NCSX Project Overview Hutch Neilson, NCSX Project Manager For the NCSX Team NCSX Conceptual Design...

25
NCSX Project Overview Hutch Neilson, NCSX Project Manager For the NCSX Team NCSX Conceptual Design Review Princeton, NJ May 21, 2002

Transcript of NCSX Project Overview Hutch Neilson, NCSX Project Manager For the NCSX Team NCSX Conceptual Design...

Page 1: NCSX Project Overview Hutch Neilson, NCSX Project Manager For the NCSX Team NCSX Conceptual Design Review Princeton, NJ May 21, 2002.

NCSX Project Overview

Hutch Neilson,

NCSX Project Manager

For the NCSX Team

NCSX Conceptual Design Review

Princeton, NJ

May 21, 2002

Page 2: NCSX Project Overview Hutch Neilson, NCSX Project Manager For the NCSX Team NCSX Conceptual Design Review Princeton, NJ May 21, 2002.

2

The National NCSX Team

UCSD, Columbia U., LLNL, ORNL, PPPL

in collaboration with

Auburn, NYU, SNL-A, Texas-Austin, Wisconsin

Australia, Austria, Germany, Japan , Russia, Spain, Switzerland, Ukraine

Page 3: NCSX Project Overview Hutch Neilson, NCSX Project Manager For the NCSX Team NCSX Conceptual Design Review Princeton, NJ May 21, 2002.

3

Stellarators Are Making Great Progress

Large Helical Device (Japan) > 3%.

Te ≈ 10 kev, Ti ≈ 5 keV.enhanced confinement.

2-minute pulses.

Wendelstein 7-X (Germany) (2006)non-symmetric optimized design.

Under construction (operates 2007).

Wendelstein 7-AS

(Germany)

> 3%.

enhanced confinement.

density control & enhanced

performance w/island divertor.

Page 4: NCSX Project Overview Hutch Neilson, NCSX Project Manager For the NCSX Team NCSX Conceptual Design Review Princeton, NJ May 21, 2002.

4

The U.S. Stellarator Program Has Moved Forward in the Past Year

Helically Symmetric Experiment (U. Wisc.)

• Successful test of quasi-symmetry.

Compact Toroidal Hybrid (Auburn)

• Construction progressing: operates 2003.

Theory Program is Emphasizing Stellarator Physics

• Successful 3D Physics Planning Workshop in January.

• New advances: 3D equilibrium reconstruction code (approved), 3D edge simulation code (proposed collaboration w/ Germany), improved optimizers.

Stellarator Collaborations are Increasing• Participation in LHD and W7-AS experiments.• Theory collaborations with Germany, Japan, Australia.

Stellarator System Studies are in the Plans• ARIES compact stellarator power plant optimization study starts soon.

Page 5: NCSX Project Overview Hutch Neilson, NCSX Project Manager For the NCSX Team NCSX Conceptual Design Review Princeton, NJ May 21, 2002.

5

U.S. Compact Stellarator Design Efforts (NCSX and QPS) Have Been Successful

Successful Physics Validation Reviews confirmed physics approach.

• NCSX: High-, quasi-axisymmetric test at PoP scale.

• QPS: Quasi-poloidal symmetry, very low aspect ratio at CE scale.

Designed by joint team using common tools.

DOE Approved Mission Need (CD-0) for Both Projects.

• Moved into conceptual design in May, 2001.

FESAC Endorsed NCSX as a Proof-of-Principle Experiment.• Citing potential to resolve reactor issues (steady-state, disruptions) and advance the

physics of 3D magnetized plasmas.

• “These gains earn for the compact stellarator an important place in the portfolio”

DOE Requested $11.8M in FY-2003 Budget Submission to Initiate

NCSX Project Starting this October.• Also, an increase for QPS conceptual design in FY-03, aiming for an -04 start.

The Compact Stellarator is Becoming a Reality.

Page 6: NCSX Project Overview Hutch Neilson, NCSX Project Manager For the NCSX Team NCSX Conceptual Design Review Princeton, NJ May 21, 2002.

6

The NCSX Mission Supports OFES Program Goals:Fusion Solutions, Plasma Science

1. Acquire physics knowledge needed to evaluate the compact stellarator as a fusion concept.

• Passively stable without active feedback; no disruptions.

• Steady state with no recirculating power for current or rotation drive.

• Enhanced confinement compatible with power & particle exhaust.

• Low aspect ratio (≤4.4) and high beta (≥ 4%) high power density.

Addresses FESAC / IPPA Milestone: “Determine attractiveness of a CS”

2. Advance understanding of 3D plasma physics for fusion and basic science. Effects of…

• Rotational transform sources (internal vs external),

• 3D plasma shaping,

• Magnetic quasi-axisymmetry, and

• 3D edge,

… on toroidal physics: equilibrium, stability, transport, boundary.

Page 7: NCSX Project Overview Hutch Neilson, NCSX Project Manager For the NCSX Team NCSX Conceptual Design Review Princeton, NJ May 21, 2002.

7

The NCSX Conceptual Design Effort Has Produced a Sound Basis on Which to Proceed

NCSX Conceptual Design Report documents…

• Design

• Plans

• Cost and schedule

• Management

Page 8: NCSX Project Overview Hutch Neilson, NCSX Project Manager For the NCSX Team NCSX Conceptual Design Review Princeton, NJ May 21, 2002.

8

A Conceptual Design Meeting NCSX Mission Requirements Has Been Developed

• Magnets provide required physics properties (stability, surface quality,

quasi-axisymmetry), are practical to build, and can be assembled over

vacuum vessel.

• Provides access for heating, diagnostics, pumping, first wall, personnel.

• Delivers required physics flexibility, startup scenario, B-field strength,

current, and pulse length with adequate engineering margins (structural,

thermal, thermo-hydraulic).

• Risk mitigation measures are being taken. Manufacturing studies by

industry were especially valuable:

– High interest in modular coils and vacuum vessel by capable suppliers.

– Their feedback improved our designs, fabrication plans, and estimates.

Page 9: NCSX Project Overview Hutch Neilson, NCSX Project Manager For the NCSX Team NCSX Conceptual Design Review Princeton, NJ May 21, 2002.

9

NCSX Plasma and Magnets

Page 10: NCSX Project Overview Hutch Neilson, NCSX Project Manager For the NCSX Team NCSX Conceptual Design Review Princeton, NJ May 21, 2002.

10

Vacuum Vessel

Page 11: NCSX Project Overview Hutch Neilson, NCSX Project Manager For the NCSX Team NCSX Conceptual Design Review Princeton, NJ May 21, 2002.

11

Completed Stellarator Core

Page 12: NCSX Project Overview Hutch Neilson, NCSX Project Manager For the NCSX Team NCSX Conceptual Design Review Princeton, NJ May 21, 2002.

12

NCSX Will Be Sited in the PLT / PBX-M Test Celland re-use PBX-M Neutral Beams and Vacuum Pumps

Designed to accept all 4 beams; 2 will be installed at first plasma.

Site is being cleared now with excess facilities disposal funds.

Page 13: NCSX Project Overview Hutch Neilson, NCSX Project Manager For the NCSX Team NCSX Conceptual Design Review Princeton, NJ May 21, 2002.

13

NCSX Also Uses D-Site Facilities

TFTR TEST Cell(NCSX sub-

assembly area)

NCSX Test Cell

D-Site Power Supplies (NCSX

Magnets)

NCSX Control Room

NCSX Magnet Power Cables

D-Site Motor-

Generators

Page 14: NCSX Project Overview Hutch Neilson, NCSX Project Manager For the NCSX Team NCSX Conceptual Design Review Princeton, NJ May 21, 2002.

14

Fabrication Project Scope: Equipment Needed at First Plasma and Installation of 2 Existing Neutral Beams

Stellarator Core (R = 1.4 m). • External magnets, vacuum vessel, limiters, cryostat.Peak ratings: B ≤ 2 T, Ip ≤ 350 kA. tflat =  0.3 s @B=1.7 T / 1.7 s @B=1.2 T

Heating, Fueling, Vacuum (Auxiliary Systems)• Neutral beam injection (3 MW) installed; gas injection, torus vacuum

pumping, glow discharge cleaning.

Diagnostics• Magnetics, interferometer, visible cameras, magnetic field mapping equip.

Power Systems• Magnet power for B = 1.5 T, Ip = 154 kA scenario; C–site AC power.

Central I&C• Facility control and timing, computer network, data acquisition, control room.

Facility Systems• Water, cryogenics, bakeout.

Integrated System Testing and First Plasma

Page 15: NCSX Project Overview Hutch Neilson, NCSX Project Manager For the NCSX Team NCSX Conceptual Design Review Princeton, NJ May 21, 2002.

15

Project Cost is Estimated to be $72M

Contingencies are estimated at the subsystem level, based on

technical, cost, and schedule risk factors.

Page 16: NCSX Project Overview Hutch Neilson, NCSX Project Manager For the NCSX Team NCSX Conceptual Design Review Princeton, NJ May 21, 2002.

16

PPPL Overhead Rates Were Approved in the Past Week

Slight changes from assumptions at press time. Bottom line unchanged.

Current estimate will be presented.

Costs in $M

Page 17: NCSX Project Overview Hutch Neilson, NCSX Project Manager For the NCSX Team NCSX Conceptual Design Review Princeton, NJ May 21, 2002.

17

Fabrication Project Can Be Completed by March, 2007

Page 18: NCSX Project Overview Hutch Neilson, NCSX Project Manager For the NCSX Team NCSX Conceptual Design Review Princeton, NJ May 21, 2002.

18

Project Funding Requirements for Mar. ’07 1st Plasma

Funding drivers:• FY-03: design and mfg. development for critical components • FY-04: award major fabrication contracts.

0.00

5.00

10.00

15.00

20.00

25.00

30.00

2003 2004 2005 2006 2007

Fiscal Year  

Contingency Incl. in B/A & B/O

B/O (Spending Planned - $72M)

B/A (Funding Needed - $72M)

B/A (DOE Guidance - $69M)

Page 19: NCSX Project Overview Hutch Neilson, NCSX Project Manager For the NCSX Team NCSX Conceptual Design Review Princeton, NJ May 21, 2002.

19

Research Preparations Will Proceed in Parallel with the Fabrication Project

Scope: prepare analytical and hardware tools needed beyond first

plasma and flux-surface mapping. (Follows NSTX approach.)

• Maintain physics connections, collaborations with other stellarator programs.

• Design and begin fabrication of upgrade hardware (diagnostics for Ohmic phase;

PFCs, 350 C bake, internal trim coils, and diagnostics for NBI phase).

• Plan research program in more detail and start building team as operation nears.

Page 20: NCSX Project Overview Hutch Neilson, NCSX Project Manager For the NCSX Team NCSX Conceptual Design Review Princeton, NJ May 21, 2002.

20

NCSX Program Funding Requirements FY03-06

Funding peak = $21.1M (vs DOE guidance of $18.6M).• Completes project on desired schedule (March, 2007), ready to proceed

with research program.

0.00

5.00

10.00

15.00

20.00

25.00

30.00

2003 2004 2005 2006 2007 2008

Fiscal Year   

Research PrepEstimate

NCSX Program Total(DOE Guidance)

NCSX Program Total

Fab. Project B/AEstimate

* Operations funding starts in FY-2007.

Page 21: NCSX Project Overview Hutch Neilson, NCSX Project Manager For the NCSX Team NCSX Conceptual Design Review Princeton, NJ May 21, 2002.

21

The Project Organization is Functioning Well

• DOE / Contractor “Integrated Project Team” is working well.– Members from DOE-PAO, DOE-OFES, PPPL, ORNL.

– Has met at least monthly since 2000.

– Planned PVR and this review. Prepared DOE acquisition documents.

• Successful PPPL-ORNL partnership will continue.– Has worked well since 1998, developed physics basis, conceptual design.

– Responsibilities for fabrication project are clearly defined.

– Strong upper management support at both Labs.

• Will follow management approach that has been successful in PPPL–managed fusion projects, e.g., TFTR D&D, NSTX.

– Central project management and work authorization system.

– All procurement and QA / QC support through PPPL.

– Line management responsible for E.S.&H.; supported by E.S.&H. professionals.

– Approved (and proven) PPPL procedures for doing work safely.

– NCSX Project Execution Plan issued as part of Conceptual Design Report.

Page 22: NCSX Project Overview Hutch Neilson, NCSX Project Manager For the NCSX Team NCSX Conceptual Design Review Princeton, NJ May 21, 2002.

22

NCSX Project Organization

Page 23: NCSX Project Overview Hutch Neilson, NCSX Project Manager For the NCSX Team NCSX Conceptual Design Review Princeton, NJ May 21, 2002.

23

DOE Acquisition Process: Next Step is CD-1, July, ’02• CD-1 deliverables are in preparation. Most, including draft Acquisition

Execution Plan, are included in C.D.R.

• NEPA process is under way.

Page 24: NCSX Project Overview Hutch Neilson, NCSX Project Manager For the NCSX Team NCSX Conceptual Design Review Princeton, NJ May 21, 2002.

24

Production of Modular Coils and Vacuum VesselNeeds to Start Early in FY-04 to Maintain Schedule

Project Schedule:

• Perform preliminary design, final design, and manufacturing development for these components in FY–03.

• Conduct DOE Preliminary Design Review of NCSX in May, 2003.

– Review overall design maturity and establish performance baseline for CD-2.

• Start procurement process for modular coil production late in FY-03.

• Award production contracts for modular coil forms (Nov. ’03), vessel (Apr. ’04).

CDs for these components need to be advanced to stay on schedule.

• At CD-1 (July, ’02), we need authorization (“CD-2”) to be able to start F.D. of the modular coils (March,’03) and vacuum vessel (May, ’03).

• At CD-2 (June, ’03), we need authorization (“CD-3”) to be able to start production of the modular coils and vacuum vessel.

• At CD-3 (April, ’04), we need approval to begin fabrication of remaining components.

Page 25: NCSX Project Overview Hutch Neilson, NCSX Project Manager For the NCSX Team NCSX Conceptual Design Review Princeton, NJ May 21, 2002.

25

Summary / Preview : Status of NCSX

• The NCSX conceptual design provides a sound technical basis on which to proceed.

• Physics and engineering analyses show that the design meets mission requirements with adequate margins (Charge #1 and #2).

• Manufacturer input has boosted confidence in the constructability of the design, R&D plans, manufacturing plans, and estimates. (#2)

• Bottoms-up estimates show the project can be completed by March, 2007 at a cost of $72M, with reasonable contingencies (#3).

• A successful project organization is well established. The management plans for NCSX follow proven models for safe and successful project execution (#3, #4).

• Research preparations and plans are commensurate with needs. (#5)

• PVR issues have been resolved, commensurate with needs. (#1)