PeopleSoft 9.2 Upgrade. Project Goals 3 Major Goals Ensure Compliance Tax, regulatory and security...
-
Upload
amos-norris -
Category
Documents
-
view
220 -
download
2
description
Transcript of PeopleSoft 9.2 Upgrade. Project Goals 3 Major Goals Ensure Compliance Tax, regulatory and security...
![Page 1: PeopleSoft 9.2 Upgrade. Project Goals 3 Major Goals Ensure Compliance Tax, regulatory and security Decrease Future Maintenance Costs Reduce the number.](https://reader033.fdocuments.in/reader033/viewer/2022052706/5a4d1ade7f8b9ab0599760bb/html5/thumbnails/1.jpg)
PeopleSoft 9.2 Upgrade
![Page 2: PeopleSoft 9.2 Upgrade. Project Goals 3 Major Goals Ensure Compliance Tax, regulatory and security Decrease Future Maintenance Costs Reduce the number.](https://reader033.fdocuments.in/reader033/viewer/2022052706/5a4d1ade7f8b9ab0599760bb/html5/thumbnails/2.jpg)
Project Goals
![Page 3: PeopleSoft 9.2 Upgrade. Project Goals 3 Major Goals Ensure Compliance Tax, regulatory and security Decrease Future Maintenance Costs Reduce the number.](https://reader033.fdocuments.in/reader033/viewer/2022052706/5a4d1ade7f8b9ab0599760bb/html5/thumbnails/3.jpg)
3
Major Goals
Ensure Compliance
• Tax, regulatory and security
Decrease Future Maintenance Costs• Reduce the number of customizations
• 30% Reduction
![Page 4: PeopleSoft 9.2 Upgrade. Project Goals 3 Major Goals Ensure Compliance Tax, regulatory and security Decrease Future Maintenance Costs Reduce the number.](https://reader033.fdocuments.in/reader033/viewer/2022052706/5a4d1ade7f8b9ab0599760bb/html5/thumbnails/4.jpg)
Scope
![Page 5: PeopleSoft 9.2 Upgrade. Project Goals 3 Major Goals Ensure Compliance Tax, regulatory and security Decrease Future Maintenance Costs Reduce the number.](https://reader033.fdocuments.in/reader033/viewer/2022052706/5a4d1ade7f8b9ab0599760bb/html5/thumbnails/5.jpg)
5
Scope
Convert Current Functionality
Apply 9.2 PUM UpdatesPeopleSoft Upgrade Manager
![Page 6: PeopleSoft 9.2 Upgrade. Project Goals 3 Major Goals Ensure Compliance Tax, regulatory and security Decrease Future Maintenance Costs Reduce the number.](https://reader033.fdocuments.in/reader033/viewer/2022052706/5a4d1ade7f8b9ab0599760bb/html5/thumbnails/6.jpg)
Project Timeline
![Page 7: PeopleSoft 9.2 Upgrade. Project Goals 3 Major Goals Ensure Compliance Tax, regulatory and security Decrease Future Maintenance Costs Reduce the number.](https://reader033.fdocuments.in/reader033/viewer/2022052706/5a4d1ade7f8b9ab0599760bb/html5/thumbnails/7.jpg)
7
Project Timeline
October 19, 2015 • Go-Live
![Page 8: PeopleSoft 9.2 Upgrade. Project Goals 3 Major Goals Ensure Compliance Tax, regulatory and security Decrease Future Maintenance Costs Reduce the number.](https://reader033.fdocuments.in/reader033/viewer/2022052706/5a4d1ade7f8b9ab0599760bb/html5/thumbnails/8.jpg)
Project Status
![Page 9: PeopleSoft 9.2 Upgrade. Project Goals 3 Major Goals Ensure Compliance Tax, regulatory and security Decrease Future Maintenance Costs Reduce the number.](https://reader033.fdocuments.in/reader033/viewer/2022052706/5a4d1ade7f8b9ab0599760bb/html5/thumbnails/9.jpg)
9
Status
On –track for October 19, 2015 Go Live
TestingMTP5 (Move to Production)Parallel TestSME Testing
• Manager Self Service (MSS)• Time and Labor• Open Enrollment• Salary Modeling
![Page 10: PeopleSoft 9.2 Upgrade. Project Goals 3 Major Goals Ensure Compliance Tax, regulatory and security Decrease Future Maintenance Costs Reduce the number.](https://reader033.fdocuments.in/reader033/viewer/2022052706/5a4d1ade7f8b9ab0599760bb/html5/thumbnails/10.jpg)
Project Success
![Page 11: PeopleSoft 9.2 Upgrade. Project Goals 3 Major Goals Ensure Compliance Tax, regulatory and security Decrease Future Maintenance Costs Reduce the number.](https://reader033.fdocuments.in/reader033/viewer/2022052706/5a4d1ade7f8b9ab0599760bb/html5/thumbnails/11.jpg)
11
Pre-Go Live Timeline
Task Date Time
Payroll Payroll - Retro Pay Cleanup 10/7/2015 6:00 PM
Systems ControlMSS transactions initiated between 10/8-10/15 effective before 9/28 are held until after go live. 10/7/2015 6:00 PM
Payroll Payment Requests unavailable 10/9/2015 5:00 PM
Supervisors/Time Approvers High Severity T&L exceptions resolved 10/9/2015 5:00 PM
Payroll Monitor outstanding unapproved reported time 9/16/2015 8:00 AM
Payroll All unapproved reported time deleted 10/15/2015Close of
Business
![Page 12: PeopleSoft 9.2 Upgrade. Project Goals 3 Major Goals Ensure Compliance Tax, regulatory and security Decrease Future Maintenance Costs Reduce the number.](https://reader033.fdocuments.in/reader033/viewer/2022052706/5a4d1ade7f8b9ab0599760bb/html5/thumbnails/12.jpg)
12
Communication
3Cs to Campus and Time Approvers/SupervisorsAll reported time must be approved prior to upgrade weekend
Lo Que PasaUAnnounceMosaic Community/Newsletter
![Page 13: PeopleSoft 9.2 Upgrade. Project Goals 3 Major Goals Ensure Compliance Tax, regulatory and security Decrease Future Maintenance Costs Reduce the number.](https://reader033.fdocuments.in/reader033/viewer/2022052706/5a4d1ade7f8b9ab0599760bb/html5/thumbnails/13.jpg)
13
Training
DemosOnline and/or In-Person Sessions?
![Page 14: PeopleSoft 9.2 Upgrade. Project Goals 3 Major Goals Ensure Compliance Tax, regulatory and security Decrease Future Maintenance Costs Reduce the number.](https://reader033.fdocuments.in/reader033/viewer/2022052706/5a4d1ade7f8b9ab0599760bb/html5/thumbnails/14.jpg)
Questions???