 45.00 3716.81 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 78.663 6.63 521.53 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.933 27.00 106.19

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 4151.46

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.5126*1= sqmt 1.610 52.88 85.15 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.5126-(0.0063*2))*1= sqmt 1.571 640.00 1005.31 (E)

Total (A+B+C+D+E) 5241.92Total without ED 4667.42

Add Water Charges @ 1% 1% 46.67Add CPOH @ 15% 15% 707.11

Total cost per meter for pipe 5421.21Total cost per kg for specials 68.92

2.5.7.23

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

500 mm nominal dia (clear internal dia) of pipe with 11.0 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

500 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 461 Schedule of Rates 2014 - 2015

Page 296: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.522 0.011

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.522-0.011)*0.011*1*7850= kg 138.622Add 5 % wastage

5% kg 6.931Total Weight kg 145.553

#REF! Cost of MS plate kg 145.553 45.00 6549.90 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 138.622 6.63 919.07 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 6.931 27.00 187.14

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 7301.15

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.522*1= sqmt 1.640 52.88 86.71 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.522-(0.011*2))*1= sqmt 1.571 640.00 1005.31 (E)

Total (A+B+C+D+E) 8393.17Total without ED 7472.02

Add Water Charges @ 1% 1% 74.72Add CPOH @ 15% 15% 1132.01

Total cost per meter for pipe 8678.75Total cost per kg for specials 62.61

2.5.7.24

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.612 0.006

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.612-0.006)*0.006*1*7850= kg 89.669Add 5 % wastage

5% kg 4.483Total Weight kg 94.153

#REF! Cost of MS plate kg 94.153 45.00 4236.87 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 89.669 6.63 594.51 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 4.483 27.00 121.05

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 4739.30

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

600 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 462 Schedule of Rates 2014 - 2015

Page 297: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

(3.1416)*0.612*1= sqmt 1.923 52.88 101.66 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.612-(0.006*2))*1= sqmt 1.885 640.00 1206.37 (E)

Total (A+B+C+D+E) 6047.34Total without ED 5385.30

Add Water Charges @ 1% 1% 53.85Add CPOH @ 15% 15% 815.87

Total cost per meter for pipe 6255.02Total cost per kg for specials 69.76

2.5.7.25

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.6126 0.0063

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.6126-0.0063)*0.0063*1*7850= kg 94.199Add 5 % wastage

5% kg 4.710Total Weight kg 98.909

#REF! Cost of MS plate kg 98.909 45.00 4450.92 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 94.199 6.63 624.54 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 4.710 27.00 127.17

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 4977.27

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.6126*1= sqmt 1.925 52.88 101.76 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.6126-(0.0063*2))*1= sqmt 1.885 640.00 1206.37 (E)

Total (A+B+C+D+E) 6285.40Total without ED 5597.17

Add Water Charges @ 1% 1% 55.97Add CPOH @ 15% 15% 847.97

Total cost per meter for pipe 6501.12Total cost per kg for specials 69.01

2.5.7.26

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.616 0.008

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850

600 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

600 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 463 Schedule of Rates 2014 - 2015

Page 298: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

(3.1416)*(0.616-0.008)*0.008*1*7850= kg 119.954Add 5 % wastage

5% kg 5.998Total Weight kg 125.951

#REF! Cost of MS plate kg 125.951 45.00 5667.81 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 119.954 6.63 795.29 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 5.998 27.00 161.94

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 6330.14

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.616*1= sqmt 1.935 52.88 102.33 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.616-(0.008*2))*1= sqmt 1.885 640.00 1206.37 (E)

Total (A+B+C+D+E) 7638.84Total without ED 6801.72

Add Water Charges @ 1% 1% 68.02Add CPOH @ 15% 15% 1030.46

Total cost per meter for pipe 7900.20Total cost per kg for specials 65.86

2.5.7.27

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.625 0.0125

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.625-0.0125)*0.0125*1*7850= kg 188.815Add 5 % wastage

5% kg 9.441Total Weight kg 198.255

#REF! Cost of MS plate kg 198.255 45.00 8921.49 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 188.815 6.63 1251.84 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 9.441 27.00 254.90

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 9947.41

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.625*1= sqmt 1.963 52.88 103.82 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.625-(0.0125*2))*1= sqmt 1.885 640.00 1206.37 (E)

Total (A+B+C+D+E) 11257.60Total without ED 10022.42

600 mm nominal dia (clear internal dia) of pipe with 12.5 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 464 Schedule of Rates 2014 - 2015

Page 299: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add Water Charges @ 1% 1% 100.22Add CPOH @ 15% 15% 1518.40

Total cost per meter for pipe 11641.04Total cost per kg for specials 61.65

2.5.7.28

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.712 0.006

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.712-0.006)*0.006*1*7850= kg 104.466Add 5 % wastage

5% kg 5.223Total Weight kg 109.689

#REF! Cost of MS plate kg 109.689 45.00 4936.02 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 104.466 6.63 692.61 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 5.223 27.00 141.03

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 5516.58

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.712*1= sqmt 2.237 52.88 118.27 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.712-(0.006*2))*1= sqmt 2.199 640.00 1407.43 (E)

Total (A+B+C+D+E) 7042.29Total without ED 6270.80

Add Water Charges @ 1% 1% 62.71Add CPOH @ 15% 15% 950.03

Total cost per meter for pipe 7283.54Total cost per kg for specials 69.72

2.5.7.29

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.7126 0.0063

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.7126-0.0063)*0.0063*1*7850= kg 109.736Add 5 % wastage

5% kg 5.487Total Weight kg 115.223

#REF! Cost of MS plate kg 115.223 45.00 5185.03 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 109.736 6.63 727.55 (B)

700 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

700 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 465 Schedule of Rates 2014 - 2015

Page 300: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_272 Cost of Scrap kg 5.487 27.00 148.14

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 5793.41

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.7126*1= sqmt 2.239 52.88 118.37 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.7126-(0.0063*2))*1= sqmt 2.199 640.00 1407.43 (E)

Total (A+B+C+D+E) 7319.22Total without ED 6517.27

Add Water Charges @ 1% 1% 65.17Add CPOH @ 15% 15% 987.37

Total cost per meter for pipe 7569.81Total cost per kg for specials 68.98

2.5.7.30

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.7142 0.0071

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.7142-0.0071)*0.0071*1*7850= kg 123.811Add 5 % wastage

5% kg 6.191Total Weight kg 130.001

#REF! Cost of MS plate kg 130.001 45.00 5850.06 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 123.811 6.63 820.87 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 6.191 27.00 167.14

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 6532.76

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.7142*1= sqmt 2.244 52.88 118.64 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.7142-(0.0071*2))*1= sqmt 2.199 640.00 1407.43 (E)

Total (A+B+C+D+E) 8058.83Total without ED 7175.52

Add Water Charges @ 1% 1% 71.76Add CPOH @ 15% 15% 1087.09

Total cost per meter for pipe 8334.37Total cost per kg for specials 67.32

2.5.7.31

700 mm nominal dia (clear internal dia) of pipe with 7.1 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

700 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 466 Schedule of Rates 2014 - 2015

Page 301: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.716 0.008

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.716-0.008)*0.008*1*7850= kg 139.683Add 5 % wastage

5% kg 6.984Total Weight kg 146.667

#REF! Cost of MS plate kg 146.667 45.00 6600.01 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 139.683 6.63 926.10 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 6.984 27.00 188.57

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 7366.51

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.716*1= sqmt 2.249 52.88 118.94 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.716-(0.008*2))*1= sqmt 2.199 640.00 1407.43 (E)

Total (A+B+C+D+E) 8892.88Total without ED 7917.82

Add Water Charges @ 1% 1% 79.18Add CPOH @ 15% 15% 1199.55

Total cost per meter for pipe 9196.55Total cost per kg for specials 65.84

2.5.7.32

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.7284 0.0142

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.7284-0.0142)*0.0142*1*7850= kg 250.108Add 5 % wastage

5% kg 12.505Total Weight kg 262.613

#REF! Cost of MS plate kg 262.613 45.00 11817.61 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 250.108 6.63 1658.22 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 12.505 27.00 337.65

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 13167.16

700 mm nominal dia (clear internal dia) of pipe with 14.2 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 467 Schedule of Rates 2014 - 2015

Page 302: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.7284*1= sqmt 2.288 52.88 121.00 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.7284-(0.0142*2))*1= sqmt 2.199 640.00 1407.43 (E)

Total (A+B+C+D+E) 14695.59Total without ED 13082.21

Add Water Charges @ 1% 1% 130.82Add CPOH @ 15% 15% 1981.95

Total cost per meter for pipe 15194.98Total cost per kg for specials 60.75

2.5.7.33

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.8142 0.0071

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.8142-0.0071)*0.0071*1*7850= kg 141.321Add 5 % wastage

5% kg 7.066Total Weight kg 148.387

#REF! Cost of MS plate kg 148.387 45.00 6677.39 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 141.321 6.63 936.96 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 7.066 27.00 190.78

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 7452.54

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.8142*1= sqmt 2.558 52.88 135.25 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.8142-(0.0071*2))*1= sqmt 2.513 640.00 1608.50 (E)

Total (A+B+C+D+E) 9196.29Total without ED 8187.85

Add Water Charges @ 1% 1% 81.88Add CPOH @ 15% 15% 1240.46

Total cost per meter for pipe 9510.19Total cost per kg for specials 67.30

2.5.7.34

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.816 0.008

Length of pipe =

1.0

800 mm nominal dia (clear internal dia) of pipe with 7.1 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

800 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 468 Schedule of Rates 2014 - 2015

Page 303: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.816-0.008)*0.008*1*7850= kg 159.412Add 5 % wastage

5% kg 7.971Total Weight kg 167.383

#REF! Cost of MS plate kg 167.383 45.00 7532.21 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 159.412 6.63 1056.90 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 7.971 27.00 215.21

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 8402.89

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.816*1= sqmt 2.564 52.88 135.55 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.816-(0.008*2))*1= sqmt 2.513 640.00 1608.50 (E)

Total (A+B+C+D+E) 10146.93Total without ED 9033.92

Add Water Charges @ 1% 1% 90.34Add CPOH @ 15% 15% 1368.64

Total cost per meter for pipe 10492.90Total cost per kg for specials 65.82

2.5.7.35

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.836 0.018

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.836-0.018)*0.018*1*7850= kg 363.116Add 5 % wastage

5% kg 18.156Total Weight kg 381.272

#REF! Cost of MS plate kg 381.272 45.00 17157.23 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 363.116 6.63 2407.46 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 18.156 27.00 490.21

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 19103.46

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.836*1= sqmt 2.626 52.88 138.87 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.836-(0.018*2))*1= sqmt 2.513 640.00 1608.50 (E)

800 mm nominal dia (clear internal dia) of pipe with 18.0 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 469 Schedule of Rates 2014 - 2015

Page 304: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Total (A+B+C+D+E) 20850.83Total without ED 18560.35

Add Water Charges @ 1% 1% 185.60Add CPOH @ 15% 15% 2811.89

Total cost per meter for pipe 21557.85Total cost per kg for specials 59.37

2.5.7.36

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.916 0.008

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.916-0.008)*0.008*1*7850= kg 179.141Add 5 % wastage

5% kg 8.957Total Weight kg 188.098

#REF! Cost of MS plate kg 188.098 45.00 8464.42 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 179.141 6.63 1187.71 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 8.957 27.00 241.84

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 4346.71 43.47 (C)

Material cost per meter Rs/meter 9453.75

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.916*1= sqmt 2.878 52.88 152.16 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.916-(0.008*2))*1= sqmt 2.827 640.00 1809.56 (E)

Total (A+B+C+D+E) 11415.47Total without ED 10164.51

Add Water Charges @ 1% 1% 101.65Add CPOH @ 15% 15% 1539.92

Total cost per meter for pipe 11806.08Total cost per kg for specials 65.90

2.5.7.37

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.9176 0.0088

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.9176-0.0088)*0.0088*1*7850= kg 197.229Add 5 % wastage

5% kg 9.861Total Weight kg 207.090

#REF! Cost of MS plate kg 207.090 45.00 9319.06 (A)

900 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

900 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 470 Schedule of Rates 2014 - 2015

Page 305: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_320 Cost of Fabrication kg 197.229 6.63 1307.63 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 9.861 27.00 266.26

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 4346.71 43.47 (C)

Material cost per meter Rs/meter 10403.90

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.9176*1= sqmt 2.883 52.88 152.43 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.9176-(0.0088*2))*1= sqmt 2.827 640.00 1809.56 (E)

Total (A+B+C+D+E) 12365.88Total without ED 11010.37

Add Water Charges @ 1% 1% 110.10Add CPOH @ 15% 15% 1668.07

Total cost per meter for pipe 12788.55Total cost per kg for specials 64.84

2.5.7.38

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.92 0.01

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.92-0.01)*0.01*1*7850= kg 224.420Add 5 % wastage

5% kg 11.221Total Weight kg 235.641

#REF! Cost of MS plate kg 235.641 45.00 10603.83 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 224.420 6.63 1487.90 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 11.221 27.00 302.97

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 4346.71 43.47 (C)

Material cost per meter Rs/meter 11832.23

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.92*1= sqmt 2.890 52.88 152.83 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.92-(0.01*2))*1= sqmt 2.827 640.00 1809.56 (E)

Total (A+B+C+D+E) 13794.62Total without ED 12281.94

Add Water Charges @ 1% 1% 122.82Add CPOH @ 15% 15% 1860.71

Total cost per meter for pipe 14265.47Total cost per kg for specials 63.57

900 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 471 Schedule of Rates 2014 - 2015

Page 306: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

2.5.7.39

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =0.935 0.0175

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(0.935-0.0175)*0.0175*1*7850= kg 395.971Add 5 % wastage

5% kg 19.799Total Weight kg 415.770

#REF! Cost of MS plate kg 415.770 45.00 18709.64 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 395.971 6.63 2625.29 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 19.799 27.00 534.56

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 4346.71 43.47 (C)

Material cost per meter Rs/meter 20843.84

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.935*1= sqmt 2.937 52.88 155.32 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.935-(0.0175*2))*1= sqmt 2.827 640.00 1809.56 (E)

Total (A+B+C+D+E) 22808.71Total without ED 20304.45

Add Water Charges @ 1% 1% 203.04Add CPOH @ 15% 15% 3076.12

Total cost per meter for pipe 23583.62Total cost per kg for specials 59.56

2.5.7.40

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.0176 0.0088

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.0176-0.0088)*0.0088*1*7850= kg 218.931Add 5 % wastage

5% kg 10.947Total Weight kg 229.878

#REF! Cost of MS plate kg 229.878 45.00 10344.49 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 218.931 6.63 1451.51 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 10.947 27.00 295.56

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 11558.40

1000 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

900 mm nominal dia (clear internal dia) of pipe with 17.5 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 472 Schedule of Rates 2014 - 2015

Page 307: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.0176*1= sqmt 3.197 52.88 169.04 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.0176-(0.0088*2))*1= sqmt 3.142 640.00 2010.62 (E)

Total (A+B+C+D+E) 13738.06Total without ED 12233.20

Add Water Charges @ 1% 1% 122.33Add CPOH @ 15% 15% 1853.33

Total cost per meter for pipe 14208.86Total cost per kg for specials 64.90

2.5.7.41

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.02 0.01

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.02-0.01)*0.01*1*7850= kg 249.081Add 5 % wastage

5% kg 12.454Total Weight kg 261.535

#REF! Cost of MS plate kg 261.535 45.00 11769.09 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 249.081 6.63 1651.41 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 12.454 27.00 336.26

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 13142.19

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.02*1= sqmt 3.204 52.88 169.44 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.02-(0.01*2))*1= sqmt 3.142 640.00 2010.62 (E)

Total (A+B+C+D+E) 15322.25Total without ED 13643.12

Add Water Charges @ 1% 1% 136.43Add CPOH @ 15% 15% 2066.93

Total cost per meter for pipe 15846.48Total cost per kg for specials 63.62

2.5.7.42

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.04 0.02

1000 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

1000 mm nominal dia (clear internal dia) of pipe with 20.0 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 473 Schedule of Rates 2014 - 2015

Page 308: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.04-0.02)*0.02*1*7850= kg 503.095Add 5 % wastage

5% kg 25.155Total Weight kg 528.249

#REF! Cost of MS plate kg 528.249 45.00 23771.22 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 503.095 6.63 3335.52 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 25.155 27.00 679.18

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 26485.52

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.04*1= sqmt 3.267 52.88 172.76 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.04-(0.02*2))*1= sqmt 3.142 640.00 2010.62 (E)

Total (A+B+C+D+E) 28668.90Total without ED 25521.59

Add Water Charges @ 1% 1% 255.22Add CPOH @ 15% 15% 3866.52

Total cost per meter for pipe 29643.33Total cost per kg for specials 58.92

2.5.7.43

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.0676 0.0088

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.0676-0.0088)*0.0088*1*7850= kg 229.782Add 5 % wastage

5% kg 11.489Total Weight kg 241.271

#REF! Cost of MS plate kg 241.271 45.00 10857.20 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 229.782 6.63 1523.46 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 11.489 27.00 310.21

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 12128.41

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.0676*1= sqmt 3.354 52.88 177.34 (D)

1050 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 474 Schedule of Rates 2014 - 2015

Page 309: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.0676-(0.0088*2))*1= sqmt 3.299 640.00 2111.15 (E)

Total (A+B+C+D+E) 14416.90Total without ED 12837.37

Add Water Charges @ 1% 1% 128.37Add CPOH @ 15% 15% 1944.86

Total cost per meter for pipe 14910.60Total cost per kg for specials 64.89

2.5.7.44

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.07 0.01

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.07-0.01)*0.01*1*7850= kg 261.412Add 5 % wastage

5% kg 13.071Total Weight kg 274.483

#REF! Cost of MS plate kg 274.483 45.00 12351.71 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 261.412 6.63 1733.16 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 13.071 27.00 352.91

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 13789.92

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.07*1= sqmt 3.362 52.88 177.74 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.07-(0.01*2))*1= sqmt 3.299 640.00 2111.15 (E)

Total (A+B+C+D+E) 16078.82Total without ED 14316.47

Add Water Charges @ 1% 1% 143.16Add CPOH @ 15% 15% 2168.94

Total cost per meter for pipe 16628.58Total cost per kg for specials 63.61

2.5.7.45

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.072 0.011

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.072-0.011)*0.011*1*7850= kg 287.824Add 5 % wastage

1050 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

1050 mm nominal dia (clear internal dia) of pipe with 11.0 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 475 Schedule of Rates 2014 - 2015

Page 310: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

5% kg 14.391Total Weight kg 302.216

#REF! Cost of MS plate kg 302.216 45.00 13599.70 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 287.824 6.63 1908.28 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 14.391 27.00 388.56

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 15177.37

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.072*1= sqmt 3.368 52.88 178.08 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.072-(0.011*2))*1= sqmt 3.299 640.00 2111.15 (E)

Total (A+B+C+D+E) 17466.60Total without ED 15551.58

Add Water Charges @ 1% 1% 155.52Add CPOH @ 15% 15% 2356.07

Total cost per meter for pipe 18063.17Total cost per kg for specials 62.76

2.5.7.46

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.1176 0.0088

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.1176-0.0088)*0.0088*1*7850= kg 240.633Add 5 % wastage

5% kg 12.032Total Weight kg 252.665

#REF! Cost of MS plate kg 252.665 45.00 11369.92 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 240.633 6.63 1595.40 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 12.032 27.00 324.85

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 12698.41

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.1176*1= sqmt 3.511 52.88 185.65 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.1176-(0.0088*2))*1= sqmt 3.456 640.00 2211.68 (E)

Total (A+B+C+D+E) 15095.75Total without ED 13441.54

Add Water Charges @ 1% 1% 134.42Add CPOH @ 15% 15% 2036.39

1100 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 476 Schedule of Rates 2014 - 2015

Page 311: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Total cost per meter for pipe 15612.34Total cost per kg for specials 64.88

2.5.7.47

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.12 0.01

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.12-0.01)*0.01*1*7850= kg 273.743Add 5 % wastage

5% kg 13.687Total Weight kg 287.430

#REF! Cost of MS plate kg 287.430 45.00 12934.34 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 273.743 6.63 1814.91 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 13.687 27.00 369.55

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 14437.66

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.12*1= sqmt 3.519 52.88 186.05 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.12-(0.01*2))*1= sqmt 3.456 640.00 2211.68 (E)

Total (A+B+C+D+E) 16835.39Total without ED 14989.81

Add Water Charges @ 1% 1% 149.90Add CPOH @ 15% 15% 2270.96

Total cost per meter for pipe 17410.67Total cost per kg for specials 63.60

2.5.7.48

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.122 0.011

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.122-0.011)*0.011*1*7850= kg 301.388Add 5 % wastage

5% kg 15.069Total Weight kg 316.458

#REF! Cost of MS plate kg 316.458 45.00 14240.59 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 301.388 6.63 1998.20 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 15.069 27.00 406.87

1100 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

1100 mm nominal dia (clear internal dia) of pipe with 11.0 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 477 Schedule of Rates 2014 - 2015

Page 312: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 15889.88

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.122*1= sqmt 3.525 52.88 186.38 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.122-(0.011*2))*1= sqmt 3.456 640.00 2211.68 (E)

Total (A+B+C+D+E) 18287.94Total without ED 16282.58

Add Water Charges @ 1% 1% 162.83Add CPOH @ 15% 15% 2466.81

Total cost per meter for pipe 18912.21Total cost per kg for specials 62.75

2.5.7.49

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.22 0.01

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.22-0.01)*0.01*1*7850= kg 298.404Add 5 % wastage

5% kg 14.920Total Weight kg 313.324

#REF! Cost of MS plate kg 313.324 45.00 14099.60 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 298.404 6.63 1978.42 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 14.920 27.00 402.85

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 15733.13

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.22*1= sqmt 3.833 52.88 202.66 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.22-(0.01*2))*1= sqmt 3.770 640.00 2412.74 (E)

Total (A+B+C+D+E) 18348.53Total without ED 16336.50

Add Water Charges @ 1% 1% 163.37Add CPOH @ 15% 15% 2474.98

Total cost per meter for pipe 18974.85Total cost per kg for specials 63.59

2.5.7.50

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

1200 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

1200 mm nominal dia (clear internal dia) of pipe with 11.0 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 478 Schedule of Rates 2014 - 2015

Page 313: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.222 0.011

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.222-0.011)*0.011*1*7850= kg 328.516Add 5 % wastage

5% kg 16.426Total Weight kg 344.942

#REF! Cost of MS plate kg 344.942 45.00 15522.37 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 328.516 6.63 2178.06 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 16.426 27.00 443.50

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 17314.89

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.222*1= sqmt 3.839 52.88 202.99 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.222-(0.011*2))*1= sqmt 3.770 640.00 2412.74 (E)

Total (A+B+C+D+E) 19930.63Total without ED 17744.57

Add Water Charges @ 1% 1% 177.45Add CPOH @ 15% 15% 2688.30

Total cost per meter for pipe 20610.31Total cost per kg for specials 62.74

2.5.7.51

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.224 0.012

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.224-0.012)*0.012*1*7850= kg 358.677Add 5 % wastage

5% kg 17.934Total Weight kg 376.611

#REF! Cost of MS plate kg 376.611 45.00 16947.48 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 358.677 6.63 2378.03 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 17.934 27.00 484.21

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 18899.25

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

1200 mm nominal dia (clear internal dia) of pipe with 12.0 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 479 Schedule of Rates 2014 - 2015

Page 314: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

(3.1416)*1.224*1= sqmt 3.845 52.88 203.32 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.224-(0.012*2))*1= sqmt 3.770 640.00 2412.74 (E)

Total (A+B+C+D+E) 21515.32Total without ED 19154.93

Add Water Charges @ 1% 1% 191.55Add CPOH @ 15% 15% 2901.97

Total cost per meter for pipe 22248.46Total cost per kg for specials 62.03

2.5.7.52

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.225 0.0125

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.225-0.0125)*0.0125*1*7850= kg 373.776Add 5 % wastage

5% kg 18.689Total Weight kg 392.465

#REF! Cost of MS plate kg 392.465 45.00 17660.91 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 373.776 6.63 2478.13 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 18.689 27.00 504.60

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 19692.40

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.225*1= sqmt 3.848 52.88 203.49 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.225-(0.0125*2))*1= sqmt 3.770 640.00 2412.74 (E)

Total (A+B+C+D+E) 22308.64Total without ED 19860.98

Add Water Charges @ 1% 1% 198.61Add CPOH @ 15% 15% 3008.94

Total cost per meter for pipe 23068.53Total cost per kg for specials 61.72

2.5.7.53

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.424 0.012

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850

1400 mm nominal dia (clear internal dia) of pipe with 12 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

1200 mm nominal dia (clear internal dia) of pipe with 12.5 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 480 Schedule of Rates 2014 - 2015

Page 315: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

(3.1416)*(1.424-0.012)*0.012*1*7850= kg 417.864Add 5 % wastage

5% kg 20.893Total Weight kg 438.758

#REF! Cost of MS plate kg 438.758 45.00 19744.10 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 417.864 6.63 2770.44 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 20.893 27.00 564.12

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 7244.52 72.45 (C)

Material cost per meter Rs/meter 22022.87

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.424*1= sqmt 4.474 52.88 236.55 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.424-(0.012*2))*1= sqmt 4.398 640.00 2814.87 (E)

Total (A+B+C+D+E) 25074.28Total without ED 22323.99

Add Water Charges @ 1% 1% 223.24Add CPOH @ 15% 15% 3382.08

Total cost per meter for pipe 25929.32Total cost per kg for specials 62.05

2.5.7.54

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.425 0.0125

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.425-0.0125)*0.0125*1*7850= kg 435.430Add 5 % wastage

5% kg 21.771Total Weight kg 457.201

#REF! Cost of MS plate kg 457.201 45.00 20574.05 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 435.430 6.63 2886.90 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 21.771 27.00 587.83

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 7244.52 72.45 (C)

Material cost per meter Rs/meter 22945.56

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.425*1= sqmt 4.477 52.88 236.71 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.425-(0.0125*2))*1= sqmt 4.398 640.00 2814.87 (E)

Total (A+B+C+D+E) 25997.15Total without ED 23145.34

1400 mm nominal dia (clear internal dia) of pipe with 12.5 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 481 Schedule of Rates 2014 - 2015

Page 316: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add Water Charges @ 1% 1% 231.45Add CPOH @ 15% 15% 3506.52

Total cost per meter for pipe 26883.31Total cost per kg for specials 61.74

2.5.7.55

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.4284 0.0142

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.4284-0.0142)*0.0142*1*7850= kg 495.243Add 5 % wastage

5% kg 24.762Total Weight kg 520.006

#REF! Cost of MS plate kg 520.006 45.00 23400.25 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 495.243 6.63 3283.46 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 24.762 27.00 668.58

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 7244.52 72.45 (C)

Material cost per meter Rs/meter 26087.58

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.4284*1= sqmt 4.487 52.88 237.28 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.4284-(0.0142*2))*1= sqmt 4.398 640.00 2814.87 (E)

Total (A+B+C+D+E) 29139.73Total without ED 25942.22

Add Water Charges @ 1% 1% 259.42Add CPOH @ 15% 15% 3930.25

Total cost per meter for pipe 30131.89Total cost per kg for specials 60.84

2.5.7.56

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.524 0.012

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.524-0.012)*0.012*1*7850= kg 447.458Add 5 % wastage

5% kg 22.373Total Weight kg 469.831

#REF! Cost of MS plate kg 469.831 45.00 21142.40 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 447.458 6.63 2966.65 (B)

1400 mm nominal dia (clear internal dia) of pipe with 14.2 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

1500 mm nominal dia (clear internal dia) of pipe with 12 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 482 Schedule of Rates 2014 - 2015

Page 317: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_272 Cost of Scrap kg 22.373 27.00 604.07

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 8693.42 86.93 (C)

Material cost per meter Rs/meter 23591.92

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.524*1= sqmt 4.788 52.88 253.16 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.524-(0.012*2))*1= sqmt 4.712 640.00 3015.93 (E)

Total (A+B+C+D+E) 26861.01Total without ED 23915.76

Add Water Charges @ 1% 1% 239.16Add CPOH @ 15% 15% 3623.24

Total cost per meter for pipe 27778.16Total cost per kg for specials 62.08

2.5.7.57

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.6284 0.0142

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.6284-0.0142)*0.0142*1*7850= kg 565.282Add 5 % wastage

5% kg 28.264Total Weight kg 593.546

#REF! Cost of MS plate kg 593.546 45.00 26709.58 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 565.282 6.63 3747.82 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 28.264 27.00 763.13

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 8693.42 86.93 (C)

Material cost per meter Rs/meter 29781.20

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.6284*1= sqmt 5.116 52.88 270.50 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.6284-(0.0142*2))*1= sqmt 5.027 640.00 3216.99 (E)

Total (A+B+C+D+E) 33268.69Total without ED 29618.58

Add Water Charges @ 1% 1% 296.19Add CPOH @ 15% 15% 4487.22

Total cost per meter for pipe 34401.98Total cost per kg for specials 60.86

2.5.7.58

1600 mm nominal dia (clear internal dia) of pipe with 14.2 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

1600 mm nominal dia (clear internal dia) of pipe with 16.0 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 483 Schedule of Rates 2014 - 2015

Page 318: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.632 0.016

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.632-0.016)*0.016*1*7850= kg 637.648Add 5 % wastage

5% kg 31.882Total Weight kg 669.530

#REF! Cost of MS plate kg 669.530 45.00 30128.86 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 637.648 6.63 4227.60 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 31.882 27.00 860.82

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 8693.42 86.93 (C)

Material cost per meter Rs/meter 33582.57

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.632*1= sqmt 5.127 52.88 271.10 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.632-(0.016*2))*1= sqmt 5.027 640.00 3216.99 (E)

Total (A+B+C+D+E) 37070.66Total without ED 33002.32

Add Water Charges @ 1% 1% 330.02Add CPOH @ 15% 15% 4999.85

Total cost per meter for pipe 38332.20Total cost per kg for specials 60.12

2.5.7.59

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.8284 0.0142

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.8284-0.0142)*0.0142*1*7850= kg 635.321Add 5 % wastage

5% kg 31.766Total Weight kg 667.087

#REF! Cost of MS plate kg 667.087 45.00 30018.91 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 635.321 6.63 4212.18 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 31.766 27.00 857.68

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 10142.33 101.42 (C)

Material cost per meter Rs/meter 33474.82

1800 mm nominal dia (clear internal dia) of pipe with 14.2 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 484 Schedule of Rates 2014 - 2015

Page 319: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.8284*1= sqmt 5.744 52.88 303.72 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.8284-(0.0142*2))*1= sqmt 5.655 640.00 3619.11 (E)

Total (A+B+C+D+E) 37397.66Total without ED 33294.94

Add Water Charges @ 1% 1% 332.95Add CPOH @ 15% 15% 5044.18

Total cost per meter for pipe 38672.08Total cost per kg for specials 60.87

2.5.7.60

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.832 0.016

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.832-0.016)*0.016*1*7850= kg 716.565Add 5 % wastage

5% kg 35.828Total Weight kg 752.393

#REF! Cost of MS plate kg 752.393 45.00 33857.68 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 716.565 6.63 4750.82 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 35.828 27.00 967.36

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 10142.33 101.42 (C)

Material cost per meter Rs/meter 37742.56

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.832*1= sqmt 5.755 52.88 304.32 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.832-(0.016*2))*1= sqmt 5.655 640.00 3619.11 (E)

Total (A+B+C+D+E) 41666.00Total without ED 37093.75

Add Water Charges @ 1% 1% 370.94Add CPOH @ 15% 15% 5619.70

Total cost per meter for pipe 43084.39Total cost per kg for specials 60.13

2.5.7.61

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =1.835 0.0175

Length of pipe =

1.0

1800 mm nominal dia (clear internal dia) of pipe with 17.5 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

1800 mm nominal dia (clear internal dia) of pipe with 16.0 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 485 Schedule of Rates 2014 - 2015

Page 320: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(1.835-0.0175)*0.0175*1*7850= kg 784.390Add 5 % wastage

5% kg 39.219Total Weight kg 823.609

#REF! Cost of MS plate kg 823.609 45.00 37062.42 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 784.390 6.63 5200.51 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 39.219 27.00 1058.93

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 10142.33 101.42 (C)

Material cost per meter Rs/meter 41305.43

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.835*1= sqmt 5.765 52.88 304.82 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.835-(0.0175*2))*1= sqmt 5.655 640.00 3619.11 (E)

Total (A+B+C+D+E) 45229.36Total without ED 40265.13

Add Water Charges @ 1% 1% 402.65Add CPOH @ 15% 15% 6100.17

Total cost per meter for pipe 46767.94Total cost per kg for specials 59.62

2.5.7.62

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =2.032 0.016

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(2.032-0.016)*0.016*1*7850= kg 795.481Add 5 % wastage

5% kg 39.774Total Weight kg 835.255

#REF! Cost of MS plate kg 835.255 45.00 37586.50 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 795.481 6.63 5274.04 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 39.774 27.00 1073.90

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 11591.23 115.91 (C)

Material cost per meter Rs/meter 41902.55

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*2.032*1= sqmt 6.384 52.88 337.55 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(2.032-(0.016*2))*1= sqmt 6.283 640.00 4021.24 (E)

2000 mm nominal dia (clear internal dia) of pipe with 16.0 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 486 Schedule of Rates 2014 - 2015

Page 321: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Total (A+B+C+D+E) 46261.34Total without ED 41185.17

Add Water Charges @ 1% 1% 411.85Add CPOH @ 15% 15% 6239.55

Total cost per meter for pipe 47836.58Total cost per kg for specials 60.14

2.5.7.63

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =2.035 0.0175

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(2.035-0.0175)*0.0175*1*7850= kg 870.705Add 5 % wastage

5% kg 43.535Total Weight kg 914.240

#REF! Cost of MS plate kg 914.240 45.00 41140.82 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 870.705 6.63 5772.78 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 43.535 27.00 1175.45

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 11591.23 115.91 (C)

Material cost per meter Rs/meter 45854.05

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*2.035*1= sqmt 6.393 52.88 338.04 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(2.035-(0.0175*2))*1= sqmt 6.283 640.00 4021.24 (E)

Total (A+B+C+D+E) 50213.34Total without ED 44702.44

Add Water Charges @ 1% 1% 447.02Add CPOH @ 15% 15% 6772.42

Total cost per meter for pipe 51921.89Total cost per kg for specials 59.63

2.5.7.64

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =2.04 0.02

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(2.04-0.02)*0.02*1*7850= kg 996.325Add 5 % wastage

5% kg 49.816Total Weight kg 1046.141

#REF! Cost of MS plate kg 1046.141 45.00 47076.34 (A)

2000 mm nominal dia (clear internal dia) of pipe with 17.5 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

2000 mm nominal dia (clear internal dia) of pipe with 20.0 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 487 Schedule of Rates 2014 - 2015

Page 322: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_320 Cost of Fabrication kg 996.325 6.63 6605.63 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 49.816 27.00 1345.04

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 11591.23 115.91 (C)

Material cost per meter Rs/meter 52452.85

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*2.04*1= sqmt 6.409 52.88 338.87 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(2.04-(0.02*2))*1= sqmt 6.283 640.00 4021.24 (E)

Total (A+B+C+D+E) 56812.96Total without ED 50576.08

Add Water Charges @ 1% 1% 505.76Add CPOH @ 15% 15% 7662.28

Total cost per meter for pipe 58744.12Total cost per kg for specials 58.96

2.5.7.65

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =2.235 0.0175

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(2.235-0.0175)*0.0175*1*7850= kg 957.020Add 5 % wastage

5% kg 47.851Total Weight kg 1004.871

#REF! Cost of MS plate kg 1004.871 45.00 45219.22 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 957.020 6.63 6345.05 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 47.851 27.00 1291.98

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 13040.13 130.40 (C)

Material cost per meter Rs/meter 50402.68

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*2.235*1= sqmt 7.021 52.88 371.27 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(2.235-(0.0175*2))*1= sqmt 6.912 640.00 4423.36 (E)

Total (A+B+C+D+E) 55197.31Total without ED 49139.76

Add Water Charges @ 1% 1% 491.40Add CPOH @ 15% 15% 7444.67

Total cost per meter for pipe 57075.83Total cost per kg for specials 59.64

2200 mm nominal dia (clear internal dia) of pipe with 17.5 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 488 Schedule of Rates 2014 - 2015

Page 323: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

2.5.7.66

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =2.24 0.02

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(2.24-0.02)*0.02*1*7850= kg 1094.971Add 5 % wastage

5% kg 54.749Total Weight kg 1149.719

#REF! Cost of MS plate kg 1149.719 45.00 51737.37 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 1094.971 6.63 7259.66 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 54.749 27.00 1478.21

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 13040.13 130.40 (C)

Material cost per meter Rs/meter 57649.21

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*2.24*1= sqmt 7.037 52.88 372.10 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(2.24-(0.02*2))*1= sqmt 6.912 640.00 4423.36 (E)

Total (A+B+C+D+E) 62444.67Total without ED 55589.88

Add Water Charges @ 1% 1% 555.90Add CPOH @ 15% 15% 8421.87

Total cost per meter for pipe 64567.65Total cost per kg for specials 58.97

2.5.7.67

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =2.2444 0.0222

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(2.2444-0.0222)*0.0222*1*7850= kg 1216.622Add 5 % wastage

5% kg 60.831Total Weight kg 1277.453

#REF! Cost of MS plate kg 1277.453 45.00 57485.39 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 1216.622 6.63 8066.20 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 60.831 27.00 1642.44

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 13040.13 130.40 (C)

Material cost per meter Rs/meter 64039.55

2200 mm nominal dia (clear internal dia) of pipe with 20.0 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

2200 mm nominal dia (clear internal dia) of pipe with 22.2 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 489 Schedule of Rates 2014 - 2015

Page 324: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*2.2444*1= sqmt 7.051 52.88 372.83 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(2.2444-(0.0222*2))*1= sqmt 6.912 640.00 4423.36 (E)

Total (A+B+C+D+E) 68835.74Total without ED 61277.91

Add Water Charges @ 1% 1% 612.78Add CPOH @ 15% 15% 9283.60

Total cost per meter for pipe 71174.29Total cost per kg for specials 58.50

2.5.7.68

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =2.54 0.02

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(2.54-0.02)*0.02*1*7850= kg 1242.940Add 5 % wastage

5% kg 62.147Total Weight kg 1305.087

#REF! Cost of MS plate kg 1305.087 45.00 58728.90 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 1242.940 6.63 8240.69 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 62.147 27.00 1677.97

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 14489.04 144.89 (C)

Material cost per meter Rs/meter 65436.51

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*2.54*1= sqmt 7.980 52.88 421.93 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(2.54-(0.02*2))*1= sqmt 7.854 640.00 5026.55 (E)

Total (A+B+C+D+E) 70884.99Total without ED 63103.33

Add Water Charges @ 1% 1% 631.03Add CPOH @ 15% 15% 9560.15

Total cost per meter for pipe 73294.52Total cost per kg for specials 58.97

2.5.7.69

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =2.5444 0.0222

2500 mm nominal dia (clear internal dia) of pipe with 22.2 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

2500 mm nominal dia (clear internal dia) of pipe with 20.0 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 490 Schedule of Rates 2014 - 2015

Page 325: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(2.5444-0.0222)*0.0222*1*7850= kg 1380.868Add 5 % wastage

5% kg 69.043Total Weight kg 1449.911

#REF! Cost of MS plate kg 1449.911 45.00 65245.99 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 1380.868 6.63 9155.15 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 69.043 27.00 1864.17

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 14489.04 144.89 (C)

Material cost per meter Rs/meter 72681.86

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*2.5444*1= sqmt 7.993 52.88 422.66 (D)

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(2.5444-(0.0222*2))*1= sqmt 7.854 640.00 5026.55 (E)

Total (A+B+C+D+E) 78131.07Total without ED 69552.32

Add Water Charges @ 1% 1% 695.52Add CPOH @ 15% 15% 10537.18

Total cost per meter for pipe 80785.02Total cost per kg for specials 58.50

2.5.7.70

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) =thickness of

pipe (t1) =2.55 0.025

Length of pipe =

1.0

Weight of MS plate = pi()*(d-t1)*t1*L*7850(3.1416)*(2.55-0.025)*0.025*1*7850= kg 1556.757Add 5 % wastage

5% kg 77.838Total Weight kg 1634.595

#REF! Cost of MS plate kg 1634.595 45.00 73556.78 (A)Quotation_Volume

III_pg no_320 Cost of Fabrication kg 1556.757 6.63 10321.30 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 77.838 27.00 2101.62

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 14489.04 144.89 (C)

Material cost per meter Rs/meter 81921.35

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*2.55*1= sqmt 8.011 52.88 423.59 (D)

2500 mm nominal dia (clear internal dia) of pipe with 25.0 mm thick plate, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 491 Schedule of Rates 2014 - 2015

Page 326: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Vol III_pg no 448

Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(2.55-(0.025*2))*1= sqmt 7.854 640.00 5026.55 (E)

Total (A+B+C+D+E) 87371.49Total without ED 77776.26

Add Water Charges @ 1% 1% 777.76Add CPOH @ 15% 15% 11783.10

Total cost per meter for pipe 90337.12Total cost per kg for specials 58.03

Delhi Jal Board 492 Schedule of Rates 2014 - 2015

Page 327: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

2.5.8

2.5.8.1

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.159 0.0045Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(0.159-0.0045)*0.0045*1*7850= kg 17.146Add 2 % wastage

2% kg 0.343Total Weight kg 17.489

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 17.489 34.21 598.30 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 17.146 6.63 113.68 (B)

Quotation_Volume III_pg no_272 Cost of scrap kg 0.343 27.00 9.26

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 289.78 2.90 (C)

Material cost per meter Rs/meter 705.61

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.159*1= sqmt 0.500 52.88 26.41 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.159-(0.0045*2))*1= sqmt 0.471 640.00 301.59 (E)

Total (A+B+C+D+E) 1033.62Total without ED 920.24

Add Water Charges @ 1% 1% 9.20Add CPOH @ 15% 15% 139.42

Total cost per meter for pipe 1068.85Total cost per kg for specials 62.34

2.5.8.2

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.21 0.005Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(0.21-0.005)*0.005*1*7850= kg 25.278Add 2 % wastage

2% kg 0.506Total Weight kg 25.784

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 25.784 34.21 882.06 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 25.278 6.63 167.59 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.506 27.00 13.65

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 471.38 4.71 (C)

200 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Providing Mild Steel Pipes / specials fabricated / manufactured out of MS coil of steel grade Fe410 as per IS 3589:2001; internally coated withfood grade epoxy coating and external / outside bitumastic coating; minimum thickness of M.S. Coil as specified; complete in all respect; withupto date amendments in relevant IS codes and as directed by Engineer-in-charge . The rates are excluding excise duty component.

150 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 505 Schedule of Rates 2014 - 2015

Page 328: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Material cost per meter Rs/meter 1040.72

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.21*1= sqmt 0.660 52.88 34.88 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.21-(0.005*2))*1= sqmt 0.628 640.00 402.12 (E)

Total (A+B+C+D+E) 1477.73Total without ED 1315.69

Add Water Charges @ 1% 1% 13.16Add CPOH @ 15% 15% 199.33

Total cost per meter for pipe 1528.18Total cost per kg for specials 60.45

2.5.8.3

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.212 0.006Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(0.212-0.006)*0.006*1*7850= kg 30.482Add 2 % wastage

2% kg 0.610Total Weight kg 31.091

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 31.091 34.21 1063.64 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 30.482 6.63 202.09 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.610 27.00 16.46

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 471.38 4.71 (C)

Material cost per meter Rs/meter 1253.99

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.212*1= sqmt 0.666 52.88 35.22 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.212-(0.006*2))*1= sqmt 0.628 640.00 402.12 (E)

Total (A+B+C+D+E) 1691.33Total without ED 1505.79

Add Water Charges @ 1% 1% 15.06Add CPOH @ 15% 15% 228.13

Total cost per meter for pipe 1748.98Total cost per kg for specials 57.38

2.5.8.4

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.2126 0.0063Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850

200 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

200 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 506 Schedule of Rates 2014 - 2015

Page 329: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

(3.1416)*(0.2126-0.0063)*0.0063*1*7850= kg 32.052Add 2 % wastage

2% kg 0.641Total Weight kg 32.693

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 32.693 34.21 1118.45 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 32.052 6.63 212.51 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.641 27.00 17.31

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 471.38 4.71 (C)

Material cost per meter Rs/meter 1318.36

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.2126*1= sqmt 0.668 52.88 35.32 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.2126-(0.0063*2))*1= sqmt 0.628 640.00 402.12 (E)

Total (A+B+C+D+E) 1755.80Total without ED 1563.17

Add Water Charges @ 1% 1% 15.63Add CPOH @ 15% 15% 236.82

Total cost per meter for pipe 1815.63Total cost per kg for specials 56.65

2.5.8.5

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.26 0.005Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(0.26-0.005)*0.005*1*7850= kg 31.443Add 2 % wastage

2% kg 0.629Total Weight kg 32.072

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 32.072 34.21 1097.20 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 31.443 6.63 208.47 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.629 27.00 16.98

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 669.85 6.70 (C)

Material cost per meter Rs/meter 1295.39

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.26*1= sqmt 0.817 52.88 43.19 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.26-(0.005*2))*1= sqmt 0.785 640.00 502.65 (E)

Total (A+B+C+D+E) 1841.23Total without ED 1639.43

Add Water Charges @ 1% 1% 16.39Add CPOH @ 15% 15% 248.37

Total cost per meter for pipe 1904.20Total cost per kg for specials 60.56

250 mm nominal dia (clear internal dia) of pipe with 5.0 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 507 Schedule of Rates 2014 - 2015

Page 330: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

2.5.8.6

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.262 0.006Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(0.262-0.006)*0.006*1*7850= kg 37.880Add 2 % wastage

2% kg 0.758Total Weight kg 38.638

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 38.638 34.21 1321.80 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 37.880 6.63 251.14 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.758 27.00 20.46

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 669.85 6.70 (C)

Material cost per meter Rs/meter 1559.19

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.262*1= sqmt 0.823 52.88 43.52 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.262-(0.006*2))*1= sqmt 0.785 640.00 502.65 (E)

Total (A+B+C+D+E) 2105.37Total without ED 1874.51

Add Water Charges @ 1% 1% 18.75Add CPOH @ 15% 15% 283.99

Total cost per meter for pipe 2177.24Total cost per kg for specials 57.48

2.5.8.7

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.2626 0.0063Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(0.2626-0.0063)*0.0063*1*7850= kg 39.821Add 2 % wastage

2% kg 0.796Total Weight kg 40.617

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 40.617 34.21 1389.52 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 39.821 6.63 264.01 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.796 27.00 21.50

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 669.85 6.70 (C)

Material cost per meter Rs/meter 1638.73

External / outside bitumastic coating

250 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

250 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 508 Schedule of Rates 2014 - 2015

Page 331: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

13.65.1 Area of coating = pi()*d*L(3.1416)*0.2626*1= sqmt 0.825 52.88 43.62 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.2626-(0.0063*2))*1= sqmt 0.785 640.00 502.65 (E)

Total (A+B+C+D+E) 2185.00Total without ED 1945.38

Add Water Charges @ 1% 1% 19.45Add CPOH @ 15% 15% 294.73

Total cost per meter for pipe 2259.56Total cost per kg for specials 56.74

2.5.8.8

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.309 0.0045Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(0.309-0.0045)*0.0045*1*7850= kg 33.792Add 2 % wastage

2% kg 0.676Total Weight kg 34.468

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 34.468 34.21 1179.17 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 33.792 6.63 224.04 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.676 27.00 18.25

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 827.95 8.28 (C)

Material cost per meter Rs/meter 1393.24

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.309*1= sqmt 0.971 52.88 51.33 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.309-(0.0045*2))*1= sqmt 0.942 640.00 603.19 (E)

Total (A+B+C+D+E) 2047.76Total without ED 1823.41

Add Water Charges @ 1% 1% 18.23Add CPOH @ 15% 15% 276.25

Total cost per meter for pipe 2117.89Total cost per kg for specials 62.67

2.5.8.9

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.3112 0.0056Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(0.3112-0.0056)*0.0056*1*7850= kg 42.205Add 2 % wastage

2% kg 0.844Total Weight kg 43.049

300 mm nominal dia (clear internal dia) of pipe with 5.6 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

300 mm nominal dia (clear internal dia) of pipe with 5 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 509 Schedule of Rates 2014 - 2015

Page 332: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 43.049 34.21 1472.71 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 42.205 6.63 279.82 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.844 27.00 22.79

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 827.95 8.28 (C)

Material cost per meter Rs/meter 1738.02

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.3112*1= sqmt 0.978 52.88 51.69 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.3112-(0.0056*2))*1= sqmt 0.942 640.00 603.19 (E)

Total (A+B+C+D+E) 2392.90Total without ED 2130.58

Add Water Charges @ 1% 1% 21.31Add CPOH @ 15% 15% 322.78

Total cost per meter for pipe 2474.67Total cost per kg for specials 58.63

2.5.8.10

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.3142 0.0071Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(0.3142-0.0071)*0.0071*1*7850= kg 53.772Add 2 % wastage

2% kg 1.075Total Weight kg 54.848

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 54.848 34.21 1876.35 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 53.772 6.63 356.51 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.075 27.00 29.04

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 827.95 8.28 (C)

Material cost per meter Rs/meter 2212.10

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.3142*1= sqmt 0.987 52.88 52.19 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.3142-(0.0071*2))*1= sqmt 0.942 640.00 603.19 (E)

Total (A+B+C+D+E) 2867.48Total without ED 2552.96

Add Water Charges @ 1% 1% 25.53Add CPOH @ 15% 15% 386.77

Total cost per meter for pipe 2965.26Total cost per kg for specials 55.14

2.5.8.11

300 mm nominal dia (clear internal dia) of pipe with 7.1 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

350 mm nominal dia (clear internal dia) of pipe with 5.0 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 510 Schedule of Rates 2014 - 2015

Page 333: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.36 0.005Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(0.36-0.005)*0.005*1*7850= kg 43.774Add 2 % wastage

2% kg 0.875Total Weight kg 44.650

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 44.650 34.21 1527.48 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 43.774 6.63 290.22 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.875 27.00 23.64

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1159.12 11.59 (C)

Material cost per meter Rs/meter 1805.65

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.36*1= sqmt 1.131 52.88 59.80 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.36-(0.005*2))*1= sqmt 1.100 640.00 703.72 (E)

Total (A+B+C+D+E) 2569.17Total without ED 2287.83

Add Water Charges @ 1% 1% 22.88Add CPOH @ 15% 15% 346.61

Total cost per meter for pipe 2657.31Total cost per kg for specials 60.70

2.5.8.12

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.3612 0.0056Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(0.3612-0.0056)*0.0056*1*7850= kg 49.110Add 2 % wastage

2% kg 0.982Total Weight kg 50.092

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 50.092 34.21 1713.66 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 49.110 6.63 325.60 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.982 27.00 26.52

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1159.12 11.59 (C)

Material cost per meter Rs/meter 2024.33

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.3612*1= sqmt 1.135 52.88 60.00 (D)

350 mm nominal dia (clear internal dia) of pipe with 5.6 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 511 Schedule of Rates 2014 - 2015

Page 334: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.3612-(0.0056*2))*1= sqmt 1.100 640.00 703.72 (E)

Total (A+B+C+D+E) 2788.05Total without ED 2482.63

Add Water Charges @ 1% 1% 24.83Add CPOH @ 15% 15% 376.12

Total cost per meter for pipe 2883.58Total cost per kg for specials 58.72

2.5.8.13

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.366 0.008Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(0.366-0.008)*0.008*1*7850= kg 70.631Add 2 % wastage

2% kg 1.413Total Weight kg 72.043

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 72.043 34.21 2464.61 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 70.631 6.63 468.28 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.413 27.00 38.14

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1159.12 11.59 (C)

Material cost per meter Rs/meter 2906.35

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.366*1= sqmt 1.150 52.88 60.80 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.366-(0.008*2))*1= sqmt 1.100 640.00 703.72 (E)

Total (A+B+C+D+E) 3670.86Total without ED 3268.33

Add Water Charges @ 1% 1% 32.68Add CPOH @ 15% 15% 495.15

Total cost per meter for pipe 3796.16Total cost per kg for specials 53.75

2.5.8.14

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.41 0.005Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(0.41-0.005)*0.005*1*7850= kg 49.940Add 2 % wastage

2% kg 0.999Total Weight kg 50.938

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 50.938 34.21 1742.61 (A)

400 mm nominal dia (clear internal dia) of pipe with 5.0 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

350 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 512 Schedule of Rates 2014 - 2015

Page 335: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_320 Cost of Fabrication kg 49.940 6.63 331.10 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 0.999 27.00 26.97

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1580.62 15.81 (C)

Material cost per meter Rs/meter 2062.55

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.41*1= sqmt 1.288 52.88 68.11 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.41-(0.005*2))*1= sqmt 1.257 640.00 804.25 (E)

Total (A+B+C+D+E) 2934.91Total without ED 2613.79

Add Water Charges @ 1% 1% 26.14Add CPOH @ 15% 15% 395.99

Total cost per meter for pipe 3035.92Total cost per kg for specials 60.79

2.5.8.15

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.412 0.006Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(0.412-0.006)*0.006*1*7850= kg 60.075Add 2 % wastage

2% kg 1.202Total Weight kg 61.277

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 61.277 34.21 2096.30 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 60.075 6.63 398.30 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.202 27.00 32.44

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1580.62 15.81 (C)

Material cost per meter Rs/meter 2477.96

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.412*1= sqmt 1.294 52.88 68.44 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.412-(0.006*2))*1= sqmt 1.257 640.00 804.25 (E)

Total (A+B+C+D+E) 3350.65Total without ED 2983.81

Add Water Charges @ 1% 1% 29.84Add CPOH @ 15% 15% 452.05

Total cost per meter for pipe 3465.69Total cost per kg for specials 57.69

2.5.8.16

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

400 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

400 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 513 Schedule of Rates 2014 - 2015

Page 336: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.4126 0.0063Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(0.4126-0.0063)*0.0063*1*7850= kg 63.126Add 2 % wastage

2% kg 1.263Total Weight kg 64.388

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 64.388 34.21 2202.74 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 63.126 6.63 418.52 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.263 27.00 34.09

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1580.62 15.81 (C)

Material cost per meter Rs/meter 2602.98

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.4126*1= sqmt 1.296 52.88 68.54 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.4126-(0.0063*2))*1= sqmt 1.257 640.00 804.25 (E)

Total (A+B+C+D+E) 3475.77Total without ED 3095.16

Add Water Charges @ 1% 1% 30.95Add CPOH @ 15% 15% 468.92

Total cost per meter for pipe 3595.03Total cost per kg for specials 56.95

2.5.8.17

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.4176 0.0088Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(0.4176-0.0088)*0.0088*1*7850= kg 88.718Add 2 % wastage

2% kg 1.774Total Weight kg 90.493

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 90.493 34.21 3095.78 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 88.718 6.63 588.20 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.774 27.00 47.91

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1580.62 15.81 (C)

Material cost per meter Rs/meter 3651.88

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.4176*1= sqmt 1.312 52.88 69.37 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

400 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 514 Schedule of Rates 2014 - 2015

Page 337: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

(3.1416)*(0.4176-(0.0088*2))*1= sqmt 1.257 640.00 804.25 (E)

Total (A+B+C+D+E) 4525.49Total without ED 4029.41

Add Water Charges @ 1% 1% 40.29Add CPOH @ 15% 15% 610.46

Total cost per meter for pipe 4680.16Total cost per kg for specials 52.75

2.5.8.18

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.462 0.006Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(0.462-0.006)*0.006*1*7850= kg 67.474Add 2 % wastage

2% kg 1.349Total Weight kg 68.823

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 68.823 34.21 2354.46 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 67.474 6.63 447.35 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.349 27.00 36.44

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 2784.70

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.462*1= sqmt 1.451 52.88 76.75 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.462-(0.006*2))*1= sqmt 1.414 640.00 904.78 (E)

Total (A+B+C+D+E) 3766.22Total without ED 3354.05

Add Water Charges @ 1% 1% 33.54Add CPOH @ 15% 15% 508.14

Total cost per meter for pipe 3895.73Total cost per kg for specials 57.74

2.5.8.19

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.4626 0.0063Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(0.4626-0.0063)*0.0063*1*7850= kg 70.894Add 2 % wastage

2% kg 1.418Total Weight kg 72.312

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 72.312 34.21 2473.81 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 70.894 6.63 470.03 (B)

450 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

450 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 515 Schedule of Rates 2014 - 2015

Page 338: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.418 27.00 38.28

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 2924.88

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.4626*1= sqmt 1.453 52.88 76.84 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.4626-(0.0063*2))*1= sqmt 1.414 640.00 904.78 (E)

Total (A+B+C+D+E) 3906.50Total without ED 3478.90

Add Water Charges @ 1% 1% 34.79Add CPOH @ 15% 15% 527.05

Total cost per meter for pipe 4040.74Total cost per kg for specials 57.00

2.5.8.20

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.47 0.01Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(0.47-0.01)*0.01*1*7850= kg 113.443Add 2 % wastage

2% kg 2.269Total Weight kg 115.712

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 115.712 34.21 3958.53 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 113.443 6.63 752.13 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.269 27.00 61.26

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 4668.71

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.47*1= sqmt 1.477 52.88 78.07 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.47-(0.01*2))*1= sqmt 1.414 640.00 904.78 (E)

Total (A+B+C+D+E) 5651.57Total without ED 5032.00

Add Water Charges @ 1% 1% 50.32Add CPOH @ 15% 15% 762.35

Total cost per meter for pipe 5844.67Total cost per kg for specials 51.52

2.5.8.21

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.512 0.006

450 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

500 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 516 Schedule of Rates 2014 - 2015

Page 339: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Length of pipe =

1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(0.512-0.006)*0.006*1*7850= kg 74.872Add 2 % wastage

2% kg 1.497Total Weight kg 76.370

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 76.370 34.21 2612.63 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 74.872 6.63 496.40 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.497 27.00 40.43

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 3087.92

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.512*1= sqmt 1.608 52.88 85.05 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.512-(0.006*2))*1= sqmt 1.571 640.00 1005.31 (E)

Total (A+B+C+D+E) 4178.28Total without ED 3720.78

Add Water Charges @ 1% 1% 37.21Add CPOH @ 15% 15% 563.70

Total cost per meter for pipe 4321.69Total cost per kg for specials 57.72

2.5.8.22

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.5126 0.0063Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(0.5126-0.0063)*0.0063*1*7850= kg 78.663Add 2 % wastage

2% kg 1.573Total Weight kg 80.236

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 80.236 34.21 2744.89 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 78.663 6.63 521.53 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.573 27.00 42.48

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 3243.26

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.5126*1= sqmt 1.610 52.88 85.15 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.5126-(0.0063*2))*1= sqmt 1.571 640.00 1005.31 (E)

500 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 517 Schedule of Rates 2014 - 2015

Page 340: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Total (A+B+C+D+E) 4333.72Total without ED 3859.12

Add Water Charges @ 1% 1% 38.59Add CPOH @ 15% 15% 584.66

Total cost per meter for pipe 4482.37Total cost per kg for specials 56.98

2.5.8.23

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.522 0.011Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(0.522-0.011)*0.011*1*7850= kg 138.622Add 2 % wastage

2% kg 2.772Total Weight kg 141.395

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 141.395 34.21 4837.15 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 138.622 6.63 919.07 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.772 27.00 74.86

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 1931.87 19.32 (C)

Material cost per meter Rs/meter 5700.68

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.522*1= sqmt 1.640 52.88 86.71 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.522-(0.011*2))*1= sqmt 1.571 640.00 1005.31 (E)

Total (A+B+C+D+E) 6792.70Total without ED 6047.60

Add Water Charges @ 1% 1% 60.48Add CPOH @ 15% 15% 916.21

Total cost per meter for pipe 7024.29Total cost per kg for specials 50.67

2.5.8.24

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.612 0.006Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(0.612-0.006)*0.006*1*7850= kg 89.669Add 2 % wastage

2% kg 1.793Total Weight kg 91.463

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 91.463 34.21 3128.96 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 89.669 6.63 594.51 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.793 27.00 48.42

500 mm nominal dia (clear internal dia) of pipe with 11.0 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

600 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 518 Schedule of Rates 2014 - 2015

Page 341: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 3704.02

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.612*1= sqmt 1.923 52.88 101.66 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.612-(0.006*2))*1= sqmt 1.885 640.00 1206.37 (E)

Total (A+B+C+D+E) 5012.06Total without ED 4463.90

Add Water Charges @ 1% 1% 44.64Add CPOH @ 15% 15% 676.28

Total cost per meter for pipe 5184.82Total cost per kg for specials 57.82

2.5.8.25

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.6126 0.0063Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(0.6126-0.0063)*0.0063*1*7850= kg 94.199Add 2 % wastage

2% kg 1.884Total Weight kg 96.083

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 96.083 34.21 3287.03 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 94.199 6.63 624.54 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 1.884 27.00 50.87

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 3889.68

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.6126*1= sqmt 1.925 52.88 101.76 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.6126-(0.0063*2))*1= sqmt 1.885 640.00 1206.37 (E)

Total (A+B+C+D+E) 5197.82Total without ED 4629.23

Add Water Charges @ 1% 1% 46.29Add CPOH @ 15% 15% 701.33

Total cost per meter for pipe 5376.85Total cost per kg for specials 57.08

2.5.8.26

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.616 0.008Length of pipe

=

600 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

600 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 519 Schedule of Rates 2014 - 2015

Page 342: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(0.616-0.008)*0.008*1*7850= kg 119.954Add 2 % wastage

2% kg 2.399Total Weight kg 122.353

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 122.353 34.21 4185.71 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 119.954 6.63 795.29 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.399 27.00 64.77

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 4945.21

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.616*1= sqmt 1.935 52.88 102.33 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.616-(0.008*2))*1= sqmt 1.885 640.00 1206.37 (E)

Total (A+B+C+D+E) 6253.91Total without ED 5569.14

Add Water Charges @ 1% 1% 55.69Add CPOH @ 15% 15% 843.73

Total cost per meter for pipe 6468.56Total cost per kg for specials 53.93

2.5.8.27

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.625 0.0125Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(0.625-0.0125)*0.0125*1*7850= kg 188.815Add 2 % wastage

2% kg 3.776Total Weight kg 192.591

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 192.591 34.21 6588.58 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 188.815 6.63 1251.84 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.776 27.00 101.96

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 7767.44

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.625*1= sqmt 1.963 52.88 103.82 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.625-(0.0125*2))*1= sqmt 1.885 640.00 1206.37 (E)

Total (A+B+C+D+E) 9077.64Total without ED 8082.25

600 mm nominal dia (clear internal dia) of pipe with 12.5 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 520 Schedule of Rates 2014 - 2015

Page 343: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add Water Charges @ 1% 1% 80.82Add CPOH @ 15% 15% 1224.46

Total cost per meter for pipe 9387.53Total cost per kg for specials 49.72

2.5.8.28

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.712 0.006Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(0.712-0.006)*0.006*1*7850= kg 104.466Add 2 % wastage

2% kg 2.089Total Weight kg 106.555

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 106.555 34.21 3645.29 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 104.466 6.63 692.61 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.089 27.00 56.41

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 4310.47

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.712*1= sqmt 2.237 52.88 118.27 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.712-(0.006*2))*1= sqmt 2.199 640.00 1407.43 (E)

Total (A+B+C+D+E) 5836.17Total without ED 5197.36

Add Water Charges @ 1% 1% 51.97Add CPOH @ 15% 15% 787.40

Total cost per meter for pipe 6036.73Total cost per kg for specials 57.79

2.5.8.29

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.713 0.0063Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(0.7126-0.0063)*0.0063*1*7850= kg 109.736Add 2 % wastage

2% kg 2.195Total Weight kg 111.931

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 111.931 34.21 3829.18 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 109.736 6.63 727.55 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.195 27.00 59.26

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

700 mm nominal dia (clear internal dia) of pipe with 6.0 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

700 mm nominal dia (clear internal dia) of pipe with 6.3 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 521 Schedule of Rates 2014 - 2015

Page 344: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Material cost per meter Rs/meter 4526.45

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.7126*1= sqmt 2.239 52.88 118.37 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.7126-(0.0063*2))*1= sqmt 2.199 640.00 1407.43 (E)

Total (A+B+C+D+E) 6052.26Total without ED 5389.67

Add Water Charges @ 1% 1% 53.90Add CPOH @ 15% 15% 816.54

Total cost per meter for pipe 6260.11Total cost per kg for specials 57.05

2.5.8.30

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.714 0.0071Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(0.7142-0.0071)*0.0071*1*7850= kg 123.811Add 2 % wastage

2% kg 2.476Total Weight kg 126.287

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 126.287 34.21 4320.31 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 123.811 6.63 820.87 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.476 27.00 66.86

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 5103.30

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.7142*1= sqmt 2.244 52.88 118.64 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.7142-(0.0071*2))*1= sqmt 2.199 640.00 1407.43 (E)

Total (A+B+C+D+E) 6629.37Total without ED 5903.30

Add Water Charges @ 1% 1% 59.03Add CPOH @ 15% 15% 894.35

Total cost per meter for pipe 6856.69Total cost per kg for specials 55.38

2.5.8.31

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.716 0.008Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850

700 mm nominal dia (clear internal dia) of pipe with 7.1 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

700 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 522 Schedule of Rates 2014 - 2015

Page 345: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

(3.1416)*(0.716-0.008)*0.008*1*7850= kg 139.683Add 2 % wastage

2% kg 2.794Total Weight kg 142.476

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 142.476 34.21 4874.15 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 139.683 6.63 926.10 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.794 27.00 75.43

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 5753.80

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.716*1= sqmt 2.249 52.88 118.94 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.716-(0.008*2))*1= sqmt 2.199 640.00 1407.43 (E)

Total (A+B+C+D+E) 7280.17Total without ED 6482.51

Add Water Charges @ 1% 1% 64.83Add CPOH @ 15% 15% 982.10

Total cost per meter for pipe 7529.44Total cost per kg for specials 53.90

2.5.8.32

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.728 0.0142Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(0.7284-0.0142)*0.0142*1*7850= kg 250.108Add 2 % wastage

2% kg 5.002Total Weight kg 255.110

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 255.110 34.21 8727.38 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 250.108 6.63 1658.22 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 5.002 27.00 135.06

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 10279.52

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.7284*1= sqmt 2.288 52.88 121.00 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.7284-(0.0142*2))*1= sqmt 2.199 640.00 1407.43 (E)

Total (A+B+C+D+E) 11807.95Total without ED 10512.22

Add Water Charges @ 1% 1% 105.12Add CPOH @ 15% 15% 1592.60

Total cost per meter for pipe 12209.95Total cost per kg for specials 48.82

700 mm nominal dia (clear internal dia) of pipe with 14.2 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 523 Schedule of Rates 2014 - 2015

Page 346: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

2.5.8.33

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.814 0.0071Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(0.8142-0.0071)*0.0071*1*7850= kg 141.321Add 2 % wastage

2% kg 2.826Total Weight kg 144.147

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 144.147 34.21 4931.30 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 141.321 6.63 936.96 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 2.826 27.00 76.31

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 5820.92

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.8142*1= sqmt 2.558 52.88 135.25 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.8142-(0.0071*2))*1= sqmt 2.513 640.00 1608.50 (E)

Total (A+B+C+D+E) 7564.67Total without ED 6735.72

Add Water Charges @ 1% 1% 67.36Add CPOH @ 15% 15% 1020.46

Total cost per meter for pipe 7823.53Total cost per kg for specials 55.36

2.5.8.34

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.816 0.008Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(0.816-0.008)*0.008*1*7850= kg 159.412Add 2 % wastage

2% kg 3.188Total Weight kg 162.600

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 162.600 34.21 5562.59 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 159.412 6.63 1056.90 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.188 27.00 86.08

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 6562.39

External / outside bitumastic coating

800 mm nominal dia (clear internal dia) of pipe with 7.1 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

800 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 524 Schedule of Rates 2014 - 2015

Page 347: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

13.65.1 Area of coating = pi()*d*L(3.1416)*0.816*1= sqmt 2.564 52.88 135.55 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.816-(0.008*2))*1= sqmt 2.513 640.00 1608.50 (E)

Total (A+B+C+D+E) 8306.44Total without ED 7395.89

Add Water Charges @ 1% 1% 73.96Add CPOH @ 15% 15% 1120.48

Total cost per meter for pipe 8590.32Total cost per kg for specials 53.89

2.5.8.35

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.836 0.018Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(0.836-0.018)*0.018*1*7850= kg 363.116Add 2 % wastage

2% kg 7.262Total Weight kg 370.378

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 370.378 34.21 12670.73 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 363.116 6.63 2407.46 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 7.262 27.00 196.08

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 2897.81 28.98 (C)

Material cost per meter Rs/meter 14911.09

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.836*1= sqmt 2.626 52.88 138.87 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.836-(0.018*2))*1= sqmt 2.513 640.00 1608.50 (E)

Total (A+B+C+D+E) 16658.45Total without ED 14829.15

Add Water Charges @ 1% 1% 148.29Add CPOH @ 15% 15% 2246.62

Total cost per meter for pipe 17224.06Total cost per kg for specials 47.43

2.5.8.36

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.916 0.008Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(0.916-0.008)*0.008*1*7850= kg 179.141Add 2 % wastage

2% kg 3.583Total Weight kg 182.724

800 mm nominal dia (clear internal dia) of pipe with 18.0 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

900 mm nominal dia (clear internal dia) of pipe with 8.0 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 525 Schedule of Rates 2014 - 2015

Page 348: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 182.724 34.21 6251.03 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 179.141 6.63 1187.71 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.583 27.00 96.74

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 4346.71 43.47 (C)

Material cost per meter Rs/meter 7385.47

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.916*1= sqmt 2.878 52.88 152.16 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.916-(0.008*2))*1= sqmt 2.827 640.00 1809.56 (E)

Total (A+B+C+D+E) 9347.19Total without ED 8323.75

Add Water Charges @ 1% 1% 83.24Add CPOH @ 15% 15% 1261.05

Total cost per meter for pipe 9668.03Total cost per kg for specials 53.97

2.5.8.37

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.918 0.0088Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(0.9176-0.0088)*0.0088*1*7850= kg 197.229Add 2 % wastage

2% kg 3.945Total Weight kg 201.173

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 201.173 34.21 6882.19 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 197.229 6.63 1307.63 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 3.945 27.00 106.50

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 4346.71 43.47 (C)

Material cost per meter Rs/meter 8126.79

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.9176*1= sqmt 2.883 52.88 152.43 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.9176-(0.0088*2))*1= sqmt 2.827 640.00 1809.56 (E)

Total (A+B+C+D+E) 10088.77Total without ED 8983.75

Add Water Charges @ 1% 1% 89.84Add CPOH @ 15% 15% 1361.04

Total cost per meter for pipe 10434.63Total cost per kg for specials 52.91

2.5.8.38

900 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

900 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 526 Schedule of Rates 2014 - 2015

Page 349: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.920 0.01Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(0.92-0.01)*0.01*1*7850= kg 224.420Add 2 % wastage

2% kg 4.488Total Weight kg 228.908

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 228.908 34.21 7831.00 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 224.420 6.63 1487.90 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 4.488 27.00 121.19

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 4346.71 43.47 (C)

Material cost per meter Rs/meter 9241.18

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.92*1= sqmt 2.890 52.88 152.83 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.92-(0.01*2))*1= sqmt 2.827 640.00 1809.56 (E)

Total (A+B+C+D+E) 11203.57Total without ED 9975.92

Add Water Charges @ 1% 1% 99.76Add CPOH @ 15% 15% 1511.35

Total cost per meter for pipe 11587.03Total cost per kg for specials 51.63

2.5.8.39

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

0.935 0.0175Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(0.935-0.0175)*0.0175*1*7850= kg 395.971Add 2 % wastage

2% kg 7.919Total Weight kg 403.891

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 403.891 34.21 13817.20 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 395.971 6.63 2625.29 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 7.919 27.00 213.82

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 4346.71 43.47 (C)

Material cost per meter Rs/meter 16272.13

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*0.935*1= sqmt 2.937 52.88 155.32 (D)

900 mm nominal dia (clear internal dia) of pipe with 17.5 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 527 Schedule of Rates 2014 - 2015

Page 350: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(0.935-(0.0175*2))*1= sqmt 2.827 640.00 1809.56 (E)

Total (A+B+C+D+E) 18237.01Total without ED 16235.65

Add Water Charges @ 1% 1% 162.36Add CPOH @ 15% 15% 2459.70

Total cost per meter for pipe 18857.71Total cost per kg for specials 47.62

2.5.8.40

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

1.018 0.0088Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(1.0176-0.0088)*0.0088*1*7850= kg 218.931Add 2 % wastage

2% kg 4.379Total Weight kg 223.310

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 223.310 34.21 7639.48 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 218.931 6.63 1451.51 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 4.379 27.00 118.22

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 9030.72

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.0176*1= sqmt 3.197 52.88 169.04 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.0176-(0.0088*2))*1= sqmt 3.142 640.00 2010.62 (E)

Total (A+B+C+D+E) 11210.38Total without ED 9983.58

Add Water Charges @ 1% 1% 99.84Add CPOH @ 15% 15% 1512.51

Total cost per meter for pipe 11595.92Total cost per kg for specials 52.97

2.5.8.41

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

1.020 0.01Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(1.02-0.01)*0.01*1*7850= kg 249.081Add 2 % wastage

2% kg 4.982Total Weight kg 254.063

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 254.063 34.21 8691.55 (A)

1000 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

1000 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 528 Schedule of Rates 2014 - 2015

Page 351: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_320 Cost of Fabrication kg 249.081 6.63 1651.41 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 4.982 27.00 134.50

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 10266.41

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.02*1= sqmt 3.204 52.88 169.44 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.02-(0.01*2))*1= sqmt 3.142 640.00 2010.62 (E)

Total (A+B+C+D+E) 12446.47Total without ED 11083.69

Add Water Charges @ 1% 1% 110.84Add CPOH @ 15% 15% 1679.18

Total cost per meter for pipe 12873.70Total cost per kg for specials 51.68

2.5.8.42

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

1.040 0.02Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(1.04-0.02)*0.02*1*7850= kg 503.095Add 2 % wastage

2% kg 10.062Total Weight kg 513.157

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 513.157 34.21 17555.21 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 503.095 6.63 3335.52 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 10.062 27.00 271.67

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 20677.02

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.04*1= sqmt 3.267 52.88 172.76 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.04-(0.02*2))*1= sqmt 3.142 640.00 2010.62 (E)

Total (A+B+C+D+E) 22860.39Total without ED 20352.05

Add Water Charges @ 1% 1% 203.52Add CPOH @ 15% 15% 3083.33

Total cost per meter for pipe 23638.90Total cost per kg for specials 46.99

2.5.8.43

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

1050 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

1000 mm nominal dia (clear internal dia) of pipe with 20.0 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 529 Schedule of Rates 2014 - 2015

Page 352: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

1.068 0.0088Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(1.0676-0.0088)*0.0088*1*7850= kg 229.782Add 2 % wastage

2% kg 4.596Total Weight kg 234.378

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 234.378 34.21 8018.12 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 229.782 6.63 1523.46 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 4.596 27.00 124.08

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 9475.45

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.0676*1= sqmt 3.354 52.88 177.34 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.0676-(0.0088*2))*1= sqmt 3.299 640.00 2111.15 (E)

Total (A+B+C+D+E) 11763.94Total without ED 10476.24

Add Water Charges @ 1% 1% 104.76Add CPOH @ 15% 15% 1587.15

Total cost per meter for pipe 12168.16Total cost per kg for specials 52.96

2.5.8.44

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

1.070 0.01Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(1.07-0.01)*0.01*1*7850= kg 261.412Add 2 % wastage

2% kg 5.228Total Weight kg 266.640

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 266.640 34.21 9121.83 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 261.412 6.63 1733.16 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 5.228 27.00 141.16

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 10771.78

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.07*1= sqmt 3.362 52.88 177.74 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

1050 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 530 Schedule of Rates 2014 - 2015

Page 353: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

(3.1416)*(1.07-(0.01*2))*1= sqmt 3.299 640.00 2111.15 (E)

Total (A+B+C+D+E) 13060.67Total without ED 11630.33

Add Water Charges @ 1% 1% 116.30Add CPOH @ 15% 15% 1761.99

Total cost per meter for pipe 13508.63Total cost per kg for specials 51.68

2.5.8.45

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

1.072 0.011Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(1.072-0.011)*0.011*1*7850= kg 287.824Add 2 % wastage

2% kg 5.756Total Weight kg 293.581

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 293.581 34.21 10043.48 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 287.824 6.63 1908.28 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 5.756 27.00 155.43

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 11854.28

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.072*1= sqmt 3.368 52.88 178.08 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.072-(0.011*2))*1= sqmt 3.299 640.00 2111.15 (E)

Total (A+B+C+D+E) 14143.51Total without ED 12594.05

Add Water Charges @ 1% 1% 125.94Add CPOH @ 15% 15% 1908.00

Total cost per meter for pipe 14627.98Total cost per kg for specials 50.82

2.5.8.46

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

1.118 0.0088Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(1.1176-0.0088)*0.0088*1*7850= kg 240.633Add 2 % wastage

2% kg 4.813Total Weight kg 245.446

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 245.446 34.21 8396.76 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 240.633 6.63 1595.40 (B)

1050 mm nominal dia (clear internal dia) of pipe with 11.0 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

1100 mm nominal dia (clear internal dia) of pipe with 8.8 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 531 Schedule of Rates 2014 - 2015

Page 354: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_272 Cost of Scrap kg 4.813 27.00 129.94

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 9920.17

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.1176*1= sqmt 3.511 52.88 185.65 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.1176-(0.0088*2))*1= sqmt 3.456 640.00 2211.68 (E)

Total (A+B+C+D+E) 12317.50Total without ED 10968.91

Add Water Charges @ 1% 1% 109.69Add CPOH @ 15% 15% 1661.79

Total cost per meter for pipe 12740.39Total cost per kg for specials 52.95

2.5.8.47

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

1.120 0.01Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(1.12-0.01)*0.01*1*7850= kg 273.743Add 2 % wastage

2% kg 5.475Total Weight kg 279.218

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 279.218 34.21 9552.10 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 273.743 6.63 1814.91 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 5.475 27.00 147.82

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 11277.15

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.12*1= sqmt 3.519 52.88 186.05 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.12-(0.01*2))*1= sqmt 3.456 640.00 2211.68 (E)

Total (A+B+C+D+E) 13674.88Total without ED 12176.97

Add Water Charges @ 1% 1% 121.77Add CPOH @ 15% 15% 1844.81

Total cost per meter for pipe 14143.55Total cost per kg for specials 51.67

2.5.8.48

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

1.122 0.011

1100 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

1100 mm nominal dia (clear internal dia) of pipe with 11.0 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 532 Schedule of Rates 2014 - 2015

Page 355: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Length of pipe =

1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(1.122-0.011)*0.011*1*7850= kg 301.388Add 2 % wastage

2% kg 6.028Total Weight kg 307.416

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 307.416 34.21 10516.78 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 301.388 6.63 1998.20 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 6.028 27.00 162.75

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 12410.19

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.122*1= sqmt 3.525 52.88 186.38 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.122-(0.011*2))*1= sqmt 3.456 640.00 2211.68 (E)

Total (A+B+C+D+E) 14808.25Total without ED 13185.67

Add Water Charges @ 1% 1% 131.86Add CPOH @ 15% 15% 1997.63

Total cost per meter for pipe 15315.15Total cost per kg for specials 50.82

2.5.8.49

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

1.220 0.01Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(1.22-0.01)*0.01*1*7850= kg 298.404Add 2 % wastage

2% kg 5.968Total Weight kg 304.372

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 304.372 34.21 10412.65 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 298.404 6.63 1978.42 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 5.968 27.00 161.14

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 12287.89

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.22*1= sqmt 3.833 52.88 202.66 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.22-(0.01*2))*1= sqmt 3.770 640.00 2412.74 (E)

1200 mm nominal dia (clear internal dia) of pipe with 10.0 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 533 Schedule of Rates 2014 - 2015

Page 356: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Total (A+B+C+D+E) 14903.29Total without ED 13270.25

Add Water Charges @ 1% 1% 132.70Add CPOH @ 15% 15% 2010.44

Total cost per meter for pipe 15413.40Total cost per kg for specials 51.65

2.5.8.50

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

1.222 0.011Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(1.222-0.011)*0.011*1*7850= kg 328.516Add 2 % wastage

2% kg 6.570Total Weight kg 335.086

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 335.086 34.21 11463.38 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 328.516 6.63 2178.06 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 6.570 27.00 177.40

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 13522.00

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.222*1= sqmt 3.839 52.88 202.99 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.222-(0.011*2))*1= sqmt 3.770 640.00 2412.74 (E)

Total (A+B+C+D+E) 16137.74Total without ED 14368.90

Add Water Charges @ 1% 1% 143.69Add CPOH @ 15% 15% 2176.89

Total cost per meter for pipe 16689.48Total cost per kg for specials 50.80

2.5.8.51

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

1.224 0.012Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(1.224-0.012)*0.012*1*7850= kg 358.677Add 2 % wastage

2% kg 7.174Total Weight kg 365.850

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 365.850 34.21 12515.83 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 358.677 6.63 2378.03 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 7.174 27.00 193.69

1200 mm nominal dia (clear internal dia) of pipe with 11.0 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

1200 mm nominal dia (clear internal dia) of pipe with 12.0 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 534 Schedule of Rates 2014 - 2015

Page 357: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 14758.13

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.224*1= sqmt 3.845 52.88 203.32 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.224-(0.012*2))*1= sqmt 3.770 640.00 2412.74 (E)

Total (A+B+C+D+E) 17374.20Total without ED 15469.35

Add Water Charges @ 1% 1% 154.69Add CPOH @ 15% 15% 2343.61

Total cost per meter for pipe 17967.65Total cost per kg for specials 50.09

2.5.8.52

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

1.225 0.0125Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(1.225-0.0125)*0.0125*1*7850= kg 373.776Add 2 % wastage

2% kg 7.476Total Weight kg 381.251

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 381.251 34.21 13042.71 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 373.776 6.63 2478.13 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 7.476 27.00 201.84

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 5795.62 57.96 (C)

Material cost per meter Rs/meter 15376.96

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.225*1= sqmt 3.848 52.88 203.49 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.225-(0.0125*2))*1= sqmt 3.770 640.00 2412.74 (E)

Total (A+B+C+D+E) 17993.19Total without ED 16020.25

Add Water Charges @ 1% 1% 160.20Add CPOH @ 15% 15% 2427.07

Total cost per meter for pipe 18607.52Total cost per kg for specials 49.78

2.5.8.53

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

1.424 0.012Length of pipe

=

1400 mm nominal dia (clear internal dia) of pipe with 12 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

1200 mm nominal dia (clear internal dia) of pipe with 12.5 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 535 Schedule of Rates 2014 - 2015

Page 358: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(1.424-0.012)*0.012*1*7850= kg 417.864Add 2 % wastage

2% kg 8.357Total Weight kg 426.222

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 426.222 34.21 14581.15 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 417.864 6.63 2770.44 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 8.357 27.00 225.65

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 7244.52 72.45 (C)

Material cost per meter Rs/meter 17198.39

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.424*1= sqmt 4.474 52.88 236.55 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.424-(0.012*2))*1= sqmt 4.398 640.00 2814.87 (E)

Total (A+B+C+D+E) 20249.81Total without ED 18030.23

Add Water Charges @ 1% 1% 180.30Add CPOH @ 15% 15% 2731.58

Total cost per meter for pipe 20942.11Total cost per kg for specials 50.12

2.5.8.54

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

1.425 0.0125Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(1.425-0.0125)*0.0125*1*7850= kg 435.430Add 2 % wastage

2% kg 8.709Total Weight kg 444.138

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 444.138 34.21 15194.08 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 435.430 6.63 2886.90 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 8.709 27.00 235.13

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 7244.52 72.45 (C)

Material cost per meter Rs/meter 17918.29

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.425*1= sqmt 4.477 52.88 236.71 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.425-(0.0125*2))*1= sqmt 4.398 640.00 2814.87 (E)

Total (A+B+C+D+E) 20969.87Total without ED 18671.08

1400 mm nominal dia (clear internal dia) of pipe with 12.5 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 536 Schedule of Rates 2014 - 2015

Page 359: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add Water Charges @ 1% 1% 186.71Add CPOH @ 15% 15% 2828.67

Total cost per meter for pipe 21686.46Total cost per kg for specials 49.80

2.5.8.55

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

1.428 0.0142Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(1.4284-0.0142)*0.0142*1*7850= kg 495.243Add 2 % wastage

2% kg 9.905Total Weight kg 505.148

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 505.148 34.21 17281.25 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 495.243 6.63 3283.46 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 9.905 27.00 267.43

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 7244.52 72.45 (C)

Material cost per meter Rs/meter 20369.73

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.4284*1= sqmt 4.487 52.88 237.28 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.4284-(0.0142*2))*1= sqmt 4.398 640.00 2814.87 (E)

Total (A+B+C+D+E) 23421.87Total without ED 20853.35

Add Water Charges @ 1% 1% 208.53Add CPOH @ 15% 15% 3159.28

Total cost per meter for pipe 24221.17Total cost per kg for specials 48.91

2.5.8.56

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

1.524 0.012Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(1.524-0.012)*0.012*1*7850= kg 447.458Add 2 % wastage

2% kg 8.949Total Weight kg 456.407

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 456.407 34.21 15613.81 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 447.458 6.63 2966.65 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 8.949 27.00 241.63

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 8693.42 86.93 (C)

1400 mm nominal dia (clear internal dia) of pipe with 14.2 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

1500 mm nominal dia (clear internal dia) of pipe with 12 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 537 Schedule of Rates 2014 - 2015

Page 360: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Material cost per meter Rs/meter 18425.77

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.524*1= sqmt 4.788 52.88 253.16 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.524-(0.012*2))*1= sqmt 4.712 640.00 3015.93 (E)

Total (A+B+C+D+E) 21694.86Total without ED 19317.91

Add Water Charges @ 1% 1% 193.18Add CPOH @ 15% 15% 2926.66

Total cost per meter for pipe 22437.75Total cost per kg for specials 50.14

2.5.8.57

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

1.628 0.0142Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(1.6284-0.0142)*0.0142*1*7850= kg 565.282Add 2 % wastage

2% kg 11.306Total Weight kg 576.588

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 576.588 34.21 19725.21 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 565.282 6.63 3747.82 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 11.306 27.00 305.25

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 8693.42 86.93 (C)

Material cost per meter Rs/meter 23254.71

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.6284*1= sqmt 5.116 52.88 270.50 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.6284-(0.0142*2))*1= sqmt 5.027 640.00 3216.99 (E)

Total (A+B+C+D+E) 26742.20Total without ED 23810.03

Add Water Charges @ 1% 1% 238.10Add CPOH @ 15% 15% 3607.22

Total cost per meter for pipe 27655.35Total cost per kg for specials 48.92

2.5.8.58

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

1.632 0.016Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850

1600 mm nominal dia (clear internal dia) of pipe with 14.2 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

1600 mm nominal dia (clear internal dia) of pipe with 16.0 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 538 Schedule of Rates 2014 - 2015

Page 361: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

(3.1416)*(1.632-0.016)*0.016*1*7850= kg 637.648Add 2 % wastage

2% kg 12.753Total Weight kg 650.401

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 650.401 34.21 22250.37 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 637.648 6.63 4227.60 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 12.753 27.00 344.33

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 8693.42 86.93 (C)

Material cost per meter Rs/meter 26220.58

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.632*1= sqmt 5.127 52.88 271.10 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.632-(0.016*2))*1= sqmt 5.027 640.00 3216.99 (E)

Total (A+B+C+D+E) 29708.67Total without ED 26450.18

Add Water Charges @ 1% 1% 264.50Add CPOH @ 15% 15% 4007.20

Total cost per meter for pipe 30721.88Total cost per kg for specials 48.18

2.5.8.59

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

1.828 0.0142Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(1.8284-0.0142)*0.0142*1*7850= kg 635.321Add 2 % wastage

2% kg 12.706Total Weight kg 648.027

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 648.027 34.21 22169.17 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 635.321 6.63 4212.18 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 12.706 27.00 343.07

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 10142.33 101.42 (C)

Material cost per meter Rs/meter 26139.70

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.8284*1= sqmt 5.744 52.88 303.72 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.8284-(0.0142*2))*1= sqmt 5.655 640.00 3619.11 (E)

Total (A+B+C+D+E) 30062.54Total without ED 26766.71

Add Water Charges @ 1% 1% 267.67Add CPOH @ 15% 15% 4055.16

Total cost per meter for pipe 31089.53Total cost per kg for specials 48.94

1800 mm nominal dia (clear internal dia) of pipe with 14.2 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 539 Schedule of Rates 2014 - 2015

Page 362: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

2.5.8.60

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

1.832 0.016Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(1.832-0.016)*0.016*1*7850= kg 716.565Add 2 % wastage

2% kg 14.331Total Weight kg 730.896

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 730.896 34.21 25004.13 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 716.565 6.63 4750.82 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 14.331 27.00 386.94

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 10142.33 101.42 (C)

Material cost per meter Rs/meter 29469.43

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*1.832*1= sqmt 5.755 52.88 304.32 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.832-(0.016*2))*1= sqmt 5.655 640.00 3619.11 (E)

Total (A+B+C+D+E) 33392.87Total without ED 29730.69

Add Water Charges @ 1% 1% 297.31Add CPOH @ 15% 15% 4504.20

Total cost per meter for pipe 34532.20Total cost per kg for specials 48.19

2.5.8.61

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

1.835 0.0175Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(1.835-0.0175)*0.0175*1*7850= kg 784.390Add 2 % wastage

2% kg 15.688Total Weight kg 800.078

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 800.078 34.21 27370.86 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 784.390 6.63 5200.51 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 15.688 27.00 423.57

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 10142.33 101.42 (C)

Material cost per meter Rs/meter 32249.22

External / outside bitumastic coating

1800 mm nominal dia (clear internal dia) of pipe with 17.5 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

1800 mm nominal dia (clear internal dia) of pipe with 16.0 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 540 Schedule of Rates 2014 - 2015

Page 363: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

13.65.1 Area of coating = pi()*d*L(3.1416)*1.835*1= sqmt 5.765 52.88 304.82 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(1.835-(0.0175*2))*1= sqmt 5.655 640.00 3619.11 (E)

Total (A+B+C+D+E) 36173.15Total without ED 32205.13

Add Water Charges @ 1% 1% 322.05Add CPOH @ 15% 15% 4879.08

Total cost per meter for pipe 37406.26Total cost per kg for specials 47.69

2.5.8.62

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

2.032 0.016Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(2.032-0.016)*0.016*1*7850= kg 795.481Add 2 % wastage

2% kg 15.910Total Weight kg 811.391

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 811.391 34.21 27757.89 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 795.481 6.63 5274.04 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 15.910 27.00 429.56

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 11591.23 115.91 (C)

Material cost per meter Rs/meter 32718.28

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*2.032*1= sqmt 6.384 52.88 337.55 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(2.032-(0.016*2))*1= sqmt 6.283 640.00 4021.24 (E)

Total (A+B+C+D+E) 37077.07Total without ED 33011.21

Add Water Charges @ 1% 1% 330.11Add CPOH @ 15% 15% 5001.20

Total cost per meter for pipe 38342.52Total cost per kg for specials 48.20

2.5.8.63

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

2.035 0.0175Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(2.035-0.0175)*0.0175*1*7850= kg 870.705Add 2 % wastage

2% kg 17.414Total Weight kg 888.119

2000 mm nominal dia (clear internal dia) of pipe with 17.5 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

2000 mm nominal dia (clear internal dia) of pipe with 16.0 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 541 Schedule of Rates 2014 - 2015

Page 364: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 888.119 34.21 30382.78 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 870.705 6.63 5772.78 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 17.414 27.00 470.18

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 11591.23 115.91 (C)

Material cost per meter Rs/meter 35801.29

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*2.035*1= sqmt 6.393 52.88 338.04 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(2.035-(0.0175*2))*1= sqmt 6.283 640.00 4021.24 (E)

Total (A+B+C+D+E) 40160.57Total without ED 35755.52

Add Water Charges @ 1% 1% 357.56Add CPOH @ 15% 15% 5416.96

Total cost per meter for pipe 41530.03Total cost per kg for specials 47.70

2.5.8.64

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

2.040 0.02Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(2.04-0.02)*0.02*1*7850= kg 996.325Add 2 % wastage

2% kg 19.926Total Weight kg 1016.251

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 1016.251 34.21 34766.21 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 996.325 6.63 6605.63 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 19.926 27.00 538.02

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 11591.23 115.91 (C)

Material cost per meter Rs/meter 40949.74

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*2.04*1= sqmt 6.409 52.88 338.87 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(2.04-(0.02*2))*1= sqmt 6.283 640.00 4021.24 (E)

Total (A+B+C+D+E) 45309.85Total without ED 40338.36

Add Water Charges @ 1% 1% 403.38Add CPOH @ 15% 15% 6111.26

Total cost per meter for pipe 46853.00Total cost per kg for specials 47.03

2.5.8.65

2000 mm nominal dia (clear internal dia) of pipe with 20.0 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

2200 mm nominal dia (clear internal dia) of pipe with 17.5 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 542 Schedule of Rates 2014 - 2015

Page 365: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

2.235 0.0175Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(2.235-0.0175)*0.0175*1*7850= kg 957.020Add 2 % wastage

2% kg 19.140Total Weight kg 976.161

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 976.161 34.21 33394.71 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 957.020 6.63 6345.05 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 19.140 27.00 516.79

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 13040.13 130.40 (C)

Material cost per meter Rs/meter 39353.36

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*2.235*1= sqmt 7.021 52.88 371.27 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(2.235-(0.0175*2))*1= sqmt 6.912 640.00 4423.36 (E)

Total (A+B+C+D+E) 44147.99Total without ED 39305.90

Add Water Charges @ 1% 1% 393.06Add CPOH @ 15% 15% 5954.84

Total cost per meter for pipe 45653.80Total cost per kg for specials 47.70

2.5.8.66

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

2.240 0.02Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(2.24-0.02)*0.02*1*7850= kg 1094.971Add 2 % wastage

2% kg 21.899Total Weight kg 1116.870

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 1116.870 34.21 38208.41 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 1094.971 6.63 7259.66 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 21.899 27.00 591.28

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 13040.13 130.40 (C)

Material cost per meter Rs/meter 45007.18

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*2.24*1= sqmt 7.037 52.88 372.10 (D)

2200 mm nominal dia (clear internal dia) of pipe with 20.0 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 543 Schedule of Rates 2014 - 2015

Page 366: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(2.24-(0.02*2))*1= sqmt 6.912 640.00 4423.36 (E)

Total (A+B+C+D+E) 49802.64Total without ED 44338.51

Add Water Charges @ 1% 1% 443.39Add CPOH @ 15% 15% 6717.29

Total cost per meter for pipe 51499.19Total cost per kg for specials 47.03

2.5.8.67

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

2.244 0.0222Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(2.2444-0.0222)*0.0222*1*7850= kg 1216.622Add 2 % wastage

2% kg 24.332Total Weight kg 1240.954

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 1240.954 34.21 42453.36 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 1216.622 6.63 8066.20 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 24.332 27.00 656.98

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 13040.13 130.40 (C)

Material cost per meter Rs/meter 49992.99

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*2.2444*1= sqmt 7.051 52.88 372.83 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(2.2444-(0.0222*2))*1= sqmt 6.912 640.00 4423.36 (E)

Total (A+B+C+D+E) 54789.18Total without ED 48776.52

Add Water Charges @ 1% 1% 487.77Add CPOH @ 15% 15% 7389.64

Total cost per meter for pipe 56653.93Total cost per kg for specials 46.57

2.5.8.68

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

2.540 0.02Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(2.54-0.02)*0.02*1*7850= kg 1242.940Add 2 % wastage

2% kg 24.859Total Weight kg 1267.799

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 1267.799 34.21 43371.70 (A)

2200 mm nominal dia (clear internal dia) of pipe with 22.2 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

2500 mm nominal dia (clear internal dia) of pipe with 20.0 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 544 Schedule of Rates 2014 - 2015

Page 367: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation_Volume III_pg no_320 Cost of Fabrication kg 1242.940 6.63 8240.69 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 24.859 27.00 671.19

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 14489.04 144.89 (C)

Material cost per meter Rs/meter 51086.10

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*2.54*1= sqmt 7.980 52.88 421.93 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(2.54-(0.02*2))*1= sqmt 7.854 640.00 5026.55 (E)

Total (A+B+C+D+E) 56534.58Total without ED 50331.51

Add Water Charges @ 1% 1% 503.32Add CPOH @ 15% 15% 7625.22

Total cost per meter for pipe 58460.05Total cost per kg for specials 47.03

2.5.8.69

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

2.544 0.0222Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(2.5444-0.0222)*0.0222*1*7850= kg 1380.868Add 2 % wastage

2% kg 27.617Total Weight kg 1408.485

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 1408.485 34.21 48184.62 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 1380.868 6.63 9155.15 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 27.617 27.00 745.67

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 14489.04 144.89 (C)

Material cost per meter Rs/meter 56738.99

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*2.5444*1= sqmt 7.993 52.88 422.66 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(2.5444-(0.0222*2))*1= sqmt 7.854 640.00 5026.55 (E)

Total (A+B+C+D+E) 62188.20Total without ED 55363.22

Add Water Charges @ 1% 1% 553.63Add CPOH @ 15% 15% 8387.53

Total cost per meter for pipe 64304.38Total cost per kg for specials 46.57

2.5.8.70

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

2500 mm nominal dia (clear internal dia) of pipe with 22.2 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

2500 mm nominal dia (clear internal dia) of pipe with 25.0 mm thick coil, internally coated with food grade epoxy coating and external / outsidebitumastic coating

Delhi Jal Board 545 Schedule of Rates 2014 - 2015

Page 368: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Detail for 1 meter Outer dia (d) = thickness of pipe (t1) =

2.550 0.025Length of pipe

=1.0

Weight of MS coil= pi()*(d-t1)*t1*L*7850(3.1416)*(2.55-0.025)*0.025*1*7850= kg 1556.757Add 2 % wastage

2% kg 31.135Total Weight kg 1587.892

Quotation_Volume III_pg no 59 - 60 Cost of MS coil kg 1587.892 34.21 54322.20 (A)

Quotation_Volume III_pg no_320 Cost of Fabrication kg 1556.757 6.63 10321.30 (B)

Quotation_Volume III_pg no_272 Cost of Scrap kg 31.135 27.00 840.65

Please refer Rate Analysis_Vol II_pg

no 20Carriage of steel 100m 1.00 14489.04 144.89 (C)

Material cost per meter Rs/meter 63947.74

External / outside bitumastic coating13.65.1 Area of coating = pi()*d*L

(3.1416)*2.55*1= sqmt 8.011 52.88 423.59 (D)

Quotation_Vol III_pg no 448 Inside food grade epoxy coating = pi()*(d-(t1*2))*L

(3.1416)*(2.55-(0.025*2))*1= sqmt 7.854 640.00 5026.55 (E)

Total (A+B+C+D+E) 69397.88Total without ED 61779.81

Add Water Charges @ 1% 1% 617.80Add CPOH @ 15% 15% 9359.64

Total cost per meter for pipe 71757.24Total cost per kg for specials 46.09

Delhi Jal Board 546 Schedule of Rates 2014 - 2015

Page 369: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

2.6 Specials (C.I. / D.I.)2.6.1

2.6.1.1 Upto 300 mm dia

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Details of cost for 1 QuintalMATERIAL:

1464 S & S C.I. standard specials upto 300 mm dia (heavy class) quintal 1 3600.00 3600.00

2309 Carriage of cast iron fittings tonne 0.10 94.65 9.47

18.24 Labour for laying quintal 1.00 255.40 255.40 (A)Total 3864.87

Total without ED 3468.85Add Water Charges @ 1% except on (A) 1% 32.13

Add CPOH @ 15% except on (A) 15% 486.84Cost of 1 quintal 3987.82

2.6.1.2 Above 300 mm dia

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Details of cost for 1 QuintalMATERIAL:

1466 S & S C.I. standard specials over 300 mm dia (heavy class) quintal 1 3700.00 3700.00

2309 Carriage of cast iron fittings tonne 0.10 94.65 9.47

18.24 Labour for laying quintal 1.00 255.40 255.40 (A)Total 3964.87

Total without ED 3557.85Add Water Charges @ 1% except on (A) 1% 33.02

Add CPOH @ 15% except on (A) 15% 500.32Cost of 1 quintal 4091.20

2.6.2

2.6.2.1 Upto 300 mm dia

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Details of cost for 1 QuintalMATERIAL:

1468 Flanged C.I. standard specials upto 300 mm dia (heavy class) quintal 1 5500.00 5500.00

2309 Carriage of cast iron fittings tonne 0.10 94.65 9.47

18.24 Labour for laying quintal 1.00 255.40 255.40 (A)Total 5764.87

Total without ED 5159.85Add Water Charges @ 1% except on (A) 1% 49.04

Add CPOH @ 15% except on (A) 15% 743.02Cost of 1 quintal 5951.91

Providing and laying S&S C.I. standard specials such as tees, bends, collars, tapers, caps etc. (Heavy class). The rates are excluding excise duty component.

Providing and laying flanged C.I. standard specials such as tees, bends, collars, tapers, caps etc., suitable for flanged jointing as per IS : 1538. The rates are excluding excise duty component.

Delhi Jal Board 663 Schedule of Rates 2014 - 2015

Page 370: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

2.6.2.2 Above 300 mm dia

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Details of cost for 1 QuintalMATERIAL:

1470 Flanged C.I. standard specials over 300 mm dia (heavy class) quintal 1 5800.00 5800.00

2309 Carriage of cast iron fittings tonne 0.10 94.65 9.47

18.24 Labour for laying quintal 1.00 255.40 255.40 (A)Total 6064.87

Total without ED 5426.84Add Water Charges @ 1% except on (A) 1% 51.71

Add CPOH @ 15% except on (A) 15% 783.47Cost of 1 quintal 6262.03

2.6.3

2.6.3.1 upto 300 mm dia

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Details of cost for 1 QuintalMATERIAL:

7710 S&S Centrifugally (Spun) C.I. Pipe specials suitable for mechanical joint as per I.S. 13382 up to 300 mm dia quintal 1 9000.00 9000.00

2309 Carriage of cast iron fittings tonne 0.10 94.65 9.47

18.24 Labour for laying quintal 1.00 255.40 255.40 (A)Total 9264.87

Total without ED 8274.83Add Water Charges @ 1% except on (A) 1% 80.19

Add CPOH @ 15% except on (A) 15% 1214.94Cost of 1 quintal 9569.97

2.6.3.2

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Details of cost for 1 QuintalMATERIAL:

7711 S&S Centrifugally (Spun) C.I. Pipe Specials suitable for mechanical joint as per I.S. 13382 over 300 mm dia quintal 1 9500.00 9500.00

2309 Carriage of cast iron fittings tonne 0.10 94.65 9.47

18.24 Labour for laying quintal 1.00 255.40 255.40 (A)Total 9764.87

Total without ED 8719.83Add Water Charges @ 1% except on (A) 1% 84.64

Add CPOH @ 15% except on (A) 15% 1282.36Cost of 1 quintal 10086.84

Providing and laying S&S C.I. Standard specials suitable for mechanical jointing as per IS : 13382. The rates are excluding excise duty component.

Above 300 mm dia

Delhi Jal Board 664 Schedule of Rates 2014 - 2015

Page 371: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

2.6.5

2.6.5.1

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Details of cost for 1 QuintalMATERIAL:

7682 Ductile Iron K - 12 specials suitable for push on jointing up to 600 mm dia quintal 1 13000.00 13000.00

2309 Carriage of cast iron fittings tonne 0.10 94.65 9.47

18.24 Labour for laying quintal 1.00 255.40 255.40 (A)Total 13264.87

Total without ED 11834.82Add Water Charges @ 1% except on (A) 1% 115.79

Add CPOH @ 15% except on (A) 15% 1754.28Cost of 1 quintal 13704.89

2.6.5.2

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Details of cost for 1 QuintalMATERIAL:

7683 Ductile Iron K - 12 specials suitable for push on jointing over 600 mm dia quintal 1 18000.00 18000.00

2309 Carriage of cast iron fittings tonne 0.10 94.65 9.47

18.24 Labour for laying quintal 1.00 255.40 255.40 (A)Total 18264.87

Total without ED 16284.80Add Water Charges @ 1% except on (A) 1% 160.29

Add CPOH @ 15% except on (A) 15% 2428.45Cost of 1 quintal 18873.55

2.6.6

2.6.6.1

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Details of cost for 1 QuintalMATERIAL:

7684 Ductile Iron specials suitable for mechanical jointing as per I.S. 9523 - up to 600 mm dia quintal 1 13700.00 13700.00

2309 Carriage of cast iron fittings tonne 0.10 94.65 9.47

18.24 Labour for laying quintal 1.00 255.40 255.40 (A)Total 13964.87

Total without ED 12457.82Add Water Charges @ 1% except on (A) 1% 122.02

Add CPOH @ 15% except on (A) 15% 1848.67Cost of 1 quintal 14428.51

2.6.6.2 Above 600 mm dia

Providing and laying D.I. specials of class K-12 suitable for push-on jointing as per IS : 9523. The rates are excluding excise duty component.

Above 600 mm dia

Upto 600 mm dia

Upto 600 mm dia

Providing and laying D.I. Specials of Class K - 12 suitable for mechanical jointing as per IS : 9523. The rates are excluding excise duty component.

Delhi Jal Board 665 Schedule of Rates 2014 - 2015

Page 372: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Details of cost for 1 QuintalMATERIAL:

7685 Ductile Iron Specials suitable for mechanical jointing as per I.S. 9523 over 600 mm dia quintal 1 19650.00 19650.00

2309 Carriage of cast iron fittings tonne 0.10 94.65 9.47

18.24 Labour for laying quintal 1.00 255.40 255.40 (A)Total 19914.87

Total without ED 17753.30Add Water Charges @ 1% except on (A) 1% 174.98

Add CPOH @ 15% except on (A) 15% 2650.93Cost of 1 quintal 20579.21

Delhi Jal Board 666 Schedule of Rates 2014 - 2015

Page 373: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

2.72.7.1

2.7.1.1 700 mm dia

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) Remark

Details of cost for 10 joints

MATERIAL:

Rubber insertions for 700 mm pipe joint ( Dia of Rubber ring, D =895mm, thickness = 3 mm, width = 49 mm) Each 10.00 146.00 1460.00

1034 Bolts & nuts 27 mm dia 130 mm long As per IS 1538:1993Dia = 27 mm

Length= 130 mmNo's= 240 no's

3.1416*(((27/1000)/2)^2)*(130/1000)*7850= 0.5843 kg

Hence, 240 no x 0.5843 kg = kg 140.23 56.00 7852.99

2205 Carriage of Materials tonne 0.14 94.65 13.27LABOUR

0116 Fitter (Grade1) day 0.85 435.00 369.75

0117 Assistant Fitter or 2nd class Fitter day 0.85 399.00 339.15

0114 Beldar day 2.20 329.00 723.80

Total 10758.96Add Water Charges @ 1% 1% 107.59

Add CPOH @ 15% 15% 1629.98Cost of 10 nos 12496.54

Cost of each 1249.65Say 1249.70

2.7.1.2 750 mm dia

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) Remark

Providing flanged joints to double flanged C.I./ D.I. pipes and specials, including testing of joints

Flanged joints to double flanged C.I./ D.I. pipes and specials

Labour output has been calculated by interpolation

of the values of labour coefficient taken from

DSR'14_item no 18.30 for dia 500 - 600 mm dia.

ITEM CODE DESCRIPTION UNIT QTY (INR) (INR) Remark

Details of cost for 10 jointsMATERIAL:

Rubber insertions for 750 mm pipe joint ( Dia of Rubber ring, D = 960mm, thickness = 3 mm, width = 51.5 mm) Each 10.00 157.00 1570.00

1034 Bolts & nuts 27 mm dia 130 mm long As per IS 1538:1993Dia = 27 mm

Length= 130 mmNo's= 240 no's

3.1416*(((27/1000)/2)^2)*(130/1000)*7850= 0.5843 kgHence, 240 no x 0.5843 kg = kg 140.23 56.00 7852.99

2205 Carriage of Materials tonne 0.14 94.65 13.27LABOUR

0116 Fitter (Grade1) day 0.90 435.00 391.50

0117 Assistant Fitter or 2nd class Fitter day 0.90 399.00 359.10

0114 Beldar day 2.30 329.00 756.70

Total 10943.56Add Water Charges @ 1% 1% 109.44

Add CPOH @ 15% 15% 1657.95Cost of 10 nos 12710.95

Labour output has been calculated by interpolation

of the values of labour coefficient taken from

DSR'14_item no 18.30 for dia 500 - 600 mm dia.

Delhi Jal Board 667 Schedule of Rates 2014 - 2015

Page 374: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) Remark

Cost of each 1271.10

Say 1271.10

2.7.1.3

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) Remark

Details of cost for 10 jointsMATERIAL:Rubber insertions for 800 mm pipe joint ( Dia of Rubber ring, D = 1015 mm, thickness = 3 mm, width = 55.5 mm)

Each 10.00 168.00 1680.00

1034 Bolts & nuts 30 mm dia 140 mm long @ 1 kg/no As per IS 1538:1993Dia = 30 mm

Length= 140 mmNo's= 240 no's

3.1416*(((30/1000)/2)^2)*(140/1000)*7850= 0.7769 kgHence, 240 no x 0.7769 kg = kg 186.46 56.00 10441.54

2205 Carriage of Materials tonne 0.19 94.65 17.65

LABOUR

0116 Fitter (Grade1) day 0.95 435.00 413.25

0117 Assistant Fitter or 2nd class Fitter day 0.95 399.00 379.05

0114 Beldar day 2.40 329.00 789.60

Total 13721.08Add Water Charges @ 1% 1% 137.21

Add CPOH @ 15% 15% 2078.74Cost of 10 nos 15937.04

Cost of each 1593.70Say 1593.80

2.7.1.4

Labour output has been calculated by interpolation

of the values of labour coefficient taken from

DSR'14_item no 18.30 for dia 500 - 600 mm dia.

800 mm dia

900 mm dia2.7.1.4

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) Remark

Details of cost for 10 jointsMATERIAL:Rubber insertions for 900 mm pipe joint ( Dia of Rubber ring, D = 1115 mm, thickness = 3 mm, width = 55.5 mm)

Each 10.00 189.00 1890.00

1034 Bolts & nuts 30 mm dia 140 mm long As per IS 1538:1993Dia = 30 mm

Length= 140 mmNo's= 280 no's

3.1416*(((30/1000)/2)^2)*(140/1000)*7850= 0.7769 kgHence, 280 no x 0.7769 kg = kg 217.53 56.00 12181.79

2205 Carriage of Materials tonne 0.22 94.65 20.59

LABOUR

0116 Fitter (Grade1) day 1.05 435.00 456.75

0117 Assistant Fitter or 2nd class Fitter day 1.05 399.00 418.95

0114 Beldar day 2.60 329.00 855.40

Total 15823.48Add Water Charges @ 1% 1% 158.23

Labour output has been calculated by interpolation

of the values of labour coefficient taken from

DSR'14_item no 18.30 for dia 500 - 600 mm dia.

900 mm dia

Delhi Jal Board 668 Schedule of Rates 2014 - 2015

Page 375: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) Remark

Add CPOH @ 15% 15% 2397.26Cost of 10 nos 18378.97

Cost of each 1837.90Say 1837.90

2.7.1.5

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) Remark

Details of cost for 10 jointsMATERIAL:Rubber insertions for 1000 mm pipe joint ( Dia of Rubber ring, D = 1230 mm, thickness = 3 mm, width = 59.5 mm)

Each 10.00 210.00 2100.00

1034 Bolts & nuts 33 mm dia 150 mm long As per IS 1538:1993Dia = 33 mm

Length= 150 mmNo's= 280 no's

3.1416*(((33/1000)/2)^2)*(150/1000)*7850= 1.0072 kgHence, 280 no x 1.0072 kg = kg 282.02 56.00 15792.90

2205 Carriage of Materials tonne 0.28 94.65 26.69

LABOUR

0116 Fitter (Grade1) day 1.15 435.00 500.25

0117 Assistant Fitter or 2nd class Fitter day 1.15 399.00 458.85

0114 Beldar day 2.80 329.00 921.20

Total 19799.89Add Water Charges @ 1% 1% 198.00

Add CPOH @ 15% 15% 2999.68Cost of 10 nos 22997.57

Cost of each 2299.76Say 2299.80

2.7.1.6

Labour output has been calculated by interpolation

of the values of labour coefficient taken from

DSR'14_item no 18.30 for dia 500 - 600 mm dia.

1000 mm dia

1050 mm dia2.7.1.6

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) Remark

Details of cost for 10 jointsMATERIAL:Rubber insertions for 1050 mm pipe joint ( Dia of Rubber ring, D = 1258 mm, thickness = 3 mm, width = 104 mm)

Each 10.00 221.00 2210.00

1034 Bolts & nuts 33 mm dia 150 mm long As per IS 1538:1993Dia = 33 mm

Length= 150 mmNo's= 280 no's

3.1416*(((33/1000)/2)^2)*(150/1000)*7850= 1.0072 kgHence, 280 no x 1.0072 kg = kg 282.02 56.00 15792.90

2205 Carriage of Materials tonne 0.28 94.65 26.69

LABOUR

0116 Fitter (Grade1) day 1.20 435.00 522.00

0117 Assistant Fitter or 2nd class Fitter day 1.20 399.00 478.80

0114 Beldar day 2.90 329.00 954.10

Total 19984.49Add Water Charges @ 1% 1% 199.84

Labour output has been calculated by interpolation

of the values of labour coefficient taken from

DSR'14_item no 18.30 for dia 500 - 600 mm dia.

1050 mm dia

Delhi Jal Board 669 Schedule of Rates 2014 - 2015

Page 376: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) Remark

Add CPOH @ 15% 15% 3027.65Cost of 10 nos 23211.98

Cost of each 2321.20Say 2321.20

2.7.1.7

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) Remark

Details of cost for 10 jointsMATERIAL:Rubber insertions for 1100 mm pipe joint ( Dia of Rubber ring, D = 1340 mm, thickness = 3 mm, width = 59.5 mm)

Each 10.00 232.00 2320.00

1034 Bolts & nuts 33 mm dia 160 mm long As per IS 1538:1993

Dia = 33 mm

Length= 160 mmNo's= 320 no's

3.1416*(((33/1000)/2)^2)*(160/1000)*7850= 1.0743 kgHence, 320 no x 1.0743 kg = kg 343.78 56.00 19251.46

2205 Carriage of Materials tonne 0.34 94.65 32.54

LABOUR

0116 Fitter (Grade1) day 1.25 435.00 543.75

0117 Assistant Fitter or 2nd class Fitter day 1.25 399.00 498.75

0114 Beldar day 3.00 329.00 987.00

Total 23633.49Add Water Charges @ 1% 1% 236.33

Add CPOH @ 15% 15% 3580.47Cost of 10 nos 27450.30

Cost of each 2745.03Say 2745.10

Labour output has been calculated by interpolation

of the values of labour coefficient taken from

DSR'14_item no 18.30 for dia 500 - 600 mm dia.

1100 mm dia

2.7.1.8

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) Remark

Details of cost for 10 jointsMATERIAL:Rubber insertions for 1200 mm pipe joint ( Dia of Rubber ring, D = 1455 mm, thickness = 3 mm, width = 63.5 mm)

Each 10.00 254.00 2540.00

1034 Bolts & nuts 36 mm dia 160 mm long As per IS 1538:1993Dia = 36 mm

Length= 160 mmNo's= 320 no's

3.1416*(((36/1000)/2)^2)*(160/1000)*7850= 1.2785 kgHence, 320 no x 1.2785 kg = kg 409.12 56.00 22910.72

2205 Carriage of Materials tonne 0.41 94.65 38.72

LABOUR

0116 Fitter (Grade1) day 1.35 435.00 587.25

0117 Assistant Fitter or 2nd class Fitter day 1.35 399.00 538.65

0114 Beldar day 3.20 329.00 1052.80

Total 27668.14

1200 mm dia

Labour output has been calculated by interpolation

of the values of labour coefficient taken from

DSR'14_item no 18.30 for dia 500 - 600 mm dia.

Delhi Jal Board 670 Schedule of Rates 2014 - 2015

Page 377: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) Remark

Add Water Charges @ 1% 1% 276.68Add CPOH @ 15% 15% 4191.72

Cost of 10 nos 32136.55Cost of each 3213.65

Say 3213.70

2.7.1.9

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) Remark

Details of cost for 10 jointsMATERIAL:Rubber insertions for 1400 mm pipe joint ( Dia of Rubber ring, D = 1675 mm, thickness = 3 mm, width = 72.5 mm)

Each 10.00 297.00 2970.00

1034 Bolts & nuts 39 mm dia 160 mm long As per IS 8329:2000Dia = 39 mm

Length= 160 mmNo's= 360 no's

3.1416*(((39/1000)/2)^2)*(160/1000)*7850= 1.5005 kgHence, 360 no x 1.5005 kg = kg 540.18 56.00 30250.08

2205 Carriage of Materials tonne 0.54 94.65 51.13

LABOUR

0116 Fitter (Grade1) day 1.45 435.00 630.75

0117 Assistant Fitter or 2nd class Fitter day 1.45 399.00 578.55

0114 Beldar day 3.40 329.00 1118.60

Total 35599.11Add Water Charges @ 1% 1% 355.99

Add CPOH @ 15% 15% 5393.26Cost of 10 nos 41348.36

Cost of each 4134.84Say 4134.90

Labour output has been calculated by interpolation

of the values of labour coefficient taken from

DSR'14_item no 18.30 for dia 500 - 600 mm dia.

1400 mm dia

2.7.1.10

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) Remark

Details of cost for 10 jointsMATERIAL:Rubber insertions for 1500 mm pipe joint ( Dia of Rubber ring, D = 1800 mm, thickness = 3 mm, width = 72.5 mm)

Each 10.00 319.00 3190.00

1034 Bolts & nuts 39 mm dia 170 mm long As per IS 1538:1993Dia = 39 mm

Length= 170 mmNo's= 400 no's

3.1416*(((39/1000)/2)^2)*(170/1000)*7850= 1.5942 kgHence, 400 no x 1.5942 kg = kg 637.68 56.00 35710.08

2205 Carriage of Materials tonne 0.64 94.65 60.36

LABOUR

0116 Fitter (Grade1) day 1.55 435.00 674.25

0117 Assistant Fitter or 2nd class Fitter day 1.55 399.00 618.45

0114 Beldar day 3.60 329.00 1184.40

Total 41437.54Add Water Charges @ 1% 1% 414.38

Add CPOH @ 15% 15% 6277.79Cost of 10 nos 48129.70

Cost of each 4812.97Say 4813.00

Labour output has been calculated by interpolation

of the values of labour coefficient taken from

DSR'14_item no 18.30 for dia 500 - 600 mm dia.

1500 mm dia

Delhi Jal Board 671 Schedule of Rates 2014 - 2015

Page 378: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

2.8 Cutting of C.I. and D.I. Pipes2.8.1

2.8.1.1

ITEM CODE DESCRIPTION UNIT QTY RATE

(INR)AMOUNT

(INR)Detail of cost for 1 cutLABOUR

0116 Fitter (Grade 1) day 0.70 435.00 304.500114 Beldar day 0.70 329.00 230.3009999 Sundries L.S. 9.01 1.78 16.04

Total 550.84Add Water Charges @ 1% 1% 5.51

Add CPOH @ 15% 15% 83.45Total cost for cutting of D.I. & C.I. pipe 639.81

Say 639.90

2.8.1.2ITEM CODE DESCRIPTION UNIT QTY RATE

(INR)AMOUNT

(INR)Detail of cost for 1 cutLABOUR

0116 Fitter (Grade 1) day 0.75 435.00 326.250114 Beldar day 0.75 329.00 246.7509999 Sundries L.S. 9.66 1.78 17.19

Total 590.19Add Water Charges @ 1% 1% 5.90

Add CPOH @ 15% 15% 89.41Total cost for cutting of D.I. & C.I. pipe 685.51

Say 685.60

2.8.1.3ITEM CODE DESCRIPTION UNIT QTY RATE

(INR)AMOUNT

(INR)Detail of cost for 1 cutLABOUR

0116 Fitter (Grade 1) day 0.80 435.00 348.000114 Beldar day 0.80 329.00 263.2009999 Sundries L.S. 10.30 1.78 18.34

Total 629.54Add Water Charges @ 1% 1% 6.30

Add CPOH @ 15% 15% 95.37Total cost for cutting of D.I. & C.I. pipe 731.21

Say 731.30

Labour for cutting C.I. / D.I. pipe with steel saw.

700 mm diameter

750 mm diameter

800 mm diameter

Delhi Jal Board 672 Schedule of Rates 2014 - 2015

Page 379: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

2.8.1.4ITEM CODE DESCRIPTION UNIT QTY RATE

(INR)AMOUNT

(INR)Detail of cost for 1 cutLABOUR

0116 Fitter (Grade 1) day 0.90 435.00 391.500114 Beldar day 0.90 329.00 296.1009999 Sundries L.S. 11.59 1.78 20.63

Total 708.23Add Water Charges @ 1% 1% 7.08

Add CPOH @ 15% 15% 107.30Total cost for cutting of D.I. & C.I. pipe 822.61

Say 822.70

2.8.1.5ITEM CODE DESCRIPTION UNIT QTY RATE

(INR)AMOUNT

(INR)Detail of cost for 1 cutLABOUR

0116 Fitter (Grade 1) day 1.00 435.00 435.000114 Beldar day 1.00 329.00 329.0009999 Sundries L.S. 12.88 1.78 22.92

Total 786.92Add Water Charges @ 1% 1% 7.87

Add CPOH @ 15% 15% 119.22Total cost for cutting of D.I. & C.I. pipe 914.01

Say 914.10

1000 mm diameter

900 mm diameter

Delhi Jal Board 673 Schedule of Rates 2014 - 2015

Page 380: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

2.9 ISI MARKED SLUICE VALVE2.9.1 CAST (SPUN) IRON SLUICE VALVE,

2.9.1.1

2.9.1.1.1

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Details of cost for 10 sluice valvesMATERIAL:

Quotation_Volume III_pg no

445 - 447Cast Iron Sluice Valve Nos 10 29070.00 290700.00

Carriage of sluice valvesWeight of Valve

450.00 kg10 Nos

2309 Carriage of fittings tonne 4.50 94.65 425.93

18.24 Labour for laying sluice valve quintal 45 255.40 11493.00 (A)18.30.8 Providing flanged joints to fixing sluice valves with bolts, nuts

and rubber insertion etc. each 20 499.45 9989.00 (B)

Total without excise duty 312607.93Add Water Charges @ 1% except on (A) & (B) 1% 2911.26

Add CPOH @ 15% except on (A) & (B) 15% 44105.58Cost of 10 valve 359624.76

Cost of each 35962.48Say 35962.48

2.9.1.1.2

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Details of cost for 10 sluice valvesMATERIAL:

Quotation_Volume III_pg no

445 - 447Cast Iron Sluice Valve Nos 10 38505.00 385050.00

Carriage of sluice valvesWeight of Valve

560.00 kg10 Nos

2309 Carriage of fittings tonne 5.60 94.65 530.04

18.24 Labour for laying sluice valve quintal 56 255.40 14302.40 (A)18.30.9 Providing flanged joints to fixing sluice valves with bolts, nuts

and rubber insertion etc. each 20 712.55 14251.00 (B)

Total without excise duty 414133.44Add Water Charges @ 1% except on (A) & (B) 1% 3855.80

Add CPOH @ 15% except on (A) & (B) 15% 58415.38Cost of 10 valve 476404.62

Cost of each 47640.46Say 47640.47

2.9.1.1.3

Providing and Fixing C.I. sluice valves (with cap) complete with bolts, nuts, rubber insertions etc. (the tail pieces ifrequired will be paid separately). ISI marked of Pressure rating PN 1.0 and of given sizes. The rates are excluding exciseduty component.

Size : 350 mm

Size : 400 mm

Size : 450 mm

Delhi Jal Board 674 Schedule of Rates 2014 - 2015

Page 381: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Details of cost for 10 sluice valvesMATERIAL:

Quotation_Volume III_pg no

445 - 447Cast Iron Sluice Valve Nos 10 48633.60 486336.00

Carriage of sluice valvesWeight of Valve

780.00 kg10 Nos

2309 Carriage of fittings tonne 7.80 94.65 738.27

18.24 Labour for laying sluice valve quintal 78 255.40 19921.20 (A)18.30.10 Providing flanged joints to fixing sluice valves with bolts, nuts

and rubber insertion etc. each 20 882.05 17641.00 (B)

Total without excise duty 524636.47Add Water Charges @ 1% except on (A) & (B) 1% 4870.74

Add CPOH @ 15% except on (A) & (B) 15% 73791.75Cost of 10 valve 603298.96

Cost of each 60329.90Say 60329.90

2.9.1.1.4

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Details of cost for 10 sluice valvesMATERIAL:

Quotation_Volume III_pg no

445 - 447Cast Iron Sluice Valve Nos 10 61067.40 610674.00

Carriage of sluice valvesWeight of Valve

880.00 kg10 Nos

2309 Carriage of fittings tonne 8.80 94.65 832.92

18.24 Labour for laying sluice valve quintal 88 255.40 22475.20 (A)18.30.11 Providing flanged joints to fixing sluice valves with bolts, nuts

and rubber insertion etc. each 20 1004.55 20091.00 (B)

Total without excise duty 654073.12Add Water Charges @ 1% except on (A) & (B) 1% 6115.07

Add CPOH @ 15% except on (A) & (B) 15% 92643.30Cost of 10 valve 752831.49

Cost of each 75283.15Say 75283.15

2.9.1.1.5

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Details of cost for 10 sluice valvesMATERIAL:

Quotation_Volume III_pg no

445 - 447Cast Iron Sluice Valve Nos 10 90627.00 906270.00

Size : 500 mm

Size : 600 mm

Delhi Jal Board 675 Schedule of Rates 2014 - 2015

Page 382: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Carriage of sluice valvesWeight of Valve

1200.00 kg10 Nos

2309 Carriage of fittings tonne 12.00 94.65 1135.80

18.24 Labour for laying sluice valve quintal 120 255.40 30648.00 (A)18.30.12 Providing flanged joints to fixing sluice valves with bolts, nuts

and rubber insertion etc. each 20 1178.95 23579.00 (B)

Total without excise duty 961632.80Add Water Charges @ 1% except on (A) & (B) 1% 9074.06

Add CPOH @ 15% except on (A) & (B) 15% 137471.98Cost of 10 valve 1108178.84

Cost of each 110817.88Say 110817.89

2.9.2 DUCTILE IRON SLUICE VALVE,2.9.2.1

2.9.2.1.1

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Details of cost for 10 sluice valvesMATERIAL:

Quotation_Volume III_pg no 83

A - 83 BDuctile Iron Sluice Valve Nos 10 46939.65 469396.54

Carriage of sluice valvesWeight of Valve

250.00 kg10 Nos

2309 Carriage of fittings tonne 2.50 94.65 236.63

18.24 Labour for laying sluice valve quintal 25 255.40 6385.00 (A)18.30.8 Providing flanged joints to fixing sluice valves with bolts, nuts

and rubber insertion etc. each 20 499.45 9989.00 (B)

Total without excise duty 486007.16Add Water Charges @ 1% except on (A) & (B) 1% 4696.33

Add CPOH @ 15% except on (A) & (B) 15% 71149.42Cost of 10 valve 561852.92

Cost of each 56185.29Say 56185.30

2.9.2.1.2

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Details of cost for 10 sluice valvesMATERIAL:

Quotation_Volume III_pg no 83

A - 83 BDuctile Iron Sluice Valve Nos 10 63019.90 630199.05

Carriage of sluice valvesWeight of Valve

350.00 kg

Providing and fixing D.I. sluice valves (with cap) complete with bolts, nuts, rubber insertions etc. (the tail pieces ifrequired will be paid separately). ISI marked of Pressure rating PN 1.0 and of given sizes. The rates are excluding exciseduty component.Size : 350 mm

Size : 400 mm

Delhi Jal Board 676 Schedule of Rates 2014 - 2015

Page 383: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

10 Nos2309 Carriage of fittings tonne 3.50 94.65 331.28

18.24 Labour for laying sluice valve quintal 35 255.40 8939.00 (A)18.30.9 Providing flanged joints to fixing sluice valves with bolts, nuts

and rubber insertion etc. each 20 712.55 14251.00 (B)

Total without excise duty 653720.32Add Water Charges @ 1% except on (A) & (B) 1% 6305.30

Add CPOH @ 15% except on (A) & (B) 15% 95525.34Cost of 10 valve 755550.97

Cost of each 75555.10Say 75555.10

2.9.2.1.3

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Details of cost for 10 sluice valvesMATERIAL:

Quotation_Volume III_pg no 83

A - 83 BDuctile Iron Sluice Valve Nos 10 73861.72 738617.17

Carriage of sluice valvesWeight of Valve

400.00 kg10 Nos

2309 Carriage of fittings tonne 4.00 94.65 378.60

18.24 Labour for laying sluice valve quintal 40 255.40 10216.00 (A)18.30.10 Providing flanged joints to fixing sluice valves with bolts, nuts

and rubber insertion etc. each 20 882.05 17641.00 (B)

Total without excise duty 766852.77Add Water Charges @ 1% except on (A) & (B) 1% 7389.96

Add CPOH @ 15% except on (A) & (B) 15% 111957.86Cost of 10 valve 886200.58

Cost of each 88620.06Say 88620.06

2.9.2.1.4

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Details of cost for 10 sluice valvesMATERIAL:

Quotation_Volume III_pg no 83

A - 83 BDuctile Iron Sluice Valve Nos 10 92820.00 928200.00

Carriage of sluice valvesWeight of Valve

500.00 kg10 Nos

2309 Carriage of fittings tonne 5.00 94.65 473.25

18.24 Labour for laying sluice valve quintal 50 255.40 12770.00 (A)18.30.11 Providing flanged joints to fixing sluice valves with bolts, nuts

and rubber insertion etc. each 20 1004.55 20091.00 (B)

Total without excise duty 961534.25

Size : 450 mm

Size : 500 mm

Delhi Jal Board 677 Schedule of Rates 2014 - 2015

Page 384: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Add Water Charges @ 1% except on (A) & (B) 1% 9286.73Add CPOH @ 15% except on (A) & (B) 15% 140694.00

Cost of 10 valve 1111514.98Cost of each 111151.50

Say 111151.50

2.9.2.1.5

ITEM CODE DESCRIPTION UNIT QTY RATE (INR) AMOUNT (INR) REMARKS

Details of cost for 10 sluice valvesMATERIAL:

Quotation_Volume III_pg no 83

A - 83 BDuctile Iron Sluice Valve Nos 10 137700.00 1377000.00

Carriage of sluice valvesWeight of Valve

700.00 kg10 Nos

2309 Carriage of fittings tonne 7.00 94.65 662.55

18.24 Labour for laying sluice valve quintal 70 255.40 17878.00 (A)18.30.12 Providing flanged joints to fixing sluice valves with bolts, nuts

and rubber insertion etc. each 20 1178.95 23579.00 (B)

Total without excise duty 1419119.55Add Water Charges @ 1% except on (A) & (B) 1% 13776.63

Add CPOH @ 15% except on (A) & (B) 15% 208715.88Cost of 10 valve 1641612.05

Cost of each 164161.21Say 164161.21

Size : 600 mm

Delhi Jal Board 678 Schedule of Rates 2014 - 2015

Page 385: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

2.10 KINETIC DOUBLE TYPE AIR VALVES2.10.1

2.10.1.1

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Details of cost for 10 air valvesMATERIAL:

Quotation_Volume III_pg no 83-

BCast Iron Air Valves Nos 10 4150.44 41504.45

Carriage of Air ValvesWeight of Valve

95.00 kg10 Nos

2309 Carriage of fittings tonne 0.95 94.65 89.92

18.24 Labour for laying Air Valves quintal 9.5 255.40 2426.30 (A)

18.30.4 Providing flanged joints to fixing air valves with bolts, nuts andrubber insertion etc.

each 20 234.55 4691.00 (B)

Total without excise duty 48711.67Add Water Charges @ 1% except on (A) & (B) 1% 415.94

Add CPOH @ 15% except on (A) & (B) 15% 6301.55Cost of 10 valve 55429.16

Cost of each 5542.92Say 5542.92

2.10.1.2

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR) REMARKS

Details of cost for 10 air valvesMATERIAL:

Quotation_Volume III_pg no

403Cast Iron Air Valves Nos 10 8415.95 84159.53

Carriage of Air ValvesWeight of Valve

175.00 kg10 Nos

2309 Carriage of fittings tonne 1.75 94.65 165.64

18.24 Labour for laying Air Valves quintal 17.5 255.40 4469.50 (A)

18.30.5 Providing flanged joints to fixing air valves with bolts, nuts andrubber insertion etc.

each 20 240.35 4807.00 (B)

Total without excise duty 93601.67Add Water Charges @ 1% except on (A) & (B) 1% 843.25

Add CPOH @ 15% except on (A) & (B) 15% 12775.26Cost of 10 valve 107220.18

Cost of each 10722.02Say 10722.02

Providing and fixing C.I. double acting air valve of approved quality with bolts, nuts, rubber insertions etc.complete (The tail pieces, tapers etc. if required will be paid separately). ISI marked of Pressure rating PN 1.0 andof given sizes. The rates are excluding excise duty component.

Size : 150 mm

Size : 200 mm

Delhi Jal Board 679 Schedule of Rates 2014 - 2015

Page 386: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

2.11 Laying of M.S. Pipes2.11.1

ITEM CODE DESCRIPTION UNIT QTY RATE (INR)

AMOUNT (INR)

18.23 Labour for laying quintal 1 137.40 137.40

Cost for 1 quintal 137.40Say 137.40

2.12 Laying of M.S. Special2.12.1

ITEM CODE DESCRIPTION UNIT QTY RATE AMOUNT

18.24 Labour for laying quintal 1 255.40 255.40

Cost for 1 quintal 255.40Say 255.40

Laying in position M.S. pipes (excluding cost of pipes) of various dia as directed byEngineer-in- charge. .

Laying in position M.S. special such as tees, bends, collars, tapers and caps etc.(excluding cost of specials).

Delhi Jal Board 680 Schedule of Rates 2014 - 2015

Page 387: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

2.13 High Density Polyethylene (HDPE) Pipes

2.13.1

2.13.1.1 110 mm nominal outer diameter (OD) HDPE pipe of material grade PE 80 / PN 6

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 110 mm dia (OD) HDPE pipe of material grade PE 80/ PN

6.0 as confirm to IS 4984.1995.

Details of Cost for 30 MMaterial

Quotation Enclosed

110 mm dia (OD) HDPE pipe of material grade PE 80/ PN 6.0 as confirm to IS 4984.1995. meter 30 249.61 7488.432

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3Diameter of HDPE Pipe = 110 mmLength of HDPE Pipe = 30 meterThickness of HDPE Pipe = 7.2 mm

3.1416*((110-7.2)/1000)*30*(7.2/1000)*946.4 = 66.02 kg

66.02 / 30 = 2.2007 kg/ mtr

(ii) Carriage of Spun iron S & S pipes 100 mm dia :-2319 Qty = 50 to consider 50% of carriage 100 meters 15 232.76 34.914

Total without excise duty = 7523.346Add 1% water charges = 1% 75.233

Add 15% CPOH = 15% 1139.787Cost of 30 mtr pipe = 8738.366

Cost for 1 meter pipe = 291.279Say = 291.3

Providing and Supplying in standard lengths High Density Polyethylene (H.D.P.E) Pipes, confirming to IS 4984:1995 and IS 7328:1992 (amended upto date), including all local & central taxes, transportation and freight charges inspection charges, loading / unloading charges, conveyance to the departmental stores / site & stacking the same in closed shade duly protecting from sunrays & rain, etc. complete. These rates are excluding excise duty component.

2.13.1.2 125 mm nominal outer diameter (OD) HDPE pipe of material grade PE 80 / PN 6

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 125 mm dia (OD) HDPE pipe of material grade PE 80/ PN

6.0 as confirm to IS 4984.1995.

Details of Cost for 30 MMaterial

Quotation Enclosed

125 mm dia (OD) HDPE pipe of material grade PE 80/ PN 6.0 as confirm to IS 4984.1995. meter 30 320.93 9627.984

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 125 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 8.10 mm3.1416*((125-8.1)/1000)*30*(8.1/1000)*946.4 = 84.46 kg

84.46 / 30 = 2.815 kg/ mtr

(ii) Carriage of Spun iron S & S pipes 125 mm dia :-2320 Qty = 50 to consider 50% of carriage 100 meters 15 310.91 46.6365

Total without excise duty = 9674.621Add 1% water charges = 1% 96.746

Add 15% CPOH = 15% 1465.705Cost of 30 mtr pipe = 11237.072

Cost for 1 meter pipe = 374.569Say = 374.6

2.13.1.3 140 mm nominal outer diameter (OD) HDPE pipe of material grade PE 80 / PN 6

Delhi 'Jal Board 1 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 388: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 140 mm dia (OD) HDPE pipe of material grade PE 80/ PN

6.0 as confirm to IS 4984.1995.

Details of Cost for 30 MMaterial

Quotation Enclosed

140 mm dia (OD) HDPE pipe of material grade PE 80/ PN 6.0 as confirm to IS 4984.1995. meter 30 404.14 12124.128

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 140 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 9.00 mm3.1416*((140-9)/1000)*30*(9/1000)*946.4 = 105.17 kg

105.17 / 30 = 3.506 kg/ mtr

(ii) Carriage of Spun iron S & S pipes 140 mm dia :-2321 Qty = 50 to consider 50% of carriage 100 meters 15 387.93 58.1895

Total without excise duty = 12182.318Add 1% water charges = 1% 121.823

Add 15% CPOH = 15% 1845.621Cost of 30 mtr pipe = 14149.762

Cost for 1 meter pipe = 471.659Say = 471.7

2.13.1.4 160 mm nominal outer diameter (OD) HDPE pipe of material grade PE 80 / PN 6

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 160 mm dia (OD) HDPE pipe of material grade PE 80/ PN

6.0 as confirm to IS 4984.1995.

Details of Cost for 30 MMaterial

Quotation Enclosed

160 mm dia (OD) HDPE pipe of material grade PE 80/ PN 6.0 as confirm to IS 4984.1995. meter 30 523.00 15690.048Enclosed 6.0 as confirm to IS 4984.1995.

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 160 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 10.30 mm3.1416*((160-10.3)/1000)*30*(10.3/1000)*946.4 = 137.54 kg

137.54 / 30 = 4.585 kg/ mtr

(ii) Carriage of Spun iron S & S pipes 140 mm dia :-2321 Qty = 50 to consider 50% of carriage 100 meters 15 387.93 58.1895

Total without excise duty = 15748.238Add 1% water charges = 1% 157.482

Add 15% CPOH = 15% 2385.858Cost of 30 mtr pipe = 18291.578

Cost for 1 meter pipe = 609.719Say = 609.7

2.13.1.5 180 mm nominal outer diameter (OD) HDPE pipe of material grade PE 80 / PN 6

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 180 mm dia (OD) HDPE pipe of material grade PE 80/ PN

6.0 as confirm to IS 4984.1995.

Details of Cost for 30 MMaterial

Quotation Enclosed

180 mm dia (OD) HDPE pipe of material grade PE 80/ PN 6.0 as confirm to IS 4984.1995. meter 30 653.75 19612.560

Weight of HDPE Pipe :-

Delhi 'Jal Board 2 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 389: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Density of HDPE Pipe = 946.4 kg/m3Diameter of HDPE Pipe = 180 mm

Length of HDPE Pipe = 30 meterThickness of HDPE Pipe = 11.50 mm

3.1416*((180-11.5)/1000)*30*(11.5/1000)*946.4 = 172.84 kg172.84 / 30 = 5.761 kg/ mtr

(ii) Carriage of Spun iron S & S pipes 200 mm dia :-2322 Qty = 50 to consider 50% of carriage 100 meters 15 631.03 94.6545

Total without excise duty = 19707.215Add 1% water charges = 1% 197.072

Add 15% CPOH = 15% 2985.643Cost of 30 mtr pipe = 22889.930

Cost for 1 meter pipe = 762.998Say = 763

2.13.1.6 200 mm nominal outer diameter (OD) HDPE pipe of material grade PE 80 / PN 6

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 200 mm dia (OD) HDPE pipe of material grade PE 80/ PN

6.0 as confirm to IS 4984.1995.

Details of Cost for 30 MMaterial

Quotation Enclosed

200 mm dia (OD) HDPE pipe of material grade PE 80/ PN 6.0 as confirm to IS 4984.1995. meter 30 808.28 24248.256

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 200 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 12.80 mm3.1416*((200-12.8)/1000)*30*(12.8/1000)*946.4 = 213.73 kg

213.73 / 30 = 7.124 kg/ mtr

(ii) Carriage of Spun iron S & S pipes 200 mm dia :-

2322 Qty = 50 to consider 50% of carriage 100 meters 15 631.03 94.65452322 Qty = 50 to consider 50% of carriage 100 meters 15 631.03 94.6545

Total without excise duty = 24342.910Add 1% water charges = 1% 243.429

Add 15% CPOH = 15% 3687.951Cost of 30 mtr pipe = 28274.291

Cost for 1 meter pipe = 942.476Say = 942.5

2.13.1.7 225 mm nominal outer diameter (OD) HDPE pipe of material grade PE 80 / PN 6

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 225 mm dia (OD) HDPE pipe of material grade PE 80/ PN

6.0 as confirm to IS 4984.1995.

Details of Cost for 30 MMaterial

Quotation Enclosed

225 mm dia (OD) HDPE pipe of material grade PE 80/ PN 6.0 as confirm to IS 4984.1995. meter 30 1022.23 30666.912

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 225 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 14.30 mm3.1416*((225-14.3)/1000)*30*(14.3/1000)*946.4 = 268.75 kg

268.75 / 30 = 8.958 kg/ mtr

(ii) Carriage of Spun iron S & S pipes 250 mm dia :-2323 Qty = 50 to consider 50% of carriage 100 meters 15 896.73 134.5095

Delhi 'Jal Board 3 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 390: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Total without excise duty = 30801.422Add 1% water charges = 1% 308.014

Add 15% CPOH = 15% 4666.415Cost of 30 mtr pipe = 35775.851

Cost for 1 meter pipe = 1192.528Say = 1192.5

2.13.1.8 110 mm nominal outer diameter (OD) HDPE pipe of material grade PE 80 / PN 10 Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 110 mm dia (OD) HDPE pipe of material grade PE 80/ PN

10 as confirm to IS 4984.1995.

Details of Cost for 30 MMaterial

Quotation Enclosed

110 mm dia (OD) HDPE pipe of material grade PE 80/ PN 10 as confirm to IS 4984.1995. meter 30 380.36 11410.944

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 110 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 10.00 mm3.1416*((110-10)/1000)*30*(10/1000)*946.4 = 89.2 kg

89.2 / 30 = 2.973 kg/ mtrCarriage of Spun iron S & S pipes 100 mm dia

2319 Qty = 50 to consider 50% of carriage 100 meter 15 232.76 34.914Total without excise duty = 11445.858

Add 1% water charges = 1% 114.459Add 15% CPOH = 15% 1734.047

Cost of 30 mtr pipe = 13294.364Cost for 1 meter pipe = 443.145

Say = 443.1

2.13.1.9 125 mm nominal outer diameter (OD) HDPE pipe of material grade PE 80 / PN 10 Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 125 mm dia (OD) HDPE pipe of material grade PE 80/ PN

10 as confirm to IS 4984.1995.Details of Cost for 30 MDetails of Cost for 30 MMaterial

Quotation Enclosed

125 mm dia (OD) HDPE pipe of material grade PE 80/ PN 10 as confirm to IS 4984.1995. meter 30 487.34 14620.272

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 125 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 11.40 mm3.1416*((125-11.4)/1000)*30*(11.4/1000)*946.4 = 115.52 kg

115.52 / 30 = 3.851 kg/ mtrCarriage of Spun iron S & S pipes 125 mm dia

2320 Qty = 50 to consider 50% of carriage 100 meter 15 310.91 46.6365Total without excise duty = 14666.909

Add 1% water charges = 1% 146.669Add 15% CPOH = 15% 2222.037

Cost of 30 mtr pipe = 17035.614Cost for 1 meter pipe = 567.854

Say = 567.9

2.13.1.10 140 mm nominal outer diameter (OD) HDPE pipe of material grade PE 80 / PN 10 Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 140 mm dia (OD) HDPE pipe of material grade PE 80/ PN

10 as confirm to IS 4984.1995.Details of Cost for 30 MMaterial

Quotation Enclosed

140 mm dia (OD) HDPE pipe of material grade PE 80/ PN 10 as confirm to IS 4984.1995. meter 30 606.21 18186.192

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Delhi 'Jal Board 4 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 391: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Diameter of HDPE Pipe = 140 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 12.80 mm3.1416*((140-12.8)/1000)*30*(12.8/1000)*946.4 = 145.23 kg

145.23 / 30 = 4.841 kg/ mtrCarriage of Spun iron S & S pipes 150 mm dia

2321 Qty = 50 to consider 50% of carriage 100 meter 15 387.93 58.1895Total without excise duty = 18244.382

Add 1% water charges = 1% 182.444Add 15% CPOH = 15% 2764.024

Cost of 30 mtr pipe = 21190.849Cost for 1 meter pipe = 706.362

Say = 706.4

2.13.1.11 160 mm nominal outer diameter (OD) HDPE pipe of material grade PE 80 / PN 10 Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 160 mm dia (OD) HDPE pipe of material grade PE 80/ PN

10 as confirm to IS 4984.1995.Details of Cost for 30 MMaterial

Quotation Enclosed

160 mm dia (OD) HDPE pipe of material grade PE 80/ PN 10 as confirm to IS 4984.1995. meter 30 796.39 23891.664

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 160 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 14.60 mm3.1416*((160-14.6)/1000)*30*(14.6/1000)*946.4 = 189.35 kg

189.35 / 30 = 6.312 kg/ mtrCarriage of Spun iron S & S pipes 150 mm dia

2321 Qty = 50 to consider 50% of carriage 100 meter 15 387.93 58.1895Total without excise duty = 23949.854

Add 1% water charges = 1% 239.499Add 15% CPOH = 15% 3628.403

Cost of 30 mtr pipe = 27817.755Cost for 1 meter pipe = 927.258

Say = 927.3

2.13.1.12 180 mm nominal outer diameter (OD) HDPE pipe of material grade PE 80 / PN 10 2.13.1.12 180 mm nominal outer diameter (OD) HDPE pipe of material grade PE 80 / PN 10 Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 180 mm dia (OD) HDPE pipe of material grade PE 80/ PN

10 as confirm to IS 4984.1995.Details of Cost for 30 MMaterial

Quotation Enclosed

180 mm dia (OD) HDPE pipe of material grade PE 80/ PN 10 as confirm to IS 4984.1995. meter 30 1010.34 30310.320

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 180 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 16.40 mm3.1416*((180-16.4)/1000)*30*(16.4/1000)*946.4 = 239.32 kg

239.32 / 30 = 7.977 kg/ mtrCarriage of Spun iron S & S pipes 200 mm dia

2322 Qty = 50 to consider 50% of carriage 100 meter 15 631.03 94.6545Total without excise duty = 30404.975

Add 1% water charges = 1% 304.050Add 15% CPOH = 15% 4606.354

Cost of 30 mtr pipe = 35315.378Cost for 1 meter pipe = 1177.179

Say = 1177.2

2.13.1.13 200 mm nominal outer diameter (OD) HDPE pipe of material grade PE 80 / PN 10 Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 200 mm dia (OD) HDPE pipe of material grade PE 80/ PN

10 as confirm to IS 4984.1995.Details of Cost for 30 MMaterial

Delhi 'Jal Board 5 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 392: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation Enclosed

200 mm dia (OD) HDPE pipe of material grade PE 80/ PN 10 as confirm to IS 4984.1995. meter 30 1236.19 37085.568

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 200 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 18.20 mm3.1416*((200-18.2)/1000)*30*(18.2/1000)*946.4 = 295.13 kg

295.13 / 30 = 9.838 kg/ mtrCarriage of Spun iron S & S pipes 200 mm dia

2322 Qty = 50 to consider 50% of carriage 100 meter 15 631.03 94.6545Total without excise duty = 37180.223

Add 1% water charges = 1% 371.802Add 15% CPOH = 15% 5632.804

Cost of 30 mtr pipe = 43184.828Cost for 1 meter pipe = 1439.494

Say = 1439.5

2.13.1.14 225 mm nominal outer diameter (OD) HDPE pipe of material grade PE 80 / PN 10 Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 225 mm dia (OD) HDPE pipe of material grade PE 80/ PN

10 as confirm to IS 4984.1995.Details of Cost for 30 MMaterial

Quotation Enclosed

225 mm dia (OD) HDPE pipe of material grade PE 80/ PN 10 as confirm to IS 4984.1995. meter 30 1569.00 47070.144

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 225 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 20.50 mm3.1416*((225-20.5)/1000)*30*(20.5/1000)*946.4 = 373.94 kg

373.94 / 30 = 12.465 kg/ mtrCarriage of Spun iron S & S pipes 250 mm dia

2323 Qty = 50 to consider 50% of carriage 100 meter 15 896.73 134.5095Total without excise duty = 47204.654

Add 1% water charges = 1% 472.047Add 15% CPOH = 15% 7151.505Add 15% CPOH = 15% 7151.505

Cost of 30 mtr pipe = 54828.205Cost for 1 meter pipe = 1827.607

Say = 1827.6

2.13.1.15 110 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 6 Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 110 mm nominal outer diameter (OD) HDPE pipe of

material grade PE 100 / PN 6 Details of Cost for 30 MMaterial

Quotation Enclosed

110 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 6 meter 30 205.00 6149.920

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 110 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 5.00 mm3.1416*((110-5)/1000)*30*(5/1000)*946.4 = 46.83 kg

46.83 / 30 = 1.561 kg/ mtrCarriage of Spun iron S & S pipes 100 mm dia

2319 Qty = 50 to consider 50% of carriage 100 meter 15 232.76 34.914Total without excise duty = 6184.834

Add 1% water charges = 1% 61.848Add 15% CPOH = 15% 937.002

Cost of 30 mtr pipe = 7183.685Cost for 1 meter pipe = 239.456

Say = 239.5

2.13.1.16 125 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 6 Code No Description Unit Qty Rate (INR) Amount (INR)

Delhi 'Jal Board 6 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 393: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

(a) Providing and supplying of (i) 125 mm nominal outer diameter (OD) HDPE pipe of

material grade PE 100 / PN 6 Details of Cost for 30 MMaterial

Quotation Enclosed

125 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 6 meter 30 265.29 7958.720

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 125 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 5.70 mm3.1416*((125-5.7)/1000)*30*(5.7/1000)*946.4 = 60.66 kg

60.66 / 30 = 2.022 kg/ mtrCarriage of Spun iron S & S pipes 125 mm dia

2320 Qty = 50 to consider 50% of carriage 100 meter 15 310.91 46.6365Total without excise duty = 8005.357

Add 1% water charges = 1% 80.054Add 15% CPOH = 15% 1212.812

Cost of 30 mtr pipe = 9298.222Cost for 1 meter pipe = 309.941

Say = 309.9

2.13.1.17 140 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 6 Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 140 mm nominal outer diameter (OD) HDPE pipe of

material grade PE 100 / PN 6 Details of Cost for 30 MMaterial

Quotation Enclosed

140 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 6 meter 30 325.58 9767.520

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 140 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 6.40 mm3.1416*((140-6.4)/1000)*30*(6.4/1000)*946.4 = 76.27 kg

76.27 / 30 = 2.542 kg/ mtr76.27 / 30 = 2.542 kg/ mtrCarriage of Spun iron S & S pipes 150 mm dia

2321 Qty = 50 to consider 50% of carriage 100 meter 15 387.93 58.1895Total without excise duty = 9825.710

Add 1% water charges = 1% 98.257Add 15% CPOH = 15% 1488.595

Cost of 30 mtr pipe = 11412.562Cost for 1 meter pipe = 380.419

Say = 380.4

2.13.1.18 160 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 6 Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 160 mm nominal outer diameter (OD) HDPE pipe of

material grade PE 100 / PN 6 Details of Cost for 30 MMaterial

Quotation Enclosed

160 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 6 meter 30 434.11 13023.360

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 160 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 7.30 mm3.1416*((160-7.3)/1000)*30*(7.3/1000)*946.4 = 99.43 kg

99.43 / 30 = 3.314 kg/ mtrCarriage of Spun iron S & S pipes 150 mm dia

2321 Qty = 50 to consider 50% of carriage 100 meter 15 387.93 58.1895Total without excise duty = 13081.550

Add 1% water charges = 1% 130.815Add 15% CPOH = 15% 1981.855

Cost of 30 mtr pipe = 15194.220

Delhi 'Jal Board 7 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 394: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Cost for 1 meter pipe = 506.474Say = 506.5

2.13.1.19 180 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 6 Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 180 mm nominal outer diameter (OD) HDPE pipe of

material grade PE 100 / PN 6 Details of Cost for 30 MMaterial

Quotation Enclosed

180 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 6 meter 30 542.64 16279.200

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 180 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 8.20 mm3.1416*((180-8.2)/1000)*30*(8.2/1000)*946.4 = 125.66 kg

125.66 / 30 = 4.189 kg/ mtrCarriage of Spun iron S & S pipes 200 mm dia

2322 Qty = 50 to consider 50% of carriage 100 meter 15 631.03 94.6545Total without excise duty = 16373.855

Add 1% water charges = 1% 163.739Add 15% CPOH = 15% 2480.639

Cost of 30 mtr pipe = 19018.232Cost for 1 meter pipe = 633.941

Say = 633.9

2.13.1.20 200 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 6 Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 200 mm nominal outer diameter (OD) HDPE pipe of

material grade PE 100 / PN 6 Details of Cost for 30 MMaterial

Quotation Enclosed

200 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 6 meter 30 663.23 19896.800

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 200 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 9.10 mm3.1416*((200-9.1)/1000)*30*(9.1/1000)*946.4 = 154.96 kg

154.96 / 30 = 5.165 kg/ mtrCarriage of Spun iron S & S pipes 200 mm dia

2322 Qty = 50 to consider 50% of carriage 100 meter 15 631.03 94.6545Total without excise duty = 19991.455

Add 1% water charges = 1% 199.915Add 15% CPOH = 15% 3028.705

Cost of 30 mtr pipe = 23220.074Cost for 1 meter pipe = 774.002

Say = 774

2.13.1.21 225 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 6 Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 225 mm nominal outer diameter (OD) HDPE pipe of

material grade PE 100 / PN 6 Details of Cost for 30 MMaterial

Quotation Enclosed

225 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 6 meter 30 844.11 25323.200

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 225 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 10.30 mm3.1416*((225-10.3)/1000)*30*(10.3/1000)*946.4 = 197.25 kg

197.25 / 30 = 6.575 kg/ mtrCarriage of Spun iron S & S pipes 250 mm dia

Delhi 'Jal Board 8 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 395: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

2323 Qty = 50 to consider 50% of carriage 100 meter 15 896.73 134.5095Total without excise duty = 25457.710

Add 1% water charges = 1% 254.577Add 15% CPOH = 15% 3856.843

Cost of 30 mtr pipe = 29569.130Cost for 1 meter pipe = 985.638

Say = 985.6

2.13.1.22 110 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 10 Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 110 mm nominal outer diameter (OD) HDPE pipe of

material grade PE 100 / PN 10 Details of Cost for 30 MMaterial

Quotation Enclosed

110 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 10 meter 30 313.53 9405.760

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 110 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 8.10 mm3.1416*((110-8.1)/1000)*30*(8.1/1000)*946.4 = 73.63 kg

73.63 / 30 = 2.454 kg/ mtrCarriage of Spun iron S & S pipes 100 mm dia

2319 Qty = 50 to consider 50% of carriage 100 meter 15 232.76 34.914Total without excise duty = 9440.674

Add 1% water charges = 1% 94.407Add 15% CPOH = 15% 1430.262

Cost of 30 mtr pipe = 10965.343Cost for 1 meter pipe = 365.511

Say = 365.5

2.13.1.23 125 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 10 Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 125 mm nominal outer diameter (OD) HDPE pipe of

material grade PE 100 / PN 10 Details of Cost for 30 MMaterial

Quotation Enclosed

125 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 10 meter 30 409.99 12299.840

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 125 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 9.20 mm3.1416*((125-9.2)/1000)*30*(9.2/1000)*946.4 = 95.03 kg

95.03 / 30 = 3.168 kg/ mtrCarriage of Spun iron S & S pipes 125 mm dia

2320 Qty = 50 to consider 50% of carriage 100 meter 15 310.91 46.6365Total without excise duty = 12346.477

Add 1% water charges = 1% 123.465Add 15% CPOH = 15% 1870.491

Cost of 30 mtr pipe = 14340.432Cost for 1 meter pipe = 478.014

Say = 478

2.13.1.24 140 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 10 Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 140 mm nominal outer diameter (OD) HDPE pipe of

material grade PE 100 / PN 10 Details of Cost for 30 MMaterial

Quotation Enclosed

140 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 10 meter 30 506.46 15193.920

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 140 mm

Delhi 'Jal Board 9 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 396: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Length of HDPE Pipe = 30 meterThickness of HDPE Pipe = 10.30 mm

3.1416*((140-10.3)/1000)*30*(10.3/1000)*946.4 = 119.16 kg119.16 / 30 = 3.972 kg/ mtr

Carriage of Spun iron S & S pipes 150 mm dia 2321 Qty = 50 to consider 50% of carriage 100 meter 15 387.93 58.1895

Total without excise duty = 15252.110Add 1% water charges = 1% 152.521

Add 15% CPOH = 15% 2310.695Cost of 30 mtr pipe = 17715.325

Cost for 1 meter pipe = 590.511Say = 590.5

2.13.1.25 160 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 10

Code No Description Unit Qty Rate (INR) Amount (INR) (a) Providing and supplying of (i) 160 mm nominal outer diameter (OD) HDPE pipe of

material grade PE 100 / PN 10 Details of Cost for 30 MMaterial

Quotation Enclosed

160 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 10 meter 30 663.23 19896.800

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 160 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 11.80 mm3.1416*((160-11.8)/1000)*30*(11.8/1000)*946.4 = 155.99 kg

155.99 / 30 = 5.200 kg/ mtrCarriage of Spun iron S & S pipes 150 mm dia

2321 Qty = 50 to consider 50% of carriage 100 meter 15 387.93 58.1895Total without excise duty = 19954.990

Add 1% water charges = 1% 199.550Add 15% CPOH = 15% 3023.181

Cost of 30 mtr pipe = 23177.720Cost for 1 meter pipe = 772.591

Say = 772.6

2.13.1.26 180 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 10 2.13.1.26 180 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 10 Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 180 mm nominal outer diameter (OD) HDPE pipe of

material grade PE 100 / PN 10 Details of Cost for 30 MMaterial

Quotation Enclosed

180 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 10 meter 30 844.11 25323.200

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 180 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 13.30 mm3.1416*((180-13.3)/1000)*30*(13.3/1000)*946.4 = 197.76 kg

197.76 / 30 = 6.592 kg/ mtrCarriage of Spun iron S & S pipes 200 mm dia

2322 Qty = 50 to consider 50% of carriage 100 meter 15 631.03 94.6545Total without excise duty = 25417.855

Add 1% water charges = 1% 254.179Add 15% CPOH = 15% 3850.805

Cost of 30 mtr pipe = 29522.838Cost for 1 meter pipe = 984.095

Say = 984.1

2.13.1.27 200 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 10 Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 200 mm nominal outer diameter (OD) HDPE pipe of

material grade PE 100 / PN 10 Details of Cost for 30 MMaterial

Delhi 'Jal Board 10 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 397: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Quotation Enclosed

200 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 10 meter 30 1049.10 31473.120

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 200 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 14.80 mm3.1416*((200-14.8)/1000)*30*(14.8/1000)*946.4 = 244.49 kg

244.49 / 30 = 8.150 kg/ mtrCarriage of Spun iron S & S pipes 200 mm dia

2322 Qty = 50 to consider 50% of carriage 100 meter 15 631.03 94.6545Total without excise duty = 31567.775

Add 1% water charges = 1% 315.678Add 15% CPOH = 15% 4782.518

Cost of 30 mtr pipe = 36665.970Cost for 1 meter pipe = 1222.199

Say = 1222.2

Delhi 'Jal Board 11 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 398: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

2.13.1.28 225 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 10 Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 225 mm nominal outer diameter (OD) HDPE pipe of

material grade PE 100 / PN 10 Details of Cost for 30 MMaterial

Quotation Enclosed

225 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 10 meter 30 1302.34 39070.080

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 225 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 16.60 mm3.1416*((225-16.6)/1000)*30*(16.6/1000)*946.4 = 308.57 kg

308.57 / 30 = 10.286 kg/ mtrCarriage of Spun iron S & S pipes 250 mm dia

2323 Qty = 50 to consider 50% of carriage 100 meter 15 896.73 134.5095Total without excise duty = 39204.590

Add 1% water charges = 1% 392.046Add 15% CPOH = 15% 5939.495

Cost of 30 mtr pipe = 45536.131Cost for 1 meter pipe = 1517.871

Say = 1517.9

2.13.1.29 110 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 6Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 110 mm nominal outer diameter (OD) HDPE pipe of

material grade PE 63 / PN 6Details of Cost for 30 MMaterial

Quotation Enclosed

110 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 6 meter 30 297.16 8914.800

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 110 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 7.70 mm3.1416*((110-7.7)/1000)*30*(7.7/1000)*946.4 = 70.27 kg

70.27 / 30 = 2.342 kg/ mtrCarriage of Spun iron S & S pipes 110 mm dia

2319 Qty = 50 to consider 50% of carriage 100 meter 15 232.76 34.914Total without excise duty = 8949.714

Add 1% water charges = 1% 89.497Add 15% CPOH = 15% 1355.882

Cost of 30 mtr pipe = 10395.093Cost for 1 meter pipe = 346.503

Say = 346.5

2.13.1.30 125 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 6Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 125 mm nominal outer diameter (OD) HDPE pipe of

material grade PE 63 / PN 6Details of Cost for 30 MMaterial

Quotation Enclosed

125 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 6 meter 30 380.36 11410.944

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 125 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 8.80 mm3.1416*((125-8.8)/1000)*30*(8.8/1000)*946.4 = 91.21 kg

91.21 / 30 = 3.040 kg/ mtrCarriage of Spun iron S & S pipes 125 mm dia

2320 Qty = 50 to consider 50% of carriage 100 meter 15 310.91 46.6365Total without excise duty = 11457.581

Add 1% water charges = 1% 114.576

Delhi 'Jal Board 12 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 399: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add 15% CPOH = 15% 1735.823Cost of 30 mtr pipe = 13307.980

Cost for 1 meter pipe = 443.599Say = 443.6

2.13.1.31 140 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 6Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 140 mm nominal outer diameter (OD) HDPE pipe of

material grade PE 63 / PN 6Details of Cost for 30 MMaterial

Quotation Enclosed

140 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 6 meter 30 475.46 14263.680

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 140 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 9.80 mm3.1416*((140-9.8)/1000)*30*(9.8/1000)*946.4 = 113.82 kg

113.82 / 30 = 3.794 kg/ mtrCarriage of Spun iron S & S pipes 140 mm dia

2321 Qty = 50 to consider 50% of carriage 100 meter 15 387.93 58.1895Total without excise duty = 14321.870

Add 1% water charges = 1% 143.219Add 15% CPOH = 15% 2169.763

Cost of 30 mtr pipe = 16634.851Cost for 1 meter pipe = 554.495

Say = 554.5

2.13.1.32 160 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 6Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 160 mm nominal outer diameter (OD) HDPE pipe of

material grade PE 63 / PN 6Details of Cost for 30 MMaterial

Quotation Enclosed

160 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 6 meter 30 629.98 18899.376

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 160 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 11.20 mm3.1416*((160-11.2)/1000)*30*(11.2/1000)*946.4 = 148.66 kg

148.66 / 30 = 4.955 kg/ mtrCarriage of Spun iron S & S pipes 160 mm dia

2321 Qty = 50 to consider 50% of carriage 100 meter 15 387.93 58.1895Total without excise duty = 18957.566

Add 1% water charges = 1% 189.576Add 15% CPOH = 15% 2872.071

Cost of 30 mtr pipe = 22019.212Cost for 1 meter pipe = 733.974

Say = 734

2.13.1.33 180 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 6Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 180 mm nominal outer diameter (OD) HDPE pipe of

material grade PE 63 / PN 6Details of Cost for 30 MMaterial

Quotation Enclosed

180 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 6 meter 30 796.39 23891.664

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 180 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 12.60 mm3.1416*((180-12.6)/1000)*30*(12.6/1000)*946.4 = 188.14 kg

188.14 / 30 = 6.271 kg/ mtr

Delhi 'Jal Board 13 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 400: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Carriage of Spun iron S & S pipes 180 mm dia 2322 Qty = 50 to consider 50% of carriage 100 meter 15 631.03 94.6545

Total without excise duty = 23986.319Add 1% water charges = 1% 239.863

Add 15% CPOH = 15% 3633.927Cost of 30 mtr pipe = 27860.109

Cost for 1 meter pipe = 928.670Say = 928.7

2.13.1.34 200 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 6Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 200 mm nominal outer diameter (OD) HDPE pipe of

material grade PE 63 / PN 6Details of Cost for 30 MMaterial

Quotation Enclosed

200 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 6 meter 30 974.68 29240.544

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 200 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 14.00 mm3.1416*((200-14)/1000)*30*(14/1000)*946.4 = 232.27 kg

232.27 / 30 = 7.742 kg/ mtrCarriage of Spun iron S & S pipes 200 mm dia

2322 Qty = 50 to consider 50% of carriage 100 meter 15 631.03 94.6545Total without excise duty = 29335.199

Add 1% water charges = 1% 293.352Add 15% CPOH = 15% 4444.283

Cost of 30 mtr pipe = 34072.833Cost for 1 meter pipe = 1135.761

Say = 1135.8

2.13.1.35 225 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 6Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 225 mm nominal outer diameter (OD) HDPE pipe of

material grade PE 63 / PN 6Details of Cost for 30 MDetails of Cost for 30 MMaterial

Quotation Enclosed

225 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 6 meter 30 1236.19 37085.568

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 225 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 15.70 mm3.1416*((225-15.7)/1000)*30*(15.7/1000)*946.4 = 293.1 kg

293.1 / 30 = 9.770 kg/ mtrCarriage of Spun iron S & S pipes 225 mm dia

2323 Qty = 50 to consider 50% of carriage 100 meter 15 896.73 134.5095Total without excise duty = 37220.078

Add 1% water charges = 1% 372.201Add 15% CPOH = 15% 5638.842

Cost of 30 mtr pipe = 43231.120Cost for 1 meter pipe = 1441.037

Say = 1441

2.13.1.36 110 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 10Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 110 mm nominal outer diameter (OD) HDPE pipe of

material grade PE 63 / PN 10Details of Cost for 30 MMaterial

Quotation Enclosed

110 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 10 meter 30 451.68 13550.496

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 110 mm

Delhi 'Jal Board 14 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 401: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Length of HDPE Pipe = 30 meterThickness of HDPE Pipe = 12.30 mm

3.1416*((110-12.3)/1000)*30*(12.3/1000)*946.4 = 107.19 kg107.19 / 30 = 3.573 kg/ mtr

Carriage of Spun iron S & S pipes 110 mm dia 2319 Qty = 50 to consider 50% of carriage 100 meter 15 232.76 34.914

Total without excise duty = 13585.410Add 1% water charges = 1% 135.854

Add 15% CPOH = 15% 2058.190Cost of 30 mtr pipe = 15779.454

Cost for 1 meter pipe = 525.982Say = 526

2.13.1.37 125 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 10Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 125 mm nominal outer diameter (OD) HDPE pipe of

material grade PE 63 / PN 10Details of Cost for 30 MMaterial

Quotation Enclosed

125 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 10 meter 30 582.43 17473.008

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 125 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 13.90 mm3.1416*((125-13.9)/1000)*30*(13.9/1000)*946.4 = 137.75 kg

137.75 / 30 = 4.592 kg/ mtrCarriage of Spun iron S & S pipes 125 mm dia

2320 Qty = 50 to consider 50% of carriage 100 meter 15 310.91 46.6365Total without excise duty = 17519.645

Add 1% water charges = 1% 175.196Add 15% CPOH = 15% 2654.226

Cost of 30 mtr pipe = 20349.067Cost for 1 meter pipe = 678.302

Say = 678.3

2.13.1.38 140 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 102.13.1.38 140 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 10Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 140 mm nominal outer diameter (OD) HDPE pipe of

material grade PE 63 / PN 10Details of Cost for 30 MMaterial

Quotation Enclosed

140 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 10 meter 30 725.07 21752.112

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 140 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 15.60 mm3.1416*((140-15.6)/1000)*30*(15.6/1000)*946.4 = 173.1 kg

173.1 / 30 = 5.770 kg/ mtrCarriage of Spun iron S & S pipes 140 mm dia

2321 Qty = 50 to consider 50% of carriage 100 meter 15 387.93 58.1895Total without excise duty = 21810.302

Add 1% water charges = 1% 218.103Add 15% CPOH = 15% 3304.261

Cost of 30 mtr pipe = 25332.665Cost for 1 meter pipe = 844.422

Say = 844.4

2.13.1.39 160 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 10Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 160 mm nominal outer diameter (OD) HDPE pipe of

material grade PE 63 / PN 10Details of Cost for 30 M

Delhi 'Jal Board 15 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 402: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

MaterialQuotation Enclosed

160 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 10 meter 30 950.91 28527.360

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 160 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 17.80 mm3.1416*((160-17.8)/1000)*30*(17.8/1000)*946.4 = 225.77 kg

225.77 / 30 = 7.526 kg/ mtrCarriage of Spun iron S & S pipes 160 mm dia

2321 Qty = 50 to consider 50% of carriage 100 meter 15 387.93 58.1895Total without excise duty = 28585.550

Add 1% water charges = 1% 285.855Add 15% CPOH = 15% 4330.711

Cost of 30 mtr pipe = 33202.116Cost for 1 meter pipe = 1106.737

Say = 1106.7

2.13.1.40 180 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 10Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 180 mm nominal outer diameter (OD) HDPE pipe of

material grade PE 63 / PN 10Details of Cost for 30 MMaterial

Quotation Enclosed

180 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 10 meter 30 1200.53 36015.792

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 180 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 20.00 mm3.1416*((180-20)/1000)*30*(20/1000)*946.4 = 285.43 kg

285.43 / 30 = 9.514 kg/ mtrCarriage of Spun iron S & S pipes 180 mm dia

2322 Qty = 50 to consider 50% of carriage 100 meter 15 631.03 94.6545Total without excise duty = 36110.447Total without excise duty = 36110.447

Add 1% water charges = 1% 361.104Add 15% CPOH = 15% 5470.733

Cost of 30 mtr pipe = 41942.284Cost for 1 meter pipe = 1398.076

Say = 1398.1

2.13.1.41 200 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 10Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 200 mm nominal outer diameter (OD) HDPE pipe of

material grade PE 63 / PN 10Details of Cost for 30 MMaterial

Quotation Enclosed

200 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 10 meter 30 1485.80 44574.000

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 200 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 22.30 mm3.1416*((200-22.3)/1000)*30*(22.3/1000)*946.4 = 353.46 kg

353.46 / 30 = 11.782 kg/ mtrCarriage of Spun iron S & S pipes 200 mm dia

2322 Qty = 50 to consider 50% of carriage 100 meter 15 631.03 94.6545Total without excise duty = 44668.655

Add 1% water charges = 1% 446.687Add 15% CPOH = 15% 6767.301

Cost of 30 mtr pipe = 51882.642Cost for 1 meter pipe = 1729.421

Say = 1729.4

Delhi 'Jal Board 16 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 403: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

2.13.1.42 225 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 10Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Providing and supplying of (i) 225 mm nominal outer diameter (OD) HDPE pipe of

material grade PE 63 / PN 10Details of Cost for 30 MMaterial

Quotation Enclosed

225 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 10 meter 30 1866.16 55984.944

Weight of HDPE Pipe :-Density of HDPE Pipe = 946.4 kg/m3

Diameter of HDPE Pipe = 225 mmLength of HDPE Pipe = 30 meter

Thickness of HDPE Pipe = 25.00 mm3.1416*((225-25)/1000)*30*(25/1000)*946.4 = 445.99 kg

445.99 / 30 = 14.866 kg/ mtrCarriage of Spun iron S & S pipes 225 mm dia

2323 Qty = 50 to consider 50% of carriage 100 meter 15 896.73 134.5095Total without excise duty = 56119.454

Add 1% water charges = 1% 561.195Add 15% CPOH = 15% 8502.097

Cost of 30 mtr pipe = 65182.745Cost for 1 meter pipe = 2172.758

Say = 2172.8

2.13.2

2.13.2.1 110 mm nominal outer diameter (OD) HDPE pipe of material grade PE 80 / PN 6

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

Lowering, laying and jointing HDPE pipe in proper position by butt fusion jointing procedure including hydraulic testing as per relevent IS Code complete with all materials for jointing procedures like butt fusion welding machine with hydraulic jack, top loading clamp etc pump and accessories for hydraulic testing and all labours as directed by engineer incharge as confirming to IS - 7634:(Part II):2012 (amended upto date).

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0471 435.00 20.507

0117 Assistant Fitter or 2nd class Fitter day 0.0471 399.00 18.810

0114 Beldar day 0.3654 329.00 120.203

09999 Sundries Ls 4.4079 1.78 7.846

Total = 167.366Add 1% water charges = 1% 1.674

Add 15% C.P = 15% 25.356Cost of 30 mtr pipe = 194.395

Cost for 1 meter pipe = 6.480Say = 6.5

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machineday 0.0233 1399.00 32.535

ii) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0086 435.00 3.760

0114 Beldar day 0.0165 329.00 5.429

Total = 41.723Add Water Charges @ 1% = 1% 0.417

Delhi 'Jal Board 17 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 404: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Add-for contractor's profit @ 15% = 15% 6.321Cost for 1 no of joint = 48.461

Say = 48.5

2.13.2.2 125 mm nominal outer diameter (OD) HDPE pipe of material grade PE 80 / PN 6

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0536 435.00 23.304

0117 Assistant Fitter or 2nd class Fitter day 0.0536 399.00 21.375

0114 Beldar day 0.4152 329.00 136.594

09999 Sundries Ls 5.0089 1.78 8.916

Total = 190.188Add 1% water charges = 1% 1.902

Add 15% C.P = 15% 28.814Cost of 30 mtr pipe = 220.904

Cost for 1 meter pipe = 7.363Say = 7.4

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machineday 0.0238 1399.00 33.310

ii) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0098 435.00 4.272

0114 Beldar day 0.0188 329.00 6.1690114 Beldar day 0.0188 329.00 6.169

Total = 43.751Add Water Charges @ 1% = 1% 0.438

Add-for contractor's profit @ 15% = 15% 6.628Cost for 1 no of joint = 50.816

Say = 50.9

2.13.2.3 140 mm nominal outer diameter (OD) HDPE pipe of material grade PE 80 / PN 6

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0600 435.00 26.100

0117 Assistant Fitter or 2nd class Fitter day 0.0600 399.00 23.940

0114 Beldar day 0.4650 329.00 152.985

09999 Sundries Ls 5.6100 1.78 9.986

Total = 213.011Add 1% water charges = 1% 2.130

Add 15% C.P = 15% 32.271Cost of 30 mtr pipe = 247.412

Cost for 1 meter pipe = 8.247Say = 8.2

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Delhi 'Jal Board 18 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 405: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Hiring and running charges of fusion butt HDPE Pipe joining machineday 0.0345 1399.00 48.241

ii) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0110 435.00 4.785

0114 Beldar day 0.0210 329.00 6.909

Total = 59.935Add Water Charges @ 1% = 1% 0.599

Add-for contractor's profit @ 15% = 15% 9.080Cost for 1 no of joint = 69.615

Say = 69.7

2.13.2.4 160 mm nominal outer diameter (OD) HDPE pipe of material grade PE 80 / PN 6 Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0686 435.00 29.829

0117 Assistant Fitter or 2nd class Fitter day 0.0686 399.00 27.360

0114 Beldar day 0.5314 329.00 174.840

09999 Sundries Ls 6.4114 1.78 11.412

Total = 243.441Add 1% water charges = 1% 2.434

Add 15% C.P = 15% 36.881Cost of 30 mtr pipe = 282.757

Cost for 1 meter pipe = 9.425Say = 9.4

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.(b) confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machineday 0.0345 1399.00 48.241

ii) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0126 435.00 5.469

0114 Beldar day 0.0240 329.00 7.896

Total = 61.606Add Water Charges @ 1% = 1% 0.616

Add-for contractor's profit @ 15% = 15% 9.333Cost for 1 no of joint = 71.555

Say = 71.6

2.13.2.5 180 mm nominal outer diameter (OD) HDPE pipe of material grade PE 80 / PN 6

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0771 435.00 33.557

0117 Assistant Fitter or 2nd class Fitter day 0.0771 399.00 30.780

Delhi 'Jal Board 19 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 406: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

0114 Beldar day 0.5979 329.00 196.695

09999 Sundries Ls 7.2129 1.78 12.839

Total = 273.871Add 1% water charges = 1% 2.739

Add 15% C.P = 15% 41.491Cost of 30 mtr pipe = 318.101

Cost for 1 meter pipe = 10.603Say = 10.6

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machineday 0.0345 1399.00 48.241

ii) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0141 435.00 6.152

0114 Beldar day 0.0270 329.00 8.883

Total = 63.277Add Water Charges @ 1% = 1% 0.633

Add-for contractor's profit @ 15% = 15% 9.586Cost for 1 no of joint = 73.496

Say = 73.5

2.13.2.6 200 mm nominal outer diameter (OD) HDPE pipe of material grade PE 80 / PN 6

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0857 435.00 37.2860116 Fitter (grade 1) day 0.0857 435.00 37.286

0117 Assistant Fitter or 2nd class Fitter day 0.0857 399.00 34.200

0114 Beldar day 0.6643 329.00 218.550

09999 Sundries Ls 8.0143 1.78 14.265

Total = 304.301Add 1% water charges = 1% 3.043

Add 15% C.P = 15% 46.102Cost of 30 mtr pipe = 353.446

Cost for 1 meter pipe = 11.782Say = 11.8

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machineday 0.0357 1399.00 49.964

ii) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0157 435.00 6.836

0114 Beldar day 0.0300 329.00 9.870

Total = 66.670Add Water Charges @ 1% = 1% 0.667

Add-for contractor's profit @ 15% = 15% 10.101Cost for 1 no of joint = 77.437

Delhi 'Jal Board 20 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 407: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Say = 77.5

2.13.2.7 225 mm nominal outer diameter (OD) HDPE pipe of material grade PE 80 / PN 6 Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0964 435.00 41.946

0117 Assistant Fitter or 2nd class Fitter day 0.0964 399.00 38.475

0114 Beldar day 0.7473 329.00 245.869

09999 Sundries Ls 9.0161 1.78 16.049

Total = 342.339Add 1% water charges = 1% 3.423

Add 15% C.P = 15% 51.864Cost of 30 mtr pipe = 397.626

Cost for 1 meter pipe = 13.254Say = 13.3

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machineday 0.0455 1399.00 63.591

ii) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0177 435.00 7.690

0114 Beldar day 0.0338 329.00 11.104

Total = 82.385Add Water Charges @ 1% = 1% 0.824Add Water Charges @ 1% = 1% 0.824

Add-for contractor's profit @ 15% = 15% 12.481Cost for 1 no of joint = 95.690

Say = 95.7

2.13.2.8 110 mm nominal outer diameter (OD) HDPE pipe of material grade PE 80 / PN 10

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0471 435.00 20.507

0117 Assistant Fitter or 2nd class Fitter day 0.0471 399.00 18.810

0114 Beldar day 0.3654 329.00 120.203

09999 Sundries Ls 4.4079 1.78 7.846

Total = 167.366Add 1% water charges = 1% 1.674

Add 15% C.P = 15% 25.356Cost of 30 mtr pipe = 194.395

Cost for 1 meter pipe = 6.480Say = 6.5

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machineday 0.0357 1399.00 49.964

Delhi 'Jal Board 21 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 408: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

ii) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0086 435.00 3.760

0114 Beldar day 0.0165 329.00 5.429

Total = 59.152Add Water Charges @ 1% = 1% 0.592

Add-for contractor's profit @ 15% = 15% 8.962Cost for 1 no of joint = 68.706

Say = 68.8

2.13.2.9 125 mm nominal outer diameter (OD) HDPE pipe of material grade PE 80 / PN 10

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0536 435.00 23.304

0117 Assistant Fitter or 2nd class Fitter day 0.0536 399.00 21.375

0114 Beldar day 0.4152 329.00 136.594

09999 Sundries Ls 5.0089 1.78 8.916

Total = 190.188Add 1% water charges = 1% 1.902

Add 15% C.P = 15% 28.814Cost of 30 mtr pipe = 220.904

Cost for 1 meter pipe = 7.363Say = 7.4

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machineday 0.0357 1399.00 49.964Hiring and running charges of fusion butt HDPE Pipe joining machineday 0.0357 1399.00 49.964

ii) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0098 435.00 4.272

0114 Beldar day 0.0188 329.00 6.169

Total = 60.405Add Water Charges @ 1% = 1% 0.604

Add-for contractor's profit @ 15% = 15% 9.151Cost for 1 no of joint = 70.161

Say = 70.2

2.13.2.10 140 mm nominal outer diameter (OD) HDPE pipe of material grade PE 80 / PN 10

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0600 435.00 26.100

0117 Assistant Fitter or 2nd class Fitter day 0.0600 399.00 23.940

0114 Beldar day 0.4650 329.00 152.985

09999 Sundries Ls 5.6100 1.78 9.986

Total = 213.011Add 1% water charges = 1% 2.130

Add 15% C.P = 15% 32.271

Delhi 'Jal Board 22 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 409: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Cost of 30 mtr pipe = 247.412Cost for 1 meter pipe = 8.247

Say = 8.2

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machineday 0.0455 1399.00 63.591

ii) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0110 435.00 4.785

0114 Beldar day 0.0210 329.00 6.909

Total = 75.285Add Water Charges @ 1% = 1% 0.753

Add-for contractor's profit @ 15% = 15% 11.406Cost for 1 no of joint = 87.443

Say = 87.5

2.13.2.11 160 mm nominal outer diameter (OD) HDPE pipe of material grade PE 80 / PN 10

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0686 435.00 29.829

0117 Assistant Fitter or 2nd class Fitter day 0.0686 399.00 27.360

0114 Beldar day 0.5314 329.00 174.840

09999 Sundries Ls 6.4114 1.78 11.412

Total = 243.441Total = 243.441Add 1% water charges = 1% 2.434

Add 15% C.P = 15% 36.881Cost of 30 mtr pipe = 282.757

Cost for 1 meter pipe = 9.425Say = 9.4

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machineday 0.0476 1399.00 66.619

ii) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0126 435.00 5.469

0114 Beldar day 0.0240 329.00 7.896

Total = 79.984Add Water Charges @ 1% = 1% 0.800

Add-for contractor's profit @ 15% = 15% 12.118Cost for 1 no of joint = 92.901

Say = 93

2.13.2.12 180 mm nominal outer diameter (OD) HDPE pipe of material grade PE 80 / PN 10

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.

Delhi 'Jal Board 23 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 410: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Details of Cost for 30 Mi) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0771 435.00 33.557

0117 Assistant Fitter or 2nd class Fitter day 0.0771 399.00 30.780

0114 Beldar day 0.5979 329.00 196.695

09999 Sundries Ls 7.2129 1.78 12.839

Total = 273.871Add 1% water charges = 1% 2.739

Add 15% C.P = 15% 41.491Cost of 30 mtr pipe = 318.101

Cost for 1 meter pipe = 10.603Say = 10.6

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machineday 0.0476 1399.00 66.619

ii) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0141 435.00 6.152

0114 Beldar day 0.0270 329.00 8.883

Total = 81.654Add Water Charges @ 1% = 1% 0.817

Add-for contractor's profit @ 15% = 15% 12.371Cost for 1 no of joint = 94.841

Say = 94.9

2.13.2.13 200 mm nominal outer diameter (OD) HDPE pipe of material grade PE 80 / PN 10

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0857 435.00 37.286

0117 Assistant Fitter or 2nd class Fitter day 0.0857 399.00 34.200

0114 Beldar day 0.6643 329.00 218.550

09999 Sundries Ls 8.0143 1.78 14.265

Total = 304.301Add 1% water charges = 1% 3.043

Add 15% C.P = 15% 46.102Cost of 30 mtr pipe = 353.446

Cost for 1 meter pipe = 11.782Say = 11.8

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machineday 0.0476 1399.00 66.619

ii) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0157 435.00 6.836

Delhi 'Jal Board 24 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 411: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

0114 Beldar day 0.0300 329.00 9.870

Total = 83.325Add Water Charges @ 1% = 1% 0.833

Add-for contractor's profit @ 15% = 15% 12.624Cost for 1 no of joint = 96.782

Say = 96.8

2.13.2.14 225 mm nominal outer diameter (OD) HDPE pipe of material grade PE 80 / PN 10

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0964 435.00 41.946

0117 Assistant Fitter or 2nd class Fitter day 0.0964 399.00 38.475

0114 Beldar day 0.7473 329.00 245.869

09999 Sundries Ls 9.0161 1.78 16.049

Total = 342.339Add 1% water charges = 1% 3.423

Add 15% C.P = 15% 51.864Cost of 30 mtr pipe = 397.626

Cost for 1 meter pipe = 13.254Say = 13.3

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machineday 0.0588 1399.00 82.294

ii) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0177 435.00 7.690

0114 Beldar day 0.0338 329.00 11.104

Total = 101.088Add Water Charges @ 1% = 1% 1.011

Add-for contractor's profit @ 15% = 15% 15.315Cost for 1 no of joint = 117.414

Say = 117.5

2.13.2.15 110 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 6

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0471 435.00 20.507

0117 Assistant Fitter or 2nd class Fitter day 0.0471 399.00 18.810

0114 Beldar day 0.3654 329.00 120.203

09999 Sundries Ls 4.4079 1.78 7.846

Total = 167.366Add 1% water charges = 1% 1.674

Add 15% C.P = 15% 25.356Cost of 30 mtr pipe = 194.395

Cost for 1 meter pipe = 6.480Say = 6.5

Delhi 'Jal Board 25 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 412: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machineday 0.0227 1399.00 31.795

ii) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0086 435.00 3.760

0114 Beldar day 0.0165 329.00 5.429

Total = 40.984Add Water Charges @ 1% = 1% 0.410

Add-for contractor's profit @ 15% = 15% 6.209Cost for 1 no of joint = 47.602

Say = 47.7

2.13.2.16 125 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 6

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0536 435.00 23.304

0117 Assistant Fitter or 2nd class Fitter day 0.0536 399.00 21.375

0114 Beldar day 0.4152 329.00 136.594

09999 Sundries Ls 5.0089 1.78 8.916

Total = 190.188Add 1% water charges = 1% 1.902

Add 15% C.P = 15% 28.814Cost of 30 mtr pipe = 220.904

Cost for 1 meter pipe = 7.363Say = 7.4

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machineday 0.0227 1399.00 31.795

ii) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0098 435.00 4.272

0114 Beldar day 0.0188 329.00 6.169

Total = 42.237Add Water Charges @ 1% = 1% 0.422

Add-for contractor's profit @ 15% = 15% 6.399Cost for 1 no of joint = 49.058

Say = 49.1

2.13.2.17 140 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 6

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

Delhi 'Jal Board 26 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 413: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

0116 Fitter (grade 1) day 0.0600 435.00 26.100

0117 Assistant Fitter or 2nd class Fitter day 0.0600 399.00 23.940

0114 Beldar day 0.4650 329.00 152.985

09999 Sundries Ls 5.6100 1.78 9.986

Total = 213.011Add 1% water charges = 1% 2.130

Add 15% C.P = 15% 32.271Cost of 30 mtr pipe = 247.412

Cost for 1 meter pipe = 8.247Say = 8.2

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machineday 0.0238 1399.00 33.310

ii) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0110 435.00 4.785

0114 Beldar day 0.0210 329.00 6.909

Total = 45.004Add Water Charges @ 1% = 1% 0.450

Add-for contractor's profit @ 15% = 15% 6.818Cost for 1 no of joint = 52.272

Say = 52.3

2.13.2.18 160 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 6

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but (a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0686 435.00 29.829

0117 Assistant Fitter or 2nd class Fitter day 0.0686 399.00 27.360

0114 Beldar day 0.5314 329.00 174.840

09999 Sundries Ls 6.4114 1.78 11.412

Total = 243.441Add 1% water charges = 1% 2.434

Add 15% C.P = 15% 36.881Cost of 30 mtr pipe = 282.757

Cost for 1 meter pipe = 9.425Say = 9.4

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machineday 0.0333 1399.00 46.633

ii) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0126 435.00 5.469

0114 Beldar day 0.0240 329.00 7.896

Delhi 'Jal Board 27 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 414: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Total = 59.998Add Water Charges @ 1% = 1% 0.600

Add-for contractor's profit @ 15% = 15% 9.090Cost for 1 no of joint = 69.688

Say = 69.7

2.13.2.19 180 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 6

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0771 435.00 33.557

0117 Assistant Fitter or 2nd class Fitter day 0.0771 399.00 30.780

0114 Beldar day 0.5979 329.00 196.695

09999 Sundries Ls 7.2129 1.78 12.839

Total = 273.871Add 1% water charges = 1% 2.739

Add 15% C.P = 15% 41.491Cost of 30 mtr pipe = 318.101

Cost for 1 meter pipe = 10.603Say = 10.6

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machineday 0.0345 1399.00 48.241

ii) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0141 435.00 6.152

0114 Beldar day 0.0270 329.00 8.883

Total = 63.277Add Water Charges @ 1% = 1% 0.633

Add-for contractor's profit @ 15% = 15% 9.586Cost for 1 no of joint = 73.496

Say = 73.5

2.13.2.20 200 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 6

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0857 435.00 37.286

0117 Assistant Fitter or 2nd class Fitter day 0.0857 399.00 34.200

0114 Beldar day 0.6643 329.00 218.550

09999 Sundries Ls 8.0143 1.78 14.265

Total = 304.301Add 1% water charges = 1% 3.043

Add 15% C.P = 15% 46.102Cost of 30 mtr pipe = 353.446

Cost for 1 meter pipe = 11.782Say = 11.8

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Delhi 'Jal Board 28 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 415: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Hiring and running charges of fusion butt HDPE Pipe joining machineday 0.0345 1399.00 48.241

ii) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0157 435.00 6.836

0114 Beldar day 0.0300 329.00 9.870

Total = 64.947Add Water Charges @ 1% = 1% 0.649

Add-for contractor's profit @ 15% = 15% 9.839Cost for 1 no of joint = 75.436

Say = 75.5

2.13.2.21 225 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 6

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0964 435.00 41.946

0117 Assistant Fitter or 2nd class Fitter day 0.0964 399.00 38.475

0114 Beldar day 0.7473 329.00 245.869

09999 Sundries Ls 9.0161 1.78 16.049

Total = 342.339Add 1% water charges = 1% 3.423

Add 15% C.P = 15% 51.864Cost of 30 mtr pipe = 397.626

Cost for 1 meter pipe = 13.254Say = 13.3

(b) Providing butt fusion welding joints to HDPE Pipe as (b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machineday 0.0357 1399.00 49.964

ii) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0177 435.00 7.690

0114 Beldar day 0.0338 329.00 11.104

Total = 68.758Add Water Charges @ 1% = 1% 0.688

Add-for contractor's profit @ 15% = 15% 10.417Cost for 1 no of joint = 79.863

Say = 79.9

2.13.2.22 110 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 10

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0471 435.00 20.507

0117 Assistant Fitter or 2nd class Fitter day 0.0471 399.00 18.810

Delhi 'Jal Board 29 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 416: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

0114 Beldar day 0.3654 329.00 120.203

09999 Sundries Ls 4.4079 1.78 7.846

Total = 167.366Add 1% water charges = 1% 1.674

Add 15% C.P = 15% 25.356Cost of 30 mtr pipe = 194.395

Cost for 1 meter pipe = 6.480Say = 6.5

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machineday 0.0345 1399.00 48.241

ii) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0086 435.00 3.760

0114 Beldar day 0.0165 329.00 5.429

Total = 57.430Add Water Charges @ 1% = 1% 0.574

Add-for contractor's profit @ 15% = 15% 8.701Cost for 1 no of joint = 66.704

Say = 66.8

2.13.2.23 125 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 10

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0536 435.00 23.304

0117 Assistant Fitter or 2nd class Fitter day 0.0536 399.00 21.375

0114 Beldar day 0.4152 329.00 136.594

09999 Sundries Ls 5.0089 1.78 8.916

Total = 190.188Add 1% water charges = 1% 1.902

Add 15% C.P = 15% 28.814Cost of 30 mtr pipe = 220.904

Cost for 1 meter pipe = 7.363Say = 7.4

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machineday 0.0345 1399.00 48.241

ii) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0098 435.00 4.272

0114 Beldar day 0.0188 329.00 6.169

Total = 58.682Add Water Charges @ 1% = 1% 0.587

Add-for contractor's profit @ 15% = 15% 8.890Cost for 1 no of joint = 68.160

Delhi 'Jal Board 30 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 417: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Say = 68.2

2.13.2.24 140 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 10

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0600 435.00 26.100

0117 Assistant Fitter or 2nd class Fitter day 0.0600 399.00 23.940

0114 Beldar day 0.4650 329.00 152.985

09999 Sundries Ls 5.6100 1.78 9.986

Total = 213.011Add 1% water charges = 1% 2.130

Add 15% C.P = 15% 32.271Cost of 30 mtr pipe = 247.412

Cost for 1 meter pipe = 8.247Say = 8.2

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machine day 0.0357 1399.00 49.964

ii) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0110 435.00 4.785

0114 Beldar day 0.0210 329.00 6.909

Total = 61.658Total = 61.658Add Water Charges @ 1% = 1% 0.617

Add-for contractor's profit @ 15% = 15% 9.341Cost for 1 no of joint = 71.616

Say = 71.7

2.13.2.25 160 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 10

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0686 435.00 29.829

0117 Assistant Fitter or 2nd class Fitter day 0.0686 399.00 27.360

0114 Beldar day 0.5314 329.00 174.840

09999 Sundries Ls 6.4114 1.78 11.412

Total = 243.441Add 1% water charges = 1% 2.434

Add 15% C.P = 15% 36.881Cost of 30 mtr pipe = 282.757

Cost for 1 meter pipe = 9.425Say = 9.4

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Delhi 'Jal Board 31 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 418: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Hiring and running charges of fusion butt HDPE Pipe joining machine day 0.0357 1399.00 49.964

ii) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0126 435.00 5.469

0114 Beldar day 0.0240 329.00 7.896

Total = 63.329Add Water Charges @ 1% = 1% 0.633

Add-for contractor's profit @ 15% = 15% 9.594Cost for 1 no of joint = 73.556

Say = 73.6

2.13.2.26 180 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 10

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0771 435.00 33.557

0117 Assistant Fitter or 2nd class Fitter day 0.0771 399.00 30.780

0114 Beldar day 0.5979 329.00 196.695

09999 Sundries Ls 7.2129 1.78 12.839

Total = 273.871Add 1% water charges = 1% 2.739

Add 15% C.P = 15% 41.491Cost of 30 mtr pipe = 318.101

Cost for 1 meter pipe = 10.603Say = 10.6

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machine day 0.0476 1399.00 66.619

ii) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0141 435.00 6.152

0114 Beldar day 0.0270 329.00 8.883

Total = 81.654Add Water Charges @ 1% = 1% 0.817

Add-for contractor's profit @ 15% = 15% 12.371Cost for 1 no of joint = 94.841

Say = 94.9

2.13.2.27 200 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 10

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0857 435.00 37.286

0117 Assistant Fitter or 2nd class Fitter day 0.0857 399.00 34.200

0114 Beldar day 0.6643 329.00 218.550

Delhi 'Jal Board 32 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 419: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

09999 Sundries Ls 8.0143 1.78 14.265

Total = 304.301Add 1% water charges = 1% 3.043

Add 15% C.P = 15% 46.102Cost of 30 mtr pipe = 353.446

Cost for 1 meter pipe = 11.782Say = 11.8

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machine day 0.0476 1399.00 66.619

ii) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0157 435.00 6.836

0114 Beldar day 0.0300 329.00 9.870

Total = 83.325Add Water Charges @ 1% = 1% 0.833

Add-for contractor's profit @ 15% = 15% 12.624Cost for 1 no of joint = 96.782

Say = 96.8

2.13.2.28 225 mm nominal outer diameter (OD) HDPE pipe of material grade PE 100 / PN 10

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0964 435.00 41.946

0117 Assistant Fitter or 2nd class Fitter day 0.0964 399.00 38.4750117 Assistant Fitter or 2nd class Fitter day 0.0964 399.00 38.475

0114 Beldar day 0.7473 329.00 245.869

09999 Sundries Ls 9.0161 1.78 16.049

Total = 342.339Add 1% water charges = 1% 3.423

Add 15% C.P = 15% 51.864Cost of 30 mtr pipe = 397.626

Cost for 1 meter pipe = 13.254Say = 13.3

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machine day 0.0476 1399.00 66.619

ii) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0177 435.00 7.690

0114 Beldar day 0.0338 329.00 11.104

Total = 85.413Add Water Charges @ 1% = 1% 0.854

Add-for contractor's profit @ 15% = 15% 12.940Cost for 1 no of joint = 99.207

Say = 99.3

Delhi 'Jal Board 33 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 420: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

2.13.2.29 110 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 6

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0471 435.00 20.507

0117 Assistant Fitter or 2nd class Fitter day 0.0471 399.00 18.810

0114 Beldar day 0.3654 329.00 120.203

09999 Sundries Ls 4.4079 1.78 7.846

Total = 167.366Add 1% water charges = 1% 1.674

Add 15% C.P = 15% 25.356Cost of 30 mtr pipe = 194.395

Cost for 1 meter pipe = 6.480Say = 6.5

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machine day 0.0345 1399.00 48.241

(b) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0086 435.00 3.760

0114 Beldar day 0.0165 329.00 5.429

Total = 57.430Add Water Charges @ 1% = 1% 0.574

Add-for contractor's profit @ 15% = 15% 8.701Add-for contractor's profit @ 15% = 15% 8.701Cost for 1 no of joint = 66.704

Say = 66.8

2.13.2.30 125 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 6

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0536 435.00 23.304

0117 Assistant Fitter or 2nd class Fitter day 0.0536 399.00 21.375

0114 Beldar day 0.4152 329.00 136.594

09999 Sundries Ls 5.0089 1.78 8.916

Total = 190.188Add 1% water charges = 1% 1.902

Add 15% C.P = 15% 28.814Cost of 30 mtr pipe = 220.904

Cost for 1 meter pipe = 7.363Say = 7.4

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machine day 0.0345 1399.00 48.241

(b) Labour for Pipe Jointing

Delhi 'Jal Board 34 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 421: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

0116 Fitter grade 1 day 0.0098 435.00 4.272

0114 Beldar day 0.0188 329.00 6.169

Total = 58.682Add Water Charges @ 1% = 1% 0.587

Add-for contractor's profit @ 15% = 15% 8.890Cost for 1 no of joint = 68.160

Say = 68.2

2.13.2.31 140 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 6

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0600 435.00 26.100

0117 Assistant Fitter or 2nd class Fitter day 0.0600 399.00 23.940

0114 Beldar day 0.4650 329.00 152.985

09999 Sundries Ls 5.6100 1.78 9.986

Total = 213.011Add 1% water charges = 1% 2.130

Add 15% C.P = 15% 32.271Cost of 30 mtr pipe = 247.412

Cost for 1 meter pipe = 8.247Say = 8.2

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machine day 0.0357 1399.00 49.964

(b) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0110 435.00 4.785

0114 Beldar day 0.0210 329.00 6.909

Total = 61.658Add Water Charges @ 1% = 1% 0.617

Add-for contractor's profit @ 15% = 15% 9.341Cost for 1 no of joint = 71.616

Say = 71.7

2.13.2.32 160 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 6

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0686 435.00 29.829

0117 Assistant Fitter or 2nd class Fitter day 0.0686 399.00 27.360

0114 Beldar day 0.5314 329.00 174.840

09999 Sundries Ls 6.4114 1.78 11.412

Total = 243.441Add 1% water charges = 1% 2.434

Add 15% C.P = 15% 36.881Cost of 30 mtr pipe = 282.757

Delhi 'Jal Board 35 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 422: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Cost for 1 meter pipe = 9.425Say = 9.4

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machine day 0.0357 1399.00 49.964

(b) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0126 435.00 5.469

0114 Beldar day 0.0240 329.00 7.896

Total = 63.329Add Water Charges @ 1% = 1% 0.633

Add-for contractor's profit @ 15% = 15% 9.594Cost for 1 no of joint = 73.556

Say = 73.6

2.13.2.33 180 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 6

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0771 435.00 33.557

0117 Assistant Fitter or 2nd class Fitter day 0.0771 399.00 30.780

0114 Beldar day 0.5979 329.00 196.695

09999 Sundries Ls 7.2129 1.78 12.839

Total = 273.871Add 1% water charges = 1% 2.739Add 1% water charges = 1% 2.739

Add 15% C.P = 15% 41.491Cost of 30 mtr pipe = 318.101

Cost for 1 meter pipe = 10.603Say = 10.6

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machine day 0.0476 1399.00 66.619

(b) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0141 435.00 6.152

0114 Beldar day 0.0270 329.00 8.883

Total = 81.654Add Water Charges @ 1% = 1% 0.817

Add-for contractor's profit @ 15% = 15% 12.371Cost for 1 no of joint = 94.841

Say = 94.9

2.13.2.34 200 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 6

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

Delhi 'Jal Board 36 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 423: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0857 435.00 37.286

0117 Assistant Fitter or 2nd class Fitter day 0.0857 399.00 34.200

0114 Beldar day 0.6643 329.00 218.550

09999 Sundries Ls 8.0143 1.78 14.265

Total = 304.301Add 1% water charges = 1% 3.043

Add 15% C.P = 15% 46.102Cost of 30 mtr pipe = 353.446

Cost for 1 meter pipe = 11.782Say = 11.8

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machine day 0.0476 1399.00 66.619

(b) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0157 435.00 6.836

0114 Beldar day 0.0300 329.00 9.870

Total = 83.325Add Water Charges @ 1% = 1% 0.833

Add-for contractor's profit @ 15% = 15% 12.624Cost for 1 no of joint = 96.782

Say = 96.8

2.13.2.35 225 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 6

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but (a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0964 435.00 41.946

0117 Assistant Fitter or 2nd class Fitter day 0.0964 399.00 38.475

0114 Beldar day 0.7473 329.00 245.869

09999 Sundries Ls 9.0161 1.78 16.049

Total = 342.339Add 1% water charges = 1% 3.423

Add 15% C.P = 15% 51.864Cost of 30 mtr pipe = 397.626

Cost for 1 meter pipe = 13.254Say = 13.3

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machine day 0.0476 1399.00 66.619

(b) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0177 435.00 7.690

0114 Beldar day 0.0338 329.00 11.104

Delhi 'Jal Board 37 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 424: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Total = 85.413Add Water Charges @ 1% = 1% 0.854

Add-for contractor's profit @ 15% = 15% 12.940Cost for 1 no of joint = 99.207

Say = 99.3

2.13.2.36 110 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 10

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0471 435.00 20.507

0117 Assistant Fitter or 2nd class Fitter day 0.0471 399.00 18.810

0114 Beldar day 0.3654 329.00 120.203

09999 Sundries Ls 4.4079 1.78 7.846

Total = 167.366Add 1% water charges = 1% 1.674

Add 15% C.P = 15% 25.356Cost of 30 mtr pipe = 194.395

Cost for 1 meter pipe = 6.480Say = 6.5

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machine day 0.0345 1399.00 48.241

(b) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0086 435.00 3.760

0114 Beldar day 0.0165 329.00 5.429

Total = 57.430Add Water Charges @ 1% = 1% 0.574

Add-for contractor's profit @ 15% = 15% 8.701Cost for 1 no of joint = 66.704

Say = 66.8

2.13.2.37 125 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 10

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0536 435.00 23.304

0117 Assistant Fitter or 2nd class Fitter day 0.0536 399.00 21.375

0114 Beldar day 0.4152 329.00 136.594

09999 Sundries Ls 5.0089 1.78 8.916

Total = 190.188Add 1% water charges = 1% 1.902

Add 15% C.P = 15% 28.814Cost of 30 mtr pipe = 220.904

Cost for 1 meter pipe = 7.363Say = 7.4

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Delhi 'Jal Board 38 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 425: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Hiring and running charges of fusion butt HDPE Pipe joining machine day 0.0345 1399.00 48.241

(b) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0098 435.00 4.272

0114 Beldar day 0.0188 329.00 6.169

Total = 58.682Add Water Charges @ 1% = 1% 0.587

Add-for contractor's profit @ 15% = 15% 8.890Cost for 1 no of joint = 68.160

Say = 68.2

2.13.2.38 140 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 10

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0600 435.00 26.100

0117 Assistant Fitter or 2nd class Fitter day 0.0600 399.00 23.940

0114 Beldar day 0.4650 329.00 152.985

09999 Sundries Ls 5.6100 1.78 9.986

Total = 213.011Add 1% water charges = 1% 2.130

Add 15% C.P = 15% 32.271Cost of 30 mtr pipe = 247.412

Cost for 1 meter pipe = 8.247Say = 8.2

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.(b) confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machine day 0.0357 1399.00 49.964

(b) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0110 435.00 4.785

0114 Beldar day 0.0210 329.00 6.909

Total = 61.658Add Water Charges @ 1% = 1% 0.617

Add-for contractor's profit @ 15% = 15% 9.341Cost for 1 no of joint = 71.616

Say = 71.7

2.13.2.39 160 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 10

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0686 435.00 29.829

0117 Assistant Fitter or 2nd class Fitter day 0.0686 399.00 27.360

Delhi 'Jal Board 39 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 426: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

0114 Beldar day 0.5314 329.00 174.840

09999 Sundries Ls 6.4114 1.78 11.412

Total = 243.441Add 1% water charges = 1% 2.434

Add 15% C.P = 15% 36.881Cost of 30 mtr pipe = 282.757

Cost for 1 meter pipe = 9.425Say = 9.4

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machine day 0.0357 1399.00 49.964

(b) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0126 435.00 5.469

0114 Beldar day 0.0240 329.00 7.896

Total = 63.329Add Water Charges @ 1% = 1% 0.633

Add-for contractor's profit @ 15% = 15% 9.594Cost for 1 no of joint = 73.556

Say = 73.6

2.13.2.40 180 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 10

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0771 435.00 33.5570116 Fitter (grade 1) day 0.0771 435.00 33.557

0117 Assistant Fitter or 2nd class Fitter day 0.0771 399.00 30.780

0114 Beldar day 0.5979 329.00 196.695

09999 Sundries Ls 7.2129 1.78 12.839

Total = 273.871Add 1% water charges = 1% 2.739

Add 15% C.P = 15% 41.491Cost of 30 mtr pipe = 318.101

Cost for 1 meter pipe = 10.603Say = 10.6

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machine day 0.0476 1399.00 66.619

(b) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0141 435.00 6.152

0114 Beldar day 0.0270 329.00 8.883

Total = 81.654Add Water Charges @ 1% = 1% 0.817

Add-for contractor's profit @ 15% = 15% 12.371Cost for 1 no of joint = 94.841

Delhi 'Jal Board 40 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 427: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Say = 94.9

2.13.2.41 200 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 10

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0857 435.00 37.286

0117 Assistant Fitter or 2nd class Fitter day 0.0857 399.00 34.200

0114 Beldar day 0.6643 329.00 218.550

09999 Sundries Ls 8.0143 1.78 14.265

Total = 304.301Add 1% water charges = 1% 3.043

Add 15% C.P = 15% 46.102Cost of 30 mtr pipe = 353.446

Cost for 1 meter pipe = 11.782Say = 11.8

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machine day 0.0476 1399.00 66.619

(b) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0157 435.00 6.836

0114 Beldar day 0.0300 329.00 9.870

Total = 83.325Add Water Charges @ 1% = 1% 0.833Add Water Charges @ 1% = 1% 0.833

Add-for contractor's profit @ 15% = 15% 12.624Cost for 1 no of joint = 96.782

Say = 96.8

2.13.2.42 225 mm nominal outer diameter (OD) HDPE pipe of material grade PE 63 / PN 10

Code No Description Unit Qty Rate (INR) Amount (INR)

(a) Lowering and laying of HDPE Pipe including testing but excluding the cost of jointing.Details of Cost for 30 M

i) Labour for lowering and laying of HDPE pipe

0116 Fitter (grade 1) day 0.0964 435.00 41.946

0117 Assistant Fitter or 2nd class Fitter day 0.0964 399.00 38.475

0114 Beldar day 0.7473 329.00 245.869

09999 Sundries Ls 9.0161 1.78 16.049

Total = 342.339Add 1% water charges = 1% 3.423

Add 15% C.P = 15% 51.864Cost of 30 mtr pipe = 397.626

Cost for 1 meter pipe = 13.254Say = 13.3

(b) Providing butt fusion welding joints to HDPE Pipe as confirm to DVS 2207 part-II.Detail of cost for 1 no of joint

i) Machinery

Hiring and running charges of fusion butt HDPE Pipe joining machine day 0.0476 1399.00 66.619

Delhi 'Jal Board 41 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 428: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

(b) Labour for Pipe Jointing

0116 Fitter grade 1 day 0.0177 435.00 7.690

0114 Beldar day 0.0338 329.00 11.104

Total = 85.413Add Water Charges @ 1% = 1% 0.854

Add-for contractor's profit @ 15% = 15% 12.940Cost for 1 no of joint = 99.207

Say = 99.3

Delhi 'Jal Board 42 Schedule of Rates 2014 -2015 (Water Supply Works)

Page 429: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

2.14 Medium Density Polyethylene (MDPE) Pipes & Fittings

2.14.1

2.14.1.1 20 mm nominal outer diameter (OD)

Code No Description Unit Qty Rate (INR)

Amount (INR) Remark

(a) Providing and supplying of (i) 20 mm nominal outer diameter (OD)

Details of Cost for 30 MMaterial

Quotation Enclosed 20 mm nominal outer diameter (OD) meter 30.00 19.00 570.00 X

Add 30% for lowering, laying, jointing, fittings, carriage etc. of X 171.00 On the analogy of items in

DSR in respect of 18.6 & 18.7

Total = 741.00 Add 1% water charges = 1% 7.41

Add 15% CPOH = 15% 112.26 Cost of 30 mtr pipe = 860.67

Cost for 1 meter pipe = 28.69 Say = 28.70

2.14.1.2 25 mm nominal outer diameter (OD)

Code No Description Unit Qty Rate (INR)

Amount (INR) Remark

(a) Providing and supplying of (i) 25 mm nominal outer diameter (OD)

Details of Cost for 30 MMaterial

Quotation Enclosed 25 mm nominal outer diameter (OD) meter 30.00 29.00 870.00 X

Add 30% for lowering, laying, jointing, fittings, carriage etc. of X 261.00 On the analogy of items in

DSR in respect of 18.6 & 18.7

Total = 1,131.00 Add 1% water charges = 1% 11.31

Add 15% CPOH = 15% 171.35 Cost of 30 mtr pipe = 1,313.66

Cost for 1 meter pipe = 43.79 Say = 43.80

2.14.1.3 32 mm nominal outer diameter (OD)

Code No Description Unit Qty Rate (INR)

Amount (INR) Remark

(a) Providing and supplying of (i) 32 mm nominal outer diameter (OD)

Details of Cost for 30 MMaterial

Quotation Enclosed 32 mm nominal outer diameter (OD) meter 30.00 47.00 1,410.00 X

Add 30% for lowering, laying, jointing, fittings, carriage etc. of X 423.00 On the analogy of items in

DSR in respect of 18.6 & 18.7

Total = 1,833.00 Add 1% water charges = 1% 18.33

Add 15% CPOH = 15% 277.70 Cost of 30 mtr pipe = 2,129.03

Providing, laying and jointing MDPE pipes conforming to latest ISO 4427 including fittings conforming to latest ISO14236 manufactured from virgin resin of minimum PE 80 Food grade compounded raw material having Blue Colouronly and having pressure rating PN16, with quality assurance certificate from agencies as approved by Engineer-in-charge, for usage in Drinking Water inclusive of all taxes; complete in all respect as per direction of Engineer-in-charge.

Delhi Jal Board 1 Schedule of Rate 2014 -2015 (Water Supply Works)

Page 430: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

Cost for 1 meter pipe = 70.97 Say = 71.00

2.14.1.4 40 mm nominal outer diameter (OD)

Code No Description Unit Qty Rate (INR)

Amount (INR) Remark

(a) Providing and supplying of (i) 40 mm nominal outer diameter (OD)

Details of Cost for 30 MMaterial

Quotation Enclosed 40 mm nominal outer diameter (OD) meter 30.00 74.00 2,220.00 X

Add 30% for lowering, laying, jointing, fittings, carriage etc. of X 666.00 On the analogy of items in

DSR in respect of 18.6 & 18.7

Total = 2,886.00 Add 1% water charges = 1% 28.86

Add 15% CPOH = 15% 437.23 Cost of 30 mtr pipe = 3,352.09

Cost for 1 meter pipe = 111.74 Say = 111.70

2.14.1.5 50 mm nominal outer diameter (OD)

Code No Description Unit Qty Rate (INR)

Amount (INR) Remark

(a) Providing and supplying of (i) 50 mm nominal outer diameter (OD)

Details of Cost for 30 MMaterial

Quotation Enclosed 50 mm nominal outer diameter (OD) meter 30.00 115.00 3,450.00 X

Add 30% for lowering, laying, jointing, fittings, carriage etc. of X 1,035.00 On the analogy of items in

DSR in respect of 18.6 & 18.7

Total = 4,485.00 Add 1% water charges = 1% 44.85

Add 15% CPOH = 15% 679.48 Cost of 30 mtr pipe = 5,209.33

Cost for 1 meter pipe = 173.64 Say = 173.60

2.14.1.6 63 mm nominal outer diameter (OD)

Code No Description Unit Qty Rate (INR)

Amount (INR) Remark

(a) Providing and supplying of (i) 63 mm nominal outer diameter (OD)

Details of Cost for 30 MMaterial

Quotation Enclosed 63 mm nominal outer diameter (OD) meter 30.00 183.00 5,490.00 X

Add 30% for lowering, laying, jointing, fittings, carriage etc. of X 1,647.00 On the analogy of items in

DSR in respect of 18.6 & 18.7

Total = 7,137.00 Add 1% water charges = 1% 71.37

Add 15% CPOH = 15% 1,081.26 Cost of 30 mtr pipe = 8,289.63

Cost for 1 meter pipe = 276.32 Say = 276.30

2.14.1.7 75 mm nominal outer diameter (OD)

Code No Description Unit Qty Rate (INR)

Amount (INR) Remark

Delhi Jal Board 2 Schedule of Rate 2014 -2015 (Water Supply Works)

Page 431: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

(a) Providing and supplying of (i) 75 mm nominal outer diameter (OD)

Details of Cost for 30 MMaterial

Quotation Enclosed 75 mm nominal outer diameter (OD) meter 30.00 258.00 7,740.00 X

Add 30% for lowering, laying, jointing, fittings, carriage etc. of X 2,322.00 On the analogy of items in

DSR in respect of 18.6 & 18.7

Total = 10,062.00 Add 1% water charges = 1% 100.62

Add 15% CPOH = 15% 1,524.39 Cost of 30 mtr pipe = 11,687.01

Cost for 1 meter pipe = 389.57 Say = 389.60

2.14.1.8 90 mm nominal outer diameter (OD)

Code No Description Unit Qty Rate (INR)

Amount (INR) Remark

(a) Providing and supplying of (i) 90 mm nominal outer diameter (OD)

Details of Cost for 30 MMaterial

Quotation Enclosed 90 mm nominal outer diameter (OD) meter 30.00 372.00 11,160.00 X

Add 30% for lowering, laying, jointing, fittings, carriage etc. of X 3,348.00 On the analogy of items in

DSR in respect of 18.6 & 18.7

Total = 14,508.00 Add 1% water charges = 1% 145.08

Add 15% CPOH = 15% 2,197.96 Cost of 30 mtr pipe = 16,851.04

Cost for 1 meter pipe = 561.70 Say = 561.70

Delhi Jal Board 3 Schedule of Rate 2014 -2015 (Water Supply Works)

Page 432: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

3.0 TUBE WELLS & DBHP

3.1

3.1.1 All type of soils3.1.1.1 150 mm dia

Code Description Unit Qty Rate (INR) Amount (INR) Remarks

Details of cost for 50 metre0020 Hydraulic Excavator (3D) with driver and fuel day 1.00 8,000.00 8,000.00 0005 Hire charges of Diesel Truck - 9 tonne day 0.4286 1,700.00 728.57

Transportation charges for to and fro to site (assume 140m of bore for one shifting) (2 x30)/140

Loading, Unloading & Erection Charges of Drilling Rig Machine

0114 Beldar day 4.00 329.00 1,316.00 0130 Mistry day 1.00 435.00 435.00 7763 Water supply tanker of 5000 ltr capacity day 1.00 800.00 800.00

Extra labour to assist M/C operator &security

0114 Beldar day 2.00 329.00 658.00 0113 Chowkidar day 1.00 329.00 329.00

Sub Total 12,266.57 Add 1% WC 1% 122.67 Add CP 15% 15% 1,858.39 Total Cost for 50 meter 14,247.62 Cost of 1 metre 284.95

Say 285.00

3.1.1.2 200 mm dia

Code Description Unit Qty Rate (INR) Amount (INR) Remark

Details of cost for 45 metre0020 Hydraulic Excavator (3D) with driver and fuel day 1.00 8,000.00 8,000.00 0005 Hire charges of Diesel Truck - 9 tonne day 0.4286 1,700.00 728.57

Transportation charges for to and fro to site (assume 140m of bore for one shifting) (2 x30)/140

Loading, Unloading & Erection Charges of Drilling Rig Machine

0114 Beldar day 4.00 329.00 1,316.00 0130 Mistry day 1.00 435.00 435.00 7763 Water supply tanker of 5000 ltr capacity day 1.00 800.00 800.00

Extra labour to assist M/C operator &security

0114 Beldar day 2.00 329.00 658.00 0113 Chowkidar day 1.00 329.00 329.00

Sub Total 12,266.57 Add 1% WC 1% 122.67 Add CP 15% 15% 1,858.39 Total Cost for 45 meter 14,247.62

Boring / drilling bore well of required dia for casing/ strainer pipe, by suitable method prescribed in IS: 2800 (part I),including collecting samples from different strata, preparing and submitting strata chart/ bore log, including hire &running charges of all equipments, tools, plants & machineries required for the job, all complete as per direction ofEngineer -in-charge, upto 90 metre depth below ground level.

Delhi Jal Board 681 Schedule of Rates 2014 - 2015

Page 433: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Code Description Unit Qty Rate (INR) Amount (INR) Remarks

Cost of 1 metre 316.61 Say 316.70

3.1.1.3 250 mm dia

Code Description Unit Qty Rate (INR) Amount (INR) Remark

Details of cost for 40 metre0020 Hydraulic Excavator (3D) with driver and fuel day 1.00 8,000.00 8,000.00 0005 Hire charges of Diesel Truck - 9 tonne day 0.4286 1,700.00 728.62

Transportation charges for to and fro to site (assume 140m of bore for one shifting) (2 x30)/140

Loading, Unloading & Erection Charges of Drilling Rig Machine

0114 Beldar day 4.00 329.00 1,316.00 0130 Mistry day 1.00 435.00 435.00 7763 Water supply tanker of 5000 ltr capacity day 1.00 800.00 800.00

Extra labour to assist M/C operator &security

0114 Beldar day 2.00 329.00 658.00 0113 Chowkidar day 1.00 329.00 329.00

Sub Total 12,266.62 Add 1% WC 1% 122.67 Add CP 15% 15% 1,858.39 Total Cost for 40 meter 14,247.68 Cost of 1 metre 356.19

Say 356.20

3.1.1.4 500 mm dia

Code Description Unit Qty Rate (INR) Amount (INR) Remark

Details of cost for 20 metre0020 Hydraulic Excavator (3D) with driver and fuel day 1.00 8,000.00 8,000.00 0005 Hire charges of Diesel Truck - 9 tonne day 0.4286 1,700.00 728.62

Transportation charges for to and fro to site (assume 140m of bore for one shifting) (2 x30)/140

Loading, Unloading & Erection Charges of Drilling Rig Machine

0114 Beldar day 4.00 329.00 1,316.00 0130 Mistry day 1.00 435.00 435.00 7763 Water supply tanker of 5000 ltr capacity day 1.00 800.00 800.00

Extra labour to assist M/C operator &security

0114 Beldar day 2.00 329.00 658.00 0113 Chowkidar day 1.00 329.00 329.00

Sub Total 12,266.62 Add 1% WC 1% 122.67 Add CP 15% 15% 1,858.39 Total Cost for 20 meter 14,247.68 Cost of 1 metre 712.38

Say 712.40

3.1.1.5 600 mm dia

Code Description Unit Qty Rate (INR) Amount (INR) Remark

Details of cost for 15 metre0020 Hydraulic Excavator (3D) with driver and fuel day 1.00 8,000.00 8,000.00

Delhi Jal Board 682 Schedule of Rates 2014 - 2015

Page 434: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Code Description Unit Qty Rate (INR) Amount (INR) Remarks

0005 Hire charges of Diesel Truck - 9 tonne day 0.4286 1,700.00 728.62 Transportation charges for to and fro to site (assume 140m of bore for one shifting) (2 x30)/140

Loading, Unloading & Erection Charges of Drilling Rig Machine

0114 Beldar day 4.00 329.00 1,316.00 0130 Mistry day 1.00 435.00 435.00 7763 Water supply tanker of 5000 ltr capacity day 1.00 800.00 800.00

Extra labour to assist M/C operator &security

0114 Beldar day 2.00 329.00 658.00 0113 Chowkidar day 1.00 329.00 329.00

Sub Total 12,266.62 Add 1% WC 1% 122.67 Add CP 15% 15% 1,858.39 Total Cost for 15 meter 14,247.68 Cost of 1 metre 949.85

Say 949.90

3.1.2 Rocky strata i/c boulders3.1.2.1 150 mm dia

Code Description Unit Qty Rate (INR) Amount (INR) Remark

Details of cost for 16 metre0020 Hydraulic Excavator (3D) with driver and fuel day 0.90 8,000.00 7,200.00

Extra Diesel required for boring in rocky strata1235 Diesel litre 1.00 55.49 55.49

0005 Hire charges of Diesel Truck - 9 tonne day 0.4286 1,700.00 728.62

Transportation charges for to and fro to site (assume 140m of bore for one shifting) (2 x30)/140

Loading, Unloading & Erection Charges of Drilling Rig Machine

0114 Beldar day 4.00 329.00 1,316.00 0130 Mistry day 1.00 435.00 435.00 7763 Water supply tanker of 5000 ltr capacity day 1.00 800.00 800.00

Extra labour to assist M/C operator &security

0134 Rock Hole Driller day 0.13 329.00 41.13 0114 Beldar day 0.50 329.00 164.50 0103 Blacksmith 2nd class day 0.38 399.00 149.63 0113 Chowkidar day 1.00 329.00 329.00

Sub Total 11,219.36 Add 1% WC 1% 112.19 Add CP 15% 15% 1,699.73 Total Cost for 16 meter 13,031.29 Cost of 1 metre 814.46

Say 814.50

3.1.2.2 200 mm dia

Code Description Unit Qty Rate (INR) Amount (INR) Remark

Details of cost for 19 metreHire

0020 Hydraulic Excavator (3D) with driver and fuel day 0.90 8,000.00 7,200.00

Delhi Jal Board 683 Schedule of Rates 2014 - 2015

Page 435: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Code Description Unit Qty Rate (INR) Amount (INR) Remarks

Extra Diesel required for boring in rockystrata

1235 Diesel litre 2.0000 55.49 110.98 0005 Hire charges of Diesel Truck - 9 tonne day 0.43 1,700.00 728.62

Transportation charges for to and fro to site (assume 140m of bore for one shifting) (2 x30)/140

Loading, Unloading & Erection Charges of Drilling Rig Machine

0114 Beldar day 4.00 329.00 1,316.00 0130 Mistry day 1.00 435.00 435.00 7763 Water supply tanker of 5000 ltr capacity day 1.00 800.00 800.00

Extra labour to assist M/C operator &security

0134 Rock Hole Driller day 0.25 329.00 82.25 0114 Beldar day 1.00 329.00 329.00 0103 Blacksmith 2nd class day 0.75 399.00 299.25 0113 Chowkidar day 1.00 329.00 329.00

Sub Total 11,630.10 Add 1% WC 1% 116.30 Add CP 15% 15% 1,761.96 Total Cost for 16 meter 13,508.36 Cost of 1 metre 844.27

Say 844.30

3.1.2.3 250 mm dia

Code Description Unit Qty Rate (INR) Amount (INR) Remark

Details of cost for 16 metre0020 Hydraulic Excavator (3D) with driver and fuel day 0.90 8,000.00 7,200.00

Extra Diesel required for boring in rockystrata

1235 Diesel litre 4.00 55.49 221.96 0005 Hire charges of Diesel Truck - 9 tonne day 0.4286 1,700.00 728.62

Transportation charges for to and fro to site (assume 140m of bore for one shifting) (2 x30)/140

Loading, Unloading & Erection Charges of Drilling Rig Machine

0114 Beldar day 4.00 329.00 1,316.00 0130 Mistry day 1.00 435.00 435.00 7763 Water supply tanker of 5000 ltr capacity day 1.00 800.00 800.00

Extra labour to assist M/C operator &security

0134 Rock Hole Driller day 0.50 329.00 164.50 0114 Beldar day 2.00 329.00 658.00 0103 Blacksmith 2nd class day 0.75 399.00 299.25 0113 Chowkidar day 1.00 329.00 329.00

Sub Total 12,152.33 Add 1% WC 1% 121.52 Add CP 15% 15% 1,841.08 Total Cost for 16 meter 14,114.93 Cost of 1 metre 882.18

Say 882.20 3.1.2.4 500 mm dia

Code Description Unit Qty Rate (INR) Amount (INR) Remark

Details of cost for 16 metre0020 Hydraulic Excavator (3D) with driver and fuel day 0.90 8,000.00 7,200.00

Delhi Jal Board 684 Schedule of Rates 2014 - 2015

Page 436: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Code Description Unit Qty Rate (INR) Amount (INR) Remarks

Extra Diesel required for boring in rockystrata

1235 Diesel litre 18.00 55.49 998.82 0005 Hire charges of Diesel Truck - 9 tonne day 0.4286 1,700.00 728.62

Transportation charges for to and fro to site (assume 140m of bore for one shifting) (2 x30)/140

Loading, Unloading & Erection Charges of Drilling Rig Machine

0114 Beldar day 4.00 329.00 1,316.00 0130 Mistry day 1.00 435.00 435.00 7763 Water supply tanker of 5000 ltr capacity day 1.00 800.00 800.00

Extra labour to assist M/C operator &security

0134 Rock Hole Driller day 1.40 329.00 460.60 0114 Beldar day 12.00 329.00 3,948.00 0103 Blacksmith 2nd class day 0.75 399.00 299.25 0113 Chowkidar day 1.00 329.00 329.00

Sub Total 16,515.29 Add 1% WC 1% 165.15 Add CP 15% 15% 2,502.07 Total Cost for 16 meter 19,182.51 Cost of 1 metre 1,198.91

Say 1,199.00 3.1.2.5 600 mm dia

Code Description Unit Qty Rate (INR) Amount (INR) Remark

Details of cost for 14 metre0020 Hydraulic Excavator (3D) with driver and fuel day 0.90 8,000.00 7,200.00

Extra Diesel required for boring in rockystrata

1235 Diesel litre 20.00 55.49 1,109.80 0005 Hire charges of Diesel Truck - 9 tonne day 0.4286 1,700.00 728.62

Transportation charges for to and fro to site (assume 140m of bore for one shifting) (2 x30)/140

Loading, Unloading & Erection Charges of Drilling Rig Machine

0114 Beldar day 4.00 329.00 1,316.00 0130 Mistry day 1.00 435.00 435.00 7763 Water supply tanker of 5000 ltr capacity day 1.00 800.00 800.00

Extra labour to assist M/C operator &security

0134 Rock Hole Driller day 1.60 329.00 526.40 0114 Beldar day 16.00 329.00 5,264.00 0103 Blacksmith 2nd class day 0.75 399.00 299.25 0113 Chowkidar day 1.00 329.00 329.00

Sub Total 18,008.07 Add 1% WC 1% 180.08 Add CP 15% 15% 2,728.22 Total Cost for 16 meter 20,916.37 Cost of 1 metre 1,307.27

Say 1,307.30

3.2

3.2.1 All type of soils

Boring/drilling bore well of required dia for casing/ strainer pipe, by suitable method prescribed in IS: 2800 (part I),including collecting samples from different strata, preparing and submitting strata chart/ bore log, including hire &running charges of all equipments, tools, plants & machineries required for the job, all complete as per direction ofEngineer -in-charge, beyond 90 metre & upto 150 m depth below ground level.

Delhi Jal Board 685 Schedule of Rates 2014 - 2015

Page 437: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Code Description Unit Qty Rate (INR) Amount (INR) Remarks

3.2.1.1 150 mm dia

Code Description Unit Qty Rate (INR) Amount (INR) Remark

Details of cost for 45 metre0020 Hydraulic Excavator (3D) with driver and fuel day 1.00 8,000.00 8,000.00 0005 Hire charges of Diesel Truck - 9 tonne day 0.4286 1,700.00 728.62

Transportation charges for to and fro to site (assume 140m of bore for one shifting) (2 x30)/140

Loading, Unloading & Erection Charges of Drilling Rig Machine

0114 Beldar day 4.00 329.00 1,316.00 0130 Mistry day 1.00 435.00 435.00 7763 Water supply tanker of 5000 ltr capacity day 1.00 800.00 800.00

Extra labour to assist M/C operator &security

0114 Beldar day 2.00 329.00 658.00 0113 Chowkidar day 1.00 329.00 329.00

Sub Total 12,266.62 Add 1% WC 1% 122.67 Add CP 15% 15% 1,858.39 Total Cost for 45 meter 14,247.68 Cost of 1 metre 316.62

Say 316.70

3.2.1.2 200 mm dia

Code Description Unit Qty Rate (INR) Amount (INR) Remark

Details of cost for 40 metre0020 Hydraulic Excavator (3D) with driver and fuel day 1.00 8,000.00 8,000.00 0005 Hire charges of Diesel Truck - 9 tonne day 0.4286 1,700.00 728.62

Transportation charges for to and fro to site (assume 140m of bore for one shifting) (2 x30)/140

Loading, Unloading & Erection Charges of Drilling Rig Machine

0114 Beldar day 4.00 329.00 1,316.00 0130 Mistry day 1.00 435.00 435.00 7763 Water supply tanker of 5000 ltr capacity day 1.00 800.00 800.00

Extra labour to assist M/C operator &security

0114 Beldar day 2.00 329.00 658.00 0113 Chowkidar day 1.00 329.00 329.00

Sub Total 12,266.62 Add 1% WC 1% 122.67 Add CP 15% 15% 1,858.39 Total Cost for 40 meter 14,247.68 Cost of 1 metre 356.19

Say 356.20

3.2.1.3 250 mm dia

Code Description Unit Qty Rate (INR) Amount (INR) Remark

Details of cost for 35 metre0020 Hydraulic Excavator (3D) with driver and fuel day 1.00 8,000.00 8,000.00 0005 Hire charges of Diesel Truck - 9 tonne day 0.4286 1,700.00 728.62

Transportation charges for to and fro to site (assume 140m of bore for one shifting) (2 x30)/140

Delhi Jal Board 686 Schedule of Rates 2014 - 2015

Page 438: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Code Description Unit Qty Rate (INR) Amount (INR) Remarks

Loading, Unloading & Erection Charges of Drilling Rig Machine

0114 Beldar day 4.00 329.00 1,316.00 0130 Mistry day 1.00 435.00 435.00 7763 Water supply tanker of 5000 ltr capacity day 1.00 800.00 800.00

Extra labour to assist M/C operator &security

0114 Beldar day 2.00 329.00 658.00 0113 Chowkidar day 1.00 329.00 329.00

Sub Total 12,266.62 Add 1% WC 1% 122.67 Add CP 15% 15% 1,858.39 Total Cost for 35 meter 14,247.68 Cost of 1 metre 407.08

Say 407.10

3.2.1.4 500 mm diameter

Code Description Unit Qty Rate (INR) Amount (INR) Remark

Details of cost for 15 metre0020 Hydraulic Excavator (3D) with driver and fuel day 1.00 8,000.00 8,000.00 0005 Hire charges of Diesel Truck - 9 tonne day 0.4286 1,700.00 728.62

Transportation charges for to and fro to site (assume 140m of bore for one shifting) (2 x30)/140

Loading, Unloading & Erection Charges of Drilling Rig Machine

0114 Beldar day 4.00 329.00 1,316.00 0130 Mistry day 1.00 435.00 435.00 7763 Water supply tanker of 5000 ltr capacity day 1.00 800.00 800.00

Extra labour to assist M/C operator &security

0114 Beldar day 2.00 329.00 658.00 0113 Chowkidar day 1.00 329.00 329.00

Sub Total 12,266.62 Add 1% WC 1% 122.67 Add CP 15% 15% 1,858.39 Total Cost for 15 meter 14,247.68 Cost of 1 metre 949.85

Say 949.90

3.2.1.5 600 mm diameter

Code Description Unit Qty Rate (INR) Amount (INR) Remark

Details of cost for 10 metre0020 Hydraulic Excavator (3D) with driver and fuel day 1.00 8,000.00 8,000.00 0005 Hire charges of Diesel Truck - 9 tonne day 0.4286 1,700.00 728.62

Transportation charges for to and fro to site (assume 140m of bore for one shifting) (2 x30)/140

Loading, Unloading & Erection Charges of Drilling Rig Machine

0114 Beldar day 4.00 329.00 1,316.00 0130 Mistry day 1.00 435.00 435.00 7763 Water supply tanker of 5000 ltr capacity day 1.00 800.00 800.00

Extra labour to assist M/C operator &security

Delhi Jal Board 687 Schedule of Rates 2014 - 2015

Page 439: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Code Description Unit Qty Rate (INR) Amount (INR) Remarks

0114 Beldar day 2.00 329.00 658.00 0113 Chowkidar day 1.00 329.00 329.00

Sub Total 12,266.62 Add 1% WC 1% 122.67 Add CP 15% 15% 1,858.39 Total Cost for 10 meter 14,247.68 Cost of 1 metre 1,424.77

Say 1,424.80

3.2.23.2.2.1 150 mm dia

Code Description Unit Qty Rate (INR) Amount (INR) Remark

Details of cost for 16 metre

0020 Hydraulic Excavator (3D) with driver and fuel day 0.90 8,000.00 7,200.00

Extra Diesel required for boring in rockystrata

1235 Diesel litre 2.00 55.49 110.98 0005 Hire charges of Diesel Truck - 9 tonne day 0.4286 1,700.00 728.62

Transportation charges for to and fro to site (assume 140m of bore for one shifting) (2 x30)/140

Loading, Unloading & Erection Charges of Drilling Rig Machine

0114 Beldar day 4.00 329.00 1,316.00 0130 Mistry day 1.00 435.00 435.00 7763 Water supply tanker of 5000 ltr capacity day 1.00 800.00 800.00

Extra labour to assist M/C operator &security

0134 Rock Hole Driller day 0.40 329.00 131.60 0114 Beldar day 2.00 329.00 658.00 0103 Blacksmith 2nd class day 0.55 399.00 219.45 0113 Chowkidar day 1.00 329.00 329.00

Sub Total 11,928.65 Add 1% WC 1% 119.29 Add CP 15% 15% 1,807.19 Total Cost for 16 meter 13,855.13 Cost of 1 metre 865.95

Say 866.00

3.2.2.2 200 mm dia

Code Description Unit Qty Rate (INR) Amount (INR) Remark

Details of cost for 16 metre0020 Hydraulic Excavator (3D) with driver and fuel day 0.90 8,000.00 7,200.00

Extra Diesel required for boring in rockystrata

1235 Diesel litre 6.00 55.49 332.94 0005 Hire charges of Diesel Truck - 9 tonne day 0.4286 1,700.00 728.62

Transportation charges for to and fro to site (assume 140m of bore for one shifting) (2 x30)/140

Loading, Unloading & Erection Charges of Drilling Rig Machine

0114 Beldar day 4.00 329.00 1,316.00 0130 Mistry day 1.00 435.00 435.00 7763 Water supply tanker of 5000 ltr capacity day 1.00 800.00 800.00

Rocky strata i/c boulders

Delhi Jal Board 688 Schedule of Rates 2014 - 2015

Page 440: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Code Description Unit Qty Rate (INR) Amount (INR) Remarks

Extra labour to assist M/C operator &security

0134 Rock Hole Driller day 0.60 329.00 197.40 0114 Beldar day 3.00 329.00 987.00 0103 Blacksmith 2nd class day 0.60 399.00 239.40 0113 Chowkidar day 1.00 329.00 329.00

Sub Total 12,565.36 Add 1% WC 1% 125.65 Add CP 15% 15% 1,903.65 Total Cost for 16 meter 14,594.67 Cost of 1 metre 912.17

Say 912.20

3.2.2.3 250 mm dia

Code Description Unit Qty Rate (INR) Amount (INR) Remark

Details of cost for 16 metre0020 Hydraulic Excavator (3D) with driver and fuel day 0.90 8,000.00 7,200.00

Extra Diesel required for boring in rockystrata

1235 Diesel litre 8.00 55.49 443.92 0005 Hire charges of Diesel Truck - 9 tonne day 0.4286 1,700.00 728.62

Transportation charges for to and fro to site (assume 140m of bore for one shifting) (2 x30)/140

Loading, Unloading & Erection Charges of Drilling Rig Machine

0114 Beldar day 4.00 329.00 1,316.00 0130 Mistry day 1.00 435.00 435.00 7763 Water supply tanker of 5000 ltr capacity day 1.00 800.00 800.00

Extra labour to assist M/C operator &security

0134 Rock Hole Driller day 0.80 329.00 263.20 0114 Beldar day 4.00 329.00 1,316.00 0103 Blacksmith 2nd class day 0.65 399.00 259.35 0113 Chowkidar day 1.00 329.00 329.00

Sub Total 13,091.09 Add 1% WC 1% 130.91 Add CP 15% 15% 1,983.30 Total Cost for 16 meter 15,205.30 Cost of 1 metre 950.33

Say 950.40

3.2.2.4 500 mm dia

Code Description Unit Qty Rate (INR) Amount (INR) Remark

Details of cost for 14 metre0020 Hydraulic Excavator (3D) with driver and fuel day 0.95 8,000.00 7,600.00

Extra Diesel required for boring in rockystrata

1235 Diesel litre 18.00 55.49 998.82 0005 Hire charges of Diesel Truck - 9 tonne day 0.4286 1,700.00 728.62

Transportation charges for to and fro to site (assume 140m of bore for one shifting) (2 x30)/140

Loading, Unloading & Erection Charges of Drilling Rig Machine

0114 Beldar day 4.00 329.00 1,316.00 0130 Mistry day 1.00 435.00 435.00 7763 Water supply tanker of 5000 ltr capacity day 1.00 800.00 800.00

Delhi Jal Board 689 Schedule of Rates 2014 - 2015

Page 441: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Code Description Unit Qty Rate (INR) Amount (INR) Remarks

Extra labour to assist M/C operator &security

0134 Rock Hole Driller day 1.40 329.00 460.60 0114 Beldar day 10.00 329.00 3,290.00 0103 Blacksmith 2nd class day 1.25 399.00 498.75 0113 Chowkidar day 1.00 329.00 329.00

Sub Total 16,456.79 Add 1% WC 1% 164.57 Add CP 15% 15% 2,493.20 Total Cost for 14 meter 19,114.56 Cost of 1 metre 1,365.33

Say 1,365.40

3.2.2.5 600 mm dia

Code Description Unit Qty Rate (INR) Amount (INR) Remark

Details of cost for 14 metre0020 Hydraulic Excavator (3D) with driver and fuel day 0.95 8,000.00 7,600.00

Extra Diesel required for boring in rockystrata

1235 Diesel litre 20.00 55.49 1,109.80 0005 Hire charges of Diesel Truck - 9 tonne day 0.4286 1,700.00 728.62

Transportation charges for to and fro to site (assume 140m of bore for one shifting) (2 x30)/140

Loading, Unloading & Erection Charges of Drilling Rig Machine

0114 Beldar day 4.00 329.00 1,316.00 0130 Mistry day 1.00 435.00 435.00 7763 Water supply tanker of 5000 ltr capacity day 1.00 800.00 800.00

Extra labour to assist M/C operator &security

0134 Rock Hole Driller day 1.60 329.00 526.40 0114 Beldar day 12.00 329.00 3,948.00 0103 Blacksmith 2nd class day 1.50 399.00 598.50 0113 Chowkidar day 1.00 329.00 329.00

Sub Total 17,391.32 Add 1% WC 1% 173.91 Add CP 15% 15% 2,634.78 Total Cost for 14 meter 20,200.02 Cost of 1 metre 1,442.86

Say 1,442.90

Delhi Jal Board 690 Schedule of Rates 2014 - 2015

Page 442: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Code Description Unit Qty Rate (INR) Amount (INR) Remarks

3.5

Code Description Unit Qty Rate (INR) Amount (INR) RemarkDetails of cost for 1 No.MATERIAL:

Quotation_Volume III_pg no 96 Cost of hand pump each 1.00 6,405.00 6,405.00

09999 Carriage of material L.S. 107.95 1.78 192.15 LABOUR:

0116 Fitter (grade 1) day 0.10 435.00 43.50 0114 Beldar day 0.10 329.00 32.90

09999 Sundries L.S. 1.29 1.78 2.29 Total 6,675.84 Add 1% WC 1% 66.76 Add CP 15% 15% 1,011.39 Cost of each 7,753.99

Say 7,754.00

3.6

Code Description Unit Qty Rate (INR) Amount (INR) RemarkDetails of cost for 1 No.MATERIAL:

Quotation_Volume III_pg no 96 Cost of hand pump each 1.00 6,510.00 6,510.00

09999 Carriage of material L.S. 109.72 1.78 195.30 LABOUR:

0138 Fitter (grade 1) day 0.11 435.00 47.85 0134 Beldar day 0.11 329.00 36.19

09999 Sundries L.S. 1.42 1.78 2.52 Total 6,791.86 Add 1% WC 1% 67.92 Add CP 15% 15% 1,028.97 Cost of each 7,888.75

Say 7,888.80

3.7

Code Description Unit Qty Rate (INR) Amount (INR) RemarkDetails of cost for 1 No.MATERIAL:

Quotation_Volume III_pg no 96 Cost of hand pump each 1.00 11,025.00 11,025.00

09999 Carriage of material L.S. 185.81 1.78 330.75 LABOUR:

0138 Fitter (grade 1) day 0.20 435.00 87.00 0134 Beldar day 0.20 329.00 65.80

09999 Sundries L.S. 2.58 1.78 4.58 Total 11,513.13 Add 1% WC 1% 115.13 Add CP 15% 15% 1,744.24 Cost of each 13,372.51

Say 13,372.60

3.8

Code Description Unit Qty Rate (INR) Amount (INR) RemarkDetails of cost for 1 No.MATERIAL:

Quotation_Volume III_pg no 95 Cost of hand pump each 1.00 11,182.50 11,182.50

Providing and fixing ISI Mark India Mark-II deep well hand pump complete with 10 Nos. MS Connecting Rods (12mmx 3 M long) Telescopic Stand Assembly

Providing and fixing ISI Mark India Mark-II extra deep well hand pump complete with 20 Nos. MS Connecting Rods(12mm x 3 M long) counter weight electro galvanized and Passivated Normal Stand Assembly

Providing and fixing ISI Mark India Mark-II extra deep well hand pump complete with 20 Nos. MS Connecting Rods(12mm x 3 M long) counter weight electro galvanized and Passivated Telescopic Stand Assembly

Providing and fixing ISI Mark India Mark-II deep well hand pump complete with 10 Nos. MS Connecting Rods (12mmx 3 M long) Normal Stand Assembly

Delhi Jal Board 681 Schedule of Rates 2014 - 2015

Page 443: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Code Description Unit Qty Rate (INR) Amount (INR) Remarks

09999 Carriage of material L.S. 188.47 1.78 335.48 LABOUR:

0138 Fitter (grade 1) day 0.24 435.00 104.40 0134 Beldar day 0.24 329.00 78.96

09999 Sundries L.S. 3.09 1.78 5.50 Total 11,706.84 Add 1% WC 1% 117.07 Add CP 15% 15% 1,773.59 Cost of each 13,597.49

Say 13,597.50

Delhi Jal Board 682 Schedule of Rates 2014 - 2015

Page 444: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

4.0

4.3

Code No Description Unit Qty Rate (INR)

Amount (INR) Remarks

Details of cost for 1 no of connectionAnnexure "A" P/F DI strap saddle of 100mm size i/c

boring & taping the distribution main of 8 mm nominal bore size

Each 1 578.04 578.04

Market rate Hex nipple 8mm bore size Each 1 82.16 82.16Market rate Providing and supply of PP compression

Metal insert elbow 90° size 20mm OD x15mm ID (connecting DI saddle to MDPE Pipe)

Each 1 103.90 103.9

Annexure "B" Laying and jointing MDPE pipe 20mm outer dia i/c all fittings

mtr 4 52.17 208.69

Market rate Female threaded Adapter of size 20 mm OD X 15 mm ID (connecting MDPE Pipe to GI pipe)

Each 1 103.90 103.9

18.10.1 Providing and fixing G.I. pipes complete with G.I. fittings and clamps 15 mm dia

mtr 1.5 215.10 322.65(A)

Annexure "C"

labour for disconnection from old line & plugging the bore hole

Each 1 132.13 132.13

Total 1531.47Add Water Charges @ 1% except on (A) 1% 12.09

Add CPOH @ 15% except on (A) 15% 183.14Cost of one water connection 1726.69

Say 1726.70

18mm bore size

Code No Description Unit Qty Rate (INR)

Amount (INR) Remarks

Tapping new distribution pipe with saddle fitted with adopter of bore size for additional control

SHIFTING OF WATER CONNECTION/NEW CONNECTIONS

Shifting of house service connection from old to new water distribution main upto water meterwhich includes providing and fixing of DI strap saddle having outer body of ductile iron,seal/gasket of EPDM, strap with integrated bolt of stainless steel, nut and washers of carbonsteel etc., having total minimum weight of 1.5 kg, hex nipple of 8 mm bore size (SS304) andfemale threaded metal insert elbow of SS 304, female threaded adopter with one sidedcompression, GI pipe of Class ‘B’ confirming to relevant IS Code of 15 mm nominal bore withall fittings upto 1.5 m length for above ground and laying & joining of MDPE pipe 20mm OD withall fittings in underground line, including tapping and boring in new water distribution main anddisconnection of existing house service connection from old water distribution main andplugging the bore hole, depositing all dismantled material i.e. ferrule, house service connectionpipe and fittings etc. in the store of department; complete in all respect as per the directions ofEngineer-in Charge. (MDPE pipe & other fittings shall be provided by department from itscentral store).

Annexure "A"

Delhi Jal Board 700 Schedule of Rates 2014 - 2015

Page 445: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

details for one saddleMarket rate DI saddle 100mm size each 1 534.54 534.54

Labour for tapping & fixing0116 Fitter grade I day 0.1 435 43.50

cost for one no. 578.04

1

Labour for 8nos. Connection

Code No Description Unit Qty Rate (INR)

Amount (INR) Remarks

0117 Fitter IInd class day 1 399 3990114 Beldar day 2 329 658

Total for 8nos. 1057cost for one no. 132.13

1

labour for 10 mtr pipe 20 mm outer dia

Code No Description Unit Qty Rate (INR)

Amount (INR) Remarks

0116 Fitter (grade 1) day 0.08 435 34.80114 Beldar day 0.16 329 52.64

Trenching and refilling etc.0114 Beldar day 0.66 329 217.140115 Coolie day 0.66 329 217.14

Total 521.72Cost for one mtr length 52.17

Annexure "B"

Disconnection of existing connection from old line and plugging the bore hole, depositing all dismentled material in the store of department, all complete as per direction by Engineer-in-charge

Laying and jointing of MDPE pipe i/c all fittings, trenching, reffiling and testing of joints as per direction of Engineer-in-charge.

Annexure "C"

Delhi Jal Board 701 Schedule of Rates 2014 - 2015

Page 446: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

5.0 MISCELLANEOUS

5.1 Disinfection of PSC/CI/MS water main5.1.1

5.1.1.1 700 mm diaCode No Description Unit Qty Rate (INR) Amount

(INR) Detail for 100 m lengthLength of pipe meter 100 Diameter of pipe meter 0.70

Bleaching powder gm/litre 0.50

MATERIAL1301 Bleaching Powder (0.5 gm/ltr)

((3*3.1416*(0.7^2))/4)*100*1000*0.5 gm/litre gm 57,727 quintal 0.5773 1,750.00 1,010.22

LABOUR0116 Fitter (grade 1) each 2.94 435.00 1,278.90 0114 Beldar each 6.57 329.00 2,161.53

09999 Sundries each 57.98 1.78 103.21 Sub Total 4,553.86

Add WC @ 1% 1% 45.54 Add CPOH @ 15% 15% 689.91

Cost for 100 m 5,289.31 Cost for 1 m 52.89

Say 52.90

5.1.1.2 800 mm diaCode No Description Unit Qty Rate (INR) Amount

(INR) Detail for 100 m lengthLength of pipe meter 100 Diameter of pipe meter 0.80 Bleaching powder gm/litre 0.50

Disinfecting water mains by flushing with water containing bleaching powder at 0.5 gms per litre of waterand cleaning the same with fresh water, operation to be repeated three times including getting the sampleof water from the disinfected main tested in the DJB laboratory.

Bleaching powder gm/litre 0.50

MATERIAL1301 Bleaching Powder (0.5 gm/ltr)

((3*3.1416*(0.8^2))/4)*100*1000*0.5 gm/litre gm 75,398 quintal 0.7540 1,750.00 1,319.47

LABOUR0116 Fitter (grade 1) each 3.26 435.00 1,418.10 0114 Beldar each 7.23 329.00 2,378.67

09999 Sundries each 63.99 1.78 113.90 Sub Total 5,230.14

Add WC @ 1% 1% 52.30 Add CPOH @ 15% 15% 792.37

Cost for 100 m 6,074.81 Cost for 1 m 60.75

Say 60.80

5.1.1.3 900 mm diaCode No Description Unit Qty Rate (INR) Amount

(INR) Detail for 100 m lengthLength of pipe meter 100 Diameter of pipe meter 0.90 Bleaching powder gm/litre 0.50

MATERIAL1301 Bleaching Powder (0.5 gm/ltr)

((3*3.1416*(0.9^2))/4)*100*1000*0.5 gm/litre gm 95,426 quintal 0.9543 1,750.00 1,669.95

LABOUR

Delhi Jal Board 703 Schedule of Rates 2014 - 2015

Page 447: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

0116 Fitter (grade 1) each 3.58 435.00 1,557.30 0114 Beldar each 7.89 329.00 2,595.81

09999 Sundries each 70.00 1.78 124.59 Sub Total 5,947.66

Add WC @ 1% 1% 59.48 Add CPOH @ 15% 15% 901.07

Cost for 100 m 6,908.20 Cost for 1 m 69.08

Say 69.10

5.1.1.4 1000 mm diaCode No Description Unit Qty Rate (INR) Amount

(INR) Detail for 100 m lengthLength of pipe meter 100 Diameter of pipe meter 1.00 Bleaching powder gm/litre 0.50

MATERIAL1301 Bleaching Powder (0.5 gm/ltr)

((3*3.1416*(1^2))/4)*100*1000*0.5 gm/litre gm 1,17,810 quintal 1.1781 1,750.00 2,061.67

LABOUR0116 Fitter (grade 1) each 3.90 435.00 1,696.50 0114 Beldar each 8.55 329.00 2,812.95

09999 Sundries each 76.00 1.78 135.28 Sub Total 6,706.40

Add WC @ 1% 1% 67.06 Add CPOH @ 15% 15% 1,016.02

Cost for 100 m 7,789.49 Cost for 1 m 77.89

Say 77.90

5.1.1.5 1100 mm diaCode No Description Unit Qty Rate (INR) Amount

(INR) Detail for 100 m lengthLength of pipe meter 100 Diameter of pipe meter 1.10 Bleaching powder gm/litre 0.50

MATERIAL1301 Bleaching Powder (0.5 gm/ltr)

((3*3.1416*(1.1^2))/4)*100*1000*0.5 gm/litre gm 1,42,550 quintal 1.4255 1,750.00 2,494.62

LABOUR0116 Fitter (grade 1) each 4.22 435.00 1,835.70 0114 Beldar each 9.21 329.00 3,030.09

09999 Sundries each 82.01 1.78 145.97 Sub Total 7,506.38

Add WC @ 1% 1% 75.06 Add CPOH @ 15% 15% 1,137.22

Cost for 100 m 8,718.67 Cost for 1 m 87.19

Say 87.20

5.1.1.6 1200 mm diaCode No Description Unit Qty Rate (INR) Amount

(INR) Detail for 100 m lengthLength of pipe meter 100 Diameter of pipe meter 1.20 Bleaching powder gm/litre 0.50

MATERIAL1301 Bleaching Powder (0.5 gm/ltr)

((3*3.1416*(1.2^2))/4)*100*1000*0.5 gm/litre gm 1,69,646 quintal 1.6965 1,750.00 2,968.81

LABOUR

Delhi Jal Board 704 Schedule of Rates 2014 - 2015

Page 448: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

0116 Fitter (grade 1) each 4.54 435.00 1,974.90 0114 Beldar each 9.87 329.00 3,247.23

09999 Sundries each 88.01 1.78 156.66 Sub Total 8,347.60

Add WC @ 1% 1% 83.48 Add CPOH @ 15% 15% 1,264.66

Cost for 100 m 9,695.74 Cost for 1 m 96.96

Say 97.00

5.1.1.7 1500 mm diaCode No Description Unit Qty Rate (INR) Amount

(INR) Detail for 100 m lengthLength of pipe meter 100 Diameter of pipe meter 1.50 Bleaching powder gm/litre 0.50

MATERIAL1301 Bleaching Powder (0.5 gm/ltr)

((3*3.1416*(1.5^2))/4)*100*1000*0.5 gm/litre gm 2,65,072 quintal 2.6507 1,750.00 4,638.76

LABOUR0116 Fitter (grade 1) each 4.86 435.00 2,114.10 0114 Beldar each 10.53 329.00 3,464.37

09999 Sundries each 94.02 1.78 167.35 Sub Total 10,384.58

Add WC @ 1% 1% 103.85 Add CPOH @ 15% 15% 1,573.26

Cost for 100 m 12,061.69 Cost for 1 m 120.62

Say 120.70

5.2 Guniting5.2.1 Guniting to surfaces of RCC structural members such as walls, columns, beams, slabs etc. with cement

mortar 1:3 of average thickness of 25 mm under pressure of 2.1 to 2.8 kg/cm2 including chipping the looseconcrete, cleaning rust by means of wire brush, providing and fixing BRC fabric (welded mesh) of 50 x 50mm size 10 gauge, necessary formwork, floating and curing etc. complete as specified and directed by

Code No Description Unit Qty Rate (INR) Amount (INR)

Details of cost for 1 sqmtAssuming thickness is equal to 25mmMATERIAL:

0367 Cement tonne 0.014 6300.00 86.18

1213 Water proofing compound kg 0.274 35.00 9.58

0983 Fine sand grade lV (Graded sand) cum 0.029 700.00 19.95 SOR Andhra

pradesh_2014_M-192 Wire mesh 50mm x 50mm size of 3mm dia of wire kg 2.45 252.00 617.40

CARRIAGE OF MATERIAL:

Cement tonne 0.014 70.71 0.97

Fine sand cum 0.0285 79.54 2.27

MACHINERIES:

Quotation_Volume III_pg no 247 and Rate Analysis enclosed for hiring charges of guniting machinery (M/s

Refra mech)

Compressor with guniting equipment along with all accessories and consumables day 0.25 1147.00 286.75

mm size 10 gauge, necessary formwork, floating and curing etc. complete as specified and directed byengineer in charge

Please refer Rate Analysis_Vol II_pg no 20

Delhi Jal Board 705 Schedule of Rates 2014 - 2015

Page 449: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

LABOUR:0114 Mazdoor day 0.0188 329.00 6.17 0101 Bhisti day 0.0018 363.00 0.64

TOTAL 1,029.90 Add 1% water charges 1% 10.30

Add 15% C.P 15% 156.03 Cost of 1 sqm 1,196.23

Say 1,196.30

Delhi Jal Board 706 Schedule of Rates 2014 - 2015

Page 450: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

5.4 Soil investigation

Taxes and Duties

Service tax 12.36%

5.4.1

Mobilization of necessary equipment menand materials etc., including setting up at alllocations (Total for all boreholes & DC testlocations)

LS 25,000.00 10,000.00 20,000.00 15,000.00 10,000.00 1,236.00 11,236.00 Quotation_Volume III_pg no 194 -196

5.4.2Boring in all types soil including clay at alldepths including Conducting required testsas per “a to f” below.

per meter 425.00 500.00 550.00 750.00 425.00 52.53 477.53 Quotation_Volume III_pg no 190 - 193

Nothing extra shall be payable for conducting these tests.

(a)Conducting SPT till refusal @ 1.5 mtsinterval and as directed in boreholes using51 mm dia, split spoon sampler for depth

(b) Grain Size analysis

(c)Atterberg limits (Liquid Limit, Plastic Limitand plasticity index, shrinkage limit andshrinkage ratio)

(d)Densities / specific gravities (Field densityand natural moisture content of undisturbedsoil samples)

M/s Foundtek Consultants

(Pvt) Ltd.

M/s Nagadi Consultants Reference

Rate (INR)

Final Price (INR) Unit Price Sr. No. Description of the item Unit

M/s Cengrs Geotechnical

(Pvt) Ltd.

M/s Ground Engineering

Ltd.

soil samples)(e) Analysis

a) Chemical Analysis of soil giving contents of sulphates, chlorides and pHb) Water Analysis (Physical / Chemical)

(f)Triaxial Shear test of undistrubed samplescollected at every 3 mts. Intervals from boreholes( Operated for item No. 5.4.2).

5.4.3Extra above Item no. 5.4.2 for drilling in rockat all depths including conducting requiredlab tests as per technical requirements.

Delhi Jal Board 715 Schedule of Rates 2014 - 2015

Page 451: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Taxes and Duties

Service tax 12.36%

M/s Foundtek Consultants

(Pvt) Ltd.

M/s Nagadi Consultants Reference

Rate (INR)

Final Price (INR) Unit Price Sr. No. Description of the item Unit

M/s Cengrs Geotechnical

(Pvt) Ltd.

M/s Ground Engineering

Ltd.

5.4.3.1 a) Weathered rock meter 4,000.00 5,000.00 5,200.00 3,000.00 3,000.00 370.80 3,370.80 Quotation_Volume III_pg no 200 - 204

5.4.3.2 b) Hard rock meter 4,000.00 6,000.00 5,800.00 3,000.00 3,000.00 370.80 3,370.80 Quotation_Volume III_pg no 200 - 204

5.4.4Dynamic Cone Penetration (DCP) test up to10 m depth @ 0.5m interval including boringand all types of soil

per meter 100.00 400.00 300.00 200.00 100.00 12.36 112.36 Quotation_Volume III_pg no 190 - 193

5.4.5 Conducting CBR Test each 3,500.00 5,000.00 4,000.00 4,000.00 3,500.00 432.60 3,932.60 Quotation_Volume III_pg no 190 - 193

5.4.6 Determination of Soil Resistivity each 3,000.00 8,000.00 3,000.00 4,000.00 3,000.00 370.80 3,370.80 Quotation_Volume III_pg no 190 - 193

5.4.7 Conducting percolation test each 3,000.00 8,000.00 2,000.00 4,000.00 2,000.00 247.20 2,247.20 Quotation_Volume III_pg no 197 - 199

5.4.8Preparation and submission of preliminary and final reports on the Geo technical investigation in 3 sets

LS 10,000.00 5,000.00 10,000.00 12,000.00 5,000.00 618.00 5,618.00 Quotation_Volume III_pg no 194 -196

Delhi Jal Board 716 Schedule of Rates 2014 - 2015

Page 452: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

5.5 Providing Lead caulked joint5.5.1

5.5.1.1 700 mm dia

Code No Description Unit Qty Rate (INR) Amount (INR)

As per C.P.W.D. DAR_1997_Item no 20.45 Detail of cost for 10 joints

MATERIAL:1881 Spun yarn kg 11.70 50.00 585.00

700 mm dia pipe = 1.17 x 10 = 11.70 kg

0761 Fuel wood quintal 2.14 525.00 1,123.50 0771 Kerosene oil Litre 3.41 48.00 163.68 9999 Sundries L.S. 18.60 1.78 33.11 9999 Carriage of material L.S. 18.60 1.78 33.11

LABOUR:0116 Fitter (grade 1) day 7.70 435 3,349.50 0117 Assistant fitter or 2nd class fitter day 7.70 399 3,072.30 0114 Beldar day 15.40 329 5,066.60

Total 13,426.80 Add water charges @ 1% 134.27

Add CPOH @ 15% 2,034.16 Total for 10 no's 15,595.22

Total for 1 no 1,559.52 Say 1,559.53

5.5.1.2 800 mm dia

Code No Description Unit Qty Rate (INR) Amount (INR)

As per C.P.W.D. DAR_1997_Item no 20.45 Detail of cost for 10 joints

MATERIAL:

Providing lead caulked joints to spun iron or C.I. pipes and specials including testing of joints but excluding the cost of pig lead:

MATERIAL:1881 Spun yarn kg 13.30 50.00 665.00

800 mm dia pipe = 1.33 x 10 = 13.30 kg0761 Fuel wood quintal 2.33 525.00 1,223.25 0771 Kerosene oil Litre 3.41 48.00 163.68 9999 Sundries L.S. 20.70 1.78 36.85 9999 Carriage of material L.S. 20.700 1.78 36.85

LABOUR:0116 Fitter (grade 1) day 8.50 435 3,697.50 0117 Assistant fitter or 2nd class fitter day 8.50 399 3,391.50 0114 Beldar day 17.00 329 5,593.00

Total 14,807.62 Add water charges @ 1% 148.08

Add CPOH @ 15% 2,243.35 Total for 10 no's 17,199.05

Total for 1 no 1,719.91 Say 1,719.91

5.5.1.3 900 mm dia

Code No Description Unit Qty Rate (INR) Amount (INR)

As per C.P.W.D. DAR_1997_Item no 20.45 Detail of cost for 10 joints

MATERIAL:1881 Spun yarn kg 15.60 50.00 780.00

900 mm dia pipe = 1.56 x 10 = 15.60 kg

Delhi Jal Board 703 Schedule of Rates 2014 - 2015

Page 453: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

0761 Fuel wood quintal 2.80 525.00 1,470.00 0771 Kerosene oil Litre 4.55 48.00 218.40 9999 Sundries L.S. 23.30 1.78 41.47 9999 Carriage of material L.S. 23.300 1.78 41.47

LABOUR:0116 Fitter (grade 1) day 10.00 435 4,350.00 0117 Assistant fitter or 2nd class fitter day 10.00 399 3,990.00 0114 Beldar day 20.00 329 6,580.00

Total 17,471.35 Add water charges @ 1% 174.71

Add CPOH @ 15% 2,646.91 Total for 10 no's 20,292.97

Total for 1 no 2,029.30 Say 2,029.30

5.5.1.4 1000 mm dia

Code No Description Unit Qty Rate (INR) Amount (INR)

As per C.P.W.D. DAR_1997_Item no 20.45 Detail of cost for 10 joints

MATERIAL:1881 Spun yarn kg 17.00 50.00 850.00

1000 mm dia pipe = 1.7 x 10 = 17.00 kg0761 Fuel wood quintal 3.00 525.00 1,575.00 0771 Kerosene oil Litre 4.55 48.00 218.40 9999 Sundries L.S. 25.90 1.78 46.10 9999 Carriage of material L.S. 25.900 1.78 46.10

LABOUR:0116 Fitter (grade 1) day 11.00 435 4,785.00 0117 Assistant fitter or 2nd class fitter day 11.00 399 4,389.00 0114 Beldar day 22.00 329 7,238.00

Total 19,147.60 Add water charges @ 1% 191.48 Add water charges @ 1% 191.48

Add CPOH @ 15% 2,900.86 Total for 10 no's 22,239.94

Total for 1 no 2,223.99 Say 2,224.00

5.5.1.5 1100 mm dia

Code No Description Unit Qty Rate (INR) Amount (INR)

As per C.P.W.D. DAR_1997_Item no 20.45 Detail of cost for 10 joints

MATERIAL:1881 Spun yarn kg 18.70 50.00 935.00

1100 mm dia pipe = 1.87 x 10 = 18.70 kg0761 Fuel wood quintal 3.36 525.00 1,764.00 0771 Kerosene oil Litre 5.13 48.00 246.24 9999 Sundries L.S. 28.50 1.78 50.73 9999 Carriage of material L.S. 28.500 1.78 50.73

LABOUR:0116 Fitter (grade 1) day 12.00 435 5,220.00 0117 Assistant fitter or 2nd class fitter day 12.00 399 4,788.00 0114 Beldar day 24.00 329 7,896.00

Total 20,950.70 Add water charges @ 1% 209.51

Add CPOH @ 15% 3,174.03 Total for 10 no's 24,334.24

Total for 1 no 2,433.42

Delhi Jal Board 704 Schedule of Rates 2014 - 2015

Page 454: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Say 2,433.43

5.5.1.6 1200 mm dia

Code No Description Unit Qty Rate (INR) Amount (INR)

As per C.P.W.D. DAR_1997_Item no 20.45 Detail of cost for 10 joints

MATERIAL:1881 Spun yarn kg 20.40 50.00 1,020.00

1200 mm dia pipe = 2.04 x 10 = 20.40 kg0761 Fuel wood quintal 3.73 525.00 1,958.25 0771 Kerosene oil Litre 5.68 48.00 272.64 9999 Sundries L.S. 31.05 1.78 55.27 9999 Carriage of material L.S. 31.050 1.78 55.27

LABOUR:0116 Fitter (grade 1) day 13.00 435 5,655.00 0117 Assistant fitter or 2nd class fitter day 13.00 399 5,187.00 0114 Beldar day 26.00 329 8,554.00

Total 22,757.43 Add water charges @ 1% 227.57

Add CPOH @ 15% 3,447.75 Total for 10 no's 26,432.75

Total for 1 no 2,643.28 Say 2,643.28

5.5.1.7 1300 mm dia

Code No Description Unit Qty Rate (INR) Amount (INR)

As per C.P.W.D. DAR_1997_Item no 20.45 Detail of cost for 10 joints

MATERIAL:1881 Spun yarn kg 22.30 50.00 1,115.00

1200 mm dia pipe = 2.23 x 10 = 22.30 kg1200 mm dia pipe = 2.23 x 10 = 22.30 kg0761 Fuel wood quintal 4.06 525.00 2,131.50 0771 Kerosene oil Litre 6.53 48.00 313.44 9999 Sundries L.S. 33.65 1.78 59.90 9999 Carriage of material L.S. 33.65 1.78 59.90

LABOUR:0116 Fitter (grade 1) day 14.50 435 6,307.50 0117 Assistant fitter or 2nd class fitter day 14.50 399 5,785.50 0114 Beldar day 29.00 329 9,541.00

Total 25,313.73 Add water charges @ 1% 253.14

Add CPOH @ 15% 3,835.03 Total for 10 no's 29,401.90

Total for 1 no 2,940.19 Say 2,940.20

5.5.1.8 1400 mm dia

Code No Description Unit Qty Rate (INR) Amount (INR)

As per C.P.W.D. DAR_1997_Item no 20.45 Detail of cost for 10 joints

MATERIAL:1881 Spun yarn kg 23.90 50.00 1,195.00

1200 mm dia pipe = 2.39 x 10 = 23.90 kg0761 Fuel wood quintal 4.36 525.00 2,289.00 0771 Kerosene oil Litre 7.01 48.00 336.48

Delhi Jal Board 705 Schedule of Rates 2014 - 2015

Page 455: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

9999 Sundries L.S. 36.20 1.78 64.44 9999 Carriage of material L.S. 36.20 1.78 64.44

LABOUR:0116 Fitter (grade 1) day 15.50 435 6,742.50 0117 Assistant fitter or 2nd class fitter day 15.50 399 6,184.50 0114 Beldar day 31.00 329 10,199.00

Total 27,075.35 Add water charges @ 1% 270.75

Add CPOH @ 15% 4,101.92 Total for 10 no's 31,448.02

Total for 1 no 3,144.80 Say 3,144.81

5.5.1.9 1500 mm dia

Code No Description Unit Qty Rate (INR) Amount (INR)

As per C.P.W.D. DAR_1997_Item no 20.45 Detail of cost for 10 joints

MATERIAL:1881 Spun yarn kg 25.20 50.00 1,260.00

1500 mm dia pipe = 2.52 x 10 = 25.20 kg0761 Fuel wood quintal 4.67 525.00 2,451.75 0771 Kerosene oil Litre 7.38 48.00 354.24 9999 Sundries L.S. 38.85 1.78 69.15 9999 Carriage of material L.S. 38.850 1.78 69.15

LABOUR:0116 Fitter (grade 1) day 16.50 435 7,177.50 0117 Assistant fitter or 2nd class fitter day 16.50 399 6,583.50 0114 Beldar day 33.00 329 10,857.00

Total 28,822.30 Add water charges @ 1% 288.22

Add CPOH @ 15% 4,366.58 Total for 10 no's 33,477.10 Total for 10 no's 33,477.10

Total for 1 no 3,347.71

Delhi Jal Board 706 Schedule of Rates 2014 - 2015

Page 456: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Say 3,347.71

5.6 Providing & fixing fire hydrant5.6.1

Code No Description Unit Qty Rate (INR) Amount (INR)

Nabhi's text book_Water supply_item no

23.38_page no 1294

Detail of cost of providing & fixing for 10 Nos fire hydrant

MaterialWeight of 10 hydrants10*28.58kg=2.858kg

Quotation_Volume III_Pg no 437 Sypply of fire hydrant 63mm standard size each 10.00 1,732.50 17,325.00

1373 Rubber insertion each 10.00 15.00 150.00 1956 Nuts and bolts each 80.00 12.00 960.00

Carriage of materialFire hydrant tonne 0.2858 86.63 24.76

Labour0116 Fitter (grade I) day 2.70 435.00 1,174.50 0114 Beldar day 4.70 329.00 1,546.30

09999 Add for carriage of other materials & white lead, etc L.S. 18.34 1.78 32.65

09999 Add for sundries L.S. 45.86 1.78 81.62 Sub Total 21,294.83

Add for water charges 1% 212.95 Add for CPOH 15% 3,226.17

Total Cost for 10 nos 24,733.95 Total cost for 1 no 2,473.39

Say 2,473.40

Providing and fixing fire hydrant of size 65 mm complete with bolts and nut and rubber insertion (as per IS 5920)

Delhi Jal Board 707 Schedule of Rates 2014 - 2015

Page 457: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

5.7 Cutting Asbestos Cement Pressure Pipe5.7.1

5.7.1.1 100 mm diameter

Code No Description Unit Qty Rate (INR) Amount (INR)

Details of 1 cut for 100 mm dia Asbestos Cement Pressure pipes with steel sawLabour Charges

0116 Fitter (grade 1) day 0.04 435.00 17.40

0114 Beldar day 0.04 329.00 13.16

09999 Sundries day 1.365 1.78 2.43 Total 32.99 Water Charges @ 1% 1% 0.33 CPOH @ 15% 15% 5.00 Cost for each cut 38.32 Say 38.40

5.7.1.2 150 mm diameter

Code No Description Unit Qty Rate (INR) Amount (INR)

Details of 1 cut for 150 mm dia Asbestos Cement Pressure pipes with steel sawLabour Charges

0116 Fitter (grade 1) day 0.075 435.00 32.63

0114 Beldar day 0.075 329.00 24.68

09999 Sundries day 2.665 1.78 4.74 Total 62.04 Water Charges @ 1% 1% 0.62 CPOH @ 15% 15% 9.40 Cost for each cut 72.06 Say 72.10

5.7.1.3 200 mm diameterCode No Description Unit Qty Rate (INR) Amount (INR)

Details of 1 cut for 200 mm dia Asbestos Cement Pressure pipes with steel sawLabour Charges

0116 Fitter (grade 1) day 0.1 435.00 43.50

0114 Beldar day 0.1 329.00 32.90

09999 Sundries day 3.575 1.78 6.36 Total 82.76 Water Charges @ 1% 1% 0.83 CPOH @ 15% 15% 12.54

Cutting for asbestos cement pressure pipes with steel saw

Delhi Jal Board 717 Schedule of Rates 2014 - 2015

Page 458: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Code No Description Unit Qty Rate (INR) Amount (INR)

Cost for each cut 96.13 Say 96.20

5.7.1.4 250 mm diameterCode No Description Unit Qty Rate (INR) Amount (INR)

Details of 1 cut for 250 mm dia Asbestos Cement Pressure pipes with steel sawLabour Charges

0116 Fitter (grade 1) day 0.125 435.00 54.38

0114 Beldar day 0.125 329.00 41.13

09999 Sundries day 4.03 1.78 7.17 Total 102.67 Water Charges @ 1% 1% 1.03 CPOH @ 15% 15% 15.56 Cost for each cut 119.26 Say 119.30

5.7.1.5 300 mm diameterCode No Description Unit Qty Rate (INR) Amount (INR)

Details of 1 cut for 300 mm dia Asbestos Cement Pressure pipes with steel sawLabour Charges

0116 Fitter (grade 1) day 0.15 435.00 65.25

0114 Beldar day 0.15 329.00 49.35

09999 Sundries day 4.94 1.78 8.79 Total 123.39 Water Charges @ 1% 1% 1.23 CPOH @ 15% 15% 18.69 Cost for each cut 143.32 Say 143.40

Delhi Jal Board 718 Schedule of Rates 2014 - 2015

Page 459: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

5.8 Water proofing in Underground Reservoir

5.8.1 Providing and Laying Integral cement based water proofing treatment tothe flooring of the under ground reservior confirming to IS 6494 – 1988at all level as directed by engineer-in-charge and consisting of;

(i) After laying the levelling course of lean concrete and allowing it tot hardenfor atleast 48 hours, water proofing membrane should be spread over it, carebeing taken to provide suitable overlaps and care should be taken to preventany damges to the membrane.(ii) Membrane should be covered over with at least 50 mm thick cementsand screed using 1 : 3 mix and integral waterproofing compound inprescribed proportions. The surface or the screed should be levelled onlywith a wooden float and should not be trowelled smooth. Before laying thestructural concrete, the surface of the screed should be wetted with cementslurry Note: All waterproofing work is to be carried out by the specialist firmapproved by Owner/Architects with 10 years guarantee under the supervisionof main contractorDetail of Cost for 1 sqmt

(I) Material3002 (i) Polyvinyle chloride sheet 400 micron thick sqmt 1.00 40.00 400367 (ii) Cement tonne 0.05 6300.00 342.720983 (iii) Fine Sand (Zone IV) cum 1.00 700.00 7001213 (iv) Water Proofing compound kg 1.00 35.00 350046 (v) Cost of Water kl 0.02 200 4.896

(vii) Carriage of MaterialCement tonne 0.05 70.71 3.85

Sand cum 1.00 79.54 79.54

1206.01

(III) Labour for placing water proofing membrane, cement mortar andcleaning surface, etc

(a) for Placing/Spreading Waterproof Membrane and water proof cementsand mortar on the flooring of Underground reservoir)

Unit

Please refer Rate Analysis_Vol II_pg

no 20

Quantity Rate (INR) Amount (INR) Item code Sr. No. Description

sand mortar on the flooring of Underground reservoir)

0128 (i) Foreman/Mason/Pavior/Mate (for PVC sheet laying) day 0.08 363.00 29.040128 (ii) Mate day 0.1 363.00 49.0050139 (iii) Skilled Beldar day 0.04 363.00 14.520114 (iv) Beldar day 0.3 329.00 85.540101 (v) Bishti day 0.3 363.00 90.75

Add for carriage of Water proofing membrane and Water proofing compound, etc Ls 1.06 1.78 1.88

Add for Wire brush , Wooden float, Hacking tool, etc. Ls 1.96 1.78 3.50Sundries Ls 4.07 1.78 7.25

281.48Total = 1487.49

Add Water Charges @ 1% = 1% 14.87Total = 1502.37

Add-for contractor's profit @ 15% = 15% 225.35Cost of 1 sqmt = 1727.72

Say = 1727.80

5.8.2Providing and Laying water proofing treatment to the walls of the underground reservior confirming to IS 6494 – 1988 at all level as directed byengineer-in-charge and consisting of;

Nabhi_Analysis of rates_Textbook_28.

3

Jogalekar_Textbook_Labour constant_sr no 315,321 & 340

Delhi Jal Board 719 Schedule of Rates 2014 - 2015

Page 460: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Unit Quantity Rate (INR) Amount (INR) Item code Sr. No. Description

(i) IAfter the side walls are constructed and allowed to undergo the specifiedcuring, the inside surface of the walls should be made rough with a hackingtool, washed clean with water and wire brushed so as to remove all the loosematerial, and a waterproof cement plaster 1 : 3 mix with suitable proportion ofan integral waterproofing compound should be applied in two coats, the firstcoat being 12 mm thick and the next 10 mm thick. The second coat shouldbe applied after allowing a time interval of at least 24 h for the first coat toharden

(ii) The outside surface of the side walls should be treated with a waterproofrendering in a similar manner but in this case, only one coat of plaster 12 mmthick may be applied instead of two successive coats

(iii) The rendering should be cured as carefully as the main concretestructure. After the outside coat of plaster has been fully cured and allowed todry for some time, it may be given a coat of hot bitumen of the industrialgrade 85/25 conforming to IS : 702-1961 as a further precaution against theseepage of ground water into the tank

Note: All waterproofing work is to be carried out by the specialist firmapproved by Owner/Architects with 10 years guarantee under the supervisionof main contractor

Detail of Cost for 4 sqmt(I) Material

0367 (i) Cement tonne 0.85 6300 53550983 (ii) Fine Sand (Zone IV) cum 3 700 21001213 (iii) Water Proofing compound kg 17 35 5950313 (iv) Bitumen of the industrial grade 85/25 conforming to IS : 702-1961 tonne 0.004 49600.00 198.40370 (v) Coal (Steam) quintal 0.008 400.00 3.2

(vi) Cost of Water kl 0.38 200 76.5(vii) Carriage of MaterialCement tonne 70.71 0.00Sand cum 79.54 0.00Bitumen tonne 0.004 79.54 0.32Steam Coal quintal 0.008 90.91 0.73

8329.15

(II) Consolidation Charges0001 (i) Hire charges of Coaltar Boiler 900 to 1400 litre day 0.0028 830.00 2.34

Please refer Rate Analysis_Vol II_pg

no 20

0007 (ii) Hire charges of Coaltar Sprayer day 0.0026 300.00 0.783.12

(III) Labour for placing water proofing membrane and cement mortar,plastering , cleaning surface, heating and spraying bitumen

(a) For Plastering Work0128 (i) Mate day 0.2 363 72.60114 (ii) Mazdoor day 0.4 329.00 144.76

0101 (iii) Bishti day 0.2 363 58.08

(b) For heating and spraying bitumen

0130 (i) Mistry day 0.002 435.00 0.87

0138 (ii) Sprayer (for bitumen, tar etc.) day 0.00 363.00 1.02

0114 (iii) Beldar day 0.03 329.00 9.87

Add for carriage of Water proofing membrane and Water proofing compound, etc Ls 1.13 1.78 2.01

Add for Wire brush , Wooden float, Hacking tool, etc. Ls 2.10 1.78 3.73Sundries Ls 4.84 1.78 8.62

301.56Total = 8633.82

Add Water Charges @ 1% = 1% 86.34Total = 8720.16

Add-for contractor's profit @ 15% = 15% 1308.02Cost for 4 sqmt of area = 10028.18Cost for 1 sqmt of area = 2507.05

Say = 2507.10

Jogalekar_Textbook_Labour

constant_sr no 348

(i) LabourConstant - DSR_16.26

Nabhi_Analysis of rates_Textbook_28.3

Delhi Jal Board 720 Schedule of Rates 2014 - 2015

Page 461: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Unit Quantity Rate (INR) Amount (INR) Item code Sr. No. Description

Delhi Jal Board 721 Schedule of Rates 2014 - 2015

Page 462: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

5.9 Taking out PSC pipe5.9.1

5.9.1.1 900 mm dia

Code No Description Unit Qty Rate (INR)

Amount (INR)

weight of one pipe of 4.0 M length = 30 qtl

18.23 Cost for taking out quintal 30.00 137.40 4,122.00 Cost for 4 meter 4,122.00 Cost for 1 meter 1,030.50

Say = 1,030.50

5.9.1.2 1000 mm dia

Code No Description Unit Qty Rate (INR)

Amount (INR)

weight of one pipe of 4.0 M length = 34.5 qtl

18.23 Cost for taking out quintal 34.50 137.40 4,740.30 Cost for 4 meter 4,740.30 Cost for 1 meter 1,185.08

Say = 1,185.10

5.9.1.3 1100 mm dia

Code No Description Unit Qty Rate (INR)

Amount (INR)

weight of one pipe of 4.0 M length = 39.5 qtl

18.23 Cost for taking out quintal 39.50 137.40 5,427.30 Cost for 4 meter 5,427.30 Cost for 1 meter 1,356.83

Say = 1,356.80

5.9.1.4 1200 mm dia

Code No ` Unit Qty Rate (INR)

Amount (INR)

weight of one pipe of 4.0 M length = 46.5 qtl

18.23 Cost for taking out quintal 46.50 137.40 6,389.10 Cost for 4 meter 6,389.10 Cost for 1 meter 1,597.28

Say = 1,597.30

Taking out S&S PSC. Pipes from the trenches after dejointing and stacking the same along the trenches with in lead of 50 metres.

Delhi Jal Board 721 Schedule of Rates 2014 - 2015

Page 463: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

5.10 Cast Iron Detachable (CID) Joint

5.10.1

5.10.1.1 100 mm diameter pipe

Code No Description Unit Qty Rate (INR) Amount (INR) Remark

Detail of cost for 10 jointsMaterial

Quotation_Volume III_Pg

no 205100 mm dia each 10.00 217.26 2,172.60

2309 Carriage of material = 5.9 x 10 nos = kg 59.00tonne 0.059 94.65 5.58

Labour0116 Fitter (grade 1) day 0.50 435.00 217.50 0117 Assistant fitter day 0.50 399.00 199.50 0114 Beldar day 2.00 329.00 658.00

Total 3,253.18 Add for water charges @ 1% 1% 32.53 Add for CPOH @ 15% 15% 492.86 Cost for10 joints 3,778.57 cost for 1 joint 377.86

Say = 377.90

5.10.1.2 150 mm diameter pipe

Code No Description Unit Qty Rate (INR) Amount (INR) Remark

Detail of cost for 10 jointsMaterial

Quotation_Volume III_Pg

no 207150 mm dia each 10.00 303.96 3,039.60

2309 Carriage of material = 9.3 x 10 nos = kg 93.00tonne 0.093 94.65 8.80

Labour0116 Fitter (grade 1) day 0.60 435.00 261.00 0117 Assistant fitter day 0.60 399.00 239.40 0114 Beldar day 2.20 329.00 723.80

Total 4,272.60 Add for water charges @ 1% 1% 42.73 Add for CPOH @ 15% 15% 647.30 Cost for10 joints 4,962.63 cost for 1 joint 496.26

Say = 496.30

5.10.1.3 200 mm diameter pipe

Code No Description Unit Qty Rate (INR) Amount (INR) Remark

Detail of cost for 10 jointsMaterial

Quotation_Volume III_Pg

no 205200 mm dia each 10.00 522.24 5,222.40

Carriage of material = 14.97 x 10 nos = kg 149.70tonne 0.150 94.65 14.17

Labour0116 Fitter (grade 1) day 0.60 435.00 261.00 0117 Assistant fitter day 0.60 399.00 239.40 0114 Beldar day 2.20 329.00 723.80

Providing and laying cast iron detachable joints to asbestos cement pressure pipes and plain ended Class 15 C.I.specials with collars rubber rings, flanges,bolts and nuts etc. complete,including testing of joints. These rates are excluding excise duty.

Delhi Jal Board 722 Schedule of Rates 2014 - 2015

Page 464: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Code No Description Unit Qty Rate (INR) Amount (INR) Remark

Total 6,460.77 Add for water charges @ 1% 1% 64.61 Add for CPOH @ 15% 15% 978.81 Cost for10 joints 7,504.18 cost for 1 joint 750.42

Say = 750.40

5.10.1.4 250 mm diameter pipe

Code No Description Unit Qty Rate (INR) Amount (INR) Remark

Detail of cost for 10 jointsMaterial

Quotation_Volume III_Pg

no 205250 mm dia each 10.00 696.66 6,966.60

Carriage of material = 22 x 10 nos = kg 220.00tonne 0.22 94.65 20.82

Labour0116 Fitter (grade 1) day 0.80 435.00 348.00 0117 Assistant fitter day 0.80 399.00 319.20 0114 Beldar day 2.60 329.00 855.40

Total 8,510.02 Add for water charges @ 1% 1% 85.10 Add for CPOH @ 15% 15% 1,289.27 Cost for10 joints 9,884.39 cost for 1 joint 988.44

Say = 988.40

5.10.1.5 300 mm diameter pipe

Code No Description Unit Qty Rate (INR) Amount (INR) Remark

Detail of cost for 10 jointsMaterial

Quotation_Volume III_Pg

no 205300 mm dia each 10.00 858.84 8,588.40

Carriage of material = 25 x 10 nos = kg 250.00tonne 0.25 94.65 23.66

Labour0116 Fitter (grade 1) day 0.80 435.00 348.00 0117 Assistant fitter day 0.80 399.00 319.20 0114 Beldar day 2.60 329.00 855.40

Total 10,134.66 Add for water charges @ 1% 1% 101.35 Add for CPOH @ 15% 15% 1,535.40 Cost for10 joints 11,771.41 cost for 1 joint 1,177.14

Say = 1,177.10

Delhi Jal Board 723 Schedule of Rates 2014 - 2015

Page 465: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

5.11 1.6 m high corrugated GI sheet barricading5.11.1

Code No Description Unit Qty Rate (INR) Amount (INR) Remark

For a length 15 m X 1.6 m = 24 sqmt

CGI Sheet 0.8 mm thick (22 gauge) Size of Sheet = 2.5 m x 0.8 m Area of sheet = 2.0 sqmt No. of sheets = 15/2.5 = 6 no's Total No of Sheets = 2*6 = 12 no's Weight of sheet = 7.03 kg/sqmt Total weight of steet = 12*(2.5*0.8)*7.03 = 168.72 168.72

I Material Cost 3050 Cost of CGI Galvanised Sheet quintal 1.6872 5,800.00 9,785.76 0302 Cost of Safeda Ballies 100 m dia meter 14.00 33.60 470.40

Total 10,256.16 Deduction of CGI sheet, safeda ballies after using 10 times @75% 7,692.12

Total 2,564.04

13.53.1 Painting on CGI Sheet sqmt 24.00 78.50 1,884.00 09999 Cost of Nails for fixing GI sheet LS 14.91 1.78 26.55

4,474.59 cost of material and painting for using 10 times Total for material = 447.46 A

II Carriage 2302 Carriage of GI sheet quintal 1.6872 9.47 15.97

2204 Carriage of Safeda Ballis, v = pi*r2*h = pi*(0.1/2)^2*14 cum 0.110 121.70 13.38

Total for carriage = 29.35 B

III Excavation

2.6.1 Earth Work in excavation = (0.3)*(0.3)*(0.4)*((15/2.5)+1) cum 0.25 155.60 39.21

2.25 Back filling = pi()*r^2*0.4*((15/2.5)+1) cum 0.022 112.40 2.47 Rate Analysis

Enclosed Disposal of extra excavated earth cum 0.23 99.43 22.87

0979 Royalty for disposing extra excated earth cum 0.23 30.00 6.90

Total for Carriage of material and excavation = 71.45 C

IV Labour 0112 Carpenter 2nd class day 0.12 399.00 47.88 0114 Beldar day 0.25 329.00 82.25

Sundries Ls 2.19 1.78 3.90

Providing & Erecting 1.6m high corrugated G.I. Sheets barricading supported on safeda ballies 100mmф, two metre high placed at 2.5m c/c corrugated G.I. sheets fixed with nails of required length and dia tosafeda ballies i/c excavating holes of size 0.3x0.3x0.40m getting out the excavated soil and thenreturning the soil i/c consolidating by ramming and watering etc. all complete i/c disposal of surplusexcavated earth with in a lead of 50m lift upto 1.5m and painting on full surface of C.G.I. Sheet (on oneside with bright paint of red & white colour in vertical strips 0.3m wide alternately as directed byEngineer-in-Charge. (The barricading provided shall remain to be the property of contractor oncompletion of the work).

Delhi Jal Board 724 Schedule of Rates 2014 - 2015

Page 466: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Code No Description Unit Qty Rate (INR) Amount (INR) Remark

Total for labours = 134.03 D Total (A+B+C+D) 682.30

Add WC @ 1% 4.52 Add CPOH @ 15% 68.51

Cost for 24 sqmt 755.33 Cost per sqmt 31.47

Say 31.50

Delhi Jal Board 725 Schedule of Rates 2014 - 2015

Page 467: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

5.12 Filling of water into water main5.12.1

5.12.1.1 100 mm dia pipe

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

Detail of cost for 100 mm dia and 4000 meter length of water main

Cost of boring with 100 mm dia casing pipe

18.42

Boring with 100 mm dia casing pipe for tube well in all soils except ordinary hard rocks requiring blasting including removing the casing pipe after the tube well is lowered and tested

18.42.1 Upto 6 metres depth meter 6 323.05 1938.318.42.2 Beyond 6 m and upto 12 m depth meter 6 383.60 2301.6

Total 4239.9 A

18.43Providing and placing in position filters of 40 mm diameter G.I. pipe with brass strainer of approved quality.

meter 3 593.65 1780.95 B

18.44Providing and fixing to filter and lowering to proper levels 40 mm G.I. pipe for tube well including cleaning and priming the tube well.

meter 9 309.30 2783.7 C

Sub total (A+B+C) 8804.55

1549 G.I. pipes 40 mm dia meter 9 220.00 1980.00 D1882 Strainer brass 40 mm dia 1.5 metre long each 2 600.00 1200.00 E

Sub total (D+E) 3180.00

GI pipes and brass strainer can be used 10 times

3180/10 = 318Credit for GI pipes and brass strainer after taking into account depreciation value @ 10%

3180-318 = 2862.00Net cost of boring

8804.55-2862 = 5942.55

Quantity of water required for 4000 m length of 100 mm internal dia pipe 100 mm

Volume of water = π x r2 x hr = 0.05 meterh = 4000 meter

hence, Volume of water =3.1416*(0.05^2)*4000 = 31.42 cum

6919.81 gallon

Assuming that a diesel pump of 5HP capacity can pump @ 3000 gallon per hour 3000 gallon

Hence, no of hours =6919.81/3000 = 2.31 hours

No of days for a shift of 8 hrs2.31/8 = 0.29 day

Filling of water into water main to the specified head, water to be arranged by sinking of tube well and pumping out the underground water and filling the same into water main including installation of pumps of sufficient capacity and head, providing and fixing delivery and suction pipe etc., all complete and as directed by Engineer-in-charge.

Delhi Jal Board 726 Schedule of Rates 2014 - 2015

Page 468: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

Consumption of diesel @ 1 ltr/hrHence, qty of diesel required in ltr =

(2.31*1)/1 = 2.31 litre

1235 Cost of Diesel litre 2.31 55.49 128.18 F0011 Hire charges of pump set day 0.289 600.00 173.25 G

09999 Sundries L.S. 598.292 1.78 1064.96 HSub total (F+G+H) 1366.39

Total 7308.94Add WC @ 1% 1% 13.66

Add CPOH @ 15% 15% 207.01Total cost of boring of pump and running of pump

for 4000 m length 7529.61

cost of filling of 100 mm Ø water main for 1 meter 1.88

Say 1.90

5.12.1.2 150 mm dia pipe

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

Detail of cost for 150 mm dia and 4000 meter length of water main

Cost of boring with 100 mm dia casing pipe

18.42

Boring with 100 mm dia casing pipe for tube well in all soils except ordinary hard rocks requiring blasting including removing the casing pipe after the tube well is lowered and tested

18.42.1 Upto 6 metres depth meter 6 323.05 1938.318.42.2 Beyond 6 m and upto 12 m depth meter 6 383.60 2301.6

Total 4239.9 A

18.43Providing and placing in position filters of 40 mm diameter G.I. pipe with brass strainer of approved quality.

meter 3 593.65 1780.95 B

18.44Providing and fixing to filter and lowering to proper levels 40 mm G.I. pipe for tube well including cleaning and priming the tube well.

meter 9 309.30 2783.7 C

Sub total (A+B+C) 8804.55

1549 G.I. pipes 40 mm dia meter 9 220.00 1980.00 D1882 Strainer brass 40 mm dia 1.5 metre long each 2 600.00 1200.00 E

Sub total (D+E) 3180.00

GI pipes and brass strainer can be used 10 times

3180/10 = 318Credit for GI pipes and brass strainer after taking into account depreciation value @ 10%

3180-318 = 2862.00Net cost of boring

8804.55-2862 = 5942.55

Quantity of water required for 4000 m length of 150 mm internal dia pipe 150 mm

Volume of water = π x r2 x hr = 0.08 meterh = 4000 meter

hence, Volume of water =3.1416*(0.075^2)*4000 = 70.69 cum

15569.57 gallon

Delhi Jal Board 727 Schedule of Rates 2014 - 2015

Page 469: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

Assuming that a diesel pump of 5HP capacity can pump @ 3000 gallon per hour 3000 gallon

Hence, no of hours =15569.57/3000 = 5.19 hours

No of days for a shift of 8 hrs5.19/8 = 0.649 day

Consumption of diesel @ 1 ltr/hrHence, qty of diesel required in ltr =

(5.19*1)/1 = 5.19 litre

1235 Cost of Diesel litre 5.19 55.49 287.99 F0011 Hire charges of pump set day 0.649 600.00 389.25 G

09999 Sundries L.S. 598.292 1.78 1064.96 HSub total (F+G+H) 1742.20

Total 7684.75Add WC @ 1% 1% 17.42

Add CPOH @ 15% 15% 263.94Total cost of boring of pump and running of pump

for 4000 m length 7966.12

cost of filling of 150 mm Ø water main for 1 meter 1.99

Say 2.00

5.12.1.3 200 mm dia pipe

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

Detail of cost for 200 mm dia and 4000 meter length of water main

Cost of boring with 100 mm dia casing pipe

18.42

Boring with 100 mm dia casing pipe for tube well in all soils except ordinary hard rocks requiring blasting including removing the casing pipe after the tube well is lowered and tested

18.42.1 Upto 6 metres depth meter 6 323.05 1938.318.42.2 Beyond 6 m and upto 12 m depth meter 6 383.60 2301.6

Total 4239.9 A

18.43Providing and placing in position filters of 40 mm diameter G.I. pipe with brass strainer of approved quality.

meter 3 593.65 1780.95 B

18.44Providing and fixing to filter and lowering to proper levels 40 mm G.I. pipe for tube well including cleaning and priming the tube well.

meter 9 309.30 2783.7 C

Sub total (A+B+C) 8804.55

1549 G.I. pipes 40 mm dia meter 9 220.00 1980.00 D1882 Strainer brass 40 mm dia 1.5 metre long each 2 600.00 1200.00 E

Sub total (D+E) 3180.00

GI pipes and brass strainer can be used 10 times

3180/10 = 318Credit for GI pipes and brass strainer after taking into account depreciation value @ 10%

3180-318 = 2862.00Net cost of boring

8804.55-2862 = 5942.55

Delhi Jal Board 728 Schedule of Rates 2014 - 2015

Page 470: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

Quantity of water required for 4000 m length of 200 mm internal dia pipe 200 mm

Volume of water = π x r2 x hr = 0.10 meterh = 4000 meter

hence, Volume of water =3.1416*(0.1^2)*4000 = 125.66 cum

27679.23 gallon

Assuming that a diesel pump of 5HP capacity can pump @ 3000 gallon per hour 3000 gallon

Hence, no of hours =27679.23/3000 = 9.23 hours

No of days for a shift of 8 hrs9.23/8 = 1.154 day

Consumption of diesel @ 1 ltr/hrHence, qty of diesel required in ltr =

(9.23*1)/1 = 9.23 litre

1235 Cost of Diesel litre 9.23 55.49 512.17 F0011 Hire charges of pump set day 1.154 600.00 692.25 G

09999 Sundries L.S. 598.292 1.78 1064.96 HSub total (F+G+H) 2269.38

Total 8211.93Add WC @ 1% 1% 22.69

Add CPOH @ 15% 15% 343.81Total cost of boring of pump and running of pump

for 4000 m length 8578.44

cost of filling of 200 mm Ø water main for 1 meter 2.14

Say 2.20

5.12.1.4 250 mm dia pipe

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

Detail of cost for 250 mm dia and 4000 meter length of water main

Cost of boring with 100 mm dia casing pipe

18.42

Boring with 100 mm dia casing pipe for tube well in all soils except ordinary hard rocks requiring blasting including removing the casing pipe after the tube well is lowered and tested

18.42.1 Upto 6 metres depth meter 6 323.05 1938.318.42.2 Beyond 6 m and upto 12 m depth meter 6 383.60 2301.6

Total 4239.9 A

18.43Providing and placing in position filters of 40 mm diameter G.I. pipe with brass strainer of approved quality.

meter 3 593.65 1780.95 B

18.44Providing and fixing to filter and lowering to proper levels 40 mm G.I. pipe for tube well including cleaning and priming the tube well.

meter 9 309.30 2783.7 C

Sub total (A+B+C) 8804.55

1549 G.I. pipes 40 mm dia meter 9 220.00 1980.00 D1882 Strainer brass 40 mm dia 1.5 metre long each 2 600.00 1200.00 E

Sub total (D+E) 3180.00

Delhi Jal Board 729 Schedule of Rates 2014 - 2015

Page 471: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

GI pipes and brass strainer can be used 10 times

3180/10 = 318Credit for GI pipes and brass strainer after taking into account depreciation value @ 10%

3180-318 = 2862.00Net cost of boring

8804.55-2862 = 5942.55

Quantity of water required for 4000 m length of 250 mm internal dia pipe 250 mm

Volume of water = π x r2 x hr = 0.13 meterh = 4000 meter

hence, Volume of water =3.1416*(0.125^2)*4000 = 196.35 cum

43248.80 gallon

Assuming that a diesel pump of 5HP capacity can pump @ 3000 gallon per hour 3000 gallon

Hence, no of hours =43248.8/3000 = 14.42 hours

No of days for a shift of 8 hrs14.42/8 = 1.803 day

Consumption of diesel @ 1 ltr/hrHence, qty of diesel required in ltr =

(14.42*1)/1 = 14.42 litre

1235 Cost of Diesel litre 14.42 55.49 800.17 F0011 Hire charges of pump set day 1.803 600.00 1081.50 G

09999 Sundries L.S. 598.292 1.78 1064.96 HSub total (F+G+H) 2946.63

Total 8889.18Add WC @ 1% 1% 29.47

Add CPOH @ 15% 15% 446.41Total cost of boring of pump and running of pump

for 4000 m length 9365.06

cost of filling of 250 mm Ø water main for 1 meter 2.34

Say 2.40

5.12.1.5 300 mm dia pipe

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

Detail of cost for 300 mm dia and 4000 meter length of water main

Cost of boring with 100 mm dia casing pipe

18.42

Boring with 100 mm dia casing pipe for tube well in all soils except ordinary hard rocks requiring blasting including removing the casing pipe after the tube well is lowered and tested

18.42.1 Upto 6 metres depth meter 6 323.05 1938.318.42.2 Beyond 6 m and upto 12 m depth meter 6 383.60 2301.6

Total 4239.9 A

Delhi Jal Board 730 Schedule of Rates 2014 - 2015

Page 472: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

18.43Providing and placing in position filters of 40 mm diameter G.I. pipe with brass strainer of approved quality.

meter 3 593.65 1780.95 B

18.44Providing and fixing to filter and lowering to proper levels 40 mm G.I. pipe for tube well including cleaning and priming the tube well.

meter 9 309.30 2783.7 C

Sub total (A+B+C) 8804.55

1549 G.I. pipes 40 mm dia meter 9 220.00 1980.00 D1882 Strainer brass 40 mm dia 1.5 metre long each 2 600.00 1200.00 E

Sub total (D+E) 3180.00

GI pipes and brass strainer can be used 10 times

3180/10 = 318Credit for GI pipes and brass strainer after taking into account depreciation value @ 10%

3180-318 = 2862.00Net cost of boring

8804.55-2862 = 5942.55

Quantity of water required for 4000 m length of 300 mm internal dia pipe 300 mm

Volume of water = π x r2 x hr = 0.15 meterh = 4000 meter

hence, Volume of water =3.1416*(0.15^2)*4000 = 282.74 cum

62278.27 gallon

Assuming that a diesel pump of 5HP capacity can pump @ 3000 gallon per hour 3000 gallon

Hence, no of hours =62278.27/3000 = 20.76 hours

No of days for a shift of 8 hrs20.76/8 = 2.595 day

Consumption of diesel @ 1 ltr/hrHence, qty of diesel required in ltr =

(20.76*1)/1 = 20.76 litre

1235 Cost of Diesel litre 20.76 55.49 1151.97 F0011 Hire charges of pump set day 2.595 600.00 1557.00 G

09999 Sundries L.S. 598.292 1.78 1064.96 HSub total (F+G+H) 3773.93

Total 9716.48Add WC @ 1% 1% 37.74

Add CPOH @ 15% 15% 571.75Total cost of boring of pump and running of pump

for 4000 m length 10325.97

cost of filling of 300 mm Ø water main for 1 meter 2.58

Say 2.60

5.12.1.6 350 mm dia pipe

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

Detail of cost for 350 mm dia and 4000 meter length of water main

Delhi Jal Board 731 Schedule of Rates 2014 - 2015

Page 473: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

Cost of boring with 100 mm dia casing pipe

18.42

Boring with 100 mm dia casing pipe for tube well in all soils except ordinary hard rocks requiring blasting including removing the casing pipe after the tube well is lowered and tested

18.42.1 Upto 6 metres depth meter 6 323.05 1938.318.42.2 Beyond 6 m and upto 12 m depth meter 6 383.60 2301.6

Total 4239.9 A

18.43Providing and placing in position filters of 40 mm diameter G.I. pipe with brass strainer of approved quality.

meter 3 593.65 1780.95 B

18.44Providing and fixing to filter and lowering to proper levels 40 mm G.I. pipe for tube well including cleaning and priming the tube well.

meter 9 309.30 2783.7 C

Sub total (A+B+C) 8804.55

1549 G.I. pipes 40 mm dia meter 9 220.00 1980.00 D1882 Strainer brass 40 mm dia 1.5 metre long each 2 600.00 1200.00 E

Sub total (D+E) 3180.00

GI pipes and brass strainer can be used 10 times

3180/10 = 318Credit for GI pipes and brass strainer after taking into account depreciation value @ 10%

3180-318 = 2862.00Net cost of boring

8804.55-2862 = 5942.55

Quantity of water required for 4000 m length of 350 mm internal dia pipe 350 mm

Volume of water = π x r2 x hr = 0.18 meterh = 4000 meter

hence, Volume of water =3.1416*(0.175^2)*4000 = 384.85 cum

84767.64 gallon

Assuming that a diesel pump of 5HP capacity can pump @ 3000 gallon per hour 3000 gallon

Hence, no of hours =84767.64/3000 = 28.26 hours

No of days for a shift of 8 hrs28.26/8 = 3.533 day

Consumption of diesel @ 1 ltr/hrHence, qty of diesel required in ltr =

(28.26*1)/1 = 28.26 litre

1235 Cost of Diesel litre 28.26 55.49 1568.15 F0011 Hire charges of pump set day 3.533 600.00 2119.50 G

09999 Sundries L.S. 598.292 1.78 1064.96 HSub total (F+G+H) 4752.61

Total 10695.16Add WC @ 1% 1% 47.53

Add CPOH @ 15% 15% 720.02Total cost of boring of pump and running of pump

for 4000 m length 11462.70

cost of filling of 350 mm Ø water main for 1 meter 2.87

Delhi Jal Board 732 Schedule of Rates 2014 - 2015

Page 474: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

Say 2.90

5.12.1.7 400 mm dia pipe

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

Detail of cost for 400 mm dia and 4000 meter length of water main

Cost of boring with 100 mm dia casing pipe

18.42

Boring with 100 mm dia casing pipe for tube well in all soils except ordinary hard rocks requiring blasting including removing the casing pipe after the tube well is lowered and tested

18.42.1 Upto 6 metres depth meter 6 323.05 1938.318.42.2 Beyond 6 m and upto 12 m depth meter 6 383.60 2301.6

Total 4239.9 A

18.43Providing and placing in position filters of 40 mm diameter G.I. pipe with brass strainer of approved quality.

meter 3 593.65 1780.95 B

18.44Providing and fixing to filter and lowering to proper levels 40 mm G.I. pipe for tube well including cleaning and priming the tube well.

meter 9 309.30 2783.7 C

Sub total (A+B+C) 8804.55

1549 G.I. pipes 40 mm dia meter 9 220.00 1980.00 D1882 Strainer brass 40 mm dia 1.5 metre long each 2 600.00 1200.00 E

Sub total (D+E) 3180.00

GI pipes and brass strainer can be used 10 times

3180/10 = 318Credit for GI pipes and brass strainer after taking into account depreciation value @ 10%

3180-318 = 2862.00Net cost of boring

8804.55-2862 = 5942.55

Quantity of water required for 4000 m length of 400 mm internal dia pipe 400 mm

Volume of water = π x r2 x hr = 0.20 meterh = 4000 meter

hence, Volume of water =3.1416*(0.2^2)*4000 = 502.65 cum

110716.92 gallon

Assuming that a diesel pump of 5HP capacity can pump @ 3000 gallon per hour 3000 gallon

Hence, no of hours =110716.92/3000 = 36.91 hours

No of days for a shift of 8 hrs36.91/8 = 4.614 day

Consumption of diesel @ 1 ltr/hrHence, qty of diesel required in ltr =

(36.91*1)/1 = 36.91 litre

1235 Cost of Diesel litre 36.91 55.49 2048.14 F0011 Hire charges of pump set day 4.614 600.00 2768.25 G

Delhi Jal Board 733 Schedule of Rates 2014 - 2015

Page 475: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

09999 Sundries L.S. 598.292 1.78 1064.96 HSub total (F+G+H) 5881.35

Total 11823.90Add WC @ 1% 1% 58.81

Add CPOH @ 15% 15% 891.02Total cost of boring of pump and running of pump

for 4000 m length 12773.73

cost of filling of 400 mm Ø water main for 1 meter 3.19

Say 3.20

5.12.1.8 450 mm dia pipe

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

Detail of cost for 450 mm dia and 4000 meter length of water main

Cost of boring with 100 mm dia casing pipe

18.42

Boring with 100 mm dia casing pipe for tube well in all soils except ordinary hard rocks requiring blasting including removing the casing pipe after the tube well is lowered and tested

18.42.1 Upto 6 metres depth meter 6 323.05 1938.318.42.2 Beyond 6 m and upto 12 m depth meter 6 383.60 2301.6

Total 4239.9 A

18.43Providing and placing in position filters of 40 mm diameter G.I. pipe with brass strainer of approved quality.

meter 3 593.65 1780.95 B

18.44Providing and fixing to filter and lowering to proper levels 40 mm G.I. pipe for tube well including cleaning and priming the tube well.

meter 9 309.30 2783.7 C

Sub total (A+B+C) 8804.55

1549 G.I. pipes 40 mm dia meter 9 220.00 1980.00 D1882 Strainer brass 40 mm dia 1.5 metre long each 2 600.00 1200.00 E

Sub total (D+E) 3180.00

GI pipes and brass strainer can be used 10 times

3180/10 = 318Credit for GI pipes and brass strainer after taking into account depreciation value @ 10%

3180-318 = 2862.00Net cost of boring

8804.55-2862 = 5942.55

Quantity of water required for 4000 m length of 450 mm internal dia pipe 450 mm

Volume of water = π x r2 x hr = 0.23 meterh = 4000 meter

hence, Volume of water =3.1416*(0.225^2)*4000 = 636.17 cum

140126.10 gallon

Assuming that a diesel pump of 5HP capacity can pump @ 3000 gallon per hour 3000 gallon

Hence, no of hours =140126.1/3000 = 46.71 hours

No of days for a shift of 8 hrs

Delhi Jal Board 734 Schedule of Rates 2014 - 2015

Page 476: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

46.71/8 = 5.839 day

Consumption of diesel @ 1 ltr/hrHence, qty of diesel required in ltr =

(46.71*1)/1 = 46.71 litre

1235 Cost of Diesel litre 46.71 55.49 2591.94 F0011 Hire charges of pump set day 5.839 600.00 3503.25 G

09999 Sundries L.S. 598.292 1.78 1064.96 HSub total (F+G+H) 7160.15

Total 13102.70Add WC @ 1% 1% 71.60

Add CPOH @ 15% 15% 1084.76Total cost of boring of pump and running of pump

for 4000 m length 14259.06

cost of filling of 450 mm Ø water main for 1 meter 3.56

Say 3.60

5.12.1.9 500 mm dia pipe

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

Detail of cost for 500 mm dia and 4000 meter length of water main

Cost of boring with 100 mm dia casing pipe

18.42

Boring with 100 mm dia casing pipe for tube well in all soils except ordinary hard rocks requiring blasting including removing the casing pipe after the tube well is lowered and tested

18.42.1 Upto 6 metres depth meter 6 323.05 1938.318.42.2 Beyond 6 m and upto 12 m depth meter 6 383.60 2301.6

Total 4239.9 A

18.43Providing and placing in position filters of 40 mm diameter G.I. pipe with brass strainer of approved quality.

meter 3 593.65 1780.95 B

18.44Providing and fixing to filter and lowering to proper levels 40 mm G.I. pipe for tube well including cleaning and priming the tube well.

meter 9 309.30 2783.7 C

Sub total (A+B+C) 8804.55

1549 G.I. pipes 40 mm dia meter 9 220.00 1980.00 D1882 Strainer brass 40 mm dia 1.5 metre long each 2 600.00 1200.00 E

Sub total (D+E) 3180.00

GI pipes and brass strainer can be used 10 times

3180/10 = 318Credit for GI pipes and brass strainer after taking into account depreciation value @ 10%

3180-318 = 2862.00Net cost of boring

8804.55-2862 = 5942.55

Quantity of water required for 4000 m length of 500 mm internal dia pipe 500 mm

Volume of water = π x r2 x hr = 0.25 meterh = 4000 meter

hence, Volume of water =

Delhi Jal Board 735 Schedule of Rates 2014 - 2015

Page 477: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

3.1416*(0.25^2)*4000 = 785.40 cum172995.19 gallon

Assuming that a diesel pump of 5HP capacity can pump @ 3000 gallon per hour 3000 gallon

Hence, no of hours =172995.19/3000 = 57.67 hours

No of days for a shift of 8 hrs57.67/8 = 7.209 day

Consumption of diesel @ 1 ltr/hrHence, qty of diesel required in ltr =

(57.67*1)/1 = 57.67 litre

1235 Cost of Diesel litre 57.67 55.49 3200.11 F0011 Hire charges of pump set day 7.209 600.00 4325.25 G

09999 Sundries L.S. 598.292 1.78 1064.96 HSub total (F+G+H) 8590.32

Total 14532.87Add WC @ 1% 1% 85.90

Add CPOH @ 15% 15% 1301.43Total cost of boring of pump and running of pump

for 4000 m length 15920.20

cost of filling of 500 mm Ø water main for 1 meter 3.98

Say 4.00

5.12.1.10 600 mm dia pipe

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

Detail of cost for 600 mm dia and 4000 meter length of water main

Cost of boring with 100 mm dia casing pipe

18.42

Boring with 100 mm dia casing pipe for tube well in all soils except ordinary hard rocks requiring blasting including removing the casing pipe after the tube well is lowered and tested

18.42.1 Upto 6 metres depth meter 6 323.05 1938.318.42.2 Beyond 6 m and upto 12 m depth meter 6 383.60 2301.6

Total 4239.9 A

18.43Providing and placing in position filters of 40 mm diameter G.I. pipe with brass strainer of approved quality.

meter 3 593.65 1780.95 B

18.44Providing and fixing to filter and lowering to proper levels 40 mm G.I. pipe for tube well including cleaning and priming the tube well.

meter 9 309.30 2783.7 C

Sub total (A+B+C) 8804.55

1549 G.I. pipes 40 mm dia meter 9 220.00 1980.00 D1882 Strainer brass 40 mm dia 1.5 metre long each 2 600.00 1200.00 E

Sub total (D+E) 3180.00

GI pipes and brass strainer can be used 10 times

3180/10 = 318Credit for GI pipes and brass strainer after taking into account depreciation value @ 10%

3180-318 = 2862.00Net cost of boring

Delhi Jal Board 736 Schedule of Rates 2014 - 2015

Page 478: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

8804.55-2862 = 5942.55

Quantity of water required for 4000 m length of 600 mm internal dia pipe 600 mm

Volume of water = π x r2 x hr = 0.30 meterh = 4000 meter

hence, Volume of water =3.1416*(0.3^2)*4000 = 1130.97 cum

249113.07 gallon

Assuming that a diesel pump of 5HP capacity can pump @ 3000 gallon per hour 3000 gallon

Hence, no of hours =249113.07/3000 = 83.04 hours

No of days for a shift of 8 hrs83.04/8 = 10.380 day

Consumption of diesel @ 1 ltr/hrHence, qty of diesel required in ltr =

(83.04*1)/1 = 83.04 litre

1235 Cost of Diesel litre 83.04 55.49 4607.89 F0011 Hire charges of pump set day 10.380 600.00 6228.00 G

09999 Sundries L.S. 598.292 1.78 1064.96 HSub total (F+G+H) 11900.85

Total 17843.40Add WC @ 1% 1% 119.01

Add CPOH @ 15% 15% 1802.98Total cost of boring of pump and running of pump

for 4000 m length 19765.39

cost of filling of 600 mm Ø water main for 1 meter 4.94

Say 5.00

5.12.1.11 700 mm dia pipe

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

Detail of cost for 700 mm dia and 4000 meter length of water main

Cost of boring with 100 mm dia casing pipe

18.42

Boring with 100 mm dia casing pipe for tube well in all soils except ordinary hard rocks requiring blasting including removing the casing pipe after the tube well is lowered and tested

18.42.1 Upto 6 metres depth meter 6 323.05 1938.318.42.2 Beyond 6 m and upto 12 m depth meter 6 383.60 2301.6

Total 4239.9 A

18.43Providing and placing in position filters of 40 mm diameter G.I. pipe with brass strainer of approved quality.

meter 3 593.65 1780.95 B

18.44Providing and fixing to filter and lowering to proper levels 40 mm G.I. pipe for tube well including cleaning and priming the tube well.

meter 9 309.30 2783.7 C

Sub total (A+B+C) 8804.55

1549 G.I. pipes 40 mm dia meter 9 220.00 1980.00 D

Delhi Jal Board 737 Schedule of Rates 2014 - 2015

Page 479: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

1882 Strainer brass 40 mm dia 1.5 metre long each 2 600.00 1200.00 ESub total (D+E) 3180.00

GI pipes and brass strainer can be used 10 times

3180/10 = 318Credit for GI pipes and brass strainer after taking into account depreciation value @ 10%

3180-318 = 2862.00Net cost of boring

8804.55-2862 = 5942.55

Quantity of water required for 4000 m length of 700 mm internal dia pipe 700 mm

Volume of water = π x r2 x hr = 0.35 meterh = 4000 meter

hence, Volume of water =3.1416*(0.35^2)*4000 = 1539.38 cum

339070.57 gallon

Assuming that a diesel pump of 5HP capacity can pump @ 3000 gallon per hour 3000 gallon

Hence, no of hours =339070.57/3000 = 113.03 hours

No of days for a shift of 8 hrs113.03/8 = 14.129 day

Consumption of diesel @ 1 ltr/hrHence, qty of diesel required in ltr =

(113.03*1)/1 = 113.03 litre

1235 Cost of Diesel litre 113.03 55.49 6272.03 F0011 Hire charges of pump set day 14.129 600.00 8477.25 G

09999 Sundries L.S. 598.292 1.78 1064.96 HSub total (F+G+H) 15814.24

Total 21756.79Add WC @ 1% 1% 158.14

Add CPOH @ 15% 15% 2395.86Total cost of boring of pump and running of pump

for 4000 m length 24310.80

cost of filling of 700 mm Ø water main for 1 meter 6.08

Say 6.10

5.12.1.12 800 mm dia pipe

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

Detail of cost for 800 mm dia and 4000 meter length of water main

Cost of boring with 100 mm dia casing pipe

18.42

Boring with 100 mm dia casing pipe for tube well in all soils except ordinary hard rocks requiring blasting including removing the casing pipe after the tube well is lowered and tested

18.42.1 Upto 6 metres depth meter 6 323.05 1938.318.42.2 Beyond 6 m and upto 12 m depth meter 6 383.60 2301.6

Total 4239.9 A

Delhi Jal Board 738 Schedule of Rates 2014 - 2015

Page 480: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

18.43Providing and placing in position filters of 40 mm diameter G.I. pipe with brass strainer of approved quality.

meter 3 593.65 1780.95 B

18.44Providing and fixing to filter and lowering to proper levels 40 mm G.I. pipe for tube well including cleaning and priming the tube well.

meter 9 309.30 2783.7 C

Sub total (A+B+C) 8804.55

1549 G.I. pipes 40 mm dia meter 9 220.00 1980.00 D1882 Strainer brass 40 mm dia 1.5 metre long each 2 600.00 1200.00 E

Sub total (D+E) 3180.00

GI pipes and brass strainer can be used 10 times

3180/10 = 318Credit for GI pipes and brass strainer after taking into account depreciation value @ 10%

3180-318 = 2862.00Net cost of boring

8804.55-2862 = 5942.55

Quantity of water required for 4000 m length of 800 mm internal dia pipe 800 mm

Volume of water = π x r2 x hr = 0.40 meterh = 4000 meter

hence, Volume of water =3.1416*(0.4^2)*4000 = 2010.62 cum

442867.69 gallon

Assuming that a diesel pump of 5HP capacity can pump @ 3000 gallon per hour 3000 gallon

Hence, no of hours =442867.69/3000 = 147.63 hours

No of days for a shift of 8 hrs147.63/8 = 18.454 day

Consumption of diesel @ 1 ltr/hrHence, qty of diesel required in ltr =

(147.63*1)/1 = 147.63 litre

1235 Cost of Diesel litre 147.63 55.49 8191.99 F0011 Hire charges of pump set day 18.454 600.00 11072.25 G

09999 Sundries L.S. 598.292 1.78 1064.96 HSub total (F+G+H) 20329.20

Total 26271.75Add WC @ 1% 1% 203.29

Add CPOH @ 15% 15% 3079.87Total cost of boring of pump and running of pump

for 4000 m length 29554.91

cost of filling of 800 mm Ø water main for 1 meter 7.39

Say 7.40

5.12.1.13 900 mm dia pipe

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

Detail of cost for 900 mm dia and 4000 meter length of water main

Delhi Jal Board 739 Schedule of Rates 2014 - 2015

Page 481: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

Cost of boring with 100 mm dia casing pipe

18.42

Boring with 100 mm dia casing pipe for tube well in all soils except ordinary hard rocks requiring blasting including removing the casing pipe after the tube well is lowered and tested

18.42.1 Upto 6 metres depth meter 6 323.05 1938.318.42.2 Beyond 6 m and upto 12 m depth meter 6 383.60 2301.6

Total 4239.9 A

18.43Providing and placing in position filters of 40 mm diameter G.I. pipe with brass strainer of approved quality.

meter 3 593.65 1780.95 B

18.44Providing and fixing to filter and lowering to proper levels 40 mm G.I. pipe for tube well including cleaning and priming the tube well.

meter 9 309.30 2783.7 C

Sub total (A+B+C) 8804.55

1549 G.I. pipes 40 mm dia meter 9 220.00 1980.00 D1882 Strainer brass 40 mm dia 1.5 metre long each 2 600.00 1200.00 E

Sub total (D+E) 3180.00

GI pipes and brass strainer can be used 10 times

3180/10 = 318Credit for GI pipes and brass strainer after taking into account depreciation value @ 10%

3180-318 = 2862.00Net cost of boring

8804.55-2862 = 5942.55

Quantity of water required for 4000 m length of 900 mm internal dia pipe 900 mm

Volume of water = π x r2 x hr = 0.45 meterh = 4000 meter

hence, Volume of water =3.1416*(0.45^2)*4000 = 2544.69 cum

560504.42 gallon

Assuming that a diesel pump of 5HP capacity can pump @ 3000 gallon per hour 3000 gallon

Hence, no of hours =560504.42/3000 = 186.84 hours

No of days for a shift of 8 hrs186.84/8 = 23.355 day

Consumption of diesel @ 1 ltr/hrHence, qty of diesel required in ltr =

(186.84*1)/1 = 186.84 litre

1235 Cost of Diesel litre 186.84 55.49 10367.75 F0011 Hire charges of pump set day 23.355 600.00 14013.00 G

09999 Sundries L.S. 598.292 1.78 1064.96 HSub total (F+G+H) 25445.71

Total 31388.26Add WC @ 1% 1% 254.46

Add CPOH @ 15% 15% 3855.03Total cost of boring of pump and running of pump

for 4000 m length 35497.74

cost of filling of 900 mm Ø water main for 1 meter 8.87

Delhi Jal Board 740 Schedule of Rates 2014 - 2015

Page 482: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

Say 8.90

5.12.1.14 1000 mm dia pipe

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

Detail of cost for 1000 mm dia and 4000 meter length of water main

Cost of boring with 100 mm dia casing pipe

18.42

Boring with 100 mm dia casing pipe for tube well in all soils except ordinary hard rocks requiring blasting including removing the casing pipe after the tube well is lowered and tested

18.42.1 Upto 6 metres depth meter 6 323.05 1938.318.42.2 Beyond 6 m and upto 12 m depth meter 6 383.60 2301.6

Total 4239.9 A

18.43Providing and placing in position filters of 40 mm diameter G.I. pipe with brass strainer of approved quality.

meter 3 593.65 1780.95 B

18.44Providing and fixing to filter and lowering to proper levels 40 mm G.I. pipe for tube well including cleaning and priming the tube well.

meter 9 309.30 2783.7 C

Sub total (A+B+C) 8804.55

1549 G.I. pipes 40 mm dia meter 9 220.00 1980.00 D1882 Strainer brass 40 mm dia 1.5 metre long each 2 600.00 1200.00 E

Sub total (D+E) 3180.00

GI pipes and brass strainer can be used 10 times

3180/10 = 318Credit for GI pipes and brass strainer after taking into account depreciation value @ 10%

3180-318 = 2862.00Net cost of boring

8804.55-2862 = 5942.55

Quantity of water required for 4000 m length of 1000 mm internal dia pipe 1000 mm

Volume of water = π x r2 x hr = 0.50 meterh = 4000 meter

hence, Volume of water =3.1416*(0.5^2)*4000 = 3141.59 cum

691980.76 gallon

Assuming that a diesel pump of 5HP capacity can pump @ 3000 gallon per hour 3000 gallon

Hence, no of hours =691980.76/3000 = 230.67 hours

No of days for a shift of 8 hrs230.67/8 = 28.834 day

Consumption of diesel @ 1 ltr/hrHence, qty of diesel required in ltr =

(230.67*1)/1 = 230.67 litre

1235 Cost of Diesel litre 230.67 55.49 12799.88 F0011 Hire charges of pump set day 28.834 600.00 17300.25 G

Delhi Jal Board 741 Schedule of Rates 2014 - 2015

Page 483: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

09999 Sundries L.S. 598.292 1.78 1064.96 HSub total (F+G+H) 31165.09

Total 37107.64Add WC @ 1% 1% 311.65

Add CPOH @ 15% 15% 4721.51Total cost of boring of pump and running of pump

for 4000 m length 42140.80

cost of filling of 1000 mm Ø water main for 1 meter 10.54

Say 10.60

5.12.1.15 1100 mm dia pipe

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

Detail of cost for 1100 mm dia and 4000 meter length of water main

Cost of boring with 100 mm dia casing pipe

18.42

Boring with 100 mm dia casing pipe for tube well in all soils except ordinary hard rocks requiring blasting including removing the casing pipe after the tube well is lowered and tested

18.42.1 Upto 6 metres depth meter 6 323.05 1938.318.42.2 Beyond 6 m and upto 12 m depth meter 6 383.60 2301.6

Total 4239.9 A

18.43Providing and placing in position filters of 40 mm diameter G.I. pipe with brass strainer of approved quality.

meter 3 593.65 1780.95 B

18.44Providing and fixing to filter and lowering to proper levels 40 mm G.I. pipe for tube well including cleaning and priming the tube well.

meter 9 309.30 2783.7 C

Sub total (A+B+C) 8804.55

1549 G.I. pipes 40 mm dia meter 9 220.00 1980.00 D1882 Strainer brass 40 mm dia 1.5 metre long each 2 600.00 1200.00 E

Sub total (D+E) 3180.00

GI pipes and brass strainer can be used 10 times

3180/10 = 318Credit for GI pipes and brass strainer after taking into account depreciation value @ 10%

3180-318 = 2862.00Net cost of boring

8804.55-2862 = 5942.55

Quantity of water required for 4000 m length of 1100 mm internal dia pipe 1100 mm

Volume of water = π x r2 x hr = 0.55 meterh = 4000 meter

hence, Volume of water =3.1416*(0.55^2)*4000 = 3801.33 cum

837296.72 gallon

Assuming that a diesel pump of 5HP capacity can pump @ 3000 gallon per hour 3000 gallon

Hence, no of hours =837296.72/3000 = 279.10 hours

No of days for a shift of 8 hrs

Delhi Jal Board 742 Schedule of Rates 2014 - 2015

Page 484: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

279.1/8 = 34.888 day

Consumption of diesel @ 1 ltr/hrHence, qty of diesel required in ltr =

(279.1*1)/1 = 279.1 litre

1235 Cost of Diesel litre 279.1 55.49 15487.26 F0011 Hire charges of pump set day 34.888 600.00 20932.50 G

09999 Sundries L.S. 598.292 1.78 1064.96 HSub total (F+G+H) 37484.72

Total 43427.27Add WC @ 1% 1% 374.85

Add CPOH @ 15% 15% 5678.93Total cost of boring of pump and running of pump

for 4000 m length 49481.05

cost of filling of 1100 mm Ø water main for 1 meter 12.37

Say 12.40

5.12.1.16 1200 mm dia pipe

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

Detail of cost for 1200 mm dia and 4000 meter length of water main

Cost of boring with 100 mm dia casing pipe

18.42

Boring with 100 mm dia casing pipe for tube well in all soils except ordinary hard rocks requiring blasting including removing the casing pipe after the tube well is lowered and tested

18.42.1 Upto 6 metres depth meter 6 323.05 1938.318.42.2 Beyond 6 m and upto 12 m depth meter 6 383.60 2301.6

Total 4239.9 A

18.43Providing and placing in position filters of 40 mm diameter G.I. pipe with brass strainer of approved quality.

meter 3 593.65 1780.95 B

18.44Providing and fixing to filter and lowering to proper levels 40 mm G.I. pipe for tube well including cleaning and priming the tube well.

meter 9 309.30 2783.7 C

Sub total (A+B+C) 8804.55

1549 G.I. pipes 40 mm dia meter 9 220.00 1980.00 D1882 Strainer brass 40 mm dia 1.5 metre long each 2 600.00 1200.00 E

Sub total (D+E) 3180.00

GI pipes and brass strainer can be used 10 times

3180/10 = 318Credit for GI pipes and brass strainer after taking into account depreciation value @ 10%

3180-318 = 2862.00Net cost of boring

8804.55-2862 = 5942.55

Quantity of water required for 4000 m length of 1200 mm internal dia pipe 1200 mm

Volume of water = π x r2 x hr = 0.60 meterh = 4000 meter

hence, Volume of water =

Delhi Jal Board 743 Schedule of Rates 2014 - 2015

Page 485: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

3.1416*(0.6^2)*4000 = 4523.89 cum996452.30 gallon

Assuming that a diesel pump of 5HP capacity can pump @ 3000 gallon per hour 3000 gallon

Hence, no of hours =996452.3/3000 = 332.16 hours

No of days for a shift of 8 hrs332.16/8 = 41.520 day

Consumption of diesel @ 1 ltr/hrHence, qty of diesel required in ltr =

(332.16*1)/1 = 332.16 litre

1235 Cost of Diesel litre 332.16 55.49 18431.56 F0011 Hire charges of pump set day 41.520 600.00 24912.00 G

09999 Sundries L.S. 598.292 1.78 1064.96 HSub total (F+G+H) 44408.52

Total 50351.07Add WC @ 1% 1% 444.09

Add CPOH @ 15% 15% 6727.89Total cost of boring of pump and running of pump

for 4000 m length 57523.04

cost of filling of 1200 mm Ø water main for 1 meter 14.38

Say 14.40

5.12.1.17 1400 mm dia pipe

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

Detail of cost for 1400 mm dia and 4000 meter length of water main

Cost of boring with 100 mm dia casing pipe

18.42

Boring with 100 mm dia casing pipe for tube well in all soils except ordinary hard rocks requiring blasting including removing the casing pipe after the tube well is lowered and tested

18.42.1 Upto 6 metres depth meter 6 323.05 1938.318.42.2 Beyond 6 m and upto 12 m depth meter 6 383.60 2301.6

Total 4239.9 A

18.43Providing and placing in position filters of 40 mm diameter G.I. pipe with brass strainer of approved quality.

meter 3 593.65 1780.95 B

18.44Providing and fixing to filter and lowering to proper levels 40 mm G.I. pipe for tube well including cleaning and priming the tube well.

meter 9 309.30 2783.7 C

Sub total (A+B+C) 8804.55

1549 G.I. pipes 40 mm dia meter 9 220.00 1980.00 D1882 Strainer brass 40 mm dia 1.5 metre long each 2 600.00 1200.00 E

Sub total (D+E) 3180.00

GI pipes and brass strainer can be used 10 times

3180/10 = 318Credit for GI pipes and brass strainer after taking into account depreciation value @ 10%

3180-318 = 2862.00Net cost of boring

Delhi Jal Board 744 Schedule of Rates 2014 - 2015

Page 486: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

8804.55-2862 = 5942.55

Quantity of water required for 4000 m length of 1400 mm internal dia pipe 1400 mm

Volume of water = π x r2 x hr = 0.70 meterh = 4000 meter

hence, Volume of water =3.1416*(0.7^2)*4000 = 6157.52 cum

1356282.29 gallon

Assuming that a diesel pump of 5HP capacity can pump @ 3000 gallon per hour 3000 gallon

Hence, no of hours =1356282.29/3000 = 452.10 hours

No of days for a shift of 8 hrs452.1/8 = 56.513 day

Consumption of diesel @ 1 ltr/hrHence, qty of diesel required in ltr =

(452.1*1)/1 = 452.1 litre

1235 Cost of Diesel litre 452.1 55.49 25087.03 F0011 Hire charges of pump set day 56.513 600.00 33907.50 G

09999 Sundries L.S. 598.292 1.78 1064.96 HSub total (F+G+H) 60059.49

Total 66002.04Add WC @ 1% 1% 600.59

Add CPOH @ 15% 15% 9099.01Total cost of boring of pump and running of pump

for 4000 m length 75701.65

cost of filling of 1400 mm Ø water main for 1 meter 18.93

Say 19.00

5.12.1.18 1500 mm dia pipe

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

Detail of cost for 1500 mm dia and 4000 meter length of water main

Cost of boring with 100 mm dia casing pipe

18.42

Boring with 100 mm dia casing pipe for tube well in all soils except ordinary hard rocks requiring blasting including removing the casing pipe after the tube well is lowered and tested

18.42.1 Upto 6 metres depth meter 6 323.05 1938.318.42.2 Beyond 6 m and upto 12 m depth meter 6 383.60 2301.6

Total 4239.9 A

18.43Providing and placing in position filters of 40 mm diameter G.I. pipe with brass strainer of approved quality.

meter 3 593.65 1780.95 B

18.44Providing and fixing to filter and lowering to proper levels 40 mm G.I. pipe for tube well including cleaning and priming the tube well.

meter 9 309.30 2783.7 C

Sub total (A+B+C) 8804.55

1549 G.I. pipes 40 mm dia meter 9 220.00 1980.00 D

Delhi Jal Board 745 Schedule of Rates 2014 - 2015

Page 487: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Item code Description Unit Qty Rate (INR) Amount (INR) Remark

1882 Strainer brass 40 mm dia 1.5 metre long each 2 600.00 1200.00 ESub total (D+E) 3180.00

GI pipes and brass strainer can be used 10 times

3180/10 = 318Credit for GI pipes and brass strainer after taking into account depreciation value @ 10%

3180-318 = 2862.00Net cost of boring

8804.55-2862 = 5942.55

Quantity of water required for 4000 m length of 1500 mm internal dia pipe 1500 mm

Volume of water = π x r2 x hr = 0.75 meterh = 4000 meter

hence, Volume of water =3.1416*(0.75^2)*4000 = 7068.58 cum

1556956.71 gallon

Assuming that a diesel pump of 5HP capacity can pump @ 3000 gallon per hour 3000 gallon

Hence, no of hours =1556956.71/3000 = 518.99 hours

No of days for a shift of 8 hrs518.99/8 = 64.874 day

Consumption of diesel @ 1 ltr/hrHence, qty of diesel required in ltr =

(518.99*1)/1 = 518.99 litre

1235 Cost of Diesel litre 518.99 55.49 28798.76 F0011 Hire charges of pump set day 64.874 600.00 38924.25 G

09999 Sundries L.S. 598.292 1.78 1064.96 HSub total (F+G+H) 68787.97

Total 74730.52Add WC @ 1% 1% 687.88

Add CPOH @ 15% 15% 10421.38Total cost of boring of pump and running of pump

for 4000 m length 85839.77

cost of filling of 1500 mm Ø water main for 1 meter 21.46

Say 21.50

Delhi Jal Board 746 Schedule of Rates 2014 - 2015

Page 488: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

5.14

ED CST/ST F,I,O & T INST & COMM PROFIT WCT

0% 0% 0% 0% 0% 0%

5.14.1 Ultrasonic testing of welded joints by our NDT level IIqualified Engineer's and reporting at your site. Rmt 120.27 0 0 0 120.27 0 0 0 120.27

Quotation_Volume III_Pg

no 208

ULTRASONIC TESTING

RemarksITEM CODE DESCRIPTION UNIT BASIC

COST (INR)

SUB TOTAL (INR)

AMOUNT (INR)

Delhi Jal Board 751 Schedule of Rates 2014-2015

Page 489: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

5.15 RE-DEVELOPMENT AND DESILTING OF RCC RANNEY WELL

NOTE: Providing cost of dummy plate will be paid seperatelyAll work will be completed as per direction of Engineer-In-Charge.

NOTE: Input based on Rainey Well, No 3, Palla, New DelhiDiameter of Rainey Well 5 meter Depth of the Rainey Well 30 meter No of Radials 20 Nos

5.15.1 REDEVELOPMENT AND DESILTING OF RANNEY WELL

5.15.1.1

Item Code Description Unit No Qty Rate (INR) Amount (INR)

Detail of cost for 30 day

(a) Hiring charges of 62 KVA DG day / shift 2 30 769.24 46154.40Quotation

Enclosed_please refer pg no 01 to 05

(a) As confirmed by contractor; 2 Nos of DG = 1 Working + 1 Stand by (b) Hiring charges of the DG without fuel has been considered for 2 no's

DSR'2014_Item no 0157 Operator day 1 30 435 13050.00

DSR'2014_Item no 0161 Operator helper day 1 30 329 9870.00

(b) Fuel Charges

Consider 4 hours working per day,

(c) 4 hours / day working has been considered for operation of DG in the redevelopment work of ranney well

(d) 8 ltr/hour

A) Cleaning of valves fixed to the radials and closing the valves.B) Desilting of Ranney Wells upto floor level and keeping below the valve level, using mechanical crab and bucket.

C) Open the radial valves once at time and clean the radials using compressing 210cfm capacity and closing the valves after cleaning to ensure the radials are free from sand and silt similarly operation will be conducted on each and every radials by opening the valve jetting the radial and closing the valve.

D) Once step (C) has been completed the same procedure adopted in step (C) will be carried out again to ensure that no silt had into any radial while jetting its adjacent radial during step (C)

F) If the valves are found that they cannot be closed or if it is observed that stone and sand are seen coming into Ranney wells from radial during step (C) and step (D) these radials will be permanently blocked by the welding a dummy plate to the face .

E) De-silt the well again to remove all silt/sand collected in the well during two step (C) and step (D)

(G) RE-erection of VT pumps and re-commissioning.

Hiring of 62 KVA heavy duty D.G. Set as required at site with fuel & operator. (min of 4 hour and max as per site required)

Reference / Remark

Diesel consumption = 8 litre / hour(d) 8 ltr/hour consumption of diesel has been considered.

Hence, Cost of Diesel

DSR'2014_Item no 1235 1 No*30 days*4 hour*8 litre* Rs. 55.49= Rs.53270.4 litre 1 960 55.49 53270.4

Diesel consumption is given in quotation of hiring charges of DG

(e) Fuel consumption has been considered for 1 no of working DG only as second DG will be on stand by basis.

Total = 122344.80 (A)Add CPOH @ 15% = 15% 18351.72 (B) = 15% * (A)

Hiring and running charges of DG including operating staff, fuel, etc. for 30 days redevelopment work at Ranney Well = 140696.52 (C) = (A+B)

Hiring and running charges of DG including operating staff, fuel, etc. for 1 days redevelopment work at Ranney Well = 4689.89 (D) = (C) / 30

Hiring and running charges of DG including operating staff, fuel, etc. for 1 hour redevelopment work at Ranney Well = 586.24 (E) = (D) / 8

Say = 586.20 Per Hour

5.15.1.2

Item Code Description Unit No Qty Rate (INR) Amount (INR)

Detail of cost for 10 days effective working for 30 days redevelopment work of Ranney Well

(a) Hiring and running charges of of Air Compressor (210 cfm) with Operating staff, Fuel and Miscellaneous items, etc

Consider 10 days effective working of the Air compressor (210 cfm) for 30 days redevelopment work of ranney well,

For 10 days working,

Reference / Remark

Hiring of Air compressor (210 cfm) as required at site with fuel & operator for desilting of laterals / radials. (min of 8 hour and max as per site required)

Delhi Jal BoardSchedule of rates'2014-2015- Water supply works

Page 490: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Item Code Description Unit No Qty Rate (INR) Amount (INR) Reference / Remark

DSR 2014_0058 10 days*8 hours* Rs.325 = Rs. 26000 hour 1 80.00 325.00 26000.00

8 hours / day working has been considered for operation of Air Compressor (210 cfm) in the redevelopment work of ranney well

Total 26000.00 (A)Add CPOH @ 15% 15% 3900.00 (B) = 15% (A)

Hiring and running charges of 80 hours effective working of Air Compressor (210 cfm) with Operating staff, Fuel and

Miscellaneous items, etc for 30 days redevelopment work of Ranney Well =

29900.00 (C) = (A+B)

For 1 hour effective working = 373.75 (D) = (C) /80Say = 373.80 Per Hour

5.15.1.3

Code No Description Unit No Qty Rate (INR) Amount (INR)

Detail of cost for 10 days effective working for 30 days redevelopment work of Ranney Well

(a) Diver using diving set(A) SOR PWD 2012_Kerala_item no 52_pg no 15

For 2 year escalation

(2013,2014) = Rs. 563*(1+0.0667)^2 = Rs. 640.61 day 2.0 10 640.61 12812.20 (B) ANNEXURE 'B' - pg

no 16

Semi skilled labour day 3.0 10 329.00 9870.00 DSR 2014_0114Skilled labour day 3.0 10 363.00 10890.00 DSR 2014_0128

Total = 33572.20 (A)Add CPOH @ 15% = 15% 5035.83 (B) = 15% (A)

Hiring charges of diver for 10 days effective working with semi skilled labour, skilled labour, oxygen cylinder for 30 days

redevelopment work of ranney well =38608.03 (C) = (A+B)

For 1 day effective working = 3860.81 (D) = (C) / 10For 1 hour effective working = 482.61 (E) = (D) / 8

Say = 482.60 Per Hour

5.15.1.4

Item Code Description Unit No Qty Rate (INR) Amount (INR)

Detail of cost for 3 days effective working for 30 days redevelopment work of Ranney Well

Hiring of Diver with Head Gear, Oxygen Cylinder, etc for valve maintenance, desilting of radials, etc under ranney well.

8 hours / day working has been considered for

operation of desilting work in the

redevelopment work of ranney well

Dismantling of Existing Verticle Pump and installation of new submersible pump

Reference / Remark

Reference / Remark

redevelopment work of Ranney Well

(a) Dismantling of existing vertical Pump (3 nos) and installation of new submersible pump ( 2 nos)

DSR 2014_0116 Fitter day 1 3.00 435.00 1305.00

DSR 2014_0160 Electrician day 1 3.00 700.00 2100.00

DSR 2014_0161 Helper day 5 3.00 329.00 4935.00

Total 8340.00 (A)Add CPOH @ 15% 15% 1251.00 (B) = 15% (A)

Total cost for 3 days effective working for dismantling of existing vertical Pump (3 nos) and installation of new dewatering

submersible pump (2 nos) for 30 days redevelopment work of Ranney Well =

9591.00 (C) = (A+B)

For 1 day effective working = 3197.00 (D) = (C) / 3For 1 hour effective working = 399.63 (E) = (D) / 8

Say 399.60 Per Hour

5.15.1.5

Item Code Description Unit No Qty Rate (INR) Amount (INR)

Detail of Cost for 30 day redevelopment work of ranney well

(a) Hiring and running charges of Submersible Pump (62 hp) with Operating staff, Fuel and Miscellaneous items, etc

Pg no - 17 -18 day/shift 2 15.00 750.19 22505.70

Total 22505.70 (A)

Add CPOH @ 15% 15% 3375.86 (B) = 15% (A)Hiring and running charges of Submersible Pump (62 hp) with Operating staff, Fuel and Miscellaneous items, etc for 30 days

redevelopment work of ranney well =25881.56 (C) = (A+B)

Reference / Remark

8 hours / day working has been considered for

dismantling o existing pump and installation of new submersible pump in the redevelopment work of ranney well

Hiring and installation of Submersible Pump (62 hp) as required at site with fuel & operator for dewatering of water in ranney well. (min of 8 hour and max as per site required)

Delhi Jal BoardSchedule of rates'2014-2015- Water supply works

Page 491: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Item Code Description Unit No Qty Rate (INR) Amount (INR) Reference / Remark

For 1 day working = 862.72 (D) = (C) / 30

For 1 hour working = 107.84 (E) = (D) / 8

8 hours / day working has been considered for

operation of submersible pump in the redevelopment work of

ranney well

Say 107.80 Per Hour

5.15.1.6

Item Code Description Unit No Qty Rate (INR) Amount (INR)

Detail of cost for 15 days effective working for 30 days redevelopment work of Ranney Well

(a) Hiring and running charges of winch

For 2 year escalation

(2013,2014) = Rs. 345*(1+0.0667)^2 = Rs. 392.56 day/shift 1 15.00 392.56 5888.40

SOR Andhra Pradesh'2012_Item no

67_Irrigation and PH_pg no 20

(b) Labour for desilting of silt from ranney well

0114 Beldar day/shift 1 15.00 329.00 4935.000115 Coolie day/shift 1 15.00 329.00 4935.00

Total 15758.40 (A)Add CPOH @ 15% 15% 2363.76 (B) = 15% (A)

Total for hire and running charges for 15 days effective working of Tripod and Mechanical Winch machine complete with operating

staff, power unit and accessories, etc for 30 days redevelopment work of ranney well =

18122.16 (C) = (A+B)

For 1 day effective working = 1208.15 (D) = (C) / 15

For 1 hour effective working = 151.02 (E) = (D) / 8

8 hours / day working has been considered for operation of hydraulic

winch in the redevelopment work of

ranney wellSay = 151.00 Per Hour

5.15.1.7NOTE: 20% extra shall be considered for work under wet well

Reference / Remark

Hiring of hydraulic winch as required at site with fuel & operator for pulling of desilting bucket, dismantled materials like pipes, valves, etc. From ranney well. (min of 8 hour and max as per site required)

Reference / Remark

Hiring and running chrages of welding machine for welding purpose. (min of 8 hour and max as per site required)

Code No Description Unit No Qty Rate (INR) Amount (INR)

Detail of cost for 5 days effective working for 30 days redevelopment work of Ranney Well

(a) Hiring and running of welding set with electric set, operating staff, miscellaneous items, etc

(a)SOR_MJP'2012_Machinery_item no 6_pg no 23

= Rs. 1100*(1+0.0667)^2 = Rs. 1251.64 day/shift 1 5 1251.63 6258.17 (B) ANNEXURE 'B' - pg no 16

(b) Welder = Rs. 363*(1+0.0667)^2 = Rs. 413.04 day/shift 1 5 413.04 2065.20 (a)SOR_MJP'2012_Mac

hinery_item no 28_pg no 22

Total 8323.37 (A)Add CPOH @ 15% 15% 1248.51 (B) = 15% (A)

Hiring and running for 5 days effective working of welding set with electric set, operating staff, miscellaneous items, etc for 30 days

redevelopment work of ranney well = day/shift 9571.88 (C) = (A+B)

For 1 day effective working = 1914.38 (D) = (C) / 5

For 1 hour effective working = 239.30 (E) = (D) / 8

8 hours / day working has been considered for

operation of welding machine in the

redevelopment work of ranney well

Extra for work under wet well = 20% 47.86 (F) = (E) * 20%20% extra shall be considered for work

under wet wellTotal for 1 hour effective working = 287.16 (G) = (E+F)

Say 287.20 Per Hour

5.15.1.8

Code No Description Unit No Qty Rate (INR) Amount (INR)

Detail of cost for 5 days effective working for 30 days redevelopment work of Ranney Well

NOTE: 20% extra shall be considered for work under wet wellHiring of gas cutter with oxygen & LPG gas cylinder for cutting of structiral steel, pipe, etc. (min of 8 hour and max as per site required)

Reference / Remark

Reference / Remark

Delhi Jal BoardSchedule of rates'2014-2015- Water supply works

Page 492: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Item Code Description Unit No Qty Rate (INR) Amount (INR) Reference / Remark

(a) Hiring and running charges of gas cutter with oxygen cylinder, operating staff, miscellaneous items, etc

By considering 8 working hours / day day/shift 1 5 1144.00 5720.00 Pg no 24 & 25

Total 5720.00 (A)Add CPOH @ 15% 15% 858.00 (B) = 15% (A)

Hiring and running for 5 days effective working ofof gas cutter with oxygen cylinder, operating staff, miscellaneous items, etc for 30

days redevelopment work of ranney well = 6578.00 (C) = (A+B)

For 1 day effective working = 1315.60 (D) = (C) / 5

For 1 hour effective working = 164.45 (E) = (D) / 8

8 hours / day working has been considered for operation of gas cutter in the redevelopment work of ranney well

Extra for work under wet well = 20% 32.89 (F) = (E) * 20%20% extra shall be considered for work

under wet wellTotal for 1 hour effective working = 197.34 (G) = (E+F)

Say 197.30 Per Hour

5.15.1.9

Code No Description Unit No Qty Rate (INR) Amount (INR)

Detail of cost for 30 days redevelopment work of ranney well

(a) Hiring charges of Halogen Light day 1 30.00 100.00 3000.00 Market Rate

Total 3000.00 (A)Add CPOH @ 15% 15% 450.00 (B) = 15% (A)

Hiring charges of Halogen Light for 30 days redevelopment work of ranney well = 3450.00 (C) = (A+B)

For 1 day working = 115.00 (D) = (C) / 30For 1 hour working = 14.38 (E) = (D) / 8

Say 14.40 Per Hour

5.15.2 DISMANTLING OF EXISTING M.S. PLATFORM AND FABRICATION AND ERECTION OF NEW M.S. PLATFORM5.15.2.1

Reference / Remark

Providing and fixing of new intermediate mild steel platform for operation of valve spindle including demolishing of RCC work, dismantling of existing structural steel work,etc as confirm and directed by engineer-In-Charge

NOTE: 20% extra shall be considered for work under wet well

Hiring of Halogen Light. (min of 8 hour and max as per site required)

Code No Description Unit No Qty Rate (INR) Amount (INR)

Detail of cost for 5 meter dia ranney well

1] Dismantling of RCC and Steel work

(a) Dismantling of existing structural steel work kg 1 2,326.99 2.15 5,003.03 DSR 2014_15.18

(b) Demolishing R.C.C. work manually / by mechanical means including stacking of steel bars and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-Charge.

Flange width = 0.10 mtr Wed height= 0.20 mtr

Length of the ISMB to be embedded inside the wall = 0.25 mtr Diameter of well = 5.00 mtr

Width of MS platform = 1.00 mtr Mid diameter of platform = 4.00 mtr Perimeter of the platform = 12.57 mtr

C/C distance of ISMB = 0.50 mtr No of ISMB to be installed = 27 Nos

For concrete to be dismantled Length = 0.10 mtr Height = 0.20 mtr

Length of the ISMB to be embedded inside the wall = 0.25 mtr No of ISMB to be installed = 27 Nos

Hence, Volume of concrete to be dismantled = 0.1*0.2*0.25*27 =0.14 cum cum 1.00 0.14 1,302.30 175.81 DSR 2014_15.3

2] Installation of new intermediate platform 2.1 Material (a) Chequered Plate :-

Width of single chequered plate = 1.00 mtrThickness of chequered plate = 0.01 mtr

Perimeter of the platform = 12.57 mtr

Hence, Weight of chequered plate =

NOTE: 20% extra shall be considered for work under wet well

Reference / Remark

As suggested by contractor

Delhi Jal BoardSchedule of rates'2014-2015- Water supply works

Page 493: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Item Code Description Unit No Qty Rate (INR) Amount (INR) Reference / Remark

12.57*1*0.01*7850 =986.75 kg kg 1 986.75 45.00 44403.53 DSR 2014_1010

(b) ISMB 200 (200 x 100 mm) :- Width of MS platform = 1.00 mtr

Length of the ISMB to be embedded inside the wall = 0.25 mtr Length of ISMB 200 = 1.25 mtr

No of ISMB to be installed = 27.00 NosUnit weight of ISMB 200 = 24.2 kg/mtr

Hence, Weight of ISMB 2001.25*27*24.2 =816.75 kg kg 1 816.75 46.36 37864.53 DSR 2014_1007 (i)

(c) ISA (100 x 100 x 10 mm) :-Hence,

Height of MS Railing = 1.00 mtr No of ISA to be installed = 27.00 Nos

Unit weight of ISA 100100 = 14.9 kg/mtr

Hence, Weight of ISA 100100 1*27*14.9 = 402.3 kg kg 1 402.30 46.36 18650.63 DSR 2014_1007 (ii)

(d) MS tube - 50mm dia :- Perimeter of the platform = 12.57 mtr

Unit weight of MS tube 50 mm dia = 5.1 kg/mtr

Hence, Weight of Ms tube 50 mm dia 12.57*5.1 = 64.11 kg kg 1 64.11 46.36 2972.14 DSR 2014_1007 (iii)

(e) M.S. Plate at the edge of ISMB Section Length = 0.1 mtrWidth = 0.2 mtr

Thickness = 0.01 mtrNo of MS plate = 27.00 Nos

Hence, Weight of MS Plate 0.1*0.2*0.01*27*7850 = 42.39 kg kg 1 42.39 46.36 1965.20 DSR 2014_1007 (iv)

Consider 5% of wastage (Scrap Value) 5%(986.745+816.75+402.3+64.11+42.39)*0.05 = 115.62 kg kg 1 115.62 27.00 3121.74 Quotation enclosed

(f) Nut and Bolts for fixing of angles to MS plate at the end of ISMB Bolts & nuts 10 mm dia 200 mm long

Dia = 0.01 mmLength = 0.2 mm

Nos of nut and bolts at each MS plate joint = 4 no'sNo of MS plate = 27.00 Nos

Total nos of nut and bolts = 108 no'sWeight of each nut,bolt with washer = 0.136 kg/no

Hence, Weight of nut and bolts108*0.136 = 14.69 kg kg 1 14.69 56.00 822.64 DSR 2014_1034

(g) Fabrication charges kg 1 231.23 6.63 1533.05 Quotation enclosed

(h) Carriage of Material tonne 1 2.44 94.65 231.19 DSR 2014_2205

2.2 Labour for fixing: DSR 2014_0116 Fitter day 1 30.26 435.00 13163.10 (a) Joglekar book_item

no 258_pg no 27

DSR 2014_0117 Helper day 1 10.48 399.00 4181.52 (b) ANNEXURE "A" - pg no 28

DSR 2014_0114 Mazdoor day 1 34.91 329.00 11485.39

3 Cement Mortar (1:2) grouting for fixing of ISMB 200 inside Ranney Well Wall cum 1 0.14 2,510.8 338.96 SOR'2014_Water

Supply_5.2.1

4 Epoxy Painting on Steel Work L.S. 5% 3,072.62 (i+ii+iii+iv)*5%

Sub-total = 142741.60 (A)

Extra for work under water = 20% 28,548.32 (B) =(A) * 20%

Total = 1,71,289.92 (C) = (A) +(B)

Say = 73.62 per kg

5.15.3 DISMANTLING OF EXISTING G.I. PIPE AND PROVIDING & FIXING OF NEW G.I. PIPE WITH ATTACHMENTS5.15.3.1 Dismantling of existing G.I. Pipe

Code No Description Unit No Qty Rate (INR) Amount (INR)

Detail of Cost for per meter

NOTE: 20% extra shall be considered for work under wet well

Reference / Remark

Delhi Jal BoardSchedule of rates'2014-2015- Water supply works

Page 494: ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS...Labour for laying dismantling Joints quint al 1.35 255.40 344.79 (B) ANALYSIS OF RATES' 2014 - WATER SUPPLY WORKS Providing and Fixing

TATA Consulting Engineers Ltd

Item Code Description Unit No Qty Rate (INR) Amount (INR) Reference / Remark

1) Dismantling of existing G.I. Pipe Dismantling of existing G.I. Pipe 50 mm dia Meter 1 1 65.25 65.25 DSR 2014_15.44.2

Extra for work under wet well = 20% 13.0520% extra shall be considered for work

under wet welltotal for dismantling of G.I. Pipe per Rmt = 78.30

Say = 78.30

5.15.3.2 Providing and fixing G.I. pipes complete with G.I. fittings

Code No Description Unit No Qty Rate (INR) Amount (INR) Detail of Cost for per meter

1) Providing and fixing G.I. pipes complete with G.I. fittings

50 mm dia nominal bore Meter 1 1 399.50 399.50 DSR 2014_15.44.2

Extra for work under wet well = 20% 79.9020% extra shall be considered for work

under wet wellTotal for P/F of G.I. Pipe per Rmt = 479.40

Say = 479.40

5.15.3.3 Providing and fixing G.I. pipes attachment

Code No Description Unit No Qty Rate (INR) Amount (INR) Reference / Remark

GI attachment from valve to spindle (lower box+cross+guide+pin) for each radial

Each per radials 1 1.00 12000.00 12000.00

Subtotal for G.I. Pipe arrangement for each radial = 12000.00Extra for work under water = 20% 2400.00

Say = 14400.00 Each per radials

NOTE: 20% extra shall be considered for work under wet well Reference / Remark

NOTE: 20% extra shall be considered for work under wet well

NOTE: Value of scrap material shall be recovered from the contractor

Delhi Jal BoardSchedule of rates'2014-2015- Water supply works