AGOS Quarter 2 2014 Summary[1] - AuScope...

5
AGOS Milestone Report No 12 February 2014 AuScope Limited Australian Geophysical Observing System AGOS Progress Quarter 2 2014 At the conclusion of Quarter 2 2014 (31 December 2013), most planned milestones had been reached in line with the AGOS Agreement. However some delays are being experienced. Construction of the 4 remote CORS GNSS sites is behind schedule although 2 sites are now complete with work in progress on the remaining 2 sites. Subsurface access projects remain behind schedule and progress is being closely monitored. The new Ocean Bottom Seismometer equipment has been delivered to Canberra from the UK however critical testing of the equipment has been delayed because of the unavailability of the research vessel operated by the Marine National Facility. This will require a revised testing plan to be implemented. Otherwise, all equipment and physical infrastructure for the AGOS infrastructure has now been acquired and deployments by enduser research groups are underway in several regions in Australia and New Zealand. The Earth Sounding Network All components of the project are now complete, with the exception of the Ocean Bottom Seismometer (OBS) pool. The Earth Data recorders, which became field ready in December 2012, continue to be heavily utilised in Australia and New Zealand. Construction of the entire pool (200 instruments) of the new generation seismic data loggers was completed on schedule in 2013.The equipment is now ready for deployment and by the end of March 2014, they will form the backbone of two new arrays in northern NSW/southern Queensland and one in Western Australia. All 20 OBS units have been shipped to Canberra from the UK. The test deployment originally planned to take place in November/December 2013 to test the first 12 and a second cruise, administered by the Marine National Facility to take place in February/March 2014 to test the remaining 8 instruments has had to be rescheduled. This has occurred due to the unavailability of the MNF ship which is still undergoing testing in Singapore prior to deployment to Australia. The revised plan is to test in March on the NW Shelf with a Guralpsupplied specialist with the result that this process will be both more difficult and costly than expected. Following successful testing, all 20 OBS units should be fieldready. As reported last quarter 50 new Trillium Compact seismometers are ready for use and will be deployed in one of the Queensland arrays and one of the Western Australian arrays.

Transcript of AGOS Quarter 2 2014 Summary[1] - AuScope...

Page 1: AGOS Quarter 2 2014 Summary[1] - AuScope …auscope.org.au/.../2015/11/AGOS-Quarter-2_2014-Summary.pdfThe%Subsurface%Observatory%petrophysics%laboratory% continuesto%run%at%capacity.%%Asa%result%of%some%new%

AGOS  Milestone  Report  No  12  February  2014  

 

 AuScope  Limited     Australian  Geophysical  Observing  System    

 

AGOS  Progress  Quarter  2  2014    

At  the  conclusion  of  Quarter  2  2014  (31  December  2013),  most  planned  milestones  had  been  reached  in  line  with  the  AGOS  Agreement.    However  some  delays  are  being  experienced.  Construction  of  the  4  remote  CORS  GNSS  sites  is  behind  schedule  although  2  sites  are  now  complete  with  work  in  progress  on  the  remaining  2  sites.    Subsurface  access  projects  remain  behind  schedule  and  progress  is  being  closely  monitored.  The  new  Ocean  Bottom  Seismometer  equipment  has  been  delivered  to  Canberra  from  the  UK  however  critical  testing  of  the  equipment  has  been  delayed  because  of  the  unavailability  of  the  research  vessel  operated  by  the  Marine  National  Facility.  This  will  require  a  revised  testing  plan  to  be  implemented.  Otherwise,  all  equipment  and  physical  infrastructure  for  the  AGOS  infrastructure  has  now  been  acquired  and  deployments  by  end-­‐user  research  groups  are  underway  in  several  regions  in  Australia  and  New  Zealand.  

 

The  Earth  Sounding  Network    

All  components  of  the  project  are  now  complete,  with  the  exception  of  the  Ocean  Bottom  Seismometer  (OBS)  pool.    

The  Earth  Data  recorders,  which  became  field  ready  in  December  2012,  continue  to  be  heavily  utilised  in  Australia  and  New  Zealand.  

Construction  of  the  entire  pool  (200  instruments)  of  the  new  generation  seismic  data  loggers  was  completed  on  schedule  in  2013.The  equipment  is  now  ready  for  deployment  and  by  the  end  of  March  2014,  they  will  form  the  backbone  of  two  new  arrays  in  northern  NSW/southern  Queensland  and  one  in  Western  Australia.  

All  20  OBS  units  have  been  shipped  to  Canberra  from  the  UK.  The  test  deployment    originally  planned  to  take  place  in  November/December  2013  to  test  the  first  12  and  a  second  cruise,  administered  by  the  Marine  National  Facility  to  take  place  in  February/March  2014    to  test  the  remaining  8  instruments  has  had  to  be  rescheduled.  This  has  occurred  due  to  the  unavailability  of  the  MNF  ship  which  is  still  undergoing  testing  in  Singapore  prior  to  deployment  to  Australia.  The  revised  plan  is  to  test  in  March  on  the  NW  Shelf  with  a  Guralp-­‐supplied  specialist  with  the  result  that  this  process  will  be  both  more  difficult  and  costly  than  expected.  Following  successful  testing,  all  20  OBS  units  should  be  field-­‐ready.  

As  reported  last  quarter  50  new  Trillium  Compact  seismometers  are  ready  for  use  and  will  be  deployed  in  one  of  the  Queensland  arrays  and  one  of  the  Western  Australian  arrays.  

 

Page 2: AGOS Quarter 2 2014 Summary[1] - AuScope …auscope.org.au/.../2015/11/AGOS-Quarter-2_2014-Summary.pdfThe%Subsurface%Observatory%petrophysics%laboratory% continuesto%run%at%capacity.%%Asa%result%of%some%new%

AGOS  Milestone  Report  No  12  February  2014  

 

 AuScope  Limited     Australian  Geophysical  Observing  System    

 

The  Geohistory  Laboratory  

Establishment  of  the  Gehistory  Laboratory  is  essentially  complete.  No  further  infrastructure  expenditure  has  been  undertaken  on  the  Melbourne  University  node  or  the  Curtin  node  of  the  laboratory.  Inter-­‐node  calibration  experiments  between  the  Melbourne  and  Curtin  have  continued.  The  possibility  of  a  Ministerial  launch  of  the  facility  is  being  investigated.    The  Subsurface  Observatory    

The  Subsurface  Observatory  petrophysics  laboratory  continues  to  run  at  capacity.    As  a  result  of  some  new  building  works  in  the  Melbourne  School  of  Earth  Sciences,  the  Petrophysics  laboratory  will  be  moved  in  the  next  quarter  and  therefore  some  preparatory  work  has  been  undertaken  to  facilitate  this.    As  a  result  of  the  move  the  lab  will  only  be  out  of  commission  for  a  period  of  one  week.  

In  addition  to  the  more  traditional  applications  of  the  equipment,  this  quarter  has  seen  AGOS  thermal  conductivity  equipment  used  to  measure  the  insulation  properties  of  balsa  wood,  a  fast  growing  tree  species  in  PNG  and  one  that  may  be  used,  with  Australian  support,  to  co-­‐develop  a  new  industry  for  local  communities  in  that  region.  

The  SOB  Access  projects  are  well  underway  and  a  number  of  new  submissions  for  a  series  of  modest  projects  in  Vic,  NSW  and  SA  have  been  received  over  the  last  two  months.  

The  Distributed  Temperature  Sensor  deployed  in  the  Loy  Yang  1  well  in  Gippsland  has  been  gathering  data  over  the  last  three  months  and  this  data  is  now  being  processed  prior  to  release  to  the  public.  

 

The  Inversion  Laboratory  

At  ANU,  four  key  pieces  of  inversion  code  for  the  iLab  were  released  during  the  Quarter  (Redback,  Surface  Wave  Dispersion,  Receiver  Function  and  Tomography).    

Progress  at  UQ  includes:  • release  of  an  escript  inversion  package  with  

bug  fixing  and  documentation  • implementation  of  2D  MT  forward  modelling  

application  • preliminary  work  on    2D  waveform  inversion    

In  relation  to  the  Terrawulf  operations,  all  of  the  TII/  TIII  compute  servers  are  operating  and  users  are  

Page 3: AGOS Quarter 2 2014 Summary[1] - AuScope …auscope.org.au/.../2015/11/AGOS-Quarter-2_2014-Summary.pdfThe%Subsurface%Observatory%petrophysics%laboratory% continuesto%run%at%capacity.%%Asa%result%of%some%new%

AGOS  Milestone  Report  No  12  February  2014  

 

 AuScope  Limited     Australian  Geophysical  Observing  System    

routinely  running  production  code  on  the  cluster.    The  cluster  has  been  running  at  an  average  60%  capacity  with  peaks  above  80%. This  usage  is  up  slightly  from  last  Quarter  despite  some  system  shutdowns.    The  Geospatial  Observatory  

The  deployable  GNSS  instrument  pool  remains  operational.    GA,  ANU,  UNSW,  UTAS  and  the  Australian  Antarctic  Division  currently  have  AGOS  supported  research  projects  underway.  

The  AGOS  GNSS  CORS  build  (4  sites)  is  ongoing.    Both  the  WA  site  and  King  Island  sites  are  fully  operational.  Contracts  for  the  civil  construction  of  the  remaining  two  sites  in  SA  and  Queensland  are  being  developed.    Completion  of  the  CORS  build  program  is  forecast  to  be  by  the  end  of  June.  

The  Robotic  GNSS  Calibration  Facility  is  fully  operational  and  a  number  of  antennae  have  been  calibrated.    Work  with  industry  partner  Locata,  has  commenced  and  the  facility  is  supporting  their  technology  development  program.    Locata  is  an  Australia  company  specialising  in  indoor  and  mine  site  positioning  systems.  

A  prototype  radar  reflector  array  has  been  built  and  deployed  at  Gunning  near  Canberra.  Four  space  agencies  are  tasking  their  radar  satellites  to  observe  the  array.    The  reflectors  are  being  tested  with  the  ultimate  aim  of  improving  sensor  calibrations.  Once  this  testing  is  complete  in  March  the  reflectors  will  deployed  to  the  Surat  Basin,  Queensland,  to  support  the  measurement  of  subsidence  in  Coal  Seam  Gas  extraction  areas.    Contracts  to  build  this  infrastructure  in  Queensland  are  in  the  tender  process.  GA  has  continued  to  employ  a  dedicated  project  manager  to  deliver  this  project  after  the  Queensland  Government  was  unable  to  participate.  

 

The  Geophysical  Education  Observatory  

This  quarter  the  Australian  Seismometers  in  Schools  Network  has  almost  completed  the  installation  phase  of  the  network.  There  are  now  39  instruments  installed  in  schools  and  installation  is  complete  in  WA,  SA,  VIC  and  Queensland.  One  instrument  still  remains  unassigned  for  the  Alice  Springs  or  Tennant  Creek  area  and  consideration  is  being  given  to  install  this  instrument  in  a  primary  school.  Focus  has  now  turned  to  keeping  schools  engaged  with  the  program  and  maintaining  data  flow  and  connectivity.  A  major  highlight  of  this  quarter  has  been  the  Australian  Seismometers  in  Schools  success  in  the  Australian  Innovation  Challenge,  winning  the  education  category.

GPS  in  Schools  program  processing  in  Tasmania  and  ACT.  Both  Jurisdictions  have  commenced  working  with  schools  to  identify  requirements  and  are  undertaking  planning.  Difficulties  working  with  the  other  jurisdictions  have  emerged  with  a  reluctance  to  sign  agreements.    Contingency  

Page 4: AGOS Quarter 2 2014 Summary[1] - AuScope …auscope.org.au/.../2015/11/AGOS-Quarter-2_2014-Summary.pdfThe%Subsurface%Observatory%petrophysics%laboratory% continuesto%run%at%capacity.%%Asa%result%of%some%new%

AGOS  Milestone  Report  No  12  February  2014  

 

 AuScope  Limited     Australian  Geophysical  Observing  System    

planning  has  commenced  to  ensure  the  success  of  the  program.  This  will  involve  targeting  those  jurisdictions  who  are  willing  to  work  on  the  program  with  proposals  for  additional  stations.  The  University  of  Tasmania  (UTAS)  has  agreed  to  provide  educational  material  explaining  the  program  which  will  be  targeted  to  high  school  students.  This  component  will  be  completed  in  February  2014.    Project  Milestones  The  status  of  project  milestones  is  shown  in  the  table  below.  Note  that  milestones  shown  incomplete  in  earlier  Quarters  are  included  below  to  show  that  progress  has  been  made.      

No.   Milestone   Projected  completion  Date  

Status  

Milestones  to  30  September  2013  (reported  not  complete  in  earlier  Reports)

43  

Geospatial  Observatory:  4  new  permanent  GNSS  CORS  stations  installed  

30  June  2013   2  sites  complete  and  operational  with  planning  for  the  two  remaining  sites  progressing  well  and  scheduled  for  completion  by  end  June  2014.  

59  

Geospatial  Observatory:  GNSS  and  radar  reflector  arrays  designed  and  installed  (first  50%)  

30  September  2013   Radar  reflector  design  complete;  prototype  built  and  undergoing  testing    on  a  site  near  Canberra  prior  to  deployment  in  Qld.  Testing  will  now  be  completed  in  March  2014  to  allow  rigorous  testing  by  4  space  agencies  prior  to  deployment.  

60  

Subsurface  Observatory:  Third  stage  sites  selected  

30  September  2013   70%  complete.  Delays  in  research  consortia  finalising  access  requirements  necessitates  a  review  of  the  status  of  this  milestone.  

Indicative  Milestones  to  31  December  2013

63  

Inversion  Laboratory:  Integration  of  inversion  capability  into  Escript  prototype  released  

31  December  2013   50%  complete.  Delayed  to  December  2014  because  the  AGOS  inversion  tools  based  on  escript  are  to  be  integrated  into  the  escript  distribution  as  a  package  and  are  distributed  with  escript  releases  rather  than  prototypes.  

64  Geophysical  Education  Observatory:  Remaining  seismometer  pool  purchased    

31  December  2013   Complete  

65  Subsurface  Observatory:  Second  stage  completed  

31  December  2013   This  milestone  is  60%  complete.  Delays  relate  largely  to  delays  experienced  by  the  3rd  party  

Page 5: AGOS Quarter 2 2014 Summary[1] - AuScope …auscope.org.au/.../2015/11/AGOS-Quarter-2_2014-Summary.pdfThe%Subsurface%Observatory%petrophysics%laboratory% continuesto%run%at%capacity.%%Asa%result%of%some%new%

AGOS  Milestone  Report  No  12  February  2014  

 

 AuScope  Limited     Australian  Geophysical  Observing  System    

research  groups  in  specifying  and  finalising  subsurface  research  activities  that  require  access  funding.  The  matter  has  been  flagged  with  DoE  for  further  discussion  and  resolution.      

66  Milestone  Report  12   31  December  2013   Complete  for  internal  

distribution