Amendment of well completion status - slrconsulting.com · 1 It should be noted that the actual...
Transcript of Amendment of well completion status - slrconsulting.com · 1 It should be noted that the actual...
APPLICATION TO AMEND
ENVIRONMENTAL MANAGEMENT
PROGRAMME BLOCK 11B/12B
Amendment of well completion status
Prepared for: Total E&P South Africa B.V.
Authority Ref: 12/3/067
SLR Project No: 720.20047.00003
Revision No: 1:
12 November 2018
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
i
DOCUMENT INFORMATION
Title Application to Amend Environmental Management Programme Block
11B/12B: Amendment of well completion status
Project Manager Jonathan Crowther
Project Manager e-mail [email protected]
Author Jonathan Crowther
Reviewer Jonathan Crowther
Keywords Block 11B/12B; Well Drilling; Amendment application
Status EIR for submission to DMR
Authority Reference No 12/3/067
SLR Project No 720.20047.00003
DOCUMENT REVISION RECORD
Rev No. Issue Date Description Issued By
A 9 November 2018 EMPR Amendment issued for client review Jonathan Crowther
B 12 November 2018 EMPR Amendment issued for I&AP review Jonathan Crowther
BASIS OF REPORT
This document has been prepared by an SLR Group company with reasonable skill, care and diligence, and taking account of the manpower, timescales
and resources devoted to it by agreement with Total E&P South Africa B.V. (the Client) for part or all of the services it has been appointed by the Client to
carry out. It is subject to the terms and conditions of that appointment.
SLR shall not be liable for the use of or reliance on any information, advice, recommendations and opinions in this document for any purpose by any
person other than the Client. Reliance may be granted to a third party only in the event that SLR and the third party have executed a reliance agreement
or collateral warranty.
Information reported herein may be based on the interpretation of public domain data collected by SLR, and/or information supplied by the Client
and/or its other advisors and associates. These data have been accepted in good faith as being accurate and valid.
SLR disclaims any responsibility to the Client and others in respect of any matters outside the agreed scope of the work.
The copyright and intellectual property in all drawings, reports, specifications, bills of quantities, calculations and other information set out in this report
remain vested in SLR unless the terms of appointment state otherwise.
This document may contain information of a specialised and/or highly technical nature and the Client is advised to seek clarification on any elements
which may be unclear to it.
Information, advice, recommendations and opinions in this document should only be relied upon in the context of the whole document and any
documents referenced explicitly herein and should then only be used within the context of the appointment.
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
ii
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
iii
EXECUTIVE SUMMARY
INTRODUCTION 1
This Executive Summary provides a comprehensive synopsis of the Environmental Management Programme
(EMPR) Amendment prepared as part of an amendment application process being undertaken by Total E&P
South Africa B.V. (hereafter referred to as “TEPSA”).
1.1 PROJECT BACKGROUND
TEPSA is the holder of an Exploration Right to undertake seismic surveys and exploration well drilling in defined
areas within Block 11B/12B. The Exploration Right area has a total extent of approximately 18 773 km2
and is
situated approximately 130 km offshore of the south coast in water depths of between 500 m and 2 000 m.
The approved drilling area covers an area of approximately 4 066 km2 (see Figure A).
Experience gained in the initial drilling of the Brulpadda well in 2014, highlighted a number of technical
difficulties facing the well drilling operation. These relate to drilling a deepwater well in a high energy marine
environment and the strongly flowing Agulhas current passing through the area of drilling interest. Taking
cognisance of the technical issue learning points, TEPSA is now applying to amend its EMPR in order to leave
the wellhead on the seafloor on completion of the drilling operation
An application to amend an EMPR is provided for in Section 37 of the Environmental Impact Assessment (EIA)
Regulations 2014, as amended, promulgated in terms of Sections 24(5) and 44 of the National Environmental
Management Act, 1998 (No. 107 of 1998), as amended (NEMA). An EMPR Amendment application must be
subjected to a public participation process before it can be approved by the competent authority, which in this
case is the Petroleum Agency SA (PASA).
SLR Consulting (South Africa) (Pty) Ltd (hereafter referred to as SLR) has been appointed by TEPSA as the
independent environmental consultant to undertake the necessary amendment application process. The
outcome of the application process will be the submission an EMPr Amendment report to PASA.
1.2 OPPORTUNITY TO COMMENT
This EMPR Amendment has been distributed for a 30-day comment period from 13 November to
13 December 2018 in order to provide Interested and Affected Parties (I&APs) with an opportunity to
comment on any aspect of the proposed project and the findings of the EMPR amendment process. Copies of
the full report have been made available on the SLR website (at http://slrconsulting.com/za/).
Any comments should be forwarded to SLR at the address, telephone/fax numbers or e-mail address shown
below. For comments to be included in the updated EIR, comments should reach SLR by no later than
13 December 2018.
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
iv
2. APPROACH AND METHODOLOGY TO THE AMENDMENT PROCESS
2.1 SPECIALISTS STUDIES
Two specialist studies were undertaken to address the key issues that required further investigation, namely
the impact on fishing and marine fauna. Specialist studies involved the gathering of data relevant to identifying
and assessing environmental impacts that may occur as a result of the proposed amendments to the project.
These impacts were then assessed according to pre-defined rating scales. Specialists also recommended
appropriate mitigation or optimisation measures to minimise potential impacts or enhance potential benefits,
respectively.
2.2 INTEGRATION AND ASSESSMENT
The above-mentioned specialist studies and other relevant information / assessments have been integrated
into the EMPR Amendment report. This report aims to present all information in a clear and understandable
format, suitable for easy interpretation by I&APs and authorities, and to provide an opportunity for I&APs to
comment on the proposed EMPR amendment and findings of the amendment process.
The following steps are envisaged for the remainder of the EMPR amendment process:
• After closure of the EMPR Amendment comment period, all comments received will be incorporated and
responded to in a Comments and Responses Report. The EMPR Amendment will then be updated into a
final report, to which the Comments and Responses Report will be appended.
• The final report will be submitted to PASA for consideration and decision-making by the Minister of
Mineral Resources (or delegated authority).
• After the competent authority has reached a decision, all I&APs on the project database will be notified
of the outcome of the application and the reasons for the decision.
• A statutory appeal period in terms of the National Appeal Regulations (GN No. R993) will follow the
issuing of the decision.
.
SLR Consulting (South Africa) (Pty) Ltd
Attention: Mandy Kula
PO Box 10145, CALEDON SQUARE, 7905
Unit 39 Roeland Square, 30 Drury Lane, CAPE TOWN, 8001
Tel: (021) 461 1118/9
Fax: (021) 461 1120
E-mail: [email protected]
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
v
FIGURE A: LOCALITY OF BLOCK 11B/12B OFF THE SOUTH COAST OF SOUTH AFRICA. THE AREA OF INTEREST FOR DRILLING IS HIGHLIGHTED.
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
vi
3. PROJECT DESCRIPTION
3.1 APPROVED WELL COMPLETION
The approved EMPr requires that once the well had been plugged to ensure well integrity1, the wellhead would
then be removed, with casing cut-off approximately 3 m below the seafloor and all sundry equipment removed
to leave the seafloor clear.
3.3 DESCRIPTION OF AMENDED WELL COMPLETION STATUS
As noted above, TEPSA is applying to amend its EMPr in order to leave the wellhead on the seafloor on
completion of the drilling operation. Detailed rationale for this approach is provided in the Risk Report that
TEPSA has compiled as part of the amendment application (see Appendix 4). A combination of the normal
challenges inherent in deepwater exploration together with the specific metocean challenges (harsh sea
conditions and strong currents) place a significant risk on the wellhead removal operation. Typical challenges
would include:
• The requirement to wait on an adequate weather window to perform the operation;
• Low reliability of the weather forecast in relation to the Agulhas Current behaviour and movement; and
• The risk of rig position loss due to current unpredictability.
Based on the perceived risk of conducting well removal under the specific metocean conditions associated with
the drilling area location, TEPSA is applying for an amendment to leave wellheads on the seafloor.
4. DESCRIPTION OF THE AFFECTED ENVIRONMENT
4.1 PHYSICAL OCEANOGRAPHY
The oceanography of the South Coast is almost totally dominated by the warm Agulhas Current which forms
between 25° and 30° S and flows southwards along the shelf edge of the southern African East Coast, as part of
the anticyclonic Indian Ocean gyre. It is a well-defined and intense jet some 100 km wide and 1 000 m deep
flowing in a south-west direction at a rapid rate, with current speeds of 2.5 m/s or more. On the eastern half of
the South Coast, the Agulhas Current flows along the shelf break at speeds of up to 3 m/sec, diverging inshore
of the shelf break south of Still Bay (before realigning to the shelf break off Cape Agulhas.
Westerly winds predominate along the South Coast in winter, frequently reaching gale force strengths. During
summer, easterly wind directions increase markedly resulting in roughly similar strength/frequency of east and
west winds during that season.
______________________
1 It should be noted that the actual wellhead has no impact on well integrity once a well has been plugged for abandonment. The well
integrity is guaranteed by plugging the well with two independent barriers provided by setting the cement plugs in the well. This
occurs irrespective of the wellhead completion status.
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
vii
On the South Coast, the majority of waves arrive from the south-west quadrant, dominating wave patterns
during winter and spring. Waves from this direction frequently exceed 6 m and can reach up to 10 m. During
summer, easterly wind-generated ‘seas’ occur.
4.2 BIOLOGICAL OCEANOGRAPHY
The Block 11B/12B Exploration Right area falls within the Agulhas Inshore and West Indian Offshore bioregions.
The biological communities occurring in the Block 11B/12B area consist of many hundreds of species, often
displaying considerable temporal and spatial variability (even at small scales). The majority of the approved
well drilling area falls within an area that is defined as least threatened in terms of the ecosystem threat status.
A very small portion in the west coincides with a vulnerable area.
The ichthyofauna on the South Coast is diverse, comprising a mixture of temperate and tropical species. The
seabed of the Agulhas Bank substrate is also diverse comprising areas of sand, mud and coral thereby
contributing to increased benthic fauna and fish species. The fish most likely to be encountered on the shelf,
beyond the shelf break and in the offshore waters of Block 11B/12B are the large migratory pelagic species,
including various tunas, billfish and sharks.
Three species of turtle occur along the Southwest Coast, namely the leatherback (Vulnerable), and occasionally
the loggerhead (Endangered) and the green (Endangered) turtle. Juvenile leatherback and the loggerhead that
reach the sea after hatching, are carried south westward by the Agulhas Current. Green turtles are non-
breeding residents often found feeding on inshore reefs.
Of the 60 seabird species that are known, or thought likely to occur, along the South Coast, fifteen species
breed in southern Africa: Cape gannet, African penguin, four species of cormorant, white pelican, three gull
and four tern species. The breeding areas are distributed around the coast with islands being especially
important.
The marine mammal fauna occurring off the southern African coast includes several species of whales and
dolphins and one resident seal species. Thirty six species or sub species/populations of cetaceans (whales and
dolphins) are known (based on historic sightings or strandings records) or likely (based on habitat projections
of known species parameters) to occur in these waters. The most common species within Block 11B/12B (in
terms of likely encounter rate not total population sizes) are likely to be the long-finned pilot whale and
humpback whale
The Cape fur seal (Arctocephalus pusillus pusillus) is the only seal species that has breeding colonies along the
South Coast, namely at Seal Island in Mossel Bay, on the northern shore of the Robberg Peninsula in
Plettenberg Bay and at Black Rocks (Bird Island group) in Algoa Bay.
4.3 MARINE PROTECTED AREAS
Numerous coastal marine protected areas (MPAs) exist along the South Coast. Of these, the Goukamma,
Robberg and Tsitsikama MPAs are located inshore of Block 11B/12B. It is noted that a network of 20 MPAs was
approved by Cabinet on 24 October 2018, however there is no overlap with the area of interest for well drilling
and these recently approved MPAs.
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
viii
5. IMPACT ASSESSMENT CONCLUSIONS
5.1 MARINE FAUNA
Considering the ecosystem threat status of ‘least threatened’ in the drilling area, and the negligible proportion
of the benthic habitat type and the wider South-west Indian Offshore Bioregion potentially affected by the
subsea infrastructure, the specialist marine fauna study assessed the impact of leaving wellheads on the
seafloor as being of Low significance and concluded that there is no reason in terms of marine fauna why the
wellheads should not be left in place on the seabed.
5.2 FISHERIES
The proposed TEPSA drilling area is located in a water depth of between 500 m and 2 000 m. In a fisheries
context, trawl fisheries have been confined to the “shelf” referring to the “continental shelf”. Historically
trawling in South African waters has been confined to depths shallower than 500 m. Generally, depths beyond
500 m are defined as being on “the shelf edge” and an area that drops off steeply and of rougher substrate
type. Currently no fisheries would be affected by leaving a wellhead on the seafloor within the drilling area.
Thus there would be no impact on any fisheries.
The fisheries specialist study concludes that possible future demersal trawling is the only likely fishery that
could present a problem related to fouling with a wellhead in the drilling area. This could mean loss of the
trawl gear, loss of trawl warps, and in extreme cases, loss of the vessel due to loss of stability resulting from the
fouling.
Historical records of research trawling in the vicinity of the approved drilling area provide support for the
future expansion of trawling into the area:
• Hake directed bottom trawling in the last decade has systematically targeted fish in increasing water
depths.
• There has in the past been interest in the shelf drop off for trawling for deep-water species, specifically
orange roughy (Hoplostehus sp.), deep-water dories (oreos), cardinal fish, alfonsino and various other
species. There are established trawl fisheries for these species in Namibia and on the South West Indian
Ocean Ridge that fish in depths of between 1 000 m and 2 000 m. All of these species occur off the
Agulhas Bank and there continues to be interest in their commercial potential.
• In the mid 1990’s South Africa did have an experimental fishery for Oreo Dorie extending from south of
Cape Point towards the tip of the Agulhas Bank and further east. The trawling industry lost interest in the
fishery due to low abundance of the target species and high risk to the trawl gear.
• In the early to mid 1990’s one operator undertook a comprehensive side scan sonar survey for orange
roughy along the edge of the Agulhas Bank. Although seamounts and other suitable habitat was found
for orange roughy, viable commercial quantities were not found.
• The Department of Agriculture Forestry and Fisheries (DAFF) has also undertaken deep-water
exploratory trawling for deep-water species in the TEPSA drilling area. The results of these trawls have
shown the area to be of high risk to trawling.
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
ix
Factors inhibiting the expansion of trawling into the drilling area include the following:
• The combination of depth and strong currents is the greatest deterrent to trawling for deep-water
species off the south and south eastern Agulhas Bank. The risk of losing trawl gear at these depths is
high.
• The Agulhas Current can reach 5 kts in places, it is irregular (and retroflects from westward moving to
eastwards) and may reverse at depth i.e. surface flowing currents may flow in the opposite direction at
the bottom.
• Weather and sea conditions are more extreme in the area, increasing the risk of losing trawl gear.
• The shelf edge and substrate type is of a generally high profile and unless suitable flat trawling ground
can be found, is difficult to trawl.
• Evidence of commercial quantities of deep-water species have to date not been found.
• Currently, targeting deep-water species is not permitted – if a fishery at these depths is found, the
trawling industry will need to apply for experimental fishing licenses.
• The area extending from the tip of Agulhas Bank eastwards to East London in depths up to 2 000 m has
been shown to have unique cold water corals and have been classified in places as a “Vulnerable Marine
Ecosystem” of VMEs. There is scientific interest in the area related to VMEs, specific habitat types and
corals. While there are no current restrictions to fishing in the area, the possibility that some habitats
may be protected in the future cannot be ruled out.
The specialist study concludes that there is currently no active fishery that would be affected by the proposed
application to abandon a wellhead in the project area. The possibility that trawling may occur in the proposed
area in the future cannot be ruled out; however, and the trawl gear used would pose a risk of damage to the
trawler should snagging occur. This risk could be mitigated by providing an over-trawlable structure to the
wellhead. Making the structure over-trawlable would mitigate the risk of damage to the fishing operation as
well as to potential damage to the wellhead.
5.3 EAP RECOMMENDATION
The findings of both specialists studies conclude that in terms of marine biophysical environment and the
current extent of fisheries, that the impact of leaving a wellhead on the seafloor would of low to negligible
significance.
The critical issue that needs to be evaluated in the decision-making process, is the implication of wellhead
infrastructure on future fisheries, specifically demersal trawl. There are indications that the demersal trawl
fishery could extend into deeper waters in the area proposed for drilling (although there are a number of
mitigations factors that also suggest fishing in deepwater with the strong Agulhas current may itself pose
problems), and could thus be affected by any infrastructure left on the seafloor. Should such a future risk not
be considered acceptable – then mitigation in the form of an over-trawlable structure should be a requirement
for well completion status within the approved drilling area. Such structures are assessed to be adequate to
remove the residual risk to future fisheries.
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
x
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
xi
CONTENTS
EXECUTIVE SUMMARY ............................................................................................................................... III
INTRODUCTION ................................................................................................................................. 1 1
PROJECT BACKGROUND ................................................................................................................................. 1 1.1
AUTHORISATION REQUIREMENTS ................................................................................................................. 1 1.2
PURPOSE OF THIS REPORT ............................................................................................................................. 3 1.3
STRUCTURE OF THIS REPORT ......................................................................................................................... 3 1.4
OPPORTUNITY TO COMMENT ........................................................................................................................ 4 1.5
LEGISLATIVE REQUIREMENTS ............................................................................................................. 5 2
OVERVIEW OF THE “ONE ENVIRONMENTAL SYSTEM” .................................................................................. 5 2.1
MINERAL AND PETROLEUM RESOURCES DEVELOPMENT ACT, 2002 ............................................................ 5 2.2
NATIONAL ENVIRONMENTAL MANAGEMENT ACT, 1998 .............................................................................. 5 2.3
APPROACH AND METHODOLOGY TO THE AMENDMENT PROCESS ....................................................... 7 3
DETAILS OF THE PROJECT TEAM .................................................................................................................... 7 3.1
3.1.1 QUALIFICATIONS AND EXPERIENCE OF THE EAP ................................................................................................................................ 7
ASSUMPTIONS ............................................................................................................................................... 7 3.2
OBJECTIVES .................................................................................................................................................... 8 3.3
SPECIALISTS STUDIES ..................................................................................................................................... 8 3.4
INTEGRATION AND ASSESSMENT .................................................................................................................. 8 3.5
3.5.1 COMPILATION AND REVIEW OF THE EMPR AMENDMENT ............................................................................................................... 8
3.5.2 COMPLETION OF THE AMENDMENT PROCESS .................................................................................................................................. 9
PROJECT DESCRIPTION ..................................................................................................................... 11 4
GENERAL PROJECT INFORMATION .............................................................................................................. 11 4.1
4.1.1 EXPLORATION RIGHT HOLDER ........................................................................................................................................................... 11
4.1.2 EXPLORATION RIGHT AREA ............................................................................................................................................................... 11
PROJECT DESCRIPTION ................................................................................................................................ 11 4.2
4.2.1 APPROVED WELL COMPLETION ........................................................................................................................................................ 11
4.2.2 DESCRIPTION OF AMENDED WELL COMPLETION STATUS .............................................................................................................. 13
DESCRIPTION OF THE AFFECTED ENVIRONMENT ............................................................................... 15 5
5.1 PHYSICAL OCEANOGRAPHY ......................................................................................................................... 15
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
xii
BIOLOGICAL OCEANOGRAPHY ..................................................................................................................... 15 5.2
MARINE PROTECTED AREAS ........................................................................................................................ 17 5.3
HUMAN UTILISATION ................................................................................................................................... 17 5.4
5.4.1 COMMERCIAL FISHERIES ................................................................................................................................................................... 17
5.4.2 MARINE TRAFFIC AND INFRASTRUCTURE ......................................................................................................................................... 21
IMPACT DESCRIPTION AND ASSESSMENT ......................................................................................... 23 6
MARINE FAUNA ........................................................................................................................................... 23 6.1
FISHERIES ..................................................................................................................................................... 24 6.2
CONCLUSIONS AND RECOMMENDATIONS ........................................................................................ 29 7
MARINE FAUNA ........................................................................................................................................... 29 7.1
FISHERIES ..................................................................................................................................................... 29 7.2
ENVIRONMENTAL MANAGEMENT PROGRAMME .............................................................................. 31 8
REFERENCES .................................................................................................................................... 47 9
APPENDICES
APPENDIX 1: CONVENTION FOR ASSIGNING SIGNIFICANCE RATINGS TO IMPACTS
APPENDIX 2: MARINE FAUNAL ASSESSMENT
APPENDIX 3: FISHERIES ASSESSMENT
APPENDIX 4: RISK REPORT
APPENDIX 5: PUBIC PARTICIPATION PROCESS
APPENDIX 5.1: I&AP DATABASE
APPENDIX 5.2: I&AP NOTIFICATION OF EMPR AMENDMENT
LIST OF TABLES
TABLE 3-1: DETAILS OF THE EIA PROJECT TEAM .............................................................................................. 7
TABLE 3-2: SPECIALISTS STUDIES ..................................................................................................................... 8
TABLE 6-1: IMPACT ON MARINE BENTHOS OF LEAVING WELLHEADS ON THE SEAFLOOR ........................... 24
TABLE 6-2: FISHERIES AND THE LIKELY IMPACT THAT WELLHEADS WOULD HAVE ON THEM ...................... 25
TABLE 6-3: IMPACT ON DEMERSAL FISHING OF LEAVING WELLHEADS ON THE SEAFLOOR ......................... 26
LIST OF FIGURES
FIGURE 1-1: LOCALITY OF BLOCK 11B/12B OFF THE SOUTH COAST OF SOUTH AFRICA. THE AREA OF
INTEREST FOR DRILLING IS HIGHLIGHTED. .................................................................................... 2
FIGURE 4-1: PHOTOGRAPH OF WELLHEAD ON THE SEAFLOOR ...................................................................... 12
FIGURE 4-2: DIAGRAMATIC CROSS SECTION OF CASING HOUSING 3.5 METRES ABOVE SEAFLOOR .............. 12
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
xiii
FIGURE 5-1: BLOCK 11B/12B IN RELATION TO THE EXISITNG MARINE PROTECTED AREAS (ALONG
THE COAST) AND OFFSHORE MARINE PROTECTED AREAS RECENTLY ACCEPTED BY
CABINET. AFTER PISCES 2018....................................................................................................... 17
FIGURE 5-2: BLOCK 11B/12B IS RELATION TO DEMERSAL TRAWL EFFORT. .................................................... 18
FIGURE 5-3: BLOCK 11B/12B IN RELATION TO DEMERSAL LONGLINE EFFORT ............................................... 19
FIGURE 5-4: BLOCK 11B/12B IN RELATION TO PELAGIC LONGLINE EFFORT ................................................... 19
FIGURE 5-5: BLOCK 11B/12B IN RELATION TO SOUTH COAST ROCK LOBSTER EFFORT .................................. 20
FIGURE 5-6: BLOCK 11B/12B IN RELATION TO DAFF RESEARCH TRAWING EFFORT ....................................... 20
FIGURE 5-7: BLOCK 11B/12B IN RELATION TO DAFF RESEARCH SIESMIC SURVEY LINES ................................ 21
FIGURE 6-1: EXAMPLE OF AN OVER-TRAWLABLE STRUCTURE ........................................................................ 27
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
xiv
ACRONYMS AND ABBREVIATIONS
Acronym /
Abbreviation Definition
CITES Convention on International Trade in Endangered Species
cm centimetres
cm/s centimetres per second
CMS Convention on Migratory Species
CO Carbon monoxide
CO2 Carbon dioxide
COLREGS Convention on the International Regulations for Preventing Collisions at Sea
DAFF Department of Agriculture, Forestry and Fisheries
DEA Department of Environmental Affairs
DMR Department of Mineral Resources
EAP Environmental Assessment Practitioner
EEZ Exclusive Economic Zone
EIA Environmental Impact Assessment
EMPR Environmental Management Programme
g/m2 grams per square metre
g/m3 grams per cubic metre
GN Government Notice
I&APs Interested & Affected Parties
IUCN International Union for Conservation of Nature
km kilometres
km2 Square kilometres
m Metres
m2 Square metres
m3 Cubic metre
MARPOL International Convention for the Prevention of Pollution from Ships, 1973/1978
mg/l Milligrams per litre
mm Millimetres
MPA Marine Protected Area
MPRDA Mineral and Petroleum Resources Development Act, 2002 (No. 28 of 2002)
NEMA National Environmental Management Act, 1998 (No. 107 of 1998)
PASA Petroleum Agency SA
SLR SLR Consulting (South Africa) (Pty) Ltd
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
1
INTRODUCTION 1
This chapter provides a brief description of the project background, summarises the legislative authorisation
requirements, describes the purpose of this report and presents the structure of the report.
PROJECT BACKGROUND 1.1
Total E&P South Africa B.V. (hereafter referred to as “TEPSA”) is the holder of an Exploration Right to
undertake seismic surveys and exploration well drilling in defined areas within Block 11B/12B (see Figure 1-1).
An Environmental Authorisation approving a Basic Assessment (BA) for undertaking exploration well drilling
was granted on 17 January 2011 in terms of the National Environmental Management Act, 1998 (No. 107 of
1998), as amended (NEMA) and a Record of Decision (ROD) was issued by the Petroleum Agency SA (PASA) for
the approval of the Environmental Management Programme Report (EMPR) amendment on 18 May 2012 in
terms of the Minerals and Petroleum Resources Development Act, 2002 (No. 28 of 2002), as amended
(MPRDA).
In terms of the project description provided in the above approved BA and EMPr, completion of exploration
well drilling would include removal of the wellhead with casings cut-off 3 m below the seafloor and all sundry
wellhead equipment removed to leave the seafloor clean. At the same time the project description also stated
the following…” technical (deep well scenario) and weather conditions (high swells and wind) may dictate that a
wellhead cannot be removed on completion of the drilling operation. A technical report would subsequently be
compiled and submitted to PASA. The report would indicate the factors leading to the abandonment and
provide a rationale as to the future status of the wellhead”.
Experience gained in the initial drilling of the Brulpadda well in 2014, highlighted a number of technical
difficulties facing the well drilling operation. These relate to drilling a deepwater well in a high energy marine
environment and the strongly flowing Agulhas current passing through the area of drilling interest. Taking
cognisance of the technical issue learning points, TEPSA is now applying to amend its EMPR in order to leave
the wellhead on the seafloor on completion of the drilling operation.
SLR Consulting (South Africa) (Pty) Ltd (hereafter referred to as SLR) has been appointed by TEPSA as the
independent environmental consultant to undertake the necessary amendment application process. The
outcome of the application process will be the submission an EMPr Amendment report to PASA.
AUTHORISATION REQUIREMENTS 1.2
The proposed amendment to the EMPr requires approval in terms of both the MPRDA and NEMA. These two
regulatory processes are summarised below and presented in more detail in Chapter 2.
Section 102 of the MPRDA provides for the amendment of, amongst others, an Environmental Management
Programme (EMPr) and requires that any amendment be approved by the Minister of Minerals and Energy (or
delegated authority). This application is facilitated by the NEMA process described below.
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
2
FIGURE 1-1: LOCALITY OF BLOCK 11B/12B OFF THE SOUTH COAST OF SOUTH AFRICA. THE AREA OF INTEREST FOR DRILLING IS HIGHLIGHTED.
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
3
An application to amend an EMPr is provided for in Section 37 of the Environmental Impact Assessment (EIA)
Regulations 2014, as amended, promulgated in terms of Sections 24(5) and 44 of the National Environmental
Management Act, 1998 (No. 107 of 1998), as amended (NEMA). An EMPr Amendment application must be
subjected to a public participation process before it can be considered by the competent authority. In this case
PASA will review the amendment application and make a recommendation to DMR as to whether the
amendment application should be accepted or rejected.
PURPOSE OF THIS REPORT 1.3
This EMPr Amendment has been compiled and distributed for review and comment as part of the above-
mentioned amendment process that is being undertaken by TEPSA.
This report summarises the:
• legislative requirements;
• approach and methodology of the amendment process;
• a description of the proposed changes to well completion;
• a summary of the key characteristics of the receiving environment;
• findings of specialist studies; and
• amendments to the EMPr, which includes the mitigation and management measures necessary to avoid
or reduce potentially significant impacts.
Interested and Affected Parties (I&APs) are asked to comment on the EMPr Amendment (see Section 1.5). The
document will then be updated into a final report, giving due consideration to the comments received. The
final EMPR Amendment will be submitted to PASA for consideration and decision-making.
STRUCTURE OF THIS REPORT 1.4
This EMPr Amendment has been prepared in compliance with Section 37 of the EIA Regulations 2014 (as
amended) and is divided into various chapters and appendices, the contents of which are outlined below.
Section Contents
Executive Summary Provides a comprehensive synopsis of the EIR Amendment.
Chapter 1 Introduction
Provides a brief description of the project background, summarises the legislative authorisation
requirements, describes the purpose of this report and presents the structure of the report.
Chapter 2 Legislative requirements
Outlines the key legislative requirements applicable to the proposed project and associated
amendment process.
Chapter 3 Approach and methodology to the amendment process
Presents the project team, assumptions, and outlines the amendment process, including the
assessment methodology and I&AP consultation process.
Chapter 4 Project description
Provides a general description of the proposed project.
Chapter 5 Description of the affected environment
Describes the existing biophysical and social environment that could potentially be affected by the
proposed amendment.
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
4
Section Contents
Chapter 6 Impact description and assessment
Describes and assesses the potential impacts related to the proposed amendments on the affected
environment. It also presents mitigation/management or optimisation measures that could be
used to reduce the significance of any negative impacts or enhance any benefits, respectively.
Chapter 7 Conclusion and recommendations
Provides conclusions to the amendment process and summarises the mitigation and monitoring
measures that would be implemented for the proposed project.
Chapter 8 Environmental management programme
Provides the EMPr Management Actions for the proposed EMPr Amendment. This includes all
measures outlined in the approved EMPr and any amended and / or additional management
actions identified, where relevant.
Chapter 9 References
Provides a list of the references used in compiling this report.
Appendices Appendix 1: Convention for assigning significance ratings to impacts
Appendix 2: Marine Faunal Assessment
Appendix 3: Fisheries Assessment
Appendix 4: Risk Report
Appendix 5: Public Participation Process
Appendix 4.1: I&AP database
Appendix 4.2: I&AP notification of EMPR Amendment
OPPORTUNITY TO COMMENT 1.5
This EMPr Amendment has been distributed for a 30-day comment period from 13 November to
13 December 2018 in order to provide I&APs with an opportunity to comment on any aspect of the
amendment application. Copies of the full report have been made available on the SLR website (at
http://slrconsulting.com/za/).
Any comments should be forwarded to SLR at the address, telephone/fax numbers or e-mail address shown
below. For comments to be included in the updated EMPr Amendment, comments should reach SLR by no
later than 12 December 2018.
SLR Consulting (South Africa) (Pty) Ltd
Attention: Mandy Kula
PO Box 10145, CALEDON SQUARE, 7905
Unit 39 Roeland Square, 30 Drury Lane, CAPE TOWN, 8001
Tel: (021) 461 1118/9
Fax: (021) 461 1120
E-mail: [email protected]
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
5
LEGISLATIVE REQUIREMENTS 2
This chapter outlines the key legislative requirements applicable to the proposed EMPR amendment.
OVERVIEW OF THE “ONE ENVIRONMENTAL SYSTEM” 2.1
The “One Environmental System” commenced on 8 December 2014 removing the environmental regulation of
prospecting, mining, exploration and production and related activities from the MPRDA and transferring it to
NEMA. Under the “One Environmental System”, the Minister of Mineral Resources (or delegated authority) is
the competent authority responsible for issuing Environmental Authorisations and associated amendments in
terms of NEMA for mining and petroleum related activities. The Minister of Environmental Affairs, however,
remains the appeal authority for these authorisations.
MINERAL AND PETROLEUM RESOURCES DEVELOPMENT ACT, 2002 2.2
TEPSA holds an existing Exploration Right for Block 11B/12B. As part of the process of applying for the
Exploration Right, a BA and EMPr were compiled and approved for the undertaking of seismic surveys and
exploration drilling within the licence area. Both of these activities have subsequently been undertaken within
the licence area to date.
Section 102 of the MPRDA provides for the amendment of, amongst others, an EMPr and requires that any
amendment be approved by the Minister of Minerals and Energy (or delegated authority). This application is
facilitated by the NEMA process described below.
NATIONAL ENVIRONMENTAL MANAGEMENT ACT, 1998 2.3
The EIA Regulations 2014 promulgated in terms of Chapter 5 of NEMA, and published in Government Notice
(GN) No. R982 (as amended by GN No. 326 of 7 April 2017) control certain listed activities, which are prohibited
until Environmental Authorisation has been obtained from the competent authority (which is the Minister of
Mineral Resources for Mining Right applications). As noted previously TEPSA was granted Environmental
Authorisation on 17 January 2011 for the above-mentioned seismic surveying and exploration well drilling
exploration programmes.
As indicated in the introduction, Section 37 of the EIA Regulations 2014, as amended, provides for the
amendment of an approved EMPR. The holder of an environmental authorisation must notify the competent
authority of such intention to amend the EMPr at least 60 days prior to submitting such amendments. TEPSA
submitted a notice of intent in this regard to PASA on 4 October 2018.
The Regulations further require that the holder of the environmental authorisation must invite comments from
potentially interested and affected parties, including the competent authority (a 30-day comment period) on
the proposed amendments to the EMPr. On completion of the public participation process, the holder of the
environmental authorisation must submit the EMPr Amendment report to PASA.
In the event that no comments are received on the Amended EMPR, the holder of the environmental
authorisation may submit the EMPr amendment to the competent authority for approval within 60 days of
inviting comment.
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
6
If comments are submitted to the holder of the environmental authorisation, the holder must submit such
comments including responses to such comments to the competent authority together with the EMPr. The
competent authority must, within 30-days of receipt EMPr Amendment (including comments and responses)
consider such information and issues a decision to approve or not.
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
7
APPROACH AND METHODOLOGY TO THE AMENDMENT PROCESS 3
This chapter presents the EMPr Amendment project team, assumptions, and outlines the amendment process,
including the assessment methodology and I&AP consultation process.
DETAILS OF THE PROJECT TEAM 3.1
Details of the project team that was involved in the preparation of this amendment report are provided in
Table 3-1. SLR has no vested interest in the proposed project other than fair payment for consulting services
rendered as part of the amendment process.
TABLE 3-1: DETAILS OF THE EIA PROJECT TEAM
General
Organisation SLR Consulting (South Africa) (Pty) Ltd
Postal address PO Box 10145, CALEDON SQUARE, 7905
Tel No. +27 (0)21 461 1118 / 9
Fax No. +27 (0)21 461 1120
Name Qualifications Professional
registrations
Experience
(Years) Tasks and roles
Jonathan Crowther
M.Sc. (Env. Sci.).
University of
Cape Town
Pr.Sci.Nat.,
CEAPSA, Member
IAIAsa
30 Report and process review
Qualifications and Experience of the EAP 3.1.1
Jonathan Crowther is the SLR Operations Manager for the Environmental Management Planning and Approvals
team in Africa. He holds a Master’s Degree in Environmental Science and has 30 years of relevant experience.
He has expertise in a wide range of environmental disciplines, including EIAs, EMPs, Environmental Planning
and Review and Public Consultation. Jonathan is a Registered Professional Natural Scientists (Pr.Sci.Nat.) and a
Certified Environmental Practitioner of South Africa (CEAPSA).
ASSUMPTIONS 3.2
The assumptions pertaining to this EMPR Amendment are listed below:
• It is assumed that SLR has been provided with all relevant project information and that it was correct and
valid at the time it was provided.
• There will be no significant changes to the project description or surrounding environment between the
completion of the amendment process and implementation of the proposed project that could
substantially influence findings and recommendations with respect to mitigation and management, etc.
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
8
OBJECTIVES 3.3
The overall objectives of this EMPr Amendment application process is to determine the likely impact
significance of the proposal by TEPSA to leave wellheads on the seafloor on completion of exploration well
drilling .
Specialist studies have been commissioned in order to assess the significance of the proposed change in the
project description and the findings of these studies evaluated in order to provide a reasoned conclusion on
the findings.
SPECIALISTS STUDIES 3.4
Two specialist studies were undertaken to address the key issues that required investigation, namely the
impact on fisheries and marine fauna. The details of the two specialist studies are provided in Table 3-2.
Specialist studies involved the gathering of data relevant to identifying and assessing environmental impacts
that may occur as a result of the proposed amendments to the project. These impacts were then assessed
according to pre-defined rating scales (see Appendix 1). Specialists also recommended appropriate mitigation
or optimisation measures to minimise potential impacts or enhance potential benefits, respectively.
TABLE 3-2: SPECIALISTS STUDIES
No. Tasks and roles organisation Name Qualifications
1
Marine Faunal
Assessment
(see Appendix 2)
Pisces Environmental
Services Andrea Pulfrich
PhD (Fisheries Biology), Christian-
Albrechts University, Kiel, Germany
2
Fisheries Assessment
(see Appendix 3) Capricorn Marine
Environmental
Dave Japp MSc (Ichthyology and Fisheries
Science), Rhodes University
Sarah Wilkinson BSc (Hons) (Botany), University of
Cape Town
In addition to the above specialist studies, TEPSA has prepared a Risk Report (see Appendix 4), which provides
a rationale for the proposal to leave the wellheads on the seafloor and provides a risk analysis of the option of
wellhead removal versus leaving wellheads on the seafloor.
INTEGRATION AND ASSESSMENT 3.5
Compilation and review of the EMPR Amendment 3.5.1
This EMPr Amendment has been prepared in compliance with Section 37 the EIA Regulations 2014 (as
amended). The specialist studies and other relevant information / assessments have been integrated into this
report. This report, therefore, contains the key information from each of the specialist studies, including the
description and assessment of impacts. Each impact is described and assessed in terms of the nature of the
effect, duration, extent, intensity and significance level, which is assigned according to pre-defined rating scales
(see Appendix 1).
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
9
This report aims to present all information in a clear and understandable format, suitable for easy
interpretation by I&APs and authorities, and to provide an opportunity for I&APs to comment on the proposed
EMPR Amendments and findings of the amendment process (see Section 1.5 for details of the comment
period).
Steps that will be undertaken as part of the draft report review process are summarised below.
• A preliminary I&AP database of authorities, Non-Governmental Organisations, Community-based
Organisations and other key stakeholders was compiled using an update of the existing database for
Block 11B/12B (see Appendix 5.1). Additional I&APs will be added to the database based on the tasks
below.
• A notification letter was distributed to all registered I&APs; and
• A copy of the report has been made available on the SLR website for the duration of the comment
period.
Copies of the notification letter will be included on the final report.
Completion of the Amendment Process 3.5.2
The following steps are envisaged for the remainder of the amendment process:
• After closure of the comment period, all comments received will be incorporated and responded to in a
Comments and Responses Report. The EMPR Amendment will then be updated into a final report, to
which the Comments and Responses Report will be appended.
• The final EMPR Amendment will be submitted to PASA for consideration and decision-making by the
Minister of Mineral Resources (or delegated authority).
• After the Minister has reached a decision, all I&APs on the project database will be notified of the
outcome of the application and the reasons for the decision.
• A statutory appeal period in terms of the National Appeal Regulations (GN No. R993) will follow the
issuing of the decision.
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
10
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
11
PROJECT DESCRIPTION 4
This chapter, provides general information, describes the need and desirability for the proposed project,
provides a project overview/description and describes the project alternatives.
GENERAL PROJECT INFORMATION 4.1
Exploration Right Holder 4.1.1
TEPSA is the Exploration Right holder.
Address: 3rd
Floor
Tygervalley Chambers Two
Willie Van Schoor Avenue
Bellville, 7530
South Africa
Responsible Persons: Mr Eduard Groenewald
Telephone: +27 21 003 4077
Email: [email protected]
Exploration Right Area 4.1.2
The Exploration Right area includes Block 11B/12B (see Figure 1-1) and has a total extent of approximately
18 773 km2 and is situated approximately 130 km offshore of the south coast in water depths of between
500 m and 2 000 m. The approved drilling area (shaded green on Figure 1-1) covers an area of approximately
4 066 km2.
PROJECT DESCRIPTION 4.2
Approved well completion 4.2.1
The approved EMPr requires that once the well had been plugged to ensure well integrity2, the wellhead would
then be removed, with casing cut-off approximately 3 m below the seafloor and all sundry equipment removed
to leave the seafloor clear.
A typical wellhead is shown Figure 4-1 and a diagrammatic cross section in Figure 4-2.
______________________
2 It should be noted that the actual wellhead has no impact on well integrity once a well has been plugged for abandonment. The well
integrity is guaranteed by plugging the well with two independent barriers provided by setting the cement plugs in the well. This occurs
irrespective of the wellhead completion status.
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
12
FIGURE 4-1: PHOTOGRAPH OF WELLHEAD ON THE SEAFLOOR
FIGURE 4-2: DIAGRAMATIC CROSS SECTION OF CASING HOUSING 3.5 METRES ABOVE SEAFLOOR
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
13
Description of amended well completion status 4.2.2
As was indicted in the introduction, the description of the well completion status made reference to the fact
that if there were technical problems, that it may not be possible to remove the wellhead. The following is
extracted directly from the approved EMPr:
“technical (deep well scenario) and weather conditions (high swells and wind) may dictate that a wellhead
cannot be removed on completion of the drilling operation. A technical report would subsequently be compiled
and submitted to PASA. The report would indicate the factors leading to the abandonment and provide a
rationale as to the future status of the wellhead”.
TEPSA gained substantial experience of the local metocean conditions during the initial drilling of the
Brulpadda well in 2014. The strong Agulhas current that flows through the approved drilling area highlighted a
number of technical difficulties facing the well drilling operation. Taking cognisance of the technical learning
points, TEPSA is now applying to amend its EMPr in order to leave the wellhead on the seafloor on completion
of the drilling operation. Detailed rationale for this approach is provided in the Risk Report that TEPSA has
compiled as part of the amendment application (see Appendix 4). A brief summary of this is provided below.
A combination of the normal challenges inherent in deepwater exploration together with the specific
metocean challenges (harsh sea conditions and strong current) place a significant risk on wellhead removal
operations. Typical challenges would include:
• The requirement to wait on an adequate weather window to perform the operation;
• Low reliability of the weather forecast in relation to the Agulhas Current behaviour and movement; and
• The risk of rig position loss due to current unpredictability.
The casing cutting operations are performed in open water (riser and blow out preventer already removed)
and require that the cutting tools for the wellhead removal are anchored inside the casing strings. The high
current and its low forecast reliability, exposes the rig to increased risk of rig loss position which could lead to
the parting and loosing of the string. This is assessed to be a sever risk. Implications are:
• If the string parted close to the seabed, then access to the wellhead would be lost (e.g. in order to install
a corrosion cap) and there would be more equipment/debris left on the seabed;
• If the string parted on the rig side, then it could result in significant equipment damage and potential
impact on the safety of the drill rig and its crew. This would also result in drill string equipment/debris,
being left on the seafloor.
Thus, based on the perceived sever risk of conducting well removal under the specific metocean conditions
associated with the drilling area location, TEPSA is applying for an amendment to leave wellheads on the
seafloor.
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
14
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
15
DESCRIPTION OF THE AFFECTED ENVIRONMENT 5
A detailed update of the affected environment description provided in the approved EMPr has been prepared
as part of this amendment application process. The detailed description of the South Coast is provided in
Appendix 2. A summary of the key aspects are provided below.
5.1 PHYSICAL OCEANOGRAPHY
The oceanography of the South Coast is almost totally dominated by the warm Agulhas Current. The current
forms between 25° and 30° S, flowing southwards along the shelf edge of the southern African East Coast
(Schumann 1998) as part of the anticyclonic Indian Ocean gyre. It is a well-defined and intense jet some 100
km wide and 1 000 m deep flowing in a south-west direction at a rapid rate, with current speeds of 2.5 m/s or
more, and water transport rates of over 60 × 106 m
3/s have being recorded. On the eastern half of the South
Coast, the Agulhas Current flows along the shelf break at speeds of up to 3 m/sec, diverging inshore of the shelf
break south of Still Bay (34° 28'S, 21° 26'E) before realigning to the shelf break off Cape Agulhas. The Agulhas
Current may produce large meanders with cross shelf dimensions of approximately 130 km, which move
downstream at approximately 20 km per day It may also shed eddies, which travel at around 20 cm/s and
advect onto the Agulhas Bank.
The surface waters of the Agulhas Current may be over 25° C in summer and 21° C in winter.
Westerly winds predominate along the South Coast in winter, frequently reaching gale force strengths. During
summer, easterly wind directions increase markedly resulting in roughly similar strength/frequency of east and
west winds during that season. The strongest winds are observed at capes, including Agulhas, Infanta, Cape
Seal, Robberg and Cape Recife. Calm periods are most common in autumn.
On the South Coast, the majority of waves arrive from the south-west quadrant, dominating wave patterns
during winter and spring. Waves from this direction frequently exceed 6 m and can reach up to 10 m. During
summer, easterly wind-generated ‘seas’ occur.
BIOLOGICAL OCEANOGRAPHY 5.2
The Block 11B/12B Exploration Right area falls within the Agulhas Inshore and West Indian Offshore bioregions.
Communities within marine habitats are largely ubiquitous throughout the southern African South Coast
region, being particular only to substrate type or depth zone. The biological communities occurring in the
Block 11B/12B area consist of many hundreds of species, often displaying considerable temporal and spatial
variability (even at small scales).
The seabed benthic communities in the Block 11B/12B area lie within the Agulhas sub-photic and continental
slope biozones, which extend from a 30 m depth to the shelf edge, and beyond to the lower slope,
respectively. The majority of the approved well drilling area falls within an area that is defined as least
threatened in terms of the ecosystem threat status. A very small portion in the west coincides with a
vulnerable area.
The Agulhas Bank hosts a diversity of deep-water corals and sponges that have establish themselves below the
thermocline where there is a continuous and regular supply of concentrated particulate organic matter, caused
by the flow of a relatively strong current. Reef-building cold water corals have also been documented within
the Southwest Indian Upper Bathyal, Agulhas Sandy Shelf Edge and in association with deep reefs and
submarine canyons on the Agulhas Inner Shelf and Shelf Edge, respectively.
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
16
The ichthyofauna on the South Coast is diverse, comprising a mixture of temperate and tropical species. As a
transition zone between the Agulhas and Benguela current systems, the South Coast ichthyofauna includes
many species occurring also along the West and/or East coasts. The seabed of the Agulhas Bank substrate is
also diverse comprising areas of sand, mud and coral thereby contributing to increased benthic fauna and fish
species.
Small pelagic shoaling species occurring along the South Coast include anchovy, pilchard, round herring, chub
mackerel and horse mackerel. The fish most likely to be encountered on the shelf, beyond the shelf break and
in the offshore waters of Block 11B/12B are the large migratory pelagic species, including various tunas, billfish
and sharks many of which are considered threatened by the International Union for the Conservation of Nature
(IUCN), primarily due to overfishing.
There is a high diversity of teleosts (bony fish) and chondrichthyans (cartilaginous fish) associated with the
inshore and shelf waters of the South Coast, many of which are endemic to the Southern African coastline and
form an important component of the demersal trawl and long-line fisheries. The Cape hake is distributed
widely on the Agulhas Bank, while the deep-water hake is found further offshore in deeper water. Apart from
the hakes, numerous other by-catch species are landed by the South Coast demersal trawling fishery including
panga, kob, gurnard, monkfish, John Dory and angel fish.
Three species of turtle occur along the Southwest Coast, namely the leatherback (Vulnerable), and occasionally
the loggerhead (Endangered) and the green (Endangered) turtle. Both the leatherback and the loggerhead
turtle nest on the beaches of the northern KwaZulu-Natal coastline in the summer months. After hatching
juvenile turtles that reach the sea, are carried south westward by the Agulhas Current. Green turtles are non-
breeding residents often found feeding on inshore reefs.
Fifteen species of seabirds breed in southern Africa: Cape gannet, African penguin, four species of cormorant,
white pelican, three gull and four tern species. The breeding areas are distributed around the coast with
islands being especially important. Overall, 60 seabird species are known, or thought likely to occur, along the
South Coast.
The marine mammal fauna occurring off the southern African coast includes several species of whales and
dolphins and one resident seal species. Thirty six species or sub species/populations of cetaceans (whales and
dolphins) are known (based on historic sightings or strandings records) or likely (based on habitat projections
of known species parameters) to occur in these waters. The distribution of cetaceans can largely be split into
those associated with the continental shelf and those that occur in deep, oceanic water. Importantly, species
from both environments may be found on the continental slope (from the shelf break - 200 m to ~2 000 m)
making this the most species rich area for cetaceans. Cetacean density on the continental shelf is usually
higher than in pelagic waters as species associated with the pelagic environment tend to be wide ranging
across 1 000s of kilometres. The most common species within Block 11B/12B (in terms of likely encounter rate
not total population sizes) are likely to be the long-finned pilot whale and humpback whale
The Cape fur seal (Arctocephalus pusillus pusillus) is the only seal species that has breeding colonies along the
South Coast, namely at Seal Island in Mossel Bay, on the northern shore of the Robberg Peninsula in
Plettenberg Bay and at Black Rocks (Bird Island group) in Algoa Bay.
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
17
MARINE PROTECTED AREAS 5.3
Numerous coastal marine protected areas (MPAs) exist along the South Coast (see Figure 5-1). There are four
MPAs on the Western Cape coast east of Cape Agulhas namely De Hoop, Goukamma, Robberg, and Tsitsikama.
Of these, the Goukamma, Robberg and Tsitsikama MPAs are located inshore of Block 11B/12B.
Following an initiative that has long been in the developing, biodiversity data was used to identify numerous
focus areas for protection on the South Coast. These focus areas were carried forward during Operation
Phakisa, which identified potential offshore MPAs. A network of 20 MPAs was approved by Cabinet on
24 October 2018, thereby increasing the ocean protection within the South African Exclusive Economic Zone
(EEZ) to 5%. Those recently approved MPAs within the broad project area are shown in Figure 5-1. There is no
overlap with the area of interest for well drilling and recently approved MPAs.
FIGURE 5-1: BLOCK 11B/12B IN RELATION TO THE EXISITNG MARINE PROTECTED AREAS (ALONG THE
COAST) AND OFFSHORE MARINE PROTECTED AREAS RECENTLY ACCEPTED BY CABINET.
AFTER PISCES 2018
HUMAN UTILISATION 5.4
Commercial Fisheries 5.4.1
South Africa has a coastline that spans two ecosystems, extending from the Orange River in the west on the
border with Namibia, to Ponta do Ouro in the east on the Mozambique border. The western coastal shelf has
highly productive commercial fisheries similar to other upwelling ecosystems around the world, while the East
Coast is considerably less productive but has high species diversity, including both endemic and Indo-Pacific
species. South Africa’s fisheries are regulated and monitored by the Department of Agriculture, Forestry and
Fisheries (DAFF). All fisheries in South Africa, as well as the processing, sale in and trade of almost all marine
resources, are regulated under the Marine Living Resources Act, 1998 (No. 18 of 1998) (MLRA).
Approximately 14 different commercial fisheries sectors currently operate within South African waters. These
are described in more detail in the fisheries specialist report (see Appendix 3). However, it should be noted
here, and it will be discussed further in Chapter 6, that only future demersal trawling and demersal is likely to
be affected by wellheads being left on the seafloor.
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
18
FIGURE 5-2: BLOCK 11B/12B IS RELATION TO DEMERSAL TRAWL EFFORT.
FIGURE 5-3: BLOCK 11B/12B IN RELATION TO MIDWATER TRAWL EFFORT
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
19
FIGURE 5-3: BLOCK 11B/12B IN RELATION TO DEMERSAL LONGLINE EFFORT
FIGURE 5-4: BLOCK 11B/12B IN RELATION TO PELAGIC LONGLINE EFFORT
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
20
FIGURE 5-5: BLOCK 11B/12B IN RELATION TO SOUTH COAST ROCK LOBSTER EFFORT
FIGURE 5-6: BLOCK 11B/12B IN RELATION TO DAFF RESEARCH TRAWING EFFORT
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
21
FIGURE 5-7: BLOCK 11B/12B IN RELATION TO DAFF RESEARCH SIESMIC SURVEY LINES
Marine traffic and infrastructure 5.4.2
A large number of vessels navigate along the South Coast on their way around the southern African
subcontinent. The majority of this vessel traffic, including commercial and fishing vessels, remains relatively
close inshore and is, therefore, expected to pass through inshore areas of the proposed survey area.
PetroSA operates the F-A production platform, which was brought into production in 1992. The F-A platform is
located 85 km south of Mossel Bay and roughly mid-way between Block 11B/12B and Mossel Bay. Gas and
associated condensate from the gas fields (F-A, F-A Satellite, E-M and E-M Satellite) are processed through the
platform. The produced gas and condensate are exported through two separate 90 km pipelines to the PetroSA
Gas-to-Liquid (GTL) plant in Mossel Bay.
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
22
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
23
IMPACT DESCRIPTION AND ASSESSMENT 6
This chapter describes and assesses the significance of the potential impacts associated with the application by
TEPSA to leave wellheads on the seafloor on completion of each of the approved 10 exploration well drilling
operation within the approved drilling area.
All impacts are systematically assessed and presented according to a predefined impact assessment protocol.
Mitigation or optimisation measures are proposed which could ameliorate negative impacts or enhance
potential benefits. The status of all impacts should be considered to be negative unless otherwise indicated.
The significance of the impacts with and without mitigation is also assessed.
MARINE FAUNA 6.1
Description of impact
A detailed discussion of the effects of oil and gas infrastructure on the seabed is provided in the Marine Faunal
Assessment (see Appendix2). Various studies (e.g. Hall 2001) have shown that infrastructure provided by
platforms can support a rich diversity of marine species, including rare and slow growing cold water corals.
Studies on the effects of platforms on the behaviour and abundance of certain fish species showed that the
presence of oil and gas infrastructure appeared to provide a sheltering habitat for fish usually associated with
complex reef habitats (Love et al. 2005; Love & York 2006).
The changes in biodiversity discussed in these various studies, however, are primarily associated with
permanent production rigs, and any alterations to community structure resulting from potentially up to 10
wellheads would occur at a much smaller scale than that reported on production infrastructure. For the
current project, the drilling area is located in between 500 m to 2 000 m depth, in Southwest Indian upper
bathyal seabed habitat, which has been assigned an ecosystem threat status of ‘least threatened’ (Sink et al.
2012). The physical presence of remaining subsea infrastructure would effectively introduce hard substratum
in an otherwise uniform area dominated by unconsolidated sediments. The infrastructure remaining on the
seabed would be available for colonisation by sessile benthic organisms typically associated with heard
substrata, and would provide shelter for demersal fish and mobile invertebrates thereby potentially increasing
the benthic biodiversity and biomass in the continental slope region. The benthic fauna inhabiting islands of
hard substrata in otherwise unconsolidated sediments of the outer shelf and continental slope are very poorly
known. Likely taxa would include urchins, anemones, sponges, gorgonians, bryozoans and octocorals, many of
which could potentially be sensitive to disturbance. Considering the close proximity of the newly discovered
biogenic coral reef structure known as Secret Reef to the drilling area, it is not unlikely that some of the fragile
and sensitive deep water corals (scleractinian corals, stylasterine corals) and byrozoans occurring there may
colonise the abandoned wellheads, although establishment of mature communities would only be expected
over the medium to long-term. Due to the water depths in the drilling area, colonisation by invasive species is
unlikely to pose a significant threat to natural biodiversity in the deep sea habitats.
Assessment
The impacts associated with the presence of subsea infrastructure (up to ten wellheads) and potential
alteration of community structure, biodiversity and biomass would be highly localised, affecting no more than
approximately 8 m2 of seabed in total. This represents a negligible proportion of Block 11B/12B (0.04 x10
-6 %),
the Southwest Indian Upper Bathyal habitat type (0.009 x 10-7
%) and of the wider South-west Indian Offshore
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
24
Bioregion (0.3 x 10-8
%). As most wells drilled to date (some of which will have been abandoned) are located in
waters shallower than 500 m depth, the cumulative impacts associated with abandoning subsea infrastructure
beyond 500 m depth is considered negligible, and any impact on benthic species, habitats or ecosystem
processes would most likely remain undetectable. The drilling area also lies beyond the depths typically
targeted by the demersal fishery, so cumulative effects of other users would likewise be negligible.
The increase in biodiversity (neutral impact) due to the presence of abandoned subsea structures would be
considered a secondary impact of low intensity. As TEPSA has indicated that the wellhead(s) would be
abandoned, the impact is irreversible but is considered to be of LOW significance without mitigation (see Table
6-1).
Should over-trawlable structures be installed above the wellhead to mitigate potential impacts to the trawl
fishery of leaving the wellheads in place, each structure would impact an area of approximately 25 m2. The
impacts associated with placing up to 10 structure on the seabed would thus likewise be highly localised
(250 m2) and be considered to be of LOW significance without mitigation.
Mitigation
No mitigation is recommended or deemed necessary.
TABLE 6-1: IMPACT ON MARINE BENTHOS OF LEAVING WELLHEADS ON THE SEAFLOOR
Impacts of petroleum infrastructure on marine biodiversity: wellhead remains on the seafloor during abandonment
Without Mitigation Assuming Mitigation
Intensity Low
No mitigation is proposed
Duration Permanent
Extent Local: limited to drilling area
Consequence Low
Probability Definite
Significance Low
Status Neutral
Confidence High
Nature of Cumulative impact Cumulative impacts at depths beyond 500 m are considered negligible.
Degree to which impact can be
reversed
Irreversible – wellheads will be permanently abandoned and changes in seabed structure
would thus also be permanent.
Degree to which impact may cause
irreplaceable loss resources
Negligible
Degree to which impact can be
mitigated
Medium
FISHERIES 6.2
Description of impact
As indicated in the affected environment section, five fisheries that operate within immediate or immediately
adjacent to the approved drilling including: demersal trawl, midwater trawl, demersal longline, large pelagic
longline and south coast rock lobster. Fisheries research cruises also occur near to the approved drilling area.
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
25
Of these fisheries and research surveys, only the likely future expansion of demersal trawl operations are
expected to be affected by leaving wellheads on the seafloor within the drilling area. A summary of the likely
impact of wellheads left on the seabed within the drilling area is provided in Table 6-2.
TABLE 6-2: FISHERIES AND THE LIKELY IMPACT THAT WELLHEADS WOULD HAVE ON THEM
Fishery Description of likelihood of fisheries
interaction with wellhead on the seafloor
Impact Description
Demersal trawl Evidence of trawling up to a depth of 600 m, just
adjacent to the northern edge of the drilling area.
Currently no trawling in drilling area.
Based on current fishery operation
locations there would be NO IMPACT.
Possible future expansion of the fishery into the
drilling area cannot be ruled out.
Medium intensity but LOW significance
due to low probability of expansion.
INSIGNIFICANT IMPACT with mitigation
of over-trawlable structure in place.
Mid-water trawl Isolated trawls up to 650 m depth. No overlap with
drilling area. Also by definition mid-water trawl
nets mostly do not touch the seabed
As there is no overlap NO IMPACT is
expected.
Demersal longline Fishing area lies adjacent to the drilling area to the
north, but does not coincide with the area.
The nature of this fishery is such that equipment
can get caught on seabed obtrusions. Thus lines
could get entangled on either a wellhead or over-
trawlable structure.
As there is no overlap there would be NO
IMPACT.
In highly unlikely event that the fishery
was to expand into the drilling area,
entanglement of lines on a wellhead
could occur. However, in comparison to
demersal trawl there would be no
resultant safety issue – rather the issue
would be one of equipment damage only.
Although infrequent, there are various
records of entanglement with reefs and
corals.
Large pelagic longline Although the drilling area coincides with the
extensive area of this fishery, the targeted fishing
depth is approximately 40 m, and thus seabed
infrastructure is unlikely to pose a threat.
As this is effectively a surface fishery, NO
IMPACT on this sector is anticipated.
South Coast Rock Lobster The drilling area does not coincide with the lobster
trap grounds as the area is deeper than the depth
range of rock lobster species
As the areas do not coincide there is no
impact NO IMPACT.
Fisheries
Research
Trawling Research trawls mostly between the coast and
1 000 m depth, with occasional trawls of up to
1 300 m.
As the areas do not coincide there is no
impact NO IMPACT.
Seismic Seismic surveys have extended into the north-
western extent of the drilling area. Acoustic survey
techniques use surface equipment.
NO IMPACT as surveys are surface based.
Assessment
An abandoned wellhead may pose an obstruction to any fishing activity directed towards the seabed (namely
any demersal fishery). The potential impact is the loss of catch as a result of preclusion from fishing grounds
around the abandoned wellhead(s). The risk of the impact of up to 10 abandoned wellheads within the
approved well-drilling area in Licence Block 11B/12B is low, as currently the only fishery identified as being
operational within the area is pelagic in nature rather than demersal.
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
26
The risk of impact on future demersal trawling activities can only relate to the opening of new fisheries based
on the discovery of additional stocks for exploitation in the affected area. The probability of this occurring is
considered to be possible.
The proposed abandonment of wellheads within the approved drilling area would likely affect future demersal
trawl operations through exclusion from localised areas of fishing grounds. The impact of exclusion from fishing
grounds is assessed to be of medium intensity (causing a moderate change to normal fishing processes). The
medium rating is given with consideration to the advanced navigational capacity of deepsea trawlers, where
often the trawl net can be accurately guided over subsea obstacles when the position of such obstacles is
charted. The overall consequence of the impact is likely to be medium but of low overall significance due to the
relatively low probability of expansion of fishing activity into the area (see Table 6-3).
Mitigation
The impact on future fishing activities could be reduced to overall insignificance if the wellhead were fitted
with an over-trawlable structure (see Figure 6-1), to minimise the risk of damage to trawl gear and vessels.
TABLE 6-3: IMPACT ON DEMERSAL FISHING OF LEAVING WELLHEADS ON THE SEAFLOOR
Impacts of demersal fishing: wellhead remains on the seafloor during abandonment
Without Mitigation Assuming Mitigation
Intensity Medium Very Low
Duration Permanent Permanent
Extent Local Local
Consequence Medium Very Low
Probability Possible Possible
Significance Low INSIGNIFICANT
Status Negative Negative
Confidence Medium Medium
Nature of Cumulative impact Cumulative impacts at depths beyond 500 m are considered negligible.
Degree to which impact can be
reversed
Irreversible – wellheads will be permanently abandoned and changes in seabed structure
would thus also be permanent.
Degree to which impact may cause
irreplaceable loss resources
Low
Degree to which impact can be
mitigated
Medium
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
27
FIGURE 6-1: EXAMPLE OF AN OVER-TRAWLABLE STRUCTURE
Risk Considerations
The fisheries specialist study provided a snag risk assessment related to leaving a wellhead on the seafloor.
The risk scale ranges from zero for pelagic fisheries too low for mesopelagic fisheries to medium for demersal
longline and high for demersal trawl sectors. The risk only applies when the wellhead is in a fishing ground. The
snag risk assessment is shown below:
Definition of snag-risk ratings:
High Risk – Incorporate risk reduction measures. A major potential accident event is probable based on the
intensity of fishing and associated gear type. Fishing operations are altered to the extent that they temporarily
or permanently cease.
Medium Risk – Incorporate risk reduction measures
A major potential accident event is possible based on the intensity of fishing and associated gear type. Fishing
operations continue, albeit in a modified way.
Low Risk – Manage for continuous improvement.
A major potential accident event is improbable based on the intensity of fishing and associated gear type.
Fishing operations continue, albeit in a slightly modified way.
No Risk
A major potential accident event is improbable based on the intensity of fishing and associated gear type.
Fishing operations continue, albeit in a slightly modified way.
Demersal trawlers regularly snag obstructions of many forms and systematically use GPS to record new or
known snags and then alter course to avoid them in future. Snagging of trawl gear is a major risk. By way of
example, a South African deepsea trawler snagged a wreck on the south coast during adverse sea conditions
which resulted in the flooding of the aft deck and engine room and the sinking of the vessel with loss of crew
within minutes.
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
28
Midwater nets are not equipped to run on the seabed; however, gear does approach close to the bottom and
there are records of midwater gear occasionally making contact with the seabed, either accidentally or
deliberately. A midwater net close to the bottom could foul a raised obstruction e.g. wreck, wellhead,
seamount, large boulder.
Demersal longlines that are used to target hake comprise a double line which allows for gear recovery using a
top line when the bottom line snags and parts. Skippers will, however, avoid known snag areas. In strong
current, gear can lift and move and drag onto snags. Gear will not be set in areas when the risk of total loss is
high. Demersal longlines can fish as deep as 2 000 m. These bottom-set lines are, however, difficult to set in
deep water and in strong currents and require specialised vessels with winches and with sufficient power and
line length to set at these depths.
Gear types associated with both midwater and demersal longlining are not expected to pose any risk to a well
or similar structure on the sea floor, although fouling on any hydrocarbon structure may result in loss of the
line gear.
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
29
CONCLUSIONS AND RECOMMENDATIONS 7
This chapter draws conclusion to the EMPr Amendment and recommends a suggested way forward regarding
the application by TEPSA to leave wellheads on the seafloor in the drilling area.
MARINE FAUNA 7.1
Considering the ecosystem threat status of ‘least threatened’ in the drilling area, and the negligible proportion
of the benthic habitat type and the wider South-west Indian Offshore Bioregion potentially affected by the
subsea infrastructure, the specialist marine fauna study concluded that there is no reason why the wellheads
should not be left in place on the seabed.
FISHERIES 7.2
The proposed TEPSA drilling area is located in a water depth of between 500 m and 2 000 m. In a fisheries
context, trawl fisheries have been confined to the “shelf” referring to the “continental shelf”. Historically
trawling in South African waters has been confined to depths shallower than 500 m. Generally, depths beyond
500 m are defined as being on “the shelf edge” and an area that drops off steeply and of rougher substrate
type.
The fisheries specialist study concludes that possible future demersal trawling is the only likely fishery that
could present a problem related to fouling with a wellhead in the drilling area. This could mean loss of the
trawl gear, loss of trawl warps, and in extreme cases, loss of the vessel due to loss of stability resulting from the
fouling.
Historical records of research trawling in the vicinity of the approved drilling area provide support for the
future expansion of trawling into the area:
• Hake directed bottom trawling in the last decade has systematically targeted fish in increasing water
depths.
• There has in the past been interest in the shelf drop off for trawling for deep-water species, specifically
orange roughy (Hoplostehus sp.), deep-water dories (oreos), cardinal fish, alfonsino and various other
species. There are established trawl fisheries for these species in Namibia and on the South West Indian
Ocean Ridge that fish in depths of between 1 000 m and 2 000 m. All of these species occur off the
Agulhas Bank and there continues to be interest in their commercial potential.
• In the mid 1990’s South Africa did have an experimental fishery for Oreo Dorie extending from south of
Cape Point towards the tip of the Agulhas Bank and further east. The trawling industry lost interest in the
fishery due to low abundance of the target species and high risk to the trawl gear.
• In the early to mid 1990’s one operator undertook a comprehensive side scan sonar survey for orange
roughy along the edge of the Agulhas Bank. Although seamounts and other suitable habitat was found
for orange roughy, viable commercial quantities were not found.
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
30
• The Department of Agriculture Forestry and Fisheries (DAFF) has also undertaken deep-water
exploratory trawling for deep-water species in the TEPSA drilling area. The results of these trawls have
shown the area to be of high risk to trawling.
Factors inhibiting the expansion of trawling into the drilling area include the following:
• The combination of depth and strong currents is the greatest deterrent to trawling for deep-water
species off the south and south eastern Agulhas Bank. The risk of losing trawl gear at these depths is
high.
• The Agulhas Current can reach 5 kts in places, it is irregular (and retroflects from westward moving to
eastwards) and may reverse at depth i.e. surface flowing currents may flow in the opposite direction at
the bottom.
• Weather and sea conditions are more extreme in the area, increasing the risk of losing trawl gear.
• The shelf edge and substrate type is of a generally high profile and unless suitable flat trawling ground
can be found, is difficult to trawl.
• Evidence of commercial quantities of deep-water species have to date not been found.
• Currently, targeting deep-water species is not permitted – if a fishery at these depths is found, the
trawling industry will need to apply for experimental fishing licenses.
• The area extending from the tip of Agulhas Bank eastwards to East London in depths up to 2 000 m has
been shown to have unique cold water corals and have been classified in places as a “Vulnerable Marine
Ecosystem” of VMEs. There is scientific interest in the area related to VMEs, specific habitat types and
corals. While there are no current restrictions to fishing in the area, the possibility that some habitats
may be protected in the future cannot be ruled out.
The specialist study concludes that there is currently no active fishery that would be affected by the proposed
application to abandon a wellhead in the project area. The possibility that trawling may occur in the proposed
area in the future cannot be ruled out; however, and the trawl gear used would pose a risk of damage to the
trawler should snagging occur. This risk could be mitigated by providing an over-trawlable structure to the
wellhead. Making the structure over-trawlable would mitigate the risk of damage to the fishing operation as
well as to potential damage to the wellhead.
EAP RECOMMENDATION 7.3
The findings of both specialists studies conclude that in terms of marine biophysical environment and the
current extent of fisheries, that the impact of leaving a wellhead on the seafloor would of low to negligible
significance.
The critical issue that needs to be evaluated in the decision-making process, is the implication of wellhead
infrastructure on future fisheries, specifically demersal trawl. There are indications that the demersal trawl
fishery could extend into deeper waters in the area proposed for drilling (although there are a number of
mitigations factors that also suggest fishing in deepwater with the strong Agulhas current may itself pose
problems), and could thus be affected by any infrastructure left on the seafloor. Should such a future risk not
be considered acceptable – then mitigation in the form of an over-trawlable structure should be a requirement
for well completion status within the approved drilling area. Such structures are assessed to be adequate to
remove the residual risk to future fisheries.
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
31
EMPR MANAGEMENT ACTIONS 8
This chapter lists the specific environmental management actions and procedures required to avoid or
minimise impacts on the environment from the proposed exploration well drilling programme. It also indicates
who is the responsible party and includes a compliance audit column for auditing purposes and the
requirements for closure. The specific environmental protection activities and procedures are addressed under
each of the project life cycle phases listed below.
8.1 PRE-ESTABLISHMENT PHASE
8.1.1 Pre-drilling planning
8.1.2 Preparation for emergencies
8.1.3 Financial provision
8.1.4 Approval of EMP
8.2 ESTABLISHMENT PHASE
8.2.1 Compliance with the environmental management plan
8.2.2 Notifying other users of the sea
8.2.3 Well / anchor position to avoid sea obstacles /
installations
8.2.4 Ensure integrity of anchor system
8.3 OPERATIONAL PHASE
8.3.1 Adherence to the EMP and Environmental Awareness
8.3.2 Continue to communicate with other users of the sea and
resource managers
8.3.3 Prevention of emergencies
8.3.4 Dealing with emergencies including major oil spills
8.3.5 Blow out prevention during well drilling
8.3.6 Disposal of drilling muds and cuttings
8.3.7 Disposal of ballast water
8.3.8 Well testing
8.3.9 Rig installation, anchor laying and well infrastructure
installation
8.3.10 Transport, storage and handling of radioactive devices
8.3.11 Pollution control and waste management of products
disposed of: into the air
8.3.12 Exclusion of other marine users from access to the
operational area for safety reasons
8.3.13 Equipment loss
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
32
8.3.14 Use of helicopters
8.3.15 Oil bunkering / refuelling at sea
8.3.16 Drill Rig lighting
8.3.17 Benthic fauna
8.4 DECOMMISSIONING AND CLOSURE
PHASE
8.4.1 Completion of wells
8.4.2 Drilling unit / vessels to leave area
8.4.3 Inform key stakeholders of survey completion
8.4.4 Final waste disposal
8.5
MONITORING, COMPLIANCE
AUDITING AND THE SUBMISSION
OF INFORMATION PHASE
8.5.1 Performance assessment / monitoring activities and
effects
8.5.2 Compile well drilling “close-out” report
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
33
PROJECT PHASE
AND ACTIVITIES
ENVIRONMENTAL
OBJECTIVES
AUDITABLE MANAGEMENT ACTIONS TO BE TAKEN TO MEET THE EMP
REPORT OBJECTIVES (WELL DRILLING)
COMPLIANCE RESPONSI-
BILITY Timing
REQUIREMENT
FOR “CLOSE-
OUT” REPORT
PRE-ESTABLISHMENT PHASE 8.1
8.1.1
Pre-drilling
planning
Accommodation of
needs for
environmental
monitoring and
liaison with fishing,
mining and other
industries
In order to minimise disruption to the drilling programme and 8.1.1.1
other users of the sea:
a) Communicate with fishing operators and the marine diamond
mining industry, as well as other vessels, regarding (1) safety
zone around the drilling unit, and (2) the timing and duration
of drilling in order to minimise disruption to the drilling
programme and other activities in the area.
TEPSA and
Contractor
Prior to
commencemen
t of operations
Provide records
of meetings
held and copies
of all
correspondence
8.1.2
Preparation for
emergencies
Preparation for any
emergency that
could result in an
environmental
impact
Have the following emergency plans, equipment and personnel in 8.1.2.1
place to deal with all emergencies:
a) Company (or representative) Emergency Response Plan. (all
contractors ER Plans to be bridged with Company plan)
b) Drilling unit contractor Emergency Response Plan (including
MEDIVAC plan).
c) Support vessel contractor Emergency Response Plan
(including MEDIVAC plan).
d) Helicopter Operator Emergency Response Plan.
e) South African Search and Rescue (SASAR) Manual.
f) Oil Spill Contingency Plan (OSCP) approved by the South
African Maritime Safety Authority (SAMSA). Note that in case
of a major oil spill, emergency responses and/or Oil Pollution
Contingency Plan(s) refer to the coastal oil spill contingency
plan(s) of DEA:MCM.
In addition to the above, ensure that: 8.1.2.2
a) Drilling unit must have Pollution Safety Certificate(s) issued
by SAMSA.
b) There is adequate protection and indemnity insurance cover
for oil pollution incidents.
c) There is a record of the drilling units and support vessel’s
seaworthiness certificate and/or classification stamp.
TEPSA and
Contractor
Prior to
commencemen
t of operation
Confirm
compliance and
maintain copies
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
34
PROJECT PHASE
AND ACTIVITIES
ENVIRONMENTAL
OBJECTIVES
AUDITABLE MANAGEMENT ACTIONS TO BE TAKEN TO MEET THE EMP
REPORT OBJECTIVES (WELL DRILLING)
COMPLIANCE RESPONSI-
BILITY Timing
REQUIREMENT
FOR “CLOSE-
OUT” REPORT
8.1.3
Financial provision
Compliance with
legislative
requirements
Ensure that financial provision is in place for the rehabilitation 8.1.3.1
and management of negative environmental impacts associated
with exploration drilling in Block 11B/12B. Such Financial
provision must be approved by PASA.
TEPSA and
Contractor
Prior to
commencemen
t of operations
Confirm that
financial
provision has
been put in
place
8.1.4
Approval of EMP
Compliance with
legislative
requirements
Ensure that the EMP has been approved by the Minister. 8.1.4.1 TEPSA and
Contractor
Prior to
commencemen
t of operations
Authorisation
letter
ESTABLISHMENT PHASE 8.2
8.2.1
Compliance with
environmental
management plan
Operator and
contractor to
commit to
adherence to EMP
Ensure that a copy of the approved EMP report and all 8.2.1.1
Authorisations is supplied to all Contractors and is on board the
drilling unit and support vessels during the operation and:
a) Ensure procedures and systems for compliance are in place.
b) Appropriately inform the drilling unit’s and support vessel’s
personnel of the purpose and requirements of the EMP.
c) Ensure correct equipment and personnel are available to
meet the requirements of the EMP.
d) Ensure responsibilities are allocated to personnel.
e) Contractor complies to the requirements of the EMP.
TEPSA and
Contractor
Prior to
commencemen
t of operation
Ensure that a
copy of the
EMP report is
provided to the
Drilling
contractor and
that an
acknowledgme
nt of receipt
form is signed
by the
Contractor
8.2.2
Notifying other
users of the sea
Ensure that other
users are aware of
the drilling
programme
TEPSA and its contractors must notify key stakeholders of the 8.2.2.1
navigational co-ordinates of the well drilling site/s and keep them
updated on the well drilling programme. The following
stakeholders shall be notified:
a) Overlapping and neighbouring users with delineated
boundaries in the oil and gas exploration and production
industries and any mining industries.
b) SAN Hydrographic Office. (Silvermine).
c) South African and foreign fishing vessels including:
Association of Small Hake Industries, SA Deep Sea Trawling
Industry Association, SA Inshore Fishing Industry Association,
South East Coast Inshore Fishing Association, SA Midwater
TEPSA and
Contractor
30 days prior to
start
Confirm that
notices were
sent to relevant
parties
Provide copy of
standard notice
and list of those
to whom it was
sent
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
35
PROJECT PHASE
AND ACTIVITIES
ENVIRONMENTAL
OBJECTIVES
AUDITABLE MANAGEMENT ACTIONS TO BE TAKEN TO MEET THE EMP
REPORT OBJECTIVES (WELL DRILLING)
COMPLIANCE RESPONSI-
BILITY Timing
REQUIREMENT
FOR “CLOSE-
OUT” REPORT
Trawling Association, SA Tuna Association, Fresh Tuna
Exporters Association, South Coast Rock Lobster Association,
Shark Longline Association, SA Pelagic Fishing Industry
Association, SA Commercial Linefish Association, and SA
Squid Management Industrial Association.
d) Fisheries and Mariculture Development Association.
e) Government departments with jurisdiction over marine
activities, particularly DEA, DEA: MCM and PASA.
f) SAMSA and local Port Captains.
TEPSA must request, in writing, the SAN Hydrographic Office 8.2.2.2
(Silvermine) to release Radio Navigation Warnings and Notices to
Mariners throughout the drilling period. The Notice to Mariners
should give notice of (1) ordinates of the well drilling activity, (2)
500 m safety zone around drilling unit, (3) well drilling
timeframes, and (4) a special note on the hazard posed by the
anchor chains and anchors.
8.2.3
Well / anchor
position to avoid
sea obstacles /
installations
Ensure that well
and anchor
positions will not
affect obstacles /
installations on the
seabed
Ensure that 8.2.3.1
a) no other mining / exploration activity, pipeline or
telecommunication cable will be affected by the drilling
activities.
b) Ensure known ammunition dumps are avoided.
c) Wells to avoid any shipwrecks and any other cultural heritage
/ archaeological material.
Notify the South African Heritage Resource Agency (SAHRA) 8.2.3.2
regarding requirements to disturb any such wrecks or any cultural
heritage / archaeological material.
TEPSA Prior to drilling
or as required
Copy of permit
from SAHRA (if
required)
8.2.4
Ensure integrity of
anchor system
Reduce
environmental risk
by minimising risk
of failures during
operation
Undertake and/or have in place the following in order to minimise 8.2.4.1
environmental risk:
a) A hazard identification and risk assessment document;
b) The Contractor must apply relevant national codes and
standards in accordance with good oil / gas field practice;
c) The Contractor must operate in accordance with procedures
Contractor
Prior to and
throughout
drilling
operations
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
36
PROJECT PHASE
AND ACTIVITIES
ENVIRONMENTAL
OBJECTIVES
AUDITABLE MANAGEMENT ACTIONS TO BE TAKEN TO MEET THE EMP
REPORT OBJECTIVES (WELL DRILLING)
COMPLIANCE RESPONSI-
BILITY Timing
REQUIREMENT
FOR “CLOSE-
OUT” REPORT
laid down in the vessel’s marine operations manual as
approved by the relevant classification society;
d) All anchor chains and anchors must be certified; and
e) The drilling unit(s) / vessel(s) must be maintained to class
standard throughout the project.
OPERATIONAL PHASE 8.3
8.3.1
Adherence to the
EMP and
Environmental
awareness
Operate in an
environmentally
responsible manner
Comply fully with the EMP (compliance would mean that all 8.3.1.1
activities were undertaken successfully and details recorded and
included in the Close-out Report).
Subscribe to the principles of an internationally acceptable 8.3.1.2
Environmental Management System onboard the drilling unit and
support vessels. This includes environmental awareness training,
waste management and environmental monitoring, record
keeping and continuous improvement.
TEPSA and
Contractor
Throughout
programme
Before
deployment to
site
Provide copies
of records
Certificate of
training
8.3.2
Continue to
communicate with
other users of the
sea and resource
managers
Promote co-
operation and
successful multiple
use of the sea,
including promotion
of safe navigation
Through normal communication channels, Radio Navigation 8.3.2.1
Warnings and Notices to Mariners, keep the following interested
and affected parties updated on the drilling programme:
a) Overlapping and neighbouring users with delineated
boundaries in the oil and gas exploration and production
industries and any mining industries.
b) SAN Hydrographic Office (Silvermine).
c) South African and foreign fishing vessels including:
Association of Small Hake Industries, SA Deep Sea Trawling
Industry Association, SA Inshore Fishing Industry Association,
South East Coast Inshore Fishing Association, SA Midwater
Trawling Association, SA Tuna Association, Fresh Tuna
Exporters Association, South Coast Rock Lobster Association,
Shark Longline Association, SA Pelagic Fishing Industry
Association, SA Commercial Linefish Association, and SA
Squid Management Industrial Association.
d) Fisheries and Mariculture Development Association.
e) Government departments with jurisdiction over marine
activities, particularly DEA, DEA:MCM and PASA.
TEPSA and
Contractor
During
operations as
required
and on
completion of
drilling
Provide copies
of written
notices and list
of those to
whom it was
sent
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
37
PROJECT PHASE
AND ACTIVITIES
ENVIRONMENTAL
OBJECTIVES
AUDITABLE MANAGEMENT ACTIONS TO BE TAKEN TO MEET THE EMP
REPORT OBJECTIVES (WELL DRILLING)
COMPLIANCE RESPONSI-
BILITY Timing
REQUIREMENT
FOR “CLOSE-
OUT” REPORT
f) SAMSA and local Port Captains.
Keep constant watch for approaching vessels during the drilling 8.3.2.2
programme and warn by radio and standby vessel, if required.
Take steps to share information and co-operate with other 8.3.2.3
marine users and resource managers in the marine environment
generally, to their mutual benefit.
8.3.3
Prevention of
emergencies
Minimise the
chance of
emergency and
subsequent
damage to the
environment
occurring
Prevent collisions by ensuring that the drilling unit and support 8.3.3.1
vessels display correct signals by day and lights by night (including
twilight), by visual radar watch and standby vessel(s).
Ensure that all well locations are surveyed and accurately charted 8.3.3.2
with the SA Navy Hydrographer.
The law also requires equipment and training to ensure the safety 8.3.3.3
and survival of the crew in the event of an accident.
Service equipment regularly and practice weekly emergency 8.3.3.4
response drills, etc. (refer to Mine Health and Safety Act and
regulations).
Establish lines of communication with the following emergency 8.3.3.5
response agencies / facilities: SAN Hydrographic Office
(Silvermine), SAMSA, DEA (Directorate of Marine Pollution), PASA
and DEA: MCM, MRCC
Ensure all hazardous materials are correctly labelled, stored, 8.3.3.6
packed and sealed with proper markings for shipping.
TEPSA and
Contractor
Throughout
operation
Provide copies
8.3.4
Dealing with
emergencies
including major oil
spills (owing to
collision, vessel
break-up,
refuelling etc.)
Minimise damage
to the environment
by implementing
response
procedures
efficiently
Adhere to obligations regarding other vessels in distress. 8.3.4.1
Implement health and safety procedures 8.3.4.2
Notify SAMSA about wrecked vessels (safety and pollution) and 8.3.4.3
the Department of Finance (salvage, customs, royalties). Give
location details to SAN Hydrographer.
In the event of an oil spill immediately implement emergency 8.3.4.4
plans and notify (a) the Principal Officer of the nearest SAMSA
office, (b) the DEA's Chief Directorate of Marine Pollution in Cape
Town and (c) PASA. Information that should be supplied when
reporting a spill includes:
TEPSA and
Contractor
In event of spill Record of all
spills (Spill
Record Book),
including spill
reports;
emergency
exercise
reports; audit
reports.
Incident log
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
38
PROJECT PHASE
AND ACTIVITIES
ENVIRONMENTAL
OBJECTIVES
AUDITABLE MANAGEMENT ACTIONS TO BE TAKEN TO MEET THE EMP
REPORT OBJECTIVES (WELL DRILLING)
COMPLIANCE RESPONSI-
BILITY Timing
REQUIREMENT
FOR “CLOSE-
OUT” REPORT
a) The type and circumstances of incident, ship type, port of
registry, nearest agent representing the ships company;
b) Geographic location of the incident, distance off-shore and
extent of oil spill;
c) Prevailing weather conditions, sea state in affected area
(wind direction and speed, weather and swell); and
d) Persons and authorities already informed of the spill.
Where diesel, which evaporates relatively quickly, has been 8.3.4.5
spilled, the water should be agitated or mixed using a propeller
boat/dinghy to aid dispersal and evaporation.
Dispersants should not be used without authorisation of DEA. 8.3.4.6
Dispersants should not be used:
a) On diesel or light fuel oil.
b) On heavy fuel oil.
c) On slicks > 0.5 cm thick.
d) On any oil spills within 5 nautical miles off-shore or in depths
less than 30 metres.
e) In areas far offshore where there is little likelihood of oil
reaching the shore.
Dispersants are most effective: 8.3.4.7
a) On fresh crude oils; under turbulent sea conditions (as
effective use of dispersants requires mixing).
b) When applied within 12 hours or at a maximum of 24 hours.
The volume of dispersant application should not exceed 20-30% 8.3.4.8
of the oil volume.
In the unlikely event of an uncontrolled gas or oil blow-out the 8.3.4.9
first objective is to ensure the safety of personnel followed by
efforts to move the drilling unit from the pool of upwelling gas
into safe waters. Once the safety of lives and equipment has been
assured the well can be brought under control using
internationally established procedures.
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
39
PROJECT PHASE
AND ACTIVITIES
ENVIRONMENTAL
OBJECTIVES
AUDITABLE MANAGEMENT ACTIONS TO BE TAKEN TO MEET THE EMP
REPORT OBJECTIVES (WELL DRILLING)
COMPLIANCE RESPONSI-
BILITY Timing
REQUIREMENT
FOR “CLOSE-
OUT” REPORT
8.3.5
Blow out
prevention during
well drilling
Ensure that the
necessary
safeguards are in
place and avoid any
uncontrolled
release of drilling
fluids, oil and/or
gas
Blow out preventers (BOPs) installed on wells during drilling must 8.3.5.1
be “fit for purpose” (i.e. appropriate for intended use,
dependable and effective when required and able to perform as
intended).
Undertake a shallow hazards analysis to address shallow gas and 8.3.5.2
shallow water flows.
Fully inspect the BOPs on the drilling unit(s) in accordance with 8.3.5.3
the American Petroleum Industries recommended practices (or
equivalent) prior to well drilling.
Ensure that all responsible personnel are qualified in accordance 8.3.5.4
with International Well Control Forum requirements or equal and
are adequately trained in both accident prevention and
immediate response.
Follow written and internationally established procedures for well 8.3.5.5
control.
Identify hazards and put risk control systems in place. 8.3.5.6
Implement monitoring and management to assist in the detection 8.3.5.7
of uncontrolled gas or oil releases.
TEPSA and
Contractor
Prior to and
during drilling
8.3.6
Disposal of drilling
muds and cuttings
Minimise
discharges into the
sea
The following mitigation measures should be implemented when 8.3.6.1
using NADF:
a) NADF should not be used in the upper part of a well (with the
exception in cases of geological or safety reasons) as specific
by the OSPAR Convention.
b) The drilling fluid should be centrifuged to remove as much of
the finer particles as possible.
c) Only Synthetic Based Drilling Fluid (OGP Type III) should be
used with a low polycyclic aromatic hydrocarbon content.
d) All recovered NADF should be stored on board and taken to
shore for treatment and reuse.
e) NADF cuttings should be treated to reduce oil-content on
cuttings to < 5% of weight before discharge to the sea.
f) NADF cuttings should be discharged 10 m below the sea
Contractor
During drilling
operation
Provide
estimates of
actual volumes
of muds and
cuttings
disposed.
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
40
PROJECT PHASE
AND ACTIVITIES
ENVIRONMENTAL
OBJECTIVES
AUDITABLE MANAGEMENT ACTIONS TO BE TAKEN TO MEET THE EMP
REPORT OBJECTIVES (WELL DRILLING)
COMPLIANCE RESPONSI-
BILITY Timing
REQUIREMENT
FOR “CLOSE-
OUT” REPORT
surface.
Optimally recycle the mud for use downhole to minimise mud 8.3.6.2
disposal overboard and reduce concentrations of mud chemicals
released.
Where they are used ROV’s should obtain video footage of the 8.3.6.3
seabed before and after drilling operations to assess the status of
cuttings disposal on the benthos.
8.3.7
Disposal of Ballast
water
Minimise the
discharge of ballast
water into the sea
and reduce the
possibility of an
impact
Avoid the unnecessary discharge of ballast water. 8.3.7.1
Adhere to the guidelines for management of ballast water 8.3.7.2
provided by the International Maritime Organisation (Guideline
A.868(20)).
Ensure that the drilling vessel has in place a ballast water 8.3.7.3
management plan.
Whenever possible, conduct the exchange of ballast water at 8.3.7.4
least 200 nautical miles from the nearest land and in water at
least 200 m in depth. Where this is not possible, the exchange
should be as far from the nearest land as possible, and in all cases
a minimum of 50 nautical miles from the nearest land and in
water at least 200 m in depth.
During the loading of ballast, every effort should be made to 8.3.7.5
avoid the uptake of potentially harmful aquatic organisms,
pathogens and sediment that may contain invasive organisms,
through adequate filtration procedures.
Where practicable, routine cleaning of the ballast tank to remove 8.3.7.6
sediments should be carried out in mid-ocean or under controlled
arrangements in port or dry dock.
Contractor
Throughout
drilling
operation
Provide
estimates of
actual volumes
of ballast water
disposed,
distance and
water depth
ballast water
was disposed.
8.3.8
Well testing
Ensure that there
are minimal
discharges into the
sea and minimise
product burned
Use high efficiency flare to maximise combustion of 8.3.8.1
hydrocarbons.
Use well control procedures to ensure that there are no 8.3.8.2
discharges to the sea.
For each drillstem flow test, provide an estimate of the volume of 8.3.8.3
any oily discharge into the sea and the size of the resulting slick /
sheen.
Contractor During well
testing
Quantity of gas
burned
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
41
PROJECT PHASE
AND ACTIVITIES
ENVIRONMENTAL
OBJECTIVES
AUDITABLE MANAGEMENT ACTIONS TO BE TAKEN TO MEET THE EMP
REPORT OBJECTIVES (WELL DRILLING)
COMPLIANCE RESPONSI-
BILITY Timing
REQUIREMENT
FOR “CLOSE-
OUT” REPORT
8.3.9
Rig installation,
anchor laying and
well infrastructure
installation
Minimise
disturbance to the
sea floor
Pre-drilling site surveys should ensure that drilling and anchoring 8.3.9.1
locations are not located within a 1 km radius of any vulnerable
habitats (e.g. hard grounds), species (e.g. cold corals, sponges) or
structural features (e.g. rocky outcrops).
Dynamically positioned vessels should be used in preference to 8.3.9.2
vessels requiring anchorage, if possible.
TEPSA and
Contractor
During pre-
drilling surveys
Throughout
drilling
operations
8.3.10
Transport, storage
and handling of
radioactive devices
Avoid human and
environmental
exposure to radio-
active material
Comply with necessary regulations for the transport, storage and 8.3.10.1
handling of radioactive devices. Transport and store radioactive
devices in specially designed secured (locked) storage containers.
Designate competent person/s in charge and to handle the 8.3.10.2
radioactive devices. Follow strict approved procedures when
handling the devices. Wear personal monitoring devices to
measure any unusual exposure.
Follow radioactive sources procedure. When radioactive sources 8.3.10.3
are to be used, secure the area between and around the storage
containers and the floor and only allowed key personnel in the
area.
Set up incident and emergency reporting procedures for actual or 8.3.10.4
suspected individual over-exposure, theft or loss, logging tools
stuck downhole in wells, and release or spillage into the
environment.
Test the sources every three to six months to document leak 8.3.10.5
levels.
TEPSA and
Contractor
Throughout
drilling
operations
Provide results
from routine
tests on
radioactive
sources to
determine leak
levels
8.3.11
Pollution control
and waste
management of
products disposed
of: into the air
(exhausts, cfcs and
incinerators), to
sea (sewage, food,
Minimise pollution,
and maximise
recycling by
implementing and
maintain pollution
control and waste
management
procedures at all
times
Comply with legal requirements for waste management and 8.3.11.1
pollution control (for air and water quality levels at sea) and
employ “good housekeeping” and monitoring practices.
a) General waste: Initiate a waste minimisation system. No
disposal overboard.
b) Galley (food) waste: Dispose overboard after macerating
according to MARPOL standard (less than 25 mm size) –
prohibited if distance to nearest land is < 3 nautical miles.
Disposal overboard without macerating – vessel must be 12
nautical miles from coast.
Contractor
Throughout
drilling
operations
Provide
summary of
waste record
book / schedule
and receipts
Report
occurrence of
minor oil spills
and destination
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
42
PROJECT PHASE
AND ACTIVITIES
ENVIRONMENTAL
OBJECTIVES
AUDITABLE MANAGEMENT ACTIONS TO BE TAKEN TO MEET THE EMP
REPORT OBJECTIVES (WELL DRILLING)
COMPLIANCE RESPONSI-
BILITY Timing
REQUIREMENT
FOR “CLOSE-
OUT” REPORT
oils), to land (used
oils etc, metals,
plastics, glass, etc.)
c) Medical waste: Seal in aseptic containers for appropriate
disposal onshore.
d) Metal: Send to shore for recycling or disposal.
e) Other waste: Send remaining waste to a licensed waste site.
Ensure waste disposal is carried out in accordance with
appropriate laws and ordinances.
f) Waste oil: Return used oil to a port with a registered facility
for processing or disposal.
g) Wastewater: Comply with MARPOL.
h) Minor oil spill: Use oil absorbent.
i) Emissions to the atmosphere: Properly tune and maintain all
engines, motors, generators and all auxiliary power to
contain the minimum of soot and unburned diesel.
j) Deck drainage: Deck drainage should be collected in oily
water separator systems. Ensure that weather decks are kept
free of spillage. Mop up any spills immediately with
biodegradable low toxicity detergents. Ensure compliance
with MARPOL standard.
k) Machinery space drainage: Drilling unit and supply vessels
must comply with international agreed standards regulated
under MARPOL.
l) Sewage - use approved treatment plants to the MARPOL
standard.
Ensure all crew is trained in spill management. 8.3.11.2
Record types and volumes of chemical and hazardous substances 8.3.11.3
brought on board (e.g. radioactive devices/materials, neon lights,
toner cartridges, etc.) and destination of wastes.
Ensure that a waste disposal contractor disposes of waste 8.3.11.4
returned to port at a licensed landfill site.
of wastes
8.3.12
Exclusion of other
marine users from
Minimise disruption
to other legitimate
users of the sea by
respecting their
Co-operate with other legitimate users of the sea to minimise 8.3.12.1
disruption to other marine activities and marine fauna.
Use effective communication channels (see Section 3.2) to inform 8.3.12.2
all other potential users about the drilling location, timing,
Contractor Throughout
drilling
operations
Confirm that
notices were
sent to relevant
parties
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
43
PROJECT PHASE
AND ACTIVITIES
ENVIRONMENTAL
OBJECTIVES
AUDITABLE MANAGEMENT ACTIONS TO BE TAKEN TO MEET THE EMP
REPORT OBJECTIVES (WELL DRILLING)
COMPLIANCE RESPONSI-
BILITY Timing
REQUIREMENT
FOR “CLOSE-
OUT” REPORT
access to the
operational area
for safety reasons
(shipping,
including fishing
and mining
vessels)
rights. priority of passage safety, 500 m exclusion zone and general
safety distances. To avoid any interference with anchors and
anchor chains it is suggested that the Notice to Mariners advises
of a stay clear area of 1 500 m from the corners of the drilling
unit(s), if applicable.
Provide copy of
standard notice
and list of those
to whom it was
sent
Record any
incidents
outside of
normal
occurrence
8.3.13
Equipment loss
Minimise hazards
left on the seabed
or floating in the
water column, and
inform relevant
parties
Keep a record of lost equipment and all items lost overboard and 8.3.13.1
not recovered.
When any items that constitute a seafloor or navigational hazard 8.3.13.2
are lost on the seabed, or in the sea, complete a standard form /
record sheet, which records the date and cause of loss, details of
equipment type, etc.
Pass information to PASA and SAMSA. Notify SAN Hydrographer, 8.3.13.3
relevant mining companies and fishing associations. SAN
Hydrographer will send out Notice to Mariners with this
information.
Contractor
Throughout
drilling
operation
Provide a list of
lost equipment
and a copy of
record sheet
8.3.14
Use of helicopters
for crew changes,
servicing, etc.
Minimise
disturbance /
damage to marine
and coastal fauna.
Establish, with pilots, flight paths that do not over-pass Ramsar 8.3.14.1
sites, islands, coastal reserves, bird and seal breeding or bird
breeding colonies / sanctuaries on the coast (minimum altitudes
of 2 000 feet above ground level over nature conservation areas).
Extensive coastal flights (parallel to the coast within 1 nautical 8.3.14.2
mile of the shore) should also be avoided. There is a restriction of
coastal flight on the South Coast between June and November in
order to avoid Southern Right Whale breeding areas.
Aircraft may not approach to within 300 m of whales. 8.3.14.3
Deviations from set flight plans must be reported. 8.3.14.4
Brief all pilots on the ecological risks associated with over flights 8.3.14.5
of seabird and seal colonies.
TEPSA and
Contractor
As required Submit copy of
set flight path.
Report
deviations from
set flight paths.
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
44
PROJECT PHASE
AND ACTIVITIES
ENVIRONMENTAL
OBJECTIVES
AUDITABLE MANAGEMENT ACTIONS TO BE TAKEN TO MEET THE EMP
REPORT OBJECTIVES (WELL DRILLING)
COMPLIANCE RESPONSI-
BILITY Timing
REQUIREMENT
FOR “CLOSE-
OUT” REPORT
8.3.15
Oil bunkering /
refuelling at sea
Minimise
disturbance /
damage to marine
life.
No discharge of any oil whatsoever is permitted within 50 nautical 8.3.15.1
miles of the coast.
Transfer of oil at sea is not permitted within the economic zone 8.3.15.2
(i.e. 200 miles from the coast) without the permission of the
Minister. In terms of the Marine Pollution (Control and Civil
Liability) Act (1981) a Pollution Safety Certificate must be
obtained before commencement of operations.
Submit an application in terms of Regulation 14 (Regulation under 8.3.15.3
the Prevention and Combating of Pollution of the Sea by Oil Act,
1984) to the Principal Officer at the port nearest, should
bunkering of oil be undertaken. Permission would cover the
duration of the drilling period.
Contractor Before
commencemen
t of operations
8.3.16
Drill Rig lighting
Minimise attraction
of marine fauna to
drilling unit(s)
Consider light shielding in order to reduce seabird mortalities. 8.3.16.1
Minimise non-essential lighting to reduce nocturnal attraction. 8.3.16.2
However, such measures should not undermine work safety
aspects or concerns.
Minimise the discharge of waste material should obvious 8.3.16.3
attraction of fauna be observed.
Contractor
8.3.17
Benthic fauna
Improve knowledge
of offshore benthic
environment.
Identify any foreign
organisms
Any underwater inspections of infrastructure (ROV and SAT diver) 8.3.17.1
should be used as opportunities to acquire footage (close-ups and
stills) of marine life associated with the infrastructure. Where
possible, samples of any dense colonies of marine life should be
captured / collected and identified by a qualified marine
ecologist.
All visual footage of infrastructure should be inspected by marine 8.3.17.2
ecologists to detect any potential invasive species.
TEPSA and
Contractor
During
operations
DECOMMISSIONING AND CLOSURE PHASE 8.4
8.4.1
Completion of
wells
Ensure that there
are no leakages and
wherever possible
ensure that nothing
is left on the
seafloor
Seal the well by inserting concrete plugs in the well bore at 8.4.1.1
various levels according to good oilfield practice. Test well
integrity.
Remove BOP stack and any other equipment that may have been 8.4.1.2
dropped on the seafloor.
Contractor On completion
of well drilling
Confirmation of
activity
completed.
Provide
photographic
evidence or
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
45
PROJECT PHASE
AND ACTIVITIES
ENVIRONMENTAL
OBJECTIVES
AUDITABLE MANAGEMENT ACTIONS TO BE TAKEN TO MEET THE EMP
REPORT OBJECTIVES (WELL DRILLING)
COMPLIANCE RESPONSI-
BILITY Timing
REQUIREMENT
FOR “CLOSE-
OUT” REPORT
Place an over-trawlable structure/cap over the wellhead if left on 8.4.1.3
the seafloor. Ensure that seafloor is clear of any debris on
completion of placement of structure.
written receipt
from waste
disposal
contractor.
8.4.2
Drilling unit /
vessels to leave
area
Leave area as it
was prior to
operation
Ensure that no construction debris or dropped equipment that 8.4.2.1
may be detrimental to the environment or other users of the sea
is left on the seafloor.
Contractor On completion
of well drilling
Confirm, where
possible,
through seabed
scan and/or
video.
Provide log of
lost objects
8.4.3
Inform relevant
parties of drilling
completion
Ensure that
relevant parties are
aware that the
drilling operation is
complete
Inform all key stakeholders (see Section 2.2) that the drilling unit 8.4.3.1
and support vessels are off location.
8.4.3.2 Notify SAN Hydrographic Office of the location of the over-
trawlable structure and request that this be recorded on the
necessary hydrographic charts
TEPSA and
Contractor
Within one
weeks after
completion of
drilling
Copies of
notification
documentation
required.
8.4.4
Final waste
disposal
Minimise pollution
and ensure correct
disposal of waste
Dispose all waste retained onboard at a licensed waste site using 8.4.4.1
a licensed waste disposal contractor.
Contractor When vessel is
in port
Receipt
required from
contractor
MONITORING, COMPLIANCE AUDITING AND THE SUBMISSION OF INFORMATION PHASE 8.5
8.5.1
Performance
assessment /
monitoring
activities and
effects
Implement the
ongoing monitoring
programmes (in
conjunction with
government if
required)
Compile monitoring programme and EMP Performance 8.5.1.1
Assessments and submit to PASA.
Undertake appropriate monitoring (as per specific topics) and 8.5.1.2
track performance against objectives and targets. Document all
activities and results for internal and external auditing.
Ensure monitoring/observation of marine fauna from drilling unit, 8.5.1.3
including:
b) Record actual bird reaction to lights and real incidents of
injury or death. Ringed or banded birds should be reported to
the appropriate scheme (details on ring); and
c) Interaction with other vessels.
TEPSA and
Contractor
Daily
throughout
operations
The frequency
of performance
assessments
shall be as
recommended
by PASA
Provide all
recorded
information
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
46
PROJECT PHASE
AND ACTIVITIES
ENVIRONMENTAL
OBJECTIVES
AUDITABLE MANAGEMENT ACTIONS TO BE TAKEN TO MEET THE EMP
REPORT OBJECTIVES (WELL DRILLING)
COMPLIANCE RESPONSI-
BILITY Timing
REQUIREMENT
FOR “CLOSE-
OUT” REPORT
8.5.2
Compile well
drilling “close-out”
report
Ensure corrective
action and
compliance and
contribute towards
improvement of
EMP
implementation
Compile a well drilling “Close-out” report for each well. 8.5.2.1
“Close–out” Report must be based on requirements of the 8.5.2.2
monitoring and EMP Performance Assessment.
Provide information / records as indicated in the “Close-out” 8.5.2.3
Report column of the EMP within 90-days of the drilling
operation.
Provide copy of report to PASA and DEA. 8.5.2.4
Provide a copy of any video footage that was shot during the 8.5.2.5
course of the drilling operation to PASA.
TEPSA On completion
of each well
Total E&P South Africa B.V.
Application to Amend Environmental Management Programme Block 11B/12B
720.20047.00003
November 2018
47
REFERENCES 9
Please refer to the specialist studies for a list of the references.