BTP Stage1 Final

download BTP Stage1 Final

of 20

Transcript of BTP Stage1 Final

  • 8/13/2019 BTP Stage1 Final

    1/20

    B tech Project Presentation

    on

    Remaining Useful Life Prediction

    Presented

    by

    Janam Shah(0900305)

    Astha Jain(0900313)

    Guided

    by

    Dr. Bhupesh Kumar Lad

    Manish Rawat (PhD Scholar)

    Mechanical Engineering Department

    School of Engineering

    INDIAN INSTITUTE OF TECHNOLOGY INDORE

  • 8/13/2019 BTP Stage1 Final

    2/20

    Objective

    Prediction of Remaining useful life of

    mechanical component (Bearing) to achieve

    goals of maintenance using two

    models/methods.

    ANN Model (Stage I)

    Markov Model (Stage II)

    2

  • 8/13/2019 BTP Stage1 Final

    3/20

    Introduction to Maintenance

    All actions necessary for retaining an item, or restoringto it to a serviceable condition, include servicing, repair,modification, overhaul, inspection and conditionverification.

    The main objective is to become consistent with the goalsof production.

    Cost

    Quality

    Delivery

    3

  • 8/13/2019 BTP Stage1 Final

    4/20

    Types Of Maintenance

    Corrective or Breakdown maintenance

    Preventive maintenance

    Predictive (Condition-based) maintenance

    4

  • 8/13/2019 BTP Stage1 Final

    5/20

    Predictive Maintenance

    In predictive maintenance, machinery conditions areperiodically monitored and this enables the maintenance

    crews to take timely actions such as, machine adjustment,

    repair or overhaul.

    One can make use of predictive maintenance by using a

    technique called signature analysis, which is intended to

    continually monitor the health of equipment by recording

    systematically signals derived in the form of vibration, noise,

    pressure, relative displacement, etc.

    5

  • 8/13/2019 BTP Stage1 Final

    6/20

    Introduction To Prognostics

    Prognostics is an engineering discipline focused on predicting

    the time at which a system or a component will no longerperform its intended function.

    Prognostics is, or should be, performed at the component or

    sub-component level.

    Prognostics involves predicting the time progression of a

    specific failure mode from its incipience to the time of

    component failure.

    6

  • 8/13/2019 BTP Stage1 Final

    7/20

    Mahamad, et al, 2010, proposed ANN model which

    uses the time and weibull hazard rate of rms and

    kurtosis for predicting the RUL of bearing.

    Normalized life percentage is selected as the output. We tried to replicate the results of this journal.

  • 8/13/2019 BTP Stage1 Final

    8/20

    Failure Parameter - Vibration

    Vibration is widely used to predict bearing failure

    because a distinctive frequency known as the

    defective frequency is excited.

    Thus, vibration analysis becomes the most suitablecondition monitoring technique for investigating the

    evolution of these defective frequencies over time.

    8

  • 8/13/2019 BTP Stage1 Final

    9/20

    Failure Signature

    RMS Value

    Kurtosis factor

    where is the mean, s is the standard deviation, and Nis thenumber of data points.

    9

  • 8/13/2019 BTP Stage1 Final

    10/20

    Test set-up

    Four bearings were installed on one shaft. On each bearing one accelerometer was installed for a total of 4

    accelerometers (one for horizontal X on each). The Figure belowshows the test rig and illustrates sensor placement.

  • 8/13/2019 BTP Stage1 Final

    11/20

    Each data file consists of 4 columns. Each column

    corresponds to one accelerometer signal.

    The column headers for the 4 columns represent the

    data coming from the 4 accelerometers. Vibration data was collected every 10 minutes till the

    bearing failure occurs.

    It is observed that the bearing 1 fails.

    Data is collected from the website of NASA www.ti.arc.nasa.gov

    11

    Data Collection

    http://www.ti.arc.nasa.gov/http://www.ti.arc.nasa.gov/
  • 8/13/2019 BTP Stage1 Final

    12/20

  • 8/13/2019 BTP Stage1 Final

    13/20

    Kurtosis curve of bearing 1

    0

    2

    4

    6

    8

    10

    12

    14

    16

    18

    0 200 400 600 800 1000 1200

    Series1

  • 8/13/2019 BTP Stage1 Final

    14/20

    Weibull Hazard rates of RMS and Kurtosis Using Weibull++ software, we calculate shape and scale

    parameter of rms and kurtosis both which are taken as inputs

    to neural network.

    The values of scale parameter() and the shape parameter()

    is found out, which comes in close proximity to the actual

    values got in the journal.

    Weibull hazard Function is (/)(t/)^-1

    Bearings RMS Kurtosis

    Bearing 1 =0.119929

    =1.948683

    =4.176532

    =3.008815

    Bearing 2 =0.105442

    =4.965653

    =3.227931

    =9.762985

    Bearing 3 =0.111056

    =5.878543

    =4.577640

    =7.872255

    Bearing 4 =0.065338

    =3.892966

    =3.209184

    =12.901483

  • 8/13/2019 BTP Stage1 Final

    15/20

    Inputs used in model

    6 inputs are used in the model:

    Time t-1

    Time t

    Weibull hazard function of rms Z1(t-1)

    Z2(t)

    Weibull hazard function of kurtosis Z2(t-1)

    Z2(t)

  • 8/13/2019 BTP Stage1 Final

    16/20

  • 8/13/2019 BTP Stage1 Final

    17/20

    Future work-plan

    The predicted RUL will be used for condition based

    maintenance planning.

    Opportunistic maintenance of a group of items can

    be done with the help of this model. Prediction of RUL by using Markov model.

    Comparison of the RUL predicted from ANN and

    Markov model

  • 8/13/2019 BTP Stage1 Final

    18/20

    Gantt Chart

  • 8/13/2019 BTP Stage1 Final

    19/20

  • 8/13/2019 BTP Stage1 Final

    20/20

    Thank you!!!