    MONTHLY REPORT

    1 | P

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    INDEX

    1.0 Project Background 2

    2.0 Third Party Quality Audit Consultant 3

    3.0 Major Activities and Review Meetings of the Month 3

    4.0 Status of TPQA Visits 4

    5.0 Progress of NCRMP works 5

    TPQA Status Report for NCRMP Works To the end of(31-03-2012) 6

    6.0 District wise status of tests conducted by TPQA 28

    7.0 Details of Audit Reports Submitted during this Month 29

    8.0 Details of Environmental & Social Reports Submitted during this Month 30

    9.0 Observations of Submitted Reports 31

    Status of Non Compliance Reports for NCRMP works to the end of 31-03-2012

    Photographs of Site Visits during the Month

  • 7/31/2019 7. March MPR 2012

    3/52

    MONTHLY REPORT

    2 | P

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    1.0 Project Background

    Andhra Pradesh (AP) state has one of the longest coastal belts in India. Out of 67,362 Km of road network in the state, the

    nine coastal districts cover 26,000 km of road length. Every year during the period of April-May and September-December,

    cyclonic situations set in to the Bay of Bengal. With the recent changes in climatic conditions, the catastrophic events are

    increasing resulting in very devastating cyclones like Laila, Jal etc where the loss is enormous. In the 97 years ranging

    from 1892 to 1989, there were as many as 67 cyclones within the State.

    It is essential to provide safe residential accommodation to the vulnerable population during any eventuality or disaster due

    to natural calamities such as cyclones and associated tidal waves and storm surges. The project is formulated based on

    experiences of Government of Andhra Pradesh in mitigating such disasters during the past and also keeping in view the

    existing facilities available in the project area in Andhra Pradesh.

    The Government of India has applied for a credit of US$ 255 Million equivalent from the International Development

    Association (IDA) toward the cost of National Cyclone Risk Mitigation Project (NCRMP), and it intends to apply the

    proceeds to payments for goods, works, related services and consulting services under this Project.

    National Cyclone Risk Mitigation Project (NCRMP) Project Implementation Unit (PIU), Andhra Pradesh, headquartered at

    Hyderabad has invited the consultants to submit proposals for providing the consultancy services for Third Party Quality

    Audit for 9 coastal districts namely Srikakulam, Vijayanagaram, Visakhapatnam, East Godavari, West Godavari, Krishna,

    Guntur, Prakasam and Nellore. The project Construction of Multipurpose Cyclone Shelters, Roads to Cyclone

    Shelters, and Roads to habitations and Roads & Bridges under NCRMP is funded by International Development

    Association and received through Government of India. This consultancy is envisaged to audit the quality of works being

    implemented by various line departments working under PIU. The number of works under progress / for which

    agreements are concluded in each district is shown in the table below.

    District

    No. of works(Under Concluded Agreements) No. of works under ProgressNo. ofworks

    notstarted

    RHB RCS MPCS BridgesRoads(R&B)

    Total RHB RCS MPCS BridgesRoads(R&B)

    Srikakulam 6 8 2 4 1 21 6 5 2 3 1 4

    Vizianagaram - - - 2 1 3 - - - 2 1 0

    Visakhapatnam 8 6 7 - - 21 8 6 7 - - 0

    East Godavari 2 8 3 - - 13 2 7 3 - - 1

    West Godavari 10 - - - - 10 9 - - - - 1

    Krishna 5 3 - - - 8 5 3 - - - 0

    Guntur 3 12 - 2 - 17 3 7 - 2 - 5

    Prakasham 14 7 2 1 - 24 14 6 2 1 - 1

    Nellore 16 8 - - - 24 16 8 - - 0

  • 7/31/2019 7. March MPR 2012

    4/52

    MONTHLY REPORT

    3 | P

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    2.0 Third Party Quality Audit Consultant.

    To provide Consulting Services of Third Party Quality Auditor for Construction of Multipurpose Cyclone Shelters, Roads to

    Cyclone Shelters, Roads to habitations, and Roads and Bridges under NCRMP in 9 coastal districts The Commissioner for

    Disaster Management & Project Director, Project Implementation Unit (PIU) NCRMP has selected Egis International in JVwith Egis India Consulting Engineers (I) Pvt. Ltd. On 31

    stMay2011, the Contract for Consultancy Service was signed

    between The Commissioner for Disaster Management & Project Director, Project Implementation Unit (PIU) NCRMP and

    the Egis International in JV with Egis India Consulting Engineers (I) Pvt. Ltd.

    3.0 Major Activities and Review Meetings of the Month

    S.No. Place Date Activity

    1 06-03-2012 Hyderabad Attended Review meeting at NCRMP office

    2 14-03-2012 Hyderabad Attended Review meeting at NCRMP office

    3 16-03-2012 Hyderabad Attended video conference at C Block in the Secretariat onNCRMP works of Panchayat Raj Department

  • 7/31/2019 7. March MPR 2012

    5/52

    MONTHLY REPORT

    4 | P

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    4.0 Status of TPQA Visits:

    The following table shows the details of TPQA visits to sites in respective districts.

    District Total Number of VisitsUp to Feb.'2012 In Mar.'2012 Up to Mar.'2012

    Srikakulam 163 25 188

    Vizianagaram 60 6 66

    Vishakhapatnam 143 36 179

    East Godavari 235 65 300

    West Godavari 204 43 247

    Krishna 137 29 166

    Guntur 152 15 167

    Prakasam 196 27 223

    Nellore 158 18 176

    No. of Visits by TPQA

  • 7/31/2019 7. March MPR 2012

    6/52

    MONTHLY REPORT

    5 | P

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    5.0 Progress of NCRMP works:

    The district wise progress of works is shown below. The works in the West Godavari are not started and the works in

    Krishna District has just started. At many places the first milestone is completed but works are not started. The line

    departments are to analyze the reasons for the slow progress and if necessary penalty for the slow progress as per the

    agreement conditions should be imposed.

    Third Party Quality Audit by Egis India consulting services

    Summary of Activities

    S.No. District

    Agreements for PackagesCommunicated

    Status of works

    PR R&B Progress Not Started

    1 Srikakulam 6 5 17 4

    2 Vizianagaram - 3 3 0

    3 Visakhapatnam 13 0 21 0

    4 East Godavari 7 0 12 1

    5 West Godavari 3 0 9 1

    6 Krishna 4 0 8 0

    7 Guntur 6 2 12 5

    8 Prakasham 12 1 23 1

    9 Nellore 16 0 24 0

    Total 67 11 129 12

    Total Packages for which Agreements are received 78

    Total Number of works in the above packages 141

  • 7/31/2019 7. March MPR 2012

    7/52

    MONTHLY REPORT

    6 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    TPQA Status Report for NCRMP Works To the end of(31-03-2012)

    S.No. District

    Packages /Works

    entrustedStatus of Works

    No.of

    Visitsof

    TPQA

    TotalNo.

    of QCtestsdone

    NCRsQC

    ReportsIssued

    Environmentaland Social

    ReportsIssued

    Issued closed Pending

    PR R&B StartedNot

    Started

    1 Srikakulam 06_16 5_5 17 4 188 526 10 9 1 13 17

    2 Vizianagaram - 3_3 3 0 66 316 - - - 7 5

    3 Visakhapatnam 13_21 - 21 0 179 1193 9 9 - 18 16

    4 East Godavari 07_13 - 12 1 300 582 4 4 - 17 3

    5 West Godavari 03_10 - 9 1 247 177 - - - 17 19

    6 Krishna 04_08 - 8 0 166 42 3 3 0 - 13

    7 Guntur 06_15 2_2 12 5 167 291 9 9 - 12 5

    8 Prakasham 12_23 1_1 23 1 223 1540 11 9 2 18 15

    9 Nellore 16_24 - 24 0 176 643 7 3 4 16 9

    Total 67_130 11_11 129 12 1712 5310 53 46 7 118 102

  • 7/31/2019 7. March MPR 2012

    8/52

    MONTHLY REPORT

    7 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in Srikakulam District up to 31.03.2012

    Category Packages allotted under Phase - 1Names of works undereach package

    Agreement No. / Date DHS DFCProgress up to31.03.2012

    RHB

    NCRMP/B-W/AP/RHB/PRED/01/Santhabommali/003

    Road from DPN R&Broad to Uddandapalem

    /2010-11, Dt.30.04.2011

    30.04.11 30.04.12WBM GR-II,GR-III &

    Shoulders

    Road from K. UmiladaJunction to Koduru (LinkRoad)

    /2010-11, Dt.30.04.2011

    30.04.11 30.04.12WBM GR-II,GR-III &

    Shoulders

    Road from Borubadra,Malagam to Kollipadu viaSeepuram, Gantapeta

    /2010-11, Dt.30.04.2011

    30.04.11 30.04.12WBM GR-II,GR-III &

    Shoulders

    NCRMP/B-W/AP/RHB/PRED/01/Polaki/006

    Road from R&B roadMobagam to

    Duubakavanipeta viaGajapathinagaram

    /2010-11, Dt.

    30.04.201130.04.11 30.04.12

    First Milestone i.eEarthwork & Cd

    works &GSB

    Road fromTalasamudram to DolaRegulator

    /2010-11, Dt.30.04.2011

    30.04.11 30.04.12

    First Milestone i.eEarthwork & Cd

    works &GSB

    NCRMP/B-W/AP/RHB/PRED/01/Polaki/005

    Road from R&B roadEdulavalasa - Killam toJonnam viaTalasamudram

    /2011-12, Dt.30.04.2011

    30.04.11 31.01.12

    First Milestone i.eEarthwork & Cd

    works &GSB

    Bridges

    NCRMP/B-W/ AP/Br/R&B/01/Patnavanipeta/001

    Construction of bridge atKm 11/6-8 of NH-5 toPatnavanipetaConnecting

    Sundarapalem

    46/2011, Dt.17.12.2010

    17.12.10 17.06.12

    First Milestone i.eFoundation up to well

    capping

    NCRMP/B-W/AP/Br/R&B/01/ Surampeta/003

    Construction of MinorBridge at Km 12/2-4 ofNH-5 to SurampetaRoad via Naruva,Mentada

    45/2010-2011,Dt17.12.2010

    17.12.10 17.03.12

    Second Milestone i.eCompletion up to

    below the deck slab.

  • 7/31/2019 7. March MPR 2012

    9/52

    MONTHLY REPORT

    8 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-W/AP/Br/R&B/01/Bendigadda/004

    Construction of Highlevel bridge acrossBendigadda at KM 4/10of Pundi-Parlakimidi roadin Srikakulam Dt, A.P.

    1/2010,Dt.11.11.2010 11.11.10 11.05.12

    First Milestone i.eFoundation up to well

    capping

    Roads NCRMP/B-W/AP/RD/R&B/01/Nowpada/006)Improvements Naupada-Venkatapuram road from0/0to15/0km

    43/2010-11,17.12.2010 17.12.10 17.03.12Second mile stonei.e.WMM,Shoulders

    RCS

    NCRMP/B-W/AP/RCS/PRED/01/V.Kotturui/002

    Road from NP road toURK Puram

    G.O.Rt.No.451, Dt.06.04.2011

    06.04.11 29.09.12E/W,pipe

    culverts,GSB,R/W

    Road from Deppuru,Bahadapalli road toOnkuluru to CycloneShelter

    G.O.Rt.No.451, Dt.06.04.2011

    06.04.11 29.09.12E/W,pipe

    culverts,GSB,R/W

    Road from R & B Roadto Devunthalada

    G.O.Rt.No.451, Dt.06.04.2011

    06.04.11 29.09.12E/W,pipe

    culverts,GSB,R/WRoad from Pollada toKomarthalada toCyclone Shelter

    G.O.Rt.No.451, Dt.06.04.2011

    06.04.11 29.09.12E/W,pipe

    culverts,GSB,R/W

    NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005

    Road from Koyyam R &B Road toMoosavanipeta

    G.O.Rt.No.451, Dt.06.04.2011

    30.04.11 07.05.12E/W, pipe culverts,

    GSB.

    Road from Mentada toDovupeta

    G.O.Rt.No.451, Dt.06.04.2011

    30.04.11 07.05.12E/W, pipe culverts,

    GSB.

    Road from Kotcherelaroad to Kollibhemavaram& Cyclone Shelter

    G.O.Rt.No.451, Dt.06.04.2011

    30.04.11 07.05.12E/W, pipe culverts,

    GSB.

    Road from Kotcherlaroad toPathesundrapalem

    G.O.Rt.No.451, Dt.06.04.2011

    30.04.11 07.05.12E/W, pipe culverts,

    GSB.

  • 7/31/2019 7. March MPR 2012

    10/52

    MONTHLY REPORT

    9 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    MPCSNCRMP/B_W/AP/MPCS/PRED/01/Sa

    nthabommali/005

    Construction of Cyclone shelterat Kollipadu

    G.o rt No451 dt

    06.04.2010

    07.01.2013

    Completion ofGround floorPlinth level

    Completion of Ground floorPlinth level

    Construction of Cyclone Shelterat Runku

    G.o rt No451 dt

    06.04.2010

    07.01.2013

    Completion ofGround floorPlinth level

    Completion of Ground floorPlinth level

    Status of works in Vizianagaram District up to 31.03.2012

    CategoryPackages allottedunder Phase - 1

    Names of works under eachpackage

    Agreement No./ Date DHS DFCProgress up to

    31.03.2012

    Bridges

    NCRMP/ B-W/ AP/Br/ R&B/ 02/

    Puligadda/ 007

    Construction of Minor Bridge atKm. 7/2 near Puligadda of Konada Ramatheertham R&B Road toKonathalapalem via Yerukonda,Pasupam, Kollayavalasa (Z.P.

    Road)

    31/2010-201 Dt.1.12.2010

    01.12.10 31.05.1293.96% of work

    completed

    NCRMP/ B-W/ AP/Br/ R&B/ 02/

    Chakaligadda / 008

    Construction of Minor Bridge atKm 15/2 near Chakaligedda of

    Konada Ramatheertham R&B roadto Konatalapalem (via) Yerukonda,

    Pasupam, Kollayavalasa (ZP

    Road)

    34/2010-2011 Dt.8.12.2010

    08.12.10 07.06.1278.76% of work

    completed

    Road (R&B)NCRMP/B-

    W/AP/RD/R&B/ 02/Konada/009

    Improvements to Road fromKonada Ramatheertham (R&B)Road to Konathalapalem (Via)

    Pasupam, Yerukonda,Kollayavalasa from Km 12/0 to

    16/5 (Km 0/0 to 4/0 i.e. up to NH-5crossing)

    33/2010-201 Dt.8.12.2010

    08.12.10 07.03.12100% of work

    completed

  • 7/31/2019 7. March MPR 2012

    11/52

    MONTHLY REPORT

    10 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in Visakhapatnam District up to 31.03.2012

    Category Packages allotted under Phase- 1Names of works

    under each

    package

    Agreement

    No. / Date

    DHS DFC Progress up to 31.03.2012

    RHB

    NCRMP/B-W/AP/RHB/PRED/03/Nakkapalli/001

    Road from Vempadu toPatimeeda

    /2010-11, Dt.11.01.2011

    11.01.11 11.01.12 Milestone is completed

    Road from R&B road toMulaparra up to Beach

    end

    /2010-11, Dt.11.01.2011

    11.01.11 27.10.11 Milestone is completed

    NCRMP/B-W/AP/RHB/PRED/03/Anandapuram/003

    Road from R&B B.PKallalu to

    Matchvanipalem

    /2010-11, Dt.10.03.2011

    10.03.11 09.12.11Milestone is completed

    NCRMP/B-W/AP/RHB/PRED/03/Paravada/004

    Road from R & B roadto Pothu Rajannapalem

    /2010-11, Dt.28.03.2011

    28.03.11 27.12.11 Milestone is completed

    Road from R & B roadto Jalaripeta

    /2010-11, Dt.28.03.2011

    28.03.22 28.12.11 Milestone is completed

    NCRMP/B-W/AP/RHB/PRED/03/Rambilli/006Road from R & B road

    to Venkayyapalem/2010-11, Dt.11.01.2011

    11.01.11 11.10.11 Milestone is completed

    NCRMP/B-W/AP/RHB/PRED/03/Atchutapuram/007

    Road from R&B road toAva- Somavaram

    /2011-12, Dt.27.04.2011

    27.04.11 26.01.12 Milestone is completed

    Road from R&B Roadto Avarajam

    /2011-12, Dt.27.04.2011

    27.04.11 26.01.12 Milestone is completed

  • 7/31/2019 7. March MPR 2012

    12/52

    MONTHLY REPORT

    11 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in Visakhapatnam District up to 31.03.2012

    CategoryPackages allotted under

    Phase - 1Names of works under each

    packageAgreement No. /

    DateDHS DFC

    Progress upto

    31.03.2012

    RCS

    NCRMP/B-W/AP/RCS/PRED/03/Anandapuram/001

    Road from NH-5 toRamarayadupalem

    /2010-11, Dt. 15.09.2011 15.09.11 14.06.12

    RoadFurniture &Shoulderwork is inprogress

    NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002

    Road from R&B road toKrishnampalem

    /2010-11, Dt. 15.09.2011 15.09.11 14.09.12

    CD works areProgress &B.T work isCompleted

    Road from R & B road toKattubolu to Marripalem /2010-11, Dt. 15.09.2011 15.09.11 14.09.12

    CD works arein progress &

    WBM Grade-3 work is inprogress

    Road from R & B road toRajakoduru

    /2010-11, Dt. 15.09.2011 15.09.11 14.09.12

    CD Work iscompleted &B.T work iscompleted

    NCRMP/B-W/AP/RCS/PRED/03/

    Nakkapalli/003

    Road from R & B road toPedateenarla to Chinateenarla

    /2010-11, Dt. 15.09.2011 15.09.11 14.06.12

    B.T & C.Croad worksareCompleted.

    Road from Upamaka RajayyapetaR & B road to Janakayyapeta

    /2010-11, Dt. 15.09.2011 15.09.11 14.06.12

    CD works areprogress &B.T work iscompleted

  • 7/31/2019 7. March MPR 2012

    13/52

    MONTHLY REPORT

    12 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in Visakhapatnam District up to 31.03.2012

    Category Packages allotted under Phase - 1Names of works under

    each packageAgreement No.

    / Date

    Milestone Completion Dates Progress w.r.t.milestone up to

    31.03.2012First Second Third

    MPCS

    NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003

    Construction of cycloneshelter at Gajapathi

    Nagaram

    /2011-12, Dt.03.10.2011

    02.02.12 02.06.12 02.10.12Earth work is in

    progress.

    Construction of cycloneshelter at Ratnayampeta

    /2011-12, Dt.03.10.2011

    02.02.12 02.06.12 02.10.12

    Stilt Slab iscompleted & 1stFloor Columns

    work are inprogress.

    NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002

    Construction of cycloneshelter at Patimeeda

    /2011-12, Dt.03.10.2011

    02.03.12 02.08.12 02.01.13

    Foundation footingwork is completedand Columns are

    progress up tobottom level ofPlinth beam and

    FoundationRefilling work is in

    progress

    Construction of cycloneshelter at Moolaparra

    /2011-12, Dt.03.10.2011

    02.03.12 02.08.12 02.01.13

    Columns lay up tobottom of plinth

    beam or Basementwork is in

    completed & Plinthbeam PCC iscompleted.

    Construction of cycloneshelter at Bangarampeta

    /2011-12, Dt.03.10.2011

    02.03.12 02.08.12 02.01.13

    Stair case & Rampworks are in

    progress, Columnslay up to Roof leveland Form work for

    Stilt Slab is inprogress.

  • 7/31/2019 7. March MPR 2012

    14/52

    MONTHLY REPORT

    13 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-W/AP/MPCS/PRED/03/Rambillii/004Construction of cyclone

    shelter atVenkayyapalem

    /2011-12, Dt.03.10.2011

    02.01.12 02.04.12 02.07.12

    Earth work inprogress, Workstopped due tofinalization of

    foundation designs.

    NCRMP/B-W/AP/MPCS/PRED/03/Parawada/001Construction of cyclone

    shelter atTikkavanipalem

    /2011-12, Dt.07.10.2011

    06.01.12 06.04.12 06.07.12

    E/W foundationexcavation is

    completed & Dueto site problem

    work is stopped.

    Status of works in East Godavari District up to 31.03.2012

    Category Packages allotted under Phase - INames of works

    under each

    package

    AgreementNo. / Date

    Mile stonesRemarks

    First Second Third

    RHB (2 )RCS (8)

    MPCS (3)

    NCRMP/B-W/AP/RHB/PRED/04/Katrenikona/003

    Road from PR roadsto Dasarivanipeta and

    to Cyclone Shelter

    /2011-12Dt:27.04.2011

    30-11-2011 30-11-2011 20-01-2012 Completed.

    NCRMP/B-W /RCS/PRED/04/Karapa/001Approach Road tocyclone Shelter at

    Adavipudi

    2011-12Dt:20.05.2011

    30-11-2011 31-10-2011 31-01-2012 Completed.

    NCRMP/B-W/AP/RHB/PRED/04/Karapa/001/

    Road fromGurajanapalli to

    Bandulavaripalem

    2011-12Dt:27.04.2011

    30-09-2011 31-10-2011 31-01-2012 Completed.

    NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

    Road from R&B Roadto P.Chodipallipeta CS

    2011-12Dt:07.09.2011

    3 months 3 months 3 months55% completed ,WBM

    Gr-III completed

    MONTHLY REPORT

  • 7/31/2019 7. March MPR 2012

    15/52

    MONTHLY REPORT

    14 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

    Road from R&B Roadto K.Chodipallipeta CS

    /2011-12Dt:07.09.2011

    3 months 3 months 3 months55% completed , WBM

    Gr

    NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

    Road from R&B Roadto Hukumpeta CS

    /2011-12Dt:07.09.2011

    3 months 3 months 3 months55% completed , WBM

    Gr

    NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

    Road from R&B Roadto Gaddipeta CS

    /2011-12Dt:07.09.2011

    3 months 3 months 3 months55% completed , WBM

    Gr

    NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

    Road from R&B Roadto Danavaipeta CS

    /2011-12Dt:07.09.2011

    3 months 3 months 3 months55% completed , WBM

    Gr

    NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004/

    Road from R&B Roadto G.Musalayyapeta

    CS2011-12

    Dt:07.09.20113 months 3 months 3 months To be started

    NCRMP/B-W/AP/RCS/PRED/04/Uppalaguptam/003

    Road from R&B Roadto Chinaraghavulapeta

    Cyclone Shelter

    /2011-12 Dt:23.09.2011

    3 months/22.11.2011

    3 months22.06.2011

    ----------- To be started

    NCRMP/B-W/AP/MPCS/PRED/04/Uppalaguptam/002

    Construction ofCyclone Shelter at

    Pedaraghavulapeta ofUppalaguptam Mandal

    E.G.Dt.

    /2011-12Dt:17.10.2011

    3 months16.01.2012

    3 months16.04.2012

    3 months16.07.2012

    11% completed, RCCRaft Completed and

    RCC Pedestals Workis in Progress

    NCRMP/B-W/AP/MPCS/PRED/04/Thondangi/004

    Construction ofCyclone Shelter atLaxamanudupadu

    inThondangi

    /2011-12Dt:07.09.2011

    11% completed, RCCRaft Completed and

    RCC Pedestals Workis in Progress

    NCRMP/B-W/AP/MPCS/PRED/04/Thondangi/004

    Construction ofCyclone Shelter at

    Avulamanda

    /2011-12Dt:07.09.2011

    5% completed, PCCwork Completed

    MONTHLY REPORT

  • 7/31/2019 7. March MPR 2012

    16/52

    MONTHLY REPORT

    15 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in West Godavari District up to 31.03.2012

    CategoryPackages allotted under Phase

    - 1Names of works under

    each packageAgreementNo. / Date

    Milestone Completion Dates Progress w.r.t.milestone up to

    31.03.2012Remarks

    First Second Third

    RHB

    Mogalthuru Mandal NCRMP

    W.G.Dist

    Road from NH 214 A atRanga Statue center to

    Harijanawada of Kalipatnam(E) (Mogalthuru Mandal

    W.G.Dist.)

    16 /2011-12

    Dt.27.04.2011

    27/4/2011to

    22/9/2011

    23/9/2011to

    24/2/2012

    25/2/2012to

    26/7/2012

    54.75%

    GSB, G-II & CC Pavement

    Completed.

    Gr-III is in Progress.

    R&B road at PanchayatOffice to Pulaparthivarithota

    via Badava(Mogalthuru Mandal

    W.G.Dist.)

    58.38%

    GSB, G-II & CC Pavement

    Completed.

    Gr-III is in Progress.

    Mogalthuru Vempa R&BRoad at Uchintha Kalava

    Bridge to Gogulamma

    Harijanapeta (MogalthuruMandal W.G.Dist.)

    75.34%

    GSB, G-II, Gr-III & CC

    Pavement Completed.

    Shoulders work is in

    Progress.

    From Narsapur MogalthurR&B road to Dayadaldaspeta

    via Venkateswara Swamytemple (Mogalthuru Mandal

    W.G.Dist.)

    73.50%

    GSB, CC Pavement

    Completed.

    Shoulders work is in

    Progress.

    Road from NH 214 A road toHarijanapeta of Kothota

    (Mogalthuru MandalW.G.Dist.)

    27/4/2011to

    22/9/2011

    23/9/2011to

    24/2/2012

    25/2/2012to

    26/7/201299.2% CC Road Completed.

    Narsapur Mandal W.G.Dist.

    R&B road to Indira Nagar(via) Pochamma temple

    (Narsapur Mandal W.G.Dist.)21 /2011-12Dt.09.05.2011

    09/05/2011to

    04/09/2011

    05/09/2011to

    06/01/2012

    07/01/2011to

    08/5/2012

    0% ..........

    Road from R&B road toPedalanka (Narsapur Mandal

    W.G.Dist.)34.75%

    G-II, Gr-III Completed.

    CC Pavement & Culverts

    work

    Is in Progress.

    MONTHLY REPORT

  • 7/31/2019 7. March MPR 2012

    17/52

    MONTHLY REPORT

    16 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in Krishna District up to 31.03.2012

    Category Packages allotted under Phase - 1Names of works under each

    packageAgreement No. /

    DateDHS DFC

    Progress up to31.03.2012

    RHB

    NCRMP/B-W/AP/RHB/PRED/06/Machipatnam/001

    Road connecting R&B roadthrough Gantalammapalem

    /2011-12Dt.27.4.2011

    27.04.11 26.01.2012CD works,GSB,Gr-II,Gr-III,BT completed

    NCRMP/B-W/AP/RHB/PRED/06/Machipatnam/002

    Road from R & B Road to B.VThota

    /2011-12Dt.27.4.2011

    27.04.11 26.01.2012

    CD works,GSB,Gr-II,Gr-III,BT completed

    Road from Potlapalem Z.P roadto Chikativanipalem

    CD works,GSB,Gr-II,Gr-III,BT completed

    NCRMP/B-W/AP/RHB/PRED/06/Kruthivennu/003

    Road from Intheru R&B Road toRangaraopet

    /2011-12Dt.27.4.2011

    27.04.11 26.01.2012

    CD works,GSB,Gr-II,Gr-III,BT completed

    Road from R&B road to CycloneShelter at Chandala

    CD works,GSB,Gr-II,Gr-III,BT completed

    Road from LB Cheria CCroad to Chillapalemm of LBCheria (Narsapur Mandal

    W.G.Dist.

    28.66%

    GSB, G-II, Gr-III Completed.

    CC Pavement & Culvert

    work

    Is in Progress.

    Kalla Mandal W.G.Dist.

    From A-U R&B Road toSatyanarayanapuram (Kalla

    Mandal W.G.Dist.)25 /2011-12Dt.26.05.2011

    26/5/2011To

    20/8/2011

    20/8/2011to

    21/11/2011

    22/11/2011To

    23/2/2012

    100% Completed.

    From A-U R&B Road toMekaladibba (Kalla Mandal

    W.G.Dist.)100% Completed.

    MONTHLY REPORT

  • 7/31/2019 7. March MPR 2012

    18/52

    17 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in Krishna Districts up to 31.03.2012

    Category Packages allotted under Phase - 1Names of works

    under eachpackage

    AgreementNo. / Date

    Milestone Completion Dates Progress

    w.r.t.milestone

    up to31.03.2012

    RemarksFirst Second Third

    RCSNCRMP/B-W

    /AP/RCS/PRED/06/Machipatnam/001

    Road fromBhogireddipalli R&B

    Road toRamakhandam

    /2011-12/Dt.02.09.2011

    01.12.2011 01.03.12 01.06.12 13.20% GSB workcompleted

    Road from R&BRoad Chinnapuram

    to Gundupalem

    /2011-12/27.04.2011

    01.12.2011 01.03.12 01.06.12

    12.14%GSB workcompleted.

    Road fromPotlapalem Z.P

    road to Pothepalli.

    /2011-12/Dt.02.09.2011

    01.12.2011 01.03.12 01.06.1231.68%

    GSB, Gr-IIcompleted

    MONTHLY REPORT

  • 7/31/2019 7. March MPR 2012

    19/52

    18 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in GUNTUR District up to 31.03.2012

    CategoryPackages allotted under

    Phase - 1Names of works under each package

    Agreement No./Date

    DHS DFCProgress up to

    31.03.2012

    RHB

    NCRMP/B-W/AP/RHB/PRED/07/KARLAPAL

    EM/001

    R/f Ganapavaram R&BRoad t o Kesavapuri ST colony 7/2011-201227.04.2011

    27.04.11 26.01.2012 Completed.

    NCRMP/B-W/AP/PRED/07/Nagaram/002

    R/f R&B Road to Mohammad Alipalem

    8/2011-201227.04.2011

    27.04.11 26.4.2012

    WBM Gr -IIImaterial collection

    is in progress.

    R/f R&B Road to Katuivaripalem.CC Road, GSB is in

    Progress.

    Bridges

    NCRMP/B-W/AP/Br/R&B/07/Bapatla/010

    Reconstruction of High level Bridge @Km5/2 of

    Bapatla-Suryalanka Road across Perali drain inGuntur

    79/2010-20111.12.2010

    01.12.10 31.5.2012

    Super structer is inprogress. 9 slabscompleted. Work

    Completed value is255.00 Lakhs.

    NCRMP/B-W/AP/Br/R&B/07/Bapatla/011

    Reconstruction of High level Bridge @Km2/4 ofBapatla-Pandurangapuram Road across Perali

    drain in Guntur78/2010-2011

    1.12.201001.12.10 31.5.2012

    10 slabs WithRailing completed,

    Approaches,Wearing Coat work

    is in Progress.Work completedvalue is 295.00

    Lakhs

    MONTHLY REPORT

  • 7/31/2019 7. March MPR 2012

    20/52

    19 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in GUNTUR District up to 31.03.2012

    Category Packages allotted under Phase - 1Names of works under each

    package

    Agreement No. /

    DateDHS DFC Progress up to 31.03.2012

    RCS

    NCRMP/B-W/AP/RCS/PRED/07/P

    Palem/001

    Road from R&B Road to

    Mandevaripalem

    /2010-11

    Dt.01.11.201101.11.11 31.07.2012 Work yet to be s tarted

    Road from R&B Road Alluru to

    Yadavapalem

    /2010-11

    Dt.01.11.201101.11.11 31.07.2012

    Work yet to be started

    NCRMP/B-

    W/AP/RCS/PRED/07/KarlaPalem/002

    Road from Ganapavaram R & B

    road to Pedamarpuvaripalem

    /2010-11

    Dt.01.11.201101.11.11 31.10.2012

    Work yet to be started

    Road from R & B Road to

    Chinapuluguvaripalem

    /2010-11

    Dt.01.11.2011 01.11.11 31.10.2011 Work yet to be started

    Road from R & B road to

    Yaramvaripalem

    /2010-11

    Dt.01.11.201101.11.11 31.10.2011

    CC Road work is Completed,Shoulders, and GSB is in

    progress.

    Road from R & B road to

    Pedagollapalem Cyclone Shelter

    /2010-11

    Dt.01.11.201101.11.11 31.10.201 CC Road work is Completed,

    Shoulder work is in progress.

    Pedagollapalem PR Road to

    Bonthagorlapalem

    /2010-11

    Dt.01.11.201101.11.11 31.10.201

    Work yet to be started

    NCRMP/B-

    W/AP/RCS/PRED/07/Nizampatnam/003

    Road from R&B Road to

    Gurunadhanagar

    /2010-11 Dt.

    17.10.201117.10.11 16.07.12 Work to be Grounded

    Road from R&B Road to Adavala

    H/O Bavajipalem

    /2010-11 Dt.

    17.10.201117.10.11 16.07.12 CC Road work is Completed,

    Shoulder work yetobe start.

    MONTHLY REPORT

  • 7/31/2019 7. March MPR 2012

    21/52

    20 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Road from R&B Road to

    Atlavaripalem

    /2010-11 Dt.

    17.10.201117.10.11 16.07.12

    CC Road work is Completed.

    NCRMP/B-W/AP/RCS/PRED/07/Bapatla/004

    Road from R&B Road to

    Hanumanthanagar 2010-11

    Dt13.10.201113.10.11 12.07.2012

    CC Road work is Completed,

    Shoulder work is in progress.

    Road from R & B road to

    AdarsanagarCC Road work is Completed,Shoulder work is in progress.

    Status of works in Prakasam District up to 31.03.2012

    CategoryPackages allottedunder Phase - 1

    Names of works

    under eachpackage

    Agreement No. /Date

    Milestone completion dates

    Progress up to31.03.2012 Remarks

    First Second Third

    BRIDGESNCRMP/B-

    W/AP/Br/R&B/08/Kanaparthy/012

    Construction ofHigh level Bridge at

    Km 16/10 ofNaguluppalapadu Kanaparthy road inPrakasam District

    76/2010-11 Dated1/12/2010

    5/31/2011Completion

    up to silllevel

    12/31/2011Completion upto below deck

    slab

    5/31/2012Completion of

    entire workincluding

    approaches

    Slab S4 and S5completed.

    Reached Milestone-III

    RHBNCRMP/B-

    W/AP/RHB/PRED/08/S.Konda/001

    Road from PakalaZP Road to

    Aulavaripalem

    Cyclone shelter

    NCRMP/B-W/AP/RHB/PRED/0

    8/S.Konda/001

    Dated 25.04.2011 8/24/2011Earth work,CD work,

    GSB

    12/24/2011WBM, Grade II

    & III

    4/24/2012 BT,Shoulders &road furniture

    CC RoadCompleted.

    Shoulders work in

    progress

    Reached Milestone-III

    Road from R&BRoad to

    Somarajupalli

    NCRMP/B-W/AP/RHB/PRED/0

    8/S.Konda/001Dated 25.04.2011

    BT Completed fromKM 1/375 to 2/146.

    WBM-Grade-IIIwork is in progress

    for the balanceportion

    Reached Milestone-III

    MONTHLY REPORT

  • 7/31/2019 7. March MPR 2012

    22/52

    21 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Road from R&Broad to

    Narravaripalem

    NCRMP/B-W/AP/RHB/PRED/0

    8/S.Konda/001Dated 25.04.2011

    Earth workCompleted & CD

    work is in progress.

    Reached Milestone-III

    NCRMP/B-W/AP/RHB/PRED/0

    8/S.Konda/002

    Road from NH5 toMulaguntapadu

    NCRMP/B-W/AP/RHB/PRED/0

    8/S.Konda/002dated 10/02/2011 6/9/2011

    Earth work,CD work,

    GSB

    10/9/2011WBM, Grade II

    & III

    2/9/2012 BT,Shoulders &road furniture

    WBM-Grade-IIwork is completed.

    Not Reached asper Mile stone-III (Awaiting forEOT Proposal)

    Road from R&Broad to

    Chalivendradibba

    NCRMP/B-W/AP/RHB/PRED/0

    8/S.Konda/002dated -10/02/2011

    CC work iscompleted from KM

    0/0 to KM 0/270

    Not Reached asper Mile stone-III (Awaiting forEOT Proposal)

    NCRMP/B-W/AP/RHB/PRED/0

    8/S.Konda/002

    Road from PakalaR&B road to

    Mosanaladinne

    NCRMP/B-W/AP/RHB/PRED/0

    8/S.Konda/002dated 10/02/2011

    6/9/2011Earth work,CD work,

    GSB

    10/9/2011WBM, Grade II

    & III

    2/9/2012 BT,Shoulders &road furniture

    WBM-Grade-IImaterial collection

    is in progress

    Not Reached asper Mile stone-III (Awaiting forEOT Proposal)

    Road from R&Broad to Binginapalli

    HarijanawadaCyclone Shelter

    NCRMP/B-W/AP/RHB/PRED/0

    8/S.Konda/002dated 10/02/2011

    Nil

    Not Reached asper Mile stone-III (Awaiting forEOT Proposal)

    NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/003

    Road from R&BRoad Allur to M T

    Raju colony

    NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/003Dated 27/04/2011

    8/26/2011Earth work,CD work,

    GSB

    12/26/2011WBM, Grade II

    & III

    4/26/2012 BT,Shoulders &road furniture

    BT Completed,Shoulders work is

    in progress

    Reached Milestone-III

    NCRMP/B-W/AP/RHB/PRED/0

    Road from KEMR&B Road to

    NCRMP/B-W/AP/RHB/PRED/0

    9/26/2011Earth work,

    2/26/2012WBM, Grade II

    7/26/2012 BT,Shoulders &

    BT completed.CDwork completed.CC

    Reached Milestone-III

    MONTHLY REPORT

  • 7/31/2019 7. March MPR 2012

    23/52

    22 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    8/Kothapatnam/004 Sankuvarigunta 8/Kothapatnam/004Dated 27/04/2011

    CD work,GSB

    & III road furniture road workcompleted

    Road from KEM R& B Road to

    Pullareddypalem

    NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/004Dated 27/04/2011

    BT Completed,Shoulders work is

    in progress

    Reached Milestone-III

    NCRMP/B-W/AP/RHB/PRED/0

    8/Ulavapadu/07

    Road from MCRoad to

    SubbarayaduSatram

    NCRMP/B-W/AP/RHB/PRED/0

    8/Ulavapadu/07dated 27/04/2011

    8/26/2011Earth work,CD work,

    GSB

    12/26/2011WBM, Grade II

    & III

    4/26/2012 BT,Shoulders &road furniture

    WBM-Grade-IIICompleted

    Reached Milestone-III

    NCRMP/B-W/AP/RHB/PRED/0

    8/Ulavapadu/08

    Road from R&Broad Tettu to

    Ramayapatnam

    NCRMP/B-W/AP/RHB/PRED/0

    8/Ulavapadu/08

    dated 27/04/2011

    8/26/2011Earth work,CD work,

    GSB

    12/26/2011WBM, Grade II

    & III

    4/26/2012 BT,Shoulders &

    road furniture

    CC road and BTlying completed,

    shoulders

    progress.

    Reached Milestone-III

    NCRMP/B-W/AP/RHB/PRED/0

    8/Tangutur/09

    Road from R&Broad Pellur toVasepallipadu

    NCRMP/B-W/AP/RHB/PRED/0

    8/Tangutur/09dated 16/03/2011

    7/15/2011Earth work,CD work,

    GSB

    11/15/2011WBM, Grade II

    & III

    3/15/2012 BT,Shoulders &road furniture

    BT Completed,Shoulders work is

    in progress

    Reached Milestone-III

    NCRMP/B-W/AP/RHB/PRED/0

    8/Tangutur/10

    Road from R&Broad to Kesupalem

    NCRMP/B-W/AP/RHB/PRED/0

    8/Tangutur/10dated 19/04/2011

    7/18/2011Earth work,CD work,

    GSB

    10/18/2011WBM, Grade II

    & II

    1/18/2012 BT,Shoulders &road furniture

    BT Completed,Shoulders work

    Completed

    Reached Milestone-III

    RCSNCRMP/B-

    W/AP/RCS/PRED/08/Vetapalem/001

    Road from R&B

    road toVijayanagaramcolony cyclone

    shelter

    NCRMP/B-W/AP/RCS/PRED/0

    8/Vetapalem/001dated 2011/12

    dated 30.09.2011

    1/29/2012Earth work,

    GSB

    5/29/2012shoulders, Gr-

    III

    9/29/2012 BT,CC pavement

    and roadfurniture

    cc road completed

    & BT roadcompleted&

    shoulders progress

    Reached Milestone-III

    Road from NH roadto

    Challareddypalem

    360 meters BTcompleted WBM-Grade-III work in

    Progress.

    Reached Milestone-III

    MONTHLY REPORT

  • 7/31/2019 7. March MPR 2012

    24/52

    23 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Road from R&Broad to jeevaraksh

    nagar colonycyclone shelter

    C.C.completed.Shoulders Progress.

    Reached Milestone-III

    Road from R&Broad to Ramnagar

    colony cycloneshelter

    C.C.completed.Shoulders Progress.

    Reached Milestone-III

    Road from R&Broad to cyclone

    shelter atMankenavaripalem

    Not Grounded

    NCRMP/B-W/AP/RCS/PRED/0

    8/Chirala/002

    Road from R&BRoad to

    Keertivaripalemcyclone shelter NCRMP/B-

    W/AP/RCS/PRED/08/Chirala/002

    dated 27.08.2011

    C.C.completed.Sho

    ulders Progress.

    Reached Mile

    stone-III

    Road from R&BRoad to Devinutulacyclone shelter ofChirala mandal in

    Prakasham district.

    C.C.completed.Shoulders Progress.

    Reached Milestone-III

    MPCSNCRMP/B-

    W/APMPCS/PRED/08/Ulavapadu/001

    Chakicharla cycloneshelter in

    Ulavapadu mandalPrakasam district

    NCRMP/B-W/AP/MPCS/PRED/08/Ulavapadu/001

    24.11.2011All items upto stilt floor

    slabincluding

    ramp, staircase

    foundations,columns,bea

    ms,pccflooring etc.,

    24.02.2012 Allitems up to

    second floorslab includingfirst floor, andin 2nd floor

    including staircase, columns

    etc.,

    24.05.2012Head room,plastering,

    flooring, watersupply

    arrangements,sanitary fitting,

    electricalitems,

    compoundwall, cc

    pavement.Earthenmounds(raised

    Terrace roof slabcompleted. Brick

    work is in progressin ground floor.

    Reached Milestone-III

    MONTHLY REPORT

  • 7/31/2019 7. March MPR 2012

    25/52

    24 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    portion), waterharvesting,septic tank,slump and

    soak pit.etc.

    NCRMP/B-W/APMPCS/PRED/

    08/NG Padu/003

    Kanaparthy cycloneshelter in

    Naguluppapadumandal Prakasam

    district

    NCRMP/B-W/AP/MPCS/PRED/08/NG Padu/003

    23.11.2011All items upto stilt floor

    slabincluding

    ramp, staircase

    foundations,columns,bea

    ms,pccflooring etc.,

    23.02.2012 Allitems up to

    first floor slaband head

    room slab in 2nd floor

    including staircase, columns

    etc.,

    23.05.2012plastering,

    flooring, watersupply

    arrangements,sanitary fitting,

    electricalitems,

    compoundwall, cc

    pavement.Earthenmounds

    (raisedportion), water

    harvesting,septic tank,slump and

    soak pit.etc.

    Stilt floor roof slabcompleted. InGround floor

    Columns work is inprogress

    As per Milestone-II, NotCompleted

    Status of works in Nellore District up to 31.03.2012

    (RCS)

    Package Number Name of Work Milestone1 Milestone2 Milestone3 Remarks

    Progress upto

    31.03.2012

    NCRMP/B-W/AP/09MUTHUKUR/RC

    S/002

    Road from R&B Roadkappaladoruvu to bandla

    palem H.wada

    3Months: EarthWork, Pipe

    Culverts, GSB

    6 Months: WBMGrII,GrII,CC

    Pavement andShoulders

    9 Months: BTCC road and

    Road Furniture

    COMPLETED,ROAD FURNITUREIS IN PROGRESS

    94% of workcompleted

    NCRMP/B-W/AP/09/D.V.SATRAM/R

    CS/008

    Road from R&B road toSullurpeta Mallam to

    berjengalapalli cyclone shelter

    3Months: EarthWork, Pipe

    Culverts, GSB

    6 Months: WBMGrII, GrII Shouldersand CC Pavement

    9 Months: BT,CC Pavement

    and RoadFurniture

    BT COMPLETED94 % of work

    completed

    MONTHLY REPORT

  • 7/31/2019 7. March MPR 2012

    26/52

    25 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-W/AP/09T.P.GUDUR/RC

    S/005

    Road from7/2 M.C Road tovenkannapalem pattapupalem

    BT COMPLETED96 % of work

    completed

    NCRMP/B-

    W/AP/09chillakur/RCS/004

    Road from KatuivaripalemR&B road to vellapalm

    3Months: Earth

    Work,CDWorks,GSB

    6 Months: WBM

    GrII, GrII andShoulders

    9 Months: BT,CC Pavement

    and RoadFurniture

    WBM Gr -III is inprogress

    76 % of workcompleted

    NCRMP/B-W/AP/09kota/RCS /001

    road from R&B road to A.SPURAM 3Months: Earth

    Work, PipeCulverts, GSB

    6 Months: WBMGrII, GrII and

    Shoulders

    9 Months: BT,CC Pavement

    and RoadFurniture

    COMPLETED,ROAD FURNITUREIS IN PROGRESS

    97 % of workcompleted

    Road from GD Road toVavillapalem

    BT Completed96 % of work

    completed

    NCRMP/B-

    W/AP/RCS/PRED/09/KAVALI/007

    Road from Kotha Satram R&Bto Indiranagar (via)

    Thumalapenta palam,

    Patharavadu palam, Ramudupalam, Karaduvari palam

    &Sreeramapuram in SPSRNellore District.

    4Months: Earth

    Work, PipeCulverts, GSB

    4 Months: WBMGrII, GrII ,

    Shoulders and CCPavement

    4 Months: BT,CC Pavement

    and RoadFurniture

    BT COMPLETED

    78 % of work

    completed

    NCRMP/B-W/AP/RCS/PRED/09/KA

    VALI/006

    Road Connecting R&B Roadthrough Voter Village in SPSR

    Nellore District.

    4 Months: EarthWork, PipeCulverts,

    GSB

    4 Months: WBMGrII, GrII ,

    Shoulders and CCPavement

    4 Months: BT,CC Pavement

    and RoadFurniture

    GSB AND CDWORKS IS IN

    progress

    16% of workcompleted

    Status of works in Nellore District up to 31.03.2012

    RHBNCRMP/B-

    W/AP/RHB/PRED/09RHB/KAVALI/004

    Road from5/8 of

    Chennayapalem Road toGummadi bandla

    5Months:Earthwork, CD

    Works,ccpavement and GSB

    10 Months: WBMGrII,GrII andShoulders

    15 Months: BTand RoadFurniture

    BT IS completed

    87 % of

    work iscompleted

    Road from PedattapupalemR&B road to Chennayapalem

    H.wada

    WBM Gr -III isCompleted

    58 % ofwork is

    completed

    MONTHLY REPORT

  • 7/31/2019 7. March MPR 2012

    27/52

    26 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Road from K.T R&B Road toAlliguntapalem

    BT IS Completed,shoulders is in

    progress

    85 % ofwork is

    completed

    NCRMP/B-W/AP/RHB/PRED/09BOGOL

    U/RHB/002

    Road from 1/6 of ZuvvaladinneR&B Road to Tellagunta KM to

    2/720

    3Months: EarthWork, Pipe

    Culverts, GSB

    6 Months: WBMGrII, GrII and

    Shoulders

    9 Months: BTand RoadFurniture

    BT IS Completed,shoulders is in

    progress

    97 % ofwork is

    completed

    NCRMP/B-W/AP/RHB/PRED/09BOGOL

    O/RHB/001

    1. Road from NH5 toSambasivapuram

    5Months: EarthWork, Pipe

    Culverts, GSB

    10 Months: WBMGrII, GrII and

    Shoulders

    15 Months: BTand RoadFurniture

    BT IS Completed,shoulders is in

    progress

    90 % ofwork is

    completed

    Road from 9/6 of JuvvaladinneR&B Road to 11/0 of

    Juvvaladinne R&B Road Via

    Vekateshpalem

    BT IS Completed,shoulders is in

    progress

    91 % ofwork is

    completed!

    NCRMP/B-W/AP/RHB/PRED/09/VIDAV

    ALURU/005

    1)Road from kt R&B ROAD TOALLAGANIPADU to Vavilla

    5Months: EarthWork, Pipe

    Culverts, GSB

    10 Months: WBMGrII, GrII and

    Shoulders

    15 Months: BTand RoadFurniture

    construction ofstructures iscompleted,ccPavement is

    Completed.GSB isin Progress

    40 % ofwork is

    completed!

    Road from R&B roadKancharapalem HW to

    Alaganipadu.

    earth work inembankment is in

    progress

    55 % ofwork is

    completed

    NCRMP/B-W/AP/RHB/PRED/09V.CHAL

    EM/RHB/007

    ROAD FROM SUVEPALLI-PUDIPARTHI ROAD TO

    SRIKANTH COLONY 4Months: EarthWork, Pipe

    Culverts, GSB

    8 Months: WBMGrII, GrII and

    Shoulders

    12 Months: BTand RoadFurniture

    COMPLETED,ROAD FURNITURE ISIN PROGRESS

    95 % ofwork is

    completed!

    providing BT Surface to theroad from R&B road to Edagali

    Kandriga

    COMPLETED,ROAD FURNITURE ISIN PROGRESS

    97 % ofwork is

    completed

    MONTHLY REPORT

    C lt S i f Thi d P t Q lit A dit (TPQA) f N ti l C l Ri k Miti ti P j t (NCRMP)

  • 7/31/2019 7. March MPR 2012

    28/52

    27 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-W/AP/RHB/PRED/09CHITTA

    MURU/003

    Road from R&B Road toMuttembake Via Pittuvanipalli

    5Months: EarthWork, Pipe

    Culverts, GSB

    10 Months: WBMGrII, GrII and

    Shoulders

    15 Months: BTand Road

    Furniture

    WBM Gr -III,GR-IIIS IN PROGRESS

    27 % ofwork is

    completed

    Road from R&B Chittamur toSoma Samudram

    WBM Gr-II is inProgress

    29 % ofwork is

    completed

    NCRMP/B-W/AP/09/MUTHUKUR/RHB/

    006

    Road from R&B roadtopatuvarikandriga

    3Months: EarthWork, Pipe

    Culverts, GSB

    6 Months: WBMGrII,GrII,CC

    Pavement andShoulders

    9 Months: BTand RoadFurniture

    BT IS completed,ccPavement

    COMPLETED,ROAD FURNITURE ISIN PROGRESS

    99 % ofwork is

    completed

    NCRMP/B-W/AP/09Allur/RHB/009

    Road from R&Broad alluru toGalidibbalu (via)Chukavani

    dibba

    5Months: Earth

    Work, PipeCulverts, GSB

    10 Months: WBM

    GrII, GrII andShoulders

    15 Months: BT

    and RoadFurniture

    GSB completed,cc

    works in progress,Gr-III

    COMPLETED

    58 % ofwork is

    completed

    NCRMP/B-W/AP/RHB/PRED/009/T.P.G

    UDUR/012

    Ring Road to TP Gudur-Salipeta R & B Road via CS

    Puram and Mandapam Village3Months: Earth

    Work, PipeCulverts, GSB

    6 Months: WBMGrII,GrII,CC

    Pavement andShoulders

    9 Months: BTand RoadFurniture

    WBM Gr -III, IS INPROGRESS

    71 % ofwork is

    completed

    Road from R & B Road C SPuram to Sivaramapuram

    WBM Gr -III is inprogress

    73 % ofwork is

    completed

    MONTHLY REPORT

  • 7/31/2019 7. March MPR 2012

    29/52

    28 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    6.0 District wise status of tests conducted by TPQA:

    Apart from monitoring the tests being conducted by the implementation team (contractors & Line department) at

    various stages, the Third party Quality Audit team also conducted tests to confirm its compliance with the standards.

    These tests are carried out in the site itself and in some cases samples are collected and testing done in outside

    laboratories. The details of tests conducted in the field till end of September 2011 are presented.

    Summary of QC Tests - Up to 31.3.2012

    S.No. DistrictTotal No. Tests

    Done

    Total no. of Tests

    Passed Failed

    1 Srikakulam 526 526 0

    2 Vizianagaram 316 316 0

    3 Visakhapatnam 1193 1184 9

    4 East Godavari 582 582 0

    5 West Godavari 177 177 0

    6 Krishna 42 42 0

    7 Guntur 291 287 4

    8 Prakasham 1540 1540 0

    9 Nellore 643 642 1

    Total 5310 5296 14

    The works in West Godavari and Krishna Districts were just started

    MONTHLY REPORT

  • 7/31/2019 7. March MPR 2012

    30/52

    29 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    7.0 Details of Quality Control Audit Reports Submitted During this Month:

    Package Number Name of Work District

    NCRMP/B-

    W/AP/RCS/PRED/04/KARAPA/001

    Road from approach road to cyclone shelter

    at Adivipudi in E.G.Dt.

    East Godavari

    NCRMP/B-

    W/AP/RHB/PRED/04/KARAPA/001

    Road from GURAJANAPALLI to

    BANDULAVARIPALEM in East Godavari

    District.

    East Godavari

    NCRMP/B-

    W/AP/RCS/PRED/04/THONDANGI/004

    Road from R&B Road to Danavaipeta East Godavari

    NCRMP/B-

    W/AP/RCS/PRED/04/THONDANGI/004

    Road from R&B Road to Gaddipeta of

    Thondangi Mandal in East Godavari District

    East Godavari

    NCRMP/B-

    W/AP/RCS/PRED/04/THONDANGI/004

    Road from R&B Road to Hukumpeta

    Cyclone Shelter

    East Godavari

    NCRMP/B-W/AP/RCS/PRED/04/THONDANGI/004

    Road from R&B Road to K.Chodipallipeta East Godavari

    NCRMP/B-

    W/AP/RCS/PRED/04/THONDANGI/004

    Road from R&B Road to P.Chodipallipeta East Godavari

    NCRMP/B-W/AP/RHB/

    PRED/05/Narsapur/002

    Road from LB Cheria CC road to

    Chillapalemm of LB Cheria of Narsapur

    Mandal in West Godavari District.

    West Godavari

    NCRMP/B-W/AP/RHB/

    PRED/05/Narsapur/002

    Road from R&B road to Pedalanka of

    Narsapur Mandal in West Godavari District.

    West Godavari

    NCRMP/B-

    W/AP/RHB/PRED/05/MOGALTHURU/001

    Road from NH 214 A road to Harijanawada

    of Kothota of Mogalthuru Mandal in West

    Godavari District.

    West Godavari

    MONTHLY REPORT

  • 7/31/2019 7. March MPR 2012

    31/52

    30 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-

    W/AP/RHB/PRED/05/MOGALTHURU/001

    Road from NH 214 A at Ranga statue

    center to Harjanawada of Kalipatnam (E) of

    Mogalthuru Mandal in West Godavari

    District.

    West Godavari

    NCRMP/B-

    W/AP/RHB/PRED/05/MOGALTHURU/001

    R&B Road at Panchayat office to

    Pulaparthivarithota via Badava of

    Mogalthuru Mandal in West Godavari

    District.

    West Godavari

    NCRMP/B-

    W/AP/RHB/PRED/05/MOGALTHURU/001

    Mogaltur Vempa R&B Road at Uchintha

    kalava Bridge to Gogulamma Harijanapeta

    of Mogalthuru Mandal in West Godavari

    District.

    West Godavari

    NCRMP/B-W/AP/RD/R&B/02/Konada/009 Improvements to Road from Konada

    Ramatheertham (R&B) Road to

    Konathalapalem (Via) Pasupam,

    Yerukonda, Kollayavalsa from Km 12/0 to

    16/5 (Km 0/0 to 4/0 i.e. up to NH-5

    crossing) in Vizianagaram District, Andhra

    Pradesh.

    Vijayanagaram

    NCRMP/B-

    W/AP/MPCS/PRED/03/Nakkapalli/002

    Construction of cyclone shelter at

    Bangarampeta in Nakkapalli

    Vishakhapatnam

    NCRMP/B-

    W/AP/MPCS/PRED/03/Payakaraopeta/003

    Construction of cyclone shelter at

    Ratnayampeta in Payakaraopeta

    Vishakhapatnam

    NCRMP/B-

    W/AP/RCS/PRED/03/Nakkapalli/003

    Road from R&B road to Pedatheernala to

    Chinatheernala

    Vishakhapatnam

    8.0 Details of Environmental and Social Reports Submitted During this Month:

    Package Number Name of Work District

    NCRMP/B-

    W/AP/RHB/PRED/06/Machilipatnam/002

    Road from R&B Road to B.V.Thota Krishna

    NCRMP/B-

    W/AP/RHB/PRED/06/Kruthivennu/003

    Road from R&B Road to Cyclone Shelter of

    Chandala

    Krishna

    NCRMP/B-

    W/AP/RHB/PRED/06/Machilipatnam/002

    Road from Potalapalem Z.P.Road to

    Chikativanipalem

    Krishna

    NCRMP/B-

    W/AP/RHB/PRED/06/Machilipatnam/001

    Road connecting R&B Road through

    Gantalammapalem

    Krishna

    NCRMP/B-

    W/AP/RCS/PRED/06/Machilipatnam/001

    Road from Chinnapuram to Gundupalem Krishna

    NCRMP/B-

    W/AP/RCS/PRED/06/Machilipatnam/001

    Road from Potalapalem Z.P.Road to

    Potepalli

    Krishna

    NCRMP/B-

    W/AP/RCS/PRED/06/Machilipatnam/001

    Road from Bhogireddipalli R&B Road to

    Ramakhandam

    Krishna

    MONTHLY REPORT

  • 7/31/2019 7. March MPR 2012

    32/52

    31 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-

    W/AP/RHB/PRED/06/Kruthivennu/003

    Road from R&B Road to Rangaraopet Krishna

    NCRMP/B-

    W/AP/MPCS/PRED/03/Payakaraopeta/003

    Construction of cyclone shelter at

    Gajapathinagaram in Visakhapatnam

    District

    Visakhapatnam

    NCRMP/B-

    W/AP/MPCS/PRED/03/Nakkapalli/002

    Construction of cyclone shelter at

    Mullaparra in Visakhapatnam District

    Visakhapatnam

    NCRMP/B-

    W/AP/MPCS/PRED/03/Nakkapalli/002

    Construction of cyclone shelter at

    Patimeeda in Visakhapatnam District

    Visakhapatnam

    NCRMP/B-

    W/AP/MPCS/PRED/03/Payakaraopeta/003

    Construction of cyclone shelter at

    Ratnayampeta in Visakhapatnam District

    Visakhapatnam

    NCRMP/B-W/AP/RHB/PRED/01/SANTHABOMMALI/00

    5

    Construction of Cyclone Shelter at

    Kollipadu

    Srikakulam

    NCRMP/B-

    W/AP/RHB/PRED/01/SANTHABOMMALI/00

    5

    Construction of Cyclone Shelter at Runku

    Srikakulam

    NCRMP/B-W/AP/RCS/PRED/01/Itcherla/005 Road from Kotcherela to Pata

    Sundarapalem & Cyclone Shelter

    Srikakulam

    NCRMP/B-W/AP/RCS/PRED/01/Itcherla/005 Road from Kotcherela Road to Kolli

    Bhimavaram & Cyclone Shelter

    Srikakulam

    NCRMP/B-

    W/AP/Br/R&B/01/Patnavanipeta/001

    Construction of High Level Bridge across at

    Km.11/6-8 of NH-5 to Patnavanipeta road in

    Srikakulam district.

    Srikakulam

    NCRMP/B-W/AP/BR/R&B/02/Puligadda/007 Construction of Minor Bridge at Km.7/2

    near Puligadda of Kona Ramatheertham

    R&B Road to Konathalapalem via

    Yerukonda, Pasupam, Kollayavalsa (ZP

    Road) in Vizianagaram District

    Vizianagaram

    NCRMP/B-

    W/AP/BR/R&B/02/Chakaligadda/008

    Construction of Minor Bridge at Km.15/2

    near Chakaligadda of Kona

    Ramatheertham R&B Road to

    Konathalapalem via Yerukonda, Pasupam,

    Kollayavalsa (ZP Road) in Vizianagaram

    District

    Vizianagaram

    9.0 Observations in the submitted reports:

    Name ofWork:

    ROAD FROM APPROACH ROAD TO CYCLONE SHELTER AT ADAVIPUDI.

    1. 100% value of the work is completed.

    2 As per the Agreement the Milestones fixed are as follows.Milestone 1 - to the end of Dt.31.11.2011, Earth work, Pipe culverts.Milestone 2 - to the end of Dt.31.11.2011, WBM Gr-II, Gr-III and Shoulders.

    Milestone 3 - to the end of Dt.31.01.2012, BT and Road Furniture.3 The measurements like width and thickness of the OGPC and Seal coat Layer from Km 0.000 to Km

    1.930 are verified and found to be fairly tallying with the required measurements. The details aregiven in Annexure - 1.

    MONTHLY REPORT

  • 7/31/2019 7. March MPR 2012

    33/52

    32 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    4 Sieve analysis, Bitumen Extraction, AIV and FIV QC tests conducted for OGPC and Seal coat inbetween Km 0.000 to Km 1.930 and Prime and tack coat QC test conducted for rate of spray of Kg/Sq m.

    5

    With M 30 Grade of concrete mix, 200 mm thick CC Pavement was completed from Km 1.917 To km1.970 .Measurements like width & thickness are checked at execution time and Slump testconducted, 6 No of cubes are casted and 3 cubes were tested for 7 day strength. 3 cubes will betested for 28 day compressive strength. Cores will be taken to confirm the compressive strength after28 days. QC tests were also conducted for FA, CA, water and Cement.

    6 The measurements like width and thickness of the WBM Gr-III Layer from Km 1.680 to Km 1.930 andKm 0.000 to Km 1.250 are verified and found to be fairly tallying with the required measurements.The details are given in Annexure - 1.

    7 Volumetric analysis tests were conducted for WBM Grade III layer from Km 1.680 to Km 1.930 andKm 0.000 to Km 1.250 QC tests were conducted for WBM Grade III ( field and lab ) i.e.

    Gredation,AIV,FIV and Water absorption. The details are given in QC Test summary. They are fairlytallying with the specification requirements of clause 405 of MORD.8 Guard stone shall be provided at L/S of the road berm portion, throughout irrigation canal from Km

    1.680 to 1.970 at an closed interval of 2.0m9 Painting is to be done with Black & White strips for the guard stones and also white painting to be

    done for speed breakers & pipe culvert body walls for the clear visibility to vehicular traffic.10 CD Works: 1) Pipe culverts 600mm dia 2no.s in KM 0/2, Km.1/6 Completed.11 Cautionary and Warning signboards at school and speed brokers locations shall be erected as per

    the NCRMP norms.12 Concrete was laid over pipe culvert portion in Km 0/2 but concrete and bituminous layers be joined

    smoothly without any bump.13 Para wise compliance report shall be furnished duly attending to the above remarks and the earlier

    QCR.

    Name ofWork:

    ROAD FROM GURAJANAPALLI TO BANDULAVANIPALEM

    1. 100% value of the work is completed.

    2. As per the Agreement the Mile stones fixed are as follows.Milestone 1 Earth work & Pipe culverts, GSB : to the end of Dt. 30.09.2011Milestone 2 CC Pavement, WBM Gr II and Gr III and Shoulders : to the end of Dt. 31.10.2011Milestone 3 BT and Road Furniture : to the end of Dt. 31.01.2012

    3. The measurements like width and thickness of the OGPC and Seal coat Layer from Km 0.000 to Km1.930 are verified and found to be fairly tallying with the required measurements. The details are givenin Annexure - 1. They are fairly tallying.

    4. Sieve analysis, Bitumen Extraction, AIV and FIV QC tests conducted for OGPC and Seal coat inbetween Km 0.000 to Km 1.930 and Prime and tack coat QC tests were conducted for cheking therate of binder spray.

    5. From Km 0.460 to Km 0.660 both sides shoulder width is less than required because of land problem.

    6. Guard stones are to be fixed along the outer edge of sharp curves and white wash is to be done toguard stones & pipe culvert body walls for the clear visibility to vehicular traffic.

    7. CD Works: Pipe culverts 600mm dia 2no.s in KM 0/2 and Km.1/6 were completed.8. Parawise compliance report shall be furnished duly attending to the above remarks and earlierQCR.

    Name ofWork:

    Road from R&B Road to Danavaipeta

    1. 30.00 % value of the work is completed. Total stretch of road 572Mts. WBM Gr-II is completed initially,Gr- III Completed recently2. Works to be done as per Milestone:

    Mile stone 1 to the end of Dt: 06.12.11 - Earthwork, Pipe Culverts, GSB and Road Furniture - 3Months

    MONTHLY REPORT

  • 7/31/2019 7. March MPR 2012

    34/52

    33 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Mile stone 2 to the end of Dt: 06.03.11 - WBM Gr-II, Gr-III , Shoulders and CC Pavement - 3 MonthsMile stone 3 to the end of Dt: 06.06.12 - BT - 3 Months

    3. 1 St Mile Stone Completed but Earth Work and Road Furniture Works are not Completed. Progress

    needs to be improved4. The measurements like width and thickness of the WBM Gr.-III Layer from Km 0.000 to Km 0.572 are

    verified and found to be fairly tallying with the required measurements. The details are given inAnnexure - 1.

    5. Volumetric analysis tests were conducted for WBM Gr- III layer from Km 0/0 to Km 0/572 .QC testswere conducted for WBM GrII (field & Lab.)I.e Gredation, AIV, FIV and Water obsorption.The Detailsare givenin QC test summary. They are fairly tallying with the specfication requirements of clause405.13 of MORD.

    6. While laying WBM simultaneously shoulders shall be also compacted.7. Parawise compliance report shall be furnished duly attending to the above remarks.

    Name ofWork:

    Road from R&B Road to Gaddipeta of Thondangi Mandal in East Godavari District.

    1. 28.75 % value of the work is completed. Total stretch of road is 457mts. WBM Gr-II and Pipe Culvert1no. Completed initially and WBM Gr - III is completed recently.

    2. Works to be done as per Milestone:Mile stone 1 to the end of Dt: 06.12.11 - Earthwork, Pipe Culverts, GSB and Road Furniture - 3MonthsMile stone 2 to the end of Dt: 06.03.11 - WBM Gr-II, Gr-III , Shoulders and CC Pavement - 3 Months

    Mile stone 3 to the end of Dt: 06.06.12 - BT - 3 Months3. 1st Milestone Completed but Earth Work and Road Furniture Works are not Completed. Progress

    needs to be improved4. The measurements like width and thickness of the WBM Gr-III Layer from Km 0/0 to Km 0/457 are

    verified and found to be fairly tallying with the required measurements. The details are given inAnnexure - 1.

    5. Volumetric analysis tests were conducted for WBM Gr- III layer from Km 0/0 to Km 0/457. QC testswere conducted for WBM GrII (field & Lab.) i.e., Gradation, AIV, FIV and Water absorption. TheDetails are given in QC test summary. They are fairly tallying with the specfication requirements ofclause 405.13 of MORD.

    6. While laying WBM shoulders shall be compacted simultaneously.7. Carriage width is not widened at curved portion. If radius of curve less than 60 m, extra width ofcarriage way shall be provided as per IRC:SP 20

    8. Village name boards, cautionary and mandatory signboards at necessary points and sand stones allalong the outer edge of sharp curves, shall be provided.

    9. Parawise compliance report shall be furnished duly attending to the above remarks.

    Name ofWork:

    Road from R&B Road to Hukumpeta Cyclone Shelter

    1. 50.00 % value of the work is completed. Total stretch of 630 mts, WBM Gr-II Completed2. Works to be done as per Milestone:

    Mile stone 1 to the end of Dt: 06.12.11 - Earthwork, Pipe Culverts, GSB and Road Furniture - 3MonthsMile stone 2 to the end of Dt: 06.03.11 - WBM Gr-II, Gr-III , Shoulders and CC Pavement - 3 MonthsMile stone 3 to the end of Dt: 06.06.12 - BT - 3 Months

    3. 1st Mile Stone Completed but Earth Work and Road Furniture Works are not Completed. Progressneeds to be improved.

    4. The measurements like width and thickness of the WBM Gr.-II Layer from Km 0.000 to Km 0.630 areis verified and found to be fairly tallying with the required measurements. The details are given in

    Annexure -1.5. Volumetric analysis tests were conducted for WBM Gr- II layer from Km 0.000 to Km 0.630 .QC tests

    were conducted for WBM Gr -II (field & Lab.)I.e Gredation, AIV, FIV and Water obsorption.The Detailsare given in a QC test summary. They are fairly tallying with the specfication requirements of clause

    MONTHLY REPORT

    C lt S i f Thi d P t Q lit A dit (TPQA) f N ti l C l Ri k Miti ti P j t (NCRMP)

  • 7/31/2019 7. March MPR 2012

    35/52

    34 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    405.13 of MORD.6. While laying WBM simultaneous compaction of shoulders shall be done.7. White wash is to be done to parapet walls of the existing culvert for the clear visibility of vehicular

    traffic.8. The measurements like width and length of parapets and pipes of all the culverts are verified and

    found tallying with the measurements in the drawing9. Village name boards, cautionary and mandatory signboards at necessary points and ground stones all

    along the outer edge of sharp curves shall be erected.10. Para wise compliance report shall be furnished duly attending to the above remarks.

    Name ofWork:

    Road from R&B Road to K.Chodipallipeta

    1. 27.82 % value of the work is completed. Total stretch of 720 Mts WBM Gr-II completed.2 Works to be done as per Milestone:

    Mile stone 1 to the end of Dt: 06.12.11 - Earthwork, Pipe Culverts, GSB and Road Furniture - 3MonthsMile stone 2 to the end of Dt: 06.03.11 - WBM Gr-II, Gr-III , Shoulders and CC Pavement - 3 MonthsMile stone 3 to the end of Dt: 06.06.12 - BT - 3 Months

    3 1st Mile Stone Completed but Earth Work and Road Furniture Works are not Completed. Progressneeds to be improved.

    4 The measurements like width and thickness of the WBM Gr.-II Layer from Km 0/0 to Km 0.720 isverified and found fairly tallying with the required measurements. The details are given in Annexure -

    1.5 Volumetric analysis tests were conducted for WBM Gr- II layer from Km 0.000 to Km 0.720 .QC tests

    were conducted for WBM GrII (field & Lab.)I.e Gredation, AIV, FIV and Water obsorption.The detailsare givenin QC test summary. They are fairly tallying with the specfication requirements of clause405.13 of MORD.

    6 While laying WBM simultaneously shoulders should to be done with proper compaction7 White washes to be done to parapet walls of the existing culvert for the clear visibility of vehicular

    traffic.8 The measurements like width and length of parapets and pipes of all the culverts are verified and

    found tallying with the estimate.

    9 Village name boards, cautionary and mandatory signboards at necessary points and ground stones allalong the outer edge of sharp curves shall be erected.10 Parawise compliance report shall be furnished duly attending to the above remarks.

    Name ofWork:

    Road from R&B Road to P.Chodipallipeta

    1. 20.68 % value of the work is completed. Total stretch of 670 mts WBM Gr-II completed2 Works to be done as per Milestone:

    Mile stone 1 to the end of Dt: 06.12.11 - Earthwork, Pipe Culverts, GSB and Road Furniture - 3

    MonthsMile stone 2 to the end of Dt: 06.03.11 - WBM Gr-II, Gr-III , Shoulders and CC Pavement - 3 MonthsMile stone 3 to the end of Dt: 06.06.12 - BT - 3 Months

    3 1st Mile Stone Completed but Earth Work and Road Furniture Works are not Completed. Progressneeds to be improved.

    4 The measurements like width and thickness of the WBM Gr II layer from Km 0.000 to Km 0.670 isverified and found to be fairly tallying with the required measurements. The details are given inAnnexure - 1.

    5 Volumetric analysis tests were conducted for WBM Gr- II layer from Km 0.000 to Km 0.670 .QC testswere conducted for WBM Gr-II (field & Lab) i.e., Gradation, AIV, FIV and Water absorption. TheDetails are givenin QC test summary. They are fairly tallying with the specfication requirements ofclause 405.13 of MORD.

    6 While laying WBM shoulders Shall be compacted simultaneously.7 Carriage width is not widened at curved portion. If radius of curve less than 60 mts, width of carriage

    way shall be widened as per IRC SP-20.

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

  • 7/31/2019 7. March MPR 2012

    36/52

    35 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    8 White wash is to be done to parapet walls of the existing culverts for the clear visibility of vehiculartraffic.

    9 The measurements like width and length of parapets and pipes of all the culverts are verified and

    found to be tallying with the measurements within the drawing.10 Village name boards, cautionary and mandatory signboards at necessary points and ground stones all

    along the outer edge of sharp curves shall be erected.11 Parawise compliance report shall be furnished duly attending to the above remarks.

    Name ofWork:

    Road from LB Cheria CC road to Chillapalemm of LB Cheria of Narsapur Mandal inWest Godavari District.

    1. 19.78 % value of the work is completed for this one work in the package which contains three no. ofworks under one agreement.

    2 Works to be done as per Milestone:Mile stone 1 (i.e, Earth work, Pipe culverts, GSB) to the end of Dt: 08.09.2011 - 27.64 lakhs.(23.07%)Mile stone 2 (I.e, WBM Gr II, Gr III and Shoulders) to the end of Dt: 08.01.2011 - 47.66 lakhs.(39.80%)Mile stone 3 (i.e, BT, CC pavement and Road furniture) to the end of Dt: 08.05.2012 - 44.46 lakhs.(37.13%)

    3 GSB of 890 meters & WBM Gr-II of 480 meters length is completed .Shoulders need to be compactedsimultaneously along with WBM layers.

    4 The thickness of the GSB is observed which is varying from 100 to 103 mm as against the

    requirement of 100mm & The thickness of the Gr-II is observed as varying from 75 to 77 mm asagainst the requirement of 75mm. Details are enclosed in annexure - 1.5 The 600mm dia single row pipe culvert (1 No's) not completed in 0/8.6 3rd milestone is in progress, but Pipe culverts & WBM Gr-III are not yet started. Progress needs to

    Be improved.7 Widening earthwork formation and CD works is to be done prior to taking up WBM layers8 The project informatory boards with all details, Cautionary sign boards at necessary points and Village

    name boards are not provided as per aggregement.The same shall be provided as per the guidelinesgiven by SPIU, NCRMP.

    9 The Quality Control Lab is not provided at site for testing of material. The line department officers arerequested to take necessary action to establish Quality Lab at site at early stage.

    Name ofWork:

    Road from R&B road to Pedalanka of Narsapur Mandal in West Godavari District.

    1. 23 % value of the work is completed for this one work in the package which contains three no. of worksunder one agreement.

    2 Works to be done as per Milestone:Mile stone 1 (i.e, Earth work, Pipe culverts, GSB) to the end of Dt: 08.09.2011 - 27.64 lakhs.(23.07%)

    Mile stone 2 (I.e, WBM Gr II, Gr III and Shoulders) to the end of Dt: 08.01.2011 - 47.66 lakhs.(39.80%)Mile stone 3 (i.e, BT, CC pavement and Road furniture) to the end of Dt: 08.05.2012 - 44.46 lakhs.(37.13%)

    3 GSB of 1236 meters & WBM Gr-II of 1070 meters length is completed .Shoulders need to becompacted simultaneously along with GSB layers.

    4 The thickness of the GSB is observed and varying from 100 to 103 mm as against the requirement of100mm. Details are enclosed in annexure - 1.

    5 The thickness of the Gr-II is observed and varying from 75 to 78 mm as against the requirement of75mm. Details are enclosed in annexure - 1.

    6 The 600mm dia single row pipe culvert (3 No's) not completed.7 3rd milestone is in progress, but Pipe culverts & WBM Gr-III is not yet started. Progress needs

    To be improved.8 Widening of earthwork formation and CD works are to be done prior to taking up WBM layers9 he project informatory boards with all details, Cautionary sign boards at necessary points and Village

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

  • 7/31/2019 7. March MPR 2012

    37/52

    36 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    name boards are not provided as per aggregement.The same shall be provided as per the guidelinesgiven by SPIU,NCRMP.

    10 The Quality Control Lab is not provided at site for testing of material. The line department officers are

    requested to take necessary action to establish Quality Lab at site at early stage.

    Name ofWork:

    Road from NH 214 A road to Harijanawada of Kothota of Mogalthuru Mandal in WestGodavari District.

    1. 100 % value of the work is completed for this one work of the package which contains five no. of worksunder one agreement.

    2 Works to be done as per Milestone for the package:Mile stone 1 (i.e, Earth work, Pipe culverts, GSB) to the end of Dt: 26.09.2011 - 16.24 lakhs.(9.03%)

    Mile stone 2 (I.e, WBM Gr II, Gr III and Shoulders) to the end of Dt: 26.02.2012 - 76.44 lakhs.(42.51%)Mile stone 3 (i.e, BT, CC pavement and Road furniture) to the end of Dt: 26.07.2012 - 87.13 lakhs.(48.46%)

    3 C.C Road of 300 meters length is completed out of 380 meters length including Key walls.4 GSB of 80 meters length is completed .Shoulders Completed for 300 mts.5 The 600mm dia single row pipe culvert (1 No's) completed.6 The thickness of the GSB Layer is observed and varying from 100 to 107 mm as against the

    requirement of 100mm. Details are enclosed in annexure - 1.7 The Quality Control Lab is not provided at site for testing of material. The line department officers are

    requested to take necessary action to establish Quality Lab at site at early stage.8 Cores will be taken to verify depth and compressive strength after 28 days of lying.9 MORD Specifications and IRC: SP-62-2004, Guidelines for the construction and design of Cement

    Concrete roads for low volume roads, need to be followed in cutting and spacing of joints and curingthe CC road as mentioned below.

    (i) Construction of joints shall be mechanically sawn joints spaced 2.5 m to 3.75 m(ii) Length of the panel in the direction of traffic shall not be less than the width of the pavement.(iii) Joints shall be cut when the pavement is neither too soft nor too hard and able to bear the

    weight of the machine and crew. Normally it may vary from 8 to 12 hrs depending on weatherconditions

    10 Construction joints shall be butt joints and placed after a days work is over or when work is suspendedfor more than 30 minutes

    11 Expansion joints shall be provided near bridges and slab culverts and consists of bitumen impregnatedjoints/ premoulded synthetic joints filler board about 20 mm thick.

    12 (i)After completion of the finishing operations, the surface of the pavement shall be covered with wetHessain cloth, burlap or jute mats. They shall be maintained fully wetted and in position for 24 hrs(ii) Upon the removal of the wet covering out the end of 24 hrs, the slab shall be thoroughly wetted andcured by ponding or sprinklers.

    13 After minimum 28 days after casting the concrete pavement ,joints groove at contraction joint shall bewidened to a 10 mm width and to a depth 18 to 20mm and shall be sealed

    Name ofWork:

    Road from NH 214 A at Ranga statue center to Harijanawada of Kalipatnam (E) ofMogalthuru Mandal in West Godavari District.

    1. 55.41 % value of the work is completed for this one work in the package which contains five no. ofworks under one agreement.

    2 Works to be done as per Milestone:Mile stone 1 (i.e, Earth work, Pipe culverts, GSB) to the end of Dt: 26.09.2011 - 16.24 lakhs.(9.03%)Mile stone 2 (I.e, WBM Gr II, Gr III and Shoulders) to the end of Dt: 26.02.2012 - 76.44 lakhs.(42.51%)

    Mile stone 3 (i.e, BT, CC pavement and Road furniture) to the end of Dt: 26.07.2012 - 87.13 lakhs.(48.46%)

    3 3rd milestone is in progress, but WBM Gr-III is not yet started. Progress needs to be improved.4 GSB of 890 meters, WBM Gr-II of 600 meters, CC Pavement of 290 meters length is completed

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

  • 7/31/2019 7. March MPR 2012

    38/52

    37 | P a g e

    Co su ta cy Se ces o d a ty Qua ty ud t ( Q ) o at o a Cyc o e s t gat o oject ( C )

    .Shoulders need to be compacted simultaneously along with WBM layers. But shoulder work is not yetstarted.

    5 The thickness of the GSB is observed which is varying from 100 to 106 mm as against the requirement

    of 100mm, The thickness of the Gr-II is observed and varying from 75 to 76 mm as against therequirement of 75mm & The thickness of the CC Pavement is observed and varying from 200 to 201mm as against the requirement of 200mm. Details are enclosed in annexure - 1.

    6 Widening earthwork formation and CD works are to be done prior to taking up WBM layers7 Cores will be taken to verify depth and compressive strength after 28 days of lying.8 MORD Specifications and IRC: SP-62-2004, Guidelines for the construction and design of Cement

    Concrete roads for low volume roads, need to be followed in cutting and spacing of joints and curingthe CC road as mentioned below.

    (i) Construction of joints shall be mechanically sawn joints spaced 2.5 m to 3.75 m(ii) Length of the panel in the direction of traffic shall not be less than the width of the pavement.(iii) Joints shall be cut when the pavement is neither too soft nor too hard and able to bear the

    weight of the machine and crew. Normally it may vary from 8 to 12 hrs depending on weatherconditions

    9 Construction joints shall be butt joints and placed after a days work is over or when work is suspendedfor more than 30 minutes

    10 Expansion joints shall be provided near bridges and slab culverts and consists of bitumen impregnatedjoints/ premoulded synthetic joints filler board about 20 mm thick.

    11 After minimum 28 dys after casting the concrete pavement ,joints groove at contraction joint shall bewidened to a 10 mm width and to a depth 18 to 20mm and shall be sealed.

    12 Cautionary sign boards at necessary points and Village name boards are not provided as peraggregement.The same shall be provided as per the guidelines given by PIU,NCRMP.

    13 The Quality Control Lab is not provided at site for testing of material. The line department officers arerequested to take necessary action to establish Quality Lab at site at early stage.

    Name ofWork:

    R&B Road at Panchayat office to Pulaparthivarithota via Badava of MogalthuruMandal in West Godavari District.

    1. 48.50 % value of the work is completed for this one work in the package which contains five no. ofworks under one agreement.

    2 Works to be done as per Milestone:Mile stone 1 (i.e, Earth work, Pipe culverts, GSB) to the end of Dt: 26.09.2011 - 16.24 lakhs.(9.03%)Mile stone 2 (I.e, WBM Gr II, Gr III and Shoulders) to the end of Dt: 26.02.2012 - 76.44 lakhs.(42.51%)Mile stone 3 (i.e, BT, CC pavement and Road furniture) to the end of Dt: 26.07.2012 - 87.13 lakhs.(48.46%)

    3 3rd milestone is in progress, but WBM Gr-II & Gr-III is not yet started. Progress needs to be improved.4 GSB of 1490 meters length is completed .Shoulders need to be compacted simultaneously along with

    GSB layers. But shoulder work is not yet started.5 The thickness of the GSB is observed which is varying from 100 to 104 mm as against the requirement

    of 100mm & The thickness of the CC Pavement is observed which is varying from 200 to 202 mm asagainst the requirement of 200mm. Details are enclosed in annexure - 1.

    6 The 600mm dia single row pipe culvert 1 No. is completed against 2 Nos. and balance 1 No. has to betaken up before WBM.

    7 White wash shall be done to parapet walls of the existing culvert for the clear visibility of vehiculartraffic.

    8 Cores will be taken to verify depth and compressive strength after 28 days of lying.9 MORD Specifications and IRC: SP-62-2004, Guidelines for the construction and design of Cement

    Concrete roads for low volume roads, need to be followed in cutting and spacing of joints and curingthe CC road as mentioned below.

    (iv) Construction of joints shall be mechanically sawn joints spaced 2.5 m to 3.75 m(v) Length of the panel in the direction of traffic shall not be less than the width of the pavement.(vi) Joints shall be cut when the pavement is neither too soft nor too hard and able to bear the

    weight of the machine and crew. Normally it may vary from 8 to 12 hrs depending on weatherconditions

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

  • 7/31/2019 7. March MPR 2012

    39/52

    38 | P a g e

    10 Construction joints shall be butt joints and placed after a days work is over or when work is suspendedfor more than 30 minutes

    11 Expansion joints shall be provided near bridges and slab culverts and consists of bitumen impregnated

    joints/ premoulded synthetic joints filler board about 20 mm thick.12 After minimum 28 dys after casting the concrete pavement ,joints groove at contraction joint shall bewidened to a 10 mm width and to a depth 18 to 20mm and shall be sealed.

    13 The project informatory boards with all details, Cautionary sign boards at necessary points and Villagename boards are not provided as per aggregement.The same shall be provided as per the guidelinesgiven by PIU,NCRMP.

    14 The Quality Control Lab is not provided at site for testing of material. The line department officers arerequested to take necessary action to establish Quality Lab at site at early stage.

    Name ofWork: Mogaltur Vempa R&B Road at Uchintha kalava Bridge to Gogulamma Harijanapeta ofMogalthuru Mandal in West Godavari District.1. 67.43 % value of the work is completed for this one work in the package which contains five no. of

    works under one agreement.2 Works to be done as per Milestone:

    Mile stone 1 (i.e, Earth work, Pipe culverts, GSB) to the end of Dt: 26.09.2011 - 16.24 lakhs.(9.03%)Mile stone 2 (I.e, WBM Gr II, Gr III and Shoulders) to the end of Dt: 26.02.2012 - 76.44 lakhs.(42.51%)Mile stone 3 (i.e, BT, CC pavement and Road furniture) to the end of Dt: 26.07.2012 - 87.13 lakhs.

    (48.46%)3 WBM Gr-II of 595 meters length is completed & GSB layer completed from CH. 595 to 1190m.Shoulders need to be compacted simultaneously along with WBM layers. But shoulder work is notyet started.

    4 Gradation is conducted for GSB & WBM Gr-II material and results are within the specified limits as peragreement specification.

    5 The thickness of the GSB is observed, which is varying from 100 to 104 mm as against therequirement of 100mm & Gr-II is observed, which is varying from 75 to 82 mm as against therequirement of 75mm. Details are enclosed in annexure - 1.

    6 C.C Road of 595 meters length is completed including Key walls. Shoulders work is not yet started.The thickness of the CC Road is observed as 200 to 205mm.

    7 The 600mm dia single row pipe culvert (2 No's) completed in 0/6.8 White wash shall be done to parapet walls of the existing culverts for the clear visibility of vehicular

    traffic.9 The measurements like width and length of parapets and pipes of all the culverts are verified and

    found to be tallying.Construction joints shall be butt joints and placed after a days work is over or when work is suspendedfor more than 30 minutes

    10 Expansion joints shall be provided near bridges and slab culverts and consists of bitumen impregnatedjoints/ premoulded synthetic joints filler board about 20 mm thick.

    11 After minimum 28 dys after casting the concrete pavement ,joints groove at contraction joint shall be

    widened to a 10 mm width and to a depth 18 to 20mm and shall be sealed.12 The Quality Control Lab is not provided at site for testing of material. The line department officers are

    requested to take necessary action to establish Quality Lab at early stage.

    Name ofWork:

    Improvements to Road from Konada Ramatheertham (R&B) Road to Konathalapalem(Via) Pasupam, Yerukonda, Kollayavalsa from Km 12/0 to 16/5 (Km 0/0 to 4/0 i.e. up toNH-5 crossing) in Vizianagaram District.

    1. 100.00 % value of the work is completed.2 Works to be done as per Combined Milestone:Mile stone 1 to the end of Dt: 07.06.11- Forming Embankment and GSB.Mile stone 2 to the end of Dt: 07.12.11- WMM, Surface dressing, Emulsion spraying and B.T.Mile stone 3 to the end of Dt: 07.03.12- Gravel Shoulders.

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

  • 7/31/2019 7. March MPR 2012

    40/52

    39 | P a g e

    3 The field officers have not furnished the bills for Bitumen used for the road. The same shall befurnished to the TPQA staff for verification.

    4 The field officers have furnished the test results for Soil, GSB, WMM and B.T obtained from

    Department of Civil Engineering, Andhra University Visakhapatnam.5 BM and SDBC samples are collected on 14.06.2011 and got tested for bitumen content and gradation.The result are found to be fairly satisfying the specification requirement as per Mirth. The result werecommunicated in the 1st QCR

    6 The formation widths are verified from Km: 12/000 to Km 13/500, Km: 13/850 to Km 15/200m and Km:15/400 to Km 15/760m and found to be varying from 6.0m to 7.0m. The field officers are requested tofurnish the reasons for not providing the full width. The field officers are requested to explore thepossibility of mocking up the required formation width.

    7 At some locations the outer edges of BT Road are not maintained true to line8 The embankment formation requires trimming of side slopes as specified in Mort & H sections 301 &

    305.9 The measurements like width and thickness of the BM and SDBC layer from KM 12/000 to KM 15/200

    and KM 15/400 to 15/900 are verified and found to be tallying with the required measurements.The approved letters of quarries like earth and aggregates have not been produced by field officersfor verification

    10 Village name boards, Guard stones, cautionary and mandatory signboards at necessary points allalong the outer edge of sharp curves and at school locations shall be erected.

    11 The Project informatory boards were erected with all details at site as per the guide lines given bySPIU, NCRMP.

    12 Para wise compliance report shall be furnished for this QCR and First QCR dated 15-07-2011 dulyattending to the above remarks.

    Name ofWork:

    Construction of cyclone shelter at Bangarampeta in Nakkapalli Mandal

    1. Three works are there in this package:1) Construction of cyclone shelter at Bangarampeta in Nakkapalli Mandal,2) Construction of cyclone shelter at Mullaparra in Nakkapalli Mandal and3) Construction of cyc