Pert Cpm Example

22
PERT / CPM

description

Critical Path Method

Transcript of Pert Cpm Example

  • PERT / CPM

  • PERT / CPM or Network Analysis

    CPM Critical Path Method Developed in 1957 by Du Pont First used in the construction of a new chemical

    plant PERT Program Evaluation Review

    Technique Developed in 1958 by Navy Used in the POLARIS missile program

  • Planning, Scheduling & Control Useful for project management

    How long will it take to complete? What are the critical task that can delay the

    completion? How long can certain task be prolonged before

    becoming critical?

  • Network Implementation Define project and all significant activities or

    tasks with single start and stop times. Develop the relationships between tasks. Draw the network with single start and end. Assign time or cost for each task. Compute the longest path through the

    network. This is the critical path. Use network to plan, schedule and manage

    project.

  • Useful Questions Building the Network

    Is this a start activity? Is it a finish activity? Which activity precedes this one? Which activity follows it? Which activity is concurrent?

  • Drawing the Network Network begins with a single event and ends

    with a single event. Each activity is represented by an arrow. Events are represented by circles and

    precede and follow each activity. Consecutive activities must be separated by

    events. No pair of events can be directly connected

    by more than one activity without intervening events.

  • Parallel Paths Require Event

  • Rules for Network Construction (continued)

    If an activity R precedes several otherwise unrelated activities S & T, then they must be separate by event.

    If several otherwise unrelated activities R & S both precede activity T, then they must be separate by event.

  • Example

    RS

    TR

    S

    T

  • Dummy Activities Some precedence relations will require one

    or more dummy activities. Dummy activities have 0 duration and are

    represented by dashed arrows. Contribute to number of alternate paths but

    not duration. Example:

    A precedes D A and B precede E B and C precede F

  • Dummy Activity Example

    A

    B

    C

    D

    E

    F

  • Example Network Table

    Activity Duration Preceded ByA 3B 3 AC 4D 1 CE 3 B, DF 2 A, B, DG 2 C, FH 4 GI 1 CJ 3 E, GK 5 F, H, I

  • CPM Example Network

    A

    B E

    J

    C

    D

    I

    F

    G

    H K

    3

    3

    4

    1

    3

    2

    1

    24

    3

    5

  • Example: Alternate Paths

    Path LengthA-B-E-J 12

    A-B-F-G-dummy-J 13A-B-F-G-H-K 19

    C-D-E-J 11C-D-F-G-dummy-J 12

    C-D-F-G-H-K 18C-I-K 10

  • Path LengthA-B-E-J 12

    A-B-F-G-dummy-J 13A-B-F-G-H-K 19

    C-D-E-J 11C-D-F-G-dummy-J 12

    C-D-F-G-H-K 18C-I-K 10

  • CPM Example NetworkCritical Path

    A

    B E

    J

    C

    D

    I

    F

    G

    H K

    3

    3

    4

    1

    3

    2

    1

    24

    3

    5

  • Alternate Paths Evaluation alternative paths relative to critical

    path Earlist Start (ES) for each activity trace forward

    from start to beginning of the activity. When several paths exist use longest.

    Latest Start (LS) for each activity trace backwards from project end to tail of each activity. When several paths exist use longest. Subtract from critical path time.

    Total Float (TL): TL = LS ES

  • CPM Example Network

    A

    B E

    J

    C

    D

    I

    F

    G

    H K

    3

    3

    4

    1

    3

    2

    1

    24

    3

    5

    F: ES=3+3=6; LS=19-(5+4+2+2)=6; TF=0

  • CPM Example Network Table

    Activity Duration ES LS TFA 3 0 0 0B 3 3 3 0C 4 0 1 1D 1 4 5 1E 3 6 13 7F 2 6 6 0G 2 8 8 0H 4 10 10 0I 1 4 13 9J 3 10 16 6K 5 14 14 0

    Project Duration =19

  • PERT Program Evaluation and Review Technique

    Allows uncertainity to be included in activity times

    Assume a Beta probability distribution Defined with three parameters:

    ts shortest time to accomplish activity

    tl longest time to complete activity

    tm most likely time

    Expected duration; te = ( ts + 4tm + tl ) / 6 Standard deviation; = (tl ts) / 6

  • PERT Example Network

    A

    B E

    J

    C

    D

    I

    F

    G

    H K

    1-3-5

    2-3-4

    3-4-101-1-5

    2-3-6

    1-2-7

    0-1-3

    1-2-43-4-6

    1-3-6

    3-5-12

  • PERT Example Network TableActivity Expected Time Variance ES LS TF

    A 3.00 0.44 0.00 0.50 0.50B 3.00 0.11 3.00 3.50 0.50C 4.83 1.36 0.00 1.00 0.00D 1.67 0.44 4.83 4.83 0.00E 3.33 0.44 6.50 14.84 8.34F 2.67 1.00 6.50 6.50 0.00G 2.17 0.25 9.17 9.17 0.00H 4.17 0.25 11.34 11.34 0.00I 1.17 0.25 4.83 14.34 9.51J 3.17 0.69 11.34 18.17 6.83K 5.83 2.25 15.51 15.51 0.00

    Project Duration = 21.34