BTP Stage1 Final
-
Upload
pradeep-kundu -
Category
Documents
-
view
236 -
download
0
Transcript of BTP Stage1 Final
-
8/13/2019 BTP Stage1 Final
1/20
B tech Project Presentation
on
Remaining Useful Life Prediction
Presented
by
Janam Shah(0900305)
Astha Jain(0900313)
Guided
by
Dr. Bhupesh Kumar Lad
Manish Rawat (PhD Scholar)
Mechanical Engineering Department
School of Engineering
INDIAN INSTITUTE OF TECHNOLOGY INDORE
-
8/13/2019 BTP Stage1 Final
2/20
Objective
Prediction of Remaining useful life of
mechanical component (Bearing) to achieve
goals of maintenance using two
models/methods.
ANN Model (Stage I)
Markov Model (Stage II)
2
-
8/13/2019 BTP Stage1 Final
3/20
Introduction to Maintenance
All actions necessary for retaining an item, or restoringto it to a serviceable condition, include servicing, repair,modification, overhaul, inspection and conditionverification.
The main objective is to become consistent with the goalsof production.
Cost
Quality
Delivery
3
-
8/13/2019 BTP Stage1 Final
4/20
Types Of Maintenance
Corrective or Breakdown maintenance
Preventive maintenance
Predictive (Condition-based) maintenance
4
-
8/13/2019 BTP Stage1 Final
5/20
Predictive Maintenance
In predictive maintenance, machinery conditions areperiodically monitored and this enables the maintenance
crews to take timely actions such as, machine adjustment,
repair or overhaul.
One can make use of predictive maintenance by using a
technique called signature analysis, which is intended to
continually monitor the health of equipment by recording
systematically signals derived in the form of vibration, noise,
pressure, relative displacement, etc.
5
-
8/13/2019 BTP Stage1 Final
6/20
Introduction To Prognostics
Prognostics is an engineering discipline focused on predicting
the time at which a system or a component will no longerperform its intended function.
Prognostics is, or should be, performed at the component or
sub-component level.
Prognostics involves predicting the time progression of a
specific failure mode from its incipience to the time of
component failure.
6
-
8/13/2019 BTP Stage1 Final
7/20
Mahamad, et al, 2010, proposed ANN model which
uses the time and weibull hazard rate of rms and
kurtosis for predicting the RUL of bearing.
Normalized life percentage is selected as the output. We tried to replicate the results of this journal.
-
8/13/2019 BTP Stage1 Final
8/20
Failure Parameter - Vibration
Vibration is widely used to predict bearing failure
because a distinctive frequency known as the
defective frequency is excited.
Thus, vibration analysis becomes the most suitablecondition monitoring technique for investigating the
evolution of these defective frequencies over time.
8
-
8/13/2019 BTP Stage1 Final
9/20
Failure Signature
RMS Value
Kurtosis factor
where is the mean, s is the standard deviation, and Nis thenumber of data points.
9
-
8/13/2019 BTP Stage1 Final
10/20
Test set-up
Four bearings were installed on one shaft. On each bearing one accelerometer was installed for a total of 4
accelerometers (one for horizontal X on each). The Figure belowshows the test rig and illustrates sensor placement.
-
8/13/2019 BTP Stage1 Final
11/20
Each data file consists of 4 columns. Each column
corresponds to one accelerometer signal.
The column headers for the 4 columns represent the
data coming from the 4 accelerometers. Vibration data was collected every 10 minutes till the
bearing failure occurs.
It is observed that the bearing 1 fails.
Data is collected from the website of NASA www.ti.arc.nasa.gov
11
Data Collection
http://www.ti.arc.nasa.gov/http://www.ti.arc.nasa.gov/ -
8/13/2019 BTP Stage1 Final
12/20
-
8/13/2019 BTP Stage1 Final
13/20
Kurtosis curve of bearing 1
0
2
4
6
8
10
12
14
16
18
0 200 400 600 800 1000 1200
Series1
-
8/13/2019 BTP Stage1 Final
14/20
Weibull Hazard rates of RMS and Kurtosis Using Weibull++ software, we calculate shape and scale
parameter of rms and kurtosis both which are taken as inputs
to neural network.
The values of scale parameter() and the shape parameter()
is found out, which comes in close proximity to the actual
values got in the journal.
Weibull hazard Function is (/)(t/)^-1
Bearings RMS Kurtosis
Bearing 1 =0.119929
=1.948683
=4.176532
=3.008815
Bearing 2 =0.105442
=4.965653
=3.227931
=9.762985
Bearing 3 =0.111056
=5.878543
=4.577640
=7.872255
Bearing 4 =0.065338
=3.892966
=3.209184
=12.901483
-
8/13/2019 BTP Stage1 Final
15/20
Inputs used in model
6 inputs are used in the model:
Time t-1
Time t
Weibull hazard function of rms Z1(t-1)
Z2(t)
Weibull hazard function of kurtosis Z2(t-1)
Z2(t)
-
8/13/2019 BTP Stage1 Final
16/20
-
8/13/2019 BTP Stage1 Final
17/20
Future work-plan
The predicted RUL will be used for condition based
maintenance planning.
Opportunistic maintenance of a group of items can
be done with the help of this model. Prediction of RUL by using Markov model.
Comparison of the RUL predicted from ANN and
Markov model
-
8/13/2019 BTP Stage1 Final
18/20
Gantt Chart
-
8/13/2019 BTP Stage1 Final
19/20
-
8/13/2019 BTP Stage1 Final
20/20
Thank you!!!