Installation Instructions for SEL-TPR
Transcript of Installation Instructions for SEL-TPR
Installation Instructions for SEL-TPR3-Phase, Remote Large Target, 600 A Junction Shield
25-0217.A
Page 1 of 2
SCHWEITZER ENGINEERING LABORATORIES, INC.2350 NE Hopkins Court • Pullman, WA 99163-5603 U.S.A.Phone: +1.509.332.1890 • Fax: +1.509.332.7990selinc.com • [email protected]
Install the Display
Install the Internal Adapter Ring (if Required) and the Phase Sensor(s)➤ Elastimold 15, 25, and 35 kV PCE elbows with molded test points require the internal adapter rings. Complete Steps A–H.
➤ Hubbell, Chardon, RTE, Cooper, or GE-Chardon elbows with molded test points do not require the adapter ring. Complete Steps E–H only.
=
➤ Mount the stainless-steel bracket to position the “L” display for optimum viewing.
➤ Use the integral threaded stud and hex nut to mount the display to the bracket. Hand tighten the hex nut. Do not overtighten.
Note: Optional Display Panel Mount Kits are sold separately. Consult the factory for ordering information.
Internal adapter ring Fold into a “U” shape Align the ridge with the groove Release the “U” shape and press the ridge into the groove
Ø2.0 (Ø50)
7.7(195)
3.2(83)
3.7(95)
∅2.5(∅64)
1.7 (43)
APPROX< 2.5(65)
Before installation of fault indicators and sensors, read and understand all instructions in their entirety. For assis-tance, contact Customer Service at (509) 332-1890 or by email at [email protected].
CAUTIONInstall fault indicators and sensors in accordance with normal safe operating practices. These instructions are not intended to replace or supersede exist-ing safety or operating requirements. Only trained qualified personnel should install or operate fault indicators and sensors.
Hex Nut
“L” Display
Stainless-Steel Bracket
Ridge
A B
Ridge
RidgeGroove
C D
25-0217.A
Page 2 of 2
SCHWEITZER ENGINEERING LABORATORIES, INC.2350 NE Hopkins Court • Pullman, WA 99163-5603 U.S.A.Phone: +1.509.332.1890 • Fax: +1.509.332.7990selinc.com • [email protected]
Installation Instructions for SEL-TPR 3-Phase, Remote Large Target, 600 A Junction Shield
Remove the test point cap. Clean and dry the test point. Apply a sili-cone dielectric grease to the inside
of the sensor boot.
Position one junction arm around the elbow. Use a sliding
motion to move the junction arm behind the cable.
When both junction arms are around the cable, slide the phase sensor up to the test point of the
T-Body.
Use a push/twist motion to seat the phase sensor on the test
point.
Magnetic Cable Guides hold cables and leads neatly within the enclosure.
Catalog Number: MCG
Test Point Cap
E F G
Test Point
H