General Information
Accredited Thermographers
2011 Thermographic Inspection
ACME Industries Pacific Hwy, North Sydney
Vol.6
Client ACME Industries Job No. 2189 Address Pacific Hwy. North Sydney Date 14/03/11 Tel. 02 5555 5555 Fax 5555 5556 Time 09:30 AM Contact ACME Boss Vol. Six (6) Location Pacific Hwy, North Sydney IR Camera Avio 600 Serial No. 0342A1141AD Visual Camera Olympus SP-310 Serial No. J35204332 Load Measurement Device Kyoritsu-2017 Serial No. KY90-1198B Thermographer Accreditation No. AINDT - 2067
An Infrared Thermal Scan of Listed Electrical Switchboards was conducted 14th March 2011. The complex was drawing load from the Local Supply Authority at time of inspection. Internal switchgear components and associated wiring were inspected for abnormal operating temperatures effected by load or equipment condition. Wiring and terminations were inspected for high resistance connections and insulation condition. Load conditions were as experienced during periods of normal demand. All inspected switchboards and associated wiring within were thermally operating within load conditions. Internal wiring insulation and terminations appear to be sound with exceptions as listed within. Malcolm Rhind
Thermal Imaging Services 8/139 Woolooware Rd Burraneer NSW 2230 T. (02) 9544 3588 F. (02) 9544 3688 E. [email protected] W. www.thermalimagingservices.com.au
-
- 2 -
General Information Application
Thermal Scanning
The information listed below is to assist in the interpretation and discharge of appropriate remedial action of reported faults or potential areas of concern. Recommendations listed within this report are within the area of our expertise and recommend you discuss the implementation of service/repair with your maintenance service provider. Scope Infrared Thermal scan of electrical switchgear and associated conductors to detect the evidence of equipment operating near or above rated thermal temperatures. Where possible load readings are taken to ensure proper diagnosis of prospective faults. Australian and IEC Standards along with Copper & Brass Association publication No.22 are used as benchmarks for assessing permissible temperature limits. Method All accessible covers are removed from the switchboards with internal PVC shrouds removed when installed in a manner that facilitates safe removal. Switchboards assigned a segregation rating greater than two (2), in accordance with AS3439, or where fitted with internal busbar shrouds can be arranged to be scanned with the arrangement of at least two shutdowns to remove and reinstall covers. Internal metal covers will not be removed whilst the switchboard is on line. An infrared radiometer with its range initially set at 20° C and 40° C is passed over all switchgear, bus system and cable connections. Areas displaying abnormal temperature variations are further investigated by means of equipment application analysis, load measurement and pinpoint temperature readings. Faults and areas of concern have infrared thermal and digital images saved for report and condition monitoring tasks. Results A priority rating schedule along with suggested remedial action plans are included for prioritising rectification works. Where faults of a life or property threatening situation are detected, notification will be immediately made to the client’s representative. Ultimately it is the owner or plant operator’s responsibility to implement or gain further advice of the recommended repairs contained within this report. Each thermal image is uniquely identified to correspond with a label placed upon the affected equipment for ready identification by maintenance personnel.
Priority Rating Recommended Action 0 No Fault. Re-scan within 12 months 1 Corrective / Evasive Action required immediately 2 Corrective Action required urgently 3 Corrective Action at next scheduled maintenance 4 Condition monitor. Possible fault developing.
Licensed electricians must perform all repairs and service.
-
- 3 -
Table of Contents
Section Equipment Priority Page Mechanical Services Switchboard Located Level 4 Plant Room
Compressor 3 Motor Starter
2
4
House Services Panel Located Level 3 Riser
Fan Isolating Switch & DB-2 Isolating Switch
2
5
DB-8A Located Level 4 Riser
Main Switch
2
6
DB-3 Located Warehouse Ramp
Circuit Breaker 89-90
1
7
DB-4.4 Located Level 1 Riser
A phase circuit breaker chassis
1
8
Summary of Inspection List of Reported Items 9
List of Inspected Assets 10 Certification Details 11
-
- 4 -
Inspected Equipment Operator:
Mechanical Services Switchboard Located Level 4 Plant Room
Malcolm Rhind
Equipment Compressor 3 Motor Starter
Equipment Type ABB A-63
Additional Information
Date 14/03/2011
Time 11:38 AM
Working conditions:
Located within a non ventilated environment
Thermoteknix TVS-600 11:38:04 AM 24/03/2011 e : 0.95 Bg : 35.9°C-20.0
300.0
17.0
60.1
Celsius
20.0
25.0
30.0
35.0
40.0
45.0
50.0
55.0
51.4
Max.
75.8
75.8
IR Image Details
Image No.
Emissivity 0.95
Spot 1 51.4°C
Spot 2 75.8°C
Area 1 Max. 75.8°C
Area 2 Max.
Background 36.0°C
Description of Fault High resistance A phase load side termination. Terminal was re-tensioned during inspection
Priority Rating 2 Recommendation Re-scan within 12 months.
Previous Fault Description Date Image Vol. Code Page Time Remedial Action Taken
Authorised
Reference Image
Thermal Image
-
- 5 -
Inspected Equipment Operator:
House Services Panel Located Level 3 Riser
Malcolm Rhind
Equipment Fan Isolating Switch & DB-2 Isolating Switch
Equipment Type Quicklag Q355C & Q3100CN
Additional Information
Date 20/04/2011
Time 07:18 AM
Working conditions:
Located within a non ventilated environment
Thermoteknix TVS-600 7:18:41 AM 20/04/2011 e : 0.95 Bg : 22.0°C-20.0
300.0
17.8
67.0
Celsius
20.0
25.0
30.0
35.0
40.0
45.0
50.0
55.0
60.0
65.0
49.4
Max.89.4
89.4 76.5
44.2
60.7
44.8
IR Image Details
Image No.
Emissivity 0.95
Spot 1 49.4°C
Spot 2 89.4°C
Area 1 Max. 89.4°C
Area 2 Max.
Background 22.0°C
Description of Fault High resistance terminations. Variation in line and load side temperatures
Priority Rating 2 Recommendation Inspect contact surfaces and re-terminate.
Ensure tunnel terminals are securely fitted to circuit breaker housings
Previous Fault Description Date Image Vol. Code Page Time Remedial Action Taken
Reference Image
Thermal Image
-
- 6 -
Inspected Equipment Operator:
DB-8A Located Level 4 Riser
Malcolm Rhind
Equipment Main Switch
Equipment Type Quicklag Q3100C
Additional Information Loading A Phase – 89 Amperes B Phase – 32 Amperes C Phase – 38 Amperes
Date 2/05/2011
Time 08:41 AM
Working conditions:
Located within a ventilated environment
Thermoteknix TVS-600 8:41:04 AM 2/05/2011 e : 0.95 Bg : 25.1°C-20.0
300.0
2.5
50.3
Celsius
5.0
10.0
15.0
20.0
25.0
30.0
35.0
40.0
45.0
31.3
Max.68.0
68.0
28.4
58.2
IR Image Details
Image No.
Emissivity 0.95
Spot 1 31.3°C
Spot 2 68.0°C
Area 1 Max. 68.0°C
Area 2 Max.
Background 25.0°C
Description of Fault High resistance A phase connection. Unbalanced load Priority Rating 2
Recommendation Ensure runnel terminal is securely fitted to circuit breaker housing. Re-tension termination. Re-distribute load over adjacent phases.
Previous Fault Description Date Image Vol. Code Page Time Remedial Action Taken
Authorised
Reference Image
Thermal Image
-
- 7 -
Inspected Equipment Operator:
DB-3 Located Warehouse Ramp
Malcolm Rhind
Equipment Circuit Breaker 89-90
Equipment Type Hager
Additional Information Neutral Conductor
Date 23/04/2010
Time 09:30 AM
Working conditions:
Located within a ventilated environment
Thermoteknix TVS-600 9:30:38 AM 23/04/2010 e : 0.95 Bg : 24.9°C-20.0
300.0
26.1
86.2
Celsius
30.0
35.0
40.0
45.0
50.0
55.0
60.0
65.0
70.0
75.0
80.0121.0
Max.121.0
60.0
IR Image Details
Image No.
Emissivity 0.95
Spot 1 121.0°C
Spot 2 60.0°C
Area 1 Max. 121.0°C
Area 2 Max.
Background 25.0°C
Description of Fault High resistance termination.
Priority Rating 1
Recommendation Make good cable end and re-terminate
Previous Fault Description Date Image Vol. Code Page Time Remedial Action Taken
Authorised
Reference Image
Thermal Image
-
- 8 -
Inspected Equipment Operator:
DB-4.4 Located Level 1 Riser
Malcolm Rhind
Equipment A phase circuit breaker chassis
Equipment Type Merlin Gerin
Additional Information
Date 24/03/2010
Time 08:26 AM
Working conditions:
Located within a non ventilated environment.
Thermoteknix TVS-600 8:26:28 AM 24/03/2010 e : 0.95 Bg : 24.9°C-20.0
300.0
35.0
183.5
Celsius
40.0
60.0
80.0
100.0
120.0
140.0
160.0
>300.033.7
IR Image Details
Image No.
Emissivity 0.95
Spot 1 300.0°C
Spot 2 33.7°C
Area 1 Max. 300.0°C
Area 2 Max.
Background 25.0°C
Description of Fault High resistance A phase connection to circuit breaker chassis
Priority Rating 1
Recommendation Replace circuit breaker chassis and make good connection hardware and conductor.
Previous Fault Description Date Image Vol. Code Page Time Remedial Action Taken
Authorised
Reference Image
Thermal Image
-
- 9 -
Summary of Inspection
List of Reported Items
Switchboard Equipment Fault Priority/Recommendation Mechanical Services Switchboard Located Level 4 Plant Room
Compressor 3 Motor Starter
High resistance A phase load side termination was detected
2
Termination re-tensioned during inspection
House Services Panel Located Level 3 Riser
Fan Isolating Switch & DB-2 Isolating Switch
High resistance terminations. Variation in line and load side temperatures
2
Inspect contact surfaces and re-terminate. Ensure tunnel terminals are securely fitted to circuit breaker housings
DB-8A Located Level 4 Riser
Main Switch
High resistance A phase connection. Unbalanced load
2
Ensure runnel terminal is securely fitted to circuit breaker housing. Re-tension termination. Re-distribute load over adjacent phases.
DB-3 Located Warehouse Ramp
Circuit Breaker 89-90
High resistance termination.
1
Make good cable end and re-terminate
DB-4.4 Located Level 1 Riser
A phase circuit breaker chassis
High resistance A phase connection to circuit breaker chassis
1
Replace circuit breaker chassis and make good connection hardware and conductor.
-
- 10 -
List of Inspected Assets
Location Switchboard Fault Comment Main Switchroom Main Switchboard Nil
PFC Unit 1 Nil
PFC Unit 2 Nil
Unmarked DB Nil
Admin. Block Data Recovery Room
UPS DB Nil
By Pass Switch Nil
Located Level 1 Riser DB-4.4 √ See Report Page 8
Under Art Department (Building Void)
DB-7 Nil
DB-8 Nil
Compressor Load Centre Nil
Under Administration Block DB-5 Nil
Air Conditioning Sub Board Nil
Warehouse Ramp DB-3 √ See Report Page 7
DB-3A Nil
Warehouse Mezzanine MCC Nil
Warehouse (Adj. Loading Dock)
DB-3C Nil
Warehouse Customer Service
DB-3D Nil
Warehouse (Rear Wall)
DB-6
Nil
DB-3CB Nil
Workshop Sub Board - No load
Located Level 4 Riser DB-8A
√ See Report Page 6
Level 4 Plant Room Mechanical Services Switchboard
√ See Report Page 4
House Services Panel Located Level 3 Riser
Fan Isolating Switch & DB-2 Isolating Switch
√ See Report Page 5
Data Room DB Nil
UPS By Pass Switch Nil
Book Fare Warehouse DB-1 Nil
Level 1 Admin. New Media
DB-2 Nil
DB-3 Nil
DB-3 (Special Purpose) Nil
Level 1 Comms. Room New Media
UPS -1 Sub Board Nil
UPS -2 Sub Board Nil
-