Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk...

60
etherlands Institute of Applied Geoscience TNO National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance of the E&P industry

Transcript of Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk...

Page 1: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

Netherlands Institute of Applied Geoscience TNO- National Geological Survey

E&P Decision & Risk Analysisby Christian Bos

D&RA for improved performance of the E&P industry

Page 2: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 2

Contents

1. Objectives of RA, tools and methods

2. Features - Events - Processes (FEP) analysis• Objective: HSE impact assessment

3. E&P Best Practice project• FUN forum for Forecasting and Uncertainty; decision-making, etc.

4. “E&P Decision & Risk Analysis”• Objective: improved economic performance• History, past performance E&P industry• Continuous & Discrete uncertainties• Hierarchical constrained optimization under uncertainty• Options modelling• Decision analysis• Modelling: degree of holistic processing, degree of probabilistic processing

3. Conclusions

Page 3: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 3

RA objectives, methods

1. Optimizing economic performance • Internal company capital investment decision-making process• Method / tools : D&RA + similar methods

2. License application / continuation• External orientation on government authorities• Focus on HSE, commerciality may have to be demonstrated• Method / tools : FEP analysis, perhaps D&RA-like approaches,

monitoring methods (Value of Information in terms of Risk)

3. Operational planning• External + internal focus: operational control• Method / tools: HAZOP

Page 4: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 4

FEP methodologyFeature-Events-Processes

a scenario-based, qualitative approachusing a mental, not physical, model of FEP interrelations +

empirical evidence / expert elicitation to assess probabilities

Feature: system propertyEvent: (exogenous) disturbance of system equilibrium

Process: reaction of system due to disturbance

(Reaction may be subject to feedback loops, delayed, through chain of effects, non-linear: System Dynamics)

Page 5: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 5

Qualitative scenario analysis

FEP identification

FEP classification

FEP selection and interaction

Scenario definition and selection

Model concept

Model buildingCons

e-quen

ceanaly

sis

SA ofkey factors

Qualitative Scenario Definition

FEP Analysis

Safety Assessment Model Development

Quantitative Impact Modelling

Page 6: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 6

Mo

del

dev

elo

pm

ent

Risk identification / classification

Risk ranking /

screening

Risk interaction/ grouping

Scena rio (element) formation

Conceptual model

development

3D <> 2D numerical

model

Probabilistic 2D numerical

simulation

Statistical processing/ assessment

Testing with (natural)

analogues

Qu

ali

tati

ve

Sce

nar

io a

nal

ysis

C

on

seq

uen

ce

anal

ysis

Qu

an

tita

tiv

e

0. Definition of assessment basis

Mo

del

dev

elo

pm

ent

Risk identification / classification

Risk ranking /

screening

Risk interaction/ grouping

Scena rio (element) formation

Conceptual model

development

3D <> 2D numerical

model

Probabilistic 2D numerical

simulation

Statistical processing/ assessment

Testing with (natural)

analogues

Qu

ali

tati

ve

Sce

nar

io a

nal

ysis

C

on

seq

uen

ce

anal

ysis

Qu

an

tita

tiv

e

0. Definition of assessment basis

Mo

del

dev

elo

pm

ent

Risk identification / classification

Risk ranking /

screening

Risk interaction/ grouping

Scena rio (element) formation

Conceptual model

development

3D <> 2D numerical

model

Probabilistic 2D numerical

simulation

Statistical processing/ assessment

Testing with (natural)

analogues

Qu

ali

tati

ve

Sce

nar

io a

nal

ysis

C

on

seq

uen

ce

anal

ysis

Qu

an

tita

tiv

e

0. Definition of assessment basis

Risk assessment workflow (scenario approach)

0.0E+00

5.0E-03

1.0E-02

1.5E-02

2.0E-02

2.5E-02

0 1000 2000 3000 4000 5000 6000 7000 8000 9000 10000

time [years] since start injection

[kg/

d/m

2]

0

200

400

600

800

1000

1200

1400

mean CO2 fluxradius

1300 3800

storage efficiency:90.0%

Mo

del

dev

elo

pm

ent

Risk identification / classification

Risk ranking /

screening

Risk interaction/ grouping

Scena rio (element) formation

Conceptual model

development

3D <> 2D numerical

model

Probabilistic 2D numerical

simulation

Statistical processing/ assessment

Testing with (natural)

analogues

Qu

ali

tati

ve

Sce

nar

io a

nal

ysis

C

on

seq

uen

ce

anal

ysis

Qu

an

tita

tiv

e

0. Definition of assessment basis

1

2

3

Page 7: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 7

1. Identification and classification of risk factors –- Database with risk factors (FEPs)

Page 8: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 8

1. Assign quantitative probability of occurrence (expert opinion) – An example –

FEP Group

(node in relational diagram)

Probability of occurrence

in 100 years

Changes natural system 0.02

Geochemical processes &

conditions

0.086

Geomechanical human induced 0.031

Gas composition 0.036

Geomechanical, natural 0.027

Geomechanical, geochemically 0.011

Leaking seal 0.02

Leaking fault 0.01

Page 9: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 9

1. Building a consistent probability framework withBayesian Belief Network (BBN)

Page 10: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 10

2. Some FEPs may be selected for modelling fluxes and concentrations (II); Well leakage scenario: A realisation of CO2 saturation after 10 000 yrs

• Average values at -300 m: 23% released from reservoir

Maximum flux after 1500 years

Affected area:0.18 km2

Page 11: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 11

E&P Performanceunderperformance due to bias &

unwillingness to learn from past & accept new methods

Page 12: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 12

FUN - Forum for forecasting and uncertainty evaluation (1997 – 2004)

• The Forum is an effort by the authorities and

industry in Norway to determine best practice and

methods for hydrocarbon resource and emissions

estimation, forecasting, uncertainty evaluation and

decision-making.

• 18 member companies plus Norwegian Petroleum

Directorate (NPD)

• Info www.fun-oil.org

Page 13: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 13

FUN - Members• A/S Norske shell U & P• Amerada Hess Norge A/S• BP Amoco Norge UA• RWE-DEA Norge A/S• Elf petroleum Norge A/S• Enterprise oil Norge ltd.• Esso Norge AS• Idemitsu petroleum Norge a.S.• Mobil exploration Norway inc.• Fortum petroleum A/S• Norsk Agip A/S• Norsk chevron A/S• Norsk Hydro ASA• Norske Conoco AS

• Norwegian Petroleum Directorate • Phillips Petroleum Company

Norway• Saga Petroleum a.s.• Den norske stats oljeselskap

(Statoil)• Total Norge A.S

Observers• Ministry of Petroleum & Energy• OLF• Miljøsok

Page 14: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 14

The appreciation factor in relation to discovery volumes (NPD)

Page 15: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 15

Oil Production Forecast NCS22 fields in production

0

20

40

60

80

100

120

140

160

180

1971

1974

1977

1980

1983

1986

1989

1992

1995

1998

2001

2004

2007

2010

2013

2016

2019

Oil

pro

duct

ion

(mill

Sm

3 /år)

PDO - Forecast Actual production Fall 90 Fall 95 Fall 98

Page 16: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 16

Comparison of investment forecasts for fields approved before 1997

Page 17: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 17

Cost & Schedule risk

• Schedule uncertainty usually poorly managed, incl. correlation to

costs!• Opex only treated superficially: we tend to forget implications!• Later, incremental investments not properly planned: real options,

corrective actions etc. + incremental costs not formally included.

Page 18: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 22

The context:decision-making under quantified uncertainty

Page 19: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 23

D

FUN Benchmark study 2004

AA BB

CC

EEFF GG

HHII

0

2

4

6

8

10

12

0 2 4 6 8 10 12

Probabilistic processing

Inte

gra

tio

n

Benchmarking study (bp, ChevTex, ConPhil, ENI, Exxon, Hydro, RWE, Statoil, Total)

Page 20: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 24

Integrated uncertainty analysis helps improving company performance

Ranking improves after introducing D&RA

0

2

4

6

8

10

12

14

16

1990 1992 1994 1996 1998 2000

Year (5 year period ending)

Ra

nk

Conoco

Chevron

Introduction of D&RA

Page 21: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 25

The D&RA Process, how mgt & staff create synergy: team work!

Page 22: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 26

Decision-making under uncertainty:full life-cycle perspective

Page 23: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 27

Decisions and Levels of Aggregation

Page 24: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 28

Using “Risk-tolerance” as optimisation constraint

• Project Risk = ∫IRR * pdf (IRR) d(IRR)

• i.e. cum.prob. x average IRR, if it is <WACC

• Project Risk = ∫NPV * pdf (NPV) d(NPV)

• i.e. cum.prob. x average NPV, if it is <0

• The decision-maker should then specify his/her risk-tolerance: for the project in question, and given other (portfolio) considerations, which cumprob x average NPV, i.e. if it is <0, am I prepared to accept?

• Risk-tolerance criterion can then be used as optimisation constraint to cut out bad decision-alternatives

WACC

- ∞

- ∞

0

Page 25: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 29

……

mo

de

llin

g

……

mo

de

llin

g

……

mo

de

llin

g

……

mo

de

llin

g

……

mo

de

llin

g

Aggregated data integration along value chain

StaticModelling

DynamicModelling

Ge

om

ech

an

ica

l mo

de

llin

g

Ge

och

em

ica

l mo

de

llin

g

Se

ism

ic m

od

elli

ng

Ge

olo

gic

al m

od

elli

ng

WellModelling

FacilitiesEngineering

Co

nce

ptu

al D

esi

gn

Co

st E

ng

ine

erin

g

EconomicModelling

Pro

ject

/ass

et li

fe-c

ycle

mod

el

Ta

x /

PS

C m

od

el

Ve

rtic

al F

low

Pe

rfo

rma

nce

Ge

om

ech

. /

fra

ctu

ring

mo

de

l

Pdf’s of KPIs• per activity• per project• per asset

• per portfolio(in time domain)

Related to“value”:

• KPI-Targets• Optim. criteria• Constraints

• Risk tolerance

Proxymodel

Proxymodel

Proxymodel

Proxymodel

Fullmodel

Mu

lti-

dis

cip

lin

ary

da

ta a

gg

reg

ati

on

Multi-disciplinary data aggregation & model integration along value chain

Page 26: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 30

Decision-making = value optimisation =hierarchical constrained optimisation under uncertainty given targets

Op

tim

isat

ion

cr

iter

ia

Op

timis

atio

n

co

ns

train

ts

Δvalue == Δprobability of meeting a set of pre-of meeting a set of pre-defineddefined time-series targets at the next hierarchical time-series targets at the next hierarchical decision-leveldecision-level

Corporate / portfolio level

Asset / field level

Project level

Operational level

Page 27: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 31

KPIs – Key Performance Indicators to be optimised• Corporate, e.g.

• EPS, ROACE, ROCE, RRR, Production Income; Quality of Earnings; Production Replacement Ratios, Excluding Acquisitions & Divestments; Finding & Development Costs, Including Acquisitions & Divestments; Discounted Future Net Cash Flow; Upstream Returns

• Asset, e.g. • NPV (EMV); IRR; UTC; P/I; POT; proved developed reserves;

expected reserves; etc.

• Project, e.g. • Capex minimisation within time constraint

• Appraisal, e.g.• Value of Information (EMV)

Page 28: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 32

Optimisation constraints• Usually, cost-related KPIs

• UTC, Maximum exposure, POT, RRR

• To be used as hurdle rate• E.g. WACC as hurdle rate for IRR, zero for NPV

• In the probabilistic mind-set, a risk-tolerance criterion should be added to act as optimisation (meta-)constraint:

• E.g. “I accept a probability-weighted NPV, if it is <0, of n $MM”• Then any project with a risk > n will be rejected.

• Other constraints:• Manpower, opportunities, HSE, time

• Integrated business models attempt to model “constrained KPI optimisation process”

Page 29: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 33

Corporate Production Planning

2000

2002

2004

2006

2008

2010

2012

2014

2016

2018

2020

2022

2024

Pro

duct

ion projects

developments

Producing fields

GAP

Target production

Probability of meeting portfolio multi-criteria objectives in time

Ref. SPE 68576 (Howell, Tyler): Using Portfolio Analysis to Develop Corporate Strategy

Page 30: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 34

Corporate Net Cash Flow Planning

2000

2002

2004

2006

2008

2010

2012

2014

2016

2018

2020

2022

2024

NC

F

projects

developments

Producing fields

NCF constraint

Probability of exceeding portfolio multi-criteria constraints in time

Risk tolerance to be specified: acceptable probability of not-meeting hurdle rate

Page 31: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 35

Portfolio time-domain feedback mechanism to be included in asset decision-making

SF1 SF2

Objective function & constraints

(outside time domain!)

Verify contribution of “optimised” asset decision against portfolio objectives. If necessary, override stand-

alone asset decision.

Corporate Production Planning

2000

2002

2004

2006

2008

2010

2012

2014

2016

2018

2020

2022

2024

Pro

duct

ion projects

developments

Producing fields

GAP

Target production

Page 32: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 36

D&RA - 5 main steps

1. Frame the

problem

2. Set-up quantitat.

models

3. Generate range of outcomes

4. Perform Sensitivity

Analysis

5. Apply Decision

Criteria

•Agree dec. crit.•Agree decisions•Agree scenarios•Construct tree•Prune tree•Agree tree

•Agree models•Populate model•Agree stoch. parameter pdf’s & scenario prob.•Agree / est. correlations•Agree KPIs•Agree risk def.

•Est. MC run parameters•Pdf’s of KPI’s•Quantify risks•Assess impact on portfolio•Est. utility fct, risk tolerance

•Tornado etc•Fine-tune decision altern.• Test robust-ness of decis: - model input - process par - utility fct - dec.sequence•VoI, VoF, ROV

•Describe process•Propose optim. solution+ impact on portfolio•Report•Monitor•Update model

Page 33: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 37

Decision-Making framework required for valuation (“No impact? No value!”)

Modelling decisions and uncertainties in a combined frameworkModelling decisions and uncertainties in a combined framework

Page 34: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 38

D&RA step 1: Pruning the tree (1)

• 96 end-nodes

Page 35: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 39

Pruning the tree (2)

• 48 end-nodes : reduced by half

Page 36: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 40

The ‘Value Loop’ (Shell)©

Execu

tion

Execu

tion

Data

Data

Physical Physical AssetAsset

ModelsModels

Dec

isio

ns

Dec

isio

ns

& P

lan

s&

Pla

ns

Asset Value Drivers &

Constraints

Data acquisition

Data acquisition

Interpre

tation

Interpre

tation

& Modelin

g

& Modelin

g

Generate &

Generate &

Evaluate

Evaluate

Options

Options

Page 37: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 41

A typical scenario / decision tree

• Decision nodes, chance nodes, end-nodes (or leaves)• What happens in end-node?

• How is total statistical information used at decision-node?

Decision nodes

Chance nodes

Page 38: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 42

Integrated, nested models to be run using Monte Carlo sampling process

1 pdf for each KPI

Page 39: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 43

Options modelling to capture value-upside and mitigate value-risk: flexibility has value!

I1

yr1 yr2

SE_I1Type 3

0

yr3

-10

PlatformConstr.Type 2

1000

1000

300

700

WellDrilling

abandon

100

wait100

100

vertical

horizontal

100

100

I1

yr1 yr2

SE_I1Type 3

0

yr3

-10

PlatformConstr.Type 2

1000

1000

300

700

WellDrilling

abandon

100

wait100

100

vertical

horizontal

100

100

optionsample year 1 year 2 year 3 year 4 year 5 year 6 year 7 year 8 year 9 NPV

1 continue continue continue continue continue continue continue continue continue 5002 continue abandon -103 continue continue continue continue continue continue continue continue continue 3004 continue continue continue special special special special special special 8005 continue continue continue wait wait continue continue continue continue 3006 continue continue continue abandon 1007 continue continue continue continue continue continue continue continue continue 2008 continue continue continue continue continue continue wait wait wait 1009 continue continue continue continue continue continue continue continue continue 200

10 continue continue continue continue continue abandon 30252

• Using automatic “triggers” in

time-series (dynamic DT)• E.g., oil price expectation after

time-step n until end of project• Triggers can be combined

using Boolean operators, e.g.

E(fut. oil price) < 15

OR

CFn, n+5<0

AND

Prodn, n+5<3000

Page 40: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 44

Problem framing: designing and evaluating options in dynamic decision trees

Quantify uncertainties

Predict probabilistically when & how theseuncertainties may be resolved in time (note 1)

Design, for each option, a decision algorithm basedon (expected) state variables /KPIs (to be applied at t=t1 …)

1. Distinguish unveiling of endogenous vs. exogenous information• Endogenous (project-specific): valuation of flexibility using EMV• Exogenous (general market, etc): valuation of flexibility using ROV

2. Unveiling of new info: distinguish model input (e.g. perm.) vs. model output parameters (e.g. qoil, NCF)

← “mapping uncertainty space onto decision space” →

Calculate, for each optional decision path in time, the NPV(by including cost of option)

← option valuation (“Value of Flexibility”) →

Design, for each scenario, options in response to (gradual) unveiling of truth (note 2)

Discontinue / delete any sub-optimal path(strike pull-out option)

← project valuation and ranking (including “Value of Flexibility”) →Calculate, for all dynamicallyoptimized (i.e. filtered), optional decision paths in time, the EMV of the full project

Compare this to EMV of alternative project definitions(with flexibilities) & rank

Select optimalproject definition

Page 41: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 45

The task of all stakeholders in E&P decision making is to

• Correctly quantify, using

the available models, the

uncertainty in the KPIs, • Reduce the associated risk

(i.e. reduce the chance of

obtaining a KPI less than a

given value), • Grasp the associated

opportunity or upside

potential (i.e. maximise the

chance of obtaining a KPI

more than a given value) byjudiciously acquiring new information

Page 42: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 46

The “modelling cube”

Page 43: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 47

integration

prec

ision

unce

rtai

nty

Utopia:the dream

Current practice

Page 44: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 48

integration

prec

ision

unce

rtai

nty

Utopia:the dream

Current practice

The high degree of model precision limits what we can achieve in terms of holistic and probabilistic modelling

Page 45: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 49

The realistic dream?

integration

prec

ision

unce

rtai

nty

The utopiandream

Current practice

Gradually increase precision (decision-driven)

Page 46: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 50

Discrete uncertainties(scenario trees)

Page 47: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 51

Decision node(with risk&opp. factors)

Chance node(can be conditional)

End node (leaf)here calculations in

Fast Models are done

Dead-end node(ltd. calc. of FM)

Scenario / decision name

Scenario chance

Optimal decision(branch coloured red)

?

Page 48: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 52

Continuous uncertainties(probability density functions)

Page 49: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 53

Integrated Asset Management1 pdf for each KPI for each end-node

Page 50: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 54

*

=

Monte Carlo Simulation Methodology, uncorrelated

*

RandomlySample

*

Revenue

Pr

Operating Expense

Pr

Capital Expenditure

Pr

Calculate

*

Cash Flow

Pr

0

Grey area = risk of NPV<0

Page 51: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 55

*

Monte Carlo Simulation Methodology, correlated parameters (here >0)

*

RandomlySample

Calculate

*

=

Revenue

Pr

Operating Expense

Pr

Capital Expenditure

Pr

Cash Flow

Pr

0

Lower risk!

Samplecorrelated

*

Page 52: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 56

Input parameters, output values and key performance indicators

SE DE RDP SF AP CO

INPUT PARAMETERS

STOIIP UR Qo(t)

#Wells

Qo(t)

CAPEX

Qo(t)

OPEX

OUTPUT VALUES

Indicators

Technical EconomicNPVetc...

STOIIPetc...

KEY PERFORMANCE INDICATORS

Page 53: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 58

Integrating continuous and discontinuous uncertainties (pdf’s & scenarios)

Establish pdf of KPIs for each end-nodeNPVP /

I IRR

Correctly model scenario dependencies !

Sample individual KPI-pdf’s and time-series at chance nodes and construct merged pdf

Page 54: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 59

Page 55: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 60

Page 56: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 62

Hierarchical optimization

• Optimized project should also be optimal for the asset’s life-cycle

• Optimized asset life-cycle should also be optimal for the company’s portfolio

• Etc.

• Risk cannot be assessed stand-alone for a project• Risk should be assessed in context of the portfolio

• Methods & tools required to preserve uncertainty relationships intra- & inter-project !

Page 57: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 63

DSS-Portfolio imports DSS-Asset information …

Page 58: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 64

… and optimises phasing of projects using objective function and EF

Page 59: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 65

Probability vs. time of meeting set of corporate KPIs is optimised

Page 60: Netherlands Institute of Applied Geoscience TNO - National Geological Survey E&P Decision & Risk Analysis by Christian Bos D&RA for improved performance.

November 8th, 2007ENGINE Workshop 7, Leiden (C. Bos) 68

Conclusion• State objective of RA very clearly

• HSE ? Are HSE-norms constraints for economic optimization?• Internal decision-making for capital allocation?• License application?• Operational planning?• Etc.

• Agree to which extent all processes can be modelled quantitatively, and whether models can be integrated

• Can impact models be integrated with economic models?

• See modelling more as a learning environment, rather than predictor of absolute truths

• Geosystem remains mainly poorly known!• Updating models & risk profiles, verifying assumptions…. LEARNING!• Design monitoring activities, design new decision options, strike options