PT Slabs Working Sequence

download PT Slabs Working Sequence

of 17

Transcript of PT Slabs Working Sequence

  • 7/29/2019 PT Slabs Working Sequence

    1/17

    Completion of Bottom shuttering.

    WORKING SEQUENCE STEP 1

  • 7/29/2019 PT Slabs Working Sequence

    2/17

    Completion of Bottom Nominal reinforcements

    WORKING SEQUENCE STEP 2

  • 7/29/2019 PT Slabs Working Sequence

    3/17

    WORKING SEQUENCE

    GI Ducts Laying

    STEP 3

  • 7/29/2019 PT Slabs Working Sequence

    4/17

    Fixing of ducts at End Anchorages.

    WORKING SEQUENCE STEP 4

  • 7/29/2019 PT Slabs Working Sequence

    5/17

    WORKING SEQUENCE

    Threading of HT strands into Ducts .

    STEP 5

  • 7/29/2019 PT Slabs Working Sequence

    6/17

    Fixing of bar chair to form tendon profile.

    WORKING SEQUENCE STEP 6

  • 7/29/2019 PT Slabs Working Sequence

    7/17

    Stressing anchorages.

    Stressing end Anchorage

    WORKING SEQUENCE STEP 7

  • 7/29/2019 PT Slabs Working Sequence

    8/17

    Fixing of Dead ends and Fixing of grout vent.

    WORKING SEQUENCE STEP 8

  • 7/29/2019 PT Slabs Working Sequence

    9/17

    WORKING SEQUENCE

    Laying of Tendons on completion

    STEP 9

  • 7/29/2019 PT Slabs Working Sequence

    10/17

    WORKING SEQUENCE

    View of PT Tendon after Laying.

    STEP 10

  • 7/29/2019 PT Slabs Working Sequence

    11/17

  • 7/29/2019 PT Slabs Working Sequence

    12/17

    25 % of initial stressing.

    Stressing of Strands to 100 % force

    WORKING SEQUENCESTEP 12

  • 7/29/2019 PT Slabs Working Sequence

    13/17

    Mono Jack Stressing Of Slab Tendons.

    Paint Mark shows Elongation

    WORKING SEQUENCESTEP 13

  • 7/29/2019 PT Slabs Working Sequence

    14/17

    WORKING SEQUENCE

    ANCHORAGES AFTER STRESSING

    STEP 14

  • 7/29/2019 PT Slabs Working Sequence

    15/17

    WORKING SEQUENCE

    ANCHORA

    GES

    AF

    TER

    STRESSING

    STEP 15

  • 7/29/2019 PT Slabs Working Sequence

    16/17

    WORKING SEQUENCE

    Patching up live end anchorages.

    STEP 16

  • 7/29/2019 PT Slabs Working Sequence

    17/17

    WORKING SEQUENCE

    PT Flat slab after Deshuttering.

    STEP 17