 TUNNEL AND ALLIED WORKS Deploy 2 Agitator cars for conveying concrete. The rate of conc reti ng for 2 agit ator car s wit h 50 min / hr wor king : : 3.50 cum / hr Progress per shift of 8 hours: ( 8 x 3.50 ) : 28 cum 1. Require ment o f mate rials : Cement for mix with 1 % wastage ( 28 x 270 x 1.01 ) : 7636 kg Cement for incidentals @ 1 kg / cum ( 28 x 1 ) :28 kg Coarse aggregate 40-20 mm size range ( 28 x 0.9 x 0.5 x 1.02 ) : 12.85 cum Coarse aggregate 20-10 mm size range ( 28 x 0.9 x 0.3 x 1.02 ) : 7.70 cum Coarse aggregate 10-4.75 mm size ( 28 x 0.9 x 0.2 x 1.02 ) : 5.15 cum Fine aggregate ( 28 x 0.4 x 1.02 ) : 11.40 cum Super plasticiser ( 28 x 0.81 x 1.02 ) : 23.00 ltrs 2. Require ment o f mach inery : Deploy 6 cum / hour rated capacity batching plant for 8 hours for production of concrete. Deploy 2 Nos 2 cum capacity agitator cars for 8 hours for conveying concrete. Deploy 1 Needle vibrater 40 mm dia for 8 hours for vibrating concrete. Deploy 1 Pump 10 hp for 4.00 hour for water required for concrete mixing / curing / cleaning etc. 3. Formwo rk & scaffo lding : For kerb / bed concreting average 1 sqm shuttering is required per cum of concrete. Requirement of shuttering for 28 cum concrete : 28 sqm 4. Require ment of workfo rce ( other than mach inery crew ) : Consider batching of materials and conveyance & laying of concrete by manual labour. Maistry ( 1 @ batching plant and 1 @ placing point ) : 2 Nos. Mason Cl I : 1 No. Mason Cl II : 1 No. Cement handling mazdoor for loading cement to BP bin : 2 Nos. Heavy mazdoor: for remixing & filling mortar pans : 2 Nos. for loading mortar pans : 2 Nos. for laying concrete : 2 Nos. for cleaning bed and assisting Mason : 1 No. for miscellaneous works at BP : 1 No. Light mazdoor: for conveying concrete @ 2 cum / day : 14 Nos. for cleaning, curing & miscellaneous : 1 No. 5. Re-han dling le ad for material s:  As cement store can be located close to BP no re-ha ndling lea d consider ed. Consider 2 cement handling mazdoors for loading cement to BP bin.  As coarse a nd fine ag gregates can be stocked near the BP no re-handlin g lead co nsidered. Consider 4 heavy and 4 light mazdoors for loading CA to BP bins @ 6 cum / day Consider 2 heavy and 2 light mazdoors for loading FA to BP bins @ 6 cum / day  RATE ANALYSIS UNIT : 28.00 cum A. MATERIALS:  Sl No Unit Amount in Rs. 1 Cement 43 Gr kg 7636.00 4.00 30544.00 Cement for incidentals @ 1 kg / cum kg 28.00 4.00 112.00 2 Fine aggregate ( screened ) cum 11.40 199.00 2268.60 Contd  Perticulars in Rs. Quantity Rate 60

Transcript of Data Rates Tunnel Works 4

8/13/2019 Data Rates Tunnel Works 4

http://slidepdf.com/reader/full/data-rates-tunnel-works-4 1/21

  TUNNEL AND ALLIED WORKS

Deploy 2 Agitator cars for conveying concrete.

The rate of concreting for 2 agitator cars with 50 min / hr working : : 3.50 cum / hr 

Progress per shift of 8 hours: ( 8 x 3.50 ) : 28 cum

1. Requirement of materials :

Cement for mix with 1 % wastage ( 28 x 270 x 1.01 ) : 7636 kg

Cement for incidentals @ 1 kg / cum ( 28 x 1 ) : 28 kg

Coarse aggregate 40-20 mm size range ( 28 x 0.9 x 0.5 x 1.02 ) : 12.85 cum

Coarse aggregate 20-10 mm size range ( 28 x 0.9 x 0.3 x 1.02 ) : 7.70 cum

Coarse aggregate 10-4.75 mm size ( 28 x 0.9 x 0.2 x 1.02 ) : 5.15 cum

Fine aggregate ( 28 x 0.4 x 1.02 ) : 11.40 cum

Super plasticiser ( 28 x 0.81 x 1.02 ) : 23.00 ltrs

2. Requirement of machinery :

Deploy 6 cum / hour rated capacity batching plant for 8 hours for production of concrete.

Deploy 2 Nos 2 cum capacity agitator cars for 8 hours for conveying concrete.

Deploy 1 Needle vibrater 40 mm dia for 8 hours for vibrating concrete.

Deploy 1 Pump 10 hp for 4.00 hour for water required for concrete mixing / curing / cleaning etc.3. Formwork & scaffolding :

For kerb / bed concreting average 1 sqm shuttering is required per cum of concrete.

Requirement of shuttering for 28 cum concrete : 28 sqm

4. Requirement of workforce ( other than machinery crew ) :

Consider batching of materials and conveyance & laying of concrete by manual labour.

Maistry ( 1 @ batching plant and 1 @ placing point ) : 2 Nos.

Mason Cl I : 1 No.

Mason Cl II : 1 No.

Cement handling mazdoor 

for loading cement to BP bin : 2 Nos.

Heavy mazdoor:

for remixing & filling mortar pans : 2 Nos.

for loading mortar pans : 2 Nos.

for laying concrete : 2 Nos.

for cleaning bed and assisting Mason : 1 No.

for miscellaneous works at BP : 1 No.

Light mazdoor:

for conveying concrete @ 2 cum / day : 14 Nos.

for cleaning, curing & miscellaneous : 1 No.

5. Re-handling lead for materials:

 As cement store can be located close to BP no re-handling lead considered.

Consider 2 cement handling mazdoors for loading cement to BP bin.

 As coarse and fine aggregates can be stocked near the BP no re-handling lead considered.

Consider 4 heavy and 4 light mazdoors for loading CA to BP bins @ 6 cum / day

Consider 2 heavy and 2 light mazdoors for loading FA to BP bins @ 6 cum / day

  RATE ANALYSIS UNIT : 28.00 cumA. MATERIALS:

 Sl No Unit Amount

in Rs.

1 Cement 43 Gr kg 7636.00 4.00 30544.00

Cement for incidentals @ 1 kg / cum kg 28.00 4.00 112.00

2 Fine aggregate ( screened ) cum 11.40 199.00 2268.60

Contd  

Perticulars

in Rs.

Quantity Rate

60

8/13/2019 Data Rates Tunnel Works 4

http://slidepdf.com/reader/full/data-rates-tunnel-works-4 2/21

  TUNNEL AND ALLIED WORKS

A. MATERIALS ( Contd ) :

 Sl No Unit Amount

in Rs.

Contd  

3 Coarse aggregate 40-20 mm cum 12.85 381.00 4895.85

Coarse aggregate 20-10 mm cum 7.70 520.00 4004.00

Coarse aggregate 10-4.75 mm cum 5.15 669.00 3445.35

4 Super plasticiser ltr 23.00 75.00 1725.00

5 Use rate of shuttering for kerb / bed sqm 28.00 117.30 3284.52

Supports for shuttering @ 5 % 164.23

6 Sundries LS 4.00 30.00 120.00

Total Rs: 50563.55

 Add for small Tools and Plants @ 1% Rs: 505.64

 Add for Contractor's Profit @ 10% Rs: 5056.35

 Add for Contractor's Overheads @ 5% Rs: 2528.18

 Add Royalty charges on CA @ ( Included in material rate ) Rs: 0.00

 Add Royalty charges on FA @ ( Included in material rate ) Rs: 0.00Total cost of Materials : Rs: 58653.72

B. MACHINERY:

 Sl No Unit Amount

in Rs.

1 Batching plant 6 cum / hr rated capacity Hour 8.00 130.00 1040.00

Fuel / Energy charges Hour 8.00 125.00 1000.00

2 Agitator car 2 cum ( 2 Nos ) Hour 16.00 628.00 10048.00

Fuel / Energy charges Hour 16.00 605.00 9680.00

3 Needle Vibrator Hour 8.00 7.00 56.00

Fuel / Energy charges Hour 8.00 5.00 40.00

4 Pump 10 hp ( Ele ) Hour 4.00 5.00 20.00

Fuel / Energy charges Hour 4.00 50.00 200.00

5 Sundries LS 3.00 30.00 90.00

Total Rs: 22174.00

 Add for small Tools and Plants @ 1% Rs: 221.74

 Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 1101.00

 Add for Contractor's Overheads @ 5% Rs: 1108.70

Total hire charges of Machinery : Rs: 24605.44

C. LABOUR:

 Sl No Unit Amount

in Rs.

1 Crew for Batching plant Hour 8.00 108.20 865.60

2 Crew for Agitator car Hour 16.00 90.80 1452.80

3 Crew for vibrator Hour 8.00 53.30 426.40

4 Crew for pump Hour 4.00 26.90 107.605 Masom Cl I Day 1.00 159.00 159.00

6 Mason Cl II Day 1.00 148.50 148.50

7 Hammerman for scaling bed Day 1.00 146.00 146.00

8 Maistry Day 2.00 141.50 283.00

Contd  

Description

Description

in Rs.

 Quantity Rate

Perticulars Quantity Rate

in Rs.

 Quantity Rate

in Rs.

61

8/13/2019 Data Rates Tunnel Works 4

http://slidepdf.com/reader/full/data-rates-tunnel-works-4 3/21

  TUNNEL AND ALLIED WORKS

C. LABOUR ( Contd ) :

 Sl No Unit Amount

in Rs.

Contd  

9 Cement handling mazdoor  

for loading cement to BP bin Day 2.00 134.00 268.00

10 Heavy mazdoor  

for miscellaneous work at BP Day 1.00 132.00 132.00

for scaling & cleaning bed Day 1.00 132.00 132.00

for loading CA to BP bins Day 4.00 132.00 528.00

for loading FA to BP bin Day 2.00 132.00 264.00

for laying concrete Day 6.00 132.00 792.00

11 Light mazdoor  

for loading CA to BP bins Day 4.00 130.50 522.00

for loading FA to BP bin Day 2.00 130.50 261.00

for conveying concrete Day 14.00 130.50 1827.00

for curing / miscellaneous Day 1.00 130.50 130.50

12 Labour charges for shuttering sqm 28.00 33.17 928.62Labour charges for supports @ 5 % 46.43

Total Rs: 9420.45

 Add for small Tools and Plants @ 1% Rs: 94.20

 Add for Contractor's Profit @ 10% Rs: 942.05

 Add for hidden cost on Labour @ 15% Rs: 1413.07

 Add for additional hidden cost on labour @ 10% Rs: 942.05

 Add for Contractor's Overheads @ 5% Rs: 471.02

Total cost of Labour : Rs: 13282.84

ABSTRACT:

 A. Cost of Materials including royalty charges Rs: 58653.72

B. Hire charges of Machinery Rs: 24605.44

C. Cost of Labour Rs: 13282.84

TOTAL Rs: 96541.99

 Add for Air and Water line @ 0.50% Rs: 482.71

 Add for Ventilation @ 0.00% Rs: 0.00

 Add for Lighting @ 1.90% Rs: 1834.30

 Add for Ele sub-station / Demand charges @ 4.20% Rs: 4054.76

 Add for other enabling works @ 1.70% Rs: 1641.21

  Total cost for 28.00 cum Rs: 104554.98

Rate per cum Rs: 3734.00

Rate approved per cum Rs: 3734.00

SECTION: TUNNEL AND ALLIED WORKS. YEAR: 2010-11   ITEM No: 18

ITEM: Providing and laying insitu vibrated M-20  ( 28 days cube compressive strength not less than

20 N / sqmm ) grade cement concrete using 40 mm and down size approved clean, hard,graded aggregates crushed from tunnel muck for sides and arch lining including cost of all

materials, machinery, labour, formwork, batching, mixing, conveying upto placing point in

agitator cars, placing in position, levelling, vibrating, finishing, curing, ventilation, lighting,

drainage and all other ancillary operations etc., complete with lead upto 1 km and all lifts.

( Cement content 300 kg / cum with use of super plasticiser ).

Description Quantity Rate

in Rs.

62

8/13/2019 Data Rates Tunnel Works 4

http://slidepdf.com/reader/full/data-rates-tunnel-works-4 4/21

  TUNNEL AND ALLIED WORKS

Note: Rubble stones and stone chips for coarse aggregate crushing shall be issued at dump yard at

specified issue rates.

DATA:Concrete mix details per cum for 80-100 mm slump:

Cement 43 Gr : 300 kg

Fine aggregate @ 700 kg / cum : 0.44 cum

Coarse aggregate 40 mm down size @ 1250 kg / cum : 0.87 cum

Blending ratio : 50 : 30 : 20

Concrete admixture ( Super plasticiser ) : 0.90 ltr  

  Excavated line

  Gantry shuttering

  Concrete lining

  Gantry frame

  Gantry track

  INDICATIVE ARRANGEMENT FOR ARCH / SIDE CONCRETING

Diameter of tunnel ( finished ) considered : 5.00 m

Hight of tunnel ( finished ) considered : 5.00 m

Track mounted collapsible gantry considered for supporting sides and arch concrete.

 Assume 9 m long collapsible type steel gantry

Quantity of concrete / gantry considering 30 cm thick lining : 32.75 cum

( considering 60 cm hight kerb above bed level already laid )

Concrete for filling support reaches & pay line margin @ 45 % : : 14.75 cum

 ( for av. 10 cm pay line margin filling & 10 % tunnel length with supports )

 Average quantity of concrete / gantry length of lining say : 48.00 cum

Placing concrete for sides and arch : Placer pump

Cycle time for one round trip:

Turning and spotting : 2 min

Loading 4 mixes of 0.5 cum @ 5 min per mix : 20 min

Running time from BP to placing point av. 1 km : 10 min

Unloading concrete to placer drum : 24 min

Return trip to BP : 10 min

Total cycle time for round trip : 66 min

Consider 2 cum capacity agitator cars for conveying concrete.

Rate of concreting for 2 agitator cars with 50 min / hr working : 3.0 cum / hr 

 ( 2 x 2 x 60 x 50 / 60 / 66 )

Progress per shift of 8 hours: ( 8 x 3.00 ) : 24 cumTime required for concreting one gantry length ( 48 / 3 ) : 16 hours

Cycle time of various operations for concreting:

Cleaning / scaling bed for laying track line : 2.00 hours

Dismantling & extending track line : 4.00 hours

63

8/13/2019 Data Rates Tunnel Works 4

http://slidepdf.com/reader/full/data-rates-tunnel-works-4 5/21

  TUNNEL AND ALLIED WORKS

Releasing / moving / aligning gantry : 4.00 hours

Cleaning & Oiling gantry / Bulk head fixing : 4.00 hours

Placer pipe assembling for different positions : 6.00 hours

Concreting 48 cum @ 3.00 cum per hour : 16.00 hours

Miscellaneous / Break downs / pipe clogging etc : 4.00 hours

Setting time before release of gantry : 12.00 hours

Considering cleaning / scaling bed / track dismsntling and erection are carried out as parallel

activities during setting time of concrete, the total cycle time for one gantry length concreting

will be about 48 hours.

Out of 6 shifts ( 48 hours ) 3 shifts are considered as concreting shifts and 3 shifts are

considered as preparatory shifts.

Consider 48 cum concrete for rate analysis.

1. Requirement of materials :

Cement for mix with 1 % wastage ( 488 x 300 x 1.01 ) : 14544 kg

Cement for incidentals @ 1 kg / cum ( 48 x 1 ) : 48 kg

Coarse aggregate 40-20 mm size range ( 48 x 0.87 x 0.5 x 1.02 ) : 21.30 cum

Coarse aggregate 20-10 mm size range ( 48 x 0.87 x 0.3 x 1.02 ) : 12.80 cum

Coarse aggregate 10-4.75 mm size ( 48 x 0.87 x 0.2 x 1.02 ) : 8.50 cum

Fine aggregate ( 48 x 0.44 x 1.02 ) : 21.55 cum

Super plasticiser ( 48 x 0.90 x 1.02 ) : 44.00 ltrs2. Requirement of machinery :

Deploy 6 cum / hour rated capacity batching plant for 16 hours for production of concrete.

Deploy 2 Nos 2 cum capacity agitator cars for 16 hours for conveying concrete.

Deploy 8.5 cmm air compressor ( ele ) for 16 hours for supplying air to placer pump.

Deploy pneumatically operated placer pump for 16 hours for pumping concrete.

Deploy 1 Needle vibrater 40 mm dia for 16 hours for vibrating concrete.

Deploy 1 Pump 10 hp for 8 hours for water required for concrete mixing / curing / cleaning etc.

3. Formwork & scaffolding :

Track mounted collapsible gantry for supporting sides / arch concrete : 100 sqm

End shuttering ( front face ) : 6 sqm

In view of track mounted gantry no scaffolding required.

4. Requirement of workforce ( other than machinery crew ) :

Consider batching of materials and conveyance & laying of concrete by manual labour.

Maistry ( 1 @ batching plant and 1 @ placing point for 2 shifts ) : 4 Nos.

Mason Cl I ( 1 in each shift for 2 shifts ) : 2 Nos.

Foreman : 1 No.

Surveyor : 1 No.

Stone chiseller Cl II : 0.5 No.

Fitter shuttering : 1 No.

Helper shuttering : 1 No.

Khalasi ( 4 for 0.5 day ) : 2 Nos.

Heavy mazdoor:

for miscellaneous works at BP ( 1 in each shift for 2 shifts ) : 2 Nos.

for miscellaneous works at placer point ( 1 in each shift for 2 shifts ) 2 Nos.

Light mazdoor:

for cleaning, curing & miscellaneous ( 1 in each shift for 2 shifts ) : 2 Nos.

5. Re-handling lead for materials: As cement store can be located close to BP no re-handling lead considered.

Consider 4 cement handling mazdoors ( 2 in each shift ) for loading cement to BP bin.

64

8/13/2019 Data Rates Tunnel Works 4

http://slidepdf.com/reader/full/data-rates-tunnel-works-4 6/21

  TUNNEL AND ALLIED WORKS

 As coarse and fine aggregates can be stocked near the BP no re-handling lead considered.

Consider 6 heavy and 6 light mazdoors ( 3 each in each shift ) for loading CA to BP bins.

Consider 4 heavy and 4 light mazdoors ( 2 each in each shift ) for loading FA to BP bins.

6. Use rate of materials :

Surface area of gantry for sides and arch portion say : 105 sqm

Weight of gantry @ 150 kg / sqm say : 16 tonnes

Cost of gantry including cost of steel, fabrication, painting, transportation and erection:

Cost of beams / angles at 50 % @ Rs: 37950.00 / tonne Rs: 303600.00

Cost of plates @ at 40 % @ Rs: 40000.00 / tonne Rs: 256000.00

Cost of wheels / Jacks at 10 % @ Rs: 90000.00 / tonne Rs: 144000.00

Cost of fabrication & painting @ Rs: 15000.00 / tonne Rs: 240000.00

Total Rs: 943600.00

 Add for rails / fixtures etc., @ 7.5% Rs: 70770.00

 Add for transportation, erection & dismantling @ 12% Rs: 113232.00

Total Rs: 1127602.00

Less salvage value @ 10% ( - ) Rs: -112760.20

Total Rs: 1014841.80

 Add for shutter oil at 0.2 ltr /sqm @ Rs: 25.00 / ltr Rs: 525.00

Total Rs: 1015366.80

Considering 100 uses cost per use of gantry Rs: 10153.67

 Add for maintenance / repairs / replacements etc., @ 25% Rs: 2538.42Total Rs: 12692.09

Use rate of gantry / sqm / use considering 100 sqm effective area Rs: 126.92

Use rate of gantry / sqm / use Rs: 126.92

Requirement of end shutter : 6 sqm

Use rate of end shutter per sqm ( Annexure-A Item-17 ) Rs: 117.30

  RATE ANALYSIS UNIT : 48.00 cum

A. MATERIALS:

 Sl No Unit Amount

in Rs.

1 Cement 43 Gr kg 14544.00 4.00 58176.00

Cement for incidentals @ 1 kg / cum kg 48.00 4.00 192.00

2 Fine aggregate ( screened ) cum 21.55 199.00 4288.45

3 Coarse aggregate 40-20 mm cum 21.30 381.00 8115.30

Coarse aggregate 20-10 mm cum 12.80 520.00 6656.00

Coarse aggregate 10-4.75 mm cum 8.50 669.00 5686.50

4 Super plasticiser ltr 44.00 75.00 3300.00

5 Use rate of end shuttering sqm 6.00 117.30 703.83

6 Use rate of steel gantry sqm 100.00 126.92 12692.09

7 Sundries ( placer pipe etc ) LS 6.00 30.00 180.00

Total Rs: 99990.16

 Add for small Tools and Plants @ 1% Rs: 999.90

 Add for Contractor's Profit @ 10% Rs: 9999.02

 Add for Contractor's Overheads @ 5% Rs: 4999.51

 Add Royalty charges on CA @ ( Included in material rate ) Rs: 0.00

 Add Royalty charges on FA @ ( Included in material rate ) Rs: 0.00

Total cost of Materials : Rs: 115988.59

B. MACHINERY:

Perticulars Quantity Rate

in Rs.

65

8/13/2019 Data Rates Tunnel Works 4

http://slidepdf.com/reader/full/data-rates-tunnel-works-4 7/21

  TUNNEL AND ALLIED WORKS

 Sl No Unit Amount

in Rs.

1 Air compressor ( Ele ) 8.5 cmm Hour 16.00 108.00 1728.00

  Fuel / Energy charges @ 75 % load Hour 12.00 282.00 3384.00

2 Batching plant 6 cum / hr rated capacity Hour 16.00 130.00 2080.00

Fuel / Energy charges Hour 16.00 125.00 2000.00

3 Agitator car 2 cum ( 2 Nos ) Hour 32.00 628.00 20096.00

Fuel / Energy charges Hour 32.00 605.00 19360.00

4 Concrete placer pump Hour 16.00 133.00 2128.00

Fuel / Energy charges Hour 16.00 3.00 48.00

5 Needle Vibrator / Shutter vibrator Hour 16.00 7.00 112.00

Fuel / Energy charges Hour 16.00 5.00 80.00

6 Pump 10 hp ( Ele ) Hour 8.00 5.00 40.00

Fuel / Energy charges Hour 8.00 50.00 400.00

7 Sundries LS 6.00 30.00 180.00

Total Rs: 51636.00

 Add for small Tools and Plants @ 1% Rs: 516.36

 Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 2545.20

 Add for Contractor's Overheads @ 5% Rs: 2581.80

Total hire charges of Machinery : Rs: 57279.36

C. LABOUR:

 Sl No Unit Amount

in Rs.

1 Crew charges for Air compressor Hour 16.00 56.40 902.40

2 Crew charges for Batching plant Hour 16.00 108.20 1731.20

3 Crew charges for Agitator car Hour 32.00 90.80 2905.60

4 Crew charges for placer pump Hour 16.00 28.80 460.80

5 Crew charges for vibrator Hour 16.00 53.30 852.80

6 Crew charges for Pump Hour 8.00 26.90 215.20

7 Stone chiseller Cl II

for scaling & cleaning Day 0.50 146.00 73.00

8 Surveyer  

for laying / aligning track Day 0.50 154.50 77.25

for moving / positioning gantry Day 0.50 154.50 77.25

9 Foreman

for laying / aligning track Day 0.50 177.00 88.50

for releasing / moving gantry Day 0.50 177.00 88.50

10 Khalasi

for releasing / moving gantry ( 4 x 0.5 ) Day 2.00 145.50 291.00

11 Fitter shuttering

for bulk head / placer pipe fixing ( 0.5 x 2 Day 1.00 148.50 148.50

12 Helper shuttering

for bulk head / placer pipe fixing ( 0.5 x 2 Day 1.00 141.50 141.50

13 Cement handling mazdoor 

for loading cement to BP bin ( 2 x 2 ) Day 4.00 134.00 536.00

Contd  

C. LABOUR ( Contd ) :

 Sl No Unit Amount

Description

Description Quantity Rate

in Rs.

 Quantity Rate

in Rs.

Description Quantity Rate

66

8/13/2019 Data Rates Tunnel Works 4

http://slidepdf.com/reader/full/data-rates-tunnel-works-4 8/21

  TUNNEL AND ALLIED WORKS

in Rs.

Contd  

14 Heavy mazdoor  

for loading CA to BP bins Day 6.00 132.00 792.00

for loading FA to BP bin Day 4.00 132.00 528.00

for miscellaneous works of BP ( 1 x 2 ) Day 2.00 132.00 264.00

for misc works @ placer point ( 1 x 2 ) Day 2.00 132.00 264.00

15 Masom Cl I

for Laying concrete by placer ( 1 x 2 ) Day 2.00 159.00 318.00

16 Light mazdoor  

for loading CA to BP bins Day 6.00 130.50 783.00

for loading FA to BP bin Day 4.00 130.50 522.00

for curing / miscellaneous Day 2.00 130.50 261.00

17 Maistry ( 2 x 2 ) Day 4.00 141.50 566.00

Total Rs: 12887.50

 Add for small Tools and Plants @ 1% Rs: 128.88

 Add for Contractor's Profit @ 10% Rs: 1288.75

 Add for hidden cost on Labour @ 15% Rs: 1933.13

 Add for additional hidden cost on labour @ 10% Rs: 1288.75

 Add for Contractor's Overheads @ 5% Rs: 644.38

Total cost of Labour : Rs: 18171.38

ABSTRACT:

 A. Cost of Materials including royalty charges Rs: 115988.59

B. Hire charges of Machinery Rs: 57279.36

C. Cost of Labour Rs: 18171.38

TOTAL Rs: 191439.32

 Add for Air and Water line @ 0.50% Rs: 957.20

 Add for Ventilation @ 0.00% Rs: 0.00

 Add for Lighting @ 1.90% Rs: 3637.35

 Add for Ele sub-station / Demand charges @ 4.20% Rs: 8040.45

 Add for other enabling works @ 1.70% Rs: 3254.47

  Total cost for 48.00 cum Rs: 207328.79

Rate per cum Rs: 4319.00

Rate approved per cum Rs: 4319.00

SECTION: TUNNEL AND ALLIED WORKS. YEAR: 2010-11   ITEM No: 19

ITEM: Drilling 32 mm diameter grout holes in concrete / rock by percussion drilling using jack

hammer or stooper drills as directed to specified depth for consolidation / contact grouting

including cost of all materials, machinery, labour, cleaning holes, ventilation, lighting, drainage

and all other ancillary operations etc., complete.

DATA:Diameter of hole for consolidation / contact grouting : 32 mm

Rate of drilling by jack hammer in open area : 8 m / hour  

The rate of drilling for consolidation / contact grouting will be slow in view of frequent shifting of 

drilling jumbo / air and water hoses from place to place.

 Average rate of drilling considering 50 % time for shifting : 4 m / hour 

Consider 100 m drilling for analysis:

Consider 4 jack hammers / stooper drills for drilling grout holes.

Hourly progress of drilling with 50 min / hr working ( 4 x 4 x 50 / 60 ) : 13.3 m

in Rs.

67

8/13/2019 Data Rates Tunnel Works 4

http://slidepdf.com/reader/full/data-rates-tunnel-works-4 9/21

  TUNNEL AND ALLIED WORKS

Time for drilling 100 m ( 100 / 13.3 ) say : 8 hours

1. Requirement of materials :

No materials required.

2. Requirement of machinery :

Deploy 1 Air compressor 15 cmm for 8 hours with 50 minutes per hour working

Deploy 4 Jack hammers / Stooper drills for 8 hours

Deploy Drilling jumbo for 8 hours.

Deploy 10 hp pump for 4 hours for pumping water to storage tank.

3. Requirement of workforce ( other than machinery crew ) :

Maistry for marking hole locations and supervision of drilling work : 1 No.

Heavy mazdoor for assisting maistry and miscellaneous works : 1 No.

4. Use rate of materials:

Cost of jack hammer drill rod 2.5m @ Rs: 5660.00 / Each Rs: 5660.00

Life of drill rod with reconditioning : 150 m

Use rate of drill rod per m drilling ( cost / life ) Rs: 37.73

Cost of air hose 25 m @ Rs: 150.00 / Rm Rs: 3750.00

Life of air hose : 800 hours

Use rate of air hose per hour ( cost / life ) Rs: 4.69

Cost of water hose 25 m @ Rs: 128.00 / Rm Rs: 3200.00

Life of water hose : 800 hours

Use rate of water hose per hour ( cost / life ) Rs: 4.00In view of shallow holes and wet drilling regular flushing is not required.

  RATE ANALYSIS UNIT : 100.00 Rm

A. MATERIALS:

 Sl No Unit Amount

in Rs.

1 Use rate of drill rod 2.5 m long Rm 100.00 37.73 3773.33

Reconditioning charges @ 10% 377.33

2 Use rate of air hose 4 Nos Hour 32.00 4.69 150.00

3 Use rate of water hose 4 Nos Hour 32.00 4.00 128.00

4 Sundries LS 3.00 30.00 90.00

Total Rs: 4518.67

 Add for small Tools and Plants @ 1% Rs: 45.19

 Add for Contractor's Profit @ 10% Rs: 451.87

 Add for Contractor's Overheads @ 5% Rs: 225.93

Total cost of Materials : Rs: 5241.65

B. MACHINERY:

 Sl No Unit Amount

in Rs.

1 Air compressor 15 cmm ( ele ) Hour 8.00 108.00 864.00

Fuel / Energy charges Hour 8.00 627.00 5016.00

2 Pump 10 hp ( ele ) Hour 4.00 5.00 20.00

Fuel / Energy charges Hour 4.00 50.00 200.00

3 Jack hammer / Stooper drills Hour 32.00 14.00 448.00

Contd  

B. MACHINERY ( Contd ) :

 Sl No Unit Amount

in Rs.

Contd  

Perticulars

Description

in Rs.

in Rs.

 Quantity Rate

in Rs.

Description Quantity Rate

Quantity Rate

68

8/13/2019 Data Rates Tunnel Works 4

http://slidepdf.com/reader/full/data-rates-tunnel-works-4 10/21

  TUNNEL AND ALLIED WORKS

Fuel / Energy charges Hour 32.00 5.00 160.00

4 Pusher leg Hour 32.00 8.00 256.00

Fuel / Energy charges Hour 32.00 3.00 96.00

5 Drilling jumbo Hour 8.00 322.00 2576.00

Fuel / Energy charges Hour 8.00 30.00 240.00

6 Sundries LS 5.00 30.00 150.00

Total Rs: 10026.00

 Add for small Tools and Plants @ 1% Rs: 100.26

 Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 586.20

 Add for Contractor's Overheads @ 5% Rs: 501.30

Total hire charges of Machinery : Rs: 11213.76

C. LABOUR:

 Sl No Unit Amount

in Rs.

1 Crew for Air compressor Hour 8.00 60.10 480.80

2 Crew for pump Hour 4.00 26.90 107.60

3 Crew for Jack hammer Hour 32.00 111.90 3580.80

4 Crew for Drilling jumbo Hour 8.00 60.50 484.00

5 Maistry Day 1.00 141.50 141.50

6 Heavy mazdoor Day 1.00 132.00 132.00Total Rs: 4926.70

 Add for small Tools and Plants @ 1% Rs: 49.27

 Add for Contractor's Profit @ 10% Rs: 492.67

 Add for hidden cost on Labour @ 15% Rs: 739.01

 Add for additional hidden cost on labour @ 10% Rs: 492.67

 Add for Contractor's Overheads @ 5% Rs: 246.34

Total cost of Labour : Rs: 6946.65

ABSTRACT:

 A. Cost of Materials Rs: 5241.65

B. Hire charges of Machinery Rs: 11213.76

C. Cost of Labour Rs: 6946.65

TOTAL Rs: 23402.06

 Add for Air and Water line @ 0.50% Rs: 117.01

 Add for Ventilation @ 0.00% Rs: 0.00

 Add for Lighting @ 1.90% Rs: 444.64

 Add for Ele sub-station / Demand charges @ 4.20% Rs: 982.89

 Add for other enabling works @ 1.70% Rs: 397.84

  Total cost for 100.00 Rm Rs: 25344.43

Rate per Rm Rs: 253.00

Rate approved per Rm Rs: 253.00

SECTION: TUNNEL AND ALLIED WORKS. YEAR: 2010-11   ITEM No: 20

ITEM: Grouting cement slurry in grout holes under specified pressure for consolidation / contact

grouting  including cost of all materials, machinery, labour, redrilling wherever necessary,

ventilation,lighting, drainage and other ancillary operations etc., complete with lead upto 1 km

and all lifts.

DATA:In contact zones, perticularly in crown portion, the grout intake will be heavy due to inadequate

Description Quantity Rate

in Rs.

69

8/13/2019 Data Rates Tunnel Works 4

http://slidepdf.com/reader/full/data-rates-tunnel-works-4 11/21

  TUNNEL AND ALLIED WORKS

packing of concrete during placement of concrete by placer pump.

The average grout intake in the contact zone is considered at 75 kg per metre. Beyond contact

zone the grout intake may vary from 25 kg per metre to 50 kg per metre depending on the

extent of opening of joints in rock during / after excavation.

The average gruot intake for consilidation / contact grouting is considered at 50 kg per metre.

The average progress of grouting per shift is considered at 1500 kg.

Consider grouting of 1500 kg cement for rate analysis.

1. Requirement of materials :

Cement with 1 % wastage ( 1500 x 1.01 ) : 1515 kg

2. Requirement of machinery :

Deploy Grout pump with accessories for 8 hours.

Deploy Drilling jumbo for 2 hours during grouting of top holes.

Deploy 10 hp pump for 2 hours for pumping water to storage tank.

3. Requirement of workforce ( other than machinery crew ) :

Maistry for supervision of grouting work : 1 No.

Heavy mazdoor for assisting maistry and for miscellaneous works : 1 No.

4. Re-handling lead for materials:

 As cement store is proposed near batching plant and is to be conveyed inside tunnel for grouting

1 km re-handling lead including load and un-loading is considered

5. Use rate of materials:

Cost of grout hose 50 m @ Rs: 150.00 / Rm Rs: 7500.00Life of grout hose : 800 hours

Use rate of grout hose per hour ( cost / life ) Rs: 9.38

Cost of water hose 50 m @ Rs: 128.00 / Rm Rs: 6400.00

Life of water hose : 800 hours

Use rate of water hose per hour ( cost / life ) Rs: 8.00

  RATE ANALYSIS UNIT : 1.50 tonne

A. MATERIALS:

 Sl No Unit Amount

in Rs.

1 Cement including 1 % wastage tonne 1.52 4000.00 6080.00

2 Use rate of grouting hose 50 m Hour 8.00 9.38 75.00

3 Use rate of water hose 50 m Hour 8.00 8.00 64.00

4 Sundries LS 2.00 30.00 60.00

Total Rs: 6279.00

 Add for small Tools and Plants @ 1% Rs: 62.79

 Add for Contractor's Profit @ 10% Rs: 627.90

 Add for Contractor's Overheads @ 5% Rs: 313.95

Total cost of Materials : Rs: 7283.64

B. MACHINERY: Sl No Unit Amount

in Rs.

1 Grouting machine Hour 8.00 19.00 152.00

Fuel / Energy charges Hour 8.00 25.00 200.00

2 Pump 10 hp ( ele ) Hour 2.00 5.00 10.00

Fuel / Energy charges Hour 2.00 50.00 100.00

3 Drilling jumbo Hour 2.00 322.00 644.00

Fuel / Energy charges Hour 2.00 30.00 60.00

Description

Perticulars

in Rs.

 Quantity Rate

in Rs.

Quantity Rate

70

8/13/2019 Data Rates Tunnel Works 4

http://slidepdf.com/reader/full/data-rates-tunnel-works-4 12/21

  TUNNEL AND ALLIED WORKS

4 Sundries LS 1.25 30.00 37.50

Total Rs: 1203.50

 Add for small Tools and Plants @ 1% Rs: 12.04

 Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 39.75

 Add for Contractor's Overheads @ 5% Rs: 60.18

Total hire charges of Machinery : Rs: 1315.46

C. LABOUR:

 Sl No Unit Amount

in Rs.

1 Crew for Grout pump Hour 8.00 89.20 713.60

2 Crew for pump Hour 2.00 26.90 53.80

3 Crew for Drilling jumbo Hour 2.00 60.50 121.00

4 Maistry Day 1.00 141.50 141.50

5 Heavy mazdoor Day 1.00 132.00 132.00

Total Rs: 1161.90

 Add for small Tools and Plants @ 1% Rs: 11.62

 Add for Contractor's Profit @ 10% Rs: 116.19

 Add for hidden cost on Labour @ 15% Rs: 174.29

 Add for additional hidden cost on labour @ 10% Rs: 116.19

 Add for Contractor's Overheads @ 5% Rs: 58.10Total cost of Labour : Rs: 1638.28

ABSTRACT:

 A. Cost of Materials Rs: 7283.64

B. Hire charges of Machinery Rs: 1315.46

C. Cost of Labour Rs: 1638.28

TOTAL Rs: 10237.38

 Add for Air and Water line @ 0.50% Rs: 51.19

 Add for Ventilation @ 0.00% Rs: 0.00

 Add for Lighting @ 1.90% Rs: 194.51

 Add for Ele sub-station / Demand charges @ 4.20% Rs: 429.97

 Add for other enabling works @ 1.70% Rs: 174.04

Total Rs: 11087.08

 Add for 1 km rehandling charges :

For cement 1.50 tonne @ Rs: 129.10 / tonne Rs: 193.65

  Total cost for 1.50 tonne Rs: 11280.73

Rate per tonne Rs: 7520.00

Rate approved per tonne Rs: 7520.00

SECTION: TUNNEL AND ALLIED WORKS. YEAR: 2010-11   ITEM No: 21

ITEM: Drilling 75 mm diameter drainage holes vertical or inclined in rock / concrete in tunnel by

percussion drilling using waggon drill or other suitable drilling equipment including cost of all

materials, machinery, labour, ventilation, lighting, drainage etc., complete.

DATA:Generally rate of drilling in rock or concrete inside tunnel will be less compared to drilling in

open area.

Rate of drilling by waggon drill in open area : 12 m / hour  

Considering about 25 percent reduction in efficiency the hourly progress of drilling by waggon

drill will be about 7.5 m considering 50 minutes per hour working.

Description Quantity Rate

in Rs.

71

8/13/2019 Data Rates Tunnel Works 4

http://slidepdf.com/reader/full/data-rates-tunnel-works-4 13/21

  TUNNEL AND ALLIED WORKS

Progress of drilling per shift by one waggon drill is considered at 60 m.

For use of 15 cmm compressor 2 waggon drills can be operated.

Progress of drilling per shift for 2 waggon drills : 120 m

Consider 120 m drilling for rate analysis.

1. Requirement of materials :

No materials required.

2. Requirement of machinery :

Deploy 1 air compressor 15 cmm for 8 hours for supplying air.

Deploy 2 waggon drills for 8 hours for drilling holes.

Deploy 10 hp pump for 6 hours for pumping water to storage tank.

3. Requirement of workforce ( other than machinery crew ) :

Maistry for marking hole locations and supervision of drilling work : 1 No.

Heavy mazdoor for assisting maistry and for miscellaneous works : 1 No.

4. Use rate of materials:

Cost of 75 mm dia T.C cross bit @ Rs: 7690.00 / Each Rs: 7690.00

Life of T.C cross bit 75 mm dia in rock : 80 m

Use rate of T.C cross bit per m drilling (cost / life) Rs: 96.13

Cost of 6 m extn rod with sleeve @ Rs: 3300.00 / Rm Rs: 19800.00

Life of extension rods : 1500 m

Use rate of 6 m extn rod per m drilling (cost / life) Rs: 13.20

Cost of air hose 20 m @ Rs: 150.00 / Rm Rs: 3000.00Life of air hose : 800 hours

Use rate of air hose 20 m per hour (cost / life) Rs: 3.75

Cost of water hose 20 m @ Rs: 128.00 Rs: 2560.00

Life of water hose : 800 hours

Use rate of water hose 20 m per hour (cost / life) Rs: 3.20

  RATE ANALYSIS UNIT: 120.00 Rm

A. MATERIALS:

 Sl No Unit Amount

in Rs.

1 Use rate of cross bit 75 mm dia Rm 120.00 96.13 11535.00

2 Use rate of air hose 20 m Hour 16.00 3.75 60.00

3 Use rate of water hose 20 m Hour 16.00 3.20 51.20

4 Use rate of extension rods Rm 120.00 13.20 1584.00

5 Sundries LS 0.50 30.00 15.00

Total Rs: 13245.20

 Add for small Tools and Plants @ 1% Rs: 132.45

 Add for Contractor's Profit @ 10% Rs: 1324.52

 Add for Contractor's Overheads @ 5% Rs: 662.26

Total cost of Materials : Rs: 15364.43

B. MACHINERY:

 Sl No Unit Amount

in Rs.

1 Waggon drill Hour 16.00 216.00 3456.00

Fuel / Energy charges Hour 16.00 9.00 144.00

2 Air compressor 15 cmm ( ele ) Hour 8.00 108.00 864.00

Fuel / Energy charges Hour 8.00 627.00 5016.00

3 Pump 10 hp ( ele ) Hour 6.00 5.00 30.00

Perticulars

Description

in Rs.

in Rs.

 Quantity Rate

Quantity Rate

72

8/13/2019 Data Rates Tunnel Works 4

http://slidepdf.com/reader/full/data-rates-tunnel-works-4 14/21

  TUNNEL AND ALLIED WORKS

Fuel / Energy charges Hour 6.00 50.00 300.00

4 Sundries LS 1.00 30.00 30.00

Total Rs: 9840.00

 Add for small Tools and Plants @ 1% Rs: 98.40

 Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 549.00

 Add for Contractor's Overheads @ 5% Rs: 492.00

Total hire charges of Machinery : Rs: 10979.40

C. LABOUR:

 Sl No Unit Amount

in Rs.

1 Crew for Waggon drill Hour 16.00 89.50 1432.00

2 Crew for Air compressor Hour 8.00 60.10 480.80

3 Crew for Pump Hour 6.00 26.90 161.40

4 Maistry Day 1.00 141.50 141.50

5 Heavy mazdoor Day 1.00 132.00 132.00

Total Rs: 2347.70

 Add for small Tools and Plants @ 1% Rs: 23.48

 Add for Contractor's Profit @ 10% Rs: 234.77

 Add for hidden cost on Labour @ 15% Rs: 352.16

 Add for additional hidden cost on labour @ 10% Rs: 234.77 Add for Contractor's Overheads @ 5% Rs: 117.39

Total cost of Labour : Rs: 3310.26

ABSTRACT:

 A. Cost of Materials Rs: 15364.43

B. Hire charges of Machinery Rs: 10979.40

C. Cost of Labour Rs: 3310.26

TOTAL Rs: 29654.09

 Add for Air and Water line @ 0.50% Rs: 148.27

 Add for Ventilation @ 0.00% Rs: 0.00

 Add for Lighting @ 1.90% Rs: 563.43

 Add for Ele sub-station / Demand charges @ 4.20% Rs: 1245.47

 Add for other enabling works @ 1.70% Rs: 504.12

  Total cost for 120.00 Rm Rs: 32115.38

Rate per Rm Rs: 268.00

Rate approved per Rm Rs: 268.00

Description Quantity Rate

in Rs.

73

8/13/2019 Data Rates Tunnel Works 4

http://slidepdf.com/reader/full/data-rates-tunnel-works-4 15/21

  TUNNEL AND ALLIED WORKS

ENABLING WORKS

ANNEXURES

DATA FOR PERCENTAGE PROVISIONS

FOR

74

8/13/2019 Data Rates Tunnel Works 4

http://slidepdf.com/reader/full/data-rates-tunnel-works-4 16/21

  TUNNEL AND ALLIED WORKS

75

8/13/2019 Data Rates Tunnel Works 4

http://slidepdf.com/reader/full/data-rates-tunnel-works-4 17/21

  TUNNEL AND ALLIED WORKS

SECTION: TUNNEL AND ALLIED WORKS. YEAR: 2010-11   Annexure-1

ITEM: Data for percentage provisions towards cost of Electric sub-station & Demand charges:

DATA:Estimation of electric power requirement for various equipments :

 Aggregate crushing plant 1 No. : 30 hp

Batching & mixing plant 1 No. : 25 hp

Vibrators 2 Nos. : 6 hp

 Air compressor 15 cmm 1 No. : 150 hp

 Air compressor 8.5 cmm 1 No. : 75 hp

Water supply / Dewatering pumps : 50 hp

Convey mucker 1 No. : 60 hp

Ventilation fans : 60 hp

Fabrication / Repair / Maintenance units : 20 hp

Major electric power consuming equipment is 15 cmm capacity air compressor.

 Air compressor 15 cmm 1 No. : 150 hp

Other equipments running simultaneously: Aggregate crushing plant 1 No. : 30 hp

Water supply / Dewatering pumps : 30 hp

Fabrication / Repair / Maintenance units : 20 hp

Total : 230 hp

Requirement of power in Kw ( 230 x 0.746 ) : 171.58 kw

 Add for lighting & miscellaneous requirements : 10.00 kw

 Add for reserve capacity @ 10 % : 18.42 kw

Total ( say ) : 200.00 kw

Capacity of sub-station required ( 200 / 0.85 ) : 250 KVA

Demand for power requirement is assumed to vary from 250 KVA to 150 KVA during

construction period of about 3 years.

 Average demand for electric power for 3 years is considered @. : : 200 KVA

Consider 2 Transformers of 250 KVA including 1 spare unit.

Capital cost of other sub-station equipments & distribution lines:

 Breakers & accessories( 2 Nos) @ Rs: 30000.00 / each Rs: 60000.00

Poles with fixtures 30 Nos @ Rs: 4200.00 / each Rs: 126000.00

HT / LT Line conductor 5 km @ Rs: 27000.00 / km Rs: 135000.00

Metering and other accessories LS Rs: 37500.00

Controls and Miscellaneous LS Rs: 37500.00

Total Rs: 396000.00

Life of sub-station equipments : 15 years

Salvage value : 10 percent

 Average capital cost 396000 x ( 15 + 1 ) / 3 Rs: 211200.00

Hire charges of sub-station equipments:

Depreciation per year 396000 x 0.9 / 15 Rs: 23760.00

Interest on av. Capital cost @ 11% Rs: 23232.00Maintenance & repairs @ 25 % of depreciation Rs: 5940.00

Miscellaneous charges @ 10 % of repair charges Rs: 594.00

Insurance charges on av capital cost @ 1% Rs: 2112.00

Total hire charges / year Rs: 55638.00

76

8/13/2019 Data Rates Tunnel Works 4

http://slidepdf.com/reader/full/data-rates-tunnel-works-4 18/21

  TUNNEL AND ALLIED WORKS

Cables & Fittings:

PVC cable 70 sqmm 100 m @ Rs: 250.00 / Rm Rs: 25000.00

PVC cable 25 sqmm 100 m @ Rs: 100.00 / Rm Rs: 10000.00

PVC cable 16 sqmm 1250 m @ Rs: 58.00 / Rm Rs: 72500.00

PVC cable 10sqmm/below 2000m @ Rs: 48.00 / Rm Rs: 96000.00

Miscellaneous fittings LS Rs: 7500.00

Total Rs: 211000.00

 Assume use of cables for 3 years with 50 percent salvage value.

Use rate of cables per year with 50 % salvage value Rs: 35166.67

  RATE ANALYSIS UNIT: 1000.00 Rm

 A. MATERIALS:

 Sl No Unit Amount

in Rs.

1 Use rate of cables Year 3.00 35166.67 105500.00

2 Anchors / supports for cables / lights LS 150.00 30.00 4500.00

3 Sundries ( tapes & consumeables ) LS 50.00 30.00 1500.00

Total Rs: 111500.00

 Add for small Tools and Plants @ 1% Rs: 1115.00 Add for Contractor's Profit @ 10% Rs: 11150.00

 Add for Contractor's Overheads @ 5% Rs: 5575.00

Total cost of Materials : Rs: 129340.00

B. MACHINERY:

 Sl No Unit Amount

in Rs.

1 Sub-station equipments Year 3.00 55638.00 166914.00

2 Transformer 250 KVA 2 Nos. Month 72.00 3523.00 253656.00

3 Demand charges for 3 years for 200 kVA

@ 85 % PF ( 200 x 3 x 12 x 0.85 ) KVA 6120.00 190.00 1162800.00

4 Sundries LS 50.00 30.00 1500.00

Total Rs: 1584870.00

 Add for small Tools and Plants @ 1% Rs: 15848.70

 Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 116430.00

 Add for Contractor's Overheads @ 5% Rs: 79243.50

Total hire charges of Machinery : Rs: 1796392.20

C. LABOUR:

 Sl No Unit Amount

in Rs.

1 Lineman 2 Nos. x 3 x 12 x 26 days Day 1872.00 141.50 264888.00

2 Electrician 2 Nos. x 3 x 12 x 26 days Day 1872.00 143.00 267696.00

3 Heavy mazdoor 2 Nos x 3 x 12 x 26 days Day 1872.00 132.00 247104.00

Total Rs: 779688.00

 Add for small Tools and Plants @ 1% Rs: 7796.88

 Add for Contractor's Profit @ 10% Rs: 77968.80 Add for hidden cost on Labour @ 15% Rs: 116953.20

 Add for additional hidden cost on labour @ 10% Rs: 77968.80

 Add for Contractor's Overheads @ 5% Rs: 38984.40

Total cost of Labour : Rs: 1099360.08

Description

Description

Perticulars RateQuantity

in Rs.

 Quantity Rate

in Rs.

Rate

in Rs.

 Quantity

77

8/13/2019 Data Rates Tunnel Works 4

http://slidepdf.com/reader/full/data-rates-tunnel-works-4 19/21

  TUNNEL AND ALLIED WORKS

D. ENABLING WORKS:

Enabling works for electric sub-station include shed for store and DG set / foundations for

sub-station equipments / fencing etc

Cost of enabling works for electric sub-station LS Rs: 60000.00

ABSTRACT:

 A. Cost of Materials Rs: 129340.00

B. Hire charges of Machinery Rs: 1796392.20

C. Cost of Labour Rs: 1099360.08

D. Enabling works Rs: 60000.00

  Total cost for 1000.00 Rm Rs: 3085092.28

Cost of electric sub-station and distribution lines is chargeable to all items as except transport

equipments all other equipments are operated using electric power.

 Approximate basic cost of 1 km tunnel:

Excavation ( Item-3 : 1.8 m / Blast ) : ( 55731.39 x 100 / 1.8 ) Rs: 30961882.78

Concrete( Item-18 : 7.7 cum/ Rm) :( 100 x 191439 x 7.7 / 48 ) Rs: 30710057.90

 All other items @ 20 % of excavation and concreting. Rs: 12334388.14

Total basic cost / km Rs: 74006328.81

Cost of electric sub-station and distribution lines ( excluding energy

charges ) as percentage of basic cost of all items:

100 x / : 4.17 say : 4.20 

SECTION: TUNNEL AND ALLIED WORKS. YEAR: 2010-11   Annexure-2

ITEM: Data for percentage provisions towards cost of air and water lines:

DATA:Consider 100 mm dia GI pipe for air line and 80 mm dia GI pipe for water line.

For 1 km tunnel consider 1250 m length air line including pipe line from air compressor shed

to tunnel / adit portal.

For 1 km tunnel consider 1500 m length water line including pipe line from pumping point to

starage water tank and from storage water tank to tunnel / adit portal.

 Air and water lines are extended inside the tunnel as the excavation progresses and are

dismantled progressively during concreting. Considering 24 months as the construction period

for 1 km tunnel the weighted average use of air and water lines will be for 18 months.

a. Cost of 1250 m 100 mm dia pipe @ Rs: 250.00 / Rm Rs: 312500.00

 Add for fittings / specials / valves etc @ 15% Rs: 46875.00

Total Rs: 359375.00

 Add for repair / replacements @ 25% Rs: 89843.75

Total cost of air line Rs: 449218.75

 As the air and water lines are laid in open and are prone to damage due blasting / rock falls

etc., the life of pipes is assumed at 6 years ( 4 uses ) with 20 percent salvage value.

Use rate of air line per year ( 0.8 x 449219 / 6 ) Rs: 59895.83

b. Cost of 1500 m 80 mm dia pipe @ Rs: 230.00 / Rm Rs: 345000.00

 Add for fittings / specials / valves etc @ 15% Rs: 51750.00

Total Rs: 396750.00

 Add for repair / replacements @ 25% Rs: 99187.50

Total cost of air line Rs: 495937.50Use rate of water line per year ( 0.8 x 495938 / 6 ) Rs: 66125.00

For laying / maintaining / dismantling air and water lines 1 pipe fitter and 2 heavy mazdoors

are assumed for 2 years with 50 percent utilisation for air / water lines.

3085092 74006329

78

8/13/2019 Data Rates Tunnel Works 4

http://slidepdf.com/reader/full/data-rates-tunnel-works-4 20/21

  TUNNEL AND ALLIED WORKS

  RATE ANALYSIS UNIT: 1000.00 Rm tunnel

 A. MATERIALS:

 Sl No Unit Amount

in Rs.

1 Use rate of 100 mm dia GI pipe Year 1.50 59895.83 89843.75

2 Use rate of 80 mm dia GI pipe Year 1.50 66125.00 99187.50

3 Sundries( sealing compound etc ) LS 50.00 30.00 1500.00

Total Rs: 190531.25

 Add for small Tools and Plants @ 1% Rs: 1905.31

 Add for Contractor's Profit @ 10% Rs: 19053.13

 Add for Contractor's Overheads @ 5% Rs: 9526.56

Total cost of Materials : Rs: 221016.25

B. MACHINERY:

 Sl No Unit Amount

in Rs.

1 NIL 0.00 0.00 0.00

0.00 0.00 0.00

Total Rs: 0.00

 Add for small Tools and Plants @ 1% Rs: 0.00

 Add for Contractor's Profit on DPOL/ Energy @ 10% Rs: 0.00 Add for Contractor's Overheads @ 5% Rs: 0.00

Total hire charges of Machinery : Rs: 0.00

C. LABOUR:

 Sl No Unit Amount

in Rs.

1 Pipe fitter ( 2 x 12 x 26 x 0.5 x 1 ) Day 312.00 152.50 47580.00

2 Heavy mazdoor ( 2 x 12 x 26 x 0.5 x 2) Day 624.00 132.00 82368.00

Total Rs: 129948.00

 Add for small Tools and Plants @ 1% Rs: 1299.48

 Add for Contractor's Profit @ 10% Rs: 12994.80

 Add for hidden cost on Labour @ 15% Rs: 19492.20

 Add for additional hidden cost on labour @ 10% Rs: 12994.80

 Add for Contractor's Overheads @ 5% Rs: 6497.40

Total cost of Labour : Rs: 183226.68

ABSTRACT:

 A. Cost of Materials Rs: 221016.25

B. Hire charges of Machinery Rs: 0.00

C. Cost of Labour Rs: 183226.68

TOTAL Rs: 404242.93

Cost of air and water lines is chargeable to all items requiring use of water.

 Approximate basic cost of 1 km tunnel:

Excavation ( Item-3 : 1.8 m / Blast ) : ( 55731.39 x 100 / 1.8 ) Rs: 30961882.78

Concrete( Item-18 : 7.7 cum/ Rm) :( 100 x 191439 x 7.7 / 48 ) Rs: 30710057.90

 All other items at 20 % of cost of excavation and concreting. Rs: 12334388.14

Total basic cost / km Rs: 74006328.81

Cost of air and water lines as percentage of basic cost of all items :100 x / : 0.55 

say : 0.50 

SECTION: TUNNEL AND ALLIED WORKS. YEAR: 2010-11   Annexure-3

Perticulars

Description

in Rs.

404243

in Rs.

Rate

74006329

RateQuantity

in Rs.

 Quantity

Description Quantity Rate

79

8/13/2019 Data Rates Tunnel Works 4

http://slidepdf.com/reader/full/data-rates-tunnel-works-4 21/21

  TUNNEL AND ALLIED WORKS

ITEM: Data for percentage provisions towards cost of ventilation system :

DATA:Length of ventilation duct 0.78 m dia for 1 km length of tunnel : 900 m

Length of v entilation duct 0.78 m dia for adit portion assumed : 300 m

Total length of ventilation duct : 1200 m

Generally twin fans of 20 hp each are installed at 300 m interval and are run for about 1 hour 

after each blast to clear off blasting fumes and dust.

It may also be necessary to run the ventilation fans for short periods during mucking in case

use of dumpers deployed for disposal of muck to remove exhaust fumes.

Requirement of materials for fabrication of 1200 m duct:

Plain GI sheet 1 mm thick Class II @ 22.5 kg per Rm : 27000 kg

MS angle 30 x 30 x 4 mm for ring @ 2 kg per Rm : 2400 kg

MS flats 50 x 4 mm for supporting pipes @ 2 kg per Rm : 2400 kg

Rivets for joints @ 0.4 kg per Rm : 480 kg

GI bolts and nuts for connecting pipes @ 0.25 kg per Rm : 300 kg

Shalimastic sealing compound for joints @ 0.2 kg per Rm : 240 kg

Binding wire @ 0.2 kg per Rm : 240 kg

 Anchors ( 2 Nos ) @ 2.5 m interval for supporting duct : 960 Nos

 Anchors ( 4 Nos ) for supporting fans at 300 m interval 16 Nos

Total : 976 Nos20 mm dia 1.2 m long rods for anchors & 2 m long rods for fans : : 3000 kg

Resin bond cement capsules for fixing anchors : 1000 Nos

Requirement of machinery :

For fabrication of ducts :

Bending machine @ 12 pipes of 2.5 m / day ( 1200 x 8 / 12 / 2.5 ) 320 hours

For conveying and erecting :

Tipper @ 6 pipes of 2.5 m / hour ( 1200 / 6 / 2.5 ) 80 hours

Drilling jumbo for fixing @ 30 m / day ( 1200 x 8 / 30 ) 320 hours

For dismantling and conveying :

Tipper @ 50 % of erection hours 40 hours

Drilling jumbo @ 50 % of erection hours 160 hours

Drilling for fixing anchor rods :

32 mm dia 1 m deep holes for anchors for duct & fans : 976 m

Cost of drilling 32 mm dia. hole ( Item 19 ) per Rm Rs: 253.00

  RATE ANALYSIS UNIT: 1200.00 Rm

FOR COST OF VENTLATION DUCT :

 A. MATERIALS:

 Sl No Unit Amount

in Rs.

1 Plain GI sheet kg 27000.00 49.80 1344600.00

2 MS angle 30 x 30 x 5 mm kg 2400.00 37.95 91080.00

3 MS flats kg 2400.00 40.00 96000.00

4 Rivets kg 480.00 50.00 24000.00

5 GI bolts and nuts kg 300.00 80.00 24000.00

6 Sundries ( gas / electrodes etc ) LS 100.00 30.00 3000.00

Total Rs: 1582680.00Contd  

 A. MATERIALS ( Contd ) :

 Sl No Unit AmountPerticulars Quantity Rate

Perticulars Quantity Rate

in Rs.