NCSX G. Gettelfinger for the NCSX Engineering Team November 10, 2004 NCSX Coil Test Facility Single...

21
NCSX G. Gettelfinger for the NCSX Engineering Team November 10, 2004 NCSX Coil Test Facility Single Phase LN 2 Mechanical/Plumbing Final Design Review

Transcript of NCSX G. Gettelfinger for the NCSX Engineering Team November 10, 2004 NCSX Coil Test Facility Single...

Page 1: NCSX G. Gettelfinger for the NCSX Engineering Team November 10, 2004 NCSX Coil Test Facility Single Phase LN 2 Mechanical/Plumbing Final Design Review.

NCSX

G. Gettelfingerfor the NCSX Engineering Team

November 10, 2004

NCSX Coil Test Facility Single Phase LN2

Mechanical/Plumbing Final Design Review

Page 2: NCSX G. Gettelfinger for the NCSX Engineering Team November 10, 2004 NCSX Coil Test Facility Single Phase LN 2 Mechanical/Plumbing Final Design Review.

November 10, 2004 NCSX Coil Test FacilityMechanical/Plumbing FDR

G. Gettelfinger 2

NCSXPREAMBLE

• The coil test facility (CTF) has had previous design sessions and reviews focusing on:– Overall ES&H themes– AC/DC high-amperage power– Low-level controls– Data Acquisition

• Electrical construction and sequencing interlocks are complete

• Today’s review focuses on plumbing

Page 3: NCSX G. Gettelfinger for the NCSX Engineering Team November 10, 2004 NCSX Coil Test Facility Single Phase LN 2 Mechanical/Plumbing Final Design Review.

November 10, 2004 NCSX Coil Test FacilityMechanical/Plumbing FDR

G. Gettelfinger 3

NCSXCHARGE FOR PLUMBING FDR

• Assure that:– [1] the requirements are documented;– [2] the design satisfies the requirements;– [3] the design has appropriate safety features

incorporated; and – [4] the design documentation is adequate and

appropriate to complete the installation.

Page 4: NCSX G. Gettelfinger for the NCSX Engineering Team November 10, 2004 NCSX Coil Test Facility Single Phase LN 2 Mechanical/Plumbing Final Design Review.

November 10, 2004 NCSX Coil Test FacilityMechanical/Plumbing FDR

G. Gettelfinger 4

NCSX

Coil Test Facility Thermo-Hydraulic Requirements

• GRD Rev.2 suggests that 3.4e6J must be removed from a particular modular coil in 15 minutes. The CTF must support this operating scenario.

• P. Goranson offers that the LN2 temperature will likely not exceed 95.4 K. He further expects 1.7 atmos. (25psid) pressure drop max. across the coil at about 6.2 gpm of liquid flow

• The CTF must provide single phase flow to a particular coil.

• All ES&H themes must be fully supported

Page 5: NCSX G. Gettelfinger for the NCSX Engineering Team November 10, 2004 NCSX Coil Test Facility Single Phase LN 2 Mechanical/Plumbing Final Design Review.

November 10, 2004 NCSX Coil Test FacilityMechanical/Plumbing FDR

G. Gettelfinger 5

NCSXCENTRIFUGAL PUMP

• A variable frequency-driven, existing-design production pump will be delivered on about Dec. 15.

• This can deliver up to about 10 gpm at 6500 rpm. The required scenario is supported at about 6100 rpm moving 7 gpm in the face of 35 psid (plenty of capability)

Page 6: NCSX G. Gettelfinger for the NCSX Engineering Team November 10, 2004 NCSX Coil Test Facility Single Phase LN 2 Mechanical/Plumbing Final Design Review.

November 10, 2004 NCSX Coil Test FacilityMechanical/Plumbing FDR

G. Gettelfinger 6

NCSXP&ID FOR COIL TEST FACILITY

Page 7: NCSX G. Gettelfinger for the NCSX Engineering Team November 10, 2004 NCSX Coil Test Facility Single Phase LN 2 Mechanical/Plumbing Final Design Review.

November 10, 2004 NCSX Coil Test FacilityMechanical/Plumbing FDR

G. Gettelfinger 7

NCSX

• The design allows for:– Warm/cold cryostat purge– Warm/cold line/load purge– Suction pressure maintenance (63.8 psig for

95K)– Batch-in of replacement liquid (for minor

leaks)– “Fill the bucket” flow measurement

P&ID FOR COIL TEST FACILITY

Page 8: NCSX G. Gettelfinger for the NCSX Engineering Team November 10, 2004 NCSX Coil Test Facility Single Phase LN 2 Mechanical/Plumbing Final Design Review.

November 10, 2004 NCSX Coil Test FacilityMechanical/Plumbing FDR

G. Gettelfinger 8

NCSXPRESSURE LEVELS / CALCULATIONS

• 64 psig Suction for 95K ops• 91 psig Likely pump press. for coil drop

plus pipe drop• 150 psig Relief valve level• 200 psig Recommended to coil engineers on

as test pressure for cooling circuits – 33% above auto action

limit• 401 psig B31.3 limit for tank design• 947 psig Non-ASME limit for G-10/11 1” pipe• 1,120 psig B31.3 limit for ¾”-M tube (Hx)• 1,390 psig B31.3 limit for 1”-L tube (majority)

Page 9: NCSX G. Gettelfinger for the NCSX Engineering Team November 10, 2004 NCSX Coil Test Facility Single Phase LN 2 Mechanical/Plumbing Final Design Review.

November 10, 2004 NCSX Coil Test FacilityMechanical/Plumbing FDR

G. Gettelfinger 9

NCSXTANK(S) DESIGN

• Schedule 10S 12-inch 304SS pipe with 10S caps form the hull of the tank.– Full penetration bevel-groove welds with backing

• Welded half couplings and half nipples comprise the outlets.– ¼’ leg fillet welds

Page 10: NCSX G. Gettelfinger for the NCSX Engineering Team November 10, 2004 NCSX Coil Test Facility Single Phase LN 2 Mechanical/Plumbing Final Design Review.

November 10, 2004 NCSX Coil Test FacilityMechanical/Plumbing FDR

G. Gettelfinger 10

NCSX

FIRST LOAD – PLANAR RACETRACK COIL

• Planar racetrack coil will first be used

• Next in queue: Twisted racetrack coil

Page 11: NCSX G. Gettelfinger for the NCSX Engineering Team November 10, 2004 NCSX Coil Test Facility Single Phase LN 2 Mechanical/Plumbing Final Design Review.

November 10, 2004 NCSX Coil Test FacilityMechanical/Plumbing FDR

G. Gettelfinger 11

NCSXHEAT EXCHANGER DESCRIPTION

• Boiling heat transfer below critical heat flux

• Calculation – A non-iterative method suggests that ONE six-foot bare ¾” copper tube immersed in LN2 may be adequate -6.3e6 J in 15 minutes (3.4e6 J required)

• Design - overkill – strong is never wrong– 18-feet of finned tube per path($40/8 ft!)

Page 12: NCSX G. Gettelfinger for the NCSX Engineering Team November 10, 2004 NCSX Coil Test Facility Single Phase LN 2 Mechanical/Plumbing Final Design Review.

November 10, 2004 NCSX Coil Test FacilityMechanical/Plumbing FDR

G. Gettelfinger 12

NCSXHx GRAPHICS (1of5)

•Hx contains 3 independent paths

Page 13: NCSX G. Gettelfinger for the NCSX Engineering Team November 10, 2004 NCSX Coil Test Facility Single Phase LN 2 Mechanical/Plumbing Final Design Review.

November 10, 2004 NCSX Coil Test FacilityMechanical/Plumbing FDR

G. Gettelfinger 13

NCSX

•Each of 3 paths has 18-feet of 2 1/8 aluminum fins

Hx GRAPHICS (2of5)

Page 14: NCSX G. Gettelfinger for the NCSX Engineering Team November 10, 2004 NCSX Coil Test Facility Single Phase LN 2 Mechanical/Plumbing Final Design Review.

November 10, 2004 NCSX Coil Test FacilityMechanical/Plumbing FDR

G. Gettelfinger 14

NCSXHx GRAPHICS (3of5)

•Bundles are provided with gravity supports

Page 15: NCSX G. Gettelfinger for the NCSX Engineering Team November 10, 2004 NCSX Coil Test Facility Single Phase LN 2 Mechanical/Plumbing Final Design Review.

November 10, 2004 NCSX Coil Test FacilityMechanical/Plumbing FDR

G. Gettelfinger 15

NCSXHx GRAPHICS (4of5)

•Support scheme has baffles to shroud upper assemblies from gas bubbles generated underneath

Page 16: NCSX G. Gettelfinger for the NCSX Engineering Team November 10, 2004 NCSX Coil Test Facility Single Phase LN 2 Mechanical/Plumbing Final Design Review.

November 10, 2004 NCSX Coil Test FacilityMechanical/Plumbing FDR

G. Gettelfinger 16

NCSXHx GRAPHICS (5of5)

•3-path assembly resides in an aluminum tub to contain secondary, boiling fluid

Page 17: NCSX G. Gettelfinger for the NCSX Engineering Team November 10, 2004 NCSX Coil Test Facility Single Phase LN 2 Mechanical/Plumbing Final Design Review.

November 10, 2004 NCSX Coil Test FacilityMechanical/Plumbing FDR

G. Gettelfinger 17

NCSXSKID ARRANGEMENT

• Shows bottom insulation, tanks, Hx, valve board, elec cab, pump, skid weldment

• Insulation is Dow Trymer 2000 (K=.19 BTU/in*hr/ft2)

Page 18: NCSX G. Gettelfinger for the NCSX Engineering Team November 10, 2004 NCSX Coil Test Facility Single Phase LN 2 Mechanical/Plumbing Final Design Review.

November 10, 2004 NCSX Coil Test FacilityMechanical/Plumbing FDR

G. Gettelfinger 18

NCSXINDUSTRIAL HYGIENE TOPICS

•Silver/Copper/Phosphorous brazing alloy will be used (many times).

•No cadmium

•Expanding polyurethane foam insulation will be used in CLOSE COORDINATION with IH personnel.

Page 19: NCSX G. Gettelfinger for the NCSX Engineering Team November 10, 2004 NCSX Coil Test Facility Single Phase LN 2 Mechanical/Plumbing Final Design Review.

November 10, 2004 NCSX Coil Test FacilityMechanical/Plumbing FDR

G. Gettelfinger 19

NCSXMECHANICAL SAFETY TOPICS

•Liquid Oxygen/Liquid Air Hazard

•LOx and LAir both condense above 77K

•Annulus between field lines and insulation shall be filled with expanding polyurethane foam

•Boil-off of N2 in conjunction with trap keeps cryostat free of atmospheric air

•Pressure Safety

•All components have adequate strength at the 150 psig relief pressure

•Every isolable zone provided with ASME relief valve

Page 20: NCSX G. Gettelfinger for the NCSX Engineering Team November 10, 2004 NCSX Coil Test Facility Single Phase LN 2 Mechanical/Plumbing Final Design Review.

November 10, 2004 NCSX Coil Test FacilityMechanical/Plumbing FDR

G. Gettelfinger 20

NCSXCOST AND SCHEDULE

• $10K pump is accounted for (due Dec 15)

• $12K additional M&S expected

• NCSX schedule shows ops in late Jan ’05

• Eng Dept to consider resource availability for Fab & Ops

• Ring-out late Feb ’05 seems plausible

Page 21: NCSX G. Gettelfinger for the NCSX Engineering Team November 10, 2004 NCSX Coil Test Facility Single Phase LN 2 Mechanical/Plumbing Final Design Review.

November 10, 2004 NCSX Coil Test FacilityMechanical/Plumbing FDR

G. Gettelfinger 21

NCSXCTF MECH/PLUMBING, SUMMARY

• Requirements are stated

• Design supports flow, heat removal objectives & fully rings out single-phase cooling concept

• Safety themes dilligently considered and acted upon

• P&ID, device/line lists, and models are ready for shop.