CPM-PERT
1
7/31/2019 CPM Pert New
2/45
Course on Project Management
Purpose of CPM
Finish fast
Quantify progress
Communicate effectively
2
7/31/2019 CPM Pert New
3/45
Course on Project Management
PM Today Necessary?
3
Frustration with cost & schedule overruns Frustration with reliability of production estimates Management challenges exist today:
Only44% of projects are completed on time On average, projects are 189% over-budget 70% of completed projects do not perform as expected 30% of projects are canceled before completion On average, projects are 222% longer than expected
PM has been shown to improve this performanceThese statistics were compiled by an independent monitoring group, TheStandish Group, and represent the US national average for 1998
7/31/2019 CPM Pert New
4/45
Course on Project Management
Advantages and Disadvantages of FormalSchedules
Saves time and money on large complex projects
Effective communication tool
Too much work
Assessment of duration of tasks Assessment of interdependencies
4
7/31/2019 CPM Pert New
5/45
Course on Project Management
Resource Oriented and Time Oriented Schedules
Resource oriented
Time oriented
5
7/31/2019 CPM Pert New
6/45
Course on Project Management
Elements of a Critical Path Chart
Activity
Precedence
Duration/cost
6
7/31/2019 CPM Pert New
7/45
7/31/2019 CPM Pert New
8/45Course on Project Management
Elements of a Critical Path Chart
Activity
Precedence
Duration/cost
8
7/31/2019 CPM Pert New
9/45Course on Project Management
Elements of a Critical Path Chart
Activity
Precedence
Duration/cost
Activity Description Precedents
A Select satisfaction survey tool
B Print survey tool A
C Select list of patientsD Sample from list C
E Mail surveys to selected patients D
F Collect responses E
G Analyze data F
9
7/31/2019 CPM Pert New
10/45Course on Project Management
Elements of a Critical Path Chart
Activity
Precedence
Duration/cost
10
7/31/2019 CPM Pert New
11/45Course on Project Management
Elements of a Critical Path Chart
Activity
Precedence
Duration/cost
Activity Description Precedents Duration
A Select satisfaction survey tool 2 weeks
B Print survey tool A 3 weeks
C Select list of patients 1 week
D Sample from list C 1 week
E Mail surveys to selected patients D 2 weeks
F Collect responses E 4 weeks
G Analyze data F 3 weeks
11
7/31/2019 CPM Pert New
12/45Course on Project Management
Branch and Node Charts
Activity on branch
Activity on node
12
7/31/2019 CPM Pert New
13/45Course on Project Management
Activity In Node
A B
C
Activity Description Precedents
A Select satisfaction survey tool
B Print survey tool A
C Obtain list of patients
D Sample from list C
E Mail surveys to selected patients D,B
F Collect responses E
G Analyze data F
D
E F G
13
7/31/2019 CPM Pert New
14/45Course on Project Management
Activity On Branches
1 3
2
Activity Description Precedents
A Select satisfaction survey tool
B Print survey tool A
C Obtain list of patients
D Sample from list C
E Mail surveys to selected patients D,B
F Collect responses E
G Analyze data F
4
5 6 7A B E F
C D
EndG
Start
14
7/31/2019 CPM Pert New
15/45Course on Project Management
Earliest and Latest Start and Finish Times
A B
C D
E F G2 3 2 4 3
1 1
End
Start
Activity Description
A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responsesG Analyze data
15
7/31/2019 CPM Pert New
16/45Course on Project Management
Earliest and Latest Start and Finish Times
A B
C D
E F G2 3 2 4 3
1 1
End
Start
Forward pass calculates early start and finish
Activity Description
A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responsesG Analyze data
16
7/31/2019 CPM Pert New
17/45Course on Project Management
Earliest and Latest Start and Finish Times
A B
C D
E F G2 3 2 4 3
1 1
End
Start
Backward pass calculates latest start and end times
Activity Description
A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responsesG Analyze data
17
7/31/2019 CPM Pert New
18/45Course on Project Management
Earliest and Latest Start and Finish Times
A B
C D
E F G2 3 2 4 3
1 1
End
Start
Critical Path includes activities where earliest starttime and latest start time are equal
Activity Description
A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responsesG Analyze data
18
7/31/2019 CPM Pert New
19/45Course on Project Management
Earliest and Latest Start and Finish Times
A B
C D
E F G2 3 2 4 3
1 1
End
Start
Activities not on the critical path have slack.
The latest start time and the earliest start date aredifferent
Activity Description
A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responsesG Analyze data
19
7/31/2019 CPM Pert New
20/45Course on Project Management
Earliest and Latest Start and Finish Times
A B
C D
E F G2 3 2 4 3
1 1
End
Start
Start Finish
Early 0
Late
Activity Description
A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responsesG Analyze data
20
7/31/2019 CPM Pert New
21/45Course on Project Management
Earliest and Latest Start and Finish Times
A B
C D
E F G2 3 2 4 3
1 1
End
Start
Start Finish
Early 0 2
Late
Activity Description
A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responsesG Analyze data
21
7/31/2019 CPM Pert New
22/45
7/31/2019 CPM Pert New
23/45Course on Project Management
Activity Description
A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responsesG Analyze data
Earliest and Latest Start and Finish Times
A B
C D
E F G2 3 2 4 3
1 1
End
Start
Start Finish
Early 2 5
Late
S F
E 0 2
L
S F
E 2 5
L
23
7/31/2019 CPM Pert New
24/45
Course on Project Management
Activity Description
A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responsesG Analyze data
Earliest and Latest Start and Finish Times
A B
C D
E F G2 3 2 4 3
1 1
End
Start
Start Finish
Early 1 2
Late
S F
E 0 2
L
S F
E 2 5
L
S F
E 0 1
L
24
7/31/2019 CPM Pert New
25/45
Course on Project Management
Activity Description
A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responsesG Analyze data
Earliest and Latest Start and Finish Times
A B
C D
E F G2 3 2 4 3
1 1
End
Start
Start Finish
Early 5 7
Late
S F
E 0 2
L
S F
E 2 5
L
S F
E 0 1
L
S F
E 1 2
L
25
7/31/2019 CPM Pert New
26/45
Course on Project Management
Activity Description
A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responsesG Analyze data
Earliest and Latest Start and Finish Times
A B
C D
E F G2 3 2 4 3
1 1
End
Start
S F
E 0 2
L
S F
E 2 5
L
S F
E 0 1
L
S F
E 1 2
L
S F
E 5 7
L
S FE 7 11
L
S FE 11 14
L
26
7/31/2019 CPM Pert New
27/45
Course on Project Management
Earliest and Latest Start and Finish Times
A B
C D
E F G2 3 2 4 3
1 1
End
Start
S F
E 0 2
L
S F
E 2 5
L
S F
E 0 1
L
S F
E 1 2
L
S F
E 5 7
L
S FE 7 11
L
S F
E 11 14
L 14
Latest finish is the minimum of latest start ofsucceeding tasks. Latest start is the latest finish
minus duration.
27
7/31/2019 CPM Pert New
28/45
Course on Project Management
Earliest and Latest Start and Finish Times
A B
C D
E F G2 3 2 4 3
1 1
End
Start
S F
E 0 2
L
S F
E 2 5
L
S F
E 0 1
L
S F
E 1 2
L
S F
E 5 7
L
S FE 7 11
L
S FE 11 14
L 11 14
Latest finish is the minimum of latest start ofsucceeding tasks. Latest start is the latest finish
minus duration.
28
7/31/2019 CPM Pert New
29/45
Course on Project Management
Earliest and Latest Start and Finish Times
A B
C D
E F G2 3 2 4 3
1 1
End
Start
S F
E 0 2
L
S F
E 2 5
L
S F
E 0 1
L
S F
E 1 2
L
S F
E 5 7
L
S F
E 7 11
L 7 11
S FE 11 14
L 11 14
Activity Description
A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responsesG Analyze data
29
7/31/2019 CPM Pert New
30/45
Course on Project Management
Earliest and Latest Start and Finish Times
A B
C D
E F G2 3 2 4 3
1 1
End
Start
S FE 0 2
L 0 2
S FE 2 5
L 2 5
S F
E 0 1
L 3 4
S F
E 1 2
L 4 5
S FE 5 7
L 5 7
S FE 7 11
L 7 11
S FE 11 14
L 11 14
Activity Description
A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responsesG Analyze data
30
7/31/2019 CPM Pert New
31/45
Course on Project Management
Slack Time
A B
C D
E F G2 3 2 4 3
1 1
End
Start
S F
E 0 2
L 0 2
S F
E 2 5
L 2 5
S F
E 0 1
L 3 4
S F
E 1 2
L 4 5
S F
E 5 7
L 5 7
S FE 7 11
L 7 11
S FE 11 14
L 11 14
Slack time = Latest start Earliest start
31
7/31/2019 CPM Pert New
32/45
Course on Project Management
Critical Path
A B
C D
E F G2 3 2 4 3
1 1
End
Start
S F
E 0 2
L 0 2
S F
E 2 5
L 2 5
S F
E 0 1
L 3 4
S F
E 1 2
L 4 5
S F
E 5 7
L 5 7
S FE 7 11
L 7 11
S FE 11 14
L 11 14
Critical path includes activities with no slack.
32
7/31/2019 CPM Pert New
33/45
Course on Project Management
Communicating Project Schedule
Time scaled network of activities
Gantt chart
Time an activity graphs and completion graphs
33
7/31/2019 CPM Pert New
34/45
Course on Project Management
Communicating Project Schedule
Time scaled network of activities
Gantt chart
Time an activity graphs and completion graphs
34
7/31/2019 CPM Pert New
35/45
Course on Project Management
Communicating Project Schedule
Time scaled network of activities
Gantt chart
Time an activity graphs and completion graphs
35
7/31/2019 CPM Pert New
36/45
Course on Project Management
Software
Discovery of Critical Path
36
7/31/2019 CPM Pert New
37/45
Course on Project Management
PERT analysis37
Draw the network. Analyze the paths through the network and find the critical path.
The length of the critical path is the mean of the project durationprobability distribution which is assumed to be normal
The standard deviation of the project duration probabilitydistribution is computed by adding the variances of the criticalactivities (all of the activities that make up the critical path) andtaking the square root of that sum
Probability computations can now be made using the normaldistribution table.
7/31/2019 CPM Pert New
38/45
Course on Project Management
Probability computation38
Determine probability that project is completed within specified time
Z =
x -
where = tp = project mean time
= project standard mean time
x = (proposed ) specified time
7/31/2019 CPM Pert New
39/45
Course on Project Management
Normal Distribution of Project Time39
= tp Timex
Z
Probability
l
7/31/2019 CPM Pert New
40/45
Course on Project Management
PERT Example
40
Immed. Optimistic Most Likely Pessimistic
Activity Predec. Time (Hr.) Time (Hr.) Time (Hr.)
A -- 4 6 8B -- 1 4.5 5C A 3 3 3D A 4 5 6E A 0.5 1 1.5F B,C 3 4 5G B,C 1 1.5 5
H E,F 5 6 7I E,F 2 5 8J D,H 2.5 2.75 4.5K G,I 3 5 7
l
7/31/2019 CPM Pert New
41/45
Course on Project Management
PERT Example
41
A
D
C
B
F
E
G
I
H
K
J
PERT Network
PERT E l
7/31/2019 CPM Pert New
42/45
Course on Project Management
PERT Example
42Activity Expected Time Variance
A 6 4/9B 4 4/9C 3 0D 5 1/9
E 1 1/36F 4 1/9G 2 4/9H 6 1/9
I 5 1J 3 1/9K 5 4/9
7/31/2019 CPM Pert New
43/45
Course on Project Management
PERT Example43
Activity ES EF LS LF SlackA 0 6 0 6 0 *criticalB 0 4 5 9 5
C 6 9 6 9 0 *D 6 11 15 20 9E 6 7 12 13 6F 9 13 9 13 0 *G 9 11 16 18 7H 13 19 14 20 1
I 13 18 13 18 0 *J 19 22 20 23 1K 18 23 18 23 0 *
7/31/2019 CPM Pert New
44/45
Course on Project Management
PERT Example44
Vpath = VA+ VC + VF + VI + VK= 4/9 + 0 + 1/9 + 1 + 4/9
= 2
path = 1.414
z= (24 - 23)/ (24-23)/1.414 = .71
From the Standard Normal Distribution table:
P(z < .71) = .5 + .2612 = .7612