Urban Water Supply - Carrathool Shire · 2015-06-28 · Overview of urban schemes ... •Supports...
Transcript of Urban Water Supply - Carrathool Shire · 2015-06-28 · Overview of urban schemes ... •Supports...
![Page 1: Urban Water Supply - Carrathool Shire · 2015-06-28 · Overview of urban schemes ... •Supports human needs ... 2022/23 Replace aerator at WTW $100,000 2028/29 Replace bore 2 90,000](https://reader034.fdocuments.in/reader034/viewer/2022050223/5f6817fcb29a0b420c3dd135/html5/thumbnails/1.jpg)
Urban Water Supply
Presentation to Community Consultation 17 January 2012
![Page 2: Urban Water Supply - Carrathool Shire · 2015-06-28 · Overview of urban schemes ... •Supports human needs ... 2022/23 Replace aerator at WTW $100,000 2028/29 Replace bore 2 90,000](https://reader034.fdocuments.in/reader034/viewer/2022050223/5f6817fcb29a0b420c3dd135/html5/thumbnails/2.jpg)
Session Agenda
Background Overview of urban schemes – towns &
villages Upgrade/renewal works completed Upgrade/renewal works – next 20 Years Options for change
![Page 3: Urban Water Supply - Carrathool Shire · 2015-06-28 · Overview of urban schemes ... •Supports human needs ... 2022/23 Replace aerator at WTW $100,000 2028/29 Replace bore 2 90,000](https://reader034.fdocuments.in/reader034/viewer/2022050223/5f6817fcb29a0b420c3dd135/html5/thumbnails/3.jpg)
Background - CSC Water Supply Network
•Largest in NSW •Supports human needs •Supports economy •All drinking water pumped from bores •Low number of customers – especially the villages •Extensive recent upgrades •CSC is a Local Water Utility - regulated •CSC consistently supplies safe drinking water to residents
![Page 4: Urban Water Supply - Carrathool Shire · 2015-06-28 · Overview of urban schemes ... •Supports human needs ... 2022/23 Replace aerator at WTW $100,000 2028/29 Replace bore 2 90,000](https://reader034.fdocuments.in/reader034/viewer/2022050223/5f6817fcb29a0b420c3dd135/html5/thumbnails/4.jpg)
Background – Water Supply Cost
Urban & Rural:
Actual 2008/09
Actual 2009/10
Actual 2010/11
Estimate 2011/12
Operation Expense 839,383 947,526 944,714 982,900
Capital Expense 533,141 185,016 163,584 605,000
TOTAL 1,372,524 1,132,542 1,108,298 1,587,900
![Page 5: Urban Water Supply - Carrathool Shire · 2015-06-28 · Overview of urban schemes ... •Supports human needs ... 2022/23 Replace aerator at WTW $100,000 2028/29 Replace bore 2 90,000](https://reader034.fdocuments.in/reader034/viewer/2022050223/5f6817fcb29a0b420c3dd135/html5/thumbnails/5.jpg)
Background - Operating costs
New electricity tender contains costs to 7%
![Page 6: Urban Water Supply - Carrathool Shire · 2015-06-28 · Overview of urban schemes ... •Supports human needs ... 2022/23 Replace aerator at WTW $100,000 2028/29 Replace bore 2 90,000](https://reader034.fdocuments.in/reader034/viewer/2022050223/5f6817fcb29a0b420c3dd135/html5/thumbnails/6.jpg)
Overview – Scheme Assets
Urban Water Supply Hillston Goolgowi/Merriwagga Carrathool
Bores/Water Source 3 2 2
Ancilliary 2
Generators/Telemetry 2 Generators/Telemetry 2 Generators/Telemetry Aerators 2 1 0
Water Mains 21Km 73Km 6.5Km
Water Pumping Stations 3 4 2
Water Reservoirs 2 9 2
Water Treatment Works 2 1 1
Est. Replacement Value (2007) $4,336,547.00 $8,243,983.00 $1,137,423.00
Total $13,717,953.00 Note: 2007 Valuation figures used
2011 Valuation in progress - values known to be higher than 2007
![Page 7: Urban Water Supply - Carrathool Shire · 2015-06-28 · Overview of urban schemes ... •Supports human needs ... 2022/23 Replace aerator at WTW $100,000 2028/29 Replace bore 2 90,000](https://reader034.fdocuments.in/reader034/viewer/2022050223/5f6817fcb29a0b420c3dd135/html5/thumbnails/7.jpg)
Urban Water Supply (20mm Connections)
HILLSTON GOOLGOWI MERRIWAGGA RANKINS SPRINGS CARRATHOOL
Customers Residential 357 114 25 19 20 Pensioners 100 16 9 18 12 Non Residential 58 29 5 10 4 Non Rateable 9 5 2 2
Total 524 164 39 49 38 Water Usage (kL) Potable -Residential 346 180 270 297 Potable - Pensioners 255 171 236 225 Potable - Non Residential 163 161 1019 354 Potable - Non Rateable 390 59 438 Raw - Residential 152 313 Raw - Pensioners 136 135 Raw - Non Residential 191 113 Raw - Non Rateable 1323 247
Average Bill (20mm Connection) Residential $509.13 $912.68 $850.74 $974.12 $805.82 Pensioner $349.45 $785.11 $731.74 $782.88 $639.43 Non Residential $374.93 $797.79 $1,427.01 $856.82 $868.53 Non Rateable $487.41 $1,445.48 $925.65 $956.80
![Page 8: Urban Water Supply - Carrathool Shire · 2015-06-28 · Overview of urban schemes ... •Supports human needs ... 2022/23 Replace aerator at WTW $100,000 2028/29 Replace bore 2 90,000](https://reader034.fdocuments.in/reader034/viewer/2022050223/5f6817fcb29a0b420c3dd135/html5/thumbnails/8.jpg)
Cost of operations Hillston
Hillston Water - Total Costs - Last 3 years
Scheme Actual
2008/09 Actual
2009/10 Actual
2010/11 Estimate 2011/12
Operational Costs $195,388 $222,162 $216,360 $238,000 Capital Costs $457,788 $70,077 $26,509 $252,000 TOTAL $653,176 $292,239 $242,869 $490,000
![Page 9: Urban Water Supply - Carrathool Shire · 2015-06-28 · Overview of urban schemes ... •Supports human needs ... 2022/23 Replace aerator at WTW $100,000 2028/29 Replace bore 2 90,000](https://reader034.fdocuments.in/reader034/viewer/2022050223/5f6817fcb29a0b420c3dd135/html5/thumbnails/9.jpg)
Asset Renewals & Capital projects Hillston
•New bore 4 & Aerodrome PS completed - $752,000 •WTW switchboard upgrade - $75,000 •WTW safety upgrade commenced - $20,000 •New bore 5 commenced – near completion - $150,000 •Commenced fire hydrant replacements - $10,000 •Upgrade radio telemetry •New radio telemetry & internet links Note: CSC successfully obtained $360,000 Drought Relief grant reimbursement 50% cost of Aerodrome PS
![Page 10: Urban Water Supply - Carrathool Shire · 2015-06-28 · Overview of urban schemes ... •Supports human needs ... 2022/23 Replace aerator at WTW $100,000 2028/29 Replace bore 2 90,000](https://reader034.fdocuments.in/reader034/viewer/2022050223/5f6817fcb29a0b420c3dd135/html5/thumbnails/10.jpg)
Cost of operations Goolgowi
Goolgowi Water - Total Costs - Last 3 years
Scheme Actual
2008/09 Actual
2009/10 Actual
2010/11 Estimate 2011/12
Operational Costs $310,545 $338,751 $353,362 $343,000 Capital Costs $58,840 $36,815 $37,677 $114,000 TOTAL $369,385 $375,566 $391,039 $457,000
![Page 11: Urban Water Supply - Carrathool Shire · 2015-06-28 · Overview of urban schemes ... •Supports human needs ... 2022/23 Replace aerator at WTW $100,000 2028/29 Replace bore 2 90,000](https://reader034.fdocuments.in/reader034/viewer/2022050223/5f6817fcb29a0b420c3dd135/html5/thumbnails/11.jpg)
Asset Renewals & Capital projects Goolgowi
•Palmyra PS major upgrade - $80,000 •Goolgowi Dam PS – raw water filtration •Goolgowi Dam PS – floating off-takes - $13,000 •Merriwagga aerator bird-proofed - $2,000 •Radio telemetery upgrades at multiple sites
![Page 12: Urban Water Supply - Carrathool Shire · 2015-06-28 · Overview of urban schemes ... •Supports human needs ... 2022/23 Replace aerator at WTW $100,000 2028/29 Replace bore 2 90,000](https://reader034.fdocuments.in/reader034/viewer/2022050223/5f6817fcb29a0b420c3dd135/html5/thumbnails/12.jpg)
Cost of operations Carrathool
Carrathool Water - Total Costs - Last 3 years
Scheme Actual
2008/09 Actual
2009/10 Actual
2010/11 Estimate 2011/12
Operational Costs $29,867 $48,108 $48,304 $34,350 Capital Costs $235 $10,644 $7,425 $15,000 TOTAL $30,102 $58,752 $55,729 $49,350
![Page 13: Urban Water Supply - Carrathool Shire · 2015-06-28 · Overview of urban schemes ... •Supports human needs ... 2022/23 Replace aerator at WTW $100,000 2028/29 Replace bore 2 90,000](https://reader034.fdocuments.in/reader034/viewer/2022050223/5f6817fcb29a0b420c3dd135/html5/thumbnails/13.jpg)
Asset Renewals & Capital projects Carrathool
•New bore 2 commissioned into service •New bore pump installed •Safety upgrade to disinfection system •Water conditioning (aerator) trialled •Leak sealing of village storage reservoirs •Installed radio telemetry at bore site •Commissioned new internet remote comms link
![Page 14: Urban Water Supply - Carrathool Shire · 2015-06-28 · Overview of urban schemes ... •Supports human needs ... 2022/23 Replace aerator at WTW $100,000 2028/29 Replace bore 2 90,000](https://reader034.fdocuments.in/reader034/viewer/2022050223/5f6817fcb29a0b420c3dd135/html5/thumbnails/14.jpg)
20 Year Forward Plan - First 5 years HILLSTON WATER 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 New Assets Hand held meter data logger 20 Hillston WTW remote quality sensing 5 Develop bore 5 150 Water quality(softening) investigation 5 Water softening Hillston WTW 50 Water softening Bore 4 40 Back up generator bore 5 50
Sub Total 180 50 40 0 0 50 Asset replacement Hillston Reservoir: int & ext condition assessment 10
Hillston WTW OH&S & facility upgrade 20 Hillston Reservoir :new ladder 30 Hydrant replacement 10 10 10 10 10 Mains replacement: AC: 118m: 12 12 Mains replacement: 200mm 20 Mains replacement: 150mm 68 Pump replacements Bore 2, 4, 5 , WTW –provision 8 8 3 3
Sub Total 97 50 81 10 13 0 Total Hillston 277 100 121 10 13 0
![Page 15: Urban Water Supply - Carrathool Shire · 2015-06-28 · Overview of urban schemes ... •Supports human needs ... 2022/23 Replace aerator at WTW $100,000 2028/29 Replace bore 2 90,000](https://reader034.fdocuments.in/reader034/viewer/2022050223/5f6817fcb29a0b420c3dd135/html5/thumbnails/15.jpg)
20 Year Forward Plan - First 5 years
GOOLGOWI / MERRIWAGGA WATER 2011/12
2012/13
2013/14
2014/15
2015/16
2016/17
New Assets Goolgowi:additional potable storage tanks 50 Merriwagga: Additional potable tanks potable: 75 Palintest water analyser 2 Remote water quality sensing: Langtree PS 8 Upgrade gas storage/detection : Langtree PS 5 Water softening: Merriwagga & Goolgowi 50
Sub Total 15 50 0 75 0 50 Asset Replacement Goolgowi: Hydrant replacements 3 3 3 3 3 3 Pump replacement – Langtree PS 15 Pump replacements - provision 4 4 4 4 4 4 Merriwagga: Hydrant replacement 3 3 3 Merriwagga: replace old aerator 75 Upgrade telemetry at Goolgowi Dam PS 3 Goolgowi: Reseal storage tanks 10
Sub Total 23 10 10 22 7 82 Total - Goolgowi 38 60 10 97 7 132
![Page 16: Urban Water Supply - Carrathool Shire · 2015-06-28 · Overview of urban schemes ... •Supports human needs ... 2022/23 Replace aerator at WTW $100,000 2028/29 Replace bore 2 90,000](https://reader034.fdocuments.in/reader034/viewer/2022050223/5f6817fcb29a0b420c3dd135/html5/thumbnails/16.jpg)
20 Year Forward Plan - First 5 years
CARRATHOOL WATER 2011/12
2012/13
2013/14
2014/15
2015/16
2016/17
New Assets Remote water quality sensing 5 New aerator 40 Water softening treatment 35
Sub Total 5 40 0 35 0 0 Replacement Asset Pump replacements - provision 2 2 2 2 2 2 Replace switchboard 35 Renew disinfection system 3
Sub Total 2 2 2 2 40 2 Total Carrathool 7 42 2 37 32 25
Note: Over the 5 year period $59,000 for communications & telemetry works common to all schemes
![Page 17: Urban Water Supply - Carrathool Shire · 2015-06-28 · Overview of urban schemes ... •Supports human needs ... 2022/23 Replace aerator at WTW $100,000 2028/29 Replace bore 2 90,000](https://reader034.fdocuments.in/reader034/viewer/2022050223/5f6817fcb29a0b420c3dd135/html5/thumbnails/17.jpg)
20 Year Forward Plan – Major items Yrs 6 - 20
Hillston 2022/23 Replace aerator at WTW $100,000 2028/29 Replace bore 2 90,000 2029/30 Mains replacements 100,000 Goolgowi 2020/21 Extend mains -east 45,000 2021/21 Extend mains – west 135,000 2022/23 Bore pump replacement 15,000 2025/26 Replace Langtree bore 100,000 2025/26 Renew mains Merriwagga 250,000
Carrathool No major planned renewals –mains replacements to commence 2040
![Page 18: Urban Water Supply - Carrathool Shire · 2015-06-28 · Overview of urban schemes ... •Supports human needs ... 2022/23 Replace aerator at WTW $100,000 2028/29 Replace bore 2 90,000](https://reader034.fdocuments.in/reader034/viewer/2022050223/5f6817fcb29a0b420c3dd135/html5/thumbnails/18.jpg)
Capital works – Urban & Rural
Schemes 2010/11 – 2014/15
2015/16 – 2019/20
2021/22 -2024/25
20025/26 – 2029/310 Total
Hillston 508,000 69,000 125,000 205,000 907,000
Goolgowi 583,000 177,000 765,000 417,000 1,942,000
Carrathool 88,000 51,000 10,000 10,000 159,000
Rankins Springs 929,000 187,000 447,000 41,000 1,604,000
Melbergen 572,000 130,000 51,000 20,000 773,000
20 year Total: $5,385,000
Proposed to use long-term loans to fund these works
![Page 19: Urban Water Supply - Carrathool Shire · 2015-06-28 · Overview of urban schemes ... •Supports human needs ... 2022/23 Replace aerator at WTW $100,000 2028/29 Replace bore 2 90,000](https://reader034.fdocuments.in/reader034/viewer/2022050223/5f6817fcb29a0b420c3dd135/html5/thumbnails/19.jpg)
End
![Page 20: Urban Water Supply - Carrathool Shire · 2015-06-28 · Overview of urban schemes ... •Supports human needs ... 2022/23 Replace aerator at WTW $100,000 2028/29 Replace bore 2 90,000](https://reader034.fdocuments.in/reader034/viewer/2022050223/5f6817fcb29a0b420c3dd135/html5/thumbnails/20.jpg)
Options for change
Community Consultation Urban Water Supply
17 January 2012
![Page 21: Urban Water Supply - Carrathool Shire · 2015-06-28 · Overview of urban schemes ... •Supports human needs ... 2022/23 Replace aerator at WTW $100,000 2028/29 Replace bore 2 90,000](https://reader034.fdocuments.in/reader034/viewer/2022050223/5f6817fcb29a0b420c3dd135/html5/thumbnails/21.jpg)
Options for change
1. Do nothing – keep things as they are 2. Consolidate urban schemes
![Page 22: Urban Water Supply - Carrathool Shire · 2015-06-28 · Overview of urban schemes ... •Supports human needs ... 2022/23 Replace aerator at WTW $100,000 2028/29 Replace bore 2 90,000](https://reader034.fdocuments.in/reader034/viewer/2022050223/5f6817fcb29a0b420c3dd135/html5/thumbnails/22.jpg)
Options for change 1. Do nothing – keep things as they are
$0.00
$200.00
$400.00
$600.00
$800.00
$1,000.00
$1,200.00
$1,400.00
$1,600.00
Residential Pensioner Non Residential
Non Rateable
Hillston Goolgowi Merriwagga Rankins Springs Carrathool
Average Bill 20mm 2010-2011
![Page 23: Urban Water Supply - Carrathool Shire · 2015-06-28 · Overview of urban schemes ... •Supports human needs ... 2022/23 Replace aerator at WTW $100,000 2028/29 Replace bore 2 90,000](https://reader034.fdocuments.in/reader034/viewer/2022050223/5f6817fcb29a0b420c3dd135/html5/thumbnails/23.jpg)
Option 1:Do nothing – no change
•The gap between Hillston charges and all villages will increase even further •Funds raised in one scheme must be spent in that scheme •Smaller schemes unable to fund larger capital works e.g. potable water for Rankins Springs •Long pay-back periods for loans by small schemes with high interest cost •Village populations may decline as charges keep going up •Long-term sustainability of some schemes may be threatened
![Page 24: Urban Water Supply - Carrathool Shire · 2015-06-28 · Overview of urban schemes ... •Supports human needs ... 2022/23 Replace aerator at WTW $100,000 2028/29 Replace bore 2 90,000](https://reader034.fdocuments.in/reader034/viewer/2022050223/5f6817fcb29a0b420c3dd135/html5/thumbnails/24.jpg)
Option 2. Consolidate schemes Five separate schemes become one All customers receive the same benefit of water from
the tap All customer categories pay the same charges All customers share combined costs Monies raised can be directed to highest priority
works when required across the network Better ability to fund major capital works ( like mains
replacements) and better ability to repay loans from larger customer base
Simplifies administration Strong trend over last decade by water utilities and
councils to consolidate
![Page 25: Urban Water Supply - Carrathool Shire · 2015-06-28 · Overview of urban schemes ... •Supports human needs ... 2022/23 Replace aerator at WTW $100,000 2028/29 Replace bore 2 90,000](https://reader034.fdocuments.in/reader034/viewer/2022050223/5f6817fcb29a0b420c3dd135/html5/thumbnails/25.jpg)
END
![Page 26: Urban Water Supply - Carrathool Shire · 2015-06-28 · Overview of urban schemes ... •Supports human needs ... 2022/23 Replace aerator at WTW $100,000 2028/29 Replace bore 2 90,000](https://reader034.fdocuments.in/reader034/viewer/2022050223/5f6817fcb29a0b420c3dd135/html5/thumbnails/26.jpg)
Comparison CSC – Griffith CC – Goldenfields Water
CSC GWCC GCC Customers 1034 10500 9900
Length of Mains (Km) 480 1780 500
Staff (FTE) 8 58 33
Customers per Kilometre 2.2 6 20
Staff per Kilometre mains 0.02 0.033 0.7
Customers per staff 130 181 300
![Page 27: Urban Water Supply - Carrathool Shire · 2015-06-28 · Overview of urban schemes ... •Supports human needs ... 2022/23 Replace aerator at WTW $100,000 2028/29 Replace bore 2 90,000](https://reader034.fdocuments.in/reader034/viewer/2022050223/5f6817fcb29a0b420c3dd135/html5/thumbnails/27.jpg)
Comparison CSC – Griffth CC – Goldenfields Water CSC GWCC GCC
Residential 20mm 150/1.83 123/0.55/1.08 Residential 25 mm 234/1.83 192/0.55/108
Non-residential 20mm 206/1.74 Non-residential 25mm 321/1.74
Rural 20mm 257/1.64 Rural 25mm 402/1.64 Rural 50mm 1287/1.64 Rural 80mm