Visio-PRDC GROUP Project Scheduling

1
ID Task Name Start Finish Duration 2015 2016 2017 2018 2019 Jan Feb Mar Apr Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Jun 1 151d 7/30/2015 1/1/2015 Assess Phase 151d 7/30/2015 1/1/2015 Feasibility Studies 3 44d 4/2/2015 2/2/2015 Environmental Impact Assessment 90d 6/5/2015 2/2/2015 Appraisal Programme 5 110d 12/31/2015 7/31/2015 Select Phase 6 45d 9/30/2015 7/30/2015 3D Seismic Data Acquisition 7 60d 10/22/2015 7/31/2015 Concept Selection 8 45d 12/24/2015 10/23/2015 Preparation of Basis for Design 9 6d 1/1/2016 12/25/2015 FDP Approval 10 210d 10/20/2016 1/1/2016 Define Phase 11 60d 3/24/2016 1/1/2016 Detailed Engineering Surveys 400d 8/28/2017 2/16/2016 Procurement of Long Lead Engineering Items 12 31d 2/15/2016 1/4/2016 Front End Engineering Design Stage 1 14 180d 10/20/2016 2/12/2016 Front End Engineering Design Stage 2 15 637d 4/1/2019 10/21/2016 Execution Phase 16 502d 9/24/2018 10/21/2016 Wells 17 100d 8/11/2017 3/27/2017 Pipelines and Flowlines 19 400d 10/5/2018 3/27/2017 Gathering Stations (Two Phases) 20 590d 1/24/2019 10/21/2016 Central Processing Facilities 21 129d 4/9/2019 10/11/2018 Modifications to Gamba Terminal Jul Aug Sep Oct Nov 4 2 13 22 48d 6/14/2019 4/10/2019 Commissioning and Start-up of Facilities 23 1d 6/17/2019 6/17/2019 First Oil 18 292d 10/10/2018 8/29/2017 Pipelines and Flowlines (Phase 2)

description

Gantt Chart for Hypothetical Project

Transcript of Visio-PRDC GROUP Project Scheduling

ID Task Name Start Finish Duration2015 2016 2017 2018 2019

Jan Feb Mar Apr Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Jun

1 151d7/30/20151/1/2015Assess Phase

151d7/30/20151/1/2015Feasibility Studies

3 44d4/2/20152/2/2015Environmental Impact

Assessment

90d6/5/20152/2/2015Appraisal Programme

5 110d12/31/20157/31/2015Select Phase

6 45d9/30/20157/30/20153D Seismic Data Acquisition

7 60d10/22/20157/31/2015Concept Selection

8 45d12/24/201510/23/2015Preparation of Basis for Design

9 6d1/1/201612/25/2015FDP Approval

10 210d10/20/20161/1/2016Define Phase

11 60d3/24/20161/1/2016Detailed Engineering Surveys

400d8/28/20172/16/2016Procurement of Long Lead

Engineering Items

12 31d2/15/20161/4/2016Front End Engineering Design

Stage 1

14 180d10/20/20162/12/2016Front End Engineering Design

Stage 2

15 637d4/1/201910/21/2016Execution Phase

16 502d9/24/201810/21/2016Wells

17 100d8/11/20173/27/2017Pipelines and Flowlines

19 400d10/5/20183/27/2017Gathering Stations (Two

Phases)

20 590d1/24/201910/21/2016Central Processing Facilities

21 129d4/9/201910/11/2018Modifications to Gamba

Terminal

Jul Aug Sep Oct Nov

4

2

13

22 48d6/14/20194/10/2019Commissioning and Start-up of

Facilities

23 1d6/17/20196/17/2019First Oil

18 292d10/10/20188/29/2017Pipelines and Flowlines (Phase

2)