TRD Production at GSI Joerg Hehner TRD Collaboration Meeting Bucharest 26.09.2005.

14
TRD Production at GSI Joerg Hehner TRD Collaboration Meeting Bucharest 26.09.2005

Transcript of TRD Production at GSI Joerg Hehner TRD Collaboration Meeting Bucharest 26.09.2005.

TRD Production at GSI

Joerg Hehner TRD Collaboration Meeting Bucharest 26.09.2005

Overview

Joerg Hehner TRD Collaboration Meeting Bucharest 26.09.2005

- Status L5C1/L4C1

- Glue System

- Testing the Properties

- Summary

30 Radiators Frames glued

21 Radiator Frames wired

23 Padplanes glued 2 Padplanes bad

Joerg Hehner TRD Collaboration Meeting Bucharest 26.09.2005

Production Status L5C1

19 Moduls tested with Fe55 Source

Closed with Tape

Gas ArCO2 70/30

HV-Anode 1620 V, HV-Drift -2000 V

O2 Concentration below 30ppm, Flush 40l/h, 8h

up to know Dark Current < 1nA

Joerg Hehner TRD Collaboration Meeting Bucharest 26.09.2005

Testing Status L5C1

Finally glued Chamber

2 Modul tested with Roentgen Source

Gas ArCO2 70/30

HV-Anode 1620 V, HV-Drift -2000 V

O2 Concentration below 10ppm, Flush 40l/h, 8h

up to know Dark Current < 1nA

Joerg Hehner TRD Collaboration Meeting Bucharest 26.09.2005

Testing Status L5C1

11 Radiators Frames glued

5 Radiator Frames wired

5 Padplanes glued

Joerg Hehner TRD Collaboration Meeting Bucharest 26.09.2005

Production Status L4C1

1 Moduls tested with Fe55 Source

Closed with Tape

Gas ArCO2 70/30

HV-Anode 1620 V, HV-Drift -2000 V

O2 Concentration below 30ppm, Flush 40l/h, 8h

up to know Dark Current < 1nA

Joerg Hehner TRD Collaboration Meeting Bucharest 26.09.2005

Testing Status L4C1

Problem with Glue System

Joerg Hehner TRD Collaboration Meeting Bucharest 26.09.2005

- Used Araldit AW 106/AW116 with Hardener HV953U

- Sticky surface after curing time

- Problem in Producing Hardener HV 953 U since 2004

Decision

Joerg Hehner TRD Collaboration Meeting Bucharest 26.09.2005

- Stop the TRD Production

Mechanical and electrical Properties

Chemical Composition was changed

- Get a Charge of an modifcated Hardener to test the

mech. and electr. Properties

Test mechanical Properties

Joerg Hehner TRD Collaboration Meeting Bucharest 26.09.2005

- cured Glue min. 24h under different

climatic Conditions

Shore Hardness is 60

- Observed Different Surface Quality, it depends on the

Huminidity and the retention time in Air

Humidity rel. 2% - 50%Temperature 23 º C – 40 º C

one Sample cured in NitrogenAtmosphere

Test Electrical Properties

Joerg Hehner TRD Collaboration Meeting Bucharest 26.09.2005

- under different Climatic Conditions

Volume Resistivity 300 G – 8 T Ohm cm

Humidity

rel. 2% - 50%

Temperature

23 º C – 40 º C

one Sample has

cured in Nitrogen

Atmosphere

CONCLUSION

Joerg Hehner TRD Collaboration Meeting Bucharest 26.09.2005

- Orderd and distributed Hardener

to finished the TRD Production

- Additional Ageing Test

SUMMARY

Joerg Hehner TRD Collaboration Meeting Bucharest 26.09.2005

- Delay of 6 weeks in the Production Scale

- 4 L5C1and 4 L4C1 finished to shipped to HD End of October

- Production Mode to build 2 TRD Chambers / 7 Working Days

Joerg Hehner TRD Collaboration Meeting Bucharest 26.09.2005

Thank you

Sandra Schwab, Anja B. Steffen

Gert Augustinski, Andre Radu,

Heinz W. Daues

and all the Students