J. McCalley Power System Operation, and Handling Wind Power Variability and Uncertainty in the Grid.
-
Upload
joy-harrell -
Category
Documents
-
view
223 -
download
0
Transcript of J. McCalley Power System Operation, and Handling Wind Power Variability and Uncertainty in the Grid.
J. McCalley
Power System Operation, and Handling Wind Power Variability and
Uncertainty in the Grid
Outline1. Basic problems, potential solutions2. Wind power equation3. Variability4. System Control5. Comments on potential solutions
2
Basic problems with wind & power balance1. Wind is a variable resource when it is
controlled to maximize its power productiona. Definition: NETLOAD.MW=LOAD.MW+LOSSES.MW-WIND.MWb. Fact: Wind increases NETLOAD.MW variability in gridc. Fact: Grid requires GEN.MW=NETLOAD.MW alwaysd. Fact: “Expensive” (based on marginal cost) gens move (ramp)
quickly, “cheap” gens don’t, some gens do not ramp at all.e. Problem: Increasing wind increases need for more and
“faster” resources to meet variability, increasing cost of wind.
2. Wind is an uncertain resourcea. Fact: Market makes day-ahead decisions for “unit
commitment” (UC) based on NETLOAD.MW forecast.b. Fact: Large forecast error requires available units compensate.c. Problem: Too many (under-forecast) or too few (over-
forecast) units may be available, increasing the cost of wind.3
Solutions to variability & uncertainty
1. We have always dealt with variability and uncertainty in the load, so no changes are needed.
2. Increase MW control capability during periods of expected high variability via control of the wind power.
3. Increase MW control capability during periods of expected high variability via more conventional generation.
4. Increase MW control capability during periods of expected high variability using demand control.
5. Increase MW control capability during periods of expected high variability using storage.
4 4
Power productionWind power equation
v1 vt v2
v
x
Swept area At of turbine blades:
The disks have larger cross sectional area from left to right because• v1 > vt > v2 and• the mass flow rate must be the same everywhere within the streamtube (conservation of mass):
ρ=air density (kg/m3)
Therefore, A 1 < At < A 2
2211
21
vAvAvA
Q Q Q
tt
t
Mass flow rate is the mass of substance which passes through a given surface per unit time.
5
Power productionWind power equation
ttt
t vAt
xA
t
mQ
3. Mass flow rate at swept area:
22212
1vvmKE
1. Wind velocity:t
xv
xAm 2. Air mass flowing:
4a. Kinetic energy change:
5a. Power extracted: 222
122
21 2
1
2
1vvQvv
t
m
t
KEP t
6a. Substitute (3) into (5a):)()2/1( 22
21 vvvAP tt
4b. Force on turbine blades:
21 vvQvt
m
t
vmmaF t
5b. Power extracted:
21 vvvQFvP ttt
6b. Substitute (3) into (5b):)( 21
2 vvvAP tt
ttttt vvvvvvvvvvvvvvvvv ))(2/1()())(()2/1()()()2/1( 12212
21212122
221
7. Equate
8. Substitute (7) into (6b): ))((4
)()))(2/1(( 2122
2121
221 vvvv
AvvvvAP t
t
9. Factor out v13: )1)()(1(
4 1
22
1
231
v
v
v
vvAP t
6
Power productionWind power equation
10. Define wind stream speed ratio, a:
1
2
v
va
)1)(1(4
231 aa
vAP t
11. Substitute a into power expression of (9):
12. Differentiate and find a which maximizes function:
1,3/10)1)(13(
0123122
0)1()1(24
222
231
aaaa
aaaaa
aaavA
a
P t
This ratio is fixed for a given turbine & control condition.
13. Find the maximum power by substituting a=1/3 into (11):
27
8
3
4
9
8
4)3
4)(9
11(
4
31
31
31 vAvAvA
P ttt
7
Power productionWind power equation
14. Define Cp, the power (or performance) coefficient, which gives the ratio of the power extracted by the converter, P, to the power of the air stream, Pin.
)1)(1(4
231 aa
vAP t
31
211
211
21 2
1
2
1
2
10
2
1vAvvAvQv
t
m
t
KEP ttin
power extracted by the converter
power of the air stream
)1)(1(2
1
21
)1)(1(4 2
31
231
aavA
aavA
P
PC
t
t
inp
15. The maximum value of Cp occurs when its numerator is maximum, i.e., when a=1/3:
5926.027
16)3
4)(9
8(2
1
inp P
PC
The Betz Limit!
312
1vACPCP tPinp
8
Power productionCp vs. λ and θ
Tip-speed ratio:11 v
R
v
u u: tangential velocity of blade tip
ω: rotational velocity of blade
R: rotor radiusv1: wind speed
Pitch: θ
GE SLE 1.5 MW 9
Power productionWind Power Equation
31),(
2
1vACPCP tPinp
So power extracted depends on 1.Design factors:
• Swept area, At 2.Environmental factors:
• Air density, ρ (~1.225kg/m3 at sea level)• Wind speed v3
3. Control factors affecting performance coefficient CP: • Tip speed ratio through the rotor speed ω• Pitch θ 10
Power productionCp vs. λ and θ
Tip-speed ratio:11 v
R
v
u u: tangential velocity of blade tip
ω: rotational velocity of blade
R: rotor radiusv1: wind speed
GE SLE 1.5 MW
Important concept #1:The control strategy of all US turbines today is to operate turbine at point of maximum energy extraction, as indicated by the locus of points on the black solid line in the figure.
Important concept #2:• This strategy maximizes the energy produced by a given wind turbine.• Any other strategy “spills” wind !!!
Important concept #3:• Cut-in speed>0 because blades need minimum torque to rotate.• Generator should not exceed rated power• Cut-out speed protects turbine in high winds
11
Power productionUsable speed range
Cut-in speed (6.7 mph) Cut-out speed (55 mph)
12
Wind Power Temporal & Spatial Variability
13
JULY2006JANUARY2006
Notice the temporal variability:• lots of cycling between blue and red;• January has a lot more high-wind power (red) than July;
Notice the spatial variability• “waves” of wind power move through the entire Eastern Interconnection;• red occurs more in the Midwest than in the East
Blue~VERY LOW POWER; Red~VERY HIGH POWER
13
Time frame 1: Transient control
14
Time frame 1: Transient control
15
Source: FERC Office of Electric Reliability available at: www.ferc.gov/EventCalendar/Files/20100923101022-Complete%20list%20of%20all%20slides.pdf
1-20 seconds
Time frames 2 & 3: Regulation and Load following
-100
-80
-60
-40
-20
0
20
40
60
80
100
07:00 07:20 07:40 08:00 08:20 08:40 09:00 09:20 09:40 10:00
RE
GU
LA
TIO
N I
N M
EG
AW
AT
TS
Regulation
=
+
Load Following Regulation
Source: Steve Enyeart, “Large Wind Integration Challenges for Operations / System Reliability,” presentation by Bonneville Power Administration, Feb 12, 2008, available athttp://cialab.ee.washington.edu/nwess/2008/presentations/stephen.ppt.
16
16
4 seconds to 3 minutesEvery 5 minutes
Analogy for supply-demand-frequency relationship
1717
Inflow SupplyOutflow DemandWater leve lFrequency
How Does Power System Handle Variability
18
Turbine-Gen 1Turbine-Gen 2Turbine-Gen …Turbine-Gen N
∆f∆Ptie
ACE=∆Ptie -10B∆f
Primary control controls output in response to transient frequency deviations
Secondary control provides regulation
B is BA’s frequency bias in MW/0.1Hz.B is negative.
How Does Power System Handle Variability
19
ACE= ΔPtie – BΔf = ΔPtie +| B|Δf
ΔPtie=Ptie,act-Ptie,sch
Δf=fact-60
If ΔPtie=0, Δf =0, then ACE=0, and generation does not change;If ΔPtie>0 which means the actual export exceeds the scheduled export, then this component would make ACE more positive therefore tending to reduce generation;If Δf>0 which means the actual frequency exceeds the scheduled frequency of 60 Hz, then this component would make ACE more positive therefore tending to reduce generation.
BA
REST OF THE INTERCONNECTION
P3P1
P2
Ptie=P1+P2+P3
Power Balance Control Levels
20
Control level
Name Time frame
Control objectives Function
1 Primary control, governor
1-20 seconds
Power balance and transient frequency
Transient control
2 Secondary control, AGC
4 secs-3 mins
Power balance and steady-state frequency
Regulation
3 Real-time market
Every 5 mins
Power balance and economic-dispatch
Load following and reserve provision
4 Day-ahead market
Every day, 24 hrs at a time
Power balance and economic-unit commitment
Unit commitment and reserve provision
Why Does Variability Matter?
NERC penalties for poor-performance Consequences of increased frequency variblty:
Some loads may lose performance (induction motors) Relays can operate to trip loads (UFLS), and gen (V/Hz) Lifetime reduction of turbine blades Frequency dip may increase for given loss of generation Areas without wind may regulate for windy areas
Consequences of increased ACE variability (more frequent MW corrections):
Increased inadvertent flows Increase control action of generators
Regulation moves gen “down the stack” cycling!21
Power Balance Control Levels
22
kkk LFLLR Load regulation component
Load following component
Load
12
......
12
1 11
T
LLLLLL
TLF TkTkkTkTk
Tk
Tkiik
Δt=2 min, 28 min rolling average, so T=7.
15
...... 7667 kkkkk
kLLLLL
LF
Regulation component varies about the mean and tends to go up as much as it goes down and is therefore normal with 0 mean.
Power Balance Control Levels
23
n
ixix x
n 1
22 )(1
Consider two random variables, X and Y.
If Z=X+Y, then
222yxz
Hourly Load Variability and Load-Wind Variability When Wind Penetration is 10%
0
500
1000
1500
2000
2500
3000
3500
4000
-800
-700
-600
-500
-400
-300
-200
-100
0 100
200
300
400
500
600
700
800
Load and Load-Wind Hourly Variability (MW)
Fre
qen
cy
Load Hourly Variability Load-Wind Hourly Variability
Characterizing Netload Variability∆T HISTOGRAMMeasure each ∆T variation for 1 yr (∆T=1min, 5min, 1 hr)Identify “variability bins” in MWCount # of intervals in each variability binPlot # against variability binCompute standard deviation σ.
Regulation
Load following
Ref: Growing Wind; Final Report of the NYISO 2010 Wind Generation Study, Sep 2010.www.nyiso.com/public/webdocs/newsroom/press_releases/2010/GROWING_WIND_-
_Final_Report_of_the_NYISO_2010_Wind_Generation_Study.pdf
24
Loads:2011: 12600 MW2013: 12900 MW2018: 13700 MW
Solutions to variability & uncertainty1. Do nothing: fossil-plants provide reg & LF (and die ).2. Increase control of the wind generation
a. Provide wind with primary control• Reg down (4%/sec), but spills wind following the control • Reg up, but spills wind continuously
b. Limit wind generation ramp rates• Limit of increasing ramp is easy to do• Limit of decreasing ramp is harder, but good forecasting
can warn of impending decrease and plant can begin decreasing in advance
3. Increase non-wind MW ramping capability during periods of expected high variability using one or more of the below:a. Conventional generation b. Load controlc. Storaged. Expand control areas
25
%/min $/mbtu $/kw LCOE,$/mwhr
Coal 1-5 2.27 2450 64
Nuclear 1-5 0.70 3820 73
NGCC 5-10 5.05 984 80
CT 20 5.05 685 95
Diesel 40 13.8125
How to decide?First, frequency control for over-frequency conditions, which requires generation reduction, can be effectively handled by pitching the blades and thus reducing the power output of the machine. Although this action “spills” wind, it is effective in providing the necessary frequency control. Second, frequency control for under-frequency conditions requires some “headroom” so that the wind turbine can increase its power output. This means that it must be operating below its maximum power production capability on a continuous basis. This also implies a “spilling” of wind.Question: Should we “spill” wind in order to provide frequency control, in contrast to using all wind energy and relying on some other means to provide the frequency control? Answer: Need to compare system economics between increased production costs from spilled wind, and increased investment, maint, & production costs from using storage & conventional gen.
26
26