The ITER Project...(prelim. design only) ORNL 100% Roughing Pumps, Vacuum Standard Components SRNL...

50
Nuclear Energy in the Future Brad Nelson Chief Engineer, US ITER The ITER Project Presentation for NE-50 Symposium on the Future of Nuclear Energy November 1, 2012

Transcript of The ITER Project...(prelim. design only) ORNL 100% Roughing Pumps, Vacuum Standard Components SRNL...

  • Nuclear Energy in the Future

    Brad Nelson

    Chief Engineer, US ITER

    The ITER Project

    Presentation for

    NE-50 Symposium on the

    Future of Nuclear Energy

    November 1, 2012

  • Fusion research is ready for the next step –

    A self-heated “burning” Plasma

    11/1/2012 NE 50 ITER 2

  • We Have Produced Fusion Power

    NE 50 ITER 11/1/2012 3

  • Joint European Torus (JET) is largest existing

    tokamak,

  • The next step is ITER:

    JET

    ~15 m

    ITER

    ~29 m

    NE 50 ITER

    R=6.2 m, a=2.0 m, Ip=15 MA, B

    T=5.3 T, 23,000 tons

    NE 50 ITER 11/1/2012 5

    500 MW fusion power, gain (Q) of 10

  • Fusion has made steady progress,

    ITER goal is a big step

    11/1/2012 6

  • ITER is a special partnership to address

    a global challenge and opportunity

    Mission:

    to demonstrate

    the scientific and

    technological

    feasibility of

    fusion energy

    Partnership:

    a unique arrangement of nations jointly responsible for

    construction, operation, and decommissioning

    NE 50 ITER 11/1/2012 7

  • The Signatories of the ITER Agreement Elysée Palace, Paris: November 21, 2006

    with French President Jacques Chirac, in Paris, France, on November 21, 2006. From left to right: Vladimir Travin (Deputy Director of the Federal Atomic Energy Agency, Russian Federation), Kim Woo Sik (Vice Prime-Minister,

    Ministry of Science and Technology, Korea), Takeshi Iwaya (Vice-Minister for Foreign Affairs, Japan), José Manuel Barroso (President of the

    European Commission), Jacques Chirac (President of the French Republic), Xu Guanhua (Minister of Science and Technology, People's

    Republic of China), Anil Kakodhar (Secretary to the Government of India, Department of Atomic Energy), Dr. Raymond Orbach (Under

    Secretary for Science, U.S. Department of Energy), and Janez Potočnik (European Commissioner for Science and Research).

    NE 50 ITER 11/1/2012 8

  • Negotiated Value Proposition

    Benefit Sharing

    • Equal access to data

    • Right to propose and

    conduct experiments

    • Participation in design

    and access to design

    information

    • U.S. industry role in

    manufacturing high-

    technology components

    • Joint ownership of

    intellectual property

    Cost Sharing (mostly in-kind)

    NE 50 ITER 11/1/2012 9

  • ITER – site is in France

    NE 50 ITER 11/1/2012 10

  • ITER – site is in France

    NE 50 ITER 11/1/2012 11

  • The ITER Site Plan shows ITER scope

    Magnet Power Convertor Buildings

    (500 MW Pulsed)

    Cryoplant Building (85 kw @ 4.5k, 1300 kw @80K)

    Hot Cell

    Cooling Towers

    (1200 MW)

    Tokamak / Assy Buildings

    2x750 ton cranes 170 m long

    PF Assy Building

    Birdseye View of the ITER Site

    • Will cover about 60 ha (150 acres)

    • Large number of systems

    NE 50 ITER 11/1/2012 12

  • The ITER Site Plan shows ITER scope

    Magnet Power Convertor Buildings

    (500 MW Pulsed)

    Cryoplant Building (85 kw @ 4.5k, 1300 kw @80K)

    Hot Cell

    Cooling Towers

    (1200 MW)

    Tokamak / Assy Buildings

    2x750 ton cranes 170 m long

    PF Assy Building

    Birdseye View of the ITER Site

    • Will cover about 60 ha (150 acres)

    • Large number of systems

    NE 50 ITER 11/1/2012 13

  • ITER Today – construction in progress

    NE 50 ITER 14 Photos by ITER organization NE 50 ITER 11/1/2012 14

  • ITER Today – construction in progress

    NE 50 ITER 15 Photos by ITER organization NE 50 ITER 11/1/2012 15

  • ITER Today – construction in progress

    NE 50 ITER 16 Photos by ITER organization NE 50 ITER 11/1/2012 16

  • ITER Today – construction in progress

    NE 50 ITER 17 Photos by ITER organization NE 50 ITER 11/1/2012 17

  • ITER Today – construction in progress

    NE 50 ITER 18 Photos by ITER organization NE 50 ITER 11/1/2012 18

  • ITER Today – construction in progress

    NE 50 ITER 19 Photos by ITER organization NE 50 ITER 11/1/2012 19

  • ITER Tokamak Building – Defined by Levels

    L5

    L4

    L3

    L2

    L1

    B1

    B2

    Seismic bearing pedestals

    NE 50 ITER 11/1/2012 20

  • ITER Tokamak Core in Building

    9/18/2012 NE 50 ITER 11/1/2012 21

  • • First Plasma November 2020

    • ~20 years operation

    ITER Level 0 Construction Schedule

    First plasma

    NE 50 ITER 11/1/2012 22

  • How do we:

    • Provide specified magnetic field over a large volume?

    • Protect the device from high heat flux and neutrons?

    • Heat the plasma and drive the plasma current?

    • Diagnose the plasma?

    • Fuel the plasma?

    • Maintain the device over time?

    ITER has many engineering challenges

    NE 50 ITER 11/1/2012 23

  • The Core of ITER

    NE 50 ITER 11/1/2012 24

  • ITER’s Magnet System

    Toroidal field (TF) coils produce confining/ stabilizing toroidal field

    Poloidal field (PF) coils position and shape plasma

    Central solenoid (CS) coil induces current in the plasma

    Magnet System weighs ~ 8,700 tons (same as frigate USS Bainbridge) NE 50 ITER 25

  • Magnets are unprecedented in size and

    performance for fusion systems

    TF coils

    11.8 Tesla, 41 GJ

    40,000 tons centering force

    40 mm dia

    NE 50 ITER 11/1/2012 26

  • Magnets are unprecedented in size and

    performance for fusion systems

    40 mm dia

    TF conductor, as formed into

    pancakes

    TF conductor close-up

    NE 50 ITER 11/1/2012 27

  • TF conductor is being delivered

    Over 70% of required 450t of Nb3Sn strand

    has been produced around the world

    NE 50 ITER 11/1/2012 28

  • TF coils are being constructed now

    A1 Segment

    B3 Segment

    TF Coil ~360 t, 16 m Tall x 9 m Wide

    NE 50 ITER 11/1/2012 29

  • Magnets are unprecedented in size and

    performance for fusion systems

    Central Solenoid

    13 Tesla, 7 GJ

    30 kV, 1.2 T/s 6 coil modules in stack

    NE 50 ITER 11/1/2012 30

  • Magnets are unprecedented in size and

    performance for fusion systems

    Central Solenoid

    13 Tesla, 7 GJ

    30 kV, 1.2 T/s 6 coil modules in stack

    Single CS module, 553 turns

    NE 50 ITER 11/1/2012 31

  • Central Solenoid Conductor

    NE 50 ITER 11/1/2012 32

    Insulation wrapping machine

    CS conductor with cabling exposed

    • Nb3Sn cable in conduit • 45 kA max current at ~13T • > 40 km finished conductor required

    Conductor forming trials

  • Inside the magnet set are the vacuum

    vessel and in-vessel components

    Toroidal

    Field Coil

    Poloidal

    Field Coils

    Vacuum Vessel 9 sectors

    Blanket 440 modules

    Divertor 54 cassettes

    NE 50 ITER 11/1/2012 33

  • Vacuum vessel is the plasma chamber

    • Double walled, water-cooled, stainless steel structure provides high quality vacuum and first confinement barrier for radioactive materials.

    • Prototype constructed to prove feasibility of double wall construction with prototypic size and tolerances.

    • Vessel must be protected from the plasma.

    +/- 15 mm

    2000 m3

    NE 50 ITER 11/1/2012 34

  • Vacuum vessel is the plasma chamber

    • Double walled, water-cooled, stainless steel structure provides high quality vacuum and first confinement barrier for radioactive materials.

    • Prototype constructed to prove feasibility of double wall construction with prototypic size and tolerances.

    • Vessel must be protected from the plasma.

    +/- 15 mm

    2000 m3

    NE 50 ITER 11/1/2012 35

  • Plasma interacts with surfaces

    Photos courtesy JET

    NE 50 ITER 11/1/2012 36

  • Divertor Exhausts a Major Part of Plasma

    Heating Power and Helium “Ash”

    Divertor Cassette (upgradeable) Challenge:

    Absorb 10–20 MW/m2 heat flux while minimizing

    impurity influx, tritium retention

    NE 50 ITER 11/1/2012 37

  • First Wall and Blanket Take Balance of

    Neutron Radiation and Plasma Heat Load

    • To remove the useful neutron power and most of the particle power

    in the plasma

    • To provide shielding of the vacuum vessel structure and S/C coils

    • To help in passive stabilization of the plasma

    The blanket serves three main functions:

    38

  • First Wall Plasma Heat Load requires

    special technology

    NE 50 ITER 11/1/2012 39 Ref: Raffray

  • Plasma Heating/Current Drive Require

    Multiple Systems

    NE 50 ITER 11/1/2012 40

  • ~ 50 Diagnostics Monitor Plasma Behavior

    Must Survive Harsh Operating Conditions

    NE 50 ITER 11/1/2012 41

    ITER relative to JET High neutron and gamma fluxes (up to x 10)

    Neutron heating (1 MW/m3) (essentially zero)

    High fluxes of energetic neutral particles from CX (up to x5)

    Long pulse lengths (up to x 100)

    High neutron fluence (> 105 ! )

  • Fueling of plasma by frozen pellets

    Pellet injection to achieve

    efficient core fueling

    Protium, Deuterium and Tritium Pellets

    @ 14° Kelvin

    NE 50 ITER 11/1/2012 42

  • Test Blanket modules demonstrate

    tritium breeding technology

    • Tritium breeding is necessary for the fusion fuel cycle.

    • Several breeding blanket concepts are under consideration.

    • ITER provides three equatorial ports for test blanket modules.

    NE 50 ITER 11/1/2012 43

  • Other challenges

    In addition to challenges already discussed

    (related to component performance requirements

    and design), there are global challenges.

    • Availability issues

    – Reliability issues

    – Remote Maintenance issues

    – Vacuum quality, leaks, and in-situ leak detection

    • Safety and interaction with regulators

    NE 50 ITER 11/1/2012 44

  • Blanket maintenance requires in-vessel

    rail and vehicle

    • Maintenance system deployed through 4 ports, requires rail, vehicle,

    system to hand components from vehicle to port, etc.

    • Larger-scale system built and tested in JA.

    • Development of new system will include significant deployment and

    use during machine assembly.

    1 blanket in months, all in ~2 years

    Demonstration of

    • Blanket module handling

    • Rail deployment NE 50 ITER 11/1/2012 45

  • What ITER Means for the US

    • Create, understand, and control a reactor-prototypical fusion plasma

    • Demonstrate the scientific and technological feasibility of a promising virtually inexhaustible and relatively clean energy source

    • Position the US to provide fusion-reactor technology

    • Create high-tech jobs and work in the US

    • International partnership: working together toward a global goal.

    NE 50 ITER 11/1/2012 46

  • US Scope is provided by multiple

    institutions

    NE 50 ITER

    ORNL 100% Central Solenoid

    Windings + JA Support

    ORNL

    8% of Toroidal Field Conductor

    + JA Support

    ORNL 100% Pellet Injector

    100% Disruption Mitigation

    ORNL Blanket/Shield

    (design only)

    ORNL 100% Tokamak Cooling

    Water System

    PPPL 75% Steady State Electrical Network

    PPPL 14% of Port-based

    Diagnostics

    ORNL 88% Ion Cyclotron Transmission Lines

    ORNL 88% Electron

    Cyclotron Transmission Lines

    PPPL In-Vessel Coils

    (prelim. design only)

    ORNL 100% Roughing Pumps,

    Vacuum Standard Components

    SRNL 100% Tokamak Exhaust

    Processing System

    NE 50 ITER 11/1/2012 47

  • US Scope is highly integrated with

    central ITER core

    NE 50 ITER 11/1/2012 48

    Cooling Water System

    ICH Transmission

    Lines

    Vacuum

    System

    TF Coil Conductor

    Blanket/Shield Design

    Pellet Injection System Disruption Mitigation

    Port Diagnostics

    Central Solenoid

    ECH Transmission

    Lines

    TEP SSEN

  • Over 80% of Project Funding will be Spent in the US

    As of June 2012,

    over $808M

    (in total value with options)

    has been awarded to US

    industry, universities, and

    DOE laboratories in 38

    states plus DC.

    Note: This data does not reflect contracts Awarded to US Industry by the EU (>$55M) or Korea (>$23M)

    NE 50 ITER 11/1/2012 49

  • Summary

    • The ITER project combines the expertise from around

    the world to build the first fusion reactor – China, EU,

    India, Japan, Korea, Russian Federation and the U.S.

    • An international organization is already operating in

    Cadarache, France, where ITER is under

    construction.

    • There are many engineering challenges, but each can

    be met.

    • ITER is proceeding toward a first plasma in 2020.

    NE 50 ITER 11/1/2012 50