ALTUS GROUP | TCDSB - St. Michael School - Structural RepairsJan 13, 2014

Community Update: January 13, 2014y p y ,

Project Background

Project Status

Description of Problem and Site Photos

j

R i /R ti P Repair/Renovation Program

Schedule: 2013

Questions

Schedule: 2014 – 2015

ALTUS GROUP | TCDSB - St. Michael School - Structural RepairsJan 13, 2014

Project BackgroundProject Background

Facilities shared by TCDSB, TDSB & y ,TCHC

Initial investigations to determine cause of

Cracks in wall & floor settlement on ground floor

Safety concerns MOL issued directives to

Initial investigations to determine cause of problem

Safety concerns – MOL issued directives to boards Initial investigation: Wash-out of fill & Initial investigation: Wash-out of fill &

voids under slab, & safety concerns

ALTUS GROUP | TCDSB - St. Michael School - Structural RepairsJan 13, 2014

Project StatusProject Status

Engineer / Design consultant hired

Project Manager hired

Detailed soil investigation completed Hazmat survey completed Detailed soil investigation completed

Structural design well advanced

Preparing public tender for repairs contractp g p p

Planning to tender contract Feb-March

T t t t t t ti l t i Target to start construction late spring

ALTUS GROUP | TCDSB - St. Michael School - Structural RepairsJan 13, 2014

Description of Problemp

Methane gas collection system below floor slab Methane gas collection system below floor slab 

Granular fill below slab poorly compacted, washed out 

& voids present not capable of proper support& voids present – not capable of proper support

Building structure not comprised  ‐ bldg supported off 

deep piles

Problems confined only to ground floor

Floor slab & any walls supported off floor slab

Additional support must be supplied to floor slabpp pp

ALTUS GROUP | TCDSB - St. Michael School - Structural RepairsJan 13, 2014

Site Photos – Tiling at stairwellg

ALTUS GROUP | TCDSB - St. Michael School - Structural RepairsJan 13, 2014

Site Photos – main hallwayy

ALTUS GROUP | TCDSB - St. Michael School - Structural RepairsJan 13, 2014

Site Photos – change room showersg

ALTUS GROUP | TCDSB - St. Michael School - Structural RepairsJan 13, 2014

Site Photos – main entrance hall & stairs

ALTUS GROUP | TCDSB - St. Michael School - Structural RepairsJan 13, 2014

Site Photos – Gymnasium wally

ALTUS GROUP | TCDSB - St. Michael School - Structural RepairsJan 13, 2014

Repair / Renovation Programp g

Removal of entire floor slab

Removal of most main floor walls, ceilings, etc.

f d Keep existing exterior façade

Repair interior face of exterior walls

Keep existing boiler / elec. room & shore up walls

K t i t fl Keep stairs to upper floors

Asbestos removal

ALTUS GROUP | TCDSB - St. Michael School - Structural RepairsJan 13, 2014

Repair / Renovation Programp g

Install new helical pile systemp y

New concrete grade beams to support floor

fl l b d b l New floor slab tied into beams & piles

New interior walls, ceilings, floors etc.

New mech. /elec. system tied into existing systems

N fl New gym floor

New cabinetry, washrooms, etc. 

ALTUS GROUP | TCDSB - St. Michael School - Structural RepairsJan 13, 2014

Schedule: 2013

Ti li L t M ti t P tTimeline:  Last Meeting to Present

Activity June July Aug Sept Oct Nov Dec Jan

Request for limited Design Competition

Public Tender for Design Consultant

Evaluation & Approval of Design Consultant & Fees

Detailed Site Investigation & Soil Testing

Structural Design UnderwayStructural Design Underway

Complete Structural Design 

ALTUS GROUP | TCDSB - St. Michael School - Structural RepairsJan 13, 2014

Schedule: 2014-2015*Public Tender for Construction February – March 2014

Evaluation & Approvals March‐May 2014

Demolition June – July 2014

Construction and Repair July, 2014 –January 2015

New Gym Floor Installation February – March 2015

New School Yard Play Area April – May  2015

Final Inspections and Approvals June 2015

School Furniture/Setup, Staff Move in July ‐ August 2015

St. Michael Students Return September 2015p

* Dates are based on best estimates as of January 9, 2014

ALTUS GROUP | TCDSB - St. Michael School - Structural RepairsJan 13, 2014

Floor Plan

ALTUS GROUP | TCDSB - St. Michael School - Structural RepairsJan 13, 2014

Floor Plan

ALTUS GROUP | TCDSB - St. Michael School - Structural RepairsJan 13, 2014