Frankfurt (Germany), 6-9 June 2011 Economic assessment of PQ solutions Helge SELJESETH – Norway...
-
Upload
gregory-white -
Category
Documents
-
view
214 -
download
1
Transcript of Frankfurt (Germany), 6-9 June 2011 Economic assessment of PQ solutions Helge SELJESETH – Norway...
Frankfurt (Germany), 6-9 June 2011
Economic assessment of PQ solutions
Helge SELJESETH – Norway – RT 2b – Economic assessment of PQ solutions
Frankfurt (Germany), 6-9 June 2011
Customer(s)complaint(s)
Evaluation/ verification of complaint(s) (measurements)
NO
NONo actionrequired
In compliance with nat.reg.(or int. std.)
May PQmitigation/solutions be economic? YES
Selecting thebest eco./tech.compromise
YES
Statistical PQmeasurement
Frankfurt (Germany), 6-9 June 2011
Examples of PQ solutions Network reinforcements Thicker lines/cables Larger transformer Increased system voltage etc
Voltage booster STATCOM Synchronized switches Petersen coils/Arc suppression coils Local production (may be both at problem and a solution) Grounding Surge arrestors Protection circuits and adjusting/tuning protection circuits Passive filters/Active filters Maintenance level Uninterruptible power supplies – UPS Soft starters and frequency converters Emergency generators ETC…
Frankfurt (Germany), 6-9 June 2011
Considerations selecting PQ solution:
Technical reasons
Economic reasons
(Environmental / Esthetic reasons)
Frankfurt (Germany), 6-9 June 2011
Relative consequences of voltage disturbances for different customer categories in Norway (1993 – 2010)
REPORT for: Council of European Energy Regulators (CEER)
Study on Estimation of Costs due to Electricity Interruptions and Voltage Disturbances
Frankfurt (Germany), 6-9 June 2011
Results from customer surveys give a better foundation for optimisation of power quality
Planning of power systems (expansions...) Basis for concession applications, justifications of investmens etc
Operation and maintenance Cost-benefit of PQ improving measures, priorities for load shedding,
contingency planning, preventive maintenance etc Policies, standards and criteria for PQ
Guaranteed PQ levels, contracts, softened N-1 criterion etc. Monitoring PQ
Actual levels vs standards, expectations etc PQ regulation (taking explicitly account of PQ costs)
Incentive based regulation, penalty schemes etc.
Frankfurt (Germany), 6-9 June 2011
Total costs VS customer costs (net costs)
Total socio-economic
costsPrivate
customer costs(net costs)
Net coststo rest of society Monetary
- Direct- Indirect
Monetary- Direct- Indirect
Non-monetary- Direct- Indirect
Non-monetary- Direct- Indirect
Total socio-economic costs of quality problems in electricity supply
Frankfurt (Germany), 6-9 June 2011
Real life experiences
Some times quite easy decision Easy to see what is the economic solution
Some times very difficult to make a decision purely on economic evaluation Difficult to specify the costs for low PQ (flicker, RVC)
Frankfurt (Germany), 6-9 June 2011
10
Location 1 Location 2
Year (1) (2) (3) (1) (2) (3)
1990 91 40 5 94 35 4
1991 145 39 8 100 60 1
1992 106 84 4 101 27 5
1993 49 0 1 61 22 3
1994 75 0 5 61 15 2
1995 110 0 4 59 20 3
1996 203 0 7 100 245 1
1997 113 0 8 124 0 1
1998 156 1 0 110 0 0
1999 114 0 5 33 1 2
1 Temporary earth faults – self extinguishing faults.2 Temporary earth faults causing short interruption – auto reclosure. 3 Sustained earth faults.4 Peterson coil in operation in location 1 from medio August 1992.5 Peterson coil in operation in location 2 from ultimo August 1996.
Petersen coil(Arc suppression coil)
Frankfurt (Germany), 6-9 June 2011
Increase the voltage at the far end of distribution lines
An alternative to distribution network reinforcements
http://www.magtech.no/
Voltagebooster
Frankfurt (Germany), 6-9 June 2011
GAS treatment and export plant
2-side supply (ring) Interruptions do not often occur The plant trips several times per year due to network related events
- mainly voltage dips. The events causing trip are mainly supplied through only one of the
supplying lines -> single sided supply would have reduced the number of plant trip to less than half
The reason for the events are to a significant extent the network configuration
The most economic solution would be to supply the plant from one side only if only the available power was high enough
Frankfurt (Germany), 6-9 June 2011
2 cases of flicker from harmonic voltages
What is the cost of flicker? How bad must the conditions be before
mitigation must be performed? In both these cases the limit value value
for Plt of EN50160 and both Pst and Plt of the Norwegian PO regulations were not exceeded.