Utracon Method statement for PT slabs 15 12 2008

53

Transcript of Utracon Method statement for PT slabs 15 12 2008

Page 1: Utracon Method statement for PT slabs 15 12 2008
Page 2: Utracon Method statement for PT slabs 15 12 2008

Method Statement of Utracon Post-Tensioning Systems U T R A C O N

UTRACON STRUCTURAL SYSTEMS PVT LTD

METHOD STATEMENT

CONTENTS

Page

1. General

2. Post Tensioning Systems

3. Materials

4. Design Data for friction 1 elongation calculation

5. Handling and Storage of Materials

6. General Work Procedures

7. Guidelines for Tendon Installation

8. Stressing

9. Grouting

UTRACON STRUCTURAL SYSTEMS PVT LTD Page 2 of 10

Page 3: Utracon Method statement for PT slabs 15 12 2008

Method Statement of Utracon Post-Tensioning Systems

UTRACON STRUCTURAL SYSTEMS PVT LTD Page 3 of 10

UTRACON STRUCTURAL SYSTEMS PVT LTD

APPENDICES

APPENDIX A.1 Details of UPS Anchorage System

APPENDIX A.2 Details of Hydraulic Jacks

APPENDIX A.3 Summary of Stressing Pressure for Jacks

APPENDIX A.4 Samples of Stressing Report and Interpretation of Stressing Reports

APPENDIX A.5 Technical Details of admixture :

APPENDIX A.6 Checklist for Post-Tensioning Works

APPENDIX A.7 Quality Assurance Procedures

Page 4: Utracon Method statement for PT slabs 15 12 2008
Page 5: Utracon Method statement for PT slabs 15 12 2008
Page 6: Utracon Method statement for PT slabs 15 12 2008
Page 7: Utracon Method statement for PT slabs 15 12 2008
Page 8: Utracon Method statement for PT slabs 15 12 2008

Method Statement of Utracon Post-Tensioning Systems

UTRACON STRUCTURAL SYSTEMS PVT LTD Page 8 of 10

8.2 Stressing of Flat Tendons

• The jack shall be carried by hand to the stressing anchorage.

• Connect jack to hydraulic pump with hydraulic hoses.

• Strand shall be inserted to the jack.

• 25% of the stressing force shall be applied to the tendon to remove slack in the strands.

• Mark shall be made to the strands.

• Proceed with the stressing to the full force.

• Measure the distance of the spray mark to the wedge plate. This will reflect the strand’s elongation from 25% to 100% force. ( assume X mm )

• Add the wedge draw-in of 6mm to the X.

• Effective strand’s elongation from 25% to 100% stressing force, Y

• The total elongation (from 0% to 100% force) shall be calculated by extrapolation of the

value Y.

• Compare the full elongation (actual elongation) against the theoretical value.

A sample of the Stressing Report and interpretation of stressing report are shown in Appendix A.4. De-Shuttering at pour strip area can be carried out after completion of concreting in that area and after achievement of required compressive strength.

Unbalance load from the floor under construction to be distributed with calculated spacing of props.

9. Grouting

Grouting shall not commence unless the consultant has approved the stressing result. Preparation for grouting

• Cut the protruding strands (stressing length) to a minimum of 10mm from the wedge plate.

• The anchorage blackouts shall be filled with the approved cementitious material. • The grouting shall be continued after a minimum period of 24 hours of drying of

the patch up. • Prior to grouting, the ducts shall be thoroughly cleaned by oil free compressed

air.

Y = X + 6mm

Total Strand’s Elongation = Y x 100 75

Page 9: Utracon Method statement for PT slabs 15 12 2008

Method Statement of Utracon Post-Tensioning Systems

UTRACON STRUCTURAL SYSTEMS PVT LTD Page 9 of 10

Proposed grout mix

• Cement in standard 50kg package

(Ordinary Portland cement 53 grade)

• Water = 0.45 x 50kg = 22.5 kg = 22.5 litres

• Admixture = 0.2% weight of cement ( 50 kg ) = 100 ml Mixing sequence = water – additive – cement Min mixing time = 3-4 min 9.1 Tests for grouting

• Viscosity

• Compressive strength. 9.2 Viscosity test

• Viscosity test will be executed by means of a flow cone. • Flow time is measured with a stop watch. • It is the measurement of time that the grout takes to completely flow out of the cone. • It is carried out after the 3-4 min minimum mixing time. • The flow time should be between 10 to 25 seconds.

76 mm

191 mm

38 mm

Filled Level

178 mm Ø

12.7 mm Ø

Page 10: Utracon Method statement for PT slabs 15 12 2008
Page 11: Utracon Method statement for PT slabs 15 12 2008
Page 12: Utracon Method statement for PT slabs 15 12 2008
Page 13: Utracon Method statement for PT slabs 15 12 2008
Page 14: Utracon Method statement for PT slabs 15 12 2008
Page 15: Utracon Method statement for PT slabs 15 12 2008
Page 16: Utracon Method statement for PT slabs 15 12 2008
Page 17: Utracon Method statement for PT slabs 15 12 2008
Page 18: Utracon Method statement for PT slabs 15 12 2008
Page 19: Utracon Method statement for PT slabs 15 12 2008
Page 20: Utracon Method statement for PT slabs 15 12 2008
Page 21: Utracon Method statement for PT slabs 15 12 2008
Page 22: Utracon Method statement for PT slabs 15 12 2008
Page 23: Utracon Method statement for PT slabs 15 12 2008
Page 24: Utracon Method statement for PT slabs 15 12 2008
Page 25: Utracon Method statement for PT slabs 15 12 2008
Page 26: Utracon Method statement for PT slabs 15 12 2008
Page 27: Utracon Method statement for PT slabs 15 12 2008
Page 28: Utracon Method statement for PT slabs 15 12 2008
Page 29: Utracon Method statement for PT slabs 15 12 2008
Page 30: Utracon Method statement for PT slabs 15 12 2008
Page 31: Utracon Method statement for PT slabs 15 12 2008
Page 32: Utracon Method statement for PT slabs 15 12 2008

INTERPRETATION OF STRESSING RESULTS

I Check Elongation ( X 1 for 1

Average Deviation per Average Deviation per

within * 8%

Note :

Average Devialion per Average Deviation per pour I over beam section pour I overpeam section

within * 8%

Average Deviation per Average Devialion per

within i 8%

( A ) The Engineer shall be informed and consulted for more thorough investigation and design check.

Page 33: Utracon Method statement for PT slabs 15 12 2008

SAMPLE

Sheet 1

FORM SS60U04 (REV 0 - 01M1102) Page 1 of 1

of 5

--____....__.-_..A --,." ".__,___..~ ---_ _- .----%" * ..D_ --. .......................... I........ .,. . . I. . .

4

TENDON STRESSING REPORT (Multistrand Anchorage - MA)

PROJECT NAME : ABC BUILDING

STOREY : 1ST STOREY JACK NO : CH 4006 - I

BEAM MARK : 1 PBI GAUGENO: 25

TENDON NO: TI STRESSING FORCE : (kN)

TENDON TYPE : 19 s STRESSING PRESSURE :

CASTING DATE : - (MPa)

Gauge Pressure

(Mpa)

0

10

20

30

40

50

62.9

Gauge Pressure

(MP4

0

Measurement mm

- 50 --

105 -- 162 -

220 -

276 - 351 --

Extension mrn

57

55

57

58

56 ---- 75

a L,

Measurement mm

-

P

358

Actual Extension (rnm) Theoretical Extension (mm)

Ex(erlsior1 m m

-------A

-

--

-

A L2

Extension in

X Extension mm

--

.

Date :

Witnessed by :

- 4

354 350

Jack

Comments

--

--

L

RESULT :

+1.14%

-- --

-- --

A Ll, f L2

358

Page 34: Utracon Method statement for PT slabs 15 12 2008

APPENDIX A.4

SUMMARY OF STRESSING RESULTS

BLOCK : WEST AREA : 3RD STOREY

REMARKS:

* Stressing force of 75% UTS was maintained for 15 seconds.

# Tendons were stressed to 80% UTS and maintained for 15 seconds.

The average deviation for the pour is +2.10% which falls within the tolerance of &8%.

Therefore, the result for the whole pour is acceptable.

Tt-IEORECTICAL

EXTENSION

170 - .....

170 - ...............................................

180

180 .........................................................

60 . . . . . . . . . . .

60 .........................................

60 .-..

6 4

90

90

1 7 i

110

ACTUAL

EXTENSION

' 175

180 -. .. .-.--

160

165 - - .. - ...

70 .. - .... -- -- - ---

70

6 5 .......

60

85

90

185

110

BEAM MARK

3PB-1

3PE3-3

3PB-4

UTS - Ultimate Tensile Strength of Strand

c

TENDON MARK

a1 -...

a2 ----- . - .....

b

a - - - - ... -.

b I

b2

c - d

e

f

a

b

DEVIATION

(%)

2.94 ....................

5.88 .............

# -11.11

# -8.33 - .... - ..........................

x 16.67 - ......... -. . . . . .

* 16.67 ............

8.33 ........

-6.25

-5.56

0.00

5.71

0.00

72 1-

AVERAGE

DEVIATION (%)

-0.76

-2.78

6.53

13.89

OVERALL DEVIATION 2.10

Page 35: Utracon Method statement for PT slabs 15 12 2008
Page 36: Utracon Method statement for PT slabs 15 12 2008
Page 37: Utracon Method statement for PT slabs 15 12 2008
Page 38: Utracon Method statement for PT slabs 15 12 2008
Page 39: Utracon Method statement for PT slabs 15 12 2008
Page 40: Utracon Method statement for PT slabs 15 12 2008
Page 41: Utracon Method statement for PT slabs 15 12 2008
Page 42: Utracon Method statement for PT slabs 15 12 2008
Page 43: Utracon Method statement for PT slabs 15 12 2008
Page 44: Utracon Method statement for PT slabs 15 12 2008
Page 45: Utracon Method statement for PT slabs 15 12 2008
Page 46: Utracon Method statement for PT slabs 15 12 2008
Page 47: Utracon Method statement for PT slabs 15 12 2008
Page 48: Utracon Method statement for PT slabs 15 12 2008
Page 49: Utracon Method statement for PT slabs 15 12 2008
Page 50: Utracon Method statement for PT slabs 15 12 2008
Page 51: Utracon Method statement for PT slabs 15 12 2008
Page 52: Utracon Method statement for PT slabs 15 12 2008
Page 53: Utracon Method statement for PT slabs 15 12 2008