Engineering Consultants for Loan 2856 BAN: Dhaka Chittagong Expressway Public Private Partnership Design Project Desember 2017 Doc. No. 5022160-034.2-002.2 SMEC International Pty Ltd in Joint Venture with Stantec Australia Pty Ltd with PT. Infra Tama Yakti, PT. SMEC Denka Indonesia, PT. Amurwa International and PT. Widyagraha Asana as Sub-Consultants LAPORAN BULANAN NO. 2

Transcript of LAPORAN BULANAN NO. 2 -...

Engineering Consultants for Loan 2856 BAN: Dhaka Chittagong Expressway Public Private Partnership Design Project

Desember 2017 Doc. No. 5022160-034.2-002.2

SMEC International Pty Ltd in Joint Venture with Stantec Australia Pty Ltd

with

PT. Infra Tama Yakti, PT. SMEC Denka Indonesia,

PT. Amurwa International and PT. Widyagraha Asana as Sub-Consultants

LAPORAN BULANAN NO. 2

Project Name: Metropolitan Sanitation Management Investment Project

Project Number: 5022160

Report for Directorate General of Human Settlements, Ministry of Public Works and Housing

Report Laporan Bulanan No 2

PREPARATION, REVIEW AND AUTHORISATION

Revision # Date Prepared by Reviewed by Approved for Issue

by

1 30/11/17 BS BH BH

2 14/2/18 BS BH BH

ISSUE REGISTER

Distribution List Date Issued Number of Copies

CPMU 19th Feb 2018 27 Hardcopies

SMEC International Pty Ltd in Joint Venture with Stantec Australia Pty Ltd with PT Infratama Yakti, PT SMEC Denka Indonesia, PT. Amurwa International and PT. Widyagraha Asana as Sub-Consultants

Jakarta: NHB Building, Jl. Melawai Raya No. 14 Kebayoran Baru, Jakarta Selatan 12160 Ph. 021 720 6334

The information within this document is and shall remain the property of the Consultant.

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 i

Table of Contents 1 Pendahuluan ................................................................................................................................... 1

1.1 Deskripsi Proyek ...................................................................................................................... 1

1.1.1 Pengaturan Kontrak ........................................................................................................ 1

1.2 Pemahaman Proyek ................................................................................................................ 1

2 Kemajuan Proyek ............................................................................................................................ 2

2.1 Laporan Kemajuan .................................................................................................................. 2

2.2 Jadwal ...................................................................................................................................... 2

2.3 Mobilisasi ................................................................................................................................ 2

2.4 Kantor Proyek .......................................................................................................................... 4

3 Aktivitas Bulanan ............................................................................................................................. 5

3.1 Rapat ....................................................................................................................................... 5

3.1.1 Sosialisasi IPAL Losari ...................................................................................................... 5

3.1.2 Workshop – Penyusunan Dokumen Anggaran Biaya dan PQ Document Contract C

Makassar ......................................................................................................................................... 7

3.1.3 Rapat Pembahasan Laporan Pendahuluan dan Laporan Kemajuan Bulanan ................. 7

4 Rencana Kegiatan ............................................................................................................................ 8

4.1 Rencana Kerja ......................................................................................................................... 8

4.2 Rapat Proyek dan Workshop .................................................................................................. 9

4.3 Kunjungan Lapangan ............................................................................................................... 9

4.4 Laporan-laporan ...................................................................................................................... 9

5 Keuangan ....................................................................................................................................... 10

5.1 Keuangan Proyek .................................................................................................................. 10

5.2 Kegiatan yang direncanakan ................................................................................................. 11

5.2.1 Status keseluruhan ........................................................................................................ 11

5.2.2 Pekerjaan yang Dibiayai Dengan Pinjaman ADB ........................................................... 11

5.2.3 Alokasi Anggaran dan Pengeluaran .............................................................................. 12

5.2.4 Pengadaan dan Kontrak ................................................................................................ 13

5.2.5 Permasalahan Utama .................................................................................................... 13

App A –Rencana Manajemen Risiko Proyek MSMIP ............................................................................. 15

App B –Status Alokasi Anggaran ........................................................................................................... 19

App C – Jadwal Proyek .......................................................................................................................... 24

App D – Staffing Schedules ................................................................................................................... 28

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 ii

App E – Risalah Rapat ............................................................................................................................ 33

List of Tables

Tabel 2.1: Rencana Mobilisasi Staf ......................................................................................................... 2

Tabel 2.2: Rencana Susunan Staf (berdasarkan Adendum No. 1) .......................................................... 3

Tabel 4.1: Rencana Kerja dan Aktivitas Konsultan .................................................................................. 8

Tabel 4.2: Rapat yang Direncanakan/Direkomendasikan ....................................................................... 9

Tabel 5.1 : Form A – Deskripsi Proyek – Pinjaman ADB ........................................................................ 10

Tabel 5.2: Form B – status dan progress ADB Loan ............................................................................. 11

Tabel 5.3: Form C – Lingkup Pekerjaan yang dibiayai Pinjaman ADB ................................................... 12

List of Figures

Figure 3.1 – Sosialisasi Pengembangan IPAL Losari di Makassar ............................................................ 5

Figure 3.2 – Sosialisasi Pengembangan IPAL Losari di Makassar ............................................................ 6

Figure 3.3 – Sosialisasi Pengembangan IPAL Losari di Makassar ............................................................ 6

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 iii

Acronyms and Abbreviations

ADB Asian Development Bank ADF Asian Development Fund APBD Anggaran Pendapatan dan Belanja Daerah/Regional Government

Budget APBN Anggaran Pendapatan dan Belanja Negara/ National

Government Budget AusAid Australian Agency for International Development BLH Biro/Badan Lingkungan Hidup/Environmental Agency BLUD Badan Layanan Umum Daerah/Regional Public Service Agency CBD Central Business District CDTA Capacity Development Technical Assistance CEMP Contractor’s Environmental Management Plan CPMU Central Project Management Unit CSS City Sanitation Strategy DAK Dana Alokasi Khusus/Special Allocation Fund DAU Dana Alokasi Umum/General Allocation Fund DD Due Diligence DED Detailed Engineering Design DESD Directorate of Environmental and Sanitation Development DFAT Department of Foreign Affairs and Trade (Australia), formerly

AusAid DGHS Directorate General of Human Settlements (Cipta Karya) DKK Dinas Kebersihan Kota/City Sanitation Agency DMF Design and Monitoring Framework EA Executing Agency EIA Environmental Impact Assessment EMP Environmental Management Plan FOPIP Financial and Operating Performance Improvement GIS Geographic Information System GoI Government of Indonesia HH Household IMB Ijin Mendirikan Bangunan/Building Permit IndII Indonesia Infrastructure Initiative ICB International Competitive Bidding IEE Initial Environmental Examination INDII Indonesian Infrastructure Initiative IPAL Instalasi Pengolahan Air Limbah/Wastewater Treatment Plant IPLT Instalasi Pengolahan Lumpur Tinja/Septage Treatment Plant IUWASH Indonesia Urban Water, Sanitation and Hygiene Project (United

States International Agency for Development) LARAP Land Acquisition and Resettlement Action Plan LIBOR London Interbank Offered Rate LPMU Local Project Management Unit MIS Management Information System MLD Megalitres per Day MOF Ministry of Finance MOHA Minister of Home Affairs MPWH Ministry of Public Works and Housing MSMHP Metropolitan Sanitation Management and Health Project

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 iv

MSMIP Metropolitan Sanitation Management Investment Project NCB National Competitive Bidding NGO Non Government Organization O&M Operation and Maintenance PAM Project Administration Manual PIU Program Implementation Unit PISC Project Implementation Support Consultant PPMU Provincial Project Management Unit POKJA Kelompok Kerja/Working Group PPLP PPLP Direktorat) Pengembangan Penyehatan Lingkungan Pemukiman/

Directorate of Environmental Sanitation Development, Directorate General of Human Settlements, Ministry of Public Works and Housing

PPP Public Private Partnership PPSP Program Percepatan Sanitasi Permukiman/Acceleration of Urban

Sanitation Development Program PPTA Project Preparation Technical Assistance PROLEGDA Program Legislasi Daerah/Local Legislation Procedure PUPR Ministry of Public Works and Housing (Kementerian Pekerjaan

Umum dan Perumahan Rakyat) PSC sAIIG

Project Support Consultants Australia Indonesia Infrastructure Grants for Sanitation

SANIMAS Program Sanitasi Berbasis Masyarakat/Community Based Sanitation Program

SATKER Satuan Kerja/Work Unit SDO Service Delivery Organization SPS SOP

Safeguards Policy Statement Standard Operational Procedure

SSK Strategi Sanitasi Kota/City Sanitation Strategy UPTD Unit Pelaksana Teknis Daerah/Local Government Technical

Implementation Unit USRI Urban Sanitation and Rural Infrastructure Support to PNPM

Mandiri Project (ADB funded) WA Withdrawal Application WWTP or WWTW Wastewater Treatment Plant or Works

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 1

1 Pendahuluan

1.1 Deskripsi Proyek

1.1.1 Pengaturan Kontrak

Pada tanggal 2 Oktober 2017, Project Implementation Support Consultant (PISC) Metropolitan

Sanitation Management Investment Project Loan 3123-INO. Ditunjuk oleh Direktorat Jendral Cipta

Karya untuk melaksanakan tugas-tugas berdasarkan Kontrak HK.02.03/MSMIP-KONS/X/11/2017. PISC

terdiri dari Konsultan utama SMEC International Pty Ltd yang bekerjasama dengan Stantec Australia

Pty Ltd (ex MWH) dan berasosiasi dengan sub-konsultan : PT. Infra Tama Yakti (ITY), PT. SMEC Denka

Indonesia, PT. Amurwa International dan PT. Widya Graha Asana (WGA).

1.2 Pemahaman Proyek

PISC akan bertugas untuk melakukan review desain dan supervisi konstruksi untuk sistem pengelolaan

air limbah pertama skala kota di Jambi, Makasar, dan Pekanbaru, yang juga membantu dalam aspek

Lingkungan, Sosial dan Keselamatan dan aspek LARAP pekerjaan selama masa pelaksanaan.

Desain-desain Jaringan Perpipaan Air Limbah dan IPAL yang telah disusun sebelumnya oleh konsultan-

konsultan lain untuk tiga kota tersebut yang akan direvew lebih jauh oleh PISC. Mengacu pada hasil

kajian awal dari dokumen perencanaan yang ada, PISC akan membuat perubahan-perubahan

substansial dan terukur yang diperlukan dan mereview desain kuat yang dapat digunakan untuk

proses Pelelangan International (ICB) atau Lelang Nasional (NCB) khususnya Instalasi Pengolahan Air

Limbah (IPAL) dan Jaringan Perpipaan Air Limbah yang akan dibiayai melalui porsi Pinjaman ADB.

Setelah dokumen desain dan dokumen lelang selesai disiapkan, maka dilanjutkan dengan proses

lelang dan tahap Konstruksi selanjutnya sudah bisa dimulai. PISC akan menyediakan jasa supervisi

konstruksi untuk pembangunan jaringan perpipaan air limbah dan IPAL untuk Kota Jambi, Makassar

dan Pekanbaru.

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 2

2 Kemajuan Proyek

2.1 Laporan Kemajuan

Laporan bulanan ini meliputi periode antara tanggal 2 November dengan 2 Desember 2017 dan

menyediakan informasi pada DJCK mengenai kemajuan proyek selama tanggal-tanggal tersebut.

2.2 Jadwal

PISC saat ini bekerja dengan program-program untuk tiap kota yang ada dalam Appendix D dari

dokumen ini. Proyek saat ini berjalan sesuai jadwal.

2.3 Mobilisasi

Selama Bulan Kedua proyek, PISC terus mendefinisikan proyek ini melalui tinjauan awal mereka. Konsultan telah menyediakan bagan organisasi dan jadwal sumber daya yang mengacu pada Addendum No. 1, yang dianggap sebagai keterampilan yang diperlukan untuk menyelesaikan pekerjaan. Selama periode peninjauan ulang Addendum ini, telah diakui bahwa proyek memerlukan kemajuan dan dengan demikian PISC telah meminta secara tertulis pada CPMU jika ada staf yang cocok dengan kriteria di Addendum, bukannya di kontrak orisinil, dibutuhkan untuk dimobilisasikan. Pada saat yang sama, staf yang akan dimobilisasi sesuai kontrak juga akan dimobilisasikan. Tabel 2.1 dan 2.1 mengilustrasikan status staf PISC saat ini pada proyek.

Tabel 2.1 mengilustrasikan rencana pemulaian staf hingga saat ini (berdasarkan kontrak).

Tabel 2.1 Rencana Mobilisasi Staf

Bulan Penempatan Mulai Berakhir

October Deputy Team Leader Sudah dimulai January 2020

Office Manager Sudah dimulai January 2020

Bilingual Secretary Mulai 27 November 2017 January 2020

GIS It Support Belum dikonfirmasi January 2020

Office Boy Sudah dimulai January 2020

Guard 1 Belum Dibutuhkan January 2020

Guard 2 Belum dibutuhkan January 2020

November Financial Management Specialist

Sudah dimulai April 2018

Sewerage Engineer Akan dimulai - 4 December 2017

January 2018

Geotechnical Specialist Akan Dimulai - 4 December 2017

December 2017

MIS Specialist Belum dikonfirmasi June 2018

Engineering Drafting Support

Sudah dimulai April 2018

1. CV untuk Accounting Specialist diserahkan ke CPMU pada tanggal 24 November 2017 –

Disetujui – Mulai bekerja 14 Desember 2017

2. CV untuk Bilingual Secretary diserahkan ke CPMU pada tanggal 20 November 2017 – Disetujui

– Mulai bekerja 27 November 2017

3. Engineering Support / Drafting memulai pada tanggal 27 November 2017

4. Sewerage Engineer memulai pada tanggal 4 Desember 2017

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 3

5. Structural Engineer memulai pada tanggal 4 Desember 2017

6. Geotechnical Engineer memulai pada tanggal 4 Desember 2017

7. Kantor yang digunakan SMEC pada saat ini adalah gedung yang sama dengan gedung utama

dan Penjaga yang dipekerjakan adalah yang sedang bekerja saat ini.

8. Wawancara untuk GIS/IT Support dan Engineering Support/Drafting akan diadakan dalam

minggu tersebut dimulai dari tanggal 27 November 2017

Adendum No.1 mengilustrasikan rencana berbeda dengan kontrak dan ini dijabarkan dalam table 2.2

di bawah ini.

Tabel 2.2 Rencana Susunan Staf (berdasarkan Adendum No. 1)

Bulan Penempatan Mulai Berakhir

October Senior Infrastructure Specialist

Dimulai January 2018

Office Manager Dimulai January 2020 Deputy Team Leader Dimulai January 2020

Office Boy Dimulai January 2020

November Financial Management Specialist

Dimulai April 2018

Cost Estimator (Makassar) Dimulai January 2018 Surveyor (Makassar) Dimulai January 2018 Bilingual Secretary Dimulai January 2020

CAD Draughter Dimulai January 2020

December MIS Specialist (Nat) Belum Teridentifikasi First period until July 2018

Electrical Engineer (Nat) Indiarto Budi –Dimulai tanggal 4 Desember

First Period until January 2018

Benefit Monitoring Specialist (Nat)

Treesnowati –Dimulai tanggal 4 Desember

Intermittent until May 2018

Civil Engineer (Nat) Wildan –Dimulai tanggal 4 Desember

September 2018

Structural Engineer (Nat) Yan Haryardi –Dimulai tanggal 4 Desember

May 2018

Mechanical Engineer (Nat) Henry Pranadjaja –Dimulai tanggal 4 Desember

May 2018

Sewerage Engineer 1 (Nat) Firdaus –Dimulai tanggal 4 Desember

May 2018

Procurement and Contract Specilaist (Nat)

Yosef –Dimulai tanggal 4 Desember

April 2018

Accounting Specialist (Nat) Ermien Fatmajulia –Dimulai tanggal 14 Desember

January 2020

Bilingual Secretary (Nat) Devi Satriani –Dimulai tanggal 27 November

January 2020

GIS IT Support (Nat) Taufiq –Dimulai tanggal 2 Januari

January 2020

Engineering Drafting Support (Nat)

Menunggu konfirmasi January 2020

Guard 1 Menunggu konfirmasi January 2020

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 4

Bulan Penempatan Mulai Berakhir

Guard 2 Menunggu konfirmasi January 2020

Document Controller (Nat) Aries –Siap memulai January 2020

Technical Translator (Nat) Chandra Barnas –Siap memulai

January 2020

Administrator (PISC) Menunggu konfirmasi January 2020

Administrator (CPMU) Menunggu konfirmasi January 2020

Catatan: Jadwal staf untuk Kontrak dan Adendum ditampilkan di Apendiks E

Komentar-komentar mengenai jadwal Staf antara Mobilisasi dan Adendum 1

1. CV untuk Accounting Specialist diserahkan ke CPMU pada tanggal 24 November 2017 –

menunggu persetujuan dari PPK - Disetujui

2. CV untuk Billingual Secretary diserahkan ke CPMU pada tanggal 20 November 2017 –

menunggu persetujuan dari PPK - Disetujui

3. Engineering Support/Drafting memulai pada tanggal 27 November 2017

4. Dalam persetujuan untuk dilanjutkan, Civil Engineer, Procurement Contract Specialist dan

Geotechnical Engineer akan memulai pada tanggal 4 Desember.

5. Kantor yang saat ini digunakan oleh SMEC ada dalam satu gedung dengan kantor utama, dan

Penjaga yang sedang dipekerjakan saat ini adalah yang sedang bertugas.

6. Wawancara-wawancara untuk GIS/IT Support dan Engineering Support/Drafting akan

diadakan dalam minggu tersebut dimulai pada tanggal 27 November 2017

7. Wawancara untuk Document Controller, Administrator untuk CPMU dan Administrator untuk

PISC akan dilanjutkan sesuai persetujuan Adendum

2.4 Kantor Proyek

Pada tahapan awal awal, PISC sudah menyiapkan kantor-kantor untuk bekerja beserta

perlengkapannnya untuk mendukung Tim Operasional. Kantor terletak di NHB Building Lt. 4, Jl.

Melawai Raya No. 14, Kebayoran Baru.

Selanjutnya, PISC sudah menyiapkan sistem dokumen database/informasi. Data/informasi yang

diterima dari CPMU dan setiap Satuan Kerja PS-PLP, akan dikumpulkan dan disusun sedemikian rupa

agar mudah untuk diakses anggota tim dalam persiapan untuk mengulas proses desain dan sistem

pelaporan. Pihak konsultan juga memiliki akses ke database yang bersangkutan/dokumen

perencanaan khususnya untuk membantu desain agar sesuai dengan standar.

Demikian pula, pengaturan sistem komunikasi internal melalui telepon dan internet dilakukan untuk

mendukung kelancaran tugas konsultan sekaligus menjaga agar informasi dan data tetap rahasia dan

tidak tersebar hingga bisa digunakan oleh pihak lain

Konsorsium SMEC International saat ini senantiasa memperbarui kesiapan para tenaga ahli dan tenaga

pendukung yang sudah termasuk dalam kontrak, dan untuk mencari pengganti yang setidaknya setara

(terutama untuk Pemimpin Tim) untuk menggantikan tenaga ahli. CV milik Malcolm Ehrlich saat ini

sudah diserahkan ke CPMU untuk disetujui pada tanggal 31 Oktober 2017 namun posisinya masih

menunggu persetujuan.

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 5

3 Aktivitas Bulanan

3.1 Rapat

3.1.1 Sosialisasi IPAL Losari

Sosialisasi dilaksanakan pada hari Rabu, 14 Desember 2017. Perwakilan dari CPMU, PPK, PISC, dan

Satker / PPK, menghadiri pertemuan tersebut. Pembicara pada pertemuan tersebut adalah:

Suharsono Adi Broto (Kepala Sub Bagian Pengelolaan Air), Imbang Muryanto (Kepala Bappeda Bidang

Pengembangan Infrastruktur Kota Makassar), Selvi Hehanusa (Ahli Sanitasi IUWASH Plus Makassar)

dan Benny Sihaloho (Deputy TL PISC MSMIP).

Satker PS-PLP Provinsi Sulawesi Selatan akan memulai pembangunan saluran air limbah dan IPAL

untuk Kota Makassar. Sebagai langkah awal untuk mendapatkan dukungan para pihak terutama di

tingkat kota, Satker PS-PLP Provinsi Sulawesi Selatan sebagai pelaksana kegiatan di tingkat provinsi

serta bertanggung jawab dalam pembangunan saluran air limbah dan IPAL keduanya dibiayai secara

langsung. dari APBN 2017-2020, dana pinjaman ADB (Asian Development Bank) akan melakukan

sosialisasi. Rincian Sosialisasi IPAL Losari dapat dilihat di Risalah rapat (terlampir).

Gambar 3.1 - Sosialisasi Pengembangan IPAL Losari di Makassar

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 6

Gambar 3.2 - Sosialisasi Pengembangan IPAL Losari di Makassar

Gambar 3.3 - Sosialisasi Pengembangan IPAL Losari di Makassar

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 7

3.1.2 Workshop – Penyusunan Dokumen Anggaran Biaya dan PQ Document Contract C Makassar

Workshop ini dilakukan karena rencana Satker untuk memulai proses Pra-Kualifikasi untuk

Pembuangan Limbah Barat Laut yang didanai oleh APBN. Paket itu terbagi menjadi dua paket yaitu C1

dan C2. C1 terutama untuk Pumping Station, Main Trunk dan pressure pipes dan C2 terutama untuk

pipa Central / Secondary dan 1000 rumah tangga. Finalisasi OE akan dilakukan pada pertemuan formal

PU yang dihadiri oleh CPMU.

3.1.3 Rapat Pembahasan Laporan Pendahuluan dan Laporan Kemajuan Bulanan

Pertemuan kemajuan tersebut dilakukan untuk mengenalkan ahli baru PISC (Civil Engineer,

Mechanical Engineer and Benefit Monitoring Specialist) serta membahas rencana PISC untuk mulai

mempersiapkan situs web QPR dan Project.

PISC akan mempersiapkan lebih detail dan memperbarui jadwal untuk tiga kota berdasarkan

kunjungan lapangan dan diskusi PISC dengan pemangku kepentingan setempat. Itu termasuk rencana

PISC untuk melakukan survei Geoteknik dan Topografi di tiga kota

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 8

4 Rencana Kegiatan

4.1 Rencana Kerja

Tabel 4.1 menyediakan informasi mengenai rencana kegiatan untuk periode 22 Desember 2017 hingga

22 Januari 2018.

Table 4.1: Rencana Kerja dan Aktivitas Konsultan

Lokasi Aktivitas Tanggal

Makassar Rencana Investigasi Geoteknik 02/12/17

Meminta dan menerima Penawaran dan Persetujuan atas pekerjaan yang akan dimulai

08/12/17

Memulai pekerjaan fisik Investigasi Geoteknik 18/12/17

Perencanaan Survei Topografi 02/12/17

Meminta dan menerima penawaran dan meminta persetujuan untuk memulai pekerjaan

08/12/17

Estimasi Biaya untuk memperkirakan Biaya Kontrak 22/12/17

Persiapan Spesifikasi untuk Kontrak C 04/12/17 to 29/12/17

Penyusunan Dokumen Tender untuk Kontrak C 19/12/17 to 08/01/18

Ulasan IPAL 22/12/17

Review Jaringan dan Rumah Pompa 22/12/17

Pekanbaru Rencana Investigasi Geoteknik 02/12/17

Meminta dan menerima Penawaran dan Persetujuan atas pekerjaan yang akan dimulai

08/12/17

Memulai pekerjaan fisik Investigasi Geoteknik 18/12/17

Perencanaan Survei Topografi 02/12/17

Meminta dan menerima penawaran dan meminta persetujuan untuk memulai pekerjaan

08/12/17

Estimasi Biaya untuk memperkirakan Biaya Kontrak 25/12/17 to 19/01/18

Persiapan Spesifikasi untuk Kontrak C 04/12/17 to 29/12/17

Penyusunan Dokumen Tender untuk Kontrak C 22/12/17

Ulasan IPAL 22/12/17

Jambi Rencana Investigasi Geoteknik 22/12/17

Meminta dan menerima Penawaran dan Persetujuan atas pekerjaan yang akan dimulai

22/12/17

Memulai pekerjaan fisik Investigasi Geoteknik 02/12/17

Perencanaan Survei Topografi 08/12/17

Meminta dan menerima penawaran dan meminta persetujuan untuk memulai pekerjaan

18/12/17

Estimasi Biaya untuk memperkirakan Biaya Kontrak 02/12/17

Persiapan Spesifikasi untuk Kontrak C 08/12/17

Penyusunan Dokumen Tender untuk Kontrak C 25/12/17 to 19/01/18

Ulasan IPAL 04/12/17 to 29/12/17

Review Jaringan dan Rumah Pompa 22/12/17

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 9

4.2 Rapat Proyek dan Workshop

Tabel 4.2 menyediakan informasi mengenai rapat dan workshop yang direncanakan dan

direkomendasikan.

Tabel 4.2: Rapat yang Direncanakan/Direkomendasikan

Lokasi Aktivitas Tanggal

Jakarta Rapat Bulanan 22/12/17

Rapat Adendum 1 04/12/17

Rapat Proyek 2 mingguan 06/12/17

Rapat Proyek 2 mingguan 20/12/17

Rapat Mingguan PISC 05/12/17

Rapat Mingguan PISC 12/12/17

Rapat Mingguan PISC 19/12/17

Rapat Mingguan PISC 27/12/17

Makassar Lokakarya – Kontrak C 12/12/17

4.3 Kunjungan Lapangan

Brian Hayden dan Benny Sihaloho akan mengunjungi Makassar pada tanggal 12 Desember 2017 untuk

mengikuti lokakarya Kontrak C. Lokakarya ini akan berfokus untuk membagi Kontrak 3 menjadi dua

kontrak terpisah dan perkiraan biaya kedua Kontrak. Pelaksanaan yang sama akan dilakukan pada

Kontrak B untuk Makassar untuk melihat apakah mungkin untuk mebagi Kontrak lebih lanjut

berdasarkan pengadaan praktis. Selama kunjungan yang sama, PISC akan memberikan masukan untuk

presentasi kepada Pemerintah Daerah mengenai isu-isu Sosial dan Perlindungan Permukiman.

Tidak ada rencana kunjungan lapangan lainnya untuk bulan ini.

4.4 Laporan-laporan Laporan Bulanan dikumpulkan pada tanggal 2 Januari 2018.

Tidak ada Laporan lagi yang harus dikumpulkan bulan ini.

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 10

5 Keuangan

5.1 Keuangan Proyek

Tujuan Proyek Investasi Manajemen Sanitasi Metropolitan – MSMIP akan menyediakan Sistem Air

Limbah di Kota Jambi, Makassar dan Pekanbaru, dimana kota-kota ini saat ini tidak memiliki jaringan

perpipaan air limbah. Pinjaman proyek ditandatangani pada tanggal 31 Maret 2014 dengan sumber

pinjaman Pendanaan ADB sebesar $ 120,0 juta, dengan $ 80,0 juta berasal dari Sumber Pinjaman Biasa

/ OCR - No.3123 INO dan sisanya $ 40,00 juta dari Dana Infrastruktur ASEAN / AIF - No.8280. Alokasi

Anggaran juga diberikan oleh Pemerintah Pusat dan Daerah.

Tabel 5.1 : Form A – Deskripsi Proyek – Pinjaman ADB

No Description ADB – OCR Loan ADB – AIF Loan

1 Loan Number ADB L 3123- INO ADB L 8280 - INO

2 Project Number 43251 - 025 43251 - 025

3 Total Loan $ 80 million $ 40 million

4 Signed Loan 13-May-14 13-May-14

5 Effective loan 09-Jul-14 09-Jul-14

6 Closing date 31-Dec-20 31-Dec-20

7 Method of Payment Special Account Special Account

8 No Special Account N/A N/A

9 Amount of Initial Deposit

N/A N/A

10 Project Location Implemented

3 ( three ) Local Government

2 ( two ) Local Government

a. Jambi City a.Makasar City

b.Makassar City b.Pekan Baru City

c.Pekanbaru City

14 Executing Agency The Directorate General of Human Settlements , Ministry of Public Works

14 Institutions Involved

a. Central Goverment DGHS,CPMU,Satker,PPK

b. Provincial Goverment PPMU,Satker,PPK

c. Local Govenment LPMU,PPK

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 11

5.2 Kegiatan yang direncanakan

5.2.1 Status keseluruhan

Pada akhir Desember 2017, proyek tersebut belum mencairkan dana yang dialokasikan untuk semua

komponen, menerima pengadaan pembebasan lahan yang didanai oleh Pemerintah Daerah (APBD).

Rincian ini diberikan dalam Form A - E dan penggunaan dana untuk setiap kategori pengeluaran

diberikan dalam uraian berikut.

Status dan kemajuan Pinjaman ADB dirangkum sebagai berikut :

Tabel 5.2: Form B – status dan progress ADB Loan

Description Loan Allocation

( $ Million ) Investment cost

( $ Million ) Contracted ( $ Million )

(% ) Percent Contracted

OCR - No

3123

AIF -No

8280

OCR No 3123

AIF No 8280

OCR No 3123

AIF No 8280

OCR No 3123

AIF No 8280

1.Jambi City

a. WWTP 14.75 -

b.WSS - West - 19.30

2. Makasar City

a. WWTP 27.20 -

b.WSS – WSS -C 13.40 -

3. Pekan Baru

a. WWTP 12.90 -

b.WSS - N - 20.70

4.Project Implementation Support 11.75 -

Total 80.00 40.00

5.2.2 Pekerjaan yang Dibiayai Dengan Pinjaman ADB

Ada sejumlah proposal program untuk penggunaan Pinjaman ADB yang diperlukan dalam proses penilaian antara Badan Pelaksana dan ADB. Ada sejumlah proposal program untuk penggunaan Pinjaman ADB yang diperlukan dalam proses evaluasi antara Badan Pelaksana dan ADB.

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 12

Table 5.3: Form C – Lingkup Pekerjaan yang dibiayai Pinjaman ADB

No

Description ADB - OCR Loan

NO.3123 INO ADB - AIF Loan NO.8280 INO

Location Scope of Works $ Mill % $ Mill %

1.

Jambi

City

A. Civil Works

a.Waste Water Treatment Plant / WWTP 14.75 18.4 0.00 0.0

b. Waste Water Sewer System / WSS West

0.00 0.0 19.30 48.3

c.Waste Water Sewer System / WSS -East

0.00 0.0 0.00 0.0

d.Property Connection 0.00 0.0 0.00 0.0

e.Community - Based System 0.00 0.0 0.00 0.0

Sub total 14.75 18.4 19.30 48.3

2.

Makasar City

B. Civil Works

a.Waste Water Treatment Plant / WWTP 27.20. 34.0 0.00 0.0

b. Waste Water Sewer System / WSS C

13.40 16.8 0.00 0.0

c. Waste Water Sewer System / WSS -NW

0.00 0.0 0.00 0.0

d. Property Connection 0.00 0.0 0.00 0.0

e. Community - Based System 0.00 0.0 0.00 0.0

Sub total 40.60 50.8 0.00 0.00

3.

PekanBaru

City

C. Civil Works

a. Waste Water Treatment Plant / WWTP 12.90 16.1 0.00 0.0

b. Waste Water Sewer System / WSS N

0.00 0.0 20.70 51.8

c. Waste Water Sewer System / WSS -S

0.00 0.0 0.00 0.0

d. Property Connection 0.00 0.0 0.00 0.0

e. Community - Based System 0.00 0.0 0.00 0.0

Sub total 12.90 16.1 20.70 51.8

D. Consulting Services 11.75 14.7 - -

Total Amount 80.00 100.00 40.00 100.0

5.2.3 Alokasi Anggaran dan Pengeluaran

Biaya proyek asli diperkirakan Rp 310,9 juta untuk 4 Kota (Jambi, Palembang, Pekanbaru dan

Makasar). Karena dana dari pemerintah Australia hanya untuk kota Palembang, maka dana sebesar

USD 48,33 juta tidak disertakan, sehingga total dana sebesar USD 223,84 juta yang termasuk dana dari

pinjaman ADB, Pemerintah Pusat dan Daerah. Untuk pelaksanaan program pada 2017, dana yang

digunakan hanya untuk program konsultasi yaitu Kontrak PISC seharga USD 4.605 juta dan Rp 60.706

juta.

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 13

Proyeksi pencairan dana pinjaman ke proyek, menunjukkan bahwa penggunaan dana secara progresif

berdasarkan pekerjaan yang ada dalam program.

Proyeksi pencairan (target dan Realisasi) selama TA 2018 diberikan dalam Form A sampai E.

5.2.4 Pengadaan dan Kontrak

Dari alokasi 11,75 juta USD untuk program konsultan, total USD 4,605 juta dan 60,706 juta telah

dikontrak dan harus dicairkan, sisanya sebagai saldo yang tidak terpakai sekitar USD 1,27 juta.

Sejumlah kontrak yang diperoleh di tingkat kota belum memenuhi pedoman dokumen yang

ditetapkan dalam panduan pengadaan.

Rincian pengadaan dan kontrak diberikan pada lampiran B.

5.2.5 Permasalahan Utama

a. Kota Jambi

Anggaran yang disetujui untuk TA 2017 telah dialokasikan sebesar Rp 17 miliar untuk

pembebasan lahan dan pembukaan lahan, dan dana sisanya akan dialokasikan pada Tahun

Anggaran 2018. Keadaan ini timbul juga sehubungan dengan tidak jelasnya penerbitan

sertifikat tanah oleh BPN (Badan Pertanahan Nasional). Sesuai dengan porsi keuangan

Pemerintah Daerah dalam proyek ini, di mana seharusnya mengalokasikan dana untuk

pembebasan lahan dan persiapan lokasi.

Untuk Pembangunan IPAL dan Sistem Sewer yang lain, alokasi anggaran untuk penggunaan

Dana Pinjaman belum dilepaskan dari Kementerian Keuangan, sehingga tidak ada kontrak

yang dimanenangkan selama tahun 2017.

b. Kota Makassar

Proses pembebasan lahan sebagian telah dilaksanakan pada tahun 2016 dengan dana Rp 16

miliar dan kegiatan ini akan berlanjut pada tahun anggaran 2017 dengan tambahan pembelian

lahan seluas 5,2 hektar dimana anggaran akan dialokasikan sebesar Rp 10 miliar. Perselisihan

lokasi mengenai IPAL dalam kaitannya status kepemilikan atau sertifikat tanah masih dalam

proses untuk menyelesaikannya di antara para pemangku kepentingan yang terlibat. Karena

proyek ini merupakan pinjaman komersial, sehingga semua aspek terutama kepemilikan lahan

merupakan isu kritis. Pemerintah Daerah telah menyelesaikan kemajuan Pekerjaan Tanah

pada tahun 2016, namun ketersediaan lahan hanya 2,5 Ha. Persiapan lahan untuk

pembangunan IPAL diperkirakan tidak akan selesai sampai akhir 2017, masih harus dilanjutkan

pada periode 2018 tahun. Untuk DED IPAL dan kemajuan koneksi akan berlangsung dimana

tawaran pekerjaan akan dilaksanakan setelah konsultan PISC dikontrak.

c. Kota Pekanbaru

Biaya pembukaan lahan telah dianggarkan pada TA 2017, dan proses DED masih dalam

persiapan pelaksanaannya. Untuk pengawasan Kontraktor dan Konsultan untuk

melaksanakan pekerjaan ini telah dikontrak, sedangkan untuk pekerjaan konstruksi IPAL

belum dilaksanakan, dimana dokumen DED masih dalam peninjauan.

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 14

Daftar Lampiran (terdapat pada lampiran B)

Status Alokasi Anggaran dan Pengeluaran

Form A. Proyeksi Penyerapan – ADB Loan 3123

Form B. Proyeksi Penyerapan – ADB Loan 8280

Form C. Proyeksi Penyerapan – APBN

Form D. Proyeksi Penyerapan – APBD

Form E. Rincian Pengadaan Jasa Konsultan TA 2018/2019

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 15

App A –Rencana Manajemen Risiko Proyek MSMIP

Identifikasi Risiko

Wilayah Risiko Uraian Dampak

Kemungkinan Konsekuensi Peringkat Risiko

Penanggung Jawab

Mitigasi

Jara

ng

Ke

mu

ngk

in

an K

eci

l

Mu

ngk

in

San

gat

Mu

ngk

in

Ham

pir

P

asti

Tid

ak

Pe

nti

ng

Ke

cil

Sed

ang

Be

sar

Fata

l

Low

Me

diu

m

Hig

h

Cri

tica

l

I PERENCANAAN DAN DESAIN

A-10 Umum – Anggaran Pekerjaan

Anggaran yang sudah dibuat untuk kontrak-kontrak yang berbeda, tidak mencukupi

Anggaran tidak tersedia untuk menyelesaikan pekerjaan

DJCK PISC menyusun RAB terhadap Kontrak dan menyusun dasar untuk anggaran yang baru

A-20 Makassar – Lokasi IPAL

Lahan tidak tersedia Tidak ada IPAL untuk memenuhi standar pembuangan

Pemda Memastikan dokumen kepemilikan diperoleh dan disetujui

A-21 Pekerjaan selesai namun tidak sesuai kontrak

Terjadinya penurunan tanah di jalan dan sepanjang perletakkan pipa

PISC Membuat Desain Geoteknik yang sesuai untuk menjamin pekerjaan desain mendatang bebas dari ketidakefisien dalam desain pekerjaan tanah

A-22 Dinas PU Provinsi Sulawesi Selatan akan membangun saluran drainase besar yang baru tepat di lokasi pembangunan IPAL yang berdampak terhadap desain yang ada,

Pengaturan umum pada unit pengolahan dan peralatan pemrosesan akan terpengaruh

PISC Konsultan akan berkoordinasi dengan Pemda Makassar dan Dinas PU Provinsi Sulawesi Selatan untuk menerima pekerjaan gambar saluran dan desain ulang

A-23 Desain IPAL tidak memenuhi Standar Pembuangan

Instalasi baru tidak memenuhi aturan daerah mengenai standar pembuangan dan bisa dikenakan denda

PISC PISC harus mendesain rencana untuk memenuhi standar pembuangan yang diperlukan

A-31 Makassar – Lokasi Rumah Pompa

Tahun 2018 Pemda Makasar akan membangun Tempat parkir di Rumah Pompa A dan telah meminta agar PISC mendesain rumah pompa di bawah lokasi tempat parkir yang baru

Upaya mendesain ulang Rumah Pompa memerlukan lokasi yang baru

DJCK – lokasi baru

PISC persoalan Desain

Memilih lokasi baru

Membuat desain kokoh dan aman

Mengidentifikasi bersama dengan desainer tempat parkir dan bekoordinasi secara efektif

A-32 Lahan untuk Rumah Pompa tidak tersedia

Tidak ada rumah pompa yang menjadi persyaratan untuk mengidentifikasi lahan baru, mendesain ulang.

Pemda Memastikan dokumen kepemilikan diperoleh dan disetujui

A-41 Makassar – Jaringan

Desain yang tidak memadai Bertambahnya waktu untuk mendesain

PISC Mendesain kajian ulang untuk menyertakan kinerja hidraulik. Mendesain ulang jika diperlukan

A-42 Survei Topografi yang tidak memadai

Bertambahnya waktu untuk mendesain

PISC Mendesain kajian ulang untuk menyertakan kinerja hidraulik. Mendesain ulang jika diperlukan

A-43 Desain IPAL tidak memenuhi Standar Pembuangan

Instalasi baru tidak memenuhi aturan daerah mengenai standar pembuangan dan bisa dikenakan denda

PISC PISC harus mendesain rencana untuk memenuhi standar pembuangan yang diperlukan

A-51 Pekanbaru – Lokasi IPAL

Lahan tidak tersedia Mencari lokasi yang baru Pemda Memastikan dokumen kepemilikan diperoleh dan disetujui

A-52 APBD terkait pekerjaan tanah tidak mencukupi.

Kontrak A pekerjaan tanah tidak selesai tepat waktu yang berdampak terhadap kerangka waktu program Kontrak B

DJCK Diskusi awal diperlukan mengenai metode pendanaan kontrak pekerjaan tanah misalnya melalui Pemda, DJCK atau ADB. Membantu Pemda menyelesaikan pekerjaan tanah.

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 16

Identifikasi Risiko

Wilayah Risiko Uraian Dampak

Kemungkinan Konsekuensi Peringkat Risiko

Penanggung Jawab

Mitigasi

Jara

ng

Ke

mu

ngk

in

an K

eci

l

Mu

ngk

in

San

gat

Mu

ngk

in

Ham

pir

P

asti

Tid

ak

Pe

nti

ng

Ke

cil

Sed

ang

Be

sar

Fata

l

Low

Me

diu

m

Hig

h

Cri

tica

l

A-53 Kondisi tanah yang sangat buruk Biaya konstruksi yang lebih tinggi dan kerangka waktu yang lebih lama dalam penyelenggaraan pekerjaan

PISC Menetapkan Investigasi Geoteknik yang sesuai dan menetapkan ulang RAB.

A-54 Pekanbaru – Rumah Pompa

Lahan untuk Rumah Pompa tidak tersedia

Tidak ada rumah pompa yang menjadi persyaratan untuk mengidentifikasi lahan baru, mendesain ulang.

Pemda Memastikan dokumen kepemilikan diperoleh dan disetujui

A-55 Kondisi tanah yang sangat buruk Biaya konstruksi yang lebih tinggi dan kerangka waktu yang lebih lama dalam penyelenggaraan pekerjaan

PISC Menetapkan Investigasi Geoteknik yang sesuai dan menetapkan ulang RAB.

A-60 Pekanbaru - Jaringan

Desain yang tidak memadai Bertambahnya waktu untuk mendesain

PISC Mendesain kajian ulang untuk menyertakan kinerja hidraulik. Mendesain ulang jika diperlukan

A-61 Survei Topografi yang tidak memadai

Bertambahnya waktu untuk mendesain

PISC Mendesain kajian ulang untuk menyertakan kinerja hidraulik. Mendesain ulang jika diperlukan

I-A-70 Jambi – Lokasi IPAL Lahan tidak tersedia Mencari lokasi yang baru Pemda Memastikan dokumen kepemilikan diperoleh dan disetujui

A-71 Sebagian dari lahan tidak tersedia Desain utk lokasi IPAL akan menjadi keliru

Pemda Mendesain ulang pekerjaan

A-72 APBD terkait pekerjaan tanah tidak mencukupi.

Kontrak A pekerjaan tanah tidak selesai tepat waktu yang berdampak terhadap kerangka waktu program Kontrak B

DJCK Diskusi awal diperlukan mengenai metode pendanaan kontrak pekerjaan tanah misalnya melalui Pemda, DJCK atau ADB. Membantu Pemda menyelesaikan pekerjaan tanah.

A-73 Kondisi tanah yang sangat buruk Biaya konstruksi yang lebih tinggi dan kerangka waktu yang lebih lama dalam penyelenggaraan pekerjaan

PISC Menetapkan Investigasi Geoteknik yang sesuai dan menetapkan ulang RAB.

A-74 Desain IPAL tidak memenuhi Standar Pembuangan

Instalasi baru tidak memenuhi aturan daerah mengenai standar pembuangan dan bisa dikenakan denda

PISC PISC harus mendesain rencana untuk memenuhi standar pembuangan yang diperlukan

A-81 Jambi – Lokasi Rumah Pompa

Lahan untuk Rumah Pompa tidak tersedia

Tidak ada rumah pompa yang menjadi persyaratan untuk mengidentifikasi lahan baru, mendesain ulang.

Pemda Memastikan dokumen kepemilikan diperoleh dan disetujui.

Memeriksa ulang dan mendesain ulang pekerjaan

A-82 Pemindahan penduduk di lokasi Biaya tinggi terkait konstruksi instalasi serta persoalan sosial terkait pemukiman kembali di lokasi.

Pemda DJCK mengrimkan surat kepada Walikota untuk meminta komitmen alokasi anggaran untuk tahun 2018.

Konsultan harus mendesain ulang

A-83 Pembatasan akses ke lokasi Tidak praktis bagi truk tangki, sulit bagi staf O&M untuk mengakses.

Pemda menemukan rute alternatif untuk jalur akses.

PISC harus mendesain ulang

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 17

Identifikasi Risiko

Wilayah Risiko Uraian Dampak

Kemungkinan Konsekuensi Peringkat Risiko

Penanggung Jawab

Mitigasi

Jara

ng

Ke

mu

ngk

in

an K

eci

l

Mu

ngk

in

San

gat

Mu

ngk

in

Ham

pir

P

asti

Tid

ak

Pe

nti

ng

Ke

cil

Sed

ang

Be

sar

Fata

l

Low

Me

diu

m

Hig

h

Cri

tica

l

A-90 Jambi – Jaringan Desain yang tidak memadai Bertambahnya waktu untuk mendesain

PISC Mendesain kajian ulang untuk menyertakan kinerja hidraulik. Mendesain ulang jika diperlukan

A-91 Survei Topografi yang tidak memadai

Bertambahnya waktu untuk mendesain

PISC Mendesain kajian ulang untuk menyertakan kinerja hidraulik. Mendesain ulang jika diperlukan

B PENGADAAN

B-01 Panitia Lelang Jumlah panitia yang memenuhi syarat di tingkat provinsi tidak dapat ditentukan. Beberapa panitia memiliki kapasitas yang wajar dalam pengadaan namun tidak berpengalaman dengan ADB.

Pelaksanaan penawaran menjadi lebih lama sehingga proyek dapat tertunda dan terjadi kelebihan biaya

DJCK Membuat model serta rencana yang

realistis bagi Panitia

Beberapa anggota Panitia Lelang berasal dari DJCK

B-02 Dokumen Penawaran

Berdasar regulasi untuk semua proyek dengan biaya lebih dari Rp 100 milyar memerlukan persetujuan dari DJCK dan ADB terkait paket ICB. Kemungkinan Dokumen Penawaran tidak dapat disetujui.

Pelaksanaan penawaran menjadi lebih lama sehingga proyek dapat tertunda dan terjadi kelebihan biaya

DJCK Komunikasi dan koordinasi yang

mendalam dengan DJCK dan ADB.

Dukungan dari PISC meliputi pelatihan di tempat kerja (on-the-job) mengenai pengadaan kepada instansi penanggung jawab dan pelaksana selama berlangsungnya proyek

B-03 Jumlah Peserta Penawaran.

Peserta terbatas yang memenuhi persyaratan minimum (teknis dan biaya) sebagaimana tercantum dalam Dokumen Penawaran

Penawaran gagal dan memerlukan pelaksanaan prakualifikasi/negosiasi tender lebih lanjut.

Seleksi kontraktor yang kurang bagus karena rendahnya penawaran, tanpa kemampuan teknis dalam menangani proyek yang menyebabkan kelebihan biaya, keterlambatan jadwal, kualitas konstruksi yang rendah, serta hasil akhir yang tidak dapat diterima

DJCK Mengidentifikasi lebih awal terhadap kontraktor yang paling memenuhi syarat melalui sistem prakualifikasi etika dan membuat konsep jenis kontrak yang paling sesuai yang dapat diterapkan pada kondisi proyek.

B-04 Intervensi dalam Penawaran

Ada pihak tertentu diluar penawaran yang ikut campur urusan panitia sehingga mempengaruhi proses dan hasil tender

Penawaran gagal, paket dibatalkan

DJCK DJCK menjamin kemandirian proses pengadaan dan menolak perilaku tidak etis.

Melaksanakan E-Procurement secara penuh

B-05 Sambungan Rumah

1,000 sambungan rumah dipasang berdasar kontrak. Pemda bertanggung jawab terhadap hal lainnya. Jika kontrak tidak dikoordinasi, maka aliran di saluran pembuangan air limbah tidak akan mencukupi.

Aliran yang tidak mencukupi di jaringa perpipaan dan membutuhkan air banyak untuk pembilasan di pipa

DJCK Mengkoordinir secara seksama antara DJCK dan Pemda mengenai penetapan waktu pekerjaan sambungan basah

Melaksanakan E-Procurement secara penuh

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 18

Identifikasi Risiko

Wilayah Risiko Uraian Dampak

Kemungkinan Konsekuensi Peringkat Risiko

Penanggung Jawab

Mitigasi

Jara

ng

Ke

mu

ngk

in

an K

eci

l

Mu

ngk

in

San

gat

Mu

ngk

in

Ham

pir

P

asti

Tid

ak

Pe

nti

ng

Ke

cil

Sed

ang

Be

sar

Fata

l

Low

Me

diu

m

Hig

h

Cri

tica

l

C KONSTRUKSI C-01 Kondisi Cuaca dan

Iklim

Musim hujan dengan curah hujan tinggi akan menghentikan sementara kegiatan di lapangan.

Pekerjaan di lokasi akan terhambat sementara, proyek akan tertunda dan terjadi kelebihan biaya

DJCK Menyusun jadwal konstruksi dengan

antisipasi penutupan sementara berdasar perubahan musim dan memberikan tambahan waktu pada jadwal sebagai kompensasi atas penundaan yang disebabkan oleh cuaca dingin; mempertimbangkan metodologi konstruksi alternatif

C-02 Prosedur keselamatan kerja yang rendah. Mengurangi risiko terhadap pekerja dan masyarakat selama konstruksi

Jumlah kecelakaan yag

melibatkan kegiatan konstruksi

Proyek akan tertunda dan terjadi kelebihan biaya

DJCK Kontraktor memastikan agar rencana

keselamatan diberikan sejak awal kegiatan konstruksi dan mengelola proses keselamatan sesuai manual dan persyaratan Pengguna jasa.

C-03 Penutupan Lalu Lintas tidak dikoordinasi dengan masyarakat sekitar

Akan muncul protes dari masyarakat sekitar proyek,

Proyek terhenti dan akan tertunda serta terjadi kelebihan biaya

DJCK

PISC untuk persoalan

Desain terkait

Sosialisasi dilaksanakan lebh awal terhadap masyarakat terkena dampak dengan melibatkan Pemda dan pihak yang berwenang yaitu polisi lalulintas.

Mendesain areal pekerjaan dengan mempertimbangkan kondisi lingkungan dan manajemen lalulintas

Hubungan masyarakat untuk memastikan masyarakat setempat benar-benar terlibat dengan proyek sejak awal.

C-04 Tumpang Tindih penjadwalan dengan proyek lain

Proyek memiliki antarmuka dengan pekerjaan lainnya yaitu Makassar dimana akan terjadi tumpang tindih antara Saluran Proyek untuk IPAL dan Tempat parkir dengan rumah pompa A

Proyek akan tertunda dan terjadi kelebihan biaya

DJCK Mengkoordinir sedini mungkin dan sesering

mungkin sehingga jadwal pekerjaan dapat disinkronkan dan perlu menyesuaikan lingkup masing-masing pekerjaan untuk mendapatkan hasil terbaik bagi kedua proyek

C-05 Pembongkaran tangki septik

Tidak ada pembongkaran tangki septik

Hydrogen sulphide menyebabkan korosi pada beton tangki septik setelah sekian lama yang menyebabkan bahaya dan situasi yang kemungkinan berakibat fatal.

DJCK DJCK harus mengidentifikasi cara menetapkan anggaran untuk pembongkaran tangki septik

C-06 Kebisingan akibat konstruksi

Kebisingan dan getaran akibat konstruksi atau pemancangan tiang berdampak pada bisnis dan penduduk yang berdekatan

Keluhan mengenai kegiatan Konstruksi

DJCK Hubungan masyarakat untuk memastikan masyarakat setempat benar-benar terlibat dengan proyek sejak awal. Menggunakan peralatan sound proofing dan penanganan getaran jika diperlukan

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 19

App B –Status Alokasi Anggaran

ADB OCR Loan NO 3123 INO ( in USD Milions )

Target Realization Target Realization Target Realization Target Realization Target Realization

1. Jambi City

1. Waste Water

Treatment Plant / 14.75 PC - 2.95 0.44 0.43 0.43 0.43

2.Waste Water Sewer

System /WSS -West 0.00 PC -

3.Waste Water Sewer

System / WSS -East 0.00 PC -

4.Property

Connection 0.00 PC -

5.Community - Based

System 0.00 PC -

2. Makasar City

1. Waste Water

Treatment Plant / 22.70 PC - 4.54 0.68 0.42 0.43 0.43

2.Waste Water Sewer

System /WSS -C 13.40 PC - 2.68 0.40 0.43 0.43 0.43

3.Waste Water Sewer

System / WSS -NW 0.00 PC -

4.Property

Connection 0.00 PC -

5.Community - Based

System 0.00 PC

3. Pekan Baru City

1. Waste Water

Treatment Plant / 12.90 PC - 2.58 0.39 0.43 0.43 0.43

2.Waste Water Sewer

System /WSS -N 0.00 PC -

3.Waste Water Sewer

System / WSS -S 0.00 PC -

4.Property

Connection 0.00 PC -

5.Community - Based

System 0.00 PC -

4. Jambi, Makasar,

Pekan Baru

Project

Implementation 11.75 C 11.17 1.89 0.274 - 0.557 - 0.590 - 0.596 - 2.016 -

TOTAL 75.50 0.00 0.00 12.75 1.91 0.00 1.70 0.00 1.71 0.00 1.71 0.00 0.00 0.00

Noted :

- USD = Rp.13.000

- PC = Pra Contract ; C = Contract

*)Assumption DP 20%

**)Assumption Quarterly 15%

Form A : Disbursement Projection For FY 2018

Location Category Works Funds AllocatedStatus

Package

Contract

Value

*)Actual

Disbursemen

t

as of Okt

2017

**)Disbursement Projection

1st Quarter

(Jan - March )

2nd Quarter

(Apr - Jun)

3rd Quarter

( July - Sept)

4th Quarter

(Oct - Dec)Total in TA 2018

- Contract Value exluding Added Value Tax /PPN

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 20

ADB AIF Loan NO 8280 INO ( in USD Milions )

Target Realization Target Realization Target Realization Target Realization Target Realization

1. Jambi City

1. Waste Water

Treatment Plant / 0.00 PC - - - - - - - - - - - -

2.Waste Water Sewer

System /WSS -West 19.30 PC - 3.86 - - - - - - - - - -

3.Waste Water Sewer

System / WSS -East 0.00 PC - - - - - - - - - - - -

4.Property

Connection 0.00 PC - - - - - - - - - - - -

5.Community - Based

System 0.00 PC - - - - - - - - - - - -

2. Pekan Baru City - - - - - - - - - - -

1. Waste Water

Treatment Plant / 0.00 PC - - - - - - - - - - - -

2.Waste Water Sewer

System /WSS -N 20.70 PC - 4.14 - - - - - - - - - -

3.Waste Water Sewer

System / WSS -S 0.00 PC - - - - - - - - - - - -

4.Property

Connection 0.00 PC - - - - - - - - - - - -

5.Community - Based

System 0.00 PC - - - - - - - - - - - -

TOTAL40.00 0.00 0.00 8.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Noted :

- USD = Rp.13.000

- PC = Pra Contract ; C = Contract

*)Assumption DP 20%

**)Assumption Quarterly 15%

Form B : Disbursement Projection For FY 2018

Actual

Disbursemen

t

as of Okt

2017

Disbursement Projection

1St Quarter

(Jan - March )

2nd Quarter

(Apr - Jun)

3rd Quarter

( July - Sept)

4th Quarter

(Oct - Dec)Total in TA 2018Location Category Works Funds Allocated

Status

Package

Contract

Value

- Contract Value exluding Added Value Tax /PPN

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 21

Central Government - APBN

Target Realization Target Realization Target Realization Target Realization Target Realization

1. Jambi City

1. Waste Water

Treatment Plant / 0.00 PC - - - - - - - - - - - -2.Waste Water Sewer

System /WSS -West 0.00 PC - - - - - - - - - - - -3.Waste Water Sewer

System / WSS -East 14.36 PC - - - - - - - - - - - -4.Property

Connection 0.50 PC - - - - - - - - - - - -5.Community - Based

System 0.00 PC - - - - - - - - - - - -

2. Makasar City

1. Waste Water

Treatment Plant / 0.00 PC -2.Waste Water Sewer

System /WSS - C 0.00 PC -3.Waste Water Sewer

System / WSS -NW 24.31 PC -4.Property

Connection 0.50 PC -5.Community - Based

System 0.00 PC

3. Pekan Baru City - - - - - - - - - - -

1. Waste Water

Treatment Plant / 0.00 PC - - - - - - - - - - - -2.Waste Water Sewer

System /WSS -N 0.00 PC - - - - - - - - - - - -3.Waste Water Sewer

System / WSS -S 22.44 PC - - - - - - - - - - - -

4.Property 0.44 PC - - - - - - - - - - - -

5.Community - Based 0.00 PC - - - - - - - - - - - -

TOTAL 62.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Noted :

- USD = Rp.13.000

- PC = Pra Contarct ; C = Contract

Form C : Disbursement Projection For FY 2018

Location Category Works Funds AllocatedStatus

Package

Contract

Value

Actual

Disbursemen

t

as of Okt

2017

Disbursement Projection

1St Quarter

(Jan - March )

2nd Quarter

(Apr - Jun)

3rd Quarter

( July - Sept)

4th Quarter

(Oct - Dec)Total in TA 2018

- Contract Value Including Added Value Tax /PPN ( 10 % )

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 22

Local Government - APBD

Target Realization Target Realization Target Realization Target Realization Target Realization

1. Jambi City

1. Waste Water

Treatment Plant /

WWTP 0.00 PC - - - - - - - - - - - -

2.Waste Water Sewer

System /WSS -West 0.00 PC - - - - - - - - - - - -

3.Waste Water Sewer

System / WSS -East 0.00 PC - - - - - - - - - - - -

4.Property

Connection 4.95 PC - - - - - - - - - - - -

5.Community - Based

System 0.88 PC - - - - - - - - - - - -

2. Makasar City

1. Waste Water

Treatment Plant /

WWTP 0.00 PC -

2.Waste Water Sewer

System /WSS - C 0.00 PC -

3.Waste Water Sewer

System / WSS -NW 0.00 PC -

4.Property

Connection 5.06 PC -

5.Community - Based

System 1.10 PC

3. Pekan Baru City - - - - - - - - - - -

1. Waste Water

Treatment Plant /

WWTP 0.00 PC - - - - - - - - - - - -

2.Waste Water Sewer

System /WSS -N 0.00 PC - - - - - - - - - - - -

3.Waste Water Sewer

System / WSS -S 0.00 PC - - - - - - - - - - - -

4.Property

Connection 4.95 PC - - - - - - - - - - - -

5.Community - Based

System 1.10 PC - - - - - - - - - - - -

TOTAL 18.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Noted :

- USD = Rp.13.000

- PC = Pra Contract ; C = Contract

Form D : Disbursement Projection For FY 2018

- Contract Value Including Added Value Tax /PPN ( 10 % )

Disbursement Projection

1St Quarter 2nd Quarter 3rd Quarter 4th Quarter Total in TA 2018Location Category Works Funds AllocatedStatus

Package

Contract

Value

Actual

Disbursemen

t

as of Oct

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 23

Form E : Detail of Consultant Services Procurement FY 2018/2019

DIPA

Allocated

( IDR ) (USD ) ( IDR )( in

Rp.000 ) WA No ( IDR ) ( USD )

1 2 3 4 5 6 7 8 9 10 11 12 13ADB OCR

Total - 60,706,784,200

DIP - 4,605,295.52 60,706,784,200

Tax - - -

- -

- -

- -

TOTAL 0.00 4,605,296 60,706,784,200 0.00 0.00 0.00 0.00 0.00 0.00

Noted :

- USD = Rp.13.000

- PC = Pra Contract ; C = Contract

- Contract Value exluding Added Value Tax /PPN

1. Jambi City

2. Makasar City

3.Pekan Baru

Project

Implementation

Support

Metropolitan

Sanitation

Management

SMEC

International Py

LTD in JV with

Stantec Australia

Pty Ltd

With Sub

ADB OCR Loan No.3123 INO

No Location Category Works /City/PCSS

Source

of

Fund

Amount Contract No

/Date / type of

proc / Duration

Use of

Fund Loan Disbursement

Remark Contracted

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 24

App C – Jadwal Proyek

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 25

Pekanbaru

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 26

Jambi

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 27

Makassar

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 28

App D – Staffing Schedules

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 29

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 402021

O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D JJAKARTA

Key Personnel (International)

16 Original 1.0 1.0 1.0 0.5 1.0 1.0 1.0 1.0 1.0 0.5 1.0 1.0 1.0 1.0 1.0 1.0 1.0 16.00

34 Addendum No. 1 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 34.00

6 Original 1.0 1.0 1.0 0.5 1.0 1.0 0.5 6.00

10.25 Addendum No. 1 0.8 0.8 0.8 0.8 0.8 0.8 0.8 1.0 1.0 1.0 1.0 1.0 10.25

4 Original 1.0 1.0 0.5 1.0 0.5 4.00

6 Addendum No. 1 1.0 1.0 1.0 1.0 1.0 1.0 6.00

3 Original 1.0 1.0 1.0 3.00

9 Addendum No. 1 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 9.00

4 Original 1.0 1.0 1.0 1.0 4.00

4 Addendum No. 1 0.5 1.0 0.5 1.0 1.0 4.00

3 Original 1.0 1.0 1.0 3.00

3 Addendum No. 1 0.5 1.0 0.5 1.0 3.00

3 Original 1.0 1.0 1.0 3.00

7 Addendum No. 1 0.5 1.0 0.5 1.0 1.0 1.0 1.0 1.0 7.00

0 Original 0.00

4 Addendum No. 1 1.0 1.0 1.0 1.0 4.00

0 Original 0.00

6 Addendum No. 1 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 6.00

0 Original 0.00

6 Addendum No. 1 0.5 1.0 1.0 1.0 1.0 1.0 0.5 6.00

0 Original 0.00

4 Addendum No. 1 1.0 1.0 1.0 1.0 4.00

0 Original 0.00

4 Addendum No. 1 0.5 1.0 1.0 1.0 0.5 4.00

0 Original 0.00

10 Addendum No. 1 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 10.00

Key Personnel (National)

40 Original 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 40.00

39.5 Addendum No. 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 39.50

16 Original 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 16.00

39 Addendum No. 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 39.00

18 Original 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 18.00

18 Addendum No. 1 0.3 1 1 1 1 1 1 1 0.8 1 1 1 1 1 1 1 1 1 1 18.00

3 Original 1 1 1 3.00

6 Addendum No. 1 1 0.5 1 1 1 1 0.5 6.00

6 Original 1 1 1 1 1 1 6.00

10 Addendum No. 1 1 1 1 1 1 1 1 1 1 1 10.00

4 Original 1 1 1 1 4.00

10 Addendum No. 1 1 1 1 1 1 1 1 1 1 1 10.00

0 Original 0.00

10 Addendum No. 1 1 1 1 1 1 1 1 1 1 1 10.00

0 Original 0.00

6 Addendum No. 1 1 1 1 1 1 1 6.00

0 Original 0.00

6 Addendum No. 1 1 1 1 1 1 1 6.00

0 Original 0.00

6 Addendum No. 1 1 1 1 1 1 1 6.00

0 Original 0.00

3 Addendum No. 1 1 1 1 3.00

0 Original 0.00

4 Addendum No. 1 1 1 1 1 4.00

0 Original 0.00

5 Addendum No. 1 1 1 1 1 1 5.00

Non Key Personnel (National)

40 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 40.00

39.5 Addendum No. 1 0.50 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 39.50

40 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 40.00

38 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 38.00

40 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 40.00

38.5 Addendum No. 1 0.50 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 38.50

40 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 40.00

38.5 Addendum No. 1 0.50 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 38.50

6 Original 1.00 1.00 1.00 1.00 1.00 1.00 6.00

38.5 Addendum No. 1 0.50 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 38.50

40 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 40.00

39 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 39.00

40 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 40.00

38.5 Addendum No. 1 0.50 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 38.50

40 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 40.00

38.5 Addendum No. 1 0.50 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 38.50

0 Original 0.00

38.5 Addendum No. 1 0.50 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 38.50

0 Original 0.00

35 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 35.00

0 Original 0.00

6 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 6.00

0 Original 0.00

6 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 6.00

0 Original 0.00

5 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 5.00

0 Original 0.00

5 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 5.00

0 Original 0.00

38.5 Addendum No. 1 0.50 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 38.50

0 Original 0.00

38 Addendum No. 2 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 38.00

0 Original 0.00

38.5 Addendum No. 1 0.50 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 38.50

0 Original 0.00

38.5 Addendum No. 1 0.50 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 38.50

Period of Services

2017 2018 2019 2020

STAFFING SCHEDULE - JAKARTA

No. Name PositionKey or Non

KeyNationality Input

Original/

Addendum No. 1

2. Anthony Gunadi Wastewater Treatment Process Engineer Key International

1.Andrew Mclernon/

Malcolm EhrlichTeam Leader / Wastewater Specialist Key International

4. Napolean Lagura Mechanical Expert Key International

3. Ananda De Costa Civil/Structural Expert Key International

6. Joselito Losario Environmental Specialist Key International

5. Rosemary Faletese Gender and Social Development Specialist Key International

8. Brian Hayden Senior Infrastructure Specialist (Start Up) Key International

7. Victoria R Pineda Social Safeguards / Resettlement Specialist Key International

10. William Sharp Civil Expert Key International

9. Paul Jenkins Design Manager Key International

12. TBN Geotechnical Expert Key International

11. TBN Senior Electrical Expert Key International

1. Benny Aryanto Deputy Team Leader Key National

13. TBN Senior Procurement & Contract Specialist Key International

3. Afdatira MIS Specialist Key National

2. Thariq Marzuki Financial Management Specialist Key National

5. Treesnowati Benefit Monitoring Specialist Key National

4. Indiarto Budi Electrical Expert Key National

7. Wildan Civil Engineer Key National

6. Budiman Cost Estimator Key National

9. Henry Mechanical Engineer Key National

8. Yani Haryardi Structural Engineer Key National

11. Leo De Santos Sewerage Engineer 2 Key National

10. Fihaus Sewerage Engineer 1 Key National

13. M. Zaki Geotechnical Engineer Key National

12. Teuku Fajar Sodik Procurement and Contract Specialist Key National

2. TBN Accounting Specialist Non Key National

1. Utami Kusumaningrum Office Manager Non Key National

4. TBN GIS - IT Support Non Key National

3. TBN Bilingual Secretary Non Key National

6. Safrizal Atmawijaya Office Boy Non Key National

5. TBN Engineering Support 1 / Drafting Non Key National

8. TBN Guard 2 Non Key National

7. TBN Guard 1 Non Key National

10. TBN Engineering Support 3 / Drafting Non Key National

9. TBN Engineering Support 2 / Drafting Non Key National

12. TBN Mechanical CAD Non Key National

11. TBN Structural CAD Non Key National

14. TBN Process CAD Non Key National

13. TBN Electrical CAD Non Key National

16. TBN Technical Translator Non Key National

15. TBN Document Controller Non Key National

18. TBN Administrator (CPMU) Non Key National

17. TBN Administrator (PISC) Non Key National

4.25

2.00

6.00

0.00

0.00

4.00

Total Person Month

OriginalAdd.

No. 1Balance

18.00

-0.50

23.00

0.00

3.00

4.00

6.00

4.00

6.00

6.00

4.00

4.00

10.00

5.00

-0.50

-2.00

-1.50

-1.50

32.50

10.00

6.00

6.00

6.00

3.00

4.00

38.50

6.00

5.00

5.00

38.50

38.00

38.50

-1.00

-1.50

-1.50

38.50

35.00

6.00

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 30

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40

2021

O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J

PEKANBARU

Key Personnel (International)

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

12 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 12.00

12 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 12.00

Subtotal 39.00 39.00 0.00

Key Personnel (National)

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

24 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 24.00

24 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 24.00

6 Original 1.00 1.00 1.00 1.00 1.00 1.00 6.00

6 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 6.00

4 Original 1.00 1.00 1.00 1.00 4.00

4 Addendum No. 1 1.00 1.00 1.00 1.00 4.00

4 Original 1.00 1.00 1.00 1.00 4.00

4 Addendum No. 1 1.00 1.00 1.00 1.00 4.00

4 Original 1.00 1.00 1.00 1.00 4.00

4 Addendum No. 1 1.00 1.00 1.00 1.00 4.00

12 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 12.00

12 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 12.00

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

4 Original 1.00 1.00 1.00 1.00 4.00

4 Addendum No. 1 1.00 1.00 1.00 1.00 4.00

6 Original 1.00 1.00 1.00 1.00 1.00 1.00 6.00

6 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 6.00

0 Original 0.00

2 Addendum No. 1 0.25 1.00 0.75 2.00

Subtotal 172.00 174.00 2.00

Non Key Personnel (National)

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

6 Original 1.00 1.00 1.00 1.00 1.00 1.00 6.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

6 Original 1.00 1.00 1.00 1.00 1.00 1.00 6.00

0 Addendum No. 1 0.00

6 Original 1.00 1.00 1.00 1.00 1.00 1.00 6.00

22 Addendum No. 1 0.25 1.00 0.75 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 22.00

6 Original 1.00 1.00 1.00 1.00 1.00 1.00 6.00

22 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 22.00

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

14. TBN Field Supervisor 6 Non Key National 0.00

19. TBN Guard 2 Non Key National 0.00

18. TBN Guard 1 Non Key National 0.00

17. TBN Office Boy Non Key National 0.00

16. TBN Field Supervisor 8 Non Key National 0.00

15. TBN Field Supervisor 7 Non Key National 0.00

8. TBN Surveyor Support 2 Non Key National 16.00

13. TBN Field Supervisor 5 Non Key National 0.00

12. TBN Field Supervisor 4 Non Key National 0.00

11. TBN Field Supervisor 3 Non Key National 0.00

10. TBN Field Supervisor 2 Non Key National 0.00

9. TBN Field Supervisor 1 Non Key National 0.00

2. TBN Accounting Specialist Non Key National 0.00

7. TBN Surveyor Support 1 Non Key National 16.00

6. TBN Engineering Support 2 / Drafting Non Key National -6.00

5. TBN Engineering Support 1 / Drafting Non Key National 21.00

4. TBN GIS - IT Support Non Key National 0.00

3. TBN Bilingual Secretary Non Key National 0.00

9. Johan KhadafiPublic Relations / Sanitation Marketing

SpecialistKey National 0.00

1. TBN Office Manager Non Key National 0.00

13. TBN Cost Estimator Key National 2.00

12. Agus Yudiarto Social Safeguard / Resettlement Key National 0.00

11. Harly Suhartono Gender and Social Development Specialist Key National 0.00

10. Julianty Health and Safety Coordinator Key National 0.00

3. Rusman Sihotang Structural Engineer Key National 0.00

8. Achmad Basari Procurement and Contract Specialist Key National 0.00

7. Bistok Panjaitan Electrical Engineer Key National 0.00

6. Adi Andhika Geotechnical Specialist Key National 0.00

5. Mohammad Alexin Putra Mechanical Engineer Key National 0.00

4. Hani Andriani Environmental Expert Key National 0.00

1. Paul JenkinsCity Office Leader / Sewerage Construction

Supervisor - PekanbaruKey International 0.00

2. Tanto Widyo Hendarto Sewerage Engineer Key National 0.00

1. Leo Sando Silvado Sewerage Engineer Key National 0.00

2. Roodolfo Nicolas WWTP / Construction Supervisor - Pekanbaru Key International 0.00

STAFFING SCHEDULE - PEKANBARU

No. Name PositionKey or Non

KeyNationality Input

Original/

Addendum No. 1

Period of ServicesTotal Person-

Month Input

Original

Addend

um No.

1

Balance2017 2018 2019 2020

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 31

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40

2021

O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J

JAMBI

Key Personnel (International)

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

12 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 12.00

12 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 12.00

Subtotal 39.00 39.00 0.00

Key Personnel (National)

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

24 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 24.00

24 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 24.00

6 Original 1.00 1.00 1.00 1.00 1.00 1.00 6.00

6 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 6.00

4 Original 1.00 1.00 1.00 1.00 4.00

4 Addendum No. 1 1.00 1.00 1.00 1.00 4.00

4 Original 1.00 1.00 1.00 1.00 4.00

4 Addendum No. 1 1.00 1.00 1.00 1.00 4.00

4 Original 1.00 1.00 1.00 1.00 4.00

4 Addendum No. 1 1.00 1.00 1.00 1.00 4.00

12 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 12.00

12 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 12.00

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

4 Original 1.00 1.00 1.00 1.00 4.00

4 Addendum No. 1 1.00 1.00 1.00 1.00 4.00

6 Original 1.00 1.00 1.00 1.00 1.00 1.00 6.00

6 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 6.00

0 Original 0.00

2 Addendum No. 1 0.25 1.00 0.75 2.00

Subtotal 172.00 174.00 2.00

Non Key Personnel (National)

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

6 Original 1.00 1.00 1.00 1.00 1.00 1.00 6.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

6 Original 1.00 1.00 1.00 1.00 1.00 1.00 6.00

0 Addendum No. 1 0.00

6 Original 1.00 1.00 1.00 1.00 1.00 1.00 6.00

22 Addendum No. 1 0.25 1.00 0.75 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 22.00

6 Original 1.00 1.00 1.00 1.00 1.00 1.00 6.00

22 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 22.00

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.00

27 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 27.0019. TBN Guard 2 Non Key National 0.00

18. TBN Guard 1 Non Key National 0.00

12. TBN Field Supervisor 4 Non Key National 0.00

17. TBN Office Boy Non Key National 0.00

16. TBN Field Supervisor 8 Non Key National 0.00

15. TBN Field Supervisor 7 Non Key National 0.00

14. TBN Field Supervisor 6 Non Key National 0.00

13. TBN Field Supervisor 5 Non Key National 0.00

6. TBN Engineering Support 2 / Drafting Non Key National -6.00

11. TBN Field Supervisor 3 Non Key National 0.00

10. TBN Field Supervisor 2 Non Key National 0.00

9. TBN Field Supervisor 1 Non Key National 0.00

8. TBN Surveyor Support 2 Non Key National 16.00

7. TBN Surveyor Support 1 Non Key National 16.00

13. TBN Cost Estimator Key National 2.00

5. TBN Engineering Support 1 / Drafting Non Key National 21.00

4. TBN GIS - IT Support Non Key National 0.00

3. TBN Bilingual Secretary Non Key National 0.00

2. TBN Accounting Specialist Non Key National 0.00

1. TBN Office Manager Non Key National 0.00

7. Agustinus Sukowidodo Electrical Engineer Key National 0.00

12. Cahaya Hondro Social Safeguard / Resettlement Key National 0.00

11. Sri Mulyasari Gender and Social Development Specialist Key National 0.00

10. Fawitasari Fransisca Health and Safety Coordinator Key National 0.00

9. BurhanuddinPublic Relations / Sanitation Marketing

SpecialistKey National 0.00

8. Slamet Haryanta Procurement and Contract Specialist Key National 0.00

1. Adung Sewerage Engineer Key National 0.00

6. Rendi Dwi Kartiko Geotechnical Specialist Key National 0.00

5. Dyos Santoso Mechanical Engineer Key National 0.00

4. Sentot Prasetyo Wijayanto Environmental Expert Key National 0.00

3. Yan Haryadi Structural Engineer Key National 0.00

2. Muhamad Nasir Sewerage Engineer Key National 0.00

2. Andrew Connel WWTP / Construction Supervisor - Jambi Key International 0.00

1. Malcolm EhrlichCity Office Leader / Sewerage Construction

Supervisor - JambiKey International 0.00

STAFFING SCHEDULE - JAMBI

No. Name PositionKey or Non

KeyNationality Input

Original/

Addendum No. 1

Period of ServicesTotal Person-

Month Input

Original

Addend

um No.

1

Balance2017 2018 2019 2020

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 32

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40

2021

O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J

MAKASSAR

Key Personnel (International)

28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

12 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 12.00

12 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 12.00

Key Personnel (National)

28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

24 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 24.00

24 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 24.00

6 Original 1.00 1.00 1.00 1.00 1.00 1.00 6.00

6 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 6.00

4 Original 1.00 1.00 1.00 1.00 4.00

4 Addendum No. 1 1.00 1.00 1.00 1.00 4.00

4 Original 1.00 1.00 1.00 1.00 4.00

4 Addendum No. 1 1.00 1.00 1.00 1.00 4.00

4 Original 1.00 1.00 1.00 1.00 4.00

4 Addendum No. 1 1.00 1.00 1.00 1.00 4.00

12 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 12.00

12 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 12.00

28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

4 Original 1.00 1.00 1.00 1.00 4.00

4 Addendum No. 1 1.00 1.00 1.00 1.00 4.00

6 Original 1.00 1.00 1.00 1.00 1.00 1.00 6.00

6 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 6.00

0 Original 0.00

2 Addendum No. 1 0.25 1.00 0.75 2.00

Non Key Personnel (National)

28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

6 Original 1.00 1.00 1.00 1.00 1.00 1.00 6.00

28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

6 Original 1.00 1.00 1.00 1.00 1.00 1.00 6.00

0 Addendum No. 1 0.00

6 Original 1.00 1.00 1.00 1.00 1.00 1.00 6.00

22 Addendum No. 1 0.25 1.00 0.75 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 22.00

6 Original 1.00 1.00 1.00 1.00 1.00 1.00 6.00

22 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 22.00

28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

28 Original 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

28 Addendum No. 1 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 28.00

17. TBN Office Boy Non Key National 0.00

16. TBN Field Supervisor 8 Non Key National

19. TBN Guard 2 Non Key National 0.00

18. TBN Guard 1 Non Key National 0.00

0.00

15. TBN Field Supervisor 7 Non Key National 0.00

14. TBN Field Supervisor 6 Non Key National 0.00

13. TBN Field Supervisor 5 Non Key National 0.00

12. TBN Field Supervisor 4 Non Key National 0.00

11. TBN Field Supervisor 3 Non Key National 0.00

10. TBN Field Supervisor 2 Non Key National 0.00

9. TBN Field Supervisor 1 Non Key National 0.00

8. TBN Surveyor Support 2 Non Key National 16.00

7. TBN Surveyor Support 1 Non Key National 16.00

6. TBN Engineering Support 2 / Drafting Non Key National -6.00

5. TBN Engineering Support 1 / Drafting Non Key National 22.00

4. TBN GIS - IT Support Non Key National 0.00

3. TBN Bilingual Secretary Non Key National 0.00

2. TBN Accounting Specialist Non Key National 0.00

1. TBN Office Manager Non Key National 0.00

13. TBN Cost Estimator Key National 2.00

12. Dwi Apriyanti Social Safeguard / Resettlement Specialist Key National 0.00

11. Euis Masripah Gender and Social Development Specialist Key National 0.00

10. Dwi Prihanto Health and Safety Coordinator Key National 0.00

9. Harudin HartonoPublic Relations / Sanitation Marketing

SpecialistKey National 0.00

8. Yosep Sri Nuryanto Procurement and Contract Specialist Key National 0.00

7. Harlen Siahaan Electrical Engineer Key National 0.00

6. Suharso Bambang Geotechnical Specialist Key National 0.00

5. Henry Pranajaya Mechanical Engineer Key National 0.00

4. Adam Yajid Environmental Expert Key National 0.00

3. Safrial Rambe Structural Engineer Key National 0.00

2. Mulia Tobing Sewerage Engineer Key Natiomal 0.00

1. Burhanuddin Muhammad Sewerage Engineer Key National 0.00

2. Carlos De La Cruz WWTP / Construction Supervisor - Makassar Key International 0.00

1. Colin LeggCity Office Leader / Sewerage Construction

Supervisor - MakassarKey International 0.00

Original

Addend

um No.

1

Balance2017 2018 2019 2020

STAFFING SCHEDULE - MAKASSAR

No. Name PositionKey or Non

KeyNationality Input

Original/

Addendum No. 1

Period of Services Total Person Month

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 33

App E – Risalah Rapat

MINUTES OF MEETING

Ref : 5022160-036-0012

Meeting Subject : Inception and Monthly Progress Report Meeting

Day/Date of Meeting : Friday, December 29, 2017

Time : 09.00 – 11.00 WIT (West Indonesian Time)

Venue : Meeting Room of DSEH, DGHS Building 7fl.

ATTENDEES:

No Name Company Email Address Mobile Phone

1 Asri Indiyani Head on CPMU

2 Olsa Riharsya Member of CPMU

3 Brian Hayden PISC MSMIP

4 Benny Sihaloho PISC MSMIP

5 Wildan PISC MSMIP

6 Tharik Marzuki PISC MSMIP

7 Henry Pranadjaja PISC MSMIP

8 Treesnowati PISC MSMIP

9

10

Ref Discussion Item Action When Status

GENERAL

Mr. Brian Hayden as Acting TL introduced new experts that have recently mobilized by PISC namely: Wildan (Civil Engineer), Hendry (Mechanical Engineer) and Tresnowati (BME Specialist).

All coordination and discussions with personnel of CPMU will be arranged by Bu Asri first as Head of CPMU.

For financial tasks Bu Asri appointed Bu Osa as PIC to coordinate with PISC and Pa Tariq, the Financial Management Specialist.

PISC also mentioned that there will be an International Gender and Social Development and Social Safeguard Resettlement Expert mobilized during January 2018 to assist Satker PSPLP Sulsel

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 34

Ref Discussion Item Action When Status

and LG of Makassar in next socialization tasks for house connections.

The Inception Report and Monthly Progress Report #1 & #2 is accepted, approved by CPMU and can be printed by PISC with the amount according to the TOR requirement. The PIC personel to monitor PISC’s progress report is Pa Taufik.

PISC is currently preparing the Quarterly report that will be prepared not only for Project interest but also for ADB, Bappenas and MoF.

PISC will soon start to develop MSMIP website through the appointed MIS Speciualist and Bu Asri asked to coordinate with Directorate of the Integration of Settlement Infrastructure as an official institution for internal information/ communication in DGHS. The MIS expert that responsible for MSMIP’s website development will be mobilized on January 5, 2018.

CPMU remind PISC to prepare Final Layout for Jambi’s IPAL latest on week 2 of February 2018 as reference for LG in budget allocation for Earthworks in 2018.

CPMU will send letter to Satker PSPLP and LG to refresh their responsibility in MSMIP implementation project.

PISC proposed that there should be a progress meeting every two weeks

MAKASSAR

CPMU asks PISC to prepare Detail Schedule with dateline for LG of Makassar to decide final site status for IPAL (full site or half site scenarios). There will be special meeting in Makassar to discuss above matter and prepare MoM signed by all related parties.

The earthworks for IPAL in FY. 2017 is stopped and will be continued in FY. 2018. Dinas PU Makassar has blacklisted the contractor due their inability to handle the social problem during the construction.

The site for PS-A still refer to initial plan in City Hall Park. The plan for Parking Area design is not clear yet from LG and PISC are to continue to the plan based on the DED document.

There will be a small Worskhop on Friday January 5, 2018 to finalize the OE of C1 and C2’s Contract prior of approval by Director General

There is no detail location of 1.000 properties for Contract C2. The housings are not socialized yet

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 35

Ref Discussion Item Action When Status

by LG. Bu Asri proposed special meeting with LG for this and ask PISC to prepare the Maps for priorities areas.

There will be meeting with Satker PSPLP to split Contract B.

JAMBI

PISC will conducted Geotechnical and Topographical Survey in Week 2 of January 2018

In week 2, PISC propose to mobilise Surveyor and Cost Estimate to work together with PPK of Jambi.

Budget allocation for FY.2018 is already set up and PISC should adjust PQ schedule.

PEKANBARU

Idem with Jambi

Asri Indiyani Head of CPMU

……………………………………

Brian Hayden SMEC International Pty Ltd

……………………………………

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 36

MINUTES OF MEETING

Ref : 5022160-036-0013

Meeting Subject : Small Workshop - Preparation of Cost Estimator Document and PQ Document Contract C Makassar

Day/Date of Meeting : Wednesday-Thursday, December 13-14, 2017

Time :

Venue : Meeting Room Satker PSPLP Prov.Sulsel

ATTENDEES:

No Name Company Email Address Mobile Phone

1 Pong Silurang Ka Satker

2 Brian Hayden PISC MSMIP

3 Benny S PISC MSMIP

4 Sulikha PISC MSMIP

5 Supiyanto PISC MSMIP

6 Joko Roosmany Konsultan Satker

7

8

9

10

Ref Discussion Item Action When Status

A

Background

PSPLP Makassar working unit already budgeted 150

billion (advance payment) in FY 2017 for Contract C

work: North - West Waste Water Collection System,

Transfer System A, and Pressure Mains. The

implementation of prequalification can not be started

by Pokja Satker PSPLP Prop South Sulawesi this year

considering the supporting documents such as

BoQ/OE and Technical Drawings have not met the

rules set out in the PUPR Ministry standards as bidding

documents.

In addition, the value of Contract C package can not

be fulfilled by the existing national contractors

because it exceeds the basic capability (KD) so that it

is feared that there are no participants who register

prequalification.

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 37

Ref Discussion Item Action When Status

Objectives of workshop are as follows :

1. Review BoQ & Owner Estimate Contract C

Makassar work

2. Break the Contract C into C-1 and C-2 in order to

be implemented in accordance with the conditions

of the current national Contractor's capabilities.

3. Prepare the PQ document for both packages

above.

The results of the Workshop are as follows:

• Initial Condition: Contract C: North - West Waste

Water Collection System, Transfer System A, and

Pressure Mains with value USD 22,550 million or

Rp.322,465,000,000 (including 10% VAT)

• Currently the estimated value of KD for Contract

C, which is able to be met by contractors is Rp.

234.663.000.000 or USD 18,051,000 and this is

based on prior experience (Npt) of at least Rp

78.221.000.000 (The highest contract value of

2016) - S1009

• Proposed New contract value is USD 28,793,259 or

Rp. 374,312,371,000 (increase 16.08%) with

details as follows :

o Contract C-1: Transfer System A, Pressure

Mains and Main Pipe with value USD

12,648,044 or Rp. 164,424,568,000.

o Contract C-2: West Waste Water Collection

System (Lateral, Secondary, Tertiary and

1,000 connections) with a value of USD

16,145,216 or Rp. 209,887,803,000

The increase in the value of the Contract C package

is due to the adjustment of unit price from 2013 to

2017 and the addition of a trenchless pipe-fitting

method, where several paths on the protocol

roads that previously could be open cut, but

requests from the mayor to do so with trenchless

method.

New scope of works :

Contract C-1

o Supply, installation and testing of pressurized

pressure pipe pipelines, DN225 (along ± 300

m '), DN762 (along ± 209 m') and DN 900

(along ± 2,321 m ') with open cut construction

and trenchless.

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 38

Ref Discussion Item Action When Status

o Supply, installation and testing of the main

waste water pipe DN 450 (along ± 608 m '),

DN 600 (along ± 646 m'), DN 750 (along ± 613

m ') DN900 (along ± 419 m') and DN 1,050

(along ± 2,997 m ') with open cut construction

and trenchless.

o Construction of Pump House A (with its

equipment) of 1 unit.

o Supply, installation and testing of

Maintenance Manhole of ± 44 units.

o Reconditions and repairing of asphalt road (±

3,707 m2), concrete road (± 1,550 m2), and

paving road (± 500 m2)

Contract C-2

o Supply, installation and testing of lateral,

secondary and tertiary DN100 wastewater

pipe (as long as ± 7,500 m '), DN 150 (along ±

18,050 m'), DN225 (along ± 675 m ') and

DN375 (along ± 1335 m') with open

excavation and non excavation / drilling

o Supply, installation and testing of

Maintenance Manhole of ± 468 units.

Reconditions and repair of asphalt road (± 5,863

m2), concrete road (± 1,520 m2), and macadam

(± 2,168 m2)

Action Plan :

Satker PSPLP and PISC and will present the results of

this workshop to the CPMU for approval including

approval from the Director General of Cipta Karya for

the value of Contract C-1 and C-2 packages and

subsequently become the tender document for Pokja

MSMIP Makassar.

Pong Silurang Kasatker

……………………………………

Brian Hayden SMEC International Pty Ltd

……………………………………

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 39

MINUTES OF MEETING

Ref : 5022160-036-0014

Meeting Subject : Socialization of IPAL Losari

Day/Date of Meeting : Wednesday, December 14, 2017

Time :

Venue : Hotel Sheraton Makassar (Four Points), Jl. Landak Baru Kota Makassar

ATTENDEES:

No Name Company Email Address Mobile Phone

1 Suharsono Adi

Broto

Kasubdit Pengelolaan

Air Lmbah

2 Imbang Muryanto Ka.Bid Infrastruktur

Pengembangan

Wilayah Bappeda

Kota Makassar

3 Selvi Hehanusa Sanitation Expert

IUWASH Plus

Makasar

4 Benny Sihaloho Deputy TL of PISC

MSMIP

5 Supiyanto PISC MSMIP

6 Joko Roosmany Konsultan Satker

7 Camat dan Lurah di 6 Kecamatan yang terdampak Proyek MSMIP

8 LPM/LSM dan Penggerak PKK di 6 Kecamatan yang terdampak Proyek MSMIP

9 SKPD Terkait (Dinas PU, Bappeda, Dinas Kesehatan, Dinas Perhubungan, Dinas Lingkungan

Hidup, UPT SPAL Makassar, Telkom, PLN, Indosat, PDAM)

10

Ref Discussion Item Action When Status

Background

Satker PS-PLP of South Sulawesi Province will start the

construction of sewerage and WWTP for Makassar

City. As a first step to get the support of the parties

especially at the city level, the Satker PS-PLP of South

Sulawesi Province as the executor of the activities at

the provincial level as well as responsible in the

construction of sewerage and WWTP both directly

financed from APBN 2017-2020, ADB (Asian

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 40

Ref Discussion Item Action When Status

Development Bank) Loan fund will carry out

socialization.

The objective of this workhop is to inform the related

stakeholders the plan of the Makassar City

Government assisted by the DGHS Ministry PWH to

build sewerage and WWTP to meet the target of 100%

viable sanitation access by 2019.

The socialization is divided into 4 (four) sessions

namely :

1. Wastewater Policy and Design of WWTP,

2. Planning Sanitation Program Makassar City,

3. The Role of IUWASH Plus in the Makassar City

Sanitation Program, and

Centralized SPAL Development Plan of Makassar City

through the MSMIP ADB Loan 3123-INO project.

Where this session was delivered by the PISC

Consultant (Project Implementation Support

Consultant).

Questions and Answers at Session 4th :

Jamal (PDAM Kota Makassar)

o Is there a plan to utilize the IPAL Losari

effluent for the fulfillment of drinking water

needs in Makassar City? There is no plan from

the Project to recommend the utilization of

WWTP Losari effluent. However, for the long

term if the raw water source is very limited it

can be done but for the limited purpose and

not for the direct consumption of the

community.

o PDAM supports MSMIP program by preparing

the existing pipeline pipeline network map to

synchronize and not overlap during

construction.

o To distinguish between drinking water pipes

and waste water pipes with different colors.

o For HH (house connections), what is the pipe

diameter and depth of pipe installation how

many meters? For the pipe diameter at the

connection of the house at least 3 "and the

depth varies slightly depending on the level

position of toilet and kitchen/bathroom, but

the slope of the pipe is planned 2%.

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 41

Ref Discussion Item Action When Status

Hasanuddin (Arkansi)

o In Makassar there are 127 units of communal

IPAL which are mostly not functioning

because of many factors. What assurance

does not suffer the same fate MSMIP project

with communal WWTP current? The design

and construction of the MSMIP pipeline will

installed made as best as possible based on

the technical standards and the principles

construction. The PISC will be strictly

monitoring from the planning stage to

construction and testing. However, no less

important is the good operational and

maintenance system, where the management

in this case UPTD Air Waste Makasar has the

ability to operate and maintain and

guarantee the availability of adequate OM

budget which while these two things above is

not owned by the communal IPAL

management.

o For houses that already have Septic Tank, can

the new waste water pipe connect to Septik

Tank? Influent pipe from Septic Tank can be

connected with waste water pipe, but also

note that besides waste from the toilet (black

water) will also be treated waste water from

kitchen and bathroom.

Ibu Sari (PKK Kel. Pasang Utara):

o PKK supports the wastewater program to be

built in their houses, but questioned is if there

was a blockage in the toilets that would be

problem overwhelmed everywhere. PISC said

that with good design followed by supervision

during construction will get good result. But

be reminded to keep flushing at least 2 scoops

after throwing water so that feces waste can

be wasted into the pipe

o What about the old pipes that already exist

today, whether to close or what?. Old pipe

will not be used, because either from the toilet

or from the bathroom and the kitchen will be

Metropolitan Sanitation Management Investment Project

Laporan Bulanan No. 2, Desember 2017 42

Ref Discussion Item Action When Status

replaced with pipes connected directly to the

pipe to the manhole on the street front

Jamal (LPM Manyang)

o Is the number of HH 14,000 units is enough

with a WWTP capacity of 19,100 m3/day.?

The consultant has calculated wastewater

generation based on drinking water

consumption and the ratio of the number of

people per household.

Edward/LPM Parerengan

o Socialization has been done several times,

but still needed more detailed socialization

to the people who will connect.

Asri Indiyani Head of CPMU

……………………………………

Brian Hayden SMEC International Pty Ltd

……………………………………