2007 - Sverrir 1 ENGINE Mid-Term Conference 10-12 January 2007, Potsdam Developments in Geothermal Drilling Sverrir Thorhallsson Head of Engineering Department ÍSOR Iceland GeoSurvey [email protected]

Transcript of Geothermal Drilling Course - ENGINEengine.brgm.fr/web-offlines/conference-Mid-Term_Conference... ·...

Page 1: Geothermal Drilling Course - ENGINEengine.brgm.fr/web-offlines/conference-Mid-Term_Conference... · Geothermal Drilling ... Drilling “blind” after total loss of circulation. 5.

2007 - Sverrir1

ENGINE Mid-Term Conference 10-12 January 2007, Potsdam

Developments in

Geothermal DrillingSverrir Thorhallsson

Head of Engineering DepartmentÍSOR Iceland GeoSurvey

[email protected]

Page 2: Geothermal Drilling Course - ENGINEengine.brgm.fr/web-offlines/conference-Mid-Term_Conference... · Geothermal Drilling ... Drilling “blind” after total loss of circulation. 5.

2007 - Sverrir2

Outline

Page 3: Geothermal Drilling Course - ENGINEengine.brgm.fr/web-offlines/conference-Mid-Term_Conference... · Geothermal Drilling ... Drilling “blind” after total loss of circulation. 5.

2007 - Sverrir3

Geothermal drilling methods

Various methods found in geothermal drilling.Yellow indicate the most common ones.

Page 4: Geothermal Drilling Course - ENGINEengine.brgm.fr/web-offlines/conference-Mid-Term_Conference... · Geothermal Drilling ... Drilling “blind” after total loss of circulation. 5.

2007 - Sverrir4

Icelandic Geothermal Drilling IndustryNational companies for:

- Jardboranir hf. for drilling deep wells. 4 drilling contractors in all.- Cementing, fishing etc. done by the drilling contractor.- Iceland GeoSurvey for geoscientific services and logging.- Consulting engineering companies for tendering and supervision.

International companies for:- Mud motors, MWD.- Aerated drilling.

Pre-drilling with a truck mounted rig-Surface casing 60-90 m, drilled dia. 24“- 28" with air-hammers.

Water used as drilling fluid whenever possible.Only large losses are cemented (>10 l/s).No delays due to coring. No cores taken.Logging or testing only at casing points.Rigs and crew only drill geothermal wells.

Page 5: Geothermal Drilling Course - ENGINEengine.brgm.fr/web-offlines/conference-Mid-Term_Conference... · Geothermal Drilling ... Drilling “blind” after total loss of circulation. 5.

2007 - Sverrir5

Geothermal drilling rigs in Iceland

Sleipnir

Trölli

Jötunn

Óðinn JB 4000 m

Geysir JB 4000 m

Jötunn JB 3300 m

Sleipnir JB 2400 m

Nýr bor RFS 1600 m

Saga JB 1350 m

Trölli RFS 1100 m

Langþr. RFS 600 m

Glámur RFS 600 m

Einráður RFS 500 m

Ýmir JB 1000 m

Hrímnir JB 300 m

Alvarr 300 m

Trítill RFS 120 m

Page 6: Geothermal Drilling Course - ENGINEengine.brgm.fr/web-offlines/conference-Mid-Term_Conference... · Geothermal Drilling ... Drilling “blind” after total loss of circulation. 5.

2007 - Sverrir6

Temperature profiles - ICELAND

Ref: Guðmundur Pálmason

Dep

th (m

)

Page 7: Geothermal Drilling Course - ENGINEengine.brgm.fr/web-offlines/conference-Mid-Term_Conference... · Geothermal Drilling ... Drilling “blind” after total loss of circulation. 5.

2007 - Sverrir7

Casing profiles of Icelandic geothermal wells

High temp. Low temp.

Page 8: Geothermal Drilling Course - ENGINEengine.brgm.fr/web-offlines/conference-Mid-Term_Conference... · Geothermal Drilling ... Drilling “blind” after total loss of circulation. 5.

2007 - Sverrir8

Drilling methods used in Iceland

Rotary Hammer Odex Holte Pressure bal.

Mostcommon

Simlutaneouscasing

Aerateddrilling

Page 9: Geothermal Drilling Course - ENGINEengine.brgm.fr/web-offlines/conference-Mid-Term_Conference... · Geothermal Drilling ... Drilling “blind” after total loss of circulation. 5.

2007 - Sverrir9

Vertical vs. directional drillingThe casingprogrammes arevirtually the same.The build-up starts at the kick off point (KOP) at 300-500 m.

Inclination of 30-40° is common in geothermalwells.

Page 10: Geothermal Drilling Course - ENGINEengine.brgm.fr/web-offlines/conference-Mid-Term_Conference... · Geothermal Drilling ... Drilling “blind” after total loss of circulation. 5.

2007 - Sverrir10

Main Types of Low Temp. Wells• Temperature gradient wells

– Depth 40-100 m (used in Iceland for exploration)– Well diameter 3-4", plastic liner HDPE where neededCost 150 €/m

• Production wells– Depth 400-2000 m– Casing sizes, mainly three diameters for production

casing 14", 10 3/4" and 8 5/8" or 7 5/8".– Casing depth í 150-800 m. Barefoot - no liner.– Cost 500-1000 €/m

Page 11: Geothermal Drilling Course - ENGINEengine.brgm.fr/web-offlines/conference-Mid-Term_Conference... · Geothermal Drilling ... Drilling “blind” after total loss of circulation. 5.

2007 - Sverrir11

Main Types of High Temp. Wells• Typical well profile:

– Depth of well 1200-2800 m– Production casing depth 600-1100 m– Production casing dia. 9-5/8", liner 7" or 7-5/8"– Cost 1200-1800 €/m. For 2500 m, 4 million €

• Large diameter well profile:– Depth of well 1200-3000 m– Production casing depth 600-850 m– Production casing dia. 13-3/8", liner 9-5/8" or barefoot– Cost 1500-2000 €/m

Page 12: Geothermal Drilling Course - ENGINEengine.brgm.fr/web-offlines/conference-Mid-Term_Conference... · Geothermal Drilling ... Drilling “blind” after total loss of circulation. 5.

2007 - Sverrir12

HT drilling activity in Iceland1958 1962 1966 1970 1974 1978 1982 1986 1990 1994 1998 2002 20060

500

1000

1500

2000

2500

3000

Leng

d ho

lu (m

)

Samtals 144 háhitaholur lengri en 500 mSverrir 2006-02-17

Mea

sure

d de

pth

(m)

144 wells deeper than 500 m

Page 13: Geothermal Drilling Course - ENGINEengine.brgm.fr/web-offlines/conference-Mid-Term_Conference... · Geothermal Drilling ... Drilling “blind” after total loss of circulation. 5.

2007 - Sverrir13

Drilling progress – days vs. depth

0 5 10 15 20 25 30 35 40 45 50 55 60 65 703000

2500

2000

1500

1000

500

00 10 20 30 40 50 60 70

Sverrir 03.05.2004

New bitincl. 5 days waitingfor csg. shipment

Days

Days from start of rig move

No linerOpen hole Slotted

liner inst.Stimulation

Rig move

Drilling12-1/4"

Runing production casing13-3/8" and cementing

Runing anchor casing and cementing

Drilling 21-1/2"

Drilling 17-1/2"

Conventional rotary drilling Drilling with mud motor to TD

Dep

th (m

)

Note:Doubling of ROPwhen drilling withmud motor.

Trouble free drilling.

Few bit changes.

Page 14: Geothermal Drilling Course - ENGINEengine.brgm.fr/web-offlines/conference-Mid-Term_Conference... · Geothermal Drilling ... Drilling “blind” after total loss of circulation. 5.

2007 - Sverrir14

WellCost

Geothermalwells are moreexpensive thanoil and gas wellsof the same depth

2500 m well2.5 million €in 2004, now~3.5 million €

Ref: Tester et al 2006

Page 15: Geothermal Drilling Course - ENGINEengine.brgm.fr/web-offlines/conference-Mid-Term_Conference... · Geothermal Drilling ... Drilling “blind” after total loss of circulation. 5.

2007 - Sverrir15

The cost is higher due to:• Directional drilling with a mud motor and

measurement while drilling (MWD) and gyro.• Drilling rig with a top-drive.• Aerated drilling fluid. Extra compressors.• Using premium casing connections.• Using cementing services from the oil industry.• Logging services from the oil industry.• Mobilization for only a few wells.

Page 16: Geothermal Drilling Course - ENGINEengine.brgm.fr/web-offlines/conference-Mid-Term_Conference... · Geothermal Drilling ... Drilling “blind” after total loss of circulation. 5.

2007 - Sverrir16

Rig control consolesOld type:SCR-DC motor contr.Rig with rotary table.

Photo: Sverrir Thorhallsson

New:All hydraulic rig.Iron roughneck.

Page 17: Geothermal Drilling Course - ENGINEengine.brgm.fr/web-offlines/conference-Mid-Term_Conference... · Geothermal Drilling ... Drilling “blind” after total loss of circulation. 5.

2007 - Sverrir17

Jarðboranir hf.

Page 18: Geothermal Drilling Course - ENGINEengine.brgm.fr/web-offlines/conference-Mid-Term_Conference... · Geothermal Drilling ... Drilling “blind” after total loss of circulation. 5.

2007 - Sverrir18 Jarðboranir hf.

Ironroughneck Top

drive

Page 19: Geothermal Drilling Course - ENGINEengine.brgm.fr/web-offlines/conference-Mid-Term_Conference... · Geothermal Drilling ... Drilling “blind” after total loss of circulation. 5.

2007 - Sverrir19

Hook Loadvs. Depth

0 500 1000 1500 2000 25000

20

40

60

80

100

5"4 1/2"4"3"

S.Þ. 1.12.2001

Hook load vs. depth capacity

13 3/8"

9 5/8"

7"

5"

4 1/2"

4"3"

Rig #2 with S.F.

Rig #2 hook loadrating 50 t

Rig #1 with safety factor 1.33 S.F.

Rig #1 hook load rating 100 t

Wei

ght i

n w

ater

(ton

nes)

Depth (m)

Casings 20 t weight on bit 10 t weight on bit

The diagram showshow deep a rig candrill, based on thehook load rating.

Example.100 tons rig can reach2300 m with 5" drillpipe2700 m with 4-1/2" dp

Page 20: Geothermal Drilling Course - ENGINEengine.brgm.fr/web-offlines/conference-Mid-Term_Conference... · Geothermal Drilling ... Drilling “blind” after total loss of circulation. 5.

2007 - Sverrir20

Jarðboranir hf.

200 t

Page 21: Geothermal Drilling Course - ENGINEengine.brgm.fr/web-offlines/conference-Mid-Term_Conference... · Geothermal Drilling ... Drilling “blind” after total loss of circulation. 5.

2007 - Sverrir21

“SLEIPNIR“SLEIPNIR”

Jarðboranir hf.

100 t

Page 22: Geothermal Drilling Course - ENGINEengine.brgm.fr/web-offlines/conference-Mid-Term_Conference... · Geothermal Drilling ... Drilling “blind” after total loss of circulation. 5.

2007 - Sverrir22

“SLEIPNIR

“SAGA”

Jarðboranir hf.

50 t

Page 23: Geothermal Drilling Course - ENGINEengine.brgm.fr/web-offlines/conference-Mid-Term_Conference... · Geothermal Drilling ... Drilling “blind” after total loss of circulation. 5.

2007 - Sverrir23

Three Cement Tanks, 50 m3 eachCROWN single skid cementing unit. The unit is comprised of a high-pressure pumping system, recirculating mixing system, all required controls, instrumentation and a hydraulic system to drive fluid handling and mixing.The system includes CAM - Continuous Automatic Mixing, which is a computer operated cement density control system with features like:Automatic Density ControlPre-job system checkReal time data storage of density, pump rate, total volume and pressureStores three cement slurry designs

Cementing unit - from drilling contr.

Jarðboranir hf.

Page 24: Geothermal Drilling Course - ENGINEengine.brgm.fr/web-offlines/conference-Mid-Term_Conference... · Geothermal Drilling ... Drilling “blind” after total loss of circulation. 5.

2007 - Sverrir24

Output curves for wells in Iceland13 3/8”

9 5/8”

Page 25: Geothermal Drilling Course - ENGINEengine.brgm.fr/web-offlines/conference-Mid-Term_Conference... · Geothermal Drilling ... Drilling “blind” after total loss of circulation. 5.

2007 - Sverrir25

Icelandic bid formsDrilling of a vertical geothermal well to 2500 m

Cased to: 50 m/ 450 m/ 1000 m/ TD 2500 m

Number Work Item Unit Unit price Quantity Sum total

III.1 TransportationIII.1.1 Preparations, mobilisation and demobilisation total 0 1 0III.1 Transportation Total: 0

III.2 Specific site preparation for drillingIII.2.1 Site preparation changing from pre-drilling to drilling(cellar, mu total 0 1 0III.2 Specific site preparation for drilling Total: 0

III.3 Drilling of a straight vertical wellIII.3.1 Drilling operation:III.3.1-A Drilling with ø 24” drill bit

Fixed price total 0 1 0Price per meter drilled m 0 50 0

III.3.1-B Drilling with ø17½” drill bitFixed price total 0 1 0Price per meter drilled m 0 400 0

III.3.1-C Drilling with ø12¼” drill bitFixed price total 0 1 0Price per meter drilled m 0 550 0

III.3.1-D Drilling with ø8½” drill bitFixed price total 0 1 0Price per meter drilled m 0 1,500 0

III.3.1 Drilling operation: Total: 0

III.3.2 Casing runing servicesIII.3.2-A ø18 5/8” casing m 0 50 0III.3.2-B ø13 3/8” casing m 0 450 0III.3.2-C ø9 5/8” casing m 0 1,000 0III.3.2-D ø7” liner m 0 1,500 0III.3.3 Casing runing services Total: 0

Page 26: Geothermal Drilling Course - ENGINEengine.brgm.fr/web-offlines/conference-Mid-Term_Conference... · Geothermal Drilling ... Drilling “blind” after total loss of circulation. 5.

2007 - Sverrir26

Some “Problems” of Geothermal Drilling1. High cost of geothermal wells.2. Well sites in protected areas. Permitting.3. Large loss of circulation zones.4. Drilling “blind” after total loss of circulation.5. Slow drilling in hard lava formations.6. Well stability during drilling.7. Wells with low permeability / low output.8. High pressures while drilling through a steam cap.9. Temperature limitations of logging tools.

Page 27: Geothermal Drilling Course - ENGINEengine.brgm.fr/web-offlines/conference-Mid-Term_Conference... · Geothermal Drilling ... Drilling “blind” after total loss of circulation. 5.

2007 - Sverrir27

Conclusions• New top-drive rigs with “iron roughnecks”,

directional drilling + MWD and instrumentation are a part of a modern drilling operations.

• Better environment: noise, wastes, mud disposal.• Big diameter casings are required for large flows.• Incentive drilling contracts have lead to improved

drilling efficiency.• Standardized well designs and uninterrupted

drilling operations will lead to lower costs.

Page 28: Geothermal Drilling Course - ENGINEengine.brgm.fr/web-offlines/conference-Mid-Term_Conference... · Geothermal Drilling ... Drilling “blind” after total loss of circulation. 5.

2007 - Sverrir28

REMINDER: ENGINE Workshop (WP4)

See you in Reykjavík, June 28-29

Drilling cost effectiveness and

feasibility of high-temperature drilling