Official PDF , 12 pages

12
ABSTRACT T his paper presents a statistical study of the geothermal resource risk in Indonesia, specifically, that the resource base and well productiv- ity are adequate and that the drilling cost per well is reasonable. This paper is timely because the Government of Indonesia is now embarking on an ambitious plan to rapidly scale up geothermal power capacity and eventually achieve a longer-term target of 9,500 MW by 2025. This study relies on the resource base estimates made by the Indonesian Government-owned enterprise P.T. Pertamina (now subsidiary Pertamina Geothermal Energy, or “PGE”) for nearly 80 sites, and productivity data on 215 wells in the country in the GeothermEx archives; these wells comprise some 80% of the total production wells drilled in Indonesia. Such a thorough national inventory of the geothermal resource base is available from very few countries. The geothermal resource base (proved-plus-probable-plus-possible) at a given site ranges from 10 MW to 800 MW with a log-normal distribution. More than 70% of the known Indonesian fields have a resource base greater than 50 MW and at least half of the fields (about 40) offer a resource base of 100 MW or more. Commercial wells in Indonesia vary in capacity from 3 MW to more than 40 MW, with a median value of 9 MW; this range and median are larger than seen in most countries; we believe the most likely range of well productivity worldwide is 4 to 6 MW. The commercial wells in Indonesia tend to fall in one of four groups in terms of capacity: (a) 3 to 5 MW representing “tight” wells; (b) 7 to 9 MW representing “typical” wells; (c) 15 to 19 MW representing wells that usually produce from The findings, interpretations, and conclusions expressed in this paper are entirely those of the authors and should not be attributed in any manner to the World Bank Group, to members of its’ board of executive direc- tors or the countries they represent, or the Government of Indonesia. Subir K. Sanyal is a Senior Advisor at GeothermEx James W. Morrow is a Database Manager at GeothermEx Migara S. Jayawardena is a Senior Energy Specialist at the World Bank Noureddine Berrah was formerly a Lead Energy Specialist at the World Bank Shawna Fei Li was formerly a Junior Professional Associate at the World Bank Suryadarma was previously the Director of Operations at PGE JUNE 2014 Geothermal Resource Risk in Indonesia A Statistical Inquiry Subir K. Sanyal, James W. Morrow, Migara S. Jayawardena, Noureddine Berrah, Shawna Fei Li, and Suryadarma Photo courtesy of GeothermEX Inc. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Transcript of Official PDF , 12 pages

Page 1: Official PDF , 12 pages

ABSTRACT

This paper presents a statistical study of the geothermal resource risk in Indonesia, specifically, that the resource base and well productiv-

ity are adequate and that the drilling cost per well is reasonable. This paper is timely because the Government of Indonesia is now embarking on an ambitious plan to rapidly scale up geothermal power capacity and eventually achieve a longer-term target of 9,500 MW by 2025. This study relies on the resource base estimates made by the Indonesian Government-owned enterprise P.T. Pertamina (now subsidiary Pertamina Geothermal Energy, or “PGE”) for nearly 80 sites, and productivity data on 215 wells in the country in the GeothermEx archives; these wells comprise some 80% of the total production wells drilled in Indonesia. Such a thorough national inventory of the geothermal resource base is available from very few countries. The geothermal resource base (proved-plus-probable-plus-possible) at a given site ranges from 10 MW to 800 MW with a log-normal distribution. More than 70% of the known Indonesian fields have a resource base greater than 50 MW and at least half of the fields (about 40) offer a resource base of 100 MW or more.

Commercial wells in Indonesia vary in capacity from 3 MW to more than 40 MW, with a median value of 9 MW; this range and median are larger than seen in most countries; we believe the most likely range of well productivity worldwide is 4 to 6 MW. The commercial wells in Indonesia tend to fall in one of four groups in terms of capacity: (a) 3 to 5 MW representing “tight” wells; (b) 7 to 9 MW representing “typical” wells; (c) 15 to 19 MW representing wells that usually produce from

The findings, interpretations, and conclusions

expressed in this paper are entirely those of

the authors and should not be attributed in

any manner to the World Bank Group, to

members of its’ board of executive direc-

tors or the countries they represent, or the

Government of Indonesia. Subir K. Sanyal is a Senior Advisor at GeothermEx

James W. Morrow is a Database Manager at GeothermEx

Migara S. Jayawardena is a Senior Energy Specialist at the World Bank

Noureddine Berrah was formerly a Lead Energy Specialist at the World Bank

Shawna Fei Li was formerly a Junior Professional Associate at the World Bank

Suryadarma was previously the Director of Operations at PGE

JUNE 2014

Geothermal Resource Risk in Indonesia A Statistical Inquiry

Subir K. Sanyal, James W. Morrow, Migara S. Jayawardena, Noureddine Berrah, Shawna Fei Li, and Suryadarma

Photo courtesy of GeothermEX Inc.

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

wb350881
Typewritten Text
89411
Page 2: Official PDF , 12 pages

2

a 100% steam-saturated but otherwise moderate-temperature reservoir or from a “steam cap”; and (d) greater than 27 MW representing “ultra-high” temperature and/or highly permeable reservoirs. The last two types of wells, which occur in relatively few countries other than Indonesia, represent 40% of the 215 wells studied in this paper.

Geothermal wells in Indonesia are mostly in the 1,000 to 2,800 m depth range and the drilling success rate ranges from 63% to 73%, which are also typical in most countries. Using an existing correlation of drilling cost versus well depth from several countries, and the defined statistics on well depth and productivity in Indonesia, we estimate that the cost per MW well capacity in Indonesia

is statistically less than seen in many countries, the most probable value being in the range of $300,000 to $400,000 per MW. The average drilling success rate and well capacity in Indonesia show a clear “learning curve” effect; both success rate and well capacity tend to increase with the number of wells drilled, eventually reaching a plateau.

Given that (a) more fields with large resource bases are encountered in Indonesia than in most other countries, (b) well capacity in  Indonesia typically is larger than in other countries, and (c) drilling cost per well in Indonesia is smaller than in most countries, the data indicates that the overall resource risk in geothermal projects in Indonesia

should be lower than in other countries.

Figure 1: Indonesia’s Geothermal Prospects

13,778

9,304 1,681

1,961

50

50

534

JAKARTAPA

PUA

NEW

GUI

NEA

A U S T R A L I A

SINGAPORE

VIETNAM

THAILAND

MYANMARCAMBODIA

TIMOR-LESTE

BRUNEIDARUSSALAM

P H I L I P P I N E S

MA L A Y

SI

A

CelebesSea

Java SeaBanda

Sea

Arafura Sea

SuluSea

PACIFIC OCEAN

I N D I A N O C E A N

PAPUA

AruIs.

KaiIs.

TanimbarIs.

Halmahera

Biak

Yapen

Morotai

Misool

Waigeo

Peleng Obi

Muna

CeramBuru

SULAWESI Sula Is.

Timor

Flores

AlorWetar

MoaBabar

Sumba

Sumbawa

Lombok

JAWA

NatunaBesar

Belitung

Madura

SUMATRABangka

Lingga

Nias

Siberut

Enggano

Simeulue

TalaudIs.

Bali

KALIMANTANM

en

t a wa i I s .

10°

10°10°

15°

10°

15°

95° 100° 105° 110° 115° 120° 125° 130°

95° 100° 105° 110° 115° 120° 125° 130°

135° 140°

135° 140°

INDONESIA

0 200

0 100 200 300 400 Miles

400 Kilometers

IBRD 41049

JULY 2014

I N D O N E S I AENERGY GEOTHERMAL POTENTIAL (MWe): SPECULATIVE = 9,533 MWe HYPOTHETICAL = 4,475 MWe PROBABLE = 10,317 MWe POSSIBLE = 728 MWe PROVEN = 2,305 MWe TOTAL = 27,358 MWe

NATIONAL CAPITAL

INTERNATIONAL BOUNDARIES

This map was produced by the Map Design Unit of The World Bank.The boundaries, colors, denominations and any other informationshown on this map do not imply, on the part of The World BankGroup, any judgment on the legal status of any territory, or anyendorsement or acceptance of such boundaries.

GSDPMMap Design Unit

Speculative(MWe)

Hypothetical(MWe)

Probable(MWe)

Possible(MWe)

Proven(MWe)

Total(MWe)

Sumatra 5,530 2,353 5,491 15 389 13,778

Kalimantan 50 — — — — 50

Sulawesi 900 125 761 110 65 1,961

Maluku 275 117 142 — — 534

Java 2,363 1,521 2,980 603 1,837 9,304

Papua 50 — — — — 50

Bali-Nusa Tenggara 365 359 943 — 14 1,681

Source: Authors based on information from Ministry of Energy and Mineral Resources, Indonesia.

Page 3: Official PDF , 12 pages

3

INTRODUCTION

Indonesia has perhaps the largest num-ber of known geothermal fields and most ambitious plans for accelerated geothermal power development in the world: 9,500 MW by 2025. Figure 1 is a map of the country with estimated geothermal potential in various islands. However, there is a perception among many geothermal developers and finan-ciers outside Indonesia that the resource related risk in geothermal development in Indonesia is substantial. Yet, we find no statistical basis for this perception, even though there are some 100 known geothermal fields and prospects in the country, and nearly 300 deep wells. In this section we ana-lyze the resource risk elements in Indonesia in a quanti-tative way and compare them to the same resource risk elements in other countries with existing or  imminent geothermal development.

There are at  least four fundamental requirements that must be satisfied for any commercial geothermal development project; these are:

a. adequate resource base;b. adequate well productivity;c. acceptable drilling cost per well; andd. benign fluid chemistry.

We will analyze here the uncertainty associated with the first three of the above requirements in  Indonesia compared to that in other countries.

ADEQUACY OF RESOURCE BASE

Before acquiring a  geother-mal development concession in a country a developer needs to have a  reasonable under-standing of the resource base available at  the site. In many countries this information is  incomplete or unavailable, whereas in Indonesia the govern-ment developer PT Pertamina had in the past systematically explored most of the prospec-tive areas, drilled deep wells in several fields and assessed the proved, probable and pos-sible resource base in nearly all prospects. Figure 2 presents

Figure 2: Histogram of total resource base in geothermal fields in Indonesia

0 200100 300 400 500 600 700 8000

2

4

6

8

10

12

14

Freq

uenc

yProved + Probable + Possible Reserves (MW)

Source: GeothermEx, Inc.

Figure 3: Frequency distribution of total geothermal resource base in Indonesia fields on a log-normal probability plot

0.01

0.05 0.

10.

20.

5 1 2 5 10 20 30 40 50 60 70 80 90 95 98 99

99.8

99.9

99.9

9

1.0

1.2

1.4

1.6

1.8

2.0

2.2

2.4

2.6

2.8

3.0800700600500400300

200

100908070605040

30

20

10

Log1

0 (R

esou

rce

Bas

e)

Frequency (%)

Reserve Base, R

(MW

)

Source: GeothermEx, Inc.

Page 4: Official PDF , 12 pages

4

a histogram of the total resource base (proved + probable + possible) in  Indonesian fields as estimated by Pertamina. The resource base displays a wide range, from 10 MW to nearly 800 MW.

As expected in any nation-wide assessment of this type, the histogram indicates the occur-rence of  progressively more fields with smaller reserves, that is, an approximately log-normal distribution of resource base. To verify this outcome, in Figure 3 we have plotted the logarithm of the total resource base as a  function of  the fre-quency of occurrence on a nor-mal probability scale. A clear linear trend of data points on this plot establishes that the dis-tribution of the resource base is  log-normal. Therefore, Per-tamina’s assessment of resource base values appears consistent, and so the prospect inventory developed by Pertamina has significant value for develop-ers looking for project sites in the country. Such a consistent national inventory of resource base is available from relatively few countries trying to attract geothermal developers.

Figure 4 is a plot of  the cumulative frequency of  resource base as a  function of  the MW capacity in Indonesian fields. This figure indicates that there is 50% cumulative probability that a geothermal field will have a resource base exceeding 100 MW; which is an attractively large scale of development for commercial development. It  is unlikely that a foreign developer would be  interested in developing a field in  Indo-nesia unless it offered the prospect for developing at least 50 MW; Figure 4 shows that more than 70% of the Indonesian fields (more than 50 fields) exceed this threshold. The occurrence of so many potentially available commercial project sites in a country is rare. The total estimated resource base in Indonesia in the

102 known fields amounts to about 16,000 MW. It is likely that further exploration and drilling will reveal even more exploitable geothermal sites and increase the inven-tory of the resource base known today. Therefore, there is a sufficient resource base in the country to justify the development target of the Government of Indonesia.

ADEQUACY OF WELL CAPACITY

We have accumulated statistics on 215 deep geothermal wells in Indonesia, which represent a large majority of all geothermal wells in the country; most of the individual well data remain confidential to the developer. This is an

Figure 4: Cumulative frequency of proven + probable + possible resource base in Indonesia

0 200100 300 400 500 600 700 8000

0.40.30.20.1

0.50.60.70.80.91.0

Cum

ulat

ive

Freq

uenc

yMW

Proven + Probable + Possible Reserves

Source: GeothermEx, Inc.

Figure 5: Histogram of well capacity, Indonesian fields (including non-commercial wells)

0 to

2

2 to

4

4 to

6

6 to

8

8 to

10

10 to

12

12 to

14

14 to

16

16 to

18

18 to

20

20 to

22

22 to

24

24 to

26

26 to

28

28 to

30

30 to

32

32 to

34

34 to

36

0%

10%

5%

15%

20%

25%

30%

35%

40%

Freq

uenc

y

MW

Source: GeothermEx, Inc.

Page 5: Official PDF , 12 pages

5

adequate database for analyzing the well capacity risk. Figure 5 presents a histogram of per-well MW capacity in Indonesia based on the data from the 215 wells. A well capacity of  less than 2 MW, and in some cases 3 MW, is considered an unsuccessful or non-commercial well and is usually turned into an injec-tion well or observation well, or is abandoned. Figure 5 indi-cates that about 38% of wells are less than 2 MW in capacity, and as such, non-commercial. Therefore, the drilling success rate in Indonesia to date is about 62%. However, this database includes exploration wells, con-firmation wells, development wells and make-up wells; the drilling success rate generally becomes higher as a project moves from exploration through the confirmation, development and operational stages in suc-cession. The average well suc-cess rate in the development and operational stages of the oldest operating field in Indone-sia (Kamojang) has been about 73%. This level of development drilling success is typical in most countries with geothermal potential.

Figure 6 presents a his-togram of MW capacity of all commercially successful wells, which are defined here as wells with a capacity of at least 3 MW. Figure 6 indicates an approxi-mately log-normal distribution with a clear peak (at 3 to 5 MW).

Figure 7 shows a plot of the cumulative frequency of well capacity of  the commercial wells in Indonesia; the wells vary in capacity from 3 MW to more than 40 MW, with a median

Figure 6: Histogram of well capacity, Indonesian fields (commercial wells only)

3 to

5

5 to

7

7 to

9

9 to

11

11 to

13

13 to

15

15 to

17

17 to

19

19 to

21

21 to

23

23 to

25

25 to

27

27 to

29

29 to

31

31 to

33

33 to

35

35 to

37

37 to

390%

10%

5%

15%

20%

25%

Freq

uenc

y

MW

Source: GeothermEx, Inc.

Figure 7: Cumulative frequency of well capacity, Indonesian fields (commercial wells only)

1.0 10.0 50.00

0.40.30.20.1

0.50.60.70.80.91.0

Cum

ulat

ive

Freq

uenc

y

MW

Source: GeothermEx, Inc.

Figure 8: Histogram of commercial well capacity, Indonesian fields, (post 1990)

3 to

5

5 to

7

7 to

9

9 to

11

11 to

13

13 to

15

15 to

17

17 to

19

19 to

21

21 to

23

23 to

25

25 to

27

27 to

29

29 to

31

31 to

33

33 to

35

35 to

37

37 to

390%

8%

4%2%

12%

16%14%

10%

6%

18%20%

Freq

ency

Capacity (MW)

Source: GeothermEx, Inc.

Page 6: Official PDF , 12 pages

6

value of 9 MW. The mean, median and maximum values of well capacity in Figure 7 are all higher than seen in other countries. Worldwide, a geo-thermal well capacity of 4 to 6 MW is most common. It  is worthwhile investigating the reason for this difference between the well capacity dis-tribution in Indonesia and most other countries.

Geothermal wells have been drilled in  Indonesia continuously since the 1970s. Given that over the last few decades the state-of-the-art and experience in geothermal well drilling and field develop-ment have improved worldwide, let us consider the statistics of wells drilled in  Indonesia only since 1990, when the pace of drilling activity accelerat-ed in  Indonesia. A histogram of the MW capacity of all wells in  Indonesia since 1990 that are at  least 3 MW in capacity is shown in Figure 8.

This figure reveals that when the pre-1990 wells are ignored, the histogram of well productivity is  no longer

log-normal but has multiple modes: Mode 1 ( 3 to 5 MW), Mode 2 (7 to 9 MW), Mode 3 (15 to 19 MW) and Mode 4 (27 to 31 MW).

This multi-modal distribution can be explained by referring to the several classes of geothermal fields discovered over the last two decades in Indonesia. Mode 1 typically represents “tight,” marginal wells that can randomly occur in any geothermal system, and as such, are not unique to Indonesia. Mode 2 (7 to 9 MW) wells are often referred to as the “most likely” in Indonesia. For example, JICA and WestJEC (2007) and JICA and WestJEC (2009) refer to 8 MW as the typical capacity for wells in Indonesia. Mode 2 wells represent those

Figure 10: Histogram of maximum well temperature, Indonesian fields

140

to 1

50

150

to 1

60

160

to 1

70

170

to 1

80

180

to 1

90

190

to 2

00

200

to 2

10

210

to 2

20

220

to 2

30

230

to 2

40

240

to 2

50

250

to 2

60

260

to 2

70

270

to 2

80

280

to 2

90

290

to 3

00

300

to 3

10

310

to 3

20

320

to 3

30

330

to 3

40

340

to 3

50

350

to 3

60

360

to 3

70

370

to 3

80

Freq

uenc

y

MW

0%

10%

5%

15%

20%

25%

Source: GeothermEx, Inc.

Figure 9: Maximum well temperatures vs. MW capacity, Indonesian fields

200 220 240 260 280 300 320 340 360 3800

20

10

30

40

50

60

MW

Cap

acity

per

Wel

l

Maximum Well Temperature ( ˚c)

Source: GeothermEx, Inc.

Photo courtesy of Migara Jayawardena / World Bank.

Page 7: Official PDF , 12 pages

7

producing from typical high-temperature liquid-dominated wells, as found in many countries. However, given that the Mode 3 and Mode 4 wells have much higher commercial value, the assumption of an 8 MW well capacity for the analysis of  the resource risk in  Indonesia significantly overestimates this risk. Let us examine what underlying resource conditions the Modes 3 and 4 wells may represent.

Figure 9 is a plot of the MW capacity versus tem-perature of all 215 wells. This figure indicates two clus-ters of wells, one in the 230°C to 250°C range and the other in the 300°C to 340°C range. It can be shown that most of the Mode 3 wells falling in the 230°C to 250°C range typically represent wells producing from a 100% saturated steam reservoir, and the Mode 4 wells falling

in the 300°C to 340°C range represent ultra-high tempera-ture liquid-dominated wells, sometimes producing from a “steam cap”. Mode 3 and Mode 4 wells occur in relatively few countries besides Indonesia.

This divers i ty in   the MW characteristics of wells in Indonesia makes the assess-ment of the resource risk more challenging. For example, Figure 10 is a histogram of the temperatures of the 215 wells; this figure shows only two modes rather than four as seen in Figure 8, but similar to what is seen in Figure 9. Figures 8 and 9 imply that Modes 3 and 4 are uniquely defined and represent well capacities more attractive than are found in all but a few countries, whereas Mode 2 represents wells with a broad range of temperatures and productivity found in many countries, and Mode 1 rep-resents generally tight and/or relatively low temperature wells. Given that the Mode 3 and Mode 4 wells together represent nearly 40% of  the

Figure 12: Well depth vs. MW capacity, Indonesian fields

500 1000 1500 2000 2500 3000 35000

15

5

10

20

25

30

35

MW

Cap

acity

per

Wel

l

Well Depth (meters)

Source: GeothermEx, Inc.

Figure 11: Histogram of well depth, Indonesian fields

0 to

200

200

to 4

00

400

to 6

00

600

to 8

00

800

to 1

000

1000

to 1

200

1200

to 1

400

1400

to 1

600

1600

to 1

800

1800

to 2

000

2000

to 2

200

2200

to 2

400

2400

to 2

600

2600

to 2

800

2800

to 3

000

3000

to 3

200

3200

to 3

400

3400

to 3

6000%

10%

4%

2%

6%

8%

12%

14%

16%

Freq

uenc

y

Depth (m)

Source: GeothermEx, Inc.

Photo courtesy of Migara Jayawardena / World Bank.

Page 8: Official PDF , 12 pages

8

215 wells, we conclude that on a nationwide basis, Indone-sia represents an unusually high occurrence of commercially attractive wells.

WELL DEPTH AND COST

Depth is the main determinant of the drilling cost of a geother-mal well. Typically drilling cost in any country increases expo-nentially with depth; see, for example, GeothermEx (2004). Therefore, the depth distribu-tion of wells in Indonesia is an important issue in the assess-ment of resource risk in the country. Figure 11 shows a histogram of the depths of the 215 wells indicating that geothermal well depth in Indonesia ranges from about 1,000 to 2,800 m, which is also representative of  the range found in most countries with geothermal fields (GeothermEx, 2004).

Although there are no detailed statistics, we know from experience that drilling cost in Indonesia is some-what lower than seen in most countries. We have already shown that drilling success rate in Indonesia is compa-rable to that in other countries. Given that (a) the well depth and drilling success rate in  Indonesia are comparable to  those in other countries, (b) the drilling cost per meter is somewhat lower in Indonesia than seen in other countries, and (c) that well capacity is gen-erally higher in Indonesia than in other countries, we conclude that the cost per MW of well capacity in Indonesia is statisti-cally lower than encountered elsewhere.

Figure 12 presents a plot of  the MW  capacity versus depth of the 215 wells. It shows two clusters. The points clus-tered around a depth of 1,500

m represent mostly Mode 3 wells while the points clustered around 2,500 m depth represent Mode 4 wells. Figure 13 is a histogram of the drilling cost per MW of successful wells in  Indonesia, based on the correlation in Geo-thermEx (2004) and the MW capacity versus depth data in Figure 12. This figure shows that the drilling cost per MW well capacity in Indonesia ranges from US$100,000 to nearly $2,000,000 the most probable range being $300,000 to $400,000 per MW; this is significantly lower than in most other countries.

Figure 14: Average drilling success rate vs. number of wells drilled in Indonesia

0 50 100 150 2000

20

10

30

40

50

60

70

80

Ave

rage

Dril

ling

Succ

ess

Rate

(%)

Number of Wells Drilled

Source: GeothermEx, Inc.

Figure 13: Histogram of drilling cost per MW for successful wells, Indonesian fields

100

200

300

400

500

600

700

800

900

1,00

0

1,10

0

1,20

0

1,30

0

1,40

0

1,50

0

1,60

0

1,70

0

1,80

0

1,90

0

2,00

0

2,10

0

2,20

00%

20%

5%

10%

15%

25%

30%

Freq

uenc

y

Drilling Cost ($1,000/MW)

Source: GeothermEx, Inc.

Page 9: Official PDF , 12 pages

9

THE LEARNING CURVE EFFECT ON RESOURCE RISK

Geothermal resource development has been going on in Indonesia for more than three decades. Over this long period the risk should have lessened due to improve-ments in technology and/or experience gained in avoid-ing or mitigating such risk. Therefore, we examine to what extent the learning curve effect may have positively influenced some elements of resource risk in Indonesia. Figure 14 is a plot of the average drilling success versus the number of wells drilled (not including some 20%

Figure 16: Average drilling success rate vs. number of wells drilled in the Kamojang field, Indonesia

0 2010 4030 50 8070600

20

10

30

40

50

60

70

80

Aver

age

Dril

ling

Succ

ess R

ate

(%)

Number of Wells Drilled

Source: GeothermEx, Inc.

of the wells on which we have no data) in Indonesia.

Clearly, the success rate in drilling has fluctuated but steadily increased as more wells have been drilled, until a stable average success rate of about 62% was reached (after about 90 wells), when the learning curve effect reached a plateau. As mentioned before, the data-base in Figure 14 includes wells in all stages of geothermal proj-ects. Since the average drill-ing success rate progressively increases through the explora-tion, confirmation, develop-ment and operational stages

of a project, a drilling success rate of 62% is an underesti-mate for the development and operational stages, when the majority of the wells are drilled in a project.

Figure 15 is a plot of the average production capacity of all wells drilled and the average production capacity of only the successful wells drilled in Indonesia as a func-tion of the total number of wells drilled. Figure 15 shows that the average capacity of the successful wells reached a plateau of 9.8 MW after about 200 wells were drilled. Figure 14 shows that the drilling success rate plateaued at 62% after 200 wells were drilled. Therefore, the average capacity of all wells drilled should have stabilized at 9.8

MW x 0.62, that is, 6.1 MW after 200 wells; this is confirmed by the lower curve in Figure 15, implying that the statistics on the learning curve effect are internally consistent.

Figure 15 shows that, the capacity per well increased until it reached a plateau after about 40 wells were drilled. Then, after about 140 wells were drilled, a steady increase in the aver-age well capacity ensued again, even though the well success rate remained nearly constant at about 62% (Figure 14) as fur-ther wells were drilled. This apparent discrepancy stems

Figure 15: Average MW per well vs. number of wells drilled in Indonesia

0 60 804020 100 120 140 160 180 2000

2

4

6

8

10

12

Capa

city

per

Wel

l (M

W)

All Wells

Number of Wells Drilled

Successful Wells

Source: GeothermEx, Inc.

Page 10: Official PDF , 12 pages

10

from the fact that over the last decade more and more wells of Mode 2 and Mode 3 have been drilled. Figure 15 shows a peak in the average capacity of successful wells of 9.8 MW, whereas the average capacity of all wells reached 6.1 MW, again reflecting an unchanged drilling success rate of 62%. Therefore, although the learning curve effect on drilling success rate plateaued at 62%, the average MW capacity per well kept on increasing because developers began tapping more Mode 3 and Mode 4 wells. In other words, the assumption that a typical well in Indonesia is slightly better than the 4 to 6 MW seen in other countries is unwarranted; it is substantially better (the average nationwide being about 10 MW) and is likely to climb even higher as new projects begin tapping Mode 3 and Mode 4 wells.

The learning curve effect on the geothermal resource risk is best illustrated by considering a specific geothermal field rather than Indonesia as a whole. The Kamojang field in Indonesia is the best example for this illustration because it has the longest exploration, development and production history in Indonesia (since the 1970s); see Sanyal et al (2000) and Suryadarma et al (2010). Figure 16 shows the average drilling success rate at the Kamojang field as a function of the number of wells drilled. Again, the drilling success rate increases with drilling until a plateau at a drilling success rate of 73% is reached after about 40 wells.

CONCLUSIONS

• PGE’s geothermal resource base assessments are consistent; such a thorough national inventory of the geothermal resource base is available from very few

countries. The resource base (proved-plus- probable-plus-possible) at a site ranges from 10 MW to 800 MW with a log-normal distribution. More than 70% of the known Indonesian fields have a resource base greater than 50 MW, and at  least half of the fields (about 40) offer a resource base of 100 MW or more.

• Commercial wells in Indonesia vary in capacity from 3 MW to more than 40 MW, with a median value of 9 MW; this range and median are larger than seen in most countries while we believe the most likely range of well productivity worldwide is 4 to 6 MW.

• The commercial wells in Indonesia tend to fall in one of four groups in terms of capacity: (a) 3 to 5 MW rep-resenting “tight” wells; (b) 7 to 9 MW representing “typical” wells; (c) 15 to 19 MW representing wells that usually produce from a 100% steam-saturated but otherwise moderate-temperature reservoir or from a “steam cap”; and (d) greater than 27 MW representing “ultra-high” temperature and/or highly permeable reservoirs. The last two types of wells, which occur in relatively few countries other than Indonesia, rep-resent 40% of the 215 wells studied in this paper.

• Geothermal wells in Indonesia are usually 1,000 to 2,800 m in depth and the drilling success rate appears to range from 63% to 73%, which are typical also in most countries. Using a correlation of drilling cost versus well depth from several countries, and the statistics on well depth and productivity in Indone-sia, we estimate that the cost per MW well capacity in  Indonesia is statistically less than seen in most countries, the most probable value being in the range of $300,000 to $400,000 per MW.

• The average drilling success rate and well capacity in  Indonesia show a clear “learning curve” effect; both success rate and well capacity tend to increase with the number of wells drilled, eventually reaching a plateau.

• This analysis also implies that there is a sufficient geothermal resource base in Indonesia and that it is possible to scale-up as proposed in the GoI devel-opment targets. However, it will be essential to have an adequate policy framework that will be seen as credible by developers and enhance the investment climate, especially if the private sector is expected to play a major role in the proposed expansion.

Phot

o co

urte

sy o

f Geo

ther

mEX

Inc.

Page 11: Official PDF , 12 pages

11

REFERENCES

GeothermEx, 2004. New Geothermal Site Identification and Quantification. Report prepared for Public Inter-est Energy Research (PIER) program of the California Energy Commission, April 2004. Available from: http://www.energy.ca.gov/pier/project_reports/500–04–051.html.

JICA and WestJEC, 2007. Master Plan Study for Geothermal Power Development in The Republic of Indonesia. Final Report, September 2007.

JICA and WestJEC, 2009. Study on Fiscal and Non-Fiscal Incentives to Accelerate Geothermal Energy Develop-ment by Private Sector in The Republic of Indonesia. Interim Report, January 2009.

Public-Private Infrastructure Advisory Facility (PPIAF), 2010. An Assessment of Geothermal Risks in  Indonesia. Prepared by GeothermEx, Inc., for The World Bank, June 2010.

Sanyal, S.K., A. Robertson-Tait, C.W. Klein, S.J. Butler, J.W. Lovekin, P.J. Brown, S. Sudarman and S. Sulaiman, 2000. Assessment of Steam Supply for the Expan-sion of Generation Capacity from 140 to 200 MW, Kamojang Geothermal Field, West Java, Indonesia. Proceedings World Geothermal Conference 2000, pp. 2195–2200.

Suryadarma, T. Dwikorianto, A.A. Zuhro and A. Yani, 2010. Sustainable Development of the Kamojang Geother-mal Field. Geothermics, Vol. 39, No. 4, December 2010, pp. 391–399.

Photo courtesy of GeothermEX Inc.

Page 12: Official PDF , 12 pages

The publication and dissemination of this paper is made possible due to the financial support from the Asia Sustainable and Alternative Energy Program (ASTAE), which is a multi-donor trust fund program administered by the World Bank. This paper was initially presented at Stanford University’s Workshop on Geothermal Reservoir Engineering, in 2011; and is based on a larger study conducted by GeothermEx for the World Bank (PPIAF, 2010) to assist the Gov-ernment of Indonesia with geothermal development. This work contributed to a program of support that is being provided by the World Bank Group to Indonesia where it is supporting the world’s largest geothermal expansion. The results of this work was also presented at an ASTAE-sponsored special session at The World Geothermal Congress 2010 held in Bali, Indonesia (27 April, 2010). The authors gratefully acknowledge the funding for this work by the Public-Private Infrastructure Advisory Facility (PPIAF) and ASTAE. The authors thank the Ministry of Energy and Mineral Resources of the Republic of Indonesia for their collaboration during the preparation of the study.