    CPM-PERT

    1

  • 7/31/2019 CPM Pert New

    2/45

    Course on Project Management

    Purpose of CPM

    Finish fast

    Quantify progress

    Communicate effectively

    2

  • 7/31/2019 CPM Pert New

    3/45

    Course on Project Management

    PM Today Necessary?

    3

    Frustration with cost & schedule overruns Frustration with reliability of production estimates Management challenges exist today:

    Only44% of projects are completed on time On average, projects are 189% over-budget 70% of completed projects do not perform as expected 30% of projects are canceled before completion On average, projects are 222% longer than expected

    PM has been shown to improve this performanceThese statistics were compiled by an independent monitoring group, TheStandish Group, and represent the US national average for 1998

  • 7/31/2019 CPM Pert New

    4/45

    Course on Project Management

    Advantages and Disadvantages of FormalSchedules

    Saves time and money on large complex projects

    Effective communication tool

    Too much work

    Assessment of duration of tasks Assessment of interdependencies

    4

  • 7/31/2019 CPM Pert New

    5/45

    Course on Project Management

    Resource Oriented and Time Oriented Schedules

    Resource oriented

    Time oriented

    5

  • 7/31/2019 CPM Pert New

    6/45

    Course on Project Management

    Elements of a Critical Path Chart

    Activity

    Precedence

    Duration/cost

    6

  • 7/31/2019 CPM Pert New

    7/45

  • 7/31/2019 CPM Pert New

    8/45Course on Project Management

    Elements of a Critical Path Chart

    Activity

    Precedence

    Duration/cost

    8

  • 7/31/2019 CPM Pert New

    9/45Course on Project Management

    Elements of a Critical Path Chart

    Activity

    Precedence

    Duration/cost

    Activity Description Precedents

    A Select satisfaction survey tool

    B Print survey tool A

    C Select list of patientsD Sample from list C

    E Mail surveys to selected patients D

    F Collect responses E

    G Analyze data F

    9

  • 7/31/2019 CPM Pert New

    10/45Course on Project Management

    Elements of a Critical Path Chart

    Activity

    Precedence

    Duration/cost

    10

  • 7/31/2019 CPM Pert New

    11/45Course on Project Management

    Elements of a Critical Path Chart

    Activity

    Precedence

    Duration/cost

    Activity Description Precedents Duration

    A Select satisfaction survey tool 2 weeks

    B Print survey tool A 3 weeks

    C Select list of patients 1 week

    D Sample from list C 1 week

    E Mail surveys to selected patients D 2 weeks

    F Collect responses E 4 weeks

    G Analyze data F 3 weeks

    11

  • 7/31/2019 CPM Pert New

    12/45Course on Project Management

    Branch and Node Charts

    Activity on branch

    Activity on node

    12

  • 7/31/2019 CPM Pert New

    13/45Course on Project Management

    Activity In Node

    A B

    C

    Activity Description Precedents

    A Select satisfaction survey tool

    B Print survey tool A

    C Obtain list of patients

    D Sample from list C

    E Mail surveys to selected patients D,B

    F Collect responses E

    G Analyze data F

    D

    E F G

    13

  • 7/31/2019 CPM Pert New

    14/45Course on Project Management

    Activity On Branches

    1 3

    2

    Activity Description Precedents

    A Select satisfaction survey tool

    B Print survey tool A

    C Obtain list of patients

    D Sample from list C

    E Mail surveys to selected patients D,B

    F Collect responses E

    G Analyze data F

    4

    5 6 7A B E F

    C D

    EndG

    Start

    14

  • 7/31/2019 CPM Pert New

    15/45Course on Project Management

    Earliest and Latest Start and Finish Times

    A B

    C D

    E F G2 3 2 4 3

    1 1

    End

    Start

    Activity Description

    A Select satisfaction survey tool

    B Print survey tool

    C Select list of patients

    D Sample from list

    E Mail surveys to patients

    F Collect responsesG Analyze data

    15

  • 7/31/2019 CPM Pert New

    16/45Course on Project Management

    Earliest and Latest Start and Finish Times

    A B

    C D

    E F G2 3 2 4 3

    1 1

    End

    Start

    Forward pass calculates early start and finish

    Activity Description

    A Select satisfaction survey tool

    B Print survey tool

    C Select list of patients

    D Sample from list

    E Mail surveys to patients

    F Collect responsesG Analyze data

    16

  • 7/31/2019 CPM Pert New

    17/45Course on Project Management

    Earliest and Latest Start and Finish Times

    A B

    C D

    E F G2 3 2 4 3

    1 1

    End

    Start

    Backward pass calculates latest start and end times

    Activity Description

    A Select satisfaction survey tool

    B Print survey tool

    C Select list of patients

    D Sample from list

    E Mail surveys to patients

    F Collect responsesG Analyze data

    17

  • 7/31/2019 CPM Pert New

    18/45Course on Project Management

    Earliest and Latest Start and Finish Times

    A B

    C D

    E F G2 3 2 4 3

    1 1

    End

    Start

    Critical Path includes activities where earliest starttime and latest start time are equal

    Activity Description

    A Select satisfaction survey tool

    B Print survey tool

    C Select list of patients

    D Sample from list

    E Mail surveys to patients

    F Collect responsesG Analyze data

    18

  • 7/31/2019 CPM Pert New

    19/45Course on Project Management

    Earliest and Latest Start and Finish Times

    A B

    C D

    E F G2 3 2 4 3

    1 1

    End

    Start

    Activities not on the critical path have slack.

    The latest start time and the earliest start date aredifferent

    Activity Description

    A Select satisfaction survey tool

    B Print survey tool

    C Select list of patients

    D Sample from list

    E Mail surveys to patients

    F Collect responsesG Analyze data

    19

  • 7/31/2019 CPM Pert New

    20/45Course on Project Management

    Earliest and Latest Start and Finish Times

    A B

    C D

    E F G2 3 2 4 3

    1 1

    End

    Start

    Start Finish

    Early 0

    Late

    Activity Description

    A Select satisfaction survey tool

    B Print survey tool

    C Select list of patients

    D Sample from list

    E Mail surveys to patients

    F Collect responsesG Analyze data

    20

  • 7/31/2019 CPM Pert New

    21/45Course on Project Management

    Earliest and Latest Start and Finish Times

    A B

    C D

    E F G2 3 2 4 3

    1 1

    End

    Start

    Start Finish

    Early 0 2

    Late

    Activity Description

    A Select satisfaction survey tool

    B Print survey tool

    C Select list of patients

    D Sample from list

    E Mail surveys to patients

    F Collect responsesG Analyze data

    21

  • 7/31/2019 CPM Pert New

    22/45

  • 7/31/2019 CPM Pert New

    23/45Course on Project Management

    Activity Description

    A Select satisfaction survey tool

    B Print survey tool

    C Select list of patients

    D Sample from list

    E Mail surveys to patients

    F Collect responsesG Analyze data

    Earliest and Latest Start and Finish Times

    A B

    C D

    E F G2 3 2 4 3

    1 1

    End

    Start

    Start Finish

    Early 2 5

    Late

    S F

    E 0 2

    L

    S F

    E 2 5

    L

    23

  • 7/31/2019 CPM Pert New

    24/45

    Course on Project Management

    Activity Description

    A Select satisfaction survey tool

    B Print survey tool

    C Select list of patients

    D Sample from list

    E Mail surveys to patients

    F Collect responsesG Analyze data

    Earliest and Latest Start and Finish Times

    A B

    C D

    E F G2 3 2 4 3

    1 1

    End

    Start

    Start Finish

    Early 1 2

    Late

    S F

    E 0 2

    L

    S F

    E 2 5

    L

    S F

    E 0 1

    L

    24

  • 7/31/2019 CPM Pert New

    25/45

    Course on Project Management

    Activity Description

    A Select satisfaction survey tool

    B Print survey tool

    C Select list of patients

    D Sample from list

    E Mail surveys to patients

    F Collect responsesG Analyze data

    Earliest and Latest Start and Finish Times

    A B

    C D

    E F G2 3 2 4 3

    1 1

    End

    Start

    Start Finish

    Early 5 7

    Late

    S F

    E 0 2

    L

    S F

    E 2 5

    L

    S F

    E 0 1

    L

    S F

    E 1 2

    L

    25

  • 7/31/2019 CPM Pert New

    26/45

    Course on Project Management

    Activity Description

    A Select satisfaction survey tool

    B Print survey tool

    C Select list of patients

    D Sample from list

    E Mail surveys to patients

    F Collect responsesG Analyze data

    Earliest and Latest Start and Finish Times

    A B

    C D

    E F G2 3 2 4 3

    1 1

    End

    Start

    S F

    E 0 2

    L

    S F

    E 2 5

    L

    S F

    E 0 1

    L

    S F

    E 1 2

    L

    S F

    E 5 7

    L

    S FE 7 11

    L

    S FE 11 14

    L

    26

  • 7/31/2019 CPM Pert New

    27/45

    Course on Project Management

    Earliest and Latest Start and Finish Times

    A B

    C D

    E F G2 3 2 4 3

    1 1

    End

    Start

    S F

    E 0 2

    L

    S F

    E 2 5

    L

    S F

    E 0 1

    L

    S F

    E 1 2

    L

    S F

    E 5 7

    L

    S FE 7 11

    L

    S F

    E 11 14

    L 14

    Latest finish is the minimum of latest start ofsucceeding tasks. Latest start is the latest finish

    minus duration.

    27

  • 7/31/2019 CPM Pert New

    28/45

    Course on Project Management

    Earliest and Latest Start and Finish Times

    A B

    C D

    E F G2 3 2 4 3

    1 1

    End

    Start

    S F

    E 0 2

    L

    S F

    E 2 5

    L

    S F

    E 0 1

    L

    S F

    E 1 2

    L

    S F

    E 5 7

    L

    S FE 7 11

    L

    S FE 11 14

    L 11 14

    Latest finish is the minimum of latest start ofsucceeding tasks. Latest start is the latest finish

    minus duration.

    28

  • 7/31/2019 CPM Pert New

    29/45

    Course on Project Management

    Earliest and Latest Start and Finish Times

    A B

    C D

    E F G2 3 2 4 3

    1 1

    End

    Start

    S F

    E 0 2

    L

    S F

    E 2 5

    L

    S F

    E 0 1

    L

    S F

    E 1 2

    L

    S F

    E 5 7

    L

    S F

    E 7 11

    L 7 11

    S FE 11 14

    L 11 14

    Activity Description

    A Select satisfaction survey tool

    B Print survey tool

    C Select list of patients

    D Sample from list

    E Mail surveys to patients

    F Collect responsesG Analyze data

    29

  • 7/31/2019 CPM Pert New

    30/45

    Course on Project Management

    Earliest and Latest Start and Finish Times

    A B

    C D

    E F G2 3 2 4 3

    1 1

    End

    Start

    S FE 0 2

    L 0 2

    S FE 2 5

    L 2 5

    S F

    E 0 1

    L 3 4

    S F

    E 1 2

    L 4 5

    S FE 5 7

    L 5 7

    S FE 7 11

    L 7 11

    S FE 11 14

    L 11 14

    Activity Description

    A Select satisfaction survey tool

    B Print survey tool

    C Select list of patients

    D Sample from list

    E Mail surveys to patients

    F Collect responsesG Analyze data

    30

  • 7/31/2019 CPM Pert New

    31/45

    Course on Project Management

    Slack Time

    A B

    C D

    E F G2 3 2 4 3

    1 1

    End

    Start

    S F

    E 0 2

    L 0 2

    S F

    E 2 5

    L 2 5

    S F

    E 0 1

    L 3 4

    S F

    E 1 2

    L 4 5

    S F

    E 5 7

    L 5 7

    S FE 7 11

    L 7 11

    S FE 11 14

    L 11 14

    Slack time = Latest start Earliest start

    31

  • 7/31/2019 CPM Pert New

    32/45

    Course on Project Management

    Critical Path

    A B

    C D

    E F G2 3 2 4 3

    1 1

    End

    Start

    S F

    E 0 2

    L 0 2

    S F

    E 2 5

    L 2 5

    S F

    E 0 1

    L 3 4

    S F

    E 1 2

    L 4 5

    S F

    E 5 7

    L 5 7

    S FE 7 11

    L 7 11

    S FE 11 14

    L 11 14

    Critical path includes activities with no slack.

    32

  • 7/31/2019 CPM Pert New

    33/45

    Course on Project Management

    Communicating Project Schedule

    Time scaled network of activities

    Gantt chart

    Time an activity graphs and completion graphs

    33

  • 7/31/2019 CPM Pert New

    34/45

    Course on Project Management

    Communicating Project Schedule

    Time scaled network of activities

    Gantt chart

    Time an activity graphs and completion graphs

    34

  • 7/31/2019 CPM Pert New

    35/45

    Course on Project Management

    Communicating Project Schedule

    Time scaled network of activities

    Gantt chart

    Time an activity graphs and completion graphs

    35

  • 7/31/2019 CPM Pert New

    36/45

    Course on Project Management

    Software

    Discovery of Critical Path

    36

  • 7/31/2019 CPM Pert New

    37/45

    Course on Project Management

    PERT analysis37

    Draw the network. Analyze the paths through the network and find the critical path.

    The length of the critical path is the mean of the project durationprobability distribution which is assumed to be normal

    The standard deviation of the project duration probabilitydistribution is computed by adding the variances of the criticalactivities (all of the activities that make up the critical path) andtaking the square root of that sum

    Probability computations can now be made using the normaldistribution table.

  • 7/31/2019 CPM Pert New

    38/45

    Course on Project Management

    Probability computation38

    Determine probability that project is completed within specified time

    Z =

    x -

    where = tp = project mean time

    = project standard mean time

    x = (proposed ) specified time

  • 7/31/2019 CPM Pert New

    39/45

    Course on Project Management

    Normal Distribution of Project Time39

    = tp Timex

    Z

    Probability

    l

  • 7/31/2019 CPM Pert New

    40/45

    Course on Project Management

    PERT Example

    40

    Immed. Optimistic Most Likely Pessimistic

    Activity Predec. Time (Hr.) Time (Hr.) Time (Hr.)

    A -- 4 6 8B -- 1 4.5 5C A 3 3 3D A 4 5 6E A 0.5 1 1.5F B,C 3 4 5G B,C 1 1.5 5

    H E,F 5 6 7I E,F 2 5 8J D,H 2.5 2.75 4.5K G,I 3 5 7

    l

  • 7/31/2019 CPM Pert New

    41/45

    Course on Project Management

    PERT Example

    41

    A

    D

    C

    B

    F

    E

    G

    I

    H

    K

    J

    PERT Network

    PERT E l

  • 7/31/2019 CPM Pert New

    42/45

    Course on Project Management

    PERT Example

    42Activity Expected Time Variance

    A 6 4/9B 4 4/9C 3 0D 5 1/9

    E 1 1/36F 4 1/9G 2 4/9H 6 1/9

    I 5 1J 3 1/9K 5 4/9

  • 7/31/2019 CPM Pert New

    43/45

    Course on Project Management

    PERT Example43

    Activity ES EF LS LF SlackA 0 6 0 6 0 *criticalB 0 4 5 9 5

    C 6 9 6 9 0 *D 6 11 15 20 9E 6 7 12 13 6F 9 13 9 13 0 *G 9 11 16 18 7H 13 19 14 20 1

    I 13 18 13 18 0 *J 19 22 20 23 1K 18 23 18 23 0 *

  • 7/31/2019 CPM Pert New

    44/45

    Course on Project Management

    PERT Example44

    Vpath = VA+ VC + VF + VI + VK= 4/9 + 0 + 1/9 + 1 + 4/9

    = 2

    path = 1.414

    z= (24 - 23)/ (24-23)/1.414 = .71

    From the Standard Normal Distribution table:

    P(z < .71) = .5 + .2612 = .7612