ALTUS GROUP | TCDSB - St. Michael School - Structural RepairsJan 13, 2014
Community Update: January 13, 2014y p y ,
Project Background
Project Status
Description of Problem and Site Photos
j
R i /R ti P Repair/Renovation Program
Schedule: 2013
Questions
Schedule: 2014 – 2015
ALTUS GROUP | TCDSB - St. Michael School - Structural RepairsJan 13, 2014
Project BackgroundProject Background
Facilities shared by TCDSB, TDSB & y ,TCHC
Initial investigations to determine cause of
Cracks in wall & floor settlement on ground floor
Safety concerns MOL issued directives to
Initial investigations to determine cause of problem
Safety concerns – MOL issued directives to boards Initial investigation: Wash-out of fill & Initial investigation: Wash-out of fill &
voids under slab, & safety concerns
ALTUS GROUP | TCDSB - St. Michael School - Structural RepairsJan 13, 2014
Project StatusProject Status
Engineer / Design consultant hired
Project Manager hired
Detailed soil investigation completed Hazmat survey completed Detailed soil investigation completed
Structural design well advanced
Preparing public tender for repairs contractp g p p
Planning to tender contract Feb-March
T t t t t t ti l t i Target to start construction late spring
ALTUS GROUP | TCDSB - St. Michael School - Structural RepairsJan 13, 2014
Description of Problemp
Methane gas collection system below floor slab Methane gas collection system below floor slab
Granular fill below slab poorly compacted, washed out
& voids present not capable of proper support& voids present – not capable of proper support
Building structure not comprised ‐ bldg supported off
deep piles
Problems confined only to ground floor
Floor slab & any walls supported off floor slab
Additional support must be supplied to floor slabpp pp
ALTUS GROUP | TCDSB - St. Michael School - Structural RepairsJan 13, 2014
Site Photos – Tiling at stairwellg
ALTUS GROUP | TCDSB - St. Michael School - Structural RepairsJan 13, 2014
Site Photos – main hallwayy
ALTUS GROUP | TCDSB - St. Michael School - Structural RepairsJan 13, 2014
Site Photos – change room showersg
ALTUS GROUP | TCDSB - St. Michael School - Structural RepairsJan 13, 2014
Site Photos – main entrance hall & stairs
ALTUS GROUP | TCDSB - St. Michael School - Structural RepairsJan 13, 2014
Site Photos – Gymnasium wally
ALTUS GROUP | TCDSB - St. Michael School - Structural RepairsJan 13, 2014
Repair / Renovation Programp g
Removal of entire floor slab
Removal of most main floor walls, ceilings, etc.
f d Keep existing exterior façade
Repair interior face of exterior walls
Keep existing boiler / elec. room & shore up walls
K t i t fl Keep stairs to upper floors
Asbestos removal
ALTUS GROUP | TCDSB - St. Michael School - Structural RepairsJan 13, 2014
Repair / Renovation Programp g
Install new helical pile systemp y
New concrete grade beams to support floor
fl l b d b l New floor slab tied into beams & piles
New interior walls, ceilings, floors etc.
New mech. /elec. system tied into existing systems
N fl New gym floor
New cabinetry, washrooms, etc.
ALTUS GROUP | TCDSB - St. Michael School - Structural RepairsJan 13, 2014
Schedule: 2013
Ti li L t M ti t P tTimeline: Last Meeting to Present
Activity June July Aug Sept Oct Nov Dec Jan
Request for limited Design Competition
Public Tender for Design Consultant
Evaluation & Approval of Design Consultant & Fees
Detailed Site Investigation & Soil Testing
Structural Design UnderwayStructural Design Underway
Complete Structural Design
ALTUS GROUP | TCDSB - St. Michael School - Structural RepairsJan 13, 2014
Schedule: 2014-2015*Public Tender for Construction February – March 2014
Evaluation & Approvals March‐May 2014
Demolition June – July 2014
Construction and Repair July, 2014 –January 2015
New Gym Floor Installation February – March 2015
New School Yard Play Area April – May 2015
Final Inspections and Approvals June 2015
School Furniture/Setup, Staff Move in July ‐ August 2015
St. Michael Students Return September 2015p
* Dates are based on best estimates as of January 9, 2014