Reducing Well Test Deferments from Clusters of Gas-Lifted Sub-Sea Wells Philip Holweg Wim der...
-
Upload
brandon-welch -
Category
Documents
-
view
214 -
download
0
Transcript of Reducing Well Test Deferments from Clusters of Gas-Lifted Sub-Sea Wells Philip Holweg Wim der...
Reducing Well Test Deferments from Clusters of
Gas-Lifted Sub-Sea Wells
Philip Holweg
Wim der Kinderen
(Shell Expro)
API Gaslift WorkshopWoodbank, Aberdeen
12 November 2001
Reducing Well Test Deferments fromClusters of Gas-Lifted Sub-Sea Wells
Outline:
• Why sub-sea clusters are difficult to test• Well testing by difference - methodology• Example from Gannet• Benefits of testing by difference• Conclusions
Issues in Well Testing Subsea Clusters #1
Significant deferment when well testing subsea
• flow line usually is a production constraint– test line often used to maximise production
• multi-rate tests result in sub-optimal production– choke wells to change THP– change gaslift to assess gaslift performance– deferring production for duration of the test
• long stabilisation times for long tie-backs– fluids must travel from near well bore to facilities to
accurately measure BSW, GOR– stabilisation time even longer for gaslifted wells
• also need to stabilise annulus pressure
Issues in Well Testing Subsea Clusters #2
Often no dedicated test line available
• single well on large flow line causes more deferment – even longer stabilisation period due to low
velocities
• single well on large flow line can induce slugging– need to choke well back to stabilise - further
deferment– long averaging period required
• risk of wax and hydrate deposition– reduced flow rates cause lower pressures and
temperatures
Approach:
• Test wells together– usually in normal configuration
• Induce controlled changes– change THP through choke or gaslift change
• Measure production change by difference
• Feed data into linear PQ curve model– calculate individual well performance (PQ curves) for
all wells
Testing Wells Together - by Difference
Linearised PQ Curves
0
10
20
30
40
50
60
70
80
90
100
0 100 200 300 400 500 600 700 800 900Gross Flow Rate (m3/d)
TH
P (
bar)
20
40
0
Gaslift(103 m3/d)
Well Model
Linearised
CQBQATHP glwellwell 1,11
cQbaTHPQ 1gl1well1well ,
rewrite:
A
Cc
A
Bb
A
1a
where:
the constant C includes reference lift gas rate
Linearised PQ curves
cQbaTHPQ 1gl1well1well ,fQedTHPQ 2gl2well2well ,
2well1welltotal QQQ
6total
5total
4total
3total
2total
1total
62gl62w61gl61w
52gl52w51gl51w
42gl42w41gl41w
32gl32w31gl31w
22gl22w21gl21w
12gl12w11gl11w
Q
Q
Q
Q
Q
Q1
1QTHP1QTHP
1QTHP1QTHP
1QTHP1QTHP
1QTHP1QTHP
1QTHP1QTHP
1QTHP1QTHP
f
e
d
c
b
a
,
,
,
,
,
,
,,,,
,,,,
,,,,
,,,,
,,,,
,,,,
Calculation for Dual Well Test
Generalised Methodology
• More test points than unknowns improves accuracy• Measurement uncertainty can be included• THP data points can be replaced by PDG
measurements– improves accuracy
• Require one single well test to avoid singular data set– unless PDG is available (measure SIBHP using PDG)
• Methodology works also with more than 2 wells
QpA
QAAAp TT 1
/AS
Examples from Gannet
• 7 fields tied back to facilities at single platform– 6 subsea fields
• Long tie backs– 3 to 15 km– most fields are gaslifted– limited test lines
FieldDistance
(km)GasliftTest Line
D 15 E 14 F 12 G 5
GD-01
GD-02
GD-03
GD-04
GD-06
Andrew Tay
6”6”4” (blocked)
4” (gas lift)
MPM Bulk Sep
Bulk Sep
R31
R32
Gannet A
Gannet G
Gannet D
Test Sep
15.5 km to Gannet A
Gannet D - Schematic Overview
THP(bar)
67.8
Test 4
Test 5
Test 6
Gaslift (103 m3/d)
Gannet D - Dual Well Test Programme
THP(bar)
Gaslift (103 m3/d)
Q gross (t/d)
Well 1 Well 2 Total
Test 3
Test 2
Test 1
71.1
58.1
53.1
49.5
38.5
36.8
44.7
20.8
69.6
57.6
52.2
50.6
41.1
38.8
0
0 862.5
1001.4
905.3
583.6
41.2 518.30 0
0 0 56.6 0 602.6
Gannet D - Derived PQ Curves
Gross Flow Rate (t/d)
0
10
20
30
40
50
60
70
80
0 200 400 600 800 1000 1200
TH
P (
bar)
Single Test 1Single Test 2Combined Test 3Combined Test 4Combined Test 5Combined Test 6
Gannet D - Derived PQ Curves
Gross Flow Rate (t/d)
0
10
20
30
40
50
60
70
80
0 200 400 600 800 1000 1200
TH
P (
bar)
Single Test 1Single Test 2Combined Test 3Combined Test 4Combined Test 5Combined Test 6
040 .103 m3/dGaslift: 20 38 45
GD-01 GD-04
Gannet D - Derived PQ Curves
Gross Flow Rate (t/d)
0
10
20
30
40
50
60
70
80
0 200 400 600 800 1000 1200
TH
P (
bar)
Single Test 1Single Test 2Combined Test 3Combined Test 4Combined Test 5Combined Test 6
040 .103 m3/dGaslift: 20 38 45
GD-01 GD-04
Benefits - Example for 2 Well Cluster
0200400600800
1000
Rate
(m
3/d
)
1 2 3 4 5 6
normal operationstabilisationmeasurement
Conventional
0 24 48 72 96 120 144 168Time (hours)
0200400600800
1000
Rate
(m
3/d
)
By Difference
Assumptions:• Individual rate: 500 m3/d• Combined rate: 800 m3/d
ConventionalBy difference
Benefit
Time(hours)
Deferment(m3)
10576
1540320
25% 80%
Testing by Difference - Provisos
• Need capability to measure cluster production– difficult when multiple fields are commingled
• Wells must be stable over test period– gas coning wells may be less suitable
• Still need one test point with single well flowing– unless a PDG is available
• Assumption of linearised PQ curves not always valid– especially for gaslifted wells at higher THPs
• apply multiple slopes for one well• gather more test points
Conclusions - Testing by Difference
• Significant reduction in well test deferment– especially for gaslifted subsea wells– typically saves 80% hydrocarbon deferment & 20 %
test time– avoids adverse flowline conditions
• slugging• low p, T
– PDGs allow further deferment reduction• no single well test point required
• Quality of well tests not affected– approximation of linearised PQ curves usually
proves not to be a limitation• extend linear model per well if necessary
– PDGs make this method more accurate & simpler