Fibre Carbon - Tensile Test (Unidirection)
Transcript of Fibre Carbon - Tensile Test (Unidirection)
-
7/28/2019 Fibre Carbon - Tensile Test (Unidirection)
1/5
TENSILE TEST FOR CARBON FIBER REINFORCED PLASTIC (UNIDIRECTION)
The tensile test was carried out according to the British Standard Aerospace SeriesBS EN 2561:1996 Carbon fibre reinforced plastics. The test was arranged at TESTECH SDN
BHD located at Selangor State.
The test was required to determine the characteristic or the properties of the carbon fibre E200
which proposed to strengthen the R.C deck slab.
Tensile Strength (MPa): 3300
Ultimate elongation (%): 1.4
Modulus of elasticity (GPa): 200
The carbon fibre E200 was camped by tensile machine with the
vertically checked to ensure the unidirectional test was carried
out. The pulling speed was preset at 2mm per min.
Specimens preparation
The specimen was cut into the 10mm width and 250 1 mm.
Both ends were bonded with the end tabs with epoxy to ensure
the griping during the pulling force applied.
-
7/28/2019 Fibre Carbon - Tensile Test (Unidirection)
2/5
The test specimen was test to failure, until the specimen was brittle.
-
7/28/2019 Fibre Carbon - Tensile Test (Unidirection)
3/5
PULL OFF TEST ON CARBON FIBRE SYSTEM
The tests are carried out on actual structural members strengthened with the composite Carbonfibre system. Although there are variations in the equipment for carrying out pull-off tests, the
general procedure can be summarized as follows:
1. After the composite strengthening system has hardened, core drill through the compositematerial and down 3 6 mm into the concrete substrate by means of an electric drill
fitted with a carbide-tipped or diamond core bit. The core bit should be of such size as toproduce a core the same diameter as the testing dolly, and which will have the appearance
of a small island of composite material. The normal size of the dolly is 50 mm diameter.Ensure that the drilling operation does not cause any detrimental effects on the system by
using wet drill techniques to minimise heat exposure, and ensure it is perpendicular to the
surface.
2. Prepare the top of the core surface to be tested. Preparation includes cleaning of thecomposite material surface, roughening it with sandpaper, and final cleaning of any dust.
-
7/28/2019 Fibre Carbon - Tensile Test (Unidirection)
4/5
4. Allow epoxy adhesive to cure sufficiently (usually 24 hours or as required).5. Zero the machine and increase the load until a specified level is reached or the specimen
fails.
6. At failure, the maximum pull-force is registered and the pull-off tensile strength iscalculated by dividing the force by the cross-sectional area of the core. The mode of
failure shall be recorded i.e., within the concrete substrate, within the composite material,
between substrate and composite material, between composite material and dolly, or any
combination of the above.
7. Pull-off tests shall be carried out on each selected area. The average of the values shall betaken as a pull-off strength result.
-
7/28/2019 Fibre Carbon - Tensile Test (Unidirection)
5/5
DATE TEST NO.
MATERIAL TYPEAGE OF
MATERIALSGauge
Reading
(N/Sq.mm)
Test size
sq. (mm)
Test Area,
A (sq.mm)
Min.
Requirement
(Tensile
strength, Mpa)
Tensile
bond
strength
(Mpa)
Failure
ModeRemarks
A B A B
22-Jun-13(Carbon fiber)
Specimen 1concrete
Mapei -Adesilex PG2
- 4 days 5.66 60 3600 1.5 3.09 6 ACCEPTED
22-Jun-13(Carbon fiber)
Specimen 2concrete
Mapei -Adesilex PG2
- 4 days 3.46 60 3600 1.5 1.89 1 ACCEPTED
22-Jun-13(Carbon fiber)
Specimen 3concrete
Mapei -
Adesilex PG2- 4 days 6.16 60 3600 1.5 3.36 1 ACCEPTED
Fr equent of test = 2 nos per proj ect or 100m per 2 nos samples
Failure Mode (A= Existing Substrate , B= Repair material , C= dolly )
Failure Mode 1 100% Bond failure at dolly (100% B/C)
Failure Mode 2 100% Cohesive failure of repair material (100% B)
Failure Mode 3 100% Bond failure of repair material (100% A/B)
Failure Mode 4 Partial Bond failure and cohesive failure of repair material (.....% A/B, .....%B)
Failure Mode 5 Partial Bond failure and cohesive failure of existing substrate (.....% A/B, .....%A)
Failure Mode 6 100% Cohesive failure at dolly (100% A)
A = Existing Substrate ( R.C Slab)
B = Repair Material
C = dolly