    National Cyclone Risk Mitigation Project

    (NCRMP)Revenue (DM) Department

    Government of Andhra Pradesh

    National Cyclone Risk Mitigation Project

    (NCRMP)Revenue (DM) Department

    Government of Andhra Pradesh

  • 7/30/2019 Mpr October 2012

    2/67

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    INDEX

    1.0 Project Background 2

    2.0 Third Party Quality Audit Consultant 3

    3.0 Major Activities and Review Meetings of the Month 3

    4.0 Status of TPQA Visits 4

    5.0 Progress of NCRMP works 5

    TPQA Status Report for NCRMP Works To the end of(31-10-2012) 6

    6.0 District wise status of tests conducted by TPQA 30

    7.0 Details of QC Audit Reports Submitted during this Month 31

    8.0 Details of Environmental & Social Reports Submitted during this Month 32

  • 7/30/2019 Mpr October 2012

    3/67

  • 7/30/2019 Mpr October 2012

    4/67

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    2.0 Third Party Quality Audit Consultant.

    To provide Consulting Services of Third Party Quality Auditor for Construction of Multipurpose Cyclone Shelters, Roads to

    Cyclone Shelters, Roads to habitations, and Roads and Bridges under NCRMP in 9 coastal districts The Commissioner for

    Disaster Management & Project Director, Project Implementation Unit (PIU) NCRMP has selected Egis International in JV

    with Egis India Consulting Engineers (I) Pvt. Ltd. On 31st May2011, the Contract for Consultancy Service was signed

    between The Commissioner for Disaster Management & Project Director, Project Implementation Unit (PIU) NCRMP and

    the Egis International in JV with Egis India Consulting Engineers (I) Pvt. Ltd.

    3.0 Major Activities and Review Meetings of the Month

  • 7/30/2019 Mpr October 2012

    5/67

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    4.0 Status of TPQA Visits:

    The following table shows the details of TPQA visits to sites in respective districts.

    District

    Total Number of Visits

    Up to Sep.'2012 In Oct.'2012Up to

    October.'2012

    Srikakulam 360 28 388

    Vizianagaram 61 5 66

    Vishakhapatnam 308 19 327

    East Godavari 542 16 558

    West Godavari 387 10 397

    Krishna 237 10 247

    Guntur 297 23 320

    Prakasam 340 27 367Nellore 285 9 294

    No. of Visits by TPQA

  • 7/30/2019 Mpr October 2012

    6/67

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    5.0 Progress of NCRMP works:

    The district wise progress of works is shown below. The works in the West Godavari are not started and the works in

    Krishna District has just started. At many places the first milestone is completed but works are not started. The line

    departments are to analyze the reasons for the slow progress and if necessary penalty for the slow progress as per the

    agreement conditions should be imposed.

    Third Party Quality Audit by Egis India consulting services

    Summary of Activities

    S.No. District

    Agreements for PackagesCommunicated

    Status of works

    PR R&B Progress Not Started

    1 Srikakulam 6 5 21 0

    2 Vizianagaram - 3 3 0

    3 Visakhapatnam 13 0 21 0

    4 East Godavari 7 0 12 1

    5 West Godavari 3 0 10 0

    6 Krishna 4 0 8 0

    7 Guntur 6 2 17 0

  • 7/30/2019 Mpr October 2012

    7/67

    MONTHLY REPORT

    6 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    TPQA Status Report for NCRMP Works To the end of (31-10-2012)

    S.No. District

    Packages /Works

    entrustedStatus of Works

    No.of

    Visitsof

    TPQA

    TotalNo.

    of QCtestsdone

    NCRsAudit

    ReportsIssued

    Environmentaland Social

    ReportsIssued

    Issued closed Pending

    PR R&B StartedNot

    Started

    1 Srikakulam 06_16 5_5 21 0 388 1364 54 38 16 71 52

    2 Vizianagaram - 3_3 3 0 66 400 3 1 2 11 9

    3 Visakhapatnam 13_21 - 21 0 327 2043 25 21 4 67 41

    4 East Godavari 07_13 - 12 1 558 1016 23 21 2 49 30

    5 West Godavari 03_10 - 10 0 397 349 20 17 3 44 37

    6 Krishna 04_08 - 8 0 247 82 3 3 0 33 21

    7 Guntur 06_15 2_2 17 0 320 568 13 12 1 50 20

    8 Prakasham 12_23 1_1 24 0 367 1890 33 26 7 109 50

    9 Nellore 16_24 - 24 0 294 976 30 26 4 105 48

    Total 67_130 11_11 140 1 2964 8688 204 165 39 539 308

  • 7/30/2019 Mpr October 2012

    8/67

    MONTHLY REPORT

    7 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in Srikakulam District up to 31.10.2012

    Category Packages allotted under Phase - 1Names of works under

    each packageAgreement No. / Date DHS DFC

    Progress up to

    31.10.2012

    RHB

    NCRMP/B-W/AP/RHB/PRED/01/Santhabommali/003

    Road from DPN R&Broad to Uddandapalem

    /2010-11, Dt.30.04.2011

    30.04.11 30.04.12 complete Entire work

    Road from K. UmiladaJunction to Koduru (LinkRoad)

    /2010-11, Dt.30.04.2011

    30.04.11 30.04.12 complete Entire work

    Road from Borubadra,Malagam to Kollipadu viaSeepuram, Gantapeta

    /2010-11, Dt.30.04.2011

    30.04.11 30.04.12 complete Entire work

    NCRMP/B-W/AP/RHB/PRED/01/Polaki/006

    Road from R&B roadMobagam toDuubakavanipeta viaGajapathinagaram

    /2010-11, Dt.30.04.2011

    30.04.11 30.04.12

    300 mts CC road

    completed, GSB layingis in progress, roadformation width vary

    from 6.00mts to 7.50mts

    Road fromTalasamudram to DolaRegulator

    /2010-11, Dt.30.04.2011

    30.04.11 30.04.12WBM GR-III laying is in

    proigress

    NCRMP/B-W/AP/RHB/PRED/01/Polaki/005

    Road from R&B roadEdulavalasa - Killam toJonnam viaTalasamudram

    /2011-12, Dt.30.04.2011

    30.04.11 31.01.12WBM Gr-II & III metal

    collection is in progress

    BridgesNCRMP/B-W/ AP/Br/R&B/01/Patnavanipeta/001

    Construction of bridge atKm 11/6-8 of NH-5 toPatnavanipetaConnectingSundarapalem

    46/2011, Dt.17.12.2010

    17.12.10 17.06.12

    Sub structure for bridgecompleted ,Approach

    roade/w,GSB,WMM,SDBC

    completed.CD,R/Wworks completed.slab

    shuttring reinforcementwork is in progress

  • 7/30/2019 Mpr October 2012

    9/67

    MONTHLY REPORT

    8 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-W/AP/Br/R&B/01/ Surampeta/003

    Construction of MinorBridge at Km 12/2-4 ofNH-5 to SurampetaRoad via Naruva,Mentada

    45/2010-2011,Dt17.12.2010

    17.12.10 17.03.12

    Deck slabs weiring coat& hand rails

    completed,Approacheroad work completed.

    NCRMP/B-W/AP/Br/R&B/01/Bendigadda/004

    Construction of Highlevel bridge acrossBendigadda at KM 4/10of Pundi-Parlakimidi roadin Srikakulam Dt, A.P.

    1/2010,Dt.11.11.2010 11.11.10 11.05.12Slabs completed andApproach road e/w

    completed.

    Roads NCRMP/B-W/AP/RD/R&B/01/Nowpada/006)Improvements Naupada-Venkatapuram road from0/0to15/0km

    43/2010-11,17.12.2010 17.12.10 17.03.12BT work completed, CC

    Road completed

    RCS

    NCRMP/B-W/AP/RCS/PRED/01/V.Kotturui/002

    Road from NP road toURK Puram

    G.O.Rt.No.451, Dt.06.04.2011

    06.04.11 29.09.12Bt layer completed &Ccroad completed

    Road from Deppuru,Bahadapalli road toOnkuluru to CycloneShelter

    G.O.Rt.No.451, Dt.06.04.2011

    06.04.11 29.09.12Bt layer completed &Ccroad completed

    Road from R & B Roadto Devunthalada

    G.O.Rt.No.451, Dt.06.04.2011

    06.04.11 29.09.12Bt layer completed &Ccroad completed

    Road from Pollada toKomarthalada toCyclone Shelter

    G.O.Rt.No.451, Dt.06.04.2011

    06.04.11 29.09.12Bt layer completed &Ccroad comlpeted

    NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005

    Road from Koyyam R &B Road to

    Moosavanipeta

    G.O.Rt.No.451, Dt.

    06.04.2011

    30.04.11 07.05.12 BT layer completed

    Road from Mentada toDovupeta

    G.O.Rt.No.451, Dt.06.04.2011

    30.04.11 07.05.12 BT layer completed

    Road from Kotcherelaroad to Kollibhemavaram& Cyclone Shelter

    G.O.Rt.No.451, Dt.06.04.2011

    30.04.11 07.05.12

    BT layer & CCroadcompleted

  • 7/30/2019 Mpr October 2012

    10/67

    MONTHLY REPORT

    9 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Road from Kotcherlaroad toPathesundrapalem

    G.O.Rt.No.451, Dt.06.04.2011

    30.04.11 07.05.12

    BT layer & CCroadcompleted

    MPCSNCRMP/B_W/AP/MPCS/PRED/01/Sa

    nthabommali/005

    Construction of Cyclone shelterat Kollipadu

    G.o rt No451 Dt

    06.04.2010

    07.01.2013

    Completion ofGround floorPlinth level

    Silt floor level slabcompleted.

    Construction of Cyclone Shelterat Runku

    G.o rt No451 Dt

    06.04.2010

    07.01.2013

    Completion ofGround floorPlinth level

    plinth beam completedsand filling is in progress,and columns above plinth

    beam is in progress

    Status of works in Vizianagaram District up to 31.10.2012

    CategoryPackages allottedunder Phase - 1

    Names of works under eachpackage

    Agreement No./ Date DHS DFCProgress up to

    31.10.2012

    Bridges

    NCRMP/ B-W/ AP/Br/ R&B/ 02/

    Puligadda/ 007

    Construction of Minor Bridge atKm. 7/2 near Puligadda of Konada Ramatheertham R&B Road toKonathalapalem via Yerukonda,

    Pasupam, Kollayavalsa (Z.P.Road)

    31/2010-201 Dt.1.12.2010

    01.12.10 31.05.12100% of work

    completed

    NCRMP/ B-W/ AP/Br/ R&B/ 02/

    Chakaligadda / 008

    Construction of Minor Bridge atKm 15/2 near Chakaligadda of

    Konada Ramatheertham R&B roadto Konathalapalem (via)Yerukonda, Pasupam,

    Kollayavalsa (ZP Road)

    34/2010-2011 Dt.8.12.2010

    08.12.10 07.06.1287% of workcompleted

  • 7/30/2019 Mpr October 2012

    11/67

    MONTHLY REPORT

    10 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Road (R&B)NCRMP/B-

    W/AP/RD/R&B/ 02/

    Konada/009

    Improvements to Road fromKonada Ramatheertham (R&B)Road to Konathalapalem (Via)

    Pasupam, Yerukonda,

    Kollayavalsa from Km 12/0 to 16/5(Km 0/0 to 4/0 i.e. up to NH-5crossing)

    33/2010-201 Dt.8.12.2010

    08.12.10 07.03.12100% of work

    completed

    Status of works in Visakhapatnam District up to 31.10.2012

    Category Packages allotted under Phase- 1Names of works

    under eachpackage

    AgreementNo. / Date

    DHS DFC Progress up to 31.10.2012

    RHB

    NCRMP/B-W/AP/RHB/PRED/03/Nakkapalli/001

    Road from Vempadu toPatimeeda

    /2010-11, Dt.11.01.2011

    11.01.11 11.01.12 Work Completed.

    Road from R&B road toMullaparra up to Beach

    end

    /2010-11, Dt.11.01.2011

    11.01.11 27.10.11 Work Completed.

    NCRMP/B-W/AP/RHB/PRED/03/Anandapuram/003

    Road from R&B B.PKallalu to

    Matchvanipalem

    /2010-11, Dt.10.03.2011

    10.03.11 09.12.11 Work Completed.

    NCRMP/B-W/AP/RHB/PRED/03/Paravada/004

    Road from R & B roadto Pothu Rajannapalem

    /2010-11, Dt.28.03.2011

    28.03.11 27.12.11 Work Completed.

    Road from R & B roadto Jalaripeta

    /2010-11, Dt.28.03.2011

    28.03.22 28.12.11 Work Completed.

    NCRMP/B-W/AP/RHB/PRED/03/Rambilli/006Road from R & B road

    to Venkayyapalem/2010-11, Dt.11.01.2011

    11.01.11 11.10.11 Work Completed.

    NCRMP/B- Road from R&B road to /2011-12, Dt. 27.04.11 26.01.12 Work Completed.

  • 7/30/2019 Mpr October 2012

    12/67

    MONTHLY REPORT

    11 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    W/AP/RHB/PRED/03/Achyutapuram/007 Ava- Somavaram 27.04.2011

    Road from R&B Road

    to Avarajam

    /2011-12, Dt.

    27.04.2011 27.04.11 26.01.12 Work Completed.

    Status of works in Visakhapatnam District up to 31.10.2012

    CategoryPackages allotted under

    Phase - 1Names of works under each

    packageAgreement No. /

    DateDHS DFC

    Progress upto

    31.10.2012

    RCS

    NCRMP/B-W/AP/RCS/PRED/03/Anandapuram/001

    Road from NH-5 toRamarayadupalem

    /2010-11, Dt. 15.09.2011 15.09.11 14.06.12

    RoadFurniture &B.T iscompleted.

    NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002

    Road from R&B road toKrishnampalem

    /2010-11, Dt. 15.09.2011 15.09.11 14.09.12

    CD works arecompleted &B.T work isCompleted

    Road from R & B road toKattubolu to Marripalem

    /2010-11, Dt. 15.09.2011 15.09.11 14.09.12

    CD works arecompleted &B.T work isCompleted

    Road from R & B road to

    Rajakoduru

    /2010-11, Dt. 15.09.2011 15.09.11 14.09.12

    CD Work iscompleted &

    B.T work iscompleted

    NCRMP/B-W/AP/RCS/PRED/03/Nakkapalli/003

    Road from R & B road toPedateenarla to Chinatheernala

    /2010-11, Dt. 15.09.2011 15.09.11 14.06.12

    B.T & C.Croad worksareCompleted.

  • 7/30/2019 Mpr October 2012

    13/67

    MONTHLY REPORT

    12 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Road from Upmaka RajayyapetaR & B road to Janakayyapeta

    /2010-11, Dt. 15.09.2011 15.09.11 14.06.12

    CD works areCompleted &B.T work iscompleted

    Status of works in Visakhapatnam District up to 31.10.2012

    Category Packages allotted under Phase - 1Names of works under

    each packageAgreement No.

    / Date

    Milestone Completion Dates Progress w.r.t.milestone up to

    31.10.2012First Second Third

    MPCS

    NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003

    Construction of cycloneshelter at Gajapathi

    Nagaram

    /2011-12, Dt.03.10.2011

    02.02.12 02.06.12 02.10.12

    Plinth beam &Staircase, Ramp andStilt columns arecompleted.Form workfor Stilt slabcompleted.Ist floorcolmns completedtupto roof levevel. Istfloor form workcompleted. Ist floorslab reinforcementplacing is inprogress.EOATsubmitted on24.08.12

    Construction of cyclone

    shelter at Ratnayampeta

    /2011-12, Dt.

    03.10.2011 02.02.12 02.06.12 02.10.12

    All Slabs arecompleted. Insideand outside wallplastering work

    completed.woodjoinery and Electricalworks are to beprogress.

    NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002Construction of cyclone

    shelter at Patimeeda/2011-12, Dt.03.10.2011

    02.03.12 02.08.12 02.01.13

    Stilt Slab & 1st floorcolumns areCompleted.Staircase, Ist floorslab reinforcementplacing work is in

  • 7/30/2019 Mpr October 2012

    14/67

    MONTHLY REPORT

    13 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    progress . EOATsubmitted on24.08.12

    Construction of cycloneshelter at Mullaparra

    /2011-12, Dt.03.10.2011

    02.03.12 02.08.12 02.01.13

    Stilt Slab & 1st floorcolumns areCompleted. Ist floorslab completed. Headroom columns arecompleted.Headroom form work is inprogress.and ceilingplastering work is inprogress.

    Construction of cycloneshelter at Bangarampeta

    /2011-12, Dt.03.10.2011

    02.03.12 02.08.12 02.01.13

    1st floor Slab, IIndfloor columns &staircase areCompleted. Iind floor

    slab completd Headroom columnscompleted upto rooflevel. Head room slabcompleted Ist floorbrick masonry work isin progress.

    NCRMP/B-W/AP/MPCS/PRED/03/Rambilli/004Construction of cyclone

    shelter atVenkayyapalem

    /2011-12, Dt.03.10.2011

    02.01.12 02.04.12 02.07.12

    Footings & Pedestalsworks are inprogress.Sand fillingin foundationcompleted.Plinthbeam work is in

    progress.EOATproposals submittedon 29.06.12.

    NCRMP/B-W/AP/MPCS/PRED/03/Paravada/001Construction of cyclone

    shelter atTikkavanipalem

    /2011-12, Dt.07.10.2011

    06.01.12 06.04.12 06.07.12Work not started dueto site problem

  • 7/30/2019 Mpr October 2012

    15/67

    MONTHLY REPORT

    14 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in East Godavari District up to 31.10.2012

    Category Packages allotted under Phase - I

    Names of works

    under eachpackage

    Agreement

    No. / Date

    Mile stones

    RemarksFirst Second Third

    RHB (2 )RCS (8)MPCS (3)

    NCRMP/B-W/AP/RHB/PRED/04/Katrenikona/003

    Road from PR roadsto Dasarivanipeta and

    to Cyclone Shelter

    /2011-12Dt:27.04.2011

    30-11-2011 30-11-2011 20-01-2012 Completed

    NCRMP/B-W /RCS/PRED/04/Karapa/001Approach Road tocyclone Shelter at

    Adivipudi

    2011-12Dt:20.05.2011

    30-11-2011 31-10-2011 31-01-2012 Completed

    NCRMP/B-W/AP/RHB/PRED/04/Karapa/001/

    Road fromGurjanapalli to

    Bandulavaripalem

    2011-12Dt:27.04.2011

    30-09-2011 31-10-2011 31-01-2012 Completed

    NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

    Road from R&B Roadto P.Chodipallipeta CS

    2011-12Dt:07.09.2011

    3 months 3 months 3 months Completed

    NCRMP/B-W

    /AP/RCS/PRED/04/Thondangi/004

    Road from R&B Road

    to K.Chodipallipeta CS

    /2011-12

    Dt:07.09.2011

    3 months 3 months 3 months Completed

    NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

    Road from R&B Roadto Hukumpeta CS

    /2011-12Dt:07.09.2011

    3 months 3 months 3 months Completed

    NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

    Road from R&B Roadto Gaddipeta CS

    /2011-12Dt:07.09.2011

    3 months 3 months 3 months Completed

  • 7/30/2019 Mpr October 2012

    16/67

    MONTHLY REPORT

    15 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

    Road from R&B Roadto Danavaipeta CS

    /2011-12Dt:07.09.2011

    3 months 3 months 3 months Completed

    NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004/

    Road from R&B Roadto G.MusalayyapetaCS

    2011-12Dt:07.09.2011

    3 months 3 months 3 months Not yet Started

    NCRMP/B-W/AP/RCS/PRED/04/Uppalaguptam/003

    Road from R&B Roadto Chinaraghavulapeta

    Cyclone Shelter

    /2011-12 Dt:23.09.2011

    3 months/22.11.2011

    3 months22.06.2011

    ----------- Completed

    NCRMP/B-W/AP/MPCS/PRED/04/Uppalaguptam/002

    Construction ofCyclone Shelter at

    Pedaraghavulapeta ofUppalaguptam Mandal

    E.G.Dt.

    /2011-12Dt:17.10.2011

    3 months16.01.2012

    3 months16.04.2012

    3 months16.07.2012

    Stair case and cattleramp 1st flight fromPB form work is inprogress. Compoundwall is in progress.

    NCRMP/B-W/AP/MPCS/PRED/04/Thondangi/004

    Construction ofCyclone Shelter at

    Laxamanudupadu inThondangi

    /2011-12Dt:07.09.2011

    Stilt floor ceiling andcolumns plastering

    work is in progress.

    NCRMP/B-W/AP/MPCS/PRED/04/Thondangi/004

    Construction ofCyclone Shelter at

    Avulamanda

    /2011-12Dt:07.09.2011

    Terrace SlabCompleted. Compoundwall is in progress

  • 7/30/2019 Mpr October 2012

    17/67

    MONTHLY REPORT

    16 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in West Godavari District up to 31.10.2012

    CategoryPackages allotted under Phase

    - 1Names of works under

    each packageAgreementNo. / Date

    Milestone Completion Dates Progress w.r.t.milestone up to

    31.10.2012

    RemarksFirst Second Third

    RHB

    NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/0

    01

    Road from NH 214 A atRanga Statue center to

    Harijanawada of Kalipatnam(E) (Mogalthuru Mandal

    W.G.Dist.)

    16 /2011-12

    Dt.27.04.2011

    27/4/2011to

    22/9/2011

    23/9/2011to

    24/2/2012

    25/2/2012to

    26/7/2012

    100% Work Completed.

    R&B road at PanchayatOffice to Pulaparthivarithota

    via Badava(Mogalthuru Mandal

    W.G.Dist.)

    100% Work Completed.

    Mogalthuru Vempa R&BRoad at Uchintha Kalava

    Bridge to Gogulamma

    Harijanapeta (MogalthuruMandal W.G.Dist.)

    100% Work Completed.

    From Narsapur MogalthuruR&B road to Dayadaldaspetavia Venkateshwara Swamytemple (Mogalthuru Mandal

    W.G.Dist.)

    100% Work Completed.

    Road from NH 214 A road toHarijanapeta of Kothota

    (Mogalthuru MandalW.G.Dist.)

    27/4/2011to

    22/9/2011

    23/9/2011to

    24/2/2012

    25/2/2012to

    26/7/2012100% Work Completed.

    NCRMP/B-W/AP/RHB/PRED/05/Narsapur/0

    02

    R&B road to Indira Nagar

    (via) Pochamma temple(Narsapur Mandal W.G.Dist.)

    21 /2011-12Dt.09.05.2011

    09/05/2011to

    04/09/2011

    05/09/2011to

    06/01/2012

    07/01/2011to

    08/5/2012

    100% Work Completed.

    Road from R&B road toPedalanka (Narsapur Mandal

    W.G.Dist.)100% Work Completed.

    Road from LB Cheria CCroad to Chillapalemm of LBCheria (Narsapur Mandal

    W.G.Dist.

    100% Work Completed.

  • 7/30/2019 Mpr October 2012

    18/67

    MONTHLY REPORT

    17 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in Krishna District up to 31.10.2012

    Category Packages allotted under Phase - 1Names of works under each

    packageAgreement No. /

    DateDHS DFC

    Progress up to31.10.2012

    RHB

    NCRMP/B-W/AP/RHB/PRED/06/Machipatnam/001

    Road connecting R&B roadthrough Gantalammapalem

    /2011-12Dt.27.4.2011

    27.04.11 26.01.2012 Work Completed.

    NCRMP/B-W/AP/RHB/PRED/06/Machipatnam/002

    Road from R & B Road to B.VThota

    /2011-12Dt.27.4.2011

    27.04.11 26.01.2012

    Work Completed.

    Road from Potalapalem Z.Proad to Chikativanipalem Work Completed.

    NCRMP/B-W/AP/RHB/PRED/06/Kruthivennu/003

    Road from Intheru R&B Road toRangaraopet

    /2011-12Dt.27.4.2011 27.04.11 26.01.2012

    Work Completed.

    Road from R&B road to CycloneShelter at Chandala Work Completed.

    NCRMP/B-W/AP/RHB/PRED/05/Kalla/003

    From A-U R&B Road toSatyanarayanapuram (Kalla

    Mandal W.G.Dist.)25 /2011-12

    Dt.26.05.2011

    26/5/2011

    To20/8/2011

    20/8/2011

    to21/11/2011

    22/11/2011

    To23/2/2012

    100% Work Completed.

    From A-U R&B Road toMekaladibba (Kalla Mandal

    W.G.Dist.)100% Work Completed.

  • 7/30/2019 Mpr October 2012

    19/67

    MONTHLY REPORT

    18 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in Krishna Districts up to 31.10.2012

    Category Packages allotted under Phase - 1

    Names of works

    under eachpackage

    AgreementNo. / Date

    Milestone Completion Dates Progressw.r.t.

    milestoneup to

    31.10.2012

    RemarksFirst Second Third

    RCSNCRMP/B-W

    /AP/RCS/PRED/06/Machipatnam/001

    Road fromBhogireddipalliR&B Road to

    Ramakhandam

    /2011-12/Dt.02.09.2011

    01.12.2011 01.03.12 01.06.12 13.20% Work Completed.

    Road from R&BRoad Chinnapuram

    to Gundupalem

    /2011-12/27.04.2011

    01.12.2011 01.03.12 01.06.12

    12.14% Work Completed.

    Road fromPotalapalem Z.Proad to Potepalli.

    /2011-12/Dt.02.09.2011

    01.12.2011 01.03.12 01.06.1231.68%

    Work Completed.

  • 7/30/2019 Mpr October 2012

    20/67

    MONTHLY REPORT

    19 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in GUNTUR District up to 31.10.2012

    CategoryPackages allotted under

    Phase - 1Names of works under each package

    Agreement No./Date

    DHS DFCProgress up to

    31.10.2012

    RHB

    NCRMP/B-W/AP/RHB/PRED/07/KARLAPAL

    EM/001

    R/f Ganapavaram R&BRoad t o Kesavapuri ST colony 7/2011-2012

    27.04.201127.04.11 26.01.2012

    Completed.

    NCRMP/B-W/AP/PRED/07/Nagaram/002

    R/f R&B Road to Mohammad Alipalem

    8/2011-201227.04.2011

    27.04.11 26.4.2012

    Completed.

    R/f R&B Road to Katuivaripalem.Completed.

    Bridges

    NCRMP/B-W/AP/Br/R&B/07/Bapatla/010

    Reconstruction of High level Bridge @Km5/2 ofBapatla-Suryalanka Road across Perali drain in

    Guntur79/2010-2011

    1.12.201001.12.10 31.5.2012 WMM completed.

    NCRMP/B-W/AP/Br/R&B/07/Bapatla/011

    Reconstruction of High level Bridge @Km2/4 ofBapatla-Pandurangapuram Road across Perali

    drain in Guntur78/2010-2011

    1.12.201001.12.10 31.5.2012

    Approaches is inprogress

  • 7/30/2019 Mpr October 2012

    21/67

    MONTHLY REPORT

    20 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in GUNTUR District up to 31.10.2012

    Category Packages allotted under Phase - 1

    Names of works under each

    package

    Agreement No. /

    Date DHS DFC Progress up to 31.10.2012

    RCS

    NCRMP/B-W/AP/RCS/PRED/07/P

    Palem/001

    Road from R&B Road to

    Mandevaripalem

    /2010-11

    Dt.01.11.201101.11.11 31.10.2012

    Completed.

    Road from R&B Road Alluru to

    Yadavapalem

    /2010-11

    Dt.01.11.201101.11.11 31.10.2012 From Km 0.574 to km 0.964

    CC completed.

    NCRMP/B-

    W/AP/RCS/PRED/07/KarlaPalem/002

    Road from Ganapavaram R & B

    road to Pedamarpuvaripalem

    /2010-11

    Dt.01.11.201101.11.11 31.10.2012

    GSB is in Progress

    Road from R & B Road toChinapuluguvaripalem

    /2010-11Dt.01.11.2011

    01.11.11 31.10.2011GSB is in Progress

    Road from R & B road to

    Yaramvaripalem

    /2010-11

    Dt.01.11.201101.11.11 31.10.2011

    Completed.

    Road from R & B road to

    Pedagollapalem Cyclone Shelter

    /2010-11

    Dt.01.11.201101.11.11 31.10.201

    Completed.

    Pedagollapalem PR Road to

    Bonthagorlapalem

    /2010-11

    Dt.01.11.201101.11.11 31.10.201

    Shoulders is in progress .

    NCRMP/B-

    W/AP/RCS/PRED/07/Nizampatnam/003

    Road from R&B Road to

    Gurunadhanagar

    /2010-11 Dt.

    17.10.201117.10.11 16.07.12

    Shoulders is in progress.

    Road from R&B Road to Adavala

    H/O Bavajipalem

    /2010-11 Dt.

    17.10.201117.10.11 16.07.12

    Completed.

  • 7/30/2019 Mpr October 2012

    22/67

    MONTHLY REPORT

    21 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Road from R&B Road to

    Atlavaripalem

    /2010-11 Dt.

    17.10.201117.10.11 16.07.12 Completed

    NCRMP/B-

    W/AP/RCS/PRED/07/Bapatla/004

    Road from R&B Road to

    Hanumanthanagar 2010-11

    Dt13.10.201113.10.11 12.07.2012

    Completed.

    Road from R & B road to

    Adarsanagar Completed.

    Status of works in Prakasam District up to 31.10.2012

    CategoryPackages allotted

    under Phase - 1

    Names of worksunder each

    package

    Agreement No. /

    Date

    Milestone completion dates

    Progress up to

    31.10.2012

    Remarks

    First Second Third

    BRIDGESNCRMP/B-

    W/AP/Br/R&B/08/Kanaparthy/012

    Construction ofHigh level Bridge at

    Km 16/10 ofNaguluppalapadu Kanaparthy road inPrakasam District

    76/2010-11 Dated1/12/2010

    5/31/2011Completion

    up to silllevel

    12/31/2011Completion upto below deck

    slab

    5/31/2012Completion of

    entire workincluding

    approaches

    Bridge work iscompleted

    As permilestonecompleted

    RHBNCRMP/B-

    W/AP/RHB/PRED/08/S.Konda/001

    Road from PakalaZP Road to

    AulavaripalemCyclone shelter

    NCRMP/B-W/AP/RHB/PRED/0

    8/S.Konda/001Dated 25.04.2011

    8/24/2011Earth work,CD work,

    GSB

    12/24/2011WBM, Grade II

    & III

    4/24/2012 BT,Shoulders &road furniture

    CC Road &Shoulders workis Completed.

    Mile stone-IIIcompleted

    Road from R&BRoad to

    Somarajupalli

    NCRMP/B-W/AP/RHB/PRED/0

    8/S.Konda/001Dated 25.04.2011

    BT, CC road &culverts arecompleted fromKM 0/0 to 2/146.

    Mile stone-IIIcompleted

    Road from R&Broad to

    Narravaripalem

    NCRMP/B-W/AP/RHB/PRED/0

    8/S.Konda/001Dated 25.04.2011

    BT, & culvertsare Completedfrom KM 0/0 to0/900. work iscompleted

    Mile stone-IIIcompleted

  • 7/30/2019 Mpr October 2012

    23/67

    MONTHLY REPORT

    22 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002

    Road from NH5 toMulaguntapadu

    NCRMP/B-W/AP/RHB/PRED/0

    8/S.Konda/002dated 10/02/2011 6/9/2011

    Earth work,CD work,

    GSB

    10/9/2011WBM, Grade II& III

    2/9/2012 BT,Shoulders &road furniture

    WBM-Grade-IIILayer Completed.OGPC + Seal CoatTo be taken up

    Not Reached asper Mile stone-III(Awaiting for2nd EOT

    Proposal)

    Road from R&Broad to

    Chalivendradibba

    NCRMP/B-W/AP/RHB/PRED/0

    8/S.Konda/002dated -10/02/2011

    WBM-Grade-IIILayer Completed.OGPC + Seal CoatTo be taken up

    Not Reached asper Mile stone-III(Awaiting for2nd EOTProposal)

    NCRMP/B-W/AP/RHB/PRED/0

    8/S.Konda/002

    Road from PakalaR&B road to

    Mosanaladinne

    NCRMP/B-W/AP/RHB/PRED/0

    8/S.Konda/002dated 10/02/2011

    6/9/2011Earth work,CD work,

    GSB

    10/9/2011WBM, Grade II

    & III

    2/9/2012 BT,Shoulders &road furniture

    WBM-Grade-IIImaterial layingwork is in progress

    Not Reached asper Mile stone-III(Awaiting for2nd EOTProposal)

    Road from R&Broad to Binginapalli

    HarijanawadaCyclone Shelter

    NCRMP/B-W/AP/RHB/PRED/0

    8/S.Konda/002dated 10/02/2011

    CC road work iscompleted from KM0/0 to KM 0/220.shoulders work areto be taken up.

    Mile stone-III(Awaiting for 2

    nd

    EOT Proposal)

    NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/003

    Road from R&BRoad Allur to M T

    Raju colony

    NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/003

    Dated 27/04/2011

    8/26/2011Earth work,CD work,

    GSB

    12/26/2011WBM, Grade II

    & III

    4/26/2012 BT,Shoulders &road furniture

    BT, CC road,shoulders &culverts arecompleted from km

    0/0 to km 3/8.workis completed

    As permilestonecompleted

    NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/004

    Road from KEMR&B Road to

    Sankuvarigunta

    NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/004Dated 27/04/2011

    9/26/2011Earth work,CD work,

    GSB

    2/26/2012WBM, Grade II

    & III

    7/26/2012 BT,Shoulders &road furniture

    BT completed.CDwork completed.CCroad workcompleted from km0/0 to km 1/430and CC dip work iscompleted

    Reached Milestone-III

  • 7/30/2019 Mpr October 2012

    24/67

    MONTHLY REPORT

    23 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Road from KEM R& B Road to

    Pullareddypalem

    NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/004Dated 27/04/2011

    BT completed.CDwork completed.CCroad and shoulderswork completedfrom from km 0/0 to

    km 3/900.

    As permilestonecompleted

    NCRMP/B-W/AP/RHB/PRED/0

    8/Ulavapadu/07

    Road from MCRoad to

    SubbarayaduSatram

    NCRMP/B-W/AP/RHB/PRED/0

    8/Ulavapadu/07dated 27/04/2011

    8/26/2011Earth work,CD work,

    GSB

    12/26/2011WBM, Grade II

    & III

    4/26/2012 BT,Shoulders &road furniture

    BT completed.CDwork completed.CCroad and shoulderswork completedfrom from km km0/0 to km 4/4. workis completed

    As permilestonecompleted

    NCRMP/B-W/AP/RHB/PRED/0

    8/Ulavapadu/08

    Road from R&Broad Tettu to

    Ramayapatnam

    NCRMP/B-W/AP/RHB/PRED/0

    8/Ulavapadu/08dated 27/04/2011

    8/26/2011Earth work,CD work,

    GSB

    12/26/2011WBM, Grade II

    & III

    4/26/2012 BT,Shoulders &road furniture

    BT completed.CDwork completed.CCroad and shoulderswork completedfrom from km 0/0 to

    km 5/086. work iscompleted

    As permilestonecompleted

    NCRMP/B-W/AP/RHB/PRED/0

    8/Tangutur/09

    Road from R&Broad Pellur toVasepallipadu

    NCRMP/B-W/AP/RHB/PRED/0

    8/Tangutur/09dated 16/03/2011

    7/15/2011Earth work,CD work,

    GSB

    11/15/2011WBM, Grade II

    & III

    3/15/2012 BT,Shoulders &road furniture

    BT completed.CDwork completed.CCroad andshoulders workcompleted from km0/0 to km 4/5. workis completed

    As permilestonecompleted

    NCRMP/B-W/AP/RHB/PRED/0

    8/Tangutur/10

    Road from R&Broad to Kesupalem

    NCRMP/B-W/AP/RHB/PRED/0

    8/Tangutur/10

    dated 19/04/2011

    7/18/2011Earth work,CD work,

    GSB

    10/18/2011WBM, Grade II

    & II

    1/18/2012 BT,Shoulders &road furniture

    BT completed.CDwork completed.CCroad and shoulderswork completedfrom from km 0/0 tokm 2/103. work iscompleted

    As permilestonecompleted

    RCSNCRMP/B-

    W/AP/RCS/PRED/08/Vetapalem/001

    Road from R&Broad to

    Vijayanagaramcolony cyclone

    shelter

    NCRMP/B-W/AP/RCS/PRED/0

    8/Vetapalem/001dated 2011/12

    dated 30.09.2011

    1/29/2012Earth work,

    GSB

    5/29/2012shoulders, Gr-

    III

    9/29/2012 BT,CC pavement

    and roadfurniture

    cc road completed,BT roadcompleted&shoulderscompleted. Road from km0/0 to km 0/525.work is completed

    As permilestonecompleted

  • 7/30/2019 Mpr October 2012

    25/67

    MONTHLY REPORT

    24 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Road from NH roadto

    Challareddypalem

    cc road completed,BT roadcompleted&shoulderscompleted. Road

    from km 0/0 to km1/735. work iscompleted

    As permilestone

    completed

    Road from R&Broad to Jeevaraksh

    nagar colonycyclone shelter

    C.C.road andShoulders arecompleted Roadfrom km 0/0 to km0/500.

    As permilestonecompleted

    Road from R&Broad to Ramnagar

    colony cycloneshelter

    C.C.completedRoad from km 0/0to km0/475.Shoulders tobe taken up.

    Reached Milestone-III

    Road from R&Broad to cyclone

    shelter atMankenavaripalem

    CC roadcompleted.Shoulders work isto be taken up.

    Reached Milestone-III

    NCRMP/B-W/AP/RCS/PRED/0

    8/Chirala/002

    Road from R&BRoad to

    Keertivaripalemcyclone shelter NCRMP/B-

    W/AP/RCS/PRED/08/Chirala/002

    dated 27.08.2011

    C.C road andShoulders arecompleted from km0/0 to km 0/265.work is completed

    As permilestonecompleted

    Road from R&BRoad to Devinutula

    cyclone shelter ofChirala Mandal in

    Prakasham district.

    C.C road andShoulders are

    completed from km0/0 to km 0/800.work is completed

    As per

    milestonecompleted

    MPCSNCRMP/B-

    W/APMPCS/PRED/08/Ulavapadu/001

    Chakicharla cycloneshelter in

    Ulavapadu MandalPrakasam district

    NCRMP/B-W/AP/MPCS/PRED/08/Ulavapadu/001

    24.11.2011All items upto stilt floor

    slabincluding

    ramp, staircase

    24.02.2012 Allitems up tosecond floor

    slab includingfirst floor, andin 2nd floor

    including stair

    24.05.2012Head room,plastering,

    flooring, watersupply

    arrangements,sanitary fitting,

    Stilt floor, G.F , &Terrace floor-roof slabcompleted. Brickwork completed,Plastering work

    As permilestonecompleted

  • 7/30/2019 Mpr October 2012

    26/67

    MONTHLY REPORT

    25 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    foundations,columns,bea

    ms,pccflooring etc.,

    case, columnsetc.,

    electricalitems,

    compoundwall, cc

    pavement.

    Earthenmounds(raised

    portion), waterharvesting,septic tank,slump and

    soak pit.etc.

    completed,Cattleplatformcompletedrevitmrnt work

    completed,flooring work iscompleted,compound wall120 metersleangthcompleted,Electrical workiscompleted.work iscompleted

    NCRMP/B-W/APMPCS/PRED/

    08/NG Padu/003

    Kanaparthy cycloneshelter in

    NaguluppapaduMandal Prakasam

    district

    NCRMP/B-W/AP/MPCS/PRED/08/NG Padu/003

    23.11.2011All items upto stilt floor

    slabincluding

    ramp, staircase

    foundations,columns,bea

    ms,pccflooring etc.,

    23.02.2012 Allitems up to

    first floor slaband head

    room slab in 2nd floor

    including staircase, columns

    etc.,

    23.05.2012plastering,

    flooring, watersupply

    arrangements,sanitary fitting,

    electricalitems,

    compoundwall, cc

    pavement.Earthenmounds

    (raisedportion), water

    harvesting,septic tank,slump and

    soak pit.etc.

    Internal &

    ExternalPlasteringcompleted.Flooring WorkCompleted.Compound WallPaintingCompleted. CCRoad Completed.Shoulder workCompleted.Painting work in

    Completed.Electrical Fittingsin progress. Tilesin bathroomswork Completed.Water harvest &Soak pit work inprogress.

    Not as perMilestone

  • 7/30/2019 Mpr October 2012

    27/67

    MONTHLY REPORT

    26 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Status of works in Nellore District up to 31.10.2012

    (RCS)

    Package Number Name of Work Milestone1 Milestone2 Milestone3

    Progress up

    to 31.10.2012

    NCRMP/B-W/AP/09MUTHUKUR/RCS/002

    Road from R&B Roadkappaladoruvu to bandla Palem

    H.wada

    3Months: EarthWork, Pipe Culverts,

    GSB

    6 Months: WBMGrII,GrII,CC Pavement

    and Shoulders

    9 Months: BTCC road and

    Road Furniture

    OGPC+ Sealcoat completed

    NCRMP/B-W/AP/09/D.V.SATRAM/RCS/008

    Road from R&B road to SullurpetaMallam to berjengalapalli cyclone

    shelter 3Months: EarthWork, Pipe Culverts,

    GSB

    6 Months: WBM GrII,GrII Shoulders and

    CC Pavement

    9 Months: BT,CC Pavement

    and RoadFurniture

    OGPC+ Sealcoat completed

    NCRMP/B-

    W/AP/09T.P.GUDUR/RCS/005

    Road from7/2 M.C Road to

    venkannapalem pattapupalem work completed

    NCRMP/B-W/AP/09chillakur/RCS/004

    Road from Katuivaripalem R&Broad to vellapalm

    3Months: EarthWork,CD Works,

    GSB

    6 Months: WBM GrII,GrII and Shoulders

    9 Months: BT,CC Pavement

    and RoadFurniture

    OGPC+ Sealcoat completed

    NCRMP/B-W/AP/09kota/RCS/001

    road from R&B road to A.SPURAM 3Months: Earth

    Work, Pipe Culverts,GSB

    6 Months: WBM GrII,GrII and Shoulders

    9 Months: BT,CC Pavement

    and RoadFurniture

    OGPC+ Sealcoat completed

    Road from GD Road toVavillapalem

    OGPC+ Sealcoat completed

    NCRMP/B-W/AP/RCS/PRED/09/KAVALI/007

    Road from Kotha Satram R&B toIndiranagar (via) Thumalapenta

    palam, Patharavadu palam,Ramudu palam, Karaduvari palam&Sreeramapuram in SPSR Nellore

    District.

    4Months: EarthWork, Pipe Culverts,

    GSB

    4 Months: WBM GrII,GrII , Shoulders and

    CC Pavement

    4 Months: BT,CC Pavement

    and RoadFurniture

    OGPC+ Sealcoat completed

  • 7/30/2019 Mpr October 2012

    28/67

    MONTHLY REPORT

    27 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-W/AP/RCS/PRED/09/KAVALI/006

    Road Connecting R&B Roadthrough Voter Village in SPSRNellore District.

    4 Months: EarthWork, Pipe Culverts,GSB

    4 Months: WBM GrII,GrII , Shoulders andCC Pavement

    4 Months: BT,

    CC Pavementand RoadFurniture

    GSB. From0.00 to 2.0800

    ,WBM Gr-II ,Gr-III from 0.00 to

    5.320 and

    OGPC+SC 0/6to 2/6is in

    completed,6nos pipeculverts iscompleted

    Status of works in Nellore District up to 31.10.2012

    RHB

    NCRMP/B-

    W/AP/RHB/PRED/09RHB/KAVALI/004

    Road from5/8 ofChennayapalem Road to

    Gummadi bandla5Months:

    Earthwork, CD

    Works,ccpavementand GSB

    10 Months:

    WBM GrII, GrIIand Shoulders

    15 Months:

    BT and RoadFurniture

    OGPC+ Seal coat completed

    Road from PedattapupalemR&B road to

    Chennayapalem H.wadaOGPC+ Seal coat completed

    Road from K.T R&B Road toAlliguntapalem

    OGPC+ Seal coat completed

    NCRMP/B-W/AP/RHB/PRED/09BOGOLU/RHB/002

    Road from 1/6 ofJuvvaladinne R&B Road to

    Tellagunta KM to 2/720

    3Months: EarthWork, Pipe

    Culverts, GSB

    6 Months:WBM GrII, GrIIand Shoulders

    9 Months: BTand RoadFurniture

    OGPC+ Seal coat completed

    NCRMP/B-W/AP/RHB/PRED/09BOGOLO/RHB/001

    1. Road from NH5 toSambasivapuram

    5Months: EarthWork, Pipe

    Culverts, GSB

    10 Months:WBM GrII, GrIIand Shoulders

    15 Months:BT and Road

    FurnitureOGPC+ Seal coat completed

  • 7/30/2019 Mpr October 2012

    29/67

    MONTHLY REPORT

    28 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Road from 9/6 ofJuvvaladinne R&B Road to11/0 of Juvvaladinne R&BRoad Via Venkateshpalem

    OGPC+ Seal coat completed

    NCRMP/B-W/AP/RHB/PRED/09/VIDAVALURU/005

    1)Road from kt R&B ROADTO ALLAGANIPADU to

    Vavilla5Months: Earth

    Work, PipeCulverts, GSB

    10 Months:WBM GrII, GrIIand Shoulders

    15 Months:BT and Road

    Furniture

    OGPC+ Seal coat completed

    Road from R&B roadKancharapalem HW to

    Alaganipadu.Embankment is in progress

    NCRMP/B-W/AP/RHB/PRED/09V.CHALEM/RHB/007

    ROAD FROM SUVEPALLI-PUDIPARTHI ROAD TO

    SRIKANTH COLONY 4Months: EarthWork, Pipe

    Culverts, GSB

    8 Months:WBM GrII, GrIIand Shoulders

    12 Months:BT and Road

    Furniture

    OGPC+ Seal coat completed

    providing BT Surface to theroad from R&B road to

    Edagali KandrigaOGPC+ Seal coat completed

    NCRMP/B-W/AP/RHB/PRED/09CHITTAMURU/003

    Road from R&B Road toMuttembake Via

    Pittuvanipalli 5Months: EarthWork, Pipe

    Culverts, GSB

    10 Months:WBM GrII, GrII

    and Shoulders

    15 Months:BT and Road

    Furniture

    OGPC+ Seal coat completed

    Road from R&B Chittamur toSoma Samudram

    OGPC+ Seal coat completed

    NCRMP/B-W/AP/09/MUTHUKUR/RHB/006

    Road from R&B road toPatuvariKandriga

    3Months: EarthWork, Pipe

    Culverts, GSB

    6 Months:WBM

    GrII,GrII,CCPavement and

    Shoulders

    9 Months: BTand RoadFurniture

    OGPC+ Seal coat completed

  • 7/30/2019 Mpr October 2012

    30/67

    MONTHLY REPORT

    29 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-W/AP/09Allur/RHB/009Road from R&Broad alluru toGalidibbalu (via)Chukavani

    dibba

    5Months: EarthWork, Pipe

    Culverts, GSB

    10 Months:WBM GrII, GrIIand Shoulders

    15 Months:BT and Road

    FurnitureOGPC+ Seal coat completed

    NCRMP/B-W/AP/RHB/PRED/009/T.P.GUDUR/012

    Ring Road to TP Gudur-Salipeta R & B Road via CS

    Puram and MandapamVillage 3Months: Earth

    Work, PipeCulverts, GSB

    6 Months:WBM

    GrII,GrII,CCPavement and

    Shoulders

    9 Months: BTand RoadFurniture

    OGPC+ Seal coat completed

    Road from R & B Road C SPuram to Sivaramapuram

    OGPC+ Seal coat completed

  • 7/30/2019 Mpr October 2012

    31/67

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    6.0 District wise status of tests conducted by TPQA:

    Apart from monitoring the tests being conducted by the implementation team (contractors & Line department) at various

    stages, the Third party Quality Audit team also conducted tests to confirm its compliance with the standards. These tests are

    carried out in the site itself and in some cases samples are collected and testing done in outside laboratories. The details of

    tests conducted in the field till end of September 2011 are presented.

    Summary of QC Tests - Up to 31.10.2012

    S.No. District

    No. TestsConductedduring the

    Month

    Total no. of TestsCumulativeTests Done

    Total no. of Tests

    Passed Failed Passed Failed

    1 Srikakulam 8 6 2 1364 1358 6

    2 Vizianagaram 34 34 0 400 400 0

    3 Visakhapatnam 72 72 0 2043 1997 46

    4 East Godavari 30 30 0 1016 1016 0

    5 West Godavari 0 0 0 349 349 0

    6 Krishna 3 3 0 82 82 0

  • 7/30/2019 Mpr October 2012

    32/67

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    7.0 Details of Quality Control Audit Reports Submitted During this Month:

    Package Number Name of Work District

    NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002

    Construction of cyclone shelter atBangarampeta in Nakkapalli Mandal

    Vishakhapatnam

    NCRMP/B-W/AP/RCS/PRED/07/Nizampatnam/0

    03

    Road from R&B Road toGurunadhanagar

    Guntur

  • 7/30/2019 Mpr October 2012

    33/67

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002

    Construction of cyclone shelter atPatimeeda in Nakkapalli Mandal

    Vishakhapatnam

    NCRMP/B-W/AP/MPCS/PRED/04/Thondangi/001

    Construction of Cyclone Shelter atAvulamanda

    East Godavari

    NCRMP/B-W/AP/MPCS/PRED/04/Thondangi/001

    Construction of Cyclone Shelter atLakshmanudipeta

    East Godavari

    NCRMP/B-

    W/AP/MPCS/PRED/04/Uppalaguptam/002

    Construction of Cyclone Shelter at

    Pedaraghavulapeta East Godavari

    NCRMP/BW/AP/BR/R&B/001/Bendigadda/004

    Construction of HLB AcrossBendigadda At KM 4/10 of Pundi to

    Parlakimidi roadSrikakulam

    NCRMP/BW/AP/BR/R&B/001/Patnavanipeta/001

    Construction of HLB Act KM 11/6-8 ofNH-5 to Patnavanipeta Road Via

    Tamada connecting SundarapalemSrikakulam

    NCRMP/BW/AP/BR/R&B/001/Surampeta/003

    Construction of Minor bridge At KM12/2-4 of Nh-5 to Surampeta road viaNaruva, Mentada

    Srikakulam

    NCRMP/B-W/AP/MPCS/PRED/01/Santhabommal

    i/005

    Construction of cyclone shelter atRunku in Santhabommali Mandal

    Srikakulam

    8.0 Details of Environmental and Social Reports Submitted During this Month:

    Package Number Name of Work District

    NCRMP/B- Reconstruction of HLB @ Km 5/2 of Guntur

  • 7/30/2019 Mpr October 2012

    34/67

    MONTHLY REPORT

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    NCRMP/B-W/AP/RCS/PRED/O7/Nizampatnam/0

    03

    Road from R&B Road toGurunadhanagar

    Guntur

    NCRMP/B-W/AP/RCS/PRED/O7/PVPalem/001

    Road from R&B Road Alluru toYadavapalem

    Guntur

    NCRMP/B-W/AP/MPCS/PRED/O4/Thondangi/00

    3

    Construction of Cyclone Shelter atLakshmanudipeta

    East Godavari

    NCRMP/B-W/AP/MPCS/PRED/O4/Uppalaguptam/002

    Construction of Cyclone Shelter atPedaraghavulapeta East Godavari

    NCRMP/B-W/AP/RCS/PRED/O4/Uppalaguptam/

    003

    Road from R&B Road toChinaraghavulapeta

    East Godavari

    NCRMP/B-

    W/AP/MPCS/PRED/O4/Thondangi/003

    Construction of Cyclone Shelter at

    Avulamanda

    East Godavari

    NCRMP/B-W/AP/RHB/PRED/O8/S.Konda/002

    Road from NH5 to Mulaguntapadu Prakasam

  • 7/30/2019 Mpr October 2012

    35/67

    MONTHLY REPORT

    34 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Consolidated E&S Report for Guntur District in the Month of October 2012:

    Third Party Quality Audit for Construction of Cyclone Shelters, Roads toCyclone Shelters & Habitations, Bridges and Culverts under NCRMP (Detailsof Guntur in October,2012)

    S.No Activity Measures to be implemented by the contractor COMPLICEDNOT

    COMPLICEDNOT

    APPLICABLETOTAL

    1Work Plan forEMPimplementation

    The Contractors Project Manager shall be responsible forimplementation of EMP provisions and will coordinate the over-allimplementation of the said plan. Along with the Work Programme, theContractor shall submit a plan including method statement and timelineabout specific actions that will be taken by him to implement theprovisions laid out in the EMP

    7 7

    2RegulatoryPermissions andConsents

    The Contractor shall obtain all requisite statutory clearances prior tocommencement of civil works, which includes obtainingpermission/consent for plants, water and extraction and borrow areasoperations. This includes:

    Consent for establishment and operation of plant (for concretework) from SPCB.

    7 7

    PUC certification for all vehicles/equipment used for/duringconstruction.

    7 7

    Permission/consent of the District Administration/MiningDepartment/other agencies for quarrying and/or borrowing operations formaterials like sand and earth.

    7 7

    Permission for water extraction, if applicable in the local areacontext.

    7 7

    The Contractor shall abide by all conditions laid out in the saidclearances.

    7 7

    3Consultation andCommunityConsent

    The Contractor shall consult and obtain written consents oflandowners(individual/panchayat/govt. agency) for temporary use of landfor all construction related activities including:

    a) Setting-up and operation of construction camp including labourcamps, stock yards etc.

    7 7

    b) borrow areas and 7 7

  • 7/30/2019 Mpr October 2012

    36/67

    MONTHLY REPORT

    35 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    c) Disposal of debris and other waste material. 7 7

    4Construction/Labour Camp

    a) Location: The camp and plant site/s location and establishment shallbe done in a manner that does not interfere or disturb the activities oflocal inhabitants, particularly those of schools and health facilities.Written permission (no objection certificate) shall be taken from the

    Gramsabha and the land owner prior to location selection and a copyshall be submitted to the Engineer approval.

    7 7

    b) Camp site shall not be located within 250mts. From a water bodyincluding village ponds.

    7 7

    c) A distance of at least 500mts. Shall be maintained fromdesignated/protected natural habitats (such as National Parks,Sanctuaries, Biosphere Reserves, Reserve Forests and Ramsar Sites)and Coastal Regulation Zone.

    7 7

    b) Accommodation and Basic Amenities: All weather shelter with therequired tenement size and toilets shall be provided, as per provisions ofLabour Laws. Separate toilet facilities shall be provided for women

    workers. If a common mess is not provided/operated additional space forcooking shall be provided. The contractor shall ensure that hygienicconditions are maintained during the operation of such camps/facilities.

    7 7

    c) Fuel for Cooking: The Contractor shall ensure that fuel wood is notused as a cooking medium in the construction /labour camp.

    7 7

    d) Potable water supply: Drinking water supply of at least 40Ipcd withthe required supply points shall be provided.

    7 7

    e) Fire Safety: Adequate fire safety precautions shall be taken andrequired fire safety equipment (such as fire extinguishers) shall beprovided by the contractor.

    7 7

    5 Site Clearance

    a) NO tree cutting is to carried out without the written instruction from

    the Employer, who in turn will ensure that relevant regulatorypermission/s (including those from Forest Dept., if required) are obtainedprior to cutting of such trees.

    7 7

    b) The non-timber grade trees are to be stacked and possession is tobe given to Employer/concerned Govt. Department.

    7 7

    c) The Contractor shall strip, store and preserve top soil from the site ofconstruction work and in the stock yards prior to stacking of materials.The top soil shall be reinstated in the cyclone shelter compound after the

    7 7

  • 7/30/2019 Mpr October 2012

    37/67

    MONTHLY REPORT

    36 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    construction is over.

    6Protection ofProperties andResources

    The Contractor shall take due care to protect and prevent damages tothe following resources during preparatory and construction work:

    a) Water supply lines 7 7

    b) Irrigation canals 7 7

    c) Cart, cattle and/or foot trail/tracks 7 7

    d) Cultural properties and sites/structures of religious importance 7 7

    e) Houses, Farmlands, Orchids and/or Trees. 7 7

    f) School and other existing buildings adjacent to the site ofconstruction.

    7 7

    In case of damage due to construction activity, the restoration/repairsshall be carried out by the contractor at his own cost.

    7 7

    7 QuarryOperations

    The Contractor shall procure material from quarries that have beenapproved/licensed by the State Govt. A copy of such an approval shallbe submitted to the Engineer prior to procuring material.

    7

    8 Borrow Areas

    a) Borrow areas for the project will be selected by the Contractorfollowing the stipulations given below: The finalisation of all suchlocations shall be dependent on the approval of the Engineer ontechnical and environmental grounds. This includes on-site verification tocross-check the accuracy of details provided by the contractor. Onlyafter receipt of the written approval from the Engineer, the Contractorshall enter into a formal agreement with landowner.

    7 7

    b) The Contractor shall not procure any kind of construction material(such as aggregates, sand and earth) from ecologically protected areas.

    7 7

    c) Identification and Selection:1. The borrow area should not be located in agriculture fields/ unlessunavoidable i.e. barren land is not available. In case borrowing needs tobe done on an agricultural land, top-soil stripping, stacking andpreservation is must.

    7 7

    2. Borrow pits shall not be located within a distance of 100mts. Fromany NH, SH or other roads.

    7 7

  • 7/30/2019 Mpr October 2012

    38/67

    MONTHLY REPORT

    37 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    3. Borrow pits shall be preferably located 500mts. away fromsettlements/habitations.

    7 7

    4. No borrow pits shall be located within 500mts. from schools,colleges, playgrounds, religious structures and health centres.

    7 7

    5. No borrow area shall be opened with in 500mts. from a reserved or

    protected forest area, protected sites, wildlife movement zone andcultural heritage site.

    7 7

    6. No tree cutting shall be undertaken. 7 7

    7. Borrow area near any surface water body will be at least 100mts.away.

    7 7

    d) Operation 7

    1. Area up to which material will be extracted shall be cleareddemarcated on ground.

    7 7

    2. A 15cm topsoil layer will be stripped and preserved in stockpiles. 7 7

    3. Borrowing of earth should be preferably limited to a depth of 1.5mtr

    from the existing ground level.

    7 7

    4. Slope at the edges will be maintained not steeper than 2:3 (Vertical: Horizontal)

    7 7

    e) Rehabilitation of Borrow Areas:

    1. Rehabilitation shall be satisfactory undertaken immediately after theuse has ceased and at least three weeks prior to monsoon

    7 7

    2. Preserved top soil has be spread uniformly over land (except incases where borrow area is developed as a water body) used as aborrow area.

    7 7

    9Water Extraction/Use

    Water for construction and for use at construction camps (includinglabour camps) is to be extracted with prior written permission of(a) the

    individual owner, in case the source is private well/tube well; (b) GramPanchayat in case the source belongs to community: and (c) IrrigationDepartment in case the source is an irrigation canal or river.

    7 1

    10Safety of RoadUsers and LocalResidents

    a) Traffic safety arrangements (including provision of warning signage,speed breakers etc.) shall be made by the contractor to ensure safety ofroad users and local people, particularly in the internal village roadswhich will be used for transporting materials.

    7 1

  • 7/30/2019 Mpr October 2012

    39/67

    MONTHLY REPORT

    38 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    b) Material shall be covered during transportation to prevent spillage,accidents and pollution.

    7 1

    c) All required measures to ensure safety of local residents includingchildren and other near-by residents shall be taken up by the Contractor.This shall include provisions to prevent un authorised entry into the

    construction.

    7 1

    11 Workers Safety

    a) All measures required for ensuring safety and health of the workersshall be taken up by the Contractor. This includes provision andenforcement of appropriate personal protective equipment; first aidfacility; emergency response arrangement; proper storage ofhazardous/toxic and polluting materials and; measures for ensuring fireelectrical and mechanical safety arrangements in camp and in work site.

    7 1

    b) All methods steps and measures are required for ensuring safety ofworkers, particularly those needed while undertaking work in or aroundexcavations; workings at height; and; while handling inflammable, toxicand/or hazardous materials shall be ensured by the contractor.

    7 1

    c) Material safety data sheet record of fuel and other inflammablechemicals shall be maintained at the site. 7 1

    12 Air pollut ion a) Wind barriers or screens shall be provided in the downwinddirection at air pollution causing sources like plant sites and fine materialstorage stock yards

    7 1

    b) Fugitive dust emissions have to be eliminated by providing dustsuppression/control measures, such as water sprinkling and cover onmaterials, based on activity and site conditions.

    7 1

    c) All plants and equipment shall comply with pollution control norms. 7 1

    d) Water shall be sprinkled at least twice during dry day on haulageroads passing through or near settlements(including at least 100mbefore the settlement)

    7 1

    13 Water Pollution

    a) All measures (including provision of temporary silt fencing tocontrol sediment run-off) required for avoiding adverse impacts to waterbodies (such as ponds, streams, canals and rivers), water sources (suchas hand pumps and wells) and adjacent farmland shall be undertaken bythe Contractor.

    7 1

    b) Storage of materials like fuel, chemicals, and cement shall be donein a manner (with impervious layer on bottom and a covered shed ontop) that does not contaminate land and ground/surface water.

    7 1

  • 7/30/2019 Mpr October 2012

    40/67

    MONTHLY REPORT

    39 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    14 Noise Pollution

    a) All noise causing activities shall be stopped during night time (9.00PM to 6.00 AM). The Contractor shall schedule construction works inconsultation with local Panchayat Authority and School Principal toensure least disturbance to school children and other adjacent residents.

    1

    b) Ear plugs shall be provided to the labour facing risk from high

    noise pollution such as plant site and those working near generators,heavy equipment /machinery.

    7 1

    c) Appropriate noise controlling devices including acoustic generatorsshall be used to minimise noise during construction work and operationof camp.

    7 1

    15Disposal Debris/wastes

    a) Debris and other construction waste, if any, shall be disposed inlocations pre-approved by the Engineer in a manner that it does notcontaminate the environment.

    7 1

    b) Location of Debris Disposal Sites: Debris disposal sites shall belocated preferably away from farmlands, water sources and waterbodies. In no case, debris shall be disposed within 500mts. ofecologically sensitive areas, including forests, wetlands and protected

    natural habitats.

    7 1

    16Restoration andRehabilitation ofSites

    All work sites and areas under temporary use (including construction andlabour camps, plant, sites, haul roads and borrow areas) shall berestored/rehabilitated to a better condition (if not at least to its originalcondition) and to the satisfaction of the Engineer and land owner uponcompletion of construction work by the Contractor.

    7 1

    Completion of work(as covered under clause 55.1 of GCC) will alsoinclude completion of rehabilitation and clean-up of the work sitesincluding camps, plants, in and around the construction site; disposal ofdebris/construction wastes at pre-approved locations and; restoration ofborrow areas and other sites/ locations used for material sourcing.

    7 1

    17 Liabilities

    Any liability arising out of Contractors agreement with landowners/ localpeople/gram anchayat ( including those related to temporary use of land,water extraction and disposal of debris) shall be settled by theContarctor.

    7 1

    MONTHLY REPORT

  • 7/30/2019 Mpr October 2012

    41/67

    MONTHLY REPORT

    40 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Consolidated E&S Report for East Godavari District in the Month of October 2012:

    Third Party Quality Audit for Construction of Cyclone Shelters, Roads to

    Cyclone Shelters & Habitations, Bridges and Culverts under NCRMP (Detailsof East Godavari in October,2012)

    S.No Activity Measures to be implemented by the contractor COMPLICEDNOT

    COMPLICEDNOT

    APPLICABLETOTAL

    1Work Plan forEMPimplementation

    The Contractors Project Manager shall be responsible forimplementation of EMP provisions and will coordinate the over-allimplementation of the said plan. Along with the Work Programme, theContractor shall submit a plan including method statement and timelineabout specific actions that will be taken by him to implement theprovisions laid out in the EMP

    4 4

    2RegulatoryPermissions andConsents

    The Contractor shall obtain all requisite statutory clearances prior tocommencement of civil works, which includes obtainingpermission/consent for plants, water and extraction and borrow areasoperations. This includes:

    Consent for establishment and operation of plant (for concretework) from SPCB.

    4 4

    PUC certification for all vehicles/equipment used for/duringconstruction.

    4 4

    Permission/consent of the District Administration/MiningDepartment/other agencies for quarrying and/or borrowing operations formaterials like sand and earth.

    4 4

    Permission for water extraction, if applicable in the local area

    context. 4 4The Contractor shall abide by all conditions laid out in the said

    clearances.4 4

    3Consultation andCommunityConsent

    The Contractor shall consult and obtain written consents oflandowners(individual/panchayat/govt. agency) for temporary use of landfor all construction related activities including:

    a) Setting-up and operation of construction camp including labourcamps, stock yards etc.

    4 4

    MONTHLY REPORT

  • 7/30/2019 Mpr October 2012

    42/67

    MONTHLY REPORT

    41 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    b) borrow areas and 4

    c) Disposal of debris and other waste material. 4

    4Construction/Labour Camp

    a) Location: The camp and plant site/s location and establishment shallbe done in a manner that does not interfere or disturb the activities oflocal inhabitants, particularly those of schools and health facilities.

    Written permission (no objection certificate) shall be taken from theGramsabha and the land owner prior to location selection and a copyshall be submitted to the Engineer approval.

    4 4

    b) Camp site shall not be located within 250mts. From a water bodyincluding village ponds.

    4 4

    c) A distance of at least 500mts. Shall be maintained fromdesignated/protected natural habitats (such as National Parks,Sanctuaries, Biosphere Reserves, Reserve Forests and Ramsar Sites)and Coastal Regulation Zone.

    4 4

    b) Accommodation and Basic Amenities: All weather shelter with therequired tenement size and toilets shall be provided, as per provisions of

    Labour Laws. Separate toilet facilities shall be provided for womenworkers. If a common mess is not provided/operated additional space forcooking shall be provided. The contractor shall ensure that hygienicconditions are maintained during the operation of such camps/facilities.

    4 4

    c) Fuel for Cooking: The Contractor shall ensure that fuel wood is notused as a cooking medium in the construction /labour camp.

    4 4

    d) Potable water supply: Drinking water supply of at least 40Ipcd withthe required supply points shall be provided.

    4 4

    e) Fire Safety: Adequate fire safety precautions shall be taken andrequired fire safety equipment (such as fire extinguishers) shall beprovided by the contractor.

    4 4

    5 Site Clearance

    a) NO tree cutting is to carried out without the written instruction fromthe Employer, who in turn will ensure that relevant regulatorypermission/s (including those from Forest Dept., if required) are obtainedprior to cutting of such trees.

    4 4

    b) The non-timber grade trees are to be stacked and possession is tobe given to Employer/concerned Govt. Department.

    4 4

    MONTHLY REPORT

  • 7/30/2019 Mpr October 2012

    43/67

    MONTHLY REPORT

    42 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    c) The Contractor shall strip, store and preserve top soil from the site ofconstruction work and in the stock yards prior to stacking of materials.The top soil shall be reinstated in the cyclone shelter compound after theconstruction is over.

    4 4

    6Protection ofProperties andResources

    The Contractor shall take due care to protect and prevent damages to

    the following resources during preparatory and construction work:a) Water supply lines 4 4

    b) Irrigation canals 1 3 4

    c) Cart, cattle and/or foot trail/tracks 4 4

    d) Cultural properties and sites/structures of religious importance 4 4

    e) Houses, Farmlands, Orchids and/or Trees. 2 2 4

    f) School and other existing buildings adjacent to the site ofconstruction.

    1 3 4

    In case of damage due to construction activity, the restoration/repairsshall be carried out by the contractor at his own cost.

    4 4

    7QuarryOperations

    The Contractor shall procure material from quarries that have beenapproved/licensed by the State Govt. A copy of such an approval shallbe submitted to the Engineer prior to procuring material.

    4 4

    8 Borrow Areas

    a) Borrow areas for the project will be selected by the Contractorfollowing the stipulations given below: The finalisation of all suchlocations shall be dependent on the approval of the Engineer ontechnical and environmental grounds. This includes on-site verification tocross-check the accuracy of details provided by the contractor. Onlyafter receipt of the written approval from the Engineer, the Contractorshall enter into a formal agreement with landowner.

    4 4

    b) The Contractor shall not procure any kind of construction material(such as aggregates, sand and earth) from ecologically protected areas.

    4 4

    c) Identification and Selection:

    1. The borrow area should not be located in agriculture fields/ unlessunavoidable i.e. barren land is not available. In case borrowing needs tobe done on an agricultural land, top-soil stripping, stacking andpreservation is must.

    4 4

    2. Borrow pits shall not be located within a distance of 100mts. Fromany NH, SH or other roads.

    4 4

    MONTHLY REPORT

  • 7/30/2019 Mpr October 2012

    44/67

    MONTHLY REPORT

    43 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    3. Borrow pits shall be preferably located 500mts. away fromsettlements/habitations.

    4 4

    4. No borrow pits shall be located within 500mts. from schools,colleges, playgrounds, religious structures and health centres.

    4 4

    5. No borrow area shall be opened with in 500mts. from a reserved or

    protected forest area, protected sites, wildlife movement zone andcultural heritage site.

    4 4

    6. No tree cutting shall be undertaken. 4 4

    7. Borrow area near any surface water body will be at least 100mts.away.

    4 4

    d) Operation

    1. Area up to which material will be extracted shall be cleareddemarcated on ground.

    4 4

    2. A 15cm topsoil layer will be stripped and preserved in stockpiles. 4 4

    3. Borrowing of earth should be preferably limited to a depth of 1.5mtrfrom the existing ground level.

    4 4

    4. Slope at the edges will be maintained not steeper than 2:3 (Vertical: Horizontal)

    4

    e) Rehabilitation of Borrow Areas:

    1. Rehabilitation shall be satisfactory undertaken immediately after theuse has ceased and at least three weeks prior to monsoon

    4 4

    2. Preserved top soil has be spread uniformly over land (except incases where borrow area is developed as a water body) used as aborrow area.

    4 4

    9

    Water Extraction

    /Use

    Water for construction and for use at construction camps (includinglabour camps) is to be extracted with prior written permission of(a) the

    individual owner, in case the source is private well/tube well; (b) GramPanchayat in case the source belongs to community: and (c) IrrigationDepartment in case the source is an irrigation canal or river.

    4 4

    10Safety of RoadUsers and LocalResidents

    a) Traffic safety arrangements (including provision of warning signage,speed breakers etc.) shall be made by the contractor to ensure safety ofroad users and local people, particularly in the internal village roadswhich will be used for transporting materials.

    4 4

    MONTHLY REPORT

  • 7/30/2019 Mpr October 2012

    45/67

    MONTHLY REPORT

    44 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    b) Material shall be covered during transportation to prevent spillage,accidents and pollution.

    4 4

    c) All required measures to ensure safety of local residents includingchildren and other near-by residents shall be taken up by the Contractor.This shall include provisions to prevent un authorised entry into the

    construction.

    4 4

    11 Workers Safety

    a) All measures required for ensuring safety and health of the workersshall be taken up by the Contractor. This includes provision andenforcement of appropriate personal protective equipment; first aidfacility; emergency response arrangement; proper storage ofhazardous/toxic and polluting materials and; measures for ensuring fireelectrical and mechanical safety arrangements in camp and in work site.

    4 4

    b) All methods steps and measures are required for ensuring safety ofworkers, particularly those needed while undertaking work in or aroundexcavations; workings at height; and; while handling inflammable, toxicand/or hazardous materials shall be ensured by the contractor.

    4 4

    c) Material safety data sheet record of fuel and other inflammablechemicals shall be maintained at the site. 4 4

    12 Air pollut ion a) Wind barriers or screens shall be provided in the downwinddirection at air pollution causing sources like plant sites and fine materialstorage stock yards

    4 4

    b) Fugitive dust emissions have to be eliminated by providing dustsuppression/control measures, such as water sprinkling and cover onmaterials, based on activity and site conditions.

    4 4

    c) All plants and equipment shall comply with pollution control norms. 4 4

    d) Water shall be sprinkled at least twice during dry day on haulageroads passing through or near settlements(including at least 100mbefore the settlement)

    4 4

    13 Water Pollution

    a) All measures (including provision of temporary silt fencing tocontrol sediment run-off) required for avoiding adverse impacts to waterbodies (such as ponds, streams, canals and rivers), water sources (suchas hand pumps and wells) and adjacent farmland shall be undertaken bythe Contractor.

    4 4

    b) Storage of materials like fuel, chemicals, and cement shall be donein a manner (with impervious layer on bottom and a covered shed ontop) that does not contaminate land and ground/surface water.

    2 2 4

    MONTHLY REPORT

  • 7/30/2019 Mpr October 2012

    46/67

    MONTHLY REPORT

    45 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    14 Noise Pollution

    a) All noise causing activities shall be stopped during night time (9.00PM to 6.00 AM). The Contractor shall schedule construction works inconsultation with local Panchayat Authority and School Principal toensure least disturbance to school children and other adjacent residents.

    4

    b) Ear plugs shall be provided to the labour facing risk from high

    noise pollution such as plant site and those working near generators,heavy equipment /machinery.

    4 4

    c) Appropriate noise controlling devices including acoustic generatorsshall be used to minimise noise during construction work and operationof camp.

    4 4

    15Disposal Debris/wastes

    a) Debris and other construction waste, if any, shall be disposed inlocations pre-approved by the Engineer in a manner that it does notcontaminate the environment.

    4 4

    b) Location of Debris Disposal Sites: Debris disposal sites shall belocated preferably away from farmlands, water sources and waterbodies. In no case, debris shall be disposed within 500mts. ofecologically sensitive areas, including forests, wetlands and protected

    natural habitats.

    4 4

    16Restoration andRehabilitation ofSites

    All work sites and areas under temporary use (including construction andlabour camps, plant, sites, haul roads and borrow areas) shall berestored/rehabilitated to a better condition (if not at least to its originalcondition) and to the satisfaction of the Engineer and land owner uponcompletion of construction work by the Contractor.

    4 4

    Completion of work(as covered under clause 55.1 of GCC) will alsoinclude completion of rehabilitation and clean-up of the work sitesincluding camps, plants, in and around the construction site; disposal ofdebris/construction wastes at pre-approved locations and; restoration ofborrow areas and other sites/ locations used for material sourcing.

    4 4

    17 Liabilities

    Any liability arising out of Contractors agreement with landowners/ local

    people/gram anchayat ( including those related to temporary use of land,water extraction and disposal of debris) shall be settled by theContarctor.

    4 4

    MONTHLY REPORT

  • 7/30/2019 Mpr October 2012

    47/67

    MONTHLY REPORT

    46 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    Consolidated E&S Report for Prakasam District in the Month of October 2012:

    Third Party Quality Audit for Construction of Cyclone Shelters, Roads to

    Cyclone Shelters & Habitations, Bridges and Culverts under NCRMP (Detailsof Prakasam in October,2012)

    S.No Activity Measures to be implemented by the contractor COMPLICEDNOT

    COMPLICEDNOT

    APPLICABLETOTAL

    1Work Plan forEMPimplementation

    The Contractors Project Manager shall be responsible forimplementation of EMP provisions and will coordinate the over-allimplementation of the said plan. Along with the Work Programme, theContractor shall submit a plan including method statement and timelineabout specific actions that will be taken by him to implement theprovisions laid out in the EMP

    1 1

    2RegulatoryPermissions andConsents

    The Contractor shall obtain all requisite statutory clearances prior tocommencement of civil works, which includes obtainingpermission/consent for plants, water and extraction and borrow areasoperations. This includes:

    Consent for establishment and operation of plant (for concretework) from SPCB.

    1 1

    PUC certification for all vehicles/equipment used for/duringconstruction.

    1 1

    Permission/consent of the District Administration/MiningDepartment/other agencies for quarrying and/or borrowing operations formaterials like sand and earth.

    1 1

    Permission for water extraction, if applicable in the local area

    context. 1 1The Contractor shall abide by all conditions laid out in the said

    clearances.1 1

    3Consultation andCommunityConsent

    The Contractor shall consult and obtain written consents oflandowners(individual/panchayat/govt. agency) for temporary use of landfor all construction related activities including:

    a) Setting-up and operation of construction camp including labourcamps, stock yards etc.

    1 1

    MONTHLY REPORT

  • 7/30/2019 Mpr October 2012

    48/67

    MONTHLY REPORT

    47 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    b) borrow areas and 1 1

    c) Disposal of debris and other waste material. 1 1

    4Construction/Labour Camp

    a) Location: The camp and plant site/s location and establishment shallbe done in a manner that does not interfere or disturb the activities oflocal inhabitants, particularly those of schools and health facilities.

    Written permission (no objection certificate) shall be taken from theGramsabha and the land owner prior to location selection and a copyshall be submitted to the Engineer approval.

    1 1

    b) Camp site shall not be located within 250mts. From a water bodyincluding village ponds.

    1 1

    c) A distance of at least 500mts. Shall be maintained fromdesignated/protected natural habitats (such as National Parks,Sanctuaries, Biosphere Reserves, Reserve Forests and Ramsar Sites)and Coastal Regulation Zone.

    1 1

    b) Accommodation and Basic Amenities: All weather shelter with therequired tenement size and toilets shall be provided, as per provisions of

    Labour Laws. Separate toilet facilities shall be provided for womenworkers. If a common mess is not provided/operated additional space forcooking shall be provided. The contractor shall ensure that hygienicconditions are maintained during the operation of such camps/facilities.

    1 1

    c) Fuel for Cooking: The Contractor shall ensure that fuel wood is notused as a cooking medium in the construction /labour camp.

    1 1

    d) Potable water supply: Drinking water supply of at least 40Ipcd withthe required supply points shall be provided.

    1 1

    e) Fire Safety: Adequate fire safety precautions shall be taken andrequired fire safety equipment (such as fire extinguishers) shall beprovided by the contractor.

    1 1

    5 Site Clearance

    a) NO tree cutting is to carried out without the written instruction fromthe Employer, who in turn will ensure that relevant regulatorypermission/s (including those from Forest Dept., if required) are obtainedprior to cutting of such trees.

    1 1

    b) The non-timber grade trees are to be stacked and possession is tobe given to Employer/concerned Govt. Department.

    1 1

    MONTHLY REPORT

  • 7/30/2019 Mpr October 2012

    49/67

    MONTHLY REPORT

    48 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    c) The Contractor shall strip, store and preserve top soil from the site ofconstruction work and in the stock yards prior to stacking of materials.The top soil shall be reinstated in the cyclone shelter compound after theconstruction is over.

    1 1

    6Protection ofProperties andResources

    The Contractor shall take due care to protect and prevent damages to

    the following resources during preparatory and construction work:a) Water supply lines 1 1

    b) Irrigation canals 1 1

    c) Cart, cattle and/or foot trail/tracks 1 1

    d) Cultural properties and sites/structures of religious importance 1 1

    e) Houses, Farmlands, Orchids and/or Trees. 1 1

    f) School and other existing buildings adjacent to the site ofconstruction.

    1 1

    In case of damage due to construction activity, the restoration/repairsshall be carried out by the contractor at his own cost.

    1 1

    7QuarryOperations

    The Contractor shall procure material from quarries that have beenapproved/licensed by the State Govt. A copy of such an approval shallbe submitted to the Engineer prior to procuring material.

    1

    8 Borrow Areas

    a) Borrow areas for the project will be selected by the Contractorfollowing the stipulations given below: The finalisation of all suchlocations shall be dependent on the approval of the Engineer ontechnical and environmental grounds. This includes on-site verification tocross-check the accuracy of details provided by the contractor. Onlyafter receipt of the written approval from the Engineer, the Contractorshall enter into a formal agreement with landowner.

    1 1

    b) The Contractor shall not procure any kind of construction material(such as aggregates, sand and earth) from ecologically protected areas.

    1 1

    c) Identification and Selection:

    1. The borrow area should not be located in agriculture fields/ unlessunavoidable i.e. barren land is not available. In case borrowing needs tobe done on an agricultural land, top-soil stripping, stacking andpreservation is must.

    1 1

    2. Borrow pits shall not be located within a distance of 100mts. Fromany NH, SH or other roads.

    1 1

    MONTHLY REPORT

  • 7/30/2019 Mpr October 2012

    50/67

    MONTHLY REPORT

    49 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    3. Borrow pits shall be preferably located 500mts. away fromsettlements/habitations.

    1 1

    4. No borrow pits shall be located within 500mts. from schools,colleges, playgrounds, religious structures and health centres.

    1 1

    5. No borrow area shall be opened with in 500mts. from a reserved or

    protected forest area, protected sites, wildlife movement zone andcultural heritage site.

    1 1

    6. No tree cutting shall be undertaken. 1 1

    7. Borrow area near any surface water body will be at least 100mts.away.

    1 1

    d) Operation 1

    1. Area up to which material will be extracted shall be cleareddemarcated on ground.

    1 1

    2. A 15cm topsoil layer will be stripped and preserved in stockpiles. 1 1

    3. Borrowing of earth should be preferably limited to a depth of 1.5mtrfrom the existing ground level.

    1 1

    4. Slope at the edges will be maintained not steeper than 2:3 (Vertical: Horizontal)

    1

    e) Rehabilitation of Borrow Areas:

    1. Rehabilitation shall be satisfactory undertaken immediately after theuse has ceased and at least three weeks prior to monsoon

    1 1

    2. Preserved top soil has be spread uniformly over land (except incases where borrow area is developed as a water body) used as aborrow area.

    1 1

    9

    Water Extraction

    /Use

    Water for construction and for use at construction camps (includinglabour camps) is to be extracted with prior written permission of(a) the

    individual owner, in case the source is private well/tube well; (b) GramPanchayat in case the source belongs to community: and (c) IrrigationDepartment in case the source is an irrigation canal or river.

    1 1

    10Safety of RoadUsers and LocalResidents

    a) Traffic safety arrangements (including provision of warning signage,speed breakers etc.) shall be made by the contractor to ensure safety ofroad users and local people, particularly in the internal village roadswhich will be used for transporting materials.

    1 1

    MONTHLY REPORT

  • 7/30/2019 Mpr October 2012

    51/67

    50 | P a g e

    Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

    b) Material shall be covered during transportation to prevent spillage,accidents and pollution.

    1 1

    c) All required measures to ensure safety of local residents includingchildren and other near-by residents shall be taken up by the Contractor.This shall include provisions to prevent un authorised entry into the

    construction.

    1 1

    11 Workers Safety

    a) All measures required for ensuring safety and health of the workersshall be taken up by the Contractor. This includes provision andenforcement of appropriate personal protective equipment; first aidfacility; emergency response arrangement; proper storage ofhazardous/toxic and polluting materials and; measures for ensuring fireelectrical and mechanical safety arrangements in camp and in work site.

    1 1

    b) All methods steps and measures are required for ensuring safety ofworkers, particularly those needed while undertaking work in or aroundexcavations; workings at height; and; while handling inflammable, toxicand/or hazardous materials shall be ensured by the contractor.

    1 1

    c) Material safety data sheet record of fuel and other inflammable

    chemicals shall be maintained at the site. 1 1

    12 Air pollut ion a) Wind barriers or screens shall be provided in the downwinddirection at air pollution causing sources like plant sites and fine materialstorage stock yards

    1 1

    b) Fugitive dust emissions have to be eliminated by providing dustsuppression/control measures, such as water sprinkling and cover onmaterials, based on activity and site conditions.

    1 1

    c) All plants and equipment shall comply with pollution control norms. 1 1

    d) Water shall be sprinkled at l