Cost of Wind 1 James McCalley Harpole Professor of Electrical & Computer Engineering.

17
Cost of Wind 1 James McCalley Harpole Professor of Electrical & Computer Engineering

Transcript of Cost of Wind 1 James McCalley Harpole Professor of Electrical & Computer Engineering.

Page 1: Cost of Wind 1 James McCalley Harpole Professor of Electrical & Computer Engineering.

Cost of Wind

1

James McCalleyHarpole Professor of

Electrical & Computer Engineering

Page 2: Cost of Wind 1 James McCalley Harpole Professor of Electrical & Computer Engineering.

Discount rate

2

Discount rate, i. •the annual payment as a percentage of the amount owed;•the value given to possession of money now rather than later, since having it now allows it to be invested to earn a return. In this sense, the discount rate is the annual income as a percentage of the amount invested, i.e., average interest rate.

Page 3: Cost of Wind 1 James McCalley Harpole Professor of Electrical & Computer Engineering.

Moving single amounts in time

3

NiFP

)1(

1

“Present” amount of money

“Future” amount of money

Number of time periods

1 2 3 4 N

P P(1+i)

P(1+i)2

F

Time Period

Mon

etar

y V

alue

NiPF )1( Observe that “F” may be a cost or a revenue. In either case, the equivalent amount of money in the present is smaller.•I prefer to incur a $100 cost later than a $100 cost now.•I prefer to obtain a $100 revenue now than a $100 revenue later.

Page 4: Cost of Wind 1 James McCalley Harpole Professor of Electrical & Computer Engineering.

Annuitizing

4

“Annual” amount of money

Note that payment A is made at the end of a period, so there is no payment made at the beginning of period 1, but there is a payment made at the end of period N.

1)1(

)1(

N

N

i

iiPA

1)1(

Ni

iFA

1 2 3 4 N

P

A

F

Time Period

Mon

etar

y V

alue

A A A A A

Page 5: Cost of Wind 1 James McCalley Harpole Professor of Electrical & Computer Engineering.

Inflation

5

The discount rate does not reflect the effects of inflation. Inflation, e, changes the buying power of money.

“Current dollars” are the actual cash flow that would occur during a particular year, m, accounting for inflation.“Constant dollars” are the dollars that would have been required if the cost was paid in the “base year,” n. We refer to this as “n dollars” as in “2012 dollars.”

Ne

FF

)1( N=m-n

Page 6: Cost of Wind 1 James McCalley Harpole Professor of Electrical & Computer Engineering.

Inflation and discounting

6

The discount rate in the absence of inflation is called the “real” discount rate, ir. The discount rate accounting for inflation is called the “nominal” discount rate, in.

NNr

Nr

Nn e

F

ii

F

i

FP

)1()1(

1

)1()1(

Current dollar amount at year N (accounting for inflation)FConstant dollar amount at year N (without inflation)F

rrrrn

rn

NNr

Nn

ieeiieeii

eii

eii

111)1)(1(

)1)(1()1(

)1()1()1(

Page 7: Cost of Wind 1 James McCalley Harpole Professor of Electrical & Computer Engineering.

Levelized cost of energyData Wind TurbinePurchase cost $1820/kW

Installation cost $600000

Levelized fixed charge rate

20%

Plant rating 1.5 MWCapacity factor 0.35

Nominal discount rate

8%

Levelized fixed charge rate:•Capital cost•Return on investment•Depreciation•Fed and state income taxes•Property tax•Insurance costs

The initial investment is($1820/kw)*1500kW+600000=$3,300,000The fixed annual charges are then 0.2*3,300,000=$660,000.This is called the levelized annual revenue requirements (LARR)The average annual energy production is=Capacity*8760hrs/yr*CapacityFactor=1.5MW*8760hrs/yr*.35=4599MWhrs

7

MWhrLCOE /51.143$4599

660000

roductionualEnergyPAverageAnn

LARR

Page 8: Cost of Wind 1 James McCalley Harpole Professor of Electrical & Computer Engineering.

Levelized cost of energyData Wind TurbinePurchase cost $1820/kW

Installation cost $600000

Levelized fixed charge rate

11.6%

Plant rating 1.5 MWCapacity factor 0.35

Nominal discount rate

8%

Levelized fixed charge rate:•Return on investment•Depreciation•Fed and state income taxes•Property tax•Insurance costs

The initial investment is($1820/kw)*1500kW+600000=$3,300,000The fixed annual charges are then 0.116*3,300,000=$382,800.This is called the levelized annual revenue requirements (LARR)The average annual energy production is=Capacity*8760hrs/yr*CapacityFactor=1.5MW*8760hrs/yr*.35=4599MWhrs

8

MWhrLCOE /24.83$4599

800,382

roductionualEnergyPAverageAnn

LARR

Page 9: Cost of Wind 1 James McCalley Harpole Professor of Electrical & Computer Engineering.

Levelized cost of energyData Wind TurbinePurchase cost $1820/kW

Installation cost $600000

Levelized fixed charge rate

20%

Plant rating 1.5 MWCapacity factor 0.40

Nominal discount rate

8%

Levelized fixed charge rate:•Return on investment•Depreciation•Fed and state income taxes•Property tax•Insurance costs

The initial investment is($1820/kw)*1500kW+600000=$3,300,000The fixed annual charges are then 0.2*3,300,000=$660,000.This is called the levelized annual revenue requirements (LARR)The average annual energy production is=Capacity*8760hrs/yr*CapacityFactor=1.5MW*8760hrs/yr*.40=5256MWhrs

9

MWhrLCOE /58.125$5256

660000

roductionualEnergyPAverageAnn

LARR

Page 10: Cost of Wind 1 James McCalley Harpole Professor of Electrical & Computer Engineering.

Levelized cost of energyData Wind TurbinePurchase cost $1820/kW

Installation cost $600000

Levelized fixed charge rate

11.6%

Plant rating 1.5 MWCapacity factor 0.40

Nominal discount rate

8%

Levelized fixed charge rate:•Return on investment•Depreciation•Fed and state income taxes•Property tax•Insurance costs

The initial investment is($1820/kw)*1500kW+600000=$3,300,000The fixed annual charges are then 0.116*3,300,000=$382,800.This is called the levelized annual revenue requirements (LARR)The average annual energy production is=Capacity*8760hrs/yr*CapacityFactor=1.5MW*8760hrs/yr*.40=5256MWhrs

10

MWhrLCOE /83.72$5256

800,382

roductionualEnergyPAverageAnn

LARR

Page 11: Cost of Wind 1 James McCalley Harpole Professor of Electrical & Computer Engineering.

Levelized cost of energyResource LCOEPC plant $59.94/MWhrNGCC plant $99.64/MWhrNuclear plant $66.49/MWhrWind, CF=0.35, FCR=20% $143.51/MWhrWind, CF=0.35, FCR=11.6% $83.24/MWhrWind, CF=0.40, FCR=20% $125.58/MWhrWind, CF=0.40, FCR=11.6% $72.83/MWhr

Page 12: Cost of Wind 1 James McCalley Harpole Professor of Electrical & Computer Engineering.

Levelized cost of energy

12

Additional note: Another term that should be added in is the annual operating expenses (AOE). This includes land lease cost, levelized O&M cost, and levelized replacement cost:

AOE=LLC+LOM+LRCwith units of $/year. So the expression for LCOE is

roductionualEnergyPAverageAnn

AOELARRLCOE

AOE is generally only about 2% of the purchase cost.

The above expression is sometimes expressed as:

AOEroductionualEnergyPAverageAnn

LARRLCOE

which implies AOE is given in $/MWhr.

Page 13: Cost of Wind 1 James McCalley Harpole Professor of Electrical & Computer Engineering.

Levelized cost of energy

13 Nuclear Energy Institute, “The cost of new generating capacity in perspective,” Sept., 2011, available online at www.nei.org/resourcesandstats/documentlibrary/newplants/graphicsandcharts/the-cost-of-new-generating-capacity-in-perspective.

Data from Electric Power Research Institute

Page 14: Cost of Wind 1 James McCalley Harpole Professor of Electrical & Computer Engineering.

Levelized cost of energy

14 Nuclear Energy Institute, “The cost of new generating capacity in perspective,” Sept., 2011, available online at www.nei.org/resourcesandstats/documentlibrary/newplants/graphicsandcharts/the-cost-of-new-generating-capacity-in-perspective.

Data from US DOE Energy Information Administration

Page 15: Cost of Wind 1 James McCalley Harpole Professor of Electrical & Computer Engineering.

Levelized cost of energy

15 Nuclear Energy Institute, “The cost of new generating capacity in perspective,” Sept., 2011, available online at www.nei.org/resourcesandstats/documentlibrary/newplants/graphicsandcharts/the-cost-of-new-generating-capacity-in-perspective.

National Research Council (National Academies of Science and of Engineering)

Page 16: Cost of Wind 1 James McCalley Harpole Professor of Electrical & Computer Engineering.

Representative split – capital costs

16

Source: P. Jamieson, “Innovation in wind turbine design,” Wiley, 2011. Note – this book has an entire chapter dedicated to “Cost of Energy.”

Component Cost fraction

Blades 0.177

Hub 0.077

Gearbox 0.143

Generator 0.076

Yaw system 0.019

Nacelle cover 0.020

Nacelle structure 0.040

Tower 0.219

Variable speed system 0.073

Pitch system 0.043

Rotor brake 0.006

Couplings 0.003

Shaft 0.041

Other 0.063

Total turbine 1.00

This is for capital (investment) costs.It is for a representative wind turbine design, but one should recognize that there are different designs. But it does provide some indication of relative splits among major wind turbine components.

Page 17: Cost of Wind 1 James McCalley Harpole Professor of Electrical & Computer Engineering.

Representative split - LCOE

17

Source: P. Jamieson, “Innovation in wind turbine design,” Wiley, 2011. Note – this book has an entire chapter dedicated to “Cost of Energy.”

Initial capital costs Turbine Rotor Rotor lock 0.0057

0.820 0.569 Blades 0.1037

Hub 0.0142

Nacelle systems Gearbox 0.0961

Generator 0.0378

Rotor brake 0.0085

Nacelle cover 0.0142

Nacelle structure 0.0193

Couplings 0.0057

Shaft 0.0171

Yaw system 0.0171

Bearings 0.0171

Electrics and control Pitch system 0.0365

Variable speed system 0.0551

Tower 0.0896

Other 0.0313

Balance of plant Roads & civil works 0.0221

0.251 Electrics and grid con 0.0761

Assembly & insttlltn 0.0073

Transportation 0.0365

Foundations 0.0675

Financial and legal 0.0414

O&M 0.180 Labor 0.0792

0.180 Parts 0.0630

Operation 0.0216

Equipment 0.0090

Facilities 0.0072