EIA & EMP Report for Expansion of Brownfield...

550
GUJARAT NARMADA VALLEY FERTILIZERS & CHEMICALS LIMITED EIA & EMP Report for Expansion of Brownfield Ammonia, Urea Plant, New Aniline, TDI-MDI Blend, Water Soluble Fertilizers (NPK) and CPSU Plants at GNFC, Narmadanagar, Bharuch, Gujarat. NOVEMBER 2014 Kadam Environmental Consultants www.kadamenviro.com Environment f or Development

Transcript of EIA & EMP Report for Expansion of Brownfield...

  • GUJARAT NARMADA VALLEY FERTILIZERS & CHEMICALS LIMITED

    EIA & EMP Report for Expansion of Brownfield Ammonia, Urea Plant, New Aniline, TDI-MDI Blend, Water Soluble Fertilizers (NPK) and CPSU Plants at GNFC, Narmadanagar, Bharuch, Gujarat.

    NOVEMBER 2014

    Kadam Environmental Consultants www. k a da m e nv i r o . co m

    Environment for Deve lopment

  • M/S GUJARAT NARMADA VALLEY FERTILIZERS & CHEMICALS LTD.

    EIA & EMP REPORT FOR EXPANSION UNITS AT GNFC, BHARUCH QUALITY CONTROL

    KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER 2014 I

    M/S GUJARAT NARMADA VALLEY FERTILIZERS & CHEMICALS LTD.

    EIA & EMP Report for Expansion of Brownfield Ammonia, Urea Plant, New Aniline, TDI-MDI Blend, Water Soluble Fertilizers (NPK) and CPSU Plants at GNFC, Narmadanagar, Bharuch, Gujarat © Kadam Environmental Consultants (‘Kadam’), November, 2014

    This report is released for the use of the Gujarat Narmada Valley Fertilizers & Chemicals Ltd, Regulators and relevant stakeholders solely as part of the subject project’s Environmental Clearance process. Information provided (unless attributed to referenced third parties) is otherwise copyrighted and shall not be used for any other purpose without the written consent of Kadam.

    QUALITY CONTROL

    Name of Publication

    EIA & EMP Report for Expansion of Brownfield Ammonia, Urea Plant, New Aniline, TDI-MDI Blend, Water Soluble Fertilizers (NPK) and CPSU Plants at GNFC, Narmadanagar,

    Bharuch, Gujarat

    Project Number 1211731618 Report No. 1 Version 1 Released November

    2014

    DISCLAIMER

    Kadam has taken all reasonable precautions in the preparation of this report as per its auditable quality plan. Kadam also believes that the facts presented in the report are accurate as on the date it was written. However,

    it is impossible to dismiss absolutely, the possibility of errors or omissions. Kadam therefore specifically disclaims any liability resulting from the use or application of the information contained in this report. The

    information is not intended to serve as legal advice related to the individual situation.

  • M/S GUJARAT NARMADA VALLEY FERTILIZERS & CHEMICALS LTD.

    EIA & EMP REPORT FOR EXPANSION UNITS AT GNFC, BHARUCH QUALITY CONTROL

    KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER 2014 III

  • M/S GUJARAT NARMADA VALLEY FERTILIZERS & CHEMICALS LTD.

    EIA & EMP REPORT FOR EXPANSION UNITS AT GNFC, BHARUCH QUALITY CONTROL

    KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER 2014 IV

  • M/S GUJARAT NARMADA VALLEY FERTILIZERS & CHEMICALS LTD.

    EIA & EMP REPORT FOR EXPANSION UNITS AT GNFC, BHARUCH QUALITY CONTROL

    KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER 2014 V

  • M/S GUJARAT NARMADA VALLEY FERTILIZERS & CHEMICALS LTD.

    EIA & EMP REPORT FOR EXPANSION UNITS AT GNFC, BHARUCH QUALITY CONTROL

    KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER 2014 VI

  • M/S GUJARAT NARMADA VALLEY FERTILIZERS & CHEMICALS LTD.

    EIA & EMP REPORT FOR EXPANSION UNITS AT GNFC, BHARUCH QUALITY CONTROL

    KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER 2014 VII

  • M/S GUJARAT NARMADA VALLEY FERTILIZERS & CHEMICALS LTD.

    EIA & EMP REPORT FOR EXPANSION UNITS AT GNFC, BHARUCH TABLE OF CONTENT

    KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER 2014 VIII

    CONTENTS

    0 EXECUTIVE SUMMARY ................................................................................. 1

    0.1 PROJECT DESCRIPTION .............................................................................. 1 0.1.1 About the Company and Project Proponent ................................................. 1 0.1.2 About Project ..................................................................................... 1 0.1.3 Regulatory Framework .......................................................................... 1 0.1.4 Location of the Project .......................................................................... 2 0.1.5 Project Cost ....................................................................................... 2 0.1.6 Raw Materials and Source ...................................................................... 2 0.1.7 Utilities ............................................................................................. 2 0.1.8 Description of the Process ...................................................................... 3 0.1.9 Waste Water ...................................................................................... 4 0.1.10 Air Emissions...................................................................................... 4 0.1.11 Hazardous and Other Solid Wastes ........................................................... 4

    0.2 DESCRIPTION OF THE ENVIRONMENT ............................................................ 4 0.2.1 Study Period and Area .......................................................................... 4 0.2.2 Land Use of the Study Area .................................................................... 5 0.2.3 Climatology ....................................................................................... 5 0.2.4 Ambient Air Quality .............................................................................. 5 0.2.5 Noise ............................................................................................... 6 0.2.6 Surface Water and Ground Water Quality ................................................... 6 0.2.7 Soil ................................................................................................. 7 0.2.8 Biological Environment .......................................................................... 7 0.2.9 Air Emissions...................................................................................... 8 0.2.10 Waste Water Quality ............................................................................ 8 0.2.11 Solid / Hazardous Waste Management ....................................................... 8

    0.3 ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES................... 8 0.3.1 Air Environment .................................................................................. 8 0.3.2 Noise Environment ............................................................................... 9 0.3.3 Water and Waste Water ...................................................................... 10 0.3.4 Land Environment ............................................................................. 11 0.3.5 Biological Environment ........................................................................ 12 0.3.6 Socio-Economic Environment ................................................................ 12

    0.4 ENVIRONMENTAL MONITORING PROGRAMME ................................................ 12 0.5 ADDITIONAL STUDIES ............................................................................. 13

    0.5.1 Public Hearing .................................................................................. 13 0.5.2 Hazard Identification and Consequence Assessment .................................... 13 0.5.3 Onsite and Offsite Emergency Plan ......................................................... 14

    0.6 PROJECT BENEFITS ................................................................................. 14 0.7 ENVIRONMENTAL MANAGEMENT PLAN ......................................................... 15 0.8 CONCLUSION ........................................................................................ 17

  • M/S GUJARAT NARMADA VALLEY FERTILIZERS & CHEMICALS LTD.

    EIA & EMP REPORT FOR EXPANSION UNITS AT GNFC, BHARUCH TABLE OF CONTENT

    KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER 2014 IX

    1 INTRODUCTION ........................................................................................ 19

    1.1 PURPOSE OF THE REPORT ......................................................................... 19 1.2 IDENTIFICATION OF PROJECT AND PROJECT PROPONENT ................................. 19 1.3 BRIEF DESCRIPTION OF THE PROJECT AND ITS IMPORTANCE TO THE COUNTRY & REGION ....................................................................................................... 21

    1.3.1 Brief Description of Project ................................................................... 21 1.3.2 Importance of the Project to Country & Region .......................................... 22

    1.4 REGULATORY FRAMEWORK ....................................................................... 22 1.4.1 Environmental Clearance for Proposed Project ........................................... 22 1.4.2 Status of Environmental Clearances & CC&A/CTO for Existing Units .................. 23 1.4.3 Statutory Clearances and Other Permissions .............................................. 23

    1.5 SCOPE OF THE STUDY .............................................................................. 25

    2 PROJECT DESCRIPTION ............................................................................. 33

    2.1 TYPE OF THE PROJECT ............................................................................. 33 2.1.1 Condensed Description of Aspects .......................................................... 33

    2.2 NEED FOR THE PROJECT ........................................................................... 33 2.2.1 Ammonia ........................................................................................ 33 2.2.2 Urea .............................................................................................. 33 2.2.3 Aniline............................................................................................ 34 2.2.4 TDI-MDI Blend (TM Blend) ................................................................... 35 2.2.5 Water Soluble Fertilizer (NPK) ............................................................... 35 2.2.6 CPSU ............................................................................................. 35 2.2.7 Condensed Description of Aspects .......................................................... 35

    2.3 LOCATION ............................................................................................ 35 2.3.1 General Location of the Site .................................................................. 35 2.3.2 Specific Location of the Site with Project Boundary ...................................... 35 2.3.3 Location of Severely Polluted Area from Site .............................................. 39 2.3.4 Approach to the site ........................................................................... 39 2.3.5 Condensed Description of Aspects .......................................................... 40

    2.4 SIZE AND MAGNITUDE OF OPERATION ......................................................... 40 2.4.1 Condensed Description of Aspects .......................................................... 42

    2.5 RAW MATERIAL, STORAGE AND MODE OF TRANSPORT ...................................... 42 2.6 LIST OF SOLVENTS AND SOLVENT RECOVERY SYSTEM ...................................... 46

    2.6.1 Naphtha ......................................................................................... 46 2.6.2 Methanol ........................................................................................ 46 2.6.3 aMDEA (Activated Methyl Di-Ethanol Amine) .............................................. 46 2.6.4 ODCB (Ortho-Di-Chloro Benzene) ........................................................... 46

    2.7 UTILITY REQUIREMENT ............................................................................ 46 2.7.1 Fuel ............................................................................................... 46 2.7.2 Power Consumption ........................................................................... 47 2.7.3 Manpower Requirement ...................................................................... 48 2.7.4 Water ............................................................................................ 48

    2.8 PROJECT IMPLEMENTATION SCHEDULE ........................................................ 48

  • M/S GUJARAT NARMADA VALLEY FERTILIZERS & CHEMICALS LTD.

    EIA & EMP REPORT FOR EXPANSION UNITS AT GNFC, BHARUCH TABLE OF CONTENT

    KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER 2014 X

    2.9 TECHNOLOGY AND PROCESS DESCRIPTION ................................................... 49 2.9.1 Ammonia (Proposed) .......................................................................... 49 2.9.2 Urea (Proposed) ................................................................................ 55 2.9.3 Water Soluble Fertilizers (Proposed) ........................................................ 58 2.9.4 Aniline (Proposed) ............................................................................. 60 2.9.5 TDI – MDI (80:20) Blend (Proposed) ....................................................... 64 2.9.6 Cogeneration Power & Steam Unit (CPSU) - 45 MW ..................................... 66

    2.10 WATER CONSUMPTION, WASTE WATER GENERATION & DISPOSAL DETAILS ......... 67 2.10.1 Unit-I ............................................................................................. 67 2.10.2 Unit-II ............................................................................................ 87

    2.11 AIR EMISSIONS .................................................................................. 108 2.11.1 Point Source Emissions ...................................................................... 108 2.11.2 Area Source Emissions ....................................................................... 118 2.11.3 Line Source Emissions ........................................................................ 119 2.11.4 Fugitive Emissions ............................................................................ 119

    2.12 SOLID AND HAZARDOUS WASTE IDENTIFICATION, QUANTIFICATION, STORAGE AND DISPOSAL ................................................................................................... 121

    2.12.1 Quantification and Classification of Solid and Hazardous Wastes generated (Unit I) 121 2.12.2 Quantification and Classification of Existing and Proposed Solid and Hazardous Wastes (Unit-II) ......................................................................................... 129 2.12.3 Details of Hazardous Waste Handling, Storage, Utilization and Disposal ............ 139 2.12.4 Other Solids Wastes .......................................................................... 140

    2.13 PROJECT DESCRIPTION ........................................................................ 141 2.13.1 Land Distribution at Site ..................................................................... 141 2.13.2 Layout Plans of Proposed Plants............................................................ 146 2.13.3 Mitigation Measures at Design Stage ...................................................... 149

    2.14 ASSESSMENT OF NEW AND UNTESTED TECHNOLOGY .................................... 152

    3 DESCRIPTION OF THE ENVIRONMENT ........................................................153

    3.1 STUDY AREA ........................................................................................... 153 3.2 PERIOD ................................................................................................ 153 3.3 COMPONENTS.......................................................................................... 153 3.4 METHODOLOGY ........................................................................................ 153

    3.4.1 Primary data Collection ...................................................................... 153 3.4.2 Secondary Data collection ................................................................... 155

    3.5 ESTABLISHMENT OF BASELINE FOR VALUED ENVIRONMENTAL COMPONENTS AND BASE MAPS ....... 155 3.5.1 Long Term Meteorology ..................................................................... 155 3.5.2 Land Use ....................................................................................... 162 3.5.3 Ambient Air Quality ........................................................................... 170 3.5.4 Noise ............................................................................................ 184 3.5.5 Vibration ........................................................................................ 188 3.5.6 Hydrology and Groundwater ................................................................ 189 3.5.7 Geology ......................................................................................... 210

  • M/S GUJARAT NARMADA VALLEY FERTILIZERS & CHEMICALS LTD.

    EIA & EMP REPORT FOR EXPANSION UNITS AT GNFC, BHARUCH TABLE OF CONTENT

    KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER 2014 XI

    3.5.8 Soil .............................................................................................. 212 3.5.9 Ecology and Biodiversity ..................................................................... 219 3.5.10 Socio-Economics .............................................................................. 236

    4 ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES ........244

    4.1 INVESTIGATED ENVIRONMENTAL IMPACTS DUE TO THE PROPOSED PROJECT ........ 244 4.1.1 Assessment of Significance of Impacts .................................................... 244

    4.2 AIR ENVIRONMENT ................................................................................ 250 4.2.1 Sources of Emissions and Emission rates ................................................. 254 4.2.2 Fugitive Emissions & Control ................................................................ 262 4.2.3 Area Source Emissions ....................................................................... 262 4.2.4 Line Source Emissions ........................................................................ 263

    4.3 NOISE ENVIRONMENT............................................................................. 269 4.3.1 Noise Modeling Study ........................................................................ 269 4.3.2 Mitigation Measures to control Noise Emission ........................................... 270

    4.4 WATER ENVIRONMENT ........................................................................... 272 4.4.1 Ground Water ................................................................................. 272 4.4.2 Impact on Ground Water .................................................................... 272 4.4.3 Mitigation measure ........................................................................... 272 4.4.4 Surface / River Water ........................................................................ 272 4.4.5 Impact on Surface Water .................................................................... 272 4.4.6 Mitigation measure ........................................................................... 273

    4.5 LAND USE AND LAND COVER ..................................................................... 277 4.5.1 Site Preparation ............................................................................... 277 4.5.2 Green Belt Development ..................................................................... 277 4.5.3 Mitigation Measures for Impact on Land Use / Land Cover ............................ 277

    4.6 SOIL CONSERVATION ............................................................................. 279 4.6.1 Mitigation Measures for Soil Conservation ................................................ 279

    4.7 ECOLOGY AND BIODIVERSITY ................................................................... 283 4.8 SOCIO ECONOMIC ................................................................................. 285 4.9 OCCUPATIONAL HEALTH AND RISK ............................................................. 288

    4.9.1 General Safety Measures .................................................................... 288 4.9.2 Mitigation Measures .......................................................................... 288

    5 ANALYSIS OF ALTERNATIVES ....................................................................292

    5.1 SITE ALTERNATIVE .................................................................................... 292 5.1.1 At Existing Site ................................................................................ 292 5.1.2 At New Site, Dahej............................................................................ 293

    5.2 ANALYSIS OF ALTERNATIVE RESOURCES & TECHNOLOGIES ........................................... 293 5.2.1 Ammonia Technologies ...................................................................... 293 5.2.2 Urea Technology .............................................................................. 294 5.2.3 Innovation in Unconventional Technologies in Ammonia production ................. 295

    5.3 NOTE ON VIABILITY OF THE PROJECT IN ABSENCE OF AVAILABILITY OF NATURAL GAS .............. 295

    6 ENVIRONMENT MONITORING PROGRAM ....................................................297

  • M/S GUJARAT NARMADA VALLEY FERTILIZERS & CHEMICALS LTD.

    EIA & EMP REPORT FOR EXPANSION UNITS AT GNFC, BHARUCH TABLE OF CONTENT

    KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER 2014 XII

    6.1 INTRODUCTION .................................................................................... 297 6.2 THE OBJECTIVES OF MONITORING ............................................................. 297 6.3 ENVIRONMENTAL MONITORING PROGRAMS.................................................. 297

    6.3.1 Air Environment ............................................................................... 297 6.3.2 Noise Environment ............................................................................ 299 6.3.3 Water Environment ........................................................................... 301 6.3.4 Land Environment ............................................................................ 304 6.3.5 Ecology and Biodiversity ..................................................................... 308

    6.4 PROJECTED EXPENDITURE ON ENVIRONMENTAL MATTERS ............................... 310

    7 ADDITIONAL STUDIES ..............................................................................313

    7.1 PUBLIC CONSULTATION ............................................................................... 313 7.1.1 Notice of Public Hearing ..................................................................... 313 7.1.2 Publicity of Public Hearing ................................................................... 313 7.1.3 Panel ............................................................................................ 314 7.1.4 Proceedings .................................................................................... 314

    7.2 QUANTITATIVE RISK ASSESSMENT .................................................................... 319 7.3 OBJECTIVE............................................................................................. 319 7.4 STUDY METHODOLOGY ................................................................................ 319

    7.4.1 Plant Data ...................................................................................... 320 7.4.2 Generic Failure Rate Data ................................................................... 320 7.4.3 Population Data ............................................................................... 320 7.4.4 Meteorological Data .......................................................................... 320 7.4.5 Ignition Source Data ......................................................................... 321

    7.5 HAZARD (OR FAILURE CASE) IDENTIFICATION ........................................................ 321 7.5.1 Hazard and Damage Assessment .......................................................... 322

    7.6 RISK ASSESSMENT / CONSEQUENCE ANALYSIS ........................................................ 324 7.6.1 Selection of Material .......................................................................... 325 7.6.2 Scenarios Considered for Risk Analysis .................................................... 327 7.6.3 Consequence Analysis ........................................................................ 328 7.6.4 Conclusion...................................................................................... 340

    7.7 CONSEQUENCE CALCULATIONS ........................................................................ 341 7.8 RISK CALCULATIONS .................................................................................. 341

    7.8.1 Risk Presentation .............................................................................. 342 7.8.2 Risk Assessment .............................................................................. 342 7.8.3 Risk Tolerability Criteria ...................................................................... 342 7.8.4 Individual Risk Criteria ....................................................................... 342 7.8.5 Group Risk Criteria – FN Curves ............................................................ 343

    7.9 THE APPROACH TO CALCULATE FAILURE FREQUENCY ................................................. 344 7.10 RESULTS ANALYSIS RESULTS ....................................................................... 346

    7.10.1 Individual Risk ................................................................................. 346 7.10.1.1 Group Risk-FN Curve....................................................................... 350 7.10.2 Risk Contribution .............................................................................. 353

    7.11 CONCLUSIONS ...................................................................................... 353

  • M/S GUJARAT NARMADA VALLEY FERTILIZERS & CHEMICALS LTD.

    EIA & EMP REPORT FOR EXPANSION UNITS AT GNFC, BHARUCH TABLE OF CONTENT

    KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER 2014 XIII

    7.12 MITIGATIONS ....................................................................................... 354 7.13 ONSITE EMERGENCY PLAN .......................................................................... 355

    7.13.1 Emergency Categorized ...................................................................... 355 7.13.1.1 Emergency controllable within the plant / area ....................................... 355 7.13.1.2 Emergency confinable within the Factory premises .................................. 355 7.13.1.3 Likelihood of vapor cloud with formation of toxic / flammable gases drifting and affecting the general public (i.e. outside of plant premises) ..................................... 355 7.13.2 On Site Emergency Plan for GNFC, Bharuch.............................................. 355 GNFC have a detailed On Site Emergency Plan in place covering all the plants for more than 15 years. The Plan is supported by the following: ................................................. 355 7.13.2.1 Mutual Aid Scheme ......................................................................... 356 7.13.2.2 Information on the Preliminary Hazard Analysis ...................................... 356 7.13.2.3 Details about the Site ...................................................................... 357 7.13.2.4 Hazards in Various Plants ................................................................. 358 7.13.2.5 Details Regarding Warning, Alarm, and Safety and Security Systems ............. 359 7.13.2.6 Rescue Tools ................................................................................ 364 7.13.2.7 Detectors .................................................................................... 365 7.13.2.8 Inventory for Fire Protection ............................................................. 366 7.13.2.9 Occupational Health of the Contract and Sub contract Workers .................... 367 7.13.2.10 Antidote and First Aid Box .............................................................. 371

    7.14 PRECAUTIONS TAKEN DURING STORAGE AND TRANSPORTATION OF HAZARDOUS CHEMICALS ..... 372

    8 PROJECT BENEFITS ..................................................................................378

    8.1 TECHNOLOGICAL BENEFITS ............................................................................ 378 8.2 SUBSTANTIAL SOCIO-ECONOMIC BENEFITS ............................................................ 378 8.3 OTHER TANGIBLE BENEFITS ........................................................................... 378

    9 ENVIRONMENTAL COST BENEFIT ANALYSIS ................................................379

    10 ENVIRONMENTAL MANAGEMENT PLAN ....................................................380

    10.1 INTRODUCTION ................................................................................. 380 10.2 PURPOSE OF EMP ................................................................................ 380 10.3 ENVIRONMENTAL MANAGEMENT PLANS .................................................... 380

    10.3.1 Air Environment ............................................................................... 380 10.3.2 Water Environment ........................................................................... 380 10.3.3 Land Environment ............................................................................ 382 10.3.4 Socio-Economic Environment ............................................................... 385

    10.4 ENVIRONMENT MANAGEMENT CELL ......................................................... 389 10.5 SUMMARY OF EMP ............................................................................... 390

    11 SUMMARY AND CONCLUSION .................................................................392

    11.1 SUMMARY ......................................................................................... 392 11.2 CONCLUSION ..................................................................................... 392

    12 DISCLOSURE OF CONSULTANTS ENGAGED ................................................393

  • M/S GUJARAT NARMADA VALLEY FERTILIZERS & CHEMICALS LTD.

    EIA & EMP REPORT FOR EXPANSION UNITS AT GNFC, BHARUCH TABLE OF CONTENT

    KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER 2014 XIV

    12.1 BRIEF RESUME AND NATURE OF CONSULTANCY .......................................... 393 12.2 EIA TEAM MEMBERS ............................................................................ 394

    13 CERTIFIED COMPLIANCE REPORT OF EC CONDITIONS ...............................399

    13.1 COMPLIANCE REPORT FOR EC FROM MOEF (FOR EXPANSION UNITS OF WNA, CAN, METHANOL, ACETIC ACID, FORMIC ACID ETC.) ............................................................................ 399 13.2 COMPLIANCE REPORT FOR EC FROM SEIAA (ETHYL ACETATE) .................................... 410 13.3 NON-COMPLIANCES / PARTLY COMPLIANCES FOR EC FROM MOEF FOR EXPANSION UNITS OF WNA, CAN, METHANOL, ACETIC ACID, FORMIC ACID ETC. ......................................................... 433 13.4 NON-COMPLIANCES / PARTLY COMPLIANCES FOR EC FROM SEIAA FOR ETHYL ACETATE ......... 438

    LIST OF ANNEXURES

    Annexure 1: The Letter/application for EC ................................................................................... 443

    Annexure 2: Document of Notified Industrial Area ....................................................................... 444

    Annexure 3: ToR Letter from MoEF, New Delhi ............................................................................ 454

    Annexure 4: Corporate Environmental, OH&S and Quality Policy of GNFC ...................................... 458

    Annexure 5: ISO 14001:2004 and OSHAS 18001:2007 Certificates ............................................... 459

    Annexure 6: Environment Clearance for the Existing Unit Issued by the Ministry ............................ 461

    Annexure 7: Copies of Consent to Operate and Authorization Accorded by the GPCB ..................... 481

    Annexure 8: ‘Permissions’ for the Drawl of Water ........................................................................ 519

    Annexure 9: Inprinciple Approval for additional 24 MLD Water Requirement for Proposed Projects .. 534

    Annexure 10: Comfort Letter for Gas Supply from GSPC & MoU with Hazira LNG Pvt. Ltd. .............. 538

    Annexure 11: Commitment Regarding No Additional Storage for Ammonia .................................... 547

    Annexure 12: CREP Compliance of GNFC .................................................................................... 548

    Annexure 13: MSDS of all Chemicals Involved in the Project ......................................................... 551

    Annexure 14: Process Description for Existing Products................................................................ 552

    Annexure 15: Block Diagram of Existing Central ETP (Unit-I) ........................................................ 566

    Annexure 16: Block Diagram Proposed Sewage Treatment Plant (Unit-I) ....................................... 567

    Annexure 17: Block Diagram for Effluent Treatment System after Proposed Expansion (Unit-I) ....... 568

    Annexure 18: Block Diagram Existing Aniline ETP (Unit-II) ........................................................... 569

    Annexure 19: Block Diagram Proposed Aniline ETP (Unit-II) ......................................................... 570

    Annexure 20: Details of Online TOC Meter and Ammonical Nitrogen Analyzer ................................ 571

    Annexure 21: Membership Certificates for Solid Waste and Hazardous Waste (Existing & Proposed) 574

    Annexure 22: Definitions of First and Second Level of Classification .............................................. 584

  • M/S GUJARAT NARMADA VALLEY FERTILIZERS & CHEMICALS LTD.

    EIA & EMP REPORT FOR EXPANSION UNITS AT GNFC, BHARUCH TABLE OF CONTENT

    KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER 2014 XV

    Annexure 23: Climatological Data for Broach (Bharuch) District .................................................... 588

    Annexure 24: National Ambient Air Quality Standards .................................................................. 590

    Annexure 25: Impact Assessment Methodology ........................................................................... 591

    Annexure 26: Air Dispersion Modeling Results and Isopleths ........................................................ 600

    Annexure 27: Details of Injury to the Contract Workers in the Year 2012 ...................................... 618

    Annexure 28: Letter from Regional Officer, MoEF regarding Certification of Compliance ................. 620

    Annexure 29: NABET Certificate – Kadam Environmental Consultants (Sr. No. 84 on Nabet’s Website, as on Feb. 5, 2014) ................................................................................................................... 622

    Annexure 30: Advertisement for Public Hearing ........................................................................... 625

    Annexure 31: Copy of Letters issued by GPCB to Concerned Authorities for PH .............................. 628

    Annexure 32: Proof of Executive Summary Distribution in 59 Villages ............................................ 635

    LIST OF APPENDIX

    Appendix 1: MoM of Public Hearing ............................................................................................ 641

    Appendix 2: MSDS of Chemicals used in Unit – 1 ......................................................................... 878

    Appendix 3: MSDS of Chemicals used in Unit – 2 ....................................................................... 1165

    LIST OF TABLES

    Table 1-1: Schedule of Proposed Project ....................................................................................... 19

    Table 1-2: GNFC’s Top Management List....................................................................................... 21

    Table 1-3: Brief Description of the Proposed Project ...................................................................... 21

    Table 1-4: Statutory Clearances and Other Permissions ................................................................. 23

    Table 1-5: Compliance with the Terms of Reference ...................................................................... 26

    Table 2-1: Projected Demand Supply Gap for Urea (‘000 tonnes of material) ................................... 33

    Table 2-2: Aniline Demand Projected by the End of 2015 ............................................................... 34

    Table 2-3: Import and Indigenous Production of Aniline ................................................................. 34

    Table 2-4: Latitude and Longitude of the Corners of the GNFC Complex .......................................... 36

    Table 2-5: Product List with Existing and Proposed Capacity for Unit 1 and Unit 2 ............................ 40

    Table 2-6: Details of Raw Material Requirement for Proposed New Plants (Unit-1) ........................... 43

    Table 2-7: Details of Raw Material Requirement for Proposed New Plants (Unit-2) ........................... 45

    Table 2-8: Fuel Consumption of Unit 1 .......................................................................................... 46

  • M/S GUJARAT NARMADA VALLEY FERTILIZERS & CHEMICALS LTD.

    EIA & EMP REPORT FOR EXPANSION UNITS AT GNFC, BHARUCH TABLE OF CONTENT

    KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER 2014 XVI

    Table 2-9: Fuel Consumption of Unit 2 .......................................................................................... 47

    Table 2-10: Mass Balance for Ammonia (Proposed) ....................................................................... 54

    Table 2-11: Mass Balance for Urea (Proposed) .............................................................................. 57

    Table 2-12: Mass Balance for Aniline and Nitro Benzene (Proposed) ............................................... 63

    Table 2-13: Mass Balance for TDI-MDI Blend (Proposed) ............................................................... 65

    Table 2-14: Water Consumption details Existing and after Proposed Expansion (Unit-I) .................... 70

    Table 2-15: Wastewater Generation for Existing and Proposed Expansion (Unit-I) ........................... 71

    Table 2-16: Design Flow, Outlet Characteristics for the Existing Central ETP (Unit-I) ........................ 76

    Table 2-17: Adequacy of Existing Central ETP based on Hydraulic Load (Unit-I) ............................... 79

    Table 2-18: Analysis Results for Samples Collected from Existing Central ETP (Unit-I) ...................... 80

    Table 2-19: Stage Wise Reduction after each Stage of Treatment of Central Aniline ETP (Unit-I) ...... 81

    Table 2-20: Design Flow, Inlet and Outlet Characteristics for the Proposed STP (Unit-I) ................... 83

    Table 2-21: Unit Sizes for Proposed Sewage Treatment Plant (Unit-I) ............................................. 86

    Table 2-22: Water Consumption Details Existing and after Proposed Expansion (Unit-II) .................. 87

    Table 2-23: Waste Water Generation Details Existing and after Proposed Expansion (Unit-II) ........... 88

    Table 2-24: Design Flow, Inlet and Outlet Characteristics for the Existing Aniline ETP (Unit-II) ......... 92

    Table 2-25: Adequacy of Existing Aniline ETP based on Hydraulic Load (Unit-II) .............................. 97

    Table 2-26: Analysis Results for Samples Collected from Existing Aniline ETP (Unit-II) ..................... 99

    Table 2-27: Stage Wise Reduction after each Stage of Treatment of Existing Aniline ETP (Unit-II) .... 99

    Table 2-28: Design Flow, Inlet and Outlet Characteristics for the Proposed Aniline ETP (Unit-II) ..... 101

    Table 2-29: Unit Sizes for Proposed Aniline Effluent Treatment Plant (Unit-II) ............................... 106

    Table 2-30: Details of Existing and Proposed Flue Gas Stacks of Unit 1 ......................................... 108

    Table 2-31: Details of Existing and Proposed Flare Stacks of Unit 1............................................... 108

    Table 2-32: Details of Existing and Proposed Process Vents of Unit 1 ............................................ 109

    Table 2-33: Details of Existing and Proposed Stacks of Unit 2 ....................................................... 110

    Table 2-34: Details of Air Pollution Control Equipment at Unit-1 .................................................... 110

    Table 2-35: Details of Air Pollution Control Equipment at Unit-2 .................................................... 112

    Table 2-36: Sizing and Specifications of Ventuary Scrubber attached to Incinerator ....................... 113

    Table 2-37: Specifications of Packed Bed Scrubber attached to Incinerator Stack ........................... 113

    Table 2-38: Specifications of Air Pollution Control Equipments in Unit 2 ......................................... 117

    Table 2-39: Details & Specifications of Proposed Air Pollution Control Equipment at Unit-1 ............. 118

    Table 2-40: Details & Specifications of Proposed Air Pollution Control Equipment at Unit-2 ............. 118

    Table 2-41: Daily Work Place Monitoring at GNFC ........................................................................ 119

  • M/S GUJARAT NARMADA VALLEY FERTILIZERS & CHEMICALS LTD.

    EIA & EMP REPORT FOR EXPANSION UNITS AT GNFC, BHARUCH TABLE OF CONTENT

    KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER 2014 XVII

    Table 2-42: Existing Solid / Hazardous Waste Generation, Management and Disposal (Unit-I) ........ 121

    Table 2-43: Proposed Solid / Hazardous Waste Generation, Management and Disposal (Unit-I) ...... 125

    Table 2-44: Summary Solid / Hazardous Waste Generation, Management and Disposal (Unit-I) ...... 126

    Table 2-45: Adequacy of Hazardous Waste Storage Facility (Unit-I) .............................................. 128

    Table 2-46: Existing Solid / Hazardous Waste Generation, Management and Disposal (Unit-II) ....... 129

    Table 2-47 Proposed Solid / Hazardous Waste Generation, Management and Disposal (Unit-II) ...... 133

    Table 2-48: Summary Solid / Hazardous Waste Generation, Management and Disposal (Unit-II) ..... 136

    Table 2-49: Adequacy of Hazardous Waste Storage Facility (Unit-II) ............................................. 138

    Table 2-50: Proximate Analysis of TDI Tar .................................................................................. 139

    Table 2-51: Coordinates of Land Allocated for Proposed Plants ..................................................... 141

    Table 2-52: Land Distribution Area Breakup for Proposed Plants (Unitwise) ................................... 145

    Table 2-53: Operational Controls at Design Stage ........................................................................ 150

    Table 3-1: Predominant Month-wise Wind Directions ................................................................... 155

    Table 3-2: Average Meteorological Condition at Bharuch (1961 – 1976) ........................................ 156

    Table 3-3: Monitoring Methodology of Meteorological Data .......................................................... 158

    Table 3-4: Mean Meteorological Data for Summer Season 2013 .................................................... 159

    Table 3-5: Synopsis of Land Use / Landcover Classification used for the Project ............................. 162

    Table 3-6: GPS Readings Enumerating Land Features within Study Area ....................................... 164

    Table 3-7: Land use / Landcover Pattern of the Study Area .......................................................... 165

    Table 3-8: Area Statistic for Land Use / Land Cover Categories in the Study Area .......................... 166

    Table 3-9: Important Feature within the Study Area .................................................................... 170

    Table 3-10: Ambient Air Quality Monitoring Location Details and Justification ................................ 170

    Table 3-11: Methodology of Ambient Air Monitoring..................................................................... 173

    Table 3-12: Ambient Air Monitoring Results ................................................................................. 174

    Table 3-13: Stack Monitoring Analysis Summary for Unit – 1 ........................................................ 178

    Table 3-14: Stack Monitoring Analysis Summary for Unit – 2 ........................................................ 182

    Table 3-15: Methodology of Noise Sampling & Monitoring ............................................................ 184

    Table 3-16: Sampling Locations for Noise ................................................................................... 184

    Table 3-17: Noise Level Readings (Unit – I) ................................................................................ 187

    Table 3-18: Noise Level Readings (Unit – II) ............................................................................... 187

    Table 3-19: Noise Level Readings (Study Area) ........................................................................... 187

    Table 3-20: Ambient Noise Levels as per Noise Regulations.......................................................... 188

    Table 3-21: Analysis Methodology of Ground Water and Surface Water ......................................... 189

  • M/S GUJARAT NARMADA VALLEY FERTILIZERS & CHEMICALS LTD.

    EIA & EMP REPORT FOR EXPANSION UNITS AT GNFC, BHARUCH TABLE OF CONTENT

    KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER 2014 XVIII

    Table 3-22: Surface Water Sampling Location (Pond & River) ....................................................... 190

    Table 3-23: Analysis Results of Surface Water Samples ................................................................ 194

    Table 3-24: Analysis Result of River Water Sample ...................................................................... 196

    Table 3-25: Ground Water Sampling Locations ............................................................................ 197

    Table 3-26: Analysis Report of Ground Water Samples ................................................................. 199

    Table 3-27: Details of Samples Collected to assess impact of GNFC Waste Water Discharge on Water Quality of River ......................................................................................................................... 203

    Table 3-28: Analytical Results of Surface Water samples collected along Garamia Nalla to assess impact of GNFC Waste Water Discharge on Water Quality of Nalla as well as Bhukhi River ............. 204

    Table 3-29: Analytical results of Water samples Collected at Junction Point of Garamia Nalla & Bhukhi River ........................................................................................................................................ 207

    Table 3-30: Comparison of GNFC Outlet with Discharge Norms Specified in Consent ...................... 209

    Table 3-31: Geological Succession of Bharuch District .................................................................. 210

    Table 3-32: Analysis Methodology of Soil .................................................................................... 214

    Table 3-33: Soil Sampling Locations ........................................................................................... 214

    Table 3-34: Soil Analysis Result .................................................................................................. 217

    Table 3-35: Formulas for Analyzing Phyto-Sociological Characteristics of Vegetation ...................... 221

    Table 3-36: Location of Quantitative Study of vegetation ............................................................. 221

    Table 3-37: Quantitative Assessment of Vegetation ..................................................................... 224

    Table 3-38: List of Flora in the Study Area .................................................................................. 225

    Table 3-39: List of Birds with its Distribution and Migratory Status ................................................ 230

    Table 3-40: List of Butterflies, Reptiles and Mammals with its Distribution and Migratory Status ...... 232

    Table 3-41: Details of Sampling Locations ................................................................................... 234

    Table 3-42: Phytoplankton Cell Count (No./Lit.) Across Sampling Locations ................................... 234

    Table 3-43: Abundance of Phytoplankton .................................................................................... 234

    Table 3-44: Zooplankton Standing Stock (No. /Lit)....................................................................... 235

    Table 3-45: Abundance of Zooplankton....................................................................................... 235

    Table 3-46: Presenting diversity (Shannon Weaver Index) Across Sampling Locations .................... 235

    Table 3-47: List of Villages, Households and Population within the Study Area ............................... 237

    Table 3-48: Gender Wise Population and Households Distribution ................................................. 238

    Table 3-49: Number of SC/ST Population within the Study Area ................................................... 238

    Table 3-50: Number of Villages having Educational Facilities within the Study Area ........................ 239

    Table 3-51: Literacy Rate within the Study Area .......................................................................... 240

    Table 3-52: Number of Villages having Health Facilities within the Study Area ............................... 240

  • M/S GUJARAT NARMADA VALLEY FERTILIZERS & CHEMICALS LTD.

    EIA & EMP REPORT FOR EXPANSION UNITS AT GNFC, BHARUCH TABLE OF CONTENT

    KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER 2014 XIX

    Table 3-53: Details of Drinking Water Facilities ............................................................................ 240

    Table 3-54: Occupational Status of the Study Area ...................................................................... 242

    Table 3-55: Number of Villages having Transportation Facilities within the Study Area ................... 242

    Table 3-56: Communication Facilities within the Study Area ......................................................... 243

    Table 4-1: Aspect – Impact Identification from Proposed Project .................................................. 245

    Table 4-2: Impact Scoring Air Environment ................................................................................. 251

    Table 4-3: Proposed Stacks of Unit – 1 ....................................................................................... 254

    Table 4-4: Proposed Stacks of Unit – 2 ....................................................................................... 255

    Table 4-5: Assumptions for Calculating Emission Estimate for Point Source ................................... 255

    Table 4-6: Emission Estimate (Point Source) from Proposed Plants in Unit – 1 ............................... 256

    Table 4-7: Emission Estimate (Point Source) from Proposed Plants in Unit – 2 ............................... 256

    Table 4-8: Summary of Air Dispersion Modeling for Proposed Stacks ............................................. 258

    Table 4-9: 24 Hr Average Incremental Increase in GLC from Proposed Project............................... 258

    Table 4-10: Road Transportation Details for Raw Material (In) ..................................................... 263

    Table 4-11: Road Transportation Details for Finished Product (Out) .............................................. 263

    Table 4-12: Transportation Details for Unit 1 ............................................................................... 264

    Table 4-13: Transportation Details for Unit 2 ............................................................................... 264

    Table 4-14: Hourly Average Traffic Survey on NH-8 (Mumbai to Delhi) .......................................... 266

    Table 4-15: Hourly Average Traffic on NH-8 (Delhi to Mumbai)..................................................... 266

    Table 4-16: Hourly Average Traffic Survey on SH-6 (Dahej to Bharuch) ........................................ 266

    Table 4-17: Hourly Average Traffic on SH-6 (Bharuch to Dahej) ................................................... 267

    Table 4-18: Noise Modelling Calculation & Results for Long Duration Noise Sources ....................... 270

    Table 4-19: Impact Scoring Noise Environment ........................................................................... 271

    Table 4-20: Impact Scoring for Water Environment ..................................................................... 274

    Table 4-21: Impact Scoring Land Use / Land Cover ..................................................................... 278

    Table 4-22: Impact Scoring Soil Conservation ............................................................................. 280

    Table 4-23: Impact Scoring – Solid Hazardous Waste Generation ................................................. 281

    Table 4-24: Impact Scoring Ecology and Biodiversity ................................................................... 284

    Table 4-25: Impact Scoring for Socio-Economic Environment ....................................................... 290

    Table 4-26: Impact Scoring for Occupational Health and Risk to Surrounding Community ............... 290

    Table 6-1: Environmental Monitoring Program for Air Environment ............................................... 298

    Table 6-2: Environmental Monitoring Program for Noise Environment ........................................... 300

    Table 6-3: Environmental Monitoring Program for Water Quality ................................................... 302

  • M/S GUJARAT NARMADA VALLEY FERTILIZERS & CHEMICALS LTD.

    EIA & EMP REPORT FOR EXPANSION UNITS AT GNFC, BHARUCH TABLE OF CONTENT

    KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER 2014 XX

    Table 6-4: Environmental Monitoring and Management Program for Soil Environment .................... 305

    Table 6-5: Environmental Monitoring and Management Program for Solid Hazardous Waste Management ............................................................................................................................ 306

    Table 6-6: Environmental Management Program for Ecological and Biodiversity Environment ......... 309

    Table 6-7: Expenditure on Environmental Matters........................................................................ 310

    Table 6-8: Summary of Environmental Monitoring Program .......................................................... 311

    Table 7-1: Issues Rose during Public Hearing .............................................................................. 315

    Table 7-2: Environment Related Key Issues for Proposed Plants and Commitment by GNFC ........... 316

    Table 7-3: Positive Response from Nearby Villages ...................................................................... 317

    Table 7-4: Population Data ........................................................................................................ 320

    Table 7-5: Weather Condition Selected ....................................................................................... 320

    Table 7-6: Event Classification ................................................................................................... 321

    Table 7-7: Damage due to Radiation Intensity............................................................................. 323

    Table 7-8: Overpressure Damage ............................................................................................... 323

    Table 7-9: Chemicals with Storage Capacity, Storage Condition and Bund Dimension ..................... 326

    Table 7-10: Radiation Level and Effect Distance due to release of Ammonia .................................. 328

    Table 7-11: Overpressure Effect Distance due to the Release of Ammonia..................................... 328

    Table 7-12: Effect Distance for Toxic Dose Due to Release of Ammonia ........................................ 329

    Table 7-13: Radiation Level and Effect Distance Due to Release of Aniline ..................................... 330

    Table 7-14: Overpressure Effect Distance Due to Release of Aniline .............................................. 330

    Table 7-15: Radiation Level and Effect Distance Due to Release of Benzene .................................. 332

    Table 7-16: Overpressure Effect Distance Due to Release of Benzene ........................................... 332

    Table 7-17: Effect Distance for Toxic Dose Due to Release of Benzene .......................................... 332

    Table 7-18: Radiation Level and Effect Distance Due to Release of Methanol ................................. 334

    Table 7-19: Overpressure Effect Distance Due to Release of Methanol .......................................... 334

    Table 7-20: Effect Distance for Toxic Dose Due to Release of Methanol......................................... 334

    Table 7-21: Radiation Level and Effect Distance Due to Release of Nitrobenzene ........................... 336

    Table 7-22: Overpressure Effect Distance Due to Release of Nitrobenzene .................................... 336

    Table 7-23: Radiation Level and Effect Distance Due to Release of Toluene ................................... 337

    Table 7-24: Overpressure Effect Distance Due to Release of Toluene ............................................ 337

    Table 7-25: Effect Distance for Toxic Dose Due to Release of TDI ................................................ 339

    Table 7-26: Conclusion .............................................................................................................. 340

    Table 7-27: Failure Cases Input to PHAST Risk ............................................................................ 345

  • M/S GUJARAT NARMADA VALLEY FERTILIZERS & CHEMICALS LTD.

    EIA & EMP REPORT FOR EXPANSION UNITS AT GNFC, BHARUCH TABLE OF CONTENT

    KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER 2014 XXI

    Table 7-28: Major Risk Contributors ........................................................................................... 353

    Table 7-29: Fire Protection Facility at Site ................................................................................... 366

    Table 7-30: Details of Checkup based on Exposure ...................................................................... 368

    Table 10-1: Available Rainwater (Annual) for Harvesting in Unit-I ................................................. 381

    Table 10-2: Available Rainwater (Maximum) for Harvesting in Unit-I ............................................. 381

    Table 10-3: Available Rainwater (Annual) for Harvesting in Unit-II ................................................ 382

    Table 10-4: Available Rainwater (Maximum) for Harvesting in Unit-II ............................................ 382

    Table 10-5: Plant Species used for Landscaping around Offices and Residential Areas .................... 382

    Table 10-6: Trees and Shrubs Species Planted in Various Locations of the Project Area .................. 383

    Table 10-7: Proposed Plantation Schedule for next Five Years ...................................................... 385

    Table 10-8: Allocation of Funds for CSR Activities in Last 5 Years.................................................. 385

    Table 10-9: Proposed CSR Activities ........................................................................................... 386

    Table 10-10: Traffic Management Plan ....................................................................................... 388

    Table 10-11: Summary of EMP ................................................................................................... 390

    Table 13-1: Status of Non and Partially compalances (Compliance Report – EC from MoEF-1) ......... 433

    Table 13-2: Status of Non and Partially Compalances (Compliance Report – EC from MoEF-2) ........ 435

    Table 13-3: Status of Non and Partially compalances (Compliance Report – EC from SEIAA) ........... 438

    LIST OF FIGURES

    Figure 2-1: Project Implementation Schedule ................................................................................ 48

    Figure 2-2: Process Flow Diagram of Ammonia Plant (Proposed) .................................................... 50

    Figure 2-3: Process Flow Diagram for Urea Plant (Proposed) .......................................................... 55

    Figure 2-4: Process Flow Diagram for Water Soluble Fertilizers ....................................................... 58

    Figure 2-5: Process Flow Diagram for Aniline Plant (Proposed) ....................................................... 61

    Figure 2-6: Process Flow Diagram for TDI-MDI Blend (Proposed) ................................................... 64

    Figure 2-7: Process Flow Diagram for CPSU (Proposed) ................................................................. 66

    Figure 2-8: Existing Water Balance Diagram (Unit-I) ...................................................................... 72

    Figure 2-9: Water Balance for Proposed Expansion of Ammonia and Urea Plant ............................... 73

    Figure 2-10: Water Balance Diagram after Proposed Expansion (Unit-I) with Recycling and Reuse .... 74

    Figure 2-11: Existing Water Balance Diagram (Unit-II) ................................................................... 89

    Figure 2-12: Water Balance Diagram of Proposed Expansion (Unit-II) ............................................. 90

  • M/S GUJARAT NARMADA VALLEY FERTILIZERS & CHEMICALS LTD.

    EIA & EMP REPORT FOR EXPANSION UNITS AT GNFC, BHARUCH TABLE OF CONTENT

    KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER 2014 XXII

    Figure 2-13: Water Balance Diagram after Proposed Expansion (Unit-II) ......................................... 91

    Figure 2-14: Google Image of Site Showing Land Distribution of Proposed Plants .......................... 142

    Figure 2-15: Site Location of Proposed Ammonia – Urea & CPSU Plants ........................................ 143

    Figure 2-16: Site Location of Proposed Water Soluble Fertilizers (NPK) Plant ................................. 143

    Figure 2-17: Site Location of Proposed Aniline Plant .................................................................... 144

    Figure 2-18: Site Location of Propsoed ETP – Unit 2 .................................................................... 144

    Figure 2-19: Site Location of Proposed TDI-MDI Blend Plant ........................................................ 145

    Figure 2-20: Site Layout Plan for Proposed Ammonia and Urea Plants ........................................... 146

    Figure 2-21: Site Layout Plan for Water Soluble Fertilizers (NPK) Plant .......................................... 147

    Figure 2-22: Site Layout Plan for Proposed Aniline Plant............................................................... 148

    Figure 2-23: Site Layout Plan for Proposed TDI – MDI Blend Plant ................................................ 149

    Figure 3-1: Windrose Diagram for Summer Season ...................................................................... 160

    Figure 7-1: Approach to QRA ..................................................................................................... 319

    Figure 7-2: Late pool fire risk contour due to 50 mm Leak in Ammonia tank at weather 4.0/D ........ 329

    Figure 7-3: Concentration risk contour - Catastrophic Rupture of Ammonia Tank at 4.0/D .............. 330

    Figure 7-4: Late pool fire risk contour - Catastrophic Rupture in Aniline tank at 4.0/D .................... 331

    Figure 7-5: Late Explosion overpressure risk contour catastrophic rupture of Aniline tank at 4.0/D .. 331

    Figure 7-6: Late pool fire risk contour - Catastrophic Rupture in Benzene tank at 4.0/D .................. 332

    Figure 7-7: Late Explosion overpressure risk contour - catastrophic rupture of Benzene tank at 4.0/D ............................................................................................................................................... 333

    Figure 7-8: Concentration risk contour - Catastrophic Rupture of Benzene tank at 4.0/D ................ 333

    Figure 7-9: Late pool fire risk contour - Catastrophic Rupture in Methanol tank at 4.0/D ................. 335

    Figure 7-10: Late Explosion overpressure risk contour - Catastrophic rupture of Methanol tank at 4.0/D ............................................................................................................................................... 335

    Figure 7-11: Late pool fire risk contour - Catastrophic Rupture in Nitrobenzene tank at 4.0/D ......... 336

    Figure 7-12: Late Explosion overpressure risk contour - Catastrophic rupture of Nitrobenzene tank at 4.0/D ....................................................................................................................................... 337

    Figure 7-13: Late pool fire risk contour - Catastrophic Rupture in Toluene tank at 4.0/D................. 338

    Figure 7-14: Late Explosion overpressure risk contour - catastrophic rupture of Toluene tank at 4.0/D ............................................................................................................................................... 338

    Figure 7-15: Concentration risk contour - Catastrophic Rupture of Toluene tank at 4.0/D ............... 339

    Figure 7-16: Concentration risk contour - Catastrophic Rupture of TDI tank at 4.0/D ..................... 340

    Figure 7-17: Criteria for Individual Risk ....................................................................................... 343

    Figure 7-18: Criteria for Group Risk ............................................................................................ 344

  • M/S GUJARAT NARMADA VALLEY FERTILIZERS & CHEMICALS LTD.

    EIA & EMP REPORT FOR EXPANSION UNITS AT GNFC, BHARUCH TABLE OF CONTENT

    KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER 2014 XXIII

    Figure 7-19: Iso-risk Contours-Overall Plant Area ........................................................................ 347

    Figure 7-20: Iso-Risk Contour Enlarged View............................................................................... 348

    Figure 7-21: Individual Risk ....................................................................................................... 349

    Figure 7-22: FN Curve of Group Risk (on-site) ............................................................................. 351

    Figure 7-23: FN curve of Group Risk (off-site) ............................................................................. 352

    Figure 10-1: Hierarchy of Environment Management Cell ............................................................. 389

    LIST OF PHOTOGRAPHS

    Photograph 2-1: Photos of Central Effluent Treatment Plant (Unit-I) ............................................... 77

    Photograph 2-2: ABB Analyzer system – EL3020.......................................................................... 112

    Photograph 3-1: Meteorological Station set up at the Site ............................................................ 160

    Photograph 3-2: Various Land uses of Study Area ....................................................................... 169

    Photograph 3-3: AAQ Sampling Stations ..................................................................................... 171

    Photograph 3-4: Noise Level Sampling Locations ......................................................................... 185

    Photograph 3-5: Surface Water Sampling Locations ..................................................................... 192

    Photograph 3-6: Ground Water Sampling .................................................................................... 198

    Photograph 3-7: Photographs of Sampling at Garamia Nalla ......................................................... 210

    Photograph 3-8: Soil Sampling Locations .................................................................................... 215

    Photograph 3-9: Vegetation Cover and Sampling in Study area .................................................... 223

    Photograph 3-10: Method of data collection used within the study area ........................................ 236

    Photograph 3-11: Educational Facilities within the Study Area ...................................................... 239

    Photograph 3-12: Animal Husbandry within Study Area................................................................ 241

    Photograph 3-13: Places of Religious Importance Present within the Study Area ............................ 243

    Photograph 7-1: Photographs of Public Hearing Publicity through Auto ......................................... 314

    Photograph 7-2: Photographs of Public Hearing........................................................................... 318

    Photograph 7-3: Rescue Tools Available ..................................................................................... 365

    Photograph 7-4: Leak Detectors installed at Site.......................................................................... 366

    Photograph 7-5: Photographs of Occupational Health Centre and Check up ................................... 372

    Photograph 10-1: Existing Landscaping and Greenbelt with Project Premise .................................. 384

    Photograph 12-1: Photographs showing EIA Team at Project Site and Study Area ......................... 397

  • M/S GUJARAT NARMADA VALLEY FERTILIZERS & CHEMICALS LTD.

    EIA & EMP REPORT FOR EXPANSION UNITS AT GNFC, BHARUCH TABLE OF CONTENT

    KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER 2014 XXIV

    LIST OF MAPS

    M- 2-1: Project Location Map ....................................................................................................... 37

    M- 2-2: Satellite Image Showing the Project Site with Coordinates .................................................. 38

    M- 2-3: Map Indicating Distance of Project site from Severely Polluted Area .................................... 39

    M- 3-1: Study Area Map showing Nearby Industries, Habitation and Surface Water Bodies ............. 154

    M- 3-2: Sampling Location Map .................................................................................................. 161

    M- 3-3: Map Showing Land Use / Land Cover .............................................................................. 168

    M- 3-4: Map Showing Extent of Garamia Nalla and Bhukhi River and Sampling Locations for Surface Water Samples collected ............................................................................................................ 208

    M- 3-5: Geomorphology of Region .............................................................................................. 211

    M- 3-6: Seismic Map of Gujarat State ......................................................................................... 212

    M- 3-7: Soil Profile of Bharuch Region ........................................................................................ 213

  • M/S GUJARAT NARMADA VALLEY FERTILIZERS & CHEMICALS LTD.

    EIA & EMP REPORT FOR EXPANSION UNITS AT GNFC, BHARUCH TABLE OF CONTENT

    KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER 2014 XXV

    ABBREVIATIONS

    AAQM : Ambient Air Quality Monitoring

    AAS : Atomic Absorption Spectroscopy

    AERMIC : American Meteorological Society/Environmental Protection Agency Regulatory Model Improvement Committee

    AERMOD : AMS/EPA Regulatory Model

    ALARP : As Low As Reasonably Practicable

    ANP : Ammonium Nitro Phosphate

    APCM : Air Pollution Control Measures

    APHA : American Public Health Association

    BASF : Badische Anilin- und Soda-Fabrik

    BATNEEC : Best Available Technology Not Entailing Excessive Costs

    BEIL : Bharuch Enviro Infrastructure Limited

    BHEL : Bharat Heavy Electricals Limited

    BLEVE : Boiling Liquid Expanding Vapor Explosion

    BOD : Biological Organic Demand

    BSI : British Standards Institution

    BVB : Bhartiya Vidya Bhavan

    CAN : Calcium Ammonium Nitrate

    CAS : Chemical Abstracts Service

    CBM : Coal Bed Methane

    CCA : Consolidated Consent and Authorization

    CCE : Center for Credentialing and Education

    CCTV : Closed Circuit Television

    CETP : Central Effluent Treatment Plant

    CAN : Concentrated Nitric Acid

    CPCB : Central Pollution Control Board

    CPSU : Cogeneration Power and Steam Unit

    CO : Carbon Monoxide

    COD : Chemical Oxygen Demand

    CREP : Corporate Responsibility for Environment Protection

    CSR : Corporate Social Responsibility

    CTO : Consent to Operate

    dB : Decibels

    DCS : Distributed Control System

    DG : Diesel Generator

    DGVCL : Dakshin Gujarat Vij Company Limited

    DM : De-mineralization

    DMIC : Delhi-Mumbai Industrial Corridor

    DMP : Disaster Management Plan

    DNV : Det Norske Veritas

    DPR : Detailed Project Report

  • M/S GUJARAT NARMADA VALLEY FERTILIZERS & CHEMICALS LTD.

    EIA & EMP REPORT FOR EXPANSION UNITS AT GNFC, BHARUCH TABLE OF CONTENT

    KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER 2014 XXVI

    EAC : Expert Appraisal Committee

    EC : Environmental Clearance

    ECG : Electrocardiogram

    EDTA : Ethylene-Diamine-Tetraacetic Acid

    EIA : Environmental Impact Assessment

    EMP : Environmental Management Plan

    EMS : Environmental Management Systems

    ERPG : Emergency Response Planning Guideline

    ESP : Electro Static Precipitator

    ETP : Effluent Treatment Plant

    FAE : Functional Area Expert

    FLOX : Flameless Oxidation

    FRV : Fiber Reinforced Vinylester

    GAIL : Gas Authority India Limited

    GC : Gas Chromatography

    GEPIL : Gujarat Enviro Protection & Infrastructure Limited

    GHGs : Green House Gases

    GIDC : Gujarat Industrial Development Corporation

    GmbH : Gesellschaft mit beschränkter Haftung

    GNFC : Gujarat Narmada Valley Fertilizers and Chemicals Limited

    GoG : Government of Gujarat

    GoI : Government of India

    GPCB : Gujarat Pollution Control Board

    GPS : Global Positioning System

    GSFC : Gujarat State Fertilizers Company Limited

    GSI : Geological Survey of India

    GSPC : Gujarat State Petroleum Corporation Limited

    GSPL : Gujarat State Petronet Limited

    HB : Hemoglobin

    HCs : Hydro-Carbons

    HDPE : High-Density PolyEthylene

    HF : Hydrogen Fluoride

    HP / MP / LP : High Pressure / Medium Pressure / Low Pressure

    HRSG : Heat Recovery Steam Generators

    HRT : Hydraulic Retention Time

    HSD : High Speed Diesel

    HTAS : Haldor Topsoe

    Hz : Hertz

    IAA : Impact Assessment Authority

    IAY : Indra Awas Yojna

    IC : Incident Controller

    ICDS : Integrated Child Development Services

    IDLH : Immediately Dangerous to Life & Health

  • M/S GUJARAT NARMADA VALLEY FERTILIZERS & CHEMICALS LTD.

    EIA & EMP REPORT FOR EXPANSION UNITS AT GNFC, BHARUCH TABLE OF CONTENT

    KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER 2014 XXVII

    IL&FS : Infrastructure Leasing & Financial Services Limited

    IMD : India Meteorological Department

    INR : Indian Rupees

    IPP : Import Party Prices

    IRC : Indian Roads Congress

    IS : Indian Standards

    ISLM : Integrating Sound Level Measurement

    ISO : International Organization for Standardization

    IUCN : International Union for Conservation of Nature

    JV : Joint Venture

    KBR : Kellogg Brown and Root

    KEC : Kadam Environmental Consultants

    KO : Knot Out

    kPa : Kilo Pascal

    kVA : Kilo Volt Amperes

    LAC : Linde Ammonia Concept

    LDO : Light Diesel Oil

    LDPE : Low-Density PolyEthylene

    LNG : Liquefied Natural Gas

    LSIR : Location Specific Individual Risk

    LSTK : Lump Sum Turn Key

    MCAS : Maximum Credible Accident Scenario

    MCC : Motor Control Center

    MLSS : Mixed Liquor Suspended Solids

    MMSCMD : Million Standard Cubic Feet per Day

    MNREGS : Mahatma Gandhi National Rural Employment Guarantee Scheme

    MTA : Metric Tons Per Annum

    MTPD : Metric Tons Per Day

    MDI : Methylene Diphenyl Diisocyanate

    MoEF : Ministry of Environment & Forest

    MSDS : Material Safety Data Sheet

    MSU : Methanol Synthesis Unit

    MW : Mega Watt

    NABET : National Accreditation Board of Education & Training

    NARDES : Narmadanagar Rural Development Society

    NB : Nitrobenzene

    NCPL : Narmada Chematur Petrochemicals Limited

    NCSC : Narmada College of Science and Commerce

    NEST : Narmada Education & Scientific Research Society

    NG : Natural Gas

    NH : National Highway

    NH3 : Ammonia

    NIHL : Noise Induced Hearing Loss

  • M/S GUJARAT NARMADA VALLEY FERTILIZERS & CHEMICALS LTD.

    EIA & EMP REPORT FOR EXPANSION UNITS AT GNFC, BHARUCH TABLE OF CONTENT

    KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER 2014 XXVIII

    NIP : New Investment Policy

    NITT : National Institute of Technical Training

    NOC : No Objection Certificate

    NOx : Oxides of Nitrogen

    NPK : Nitrogen, Phosphorus & Potassium

    NRHM : National Rural Health Mission

    NRSA : National Remote Sensing Agency

    ODCB : Ortho Di Chloro Benzene

    ODS : Oxide Dispersion Stabilized

    OHS : Occupational Health & Safety

    OM : Office Memorandum

    OMIFCO : Oman India Fertilizer Company

    OSHAS : Occupation Health and Safety Assessment Series

    P&ID : Piping and Instrumentation Diagram

    PCM : Pollution Control Measures

    PCPIR : Petroleum, Chemicals and Petrochemicals Investment Region

    PCU : Passenger Car Unit

    PDIL : Projects and Development India Limited

    PEL : Permissible Exposure Level

    PESO : Petroleum and Explosives Safety Organization

    PFD : Process Flow Diagram

    PFR : Pre-Feasibility Report

    PFT : Pulmonary Function Test

    pH : Power of Hydrogen

    PHAST : Process Heating Assessment and Survey Tool

    PM : Particulate Matter

    PP : Polypropylene

    PPE : Personal Protective Equipment

    ppm : Parts per Million

    PSA : Pressure Swing Adsorption

    PUCC : Pollution Under Control Certificates

    QCI : Quality Council of India

    QRA : Quantitative Risk Assessment

    GLC : Ground Level Concentration

    GNFC : Gujarat Narmada Valley Fertilizers and Chemicals Limited

    GSFC : Gujarat State Fertilizers Company Limited

    RO : Regional Officer

    RO : Reverse Osmosis

    RLNG : Regasified Liquefied Natural Gas

    RWH : Rain Water Harvesting

    SAC : Sulphuric Acid Concentration

    SAY : Sardar Awas Yojna

    SEIAA : State Environmental Impact Assessment Authority

  • M/S GUJARAT NARMADA VALLEY FERTILIZERS & CHEMICALS LTD.

    EIA & EMP REPORT FOR EXPANSION UNITS AT GNFC, BHARUCH TABLE OF CONTENT

    KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER 2014 XXIX

    SEZ : Special Economic Zone

    SGPT : Serum Glutamic Pyruvate Transaminase (Liver Test)

    SH : State Highway

    SMC : Site Main Controller

    SPL : Sound Pressure Level

    SS : Suspended Solids

    STP : Sewage Treatment Plant

    TDI : Toluene Di-Isocyanate

    TDS : Total Dissolved Solids

    TEC : Toyo Engineering Corporation

    TEFR : Techno-Economic Feasibility Report

    TM Blend : TDI - MDI Blend

    TOC : Total Organic Carbon

    ToR : Terms of Reference

    TSDF : Treatment, Storage and Disposal Facility

    USEPA : United States Environmental Protection Agency

    VOCs : Volatile Organic Compounds

    VSCC : Vertical Submerged Carbamate Condenser

    VTC : Vocational Training Center (VTC)

    WNA : Weak Nitric Acid

    ZSI : Zoological Survey of India

  • M/S GUJARAT NARMADA VALLEY FERTILIZERS & CHEMICALS LTD.

    EIA & EMP REPORT FOR EXPANSION UNITS AT GNFC, BHARUCH TABLE OF CONTENT

    KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER 2014 XXX

    LIST OF PERSONS AND INSTITUTIONS MET

    GNFC Personnel

    1 Mr. A. T. Patadia Executive Director

    2 Mr. V. S. Sirohi General Manager

    3 Mr. V. K. Nema General Manager

    4 Mr. S. K. Mehta General Manager

    5 Mr. P. G. Dave Additional General Manager

    6 Mr. K. N. Jaggi Additional General Manager

    7 Mr. V. C. Bhatt Additional General Manager

    8 Mr. K. H. Patel Chief Manager

    9 Mr. B. T. Golwala Chief Manager

    10 Mr. P. K. Purohit Chief Manager

    11 Mr. Y. C. Prajapati Sr. Manager

    12 Mr. T.S Santa Sr. Manager

    13 Mr. D.B. Shah Sr. Manager

    14 Mr. V. N. Patel Sr. Manager

    15 Dr. A. D. Thakkar Sr. Manager

    16 Dr. J. B. Joshi Manager

    17 Mr. Y. A. Patel Manager

    18 Mr. S. R. Desai Manager

    19 Mr. D. K. Patel Sr. Environmental Engineer

    20 Mr. Anurag Srivastava NARDES - Manager

    Others

    1 Shri Jagdishbhai Patel Local Resident (Umraj Village)

    2 Shri Madhusudan Patel Sarpanch (Umraj Village)

    3 Shri Vasava Taraben Melabhai Sarpanch (Haldarva Village)

    4 Shri Raijibhai Narsinhbhai Vasava Local Resident (Chavaj Village)

    5 Shri Dahyabhai Premabhai Parmar Local Resident (Vadadla Village)

    6 Smt Rashmika Parmar Local Resident (Vadadla Village)

    7 Shri Ishwarbhai Ratanbhai Parmar Sarpanch (Vadadla Village)

  • M/S GUJARAT NARMADA VALLEY FERTILIZERS & CHEMICALS LTD.

    EIA & EMP REPORT FOR EXPANSION UNITS AT GNFC, BHARUCH EXECUTIVE SUMMARY

    KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER 2014 1

    0 EXECUTIVE SUMMARY

    0.1 PROJECT DESCRIPTION

    0.1.1 About the Company and Project Proponent

    GNFC is a joint sector enterprise promoted by the Government of Gujarat and the Gujarat State Fertilizer Company Ltd. (GSFC). It was set up in Bharuch, Gujarat in 1976. Located at Bharuch in an extremely prosperous industrial belt, GNFC draws on the resources of the natural wealth of the land as well as the industrially rich reserves of the area. For more than 30 years it is serving nation by making Fertilizers and Chemicals. It is a partner to the Nation's progress, its fertilizers playing a key role in enhancing agricultural output and its chemicals helping the Indian industrial revolution.

    GNFC started its manufacturing and marketing operations by setting up in 1982, one of the world's largest single-stream ammonia-urea fertilizer complexes. Over the next few years, GNFC successfully commissioned different projects - in fields as diverse as chemicals, fertilizers and electronics.

    GNFC has an enterprising, strategic view towards expansion and diversification. GNFC promoted Narmada Chematur Petrochemicals Limited. Now, it is merged as Unit – 2 in year 2007. As on date, Unit – 1 and Unit – 2 has separate Consent Orders from Gujarat Pollution Control Board (GPCB).

    GNFC is run by experienced chairman, managing director, directors and executive directors with well qualified employees. GNFC has won various prestigious National and International awards with its state-of-the-art technology, high quality standards and productivity-conscious work-force. Recent award includes National Energy Conservation Award - 2013 in Fertilizer Sector. The award was bestowed to the MD-GNFC, Dr. Rajiv Kumar Gupta, IAS at the hands of Hon’ble President of India. Also, GNFC has won the prestigious FAI (Fertilizer Association of India) Award for the best production performance in Complex Fertilizer NP/NPK category for the year 2012-13.This award was given based on performance in production, specific energy consumption and P2O5 efficiency.

    It intends to expand its manufacturing facilities for fertilizers and chemicals within its existing Fertilizer Complex at Bharuch.

    0.1.2 About Project

    Proposed project comprises of Brownfield Ammonia (2,800 MTD), Urea (3,850 MTD), various grades of Water Soluble Fertilizers (NPK) (5,000 MTA) and a 45 MW Co-generation Power & Steam Unit (CPSU) for Unit 1, whereas new Aniline (78,000 MTA) and TDI – MDI Blend (7,800 MTA) for Unit 2.

    0.1.3 Regulatory Framework

    The existing manufacturing facility has received environmental clearances for existing products from MoEF, New Delhi and SEIAA, Gujarat. Conditions as stipulated in valid consents are being complied with. Certification of compliance for environmental clearance conditions by MoEF, Bhopal has been received.

    The proposed project is classified as Category “A” Project. Various components of the proposed expansion project lie under the following Project or Activity and Categories as per the schedule in EIA Notification 2006 amended till date:

    1. 5(a) for Chemical Fertilizers : Category “A”

  • M/S GUJARAT NARMADA VALLEY FERTILIZERS & CHEMICALS LTD.

    EIA & EMP REPORT FOR EXPANSION UNITS AT GNFC, BHARUCH EXECUTIVE SUMMARY

    KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER 2014 2

    2. 5(f) for Synthetic Organic Chemicals Industries : Category “B” 3. 1(d) for Thermal Power Plants : Category “B”

    Considering that the expansion projects are part of an integrated fertilizers and chemicals complex, these are submitted to the Impact Assessment Authority (IAA), Ministry of Environment and Forests (MoEF), New Delhi for consideration as an integrated project.

    0.1.4 Location of the Project

    The project site is located at Survey No. 5, 24/1-B, 99/3-A, 127, 38, 15 and 74 in Notified Industrial Area as per gazette notification enacted by Government of Gujarat (Ref. Map, M- 2-1). It is surrounded by Mumbai-Delhi National Highway (NH-8) at a distance of 0.5 km in East Direction and adjacent State Highway (SH – 6) connecting Dahej, a major sea port at approximately 48 km, Bharuch Railway Station is at ~3.9 km distance in SW direction, nearest airport is Surat Airport at a distance of 70.6 kms in SW Direction. The base elevation of site is at 19.2 m above mean sea level.

    0.1.5 Project Cost

    The estimated project cost INR 4,463 Crore includes environmental management cost ~ INR 153.67 Crore and recurring expenditure ~ INR 6.41 Crore per annum.

    GNFC is engaged in the CSR activities like Education,