A PQ Case Study · Case study 40 Distribution Network Voltage related power quality issues in a...
Transcript of A PQ Case Study · Case study 40 Distribution Network Voltage related power quality issues in a...
Case study 40 Distribution Network Voltage related power quality issues in a food and beverage industry
A PQ Case Study
APQI (C) Copyright 2014 (December 2014) All Rights Reserved 1
A PQ Case Study CS 40 FNB 14
Distribution Network Voltage related power quality issues
in a food and beverage industry
Case study 40 Distribution Network Voltage related power quality issues in a food and beverage industry
A PQ Case Study
APQI (C) Copyright 2014 (December 2014) All Rights Reserved 2
40 Abstract: Power quality issues generated from
incoming grid are one of the prevalent
problems of power quality. Any
disturbance on the grid in the form of
huge load variation will affect entire grid.
Voltage dips, sags, swells, under voltage
and interruptions are still quite common
in Indian grid.
Digital electronics, computers and other
microprocessor based equipment are
more sensitive to power line disturbances
than other electrical equipment
depending on the quality of their power
supply and how they are interconnected.
The circuits in electronic equipment
operate on direct current (DC) power. The
source is an internal DC power supply
which converts, or rectifies, the AC power
supplied by the utility to the various DC
voltage levels required. Variations in the
AC power supply can therefore cause
power quality anomalies in computers
and power electronic components.
If there are heavy loads connected on the
same grid as of a sensitive process driven
manufacturing facility, any variation in the
heavy load at the grid will cause voltage
disturbances at the manufacturing facility.
In modern and state of the art automatic
food processing industries, any
disturbance in supply voltage parameter
in the form of voltage dip, sag, swell or
interruption can result in stoppage of the
manufacturing process.
The Case study below presents problems
faced by a beverage facility due to above
mentioned reasons. The power quality
issues were generated due to traction
load connected on the same grid as of the
industry. The case study also analyses
monetary loss due to each event of
voltage disturbance and mitigation
measure adopted by the industry.
Case study 40 Distribution Network Voltage related power quality issues in a food and beverage industry
A PQ Case Study
APQI (C) Copyright 2014 (December 2014) All Rights Reserved 3
Introduction Voltage related power quality issues are quite common and faced by most of the industries
in some way or other. Most of the time these voltage related power quality issues are not
taken seriously by concerned distribution companies and industries continue to pay a price
for these problems. Voltage sags/swell/interruptions are few voltage related power quality
issues that can have severe financial impact on industries. These events are time bound and
adversity of the events also depends on duration of each event. Information Technology
Industry Council (ITIC) developed a graph known as ITIC curve that provides a guideline for
safe operating limit of electronic equipment in case of there are any voltage variation.
Voltage Sag/Swells:
Voltage Sags are brief reductions in voltage, typically lasting from a cycle to a second or so,
or tens of milliseconds to hundreds of milliseconds. Voltage swells are brief increases in
voltage over the same time range. If reduction or increase in voltage lasts for longer
duration of time, then the phenomenon is known as under voltage or over voltage.
Voltage sags are caused by abrupt increases in loads such as short circuits or faults, motors
starting, or electric heaters turning on, or they are caused by abrupt increases in source
impedance, typically caused by a loose connection. Voltage swells are almost always caused
by an abrupt reduction in load on a circuit with a poor or damaged voltage regulator,
although they can also be caused by a damaged or loose neutral connection.
Fig-1 shows a typical voltage waveform related to sag.
Fig.1 Voltage waveform during sag event
Case study 40 Distribution Network Voltage related power quality issues in a food and beverage industry
A PQ Case Study
APQI (C) Copyright 2014 (December 2014) All Rights Reserved 4
Electronic or any sensitive equipments are affected most due to voltage sags and are prone
to malfunction or failure during the event of sag.
Voltage Interruptions:
A voltage interruption is a large decrease in RMS voltage to less than a small percentile of
the nominal voltage, or a complete loss of voltage.
Voltage interruptions may come from accidents like faults and component malfunctions, or
from scheduled downtime. Short voltage interruptions are typically the result of a
malfunction of a switching device or a deliberate or inadvertent operation of a fuse, circuit
breaker, or re-closer in response to faults and disturbances. Long interruptions are usually
the result of scheduled/unscheduled downtime, where part of an electrical power system is
disconnected in order to perform maintenance or repairs. Figure 2 shows voltage waveform
for an interruption event.
Fig.2 Voltage waveform during short interruption event
CBEMA/ITIC Curve:
In the 1970s, Computer and Business Equipment Manufacturers' Association (CBEMA)
developed one of the most frequently employed power acceptability curves as a guideline
for the organization's members' design of their power supplies. Basically, the CBEMA curve
was originally derived to describe the tolerance of mainframe computer business equipment
to the magnitude and duration of voltage variations on the power system. It eventually
became a standard design target for sensitive equipment to be applied on the power system
Case study 40 Distribution Network Voltage related power quality issues in a food and beverage industry
A PQ Case Study
APQI (C) Copyright 2014 (December 2014) All Rights Reserved 5
and a common format for reporting power quality variation data. It was later renamed as
Information Technology Industry Council (ITIC) curve. Fig 3 shows ITIC curve defining safe
zone for operation of electronic equipments.
A change in voltage causes a decrease or an increase in the amount of energy supplied to
components in an electrical power system, which leads to an amount of energy that is
different from the amount required for normal operations. A decrease in energy during a
voltage dip can cause equipment to reset or shut down and cause mechanical devices, such
as motors, to stall or overheat. An increase in voltage during a voltage swell can cause
immediate or long-term breakdown of components because of overheating.
Because the voltage level during a voltage interruption rapidly decays to zero, or to almost
zero, no energy is transferred to components in an electrical power system when there are
voltage interruptions. A voltage interruption therefore can cause the complete shutdown of
equipment and also can lead to damage. The curve has change in nominal change in voltage
(percentage) on Y axis and duration of the event on X axis in cycles and seconds.
Fig – 3 ITIC Curve
Voltage related events like voltage sags, swells or interruption can cause damage to
electronic equipments, resulting in loss of production and time for a continuous plant.
Case study 40 Distribution Network Voltage related power quality issues in a food and beverage industry
A PQ Case Study
APQI (C) Copyright 2014 (December 2014) All Rights Reserved 6
Background
Coca Cola is one of the leading beverage manufacturing companies in the world. Since its
inception in the year 1892, the company grew over the years to become leader in non
alcoholic beverages. Over the years it adopted best available manufacturing processes and
now its plants across the globe have most modern and automated manufacturing lines.
Hindustan Coca Cola Beaverages Pvt. Ltd (HCCB) Plant in Khurda Industrial Estate in one of
the largest and key bottling facilities in CBO with 2400bpm+ manufacturing capacity,
supported by 6 lines. Existing capacity includes 600bpm of Sparkling RGB, 600bpm of Juice
RGB, 720bpm (including 600bpm high speed line) of sparkling PET, 400ppm of Juice
Tetrapak and 75bpm retail Water. For the last few years, Khurda Industrial estate has been
experiencing poor quality of incoming power from Odisha State Electricity Board and all
major industries (including HCCB) in this estate have been impacted badly due to this issue.
It has become more significant for HCCB with addition of high speed PET, juice RGB and
Tetra capacities.
Current substation at Khurda industrial estate is connected to 220Kv grid from Menthsal
(about 25 kmtrs away from Khurda) through an incoming feeder near Khurda town.
Menthsal Grid is also connected to a railway feeder. There are frequent voltage drops and
unscheduled power cuts at Khurda substation due to distribution issues from this grid. This
gets further aggravated, with railway feeder also getting connected to this supply due to
frequent distribution issues. We have done various audits like Power quality audit, Energy
audit to find the actual root cause of the problem. With power quality getting deteriorated,
all major industries in Khurda has started working on to find a solution for the same.
The plant was facing problem of stoppage of production line causing loss of productivity.
The problems were mainly due to interruptions in power supply and under voltage events.
Apart from this, plant was also facing problems due to over voltage particularly failure of
electronic cards.
After each power supply interruption, there was some time required to resume
productivity. Time required to resume productivity after resumption of power varies from
10-15 minute. Table – 1 shows monetary loss plant was facing due to each event of supply
interruption.
Case study 40 Distribution Network Voltage related power quality issues in a food and beverage industry
A PQ Case Study
APQI (C) Copyright 2014 (December 2014) All Rights Reserved 7
Sl No Line
Line running time after
power resume in mins
Production Capacity per hour (No of
cases per hour)
Load factor
Actual Cases Lost
Monetary Loss in Rs per event
1 Krones 15 1500 80% 300 3168
2 Maaza 12 1500 80% 240 2534.4
3 RGB 10 1500 80% 200 2112
4 Kinley 10 300 80% 40 422.4
5 PET-140
15 933 80% 187 1970.496
Total Loss 10207
Table – 1 Monetary loss due to power supply interruption
Table – 2 shows number of events of power supply interruptions in each month.
Month Unscheduled Power cut Unbalanced Voltage Total No of Occurrences
No. of Occurrences No. of Occurrences
January'14 10 9 19
February'14 17 8 25
March'14 45 42 87
April'14 68 51 119
Table – 2 Power supply interruptions in each month
From above table it can be seen that from January to April 2014, number of under voltage
and unscheduled power supply interruptions were 250. With cost of each event being INR
10,207.00, plant lost around INR 2,551,750.00 during January – April 2014. Apart from loss
in productivity, plant also spent more money for operating DG set due to each event. This
increased energy cost along with GHG emission. From June 2014 onward Electrical energy
generated from DG set was 60% of total electrical energy usage. With average electricity
consumption of 9 lakh units per month, 5.4 lakh units were generated using DG set. With
average cost of electricity generation using DG set is around INR 17 per kWh and for grid
power cost of electrical energy being INR 8.5 per kWh, differential energy cost of DG set and
grid power is INR 8.5 per kWh. Plant is spending INR 4.5 Million per month additionally
Case study 40 Distribution Network Voltage related power quality issues in a food and beverage industry
A PQ Case Study
APQI (C) Copyright 2014 (December 2014) All Rights Reserved 8
towards electrical energy. With this trend, annual additional cost of electricity will be INR 55
Million due to furnace oil utilisation. In four months, production loss was around INR 2.5
Million. Extrapolating this, annual loss would be around INR 7.5 Million due to loss in
productivity. Total monetary loss incurred by the plant due to power supply interruptions
would be 62.5 Million INR per year.
In addition to cost, utilization of furnace oil will lead to release of additional 180 tonnes of
CO2eq to the atmosphere annually.
The increased use of DG is not due to non availability of power but due to poor quality of
supply power. With poor quality of supply, which is not desirable for the equipments, plant
is forced to use DG set despite availability of power. This has not only increased operating
cost of the plant but also carbon emission from plant.
CORRECTIVE ACTIONS BY PLANT: This being a frequent and quite common problem with regular occurrence, plant took
various measures like automatic switch over system for DG sets during power failure,
forward and reverse synchronisation system, and SCADA system.
SCADA system helped the operation team to monitor the voltage profile more closely. After
installation of SCADA system, plant team could identify cause of malfunctioning of various
sensitive equipments. After monitoring of the voltage profile at SCADA, it came to the
knowledge of the plant team that there are voltage dips in the system. Voltage drops to as
low as 15-20 Volts on the LT side for couple of mili seconds. During the events of voltage
dips, sensitive equipments do malfunction or drop out.
Synchronisation with Grid – forward and reverse process helped the operation team to
transfer power from switch over either to grid or to DG sets without interrupting the
production lines. During forward synchronization, DG's are switched on half an hour before
schedule power interruption. Before scheduled power interruptions, load is switched over
to DG sets. During reverse synchronization DG sets are kept running even after power from
the grid resumes. Once the system is synchronized, then load is transferred from DG set to
grid power without any disturbance to the manufacturing process. However,
Case study 40 Distribution Network Voltage related power quality issues in a food and beverage industry
A PQ Case Study
APQI (C) Copyright 2014 (December 2014) All Rights Reserved 9
synchronisation system helped only during the scheduled power interruptions. For un-
scheduled power interruptions, synchronization system was of little help.
In order to find more reliable solution during the un-scheduled power interruptions and
voltage variations, plant team carried out a detailed power quality study to find reason of
voltage variations and possible solution to mitigate the problem.
Summary of PQ Audit: The plant carried out a detailed power quality audit to find root cause of the problem.
Measurements were carried out at all critical locations and logged for longer duration of
time to record number of events and duration of each event.
The plant receives electrical power from state electricity Distribution Company from a
shared grid with railway traction. Fig-4 shows representative single line diagram of electrical
power supply to Coca Cola plant.
Fig – 4 Representative single line diagram of electrical power supply
As seen in the single line diagram, Coca Cola and other food processing industries in this
industry zone are connected to the 33 kV grid which is shared by traction load. Traction
substation is located at around 15 km from the plant. Traction load receives main power
Case study 40 Distribution Network Voltage related power quality issues in a food and beverage industry
A PQ Case Study
APQI (C) Copyright 2014 (December 2014) All Rights Reserved 10
from a dedicated traction supply feeder. During maintenance or any breakdown on the
traction feeder, power for the traction load is drawn from the industrial feeder as shown in
figure 4.
Fig 5 shows simplified single line diagram of the plant. The facility is getting 33 kV supply
from Central Electricity Supply Utility of Odisha (CESU). Contract demand is 4000 kVA with a
billing demand of 5628 kVA. The 33kV is stepped down to 440 V through one 2 MVA and
one 3.15 MVA transformer. In addition to supply from grid, the facility has 6 numbers of DG
sets and operated during scheduled/un-scheduled power cuts. Out of these 6 DG sets, 3 DG
are 1250 kVA, and rest 3 are 750 kVA, 500 kVA and 250 kVA rating.
Fig – 5 Simplified plant SLD
During the power quality audit, measurements were carried out at following points.
Sr. Number Measurement Point
1 33 kV main HT incomer
2 2000 kVA transformer – LT side
3 3150 kVA transformer – LT side
4 Krone UPS
Table – 3 Measurement points
In addition to above major locations, measurements were carried out at all load end MCC’s,
UPS and servo stabilizer. One of the UPS at Krone line was studied in detail.
Section below shows analysis of measurements at above locations.
Case study 40 Distribution Network Voltage related power quality issues in a food and beverage industry
A PQ Case Study
APQI (C) Copyright 2014 (December 2014) All Rights Reserved 11
33 kV main HT incomer:
Voltage Profile:
Measurements were carried out at 33 kV main incomer. Figure – 6 shows voltage profile at
the 33 kV incomer.
Fig – 6 Voltage profile at 33 kV main incomer
From the figure – 6 it can be seen that maximum voltage at HT incomer is 34.2 kV where as
minimum voltage at the incomer is 26.7 kV. As per Indian Electricity rules 2005 in the case
of high voltage (33kV), voltage variation should not be more than 6 per cent on the higher
side or by more than 9 per cent on the lower side. Voltage is dropping by 19% from 33 kV to
26.7 kV which is not acceptable as per Indian Electricity Rules.
Total Harmonics Distortions:
Figure – 7 shows total harmonic distortion at the 33 kV incoming feeder.
Fig – 7 Total Harmonic distortions at 33 kV incomer
Case study 40 Distribution Network Voltage related power quality issues in a food and beverage industry
A PQ Case Study
APQI (C) Copyright 2014 (December 2014) All Rights Reserved 12
Total voltage harmonic distortion at the 33 kV incomer were found to be within limit (5% as
specified by IEEE-519) at a maximum value of 4.3% but current harmonics were found to be
at a maximum value of 22.7% which is above acceptable limits of 15% as specified by IEEE-
519. At 33 kV feeders, voltage variation and current harmonics were found to be major
areas of concern.
Transformer – 2000 kVA & 3150 kVA:
Voltage Profile:
Measurements were carried out on LT side of 2000 and 3150 kVA transformer to record
voltage profile. Fig 8 & 9 shows voltage profile on LT side of the 2000 and 3150 kVA
transformer.
Fig – 8 Voltage profile at 2000 kVA transformer LT side
Fig – 9 Voltage profile at 3150 kVA transformer LT side
For 2000 kVA transformer the voltage varies from 203V to 252.3V whereas for 3150 kVA
transformer the voltage variation is from 199.3V to 266V. The voltage variation is more than
Case study 40 Distribution Network Voltage related power quality issues in a food and beverage industry
A PQ Case Study
APQI (C) Copyright 2014 (December 2014) All Rights Reserved 13
specified limit of Indian Electricity Rule. As per IE rule, in the case of low or medium voltage,
voltage variation should not be more than 6 per cent. The variation on LT side of the system
is due to voltage variation from grid at 33 kV. As the voltage variation on HT side is around
19% on the lower side, OLTC being a dynamic system is associated with time delay will not
able to response to sudden drop in voltage.
Total Harmonic Distortion:
Figure 10 and 11 shows total harmonic distortion at 2000 and 3150 kVA transformers on
their LT side.
Fig – 10 THD at 2000 kVA transformer
Fig – 11 THD at 3150 kVA transformer
The voltage harmonics at 2000 kVA transformer are varying from 2.2 to 5.6%. As per IEEE
519 standard, the voltage harmonic limit is 5%. Current Harmonics varies from 5.3 to 26.7%
which is above the limit.
Case study 40 Distribution Network Voltage related power quality issues in a food and beverage industry
A PQ Case Study
APQI (C) Copyright 2014 (December 2014) All Rights Reserved 14
The voltage harmonics are varying from 1.2 to 6.1%. As per IEEE 519 standard, the voltage
harmonic limit is 5%. Current Harmonics varies from 6.4 to 49% which is above the limit. As
per IEEE 519 standard, the current harmonic limit is 8%.
Above measurement result shows that there could be problem for the equipments installed
at the plant due to current harmonics and voltage variations. However, further analysis was
carried out to find if voltage variations are safe or unsafe for electronic components at the
plant.
As per the IEC 61000-4-30 standard for the power quality, the power quality analyzer
connected at the LT incomer of 2000 kVA Transformer – 1, 3150 kVA Transformer – 2 &
1600 KVA Servo Stabilizer output side which is under the transformer – 2. The following
parameters set in the meter to capture any deviations.
Nominal Voltage : 240Volts (L-N) 415Volts (L-L)
Voltage upper limit : 110%
Voltage lower limit : 90%
Nominal frequency : 50Hz
Recorded events of voltage variations were plotted against ITIC curve.
Figure 12 and 13 shows analysis of under voltage and over voltage event with ITIC curve at
transformer 2000 kVA and 3150 kVA respectively.
Fig – 12 Sags and over voltage events on ITIC curve 2000 kVA transformer
Over voltage events
Under voltage events
Case study 40 Distribution Network Voltage related power quality issues in a food and beverage industry
A PQ Case Study
APQI (C) Copyright 2014 (December 2014) All Rights Reserved 15
Fig – 12 Sags and over voltage events on ITIC curve 3150 kVA transformer
In addition to transformers, measurements were carried out on output side of servo
stabilizer for sag, over voltage & interruption events and are recorded during the study. The
detail of the same are given below in figure 13.
Fig – 13 Sags and over voltage events on ITIC curve – 1600 kVA Servo stabilizer
From the measurement and analysis of the voltage variation, sags, over voltage and
interruptions, it was evident that voltage fluctuations, over voltages, voltage sags and
interruptions due to un-scheduled power cuts were main reason for the failure of critical
components in the plant. Even servo stabilizer was not able to control the issues and there
was variation in the output voltage of the servo stabilizer.
Over voltage events
Under voltage events
Interruptions due
to power cuts
Over voltage events
Under voltage events
Interruptions due
to power cuts
Case study 40 Distribution Network Voltage related power quality issues in a food and beverage industry
A PQ Case Study
APQI (C) Copyright 2014 (December 2014) All Rights Reserved 16
The plant also have few number of UPS installed which were installed along with installation
of the line as part of project. Some of the sections at the Krone line were provided with UPS
at the design stage. Measurements were carried out at the installed UPS output for voltage
profile. Figure – 14 shows voltage profile at the output of UPS.
Fig – 14 Voltage, current and power profile at UPS
It can be seen that there is negligible variation in voltage profile at the output of UPS. Even
though there are variation in the supply voltage more than 10 %, there is negligible (0.1%)
variation in voltage profile at the output of the UPS.
Problem definition and mitigation:
As seen from Figure – 4, Coca Cola plant receives its supply from 132 kV grid and stepped
down to 33 kV at utility sub-station. The same 33 kV grid also supplies to traction load
during maintenance or breakdown at dedicated grid of traction. When traction load is on
the industry grid of 33 kV and electrical rail is comes in operation, there are frequent
changes in the operating condition. The load varies from starting, accelerating, idle running
and braking. Due to frequent change in load and various trains operating at a given time,
there is huge load variation on the grid. Due to sudden change in high loads, voltage across
the grid and downstream of the grid gets affected. The variation in voltage and interruptions
at downstream of the grid will affect all industries connected on the same grid.
As the problem is generated from outside the boundary limit of the plant, the plant
requested state electricity DISCOM to separate traction load from industrial supply. Plant is
Voltage – 396 to 397
Volts
Case study 40 Distribution Network Voltage related power quality issues in a food and beverage industry
A PQ Case Study
APQI (C) Copyright 2014 (December 2014) All Rights Reserved 17
losing around INR 62.5 Million per year due to higher energy cost and loss in productivity. In
addition to monetary loss, around 180 tonnes of additional green house gas is being
released to atmosphere due to use of diesel in DG sets.
As the issue is with distribution system, mitigation at distribution needs to be carried out. As
is understood, serious PQ issues occur when the industry is fed from Narendrapur, 150 km
away over a 132 kV single ckt line, through two levels of transformation. The short ckt level
at Khurda 33kV bus is very low causing high variations in voltage for small increase or
decrease in load. When the feed is from the Chandaka grid the situation is better but the
reliability of supply from Chandaka is poor because of disturbances at Meramundli and
other upstream grid s/s.
The other major PQ issue arises when traction load is supplied from 33 kV industry feeder
and the loaded phase experiences serious under voltage and rapid variations. Traction load
does introduce 2nd 3rd and 5th harmonics and under un favorable conditions this could cause
voltage amplification. An SVC with ‘Load balancing control’ can balance out the voltage
supply but can be an expensive solution.
As mentioned in the case study short time severe voltage dips are being recorded by SCADA.
This could be due to flash faults in nearby grid, discharges across weak insulators, lightning
arrester operation nearby, or loose earth connections. This may not be a serious problem ,
but if it is causing tripping/ load dropping, the protection settings have to be adjusted and
reason for these 2ms duration dips identified. We should also see if these are reflected in
the recordings taken upstream and downstream.
Interruption records are alarming, as much as 60 times in some months! Auto changeover of
supply through RMUs could be a solution, provided an alternate supply was available. Not
having an alternate dedicated feeder clearly shows a gap in planning. Such an industry
complex having a load of about 18 to 20 MW should have alternate supplies from two
equally reliable HV circuits with auto change over. In this case the alternate stand-by
sources from Puri and Narendrapur are very weak and unreliable.
It is understood from CESU that at Arugul where IIT Bhubaneswar is coming up, a 3*40 MVA
station is under commissioning and a 20 MVA transformer is already commissioned.
Case study 40 Distribution Network Voltage related power quality issues in a food and beverage industry
A PQ Case Study
APQI (C) Copyright 2014 (December 2014) All Rights Reserved 18
Apparently the industries , can draw power from there, by drawing a 12 km feeder. It
probably needs to convince CESU that CESU should plan to supply the 20 and odd MW load
to industry complex from the new S/S from their own resources.
The other alternative is when a sub station ATRI gets commissioned by OPTCL and Khurda
gets strengthened by a connection from Mendhasal which is a stronger bus. The down
stream connections from the ATRI bus are not frozen and the Industry consortium can try
for the connection. One of the above two alternatives has to be sorted out with the
CESU/OPTCL authorities. The traction load must have a separate connection from a voltage
level one or two steps higher and the supply feeder to Traction should be provided with an
SVC with load balancing features. All this needs to be checked through a system study to
ensure that voltage sags and O/V , stay within permissible limits , that the system recovers
from faults fast without load dropping, and voltage unbalance with Traction load is within
limit.
To handle frequent interruptions due to faults a study may be done to have sectionalizers
and autoreclosures installed as a reliability enhancement measure.
As of now, In order to protect its failures and loss of productivity, based on the power
quality study and its finding, the plant team has decided to install two numbers of UPS each
of 600 kVA at critical locations to avoid breakdown arising due to voltage variations and un-
scheduled power interruptions.
The present case is an example of ‘how poor quality power supply’ can affect a running
industry and be counterproductive to industrial growth . In some states special Electronic
zones (SEZs) have been created by Industry consortiums to ensure quality power and
uninterrupted production.
Case study 40 Distribution Network Voltage related power quality issues in a food and beverage industry
A PQ Case Study
APQI (C) Copyright 2014 (December 2014) All Rights Reserved 19
About the authors:
Mr. Sampath Arul:
Mr. Sampath Arul is a Graduate in BE Electrical Engineering with 16yrs of Industrial experience. Presently, working in Maintenance in Hindustan Coca –Cola Khurda. Had successfully completed various Kaizen Projects on Energy saving like Lob/Kwh and DG efficiency improvement from
2.82units/lit to 3.5units/lit
Prof. A. K. Tripathy – Expert Review
Prof. A. K. Tripathy is presently Advisor (research) at Silicon Institute of Technology Bhubaneswar Odisha.
Professor A. K. Tripathy is a graduate in Electrical Engineering from NIT Rourkela and M.Tech from I.I.S c Bangalore. He started his career in SAIL as a maintenance engineer between 1972 and 1976 before he joined BHEL in 1976 in its consultancy division. Till 2004 Prof. Tripathy was in BHEL and Chief of Transmission and Distribution of BHEL. He
was involved in several high technology projects in the area of HVDC, FACTS, UHV Transmission, Substation design, industrial consultancy and power system analysis. In 2004 he was awarded BHEL’s Anusandhan award and in 2005 , the P.M.Ahluwalia award for outstanding contribution to Power sector.
He was Director General of Central Power research institute (CPRI) Bangalore between 2004 and 2008. During this period he was chairman of ETDC-40 committee of Bureau of Indian standards and also headed the Transformer standards committee.
Prof. Tripathy during his 42 years of experience in industry and academics has contributed immensely to the area of Power Electronics application, Energy Conservation and Power Quality improvement, with focus on system analysis, design, equipment standardization, and testing. At present he is listed as an adjunct professor with NIT Rourkela, is a member of State advisory Committee of OERC, a consultant with OPTCL and a Board member of CESU Odisha.
He is a Steering Committee member of National Mission on Power Electronics projects, Department of electronics and IT Govt. of India.
Prof Tripathy is a Fellow of Indian National Academy of Engineering, a Fellow of Institution of Engineers, a senior member of IEEE, and a life fellow of ISTE.
Disclaimer: The sole responsibility for the content of this document lies with the authors. It does not represent the opinion of
the Asia Power Quality Initiative and ICA network. APQI and ICA network are not responsible for any use that may be made
of the information contained therein.