Wind Final
-
Upload
drew-peden -
Category
Documents
-
view
27 -
download
0
Transcript of Wind Final
Green Energy Design Project
By:Grace AyodeleEric HeckmanDrew Peden
Ryley Rosenfeldt
Mechanical Engineering 111Engineering Fundamentals II
College of Engineering and Applied SciencesUniversity of Wisconsin-Milwaukee
Milwaukee, WI 53201
5 May 2014
i
Executive Summary
The main object of this report is to explain the design process behind the windmill
prototype. The problem presented was to design and build a model of a quiet, roof mountable
green energy system. The system was to be used to recharge a home battery backup. Through the
design process, the following limitations were implemented: materials, cost, no internal
combustion engine, no use of lithium-ion batteries, and finally the prototype could be no taller
than two feet and must have a volume of four cubic feet or less. The conducted research showed
that viable production methods included solar power, micro hydro power, vertical blade drag
design and horizontal wind power. Each method was evaluated based on criteria outlined in the
design objectives and decision matrix. Horizontal power was the final choice for our green
energy system. The following report details the research process, green energy source selection,
design process, prototype development and the final design solution. A final recommendation
will be given based off of the projects results.
ii
Table of Contents
Title Page i
Executive Summary ii
Table of Contents iii
Conclusions and Recommendations 1
Introduction 2
Body of Report
Revised Problem Statement 3
Proposed Design Solutions 3
Contribution of Team Members 6
Economic Analysis 8
Bibliography 9
Appendices 10
1
Conclusions and Recommendations
In a wind with a velocity of 5 ms the final design had an output of 2.3 V and 35 mA (G1).
This was enough to overcome the forward voltage of the LED chosen (1.8 V f ¿ . At lower
velocities, the final design produced much less voltage. In the initial calculations several things
had to be assumed. One was the tip to speed ratio (TSR) of the design. Using a less than ideal
wind velocity (G2.1) and a TSR of 1.75 to determine the rpm (G2.2) the torque predicted was
100 Nmm (G2.3). Based on this modelling a generator was chosen with a torque rating of 39
Nmm with an operating range of 4.5-12 volts and max efficiency at 190 rpm. Gears were
purchased with a 3:4 ratio to slightly exceed the ideal rpm (G2.4). Therefore our predicted
voltage output was initially a minimum of 4.5 volts. Upon initial assembly and testing at
velocities of 2-3 ms it became apparent that the design did not produce enough torque to turn the
motor. Due to the exponential relationship between wind velocity and power (G2) and therefor
torque these were not ideal testing conditions. A lower torque motor was chosen that would
produce 12 V at an ideal rpm of 14,000. Although it easily produces small amounts of voltage in
low wind velocity conditions, the gear ratio could not be changed due to time and financial
considerations. Later experimental data with an air velocity of 5 ms indicated that the design
would achieve 400 Nmm of torque (G1.1), which is more than enough to turn the motor the
initial design called for. However with the new motor the design only produced 2.3 V (G1.4).
This was enough to light our LED, but under our initial expectations.
The design was, for the most part, successful. The prototype was capable of producing
power in the given test conditions. At this point it is recommended that the initial motor be re-
installed in order to produce a more appreciable amount of voltage and new experimental data
gathered in order to adjust the circuit as well. At low wind velocities the new recommended
design will not produce electricity, but in average to above average winds the voltage level will
be more useful and will take advantage of the gear ratio calculated in the initial mathematical
modelling. All other components of the design were successful and will transition well into the
production model.
2
Introduction
The goal of the project was to design a prototype that generates power from a green
energy source. From this problem statement, three design objectives were created. The main
design objectives implemented were efficiency, safety, and user friendliness. The project also
included several design constraints that restricted certain solutions. These constraints included
the physical limitations that the prototype had to be equal to or less than 4 cubic feet and no taller
than two feet. In addition, the design could not include lithium-ion batteries or an internal
combustion engine due to safety reasons. Ideally, the chosen design should be efficient, quiet,
and pleasant to the eye in case of installation in an urban environment. Using the design
objectives and decision matrix, viable power production methods were evaluated on a utility
point scale based on how close they fit the criteria. The following report will explain the process
behind choosing the current prototype design.
3
Body of Report
Revised Problem Statement
Design a prototype that generates power from a green energy source.
Proposed Design Solution
Through the research, the three main green energy types in consideration were solar,
wind, and hydro. After learning about possible solutions, a list of objectives was created to
determine which of the possible solutions best fit the problem statement. A weighted objective
tree was then created to summarize which objectives were most important (see Appendix B). A
larger weight was placed on the objective of efficiency (broken down into power and cost)
because it was deemed the most important part of the design. Each possible design solution was
then evaluated through the use of a detailed decision matrix that used a utility scale and relative
weights of the objectives to determine which proposed solution best fit the original problem (see
Appendix C). Popular solutions, such as solar panels, were disregarded due to their immense
initial costs. Hydroelectric generators, the other competing design, were removed due to its
requirement of a nearby water supply. The results determined that wind with a horizontal shaft
was the best design solution for the given criteria. This conclusion resulted from the outside
factors of cost, efficiency, sound, and safety presented in the weighted objective tree.
After a horizontal wind design was chosen, calculations had to be completed properly
before the prototype could be assembled. The required calculations were used to determine the
gear train, blade size, and power all routed back to one another. Due to the Betz Limit, a
windmill can only produce 60% of the energy provided. Using 60% as a stepping stone, working
backwards proved what RPM would be valid as well as the size of gears. Staying on the
conservative side, a 30% efficiency rate was used when calculating the blade speed. Using a
4
Milwaukee wind average of 3.15 m/s, an efficiency rate of 30%, and an estimated TSR of 1.75,
the blade length was calculated at roughly 0.29m (see Appendix G2 – figure 1). This blade
length was calculated to produce 107 Nmm of torque (G2.3) at 181 rpm (G2.2). The gear ratio
was then calculated to find that a ratio of 3:4 would achieve an ideal rpm for the initially chosen
motor.
The blades themselves were cut out of 1/8” abs plastic sheeting due to the strength and
light weight of the material. The blades are 10 inches in length and are in a teardrop shape that
comes to a sharp point (see Appendix A – figure 3). The blades are attached to the assembly
through the use of a threaded eye bolt. A hole is located at the base of each blade. A ¼-20 size
eye bolt is fastened to the back side of each blade using a nut, bolt and washer. Each blade
assembly is then screwed into one of three evenly spaces holes at 120 degrees apart on the nose
of the windmill (A.3). The current blade design is capable of harnessing enough wind energy to
produce a sufficient amount of power. After testing, it was found that the blades have a slight
flex. It may be beneficial to increase the thickness of the material used in order to reduce this
issue.
The blades assembly is attached to a ¼ aluminum shaft, due to its strength and light
weight. Two ¼” ball bearings attach the shaft to the housing and allow it to freely spin with
minimal resistance. The rotational energy from the shaft is transferred to a DC motor by two
small gears. The original design placed the motor parallel and directly below the shaft (A.4).
However, at the start of assembling the prototype, it was discovered that the outside gear
diameter was smaller than anticipated and that the motor could not lie against the shaft without
rubbing. An alteration was made that involved shortening the shaft, moving the rear bearing into
a new, internal wall and building a small platform for the motor to lie on (A.2). The new location
5
for the gear is now at the end of the shaft. This allows for the gears to rotate the motor without
the shaft rubbing. The new design works just as intended and does not seem to have an impact on
power production. For testing purposes, a 1.8v LED was attached to the back of the unit to
indicate power production. A 60 Ohm resistor was added to the circuit to prevent the LED from
being damaged.
After the model was confirmed to work, several safety analyses were conducted to
determine the security of the model. A Failure Mode and Effects Analysis (FMEA) report was
filled out to identify and prevent any problems (see Appendix D). It looked for all the possible
ways that the model could fail and established what actions to take to reduce the risk of priority
areas. The FMEA determined that components like snap rings and electrical wiring were a
relatively low risk priority. The eye bolts and motor, however, were identified as having high
risk priority numbers. Actions were taking by assuring that a high quality motor was used and
Loctite adhesive was applied to the threaded fasteners in the blade assembly.
6
Contribution of Team Members
Grace Ayodele – Semester Project Work Completed
Her contributions to the project included initial research that was used to narrow down
the selection of green energy production and some of the initial design work for the assembly.
For the decision matrix, she focused on assigning more weight to be allotted for safety over the
over objectives. She was also in charge of in the initial design for the base, shaft and housing in
the design assembly, although changes were made for the final design.
Eric Heckman – Semester Project Work Completed
Eric’s initial contributions included online research of green energy projects and
delegating work to the other team members. The majority of his contributions involved the oral
and written reports for the group. He was in charge of putting together the visual aids for all four
PowerPoint presentations and assigned sections to the group. For the initial prototype design, he
was in charge of researching blade types and the final result was his design. He drew the models
for the blades, blade assembly, and revised housing. He was in charge of assembling the
complete CAD assembly after the other team members finished some of the individual parts.
Eric completed both the safety and economic analysis of the prototype. This included the FMEA,
safety labels, and cost breakdown of the model. He assisted Drew in the overall construction of
the prototype and any experimental testing. Lastly, Eric wrote the majority of the body and
economic analysis within the final report, as well as attach all the images in the appendix. He
also assembled and formatted the final report after receiving individual sections from the other
team members.
7
Drew Peden – Semester Project Work Completed
Drew initially conducted online research into various forms of green energy in order to gather
metrics for the design choice. After the research was complete he compiled the team research
into a design matrix in order to determine the direction of the final design. Once the design
matrix determined that a horizontal wind generator would be ideal Drew contributed to initial
mathematical modelling for determination of component parts. He calculated electrical
component values as well. After mathematical modelling and electrical components were
determined Drew spearheaded prototype construction with team assistance due to having more
space available. He assembled the circuit on the prototype as well. Once the prototype was
complete he participated in final tests of the design. He contributed to the conclusions and
recommendations, overall report format, and operating instructions for the final report.
Ryley Rosenfeldt – Semester Project Work Completed
For the engineering analysis, he looked at the different ways that power output was possible
through gears, belts, and chains. He then used this data in order to calculate which gear ratio
would be most efficient as well as not having to worry about the slip that belts and chains can get
once in a while. For the assembly, he drew up all the shaft and bearing assembly along with the
gears. This was then passed onto the team and assembled as a whole.
8
Economic Analysis
Before moving on to a production model, an economic analysis of the design had to be
completed. A detailed spreadsheet of the cost breakdown can be found in Appendix D. The cost
breakdown of the model included both recurring and non-recurring costs of production.
Recurring costs must be paid for each model that is produced and included expenses such as
materials, parts and labor. The majority of the prices were based off of material costs for the
model. The acceptation to this is the housing, which was made out of wood for the model and
would be replaced with an aluminum paneling for the final product. Labor time is also predicted
to lower through the use of modern manufacturing techniques since the figures are based off of
the prototype and is likely to be more expensive than the production model. The overall
estimation for recurring costs was $420. Non-recurring costs include expenses for machinery and
non-labor related time spent on the design or research on the project. The non-recurring expenses
are evenly distributed over each model that is produced are have a smaller overall cost per unit as
more units are produced. The two main tools listed for this design are a molding and stamping
die for the production of windmill blades and paneling for the housing. The estimation for non-
recurring costs is at $46,000. Spread evenly over a 1000 unit run, the overall cost per unit would
be at $46, bringing the total production cost to $466. If the model is sold for a 20% rate of return,
the retail price of the windmill would be set at $560. This fits right into the $400 - $1,200
average range for household, consumer-grade windmills.
9
Bibliography
Fink, Dan. "Small Wind Turbine Basics." Energy Self Sufficiency Newsletter (July 2005): 12-16.
Web.
Gore, Jessica. "A Green Electricity Comparison." Suite. Suite.com, 8 Jan. 2010. Web. 11 May
2014.
"Grid-Tied Solar Power Systems." Whole Sale Solar. N.p., n.d. Web. 10 Apr. 2014.
Klemen, Michael. "Perfect Turbine." Turbines. North Dakota State University, 1 June 2009.
Web. 11 May 2014.
Kroh, Kiley. "Germany Breaks Its Own Record For Solar Power Generation."
ThinkProgress.org. Climate Progress, 22 Aug. 2013. Web. 27 Apr. 2014.
"Solar Water Heaters." Energy.gov. U.S. Department of Energy, 7 May 2012. Web. 10 Apr.
2014.
"Understanding Coefficient of Power (Cp) and Betz Limit." Kid Wind. Kid Wind Project, Mar.
2011. Web.
"Wind Power Your Home | Wind Energy Foundation." Wind Power Your Home. Wind Energy
Foundation, n.d. Web. 4 Mar. 2014.
10
Appendix A – CAD Drawings
Figure 1. Top, front, left and isometric views
Figure 2. Internal view
11
Figure 3. Blade shape and assembly
Blades
Drive and Gearing
Housing
Generator and Circuit
Figure 4. Initial design concepts
Appendix B – Weighted Objective Tree
Energy Source
1.0/1.0
Efficient
.40/.40
Powerful.40/.16
Cost.60/.24
Safe.30/.30
Installing.50/.15
Maintenance.50/.15
User Friendly
.30/.30
Installation.30/.09
Operation.70/.21
12
Appendix C – Decision Matrix
Solar Hydro
Horizontal
Wind
Vertical
Wind
Objective Weight Utility Score Utility Score Utility Score Utility
Power
Generation 0.16 6 0.96 5 0.8 5 0.8 4
Cost 0.24 3 0.72 5 1.2 6 1.44 5
Safety of
Installation 0.15 5 0.75 4 0.6 5 0.75 5
Ease of
Maintenance 0.15 5 0.75 4 0.6 5 0.75 5
Ease of
Installation 0.09 6 0.54 2 0.18 6 0.54 4
Operation 0.21 7 1.47 2 0.42 6 1.26 4
Total Score: 1 32 5.19 22 3.8 33 5.54 27
Appendix D – FMEA
13
System/Component/Function
PotentialFailure Mode
PotentialEffect(s) ofFailure
Seve
rity
PotentialCause(s) ofFailure
Occ
urre
nce
CurrentControls
Det
ectio
nR
PN
RecommendedAction
Snap Rings Bend/Break
Loosen and misalign the shaft 4
Too much play/tension1
High tolerances1 4
Make sure tolerances are tight
ElectricalShort circuit/ Electrical Fire
Loss of power production/ Fire hazard 3
Water/ Circuit overload 1
Proper build quality and tolerences 2 6
Test for leaks and electrical current
Gears Chip Gears can slip 3
Over torque/ Corrosion 2
Higher quality materials 2 12
Use high quality gears
Bearings Wear/Rust
Loss of RPM/ Power production 2
General usage/ Moisture 4
Use high quality bearings and grease 2 16
Test wear levels for bearings
BladesCrack/Fracture from inpact
Loss of balance/ Power production 4
Impact/ Debris buildup 2
Use materials that do not crack easily 3 24
Proper maintenance by the user
DC Motor Wear
Reduction/Loss of power production 3
Over torque/ General wear 3
Use gear ratios to lower the torque 3 27
Make sure torque calculations are correct
Eye BoltsStripping/Loosening
Loss of balance/ Detachment of Blade 5
Improper installation of blades 2
Adhere with Loctite 3 30
Properly assemble blades
14
Appendix F – Economic analysis
Appendix G – Calculations
G1. Experimentally Determined Values of Final Design
Experimentally Determined Values with Wind Velocity of 5 ms
(1) Torque: 0.4 Nm
(2) RPM: 163 = 17 rad
s(3) Current: 35 mA (0.035 A)
(4) Voltage: 2.3 VSwept Area: 0.29 m2
Power Available in Wind: 12
ρ V 3 A= 12 (1.3 kg
m3 )¿23.7 W
Power Generated: Tω = (0.4 Nm)(17rads
¿=¿6.8 W
Percent Efficiency: 6.8
23.7x 100=28.7 %
15
TSR = ωrV
=(17 ) 0.3048
5=1
G2. Initial Calculations
Initial Calculations
(1) Velocity of Wind (5 ms
¿ (0.66 )=3.15 ms
The 5 ms is the yearly average wind velocity of Milwaukee 1948-90 taken from the Wisconsin
Climatology Office at 20 ft.http://www.aos.wisc.edu/~sco/clim-history/stations/mke/milwind.html
The 0.66 coefficient was added to account for less than average wind speeds.
Power Available in Wind: 12
ρ V 3 A=12 (1.3 kg
m3 )¿6.77 W
Including estimated efficiency of 30% (half of Betz Limit) P = 6.77(.03) = 2.03 WIn computing the angular velocity a Tip Speed Ratio (TSR) had to be guessed, we used 1.75
(2) ω=Vr
TSR= 50.3048
1.75=18.9 radsec
=181 rpm
(3) Torque = Pω =
2.03 W
18.9 radsec
= 0.107 Nm = 107 Nmm
(4) Nω=Nω(4)181
3=241 rpm
16
0 1 2 3 4 5 6 7 80
10
20
30
40
50
60
70
Power in Wind (Watts)
Wind Velocity (m/s)
Power Available in Wind (W)