Data Rates-Dam Works-Part 8

download Data Rates-Dam Works-Part 8

of 21

Transcript of Data Rates-Dam Works-Part 8

  • 8/13/2019 Data Rates-Dam Works-Part 8

    1/21

    DAM ALLIED WORKS

    DATA:Capacity of shovel bucket : 0.85 cum

    Capacity of shovel bucket under heaped condition : 1.00 cum

    Capacity of dumper : 5.00 cum

    initial lead considered for analysis : 1.00 km

    Speed for loaded tipper under haul road condition : 15 km / hr

    Speed for empty tipper under haul road condition : 20 km / hr

    Turning and unloading time : 2.00 min

    Shovel digging and loading cycle per bucket : 50 sec

    Number of buckets per load ( 5.00 / 1.00 ) say : 5 buckets

    Ideal cycle time for loading 5 buckets ( 5 x 50 / 60 ) : 4.17 min

    The ideal cycle time for shovel requires spotting of a dumper within 4.17 minutes near the

    shovel. However, in practice the space available at quarry may not permit positioning of tipper

    for loading on either side of shovel. Generally one tipper has to move after loading to position

    the next tipper for loading. Assuming one extra cycle for shovel, the corrected cycle time

    for the shovel will be : ( 4.17 + 50 / 60 ) : 5.00 min

    Round trip cycle time for tipper:

    Ideal cycle time of shovel for digging & loading : 5.00 min

    Time for 1km haulage under load ( 60 / 15 ) : 4.00 min

    Time for turning and un-loading( considering slow movement on rockfill ) : 2.50 min

    Time for 1 km return trip ( 60 / 20 ) : 3.00 min

    Time for turning and spotting : 0.50 minTotal : 15.00 min

    No.of tippers to match corrected cycle time of shovel ( 15.0 / 5 ) : 3 Nos

    Output of tipper / hr with 50 min working / hr ( 50 x 5.00 / 15.00 ) : 16.67 cum

    Output for 3 tippers per day ( 3 x 16.67 x 8 ) say : 400 cum

    The bulkage of graded rockfill material for conveyance is assumed at about 40 to 45 percent.

    Considering av. 42.5 % bulkage, insitu qty will be ( 400 / 1.425 ) say : 281 cum

    Consider 2 % wastage of rock in handling.

    Insitu quantity of rock available for rock f il l layer ( 281 x 0.98 ) say : 276 cum

    Assume 30 % voids in graded dozer levelled and hand packed rockfill.

    Quantity of rockfill in layer ( 276 / 0.70 ) say : 394 cum

    Quantity of rock for royalty charges @ 1.85 t / cum ( 394 x 1.85 ) : 729 tonnes

    Consider 394 cum rock fill embankment for rate analysis.

    1. Removal of overburden :

    Consider average 1 m depth of overburden material consisting of soil and soft rock

    Consider 9 m depth of cut on hard rock in benches of 2.25 m.

    Area of overburden for 281 cum insitu rock ( 281 / 9 ) say : 32 sqm

    Quantity of overburden soil / soft rock for 32 sqm ( 32 x 1 ) : 32 cum

    Consider removal of overburden by manual labour.

    Consider output of 1 heavy and 1 light mazdoor @ 4 cum / day.

    2. Drilling and Blasting :

    As the density of rockfill is dependant on gradation the drilling and blasting operations at quarryshall be planned properly to produce graded material.

    For 300 mm down size rockfill consider 32 mm dia jack hammer drilling.

    For good fragmentation consider burden at 25 times dia of hole say : 0.80 m

    Consider spacing at 1.25 times burden : 1.00 m

    Grid spacing of holes in m : 0.80 x 1.00 m

    Depth of hole ( generally not less than twice the burden ) : 2.40 m

    Effective depth of hole ( 2.40 - 0.15 ) : 2.25 m

    Area of excavation for 281 cum ( 281 / 2.25 ) : 125.00 sqm

    140

  • 8/13/2019 Data Rates-Dam Works-Part 8

    2/21

    DAM ALLIED WORKS

    Nos. of holes for 125 sqm area 125 / ( 0.80 x 1.00 ) : 156 Nos.

    Depth of drill ing for 156 holes ( 156 x 2.40 ) : 375 m

    Add for secondary drilling @ 5 % holes of 0.6 m depth say : 5 m

    Tota depth of drilling including holes for secondary blast ( 375 + 5 ) : 380 m

    No. of secondary blast holes : 8 Nos

    Rated rate of drilling in hard rock by jack hammer : 8.00 m / hour

    Rate of drilling in hard rock with 50 min / hr working ( 8 x 50 / 60 ) : 6.7 m / hour

    Consider 6 jack hammers for drilling holes.

    Time required for drilling with 6 jack hammers ( 380 / 6 / 6.7 ) say : 9.50 hours

    Quantity of explosive small dia considering good fragmentation : 0.40 kg / cum

    Quantity of explosive small dia for secondary blasting of large fragments : 0.20 kg / cum

    Electric detonators for main blast : 1 / hole

    Ordinary detonators for secondary blasting : 1 / hole

    Detonating fuse coil : 200 Rm

    3. Spreading and packing :

    Rockfill material collected can be levelled manually or by using dozer or by both.

    For the purpose of rate analysis a combination of dozer and manual labour is assumed.

    Output of dozer / hour for spreading & levelling : 200 cum

    Time for spreading & levelling by dozer @ 150 cum/ hr ( 400 / 150 ) say : 3 hours

    4. Surface finishing :

    Assume average 5 sqm surface finishing for 100 cum of rockfill.Area of surface finishing ( 394 x 5 / 100 ) say : 20 sqm

    5. Requirement of materials:

    Jack hammer drill rods for drilling : 380 m drilling

    Air hose for supplying air to 6 jack hammers ( 9.5 x 6 ) : 57 hours

    Small dia.Explosive at 0.40 kg / cum for 281 cum ( 281 x 0.40 ) : 112.00 kg

    Explosive at 0.20 kg / cum for secondary blast ( 281x0.05x0.2 ) : 3.00 kg

    Total quantity of explosive for 394 cum rockfill : 115 kg

    Ele.detonators at 1 per hole for 156 main blast holes ( 156 x 1 ) : 156 Nos.

    Ord.detonators @ 1 per hole for 8 secondary holes ( 8 x 1 ) : 8 Nos.

    Detonating fuse coil : 200 Rm

    6. Requirement of machinery :

    Deploy 3 air compressors 8.5 cmm capacity for 9.5 hours for drilling.

    Deploy 6 jack hammers for 9.5 hours for drilling.

    Deploy 0.85 cum capacity shovel for 8 hours for digging and loading 400 cum.

    Deploy 3 tippers of 5 cum capacity for conveying 400 cum rockfill material.

    Deploy 1 dozer for 3 hours for spreading and levelling collected rockfill material.

    7. Requirement of workforce ( other than machinery crew ) :

    Removal of overburden :

    Heavy mazdoor : 8 Nos.

    Light mazdoor : 8 Nos.Drilling and blasting :

    Blaster ( licensed ) : 1 No.

    Helper ( blasting ) : 1 No.

    For packing voids in dozed layer and hand packing at edges.

    Heavy mazdoor : 4 Nos.

    Light mazdoor : 4 Nos.

    For surface finishing 20 sqm.

    Mason Class-II : 2 Nos.

    141

  • 8/13/2019 Data Rates-Dam Works-Part 8

    3/21

    DAM ALLIED WORKS

    Heavy mazdoor : 2 Nos.

    Maistry ( 1 at quarry and 1 at site ). : 2 Nos.

    8. Use rate of materials :

    Cost of drill rod 2.5 m long @ Rs: 5660.00 / Each Rs: 5660.00

    Life of drill rod for drilling in hard rock with reconditioning : 150 m

    Use rate of drill rod per Rm drilling ( cost / life ) Rs: 37.73

    Cost of air hose 50 m long @ Rs: 150.00 / Rm Rs: 7500.00

    Life of 25 mm dia air hose : 800 hours

    Use rate of air hose per hr ( cost / life ) Rs: 9.38

    RATE ANALYSIS UNIT : 394.00 cum

    A. MATERIALS:

    Sl No Unit Amount

    in Rs.

    1 Use rate of drill rod 2.5 m long Rm 380.00 37.73 14338.67

    Reconditioning charges @ 10 % 1433.87

    2 Use rate of 25 mm dia air hose 6 Nos. Hour 57.00 9.38 534.38

    3 Explosive small dia kg 115.00 45.00 5175.00

    4 Electric detonators Nos 156.00 10.00 1560.00

    5 Detonator ordinary Nos 8.00 5.50 44.006 Fuse coil Rm 200.00 8.00 1600.00

    7 Sundries ( waste tyres etc ) LS 10.00 30.00 300.00

    Total Rs: 24985.91

    Add for small Tools and Plants @ 1% Rs: 249.86

    Add for Contractor's Profit @ 10% Rs: 2498.59

    Add for Contractor's Overheads @ 5% Rs: 1249.30

    Add royalty charges for 729 t rock @ Rs: 30.00 / tonne Rs: 21870.00

    Total cost of Materials : Rs: 50853.65

    B. MACHINERY:

    Sl No Unit Amount

    in Rs.

    1 Air compressor 8.5 cmm ( diesel ) 3 Nos Hour 28.50 202.00 5757.00

    Fuel / Energy charges Hour 28.50 619.00 17641.50

    2 Jack hammer 6 Nos Hour 57.00 14.00 798.00

    Fuel / Energy charges Hour 57.00 5.00 285.00

    3 Angle dozer 90 hp Hour 3.00 1154.00 3462.00

    Fuel / Energy charges Hour 3.00 423.00 1269.00

    4 Shovel 0.85 cum Hour 8.00 1199.00 9592.00

    Fuel / Energy charges Hour 8.00 605.00 4840.00

    5 Tipper 5 cum Hour 24.00 271.00 6504.00 Fuel / Energy charges Hour 24.00 208.00 4992.00

    Total Rs: 55140.50

    Add for small Tools and Plants @ 1% Rs: 551.41

    Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 2902.75

    Add for Contractor's Overheads @ 5% Rs: 2757.03

    Total hire charges of Machinery : Rs: 61351.68

    C. LABOUR:

    Description

    Perticulars

    in Rs.

    Quantity Rate

    Quantity Rate

    in Rs.

    142

  • 8/13/2019 Data Rates-Dam Works-Part 8

    4/21

    DAM ALLIED WORKS

    Sl No Unit Amount

    in Rs.

    1 Crew for Air compressor Hour 28.50 72.10 2054.85

    2 Crew for Jack hammer Hour 57.00 111.90 6378.30

    3 Crew for Shovel Hour 8.00 77.50 620.00

    4 Crew for Tipper Hour 24.00 56.70 1360.80

    5 Crew for Dozer Hour 3.00 77.50 232.50

    6 Blaster licensed Day 1.00 147.00 147.00

    7 Helper blaster Day 1.00 141.50 141.50

    8 Maistry Day 2.00 141.50 283.00

    9 Mason Class-II Day 2.00 148.50 297.00

    10 Heavy mazdoor Day 14.00 132.00 1848.00

    11 Light mazdoor Day 12.00 130.50 1566.00

    Total Rs: 14928.95

    Add for small Tools and Plants @ 1% Rs: 149.29

    Add for Contractor's Profit @ 10% Rs: 1492.90

    Add for hidden cost on Labour @ 15% Rs: 2239.34

    Add for additional hidden cost on labour @ 5% Rs: 746.45

    Add for Contractor's Overheads @ 5% Rs: 746.45

    Total cost of Labour : Rs: 20303.37

    ABSTRACT:

    A. Cost of Materials including royalty charges Rs: 50853.65

    B. Hire charges of Machinery Rs: 61351.68

    C. Cost of Labour Rs: 20303.37

    132508.71

    Add for enabling works @ 1.40% Rs: 1855.12

    Total cost for 394.00 cum Rs: 134363.83

    Rate per cum Rs: 341.00

    Rate approved per cum Rs: 341.00

    SECTION: DAM AND ALLIED WORKS. YEAR : 2010-11 ITEM No: 48

    ITEM: Providing and constructing dry rubble rock-toe using rubble and stone chips from

    approved source including cost of all materials, machinery, labour, hand packing rubble

    and stone chips, finishing top and sides to required slopes etc., complete with initial lead upto

    1 km and all lifts.

    DATA:Top width : 1.50 m

    Side slope upstream side : 1 (V) : 1 (H)

    Side slope down stream side : 1 (V) : 2 (H)

    Height : 3.00 m

    Embankment 1.5m 1 2

    1 1

    Rock-toe 3 m

    Description

    TOTAL Rs:

    SKETCH SHOWING DETAILS OF ROCK-TOE

    ( filters below and behind rock-toe not shown )

    Quantity Rate

    in Rs.

    143

  • 8/13/2019 Data Rates-Dam Works-Part 8

    5/21

    DAM ALLIED WORKS

    Cross sectional area ( 1.50 + 10.50 ) x 3 / 2 : 18.00 sqm

    Consider 100 cum rock toe:

    1. Requirement of materials :

    Requirement of materials for 100 cum based on data for 400 cum in item - 47:

    Jack hammer drill rod 2.5 m length ( 387 x 100 / 400 ) : 97 Rm

    Explosive small dia ( Kelvex-220 ) ( 118 x 100 / 400 ) : 30 kg.

    Electric detonator ( 159 x 100 / 400 ) : 40 Nos

    Detonator ordinary ( 8 x 100 / 400 ) : 2 Nos.

    detonating fuse coil ( 200 x 100 / 400 ) : 50 Rm

    Quantity of rock for royalty charges @ 1.85 t / cum ( 100 x 1.85 ) : 185 tonnes

    2. Requirement of machinery :

    Requirement of machinery for 100 cum based on data for 400 cum in item -47:

    Air compressor 8.5 cmm ( 30 x 100 / 400 ) : 7.5 hours

    Jack hammer ( 60 x 100 / 400 ) : 15 hours

    Shovel 0.85 cum ( 8 x 100 / 400 ) : 2 hours

    Tipper 5 cum ( 24 x 100 / 400 ) : 6 hours

    Surface finishing required ( 12.40 x 100 / 18 ) : 69 sqm

    3. Requirement of workforce ( other than machinery crew ) :

    Blaster ( licinsed ) : 0.5 No.

    Helper ( blasting : 1 No.

    Rock-toe material can be spread partly by dumping the material directly at spot and partly byconveying manually. Assuming 50 % manual conveying.

    For conveying, spreading and packing :

    Heavy mazdoor for rubble : 10 Nos.

    Light mazdoor for chips : 2 Nos.

    For packing and surface finishing.

    Mason Class-II : 7 Nos.

    Heavy mazdoor : 7 Nos.

    Maistry : 1 No.

    4. Use rate of materials :

    Cost of drill rod 2.5 m long @ Rs: 5660.00 / Each Rs: 5660.00

    Life of drill rod for drilling in hard rock with reconditioning : 150 m

    Use rate of drill rod per Rm drilling ( cost / life ) Rs: 37.73

    Cost of air hose 50 m long @ Rs: 150.00 / Rm Rs: 7500.00

    Life of 25 mm dia air hose : 800 hours

    Use rate of air hose per hr ( cost / life ) Rs: 9.38

    RATE ANALYSIS UNIT : 100.00 cum

    A. MATERIALS:

    Sl No Unit Amount

    in Rs.

    1 Use rate of drill rod 1.5 m long Rm 97.00 37.73 3660.13

    Reconditionong charges @ 10 % 366.012 Use rate of 25 mm dia air hose Hour 15.00 9.38 140.63

    3 Explosive small dia kg 30.00 45.00 1350.00

    4 Electric detonator Nos 40.00 10.00 400.00

    5 Detonator ordinary Nos 2.00 5.50 11.00

    6 Fuse coil Rm 50.00 8.00 400.00

    7 Sundries LS 2.00 30.00 60.00

    Total Rs: 6387.77

    Add for small Tools and Plants @ 1% Rs: 63.88

    Perticulars Quantity Rate

    in Rs.

    144

  • 8/13/2019 Data Rates-Dam Works-Part 8

    6/21

    DAM ALLIED WORKS

    Add for Contractor's Profit @ 10% Rs: 638.78

    Add for Contractor's Overheads @ 5% Rs: 319.39

    Add royalty charges for 185 t rock @ Rs: 30.00 / tonne Rs: 5550.00

    Total cost of Materials : Rs: 12959.82

    B. MACHINERY:

    Sl No Unit Amount

    in Rs.

    1 Air compressor 8.5 cmm ( diesel ) Hour 7.50 202.00 1515.00

    Fuel / Energy charges Hour 7.50 619.00 4642.50

    2 Jack hammer Hour 15.00 14.00 210.00

    Fuel / Energy charges Hour 15.00 5.00 75.00

    3 Shovel 0.85 cum Hour 2.00 1199.00 2398.00

    Fuel / Energy charges Hour 2.00 605.00 1210.00

    4 Tipper 5 cum Hour 6.00 271.00 1626.00

    Fuel / Energy charges Hour 6.00 208.00 1248.00

    Total Rs: 12924.50

    Add for small Tools and Plants @ 1% Rs: 129.25

    Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 717.55

    Add for Contractor's Overheads @ 5% Rs: 646.23

    Total hire charges of Machinery : Rs: 14417.52

    C. LABOUR :

    Sl No Unit Amount

    in Rs.

    1 Crew for Air compressor Hour 7.50 72.10 540.75

    2 Crew for Jack hammer Hour 15.00 111.90 1678.50

    Contd

    C. LABOUR ( Contd ) :

    Sl No Unit Amount

    in Rs.

    Contd

    3 Crew for Shovel Hour 2.00 77.50 155.00

    4 Crew for Tipper Hour 6.00 56.70 340.20

    5 Blaster licensed Day 0.50 147.00 73.50

    6 Helper blaster Day 1.00 141.50 141.50

    7 Maistry Day 1.00 141.50 141.50

    8 Mason Class-II Day 7.00 148.50 1039.50

    9 Heavy mazdoor Day 17.00 132.00 2244.00

    10 Light mazdoor Day 2.00 130.50 261.00

    Total Rs: 6615.45

    Add for small Tools and Plants @ 1% Rs: 66.15

    Add for Contractor's Profit @ 10% Rs: 661.55Add for hidden cost on Labour @ 15% Rs: 992.32

    Add for additional hidden cost on labour @ 5% Rs: 330.77

    Add for Contractor's Overheads @ 5% Rs: 330.77

    Total cost of Labour : Rs: 8997.01

    ABSTRACT:

    A. Cost of Materials including royalty charges Rs: 12959.82

    B. Hire charges of Machinery Rs: 14417.52

    Description

    Description Quantity Rate

    in Rs.

    Quantity Rate

    in Rs.

    Description

    Quantity Rate

    in Rs.

    145

  • 8/13/2019 Data Rates-Dam Works-Part 8

    7/21

    DAM ALLIED WORKS

    C. Cost of Labour Rs: 8997.01

    36374.35

    Add for enabling works @ 1.40% Rs: 509.24

    Total cost for 100.00 cum Rs: 36883.59

    Rate per cum Rs: 369.00

    Rate approved per cum Rs: 369.00

    SECTION: DAM AND ALLIED WORKS. YEAR : 2010-11 ITEM No: 49

    ITEM: Providing and constructing dry rubble rock-toe with rubble and stone chips from dump

    yardincluding cost of all materials, machinery, labour, hand packing rubble and stone chips,

    finishing top and sides to required slopes etc., complete with initial lead upto 1 km and all

    lifts.

    Note: Useful rubble and stone chips will be issued at dump yard at the issue rate for usefull rubble /

    stone chips. Sorting out and breaking charges are included in rate analysis.

    DATA:Top width : 1.50 m

    Side slope upstream side : 1 (V) : 1 (H)

    Side slope down stream side : 1 (V) : 2 (H)

    Height : 3.00 mCross sectional area (1.50 + 10.50 ) x 3 / 2 : 18.00 sqm

    Consider 100 cum rock toe:

    Length of rock-toe for 100 cum ( 100 / 18 ) : 5.55 m

    Area of surface finishing for top & sides : 69 sqm

    1. Requirement of materials:

    Quantity of rubble : 100 cum

    Quantity of stone chips for packing @ 15 % ( 100 x 0.15 ) : 15 cum

    2. Requirement of machinery :

    For 100 cum rock-toe same as in Item : 48.

    0.85 cum shovel 1 No. : 2 hours

    5.00 cum tippers 3 Nos : 6 hours

    3. Requirement of workforce ( other than machinery crew ) :

    For sorting out & breaking useful rubble and chips:

    For sorting out and breaking over size stones in dump yard :

    Stone breaker : 2 Nos.

    Heavy mazdoor : 2 Nos.

    Rock-toe material can be spread partly by dumping the material directly at spot and partly by

    conveying manually. Assuming 50 % manual rehandling.

    For rehandling and spreading rubble at rock-toe:

    Heavy mazdoor : 10 Nos.Light mazdoor : 2 Nos.

    For packing and finishing:

    Heavy mazdoor : 7 Nos.

    Mason Class-II : 7 Nos.

    Maistry : 1 No.

    RATE ANALYSIS UNIT : 100.00 cum

    A. MATERIALS:

    TOTAL Rs:

    146

  • 8/13/2019 Data Rates-Dam Works-Part 8

    8/21

    DAM ALLIED WORKS

    Sl No Unit Amount

    in Rs.

    1 Useful rubble ( at dump yard ) cum 100.00 135.00 13500.00

    2 Useful stone chips ( at dump yard ) cum 15.00 160.00 2400.00

    Total Rs: 15900.00

    Add for small Tools and Plants @ 1% Rs: 159.00

    Add for Contractor's Profit @ 10% Rs: 1590.00

    Add for Contractor's Overheads @ 5% Rs: 795.00

    Add royalty charges for stones @ ( Included in material rate) Rs: 0.00

    Total cost of Materials : Rs: 18444.00

    B. MACHINERY:

    Sl No Unit Amount

    in Rs.

    1 Shovel 0.85 cum Hour 2.00 1199.00 2398.00

    Fuel / Energy charges Hour 2.00 605.00 1210.00

    2 Tipper 5 cum Hour 6.00 271.00 1626.00

    Fuel / Energy charges Hour 6.00 208.00 1248.00

    Total Rs: 6482.00

    Add for small Tools and Plants @ 1% Rs: 64.82

    Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 245.80Add for Contractor's Overheads @ 5% Rs: 324.10

    Total hire charges of Machinery : Rs: 7116.72

    C. LABOUR:

    Sl No Unit Amount

    in Rs.

    1 Crew for Shovel Hour 2.00 77.50 155.00

    2 Crew for Tipper Hour 6.00 56.70 340.20

    3 Mason Class-II Day 7.00 148.50 1039.50

    4 Maistry Day 1.00 141.50 141.50

    5 Stone breaker Day 2.00 146.00 292.00

    6 Heavy mazdoor Day 19.00 132.00 2508.00

    7 Light mazdoor Day 2.00 130.50 261.00

    Total Rs: 4737.20

    Add for small Tools and Plants @ 1% Rs: 47.37

    Add for Contractor's Profit @ 10% Rs: 473.72

    Add for hidden cost on Labour @ 15% Rs: 710.58

    Add for additional hidden cost on labour @ 5% Rs: 236.86

    Add for Contractor's Overheads @ 5% Rs: 236.86

    Total cost of Labour : Rs: 6442.59

    ABSTRACT:

    A. Cost of Materials including royalty charges Rs: 18444.00

    B. Hire charges of Machinery Rs: 7116.72

    C. Cost of Labour Rs: 6442.59

    32003.31

    Add for enabling works @ 1.40% Rs: 448.05

    Total cost for 100.00 cum Rs: 32451.36

    Description

    TOTAL Rs:

    Perticulars

    Description

    Quantity Rate

    Quantity Rate

    in Rs.

    in Rs.

    Quantity Rate

    in Rs.

    147

  • 8/13/2019 Data Rates-Dam Works-Part 8

    9/21

    DAM ALLIED WORKS

    Rate per cum Rs: 325.00

    Rate approved per cum Rs: 325.00

    SECTION: DAM AND ALLIED WORKS. YEAR : 2010-11 ITEM No: 50

    ITEM: Providing and laying 300 mm diameter open jointed hume pipes with collars in rock-toefor

    drainage including cost of all materials, machinery, labour etc., complete withlead upto 1 km

    and all lifts.

    DATA:Consider 100 m open jointed hume pipe drain for analysis.

    1. Requirement of materials :

    300 mm dia hume pips : 100 m

    Number of collars for 100 m length : 40 Nos

    Weight of pipe and collars @ 80 kg / m : 8.00 tonnes

    2. Requirement of machinery :

    No machinery is required.

    3. Requirement of workforce ( other than machinery crew ) :

    Mason Cl-II for laying pipe @ 50 Rm / day : 2 Nos.

    Heavy mazdoors for assisting mason : 2 Nos.

    Heavy mazdoors for handling pipes and collars : 4 Nos4. Rehandling / Initial lead for materials:

    Consider 1 km initial lead for materials.

    RATE ANALYSIS UNIT : 100.00 Rm

    A. MATERIALS:

    Sl No Unit Amount

    in Rs.

    1 Hume pipe 300 mm dia.with collar Rm 100.00 325.00 32500.00

    0.00 0.00 0.00

    Total Rs: 32500.00

    Add for small Tools and Plants @ 1% Rs: 325.00

    Add for Contractor's Profit @ 10% Rs: 3250.00

    Add for Contractor's Overheads @ 5% Rs: 1625.00

    Total cost of Materials : Rs: 37700.00

    B. MACHINERY:

    Sl No Unit Amount

    in Rs.

    1 NIL 0.00 0.00 0.00

    0.00 0.00 0.00

    Total Rs: 0.00Add for small Tools and Plants @ 1% Rs: 0.00

    Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 0.00

    Add for Contractor's Overheads @ 5% Rs: 0.00

    Total hire charges of Machinery : Rs: 0.00

    C. LABOUR:

    Sl No Unit Amount

    in Rs.in Rs.

    Quantity Rate

    Description

    Description

    Perticulars

    in Rs.

    Rate

    Quantity Rate

    in Rs.

    Quantity

    148

  • 8/13/2019 Data Rates-Dam Works-Part 8

    10/21

    DAM ALLIED WORKS

    1 Mason Cl- II Day 2.00 148.50 297.00

    2 Heavy mazdoor Day 6.00 132.00 792.00

    Total Rs: 1089.00

    Add for small Tools and Plants @ 1% Rs: 10.89

    Add for Contractor's Profit @ 10% Rs: 108.90

    Add for hidden cost on Labour @ 15% Rs: 163.35

    Add for additional hidden cost on labour @ 5% Rs: 54.45

    Add for Contractor's Overheads @ 5% Rs: 54.45

    Total cost of Labour : Rs: 1481.04

    ABSTRACT:

    A. Cost of Materials Rs: 37700.00

    B. Hire charges of Machinery Rs: 0.00

    C. Cost of Labour Rs: 1481.04

    TOTAL Rs: 39181.04

    Add for enabling works @ 1.40% Rs: 548.53

    Total Rs: 39729.57

    Add for 1 km rehandling / initial lead including loading / unloading:

    Hume pipes & collars 8.00 tonnes @ Rs: 129.10 / tonne Rs: 1032.80

    Total cost for 100.00 Rm Rs: 40762.37

    Rate per Rm Rs: 408.00Rate approved per Rm Rs: 408.00

    SECTION: DAM AND ALLIED WORKS. YEAR : 2010-11 ITEM No: 51

    ITEM: Providing and constructing 1.20 m internal diameter and average 3 m height RCC manholewith

    600 mm dia. top cover in M-15grade cement concrete using 20 mm downgraded, clean, hard

    coarse aggregate, 200 mm thick for bed / sides / top slab / 1.5 m long cut-off wall and 75 mm

    thick for cover including providing 12 mm dia reinforcement bars at 300 mm c / c bothways for

    bed /sides /cut-off wall / top slab / rungs and 8 mm dia bars at 150 mm c / c bothways for cover,

    excavation for foundation, providing 300 mm dia hume pipe outlet, cost of all materials, labour,

    machinery, formwork, scaffolding, batching, mixing, laying, vibrating, finishing, curing etc.,

    complete with lead upto 1 km and all lifts.

    DATA:Consider one manhole for analysis.

    The work involves :

    a. Excavation for foundation;

    b. Laying bed concreting;

    c. Constructing RCC man-hole with top cover and cut-off wall;

    d. Fixing out-let pipe

    Quantity of materials for 1 cum of M-15 CC using 20 mm down CA :Cenemt : 290 kg Fine aggregate : 0.44 cum Coarse aggregate : 0.80 cum

    Wastage : 1 % for cement , 2 % for CA & FA and 2.5 % for steel.

    1.5 m D / S Embankment

    Key-wall

    2 1

    149

  • 8/13/2019 Data Rates-Dam Works-Part 8

    11/21

    DAM ALLIED WORKS

    Manhole 1 1.2 m 1

    Cover 1.6 m

    Rock-toe 3.0 m

    In-let pipe

    Out-let

    2.0 m

    Manhole details - Plan Manhole - Section ( reinforcement not shown )

    1. Excavation for foundation :( 0.786 x 2 x 2 x 2 ) + ( 1.5 x 0.4 x 2) : 7.50 cum

    M-15 grade CC :

    for bed ( 0.786 x 2 x 2 x 0.2 ) + ( 1.7 x 0.4 x 0.2 ) : 0.765 cum

    for sides ( 3.142 x 1.4 x 2.8 x 0.2 ) + ( 1.5 x 2.8 x 0.2 ) : 3.303 cum

    for slab 0.786 x 0.2 ( 1.6 x 1.6 - 0.6 x 0.6 ) : 0.346 cum

    for cover 0.786 x 0.65 x 0.65 x 0.075 : 0.025 cum

    Total : 4.439 cum

    2. Requirement of materials :

    Cement : ( 4.439 x 290 x 1.01 ) : 1300 kg

    Coarse aggregate 20 - 10 mm ( 4.439 x 0.80 x 0.65 x 1.02 ) : 2.35 cum

    Coarse aggregate 20 - 10 mm ( 4.439 x 0.80 x 0.35 x 1.02 ) : 1.27 cum

    Fine aggregate ( 4.439 x 0.44 x 1.02 ) : 2.00 cumSuper plasticiser ( 4.439 x 0.87 ) : 4.00 ltr

    Reinforcement steel :

    for man hole bed ( 2 x 1.9 + 4 x 1.7 + 4 x 1.5 + 4 x 0.7 ) x 0.89 : 17.27 kg

    for cut-off bed ( 2 x 1.7 ) x 0.89 : 03.03 kg

    for manhole sides ( 15 x 3.3 + 9 x 4.5 ) x 0.89 : 80.10 kg

    for cut-off wall ( 5 x 1.5 + 9 x 3.3 ) x 0.89 : 33.10 kg

    for rungs ( 8 x 1 ) x 0.89 : 07.12 kg

    for top slab ( 2 x 1.5 + 4 x 1.3 + 4 x 1.1 + 4 x 0.3 ) x 0.89 : 12.28 kg

    for cover LS : 03.00 kg

    Total : 155.90 kg

    Add for wastage @ 2.50% : 3.90 kg

    say : 160.00 kg

    3. Requirement of machinery :

    Except for side walls the quantity of concrete required for other components is very small.

    A combination of mechanical mixer for wall concreting and manual mixing for bed and top slab

    is assumed. Light mazdoor engaged for conveying water for concreting and curing.

    Deploy 300 / 200 mixer for 4 hours for mixing concrete.

    Deploy 40 mm needle vibrator for vibrating concrete.

    4. Requirement of workforce ( other than machinery crew ) :

    Mason Cl- II : 1 No.

    Bar bender : 1 No.Maistry : 1 No.

    Heavy mazdoor

    for excavation for foundation : 2 Nos

    for bar bending : 1 No.

    for concreting : 5 Nos

    Light mazdoor

    for excavation for foundation : 2 Nos.

    for concreting : 4 Nos

    150

  • 8/13/2019 Data Rates-Dam Works-Part 8

    12/21

    DAM ALLIED WORKS

    for curing : 1 No.

    Labour charges for shuttering per sqm ( Annexure-B Item : 13 ) Rs: 33.17

    5. Formwork / shuttering :

    for sides ( 3.142 x 1.6 x 3 + 3.142 x 1.2 x 2.8 ) : 25.64 sqm

    for cut-off wall ( 2 x 1.5 x 2.8 ) : 08.40 sqm

    for top slab ( 0.7857 x 1.2 x 1.2 ) : 01.13 sqm

    Total ( say ) : 36 sqm

    6. Rehandling / Initial lead for materials:

    Consider 1 km rehandling lead for cement and 1 km initial lead for other materials.

    7. Use rate of materials :

    Use rate of normal shuttering per sqm ( Annexure-A Item : 13 ) Rs: 151.07

    RATE ANALYSIS UNIT : 1.00 Each

    A. MATERIALS:

    Sl No Unit Amount

    in Rs.

    1 Cement with 1 % wastage kg 1300.00 4.00 5200.00

    Cement for incidentals @ 3 kg / cum kg 13.50 4.00 54.00

    2 Coarse aggregate 20 to 10 mm cum 2.35 520.00 1222.00

    Coarse aggregate 10 to 4.75 mm cum 1.27 669.00 849.63

    3 Fine aggregate ( screened ) cum 2.00 199.00 398.00Contd

    A. MATERIALS ( Contd ) :

    Sl No Unit Amount

    in Rs.

    Contd

    4 Super plasticiser ltr 4.00 75.00 300.00

    5 Reinforcement steel with 2.5 % wastage kg 160.00 36.20 5792.00

    6 Binding wire kg 4.00 50.00 200.00

    7 Hume pipe 300 mm dia Rm 1.00 325.00 325.00

    8 Use rate of shuttering sqm 36.00 151.07 5438.35

    9 Scaffolding @ 5 % of shuttering 271.92

    10 Sundries LS 2.00 30.00 60.00

    Total Rs: 20110.90

    Add for small Tools and Plants @ 1% Rs: 201.11

    Add for Contractor's Profit @ 10% Rs: 2011.09

    Add for Contractor's Overheads @ 5% Rs: 1005.54

    Add royalty charges on CA @ ( Included in material rate) Rs: 0.00

    Add royalty charges on Sand @ ( Included in material rate) Rs: 0.00

    Total cost of Materials : Rs: 23328.64

    B. MACHINERY:

    Sl No Unit Amountin Rs.

    1 Concrete mixer 300 / 200 ( ele ) Hour 4.00 38.00 152.00

    Fuel / Energy charges Hour 4.00 25.00 100.00

    2 Needle vibrator 40 mm dia ( ele ) Hour 4.00 7.00 28.00

    Fuel / Energy charges Hour 4.00 5.00 20.00

    3 Sundries LS 1.00 30.00 30.00

    Total Rs: 330.00

    Add for small Tools and Plants @ 1% Rs: 3.30

    Description

    Perticulars

    Quantity Rate

    Quantity Rate

    in Rs.

    in Rs.

    Perticulars Quantity Rate

    in Rs.

    151

  • 8/13/2019 Data Rates-Dam Works-Part 8

    13/21

    DAM ALLIED WORKS

    Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 15.00

    Add for Contractor's Overheads @ 5% Rs: 16.50

    Total hire charges of Machinery : Rs: 364.80

    C. LABOUR:

    Sl No Unit Amount

    in Rs.

    1 Mason Cl- II Day 1.00 159.00 159.00

    2 Bar bender Day 1.00 159.00 159.00

    3 Maistry Day 1.00 141.50 141.50

    4 Heavy mazdoor

    for excavation for foundation Day 2.00 132.00 264.00

    for bar bending Day 1.00 132.00 132.00

    for concreting Day 5.00 132.00 660.00

    5 Light mazdoor

    for excavation for foundation Day 2.00 130.50 261.00

    for concreting Day 5.00 130.50 652.50

    for curing Day 1.00 130.50 130.50

    6 Labour for shuttering sqm 36.00 33.17 1193.94

    Total Rs: 3753.44

    Contd

    C. LABOUR ( Contd ) :

    Sl No Unit Amount

    in Rs.

    Contd

    Add for small Tools and Plants @ 1% Rs: 37.53

    Add for Contractor's Profit @ 10% Rs: 375.34

    Add for hidden cost on Labour @ 15% Rs: 563.02

    Add for additional hidden cost on labour @ 5% Rs: 187.67

    Add for Contractor's Overheads @ 5% Rs: 187.67

    Total cost of Labour : Rs: 5104.68

    ABSTRACT:

    A. Cost of Materials including royalty charges Rs: 23328.64

    B. Hire charges of Machinery Rs: 364.80

    C. Cost of Labour Rs: 5104.68

    TOTAL Rs: 28798.12

    Add for enabling works @ 1.40% Rs: 403.17

    Total Rs: 29201.29

    Add for 1 km rehandling / initial lead including loading / unloading:

    Cement 1313.5 kg @ Rs: 129.10 / tonne Rs: 169.57

    Coarse aggregates 3.62 cum @ Rs: 121.90 / cum Rs: 441.28

    Fine aggregate 2.00 cum @ Rs: 84.90 / cum Rs: 169.80Inlet / outlet pipes 80 kg @ Rs: 129.10 / tonne 10.33

    Reinforcement steel 160 kg @ Rs: 129.10 / tonne Rs: 20.66

    Total cost for 1.00 Each Rs: 30012.93

    Rate per Each Rs: 30015.00

    Rate approved per Each Rs: 30015.00

    SECTION: DAM AND ALLIED WORKS. YEAR : 2010-11 ITEM No: 52

    Description Quantity Rate

    in Rs.

    in Rs.

    Description Quantity Rate

    152

  • 8/13/2019 Data Rates-Dam Works-Part 8

    14/21

    DAM ALLIED WORKS

    ITEM: Providing and constructinglongitudinal and crossgraded filter drainsusing sand and 80 to

    20 mm and 20 mm down graded aggregates satisfying specified filter creteria in layers as per

    specifications including cost of all materials, machinery, labour, laying to required slopes,

    compaction etc. complete with initiallead upto 50 m and all lifts.

    DATA:Bottom width : 1.00 m

    Side slopes : : 1( V ):0.5(H)

    Depth : 1.30 m

    Top width : 2.30 m

    Cross sectional area ( 1.00 + 2.30 ) x 1.30 / 2 : 2.145 sqm

    Compacted embankment

    200 mm thick Sand

    1.30 m 0.5 80 mm down filter

    1 200 mm thick 20 mm down filter

    1.00 m

    Thickness of sand layer : 200 mm

    Thickness of 20 mm down CA layer : 200 mm

    Consider 100 cum filter drain:

    Length of drain for 100 cum ( 100 / 2.145 ) : 46 62 m

    1. Requirement of materials :

    Quantity of 80-20 mm filter aggregate.

    ( 0.60 + 1.10 ) x 0.50 x 46.62 x 1.02 / 2 : 20 20 cum

    80-20 mm filter shall contain 90 % 80-40 mm & 10 % 40-20 mm

    Quantity of 20 mm down filter aggregate.

    ( 0.80 + 1.70 ) x 0.90 x 46.62 x 1.02 / 2 - 20.20 : 33.30 cum

    20 mm down filter shall contain 75 % 20-10 mm & 25 % 10 mm down

    Quantity of filter sand ( 2.145x 46.62x 1.02 - 53.5 ) : 48.50 cum

    2. Requirement of machinery :

    No machinery is required.

    3. Requirement of workforce ( other than machinery crew ) :

    For conveying & laying sand ( 1 heavy & 1 light 6 cum / day ).

    Heavy mazdoor : 8 Nos.

    Light mazdoor : 8 Nos.

    For conveying & laying 20 mm down CA ( 12 heavy & 1 light 5 cum / day ).

    Heavy mazdoor : 7 Nos.

    Light mazdoor : 7 Nos.

    For conveying & laying 80-20 mm CA ( 1 heavy & 1 light 5 cum / day ).

    Heavy mazdoor : 4 Nos.Light mazdoor : 4 Nos.

    Maistry : 1 No.

    RATE ANALYSIS UNIT : 100.00 cum

    A. MATERIALS:

    Sl No Unit Amount

    in Rs.

    1 Sand ( unscreened ) cum 48.50 154.00 7469.00

    Quantity Rate

    in Rs.

    SKETCH SHOWING DETAILS OF CROSS DRAIN

    Perticulars

    153

  • 8/13/2019 Data Rates-Dam Works-Part 8

    15/21

    DAM ALLIED WORKS

    2 Coarse aggregate 80-40 mm cum 18.20 267.00 4859.40

    3 Coarse aggregate 40-20 mm cum 2.00 381.00 762.00

    4 Coarse aggregate 20-10 mm cum 25.00 520.00 13000.00

    5 Coarse aggregate 10 mm down cum 8.30 669.00 5552.70

    Total Rs: 31643.10

    Add for small Tools and Plants @ 1% Rs: 316.43

    Add for Contractor's Profit @ 10% Rs: 3164.31

    Add for Contractor's Overheads @ 5% Rs: 1582.16

    Add royalty charges on Sand @ ( Included in material rate) Rs: 0.00

    Add royalty charges CA @ ( Included in material rate) Rs: 0.00

    Total cost of Materials : Rs: 36706.00

    B. MACHINERY:

    Sl No Unit Amount

    in Rs.

    1 NIL 0.00 0.00 0.00

    0.00 0.00 0.00

    Total Rs: 0.00

    Contd

    B. MACHINERY ( Contd ) :

    Sl No Unit Amount

    in Rs.

    Contd

    Add for small Tools and Plants @ 1% Rs: 0.00

    Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 0.00

    Add for Contractor's Overheads @ 5% Rs: 0.00

    Total hire charges of Machinery : Rs: 0.00

    C. LABOUR:

    Sl No Unit Amount

    in Rs.

    1 Maistry Day 1.00 141.50 141.50

    2 Heavy mazdoor Day 19.00 132.00 2508.00

    3 Light mazdoor Day 19.00 130.50 2479.50

    Total Rs: 5129.00

    Add for small Tools and Plants @ 1% Rs: 51.29

    Add for Contractor's Profit @ 10% Rs: 512.90

    Add for hidden cost on Labour @ 15% Rs: 769.35

    Add for additional hidden cost on labour @ 5% Rs: 256.45

    Add for Contractor's Overheads @ 5% Rs: 256.45

    Total cost of Labour : Rs: 6975.44

    ABSTRACT:A. Cost of Materials including royalty charges Rs: 36706.00

    B. Hire charges of Machinery Rs: 0.00

    C. Cost of Labour Rs: 6975.44

    43681.44

    Add for enabling works @ 1.40% Rs: 611.54

    Total cost for 100.00 cum Rs: 44292.98

    Rate per cum Rs: 443.00

    Rate approved per cum Rs: 443.00

    Description Quantity Rate

    in Rs.

    Rate

    in Rs.

    Description

    Description

    Quantity Rate

    TOTAL Rs:

    Quantity

    in Rs.

    154

  • 8/13/2019 Data Rates-Dam Works-Part 8

    16/21

    DAM ALLIED WORKS

    SECTION: DAM AND ALLIED WORKS. YEAR : 2010-11 ITEM No: 53.a

    ITEM: Providing and constructing sand layerfor vertical / inclined graded filter media consisting of

    sand and coarse aggregate layers using approved materials satisfying specified filter creteria

    as per specifications including cost of all materials, machinery, labour, laying to required slope,

    compaction etc., complete with initiallead upto 50 m and all lifts.

    DATA:Consider 100 cum sand layer for vertical / inclined filter drain:

    Hearting embankment Sand layer

    Casing embankment

    1. Requirement of materials :

    Quantity of filter sand. (100 x 1.02 ) : 102.00 cum

    2. Requirement of machinery :

    No machinery is required.

    3. Requirement of workforce ( other than machinery crew ) :

    For conveying & laying sand ( 1 heavy & 1 light 6 cum / day ).

    Heavy mazdoor : 17 Nos.

    Light mazdoor : 17 Nos.

    Maistry : 1 No.

    RATE ANALYSIS UNIT : 100.00 cum

    A. MATERIALS:

    Sl No Unit Amount

    in Rs.

    1 Sand ( unscreened ) cum 102.00 154.00 15708.00

    0.00

    Total Rs: 15708.00

    Add for small Tools and Plants @ 1% Rs: 157.08

    Add for Contractor's Profit @ 10% Rs: 1570.80

    Add for Contractor's Overheads @ 5% Rs: 785.40

    Add royalty charges on Sand @ ( Included in material rate) Rs: 0.00

    Add royalty charges on CA @ ( Included in material rate) Rs: 0.00

    Total cost of Materials : Rs: 18221.28

    B. MACHINERY:Sl No Unit Amount

    in Rs.

    1 NIL 0.00 0.00 0.00

    0.00 0.00 0.00

    Total Rs: 0.00

    Add for small Tools and Plants @ 1% Rs: 0.00

    Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 0.00

    Add for Contractor's Overheads @ 5% Rs: 0.00

    Quantity

    Description

    Perticulars

    Quantity Rate

    in Rs.

    SKETCH SHOWING DETAILS OF INCLINED FILTER

    Rate

    in Rs.

    155

  • 8/13/2019 Data Rates-Dam Works-Part 8

    17/21

    DAM ALLIED WORKS

    Total hire charges of Machinery : Rs: 0.00

    C. LABOUR:

    Sl No Unit Amount

    in Rs.

    1 Maistry Day 1.00 141.50 141.50

    2 Heavy mazdoor Day 17.00 132.00 2244.00

    3 Light mazdoor Day 17.00 130.50 2218.50

    Total Rs: 4604.00

    Add for small Tools and Plants @ 1% Rs: 46.04

    Add for Contractor's Profit @ 10% Rs: 460.40

    Add for hidden cost on Labour @ 15% Rs: 690.60

    Add for additional hidden cost on labour @ 5% Rs: 230.20

    Add for Contractor's Overheads @ 5% Rs: 230.20

    Total cost of Labour : Rs: 6261.44

    ABSTRACT:

    A. Cost of Materials including royalty charges Rs: 18221.28

    B. Hire charges of Machinery Rs: 0.00

    C. Cost of Labour Rs: 6261.44

    24482.72

    Add for enabling works @ 1.40% Rs: 342.76

    Total cost for 100.00 cum Rs: 24825.48

    Rate per cum Rs: 248.00

    Rate approved per cum Rs: 248.00

    SECTION: DAM AND ALLIED WORKS. YEAR : 2010-11 ITEM No: 53.b

    ITEM: Providing and constructing 10 mm down coarse aggregate layer for vertical / inclined

    graded filter media consisting of sand and coarse aggregate layers using approved materials

    satisfying specified filter creteria as per specifications including cost of all materials, machinery,

    labour, laying to required slope, compaction etc., complete with initiallead upto 50 m and all

    lifts.

    DATA:Consider 100 cum 10 mm down coarse aggregate layer for filter drain:

    Hearting embankment 10 mm down coarse aggregate filter layer

    Casing embankment

    1. Requirement of materials :

    Quantity of 10 mm down filter aggregate. ( 100 x 1.02 ) : 102.00 cum

    2. Requirement of machinery :

    No machinery is required.

    3. Requirement of workforce ( other than machinery crew ) :

    For conveying & laying 10 mm down CA ( 1 heavy & 1 light 5 cum / day ).

    Heavy mazdoor : 20 Nos.

    in Rs.

    TOTAL Rs:

    Description Quantity Rate

    SKETCH SHOWING DETAILS OF INCLINED FILTER

    156

  • 8/13/2019 Data Rates-Dam Works-Part 8

    18/21

    DAM ALLIED WORKS

    Light mazdoor : 20 Nos.

    Maistry : 1 No.

    RATE ANALYSIS UNIT : 100.00 cum

    A. MATERIALS:

    Sl No Unit Amount

    in Rs.

    1 Coarse aggregate 10 mm down cum 102.00 669.00 68238.00

    0.00 0.00 0.00

    Total Rs: 68238.00

    Add for small Tools and Plants @ 1% Rs: 682.38

    Add for Contractor's Profit @ 10% Rs: 6823.80

    Add for Contractor's Overheads @ 5% Rs: 3411.90

    Add royalty charges on Sand @ ( Included in material rate) Rs: 0.00

    Add royalty charges on CA @ ( Included in material rate) Rs: 0.00

    Total cost of Materials : Rs: 79156.08

    B. MACHINERY:

    Sl No Unit Amount

    in Rs.

    1 NIL 0.00 0.00 0.00

    0.00 0.00 0.00

    Total Rs: 0.00

    Add for small Tools and Plants @ 1% Rs: 0.00

    Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 0.00

    Add for Contractor's Overheads @ 5% Rs: 0.00

    Total hire charges of Machinery : Rs: 0.00

    C. LABOUR:

    Sl No Unit Amount

    in Rs.

    1 Maistry Day 1.00 141.50 141.50

    2 Heavy mazdoor Day 20.00 132.00 2640.00

    3 Light mazdoor Day 20.00 130.50 2610.00

    Total Rs: 5391.50

    Add for small Tools and Plants @ 1% Rs: 53.92

    Add for Contractor's Profit @ 10% Rs: 539.15

    Add for hidden cost on Labour @ 15% Rs: 808.73

    Add for additional hidden cost on labour @ 5% Rs: 269.58

    Add for Contractor's Overheads @ 5% Rs: 269.58

    Total cost of Labour : Rs: 7332.44

    ABSTRACT:

    A. Cost of Materials including royalty charges Rs: 79156.08B. Hire charges of Machinery Rs: 0.00

    C. Cost of Labour Rs: 7332.44

    86488.52

    Add for enabling works @ 1.40% Rs: 1210.84

    Total cost for 100.00 cum Rs: 87699.36

    Rate per cum Rs: 877.00

    Rate approved per cum Rs: 877.00

    Rate

    Perticulars Quantity Rate

    in Rs.

    Description Quantity

    in Rs.

    Rate

    in Rs.

    Description Quantity

    TOTAL Rs:

    157

  • 8/13/2019 Data Rates-Dam Works-Part 8

    19/21

    DAM ALLIED WORKS

    SECTION: DAM AND ALLIED WORKS. YEAR : 2010-11 ITEM No: 53.c

    ITEM: Providing and constructing 20 mm down coarse aggregate layer for vertical / inclined

    graded filter media consisting of sand and coarse aggregate layers using approved materials

    satisfying specified filter creteria as per specifications including cost of all materials, machinery,

    labour, laying to required slope, compaction etc., complete with initiallead upto 50 m and all

    lifts.

    DATA:Consider 100 cum 20 mm down coarse aggregate layer for filter drain:

    Hearting embankment 20 mm down coarse aggregate filter layer

    Casing embankment

    1. Requirement of materials :Quantity of 20 mm down filter aggregate. ( 100 x 1.02 ) : 102.00 cum

    20 mm down filter shall contain 75 % 20-10 mm & 25 % 10 mm down

    2. Requirement of machinery :

    No machinery is required.

    3. Requirement of workforce ( other than machinery crew ) :

    For conveying & laying 20 mm down CA ( 1 heavy & 1 light 5 cum / day ).

    Heavy mazdoor : 20 Nos.

    Light mazdoor : 20 Nos.

    Maistry : 1 No.

    RATE ANALYSIS UNIT : 100.00 cum

    A. MATERIALS:

    Sl No Unit Amount

    in Rs.

    1 Coarse aggregate 20-10 mm ( 75 % ) cum 76.50 520.00 39780.00

    2 Coarse aggregate 10 mm down ( 25 % ) cum 25.50 669.00 17059.50

    Total Rs: 56839.50

    Add for small Tools and Plants @ 1% Rs: 568.40

    Add for Contractor's Profit @ 10% Rs: 5683.95

    Add for Contractor's Overheads @ 5% Rs: 2841.98

    Add royalty charges on Sand @ ( Included in material rate) Rs: 0.00

    Add royalty charges on CA @ ( Included in material rate) Rs: 0.00

    Total cost of Materials : Rs: 65933.82

    B. MACHINERY:

    Sl No Unit Amount

    in Rs.1 NIL 0.00 0.00 0.00

    0.00 0.00 0.00

    Total Rs: 0.00

    Add for small Tools and Plants @ 1% Rs: 0.00

    Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 0.00

    Add for Contractor's Overheads @ 5% Rs: 0.00

    Total hire charges of Machinery : Rs: 0.00

    SKETCH SHOWING DETAILS OF INCLINED FILTER

    Perticulars Rate

    Quantity

    in Rs.

    Rate

    in Rs.

    Quantity

    Description

    158

  • 8/13/2019 Data Rates-Dam Works-Part 8

    20/21

    DAM ALLIED WORKS

    C. LABOUR:

    Sl No Unit Amount

    in Rs.

    1 Maistry Day 1.00 141.50 141.50

    2 Heavy mazdoor Day 20.00 132.00 2640.00

    3 Light mazdoor Day 20.00 130.50 2610.00

    Total Rs: 5391.50

    Add for small Tools and Plants @ 1% Rs: 53.92

    Add for Contractor's Profit @ 10% Rs: 539.15

    Add for hidden cost on Labour @ 15% Rs: 808.73

    Add for additional hidden cost on labour @ 5% Rs: 269.58

    Add for Contractor's Overheads @ 5% Rs: 269.58

    Total cost of Labour : Rs: 7332.44

    ABSTRACT:

    A. Cost of Materials including royalty charges Rs: 65933.82B. Hire charges of Machinery Rs: 0.00

    C. Cost of Labour Rs: 7332.44

    73266.26

    Add for enabling works @ 1.40% Rs: 1025.73

    Total cost for 100.00 cum Rs: 74291.99

    Rate per cum Rs: 743.00

    Rate approved per cum Rs: 743.00

    SECTION: DAM AND ALLIED WORKS. YEAR : 2010-11 ITEM No: 53.d

    ITEM: Providing and constructing 40 mm down coarse aggregate layer for vertical / inclined

    graded filter media consisting of sand and coarse aggregate layers using approved materials

    satisfying specified filter creteria as per specifications including cost of all materials, machinery,

    labour, laying to required slope, compaction etc., complete with initiallead upto 50 m and all

    lifts.

    DATA:Consider 100 cum 40 mm down coarse aggregate layer for filter drain:

    Hearting embankment 40 mm down coarse aggregate filter layer

    Casing embankment

    1. Requirement of materials :

    Quantity of 40-10 mm filter aggregate. ( 100 x 1.02 ) : 102.00 cum

    40-10 mm filter shall contain 85 % 40-20 mm & 15 % 20-10 mm.2. Requirement of machinery :

    No machinery is required.

    3. Requirement of workforce ( other than machinery crew ) :

    For conveying & laying 40-10 mm CA ( 1 heavy & 1 light 5 cum / day ).

    Heavy mazdoor : 20 Nos.

    Light mazdoor : 20 Nos.

    Maistry : 1 No.

    in Rs.

    TOTAL Rs:

    Quantity RateDescription

    SKETCH SHOWING DETAILS OF INCLINED FILTER

    159

  • 8/13/2019 Data Rates-Dam Works-Part 8

    21/21

    DAM ALLIED WORKS

    RATE ANALYSIS UNIT : 100.00 cum

    A. MATERIALS:

    Sl No Unit Amount

    in Rs.

    1 Coarse aggregate 40-20 mm ( 85 % ) cum 86.70 381.00 33032.70

    2 Coarse aggregate 20-10 mm ( 15 % ) cum 15.30 520.00 7956.00

    Total Rs: 40988.70

    Add for small Tools and Plants @ 1% Rs: 409.89

    Add for Contractor's Profit @ 10% Rs: 4098.87

    Add for Contractor's Overheads @ 5% Rs: 2049.44

    Add royalty charges on Sand @ ( Included in material rate) Rs: 0.00

    Add royalty charges on CA @ ( Included in material rate) Rs: 0.00

    Total cost of Materials : Rs: 47546.89

    B. MACHINERY:

    Sl No Unit Amount

    in Rs.1 NIL 0.00 0.00 0.00

    0.00 0.00 0.00

    Total Rs: 0.00

    Add for small Tools and Plants @ 1% Rs: 0.00

    Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 0.00

    Add for Contractor's Overheads @ 5% Rs: 0.00

    Total hire charges of Machinery : Rs: 0.00

    C. LABOUR:

    Sl No Unit Amount

    in Rs.

    1 Maistry Day 1.00 141.50 141.50

    2 Heavy mazdoor Day 20.00 132.00 2640.00

    3 Light mazdoor Day 20.00 130.50 2610.00

    Total Rs: 5391.50

    Add for small Tools and Plants @ 1% Rs: 53.92

    Add for Contractor's Profit @ 10% Rs: 539.15

    Add for hidden cost on Labour @ 15% Rs: 808.73

    Add for additional hidden cost on labour @ 5% Rs: 269.58

    Add for Contractor's Overheads @ 5% Rs: 269.58

    Total cost of Labour : Rs: 7332.44

    ABSTRACT:

    A. Cost of Materials including royalty charges Rs: 47546.89

    B. Hire charges of Machinery Rs: 0.00

    C. Cost of Labour Rs: 7332.44

    54879.33Add for enabling works @ 1.40% Rs: 768.31

    Total cost for 100.00 cum Rs: 55647.64

    Rate per cum Rs: 556.00

    Rate approved per cum Rs: 556.00

    SECTION: DAM AND ALLIED WORKS. YEAR : 2010-11 ITEM No: 53.e

    ITEM: Providing and constructing 80 mm down coarse aggregate layer for vertical / inclined

    Rate

    in Rs.

    Description Quantity Rate

    Perticulars Quantity

    in Rs.

    TOTAL Rs:

    in Rs.

    Description Quantity Rate