Mpr October 2012
-
Upload
henrique-xavi-inesta -
Category
Documents
-
view
228 -
download
1
Transcript of Mpr October 2012
-
7/30/2019 Mpr October 2012
1/67
National Cyclone Risk Mitigation Project
(NCRMP)Revenue (DM) Department
Government of Andhra Pradesh
National Cyclone Risk Mitigation Project
(NCRMP)Revenue (DM) Department
Government of Andhra Pradesh
-
7/30/2019 Mpr October 2012
2/67
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
INDEX
1.0 Project Background 2
2.0 Third Party Quality Audit Consultant 3
3.0 Major Activities and Review Meetings of the Month 3
4.0 Status of TPQA Visits 4
5.0 Progress of NCRMP works 5
TPQA Status Report for NCRMP Works To the end of(31-10-2012) 6
6.0 District wise status of tests conducted by TPQA 30
7.0 Details of QC Audit Reports Submitted during this Month 31
8.0 Details of Environmental & Social Reports Submitted during this Month 32
-
7/30/2019 Mpr October 2012
3/67
-
7/30/2019 Mpr October 2012
4/67
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
2.0 Third Party Quality Audit Consultant.
To provide Consulting Services of Third Party Quality Auditor for Construction of Multipurpose Cyclone Shelters, Roads to
Cyclone Shelters, Roads to habitations, and Roads and Bridges under NCRMP in 9 coastal districts The Commissioner for
Disaster Management & Project Director, Project Implementation Unit (PIU) NCRMP has selected Egis International in JV
with Egis India Consulting Engineers (I) Pvt. Ltd. On 31st May2011, the Contract for Consultancy Service was signed
between The Commissioner for Disaster Management & Project Director, Project Implementation Unit (PIU) NCRMP and
the Egis International in JV with Egis India Consulting Engineers (I) Pvt. Ltd.
3.0 Major Activities and Review Meetings of the Month
-
7/30/2019 Mpr October 2012
5/67
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
4.0 Status of TPQA Visits:
The following table shows the details of TPQA visits to sites in respective districts.
District
Total Number of Visits
Up to Sep.'2012 In Oct.'2012Up to
October.'2012
Srikakulam 360 28 388
Vizianagaram 61 5 66
Vishakhapatnam 308 19 327
East Godavari 542 16 558
West Godavari 387 10 397
Krishna 237 10 247
Guntur 297 23 320
Prakasam 340 27 367Nellore 285 9 294
No. of Visits by TPQA
-
7/30/2019 Mpr October 2012
6/67
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
5.0 Progress of NCRMP works:
The district wise progress of works is shown below. The works in the West Godavari are not started and the works in
Krishna District has just started. At many places the first milestone is completed but works are not started. The line
departments are to analyze the reasons for the slow progress and if necessary penalty for the slow progress as per the
agreement conditions should be imposed.
Third Party Quality Audit by Egis India consulting services
Summary of Activities
S.No. District
Agreements for PackagesCommunicated
Status of works
PR R&B Progress Not Started
1 Srikakulam 6 5 21 0
2 Vizianagaram - 3 3 0
3 Visakhapatnam 13 0 21 0
4 East Godavari 7 0 12 1
5 West Godavari 3 0 10 0
6 Krishna 4 0 8 0
7 Guntur 6 2 17 0
-
7/30/2019 Mpr October 2012
7/67
MONTHLY REPORT
6 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
TPQA Status Report for NCRMP Works To the end of (31-10-2012)
S.No. District
Packages /Works
entrustedStatus of Works
No.of
Visitsof
TPQA
TotalNo.
of QCtestsdone
NCRsAudit
ReportsIssued
Environmentaland Social
ReportsIssued
Issued closed Pending
PR R&B StartedNot
Started
1 Srikakulam 06_16 5_5 21 0 388 1364 54 38 16 71 52
2 Vizianagaram - 3_3 3 0 66 400 3 1 2 11 9
3 Visakhapatnam 13_21 - 21 0 327 2043 25 21 4 67 41
4 East Godavari 07_13 - 12 1 558 1016 23 21 2 49 30
5 West Godavari 03_10 - 10 0 397 349 20 17 3 44 37
6 Krishna 04_08 - 8 0 247 82 3 3 0 33 21
7 Guntur 06_15 2_2 17 0 320 568 13 12 1 50 20
8 Prakasham 12_23 1_1 24 0 367 1890 33 26 7 109 50
9 Nellore 16_24 - 24 0 294 976 30 26 4 105 48
Total 67_130 11_11 140 1 2964 8688 204 165 39 539 308
-
7/30/2019 Mpr October 2012
8/67
MONTHLY REPORT
7 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Status of works in Srikakulam District up to 31.10.2012
Category Packages allotted under Phase - 1Names of works under
each packageAgreement No. / Date DHS DFC
Progress up to
31.10.2012
RHB
NCRMP/B-W/AP/RHB/PRED/01/Santhabommali/003
Road from DPN R&Broad to Uddandapalem
/2010-11, Dt.30.04.2011
30.04.11 30.04.12 complete Entire work
Road from K. UmiladaJunction to Koduru (LinkRoad)
/2010-11, Dt.30.04.2011
30.04.11 30.04.12 complete Entire work
Road from Borubadra,Malagam to Kollipadu viaSeepuram, Gantapeta
/2010-11, Dt.30.04.2011
30.04.11 30.04.12 complete Entire work
NCRMP/B-W/AP/RHB/PRED/01/Polaki/006
Road from R&B roadMobagam toDuubakavanipeta viaGajapathinagaram
/2010-11, Dt.30.04.2011
30.04.11 30.04.12
300 mts CC road
completed, GSB layingis in progress, roadformation width vary
from 6.00mts to 7.50mts
Road fromTalasamudram to DolaRegulator
/2010-11, Dt.30.04.2011
30.04.11 30.04.12WBM GR-III laying is in
proigress
NCRMP/B-W/AP/RHB/PRED/01/Polaki/005
Road from R&B roadEdulavalasa - Killam toJonnam viaTalasamudram
/2011-12, Dt.30.04.2011
30.04.11 31.01.12WBM Gr-II & III metal
collection is in progress
BridgesNCRMP/B-W/ AP/Br/R&B/01/Patnavanipeta/001
Construction of bridge atKm 11/6-8 of NH-5 toPatnavanipetaConnectingSundarapalem
46/2011, Dt.17.12.2010
17.12.10 17.06.12
Sub structure for bridgecompleted ,Approach
roade/w,GSB,WMM,SDBC
completed.CD,R/Wworks completed.slab
shuttring reinforcementwork is in progress
-
7/30/2019 Mpr October 2012
9/67
MONTHLY REPORT
8 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/Br/R&B/01/ Surampeta/003
Construction of MinorBridge at Km 12/2-4 ofNH-5 to SurampetaRoad via Naruva,Mentada
45/2010-2011,Dt17.12.2010
17.12.10 17.03.12
Deck slabs weiring coat& hand rails
completed,Approacheroad work completed.
NCRMP/B-W/AP/Br/R&B/01/Bendigadda/004
Construction of Highlevel bridge acrossBendigadda at KM 4/10of Pundi-Parlakimidi roadin Srikakulam Dt, A.P.
1/2010,Dt.11.11.2010 11.11.10 11.05.12Slabs completed andApproach road e/w
completed.
Roads NCRMP/B-W/AP/RD/R&B/01/Nowpada/006)Improvements Naupada-Venkatapuram road from0/0to15/0km
43/2010-11,17.12.2010 17.12.10 17.03.12BT work completed, CC
Road completed
RCS
NCRMP/B-W/AP/RCS/PRED/01/V.Kotturui/002
Road from NP road toURK Puram
G.O.Rt.No.451, Dt.06.04.2011
06.04.11 29.09.12Bt layer completed &Ccroad completed
Road from Deppuru,Bahadapalli road toOnkuluru to CycloneShelter
G.O.Rt.No.451, Dt.06.04.2011
06.04.11 29.09.12Bt layer completed &Ccroad completed
Road from R & B Roadto Devunthalada
G.O.Rt.No.451, Dt.06.04.2011
06.04.11 29.09.12Bt layer completed &Ccroad completed
Road from Pollada toKomarthalada toCyclone Shelter
G.O.Rt.No.451, Dt.06.04.2011
06.04.11 29.09.12Bt layer completed &Ccroad comlpeted
NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005
Road from Koyyam R &B Road to
Moosavanipeta
G.O.Rt.No.451, Dt.
06.04.2011
30.04.11 07.05.12 BT layer completed
Road from Mentada toDovupeta
G.O.Rt.No.451, Dt.06.04.2011
30.04.11 07.05.12 BT layer completed
Road from Kotcherelaroad to Kollibhemavaram& Cyclone Shelter
G.O.Rt.No.451, Dt.06.04.2011
30.04.11 07.05.12
BT layer & CCroadcompleted
-
7/30/2019 Mpr October 2012
10/67
MONTHLY REPORT
9 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Road from Kotcherlaroad toPathesundrapalem
G.O.Rt.No.451, Dt.06.04.2011
30.04.11 07.05.12
BT layer & CCroadcompleted
MPCSNCRMP/B_W/AP/MPCS/PRED/01/Sa
nthabommali/005
Construction of Cyclone shelterat Kollipadu
G.o rt No451 Dt
06.04.2010
07.01.2013
Completion ofGround floorPlinth level
Silt floor level slabcompleted.
Construction of Cyclone Shelterat Runku
G.o rt No451 Dt
06.04.2010
07.01.2013
Completion ofGround floorPlinth level
plinth beam completedsand filling is in progress,and columns above plinth
beam is in progress
Status of works in Vizianagaram District up to 31.10.2012
CategoryPackages allottedunder Phase - 1
Names of works under eachpackage
Agreement No./ Date DHS DFCProgress up to
31.10.2012
Bridges
NCRMP/ B-W/ AP/Br/ R&B/ 02/
Puligadda/ 007
Construction of Minor Bridge atKm. 7/2 near Puligadda of Konada Ramatheertham R&B Road toKonathalapalem via Yerukonda,
Pasupam, Kollayavalsa (Z.P.Road)
31/2010-201 Dt.1.12.2010
01.12.10 31.05.12100% of work
completed
NCRMP/ B-W/ AP/Br/ R&B/ 02/
Chakaligadda / 008
Construction of Minor Bridge atKm 15/2 near Chakaligadda of
Konada Ramatheertham R&B roadto Konathalapalem (via)Yerukonda, Pasupam,
Kollayavalsa (ZP Road)
34/2010-2011 Dt.8.12.2010
08.12.10 07.06.1287% of workcompleted
-
7/30/2019 Mpr October 2012
11/67
MONTHLY REPORT
10 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Road (R&B)NCRMP/B-
W/AP/RD/R&B/ 02/
Konada/009
Improvements to Road fromKonada Ramatheertham (R&B)Road to Konathalapalem (Via)
Pasupam, Yerukonda,
Kollayavalsa from Km 12/0 to 16/5(Km 0/0 to 4/0 i.e. up to NH-5crossing)
33/2010-201 Dt.8.12.2010
08.12.10 07.03.12100% of work
completed
Status of works in Visakhapatnam District up to 31.10.2012
Category Packages allotted under Phase- 1Names of works
under eachpackage
AgreementNo. / Date
DHS DFC Progress up to 31.10.2012
RHB
NCRMP/B-W/AP/RHB/PRED/03/Nakkapalli/001
Road from Vempadu toPatimeeda
/2010-11, Dt.11.01.2011
11.01.11 11.01.12 Work Completed.
Road from R&B road toMullaparra up to Beach
end
/2010-11, Dt.11.01.2011
11.01.11 27.10.11 Work Completed.
NCRMP/B-W/AP/RHB/PRED/03/Anandapuram/003
Road from R&B B.PKallalu to
Matchvanipalem
/2010-11, Dt.10.03.2011
10.03.11 09.12.11 Work Completed.
NCRMP/B-W/AP/RHB/PRED/03/Paravada/004
Road from R & B roadto Pothu Rajannapalem
/2010-11, Dt.28.03.2011
28.03.11 27.12.11 Work Completed.
Road from R & B roadto Jalaripeta
/2010-11, Dt.28.03.2011
28.03.22 28.12.11 Work Completed.
NCRMP/B-W/AP/RHB/PRED/03/Rambilli/006Road from R & B road
to Venkayyapalem/2010-11, Dt.11.01.2011
11.01.11 11.10.11 Work Completed.
NCRMP/B- Road from R&B road to /2011-12, Dt. 27.04.11 26.01.12 Work Completed.
-
7/30/2019 Mpr October 2012
12/67
MONTHLY REPORT
11 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
W/AP/RHB/PRED/03/Achyutapuram/007 Ava- Somavaram 27.04.2011
Road from R&B Road
to Avarajam
/2011-12, Dt.
27.04.2011 27.04.11 26.01.12 Work Completed.
Status of works in Visakhapatnam District up to 31.10.2012
CategoryPackages allotted under
Phase - 1Names of works under each
packageAgreement No. /
DateDHS DFC
Progress upto
31.10.2012
RCS
NCRMP/B-W/AP/RCS/PRED/03/Anandapuram/001
Road from NH-5 toRamarayadupalem
/2010-11, Dt. 15.09.2011 15.09.11 14.06.12
RoadFurniture &B.T iscompleted.
NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002
Road from R&B road toKrishnampalem
/2010-11, Dt. 15.09.2011 15.09.11 14.09.12
CD works arecompleted &B.T work isCompleted
Road from R & B road toKattubolu to Marripalem
/2010-11, Dt. 15.09.2011 15.09.11 14.09.12
CD works arecompleted &B.T work isCompleted
Road from R & B road to
Rajakoduru
/2010-11, Dt. 15.09.2011 15.09.11 14.09.12
CD Work iscompleted &
B.T work iscompleted
NCRMP/B-W/AP/RCS/PRED/03/Nakkapalli/003
Road from R & B road toPedateenarla to Chinatheernala
/2010-11, Dt. 15.09.2011 15.09.11 14.06.12
B.T & C.Croad worksareCompleted.
-
7/30/2019 Mpr October 2012
13/67
MONTHLY REPORT
12 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Road from Upmaka RajayyapetaR & B road to Janakayyapeta
/2010-11, Dt. 15.09.2011 15.09.11 14.06.12
CD works areCompleted &B.T work iscompleted
Status of works in Visakhapatnam District up to 31.10.2012
Category Packages allotted under Phase - 1Names of works under
each packageAgreement No.
/ Date
Milestone Completion Dates Progress w.r.t.milestone up to
31.10.2012First Second Third
MPCS
NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003
Construction of cycloneshelter at Gajapathi
Nagaram
/2011-12, Dt.03.10.2011
02.02.12 02.06.12 02.10.12
Plinth beam &Staircase, Ramp andStilt columns arecompleted.Form workfor Stilt slabcompleted.Ist floorcolmns completedtupto roof levevel. Istfloor form workcompleted. Ist floorslab reinforcementplacing is inprogress.EOATsubmitted on24.08.12
Construction of cyclone
shelter at Ratnayampeta
/2011-12, Dt.
03.10.2011 02.02.12 02.06.12 02.10.12
All Slabs arecompleted. Insideand outside wallplastering work
completed.woodjoinery and Electricalworks are to beprogress.
NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002Construction of cyclone
shelter at Patimeeda/2011-12, Dt.03.10.2011
02.03.12 02.08.12 02.01.13
Stilt Slab & 1st floorcolumns areCompleted.Staircase, Ist floorslab reinforcementplacing work is in
-
7/30/2019 Mpr October 2012
14/67
MONTHLY REPORT
13 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
progress . EOATsubmitted on24.08.12
Construction of cycloneshelter at Mullaparra
/2011-12, Dt.03.10.2011
02.03.12 02.08.12 02.01.13
Stilt Slab & 1st floorcolumns areCompleted. Ist floorslab completed. Headroom columns arecompleted.Headroom form work is inprogress.and ceilingplastering work is inprogress.
Construction of cycloneshelter at Bangarampeta
/2011-12, Dt.03.10.2011
02.03.12 02.08.12 02.01.13
1st floor Slab, IIndfloor columns &staircase areCompleted. Iind floor
slab completd Headroom columnscompleted upto rooflevel. Head room slabcompleted Ist floorbrick masonry work isin progress.
NCRMP/B-W/AP/MPCS/PRED/03/Rambilli/004Construction of cyclone
shelter atVenkayyapalem
/2011-12, Dt.03.10.2011
02.01.12 02.04.12 02.07.12
Footings & Pedestalsworks are inprogress.Sand fillingin foundationcompleted.Plinthbeam work is in
progress.EOATproposals submittedon 29.06.12.
NCRMP/B-W/AP/MPCS/PRED/03/Paravada/001Construction of cyclone
shelter atTikkavanipalem
/2011-12, Dt.07.10.2011
06.01.12 06.04.12 06.07.12Work not started dueto site problem
-
7/30/2019 Mpr October 2012
15/67
MONTHLY REPORT
14 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Status of works in East Godavari District up to 31.10.2012
Category Packages allotted under Phase - I
Names of works
under eachpackage
Agreement
No. / Date
Mile stones
RemarksFirst Second Third
RHB (2 )RCS (8)MPCS (3)
NCRMP/B-W/AP/RHB/PRED/04/Katrenikona/003
Road from PR roadsto Dasarivanipeta and
to Cyclone Shelter
/2011-12Dt:27.04.2011
30-11-2011 30-11-2011 20-01-2012 Completed
NCRMP/B-W /RCS/PRED/04/Karapa/001Approach Road tocyclone Shelter at
Adivipudi
2011-12Dt:20.05.2011
30-11-2011 31-10-2011 31-01-2012 Completed
NCRMP/B-W/AP/RHB/PRED/04/Karapa/001/
Road fromGurjanapalli to
Bandulavaripalem
2011-12Dt:27.04.2011
30-09-2011 31-10-2011 31-01-2012 Completed
NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004
Road from R&B Roadto P.Chodipallipeta CS
2011-12Dt:07.09.2011
3 months 3 months 3 months Completed
NCRMP/B-W
/AP/RCS/PRED/04/Thondangi/004
Road from R&B Road
to K.Chodipallipeta CS
/2011-12
Dt:07.09.2011
3 months 3 months 3 months Completed
NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004
Road from R&B Roadto Hukumpeta CS
/2011-12Dt:07.09.2011
3 months 3 months 3 months Completed
NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004
Road from R&B Roadto Gaddipeta CS
/2011-12Dt:07.09.2011
3 months 3 months 3 months Completed
-
7/30/2019 Mpr October 2012
16/67
MONTHLY REPORT
15 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004
Road from R&B Roadto Danavaipeta CS
/2011-12Dt:07.09.2011
3 months 3 months 3 months Completed
NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004/
Road from R&B Roadto G.MusalayyapetaCS
2011-12Dt:07.09.2011
3 months 3 months 3 months Not yet Started
NCRMP/B-W/AP/RCS/PRED/04/Uppalaguptam/003
Road from R&B Roadto Chinaraghavulapeta
Cyclone Shelter
/2011-12 Dt:23.09.2011
3 months/22.11.2011
3 months22.06.2011
----------- Completed
NCRMP/B-W/AP/MPCS/PRED/04/Uppalaguptam/002
Construction ofCyclone Shelter at
Pedaraghavulapeta ofUppalaguptam Mandal
E.G.Dt.
/2011-12Dt:17.10.2011
3 months16.01.2012
3 months16.04.2012
3 months16.07.2012
Stair case and cattleramp 1st flight fromPB form work is inprogress. Compoundwall is in progress.
NCRMP/B-W/AP/MPCS/PRED/04/Thondangi/004
Construction ofCyclone Shelter at
Laxamanudupadu inThondangi
/2011-12Dt:07.09.2011
Stilt floor ceiling andcolumns plastering
work is in progress.
NCRMP/B-W/AP/MPCS/PRED/04/Thondangi/004
Construction ofCyclone Shelter at
Avulamanda
/2011-12Dt:07.09.2011
Terrace SlabCompleted. Compoundwall is in progress
-
7/30/2019 Mpr October 2012
17/67
MONTHLY REPORT
16 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Status of works in West Godavari District up to 31.10.2012
CategoryPackages allotted under Phase
- 1Names of works under
each packageAgreementNo. / Date
Milestone Completion Dates Progress w.r.t.milestone up to
31.10.2012
RemarksFirst Second Third
RHB
NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/0
01
Road from NH 214 A atRanga Statue center to
Harijanawada of Kalipatnam(E) (Mogalthuru Mandal
W.G.Dist.)
16 /2011-12
Dt.27.04.2011
27/4/2011to
22/9/2011
23/9/2011to
24/2/2012
25/2/2012to
26/7/2012
100% Work Completed.
R&B road at PanchayatOffice to Pulaparthivarithota
via Badava(Mogalthuru Mandal
W.G.Dist.)
100% Work Completed.
Mogalthuru Vempa R&BRoad at Uchintha Kalava
Bridge to Gogulamma
Harijanapeta (MogalthuruMandal W.G.Dist.)
100% Work Completed.
From Narsapur MogalthuruR&B road to Dayadaldaspetavia Venkateshwara Swamytemple (Mogalthuru Mandal
W.G.Dist.)
100% Work Completed.
Road from NH 214 A road toHarijanapeta of Kothota
(Mogalthuru MandalW.G.Dist.)
27/4/2011to
22/9/2011
23/9/2011to
24/2/2012
25/2/2012to
26/7/2012100% Work Completed.
NCRMP/B-W/AP/RHB/PRED/05/Narsapur/0
02
R&B road to Indira Nagar
(via) Pochamma temple(Narsapur Mandal W.G.Dist.)
21 /2011-12Dt.09.05.2011
09/05/2011to
04/09/2011
05/09/2011to
06/01/2012
07/01/2011to
08/5/2012
100% Work Completed.
Road from R&B road toPedalanka (Narsapur Mandal
W.G.Dist.)100% Work Completed.
Road from LB Cheria CCroad to Chillapalemm of LBCheria (Narsapur Mandal
W.G.Dist.
100% Work Completed.
-
7/30/2019 Mpr October 2012
18/67
MONTHLY REPORT
17 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Status of works in Krishna District up to 31.10.2012
Category Packages allotted under Phase - 1Names of works under each
packageAgreement No. /
DateDHS DFC
Progress up to31.10.2012
RHB
NCRMP/B-W/AP/RHB/PRED/06/Machipatnam/001
Road connecting R&B roadthrough Gantalammapalem
/2011-12Dt.27.4.2011
27.04.11 26.01.2012 Work Completed.
NCRMP/B-W/AP/RHB/PRED/06/Machipatnam/002
Road from R & B Road to B.VThota
/2011-12Dt.27.4.2011
27.04.11 26.01.2012
Work Completed.
Road from Potalapalem Z.Proad to Chikativanipalem Work Completed.
NCRMP/B-W/AP/RHB/PRED/06/Kruthivennu/003
Road from Intheru R&B Road toRangaraopet
/2011-12Dt.27.4.2011 27.04.11 26.01.2012
Work Completed.
Road from R&B road to CycloneShelter at Chandala Work Completed.
NCRMP/B-W/AP/RHB/PRED/05/Kalla/003
From A-U R&B Road toSatyanarayanapuram (Kalla
Mandal W.G.Dist.)25 /2011-12
Dt.26.05.2011
26/5/2011
To20/8/2011
20/8/2011
to21/11/2011
22/11/2011
To23/2/2012
100% Work Completed.
From A-U R&B Road toMekaladibba (Kalla Mandal
W.G.Dist.)100% Work Completed.
-
7/30/2019 Mpr October 2012
19/67
MONTHLY REPORT
18 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Status of works in Krishna Districts up to 31.10.2012
Category Packages allotted under Phase - 1
Names of works
under eachpackage
AgreementNo. / Date
Milestone Completion Dates Progressw.r.t.
milestoneup to
31.10.2012
RemarksFirst Second Third
RCSNCRMP/B-W
/AP/RCS/PRED/06/Machipatnam/001
Road fromBhogireddipalliR&B Road to
Ramakhandam
/2011-12/Dt.02.09.2011
01.12.2011 01.03.12 01.06.12 13.20% Work Completed.
Road from R&BRoad Chinnapuram
to Gundupalem
/2011-12/27.04.2011
01.12.2011 01.03.12 01.06.12
12.14% Work Completed.
Road fromPotalapalem Z.Proad to Potepalli.
/2011-12/Dt.02.09.2011
01.12.2011 01.03.12 01.06.1231.68%
Work Completed.
-
7/30/2019 Mpr October 2012
20/67
MONTHLY REPORT
19 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Status of works in GUNTUR District up to 31.10.2012
CategoryPackages allotted under
Phase - 1Names of works under each package
Agreement No./Date
DHS DFCProgress up to
31.10.2012
RHB
NCRMP/B-W/AP/RHB/PRED/07/KARLAPAL
EM/001
R/f Ganapavaram R&BRoad t o Kesavapuri ST colony 7/2011-2012
27.04.201127.04.11 26.01.2012
Completed.
NCRMP/B-W/AP/PRED/07/Nagaram/002
R/f R&B Road to Mohammad Alipalem
8/2011-201227.04.2011
27.04.11 26.4.2012
Completed.
R/f R&B Road to Katuivaripalem.Completed.
Bridges
NCRMP/B-W/AP/Br/R&B/07/Bapatla/010
Reconstruction of High level Bridge @Km5/2 ofBapatla-Suryalanka Road across Perali drain in
Guntur79/2010-2011
1.12.201001.12.10 31.5.2012 WMM completed.
NCRMP/B-W/AP/Br/R&B/07/Bapatla/011
Reconstruction of High level Bridge @Km2/4 ofBapatla-Pandurangapuram Road across Perali
drain in Guntur78/2010-2011
1.12.201001.12.10 31.5.2012
Approaches is inprogress
-
7/30/2019 Mpr October 2012
21/67
MONTHLY REPORT
20 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Status of works in GUNTUR District up to 31.10.2012
Category Packages allotted under Phase - 1
Names of works under each
package
Agreement No. /
Date DHS DFC Progress up to 31.10.2012
RCS
NCRMP/B-W/AP/RCS/PRED/07/P
Palem/001
Road from R&B Road to
Mandevaripalem
/2010-11
Dt.01.11.201101.11.11 31.10.2012
Completed.
Road from R&B Road Alluru to
Yadavapalem
/2010-11
Dt.01.11.201101.11.11 31.10.2012 From Km 0.574 to km 0.964
CC completed.
NCRMP/B-
W/AP/RCS/PRED/07/KarlaPalem/002
Road from Ganapavaram R & B
road to Pedamarpuvaripalem
/2010-11
Dt.01.11.201101.11.11 31.10.2012
GSB is in Progress
Road from R & B Road toChinapuluguvaripalem
/2010-11Dt.01.11.2011
01.11.11 31.10.2011GSB is in Progress
Road from R & B road to
Yaramvaripalem
/2010-11
Dt.01.11.201101.11.11 31.10.2011
Completed.
Road from R & B road to
Pedagollapalem Cyclone Shelter
/2010-11
Dt.01.11.201101.11.11 31.10.201
Completed.
Pedagollapalem PR Road to
Bonthagorlapalem
/2010-11
Dt.01.11.201101.11.11 31.10.201
Shoulders is in progress .
NCRMP/B-
W/AP/RCS/PRED/07/Nizampatnam/003
Road from R&B Road to
Gurunadhanagar
/2010-11 Dt.
17.10.201117.10.11 16.07.12
Shoulders is in progress.
Road from R&B Road to Adavala
H/O Bavajipalem
/2010-11 Dt.
17.10.201117.10.11 16.07.12
Completed.
-
7/30/2019 Mpr October 2012
22/67
MONTHLY REPORT
21 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Road from R&B Road to
Atlavaripalem
/2010-11 Dt.
17.10.201117.10.11 16.07.12 Completed
NCRMP/B-
W/AP/RCS/PRED/07/Bapatla/004
Road from R&B Road to
Hanumanthanagar 2010-11
Dt13.10.201113.10.11 12.07.2012
Completed.
Road from R & B road to
Adarsanagar Completed.
Status of works in Prakasam District up to 31.10.2012
CategoryPackages allotted
under Phase - 1
Names of worksunder each
package
Agreement No. /
Date
Milestone completion dates
Progress up to
31.10.2012
Remarks
First Second Third
BRIDGESNCRMP/B-
W/AP/Br/R&B/08/Kanaparthy/012
Construction ofHigh level Bridge at
Km 16/10 ofNaguluppalapadu Kanaparthy road inPrakasam District
76/2010-11 Dated1/12/2010
5/31/2011Completion
up to silllevel
12/31/2011Completion upto below deck
slab
5/31/2012Completion of
entire workincluding
approaches
Bridge work iscompleted
As permilestonecompleted
RHBNCRMP/B-
W/AP/RHB/PRED/08/S.Konda/001
Road from PakalaZP Road to
AulavaripalemCyclone shelter
NCRMP/B-W/AP/RHB/PRED/0
8/S.Konda/001Dated 25.04.2011
8/24/2011Earth work,CD work,
GSB
12/24/2011WBM, Grade II
& III
4/24/2012 BT,Shoulders &road furniture
CC Road &Shoulders workis Completed.
Mile stone-IIIcompleted
Road from R&BRoad to
Somarajupalli
NCRMP/B-W/AP/RHB/PRED/0
8/S.Konda/001Dated 25.04.2011
BT, CC road &culverts arecompleted fromKM 0/0 to 2/146.
Mile stone-IIIcompleted
Road from R&Broad to
Narravaripalem
NCRMP/B-W/AP/RHB/PRED/0
8/S.Konda/001Dated 25.04.2011
BT, & culvertsare Completedfrom KM 0/0 to0/900. work iscompleted
Mile stone-IIIcompleted
-
7/30/2019 Mpr October 2012
23/67
MONTHLY REPORT
22 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002
Road from NH5 toMulaguntapadu
NCRMP/B-W/AP/RHB/PRED/0
8/S.Konda/002dated 10/02/2011 6/9/2011
Earth work,CD work,
GSB
10/9/2011WBM, Grade II& III
2/9/2012 BT,Shoulders &road furniture
WBM-Grade-IIILayer Completed.OGPC + Seal CoatTo be taken up
Not Reached asper Mile stone-III(Awaiting for2nd EOT
Proposal)
Road from R&Broad to
Chalivendradibba
NCRMP/B-W/AP/RHB/PRED/0
8/S.Konda/002dated -10/02/2011
WBM-Grade-IIILayer Completed.OGPC + Seal CoatTo be taken up
Not Reached asper Mile stone-III(Awaiting for2nd EOTProposal)
NCRMP/B-W/AP/RHB/PRED/0
8/S.Konda/002
Road from PakalaR&B road to
Mosanaladinne
NCRMP/B-W/AP/RHB/PRED/0
8/S.Konda/002dated 10/02/2011
6/9/2011Earth work,CD work,
GSB
10/9/2011WBM, Grade II
& III
2/9/2012 BT,Shoulders &road furniture
WBM-Grade-IIImaterial layingwork is in progress
Not Reached asper Mile stone-III(Awaiting for2nd EOTProposal)
Road from R&Broad to Binginapalli
HarijanawadaCyclone Shelter
NCRMP/B-W/AP/RHB/PRED/0
8/S.Konda/002dated 10/02/2011
CC road work iscompleted from KM0/0 to KM 0/220.shoulders work areto be taken up.
Mile stone-III(Awaiting for 2
nd
EOT Proposal)
NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/003
Road from R&BRoad Allur to M T
Raju colony
NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/003
Dated 27/04/2011
8/26/2011Earth work,CD work,
GSB
12/26/2011WBM, Grade II
& III
4/26/2012 BT,Shoulders &road furniture
BT, CC road,shoulders &culverts arecompleted from km
0/0 to km 3/8.workis completed
As permilestonecompleted
NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/004
Road from KEMR&B Road to
Sankuvarigunta
NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/004Dated 27/04/2011
9/26/2011Earth work,CD work,
GSB
2/26/2012WBM, Grade II
& III
7/26/2012 BT,Shoulders &road furniture
BT completed.CDwork completed.CCroad workcompleted from km0/0 to km 1/430and CC dip work iscompleted
Reached Milestone-III
-
7/30/2019 Mpr October 2012
24/67
MONTHLY REPORT
23 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Road from KEM R& B Road to
Pullareddypalem
NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/004Dated 27/04/2011
BT completed.CDwork completed.CCroad and shoulderswork completedfrom from km 0/0 to
km 3/900.
As permilestonecompleted
NCRMP/B-W/AP/RHB/PRED/0
8/Ulavapadu/07
Road from MCRoad to
SubbarayaduSatram
NCRMP/B-W/AP/RHB/PRED/0
8/Ulavapadu/07dated 27/04/2011
8/26/2011Earth work,CD work,
GSB
12/26/2011WBM, Grade II
& III
4/26/2012 BT,Shoulders &road furniture
BT completed.CDwork completed.CCroad and shoulderswork completedfrom from km km0/0 to km 4/4. workis completed
As permilestonecompleted
NCRMP/B-W/AP/RHB/PRED/0
8/Ulavapadu/08
Road from R&Broad Tettu to
Ramayapatnam
NCRMP/B-W/AP/RHB/PRED/0
8/Ulavapadu/08dated 27/04/2011
8/26/2011Earth work,CD work,
GSB
12/26/2011WBM, Grade II
& III
4/26/2012 BT,Shoulders &road furniture
BT completed.CDwork completed.CCroad and shoulderswork completedfrom from km 0/0 to
km 5/086. work iscompleted
As permilestonecompleted
NCRMP/B-W/AP/RHB/PRED/0
8/Tangutur/09
Road from R&Broad Pellur toVasepallipadu
NCRMP/B-W/AP/RHB/PRED/0
8/Tangutur/09dated 16/03/2011
7/15/2011Earth work,CD work,
GSB
11/15/2011WBM, Grade II
& III
3/15/2012 BT,Shoulders &road furniture
BT completed.CDwork completed.CCroad andshoulders workcompleted from km0/0 to km 4/5. workis completed
As permilestonecompleted
NCRMP/B-W/AP/RHB/PRED/0
8/Tangutur/10
Road from R&Broad to Kesupalem
NCRMP/B-W/AP/RHB/PRED/0
8/Tangutur/10
dated 19/04/2011
7/18/2011Earth work,CD work,
GSB
10/18/2011WBM, Grade II
& II
1/18/2012 BT,Shoulders &road furniture
BT completed.CDwork completed.CCroad and shoulderswork completedfrom from km 0/0 tokm 2/103. work iscompleted
As permilestonecompleted
RCSNCRMP/B-
W/AP/RCS/PRED/08/Vetapalem/001
Road from R&Broad to
Vijayanagaramcolony cyclone
shelter
NCRMP/B-W/AP/RCS/PRED/0
8/Vetapalem/001dated 2011/12
dated 30.09.2011
1/29/2012Earth work,
GSB
5/29/2012shoulders, Gr-
III
9/29/2012 BT,CC pavement
and roadfurniture
cc road completed,BT roadcompleted&shoulderscompleted. Road from km0/0 to km 0/525.work is completed
As permilestonecompleted
-
7/30/2019 Mpr October 2012
25/67
MONTHLY REPORT
24 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Road from NH roadto
Challareddypalem
cc road completed,BT roadcompleted&shoulderscompleted. Road
from km 0/0 to km1/735. work iscompleted
As permilestone
completed
Road from R&Broad to Jeevaraksh
nagar colonycyclone shelter
C.C.road andShoulders arecompleted Roadfrom km 0/0 to km0/500.
As permilestonecompleted
Road from R&Broad to Ramnagar
colony cycloneshelter
C.C.completedRoad from km 0/0to km0/475.Shoulders tobe taken up.
Reached Milestone-III
Road from R&Broad to cyclone
shelter atMankenavaripalem
CC roadcompleted.Shoulders work isto be taken up.
Reached Milestone-III
NCRMP/B-W/AP/RCS/PRED/0
8/Chirala/002
Road from R&BRoad to
Keertivaripalemcyclone shelter NCRMP/B-
W/AP/RCS/PRED/08/Chirala/002
dated 27.08.2011
C.C road andShoulders arecompleted from km0/0 to km 0/265.work is completed
As permilestonecompleted
Road from R&BRoad to Devinutula
cyclone shelter ofChirala Mandal in
Prakasham district.
C.C road andShoulders are
completed from km0/0 to km 0/800.work is completed
As per
milestonecompleted
MPCSNCRMP/B-
W/APMPCS/PRED/08/Ulavapadu/001
Chakicharla cycloneshelter in
Ulavapadu MandalPrakasam district
NCRMP/B-W/AP/MPCS/PRED/08/Ulavapadu/001
24.11.2011All items upto stilt floor
slabincluding
ramp, staircase
24.02.2012 Allitems up tosecond floor
slab includingfirst floor, andin 2nd floor
including stair
24.05.2012Head room,plastering,
flooring, watersupply
arrangements,sanitary fitting,
Stilt floor, G.F , &Terrace floor-roof slabcompleted. Brickwork completed,Plastering work
As permilestonecompleted
-
7/30/2019 Mpr October 2012
26/67
MONTHLY REPORT
25 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
foundations,columns,bea
ms,pccflooring etc.,
case, columnsetc.,
electricalitems,
compoundwall, cc
pavement.
Earthenmounds(raised
portion), waterharvesting,septic tank,slump and
soak pit.etc.
completed,Cattleplatformcompletedrevitmrnt work
completed,flooring work iscompleted,compound wall120 metersleangthcompleted,Electrical workiscompleted.work iscompleted
NCRMP/B-W/APMPCS/PRED/
08/NG Padu/003
Kanaparthy cycloneshelter in
NaguluppapaduMandal Prakasam
district
NCRMP/B-W/AP/MPCS/PRED/08/NG Padu/003
23.11.2011All items upto stilt floor
slabincluding
ramp, staircase
foundations,columns,bea
ms,pccflooring etc.,
23.02.2012 Allitems up to
first floor slaband head
room slab in 2nd floor
including staircase, columns
etc.,
23.05.2012plastering,
flooring, watersupply
arrangements,sanitary fitting,
electricalitems,
compoundwall, cc
pavement.Earthenmounds
(raisedportion), water
harvesting,septic tank,slump and
soak pit.etc.
Internal &
ExternalPlasteringcompleted.Flooring WorkCompleted.Compound WallPaintingCompleted. CCRoad Completed.Shoulder workCompleted.Painting work in
Completed.Electrical Fittingsin progress. Tilesin bathroomswork Completed.Water harvest &Soak pit work inprogress.
Not as perMilestone
-
7/30/2019 Mpr October 2012
27/67
MONTHLY REPORT
26 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Status of works in Nellore District up to 31.10.2012
(RCS)
Package Number Name of Work Milestone1 Milestone2 Milestone3
Progress up
to 31.10.2012
NCRMP/B-W/AP/09MUTHUKUR/RCS/002
Road from R&B Roadkappaladoruvu to bandla Palem
H.wada
3Months: EarthWork, Pipe Culverts,
GSB
6 Months: WBMGrII,GrII,CC Pavement
and Shoulders
9 Months: BTCC road and
Road Furniture
OGPC+ Sealcoat completed
NCRMP/B-W/AP/09/D.V.SATRAM/RCS/008
Road from R&B road to SullurpetaMallam to berjengalapalli cyclone
shelter 3Months: EarthWork, Pipe Culverts,
GSB
6 Months: WBM GrII,GrII Shoulders and
CC Pavement
9 Months: BT,CC Pavement
and RoadFurniture
OGPC+ Sealcoat completed
NCRMP/B-
W/AP/09T.P.GUDUR/RCS/005
Road from7/2 M.C Road to
venkannapalem pattapupalem work completed
NCRMP/B-W/AP/09chillakur/RCS/004
Road from Katuivaripalem R&Broad to vellapalm
3Months: EarthWork,CD Works,
GSB
6 Months: WBM GrII,GrII and Shoulders
9 Months: BT,CC Pavement
and RoadFurniture
OGPC+ Sealcoat completed
NCRMP/B-W/AP/09kota/RCS/001
road from R&B road to A.SPURAM 3Months: Earth
Work, Pipe Culverts,GSB
6 Months: WBM GrII,GrII and Shoulders
9 Months: BT,CC Pavement
and RoadFurniture
OGPC+ Sealcoat completed
Road from GD Road toVavillapalem
OGPC+ Sealcoat completed
NCRMP/B-W/AP/RCS/PRED/09/KAVALI/007
Road from Kotha Satram R&B toIndiranagar (via) Thumalapenta
palam, Patharavadu palam,Ramudu palam, Karaduvari palam&Sreeramapuram in SPSR Nellore
District.
4Months: EarthWork, Pipe Culverts,
GSB
4 Months: WBM GrII,GrII , Shoulders and
CC Pavement
4 Months: BT,CC Pavement
and RoadFurniture
OGPC+ Sealcoat completed
-
7/30/2019 Mpr October 2012
28/67
MONTHLY REPORT
27 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/RCS/PRED/09/KAVALI/006
Road Connecting R&B Roadthrough Voter Village in SPSRNellore District.
4 Months: EarthWork, Pipe Culverts,GSB
4 Months: WBM GrII,GrII , Shoulders andCC Pavement
4 Months: BT,
CC Pavementand RoadFurniture
GSB. From0.00 to 2.0800
,WBM Gr-II ,Gr-III from 0.00 to
5.320 and
OGPC+SC 0/6to 2/6is in
completed,6nos pipeculverts iscompleted
Status of works in Nellore District up to 31.10.2012
RHB
NCRMP/B-
W/AP/RHB/PRED/09RHB/KAVALI/004
Road from5/8 ofChennayapalem Road to
Gummadi bandla5Months:
Earthwork, CD
Works,ccpavementand GSB
10 Months:
WBM GrII, GrIIand Shoulders
15 Months:
BT and RoadFurniture
OGPC+ Seal coat completed
Road from PedattapupalemR&B road to
Chennayapalem H.wadaOGPC+ Seal coat completed
Road from K.T R&B Road toAlliguntapalem
OGPC+ Seal coat completed
NCRMP/B-W/AP/RHB/PRED/09BOGOLU/RHB/002
Road from 1/6 ofJuvvaladinne R&B Road to
Tellagunta KM to 2/720
3Months: EarthWork, Pipe
Culverts, GSB
6 Months:WBM GrII, GrIIand Shoulders
9 Months: BTand RoadFurniture
OGPC+ Seal coat completed
NCRMP/B-W/AP/RHB/PRED/09BOGOLO/RHB/001
1. Road from NH5 toSambasivapuram
5Months: EarthWork, Pipe
Culverts, GSB
10 Months:WBM GrII, GrIIand Shoulders
15 Months:BT and Road
FurnitureOGPC+ Seal coat completed
-
7/30/2019 Mpr October 2012
29/67
MONTHLY REPORT
28 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Road from 9/6 ofJuvvaladinne R&B Road to11/0 of Juvvaladinne R&BRoad Via Venkateshpalem
OGPC+ Seal coat completed
NCRMP/B-W/AP/RHB/PRED/09/VIDAVALURU/005
1)Road from kt R&B ROADTO ALLAGANIPADU to
Vavilla5Months: Earth
Work, PipeCulverts, GSB
10 Months:WBM GrII, GrIIand Shoulders
15 Months:BT and Road
Furniture
OGPC+ Seal coat completed
Road from R&B roadKancharapalem HW to
Alaganipadu.Embankment is in progress
NCRMP/B-W/AP/RHB/PRED/09V.CHALEM/RHB/007
ROAD FROM SUVEPALLI-PUDIPARTHI ROAD TO
SRIKANTH COLONY 4Months: EarthWork, Pipe
Culverts, GSB
8 Months:WBM GrII, GrIIand Shoulders
12 Months:BT and Road
Furniture
OGPC+ Seal coat completed
providing BT Surface to theroad from R&B road to
Edagali KandrigaOGPC+ Seal coat completed
NCRMP/B-W/AP/RHB/PRED/09CHITTAMURU/003
Road from R&B Road toMuttembake Via
Pittuvanipalli 5Months: EarthWork, Pipe
Culverts, GSB
10 Months:WBM GrII, GrII
and Shoulders
15 Months:BT and Road
Furniture
OGPC+ Seal coat completed
Road from R&B Chittamur toSoma Samudram
OGPC+ Seal coat completed
NCRMP/B-W/AP/09/MUTHUKUR/RHB/006
Road from R&B road toPatuvariKandriga
3Months: EarthWork, Pipe
Culverts, GSB
6 Months:WBM
GrII,GrII,CCPavement and
Shoulders
9 Months: BTand RoadFurniture
OGPC+ Seal coat completed
-
7/30/2019 Mpr October 2012
30/67
MONTHLY REPORT
29 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/09Allur/RHB/009Road from R&Broad alluru toGalidibbalu (via)Chukavani
dibba
5Months: EarthWork, Pipe
Culverts, GSB
10 Months:WBM GrII, GrIIand Shoulders
15 Months:BT and Road
FurnitureOGPC+ Seal coat completed
NCRMP/B-W/AP/RHB/PRED/009/T.P.GUDUR/012
Ring Road to TP Gudur-Salipeta R & B Road via CS
Puram and MandapamVillage 3Months: Earth
Work, PipeCulverts, GSB
6 Months:WBM
GrII,GrII,CCPavement and
Shoulders
9 Months: BTand RoadFurniture
OGPC+ Seal coat completed
Road from R & B Road C SPuram to Sivaramapuram
OGPC+ Seal coat completed
-
7/30/2019 Mpr October 2012
31/67
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
6.0 District wise status of tests conducted by TPQA:
Apart from monitoring the tests being conducted by the implementation team (contractors & Line department) at various
stages, the Third party Quality Audit team also conducted tests to confirm its compliance with the standards. These tests are
carried out in the site itself and in some cases samples are collected and testing done in outside laboratories. The details of
tests conducted in the field till end of September 2011 are presented.
Summary of QC Tests - Up to 31.10.2012
S.No. District
No. TestsConductedduring the
Month
Total no. of TestsCumulativeTests Done
Total no. of Tests
Passed Failed Passed Failed
1 Srikakulam 8 6 2 1364 1358 6
2 Vizianagaram 34 34 0 400 400 0
3 Visakhapatnam 72 72 0 2043 1997 46
4 East Godavari 30 30 0 1016 1016 0
5 West Godavari 0 0 0 349 349 0
6 Krishna 3 3 0 82 82 0
-
7/30/2019 Mpr October 2012
32/67
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
7.0 Details of Quality Control Audit Reports Submitted During this Month:
Package Number Name of Work District
NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002
Construction of cyclone shelter atBangarampeta in Nakkapalli Mandal
Vishakhapatnam
NCRMP/B-W/AP/RCS/PRED/07/Nizampatnam/0
03
Road from R&B Road toGurunadhanagar
Guntur
-
7/30/2019 Mpr October 2012
33/67
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002
Construction of cyclone shelter atPatimeeda in Nakkapalli Mandal
Vishakhapatnam
NCRMP/B-W/AP/MPCS/PRED/04/Thondangi/001
Construction of Cyclone Shelter atAvulamanda
East Godavari
NCRMP/B-W/AP/MPCS/PRED/04/Thondangi/001
Construction of Cyclone Shelter atLakshmanudipeta
East Godavari
NCRMP/B-
W/AP/MPCS/PRED/04/Uppalaguptam/002
Construction of Cyclone Shelter at
Pedaraghavulapeta East Godavari
NCRMP/BW/AP/BR/R&B/001/Bendigadda/004
Construction of HLB AcrossBendigadda At KM 4/10 of Pundi to
Parlakimidi roadSrikakulam
NCRMP/BW/AP/BR/R&B/001/Patnavanipeta/001
Construction of HLB Act KM 11/6-8 ofNH-5 to Patnavanipeta Road Via
Tamada connecting SundarapalemSrikakulam
NCRMP/BW/AP/BR/R&B/001/Surampeta/003
Construction of Minor bridge At KM12/2-4 of Nh-5 to Surampeta road viaNaruva, Mentada
Srikakulam
NCRMP/B-W/AP/MPCS/PRED/01/Santhabommal
i/005
Construction of cyclone shelter atRunku in Santhabommali Mandal
Srikakulam
8.0 Details of Environmental and Social Reports Submitted During this Month:
Package Number Name of Work District
NCRMP/B- Reconstruction of HLB @ Km 5/2 of Guntur
-
7/30/2019 Mpr October 2012
34/67
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/RCS/PRED/O7/Nizampatnam/0
03
Road from R&B Road toGurunadhanagar
Guntur
NCRMP/B-W/AP/RCS/PRED/O7/PVPalem/001
Road from R&B Road Alluru toYadavapalem
Guntur
NCRMP/B-W/AP/MPCS/PRED/O4/Thondangi/00
3
Construction of Cyclone Shelter atLakshmanudipeta
East Godavari
NCRMP/B-W/AP/MPCS/PRED/O4/Uppalaguptam/002
Construction of Cyclone Shelter atPedaraghavulapeta East Godavari
NCRMP/B-W/AP/RCS/PRED/O4/Uppalaguptam/
003
Road from R&B Road toChinaraghavulapeta
East Godavari
NCRMP/B-
W/AP/MPCS/PRED/O4/Thondangi/003
Construction of Cyclone Shelter at
Avulamanda
East Godavari
NCRMP/B-W/AP/RHB/PRED/O8/S.Konda/002
Road from NH5 to Mulaguntapadu Prakasam
-
7/30/2019 Mpr October 2012
35/67
MONTHLY REPORT
34 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Consolidated E&S Report for Guntur District in the Month of October 2012:
Third Party Quality Audit for Construction of Cyclone Shelters, Roads toCyclone Shelters & Habitations, Bridges and Culverts under NCRMP (Detailsof Guntur in October,2012)
S.No Activity Measures to be implemented by the contractor COMPLICEDNOT
COMPLICEDNOT
APPLICABLETOTAL
1Work Plan forEMPimplementation
The Contractors Project Manager shall be responsible forimplementation of EMP provisions and will coordinate the over-allimplementation of the said plan. Along with the Work Programme, theContractor shall submit a plan including method statement and timelineabout specific actions that will be taken by him to implement theprovisions laid out in the EMP
7 7
2RegulatoryPermissions andConsents
The Contractor shall obtain all requisite statutory clearances prior tocommencement of civil works, which includes obtainingpermission/consent for plants, water and extraction and borrow areasoperations. This includes:
Consent for establishment and operation of plant (for concretework) from SPCB.
7 7
PUC certification for all vehicles/equipment used for/duringconstruction.
7 7
Permission/consent of the District Administration/MiningDepartment/other agencies for quarrying and/or borrowing operations formaterials like sand and earth.
7 7
Permission for water extraction, if applicable in the local areacontext.
7 7
The Contractor shall abide by all conditions laid out in the saidclearances.
7 7
3Consultation andCommunityConsent
The Contractor shall consult and obtain written consents oflandowners(individual/panchayat/govt. agency) for temporary use of landfor all construction related activities including:
a) Setting-up and operation of construction camp including labourcamps, stock yards etc.
7 7
b) borrow areas and 7 7
-
7/30/2019 Mpr October 2012
36/67
MONTHLY REPORT
35 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
c) Disposal of debris and other waste material. 7 7
4Construction/Labour Camp
a) Location: The camp and plant site/s location and establishment shallbe done in a manner that does not interfere or disturb the activities oflocal inhabitants, particularly those of schools and health facilities.Written permission (no objection certificate) shall be taken from the
Gramsabha and the land owner prior to location selection and a copyshall be submitted to the Engineer approval.
7 7
b) Camp site shall not be located within 250mts. From a water bodyincluding village ponds.
7 7
c) A distance of at least 500mts. Shall be maintained fromdesignated/protected natural habitats (such as National Parks,Sanctuaries, Biosphere Reserves, Reserve Forests and Ramsar Sites)and Coastal Regulation Zone.
7 7
b) Accommodation and Basic Amenities: All weather shelter with therequired tenement size and toilets shall be provided, as per provisions ofLabour Laws. Separate toilet facilities shall be provided for women
workers. If a common mess is not provided/operated additional space forcooking shall be provided. The contractor shall ensure that hygienicconditions are maintained during the operation of such camps/facilities.
7 7
c) Fuel for Cooking: The Contractor shall ensure that fuel wood is notused as a cooking medium in the construction /labour camp.
7 7
d) Potable water supply: Drinking water supply of at least 40Ipcd withthe required supply points shall be provided.
7 7
e) Fire Safety: Adequate fire safety precautions shall be taken andrequired fire safety equipment (such as fire extinguishers) shall beprovided by the contractor.
7 7
5 Site Clearance
a) NO tree cutting is to carried out without the written instruction from
the Employer, who in turn will ensure that relevant regulatorypermission/s (including those from Forest Dept., if required) are obtainedprior to cutting of such trees.
7 7
b) The non-timber grade trees are to be stacked and possession is tobe given to Employer/concerned Govt. Department.
7 7
c) The Contractor shall strip, store and preserve top soil from the site ofconstruction work and in the stock yards prior to stacking of materials.The top soil shall be reinstated in the cyclone shelter compound after the
7 7
-
7/30/2019 Mpr October 2012
37/67
MONTHLY REPORT
36 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
construction is over.
6Protection ofProperties andResources
The Contractor shall take due care to protect and prevent damages tothe following resources during preparatory and construction work:
a) Water supply lines 7 7
b) Irrigation canals 7 7
c) Cart, cattle and/or foot trail/tracks 7 7
d) Cultural properties and sites/structures of religious importance 7 7
e) Houses, Farmlands, Orchids and/or Trees. 7 7
f) School and other existing buildings adjacent to the site ofconstruction.
7 7
In case of damage due to construction activity, the restoration/repairsshall be carried out by the contractor at his own cost.
7 7
7 QuarryOperations
The Contractor shall procure material from quarries that have beenapproved/licensed by the State Govt. A copy of such an approval shallbe submitted to the Engineer prior to procuring material.
7
8 Borrow Areas
a) Borrow areas for the project will be selected by the Contractorfollowing the stipulations given below: The finalisation of all suchlocations shall be dependent on the approval of the Engineer ontechnical and environmental grounds. This includes on-site verification tocross-check the accuracy of details provided by the contractor. Onlyafter receipt of the written approval from the Engineer, the Contractorshall enter into a formal agreement with landowner.
7 7
b) The Contractor shall not procure any kind of construction material(such as aggregates, sand and earth) from ecologically protected areas.
7 7
c) Identification and Selection:1. The borrow area should not be located in agriculture fields/ unlessunavoidable i.e. barren land is not available. In case borrowing needs tobe done on an agricultural land, top-soil stripping, stacking andpreservation is must.
7 7
2. Borrow pits shall not be located within a distance of 100mts. Fromany NH, SH or other roads.
7 7
-
7/30/2019 Mpr October 2012
38/67
MONTHLY REPORT
37 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
3. Borrow pits shall be preferably located 500mts. away fromsettlements/habitations.
7 7
4. No borrow pits shall be located within 500mts. from schools,colleges, playgrounds, religious structures and health centres.
7 7
5. No borrow area shall be opened with in 500mts. from a reserved or
protected forest area, protected sites, wildlife movement zone andcultural heritage site.
7 7
6. No tree cutting shall be undertaken. 7 7
7. Borrow area near any surface water body will be at least 100mts.away.
7 7
d) Operation 7
1. Area up to which material will be extracted shall be cleareddemarcated on ground.
7 7
2. A 15cm topsoil layer will be stripped and preserved in stockpiles. 7 7
3. Borrowing of earth should be preferably limited to a depth of 1.5mtr
from the existing ground level.
7 7
4. Slope at the edges will be maintained not steeper than 2:3 (Vertical: Horizontal)
7 7
e) Rehabilitation of Borrow Areas:
1. Rehabilitation shall be satisfactory undertaken immediately after theuse has ceased and at least three weeks prior to monsoon
7 7
2. Preserved top soil has be spread uniformly over land (except incases where borrow area is developed as a water body) used as aborrow area.
7 7
9Water Extraction/Use
Water for construction and for use at construction camps (includinglabour camps) is to be extracted with prior written permission of(a) the
individual owner, in case the source is private well/tube well; (b) GramPanchayat in case the source belongs to community: and (c) IrrigationDepartment in case the source is an irrigation canal or river.
7 1
10Safety of RoadUsers and LocalResidents
a) Traffic safety arrangements (including provision of warning signage,speed breakers etc.) shall be made by the contractor to ensure safety ofroad users and local people, particularly in the internal village roadswhich will be used for transporting materials.
7 1
-
7/30/2019 Mpr October 2012
39/67
MONTHLY REPORT
38 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
b) Material shall be covered during transportation to prevent spillage,accidents and pollution.
7 1
c) All required measures to ensure safety of local residents includingchildren and other near-by residents shall be taken up by the Contractor.This shall include provisions to prevent un authorised entry into the
construction.
7 1
11 Workers Safety
a) All measures required for ensuring safety and health of the workersshall be taken up by the Contractor. This includes provision andenforcement of appropriate personal protective equipment; first aidfacility; emergency response arrangement; proper storage ofhazardous/toxic and polluting materials and; measures for ensuring fireelectrical and mechanical safety arrangements in camp and in work site.
7 1
b) All methods steps and measures are required for ensuring safety ofworkers, particularly those needed while undertaking work in or aroundexcavations; workings at height; and; while handling inflammable, toxicand/or hazardous materials shall be ensured by the contractor.
7 1
c) Material safety data sheet record of fuel and other inflammablechemicals shall be maintained at the site. 7 1
12 Air pollut ion a) Wind barriers or screens shall be provided in the downwinddirection at air pollution causing sources like plant sites and fine materialstorage stock yards
7 1
b) Fugitive dust emissions have to be eliminated by providing dustsuppression/control measures, such as water sprinkling and cover onmaterials, based on activity and site conditions.
7 1
c) All plants and equipment shall comply with pollution control norms. 7 1
d) Water shall be sprinkled at least twice during dry day on haulageroads passing through or near settlements(including at least 100mbefore the settlement)
7 1
13 Water Pollution
a) All measures (including provision of temporary silt fencing tocontrol sediment run-off) required for avoiding adverse impacts to waterbodies (such as ponds, streams, canals and rivers), water sources (suchas hand pumps and wells) and adjacent farmland shall be undertaken bythe Contractor.
7 1
b) Storage of materials like fuel, chemicals, and cement shall be donein a manner (with impervious layer on bottom and a covered shed ontop) that does not contaminate land and ground/surface water.
7 1
-
7/30/2019 Mpr October 2012
40/67
MONTHLY REPORT
39 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
14 Noise Pollution
a) All noise causing activities shall be stopped during night time (9.00PM to 6.00 AM). The Contractor shall schedule construction works inconsultation with local Panchayat Authority and School Principal toensure least disturbance to school children and other adjacent residents.
1
b) Ear plugs shall be provided to the labour facing risk from high
noise pollution such as plant site and those working near generators,heavy equipment /machinery.
7 1
c) Appropriate noise controlling devices including acoustic generatorsshall be used to minimise noise during construction work and operationof camp.
7 1
15Disposal Debris/wastes
a) Debris and other construction waste, if any, shall be disposed inlocations pre-approved by the Engineer in a manner that it does notcontaminate the environment.
7 1
b) Location of Debris Disposal Sites: Debris disposal sites shall belocated preferably away from farmlands, water sources and waterbodies. In no case, debris shall be disposed within 500mts. ofecologically sensitive areas, including forests, wetlands and protected
natural habitats.
7 1
16Restoration andRehabilitation ofSites
All work sites and areas under temporary use (including construction andlabour camps, plant, sites, haul roads and borrow areas) shall berestored/rehabilitated to a better condition (if not at least to its originalcondition) and to the satisfaction of the Engineer and land owner uponcompletion of construction work by the Contractor.
7 1
Completion of work(as covered under clause 55.1 of GCC) will alsoinclude completion of rehabilitation and clean-up of the work sitesincluding camps, plants, in and around the construction site; disposal ofdebris/construction wastes at pre-approved locations and; restoration ofborrow areas and other sites/ locations used for material sourcing.
7 1
17 Liabilities
Any liability arising out of Contractors agreement with landowners/ localpeople/gram anchayat ( including those related to temporary use of land,water extraction and disposal of debris) shall be settled by theContarctor.
7 1
MONTHLY REPORT
-
7/30/2019 Mpr October 2012
41/67
MONTHLY REPORT
40 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Consolidated E&S Report for East Godavari District in the Month of October 2012:
Third Party Quality Audit for Construction of Cyclone Shelters, Roads to
Cyclone Shelters & Habitations, Bridges and Culverts under NCRMP (Detailsof East Godavari in October,2012)
S.No Activity Measures to be implemented by the contractor COMPLICEDNOT
COMPLICEDNOT
APPLICABLETOTAL
1Work Plan forEMPimplementation
The Contractors Project Manager shall be responsible forimplementation of EMP provisions and will coordinate the over-allimplementation of the said plan. Along with the Work Programme, theContractor shall submit a plan including method statement and timelineabout specific actions that will be taken by him to implement theprovisions laid out in the EMP
4 4
2RegulatoryPermissions andConsents
The Contractor shall obtain all requisite statutory clearances prior tocommencement of civil works, which includes obtainingpermission/consent for plants, water and extraction and borrow areasoperations. This includes:
Consent for establishment and operation of plant (for concretework) from SPCB.
4 4
PUC certification for all vehicles/equipment used for/duringconstruction.
4 4
Permission/consent of the District Administration/MiningDepartment/other agencies for quarrying and/or borrowing operations formaterials like sand and earth.
4 4
Permission for water extraction, if applicable in the local area
context. 4 4The Contractor shall abide by all conditions laid out in the said
clearances.4 4
3Consultation andCommunityConsent
The Contractor shall consult and obtain written consents oflandowners(individual/panchayat/govt. agency) for temporary use of landfor all construction related activities including:
a) Setting-up and operation of construction camp including labourcamps, stock yards etc.
4 4
MONTHLY REPORT
-
7/30/2019 Mpr October 2012
42/67
MONTHLY REPORT
41 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
b) borrow areas and 4
c) Disposal of debris and other waste material. 4
4Construction/Labour Camp
a) Location: The camp and plant site/s location and establishment shallbe done in a manner that does not interfere or disturb the activities oflocal inhabitants, particularly those of schools and health facilities.
Written permission (no objection certificate) shall be taken from theGramsabha and the land owner prior to location selection and a copyshall be submitted to the Engineer approval.
4 4
b) Camp site shall not be located within 250mts. From a water bodyincluding village ponds.
4 4
c) A distance of at least 500mts. Shall be maintained fromdesignated/protected natural habitats (such as National Parks,Sanctuaries, Biosphere Reserves, Reserve Forests and Ramsar Sites)and Coastal Regulation Zone.
4 4
b) Accommodation and Basic Amenities: All weather shelter with therequired tenement size and toilets shall be provided, as per provisions of
Labour Laws. Separate toilet facilities shall be provided for womenworkers. If a common mess is not provided/operated additional space forcooking shall be provided. The contractor shall ensure that hygienicconditions are maintained during the operation of such camps/facilities.
4 4
c) Fuel for Cooking: The Contractor shall ensure that fuel wood is notused as a cooking medium in the construction /labour camp.
4 4
d) Potable water supply: Drinking water supply of at least 40Ipcd withthe required supply points shall be provided.
4 4
e) Fire Safety: Adequate fire safety precautions shall be taken andrequired fire safety equipment (such as fire extinguishers) shall beprovided by the contractor.
4 4
5 Site Clearance
a) NO tree cutting is to carried out without the written instruction fromthe Employer, who in turn will ensure that relevant regulatorypermission/s (including those from Forest Dept., if required) are obtainedprior to cutting of such trees.
4 4
b) The non-timber grade trees are to be stacked and possession is tobe given to Employer/concerned Govt. Department.
4 4
MONTHLY REPORT
-
7/30/2019 Mpr October 2012
43/67
MONTHLY REPORT
42 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
c) The Contractor shall strip, store and preserve top soil from the site ofconstruction work and in the stock yards prior to stacking of materials.The top soil shall be reinstated in the cyclone shelter compound after theconstruction is over.
4 4
6Protection ofProperties andResources
The Contractor shall take due care to protect and prevent damages to
the following resources during preparatory and construction work:a) Water supply lines 4 4
b) Irrigation canals 1 3 4
c) Cart, cattle and/or foot trail/tracks 4 4
d) Cultural properties and sites/structures of religious importance 4 4
e) Houses, Farmlands, Orchids and/or Trees. 2 2 4
f) School and other existing buildings adjacent to the site ofconstruction.
1 3 4
In case of damage due to construction activity, the restoration/repairsshall be carried out by the contractor at his own cost.
4 4
7QuarryOperations
The Contractor shall procure material from quarries that have beenapproved/licensed by the State Govt. A copy of such an approval shallbe submitted to the Engineer prior to procuring material.
4 4
8 Borrow Areas
a) Borrow areas for the project will be selected by the Contractorfollowing the stipulations given below: The finalisation of all suchlocations shall be dependent on the approval of the Engineer ontechnical and environmental grounds. This includes on-site verification tocross-check the accuracy of details provided by the contractor. Onlyafter receipt of the written approval from the Engineer, the Contractorshall enter into a formal agreement with landowner.
4 4
b) The Contractor shall not procure any kind of construction material(such as aggregates, sand and earth) from ecologically protected areas.
4 4
c) Identification and Selection:
1. The borrow area should not be located in agriculture fields/ unlessunavoidable i.e. barren land is not available. In case borrowing needs tobe done on an agricultural land, top-soil stripping, stacking andpreservation is must.
4 4
2. Borrow pits shall not be located within a distance of 100mts. Fromany NH, SH or other roads.
4 4
MONTHLY REPORT
-
7/30/2019 Mpr October 2012
44/67
MONTHLY REPORT
43 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
3. Borrow pits shall be preferably located 500mts. away fromsettlements/habitations.
4 4
4. No borrow pits shall be located within 500mts. from schools,colleges, playgrounds, religious structures and health centres.
4 4
5. No borrow area shall be opened with in 500mts. from a reserved or
protected forest area, protected sites, wildlife movement zone andcultural heritage site.
4 4
6. No tree cutting shall be undertaken. 4 4
7. Borrow area near any surface water body will be at least 100mts.away.
4 4
d) Operation
1. Area up to which material will be extracted shall be cleareddemarcated on ground.
4 4
2. A 15cm topsoil layer will be stripped and preserved in stockpiles. 4 4
3. Borrowing of earth should be preferably limited to a depth of 1.5mtrfrom the existing ground level.
4 4
4. Slope at the edges will be maintained not steeper than 2:3 (Vertical: Horizontal)
4
e) Rehabilitation of Borrow Areas:
1. Rehabilitation shall be satisfactory undertaken immediately after theuse has ceased and at least three weeks prior to monsoon
4 4
2. Preserved top soil has be spread uniformly over land (except incases where borrow area is developed as a water body) used as aborrow area.
4 4
9
Water Extraction
/Use
Water for construction and for use at construction camps (includinglabour camps) is to be extracted with prior written permission of(a) the
individual owner, in case the source is private well/tube well; (b) GramPanchayat in case the source belongs to community: and (c) IrrigationDepartment in case the source is an irrigation canal or river.
4 4
10Safety of RoadUsers and LocalResidents
a) Traffic safety arrangements (including provision of warning signage,speed breakers etc.) shall be made by the contractor to ensure safety ofroad users and local people, particularly in the internal village roadswhich will be used for transporting materials.
4 4
MONTHLY REPORT
-
7/30/2019 Mpr October 2012
45/67
MONTHLY REPORT
44 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
b) Material shall be covered during transportation to prevent spillage,accidents and pollution.
4 4
c) All required measures to ensure safety of local residents includingchildren and other near-by residents shall be taken up by the Contractor.This shall include provisions to prevent un authorised entry into the
construction.
4 4
11 Workers Safety
a) All measures required for ensuring safety and health of the workersshall be taken up by the Contractor. This includes provision andenforcement of appropriate personal protective equipment; first aidfacility; emergency response arrangement; proper storage ofhazardous/toxic and polluting materials and; measures for ensuring fireelectrical and mechanical safety arrangements in camp and in work site.
4 4
b) All methods steps and measures are required for ensuring safety ofworkers, particularly those needed while undertaking work in or aroundexcavations; workings at height; and; while handling inflammable, toxicand/or hazardous materials shall be ensured by the contractor.
4 4
c) Material safety data sheet record of fuel and other inflammablechemicals shall be maintained at the site. 4 4
12 Air pollut ion a) Wind barriers or screens shall be provided in the downwinddirection at air pollution causing sources like plant sites and fine materialstorage stock yards
4 4
b) Fugitive dust emissions have to be eliminated by providing dustsuppression/control measures, such as water sprinkling and cover onmaterials, based on activity and site conditions.
4 4
c) All plants and equipment shall comply with pollution control norms. 4 4
d) Water shall be sprinkled at least twice during dry day on haulageroads passing through or near settlements(including at least 100mbefore the settlement)
4 4
13 Water Pollution
a) All measures (including provision of temporary silt fencing tocontrol sediment run-off) required for avoiding adverse impacts to waterbodies (such as ponds, streams, canals and rivers), water sources (suchas hand pumps and wells) and adjacent farmland shall be undertaken bythe Contractor.
4 4
b) Storage of materials like fuel, chemicals, and cement shall be donein a manner (with impervious layer on bottom and a covered shed ontop) that does not contaminate land and ground/surface water.
2 2 4
MONTHLY REPORT
-
7/30/2019 Mpr October 2012
46/67
MONTHLY REPORT
45 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
14 Noise Pollution
a) All noise causing activities shall be stopped during night time (9.00PM to 6.00 AM). The Contractor shall schedule construction works inconsultation with local Panchayat Authority and School Principal toensure least disturbance to school children and other adjacent residents.
4
b) Ear plugs shall be provided to the labour facing risk from high
noise pollution such as plant site and those working near generators,heavy equipment /machinery.
4 4
c) Appropriate noise controlling devices including acoustic generatorsshall be used to minimise noise during construction work and operationof camp.
4 4
15Disposal Debris/wastes
a) Debris and other construction waste, if any, shall be disposed inlocations pre-approved by the Engineer in a manner that it does notcontaminate the environment.
4 4
b) Location of Debris Disposal Sites: Debris disposal sites shall belocated preferably away from farmlands, water sources and waterbodies. In no case, debris shall be disposed within 500mts. ofecologically sensitive areas, including forests, wetlands and protected
natural habitats.
4 4
16Restoration andRehabilitation ofSites
All work sites and areas under temporary use (including construction andlabour camps, plant, sites, haul roads and borrow areas) shall berestored/rehabilitated to a better condition (if not at least to its originalcondition) and to the satisfaction of the Engineer and land owner uponcompletion of construction work by the Contractor.
4 4
Completion of work(as covered under clause 55.1 of GCC) will alsoinclude completion of rehabilitation and clean-up of the work sitesincluding camps, plants, in and around the construction site; disposal ofdebris/construction wastes at pre-approved locations and; restoration ofborrow areas and other sites/ locations used for material sourcing.
4 4
17 Liabilities
Any liability arising out of Contractors agreement with landowners/ local
people/gram anchayat ( including those related to temporary use of land,water extraction and disposal of debris) shall be settled by theContarctor.
4 4
MONTHLY REPORT
-
7/30/2019 Mpr October 2012
47/67
MONTHLY REPORT
46 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Consolidated E&S Report for Prakasam District in the Month of October 2012:
Third Party Quality Audit for Construction of Cyclone Shelters, Roads to
Cyclone Shelters & Habitations, Bridges and Culverts under NCRMP (Detailsof Prakasam in October,2012)
S.No Activity Measures to be implemented by the contractor COMPLICEDNOT
COMPLICEDNOT
APPLICABLETOTAL
1Work Plan forEMPimplementation
The Contractors Project Manager shall be responsible forimplementation of EMP provisions and will coordinate the over-allimplementation of the said plan. Along with the Work Programme, theContractor shall submit a plan including method statement and timelineabout specific actions that will be taken by him to implement theprovisions laid out in the EMP
1 1
2RegulatoryPermissions andConsents
The Contractor shall obtain all requisite statutory clearances prior tocommencement of civil works, which includes obtainingpermission/consent for plants, water and extraction and borrow areasoperations. This includes:
Consent for establishment and operation of plant (for concretework) from SPCB.
1 1
PUC certification for all vehicles/equipment used for/duringconstruction.
1 1
Permission/consent of the District Administration/MiningDepartment/other agencies for quarrying and/or borrowing operations formaterials like sand and earth.
1 1
Permission for water extraction, if applicable in the local area
context. 1 1The Contractor shall abide by all conditions laid out in the said
clearances.1 1
3Consultation andCommunityConsent
The Contractor shall consult and obtain written consents oflandowners(individual/panchayat/govt. agency) for temporary use of landfor all construction related activities including:
a) Setting-up and operation of construction camp including labourcamps, stock yards etc.
1 1
MONTHLY REPORT
-
7/30/2019 Mpr October 2012
48/67
MONTHLY REPORT
47 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
b) borrow areas and 1 1
c) Disposal of debris and other waste material. 1 1
4Construction/Labour Camp
a) Location: The camp and plant site/s location and establishment shallbe done in a manner that does not interfere or disturb the activities oflocal inhabitants, particularly those of schools and health facilities.
Written permission (no objection certificate) shall be taken from theGramsabha and the land owner prior to location selection and a copyshall be submitted to the Engineer approval.
1 1
b) Camp site shall not be located within 250mts. From a water bodyincluding village ponds.
1 1
c) A distance of at least 500mts. Shall be maintained fromdesignated/protected natural habitats (such as National Parks,Sanctuaries, Biosphere Reserves, Reserve Forests and Ramsar Sites)and Coastal Regulation Zone.
1 1
b) Accommodation and Basic Amenities: All weather shelter with therequired tenement size and toilets shall be provided, as per provisions of
Labour Laws. Separate toilet facilities shall be provided for womenworkers. If a common mess is not provided/operated additional space forcooking shall be provided. The contractor shall ensure that hygienicconditions are maintained during the operation of such camps/facilities.
1 1
c) Fuel for Cooking: The Contractor shall ensure that fuel wood is notused as a cooking medium in the construction /labour camp.
1 1
d) Potable water supply: Drinking water supply of at least 40Ipcd withthe required supply points shall be provided.
1 1
e) Fire Safety: Adequate fire safety precautions shall be taken andrequired fire safety equipment (such as fire extinguishers) shall beprovided by the contractor.
1 1
5 Site Clearance
a) NO tree cutting is to carried out without the written instruction fromthe Employer, who in turn will ensure that relevant regulatorypermission/s (including those from Forest Dept., if required) are obtainedprior to cutting of such trees.
1 1
b) The non-timber grade trees are to be stacked and possession is tobe given to Employer/concerned Govt. Department.
1 1
MONTHLY REPORT
-
7/30/2019 Mpr October 2012
49/67
MONTHLY REPORT
48 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
c) The Contractor shall strip, store and preserve top soil from the site ofconstruction work and in the stock yards prior to stacking of materials.The top soil shall be reinstated in the cyclone shelter compound after theconstruction is over.
1 1
6Protection ofProperties andResources
The Contractor shall take due care to protect and prevent damages to
the following resources during preparatory and construction work:a) Water supply lines 1 1
b) Irrigation canals 1 1
c) Cart, cattle and/or foot trail/tracks 1 1
d) Cultural properties and sites/structures of religious importance 1 1
e) Houses, Farmlands, Orchids and/or Trees. 1 1
f) School and other existing buildings adjacent to the site ofconstruction.
1 1
In case of damage due to construction activity, the restoration/repairsshall be carried out by the contractor at his own cost.
1 1
7QuarryOperations
The Contractor shall procure material from quarries that have beenapproved/licensed by the State Govt. A copy of such an approval shallbe submitted to the Engineer prior to procuring material.
1
8 Borrow Areas
a) Borrow areas for the project will be selected by the Contractorfollowing the stipulations given below: The finalisation of all suchlocations shall be dependent on the approval of the Engineer ontechnical and environmental grounds. This includes on-site verification tocross-check the accuracy of details provided by the contractor. Onlyafter receipt of the written approval from the Engineer, the Contractorshall enter into a formal agreement with landowner.
1 1
b) The Contractor shall not procure any kind of construction material(such as aggregates, sand and earth) from ecologically protected areas.
1 1
c) Identification and Selection:
1. The borrow area should not be located in agriculture fields/ unlessunavoidable i.e. barren land is not available. In case borrowing needs tobe done on an agricultural land, top-soil stripping, stacking andpreservation is must.
1 1
2. Borrow pits shall not be located within a distance of 100mts. Fromany NH, SH or other roads.
1 1
MONTHLY REPORT
-
7/30/2019 Mpr October 2012
50/67
MONTHLY REPORT
49 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
3. Borrow pits shall be preferably located 500mts. away fromsettlements/habitations.
1 1
4. No borrow pits shall be located within 500mts. from schools,colleges, playgrounds, religious structures and health centres.
1 1
5. No borrow area shall be opened with in 500mts. from a reserved or
protected forest area, protected sites, wildlife movement zone andcultural heritage site.
1 1
6. No tree cutting shall be undertaken. 1 1
7. Borrow area near any surface water body will be at least 100mts.away.
1 1
d) Operation 1
1. Area up to which material will be extracted shall be cleareddemarcated on ground.
1 1
2. A 15cm topsoil layer will be stripped and preserved in stockpiles. 1 1
3. Borrowing of earth should be preferably limited to a depth of 1.5mtrfrom the existing ground level.
1 1
4. Slope at the edges will be maintained not steeper than 2:3 (Vertical: Horizontal)
1
e) Rehabilitation of Borrow Areas:
1. Rehabilitation shall be satisfactory undertaken immediately after theuse has ceased and at least three weeks prior to monsoon
1 1
2. Preserved top soil has be spread uniformly over land (except incases where borrow area is developed as a water body) used as aborrow area.
1 1
9
Water Extraction
/Use
Water for construction and for use at construction camps (includinglabour camps) is to be extracted with prior written permission of(a) the
individual owner, in case the source is private well/tube well; (b) GramPanchayat in case the source belongs to community: and (c) IrrigationDepartment in case the source is an irrigation canal or river.
1 1
10Safety of RoadUsers and LocalResidents
a) Traffic safety arrangements (including provision of warning signage,speed breakers etc.) shall be made by the contractor to ensure safety ofroad users and local people, particularly in the internal village roadswhich will be used for transporting materials.
1 1
MONTHLY REPORT
-
7/30/2019 Mpr October 2012
51/67
50 | P a g e
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
b) Material shall be covered during transportation to prevent spillage,accidents and pollution.
1 1
c) All required measures to ensure safety of local residents includingchildren and other near-by residents shall be taken up by the Contractor.This shall include provisions to prevent un authorised entry into the
construction.
1 1
11 Workers Safety
a) All measures required for ensuring safety and health of the workersshall be taken up by the Contractor. This includes provision andenforcement of appropriate personal protective equipment; first aidfacility; emergency response arrangement; proper storage ofhazardous/toxic and polluting materials and; measures for ensuring fireelectrical and mechanical safety arrangements in camp and in work site.
1 1
b) All methods steps and measures are required for ensuring safety ofworkers, particularly those needed while undertaking work in or aroundexcavations; workings at height; and; while handling inflammable, toxicand/or hazardous materials shall be ensured by the contractor.
1 1
c) Material safety data sheet record of fuel and other inflammable
chemicals shall be maintained at the site. 1 1
12 Air pollut ion a) Wind barriers or screens shall be provided in the downwinddirection at air pollution causing sources like plant sites and fine materialstorage stock yards
1 1
b) Fugitive dust emissions have to be eliminated by providing dustsuppression/control measures, such as water sprinkling and cover onmaterials, based on activity and site conditions.
1 1
c) All plants and equipment shall comply with pollution control norms. 1 1
d) Water shall be sprinkled at l