PERT - CPM

By

Naveed I. Salman

Page 2: Pert   Cpm Nis

2

Quote

A dream is just a dream. A goal is a dream with a plan and a deadline.

- Harvey Mackay 

Page 3: Pert   Cpm Nis

3

Project Management

What is a project?

A project is a series of activities directed toward the accomplishment of a desired objective.

Page 4: Pert   Cpm Nis

4

Project Management

• Characteristics of Projects– Unique, one-time operations– Involve a large number of activities that must be planned and

coordinated– Long time-horizon or critical time constraints– Goals of meeting completion deadlines and budgets

• Examples– Building a house– Planning a meeting– Introducing a new product

Page 5: Pert   Cpm Nis

5

Project Scheduling Management

Project scheduling is concerned with the techniques that can be employed to manage the activities that need to be undertaken during the development of a project.

Scheduling is carried out in advance of the project commencing and involves:

1. identifying the tasks that need to be carried out;

2. estimating how long they will take;

3. allocating resources (mainly personnel);

4. scheduling when the tasks will occur.

Page 6: Pert   Cpm Nis

6

Project Scheduling Management

• Once the project is underway control needs to be exerted to ensure that the plan continues to represent the best prediction of what will occur in the future:

– based on what occurs during the development;

– often necessitates revision of the plan.

• Effective project planning will help to ensure that the systems are delivered:

– within cost;

– within the time constraint;

– to a specific standard of quality.

Page 7: Pert   Cpm Nis

7

Project Management Tools

• Older simpler - Gantt Chart• More modern – CPM/PERT• Newest – Microsoft Project ™

Page 8: Pert   Cpm Nis

8

Gantt Chart

Foundation

Framing

Plumbing

Electrical

Siding

Wall Board

Paint Interior

Paint Exterior

Fixtures

Activity Start 5 10 15 20 25 30 35 40 45 50Days After Start

Days After StartStart 5 10 15 20 25 30 35 40 45 50

Page 9: Pert   Cpm Nis

9

Advantages of Gantt

1. Easy to understand

2. Easy to construct

Page 10: Pert   Cpm Nis

10

Project Management

• PERT - Project Evaluation and Review Technique

• CPM - Critical Path Method

Page 11: Pert   Cpm Nis

11

PERT/CPM• PERT

– Program Evaluation and Review Technique

– Developed by U.S. Navy for Polaris missile project– Developed to handle uncertain activity times

• CPM– Critical Path Method– Developed by Du Pont & Remington Rand– Developed for industrial projects for which activity times generally

were known

• Today’s project management software packages have combined the best features of both approaches.

Page 12: Pert   Cpm Nis

12

Project Management PERT/CPM

• In projects that are non-repetitive information necessary for control is sparse, non-existent or only marginally relevant.

• Project control then requires:– A logical methodology showing the required tasks and

the interrelationships of these tasks– Estimation of the resources required for each

activity/step• Time• Money• Personnel• Equipment

Page 13: Pert   Cpm Nis

13

PERT/CPM Type Projects

• Construction

• Engineering

• Software Development

• Equipment Cut-over

• Anything with many interdependent activities/steps

Page 14: Pert   Cpm Nis

14

Network Diagram

• Activities

• Events

Page 15: Pert   Cpm Nis

15

ACTIVITIES• Activities are shown as lines or arrows

• Activities require time and other recourses

Page 16: Pert   Cpm Nis

16

Activities

• Some may be executed simultaneously

• Some cannot be performed until others are completed

DO THIS

AND AT THE SAME TIME DO THAT

Page 17: Pert   Cpm Nis

17

Situations in network diagram

AB

C

A must finish before either B or C can start

A

B

C both A and B must finish before C can start

D

C

B

Aboth A and C must finish before either of B or D can start

A

C

B

D

Dummy

A must finish before B can start

both A and C must finish before D can start

Page 18: Pert   Cpm Nis

18

EVENTS

• Events or nodes or mileposts or circles

• They consume NO time and show connections between activities

• Every PERT/CPM chart has one Start event and one end event

Page 19: Pert   Cpm Nis

19

CPM -Critical Path Method

• A tool to determine duration based on the identification of the Critical Path through the activity network.

• Times are known with some high degree of certainty.

• Management can determine the duration of a project and concentrate efforts on Critical Path activities.

Page 20: Pert   Cpm Nis

20

PERT Program Evaluation and Review Technique

• Time are NOT known well (uncertainty)

• Statistics used to estimate probability of finishing within a given time

Page 21: Pert   Cpm Nis

21

The Six Steps Common to PERT & CPM

1. Define the project and identify each activity2. Develop relationships among the activities.

(Decide which activities must precede and which must follow others.)

3. Draw the network connecting all of the activities4. Assign time and/or cost estimates to each

activity5. Compute the longest time path through the

network. This is called the critical path6. Use the network to help plan, schedule, monitor,

and control the project

Page 22: Pert   Cpm Nis

22

Simple CPM Chart

START 1 END

Open Book Read Chapter

Page 23: Pert   Cpm Nis

23

Calculating times

• Time for top route = 2 + 4 + 4 + 3 = 13• Time for bottom route = 2 + 3 + 2 + 4 = 11

START END

24

4

3

32

4

Page 24: Pert   Cpm Nis

24

Critical Path

• Time for top route = 2 + 4 + 4 + 3 = 13• Time for bottom route = 2 + 3 + 2 + 4 = 11

• Top is Critical path

START END

24

4

3

32

4

Page 25: Pert   Cpm Nis

25

Slack time

• Time for top route = 2 + 4 + 4 + 3 = 13• Time for bottom route = 2 + 3 + 2 + 4 = 11• For activities not on Critical path Slack time = 2

START END

24

4

3

32

4

No SLACK here

Page 26: Pert   Cpm Nis

26

Slack time

• For activities not on critical path the slack time is extra time that could be used if necessary

• If event B is reached in 6 days is there a significant problem?

• No, not if the cause was the activity that should have taken 3 days took 4 • Yes, if the cause was the 2 day activity following start took 3 days

START END

24

4

3

32

4B

Page 27: Pert   Cpm Nis

27

Review of PERT/CPM• A project network can be constructed to

model the precedence / order of the activities and the relationship between activities.

• The Lines of the network represent the activities.

• The Circles of the network show events.

• A critical path for the network is a path consisting of activities with zero slack.

Page 28: Pert   Cpm Nis

28

• 3 time estimates– Optimistic times (a)– Most-likely time (m)– Pessimistic time (b)

• Follow normal distribution

• Expected time: t = (a + 4m + b)/6

• Variance of times: v = ((b - a) /6) 2

PERT Activity Times

Page 29: Pert   Cpm Nis

29

Time Estimation

• Estimates of Activity Times Activity time is the elapsed time required for an activity. Estimating activity times is probably one of PERT’s most critical features.

• Managers are reluctant to commit themselves to a rigid time schedule. – Weather conditions, alone, prompt uncertainties and make it

difficult for the manager to develop a single time estimate. However, experience has shown that managers are less reluctant if allowed three different estimates, especially when they understand PERT and how the concept of three time estimates is used. PERT, therefore, calls for not one, but three estimates of every activity time and allows the manager an opportunity to express his uncertainty about the possible time range of an activity.

Page 30: Pert   Cpm Nis

30

Time Estimation• All three time estimates assume a static level of

resource use. The estimates should be as good as possible because PERT results depend directly on them. To obtain accurate estimates is not easy. It will require research, collaboration with planning team members, and homework.

• Simple guesswork is inadequate. If some time estimates are mere guesses, the manager

will soon realize that they jeopardize or needlessly extend the project schedule date. Once the estimator realizes that his contributions are a small, but vital component of the PERT system, he will try to steadily improve his estimates. In short, guesswork will not replace intelligently derived estimates.

Page 31: Pert   Cpm Nis

31

Time Estimation

• The person most familiar with the operation and requirements of each activity should submit the three time estimates. These should meet the following criteria:– 1) Optimistic Time -- the minimum time

period in which the activity can be accomplished, i.e., the time it would take to complete it if everything proceeded better than expected. (labeled a.)

Page 32: Pert   Cpm Nis

32

Time Estimation2) Most Likely Time -- the best estimate of the time

period in which the activity can be accomplished, i.e., the estimate submitted if one (only) had been requested. (labeled m.)

3) Pessimistic Time -- the maximum time period it would take to accomplish the activity, i.e., the time required if everything went wrong, excluding major catastrophes. (labeled b.)

Page 33: Pert   Cpm Nis

33

Time Estimation• It is acceptable to state these estimates in

days, weeks, or months as long as the measure is used consistently. Once made, activity time estimates are firm and should not be changed without a change in the nature and scope of the activity or in the level of resources allocated to it. The following time relationships must be adhered to: ... a equal or less than m which is equal or less then b

Page 34: Pert   Cpm Nis

34

Some Important Points

• The process is no better than the network and the time estimates– People do this– Knowledgeable people must determine which activities must

proceed others and the time each activity will require– Some careful estimates are still better than no information

• The resulting schedule should be a normal schedule.– A Crash schedule exists when extra resources are added to

reduce time.

Page 35: Pert   Cpm Nis

35

Advantages of PERT/CPM• Especially useful when scheduling and controlling

large projects.• Straightforward concept and not mathematically

complex.• Graphical networks aid perception of relationships

among project activities.• Critical path & slack time analyses help pinpoint

activities that need to be closely watched.• Project documentation and graphics point out who is

responsible for various activities.• Applicable to a wide variety of projects.• Useful in monitoring schedules and costs.

Page 36: Pert   Cpm Nis

36

Benefits of CPM/PERT• Useful at many stages of project management• Mathematically simple• Give critical path and slack time• Provide project documentation• Useful in monitoring costs

•How long will the entire project take to be completed? What are the risks involved? •Which are the critical activities or tasks in the project which could delay the entire project if they were not completed on time? •Is the project on schedule, behind schedule or ahead of schedule? •If the project has to be finished earlier than planned, what is the best way to do this at the least cost?

CPM/PERT can answer the following important questions:

Page 37: Pert   Cpm Nis

37

A. Toast BreadB. Make an egg omelet C. Spread butter on toastD. Spread omelet on toast

3 minutes 2 minutes 1 minute 1 minute

7 minutes

Sandwich PERT Chart

5 minutes

Page 38: Pert   Cpm Nis

Practice Exercise

Activities Pre - Activity

Duration in Weeks

Cost in (000) Rs

a - 6 2

b - 8 3

c - 5 5

d b 13 7

e c 9 11

f a 15 9

g a 17 5

h f 9 8

i g 6 4

j d, e 12 6

Page 39: Pert   Cpm Nis

[email protected], 03215168779

39

Questions / Answers

• ??

Page 40: Pert   Cpm Nis

[email protected], 03215168779

40

Solution

• Critical Path

a, 6a, 6a, 6a, 6

f, 15f, 15f, 15f, 15

b, 8b, 8b, 8b, 8

c, 5c, 5c, 5c, 5

e, 9e, 9e, 9e, 9

d, 13d, 13d, 13d, 13

g, 17g, 17g, 17g, 17 h, 9h, 9h, 9h, 9

i, 6i, 6i, 6i, 6

j, 12j, 12j, 12j, 12

Page 41: Pert   Cpm Nis

41

Your Presenter

• Naveed I. SalmanM. Sc (Mathematics),MCS, MIT, M.A.(EPM)

[email protected]• 0321 5168 779

Page 42: Pert   Cpm Nis

[email protected], 03215168779

42

The End